Design-Construction of Precast Prestressed Concrete Floating Wave Attenuator

Total Page:16

File Type:pdf, Size:1020Kb

Load more

Design-Construction of Precast Prestressed Concrete Floating Wave Attenuator Roderic A. Ellman, Jr., P.E. Precast prestressed concrete was used imaginatively Senior Associate Mueser Rutledge to build the first phase of a 960 ft (293 m) floating Consulting Engineers wave attenuator in Flushing BaYt New York. The New York, New York precast system proved to be cost effective and efficiently constructable, while also solving the site constraints and environmental issues. The attenuator features three 76 ft (4.9 m) wide, 320 ft (97.5 m) long sections comprising 8 ft (2.4 m) wide, 40 ft (7 2.2 m) long precast, prestressed polystyrene-filled Simon Harton, P.E. concrete box units transversely post-tensioned Ch ief Structural Engineer together. This article provides the conceptual LEAP Associates International, Inc. system, bidding process, design criteria and Tampa, Florida structural design considerations of the project as well as highlights of the manufacture, transportation, and erection of the precast segments. he World's Fair Marina is located southeast of La Guardia Airport on Flushing Bay in New York. A runway extension project for the airport required re­ Harold E. Wescott T moval of an existing rubble mound breakwater that pro­ General Manager vided wave protection to the marina. Mueser Rutledge Precast Structures, Inc. Auburn, Maine Consulting Engineers (MRCE) was retained by the Port Authority of New York and New Jersey to design a re­ placement breakwater for the facility. Selection of a suitable replacement breakwater was based on the need to meet the performance criteria of the marina, site constraints and environmental issues. MRCE performed a geotechnical investigation that revealed subsurface condi­ tions to include approximately 50ft (15.2 m) of soft organic silt above the glacial outwash sand. Environmental regula­ tions prohibited any filling, which ruled out a replacement rubble mound breakwater. Also, the navigable area was lim­ ited between the marina and an adjacent Federal Anchorage 30 PCI JOURNAL Fig. 1. Aerial view of floating wave attenuator. Area, restricting breakwater location and movement. MRCE designed a cantilevered steel pipe pile anchorage system that was capable of developing the required lat­ eral resistance in the soft subsurface soils while maintaining the structure's ! location within acceptable limits. Pre­ dicted wave forecasts and required wave protection within the marina led to the selection of a precast, pre­ stressed, post-tensioned, prismatic concrete floating wave attenuator. The total planned length of the new wave attenuator is approxi­ mately 1650 linear ft (503 m). The project was phased to accommodate future marina development with the first stage comprising 960 linear ft (293 m), constructed in three 320 ft Fig. 2. Location plan of floating wave attenuator. July-August 1997 31 F L U S H N G 8 A Y 190'-0" 20'-G 7-SPACES 0 40'- 0" • 280'- 0" UNE OF FEDERAL • ~CHORAGE AA/ fSTEEL PIPE t /24PILE (TYPICAL) ~------+-~----~------~+--------------/~---------------4--H----- 10' -0" _] T+-----16-,-_-0"-__1-.---rlt•::t::jt::;;::-1""'0:...:---....,-r--- _-:i•==~;::::-~:::;:::oi::::;;:::Jo~== ;;::J•~==:.==~•i: ::t{~::;;::...z:....,.,...O --, 0 0 • • • • s·-O"....J t I L MC SERIES PRESTRESSED CONC. BREAKWATER (lYPICAL.) 8-SPACES 0 40'-0" • 320'-0" 120'-(] 4'-Cf PLAN 40'-- 20-' 0 40'- 80' Fi g. 3. Plan of floating wave attenuator (for Section A-A, see Fig. 4) . (97 .5 m) sections. The Stage 1 struc­ DESIGN CRITERIA AND miles per hour (96 km!hr). Tidal varia­ ture, described in this paper, was STRUCTURAL DESIGN tion measured approximately 17 ft completed in March 1996 (see Fig. 1). (5 .2 m) between mean low water and CONSIDERATIONS the 100-year flood tide. Historical data Several wave attenuator systems for the original rubble mound break­ BIDDING PROCESS were evaluated for use on this project water indicated a maximum transmit­ Due to the specialized aspect of the including timber, timber/concrete ted wave height of 2ft (0.61 m). floating wave attenuator structure, it composites, timber/steel composites Based on the design criteria, site was decided to use a proprietary sys­ and prestressed concrete. The wave at­ conditions and required attenuation tem. MC Series prestressed concrete tenuator had to meet the following de­ performance, the required nominal di­ floating segments - designed jointly sign criteria: mensions of the floating wave attenua­ by Marina Components, Inc. and Pre­ • Provide a minimum 50 percent wave tor were 4 ft 3 in. deep by 16 ft wide cast Structures, Inc., engineered by attenuation performance of the spec­ (1.3 x 4.9 m). The anchorage system LEAP Associates International, Inc. and ified design wave and furnish a min­ included 24 in. (610 mm) diameter manufactured by Precast Structures, imum 1 ft (0.30 m) of free board open ended steel pipe piles spaced 20 Inc. - were selected for this project. above the still water level. ft (6.1 m) on centers. Contract documents indicated de­ • Simultaneously resist all vertical Figs. 3 and 4 show the plan and sec­ sign and performance criteria for the and horizontal forces generated by tion of the floating wave attenuator. floating wave attenuator and required the specified design wave and dis­ the use of the MC Series prestressed placements of the anchorage system. concrete floating segments. The final • Allow ease of assembly and trans­ STRUCTURAL SYSTEM design and detailing of the segments port to the site. The precast, prestressed wave atten­ was performed by LEAP Associates • Provide long-term durability with uator structure is designed and built for the successful bidder. Bids were simple maintenance in a marine en­ based on the principles of segmental received from several marine contrac­ vironment. construction. Individual 8 ft wide, 4 ft tors with a fixed price for floats. Gen­ For this particular site (see Fig. 2), 3 in. deep, 40 ft long (2.4 m wide, 1.3 eral Contractor Simpson & Brown, the design wave height was 3.5 ft (1.1 m deep, 12.2 m long) segments were Inc. was the low bidder and was se­ m) with a period of 3.0 seconds and a prefabricated and shipped to the job­ lected to install the floating wave wave length of 50ft (15.2 m). The de­ site. At the jobsite, the units were set attenuator. sign wind speed was established as 60 in the water and connected together by 32 PCI JOURNAL F L U S H N G 8 A Y 8 ---SPACES 0 40' o" =320' o" ~ - ... 0 0 0 0 0 0 0 • • • 0 • tJ 7-SPACES 0 40'-o" • 280'-o" 20'-0 b I 40'- o" io ('.1 ~ 8-SPACES 0 40'-o"=320'-o" I • + • • • + • + • + • • tl 7- SPACES 0 40'-o"• 280'-o" Fig. 3 (cont.). Plan of floating wave atten uator (for Section A-A, see Fig. 4) . post-tensioning rods to build three 16 ft wide, 4ft 3 in. deep, 320ft long (4.9 PROlECTIVE PILE Cfof· m wide, 1.3 m deep, 97.5 m long) structures. The segments are EL.+20.0' polystyrene-filled, thin walled con­ crete boxes for the permanent floating El.+16.7'= EHW requirement. The exterior walls (sides) ( 100 YR . FLOOD) and flanges (top and bottom) of the in­ MONO- STRAN D POST TENSIONING CABLES dividual units are prestressed for (TOP SLAB ONLY) strength and crack control. POST TENSIONING CABLES The method of connecting the indi­ vidual segments into the continuous structure is somewhat unique. The EL. +6.8' - MHW structure consists of two rows of 40 ft (12.2 m) long precast segments placed side by side with alternately overlap­ CONCRETE ping butt joints at 20 ft (6.1 m) inter­ 16'- 0" ENCASEMENT EL. 0.0'= MLW vals. At both sides of each splice joint there are two post-tensioned rods placed transversely through 4 in. (102 EXISTING BAY BOTIOM 3 El.-7' ± mrn) diameter sleeves located 5 / 4 in. ( 146 mrn) from the top and the bottom of the segments (see Figs. 5 and 6). In­ stead of being post-tensioned longitu­ dinally, as is common practice in seg­ mental construction, the segments are SECTION A-A post-tensioned transversely. This method of assembly proved to be very MIN . TI P EL. - 60.0' D D convenient during construction, en­ abling a relatively simple operation in Fig. 4. Cross section of wave attenuator (for plan of structure, see Fig. 3) . July-August 1997 33 24"f SI[[L PIPE PILES 20'-o" 20'-o· 20'-0" 20'-o· 1/2" \>----------=J9:.__'-_::.II"~(_::.PRE::::C::.:AS:.__T),___ _____ _ _____,f-r--------'J"-9'--'-11-" -';-(PRE_:c:._CA_:_ST.:_) _______ --fl/2" 1/2" C.L. POST- TENS ION ING (P.T.) 2'-1 l/ 8" 2'- 1 7/8" L__, SI:QUENCE Of POST TENSI ON ING SI:E SCHEDULE I CEN)[ RU NE OF ~ 24" o STEEL PIPE PILE. 19' - II" (PRECAST) 39'-11" (PRECAST) Fig. 5. Detailed plan of wave attenuator structure showing precast, prestressed concrete segments and sequence of post-tensioning. the water assembly of each 320 ft (97.5 m) structure. EPOXY GROUT As mentioned above, the continuity (m>.) of the structure is achieved by assem­ 0 bling the units in a staggered pattern fr···~ ( so the units are spliced to each other ' . ~ at the butt joints (see Fig. 7). The L J loads that occur in the units at the butt 1;;. -'7. joints must be transferred into the ad­ [ ,.; jacent units to provide continuity. The l transfer of these loads is provided by ~ the lateral post-tensioning. The hori­ \__ P.1. BOTTOM zontal moment capacity is provided r I K£YWAY [!! i! by the moment couple equal to the 1-n Sf! 1-n S/8" I I ~"' tension capacity of the post-tension­ ~ ~ ing rods multiplied by the horizontal "' distance between them.
Recommended publications
  • Port Dock 5 Technical Specs.Pdf

    Port Dock 5 Technical Specs.Pdf

    TABLE OF CONTENTS FOR TECHNICAL SPECIAL PROVISIONS SECTION 00210 - MOBILIZATION ....................................................................................... 2 SECTION 00220 - ACCOMMODATIONS FOR PUBLIC TRAFFIC ....................................... 2 SECTION 00225 - WORK ZONE TRAFFIC CONTROL ........................................................ 2 SECTION 00250 - TEMPORARY WALKWAYS .................................................................... 2 SECTION 00253 - TEMPORARY WORK ACCESS AND CONTAINMENT .......................... 5 SECTION 00280 - EROSION AND SEDIMENT CONTROL ................................................. 5 SECTION 00290 - ENVIRONMENTAL PROTECTION ......................................................... 6 SECTION 00405 - TRENCH EXCAVATION, BEDDING, AND BACKFILL .......................... 18 SECTION 00440 - COMMERCIAL GRADE CONCRETE ................................................... 18 SECTION 00445 - SANITARY, STORM, CULVERT, SIPHON, AND IRRIGATION PIPE ...................................................................................................... 18 SECTION 00490 - WORK ON EXISTING SEWERS AND STRUCTURES ......................... 19 SECTION 00495 - TRENCH RESURFACING ..................................................................... 19 SECTION 00501 - BRIDGE REMOVAL .............................................................................. 20 SECTION 00520 - DRIVEN PILES ...................................................................................... 21 SECTION 00521 – PASSIVE CATHODIC
  • CRACK-RESISTANT CONCRETE MIX Pre-Blended, Fiber-Reinforced, Portland Cement and Sand Mix for 1½” Or Greater Depth

    CRACK-RESISTANT CONCRETE MIX Pre-Blended, Fiber-Reinforced, Portland Cement and Sand Mix for 1½” Or Greater Depth

    CRACK-RESISTANT CONCRETE MIX Pre-blended, fiber-reinforced, Portland cement and sand mix for 1½” or greater depth 1. PRODUCT NAME Coverage Tech-Mix® Crack-Resistant Concrete Mix • 60 lb. (27.2 kg) bag yields approximately 0.45 cu. ft. (12.7 L) of wet mortar. Coverage will vary based on waste and job site 2. MANUFACTURER conditions. Tech-Mix® is a registered trademark of TCC Materials 2025 Centre Pointe Blvd., Suite 300 5. INSTALLATION Mendota Heights, MN 55120 USA Preparation Phone: 1.651.688.9116 Read all directions before starting work. Stake out the planned Web: techmixpro.com area and remove sod or soil to the desired depth. Nail and stake forms securely in place. Tamp and compact the sub-base 3. PRODUCT DESCRIPTION until firm. Subgrade surface should be brought to a saturated Tech-Mix® Crack-Resistant Concrete Mix consists of a pre- surface dry (SSD) condition with potable water. All repair blended mixture of Portland cement, aggregates, air-entraining overlay surfaces must be sound and be clean of any admixtures, special synthetic reinforcing fibers, and other contaminants. Dampen adjoining concrete surfaces to SSD ingredients to reduce shrinkage cracks and improve impact condition with potable water. For increased bond to existing resistance. The special reinforcing fibers eliminate the need for concrete, a latex bonding additive such as Akona Concrete wire mesh in typical slab-on-grade applications. Use for Bonding Additive may be used. pouring concrete 1½ in. (38 mm) thick or greater. It is also used for building or repairing steps, walks, and floors. Note: It is the responsibility of the installer/applicator to ensure the suitability of the product for its intended use.
  • Concrete Quarterly, Summer 2016

    Concrete Quarterly, Summer 2016

    CONCRETE QUARTERLY SUMMER 2016 | ISSUE NUMBER 256 LAUNCHING IN STYLE SHAPE-SHIFTER A MEETING WITH M Make reinvents the office – with Herzog & de Meuron lands a Paul Monaghan of Stirling winner exposed concrete, woven brick mysterious object in the heart AHMM on how the road to success and a Soviet missile of historic Oxford was paved with concrete CONTENTS AGENDA INSPIRATION Known unknowns 4 DREAMING SPIRALS Of the many specialist disciplines involved in shaping the built Herzog & de Meuron gives a tutorial on environment, one that is sadly lacking is clairvoyance. Sustainable design building iconic architecture in the heart increasingly encompasses the whole-life impacts of buildings, which of Oxford presents the impossible challenge of foreseeing what a building may have to contend with over its lifespan, and how it can be designed for a future 8 MISSION CONTROL that may look very different from today while meeting the demands of now. Make puts a rocket up the traditional One answer will surely be greater reuse and refurbishment compared insurance office to new build. Buildings do become outdated and replacement is an inevitable part of progress. But the sums are changing. It is far less 11 VEIN GLORIOUS carbon-intensive to reuse elements of buildings such as structure and … Or what happens when in-situ concrete foundations than to demolish and start again – a point that enlightened meets the ghost of Jackson Pollock Guy Thompson clients are just beginning to take on board. These elements can, in Head of architecture, any case, last much longer than the commonly used 60-year study period, FOCUS housing and raising the question as to whether this remains a valid approach.
  • 00010 Table of Contents

    00010 Table of Contents

    DOCUMENT 00010 TABLE OF CONTENTS INTRODUCTORY INFORMATION Document 00001 Project Title Page 00010 Table of Contents BIDDING REQUIREMENTS Document 00220 Geotechnical Data CONTRACTING REQUIREMENTS Document 00500 Agreement Form (AIA A101 ) 00700 General Conditions (AIA A201) SPECIFICATIONS DIVISION 1 GENERAL REQUIREMENTS Section 01110 Summary 01250 Substitution Procedures 01260 Contract Modifications 01290 Payment procedure 01310 Project Management and Coordination 01320 Construction Process Documentation 01330 Submittal Procedures 01400 Quality Requirements 01420 References 01500 Temporary Facilities and Controls 01539 Temporary Tree and Plant Protection 01600 Product Requirement 01730 Execution 017419 Construction Waste Management and Disposal 01770 Closeout Procedures 017823 Operation and Maintenance Data 017839 Project Record Documents DIVISION 2 SITE CONSTRUCTION Section 02020 Geotechnical Data 02080 Pipe Utilities 02221 Demolition 02230 Site Clearing 02750 Integral Colored Ground and Polished Concrete See Civil and Landscape Drawings for civil and landscape specifications DIVISION 3 CONCRETE 03100 Concrete Formwork Whitfield Associates 00010 - 1 Table of Contents Laguna Beach Lifeguard Headquarters May 25, 2012 03200 Concrete Reinforcement 03300 Cast in Place Concrete 0336 Shotcrete 0311116 Concrete Form Liners DIVISION 4 MASONRY Not Used DIVISION 5 METALS Section 05120 Structural Steel 05410 Light Gage Metal Framing 05500 Metal Fabrications 055214 Aluminum Railing Systems DIVISION 6 WOOD AND PLASTICS Section 06105 Miscellaneous Rough
  • UFGS 35 51 13.00 20 Concrete Floating Pier for Small Craft

    UFGS 35 51 13.00 20 Concrete Floating Pier for Small Craft

    ************************************************************************** USACE / NAVFAC / AFCEC / NASA UFGS-35 51 13.00 20 (April 2006) ------------------------------------ Preparing Activity: NAVFAC Replacing without change UFGS-03420N (August 2004) UNIFIED FACILITIES GUIDE SPECIFICATIONS References are in agreement with UMRL dated July 2021 ************************************************************************** SECTION TABLE OF CONTENTS DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION SECTION 35 51 13.00 20 CONCRETE FLOATING PIER FOR SMALL CRAFT 04/06 PART 1 GENERAL 1.1 REFERENCES 1.2 MODIFICATIONS TO REFERENCES 1.3 SUBMITTALS 1.4 PRECAST FLOATS 1.5 QUALITY CONTROL 1.5.1 Precast Concrete Float Design 1.5.1.1 Pier Loading 1.5.1.2 Performance 1.5.2 Gangway Design 1.5.2.1 Gangway Loading 1.5.2.2 Performance 1.5.3 PCI Quality Certifications 1.5.3.1 Product Quality Control 1.6 DELIVERY AND STORAGE 1.7 FACTORY INSPECTION 1.8 QUALITY ASSURANCE 1.8.1 Drawing Information 1.8.2 Design Calculations 1.8.3 Concrete Mix Design 1.8.4 Paint Coating System PART 2 PRODUCTS 2.1 CONTRACTOR-FURNISHED MIX DESIGN 2.2 PRECAST FLOAT MATERIALS 2.2.1 Cement 2.2.1.1 Fly Ash and Pozzolan 2.2.1.2 Ground Iron Blast-Furnace Slag 2.2.2 Water 2.2.3 Aggregates 2.2.3.1 Aggregates Selection 2.2.4 Grout SECTION 35 51 13.00 20 Page 1 2.2.4.1 Nonshrink Grout 2.2.4.2 Cementitious Grout 2.2.5 Admixtures 2.2.5.1 Air-Entraining 2.2.5.2 Accelerating 2.2.5.3 Water Reducing 2.2.5.4 Corrosion Inhibitor 2.2.6 Reinforcement 2.2.6.1 Reinforcing Bars 2.2.6.2 Welded Wire Fabric 2.2.7
  • M-82 (M0820001.714)

    M-82 (M0820001.714)

    M-82 (M0820001.714) Standard Protocol to Evaluate the Performance of Corrosion Mitigation Technologies in Concrete Repairs July 2014 United States Department of the Interior Bureau of Reclamation Denver Federal Center Technical Service Center Concrete, Geotechnical, & Structural Laboratory Denver, Colorado 80225-0007 M-82 (M0820001.714 7-31-2014 Introduction The protocol for measuring the performance of corrosion mitigation technologies for concrete reinforcing steel was first suggested by a group of industry recognized experts and strategic planners in support of goals outlined in Vision 2020: “A Vision for the Concrete Repair, Protection and Strengthening Industry”. Vision 2020 is an industry created strategic plan and roadmap; documents were developed over a several year period which began in 2003. Information about these documents is available at the American Concrete Institute (ACI) Foundation’s Strategic Development Council (SDC) website. One goal of the Vision 2020 group was to develop a test protocol which could be used to evaluate the effectiveness of steel reinforcement corrosion mitigation techniques for existing structures. As a first step toward achieving that goal, a panel of industry experts met to discuss a proposed protocol during the summer of 2008. The panel reviewed and discussed currently available test methods, concrete repair industry needs, and current research programs. The panel stressed the importance of having a flexible test program that would properly evaluate the performance of current corrosion mitigation options while allowing for future innovations. The panel recommended a pilot program be conducted prior to final adoption of a testing protocol or initiation of any full scale testing program to validate the repeatability and reproducibility of the protocol.
  • Arizona Department of Education

    Arizona Department of Education

    Arizona Department of Education Career and Technical Education Recommended Equipment List Program: Construction Technologies CIP#: 46.0400.20 NOTE: The following items and descriptions are the recommended equipment guidelines for each CTE Construction Technologies program. Please note that this list of recommended items does not necessarily need to be supported financially by Federal Perkins or State Priority funding sources. In many cases, local school district funds are used to purchase items on a regular basis (i.e. furniture, consumables, etc.) Further, please understand that this is not an exhaustive list. Please contact ADE-CTE Program Specialist for Construction Science Technologies, Jamie Miller ([email protected]), if you have questions regarding the appropriateness of any item you are considering for addition to your CTE Construction Technologies program. Recommended Equipment and Software Item Items Highest Priority* MUST HAVE Safety glasses with side shields Z87 8”-10: concrete finishing trowel Set of cold chisels Steel concrete edger Architect / engineer scale Floor broom 16' - 30' push pull tape Workbench brush 100' tape measure Drill bits with index - 1/16"-1/4" HS 16-20 oz. smooth-faced trim hammer 2”, 4”, 6", 8” and 12" drywall taping knives 22-24 oz. framing hammer Circular saw 7-1/4" with combination blade 8 point handsaw Cordless drill or drill / impact driver combo kit 2’ level Drywall hammer 4' Level 4' T-square Rulers-straight edge, standard, metric Work bench Screwdrivers - Phillips & regular Safety / hazard / exit signs 3-1/2” brick chisel Channel-lock pliers Set of 4 wood chisels: 1/4", 1/2", 3/4" and 1" Dust masks - 3M - Model 8210, for insulation Speed square Extension cord - grounding type - 50'minimum 100' chalk box Round shovel Utility knife and blades- hook bill, straight Pointed shovel Cat's paw Work gloves Framing square (with rafter tables) Transit level or builder's level Bars - wrecking bar, wonder bar, flat, chisel Range pole 12-oz.
  • FG-Mason Concrete

    FG-Mason Concrete

    Mason Concrete Facilitator Guide Sector Construction Sub-Sector Real Estate and Infrastructure Mason Construction Occupation Concrete Masonry Reference ID: CON/Q0105, Version 1.0 NSQF Level 3 Facilitator Guide Published by ABC Company Ltd. 7, NSDC Marg, New Delhi - 110002. Email: Website: All Rights Reserved, First Edition, March 2016. ISBN 978-1-111-22222-45-7 Printed in India at XYZ Company New Delhi - 110016. Copyright © 2016 Construction Skill Development Council of India CSDC Contact Details: Address : 204, Aashirwad Complex, D-1, Green Park, New Delhi – 110016 Email : [email protected] Phone : 011 46584466 Disclaimer The information contained herein has been obtained from sources reliable to Construction Skill Development Council of India. Construction Skill Development Council of India disclaims all warranties to the accuracy, completeness or adequacy of such information. Construction Skill Development Council of India shall have no liability for errors, omissions, or inadequacies, in the information contained herein, or for interpretations thereof. Every effort has been made to trace the owners of the copyright material included in the book. The publishers would be grateful for any omissions brought to their notice for acknowledgments in future editions of the book. No entity in Construction Skill Development Council of India shall be responsible for any loss whatsoever, sustained by any person who relies on this material. The material in this publication is copyrighted. No parts of this publication may be reproduced, stored or distributed in any form or by any means either on paper or electronic media, unless authorized by the Construction Skill Development Council of India. Mason Concrete Skilling is building a better India.
  • Specifications

    Specifications

    SECTION 03 15 00 CONCRETE ACCESSORIES PART 1 - GENERAL 1.1 Work Included A. Materials, testing, and installation of waterstops and construction joints. B. Refer to Section 33 05 37 for concrete accessories around pipe penetrations. 1.2 Related Work A. Section 01 33 00: Submittal Procedures B. Section 01 40 00: Quality Requirements C. Section 01 61 00: Common Product Requirements D. Section 01 65 00: Product Delivery Requirements E. Section 01 66 00: Product Storage and Handling Requirements F. Section 01 73 00: Execution G. Section 01 74 00: Cleaning and Waste Management H. Section 03 10 00: Concrete Forming I. Section 03 20 00: Concrete Reinforcing J. Section 05 50 00: Metal Fabrications K. Section 33 05 37: Wall Pipes, Seep Rings and Penetrations 1.3 System Description A. Furnish and install concrete accessories where shown, including waterstops and construction joints materials. 1.4 Quality Assurance A. Use adequate numbers of skilled workmen trained and experienced in necessary trades and crafts and completely familiar with specified requirements and methods for proper performance of Work of this section. 1.5 References A. California Building Code (CBC) 1.6 Submittals A. Furnish the following submittals: SUBMITTAL DESCRIPTION Catalog Data Required for waterstops and other accessories per catalog data requirements. Installation Instructions Required for accessories per installation instruction requirements. Certificate of Compliance At least 24 hours before placing concrete, submit certification from each trade having embedded items in concrete to be placed stating embedded items for each trade are properly located, placed and braced. Warranty Furnish one-year warranty from date of final acceptance B.
  • Research and Applications of Concrete During World War I Vyta

    Research and Applications of Concrete During World War I Vyta

    Engineering the Permanent Material: Research and Applications of Concrete During World War I Vyta Baselice, The George Washington University In 1904, the American Society for Testing Materials produced specifications for manufacturing cement. To test consistency, researchers were instructed to first create a paste by mixing cement with water, form it into a ball with their hands, and then complete the process by “tossing [the ball] six times from one hand to the other, maintained about six inches apart.”1 Resembling cooking rather than industrial manufacturing, early practices of cement testing were deeply inaccurate and unreliable. The making of concrete was similarly inconsistent, involving a haphazard pouring and mixing of various materials whose properties were virtually unknown and quantities poorly calculated. Research and application efforts of concrete during World War I radically transformed the making and testing of this “civilizing medium.” Indeed, American manufacturers reveled in the fact that while the invention of concrete could be traced to Europe, its elevation to a material of ubiquity rested in the expert hands of American researchers.2 Employing wartime scientific advances in geological research, testing, and construction, American scientists learned to engineer the material to build almost anything. This paper argues that the wartime investments that the American government, universities, and businesses made in concrete technologies cemented American dominance of the industry and shaped global knowledge of the material. By examining the work of governmental bodies and science organizations, like the Emergency Fleet Corporation and the National Research Council, alongside that of private players, like the Edison Portland Cement Company, the narrative brings to light the conflict’s transformation of the American concrete industry and its new positioning on the global stage.
  • Investigation of Polyester Concrete Overlay Rehabilitation Strategy to Extend the Service Life of Concrete Bridge Decks

    Investigation of Polyester Concrete Overlay Rehabilitation Strategy to Extend the Service Life of Concrete Bridge Decks

    TECHNICAL REPORT DOCUMENTATION PAGE 1. Report No. 2. Government Access No. 3. Recipient’s Catalog No. CA19-2543 4. Title and Subtitle 5. Report Date Investigation of Polyester Concrete Overlay Rehabilitation October 2019 Strategy to Extend the Service Life of Concrete Bridge 6. Performing Organization Code Decks 7. Author(s) 8. Performing Organization Report Code Eli Cuelho and Jerry Stephens 9. Performing Organization Name and Address 10. Work Unit No. (TRAIS) Western Transportation Institute PO Box 174250 11. Contract or Grant No. Montana State University – Bozeman MSU G&C #4W4557 Bozeman, Montana 59717-4250 Caltrans Project #65A0490 12. Sponsoring Agency Names and Addresses 13. Type of Report and Period Covered Department of Research and Innovation Final Report California Department of Transportation July 2013– June 2016 14. Sponsoring Agency Code 15. Supplementary Notes 16. Abstract 17. Key Words 18. Distribution Statement polymer concrete overlay, concrete bridge deck, box girder, accelerated testing, 19. Security Classif. (of this report) 20. Security Classif. (of this page) 21. No. of Pages 22. Price Unclassified Unclassified 47 Western Transportation Institute i DISCLAIMER STATEMENT The contents of this report reflect the views of the authors, who are responsible for the facts and the accuracy of the data presented herein. The contents do not necessarily reflect the official views or policies of the State of California or the Federal Highway Administration. This report does not constitute a standard, specification or regulation. The United States Government does not endorse products or manufacturers. Trade and manufacturers’ names appear in this report only because they are considered essential to the object of the document.
  • Eric Molobi Booklet for the NHBRC Website

    Eric Molobi Booklet for the NHBRC Website

    Eric Molobi Housing Innovation Hub ERIC MOLOBI Innovation Hub 1618 Juventus Street Block XX Soshanguve A Pretoria Tel: 011 525 5552 CONTENTS 1. Background on Eric Molobi Housing Innovation Hub 2 3. Images and descriptions of Innovative Building Technology Houses, Conference Centre and Testing Centre: 1.1 Eric Marooi Molobi 2 3.1 IKHAYA 5 3.13 UBOMI 27 3.2 STYROX 7 3.14 POWERWALL 28 3.3 LEPA 9 3.15 A & D HOLDINGS 30 3.4 ROBUST 11 3.16 ECO INNOVATIONS 31 2. Objectives of IBT Houses, Construction Testing 3.5 MOLADI 13 3.17 SOLBIC 32 Centre and Training Centre 3 3.6 IPOZI / HOESCH 3.18 ABŌD 33 2.1 NHBRC and ABSA Housing Innovation BAUSYSTEME 14 3.19 ECODWELL 34 Competition 3 3.7 ECO BEAM 16 3.20 EPS BYGG 35 2.2 The Martha Molobi Training Centre 4 3.8 PROFICA/VELA 18 3.21 HOMECREST 36 2.3 Construction Testing Laboratory 4 3.9 FINNBUILDER 20 3.22 SA STEEL 37 3.10 SHIEBROOK 22 3.23 THE MARTHA MOLOBI 3.11 EEZYBUILT 24 TRAINING CENTRE 39 3.12 INTERCON 26 3.24 CONSTRUCTION TESTING LABORATORY 40 NHBRC Eric Molobi Housing Innovation Hub 1 1. Background on 1.1 Eric Marooi Molobi (05 June 1947 – 04 June 2006) Eric Molobi Housing The late Eric Molobi was born on 5 June 1947 in the Alexander Township. He was the second of five children Innovation Hub born to Mr Enoch Rampofeng Molobi and Mrs Welhemina Majoele Molobi. 1947 The Eric Molobi Housing Innovation Hub is a response to the challenges faced by the housing sector.