LANDSLIDE RISK MANAGEMENT AT BC HYDRO

Experience with Landslide monitoring and drainage

Tom Stewart, January 2017 PRESENTATION OVERVIEW

1. BC Hydro - Overview

2. Landslide / Reservoir Slopes Program

3. Landslide Case Histories . Downie Slide . Dutchman’s Ridge . Revelstoke

4. BC Hydro Experience – Lessons Learned

2 1. About BC Hydro

BC Hydro is a “Crown” (State-run) corporation, established in 1961, owned by the Province of and regulated by the British Columbia Utilities Commission (BCUC), an independent body. . one of North America’s leading providers of clean, renewable energy . largest electric utility in British Columbia . approximately 1.8 million customers . serves about 95 per cent of the province’s population Capacity . 43 dam sites - 11,300 megawatts (MW) installed capacity . 97% of generation based on clean, renewable . BC Hydro customers enjoy some of the world's lowest electricity rates Transmission . 18,600 kilometres of transmission lines . 57,278 kilometres of distribution lines

3 BC HYDRO – GEOGRAPHIC CONTEXT

1. Aberfeldie Dam 2. Alouette Dam 3. Bear Creek Dam 4. Buntzen Dam 5. Cheakamus Dam 6. Clayton Falls Dam 7. Clowhom Dam 8. Comox Dam 9. Coquitlam Dam (1902) (2001) 10. Coursier Dam (decommissioned) 11. Duncan Dam 12. Elko Dam 13. Elliott Dam 14. Elsie Dam 15. Falls River Dam 29. Ruskin Dam 16. Heber Diversion Dam 30. Salmon River Diversion Dam 17. Hugh 31. Seton Dam 18. John Hart Dam 32. Seven Mile Dam 19. Jordan Diversion Dam 33. Spillimacheen Dam 20. Kootenay Canal Dam 34. Stave Falls Dam 21. La Joie Dam 35. Strathcona Dam 22. Ladore Dam 36. Sugar Lake Dam 23. 37. Terzaghi Dam 24. Peace Canyon Dam 38. W.A.C. Bennett Dam 25. Puntledge Diversion Dam 39. Wahleach Dam 26. Quinsam Diversion Dam 40. Walter Hardman Dam 27. Quinsam Storage Dam 41. Whatshan Dam 28. (1985) 42. Wilsey Dam 43. Site C - current 4 2. BC Hydro – Landslide Program

Upper Peace Columbia 8 of 15 monitored landslides in this area

43 Dam sites

15 Monitored Landslides Kootenays

3000 km Reservoir Shoreline

Fraser Vancouver Valley- Island Bridge 5 3. Upper Columbia - Landslide Factors

Dutchman’s Ridge Large topographic relief (3500 m+) steep slopes (20 – 60o) Adverse geologic conditions (continuous structures: faults, foliation) Extensive precipitation 1500 – 2000 mm/yr

Downie Slide

6 3. Landslide - Drainage Case Histories

Dutchman’s Ridge

All on west side of Columbia valley All structurally controlled along foliation / shears

Downie Slide Precedent for large, rapid rock slides (2 in last 200 yrs)

Moderate seismic zone (pga ~ 0.3 g) Revelstoke Dam

7 DOWNIE SLIDE - OVERVIEW

Head scarp

• Identified 1950’s • Extensively investigated (1965-present) • 1.5 B m3 (9.5 km2 x 250m deep)

8 Downie Slide – Key Dam Safety Issues

1. Landslide generated wave - Dam over-topping – dam breach

2. Reservoir blockage

3. Dam flooding (Mica)

9

Figure 1: Key physiographic features of Downie Slide; bounding scarps and steep bulging toe Downie Slide – Revelstoke Dam

 Dam Approval linked to Downie Stabilization  Extensive Public Consultation

Figure 1: Key physiographic features of Downie Slide; bounding scarps and steep bulging toe and review process  Drainage selected  “to more than offset filling of reservoir” 10 Downie Slide – Geologic Section  Detailed geologic model required for drainage design

Head scarp

• Identified 1950’s • Extensively drilled 1968-92 • 1.5 B m3 • Slowly moving (3 to 200 mm/yr) o Drilling - Monitoring installed 20-25 downslope dip • 1974-82 drainage  Geology  Mica schist/gneiss; continuous structures • 2008 drainage upgrades  Groundwater  Multiple water levels • Extensive ADAS  Movement  Slowly moving (3 to 200 mm/yr) • DS Issues: Overtopping wave / reservoir blockage / impact to reservoir users (on 2 main surfaces) 11 Downie Slide – Drainage Program

Head scarp

Drainage Adit

 Adits - constructed using “Observational” approach (piezometers)  Completed in three stages 1974-1977-1981 12 Downie Slide – Drainage Program

Head scarp

• Identified 1950’s • Extensively drilled 1968-92 • 1.5 B m3 • Slowly moving (3 to 200 mm/yr) Drainage Adit • 1974-82 drainage • 2008 Adits drainage primarily upgrades in slide mass • Extensive 2.45 kmADAS of adit • DS Issues:24,000 Overtopping m of drain wave holes / reservoir blockage / impact to reservoir users 13 Downie Slide – Drainage Adits

JHT

Conventional drill and blast; “horseshoe” shape; extensively supported 14 Downie Slide - Groundwater Response

2700 2700 2675 2650 2625 2600 2575 2550 2525 2500 -Rsp Test 2500

)

t

)

e

t

2475 f

e

(

f

(

-Rsp Test

n

n

2450 o

i

o

t

i

t S49 P1/P2 a

a 2425 v

v

e

7 1

l e -Rsp Test connected to ADAS Nov 2007

l

7 8

E

t t E 2400

c

s s

i

r

n n

c

t

i

o o

r

2375 e

t

C C

e

m

n n o

m 2350 i i

z

o

a a

e

r r

t

z

i

r

e

d

D D

P i 2325

a

t n

P

S E

P2 above Lower Shear 2300 l l 2300

l l

i i

1 F F

2275 s s

e e

2250 R R 2225 P1 below Lower Shear 2200 2175 3 Drainhole drilling Nov 2007 - Jun 2008 2150 2125 2 2100 2100

6 7 8 9 0 1 2 3 4 5 6 7 8 9 0 1 2 3 4 5 6 7 8 9 0 1 2 3 4 5 6 7 8 9 0 1 2 3 4 5 6 7

7 7 7 7 8 8 8 8 8 8 8 8 8 8 9 9 9 9 9 9 9 9 9 9 0 0 0 0 0 0 0 0 0 0 1 1 1 1 1 1 1 1

9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2

Y1 Legend Y2 Legend DHS49P1A DHS25P1 DHS49P1 DOWNIE SLIDE

STANDPIPE PIEZOMETERS (MANUAL) North Knob Area S25 P1 and P2

TWSPZ77 January 27, 2017

1. Significant drainage effects – up to 100 m pressure reductions 2. Met initial objective but increasing pressure trends observed 3. Additional drainage required (2007-08) 15 Downie Slide - Groundwater Response

2500 2500 2490 2490 2480 2480

2470 2470 S

2460 A 2460

2450 D 2450

S42 Sensor tip elevations: A 2440 2440 P5 2286.6 n

2430 O 2430 P4 2214.6' 2420 2420 2410 P3 2159.6' 2410 2400 P2 2160.1 2400 2390 P1 2089.6' 2390 2380 2380 2370 2370

) )

t 2360 2360 t

e e

e 2350 2350 e

f f

( (

2340 2340

n n

o 2330 2330 o

i i t 2320 2320 t a P4 above Lower Shear a v 2310 2310 v

e e

l l

E 2300 2300 E

c 2290 2290 c

i i

r r

t 2280 2280 t e 2270 2265' P3 Stability Check Level 2270 e

m m

o 2260 2260 o

z z

e e i 2250 2236' P3 Base Level 2250 i

P 2240 2240 P 2230 1 2 P3 in Lower Shear 2230 2220 1 2220

8

t 2210 t 2210

r

s

d

a

2200 n 2200

t n

o

S E

2190 2190

l l

C

l l

2180 i i 2180

n

F F

i 2177' P2 Base Level 2170 a 2170

s s

r

e e

2160 D 2160 2150 R R 2150 2140 2140 2130 2130 2120 P1 / P2 below Lower Shear 2120 2110 2110 2100 3 2100

1 2 3 4 5 6 7 8 9 0 1 2 3 4 5 6 7 8 9 0 1 2 3 4 5 6 7 8 9 0 1 2 3 4 5 6 7

8 8 8 8 8 8 8 8 8 9 9 9 9 9 9 9 9 9 9 0 0 0 0 0 0 0 0 0 0 1 1 1 1 1 1 1 1

9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2

Y1 Legend Y2 Legend DHS42P5 DHS42P5A DHS42P4 DHS42P4A DOWNIE SLIDE DHS42P3 DHS42P3A DHS42P2 DHS42P2A STANDPIPE PIEZOMETERS DHS42P1 DHS42P1A South Scarp area near toe S42 P1 to P5 TWSPZ18 January 17, 2017

1. Most piezometers encountered “perched” water levels 2. Water typically perched above the 2 active zones 3. Piezometers below slide base could indicate “dry” conditions 16 Downie Slide - Displacement

3 (2 mm/yr) Slope displacement response to drainage, measured across lower slide plane:

1. Slight reduction following drainage (5 > 3 mm/yr)

2. Increase during reservoir filling 1 (10 mm/yr) 2 3. Relatively consistent post reservoir fill ( 2 – 3 mm/yr)

17 Downie Slide – Summary

1. Groundwater levels reduced to below pre-reservoir levels

2. Displacement rates are similar or less than pre-reservoir conditions 3. Stability increased by ~ 7% (FOS) 4. Water License Requirement – must maintain system

18 BC HYDRO LANDSLIDES – Mica Dam

LCS DR

Mica Dam - 250 m high earthfill dam

The most upstream of 14 dams on

Major upstream landslides

19 Dutchman’s Ridge Potential Slide

• Identified mid-1960’s (airphotos)

• 1969 drilling

• 30 M m3 • Physical wave model studies (50 m+ waves)

• Dam construction revised to accommodate slide waves

• Decision not

to drain 20 Dutchman’s Ridge - Displacement

1. Pre-reservoir – negligible displacement detected

2. Reservoir filling (190 m) – initiated movements of 25 mm/yr 3 3. Slope displacement acceleration resulted in decision to further investigate 2

1

Slope displacement response to reservoir filling (pre-drainage) 21 Dutchman’s Ridge – Investigations

Geological Model (Updated): • Well defined continuous basal sliding surface • Depth of sliding – 75 to 150 m Slide Base • Movements of up to 200mm occurred during reservoir filling • 115 M m3 (~4x original)

Drainage Adit

Analyses concluded: • Raising of reservoir reduced stability by ~ 10% • Large, first time slide possible

• Remediation preferred – drainage option selected 22 Dutchman’s Ridge Slide - Reservoir • 1969 estimate of slide volume 30 M m3

• Post - Outline of currently active slide reservoir re- evaluation (1982)

• Slide size reassessed 115 M m3

• Additional analyses (larger wave) Drainage Adit • Decision to install drainage system 23 Relevance of Dutchman’s Ridge – Aknes

Similarities: • Size • Geology • Setting Aknes • Landslide wave hazard

Dutchman’s Ridge

British Columbia 24 Dutchman’s Ridge – Drainage Design

• Extensive monitoring system installed (350 measurement ports):  To identify where water pressures could be drained  To evaluate effectiveness of drainage system 25 Dutchman’s Ridge – Drilling Observations

Piezo profiling during drilling

Slide Base Open hole measurements could be dry below slide

Most drill holes showed “perched” water levels Testing allowed optimum design of piezo installation 26 Dutchman’s Ridge – Piezo Testing

Piezometric testing during drilling Custom “through-the-drill-string” set up Reliable – no issues with getting stuck Data immediately available

27 Dutchman’s Ridge – Drainage Layout

982 m of Adit installed (1986-88) ; 20,000 m of drainholes 28 Dutchman’ Ridge – Groundwater TH

940

930

920

Drainage - Construction 910

) 900

s

e

r

t

e

M

(

n 890

o

i

t

a

v

e

l

E 880

870 Potential Slide Base - 864.4 m

860 MP’s dry

850

840

6 7 8 9 0 1 2 3 4 5 6 7 8 9 0 1 2 3 4 5 6 7 8 9 0 1 2 3 4 5 6 7

8 8 8 8 9 9 9 9 9 9 9 9 9 9 0 0 0 0 0 0 0 0 0 0 1 1 1 1 1 1 1 1

9 9 9 9 9 9 9 9 9 9 9 9 9 9 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

1 1 1 1 1 1 1 1 1 1 1 1 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2

8633MP37 8633MP35 8633MP33 MICA RESERVOIR SLOPES 8629MP31 8633MP29 Dutchman's Ridge 8633MP27 Multi-Point Piezometers 86-33A Ports 27-37 (2 of3) PBS DMRPZ27 January 18, 2017 1. Large portions of potential slide fully drained. 2. Up to 100 m pressure drawdown – lasting effect 29 Dutchman’s Ridge - Displacement

Inclinometer – Across Slide Base

Pre-drainage Post-drainage 0.5 mm/yr ~15 mm/yr

Slope displacement response to drainage - rate reduced by > order of magnitude30 Dutchman’s Ridge – Adit Conditions

Flow rates have reduced but pressures have remained “fully drained” 31 Dutchman’s Ridge – Compared to Downie

Slide Base

Drainage Adit

 Smaller slide mass - easier to effectively drain  Single sliding plane (DMR) vs two + planes (Downie)  Slightly better rock quality – less previous slide displacement  Adit below slide in competent rock  Nearly “fully” drained condition – effectively halted movements 32 Revelstoke Dam – Marble Shear Block

• 175 m high concrete gravity; with earthfill wing dam

• 1985 dam completion

• Slope instability on right bank (Marble Shear Block) 200,000 m3

• Potential to undermine spillway; block tailrace

33 Marble Shear Block - Geology

1. Quartzite / Mica Gneiss

2. Persistent planes of Pre-drainage Post-drainage weakness (foliation / shears) dipping down slope 13 mm/yr 3. Considerable groundwater

Risk Management 1. Risk to spillway / discharge facilities considered unacceptable

2. Drainage selected as remedial option

34 Marble Shear Block – Drainage

1. Spillway Structure

2. Sliding Plane

3. Adit (40 m long)

4. With ~1000 m of drainholes

35 Marble Shear Block – Groundwater TH

1650

g

n

i

l

l 1640 i

r

Start of MSB Drainage Adit d

and Drainhole Drilling 4 1630 1 Aug 1998 0

2 1620 Falling Head Test 1610

1600

1590 2

1

)

t

0

f

2

(

y

n 1580 a

o

i M

t

&

a

v

b

e e 1570

l

F

E

,

t

79AT25 Threshold 1563'

i

c

d

i

a

r

t 1560

B

e

S

m

M

o

1550 n

z

i

e

g

i Tip 1544'

n

i

P

1540 m

a

e

r

1 d

n

1530 a

g

n

i

n

1520 a

e 79AT24 Threshold 1513' l

c

n

i

a

1510 r

D 1500

1490 2 Tip 1483' 1480

8 9 0 1 2 3 4 5 6 7 8 9 0 1 2 3 4 5 6 7 8 9 0 1 2 3 4 5 6 7 8 9 0 1 2 3 4 5

7 7 8 8 8 8 8 8 8 8 8 8 9 9 9 9 9 9 9 9 9 9 0 0 0 0 0 0 0 0 0 0 1 1 1 1 1 1

9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2

79AT24 79AT24A 79AT25A REVELSTOKE ROCKSLOPES 79AT25D 79AT25 Marble Shear Block - Piezometric Pressures Piezometers Near Section C (6+35) Threshold Levels TWSPZ56 August 19, 2015 1. Significant pressure reductions (up to 15 m) from drainage 2. Remedial effects are persisting over 15 years – lasting results 36 Marble Shear Block - Displacement

1. Minor Inclinometer – slide plane displacement prior to 3 drainage 2 installation (2mm/yr) 1 2. Drainage 1998-99

3. Slope displacement effectively stopped following drainage

37 LANDSLIDE REMEDIATION THROUGH DRAINAGE Lessons Learned – Summary: 1. Drainage has been effective – objectives achieved

940  Dewatering 930 /depressurizing 920 Drainage - Construction 910  Displacement ) 900

s

e

r

t

e

M

(

reduced/stopped n 890

o

i

t

a

v

e

l  Improved stability E 880

870 (5-10% FOS) Potential Slide Base - 864.4 m

860

850

840

6 7 8 9 0 1 2 3 4 5 6 7 8 9 0 1 2 3 4 5 6 7 8 9 0 1 2 3 4 5 6 7

8 8 8 8 9 9 9 9 9 9 9 9 9 9 0 0 0 0 0 0 0 0 0 0 1 1 1 1 1 1 1 1

9 9 9 9 9 9 9 9 9 9 9 9 9 9 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

1 1 1 1 1 1 1 1 1 1 1 1 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2

8633MP37 8633MP35 8633MP33 MICA RESERVOIR SLOPES 8629MP31 8633MP29 Dutchman's Ridge 8633MP27 Multi-Point Piezometers 86-33A Ports 27-37 (2 of3) PBS DMRPZ27 January 18, 2017

Tom Stewart, January 2017 LANDSLIDE REMEDIATION THROUGH DRAINAGE Lessons Learned – Summary: 2. Well positioned monitoring system required (plan/evaluate) Need to understand where water is located Detailed site investigation and monitoring required Needs to be installed before drainage

Tom Stewart, August 2015 LANDSLIDE REMEDIATION THROUGH DRAINAGE Lessons Learned – Summary: 3. Well positioned monitoring system required (plan/evaluate) 1. Need to conduct in situ testing during drilling to understand where water is located – 2. Identifies perched zones and downhole gradients that are otherwise missed 3. Allows planning for permanent piezometric monitoring. 4. Use of multi-port type piezometers highly effective (i.e. “Westbay” type). LANDSLIDE REMEDIATION THROUGH DRAINAGE Lessons Learned – Summary: 4. Drainage response typically confined to treated area only overage installation network spatially

Tom Stewart, August 2015 LANDSLIDE REMEDIATION THROUGH DRAINAGE Lessons Learned – Summary: 5. Plan for maintenance – successful results come from long- term commitment

• Lighting, ventilation, power supply

• Drainhole replacement (cleaning ineffective)

• Requirement to install additional monitoring

• Rock support

Tom Stewart, January 2017 LANDSLIDE REMEDIATION THROUGH DRAINAGE

Questions / Discussion ?

Tom Stewart, January 2017 BRITISH COLUMBIA – NORWEGIAN CONTEXT

British Columbia Norway 944,735 sq. km 304,282 sq. km 1900 km long 1347 km long 505 km wide 304 km wide

23. Mica Dam Mountainous 28. Revelstoke Dam Mountainous Lots of snow Lots of snow Lots of fjords Lots of fjords

3% of population of Norwegian descent

44