DEPARTMENT OF THE INTERIOR PROGRAM for the BUREAU OF RECLAMATION

ARIZONA

CONSTRUCTION PROGRAM

Modifications and Additions to Completed Facilities (---)

Fiscal Year 1983 Appropriation •••••••••• • ••••• ••• •••••••• • ••••• •••• •• $ 990,000 Fiscal Year 1984 Appropriation Request ••••••••••••••••••••••••••••••• $1,056,000

In Arizona, $191,000 will be needed, $361,000 in Colorado, $468,000 in New Mexico, and $36,000 in Utah to carry out the program. This program provides design of a grouting program for the abutments of Navajo . This program also provides for minor completion of additions to substantially completed facilities and for procurement of permanent operation equipment. \

COLORADO

CONSTRUCTION PROGRAM

Dallas Creek (Colorado)

Fiscal Year 1983 Appropriation ••••••••••••••••••••••••••••••••••••••• $18,561,000 Fiscal Year 1984 Appropriation Request ••••••••••••• • ••••••••••••••••• $16,200,000

Construction on Ridgway Dam, Stage II will continue; a contract will be awarded for reservoir clearing.

Dolores Project (Colorado)

Fiscal Year 1983 Appropriation ••••••••••••••••.•••••••••••••••••••••• $40,120,000 Fiscal Year 1984 Appropriation Request ••••••••••••••••••••••••••••••• $37,200,000

The program provides for completion of construction on McPhee Dam, Dolores Tunnel and Canal, Dolores S~~age Plant, Glade, and Ormiston Point.

Construction on the Great Cut Pumping Plant will continue. Archeological salvage will also keep in operation. Contracts will be awarded for the Dolores, Norwoodt May Canyon Roads, Lone Dome, Williams Draw Road, Dove Creek Canal Reach I, Dolores Landfill and Protective Dike, and Great Cut Pumping Plant Switchyard and Trans­ mission Lines. COLORADO

CONSTRUCTION PROGRAM - 2

Colorado River Basin Salinity Control Projects, Title II, Grand Valley Unit (Colorado)

Fiscal Year 1983 Appropriation •••••••••••••••••••••• • ••••••••••••• $8,860,000 Fiscal Year 1984 Appropriation Request ••••••••••••••••••••• -••••••• $3,915,000

Construction will be completed on moss and trash screens on the Government Highline Canal and Stage I of the Government Highline Laterals. Purchase of service facilities equipment, and preconstruction activities on other features will continue.

Colorado River Basin Salinity Control Projects, Title II, Paradox Valley Unit (Colorado)

Fiscal Year 1983 Appropriation ••••••••••• • ••• • ••••••••••••••••••• ~$3,301,000 Fiscal Year 1984 Appropr\ ation Request ••••••• • •••• • •••••••• 1••••••• $6,068,000 A contract will be awarded to drill and construct a deep brine disposal well. Preconstruction activities on other features will continue.

Grand- Valley Project, Orchard Mesa Division (Colorado)

Fiscal Year 1983 Appropriation •••••••••••••••••••• • ••••••••••••••• $2,150,000 Fiscal Year 1984 Appropriation Request •••••••••••••••••••••••••••• $ 348,000

Construction will be completed on Orchard Mesa Structure Replacement and on rehabilitation of Orchard Mesa Pumping Plant.

Modifications and Additions to Completed Facilities (Arizona-Colorado-New Mexico-Utah)

Fiscal Year 1983 Appropriation •••••••••••••••••••••••••••••••••••• $ 990,000 Fiscal Year 1984 Appropriation Request •••••••••••••••••••••••••••• $1,056,000

In Arizona $191,000 will be needed, $361,000 in Colorado, $468,000 in New Mexico, and $36,000 in Utah. This program provides for design of remedial grouting program of the abutments of Navajo Dam. This program also provides for minor completion on additions to substantially complete facilities and for procurement of permanent operation equipment.

Recreational and Fish and Wildlife Facilities, Upper Colorado River Storage Project (Colorado)

Fiscal Year 1983 Appropriation ••••••••••••••••••••••••• • •••••••••• $7,441,000 Fiscal Year 1984 Appropriation Request •••••••••••••••••••••••••••• $5,596,000 COLORADO

CONSTRUCTION PROGRAM - 3

This budget request wi ll provide for the completion of construction of recreati on facilities on the Wayne N. Aspinall Unit and the boat ramps at McPhee Reservoir, Dolores Project. Construction will continue on the r ecreational portion of Ridgway Dam construction on the Dallas Creek Participating Project.

Uncompahgre Project (Colorado)

Fiscal Year 1983 Appropriation ••••••••• • • •• •• •• •••••• • •• •• •• • • • • • • • • • $1,128,000 Fiscal Year 1984 Appropriation Request • • •••• ••• ••• • • • •••• •• • •• •• • • • • • $ 650,000

Co~struction will continue on the rehabilitation of the diversion works and project canals and conduits. \

NEW MEXICO

CONSTRUCTION PROGRAM

Modifications and Additions to Completed Facilities (Arizona-Colorado-New Mexico-Utah)

Fiscal Year 1983 Appropriation • ••• ••••• • ••••••• •• •••• • •••••••• • • • • •• • $ 990,000 Fi scal Year 1984 Appropriation Request ••••••• • • •• ••••••• • •••••• • •• • • • $1,056,000

In Arizona, $191,000 will be needed, $361,000 in Colorado, $468,000 in New Mexico, and $36,000 in Utah. The program provides design of remedial grouting program of the abutments of Navajo Dam. This program also provides for minor completion on additions to substantially completed facilities and for procurement of permanent operation equipment. UTAH

CONSTRUCTION PROGRAM

Central Utah Project - Bonneville Unit (Utah)

Fiscal Year 1983 Appropriation ••••••••••••••••••••••.••••••••••••••••• $ 67,955,000 Fiscal Year 1984 Appropriation Request •••••••••••••••••••••••••••••••• $101,607,000

Construction will be completed on Strawberry Tunnel Inlet Rehabilitation, Currant Creek Road Gravel Source, Utah Projects Office Complex, Duchesne Office and Trailerhouse Replacement. Work will continue on Aggregate Processing for Upper Stillwater Dam, Stillwater Tunnel and Jordan Aqueduct - Reach 4 and Alpine Aqueduct - Reach 3. Contracts will be awarded for Upper Stillwater Dam - Stage II and Pipeline, Taylor Canal Area Drains, North Fork Siphon, Soldier Creek Remedial Work on Right Abutment, Soldier Creek Dam Rip-rap Replacement, Relocate Highways 40 and 189 around Jordanelle Reservoir, Exploratory Shaft for Fifth Water Powerplant, the Diamond Fork Road System, and Garage and Storage Areas for Employees, Duchesne Camp. Also, land purchases for Jordanelle Dam and Reservoir will be mitrated. \ - Jensen Unit (Utah)

Fiscal Year 1983 Appropriation •••••••••••••••••••••••••••••••••••••••• $ 3,616,000 Fiscal Year 1984 Appropriation Request •••••••••••••• • ••••••••••••••••• $ 1,725,000

Construction will be completed on Jensen Drains. Work will continue on Tyzack Aqueduct - Reach 2. Acquisition of miscellaneous laboratory and work equipment will continue. \ Central Utah Project - Uintah Unit (Utah)

Fiscal Year 1983 Appropriation •••••••••••••••••••••••••••••••••••••••• $ 500,000 Fiscal Year 1984 Appropriation Request •••• • , •• • •• • •• ; ••••••••••••••••• $ 550,000

The program provides for continuation of preconstruction activities including preparation of environmental statement, designs and estimates, and definite plan report.

Central Utah Project - Upalco Unit (Utah)

Fiscal Year 1983 Appropriation ••••••••••••••.•••••••••••••••••••••• ••• $ 1,000,000 Fiscal Year 1984 Appropriation Request ••.•••••••••••••••••••••••••• •• • $ 2,015,000

Land will be acquired for Taskeech Dam and Reservoir and for Taskeech Service Canal and Canal Rehabilitation. Preconstruction activities will continue on other features. UTAH

CONSTRUCTION PROGRAM - 2

Modifications and Additions to Completed Facilities (Arizona-Colorado-New Mexico-Utah)

Fiscal Year 1983 Appropriation ••• • ••••••••••••••••••••••••••••••••• $ 990,000 Fiscal Year 1984 Appropriation Request ••••••••••••••••••••••••••••• $1,056,000

In Arizona, $191,000 will be needed, $361,000 in Colorado, $468,000 in New Mexico, and $36,000 in Utah. This program provides for design of remedial grouting of the abutments of Navajo Dam. This program also provides for minor completion on additions to substantially completed facilities and for procurement of permanent operation equipment.

Recreational and Fish and Wildlife Facilities, Upper Colorado River Storage Project (Utah) i Fiscal Year 1983 Appropriation •••••••••••••••••••••.••••••••••••••• $1,810,000 Fiscal Year 1984 Approprfation Request •••••••••• • •••••••••••••••••• $ 793,000

In 1984 these funds will provide for continued construction of recreation facilities at .

Strawberry Valley Project (Utah)

Fiscal Year 1983 Appropriation ••••••••••••• •• ••• • •••••••••••••••• • • $ 300,000 Fiscal Year 1984 Appropriation Request •••••••••••.•••••••.••••••••• $ 664,000

Program provides for award of contract for replacement of the Diversion Dam.

Weber Basin Project (Utah)

Fiscal Year 1983 Appropriation ••••••• • •••• , •• ,,., •••• ,, •• ,.,., ••• ,.$ 300,000 Fiscal Year 1984 Appropriation Request •••••••.•••••••••••••• • •••••• $ 350,000

Preconstruction activities for the rehabilitation of Watkins Dam will be initiated.

CONSTRUCTION PROGRAM

Eden Project (Wyoming) Fiscal Year 1983 Appropriation •••••••••••••••••••••••••••••••••••• $ -o- Fiscal Year 1984 Appropriation Request •• • • •••••• • • ••••••••• ••••••• $ 300,000

Provides for initiation of design and award of contract for modification of the spillway structure at Big Sandy Dam.

Recreational and Fish and Wildlife Facilities, Upper Colorado River Storage Project (Wyoming)

Fiscal Year 1983 Appropriation ••••••••• ••• ••••••••••••• •••• •••• • •• $1,320,000 Fiscal Year 1984 Appropriation Request •••••••••••••••••••••••••••• $1,227,000 I The program provides for continuation of development of National Wildlife Refuge, Seedskadee Participating Project.

Lyman Project (Wyoming)

Fiscal Year 1983 Appropriation •••••••••••••••••••••••••••••••••••• $ -0- Fiscal Year 1984 Appropriation Request •••••••••••••• • ••••••••• • • •• $ 251,000

A contract will be awarded to perform remedial work on the Stilling Basin at Meeks Cabin Dam.

Seedskadee Project (Wyoming)

Fiscal Year 1983 Appropriation ••••••.••••••••••••••••••••••••••••• $ Fiscal Year 1984 Appropriation Request •••••••••••••••••••••••••••• $ 500,000

A contract will be awarded to perform remedial grouting work at Fontenelle Dam.