Initial Environment Examination

Project Number: 40648-033 June 2014

IND: Infrastructure Development Investment Program for Tourism – Tranche 2

Submitted by

Department of Tourism, Government of

This report has been submitted to ADB by the Government of Uttarakhand, Dehradun and is made publicly available in accordance with ADB’s public communications policy (2011). It does not necessarily reflect the views of ADB.

Environmental Assessment Document

Revised Initial Environmental Examination (IEE) Loan No. 2833 IND June 2014

Infrastructure Development Investment Program for Tourism, Uttarakhand

Subproject – Landscaping, Floriculture and Tourism/Pilgrim Infrastructure Development Works at Mostmanu Temple Complex

Prepared by the Government of Uttarakhand for the Asian Development Bank

This IEE is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature.

Initial Environmental Examination (IEE) Landscaping, floriculture and tourism/pilgrim infrastructure development works at Mostmanu temple complex

ABBREVIATIONS

ADB - Asian Development Bank BOD - Biological Oxygen Demand BOQ - Bill of Quantities CO - Carbon monoxide CPCB - Central Pollution Control Board DSC - Design and Supervision Consultant EA - Executing Agency EAC - Expert Appraisal Committee EARF - Environment Assessment and Review Framework EIA - Environmental Impact Assessment EMP - Environment Management Plan ES - Environmental Specialist GC - General Conditions GoI - Government of GoUK - Government of Uttarakhand IDIPT - Infrastructure Development Investment Program for Tourism IEE - Initial environmental examination INR - Indian Rupee IPIU - Investment Program Implementation Unit IPMU - Investment Program Management Unit KMVN Kumaon Mandal Vikas Nigam PUC - Pollution Under Control Certificate MLD - Million Liters per day MoEF - Ministry of Environment and Forests MFF - Multi- Trench Financing Facility NGO - Non-Governmental Organization NOx - Nitrogen oxide PD - Project Director PIU - Project Implementation Unit PM - Particulate Matter PMU - Project Management Unit RP - Resettlement Plan RPM - Respirable Particulate Matter SC - Scheduled Castes SEAC - State Expert Appraisal Committee SO2 - Sulphur dioxide SPM - Suspended Particulate Matter SPS - Safeguards Policy Statement ST - Scheduled Tribe

Initial Environmental Examination (IEE) Landscaping, floriculture and tourism/pilgrim infrastructure development works at Mostmanu temple complex CONTENTS

S. Chapter Page No. No. EXECUTIVE SUMMARY 5 I Introduction 8 A. Background 8 B. Purpose of the IEE 9 C. Environmental Regulatory Compliance 10 D. Report Structure 11

II Description of Project Components 12 A. Project Overview 12 B. Present Status 12 C. Project Components 13 D. Project Implementation Schedule 13

III Description of Existing Environment 14 A. Environmental Profile – Physical Resources 14 B. Ecological Resources and Biodiversity 16 C. Economic Resources 18 D. Social and Cultural Resources 19

IV Environmental Impacts and Mitigation Measures 22 A. Land Acquisition and Resettlement 22 B. Environmental Impacts 22

V Environmental Management Plan (EMP) 34 A. Institutional Arrangements 34 B. Environment Management 35 C. Environmental Monitoring Plan 44 D. Capacity Building 45 E. Environmental Budget 47 F. Environmental Monitoring and Reporting 49

VI. Public Consultation and Information Disclosure 50 A. Process For Consultation Followed 50 B. Future Consultation and Information Disclosure 51 C. Grievance Redress Mechanism 52

VII Findings & Recommendations 54

VIII Conclusions 54

Initial Environmental Examination (IEE) Landscaping, floriculture and tourism/pilgrim infrastructure development works at Mostmanu temple complex List of Tables

Table Description Page No. No.

1. Environmental Regulatory Compliance 10 2. Ambient Air Quality (24 hours basis) 18 3. Ambient Noise Quality 18 4. Demographic profile of Project Area 19 5. Basic Amenities of Project Area 20 6. Summary of Environmental Impacts and Mitigation Measures 29 7. Generic EMP to guide the contractor 37 8. Environmental Monitoring Plan 44 9. Training Modules for Environmental Management Consultations 46 10. Environmental Budget 48 11. Consultations with Stakeholders 50

List of Annexures

Annexure Description Page no. 1. Rapid Environmental Assessment (REA) Checklist 55-59 2. Compliance with sub project selection criteria 60-64 3. Location Map 65 4. Photographs of Mostmanu Temple Project Area 66 5. NOC's from Stake Holders 67-71 6. Sub project Monitoring Committee 72 7. Ambient Air Quality, Noise Level Monitoring Report 73-76 8. Public Consultation Photographs 77 9. Public Consultations 78-95 10 Public Disclosure through newspapers 96-97

Initial Environmental Examination (IEE) Landscaping, floriculture and tourism/pilgrim infrastructure development works at Mostmanu temple complex

EXECUTIVE SUMMARY 1. The Infrastructure Development Investment Program for Tourism (IDIPT) envisages an environmentally and culturally sustainable and socially inclusive tourism development, in the project states of Himachal Pradesh, Punjab, Tamil Nadu and Uttarakhand, delivered through a multi-tranche financing facility (MFF) modality. Project 2 includes the states of Uttarakhand and Tamil Nadu. 2. The Mostamanu temple is located at Chandak named after Godess Chandika. The Chandika is a hill 8 km north west of town. Access to the hill is also through a three km pedestrian trail from Pithoragarh. Chandak hill has scenic and pilgrimage values and great potential to develop as an aero sports activity destination. The hill of Chandak provides a panoramic view of Himalayan snow peaks extending from Trishul-Nanda Devi and Panchchuli Group to Mount Appi of Nepal. This hill also offers beautiful view of Svalek valley. 3. This Initial Environmental Examination (IEE) has been prepared for the sub project "Landscaping, floriculture and tourism/pilgrim infrastructure development works at Mostamanu temple complex" Utttarakhand under Tranche 2. The IEE has been prepared based on the primary, secondary data, field visits, reconnaissance survey and public and stake holder's consultations. 4. The place is visited throughout the year by local community and tourists which comes to Pithoragarh town. It is a favourite picnic spot for the people of Pithoragarh town and during weekends and national holidays, there is heavy rush in this area. Therefore the Mostamanu temple is a historic institution of substantial regional significance. The annual fair held on the occasion of Nag Panchami in autumn attracts a large number of people from around the region. 5. This subproject aims at launching a focused programme of reinforcing the existing linkages of the temple site to the Pithoragarh-Chandak trekking trail segment and sustainably develop the site to enhance its historic and religious values and supporting the age-old pilgrimage and cultural practices. 6. The subproject is needed to strengthen the tourism potential of this area as this site is very popular among local visitors, nature lovers, 7. The proposed subproject mainly comprises of  Ugradation of Existing Children’s Park  Landscaping and Environmental Improvement of temple complex-  Demolition of inappropriate structures  Provisions for paved pedestrian access and pathway to the temple with adequate plantation  Development of view points around/along the temple and parking facility near temple complex.  Provision of Visitor Amenities and facilities  Proposal for Toilet (better liquid and solid waste management and sanitation) and  Water facilities(underground water storage facility with drinking water points),  Amphitheater up-gradation, proposal for large congregations (for camping, cooking and set up for temporary shops),

5

Initial Environmental Examination (IEE) Landscaping, floriculture and tourism/pilgrim infrastructure development works at Mostmanu temple complex

 Illumination of temple and surroundings  Provision of Street furniture- Design proposals for benches, weather shelters, boundary wall upgradation, dust-bins etc  Landscaping and Beautification of Dunga Bhool., village DPR  Environmental Up-gradation of the Palquin trail: Including soft paving, plantations, treatment of pause and vantage points, illumination  Provision of Signage and Street furniture along the Palquin route. 8. Construction of all elements will begin in the Second quarter of the year 2014, and work will be completed in the third quarter of 2015. Total implementation period is 14 months. 9. The project 'Landscaping, Floriculture and Tourism/Pilgrim Infrastructure Development Works at Mostamanu Temple Complex' is located in the Chandak hill of Pithoragarh, about 8 km from Pithoragarh town which is the district head quarters of the same name. The district forms the north-eastern part of the Kumaon Division and lies between Lat. 29º27´N. and 30º49´N. and Long. 79º50´E. and 81º3’E., the length from north to south, being about 151 Km. at its maximum, and the breadth from east to west, reaching its maximum at about 119 Km. It is bounded by Tibet on the north, Nepal on the east, district Almora on the south and the districts Almora and Chamoli on the west. 10. The Mostmanu temple is located uphill on Chandak on the northern part of the Soar valley. The Himalayan ranges and the widely extending Soar valley are visible from Chandak and this hill provides a scenic trek to visitors. The defunct Magnesite mining factory is located on this hill. The Power Grid Corporation of India is located adjacent to the Mostmanu temple. 11. The Mostmanu Temple is located in Chandak. There are 15 revenue villages situated in the surroundings of Chandak within a periphery of 8 kms. The population of these villages is about 3249 with 659 households, mainly Brahmins, Rajputs and scheduled castes. The people of these villages are dependent on religious tourism based activities for their livelihoods. There is potential of tourism development in the area which will provide more employment to the local youth and improve the livelihoods security of local community. Due to favorable climate, there is scope of floriculture, vegetable cultivation and dairy in the area.

12. The subproject has been categorized as B as per the ADB‘s Safeguard Policy Statement (2009). The subproject is not covered in the ambit of the EIA notification 2006 and EIA Act 2009. As a result, the categorization, and the subsequent environmental assessment and clearance either from the state or the central Government is not required. 13. As part of IEE, a detailed assessment of impacts due to location, design and pre- construction, construction, operation and maintenance have been made. But mitigation measures will be applied to minimize these impacts. 14. An Environmental Management plan (EMP) outlining the specific environmental measures to be adhered to during various phases of implementation of the subproject has been prepared. The subproject will conform to all Government regulations, policies, and standards, as well as Asian Development Bank‘s Safeguard Policy Statement (2009) 15. A stakeholder discussion has been conducted. The project design incorporates the views of primary and secondary stakeholders including local communities, temple committee and local officials who were all meaningfully consulted during IEE and project

6

Initial Environmental Examination (IEE) Landscaping, floriculture and tourism/pilgrim infrastructure development works at Mostmanu temple complex

preparation 16. The environmental impacts of the project are therefore not significant and at Category B level, as per ADB's Safeguards Policy Statement. The specific measures stated in the EMP will address all adverse environmental impacts due to the subproject. Impacts are readily mitigated through careful siting, specific selection criteria for procuring contractors with demonstrated experience; execution of proven mitigation measures during the design; and adoption of good engineering practices during construction and implementation. A detailed monitoring plan prepared as part of this IEE will further mitigate negative environmental impacts during implementation 17. A Project Management Unit (PMU) is established in Dehradun for the overall project management and Project Implementation Units (PIU) is also established at Bhimtal. A Safeguards Specialist within the PMU will be responsible for implementation of the resettlement and environmental safeguard provisions. Project Management Consultants (PMC) and Design and Supervision Consultants (DSC) provide assistance to the PMU/PIUs in project implementation. Within the PMC team a Safeguards Specialist will provide overall management of environmental and social issues, and will provide technical support to the PMU including implementation of the environmental and resettlement issues according to ADB’s requirements, and assist in monitoring impacts and mitigation measures associated with sub- projects. The Safeguards Specialist of the DSC team will be responsible for preparation of the Environmental Assessment documents in line with the EARF and supervise the implementation of the EMP provisions in the various sub-projects. 18. The DSC Safeguards Specialist will support environmental management functions including updating sub-project IEEs in respect to environmental management plans, assisting in preparing IEEs, and assist in monitoring impacts and mitigation measures associated with sub- projects. He/she will be required to include mitigation measures in designs where appropriate, and to specify other measures in construction contracts. Contractors will be required by their contracts to implement all specified mitigation, monitoring, and reporting assigned to contractors as presented in sub-project IEE. 19. The subproject is unlikely to cause significant adverse impacts. The potential adverse impacts that are associated with design, construction, and operation can be mitigated to standard levels without difficulty through proper engineering design and the incorporation or application of recommended mitigation measures and procedures. Based on the findings of the IEE, the classification of the Project as Category “B” is confirmed, and no further special study or detailed EIA needs to be undertaken to comply with ADB SPS (2009) or GoI EIA Notification (2006).

1

1 This proposed subprojects in aims at launching a focused programme of reinforcing the existing linkages of the Mostmanu temple site to the Pithoragarh-Chandak trekking trail segment and sustainably develop the site to enhance its historic and religious values and supporting the age-old pilgrimage and cultural practices. As both subprojects are in proximity and the ultimate objective is the utilization of tourism potential of the Pithoragarh area as a whole, the background data and consultation section of IEEs of (i) Revival and Development of Trekking Trail and Vantage Points at Pithoragarh to Chandak and (ii) Landscaping, Floriculture and Tourism/Pilgrim Infrastructure Development Works at Mostamanu Temple Complex are almost same. 7

Initial Environmental Examination (IEE) Landscaping, floriculture and tourism/pilgrim infrastructure development works at Mostmanu temple complex

I. INTRODUCTION A. Background

1. The India Inclusive Tourism Infrastructure Development Project (IITIDP) envisages an environmentally and culturally sustainable and socially inclusive tourism development, in the project states of Himachal Pradesh, Punjab, Tamil Nadu and Uttarakhand. The expected Impact of the Project in the four states is sustainable and inclusive tourism development in priority State tourism sub circuits divided into marketable cluster destinations that exhibit enhanced protection and management of key natural and cultural heritage tourism sites, improved market connectivity, enhanced destination and site environment and tourist support infrastructure, and enhanced capacities for sustainable destination and site development with extensive participation by the private sector and local communities. 2. The proposed subproject mainly comprises of ,  Ugradation of Existing Childrens Park  Landscaping and Environmental Improvement of temple complex-  Demolition of inappropriate structures  Provisions for paved pedestrian access and pathway to the temple with adequate plantation  Development of viewpoints around/along the temple and parking facility near temple complex.  Provision of Visitor Amenities and facilities  Proposal for Toilet (better liquid and solid waste management and sanitation) and  Water facilities(underground water storage facility with drinking water points),  Amphitheater up-gradation, proposal for large congregations (for camping, cooking and set up for temporary shops),  Illumination of temple and surroundings  Provision of Street furniture- Design proposals for benches, weather shelters, boundary wall upgradation, dust-bins etc  Landscaping and Beautification of Dunga Bhool.  Environmental Up-gradation of the Palki trail: Including soft paving, plantations, treatment of pause and vantage points, illumination  Provision of Signage and Street furniture along the Palki route. 3. Construction of all elements will begin in the second quarter of the year 2014, and work will be completed in the third quarter of 2015. Total implementation period is 14 months.

4. As per the Asian Development Bank’s (ADB) Environmental Assessment Guidelines,

8

Initial Environmental Examination (IEE) Landscaping, floriculture and tourism/pilgrim infrastructure development works at Mostmanu temple complex

and in line with the Environment Assessment and Review Framework (EARF) for the project, all the sub-project components for the proposed works are categorized as ‘B’ and an Initial Environmental Examination (IEE) prepared. This Initial Environmental Examination (IEE) assesses the environmental impacts due to the proposed "Landscaping, floriculture and tourism/pilgrim infrastructure development works at Mostamanu temple complex" and specifies measures towards addressing the impacts. The IEE was based on a review of sub- project site plans and reports; field visits, collection of primary and secondary data to characterize the environment and identify potential impacts; and interviews and discussions with stakeholders. 5. Based on the findings of the IEE, an Environmental Management Plan (EMP) has been prepared, outlining the specific environmental measures to be adhered to during various phases implementation of the sub project. This EMP forms part of the contract document, and shall enable integration of environmental provisions / management measures in the Contract Document. B. Purpose of IEE 6. The present proposal is aimed at "Landscaping, floriculture and tourism/pilgrim infrastructure development works at Mostamanu temple complex". The environmental impacts due to this subproject are mostly related to the location of the site, construction impacts and Operation & Maintenance as well. Therefore, as per the Asian Development Bank’s (ADB) Environmental Assessment Guidelines, the sub-project components are categorized as ‘B’ and this IEE has been carried out. This IEE provides mitigation measures for impacts related to location and design, construction, operation, and maintenance. C. Environmental Regulatory Compliance 7. The realm of environmental regulations and mandatory requirements for the proposed subproject is shown in Table 1. The Environmental Impact Assessment (EIA) notification, 2006 by the Ministry of Environment and Forests (MoEF, GoI) specifies the mandatory environmental clearance requirements. Accordingly, all projects and activities are broadly categorized into two categories2 - Category A and Category B, based on the spatial extent of potential impacts and potential impacts on human health and natural and man-made resources. The said sub-project is not covered in the ambit of the EIA notification, accordingly environment clearance requirements from the GoI are not triggered.

2 All projects or activities included as Category ‘A’ in the Schedule, including expansion and modernization of existing projects or activities and change in product mix, will require prior environmental clearance from the Central Government in the Ministry of Environment and Forests (MoEF) on the recommendations of an Expert Appraisal Committee (EAC) to be constituted by the Central Government for the purposes of this notification; All projects or activities included as Category ‘B’ in the Schedule, including expansion and modernization of existing projects or activities as specified in sub paragraph (ii) of paragraph 2, or change in product mix as specified in sub paragraph (iii) of paragraph 2, but excluding those which fulfil the General Conditions (GC) stipulated in the Schedule, will require prior environmental clearance from the State/Union territory Environment Impact Assessment Authority (SEIAA). The SEIAA shall base its decision on the recommendations of a State or Union territory level Expert Appraisal Committee (SEAC) as to be constituted for in this notification. In addition, General Condition (GC) of the notification specifies that any project or activity specified in Category ‘B’ will be treated as Category A, if located in whole or in part within 10 km from the boundary of: (i) Protected Areas notified under the Wild Life Protection) Act, 1972, (ii) Critically Polluted areas as notified by the Central Pollution Control Board from time to time, (iii) Notified Eco-sensitive areas, (iv) inter-State boundaries and international boundaries

9

Initial Environmental Examination (IEE) Landscaping, floriculture and tourism/pilgrim infrastructure development works at Mostmanu temple complex

Table 1: Environmental Regulatory Compliance for the sub project- landscaping, floriculture and tourism/pilgrim infrastructure development works at Mostamanu temple complex in Pithoragarh district District Applicability of Acts/Guidelines Compliance Criteria The EIA notification, 2006 (and its It delineates the steps required for obtaining Environmental subsequent amendments in 2009) clearance. As per the notification, a list of projects, requiring provides for categorization of projects Environmental Clearance from regulatory agencies at the State into category A and B, based on extent or Central government level has been provided. of impacts. The sub-project is not covered in the ambit of the EIA notification as this is not covered either under Category A or Category B of the notification. As a result, the categorization, and the subsequent environmental assessment and clearance requirements, either from the state or the GoI is not triggered. The Water (Prevention and Control The Act and Rules outlines the activities which are prohibited on of Pollution) Act 1974 and The Water account of their potential to cause water pollution. Pollution from (Prevention and Control of Pollution) various sources from temple needs to be controlled as per this Rules 1975 Act and Rules The Ancient Monuments and Project site is not an ASI protected monument and there are no any Archaeological Sites and Remains monuments of this nature within the jurisdiction.. Act, 1958, and the rules, 1959 provide guidance for carrying out activities, Therefore, the provisions of the act does not apply including conservation, construction and reuse in and around the protected monuments. Forest (Conservation) Act, 1980 This act provides guidelines for conservation of forests and diversion of forest land for non-forest use. The law also states guidelines on de-reservation of various categories of forests for diversion of forest land. This law describes the penalty for contravention of the provisions of the Act. Restriction on the de- reservation of forests or use of forest land for non-forest purpose. No forest land is to be acquired for the project. For felling of the tree if any permission will be required from local forest office. The Indian Wildlife (Protection) Act, This Act provides guidelines for protection of [Wild animals, birds 1972, amended 1993, The Wild Life and plants] and for matters connected therewith or ancillary or (Protection) Amendment Act, 2002 incidental thereto. It also states the norms for hunting of wild animals, prohibition of picking, uprooting, etc., of specified plants. The Act deals with the declaration of area as Sanctuary, National Park, and closed area and also states the restriction of entries in the sanctuary. Not Applicable for the subproject Biodiversity Act 2002 and The Act essentially controls access to indigenous biodiversity Biodiversity Rules 2004 resources. No agency/person referred to in sub-section (2) shall, without previous approval of the National Bio-diversity Authority, obtain any biological resource occurring in India or knowledge associated thereto for research or for commercial utilization or for bio-survey and bio-utilization. Not Applicable for the subproject

10

Initial Environmental Examination (IEE) Landscaping, floriculture and tourism/pilgrim infrastructure development works at Mostmanu temple complex

Applicability of Acts/Guidelines Compliance Criteria ADB Safeguard Policy Statement, Categorization of subproject components into A, B or C and (2009) developing required level of environmental assessment for each component. Sub-project is Category B as no significant impacts are envisaged.

8. It can be observed from Table-1, that the proposed sub-project does not need to go through a full-scale environmental assessment process; as the scale of impacts and categorization of the sub-project components will not require clearances from Competent Authorities. The sub-project selection criteria specify that all project activities pertaining to "Landscaping, floriculture and tourism/pilgrim infrastructure development works at Mostamanu temple complex" are in accordance with the provisions of the Management Plan.

9. The ADB guidelines, stipulate addressing environmental concerns, if any, of a proposed activity in the initial stages of Project preparation. For this, the ADB Guidelines categorizes the proposed components into categories (A, B or C) to determine the level of environmental assessment required to address the potential impacts.3 The Rapid Environmental Assessment (REA) checklist method was followed as per ADB requirement to assess the potential impacts of the project in planning phase. The REA checklist is attached as Annexure 1 with this report. The subproject has been categorized as B as per the ADB‘s Safeguard Policy Statement (2009). Accordingly this IEE has been prepared to address the potential impacts, in line with the recommended IEE content and structure for Category B project. The IEE has been conducted based on Primary and secondary sources of information and field reconnaissance surveys and stakeholder consultations. Evaluation has been conducted for impacts likely to accrue due to due to location, design & pre-construction, construction, operation & maintenance. An EMP outlining the specific environmental measures to be adhered to during implementation of the subproject has been prepared.

D. Report Structure

10. This Report contains eight (8) sections including this introductory section: (i) Introduction; (ii) Description of Project Components; (iii) Description of the Existing Environment; (iv) Environmental Impacts and Mitigation Measures; (v) Environmental Management Plan; (vi) Public consultation & Information Disclosure; (vii) Findings and Recommendations; and (viii) Conclusions

3 As per SPS 2009 projects are assigned to one of the following four categories: (i) Category A. A proposed project is classified as category A if it is likely to have significant adverse environmental impacts that are irreversible, diverse, or unprecedented. These impacts may affect an area larger than the sites or facilities subject to physical works. An environmental impact assessment is required. (ii) Category B. A proposed project is classified as category B if its potential adverse environmental impacts are less adverse than those of category A projects. These impacts are site-specific, few if any of them are irreversible, and in most cases mitigation measures can be designed more readily than for category A projects. An initial environmental examination is required. (iii) Category C. A proposed project is classified as category C if it is likely to have minimal or no adverse environmental impacts. No environmental assessment is required although environmental implications need to be reviewed (iv) Category FI. A proposed project is classified as category FI if it involves investment of ADB funds to or through a FI (paras. 65-67).

11

Initial Environmental Examination (IEE) Landscaping, floriculture and tourism/pilgrim infrastructure development works at Mostmanu temple complex

II. DESCRIPTION OF PROJECT COMPONENTS

A. Project Overview

11. The project for the "Landscaping, floriculture and tourism/pilgrim infrastructure development works at Mostamanu temple complex" is located in Pithoragarh which is the district head quarters of the same name. The district forms the north-eastern part of the Kumaon Division and lies between Lat. 29º27´N. and 30º49´N. and Long. 79º50´E. and 81º3’E., the length from north to south, being about 151 Km. at its maximum, and the breadth from east to west, reaching its maximum at about 119 Km. It is bounded by Tibet on the north, Nepal on the east, district Almora on the south and the districts Almora and Chamoli on the west.

12. Pithoragarh is a small town that lies in the centre of the western half of the Soar Valley surrounded by four distinct hills Chandak, Dhwaj, Kumdar and Thal Kedar, and stretches in the southern flank to Jhulaghat demarcated by the Kali river adjoining the barren peaks of Nepal Hills. It is snuggled in the folds of four kots Bhatkot, Dungerkot, Udaikot and Unchakot. The view from some of the higher altitudes in Pithoragarh captures the snow-capped peaks of Panch Chulhi, Nanda Devi and Nanda Kot.

13. The scope of this sub-project includes:

 Landscaping and Floriculture works in Mostmanu Temple Complex and Dhunga Bhool Area

 Tourism Pilgrim Infrastructure Development

14. Project location map is shown in Annexure 3. Photo illustration of project location is depicted in Annexure 4.

B. Present status

15. Following intensive discussion and site visit carried out by the team the condition of the site has been evaluated as follows  Intensive use during festival spells needs addressing  Provision of visitor amenities such as drinking water, toilets, shoe deposit  Inappropriate design vocabulary for new built elements on site: the front entryway, the stage on side with aluco-bond paneling, plastering of hitherto exposed stone walls  The site needs to be protected from indiscriminate development to retain its historic setting in the landscape  Haphazard filling to create level terraces has resulted in slope failure and loss of mature trees along the NW edge that potentially poses a danger for further slope failure  Future development and interventions needs to be low impact interventions so that the area can survive as a spiritual domain

12

Initial Environmental Examination (IEE) Landscaping, floriculture and tourism/pilgrim infrastructure development works at Mostmanu temple complex

C. Project components

(i) Ugradation of Existing Childrens Park (ii) Landscaping and Environmental Improvement of temple complex (iii) Demolition of inappropriate structures: details with ownership, existing use (iv) Provisions for paved pedestrian access and pathway to the temple with adequate plantation (v) Development of view points around/along the temple and parking facility near temple complex. (vi) Provision of Visitor Amenities and facilities (vii) Proposal for Toilet (better liquid and solid waste management and sanitation) and (viii) Water facilities(underground water storage facility with drinking water points), (ix) Amphitheater up-gradation, proposal for large congregations (for camping, cooking and set up for temporary shops), (x) Illumination of temple and surroundings (xi) Provision of Street furniture- Design proposals for benches, weather shelters, boundary wall upgradation, dust-bins etc (xii) Landscaping and Beautification of Dunga Bhool - soft paving, retaining wall, treatment of ground in the Dhunga Bhool area in order to enhance the spot extensively used during the annual fair for halting of the traditional Palki on its way to the temple at Mostmanu temple. (xiii) Environmental Up-gradation of the Palki trail: Including soft paving, plantations, treatment of pause and vantage points, illumination. (xiv) Provision of Signage and Street furniture along the Palki route.

16. No objection certificate from Mostmanu Mandir Committee, Sarpanch, Gram Panchayat, Dhunga Bhool and Van Panchayat, Bakarkatiya are attached as Annexure 5.

D. Project Implementation Schedule

17. The implementation period for the proposed subproject is 14 months. Concept Plan preparation started in May 2013. Detailed design started in August 2013. Construction of all elements will begin in the Second quarter of 2014, and work will be completed in the third quarter of 2015.

13

Initial Environmental Examination (IEE) Landscaping, floriculture and tourism/pilgrim infrastructure development works at Mostmanu temple complex

III. DESCRIPTION OF EXISTING ENVIRONMENT

A. Environmental profile- Physical Resources

18. Uttarakhand became a separate state carved out of hill districts and sub Himalayan regions of Uttar Pradesh in the year 2000 and is the newly formed hill state in the Indian Himalayan Region. The geographical location (28°43' N to 31°27' N and 77°34' E to 81°02' E) resource setting of Uttarakhand is unique and shares its borders with China and Nepal. It borders the Tibet Autonomous Region on the north, Nepal on the east and the Indian states of Uttar Pradesh to the South, Haryana to the West and Himachal Pradesh to the North West. There are 13 districts in Uttarakhand which are grouped into two divisions: Kumaon division and Garhwal division. The Kumaon division includes six districts: (i) Almora, (ii) Bageshwar, (iii) Champawat, (iv) Nainital, (v) Pithoragarh, and (vi) Udham Singh Nagar. The Garhwal division includes seven districts: (i) Dehradun; (ii) Haridwar; (iii) Tehri Garhwal; (iv) Uttarkashi; (v) Chamoli; (vi) Pauri Garhwal (commonly known as Garhwal); and (vii) Rudraprayag.

19. Uttarakhand has a total geographical area of 51,125 km², of which 64% is covered by forest. A large part of the state is made mountainous. Most of the northern parts of the state are part of Greater Himalaya ranges, covered by the high Himalayan peaks and glaciers, while the lower foothills were densely forested. The difference in altitude between the lowest parts and the highest part (snow peaks of Nandadevi) is almost 7,000 meters.

Topography 20. Pithoragarh is located at 29.58°N 80.22°E. It has an average elevation of 1,514 metres (4,967 feet). Pithoragarh is a small town, which gives its name to the district. It lies in the centre of the western half of the Soar Valley which resembles the Kashmir valley on a miniature scale. It is prettily dotted with villages, generally placed on eminences. The view from some of the higher altitudes in Pithoragarh captures the snow-capped peaks of Panch Chulhi, Nanda Devi and Nanda Kot. The town is set in a valley popularly known as "Soar" (root meaning is Cool) and lies in the centre of four hills Chandak, Dhwaj, Kumdar and Thal Kedar, and stretches in the southern flank to Jhulaghat demarcated by the Kali river adjoining the barren peaks of Nepal Hills. It is snuggled in the folds of four kots Bhatkot, Dungerkot, Udaikot and Unchakot.

21. Pithoragarh, is known as the gateway to the from the north, as pilgrims trek through this town to the Kailash, Lake Manasarovar, and Om Parvat.The district is named after its headquarters town, Pithoragarh. Tradition has it that during the reign of the Chand rajas of Kumaon, one Piru, also called Prithvi Gosain, built a forthere and named it Prithvigarh which in, in course of time, got changed into Pithoragarh. According to another local legend, Pithora, a Gurkha raja, constructed a fort here and called the place Pithoragarh. According to the 2011 census Pithoragarh district has a population of 485,993., The district has a population density of 69 inhabitants per square kilometre (180 /sq mi). Its population growth rate over the decade 2001–2011 was 5.13%. Pithoragarh has a sex ratio of 1021 females for every 1000 males, and a literacy rate of 82.93%. Native tribes in the district include the Van Rawats and Bhotiya (an exonym). Van Rawats are hunter-gatherers. Bhotiyas are traders. In

14

Initial Environmental Examination (IEE) Landscaping, floriculture and tourism/pilgrim infrastructure development works at Mostmanu temple complex

Pithoragarh, the Bhotiya are divided into two main tribes – Johari Shauka and Rung. The Johari Shauka community inhabits the areas in Munsiyari while Rung tribes are spread among the three valleys of Darma, Chaundas, and Byans. Kandali Festival, celebrated once every 12 years by inhabitants of Chaundas Valley, is one of the major festivals in this area.

Geology 22. The district lies in the Himalayas which are the youngest mountains in the world and the land mass now covered by them was occupied by the great geosynclinal Tethys sea during the Mesozoic period. The probable date of commencement of the elevation of the Himalayas is about the close of the Mesozoic period. According to geological formations of the district, it may be divided into four broad belts, viz., (1) the innermost Siwalik hill ranges, (2) the lesser and middle Himalayas, (3) the inner Himalayas and (4) the thin belt bordering the Tibetan Himalayas, roughly tending east-south-east.

23. The belt of the innermost hill ranges of the Siwalik group lies in the southern part of the district. In the rock formations here sandstones alternate with clayey shales. The sandstones are dirty, friable and micaceous and are, therefore, unsuitable for the building, ballast and industry. The second belt, comprising the ranges of the lesser and middle Himalayas, extend north of the Siwalik group to Dharchula. It contains sedimentary and low to medium grade metamorphic rocks such as limestone, slate, quartzite, phyllite and mica-garnet schist. Mineralization of copper, magnesite, soap-stone, etc., is known to occur in this belt. The third belt, containing higher ranges of the inner Himalayas, is wholly composed of crystalline metamorphic rocks such as mica and garnet schists, kyanite and sillimanite schists, gneisses, granulites and quartzites. This belt is very little known geologically. The belt extends from near Dharchula to Garbyang. The fourth belt, bordering the Tibetan Himalayas has an average width of about 7 km. It contains marine sedimentary rocks such as quartzites, fossiliferous limestones and shale. Minerals like copper, manganesite, soapstone, arsenic, sulphur, kyanite, graphite, slate, limestone etc are found in various pockets in Pithoragarh district.

Climate 24. The elevation of the district ranges from 500 m. above sea level in the valleys in the south to over 7000 m. in the snow-bound Himalayas in the north and north-west. The climate, therefore, largely depends on altitude and varies according to aspect and elevation. Although tropical beat may be experienced in the southern valleys during the summer, the winters are severe. As most of the district is situated on the southern slopes of the Himalayas, monsoon currents penetrate through the deep valleys and rainfall is at the maximum in the monsoon season (June to September), particularly in the southern half of the district. The northern half of the district also gets considerable rain during the winter season which lasts from mid- November to March.

25. Pithoragarh town, being in a valley, is relatively warm during summer and cool during winter. During the coldest months of December and January, the tropical and temperate mountain ridges and high locations receive snowfall and have an average temperature of 5.5–8.0 °C (42–46 °F). Pithoragarh district has extreme variation in temperature due to the large variations in altitude. The temperature rises from mid-March through mid-June. The areas above 3,500 metres (11,500 ft) remain in a permanent snow

15

Initial Environmental Examination (IEE) Landscaping, floriculture and tourism/pilgrim infrastructure development works at Mostmanu temple complex

cover. Regions lying at 3,000–3,500 metres (9,800–11,500 ft) become snow bound for four to six months. At places like the river gorges at Dharchula, Jhulaghat, Ghat and Sera, temperatures reach 40 °C (104 °F). The annual average rainfall is 36.7 centimetres (14.4 in). After June the district receives monsoon showers. Winter is a time for transhumance – the seasonal migration of the Bhotiya tribe with their herds of livestock to lower, warmer areas.

Soils 26. The soil texture in the area varies from coarse loamy, to clayey loamy to silty clay depending on location in the catchment. The majority of forest soil belongs to brown forest soil category. Textural variation is high and within small area, sand content varies from 4.5 to 65%. Silt content ranged from 6.6 to 46.7% and clay content ranged from 3.1 to 56%. Variations are explained by the change of parent material. Sand, stones and shales occur side by side, where as limestone may be found erratically. Alluvium derives forms may vary within short distances depending on the nature of streams.

Water Quality 27. There is no water body near the Mostmanu Temple Complex. The source of water in the temple is public supply. Proposed project components entails provision of underground water storage facility with drinking water points to cater to normal day and festival day visitors.

B. Ecological Resources and Biodiversity Flora 28. The northern part of the district, comprising the larger portions of tahsils Munsyari and Dharchula, where there are high mountains and ridges, is rocky, bland and covered with perpetual snow. The forests are confined to the river valleys and the southern parts of the district. Taking into consideration the differences in the altitudes and the climatic conditions which obtain in the district, its flora may be divided into four main forest types i.e. the sal forest, chir forests, oak forests and the coniferous forests. The willow and older trees are, however, common everywhere in damp situations. The deodars are introduced plants in the district but have become wild. They are found in the southern part of the district around the temples where they had been planted for many generations, their magnificent groves being seen around .

29. Sal Forests: These forests occur in the southern part of the district and the chief tree, sal, is found up to a height of about 1,220 m. and as far as north as patti Malla . On the hills the sal does not attain the height to which it grows in the plains. Other associated trees which also grow in these forests are the haldu, sain, kharik, and tun kharik, the last two being comparatively less common. The sal logs are chiefly used for building purposes. The bhyunl, an extremely useful tree, grows in the valleys and lower hilly slopes and is carefully protected, for its leaves afford excellent fodder for cattle, and the fibres of its young shoots are twisted into ropes. Up to heights of about 900 m., trees common in the plains, viz., the mango, pipal, banyan and, sissoo are very frequently in evidence.

30. Chir Forests: The chir is the principal component of forests up to altitudes of about 1,800 m., growing between 500m., when not unduly exposed to the sun, and 2,200 m. on a south

16

Initial Environmental Examination (IEE) Landscaping, floriculture and tourism/pilgrim infrastructure development works at Mostmanu temple complex

aspect. Chir trees are usually found alone, for they appear to have the power of driving away all other vegetation from the tract where they are found Chir is the staple building timber in the hills, while vast quantities of it are exported in the shape of sleepers. Torches are cut out of the living wood. Resin is also extracted from the tree. Its seeds are eaten.

31. Oak Forests: The principal varieties of oak found in the district are the banj, tilonj and the kharsu, each occupying a more or less distinct altitudinal zone. Banj begins to grow at heights of 1,800 m. and 2,450 m. The tree usually attains no great height. Its wood, being hard and gnarled, is used for agricultural implements and fuel. It has the capacity to establish itself on the highly unfavorable south aspect. Banj forests are usually dense on the north aspects but open on the south aspects. The other trees found in these forests are the rhododendron and ringal which occurs in clumps rising to about 4 m. to 6 m. and containing as many as one hundred shoots. Between the altitudes of 2,150m. and 2,450m. tilonj, is the chief species of the oak forest and between the altitudes of 2,450 m. and 3,550 m. kharsu is the dominant tree. The main associated trees of the tilonj and kharsu forests are the horse-chestnut and the syeamore. The tilonj and kharsu, the hardier oaks, resemble the banj and are used for the same purpose, but they are straighter and less knotted.

32. Coniferous Forests: Between the altitudes of 3,250 m. and 4,000 m. the dominant species are the conifers. The chief species are the deodar and the ragha (Himalayan silver fir) which mainly occurs between the heights of 3,250 m. above the sea-level. The blue pine (chil), the yew (thaner) and the cypress (surain) are also found in this region. The cypress sometimes attains an enormous size. The wood is hard, tough and durable and too heavy for floatation by itself. With these forests is found the variegated bush rhododendron with flowers of all colours, pink, purple, blue and pure white. The birch grows up to heights of about 4,000m. and its stems give the famous bhurjapatra of Bhoj-patra which in earlier times, was used as writing material before the invention of paper. Fauna 33. Animal: The wild animals of the district have greatly declined in number and variety during the past few decades. Of the animals in the district, the sambur which is the most widely distributed of all the deer tribe is found up to an altitude of about 3,050 m. above sea-level. The kakar or barking deer is also met with up to the same height. The musk-deer (kastura) is found in the upper ranges above an altitude of 2,400 m. above sea level. The tiger found here is different from that found in the plains, being stouter in build and with longer and more furry hair and shorter and thicker tail. The bagh, baghera or panther is common throughout the district. It lives upon cattle, goats and sheep and is bold and bloodthirsty beast. The snow leopard is rare in the tract south of the snowy range. The Himalayan black bear is common throughout the district and is generally seen during the rains. The jackal is found up to a height of 2,150 m. and the wild pig up to that of 3,050 m. Monkeys and langurs are found throughout the district.

34. Birds: The district is very rich in birds. Birds of prey like eagles hawks, falcons and vultures, are very common. Among game-birds the lungi pheasant is found at an altitude of about 3,700 m. and the monal pheasant at elevations between 2,400 m. and 3,700 m. The kokla or pokra is seen between heights of 1,800 m. and 3,700 and the chir pheasant is found

17

Initial Environmental Examination (IEE) Landscaping, floriculture and tourism/pilgrim infrastructure development works at Mostmanu temple complex

between altitudes of 1,500 m. and 2,400 m. above sea-level. The kalij a common pheasant, and black partridge frequent the thick forests up to a height of about 2,400 m. The chakor is a very common bird among partridges. The snow partridges are rare. The Himalayan snow cock is found on or near the snowline. Among pigeons, the wood-pigeons are also seen in the higher ranges. Duck and teal occasionally rest on the rivers.

35. The project area is not within forest and no endangered species are reported at site. Trees of Pine, Deodar and surai are reported around the site.

Ambient Air Quality 36. Ambient air quality measurements in Chandak area are shown in Table 2. (Details in Annexure 7) The monitoring was done on 06/11/2013. All parameters measured are well below the permissible limit which is expected in an area with no major sources of air pollution.

Table 2: Ambient Air Quality (24 hours basis) Parameters measured Unit At Treck Trail At Mostmanu Allowable Limit* Temple Respirable Particulate µg/m3 64 56 100 Matter (PM10) Respirable Particulate µg/m3 31 27 60 Matter (PM2.5) 3 Sulphur Dioxide (SO2) µg/m 10 08 80 3 Nitrogen Dioxide (NO2) µg/m 14 18 80 Carbon Monoxide (CO) mg/m3 0.14 0.1 For 08 hrs is 02 and for 01 hrs is 04 *Allowable Limit = National Ambient Air Quality Standards as per CPCB Notification New Delhi, 18 Nov,2009, Date of sampling= 06.11.2013

Ambient Noise Levels 37. Ambient noise quality has been monitored during preparation of this report. The data of noise monitoring are shown in Table 3 (Details in Annexure 7). The day time equivalent noise level ranged from 41.6 to 43.5 dB(A), which is well below the permissible limit.

Table 3: Ambient Noise Quality at Chandak area S.No. Location Unit Measured values Allowable limits (*Leq Values) /Specification (CPCB)/Leq (dB (A) 1. At Treck Trail dB(A) 43.5 2. At Mostmanu Temple dB(A) 41.6 55 *Leq Values = Equivalent Continuous Sound Pressure Level Date of sampling= 06.11.2013

C. Economic Resources Livestock 38. Livestock is mainly reared for milk production and compost agriculture is the project area is closely integrated with forests and animal husbandry. The agriculture is predominantly subsistence based and majority of population is dependent on market fall grains, pulses,

18

Initial Environmental Examination (IEE) Landscaping, floriculture and tourism/pilgrim infrastructure development works at Mostmanu temple complex

vegetables and milk. Tourism and allied activities are the main occupation of local community. Due to closeness from the block and district head quarters and being a tourist destination the project has almost all infrastructure facilities like road, electricity, education, drinking water, health banks, post office, market, police station etc. within a periphery of 5 kms. Livelihood and Employment 39. The economy of the area is largely agriculture and tourism based with allied activities like horticulture, and animal husbandry. Non-Agricultural economic activities includes skilled and unskilled labour in construction works, Government service, private jobs, shop-keeping, tailoring, transport service etc. and tourism related activities like selling of wild edibles, fruits etc. The average monthly income of each household is INR 4,000 per month. There is huge potential of tourism development in the area which will provide more employment to the local youth and improve the livelihoods security of local community. 40. The number of females per thousand males is 888. The women face the challenge of doing maximum households chores and most of the agricultural tasks. The time use analysis shows that on average women spend 17, 15 and 14 hours per day in various households and agricultural works during summers, winters and rainy season respectively.

D. Social and Cultural Resources Demography 41. The subproject area lies in Bin block of Pithoragarh District. There are 20 revenue villages situated in the surroundings of Mostamanu temple within a periphery of 8 kms. The population of these villages is about 3249 with 659 households, mainly Brahmins, Rajputs and scheduled castes. The people of these villages are dependent on religious tourism based activities for their livelihoods. There is potential of tourism development in the area which will provide more employment to the local youth and improve the livelihoods security of local community. As per information received from the community, there is gender disparity among boy and girl child. Also there is lack of entrepreneur skills among the youths. Due to favourable climate, there is scope of floriculture, vegetable cultivation and dairy in the area. Important baseline data related parameters are summarized in the following table (as received from Himalayan Seva Samiti, a local NGO which conducted this survey in 2012)

Table 4: Demographic profile of Project Area S.N. Name of Distance Total Total Total SC Tota BPL Total Total Village from House- Population Population Households literates Geographical Chandak holds area (Ha) (Km) 1 Cheda 4 90 444 192 43 312 93.8 2 Dharigaon 5 33 172 26 9 119 14.9 3 Chanapandey 6 81 364 197 47 280 201.2 4 Guruda 7 29 130 7 13 91 31.9 5 Naikina 8 44 189 40 32 128 99.3 6 Bhurmuni 7 160 796 134 78 595 215.1 7 Nakot 5 37 179 68 23 119 27.0 8 Majhera 4 33 166 19 11 124 59.7 9 Kante 3 13 56 0 4 38 17.8 10 Ratwali 3 39 179 0 5 148 28.4 11 Dharapani 1 9 51 0 1 38 35.1

19

Initial Environmental Examination (IEE) Landscaping, floriculture and tourism/pilgrim infrastructure development works at Mostmanu temple complex

12 Halpati 2 14 71 0 3 51 99.9 13 Bakarkatia 2 18 105 0 4 80 106.5 14 Gauriagaon 2 13 72 0 3 54 24.5 15 Dhungabhool 3 46 275 125 21 193 13.4 Total 15 villages 659 3249 808 297 2370 1055.1

Basic Amenities and Infrastructure 42. Due to closeness from the block and district headquarters, the project has almost all basic infrastructure facilities but their management is poor. All the villages are accessible by motorable roads, electricity and telephone/mobile-phone. The primary and secondary education facility are available in the project area, but the nearest primary health facilities are available at Pithoragarh (8 kms). Bank and postal services are also available in the project area. Pithoragarh is the main market of the project area. The details of basic amenities and infrastructure available in the project area is given in the Table 5

Table 5: List of Basic Amenities in the project area S. No. Basic amenities and Infrastructure Location & Distance (km) 1 Primary Health Centre Pithoragarh (8 kms) 2 Intermediate School Pithoragarh (8 kms) 3 Post Graduate College Pithoragarh (8 kms) 4 Post Office Pithoragarh (8 kms) 5 Bank Chandak (1 kms), Pithoragarh (8 kms) 6 Veterinary Hospital Pithoragarh (8 kms) 7 Petrol Pump Pithoragarh (8 kms) 8 Main Market Pithoragarh (8 kms) 9 Mandi/market for selling of produce Pithoragarh (8 kms) 10 Police Station Pithoragarh (8 kms)

SWOT Analysis 43. The SWOT analysis of Mostmanu temple as a tourist destination was done with the objective of assessing its tourism potential and possibilities for sustainable tourism development in the city. The strengths, weakness, opportunities and threats of which are summarized below: The study of SWOT analysis shows that the important and accepted livelihood option is tourism based. The strengths, weakness, opportunities and threats of which are summarized below. Strengths: Opportunities: o Mostamanu temple is located 8 kms from o A large annual fair (mela) is held at Pithoragarh and nearby temples such as Mostamanu temple on the occasion of Rishi Pashupatinath temple attracts lot of local and Panchami/Nag Panchami (September), regional devotees every year. marking a major occasion for local and o Climate and geographical conditions around regional level trade for locals and tourists. the temple complex are soothing and o Visit to the temple Complex can be centred abundance of natural endowments due to around its linkages to the nearby trekking trail nearby forests. for visiting tourists. o Majestic view of the Himalayas visible from o Besides local cultural and religious events the temple complex. the temple complex can be promoted to tourists engaged in intra regional tours.

20

Initial Environmental Examination (IEE) Landscaping, floriculture and tourism/pilgrim infrastructure development works at Mostmanu temple complex

Weakness: Threats:  Existing Infrastructural facilities in the temple  Threats from insensitive new development that complex underutilized. distorts and diminishes its historic setting and  No formal/ registered body to put into place a relation to the surrounding sacred geography. management system for the site.  Environmental degradation of site including  Lack of effective marketing of the temple slope failure and loss of mature trees. complex as a tourist destination for domestic  Environmental concerns like garbage and foreign tourists. generation and waste disposal.  Poor capacity and lack of proper training among the caretakers of the temple.  Maintenance of site assets not systematic and lack of dedicated budget for the same.  Underutilized synergy among District Administration and local body and the temple stakeholders.

21

Initial Environmental Examination (IEE) Landscaping, floriculture and tourism/pilgrim infrastructure development works at Mostmanu temple complex

IV. ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES 44. The assessment for environmental impacts due to the implementation of this project has been carried out for potential impacts during the following stages of the project planning and implementation:

 Location impacts: Impacts associated with site selection, including impacts on environment and resettlement or livelihood related impacts on communities and wildlife  Design impacts: Impacts arising from project design, including the technology used, scale of operations, discharge standards etc  Construction impacts: Impacts resulting from construction activities including site clearance, earthworks, civil works, etc.  O&M impacts: Impacts associated with the operation and maintenance of the infrastructure built in the project.

Location Impact:

A. Land Acquisition and Resettlement

45. The location considered for the subproject is within the area designated for eco- tourism as part of developing Uttarakhand‘s conservation, heritage, natural and cultural attractions, and are outside areas demarcated for habitat protection and conservation. The proposed sub- project envisages "Landscaping, floriculture and tourism/pilgrim infrastructure development works at Mostmanu Temple Complex". The subproject will not require any permanent land acquisition because it will be undertaken within the existing Mostmanu Temple Complex. The stakeholders of the subproject area have given the NOCs. These are captioned in Annexure 5.

B. Environmental Impacts

Design Impacts and Pre-Construction Impacts 46. Impacts arising from the inappropriate designs of proposed facilities would in general include the contemporary designs for the traditional and cultural environment, etc. Selection of materials, if not carefully chosen, will adversely impact the aesthetic appeal of the surroundings. The results of interventions are unobtrusive and will be integral part of the overall ambience so as to avoid impacts on the aesthetics of the site. Structural designs to be worked out in such a manner that over ground structures do not affect the aesthetics of the area. All component designs will be worked out to minimize any impacts on the adjoining properties, and considering the drainage and sewerage connections. Given that there is a need for disposal of construction wastes, the contractors will be required to consult with the Project Implementation Unit (PIU) and Uttarakhand Environment Protection and Pollution Board (UEPPB) for safe disposal sites. 47. No additional land is required for the sub-project. The entire "Landscaping, floriculture and tourism/pilgrim infrastructure development works at Mostmanu Temple Complex" will be carried out within the available land. Thus, telephone lines, electric poles and wires, water

22

Initial Environmental Examination (IEE) Landscaping, floriculture and tourism/pilgrim infrastructure development works at Mostmanu temple complex

and sewer lines will not be affected. The storm water runoff from alterations of the site‘s natural drainage patterns due to landscaping, excavation works in the Mostmanu Temple area and landscaping near the surroundings will be taken care in the designs. Selection of materials and construction technologies shall be carefully chosen, so that it does not adversely impact the aesthetic appeal of the destinations. Designs will ensure energy conservation. 48. All construction activities to be undertaken at the site will be approved by PIU before start of any such activity in the vicinity of the site so that the history and sanctity as well as the usability of the site is not hampered. The construction stage impacts due to the proposed project components are generic to the construction activities. The EMP emphasizes on the construction impacts and necessary mitigation measures to be strictly followed by the contractor and supervised by the DSC and PIU. The key impacts are covered in the following paragraphs. 49. Majority of the significant impacts will occur during the construction phase and are generic to the construction activities. Key impacts during construction phase are envisaged on the following aspects: (i) drainage, (ii) quarry/borrow pit operations, (iii) dust generation, air and noise pollution from construction activities, (iv) handling of construction materials at site, (v) disposal of construction waste materials, and (vi) adoption of safety measures during construction. 50. Impacts due to stock piles of waste and top soil: Improper stockpiling of construction materials and top soil can obstruct drainage, disturb local people, tourists, etc. Due consideration will be given for material storage and construction sites such that it doesn‘t cause any hindrance to public movement within the site. Stockpiles will be covered to protect from dust and erosion.

51. Disposal of construction waste: Safe disposal of the construction wastes, extraneous material will be ensured in the pre-identified disposal locations. In no case, any construction waste will be disposed around the project site indiscriminately. Maximum utilization will be done for construction of retaining walls, embankments and as filling material. Remaining material if any will be disposed off safely at the disposal sites approved by the DSC Engineer and PIU.

52. Debris/solid waste will be generated due to, excavated earth material and waste generated from construction camps if any. Debris/excavated earth material will be reused subject to the approval of the Engineer during the construction. Waste generated from the construction activities will be disposed off as per law to the satisfaction of the Engineer.

53. Quarry/Borrow pits operations: The construction material required shall be procured for market areas. If some stone/rock material is required, then the same shall be taken from existing quarries. No new quarry is proposed to be opened for the project, which will be procured from market. No quarrying/borrow pit operation are required. Hence there are no impacts in this subject. 54. Ground water will not be used for construction purposes and the problem of ground water contamination is not anticipated during the construction phase as there will be proper disposal of the sludge. 55. Generation of dust is anticipated during transportation, excavation and construction activities. Certain volumes of dust and gaseous emissions will also be generated during the

23

Initial Environmental Examination (IEE) Landscaping, floriculture and tourism/pilgrim infrastructure development works at Mostmanu temple complex

construction period from construction machineries like mixers, vehicles engaged in transportation of construction materials. Pollutants of primary concern at this stage include

Respirable and Suspended Particulate Matter (SPM) and gaseous emissions (NOX, SO2, CO, etc). However, transportation of construction materials will be confined to adequate trips per day depending upon extent of construction activity. Therefore, impact at this stage will be temporary and restricted to the close vicinity of the construction activities only. 56. All vehicles and construction equipment operating for the contractor and the consultant will obtain and maintain “Pollution under Control” (PUC) Certificates. To control dust emissions, vehicles deployed for borrow material, sand and aggregate haulage, shall be covered with tarpaulins to be spillage proof. Regular sprinkling of water during excavations, loading, unloading, vehicular movement and raw material transport, provisions shall be made during the construction period. 57. Periodic air quality monitoring to ensure emissions comply with standards will be conducted. The Contractor will submit annual emission monitoring results required by the SPCB as part of the annual consent to operate (CTO) renewal. 58. During construction phase, some noise will be generated from the various construction activities like equipment and vehicles engaged in transportation of construction materials. However, transportation of construction materials will be confined to the requirement per day, depending upon extent of construction activity. Further the noise associated with the equipments shall be reduced with the application of the lubricant. The increase in noise levels is expected to be between 5 - 10 %. However, these noise levels will be confined to the work sites only and will be temporary in nature and also short duration as well. 59. The construction activity will be carried out away from environmentally sensitive area. Therefore, no adverse impact on fauna and flora is anticipated due to the proposed activity. 60. The clean-up and restoration operations are to be implemented by the contractor prior to demobilization. The contractor will clear all temporary structures and dispose of all garbage. All construction zones used/affected by the sub-project will be left clean and tidy, at the contractor’s expense as per the satisfaction the Engineer. 61. The Contractor is likely to engage local labour for various construction activities. However, in case of engaging migratory labour for the purpose, the contractor has to establish properly designed labour camp with all basic amenities such as potable drinking water supply and sanitation facilities. EMP envisages mitigation measures for likely adverse impacts associated with the labour camps. 62. The implementation of the sub project will not involve dislocation or involuntary resettlement of people. Positive impact is anticipated in terms of employment opportunity as many skilled, semi-skilled and un-skilled personnel will get direct and indirect employment during construction phase. 63. Most of the predicted impacts are associated with the construction process, and are produced because that process is invasive, involving ground disturbance. However the routine nature of the impacts means that most can be easily mitigated. The project is relatively small in scale and involves straightforward construction and low-maintenance operation, so it is unlikely that there will be major impacts.

24

Initial Environmental Examination (IEE) Landscaping, floriculture and tourism/pilgrim infrastructure development works at Mostmanu temple complex

64. Impacts on drainage pattern: Proper care has been taken for location of construction sites. Hence, no impact is expected on drainage pattern in the area.

65. Impacts due to sewage disposal: About 20-30 labor and technical staff are likely to be involved in the project construction activities. The labor will be locally available. Hence no labor colony will be established. Community toilets will be constructed near construction sites. The sewage generated by labour population during their working hours at construction site will be treated in a septic tank, prior to disposal.

66. Disturbance to traffic during construction phase: At the time of construction there will be disturbance and inconvenience for the movement of the public and vehicles due to project construction activities, particularly during transportation of construction materials. These impacts will be temporary in nature and last for a very short period.

67. Impacts on cultural properties: The proposed project interventions shall improve the quality of facilities and services in the Most Manu temple Complex to promote tourism by enhancing the quality of visitor experience and safeguarding the environmental integrity of the site.

68. Impacts on utilities: The entire construction work will be done within the existing trail alignment. Hence no adverse impact is envisaged.

Operation and Maintenance Impacts 69. The most significant beneficial impact on the environment is through improvement of infrastructure at Mostmanu temple complex. This together with enhancing the visitor experience will also safeguard environmental integrity of the site by addressing the issues of liquid and solid waste management and sanitation in the site. The project initiatives will encourage tourist populations to these destinations. The project will also build the capacity of primary and secondary stakeholders by training on environmental and livelihood aspect.

Environmental Mitigation Measures 70. The specific measures stated in the EMP will address all adverse environmental impacts due to the subproject. A detailed monitoring plan prepared as part of this IEE will ensure negative environmental impacts during implementation are mitigated. During the detailed design stage, the IEE/EMP further updated and stand-alone EMPs for each of the procurement packages will be prepared. These EMPs will be appended to the respective contract documents to enable integration of environmental provisions in the contract. Based on the environmental baseline conditions, planned project activities and impacts assessed earlier, the set of measures to be adopted to ameliorate the adverse impacts are listed in following paragraphs.

71. Measures to Mitigate Location Impacts . In accordance with the provisions in the subproject selection criteria, the subproject design will include adequate provisions for ensuring effective maintenance and protection of the assets created so as to ensure the long term sustainability of the sites.

25

Initial Environmental Examination (IEE) Landscaping, floriculture and tourism/pilgrim infrastructure development works at Mostmanu temple complex

. Designs will be worked out and implemented in accordance with the provisions. Further, the design guidelines for the project components will strictly conform to Uttarakhand architecture. 72. Measures to Mitigate Design Impacts . Design of proposed components will enable efficient drainage at the project site and maintain natural drainage patterns. . Designs will be worked out in such a manner that exposed steel and concrete structures are avoided. The obsolete and inappropriate additions will be removed. The design brief for all components proposed will strictly conform to the Uttarakhand architecture. The usage of construction machinery within the existing premises will be disallowed, except for handheld equipments, if necessary. Any new landscaping elements will only utilize native species to protect local biodiversity 73. Measures to Mitigate Impacts due to Pre-construction Activities . Prior to commencement of site activities and mobilization on ground, the Contractor will prepare and get approved by the PIU and DSC, circulation plan during construction for safe passage of tourists during construction stage, including development of alternative access routes, traffic regulations, signage, etc. during construction. . The commencement of site clearance activities will be undertaken with due permission from the Environment Specialist of the DSC consultant to minimize environmental impacts. . All areas used for temporary construction operations will be subject to complete restoration to their former condition with appropriate rehabilitation procedures. . Location of disposal sites will be finalized by the Environmental Specialist of the DSC so that disposal of the material does not impact natural drainage courses or surface water bodies or low lying areas and that no endangered / rare flora is impacted by such materials 74. Measures to Mitigate Construction Impacts . Due consideration will be given for material storage and construction sites such that it doesn‘t cause any hindrance to tourist movement within the site. . Stockpiles will be covered to protect from dust and erosion. . The topsoil from borrow areas, areas of cutting and areas will be stripped to a specified depth of 150mm, translocated and stored in stockpiles. . The stockpile will be designed such that the slope does not exceed 1:2 (vertical to horizontal). . Stockpiles will not be surcharged or otherwise loaded and multiple handling will be kept to a minimum to ensure that no compaction will occur. The stockpiles will be covered with gunny bags or tarpaulin. . Slope protection measures will be undertaken along slopes. The work will consist of measures as per design, or as directed by the Engineer to control soil erosion, sedimentation and water pollution.

26

Initial Environmental Examination (IEE) Landscaping, floriculture and tourism/pilgrim infrastructure development works at Mostmanu temple complex

. The contractor will take every precaution to reduce the levels of dust at construction sites to the satisfaction of the Engineer. All earthworks to be protected/covered in a manner acceptable to the satisfaction of the engineer to minimize dust generation. Clearance will be affected immediately by manual sweeping and removal of debris, or if so directed by the Engineer. . The discharge standards promulgated under the Environmental Protection Act, will be strictly adhered to. All vehicles, equipment and machinery used for construction will conform to the relevant Standard. . All vehicles, equipment and machinery used for construction will be regularly maintained to ensure that pollution emission levels comply with the relevant requirements. . Noise level for construction equipment used in this project (measured at one meter from the edge of the equipment in free field) such as compactors, rollers, front loaders, concrete mixers, will not exceed 75 dB (A). Notwithstanding any other conditions of contract, noise level from any item of plant(s) will comply with the relevant legislation for levels of noise emission. . All workers employed on cement, lime mortars, concrete etc., will be provided with protective footwear and protective goggles. . Cut material generated because of cutting of hill slopes will be utilized for construction of retaining walls, embankments and as filling material. Remaining material if any will be disposed off safely at the disposal sites. . All necessary steps will be taken for prompt first aid treatment of all injuries likely to be sustained during the course of work. . Contractor to prepare site restoration plans for approval by the Engineer. The plan is to be implemented by the contractor prior to demobilization. . On completion of the works, all temporary structures will be cleared away, all rubbish burnt, excreta or other disposal pits or trenches filled in and effectively sealed off and the site left clean and tidy, at the Contractor‘s expense, to the entire satisfaction of the Engineer. 75. Measures to Mitigate O&M Impacts . In line with the Government targets of coverage of all urban and rural areas with environmentally safe solid waste management systems, tourist destinations will be covered with integrated waste management facilities, including treatment and disposal, in line with the Solid Waste Handling Rules, 2000. 76. Responsibilities of Contractors . Abide by the environmental laws formulated by the community institution. . Regularly remove trash from the site on daily basis. . Area should be declared as plastic free, smoking free and silence zone and sign boards for the purpose should be displayed at work site and workers should be made aware about it by training

27

Initial Environmental Examination (IEE) Landscaping, floriculture and tourism/pilgrim infrastructure development works at Mostmanu temple complex

. Cutting and collection of fuel wood by the construction workers from the nearby forest should be strictly prohibited . It will be ensured by the contractor that the topsoil will not be unnecessarily trafficked either before stripping or when in stockpiles. Such stockpiled topsoil will be returned to cover the disturbed area and cut slopes. . Contractor with support of the PIU will carry out dissemination of these information and circulation plan at key entry points to the respective destinations . Contractor will be responsible for arrangement of water in every workplace at suitable and easily accessible place for the whole construction period. . Sufficient supply of potable water to be provided and maintained. If the drinking water is obtained from an intermittent public water supply then, storage tanks will be provided. . Contractor will ensure that construction activities do not result any contamination of land, water or air by polluting substances . Contractor will ensure that no trees or shrubs or water side vegetation are felled or harmed except those required to be cleared for execution of work. The Contractor will protect tree and vegetation from damage to satisfaction of the engineer. 77. Responsibilities of PIU & DSC . Sponsor seminars and/or distribute educational materials to contractors and visitors about environmentally beneficial conservation procedures

. Organize workers’ training program for the contractors for environmental management during construction works . Educate the contractors regarding the eco-sensitivity of the area and explain how to protect bio-diversity during construction works . Regular site visit and reporting during construction works to check whether objectives of EMP being followed.

28

Initial Environmental Examination (IEE)

Landscaping, floriculture and tourism/pilgrim infrastructure development works at Mostamanu temple complex 78. The summary of Environmental Impacts and Mitigation Measures to be followed in this project are given in Table 6.

Table-6: Summary of Environmental Impacts and Mitigation Measures Field Duration/ Magnitude Mitigation Measures Responsibility Extent 1. Location Impacts 1.1 Lack of sufficient planning to Permanent Major In accordance with the provisions in the subproject selection PIU/DSC assure long term sustainability of criteria, the subproject design will include adequate provisions for the improvements and ensure ensuring effective maintenance and protection of the assets protection of the assets created created so as to ensure the long term sustainability of the sites. and the architectural character of The designs are be worked out and implemented in accordance the surroundings. with the provisions. Further, the design guidelines for the project components will strictly conform to Uttarakhand architecture. 2. Design Impacts 2.1 Increased storm water runoff from Permanent Moderate Design of proposed components will enable efficient drainage of PIU/DSC alterations of the site‘s natural the sites and maintain natural drainage patterns. drainage patterns due to additional structures and landscaping works in the area. 2.2 Selection of materials and Permanent Moderate Designs to be worked out in such a manner that exposed steel PIU/DSC construction technologies, if not and concrete structures are avoided. The design brief for all carefully chosen, will adversely components proposed will strictly conform to the Uttarakhand impact the aesthetic appeal of the architecture. New landscaping elements will only utilize native destinations species to protect local biodiversity 2.3 Integration of energy efficiency Permanent Minor The detailed designs for the subproject components will ensure PIU/DSC and energy conservation energy efficiency programs in design of subproject components 3. Pre-construction Activities 3.1 Circulation plan during Temporary Moderate Prior to commencement of site activities and mobilization on Contractor/ construction in the tourist ground, the Contractor will prepare and get approved by the DSC/PIU destinations Engineer, circulation plan during construction for safe passage of tourists during construction stage, including development of alternative access routes, traffic regulations, signages, etc., during 29

Initial Environmental Examination (IEE)

Landscaping, floriculture and tourism/pilgrim infrastructure development works at Mostamanu temple complex Field Duration/ Magnitude Mitigation Measures Responsibility Extent construction. The Contractor with support of the PIU will carry out dissemination of these information and circulation plan at key entry points to the respective destinations. 3.2 Site clearance activities, including Temporary Moderate The commencement of site clearance activities will be undertaken Contractor/ delineation of construction areas with due permission from the Environment Specialist of the DSC DSC consultant to minimize environmental impacts. All areas used for temporary construction operations will be subject to complete restoration to their former condition with appropriate rehabilitation procedures. 3.3 Drinking water availability and Temporary Major The contractor will be responsible for arrangement of water in every Contractor/ water arrangement workplace at suitable and easily accessible place for the whole DSC construction period. Sufficient supply of potable water to be provided and maintained. If drinking water is obtained from an intermittent public water supply then, storage tanks will be provided. 3.4 Identification of sites for disposal of Permanent Major Location of disposal sites will be finalized by the Environmental Contractor/ construction and demolition work Specialist of the DSC so that disposal of the material does not DSC impact natural drainage courses or surface water bodies or low lying areas and that no endangered / rare flora is affected by disposal of construction and demolition waste 4. Construction Impacts 4.1 Improper stockpiling of Temporary Minor Due consideration will be given for material storage and Contractor/ construction materials cause construction sites such that it doesn‘t cause any hindrance to DSC impacts starting from obstruction movement within the site. Stockpiles will be covered to protect from of drainage, disturbance/ safety dust and erosion. hazard to tourists, etc. 4.2 Stripping, stocking and Permanent Minor The topsoil from borrow areas, areas of cutting and areas will be Contractor/ preservation of top soil stripped to a specified depth of 150mm, translocated and stored in DSC stockpiles. The stockpile will be designed such that the slope does not exceed 1:2 (vertical to horizontal). Stockpiles will not be surcharged or otherwise loaded and multiple handling will be kept to a minimum to ensure that no compaction will occur. The stockpiles will be covered with gunny bags or tarpaulin. It will be 30

Initial Environmental Examination (IEE)

Landscaping, floriculture and tourism/pilgrim infrastructure development works at Mostamanu temple complex Field Duration/ Magnitude Mitigation Measures Responsibility Extent ensured by the contractor that the topsoil will not be unnecessarily trafficked either before stripping or when in stockpiles. Such stockpiled topsoil will be returned to cover the disturbed area and cut slopes. 4.3 Soil Erosion Temporary Minor Slope protection measures will be undertaken along slopes of the Contractor/ parking area and other sites vulnerable to soil erosion. The work DSC will consist of measures as per design, or as directed by the Engineer to control soil erosion, sedimentation and water pollution. 4.4 Soil and Water Pollution due to fuel Temporary Minor The fuel storage will be stationed such that fuel discharge does not Contractor/ and lubricants, construction waste drain into the water body. Soil and water pollution parameters will DSC be monitored as per monitoring plan. 4.5 Generation of Dust Temporary Minor The contractor will take every precaution to reduce the levels of Contractor/ dust at construction sites to the satisfaction of the Engineer. All DSC earthworks to be protected/covered in a manner acceptable to the satisfaction of the engineer to minimize dust generation. Clearance will be affected immediately by manual sweeping and removal of debris, or if so directed by the Engineer, the road surfaces will be hosed or watered using necessary equipment. 4.7 Emission from construction Temporary Minor The discharge standards promulgated under the Environmental Contractor/ vehicles, equipment and Protection Act will be strictly adhered to. All vehicles, equipment DSC machinery and machinery used for construction will conform to the relevant Standard. All vehicles, equipments and machinery used for construction will be regularly maintained to ensure that pollution emission levels comply with the relevant requirements. 4.8 Noise from construction Temporary Minor Maintenance of vehicles, equipment and machinery will be regular Contractor/ equipment and to the satisfaction of the Engineer, to keep noise from these at DSC a minimum. All vehicles and equipment used for construction will be fitted with exhaust silencers. During routine servicing operations, the effectiveness of exhaust silencers will be checked and if found to be defective will be replaced. Noise limits for construction equipment used in this project 31

Initial Environmental Examination (IEE)

Landscaping, floriculture and tourism/pilgrim infrastructure development works at Mostamanu temple complex Field Duration/ Magnitude Mitigation Measures Responsibility Extent (measured at one meter from the edge of the equipment in free field) such as compactors, rollers, front loaders, concrete mixers, will not exceed 75 dB (A). Notwithstanding any other conditions of contract, noise level from any item of plant(s) will comply with the relevant legislation for levels of noise emission. 4.9 Material Handling at Site Temporary Minor All workers employed on mixing cement, concrete etc., will be Contractor/ provided with protective footwear and protective goggles. DSC Workers, who are engaged in welding works, will be provided with welder‘s protective eye-shields. Workers engaged in stone breaking activities will be provided with protective goggles and clothing and will be seated at sufficiently safe intervals. 4.10 Disposal of Construction Waste/ Temporary Minor In no case, any construction waste will be disposed around the site Contractor/ Debris / Cut Material indiscriminately. DSC Cut material generated because of cutting of hill slopes will be utilized for construction of retaining walls, embankments and as filling material. Remaining material if any will be disposed off safely at the disposal sites. 4.11 Safety Measures During Temporary Moderate Personal Protective Equipment for workers on the project and Contractor/ Construction adequate safety measures for workers during handling of materials DSC at site will be taken up. The contractor has to comply with all regulations regarding safe scaffolding, ladders, working platforms, gangway, stairwells, excavations, trenches and safe means of entry and egress. 4.12 Risk caused by Force Majeure Temporary Minor All reasonable precautions will be taken to prevent danger of the Contractor/ workers and the public from fire, flood, drowning, etc. All necessary DSC steps will be taken for prompt first aid treatment of all injuries likely to be sustained during the course of work. 4.13 Malaria Risk Temporary Minor The Contractor will, at his own expense, conform to all anti-malaria Contractor/ instructions given to him by the Engineer. DSC 5. O&M Impacts 5.1 Environmental Conditions Temporary Moderate The tourism department will undertake seasonal monitoring of air, Tourism water, and noise and soil quality through an approved monitoring department

32

Initial Environmental Examination (IEE)

Landscaping, floriculture and tourism/pilgrim infrastructure development works at Mostamanu temple complex Field Duration/ Magnitude Mitigation Measures Responsibility Extent agency. The parameters to be monitored, frequency and duration of monitoring as well as the locations to be monitored will be as per the Monitoring Plan prepared. 5.2 Increased Pollution load on the Temporary Moderate Increased Pollution load will be addressed through better facilities. Tourism Ecosystem in peak tourist season Solid waste management shall be through prevalent local ULB department system with provision of segregation at source through biodegradable and non- biodegradable bins (sub project component) or other alternate measures. Proper walkways in and around the temple complex shall be designated to minimize any chances of trampling impacts on vegetation and soil. The subproject will have positive impacts on the socio economic conditions of people of project area by way of providing better facilities, water supply & allied facilities 5.2 Unhygienic condition due to poor Permanent Moderate New facilities will cater to additional load. Regular maintenance of Tourism maintenance of sanitation facilities the toilets, collection and disposal of wastes will be carried out. department, and irregular solid waste collection Gram Panchayat, Van Panchayat

33

Initial Environmental Examination (IEE) Landscaping, floriculture and tourism/pilgrim infrastructure development works at Mostamanu temple complex V. ENVIRONMENTAL MANAGEMENT PLAN (EMP)

A. Institutional Arrangements

79. The institutional arrangements specify the arrangements for the implementation of environmental provisions of the entire project, and include the proposed subproject also.

Project Management Unit (PMU) and Project Implementation Unit (PIU) 80. The Department of Tourism, Government of Uttarakhand is the Executing Agency (EA). Project Management Unit (PMU) will be established in Dehradun for the overall project management and Project Implementation Units (PIU) will be established for each of the three circuits. The proposed sub-project will be implemented by the PIU, Bhimtal. A Safeguards Specialist is proposed within the PMU, and will be responsible for implementation of the resettlement and environmental safeguard provisions. A Forest Conservation Specialist is also proposed in PMU and DSC to look the matters of forests in all the projects.

Project Management Consultant (PMC) and Design and Supervision Consultants (DSC) 81. Project Management Consultants (PMC) and Design and Supervision Consultants (DSC) are recruited to provide assistance to the PMU and PIUs respectively in project implementation. Within the PMC team an Environment Safeguards Specialist will provide overall direction for management of environmental issues, and will provide technical support to the PMU including implementation of the environmental requirements according to ADB requirements, and assist in monitoring impacts and mitigation measures associated with sub-projects. The Safeguards Specialist of the DSC team will be responsible for preparation of the Environmental Assessment documents in line with the EARF and supervise the implementation of the EMP provisions in the various sub-projects. The PMU, will oversee the implementation of the environmental provisions related to subproject implementation, its responsibilities include preparation and updating of IEEs consistent with the ADBs Environmental Assessment Guidelines and the environmental compliance requirements of the Government of Uttarakhand and the Government of India. 82. The DSC Safeguards Specialist will support environmental management functions including updating sub-project IEEs in respect to environmental management plans, assisting in preparing IEEs, and assist in monitoring impacts and mitigation measures associated with sub-projects. He/she will be required to include mitigation measures in designs where appropriate, and to specify other measures in construction contracts. Contractors will be required by their contracts to implement all specified mitigation, monitoring, and reporting assigned to contractors as presented in sub-project IEE. Environmental monitoring will be undertaken by the PMU supported by the DSC- Safeguards Specialist. 83. Towards addressing the environmental issues in the project components during design and implementation, the DSC will include provisions for inputs of an Environmental Specialist. In addition to addressing the issues related to environmental management in the project, the Environmental Specialist will play a central role in ensuring capability building on Environmental Management of the PMU/PIU, Contractor and Line Departments.

34

Initial Environmental Examination (IEE) Landscaping, floriculture and tourism/pilgrim infrastructure development works at Mostamanu temple complex Sub Project Monitoring Committee

84. A sub project Monitoring Committee has been constituted to monitor, supervise and facilitate the execution of works in the sub project under the Chairmanship of Distt. Magistrate, & including the representatives of project stakeholders including Tourism department, Mostamanu temple Committee, Nagar Palika Parishad, Pithoragarh etc. and concerned villages to ensure successful project implementation and sustainability of project pertaining to Mostamanu site development and trek-trail development.

B. Environmental Management Plan 85. All works undertaken towards protection of environmental resources as part of the EMP and as part of good engineering practices while adhering to relevant specifications will be deemed to be incidental to works being carried out and no separate payment will be made unless otherwise specified explicitly. The costs towards environmental management as per EMP unless otherwise provided as a separate head, will be deemed to be part of the BoQ of the project. The scope of works of the contractor towards the implementation of the environmental provisions shall be as follows:

 Abide by all existing Environmental regulations and requirements of the Government of Uttarakhand and Government of India, during implementation,  Compliance with all mitigation measures and monitoring requirements set out in the environmental Management Plan (EMP)  Submission of a method statement detailing how the subproject EMP will be complied with as per the schedule of monitoring given in subsequent paragraphs.  Monitoring of project environmental performance and periodic submission of monitoring reports.  Compliance with all measures required for construction activities in line with the regulatory requirements and the guidelines set forth in the management plans for these areas.  Compliance of all safety rules and regulations applicable at work, and provision of adequate health and safety measures such as water, food, sanitation, personal protective equipment, workers insurance, and medical facilities.

86. The detailed provisions for specific environmental issues shall be as outlined in the Table 6. Key clauses are outlined in the following sections.

Debris Disposal . The contractor will, prior to start of construction operations, identify potential sites for disposal of construction debris, sites for general construction wastes. The contractor will obtain approval on identified sites from the Engineer of PIU and Supervision Consultant and disposal will be only after consent letter from the Engineer.

Precautions for protection of Environmental Measures . The Contractor shall ensure that construction activities do not result in any contamination of land or water by polluting substances.

35

Initial Environmental Examination (IEE) Landscaping, floriculture and tourism/pilgrim infrastructure development works at Mostamanu temple complex . Unless otherwise provided in the specifications, the Contractor shall ensure that no trees or shrubs or other vegetation are felled or harmed except those required to be cleared for execution of the works. The Contractor shall protect trees and vegetation from damage to the satisfaction of the Engineer.

. In the conduct of cleaning activities and operation of equipment, the Contractor will utilize such practicable methods and devices as are reasonably available to control, prevent and otherwise minimize air/noise pollution.

Noise and Air Pollution

. All works will be carried out without unreasonable noise and air pollution. Subject and without prejudice to any other provision of the Contract and the law of the land and its obligation as applicable, the Contractor will take all precautions outlined in the EMP to avoid the air and noise pollution.

. The Contractor shall monitor the environmental parameters periodically as specified in the monitoring plan and report to the Engineer. The Contractor shall reduce the dust emission due to construction activities by regular water sprinkling in the affected areas.

. All the construction equipments and vehicles shall have Pollution Under Control (PUC) Certificate to ensure that no air pollution may be caused due to operation of their equipments and vehicles. All the construction equipment and vehicles should remain all time in good conditions up to satisfaction of site engineers.

. The Contractor shall indemnify and keep indemnified the Employer from and against any liability for damages on account of noise or other disturbance created while carrying out the work, and from and against all claims, demands, proceedings, damages, costs, charges, and expenses, whatsoever, in regard or in relation to such liability.

Occupational Health and Safety During Construction

. The Contractor shall, in accordance with the safety and health provisions specified in the EMP, provide workers with a safe and healthy working environment, in the work areas, through application of preventive and protective measures consistent with international good practice, as reflected in internationally recognized standards such as the ADB’s Environment, Health and Safety Guidelines. The borrower/client will take steps to prevent accidents, injury, and disease arising from, associated with, or occurring during the course of work by-  Providing preventive and protective measures, including modification, substitution, or elimination of hazardous conditions or substances;  Providing appropriate equipment to minimize risks and requiring and enforcing its use;  Training workers and providing them with appropriate incentives to use and comply with health and safety procedures and protective equipment;  Documenting and reporting occupational accidents, diseases, and incidents; and  Having emergency prevention, preparedness, and response arrangements in place.  Provide first aid facilities in all the work sites and workers camp and having

36

Initial Environmental Examination (IEE) Landscaping, floriculture and tourism/pilgrim infrastructure development works at Mostamanu temple complex qualified first aider to give first aid at the time of any accident.  Contractor shall provide safe drinking water, clean eating and resting points.  Contractor shall prepare emergency response plan with full details and methods of emergency response during any accident and shall have and display the emergency Contact numbers at site.  Contractor should follow all the applicable rules and regulations for workers safety.

Post Construction Clearance

1. On completion of work, wherever applicable, the Contractor shall clear away and remove from the sites all constructional plant, surplus materials, rubbish, scaffoldings, and temporary works of every kind and leave the whole of the sites and works in a clean condition to the satisfaction of the Engineer. Table 7 presents a generic EMP to guide the contractor in mitigating environmental impacts. Table 7: Generic EMP to guide the contractor in mitigating environmental impacts

Sl. Environmental Mitigation Measures Location Implementation Supervision No. Issues 1 Location Impacts 1.1 Lack of sufficient Design will include provisions Subproject PIU / DSC PMU planning to assure for ensuring effective site long term maintenance and protection sustainability of the of the assets created so as to improvements and ensure the long term ensure protection of sustainability. the assets created Designs are to be worked out and the architectural and implemented in character of the accordance with the surroundings Uttarakhand architecture. 2 Design Impacts and Pre-construction Impacts 2.1 Layout of The project components Subproject PIU / DSC PMU components to avoid siting will avoid impacts on site impacts on the the aesthetics of the site and aesthetics of the site to ensure minimal impacts.

2.2 Slope stability Along areas vulnerable to Subproject PIU / DSC PMU related issues slope failures and along site steep stretches, the designs of subproject components will include slope protection measures for uncovered slopes as pitching, vegetation, benching, paving etc. 2.3 Increased storm Design of proposed Subproject PIU/DSC PMU water runoff from components will enable site alterations of the efficient drainage of the sites site’s natural and maintain natural drainage patterns drainage patterns. due to additional

37

Initial Environmental Examination (IEE) Landscaping, floriculture and tourism/pilgrim infrastructure development works at Mostamanu temple complex Sl. Environmental Mitigation Measures Location Implementation Supervision No. Issues structures and landscaping works in the area 2.4 Selection of Selection of materials and Subproject PIU / DSC PMU materials and construction technologies site construction proposed will strictly conform technologies, if not to the Uttarakhand carefully chosen, will architecture. Any new adversely impact the landscaping elements will aesthetic appeal of only utilize native species. the destinations 2.5 Integration of energy The detailed designs for the Subproject PIU/DSC PMU efficiency and energy sub-project components site conservation shall ensure environmental programs in design sustainability principles, of sub-project including energy efficiency, components water efficiency, use of indigenous materials, waste minimization, etc. 3 Pre -Construction Impacts 3.1 Circulation plan Prior to commencement of Subproject Contractor DSC / PIU during construction site activities and site in the tourist mobilization on ground, the destinations Contractor will prepare and get approved by the Engineer, circulation plan during construction for safe passage of tourists/pilgrims during construction stage, including development of alternative access routes, traffic regulations, signage, etc., during construction. The Contractor with support of the PIU will carry out dissemination of these information and circulation plan at key entry points to the respective destinations. 3.2 Site clearance Vegetation shall be removed Subproject Contractor DSC / PIU activities, including from construction site before site delineation of commencement of construction areas construction. All works shall be carried out such that the damage or disruption of flora other than those identified for cutting is the minimum. Only ground cover/shrubs that impinge directly on the permanent works or necessary temporary works shall be removed with prior approval from the Environmental Expert of DSC All areas used for temporary construction operations will

38

Initial Environmental Examination (IEE) Landscaping, floriculture and tourism/pilgrim infrastructure development works at Mostamanu temple complex Sl. Environmental Mitigation Measures Location Implementation Supervision No. Issues be subject to complete restoration to their former condition with appropriate rehabilitation procedures 3.3 Drinking water Sufficient supply of cold Subproject Contractor DSC/ PIU availability potable water to be provided site and maintained. If the drinking water is obtained from an intermittent public water supply then storage tanks will be provided. 3.4 Identification of sites The pre-identified disposal Subproject Contractor DSC/PIU for disposal of location shall be part of site construction and Comprehensive Waste demolition work Disposal Plan/ Solid Waste Management Plan to be prepared by the Contractor in consultation and with approval of Environmental Specialist of DSC. The Environmental Specialist of DSC shall approve these disposal sites after conducting a joint inspection on the site with the Contractor and the existing municipal body responsible for waste management in the area. Contractor shall ensure that waste shall not be disposed off near the water course or agricultural land, Orchards and Natural Habitats like Grasslands 4 Construction Impacts 4.1 Construction Camps Siting of the construction Constructio Contractor DSC/ PIU - Location, camps shall be as per the n camps Selection, Design guidelines below and details and Layout of layout to be approved by DSC. Construction camps shall not be proposed within 500m from the nearest settlements to avoid conflicts and stress over the infrastructure facilities with the local community. Location for stockyards for construction materials shall be identified at least 300m away from watercourses. Construction camps will be located away from settlements and drainage from and through the camps will not endanger any

39

Initial Environmental Examination (IEE) Landscaping, floriculture and tourism/pilgrim infrastructure development works at Mostamanu temple complex Sl. Environmental Mitigation Measures Location Implementation Supervision No. Issues domestic or public water supply. Construction camps including sanitation facilities must be adequately drained. 4.2 Defining of Construction work area will Subproject Contractor DSC / PIU/ construction/work be demarcated on ground. site areas on ground Free-standing fencing will be erected in advance of construction works to protect the working areas. 4.3 Stockpiling of Due consideration will be Subproject Contractor DSC/ PIU construction given for material storage site materials and construction sites such that it doesn‘t cause any hindrance to visitors movement within the site. Stockpiling of construction materials does not impact obstruct the drainage and Stockpiles will be covered to protect from dust and erosion. 4.4 Quarry Operations Contractor shall finalize the Quarry site Contractor DSC / PIU quarry for procurement of construction materials after assessment of the availability of sufficient quantity of materials, quality and other logistic arrangements. The Contractor shall obtain materials from quarries only after consent of the Department of Mines and Geology and District Administration. Adequate safety precautions will be ensured during transportation of quarry material from quarries to the construction site. Vehicles transporting the material will be covered to prevent spillage. 4.5 Arrangement for The contractor shall use Subproject Contractor DSC / PIU Construction Water ground/surface water as a site source of water for the construction with the written consent from the concerned Department. To avoid disruption/ disturbance to other water users, the Contractor shall extract water from fixed locations and consult DSC before finalizing the locations.

40

Initial Environmental Examination (IEE) Landscaping, floriculture and tourism/pilgrim infrastructure development works at Mostamanu temple complex Sl. Environmental Mitigation Measures Location Implementation Supervision No. Issues 4.6 Soil/land Erosion Slope protection measures Subproject Contractor DSC/ PIU will be undertaken as per site design to control soil erosion. 4.7 Water Pollution from The Contractor shall take all Subproject Contractor DSC/ PIU Construction Wastes precautionary measures to site prevent entering of wastewater into streams, water bodies or the irrigation system during construction. Contractor shall not wash his vehicles in river/stream water and shall not enter riverbed nearby the water resource area for that purpose. 4.8 Water Pollution from The Contractor shall ensure Subproject Contractor DSC/ PIU Fuel and Lubricants that all construction vehicle site parking locations, fuel/ lubricants storage sites, vehicle, machinery and equipment maintenance and refuelling sites shall be located at least 300 m away from rivers/streams Contractor shall ensure that all vehicle/machinery and equipment operation, maintenance and refuelling shall be carried out in such a manner that spillage of fuels and lubricants does not contaminate the ground. 4.9 Soil Pollution due to The fuel storage and vehicle Subproject Contractor DSC / PIU fuel and lubricants, cleaning area will be site construction waste stationed such that spillage of fuels and lubricants does not contaminate the ground. 4.10 Generation of dust The contractor will take every Subproject Contractor DSC /PIU precaution to reduce the site levels of dust at construction site. All earthworks to be protected/ covered in a manner to minimize dust generation. 4.11 Emission from The discharge standards Subproject Contractor DSC/ PIU Construction promulgated under the site Vehicles, Equipment Environmental Protection Act and Machinery will be strictly adhered to. All vehicles, equipment and machinery used for construction will conform to the relevant Standard. All vehicles, equipments and machinery used for construction will be regularly maintained to ensure that pollution emission levels

41

Initial Environmental Examination (IEE) Landscaping, floriculture and tourism/pilgrim infrastructure development works at Mostamanu temple complex Sl. Environmental Mitigation Measures Location Implementation Supervision No. Issues comply with the relevant requirements. 4.12 Noise Pollution The Contractor shall confirm Subproject Contractor DSC/ PIU that all Construction site equipment used in construction shall strictly conform to the MoEF/CPCB noise standards and all Vehicles and equipment used in construction shall be fitted with exhaust silencers. At the construction sites noisy construction work such as crushing, operation of DG sets, use of high noise generation equipment shall be stopped during the night time between 10.00 pm to 6.00 am. Noise limits for construction equipment used in this project will not exceed 75 dB (A). 4.13 Material Handling at Workers employed on mixing Subproject Contractor DSC/ PIU Site cement, lime mortars, site concrete etc., will be provided with protective footwear and protective goggles. Workers, who are engaged in welding works, will be provided with welder’s protective eye-shields. Workers engaged in stone breaking activities will be provided with protective goggles and clothing. The use of any toxic chemical will be strictly in accordance with the manufacturer’s instructions. The Engineer will be given at least 6 working days’ notice of the proposed use of any chemical. A register of all toxic chemicals delivered to the site will be kept and maintained up to date by the Contractor. 4.14 Disposal of The Contractor shall confirm Disposal Contractor DSC/ PIU Construction Waste / that safe disposal of the site Debris / Cut Material construction waste will be ensured in the pre-identified disposal locations. In no case, any construction waste will be disposed around the project site indiscriminately.

42

Initial Environmental Examination (IEE) Landscaping, floriculture and tourism/pilgrim infrastructure development works at Mostamanu temple complex Sl. Environmental Mitigation Measures Location Implementation Supervision No. Issues 4.15 Safety Measures Personal Protective Subproject Contractor DSC/ PIU During Construction Equipment for workers on the site project and adequate safety measures for workers during handling of materials at site will be taken up. The contractor has to comply with all regulations regarding safe scaffolding, ladders, working platforms, gangway, stairwells, excavations, trenches and safe means of entry and egress. The contractor has to comply with all regulations for the safety of workers. Precaution will be taken to prevent danger of the workers from fire, etc. First aid treatment will be made available for all injuries likely to be sustained during the course of work. The Contractor will conform to all anti-malaria instructions given to him by the Engineer. 4.16 Clearing of Contractor to prepare site Subproject Contractor DSC/ PIU Construction of restoration plans for approval site Camps and by the Engineer. The plan is Restoration to be implemented by the contractor prior to demobilization. On completion of the works, all temporary structures will be cleared away, all rubbish burnt, excreta or other disposal pits or trenches filled in and effectively sealed off and the site left clean and tidy, at the Contractor’s expense, to the entire satisfaction of the Engineer 5 Operation and Maintenance impacts 5.1 Environmental The periodic monitoring of Subproject Pollution Tourism Conditions the ambient air quality, noise site Monitoring Agency department / level, water (both ground and PMU surface water) quality, in the subproject area as suggested in environmental monitoring plan through an approved monitoring agency. 5.2 Uncontrolled tourism While the environment Subproject Tourism PIU/ PMU flow monitoring plan actions site department during the operation stage will monitor the environmental impacts during implementation, the Tourist flow will be regulated

43

Initial Environmental Examination (IEE) Landscaping, floriculture and tourism/pilgrim infrastructure development works at Mostamanu temple complex Sl. Environmental Mitigation Measures Location Implementation Supervision No. Issues as per the Carrying capacity assessment* and the Tourism Master Plan recommendations will be implemented strictly to avoid uncontrolled tourism flow. 5.3 Unhygienic condition The temple committee will Subproject Temple Tourism due to poor carry out maintenance of the site Committee in Department maintenance of toilets, and carry out the coordination with sanitation facilities regular collection and Gram Panchayat, and irregular solid disposal of wastes to a Van Panchayat waste collection designated waste treatment site in consultation with the local municipal body. The Tourism Dept. will ensure that sanitation improvements do not result in pollution of surface/ground water and do not cause nuisance to neighboring areas. The transfer of waste will also ensure no spillage and waste transportation/disposal to the designated treatment site will be done in consultation with the municipal body.

C. Environmental Monitoring Plan

87. Environmental monitoring will be done during construction in three levels; namely monitoring development of project performance indicators done by the DSC Environmental Specialist, monitoring implementation of mitigation measures done by the Contractor; and overall regulatory monitoring of the environmental issues done by the PMU Environmental Specialist. The Environmental Monitoring Plan for the project is presented in Table-8. The proposed monitoring of all relevant environmental parameters, with a description of the sampling stations, frequency of monitoring, applicable standards and responsible agencies are presented.

Table 8: Environmental Monitoring Plan S. Attributes Stage Parameters Location Frequency Responsibility No. to be Monitored 1 Debris Construction Safe disposal of Major Random checks Contractor /Construction Stage construction construction materials wastes including sites bituminous disposal wastes 2 Ambient Air Construction PM10, SO2, NO2, Major Once in a season Contractor, to be Quality Stage CO construction (except monitor through sites monsoons) for the engagement of

44

Initial Environmental Examination (IEE) Landscaping, floriculture and tourism/pilgrim infrastructure development works at Mostamanu temple complex S. Attributes Stage Parameters Location Frequency Responsibility No. to be Monitored entire construction agency approved period under NABL Accreditation norm 3 Water quality Construction TDS, TSS, pH, Three Twice a year (pre- Contractor, to be stage DO, BOD, COD, Locations monsoon and monitor through Faecal Coliform, post- monsoon) engagement of Ammonia, for the entire agency approved Nitrogen, period of under NABL Organophosphat construction Accreditation norm es, 4 Noise Levels Construction Equivalent Day All Once in a season Contractor, to monitor and & Night Time Construction during through on approved Operation Noise Levels sites construction and Monitoring Agency Stage operation stages 5 Supply of Construction Provision of PPE All Continuous Contractor PPE Stage on site, Construction adequacy of sites equipment

D. Capacity Building

Institutional Strengthening 88. The Department of Tourism, Government of Uttarakhand is the Executing Agency (EA). Project Management Unit (PMU) will be established in Dehradun for the overall project management. This sub-project will be implemented by the PIU, Bhimtal. A Safeguards Specialist is proposed within the PMU, and will be responsible for implementation of the resettlement and environmental safeguard provisions. Project Management Consultants (PMC) and Design and Supervision Consultants (DSC) are recruited to provide assistance to the PMU/PIUs in project implementation. Within the PMC team a Safeguards Specialist will provide overall direction for management of environmental and social issues, and will provide technical support to the PMU including implementation of the environmental and resettlement requirements according to ADB requirements, and assist in monitoring impacts and mitigation measures associated with sub- projects. The Safeguards specialist of the DSC team will be responsible to assist in preparation of IEE and EMP report and supervise the implementation of the EMP provisions in the sub- projects. The PMU will oversee the implementation of the environmental provisions related to subproject implementation, consistent with the ADBs Environmental Assessment Guidelines and the environmental compliance requirements of the Government of Uttarakhand and the Government of India.

Training and Capacity Building 89. The Environmental Specialist of the PMC and DSC will provide the basic training required for environmental awareness followed by specific aspects of infrastructure improvement projects along with environmental implications for projects located within / in the vicinity of natural and cultural heritage sites. Specific modules customized for the available skill set will be devised after assessing the capabilities of the members of the Training Programme and the requirements of

45

Initial Environmental Examination (IEE) Landscaping, floriculture and tourism/pilgrim infrastructure development works at Mostamanu temple complex the project. The entire training would cover basic principles of environmental assessment and management; mitigation plans and programmes, implementation techniques, monitoring methods and tools. The proposed training program along with the frequency of sessions is presented in Table 9 below.

Table 9: Training Modules for Environmental Management Training Form of Duration/ Program Description Participants Conducting Training Location Agency A. Pre-Construction Stage Sensitization Introduction to Environment: Tourism / Forest / Workshop 1 Environmental Workshop Basic Concept of Roads / Culture Working Specialist of environment Environmental Department Day the PMC Regulations and Statutory Officials, Project requirements as per Director (PD) and Government of Environmental India and ADB Specialist (ES) of the PMU/PIU Session I Module I Introduction to Environment: PMU/PIU Lecture 1Working Safeguards Basic Concept of (including the ES) Day Specialist of environment Safeguards and Engineering the PMC Regulations and Statutory staff of the requirements as per Govt. of implementing India and ADB Guidelines on agencies cultural resources, Environmental considerations in planning, design and implementing projects

Module II Environmental components PMU/ PIU Workshop 1 Safeguards impacted in construction and (including Working Specialist of operation stages Activities the ES) and Day the PMC causing pollution during Engineering staff construction and operation of Tourism dept stages Environmental Management Environmental Provisions Implementation Arrangements Methodology of Assessment Good engineering practices to be integrated into contract documents Module III Improved Co-ordination with PMU/PIU Lecture / 1Working Safeguards Other Departments: (including Interactive Day Specialist of the ES) and Statutory Permissions – Sessions the Engineering staff PMC Procedural Requirements of Co-operation & Coordination Tourism dept with other Departments.

46

Initial Environmental Examination (IEE) Landscaping, floriculture and tourism/pilgrim infrastructure development works at Mostamanu temple complex Training Form of Duration/ Program Description Participants Conducting Training Location Agency Module IV Environmental PMU/PIU Lecture / 2 Working Safeguards considerations (including the ES) Interactive days specialist of in planning, designing and and Engineering Sessions the PMC with implementing heritage staff of and site support from Tourism dept the buildings and conservation visits Conservation projects specialist of the PMC

Module V Environmental principles of Local Community Lecture / 1 Specialist eco-tourism (as per Groups, NGOs Interactive Working from DSC Uttarakhand eco tourism Sessions Day and PIU policies) and training and awareness building on Conservation and management aspects of the area.

B. Construction Stage Session II Module VI Role during Construction- Engineers and Lecture / 1 Safeguards Roles and Responsibilities of staff of line Interactive Working Specialist of officials / contractors / departments of the Sessions Day the consultants towards DSC Government of protection of environment Implementation Uttarakhand, and Arrangements Monitoring PMU/PIU mechanisms (including the ES) Module VII Monitoring and Reporting Engineers and Lecture / 1 Safeguards System staff of Interactive Working Specialist of implementing Sessions Day the DSC agencies and PMU/PIU (including the ES) Session III Module VIII Skill upgrade on ecotourism Youth in the Site visits, 2 Tourism and nature guides villages in the interactive working department periphery, and Hospitality, Interpretational sessions days skills, micro- planning, other NGOs in the Biodiversity etc district Notes: PMU = Project Management Unit; PIU = Project Implementation Unit; PMC = Project Management Consultant; DSC = Design and Supervision Consultant; ES = Environment Specialist; NGO= non- government organization

E. Environmental Budget 90. As part of good engineering practices in the project, there have been several measures as erosion prevention, rehabilitation of borrow areas, safety, signage, provision of temporary drains, etc., the costs for which will be included in the design costs of specific subprojects. Therefore, these items of costs have not been included in the IEE budget. Only those items not covered under budgets for construction are considered in the IEE budget.

47

Initial Environmental Examination (IEE) Landscaping, floriculture and tourism/pilgrim infrastructure development works at Mostamanu temple complex 91. This is a small construction project and there are no major structures to be constructed therefore it is not expected to cause much significant air, water and noise pollution. The main EMP cost will arise from monitoring of environmental parameters (air, water and noise).

92. The costs of personal protective equipments to construction workers shall be borne by contractor as part of conditions of contract. In addition the sources of funds for Mitigation measures during construction stage including monitoring during construction stage are also to be borne by the contractor. These are deemed to be included as part of the contract price amount quoted by the contractor for the works. The costs of components for monitoring in operation stage and the capacity building costs are to be funded by the PMU. The EMP cost is given in the Table 10.

Table 10: Environmental Budget S. Particulars Stage Unit Total Rate Cost (INR) Source of No. number (INR) fund A. Monitoring Measures During Construction Period 1 Water quality Construction Per 12 samples 8,000 96,000 Contractor sample {Twice a year (pre monsoon and Post Monsoon) at three locations (Surface and bottom)} 2 Air quality Construction Per 12 nos. 9,000 108,000 Contractor monitoring sample {Once per season at three locations for pre- monsoon and post- monsoon season} 3 Noise Levels – Construction Per 18 samples 2,000 36,000 Contractor silence zones Sample {Once in a season for 3 seasons at three locations}

B. Monitoring Measures During Operation Phase 1 Noise Levels – Operation Per 6 samples 2,000 12,000 O & M silence zones Sample {Once in a season for 3 contractor seasons at three locations}

2 Disposal of Operation - 16 samples 8,000 128,000 O & M Sewage and {Twice a year (pre contractor effluents monsoon and post monsoon) at four locations (Surface and Sub -Total (A+B) 3,80,000 C. Capacity Building (All the workshops and trainings will be held in Pithoragarh)

1 Sensitization Pre- L.S 1,00,000 PMU Workshop Construction 2 Training Session Pre- L.S 4,00,000 PMU I Construction 3 Training Session Construction L.S 2,00,000 DSC II

48

Initial Environmental Examination (IEE) Landscaping, floriculture and tourism/pilgrim infrastructure development works at Mostamanu temple complex S. Particulars Stage Unit Total Rate Cost (INR) Sou rc e of No. number (INR) fund 4 Training Session Construction L.S 5,00,000

Sub -Total (C) 12,00,000

Total Rupees Fifteen Lakhs and Eighteen Thousand only (A+B+C) 15,80,000

*The above costs are subject to change based on actual number of samples and locations due to implementation of 03 subprojects in the same area.

F. Environmental Monitoring and Reporting

93. The PMU will monitor and measure the progress of EMP implementation. The monitoring activities will be corresponding with the project’s risks and impacts and will be identified in the EIAs/IEEs for the subprojects. In addition to recording information of the work, deviation of work components from original scope, the PMU and PIU will undertake site inspections and document

review to verify compliance with the EMP and progress toward the final outcome. 94. DSC will submit monthly monitoring and implementation reports to PIU, who will take follow- up actions, if necessary. PIU will submit the quarterly monitoring and implementation reports to PMU who will then submit to the PD. The PMU will submit semi-annual monitoring reports to ADB. Project budgets will reflect the costs of monitoring and reporting requirements. For subprojects likely to have significant adverse environmental impacts during operation, reporting will continue at the minimum on an annual basis. Monitoring reports will be posted in a location accessible to the public. 95. For projects likely to have significant adverse environmental impacts, the EA will retain qualified and experienced external experts to verify its monitoring information. The EA will document monitoring results, identify the necessary corrective actions, and reflect them in a corrective action plan. The EA, in each quarter, will study the compliance with the action plan developed in the previous quarter. Compliance with loan covenants will be screened by the EA.

96. ADB will review project performance against the EA’s commitments as agreed in the legal documents. The extent of ADB's monitoring and supervision activities will be commensurate with the Project’s risks and impacts. Monitoring and supervising of social and environmental safeguards will be integrated into the project performance management system. ADB will monitor projects on an ongoing basis until a project completion report is issued. ADB will carry out the following monitoring actions to supervise project implementation:

o conduct periodic site visits for projects with adverse environmental or social impacts; o conduct supervision missions with detailed review by ADB’s safeguard specialists/ officers or consultants for projects with significant adverse social or environmental impacts; o review the periodic monitoring reports submitted by EA to ensure that adverse impacts and risks are mitigated as planned and as agreed with ADB; o work with EA to rectify to the extent possible any failures to comply with their safeguard commitments, as covenanted in the legal agreements, and exercise remedies to re- establish compliance as appropriate; and prepare a project completion report that assesses whether the objective and desired outcomes of the safeguard plans have

49

Initial Environmental Examination (IEE) Landscaping, floriculture and tourism/pilgrim infrastructure development works at Mostamanu temple complex been achieved, taking into account the baseline conditions and the results of monitoring.

VI. PUBLIC CONSULTATION AND INFORMATION DISCLOSURE

A. Process for Consultation followed 97. During Project preparation, consultations have been held with the District Administration, Nagar Palika, Forest Department, Mostmanu Mandir Committee, public representatives of project area villages, Hotel Owners, villagers of concerned various villages in vicinity of sub-project site and tourists on project orientation, issues pertaining to land acquisition problems and addressing the current gaps in provision of basic services and improvement of tourist infrastructure. These consultations (Table-11) provided inputs in identification of the felt needs of the communities, and the relevant stakeholders. Photographs of consultations are attached as Annexure-6 with this report.

Table 11: Consultations with Stakeholders S. Place Date Consulted Issues discussed / Output Received No. persons/ Community 1. Pithoragarh 07-10 April  Local Community  Preliminary Site visit for Preparation & Chandak 2013  Nagar Palika of Inception Report  Collection of Secondary Information  Introduction to Stakeholders 2. Pithoragarh & 11-12 July  Mostmanu Temple  Meeting with Mostamannu Temple Chandak 2013 Committee Committee Minutes to be provided  Project Orientation to Committee  Project Orientation and Need Assessment  Transect walk around chandak trekking trail  Baseline information collection

3. Pithoragarh & 10-12  Temple  Meeting with Temple Committee Chandak September Committee Members 2013  CDO  NOC from Nagar Palika and Mandir  DM committee received  Nagar Palika  Trek Trail and Mostamannu Temple Survey

4. Pithoragarh & 21-22  Temple  Sharing of plans and Survey findings Chandak September Committee 2013  CDO  DM  Nagar Palika

50

Initial Environmental Examination (IEE) Landscaping, floriculture and tourism/pilgrim infrastructure development works at Mostamanu temple complex S. Place Date Consulted Issues discussed / Output Received No. persons/ Community 5. Pithoragarh & 30-09-2013  Temple  Subproject Monitoring Committee Chandak & 01-10- Committee Meeting 2013  CDO Minutes Annexure 9  DM  DTO

6. Most Manu 10-10-2013  Mela committee  Plan was shared with local peoples Temple  Local shop and mela committee Complex keepers  Major issues of mela committee were  Local tourists discussed  Major problems identified include toilet facility and drinking water Annexure 9

7. Pithoragarh & 26-29  Temple  Collection of Revenue Records Chandak October Committee 2013  Forest Department  Nagar Palika  Tehsildar

8. Pithoragarh & 26-30  CDO Minutes of Meeting enclosed as Chandak December  DM Annexure 9 2013 9. Pithoragarh & 06-09  Temple Minutes of Meeting enclosed as Chandak January Committee Annexure 9 2014  CDO  DM

10. Public Annexure - 10 Disclosure through news media

B. Future Consultation and Information Disclosure 98. To ensure continued public participation, provisions to ensure regular and continued stakeholder participation, at all stages during the project design and implementation is proposed. A grievance redress cell will be set up within the PIU and PMU to register grievances of the people regarding technical, social and environmental aspects. This participatory process will ensure that all views of the people are adequately reviewed and suitably incorporated in the design and implementation process. Further, to ensure an effective disclosure of the project proposals to the stakeholders, an extensive project awareness campaign will be carried out. 99. For the information and benefit of the community the summary of IEE will be translated in the local language (Hindi) and made available at: (i) Office of the PIU/PMU; and, (ii) Office of the

51

Initial Environmental Examination (IEE) Landscaping, floriculture and tourism/pilgrim infrastructure development works at Mostamanu temple complex District Magistrate, Pithoragarh and other relevant line departments in the District. These copies will be made available free of cost to any person seeking information on the same. Hard copies of the IEE will be available in the PMU/PIU as well as the district library at Pithoragarh, and accessible to citizens as a means to disclose the document and at the same time creating wider public awareness. On demand, the person seeking information can obtain a hard copy of the complete IEE document at the cost of photocopy from the office of the PMU/PIU, on a written request and payment for the same to the Project Director. Electronic version of the IEE will be placed in the official website of the Tourism Department and the website of ADB after approval of the documents by Government and ADB. This will create awareness of the project implementation among the public.

C. Grievance Redress Mechanism 100. The affected person/aggrieved party can give their grievance verbally or in written to the local grievances committee. Grievances of affected person will first be brought to the attention of the implementing NGO who can resolve the issue at site level. If the matter is not solved within 7 days period by the NGO or PIU, it will be brought to the Grievance Redress Committee constituted for the purpose in PIU. This GRC shall discuss the issue in its monthly meeting and resolve the issues within one month of time after receiving the grievance. If the matter is not resolved by GRC at PIU level within stipulated time, it shall be referred to GRC at PMU level by Executive Engineer of PIU. 101. GRC at PMU shall discuss the issue and try to resolve it and inform the PIU accordingly. If the matter is not resolved by the GRC at PMU level within one month of time, the aggrieved person/party can bring the matter to The Court of Law. The PIU shall keep records of all grievances received including contact details of complainant, date of receiving the complaint, nature of grievance, agreed corrective actions and the date these were affected and final outcome. The grievance redress process is shown below.

Composition and functions of GRC

102. Local Grievance Committee.(LGC) – In this LGC has worked with NGO, SHG, Line Agency, representative of Gram Panchayat ,Special invitee. 103. Grievance Redress Committee (GRC) at PIU- In each PIU there shall be one GRC, which will include Project Manager (PIU), District Tourist Officer of Department of Tourism of Govt. Of Uttarakhand, Community Development Officer of PIU, nominated representative of District Magistrate and nominated representative committee shall be headed by Project Manager (PIU). The committee will meet at least once in every month. Agenda of meeting shall be circulated to all the members and affected persons/aggrieved party along with venue, date and time; informed in written at least 7 days in advance of meeting. The matters shall remain with GRC at PIU level for one month and if grievance is not resolved within this time period, the matter shall be referred to GRC at PMU. 104. GRC within Environmental and Social Management Cell (ESMC) at PMU- There shall be one GRC in PMU. The matters not resolved by the GRC at PIU level within one month shall come under GRC at PMU. GRC at PMU will include Community Development Expert of PMU,

52

Initial Environmental Examination (IEE) Landscaping, floriculture and tourism/pilgrim infrastructure development works at Mostamanu temple complex Safeguard Specialist of PMU and Additional Project Director (APD) of PMU. The Committee shall be headed by APD of PMU. This committee shall look the matters, which are referred to and not resolved by GRC at PIU level. If the matter is not resolved by the GRC at PMU level within one month of time, the aggrieved person/party can bring the matter to The Executive Committee/State Level Empowered Committee (SLEC).

Approach to GRC 105. Affected person/aggrieved party can approach to GRC for redress of his/their grievances through any of the following modes- (a) Web based: A separate corner will be developed at the program website so that public / community/ affected person can register their complaint in the online column. (b) Telecom based: A toll free no. Will be issued by the PMU/ PIU so that general public can register their complaint through telephone / mobile phone to the PIU/PMU office. (c) Through implementing NGO: The local representative of the NGO appointed for the purpose will collect the problems & issues of the community or affected person and pass on the same to PIU/ PMU.

Figure 1: Grievance Redress Mechanism in IDIPT, Uttarakhand Note: 1. LGC - NGO, SHG, Line Agency, Representative of Gram Panchayat, Special invitee 2. GRC – PM, CDO, Engineer, DFO, DTO, SDM 3. GRC in Environment and Social Management Cell (ESMC) – PMU (APD, SS, CDS, FS), PMC (EE, CDE)

53

Initial Environmental Examination (IEE) Landscaping, floriculture and tourism/pilgrim infrastructure development works at Mostamanu temple complex VII. FINDINGS & RECOMMENDATIONS

106. The proposed components of the project are in line with the sub-project selection criteria for the IDIPT. The subproject conforms to all GoI, GoUK and ADB regulations, policies, and standards including all necessary government permits and clearances. 107. The significance of the environmental impacts will be more due to the construction related impacts. It is to be noted that the resultant potential impacts from these proposals can be offset through provision of proven mitigation measures during the design and adoption of good engineering practices during construction and implementation. Further, the provision of environmental infrastructure will better the environmental conditions and minimize the pollution related and aesthetic quality near the tourist areas and the other destinations. 108. The specific management measures laid down in the IEE will effectively address any adverse environmental impacts due to the sub-project. The effective implementation of the measures proposed will be ensured through the building up of capacity towards environmental management within the PMU supplemented with the technical expertise of a Safeguards Specialist as part of the DSC Consultants. Further, the environmental monitoring plans provide adequate opportunities towards course correction to address any residual impacts during construction or operation stages.

VIII. CONCLUSIONS

109. As Mostmanu temple is a site of great regional significance, attracting a number of pilgrims and devotees regularly and during the annual fair, the sub project aims to enhance the visitor experience by up-gradation of public amenities as well as consideration of environmental safeguards to protect the environmental integrity of the site which forms the basis of the project interventions envisaged for the site. The asset creation around the Temple will involve the creation of a Public Good, benefiting the general populace. It is expected that the proposed subproject will enhance economic growth and provision of livelihood opportunities for local communities with a focus on preservation and development of natural and cultural heritage and incidental services. The proposed Project under the Facility is provided to support the State of Uttarakhand, to enhance and develop the tourism sector as a key driver for economic growth. 110. The IEE carried out for the sub-project show that the proposed sub-components will result in net environmental benefits in terms of enhanced tourism facilities and revenue generation, and that any adverse environmental impact can be addressed through proper location, planning, and design of the proposed sub-project; control of construction activity and mitigation measures. The EMP provided for mitigation of all identified short term impacts and the contract clauses for the environmental provisions will be part of the civil works contracts. Further, the proposed designs have been consulted with the stakeholders and no significant issues requiring redress in terms of environmental safeguards exist.

54

Initial Environmental Examination (IEE) Landscaping, floriculture and tourism/pilgrim infrastructure development works at Mostamanu temple complex

ANNEXURE- I

RAPID ENVIRONMENTAL ASSESSMENT (REA) CHECKLIST

Instructions:

i. The project team completes this checklist to support the environmental classification of a project. It is to be attached to the environmental categorization form and submitted to the Environment and Safeguards Division (RSES) for endorsement by the Director, RSES and for approval by the Chief Compliance Officer. ii. This checklist focuses on environmental issues and concerns. To ensure that social dimensions are adequately considered, refer also to ADB's (a) checklists on involuntary resettlement and Indigenous Peoples; (b) poverty reduction handbook; (c) staff guide to consultation and participation; and (d) gender checklists.

iii. Answer the questions assuming the “without mitigation” case. The purpose is to identify potential impacts. Use the “remarks” section to discuss any anticipated mitigation measures.

Country/Project Title: IDIPT: India/ Uttarakhand, Landscaping, floriculture and tourism/pilgrim infrastructure development works at Mostmanu temple complex

SCREENING QUESTIONS Yes No REMARKS A. Project Siting: Is the project area adjacent to or within any of the following areas?  Densely populated?  Sparsely populated and around 15 villages in periphery of around 5-8 kms.  Heavy with development  activities?  Adjacent to or within any  Van Panchayat Bhakarkatiya environmentally sensitive areas?  Cultural heritage site   Protected Area   Wetland   Mangrove   Estuarine   Buffer zone of protected  area  Special area for protecting  biodiversity  Bay  B. Potential Environmental Impacts Will the Project cause….

55

Initial Environmental Examination (IEE) Landscaping, floriculture and tourism/pilgrim infrastructure development works at Mostamanu temple complex SCREENING QUESTIONS Yes No REMARKS  Impacts on the  During construction demolition waste and sustainability of associated excavated soil is expected as solid waste, sanitation and solid waste disposal which shall be disposed as per norms/ systems and their interactions with provisions in the EMP. Sub project entails other urban services. provision of sanitation and solid waste management system. During Operation stage these impacts shall result if the sanitation and solid waste management systems are not maintained in the proposed sites. It will also be dependent on the efficiency/capability of community institutions and inaction of environmental laws developed by community.  Deterioration of  Presently there is sparse population growth in surrounding environmental the range of 8 kms from the Temple. conditions due to rapid urban The project involves minor construction works with addition of amenities and such population growth, commercial interventions shall contribute to enhanced and industrial activity, and visitor experience due to added facilities, increased waste generation to the which is not anticipated to result in heavy point that both manmade and population growth. natural systems are overloaded The impacts pertaining to regulation of tourist and the capacities to manage movements, etc. will be addressed through these systems are overwhelmed? an assessment of the carrying capacity and sustainable development. (proposed to be carried out by GoI)  Degradation of land and  ecosystems (e.g. loss of wetlands and wild lands, coastal zones, watersheds and forests)?  Dislocation or involuntary  resettlement of people  Degradation of cultural  The sub project interventions will lead to property, and loss of cultural enhancement in an improved environment in heritage and tourism revenues? and around the temple site through improved infrastructural services and better amenities.  Occupation of low-lying  No such conditions in the proposed site. lands, floodplains and steep hillsides by squatters and low- income groups, and their exposure to increased health hazards and risks due to pollutive industries?  Water resource problems  Only water from public water supply scheme shall be used. (e.g. depletion/ degradation of available water supply, No use of ground water or any other surface water is proposed. deterioration for surface and

56

Initial Environmental Examination (IEE) Landscaping, floriculture and tourism/pilgrim infrastructure development works at Mostamanu temple complex SCREENING QUESTIONS Yes No REMARKS ground water quality, and pollution of receiving waters?  Air pollution due to urban  emissions?  Risks and vulnerabilities  Only physical hazards to workers due to related to occupational health accidents may come across during and safety due to physical, construction for which safety of workers chemical and biological should be taken in priority. hazards during project construction and operation?  Social conflicts between  Local labor will be hired construction workers from other areas and local workers?  Road blocking and  temporary flooding due to land excavation during rainy season?  Noise and dust from  Minor impact envisaged during the construction activities? construction and post construction activity due to construction machinery and equipment. Adoption of mitigation measures shall effectively address such impact during construction.  Traffic disturbances due to  Minor impact envisaged during construction construction material transport near temple premises adjacent to the road. and wastes? Due care will be taken during construction to avoid traffic disturbances  Temporary silt runoff due to  Temporary silt runoff is expected due to construction? construction activities which is required to be mitigated by silt traps and preventing the washing away of construction material into drainage system through suitable means.  Hazards to public health  Minor construction works proposed. Impacts due to ambient, household and envisaged only during construction activity. occupational pollution, thermal Adoption of mitigation measures shall inversion, and smog formation? effectively address such impact during construction  Water depletion and/or  Not envisaged due to use of existing water degradation? supply system  Overpaying of ground  Not expected water, leading to land subsidence, lowered ground water table, and salinization?  Contamination of surface Due to increase in tourist inflow, it is and ground waters due to envisaged that garbage and other solid waste improper waste disposal? may increase which may result in

57

Initial Environmental Examination (IEE) Landscaping, floriculture and tourism/pilgrim infrastructure development works at Mostamanu temple complex SCREENING QUESTIONS Yes No REMARKS contamination of land and water. Adoption of mitigation measures like implementation of environmental laws, developing solid waste management systems like composting etc. shall effectively address such impact during construction and post construction.  Pollution of receiving  waters resulting in amenity losses, fisheries and marine resource depletion, and health problems?  Large population influx  during project construction and operation that causes increased burden on social infrastructure and services (such as water supply and sanitation systems)?  Social conflicts if workers  from other regions or countries are hired?  Risks to community health  and safety due to the transport, storage, and use and/or disposal of materials such as explosives, fuel and other chemicals during operation and construction?  Community safety risks  due to both accidental and natural hazards, especially where the structural elements or components of the project are accessible to members of the affected community or where their failure could result in injury to the community throughout project construction, operation and decommissioning? Climate Change and Disaster Risk Questions The following questions are not for environmental categorization. They are included in this checklist to help identify potential climate and disaster risks.

 Is the Project area subject  The project area is located in an area prone to hazards such as earthquakes, to landslides, cloud bursts, earthquakes etc floods, landslides, tropical as it is located in the seismic Zone V as per cyclone winds, storm surges, IS 1893:2002.

58

Initial Environmental Examination (IEE) Landscaping, floriculture and tourism/pilgrim infrastructure development works at Mostamanu temple complex SCREENING QUESTIONS Yes No REMARKS tsunami or volcanic eruptions and climate changes  Could changes in  The project area lies in the hilly region having precipitation, temperature, landslides a major environmental problem salinity, or extreme events over during monsoons. In case of such events, the the Project lifespan affect its road blockage may hamper project progress. sustainability or cost?  Are there any demographic  or socio- economic aspects of the Project area that are already vulnerable (e.g. high incidence of marginalized populations, rural- urban migrants, illegal settlements, ethnic minorities, women or children)?  Could the Project  Impact on climatic or disaster vulnerability not potentially increase the climate or anticipated. disaster vulnerability of the Due to development of tourism infrastructure, surrounding area (e.g., increasing it is envisaged that tourist inflow in the area traffic or housing in areas that will will increase resulting to increase solid waste be more prone to flooding, by and noise pollution in the area. Also more encouraging settlement in enterprises like home-stays and shops are earthquake zones)? likely to come. Regulation based on carrying capacity shall address such problems in future.

59

Initial Environmental Examination (IEE) Landscaping, floriculture and tourism/pilgrim infrastructure development works at Mostamanu temple complex

ANNEXURE- 2

COMPLIANCE WITH SUB PROJECT SELECTION CRITERIA (AS PER EARF TABLE 6)

Component Criteria Remarks Overall 1. Will be fully consistent with management plans or No specific Management plan for the area. selection master plans for the area 2. Will avoid resettlement/relocation. If unavoidable No such impact anticipated. criteria the extent of resettlement will be minimized. (DDR prepared and approved dt. 13.06.14) 3. Will not result in destruction of or encroachment No environmentally sensitive zones in the onto protected areas, including National Parks. vicinity Sanctuaries, Conservation Reserves and Community Reserves, environmentally sensitive zones and Biosphere reserves. 4. Will be in line with the Conservation NA Plan/management plan for the conservation and management of the Protected areas 5. Will promote tourism related activities in protected The site is already a known religious tourism areas, in the zones earmarked for tourism point where the project interventions will development, the scale and extent of which shall be supplement infrastructure for tourism. in line with the provisions in the Management Plan 6. Will not result in destruction of or encroachment Not an ASI Site onto archaeological monuments/heritage sites and will be in line with the master plan proposals for the conservation and preservation of the site/monuments 7. Will not involve major civil works within the Not an ASI Site prohibited and regulated areas, as defined in the ASI refutations, to minimize any potential impacts on safety to the structures/ monuments 8. Will reflect inputs from public consultation and Meaningful public consultations have been disclosure for site selection done from planning phase and inputs have been considered in the project design 9. Will not introduce any elements or components No such intervention proposed. The that are invasive upon the sanctity and significance sanctity of the site as a religious center shall of the cultural heritage site, including large scale be retained commercial activities or creation of new land uses with potential to trigger induced development and land use changes around the sites 10. Will introduce landscaping and other tourist No new/alien species shall be introduced. infrastructure in line with the environmental quality Landscaping plan has been prepared to of the tourist destinations, such as landscaping in enhance the natural and scenic beauty of harmony with the natural vegetation and diversity the place. Only native and drought tolerant and not encourage introduction of species that are species will be planted. invasive 11. Will not result in development of physical O&M has been linked with the local infrastructure/ tourism amenities that would impair stakeholders to ensure project the environmental conditions due to lack of sustainability and enhanced environment management capacities or high O&M costs management.

60

Initial Environmental Examination (IEE) Landscaping, floriculture and tourism/pilgrim infrastructure development works at Mostamanu temple complex Component Criteria Remarks Conservation 12. Will observe the principle of not altering the historic T L TP measures and condition and shall involve treatment of damage Infrastructure Development Works at excavation caused by natural processes and human actions and M T C are centered measures-in prevention of further deterioration, using both on reinforcing the existing linkages of the and around technical and management measures. temple site to its surrounding regions by Cultural enhancing its historic and religious values properties and and supporting the age-old pilgrimage and protected cultural practices to sustainably develop the Monuments/ site Structures. 13. Will promote in situ conservation and only in the face of uncontrollable natural threats and relocation is the sole means of saving elements of a site may they be moved in their historic condition. 14. Will ensure that intervention be minimal. Every Designs are in sync with the architectural intervention proposed shall have clear objectives character of the surroundings and use tried and proven methods and materials. 15. Will ensure that physical remains are conserved in It is proposed to enhance the spiritual their historic condition without loss of evidence. experience of the site through minimal Respect for the significance of the physical emails interventions which will not compromise must guide any restoration. Technical interventions original fabric of the site. should not compromise subsequent treatment of the original fabric. The results of intervention should be unobtrusive when compared to the original fabric or to previous treatments, but still should be distinguishable 16. Will ensure that the adaptive reuse of any particular Sub project interventions only focus on building of monuments/structures does not intrude developing tourist amenities in the temple or induce impacts on other areas of the monument complex and landscaping to enhance visitor experience. 17. Will ensure preservation of traditional technology Project designs are based on guidelines and craftsmanship. New materials and techniques conforming to Uttarakhand architecture may only be used after they have been tried and proven, and should in no way cause damage to site. 18. Will ensure that the setting of a heritage site be Approach has been centered on reinforcing conserved. Natural and cultural landscapes that the existing linkages of the temple site to its form part of a sites setting contribute to its surrounding regions by enhancing its significance and should be integrated with its historic and religious values and supporting conservation the age-old pilgrimage and cultural practices to sustainably develop the site 19. Will ensure that during archaeological excavation NA care be taken to conserve the physical remains. A practical plan for the conservation of a site-both during and after excavation-should be submitted for all site programmed for excavation 20. Will ensure that treatment of the cultural heritage Incidental landscaping of appreciation site and its environs is a comprehensive measure to foregrounds with minimal interventions to prevent damage form natural processes and human enhance and appreciate the scenic beauty actions, to reveal the historic condition of a site, and of the place has been proposed. to allow its rational use. The existing specimens of a rare tree, the Service building should be as far as possible form Shilling (Osmanthus fragrans), which has the principal area of the site. religious significance is retained and the Landscaping should aim to restore the site to its stepped platform renovated so as to ensure historic state and should not adversely affect the that the roots of the tree receive proper water and air for it to thrive.

61

Initial Environmental Examination (IEE) Landscaping, floriculture and tourism/pilgrim infrastructure development works at Mostamanu temple complex Component Criteria Remarks site: contemporary gardening and landscape The sloping grounds all around are concepts and designs should not be introduced. proposed to be seeded with native wildflowers and grasses to create a wildflower meadow which will provide a fitting naturalized setting for the temple. Clusters of native Padum tree (Himalayan Wild Cherry) are proposed for seasonal colour as well as to provide shade during summer. The trees suggested for plantation, both Padum (Prunus cerasoides) and Champa (Magnolia champaca), have religious significance and are traditionally offered to the Gods. Their addition on the site adds to the spiritual experience. Conservation 21. Will observe the principle of not adversely Ensured and habitat impacting the habitat quality of the protected area protection and shall involve treatment of damage caused by measures- in natural processes and human actions and and around the prevention of further deterioration, using both natural technical and management measures. heritage assets 22. Will ensure that intervention, in form of additional and protected civil works within the protected areas, be minimal. areas. Every intervention proposed shall have clear objectives and use tried and proven methods and materials. 23. Will not open up new areas of tourist movement, Not envisaged as site is a popular religious including opening up of new routes for boating in centre and proposed interventions shall wetlands etc, especially in areas identified as core retain its religious and natural significance or zone identified for conservation in the together with enhancing visitor experience. management plan for the protected area. 24. Will ensure that the areas of significant habitat NA diversity habitats are conserved in their natural condition. 25. The results of intervention should be unobtrusive Proposed interventions are as per original when compared to the original fabric or to previous fabric and architectural character of the treatments, but still should be distinguishable surroundings

26. New materials and techniques may only be used No new materials and techniques are used after they have been tried and proven, and should in no way cause damage to the site.

27. Service buildings should be as far as possible from NA the principal area of the site. Water supply 28. Will be taken up from existing potable treatment Existing potable system is used. Project only systems nearby, unless on such systems are contains provision of water storage system. available in the vicinity 29. Will not result in excessive abstraction of ground Not envisaged water or result in excessive groundwater pumping impairing ground water quality 30. Will ensure adequate protection form pollution of Will be ensured intake points 31. Will not result in unsatisfactory raw water supply Potable water supply is through existing (e.g. supply with excessive pathogens or mineral water supply scheme of Jal Sansthan. constituents)

62

Initial Environmental Examination (IEE) Landscaping, floriculture and tourism/pilgrim infrastructure development works at Mostamanu temple complex Component Criteria Remarks 32. Will ensure proper and adequate treatment and Not much waste water generation disposal facilitates for increased volumes of envisaged. Provision of septic tanks/sock wastewater generation pits exists Sanitation and 33. Will ensure that the site selection for the septic Ensured and forms part of EMMP toilet facilities tank/ or any/ or any other treatment method proposed is not close to water intake or water usage points, or areas prone to flooding or water logging 34. Will ensure that sanitation improvements proposed Ensured and forms part of EMMP do not result in pollution of groundwater.

35. Will not interfere with other utilities and block access to buildings, cause nuisance to neighboring areas due to noise, smell, and influx of insects, rodents, etc. 36. Will not impair downstream water quality due to inadequate sewage treatment or release of untreated sewage, 37. Will not cause overflows and flooding of surroundings, especially around the heritage sites with raw sewage. Solid waste 38. Will ensure that the disposal of solid wastes will not There is provision of waste segregation at management result in degradation of aesthetics in the vicinity of source through separate Bio-degradable the proposed tourist areas and Non- Biodegradable Waste bins and suitable disposal arrangements. Biodegradable Waste bin This would be a retractable pit type waste bin with an overall opening size of 500mm X 500mm and an overall height of 850mm. The outer structures would be made of wooden battens with the exposed wooden faces primer coated and melamine polished with GI sheet for sign display. The bottom would be excavation for making a self compost pit; and the pit lined with geo- textile fibre sheet. The bio-degradable waste would be collected in the compost pit and cleaned occasionally by lifting up the retractable waste bin. This is a low regular clearing. Non-bio degradable Waste Bin This would be a retractable back door, top covered type of waste bin with an overall opening size of 500mm X 500mm and an overall height of 850mm. The outer structure would be made of wooden battens and with an inner lining in FRP retractable waste bucket of overall size of 450mm X 450mm X 475mm with a guage GI sheet for sign display. The exposed wooden faces would be primer coated and melamine polished; with a painted signage. T

63

Initial Environmental Examination (IEE) Landscaping, floriculture and tourism/pilgrim infrastructure development works at Mostamanu temple complex Component Criteria Remarks be opened for carrying away the waste at regular intervals.

39. Will ensure buffer of greenbelt and earth works During construction phase suitable buffer around the site to avoid nuisance to neighboring will be provided as per EMMP. Project also areas due to foul odor and influx of insects, rodents, has provisions for landscaping and etc. maintenance of rich green belt with native species 40. Will ensure that for composting pits for protected NA areas, the locations are devoid of any wildlife population, especially wild boars, porcupines

41. Will ensure any on site waste management done in It will be ensured compliance with government regulations and in coordination with municipal authorities. Roads 42. Will ensure minimal clearing of vegetation Clearing of vegetation not envisaged 43. Will ensure on dislocation and involuntary No dislocation and involuntary resettlement of people living in right of way. resettlement envisaged 44. Will not lead to alteration of surface water No surface water body in the vicinity. hydrology of streams/waterways that may result in Erosion from construction sites will be increased sediment load due to erosion form controlled as per EMMP provisions. construction sites. Drainage and 45. Will ensure improvements are identified to cater to No alterations to the existing drainage flood the watershed or drainage zones and not individual patterns are expected due to project protection drains. interventions 46. Will ensure adequacy of outfall of proposed NA drainage works, to avoid any impacts associated with flooding in downstream areas, or areas not covered 47. Will ensure effective drainage of the monument Proposed interventions shall improve the area, and provide for improved structural stability structural stability of the monuments Development 48. Will ensure no deterioration of surrounding Any new growth or expansion will be within of parking and environmental conditions due to uncontrolled the regulations of other tourist growth around these facilities, increased traffic and infrastructure increased waste generation resulting from amenities improved infrastructure facilities 49. Will not create structures or buildings that are physically or visually intrusive, in terms of size, Not envisaged. Project shall add to the scale, location that shall have an adverse impact on aesthetic beauty of the site and enhance the aesthetic quality or the site, through careful the visitor experience. designs in terms of built form, construction materials etc.

64

Initial Environmental Examination (IEE) Landscaping, floriculture and tourism/pilgrim infrastructure development works at Mostamanu temple complex ANNEXURE- 3

PROJECT LOCATION MAP

65

Initial Environmental Examination (IEE) Landscaping, floriculture and tourism/pilgrim infrastructure development works at Mostamanu temple complex ANNEXURE 4 PROJECT PHOTOGRAPHS

Entrance to the Temple Complex Existing Pathways

Entrance to the Temple Existing position of Public Amenities

View of Rangmanch Current situation of the Children's Park

Landscape and slope grading of the temple surrounding area Mostmanu Temple

66

Initial Environmental Examination (IEE) Landscaping, floriculture and tourism/pilgrim infrastructure development works at Mostamanu temple complex

ANNEXURE 5

67

Initial Environmental Examination (IEE) Landscaping, floriculture and tourism/pilgrim infrastructure development works at Mostamanu temple complex

No objection certificate from Mostmanu Mandir Committee, Pithoragarh

68

Initial Environmental Examination (IEE) Landscaping, floriculture and tourism/pilgrim infrastructure development works at Mostamanu temple complex

No objection certificate from Mostmanu Mandir Committee, Pithoragarh

69

Initial Environmental Examination (IEE) Landscaping, floriculture and tourism/pilgrim infrastructure development works at Mostamanu temple complex

No objection certificate from Sarpanch, Gram Panchayat Dunga Bhool

70

Initial Environmental Examination (IEE) Landscaping, floriculture and tourism/pilgrim infrastructure development works at Mostamanu temple complex

No objection certificate from Van Panchayat Bakarkatiya

71

Initial Environmental Examination (IEE) Landscaping, floriculture and tourism/pilgrim infrastructure development works at Mostamanu temple complex

ANNEXURE 6

Constitution Of Sub Project Monitoring Committee

72

Initial Environmental Examination (IEE) Landscaping, floriculture and tourism/pilgrim infrastructure development works at Mostamanu temple complex

ANNEXURE 7

AMBIENT AIR QUALITY REPORT

73

Initial Environmental Examination (IEE) Landscaping, floriculture and tourism/pilgrim infrastructure development works at Mostamanu temple complex

74

Initial Environmental Examination (IEE) Landscaping, floriculture and tourism/pilgrim infrastructure development works at Mostamanu temple complex NOISE MONITORING REPORT

75

Initial Environmental Examination (IEE) Landscaping, floriculture and tourism/pilgrim infrastructure development works at Mostamanu temple complex

76

Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoragarh to Chandak

ANNEXURE 8

STAKEHOLDER CONSULTATION PHOTOGRAPHS

Public Consultation at Mostmanu Temple Public Consultation at Mostmanu Temple

Public Consultation at Mostmanu Temple Public Consultation at Mostmanu Temple

Public Consultation with local historian Public Consultation with local historian

77

Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoragarh to Chandak

PUBLIC CONSULTATION ANNEXURE- 9a

78

Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoragarh to Chandak

79

Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoragarh to Chandak

ANNEXURE- 9b

80

Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoragarh to Chandak

Consultations with Villagers during Fair in Mostmanu Temple Complex

81

Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoragarh to Chandak

82

Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoragarh to Chandak ANNEXURE- 9c

Public Consultation Meeting at Pithoragarh

(Venue: Mostmanu Temple; Date: 30-12-13)

A team experts from WAPCOS and PIU Bhimtal organized a pubic consultation meeting with the local community at Mostmanu Temple at Chandak, Pithoragarh on 29.12.2013 at 12.00 hrs. The List of participants is attached

Minutes of meeting

1- The workable plan of the temple was reintroduced during the meeting and all aspects of workable plan discussed in detail. 2- The issue of Dharmshala Building discussed in the meeting and it has been decided by temple committee that the said building should not be replaced. 3- The team members motivated for the registration of temple committee as a trust. The committee informed that the matter will be decided in next meetings. 4- After discussion on all the issues and workable plan the committee provides NOC for proposed work under IDIPT project.

Photographs of Meeting

List of participants enclosed

83

Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoragarh to Chandak

84

Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoragarh to Chandak

Minutes of Meeting ANNEXURE- 9d

Date 27 Dec 2013

Venue -Vikas Bhawan Pithoragarh

Chaired by- Dr Anand Srivastava, Chief Development Officer

CO-chaired by – S.D.M Pithoragarh

Attended By – Mr Tushar Chakravarty [Consultant DSC Bhimtal]

Ms Paromita De Sarkar [Consultant DSC Bhimtal

Mr Rajeeve Kulshrestra [ Team leader DSC Bhimtal]

Dr Jagat Sontiyal [C.D.O PIU Bhimtal]

Mr Raja Joshi [ S.E PIU Bhimtal]

1. The Meeting was held to discuss proposed concept plan of the Pithoragarh fort. The consultant presented various aspects of the project including the overall vision, goals and objectives, description of various interventions proposed in the fort enclosure complex and the precinct, the re-use plan, and the road map for the proposed re-use of buildings.

2. The site issues pertaining to the projects was discussed and the consultants highlighted the issue of unregulated high rise structures in the vicinity of the fort precinct and the need to regulated high rise structure in the fort precinct. The CDO mentioned that development works in Pithoragarh in currently regulated and asked the SDM to look into this matter.

3. The matter of Ram Leela ground came up for discussion in the context of the proposed development works proposed by the consultants. The SDM mentioned that the land is currently under the use of Ram Leela Committee for over a century.

4. Regarding the proposal to display artefacts in the local history museum, the CDO mentioned the museum set by Mr Pangti on Bhutia culture located in , and that exhibits from such museums in the region can be put upat the Pithroagarh fort local museum as travelling exhibition and therefore the consultants in their re-use plan for the tehsil office can make provisions for that.

5. Highlighting the danger of unsustainability of tourist destinations, the CDO highlighted the case of Kasardevi in Almora district.

6. The CDO mentioned that necessary action has been taken for the rehabilitation of Tehsil office.

85

Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoragarh to Chandak

7. In the context of the proposed interventions highlighted in the Concept Plan, the SDM assure the team of consultants that necessary help would be provided to resolve any land and other related issues at administration level.

8. The consultants requested the CDO for another meeting to discuss project related issues following the teams site work.

Meeting with Executive Officer, Nagar Palika Pithoragarh

1. Regarding land ownership of trek trail beyond 3 m belonging to the Van Panchayat, the EO mentioned that the land of Van Panchayat belonged to the Van Panchayat of Shera village and Bajeti village.

2. Regarding the ownership of Ram Leela grounds the JE mentioned that the land belonged to Nagar Palika but it is occupied by Ram Leela committee and therefore it may be feasible to take NOC from Nagar Palika, but consultation with the Ram Leela committee would be necessary to implement any development activity proposed for the Ram Leela ground.

3. Regarding O& M cost of heritage trail, the EO stated the Nagar Palika lack of budget for the O&M of the heritage trail. This matter would need to be discussed with the CDO/DM.

4. Regarding the proposal for the Nagar Palika Chowk and the proposed interventions the JE mentioned that NOC would have to be taken from the PWD.

Meeting with Tehsildar

1. The rehabilitation of the Tehsil staff would need to be addressed for successful implementation of the proposed Fort project. This issue has to be discussed further with the DM/CDO.

2. The rehabilitation of the Tehsil office along with their proposal must be mentioned in the Resettlement Plan.

3. The Tehsildar assured that the revenue records of trek trail and Mostmanu would be provided to the team by the Revenue officer.

Meeting with Chief Development Officer, Pithoragarh

Venue: Vikas Bhawan, Pithoragarh

DAY 1: Friday 27th December 2013

Chaired by- Dr Anand Srivastava, Chief Development Officer

86

Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoragarh to Chandak

CO-chaired by – S.D.M Pithoragarh

Attended By :

Mr Rajeeve Kulshrestra [ Team leader DSc Bhimtal]

Dr Jagat Sontiyal [Community Development Officer, PIU Bhimtal]

Mr Raja Joshi [ Support Engineer PIU Bhimtal]

Mr Tushar Chakravarty [Cultural Heritage Management Expert DSC Bhimtal]

Ms Paromita De Sarkar [Cultural Heritage Conservation Specialist DSC Bhimtal]

The Meeting was held to discuss proposed concept plan of the Pithoragarh fort. The consultant presented various aspects of the project including the overall vision, goals and objectives, description of various interventions proposed in the fort enclosure complex and the precinct, the re-use plan, and the road map for the proposed re-use of buildings.

1. The site issues pertaining to the projects was discussed and the consultants highlighted the issue of unregulated high rise structures in the vicinity of the fort precinct and the need to regulated high rise structure in the fort precinct. The CDO mentioned that development works in Pithoragarh in currently regulated and asked the SDM to look into this matter.

2. The matter of Ram Leela ground came up for discussion in the context of the proposed development works proposed by the consultants. The SDM mentioned that the land is currently under the Ram Leela Committee.

3. Regarding the proposal to display artefacts in the local history museum, the CDO mentioned the museum set by Mr Pangti on Bhutia culture located in Munsiari, and that exhibits from such museums in the region can be put up at the Pithroagarh fort local museum as travelling exhibition and therefore the consultants in their re-use plan for the Tehsil office can make provisions for that.

4. Highlighting the danger of unsustainability of tourist destinations, the CDO highlighted the case of Kasardevi in Almora district.

5. The CDO mentioned that necessary action has been taken for the rehabilitation of Tehsil office.

6. In the context of the proposed interventions highlighted in the Concept Plan, the SDM assure the Dsc and PIU team that necessary help would be provided to resolve any land and other related issues at administration level.

7. The consultants requested the CDO for another meeting to discuss project related issues following the team’s site work.

87

Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoragarh to Chandak

DAY 2: Saturday 28th December 2013

Chaired by- Dr Anand Srivastava, Chief Development Officer

Attended By

 Mr Rajeeve Kulshrestra [ Team leader DSc Bhimtal]  Dr Jagat Sontiyal [Community Development Officer, PIU Bhimtal]  Mr Raja Joshi [ Support Engineer PIU Bhimtal]  Mr Tushar Chakravarty [Cultural Heritage Management Expert DSC Bhimtal]  Ms Paromita De Sarkar [Cultural Heritage Conservation Specialist DSC Bhimtal]

1. The DSc and PIU informed the CDO about the discussions held with various stakeholders and issues identified for the consideration of the District Administration for their perusal.

2. The issue pertaining to the ownership of Ram Leela ground was discussed. It was informed that the land ownership of the historic Ram leela ground in the Fort precinct was with the Nagar Palika Pithoragarh however the ground is currently occupied by the Ram Leela Committee and therefore it would be necessary to initiate a dialogue with the Ram Leela Committee to take their consonance for the proposed interventions in the Ram Leela ground.

3. The CDO informed the team that the SDM would help in coordinating between the Nagar Palika and the Ram Leela Committee to resolve all matters in hand pertaining to the proposed interventions in the Ram Leela ground.

4. The visiting team recommended that it would be appropriate to notify the Pithoragarh fort enclosure after the evacuation of the Tehsil office and its ancillary buildings to minimize the risk of appropriation.

5. The PIU and DSc team informed the CDO about their meeting with the Tehsildar Pithoragarh on 28th December 2013 and need to address the issue of rehabilitation of Tehsil staff residences at present located in the Fort enclosure and precinct area. The DSc team informed the CDO that nearly 22 staff members together with their family would need to be relocated. The CDO informed that following the shifting of the Tehsil Office the shifting of the staff members would also be considered after discussion as a proposal would have to be forwarded to the Revenue board and this would take some time.

6. In view of the proposed resettlement of the Tehsil staff, the chair was of the opinion that the project should be phased in such a manner that the proposal for the fort enclosure should be executed in the first phase and subsequently the proposals outside the fort in the precinct area could be implemented. During this period an alternate residential arrangement can be worked out for the Tehsil staff.

7. For the Resettlement Plan of the Pithoragarh Fort enclosure the DSc requested for a letter confirming the shifting of the Tehsil Office to the new site, the CDO informed that the SDM can be requested for the same. 88

Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoragarh to Chandak

8. The DSc informed the CDO about the need to look into the issue of O& M of the Chandak Heritage trail project. The CDO informed the team that the matter would be taken up with the Nagar Palika and the District administration would advice them with options for revenue generation that can be ring-fenced to operate and maintain the trail including PPP options.

89

Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoragarh to Chandak

ANNEXURE- 9e

Report on Trip to Pithoragarh, 6-8 January 2014

Day 1, 6 January 2014: Travel to Pithoragarh Meeting 1: Shri Manoj Matwal, Harela Society, Pithoragarh Points of discussion: 1. There are many other significant sites around Pithoragarh, that could be taken up for appropriate tourism development. For instance, the Devdar forest behind the abandoned factory site could be taken up for trail development. 2. There are many mineral deposits in the area, and Harela had organised geological walks for students to experience them. 3. Udaipur hill fort is a historic structure which ought to be showcased and protected. 4. There are sites where fossil remains are found between Chandak and Udaipur Fort. The two resources can be combined for a comprehensive trail experience. 5. Chandika Devi temple is another important shrine, as significant as Mostamanu temple. 6. The forest near Mostamanu temple is a sacred grove, with dense Oak forests that are a catchment area for Rai Gaard (stream). In order to ensure the protection of the water catchment area, the local villagers have taken wood from the sacred grove and offered it at the Kot Gaadi (Goddess) temple, thereby symbolically ensuring its protection. This affirmative action on the part of the village community demonstrates their awareness of the environmental significance of the forest, as also their desire to protect it. This should be respected. 7. It was suggested that website and social media should be used to showcase the cultural and environmental heritage of Pithoragarh to visitors. Events like Sharadotsav festivals should be vehicles to promote Kumaoni performing arts like Chhalia dance etc. 8. It was decided that a Cultural Walk be undertaken by the project team on Day 3 to experience a traditional settlement (Kot) of Pithoragarh.

Day 2, 7 January 2014 Meeting with Chief Development Officer, Shri Anand Srivastava (09412151050; [email protected]) Project team: Dr. Yaaminey Mubayi, PRIMA-ACS, Dr K.K. Gaur, WAPCOS, Mr Tyagi, WAPCOS, Dr Suresh Mathpal, Shri Arun Dev, DSC Bhimtal, Representative of PIU Points of Discussion: 1. Pithoragarh Fort: - Regarding the issue of full evacuation of the Fort for restoration work, CDO agreed that rehabilitation of residents and staff will be carried out via alternate accommodation. He said the matter had been discussed with DM who was fully apprised of the situation. - Regarding the situation vis-a-vis the Ramlila Committee, CDO agreed that a detailed Public Consultation should be carried out involving multiple stakeholders, including Nagar Palika, Ramlila Committee, Market Associations, residents and local institutions. It may be chaired 90

Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoragarh to Chandak

by SDM, who was the appropriate officer in charge of the Tehsil and other land related matters. It was recommended that stages of public consultations could be carried out to resolve any issues in the area. It was also agreed that draft plans for the project should be placed in the public domain, so that feedback from various stakeholders could be elicited. - The Reuse Plan for the Fort, including the involvement of DRDA and SHGs in running the Craft Centre and Cafeteria, had already been communicated to the CDO, who approved of them in principle. - Regarding notification of the Fort by State Department of Culture following its restoration, it was agreed that it was a favourable option for future maintenance and sustainability. CDO was apprised of the possibility of Buffer Zone Regulations coming into play, and recommended that the matter be further discussed at various levels. 2. Mostamanu Temple: - CDO was informed that there appeared to be conflicting claims (Mandir Committee, Mostamanu Vikas Samiti) for the position responsible for the temple affairs. It was stated that the Mandir Committee was an unregistered body. He recommended that registration of the Committee under the Societies Act of 1860 was not a problem, and could be immediately done in Pithoragarh itself by the Chief Treasury Officer (Shri Hemendra Gangwar). He said that the District Administration would help to facilitate the registration process. - The issue of ownership of land relating to the temple was discussed in detail and it was stated that the two nalis (approximately) of land on which the temple was located, was registered at “Mandir Prangan” (temple courtyard) in the land records, thereby indicating its position following the settlement (bandobast) of the area carried out in 1960. The surrounding land on which the proposed project interventions were to be located, according to CDO, may not be Nazul land as initially assumed, but registered under two Gram Panchayats of villages Dhunga and Bakarkatiya respectively. - CDO stated that all NOCs had to be on a valid letterhead with stamp of Tehsildar or other signing authority, in order to be valid. NOCs on plain paper without stamp were not valid. - CDO directed that the project team meet with the Patwari and clarify all land ownership by checking the records. 3. Chandak Trails: - CDO was asked whether ownership of the land on which the trails were located rested with the Nagar Palika. He clarified that there was a difference between “ownership” of the land and “management authority” over the area, and it was to be ascertained whether Nagar Palika was actually the owner or simply the manager. Even if they were the managers responsible for maintenance of the trails, NOCs would be required from other stakeholders like Van Panchayats and any others to mitigate the risk of any dispute arising in the future. 4. In summation: - Regarding overall strategy for tourism development in the region, CDO stated that it was dependent on the “convergence” of different factors, i.e. the opening of the Naini Saini airport proposed for October 2014, the parallel development of better hotels and tourist accommodation and facilities in Pithoragarh. Only then would the proposed project activities find a viable market for successful operations and sustainability.

91

Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoragarh to Chandak

Visit to Nagar Palika and meeting with Shri Madan Singh Bora, PWC (09760299236). List of contacts given: - Shri Jagat Singh Khati, Chairman, Nagar Palika (07599093844/09690234555) - Shri Khemanand Joshi, Executive Officer, Nagar Palika (09410113386) - Shri N.C Pandey, Patwari Meeting with Shri Pandey, Patwari, and verification of land records by some members of project team. Visit to Trail site along with Patwari to verify some details. Meeting with Shri Jagat Singh Khati, Chairman, Nagar Palika, Pithoragarh 1. Fort: The Chairman stated that he was reluctant to engage in conflict with any citizens group, particularly the Ramlila Committee, and was willing to find mutually acceptable solutions to any issues that may arise. The Nagar Palika would participate in any public consultation that may be held regarding the Fort project. 2. Trails project: The trails are located within the territorial jurisdiction of the Nagar Palika. The Palika would also take up any responsibility for maintenance that is entrusted to it. Regarding any cess or other funding source, the idea is not viable at this point. 3. Chairman suggested lighting be installed along the trail to facilitate people’s movement. 4. Regarding NOCs for the trail, the Nagar Palika is willing to give a blanket NOC for the entire trail. Day 3, 8 January 2014 Cultural Geography Walk at Kumaur, a village adjoining Pithoragarh town. Participants: Entire project team, guided by Shri Manoj Matwal of Harela Society Observations: - The “village” is heavily urbanised in an unplanned and agglomerated manner. There is heavy traffic and the approach is dangerous in terms of fast vehicles and no traffic controls. There is s sense of dilapidation and lack of care about the space and its people, which is subordinated to the interest of the town of Pithoragarh. - While some aspects of the traditional morphology and layout of streets still exist, the buildings are completely transformed, with vernacular structures replaced by brick and cement buildings. - As one goes deeper into the village settlement, there are some remaining vernacular houses, possible inhabited by rural households that have not yet managed to urbanise their homes, livelihoods and lifestyles. Thus one finds a few domestic animals, well-drawn water usage etc. not visible in the urbanised fringes that are closer to Pithoragarh. - The Kot was traditionally the citadel or centre of the settlement, home to 40-50 families of the land-owning aristocracy of the village. It consists of a central double storeyed building constructed with mud mortar with wooden beams and roof. Two wings abut the central building, all opening onto a central courtyard. Carved wooden balconies face the courtyard from the upper stories. Water was supplied from the Naulas (springs) from the lower slopes. - The building was the focus of several community based practices and festivals, such as the Yatras in the month of Chaitra (April) and Bhitoli (festive gifts to the sister’s village). Such Yatras were a symbolic means of interaction and links of reciprocity between the village communities in the region. - The building is possibly about 300 years old. Ownership is possibly with the Gram 92

Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoragarh to Chandak

Panchayat. It is abandoned and in an advanced stage of dilapidation. It requires urgent conservation.

Meeting with Shri Bahadur Singh Mahar, Elderly resident of Kumaur

- Origin myth of the settlement: Four brothers of the Mahar family based in Chittor (Rajasthan), owing to a quarrel with a rival clan, came away to Pithoragarh about 400 years ago. They took shelter in the hut of an old woman who stayed in the village of Pandeygaon (Brahmin village in the vicinity). She warned them about a man-eating tiger that had terrorised the settlement. At night, the tiger came to the hut and tried to tear off the roof. The brothers fought with it and killed it, cutting off its paw as proof. The next morning, the dead tiger was found by a local resident, who reported it to the king as his kill. The king had declared a reward for whoever killed the man-eater, and accordingly was about to give it to the finder. However, the queen asked him to produce the missing paw as proof of his having killed it. When the false claimant failed to do so, the four brothers came forward and produced the paw. The king offered them as much land as they could see with the naked eye, and this became the settlement of Kumaur. The word “Kumaur” is derived from “Kuru Mahar”, the name of the eldest brother.

93

Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoragarh to Chandak

ANNEXURE- 9f

Meeting with District Magistrate, Dr. Neeraj Khairwal (08193396001) Participants: Full Project Team, Shri Anand Srivastava, CDO

Points of Discussion: 1. The DM requested to view the project presentation, which he had not yet seen. The presentation was made by Shri Arun Dev and Dr. Yaaminey Mubayi. 2. The DM was briefed on the previous day’s discussion by CDO. 3. The Fort: - DM assured the team that the fort would be evacuated before the project began. However, he emphasised that he should be informed about the date of commencement of the project work, and accordingly he would have the fort evacuated. He did not want to clear the fort and have it lying empty for long, in case the project was delayed. - The residential areas of the Tehsil would also be cleared, it was assured. - He wished to have the details of the interventions at the Fort explained to him on a room- to-room basis, and recommended an on-site meeting for the purpose. - He had some comments regarding the proposals for interventions, for example, he recommended that the walking pathway be paved in heavy stone for longer lasting and durable usage. 4. Mostamanu Temple: - Having been briefed by the CDO regarding the issues at the temple, DM called for the SDM and directed him to hold a Mediation Meeting with all concerned parties related to the temple. He said the threat of takeover of temple management by District Administration could be used as a last resort to decide which agency would manage the temple. 5. NOCs pertaining to Mostamanu Temple and Trails: - DM stated that regardless of whether the areas lay in the Nagar Palika’s jurisdiction, it was imperative to get NOCs from all owners registered in the land records, including Van Panchayats, Gram Panchayats etc. This is to mitigate the risk of any dispute regarding ownership in the future. Meeting at Mostamanu Temple, Chandak Two attempts were made to have a discussion with the temple committee, however, on both occasions, only the Temple Pujari and the MLA’s representative, Shri Mahendar Singh Bisht, were present. Points of discussion: 1. The matter was discussed and the stipulations of ADB regarding the existence of a formal registered body with transparent functioning, auditing systems etc. to hand over the assets created as part of the project, were explained. 2. Shri Bisht informed us that there was another committee, Mostamanu Vikas Samiti, of which the Mandir Committee was a part, which was registered and appropriate for the job. 3. The Secretary of the Mandir Committee in a separate interview, declared that the Mandir Committee had nothing to do with the registered entity, and would not allow them to enter the temple premises. 94

Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoragarh to Chandak

4. The team intimated the Pujari that it was imperative that a resolution to the issue must be found soon. We urged the Mandir Committee to complete the registration process, asking them the reason for their delay in registering. We emphasised that the District Administration had offered to facilitate the process of registration. 5. The team was informed that the Mandir Committee would have a meeting in the next two days to decide the issue. However, subsequently it was learned that the meeting did not take place as the President had hurt his leg and was hospitalised. 6. It is hoped that the matter would be decided via mediation by SDM, as indicated by DM.

95

Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoragarh to Chandak

Public Disclosure Through Newspaper Annexure 10

96

Initial Environmental Examination (IEE) Revival and Development of Trekking Trail and Vantage Points at Pithoragarh to Chandak

97

Response Matrix For IEE L F TP I D W M T C

S. No. Comments Remarks 1. Project components  Project entails demolishing brick P work, doors and windows of the s C each structure, ownership, store including chowkhats, and use, and clarify if any resettlement issues architrave, holdfasts etc. exist.  The structure inside the temple complex under the ownership of the temple committee.  This will be done manually as per direction of DSC Engineer in consultation with the Environment Specialist.  No resettlement issue exists and all proposed works are in due consultation with the Temple Committee, for which they have agreed and NOC attached as Annexure 4 of the IEE. 2. Signage  In the subproject, a signage Please confirm that proposed signage locations strategy has been developed are based upon a tourism circulation based on Tourism circulation development and/ or management plan for the development/ management plan site, as per the FAM Appendix 3, Para 17 of the site to inform users about the amenities provided in temple complex.  Signs are proposed to be located at locations where they can easily be seen by trail users.  Signage will present information in an understandable format with limited text and bi-lingual, supplemented by graphics that can be universally understood.  These signage are proposed to be made using local and readily available material - Wood and Stone.  Three types of signage are proposed for the temple complex: Directional Signage, Statutory Signage and Interpretive Signage.  Wood will be used for the Directional and Statutory signs, and interpretive signs will use sand stone as component.  Planning and design of signage within temple complex to be provided with strategically placed signage will orient visitors around the site and interpretive signs will aid understanding of the legends and beliefs associated with the temple and its surrounding natural as well as cultural context. Extensive and carefully designed signage that blends with the surroundings and which is built using local materials will be developed and put in place at strategic points in the temple complex. 3. Municipal services  Proposed Infrastructure More tourists will create more solid waste and provisions are made in view of sanitation requirements, requiring a clear the inadequacy of the existing environmental management system at the sites sanitation and solid waste to avoid nuisances which risk deteriorating the management systems. sites attraction quality. In the REA checklist and  02 nos. of toilet blocks are Environmental Management Plan, please include proposed with 08 nos. urinals a more concrete response for SWM and septage and three toilets. management at the site. Clarify who will manage  Involvement of the stakeholders these services. Please note that Para 8 of i.e. Temple Management Schedule 4 of the FFA (subproject selection Committee and local A communities in the operation services linked to subprojects such as water and management of the tourism supply, sanitation, solid waste management, facilities will address the drainage, and flood control, shall be eligible operation stage impacts. under the subproject subject to following the  The participation of the local FAM communities will include See FAM Appendix 3 Section B for more details. collection and segregation of wastes, operation and maintenance of toilet facilities with regular cleaning, and timely cleanup of waste disposed by the tourists in coordination with the Pithoragarh Municipal body.

Added at relevant section in the REA checklist and EMP. 4. Table 6 に Summary of Impacts and Mitigation Scope of work for this subproject is Measures limited where no major It is not sufficient to provide general statements construction is proposed but in explaining mitigation measures. For example, energy efficiency measures shall be it states T observed wherever possible: subproject components will ensure energy  Use of LED lighting to reduce M required on how energy cost, maintenance cost. this will be done. Please avoid general  All electric equipments including statements and improve Table 6 to include fans, lights and switches would details of proposed mitigation measures. be as per BEE star rating.  Design of toilet block has been done for maximum utilization of natural light and ventilation in the day time  Use of Vernacular architecture: Locally available materials are proposed in construction viz slate stone and in signages (as explained in para 2) thereby cutting processing and transportation cost of material procurement  Preserving natural landscape features and use of native plant species will minimize irrigation cost  Use of regionally appropriate, low water-using and native plants in landscaping to save water as once established, these plants require little water beyond normal rainfall. And also, because native plants are better adapted to local soils and climatic conditions, they rarely require the addition of fertilizer and are more resistant to pests and diseases thereby cutting irrigation and maintenance costs.  Use of water efficient fixtures 5. Disturbance to tourists  Construction schedule will be The IEE and EMP are silent on how the works will planned in consultation with the be conducted during tourist peak periods Temple Committee and other without disturbing visitors to the sites. Please local stakeholders and will also provide more details on how contractors will be suitably displayed. ensure access and minimize disturbance to  The Temple Complex has 2 gates tourists. on east and west sides. Plan of execution is made such as to utilize one gate for tourists till the other gate with approach is constructed.  The contractor will work as per approved circulation plan for safe passage of tourists, traffic regulations and signages with proper dissemination at suitable points.  Minimum footpath width will be maintained

EMP modified accordingly 6. Compliance with subproject selection criteria from EARF Table 6 Checklist included as annexure 2 Please include one checklist as an appendix on page 60 compliance with the environmental selection criteria from Table 6 of the EARF. This should provide explanations on how the subproject complies with each relevant criteria.