Arab Republic of Egypt Ministry of Planning and Monitoring Administrative Reform

Sharing Knowledge on Development and

Implementation of Execution Plans Project

in Egypt (Phase 2)

Completion Report

September 2017

Japan International Cooperation Agency (JICA) Naruo Research Institute, Ltd.

Vision and Spirit for Overseas Cooperation Co., Ltd. 7R JR 17-018

Table of Contents

List of figures ...... ii

Abbreviation ...... iii

1. Background of the Project ...... 1

1.1. Background ...... 1

1.2. Objectives ...... 2

1.3. History of the Project ...... 3

1.4. SDS2030 (external factors) ...... 5

2. Overview and progress of the Project...... 6

2.1. Contents of operations ...... 6

2.2. Operation flows ...... 7

2.3. Report on activities and outputs ...... 8

3. Issues, solutions, and lessons in implementing and operatint ...... 44

3.1 Organizing the preconditions for the Project ...... 44

3.2 Issues, solutions, and lessons for the outputs of the Project (first half of Phase 2: October 2015 – September 2016) ...... 48

3.3 Comprehensive issues, solutions, and lessons learned...... 55

4. Proposals to achieve the Overall Goal ...... 62

4.1 Overall Goal ...... 62

4.2 Proposals to achieve the Overall Goal ...... 62

5. Attachments ...... 65

5.1. PDM (latest edition, background of changes) ...... 65

5.2. Operation Flow Chart ...... 65

i

5.3. Records of the Dispatched Experts (Personnel Plan) ...... 65

5.4. Records of the Accepted Trainees ...... 65

5.5. Records of the Training Courses and Seminars...... 65

5.6. Records of the Purchased Equipment ...... 65

5.7. JCC Minutes ...... 65

5.8. Records of Other Activities ...... 65

List of figures

Figure 1 Basic framework of the Project ...... 2

Figure 2 History of the Project ...... 3

Figure 3 Recent history of planning in Egypt ...... 5

Figure 4 Operation flows of the Project ...... 8

Figure 5 The project original proposal (Master Plan) (year 2012) to EPPC ...... 45

Figure 6 The history of the project and the environment surrounding it ...... 47

Figure 7 Positioning of JICA's technical cooperation and changes in MOPMAR ...... 50

Figure 8 Support from MOPMAR for the planning unit of each ministry ...... 52

Figure 9 Concept of operation system for technical cooperation ...... 53

Figure 10 This is the basic concept of the JICA projects when the R/D was signed ...... 55

Figure 11 Structural changes of the "roles of MOPMAR" before and after ...... 57

Figure 12. Project support scheme (bird's-eye view) ...... 58

ii

Abbreviation

BK: Benkyo-kai

BOF: Business Operation Flow

CAOA: Central Agency for Organization and Administration

CAPMAS: Central Agency for Public Mobilization and Statistics

CBE: Central Bank of Egypt

CP: Counterpart

E-JUST: Egypt-Japan University of Science and Technology

EP: Execution Plan

FILP: Fiscal Inverstment and Loan Program

GD: Grand Design

GDP: Gross Domestic Product

H/W: Hard Ware

HR: Human Resource

IMF: International Monetary Fund

INP: Institute of National Planning

IT: Information Technology

JCC: Joint Coordination Committee

JETRO: Japan External Trade Organization

JICA: Japan International Cooperation Agency

MOF: Ministry of Finance

MOPMAR: Ministry of Planning, Monitoring and Administrative Reform

MOPIC: Ministry of Planning and International Cooperation (Old, until 2014 June)

iii

MSAD: Ministry of State Administration Development (Old, until 2014 June)

MOE&TE: Ministry of Education and Technical Education

MOHE&SR: Ministry of Higher Education and Schetific Resaerch

MTP: Mid-term Plan

NGO: Non Government Organaization

NIB: National Investment Bank

NSDI: National Spatial Data Infrastructure

PC: Planning Committee

PDM: Project Design Matrix

PIM: Public Investment Management

PO: Plan of Operation

PROMIS: Project Management Infrastructure System

PPP: Policy, Plan and Project

RBF: Rockefeller Brothers Fund

RBM: Results-based management

R/D: Record of Discussion

SC: Steering Committee

SDS2030: Sustainable Development Strategy: Egypt’s vision 2030

SCPD: Supreme Council of Planning & Development

SME: Small- and Medium-Sized Enterprise

iv

1. Background of the Project 1.1. Background

Egypt formulated “five-year plans”, which summarize investment plans for major national five-year projects by ministries and agencies, up to the sixth plan (July 2006– December 2011). After the revolution in 2011, however, it was expected to formulate and implement a more strategic and transparent development plan, which shows and realizes a vision of the new nation and society reflecting the popular will, instead of simply reflecting the demands of ministries and agencies, under the deteriorating economy and increasing civic consciousness. With this situation, the Egyptian government requested Japan in March 2011 to help the formulation of a new national development plan, and Japan supported their planning through JICA’s dispatch of experts for a year and a half. As a result, in June 2012, the Ministry of Planning and International Cooperation (“MOPIC”) first formulated the “Strategic Framework for Economic and Social Development Plan until 2022” (“Strategic Framework”), which states the outlook and strategies of the national development after the revolution.

MOPIC was planning to formulate and implement a public works investment plan based on the Strategic Framework. The issue was that MOPIC had formulated annual investment plans in a bottom-up style, meaning that they had compiled a list of new works submitted by sector ministries and agencies or regional governments and then assigned the budget per sector or region. They had not created budgeting plans in accordance with a national development policy, in other words, their organization was not ready for planning and they lacked expertise for implementation. The public works budgets managed by MOPIC were approximately 15% of the national finances, and there was a growing need for organizational and human resources development in MOPIC to build a system to implement the budget in a more strategic and structured way, along with the increasing financial deficit and deteriorating economic conditions in recent years.

In order to advance these endeavors, the Egyptian government requested Japan in October 2012, to work on this technical cooperation project with the objectives of organizing the structure, including a planning committee needed for the planning and its implementation, and developing human resources. JICA signed the Record of Discussion (R/D) on the Project in April 2013, after the study on the formulation of the detailed plan in March 2013. The Project could not start as planned because of the political change in 2013, and we kept studying and gathering the information on the national conditions after the change. Thereafter, triggered by the inauguration of President el-Sisi and his new cabinet in June 2014, we started the Project in October 2014. We collected the information and compiled the support plan in a one-year phase of the detailed plan formulation (“Phase 1”), and agreed in September 2015 on the PO (Plan of Operation) and PDM (Project Design Matrix) through M/M (Minutes of Meetings) regarding the R/D change, toward the phase of implementation (“Phase 2”). This project aims to carry out the tasks of Phase 2, in accordance with the agreements in Phase 1.

In June 2014, when the new cabinet was formed, the Ministry of International Corporation was separated from MOPIC, and then was integrated into the Ministry of State for Administrative Development

1

(MSAD). Currently it is the Ministry of Planning, Monitoring and Administrative Reform (“MOPMAR”). MOPMAR formulates a public investment budget plan every year and submits it to the government.

1.2. Objectives

Egypt currently does not have a complete framework for planning administration. Furthermore, they lack experience in planning policy layers. To resolve these issues of Egyptian government, JICA’s project team has implemented project activities to develop a Master Plan (long-term plan) and mid-term Execution Plan (“EP”) as planning frameworks, and we have also proposed the establishment of a Planning Committee (“PC”) to steer the preparation and execution of plans.

JICA’s project team regards the Sustainable Development Strategy: Egypt’s Vision 2030 (“SDS2030”1) as a long-term plan (Master Plan (“MP”) (A. on Figure 1)), and will understand the directions of the government, important policies, and development guidelines according to the MP to reflect them in the "Execution Plan ("EP")” (B on Figure 1) as a mid-term plan. We have repeatedly proposed and consistently explained to MOPMAR about the importance of flexibly changing and coordinating the EP based on the direction of the long-term plan in consideration of changes in the economic environment and the priority of the policies promoted by the administration of the time. Basic Framework of the project 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 A. A. SDS2030 Egypt future vision Long term Study & review PC is responsible for Planning committee (PC) 1. Prepare EP (“Supreme council of Urban Planning and 2. Monitoring the implementation Development” will be redefined as PC) 3. Evaluate the result of EP Prepare Monitoring Evaluate EP EP should cover for B. Execution Plan (EP) 1. National policy priority /Integration 2. Public investment coordination B. (Ex; 2 years: 2016-2018) 3. Economic Development strategy Mid- term 4. Social development strategy 5. National mega project outline C. Annual plan C. Annual plan C. (2016/2017) (2017/2018) Annual plan/Public investment Short term 1. Public investment 2. Macro economic analysis 3. National project ,,, Annual public Annual public investment investment (2016/2017) (2016/2017)

Figure 1 Basic framework of the Project

1 The formulation of SDS2030 was started by the former MOP around 2014, and was continued after the formation of MOPMAR (June 2014). SDS2030 was then made public by President el-Sisi in February 2016.

2

The structure of MOPMAR has also changed after signing the R/D, and MOPMAR’s current staff is more likely to lack a full understanding of the context of EP and PC; however, we repeatedly explained that the establishment of PC and development of EP are indispensable for improving planning administration in Egypt.

PDM has established the following Overall Goal:

The process of the national development planning and implementation according to national priories is improved.

That is to say, the objective of execution of operations is to improve the process of planning administration in Egypt based on the national priorities through technical cooperation projects.We did not change the objectives of the Project throughout the implementation period.

1.3. History of the Project

JICA signed the R/D on “Sharing Knowledge on Development and Implementation of the Execution Plans Project in Egypt” ("the Project") with the MOPIC in April 2013. Due to the political change and the succeeding deterioration of government functions in Egypt that took place in July 2013, however, the implementation of the Project was forced to be postponed as shown below (Figure 2).

1. JICA Technical Cooperation. Egypt side (MOPMAR) Japan side (JICA) RD 1. RD was Mutually signed Record of Signed in April 2013 April 15th 2013 discussion

2. MOPMAR and JICA Confirmed the modified Egypt office had agreed Comparison table points about the technical to keep “RD” basic between cooperation. Mutually agreed Keep “RD” basic schema. Schema with some at June 17th 2015 Y2013(Signed) and Modification. Y2015(Now)

Phase2 Concrete 3. Concrete design detailed project schema work plan to describe and preparation Next step For Phase 2. (In Aug) Phase 2.

3. Official procedure for Phase 2. (In Sep) 1. PDM 2. PO (Modified) (Modified) 3. Minutes (Signed)

Figure 2 History of the Project

Subsequently, JICA decided to launch the Project by dividing it into two stages: Phase 1 (October 2014- September 2015) (formulation of a detailed plan) and Phase 2 (October 2015-September 2017) (implementation of the detailed plan agreed on in Phase 1).

3

During Phase 1, we formulated a detailed plan for Phase 2 based on changes in the circumstances between the time the R/D was signed in 2013 and the time the operations were conducted for Phase 1 in 2015. As revising the PDM and PO, we signed the M/M in September 2015.

After the start of the operations for Phase 2, the parliamentary election was held from October to December 2015, and a new Cabinet and parliament were set up in January 2016. The JICA project team has continued its activities in line with the moves of MOPMAR.

Subsequently, as a result of the reorganization of the Cabinet on March 24, 2016, First Assistant to the Minister of MOPMAR Dr. Nihal (in charge of preparing the SDS2030) became the deputy minister of MOPMAR.

The following outlines the progress of planning formulation after 2013 in Egypt.

The former MOP had formulated the five-year plan until 2013; however, it did not formulate the following five-year plan (from 2014 through 2019) after the change of government in 2013. The Ministry of Finance (“MOF”) and MOPMAR intended to formulate the two-year mid-term plan in 2015, but ministries and agencies did not submit enough materials. Consequently, they did not continue the formulation of the mid-term plan and prepared the annual plan as they do every year. According to MOPMAR's explanation, the government decided that the formulation of the mid-term plan (by MOPMAR) was difficult and shifted to the formulation of the Government’s Program 2016-20182 formulated by the Cabinet Office. Separately from this Government’s Program 2016-2018, President el- Sisi released SDS2030 formulated by MOPMAR on February 24, 2016. The Cabinet released the Government’s Program 2016-2018 in March 2016, and obtained the approval of the parliament on April 20, 2016. (Figure 3).

2 The Egyptian government formulated the economic development implementation plan 2016-18 (the tenure of President el-Sisi), which was approved by Parliament in March 2016. The difference between SDS2030 and the Government’s Program 2016-2018 is that the former was submitted to and approved by Parliament while the latter did not obtain the approval of the Parliament.

4

Recent history of Planning in Egypt 2015 2016 1. 5 year Strategy (2014-2019) 5 year Disappeared EEDC prepared. Strategy (Egypt Economic MOF and MOPMAR intended to formulate the two- Development 50 pages paper year mid-term plan in 2015, but ministries and agencies did not submit enough materials. Conference) MOF and MOPMAR intended to formulate the two-year mid- termConsequently, plan in 2015, but they ministries gave upand the agencies formulation did not of submit the enoughmid- termmaterials. plan Consequently, and prepared they the gave annual up the plan formulation as they 2. 2year mid-term plan MOF Budget of thedo mid-termevery year. plan It and seems prepared that thethis annual decision plan wasas they made do everyin Februaryyear. It seems 2016 that. In this our decision opinion, was the made government in February (State general budget & 2013.shifted In our to opinion, the formulation the government of the shifted Cabinet to the Program. Public investment) MOPMAR PI formulation of the Cabinet Program. Feb 2016 SDS 2016-2030 (15 year) 3. SDS2030 2030 ??????? Mid-term (MOPMAR) Plan 2017-20 Mar 2016 Cabinet 2016-2018 (2 year) 4. Government action Program Program (Cabinet office) June 2016 June 2015 2016/17 (1 year) Annual 5. Annual PI Plan Annual plan plan (MOPMAR) Aug 2016 6. Economic Reform Program ERP 2016-2019 (3 year) (Mainly MOF and (IMF) CB)

Figure 3 Recent history of planning in Egypt

1.4. SDS2030 (external factors)

At the time of the signing of the R/D on the Project (April 2013), the MP (Master Plan “National Income Doubling Plan: 10-year Strategic Framework 2012-2022”), which was approved by the Cabinet in July 2012, was defined as a long-term plan; subsequently, President el-Sisi himself released SDS2030, which MOPMAR had made efforts to formulate as a long-term plan since 2014, on February 24, 2016 through live TV broadcast.

MOPMAR regards this SDS2030 as the general plan of the Egyptian government and placed it at the core to link it with mid-term plans, short-term (annual) plans, and individual plans that other ministries and agencies set for each important policy.

The policy that remains unchanged as JICA’s project team, regardless of these external environment changes, is to support the planning administration promoted by MOPMAR, as well as to point out and make improvements to any inadequacies of the framework for planning administration.

5

2. Overview and progress of the Project

The activities of the Project are as defined in "The contents of operations" of "The work plan (October 2015)".

2.1. Contents of operations

(1) Overall Goal

The process of the national development planning and implementation according to national priorities is improved.

(2) Project Purpose

National development plans are developed and implemented according to national priorities as decided by MOPMAR in cooperation with the Egyptian development partners.

(3) Outputs

Output 1: Execution plan is developed in compliance with Sustainable Development Strategy Egypt's Vision 2030 (hereafter, SDS 2030).

Output 2: The organizational framework of MOPMAR is streamlined, and the capacity of MOPMAR staff is strengthened to develop and implement execution plan.

(4) Activities

Output 1: Activities for formulation of the Execution Plan (Refer to p. 9 to p. 45 for detailed report on activities and outputs)

(a) Support for the establishment of the Planning Committee for the formulation and implementation of the Execution Plan, and for formulation and implementation of the plan (Figure 4, 1-1)

(b) Support for organizing the roles of the Planning Committee (Figure 4, 1-1)

(c) Support for the establishment of the Planning Committee and for the formulation of the administration rules of its secretariat (Figure 4, 1-1)

(d) Support for the formulation of the Execution Plan by MOPMAR and the Planning Committee and for the approval by supervising ministries and agencies (Figure 4, 1-2)

(e) Support for the implementation of the Execution Plan and for the preparation of a monitoring report by the Planning Committee on the implementation of the Execution Plan (Figure 4, 1-2)

*In the event the Supreme Council of Urban Planning and Development serves the function of the Planning Committee, technical support will be provided to the council.

6

Output 2: Restructuring of the organizational framework of MOPMAR and support for enhancing the capacity of MOPMAR’s staff

(a) Hold a knowledge-sharing seminar on issues such as policy formation by dispatching Japanese short- term experts (Figure 4, 2-1)

(b) Provide training in Japan as well as workshops and seminars prior to and after the training sessions (Figure 4, 2-2)

(c) Conduct training in third-party countries as well as workshops and seminars prior to and after the training sessions (Figure 4, 2-3)

(d) Support the establishment of MOPMAR’s Strategic Planning and Policy Unit by examining its roles and functions (Figure 4, 3. And 4.)

2.2. Operation flows

1. Output 1 "The activities for the formulation of the Execution Plan" had been conducted according to the procedures mentioned in "Operation flows of the Project" (Figure 4).

JICA’s project team supported the development of the framework of planning administration by conducting the Project’s core tasks of establishing the PC and formulating the EP. (Figure 4, 1)

Although there were some problems, such as ambiguous positioning of SDS2030, which was released in February 2016, we supported planning administration with a focus on the PC and EP.

2. Output 2 "Restructuring of the organizational framework of MOPMAR and support for enhancing the capacity of MOPMAR’s staff" was conducted according to the following procedures. (Figure 4, 2)

Policy is essentially the precondition for formulating plans. Plans are drawn up to attain policy goals, and policy goals are attained through the implementation of plans.

The capacity for policy formulation needs to improve in Egypt at present. Policy goals reflect the values judged by the government. Therefore, to plan policy goals, the government is required to set priorities on policy and optimize the allocation of policy resources (funds, human resources, etc.), while heeding the voice of the people.

To contribute to formulating policy, which is the precondition for the plan, we dispatched short-term experts and provide training in Japan and in the Third Country to share the knowledge necessary to formulate policy.

3. Organizational development (Figure 4, 3)

Assistant to the Minister of MOPMAR Mostafa, the Counterpart (“CP”) of the Project, was scheduled to supervise the function of the Strategic Planning and Policy Division at MOPMAR. Since this function was critical for planning administration, we provided support for him.

7

4. Human resources development (Figure 4, 4)

Although about 200 staff members are engaged in the compilation of the public investment budget in MOPMAR, few people are charged with policy-level planning administration. Bearing this in mind, we worked on the development of human resources and organizational rejuvenation in MOPMAR through the Result Base Management (“RBM”) project.

2015 2016 2017 10 11 12 01 02 03 04 05 06 07 08 09 10 11 12 01 02 03 04 05 06 07 08 09

1. Outcome1. Outcome 1: The 1activities: The activities for the formulationfor the formulation of the Execution of the Functional design Operation (EP preparation, coordination within the government, M&E) Plan (PDM:Execution Output Plan 1) (PDM: Output 1) 1-1. Planning Committee (PC) 1-1. Planning Committee (PC) (PDM: Activity 1-1 to 1-2) Preparation (PDM: Activity 1-1 to 1-2) (MOPMAR) EP 1-2. Execution Plan (EP) Approval 1-2. Execution(PDM: ActivityPlan (EP) 1-3 to(PDM: 1-4) (In Cabinet) Implementation (Policy integration, Feedback, M&E) Activity 1-3 to 1-4) 2. Outcome 2: Restructuring 2. Outcomeof the 2: organizational Restructuring of framework of MOPMAR and the organizational framework of support for enhancing the MOPMARcapacity and supportof MOPMAR’s for staff Short term expert, Training in Japan, Seminar in Egypt, enhancing(PDM: the Output capacity 2) of MOPMAR’s2-1. Short-term staff (PDM: experts Output on 2) policy formulation 2-1. Short2-2.-term Training experts in Japan on policy formulation2-3. Training in third-party Functional design 2-2. Trainingcountries in Japan Operation as newly integrated organization 2-3. Training3. Organizational in third-party countriesdevelopment (Strategic Planning and Policy Unit) 3. Organizational(PDM: Activity development 2-4) (Strategic4. PlanningHuman resources and Policy 7 step approach Next step (To be determined) Unit) (PDM:development Activity 2(PDM:-4) Activity 2-4) Opening Capacity building 4-1. Support for RBM ceremony (Organization, Mechanism, HR) Next step (To be determined) 4-2. Support for INP 4. Human resources development (PDM: Activity 2-4) 4-1. Support for RBM 4-2. Support for INP

Figure 4 Operation flows of the Project

2.3. Report on activities and outputs

We make a monthly report on detailed activity contents of Output 1 and 2 by item as follows:

1. Activities for formulation of the Execution Plan (PDM Output 1) (Figure 4, 1.)

1-1. Planning Committee (PC) (PDM: Activity 1-1 to 1-2) (Figure 4, 1-1.)

(1) Setting up the Planning Committee

(a) Overview of outputs of setting up the PC

8

We set up the PC preparatory committee and held five meetings. The organization name of the Supreme Council of Planning Development (“SCPD”)3, which we agreed on with Minister Dr. Ashraf and which performs the functions of the PC, has not been changed yet. Under these conditions, in order to promote SDS2030, the establishment concepts of the "Ministerial Committee" and "Technical Secretariat" as organizations to put together mid-term plans by ministries and agencies, were released on August 2, 2016. Although JICA’s R/D model and MOPMAR’s SDS2030 model are similar in structure, there is a significant difference between the JICA model, which is based on integrated plans/deliberative planning administration, and the MOPMAR model, which is based on dispersive (separative) plans/theatrical planning administration. The Ministerial Committee and Technical Secretariat do not have the functions of adjusting each sector’s plans and integrating them into the national plan. (Refer to p.42 “Figure 7 Positioning of JICA’s technical cooperation and changes in the MOPMAR planning administration’s trends”). Minister Dr. Ashraf left after the reorganization of the Cabinet (approved by the parliament on February 14, 2017), and Dr. Hala Al-Saeed was appointed as the new minister. There is no hope for the change of the name to SCPD, although the new minister has taken up this post.

(b) Monthly activities related to the establishment of the PC

2015 Toward the establishment of the PC, MOPMAR started preparation to change the name of the present "Supreme Council of Urban Planning and Development" to "Supreme October Council of Planning and Development". Minister Dr. Ashraf informed us that they had already submitted the application for change of the name of the Supreme Council to the Cabinet Office.

November We had a meeting with First Assistant Dr. Nihal on November 4 toward the establishment of the PC, and agreed that we would form the PC preparatory committee. The Project team proposed that this committee should be composed of Dr. Nihal, Eng. Mostafa, and Dr. Shereen from the MOPMAR side, and three experts from JICA's project team. At the first meeting, First Assistant Dr. Nihal reported again that they had already submitted the application for change of the name of the Supreme Council from the present "Supreme Council of Urban Planning and Development" to the Cabinet Office.

December Toward the establishment of the PC, we had a talk with Minister Dr. Ashraf on December 27 (joined by First Assistant Dr. Nihal, Assistant to the Minister of MOPMAR Mostafa, Dr. Naruo, and Dr. Hisada) and confirmed the following activities. Minister Dr. Ashraf reported that the change of the name of "Supreme Council of Urban Planning and Development" (delete "Urban") had been agreed by the Cabinet Office and was in the process of the change of name.

3MOPMAR has, since 2015, aimed to change the name of the Supreme Council of Urban Planning Development to the Supreme Council of Planning Development (SCPD) by removing “Urban” from it and to establish a Supreme Council designed for planning administration (development). Recognizing that functions of this SCPD are able to perform roles of the PC, the Project has been working to promote the name change to SCPD as a PC start-up task.

9

Dr. Naruo made a proposal on forming the PC preparatory committee, and we agreed that it would be organized by about 10 people including Dr. Nihal, Eng. Mostafa, and Dr. Naruo. Minister Dr. Ashraf instructed that the SDS2030 Committee should serve as the PC preparatory committee.

2016 Minister Dr. Ashraf explained that the Cabinet Office had already (orally) agreed to the change of the name of "Supreme Council of Urban Planning and Development" (delete January "Urban") toward the establishment of the PC but the procedure was delayed because the Cabinet Office concentrated its efforts on responses to the parliament in session.

February Toward the establishment of the PC, we had a preliminary talk on the functions, constitution, and provisions (draft) of the PC with Assistant to the Minister of MOPMAR Mostafa (C/P) (February29), and prepared materials to explain and propose to the minister.

March Toward the establishment of the PC, the JICA team had the first meeting of the PC preparatory committee with First Assistant to the Minister of MOPMAR Dr. Nihal and Assistant to the Minister of MOPMAR Mostafa (March 3). 1) We discussed and agreed to the basic constitution and functions of the PC (Supreme Council of Planning Development) with First Assistant Dr. Nihal and Assistant to the Minister of MOPMAR Mostafa, key members of the Egyptian government. The PC will have four subcommittees (long-term plan, mid-term plan, annual plan, and comprehensive integration of policy functions). 2) The Egypt side is preparing to officially register the PC (Supreme Council of Planning Development) (requires prime minister's decree), but the date of registration completion is not yet fixed. We will check the date at the next meeting with the minister. 3) We will rearrange a meeting of the PC immediately after the Supreme Council of Planning Development was officially registered. 4) We proposed and prepared for the second meeting of the PC preparatory committee, but it was postponed on March 31, the meeting date, due to the minister's schedule. A date for the next meeting was arranged. 5) To build closer relationships with ministries and agencies scheduled to join the PC and develop human resources, we selected candidates for the second training in Japan (Planning administration) mainly from these ministries and agencies, and confirmed the nomination list as of March 31 with the minister.

April Toward the establishment of the PC, we had the second meeting of the PC preparatory committee at the MOPMAR’s Central Department for the Minister’s Office Affairs (April 7). Minister Dr. Ashraf, Deputy Minister Dr. Nihal, Assistant to the Minister of MOPMAR Mostafa, and Dr. Naruo attended the meeting. The main topics: (1) Confirmation of the progress of the change of the name and members of "Supreme Council of Planning Development (SCPD) (2) Confirmation of the status of the application for the second training in Japan (planning administration) from each ministry and the extension of the final deadline (3) Report on the progress of the support for preparing an English version of SDS2030.

10

The main points confirmed: (a) Deputy Minister Dr. Nihal reported that they tried to define the SCPD in the new Planning Law, but the legislation was stuck. (b) We confirmed with Minister Dr. Ashraf that we would wait for the prime minister to issue the SCPD decree. (c) We are uncertain about the deliberation, but once the Prime Minister Decree that redefines the SCPD is issued, we will be able to have the first meeting of SCPD based on the decree. (Topic (2) was reported along with the following item of the training in Japan, and Topic (3) along with the item of the Execution Plan.)

May Toward the establishment of the PC, we met Deputy Minister Dr. Nihal and discussed the progress and prospect of the change of the name to the "Supreme Council of Planning Development (SCPD)". The Project team requested Deputy Minister Dr. Nihal to promote the change. The Project team requested Deputy Minister Dr. Nihal and Assistant to the Minister of MOPMAR Mostafa to establish the PC early and call the first meeting of the PC. June Toward the establishment of the PC, we had the third meeting of the PC preparatory committee at MOPMAR’s Central Department for the Minister’s Office Affairs (June 21). Minister Dr. Ashraf, (Deputy Minister Dr. Nihal was absent), Assistant to the Minister of MOPMAR Mostafa, Dr. Naruo, Dr. Hisada and Mr. Maeda, experts attended the meeting. The main topic was the change of the name to "Supreme Council of Planning Development (SCPD)" (four other topics were reported along with the following items). The main points confirmed: As to the change of the name to SCPD, Minister Dr. Ashraf reported on the present state saying, "The change of the name to SCPD has not made any progress because the parliament deliberations on the new Public Officials Law and the new Planning Law are behind." Dr. Naruo stated, "SCPD is an organization to serve as the PC, so I hope that it is renamed soon." We reconfirmed the relation between the PC, EP, and SDS2030 in R/D (the Project). (Attachment 3)

July PC related activity: As an activity of the PC preparatory committee, we requested Assistant to the Minister of MOPMAR Mostafa to share information on the progress of the change of the name to Supreme Council of Planning Development (SCPD), and we continued to follow it.

August As an activity for the PC preparatory committee, we held the fourth meeting with Minister Dr. Ashraf (August 11). The minister gave an explanation of the SDS2030 follow-up seminar (held on August 2). MOPMAR was preparing laws related to the Ministerial Committee and the Technical Secretariat (functions as the secretariat) for SDS2030 follow-up. The change of the name to Supreme Council of Planning Development (SCPD) will probably take a while. (The Ministerial Committee and the Technical Secretariat are still at the planning phase, and their respective roles after the change of the name to SCPD have not yet been explicitly defined by MOPMAR.)

September As to the establishment of the PC, Minister Dr. Ashraf reported to the JICA Team that the change of the name to "Supreme Council of Planning and Development" (SCPD) proposed in August 2015 has not progressed for the past 12 months and that he could not see the end to this issue in sight, and explained the reasons.

11

October The change of the name to "Supreme Council of Planning and Development" (SCPD) has not progressed and we could not see when it would be realized.

November The fifth PC preparatory meeting was held on November 23, attended by Minister Dr. Ashraf, Deputy Minister Dr. Nihal, and the Assistant to the Minister of MOPMAR Mostafa. Deputy Minister Dr. Nihal said that he was preparing a draft application for the changing of the name from the present "Supreme Council of Urban Planning and Development (SCUPD)" to "Supreme Council of Planning and Development (SCPD)” and expected to be able to report the progress of this issue in December. We requested that he share the draft even if it were in Arabic, told them that the Project Team would send the definition document for the PC again, and sent the document.

December A meeting for “Reviewing the Project activities from July 2016 up to the present and confirming the scheduled Project activities starting in January 2017” concerning the Project was held on December 21, and was attended by Minister Dr. Ashraf and an Assistant to the Minister of MOPMAR Mostafa from MOPMAR, Mr. Sakamoto from JICA’s Egypt Office, Dr. Naruo and Dr. Hisada from the Project Team. The minister and the Dr. Naruo recorded the minutes of the meeting. We confirmed that the Project activities we conducted in response to MOPMAR’s announcement on August 2, 2016 helped us to formulate the mid-term plan for the education field. We confirmed at the above meeting that the Project Team would continue to help register and set up the Supreme Council of Planning Development (SCPD) after January as part of the activities for establishing the PC.

2017 There were no PC-related activities in January due to the preparing and conducting of the training course in Japan. January

February The reorganization of the Cabinet (approved by the parliament on February 14) caused the Minister Dr. Ashraf of MOPMAR and Deputy Minister Dr. Nihal of MOPMAR to be replaced by others. However, Dr. Nihal remained in the ministry as the Deputy Minister in charge of the monitoring by changing his position to that of an official of the ministry. We had the first meeting on February 19 with Dr. Hala Al-Saeed, the new Minister of MOPMAR. Minister Dr. Ashraf did not update any information on the PC this month.

March There was no update for any information on the PC. However, we confirmed with Minister Dr. Hala that we would prepare for the EK-P1 scheduled to be held jointly with the other ministries and agencies as described below:

We had a meeting with Minister Dr. Hala of MOPMAR, Deputy Minister Dr. Saleh, and Deputy Minister Nihal (in charge of the monitoring) on March 7 to brief them on the Project.

 Topic: JICA Project report to the Minister (In the past “June 2011–Feb 2017” and in the future “until Sep 2017”)  Date & Time: Tuesday, March 7, 2017, from 13:45 to 14:15  Place: Minister’s office at MOPMAR  Participants: Dr. Hala Helmy Al-Saeed Younis (new Minister of MOPMAR), Dr. Saleh Abdel-Rahman (new Deputy Minister of MOPMAR, Deputy Minister in 12

charge of MSAD, only present for the introduction), Dr. Nihal El Magharbel (MOP’s Deputy Minister in charge of monitoring, MOPMAR, left when the First Assistant in charge of MSAD was being introduced), Dr. Naruo (responsible for the summarization), and Dr. Hisada (responsible for the recording)

At the beginning of the meeting, Dr. Naruo explained to Minister Dr. Hala of MOPMAR the background of the JICA Project Team’s technical support and the present activities, and suggested a number of support activities to be conducted in the future.

The topics were as follows: A. History (Past): Briefing “JICA support activities for MOPMAR” (June 2011–Feb 2017) B. Current Situation (Now): Three themes in Planning the System in Egypt C. Future Proposal: Proposal of 3 options (April 2017–Sep 2017)

1. We explained the following three options for the activities to be conducted in the future regarding Topic C. Deputy Minister Dr. Saleh wished to hold a “Benkyo-kai” in the Planning One (BK-P1) “Cross-functional planning approach” stage in around July, after which MOPMAR would compile the budget. Planning 1.Cross-functional planning approach by BK =>Topics: Common planning platform in Egypt Planning 2.Bottom-up planning approach by BK =>Topics: Local government system and planning Planning 3.Integrated planning approach by BK =>Topics: How to develop a “policy plan” in MOPMAR.

2. Minister Dr. Hala appointed Deputy Minister Dr. Saleh as MOPMAR’s counterpart to hold the above BK-P1 and introduced him to the JICA Project Team. After the meeting with Minister Dr. Hala, we explained the background and the status of the Project, and outlined the planned future activities at the Deputy Minister’s office. 3. Minister Dr. Hala instructed us to distribute the National Planning Administration Text Book (the Arabic version compiled and translated by the JICA Project Team) to the other ministries and agencies, so we provided Deputy Minister Dr. Saleh with 40 books for distribution. We also provided textbooks to MOPMAR, and distributed them to the Director-level Officials, Secter Heads, Central Department Heads, General Department Heads, and the new Officials (total: 139 persons).

April There was no update for the information about the PC.

However, we continuously prepared for holding the Benkyo-kai on the Planning Administration (BK-P1) (agreed between Minister Dr. Hala of MOPMAR and us to take place in March) that would also be attended by the other ministries and agencies in charge of the Social and Economic Development Plan.

May There was no update for the information about the PC.

However, we had a meeting with the Deputy Minister of MOPMAR Dr. Saleh on May 13 and 23 concerning the Benkyo-kai on the Planning Administration (BK-P1) (agreed between Minister Dr. Hala of MOPMAR and us to take place in March) that would also

13

be attended by the other ministries and agencies in charge of the Economic and Social Development Plan, and talked about the following topics.

 Date & Time: Saturday, May 13, from 10:00 to 11:00  Place: Deputy Minister’s office on the 2nd Floor of MOPMAR  Participants: Deputy Minister Dr. Saleh, Mr. Iwasaki and Mr. Sakamoto (JICA’s Egypt Office), Dr. Naruo, Dr. Hisada  Main topics and contents: 1) Preparation for the holding of the first Benkyo-kai on the Planning Administration (BK-P1) and a Benkyo-kai on the training of trainers (BK-TOT): We confirmed with Deputy Minister Dr. Saleh that MOPMAR and the Project Team would work together to prepare for the BK-P1. Deputy Minister Dr. Saleh requested that a training course of the trainers (TOT) should be held on the method of the Benkyo-kai (BK) for the managers of the Human Resources Departments being reorganized in the ministries. The purpose of the BK-TOT was human resource development and to teach around 90 staff members from the ministries and agencies (about three staff members from each ministry and agency, excluding the Cabinet Office and the military-related ministries) how to apply the BK methods to their personnel system reforms. The participants were selected from among the staff (around 30 staff members in each ministry and agency) of the Human Resources Departments, which were planned to be reorganized a few months later. We confirmed that the BK-TOT and BK-P1 would be held on July 18 and July 19 respectively, and the Project Team proposed the concept paper for holding the BK-TOT and BK-P1 to Deputy Minister Dr. Saleh. 2) JICA’s mission and adjustment of the schedule: We confirmed that the meeting would be held on Tuesday, May 23, at 14:00. 3) “Constitution Constitution in Your Hand”: Deputy Minister Dr. Saleh suggested that we should distribute the handbooks to all ministries and agencies and members of the parliament, so we are now preparing for this. 4) Others: Duputy Minister Dr. Saleh requested that we hold a Benkyo-kai on the planning administration for the senior managers of MOPMAR (this was previously scheduled for Saturday, May 20, but was postponed). Dr. Saleh requested that we provide information on the reform of the administrative organization of the MSAD (Ministry of State for Administrative Development under MOPMAR), and we shared the knowledge of Japan by providing the relevant materials.

 Date & Time: Tuesday, May 23, from 14:00 to 15:30  Place: Deputy Minister’s office on the 1st Floor of MSAD (Ministry of State for Administrative Development under MOPMAR)  Participants: Deputy Minister Dr. Saleh, Mr. Ono (Middle East Section 1 of JICA Head Office), Mr. Iwasaki and Mr. Sakamoto (JICA’s Egypt Office), Dr. Naruo, Dr. Hisada  Main topics and contents: 1) BK-TOT and BK-P1: We explained the Concept Paper (proposed on May 13) again. We confirmed again that we would hold the BK-TOT on July 18 and the BK-P1 on July 19 on the condition that the MOPMAR would prepare a participant list by July 5. 2) “Constitution Constitution in Your Hand”: The Project Team prepared 950 sets (of the 3-volume series). Deputy Minister Dr. Saleh requested that we additionally paste the logo of MOPMAR on the inside of the front cover, so we decided to prepare a sample to provide to the Deputy Minister Dr. Saleh. He also 14

requested the posting of a soft copy of the “Constitution Constitution in Your Hand” series on the MOPMAR’s website, so we provided this. 3) The Benkyo-kai on the planning administration for the senior managers of MOPMAR: The Project Team stated that we were always ready if the date and time for the Benkyo-kai could be fixed. (This Benkyo-kai (originally scheduled for May 27) was postponed and the date and time has subsequently not been determined. Deputy Minister Dr. Saleh was asked to consider the date and time, and will inform the Project Team of this after he has determined it.) 4) Administrative reform: We have already provided the materials about the knowledge of Japan (administrative organizations, systems and the E-government in Japan). 5) Support for holding the BK-E6: At the Ministry of Higher Education and Scientific Research, Minister Dr. Hala attended the start of the meeting. We reported that we helped hold the BK-E6 in the morning of May 23, and provided him with the materials from the BK-E6. 6) Project Terminal Evaluation Mission at the end of the Project: Mr. Ono explained the purpose of the group and the schedule. We confirmed that a study would be conducted in late August, and we agreed that the MOPMAR and the JICA Team would jointly conduct such a study. Deputy Minister Dr. Saleh intended to ask Minister Dr. Hala of MOPMAR whether or not Deputy Minister Dr. Saleh would be the supervisor for MOPMAR and the consensus document signer.

1-2. Execution Plan (EP) (PDM: Activity 1-3 to 1-4) (Figure 4, 1-2.)

(1) Support for SDS2030

(a) Overview of the outputs related to the support for SDS2030

We gave support for editing and analyzed the contents of the English version of SDS2030, positioned as the long-term national plan. The analyzed contents was the basic data for the EP which would to be developed in the future.

(b) Monthly activities related to the support for SDS2030

2015 MOPMAR intends to complete SDS2030 by November, and externally had an explanatory meeting for private sectors. October

November First Assistant Dr. Nihal said (November 4) that they aimed to complete SDS2030 by the end of November, but subsequently we were informed by the Project team of First Assistant Dr. Nihal that the completion had changed to the end of December.

December First Assistant Dr. Nihal said that as SDS2030 had been completed in the Arabic version and English version, they would share a soft copy of them with JICA's project team (at the meeting with the minister on December 27). First Assistant Dr. Nihal said that as they wanted to translate the introduction to SDS2030 into several languages to distribute

15

them to the embassies of various nations, they wanted to ask JICA's project team to translate it into Japanese.

2016 We received a letter of invitation by email dated January 20 to the meeting where SDS2030 was publicly released. This meeting, organized by Minister Dr. Ashraf of January MOPMAR, was called on January 28. As SDS2030 is an important base for the PC to develop EP (Execution Plan), Dr. Naruo made an official trip to attend the meeting (engaged in local operations from January 27 to 30, 2016). It was suddenly decided at the meeting for the prime minister and key members of the Cabinet (January 26), called by the president, that the SDS2030 meeting (scheduled to be held on January 28), called by Minister Dr. Ashraf, would be postponed. It was decided at the above meeting that the president would attend the SDS2030 meeting. The government regards the SDS2030 meeting as a very important meeting, so the date and venue of the meeting were announced later by the office of the president.

February President el-Sisi officially unveiled SDS2030 live on the TV (February 24). We gained the information at the MOPMAR on February 23, the day before (The information was also posted on the Internet in the afternoon of February 23). As to the official announcement of SDS2030, we analyzed the content aired on the TV and the content reported in newspapers. We received a book in Arabic after the official announcement of SDS2030 on February 28, and downloaded the data in Arabic and the abridged English version from the website of SDS2030. We received the written request from Dr. Nihal for support for reviewing and editing the English version (entirely translated from Arabic) of SDS2030 (February 28). We received a soft copy of the English version (February 29) and made a brief review on the same day. The Project team decided that it was necessary to complete the English version of SDS2030 early to examine the contents, and gave support for reviewing and editing it.

March While the president unveiled the abridged English version of SDS2030 in February, the entirely translated version had not been completed. We were requested by First Assistant Dr. Nihal and Minister Dr. Ashraf to support editing of the English version (March 1). We decided that it was essential to examine the English version to develop the EP, which the Project aims for, and started supporting editing work.

April To grasp and analyze the full text of SDS2030, we helped them to have a native speaker check and edit (the contents translated from Arabic into English) to complete the entirely translated version. We submitted a bound copy in color and a compact disc of the entirely translated version to Minister Dr. Ashraf (April 13). We bound the entirely translated version into books, and provided them to Deputy Minister Dr. Nihal and Assistant to the Minister of MOPMAR Mostafa.

May We obtained the information that although SDS2030 was just unveiled in February, the team of Deputy Minister Dr. Nihal was following it.

June JICA's team analyzed the relations between the 10 pillars and the indexes of SDS2030. At the meeting with the minister (June 21), we confirmed that the team of Deputy Minister Dr. Nihal was sorting out items by theme based on the10 pillars of SDS2030. The Project team analyzed the above contents.

16

August Minister Dr. Ashraf and Deputy Minister Dr. Nihal explained the implementation of SDS2030 to people involved (The meeting was held on August 2, and participated in by about 300 people). Media people also participated and it was aired live on the TV. There are three subcommittees under the Ministerial Committee organized by the prime minister and the Technical Secretariat (functions as the secretariat) organized by the minister of MOPMAR. Under the subcommittees, there are 10 task force teams which develop mid- term plans for individual themes (2017-20), and manage and report on the progress. The teams have 220 people assigned by theme from related ministries and agencies, and are joined by members of the parliament, professionals from private sectors, and experts from universities to develop plans and manage progress. Deputy ministers, ministerial Assistants, and directors from related ministries and agencies have been already assigned to task force teams, and the first task force meeting has been held. For leaders of task force teams, First Assistant to the Minister of Electricity and Energy Omar, Special Assistant to the Ministry of Higher Education and Scientific Research Dr. Khaled and other participants in the NPA training in Japan have been nominated. We met Deputy Minister Dr. Nihal on August 15 to confirm the content of SDS2030 follow-up activities. JICA’s project team confirmed that they would support task force activities.

September We have described the (task force support) activities after September 2016 in the to May following item “(3) Support for the formulation of the mid-term plan (MTP) (from 2017 2017 to 2020) related to the educational administration”.

(2) Support for developing the EP

(a) Overview of the outputs related to the support for the development of the EP

Although the members of the PC have not been organized yet, we prepared a Policy Paper (PP) as the prototype for the EP, which was supposed to be developed by the PC, and shared it with the section which prepares MOPMAR's public work annual budget. Sector managers who are responsible for the public works annual budget requested to share a soft copy of the Project’s Policy Paper for reference to compile the public works budget for FY 2016/17. Details on the use of the Policy Paper will be investigated during the next revision.

(b) Monthly activities related to the support for the development of the EP

2015 We were planning to immediately start preparing for the development of the EP (Execution Plan) after the PC preparatory committee was set up. We undertook the October development of the proposed organization for planning administration in Egypt (field, relation, class, basic laws, and responsibilities for development/execution). We started preparing the framework for planning administration based on the constitution of 2014, Presidential Decree No. 122 of 2015, and MOPMAR's current operations.

November We started preparing for the creation of Policy Paper, the prototype for the EP (Execution Plan). Instructed by the prime minister, Minister Dr. Ashraf started preparing MOPMAR's 17

mid-term investment plans (from June 2016 through June 2018). First Assistant Dr. Nihal was in charge of preparing this. After being prepared, the plans needed to be approved by the parliament.

December We reported that after preparing Policy Paper (the prototype for EP) for the public investment system, we would share it with MOPMAR's sector in charge, and gained approval of sharing from the minister. We prepared a Policy Paper, the prototype for EP, for the public investment (mid-term investment plans (from June 2016 through June 2018)) (English version), and started preparing for the translation (Arabic). Minister Dr. Ashraf instructed us to promptly report on the Egypt version of the Fiscal Investment and Loan Program (FILP) proposed by Dr. Naruo after discussing with First Assistant Dr. Nihal and Assistant to the Minister of MOPMAR Mostafa. Minister Dr. Ashraf instructed First Assistant Dr. Nihal to share Policy Paper for rural development with people involved. Minister Dr. Ashraf instructed First Assistant Dr. Nihal and Assistant to the Minister of MOPMAR Mostafa to report on Policy Paper for rural development proposed by Dr. Naruo after discussion.

2016 We developed a Policy Paper supporting public investment budget making, regarded as the prototype for the EP. (Dr. Naruo reported the minister on January 28 that he would January share this Policy Paper for public investment budget making with MOPMAR's sector in charge when it was prepared.) We developed Policy Paper that reflects policy requirements in the process of public investment budget making, handed it to our counterpart (Eng. Mostafa), sector managers (Dr. Hazem Fahmy: Sector manager of Infrastructure and production activities and Mr. Mohamed Faried: Sector manager of Human and social development). Sector managers requested us to provide a soft copy as they wanted to refer to it when developing the public investment plan for FY 2016/17, so we sent the file. As the Policy Paper is the prototype for the EP, we continued to monitor and follow the reflection of it in the mid-term public investment plan for 2016/2018.

February We edited and bound the Policy Paper (draft version) supporting public investment budget making, regarded as the prototype for the EP, and prepared to distribute it to the related sectors and sections of MOPMAR.

March We added information and bound the booklet of the Policy Paper (the prototype for the EP to be prepared in the future) distributed to related departments within MOPMAR (December 2015) as a reference to develop the annual plans for FY 2016/17. We shared the bound Policy Paper again with MOPMAR's related departments. We provided and explained the Policy Paper individually to all the sector managers of MOPMAR, and asked them to share it with the central manager of each organization. We felt that it penetrated through organizations remarkably because some parts were translated into Arabic. Most of the managers expressed their understanding and gratitude for the contents. After the preparation in December 2015, SDS2030 and the Government Program were unveiled in February 2016 and March 2016, respectively. We continue to update information and intend to issue the revised version before the start of preparing the annual plan for FY 2017/18 (around December 2016).

April Preparation for revising the Policy Paper, the prototype for the EP:

18

The government submitted the Government’s Program unveiled in March 2016 to the parliament (April 3). The parliament approved the Government’s Program with the consent of 433 (91%) lawmakers (April 20). The Policy Paper developed in January does not include any details of the Government’s Program because the program was not yet announced. Therefore, the preparation for revising the Policy Paper was started after the parliament approval.

May We obtained all the text of the Government’s Program 2016-18 (approved by the parliament on April 20) in Arabic (205 pages) and started translating it from Arabic into English. We will incorporate the Government’s Program 2016-18 as guidelines for the Policy Paper regarded as the prototype for the EP.

June We finished translating all the text of the Government’s Program 2016-18 (approved by the parliament on April 20) from Arabic (205 pages) into English (236 pages).

August We analyzed the difference between the EP of JICA’s R/D model and the mid-term plan of MOPMAR’s SDS2030 model, based on details of SDS2030 follow-up activities announced by MOPMAR on August 2.

(3) Support for the formulation of the mid-term plan (MTP) (from 2017 to 2020) related to the educational administration (a) Overview of the outputs related to the support for the mid-term plan

Minister Dr. Ashraf and the Project Team concluded the minutes of the meeting on December 21, and confirmed that “the Project activities we conducted in response to the MOPMAR’s announcement on August 2, 2016 helped to formulate the mid-term plan for the education field.” Prior to the signing, MOPMAR, the Ministry of Education and Technical Education (MOE&TE), and the Ministry of Higher Education and Scientific Research (MOHE&SR) jointly held the third “Benkyo-kai” on the education policy/planning on December 14. During the opening speech, Minister Dr. Ashraf of MOPMAR said that the “Benkyo-kai” jointly held by the MOE&TE and the MOHE&SR was important for the formulation of the mid-term plan for SDS2030 and that he expected that the Benkyo-kai would make contributions to this plan. We helped formulate the mid-term plan (from 2017 to 2020) related to education (Pillar 3 “Knowledge, Innovation and Scientific Research” and Pillar 7 “Education and Training (Public Elementary Education (Pre-University), Technical Education and Training, University or Higher Education”) for SDS2030 implemented by MOPMAR, and the mid-term plan related to education (Public investment plan from 2017 to 2020) (hereinafter, the “MTP”) that was submitted to MOPMAR in February 2017 as scheduled. The Project Team analyzed the submitted MTP, and gave feedback to the Ministry of Higher Education and Scientific Research (MOHE&SR) and the Ministry of Education and Technical Education (MOE&TE). We prepared a working paper for the results of the MTP analysis of the general education, technical education, and higher education with three working groups from the ministries. A “Benkyo-kai” to share the working paper was held jointly with the MOHE&SR (attended by the minister).

19

(b) Monthly activities related to the support for the mid-term plan

2016 We talked with Mr. Khaled, Special Assistant to the Minister of the MOHE&SR (September 4) about the formulation of the mid-term plan (2017-20) for the MOHE&SR September and the third training course in Japan, and we agreed on the way of the future support. At the meeting to report on the progress of the Project to JICA’s Middle East and Europe Department (September 23), we agreed that we would help the MOE&TE to formulate their mid-term plan in addition to the MOHE&SR, and would aim to support the formulation of a comprehensive mid-term plan for the education field.

October As support for the formulation of the mid-term plan (from 2017 to 2020) for SDS2030 implemented by MOPMAR, we gave cross-ministry support to the Ministry of Higher Education and Scientific Research (MOHE&SR) and the MOE&TE. We talked with Dr. Ahmed Elgeushey, Deputy Minister of the MOE&TE (in charge of TVET) (October 8), where we suggested that the minister should participate in a “Benkyo-kai (Japanese-style training course)” and we agreed to hold it on October 24. Based on the outputs of the first Benkyo-kai (BK-E1), we suggested quotas for the recommendations regarding the numbers of trainees to the MOHE&SR, MOE&TE, and MOPMAR. He said that he would request 10 officials from the MOHE&SR, 5 officials from the MOE&TE, and 4 officials from the MOPMAR.

We talked with Mr. Khaled, First Assistant to the Minister of the MOHE&SR on October 3 and 18 and to Dr. Ahmed Elgeushey, Deputy Minister of the MOE&TE on October 5 and 18 about holding a “Benkyo-kai” on the education policy/planning to help formulate the mid-term plan for the Ministry of Higher Education and Scientific Research (MOHE&SR) and the MOE&TE. We agreed to hold three “Benkyo-kais” on the education policy/planning before the training course to be held in Japan (scheduled for late January 2017). We agreed that the first Benkyo-kai (October 24) would be held by the MOE&TE with 52 participants (80% from the MOE&TE and 20% from the MOHE&SR), and the second Benkyo-kai (November 8) would be held by the MOHE&SR with 80% of the participants from the MOHE&SR and 20% from the MOE&TE. We also agreed that the third Benkyo-kai (scheduled for mid-December) jointly held by both ministries would be attended by the same numbers of participants from the two ministries.

November The second “Benkyo-kai” on the education policy/planning was held by the Ministry of Higher Education and Scientific Research (MOHE&SR) on November 8. During the opening, Minister Dr. Ashraf of the MOHE&SR made a speech in front of the media, and stated the future plans for higher education and scientific research, and the importance of developing human resources who can respond to industrial needs.

December The third “Benkyo-kai” on the education policy/planning was jointly held by the MOPMAR, MOE&TE, and the Ministry of Higher Education and Scientific Research (MOHE&SR) on December 14. During the opening speech, Minister Dr. Ashraf of MOPMAR said that the “Benkyo-kai” jointly held by the MOE&TE and MOHE&SR was important for the formulation of the mid-term plan for SDS2030 and that he expected that the Benkyo-kai would make contributions to this plan.

2017 Participants in the training course in Japan shared the information that the MOE&TE and the Ministry of Higher Education and Scientific Research (MOHE&SR) submitted in January their (draft) mid-term plans to the MOPMAR just before their participation in the

20

training course in Japan. We obtained and examined the submitted mid-term plans, and then helped to formulate the mid-term plan by utilizing the outputs of the training course held in Japan.

February We held the fourth education-related “Benkyo-kai” on February 22 to help formulate the mid-term plan (from 2017 to 2020) related to the education (Pillar 3 “Knowledge, Innovation and Scientific Research” and Pillar 7 “Education and Training (Public Elementary Education (Pre-university), Technical Education and Training, University or Higher Education”) for SDS2030.

March The Project Team analyzed (Note 1) the mid-term plan (Public investment financial plan from 2017 to 2020) (hereinafter, the “MTP”) formulated by the MOE&TE and the MOHE&SR, and gave feedback to the MOHE&SR (March 22) and the MOE&TE (March23). We encouraged both ministries to share the results of the MTP analysis between themselves. The Project Team started formulating a “new integrated MTP” based on the analysis results of both ministries’ MTPs. (Note 1: “Overview notes” indicate the “(Draft) Internal working paper to study for mid- term plan pre-university education” (MOE&TE) and the “(Draft) Internal working paper to study for mid-term plan higher education” (MOHE&SR).)

April Based on the results of the analysis of the mid-term plan (Public investment financial plan from 2017 to 2020) (hereinafter, the “MTP”) (Note 1) provided by the Project Team to the MOE&TE and the MOHE&SR, we completed reviews with the planning teams of both ministries: 10 times with the General Education Planning Team of the MOE&TE, 5 times with the Technical Education Planning Team of the MOE&TE, and 3 times with the MOHE&SR. We helped hold a “Benkyo-kai (BK-E6)” to formulate an MTP that would integrate the MTPs of the MOE&TE and the MOHE&SR.

May Based on the analysis result of the mid-term plan (Public investment financial plan from 2017 to 2020) (hereinafter, the “MTP”) (Note 1) provided by the Project Team to the MOE&TE and MOHE&SR, we prepared a working paper for the results of the MTP analysis of the general education, technical education, and higher education with the three working groups from the ministries.

(4) Support for annual plans

(a) Overview of the outputs related to the support for annual plans

We translated into English and analyzed the content of the social and economic development (public investment) annual plans 2015/16 of the public works annual budgets FY 2015/16, and posted it on the website of the Project to share information with aid agencies including international organizations.

For annual plans, MOPMAR annually formulates public investment budget documents, and we will help MOPMAR with annual planning for FY 2016/17 if it requests us to do so.

(b) Monthly activities related to the support for annual plans

21

2015 We helped translate social and economic development (public investment) annual plans 2015/16 and completed the first draft translated version. October

November As to the support for the translation (from Arabic into English) of the social and economic development (public investment) annual plans 2015/16, we finished reviewing it within JICA's project team on November 30. The review work we were engaged in with First Assistant Dr. Nihal’s team at the same time had not finished in November, so we continuously urged them to finish the review work.

December First Assistant Dr. Nihal reported at the meeting with the minister that they had finished translating the social and economic development (public investment) annual plans 2015/16 (from Arabic into English) with support of the Project team. The Project team suggested that we should print dozens of copies of the plans and distribute them jointly with MOPMAR to major international aid agencies and major government bodies including the Executive Office of the President and Prime Minister's Office to confirm and share the relation between the plan and SDS2030, which was approved.

2016 We bound the English version of the public investment annual plans FY 2015/16, translated by the Project team, and made a distribution list of the plans. February

March We bound 50 booklets of the English version of the public investment annual plans FY 2015/16, of which 40 booklets (provided to First Assistant Dr. Nihal) were distributed directly to related organizations by MOPMAR. MOPMAR plans to post it on the website, but we made it available on the website of the Project as well.

2. Restructuring of the organizational framework of MOPMAR and support for enhancing the capacity of MOPMAR’s staff (PDM: Output 2) (Figure 4, 2.)

2-1.Policy formulation local training (short-term dispatched experts) (PDM: Activity 2-2) (Figure 4, 2-1.)

(a) Education/vocational training policy

(a) Overview of the outputs related to education/vocational training policy (Dr. Hiromi Nagao, expert)

In response to the request for a lecture on “educational councils” from Mr. Khaled, First Assistant to the Ministry of Higher Education, who participated in the second training in Japan, we gave a lecture on the organization, functions, and operations of Japan's educational administration councils to the minister and assistants at the Ministry of Higher Education in Egypt (July 3). We exchanged opinions (question and answer session) so that Egypt would be able to adopt knowledge of Japan, and it has been recognized by participants including the minister that the country also needs council functions in order to vitalize educational administration.

22

(b) Monthly activities related to education/vocational training policy (Dr. Hiromi Nagao, expert)

2015 We conducted a study on the Projects related to education programs provided in Egypt December with respect to the operations by short-term dispatched experts in education/vocational training policy. JICA's project team reported Minister Dr. Ashraf that we were prepared for holding a joint seminar related to education development in cooperation with the Ministry of Education and Vocational Training and MOPMAR (December 27). The minister instructed us to give priority for considering how we conduct projects related to education.

2016 We explained to Presidential Faiza Abou el-Naga, Minister Dr. Ashraf, Mr. Ito, the Chief Representative of JICA’s Egypt Office, and Ambassador Kagawa that we would have Dr. January Hiromi Nagao, expert (in vocational training) from February 12 until February 22, and started arranging school visits (E-JUST, public elementary and junior high schools) and a study.

February As an activity by short-term dispatched experts, Dr. Hiromi Nagao, expert (education/vocational training) conducted the first local activity, and we reported it to JICA’s Egypt Office (February 21). We reported the activity by the expert at a television conference with JICA (February 24) and confirmed the next activity.

June As to short-term dispatched experts, Dr. Naruo explained the contents of operations by Dr. Hiromi Nagao, expert (education/vocational training) (scheduled to be dispatched to Egypt from July 1 until July 5) and Mr. Takayuki Tsumori (transport policy), expert (scheduled to be dispatched to Egypt from July 18 until 21) to Minister Dr. Ashraf, and gained his approval. First Assistant to the Minister of Higher Education, a participant in the second training in Japan, requested Dr. Nagao, expert, to give a lecture on "education council".

July As Mr. Khaled, First Assistant to the Minister of Higher Education, a participant in the second training in Japan requested Dr. Nagao, expert, to give a lecture on "education council", she gave a lecture to the minister, Assistants to the minister, and other staff (about 15 persons) and answered their questions (July 3). - We exchanged opinions with Presidential Aide Dr. Faiza Abou el-Naga (the former minister of MOPIC) about education systems in Japan and Egypt (July 3). We visited a Japanese school in Egypt, YMCA, and ASHOKA, and exchanged opinions about education issues. We put recommendations together on education/vocational training policy (work in Japan).

(b) Industrial policy and energy policy

(a) Overview of the outputs related to industrial policy (Dr. Daiji Fujii and Dr. Shinji Naruo, experts) and energy policy (Dr. Masao Tsuri, expert)

23

We held a seminar on industrial policy and energy policy jointly with INP, and exchanged opinions about knowledge of Japan. Through this seminar and the study in the first dispatch, we prepared a resume for the same field "(knowledge sharing) Benkyo-kai (unique Japanese participatory learning style workshop)" in the second dispatch, and held a seminar on the same field for MOPMAR's staff.

We translated the reports prepared by the short-term dispatched experts in the energy policy and industrial policy into English and Arabic in order to distribute them to the participants in the “Benkyo-kai” from the related ministries and agencies and universities.

(b) Monthly activities related to industrial policy (Dr. Daiji Fujii and Dr. Shinji Naruo, experts) and energy policy (Dr. Masao Tsuri, expert)

2015 As support for policymaking, we started a study in Japan (Okayama University) and Egypt to prepare to accept short-term dispatched experts by raising the priority. November

2016 We prepared to accept Dr. Fujii and Dr. Naruo, experts (industrial policy) and Dr. Tsuri, expert (energy policy) (from March 11 until 22) by prior collection of information related February to their field studies.

March Dr. Masao Tsuri, short-term dispatched expert (energy policy) implemented operations of macroeconomics, fiscal policy, and housing policy in Egypt (from March 10 until 23). Dr. Daiji Fujii and Dr. Shinji Naruo, experts (industrial policy (1) (2)) conducted field studies on SME policy, industrial organization policy, and business innovation (from March 10 until 23). We held a "Workshop for FILP and business innovation" jointly with INP (March 17) where Dr. Tsuri, expert, Dr. Fujii, expert, and Dr. Naruo gave a presentation on "Japan's Fiscal Investment and Loan Program and Housing", "Business Innovation", and "Industrial Policy", respectively, and exchanged opinions.

August Dr. Masao Tsuri (energy policy): He considers the revitalization of energy services in Egypt from the perspective of fiscal investment and loans. We held a “Benkyo-kai” on energy policy and investment and loans for those involved in industry-academia- government, cross-ministry and agency policy fields (August 30). Dr. Daiji Fujii (transport policy): He considers the revitalization of industries in Egypt from the perspective of the private sector. We held an industrial policy seminar for MOPMAR’s staff (August 31).

September Support for the onsite learning for the officials of MOPMAR (on-the-job training for public investment examination officials): 1) Visit to an automobile assembly company and the factory of a food company in the Bolg El-Arab Industrial Zone (September 1, 1 participant from the Industrial Infrastructure Team) 2) Visit to E-JUST (September 1, 7 participants from the Higher Education Investment Team)

Workshop with E-JUST:

24

1) After the visit to E-JUST, Dr. Fujii explained the purpose of the visit and exchanged opinions with President El-Gohary and the other faculty staff (September 1). 2) Opinions were exchanges with Director Farid of MOPMAR (education/medical/public service investments) and the Secretary-General of E- JUST (September 1).

Study activities by the short-term experts: Borg El-Arab Industrial zone (visits to industries in Egypt and industrial zones) (September 1)

Dr. Tsuri held the energy policy seminar “FILP for Housing and Energy: Application of Japan’s Economic Policy in Egypt” (September 4). Dr. Fujii held the industrial policy seminar “Semi-Hierarchical Inter-Organizational Arrangements and their Adaptive Rationality under a Highly Uncertain Business Environment” (September 5). We reviewed the policies in a Japanese-style “Benkyo-kai”. Some institutional participants asked us if a Benkyo-kai could be held at their institutions.

2017 We translated the report prepared by the short-term dispatched experts in the energy policy and industrial policy from English into Arabic, and continued to compile it. April

May We translated the report from English into Arabic, and also compiled and printed the report prepared by the short-term dispatched experts in the energy policy and industrial policy.

August We distributed the English and Arabic versions of the report prepared by the short-term dispatched experts in the energy policy and industrial policy titled “National Planning Administration: Policy Textbook, Specific Policies, Fiscal Investment and Loan Program (FILP) for Energy and Housing, Maritime Transportation, and Industry” to the organizations visited by the short-term experts and to the participants in the Benkyo-kai.

(c) Transport policy

(a) Overview of the outputs related to transport policy (Mr. Takayuki Tsumori, expert)

Mr. Tsumori held a workshop on maritime transport policy at the Canal Authority, and exchanged opinions about knowledge of Japan (question and answer session). Through this seminar and the study in the first dispatch, we prepared a resume for the same field "(knowledge sharing) Benkyo-kai" in the second dispatch, and conducted a seminar on the same field for MOPMAR's staff.

We translated the report prepared by the short-term dispatched experts in the transport policy from English into Arabic, and distributed it to the participants in the “Benkyo-kai” from the related ministries and agencies and universities.

25

(b) Monthly activities related to transport policy (Mr. Takayuki Tsumori, expert)

2015 As support for policymaking, we started a study in Japan (Okayama University) and Egypt to prepare to accept a short-term dispatched expert by raising the priority. November

2016 We exchanged opinions about the situation of maritime transport at INP (July 17). We visited the Arab Academy for Science, Technology and Maritime Transport) and July exchanged opinions (July 18). We visited the Economic Zone and exchanged opinions (July 18). We exchanged opinions with MOPMAR's staff in charge of transport policy (July 19). We visited JETRO in Egypt and exchanged opinions (July 19). We explained the situation of Japan's maritime transport and exchanged opinions at the Suez Canal Development Agency (Ismailia) (July 20). Subsequently, we visited the Suez Canal and the second Suez Canal by boat.

August We considered maritime transport and port logistics, and held a transport policy seminar for MOPMAR’s staff (August 29).

September Support for onsite learning for the officials of MOPMAR (on-the-job training for public investment examination officials): 1) Visit to a Authority (September 1, 1 participant from the Transportation Infrastructure Team) 2) Visit to an Alexandria Port Authority (September 2, 1 participant from the Transportation Infrastructure Team)

Study activities by the short-term experts: 1) Visit to a Port Said Authority (study on the management and inspection of Suez- related harbors) (September 1) 2) Visit to an Alexandria Port Authority (study and inspection of the management of harbors) (September 2)

We held a transport policy seminar concerning the “Agglomeration of Logistics Functions and Economic Development in Egypt” (September 3).

2017 We translated the report prepared by a short-term dispatched expert in the transport policy from English into Arabic, and continued to compile it. April

May We translated the report from English into Arabic, and also compiled and printed the report prepared by a short-term dispatched expert in the transport policy.

August We distributed the English and Arabic versions of the report prepared by the short-term dispatched experts in the energy policy and industrial policy “National Planning Administration: Policy Textbook, Specific Policy, Fiscal Investment and Loan Program (FILP) for Energy and Housing, Maritime Transportation, and Industry” to the organizations visited by the short-term experts and to the participants in the Benkyo-kai.

(d) Seminar in Egypt (“Benkyo-kai”)

26

(a) Overview of the outputs related to the seminar in Egypt (“Benkyo-kai”)

With regard to the above-mentioned “Support for the formulation of the mid-term plan (MTP) (from 2017 to 2020)” related to the educational administration, we held six “Benkyo-kais” on the education policy/planning to support the “Education and Training (Public Elementary Education (Pre-university), Technical Education and Training, University or Higher Education)” (Pillar 7) and the “Knowledge, Innovation and Scientific Research” (Pillar 3) in the mid-term plan (from 2017 to 2018) for SDS 2030.

Knowledge learned through the “Benkyo-kais” helped us to submit the Pillar 7 and Pillar 3 MTPs for the SDS2030 as scheduled, and to improve the quality. The Project Team analyzed the submitted MTP, and gave feedback to the Ministry of Higher Education and Scientific Research (MOHE&SR) and the Ministry of Education and Technical Education (MOE&TE). Subsequently, we prepared a working paper for the results of the MTP analysis of the general education, technical education, and higher education with three working groups from the ministries. The MOHE&SR held a “Benkyo-kai” to share the knowledge of the working paper (attended by the minister).

(b) Monthly activities related to the seminar in Egypt (“Benkyo-kais”)

2016 We held the first “Benkyo-kai” on the education policy/planning to support the “Education and Training (Public Elementary Education (Pre-university), Technical October Education and Training, University or Higher Education)” (Pillar 7) and the “Knowledge, Innovation and Scientific Research” (Pillar 3) in the mid-term plan (from 2017 to 2018) for SDS2030. 1) Date: October 24 2) No. of participants: 52 (MOE&TE: 31, MOHE&SR: 1, MOPMAR: 2, others (private enterprises, universities, research institutes, etc.): 18) 3) Main contents: Introduction of the concept and method of a “Benkyo-kai”; Keynote speech: Mechanisms of education (education in Japan, vocational education in Egypt, education before entering university in Egypt, required human resources and the development of human resources by looking at an example of the steel industry in Egypt); planning process for the formulation of a mid-term plan; group discussion (six themes: quality of education, school operation/management, human resources needs in the society and in industry, education infrastructure, quality of teachers, and the education industry); and the presentation of the discussion results

November As support for the education-related pillars (Pillar 3 “Knowledge, Innovation and Scientific Research” and Pillar 7 “Education and Training (Public Elementary Education (Pre-university), Technical Education and Training, University or Higher Education”) in the mid-term plan (from 2017 to 2018) for SDS2030, we held three “Benkyo-kais” on the education policy/planning in a series for the MOE&TE and the Ministry of Higher Education and Scientific Research (MOHE&SR) starting in October 2016. The second “Benkyo-kai” was held mainly for the MOHE&SR. 1) Date: November 8 2) No. of participants: 66 (MOHE&SR: 16, science and technology-related institutes: 12, universities: 19, MOE&TE 6, MOPMAR: 3, INP: 3, private industries: 2, JICA Egypt: 2, others: 3)

27

3) Purpose: “Root cause analysis” by taking the project planned by the MOHE&SR as an example 4) Concept: Raising awareness of the relationship between the education-related policy and planning with regard to the formulation of the mid-term plan 5) Main contents: Opening speech: medium and long-term plans for higher education and scientific research in Egypt; Keynote speech: Introduction of the concept and method of a “Benkyo-kai”; mechanisms of higher education and the scientific research education in Japan and Egypt; required human resources and the development of human resources by looking at an example of the steel industry, one of the key manufacturing industries in Egypt (Ezz Steel, Instructor: Senior Manager, Process & Quality Control); the process for formulating the mid-term plan; group discussion on 6 themes (university admission system, academic staff and instructors at universities, issues facing university students, autonomy and management of universities, issues related to securing the academic levels of universities, information technology and education) using the Toyota Production System’s “5 Whys Method”; and the presentation of the discussion results December As support for the education-related pillars (Pillar 3 “Knowledge, Innovation and Scientific Research” and Pillar 7 “Education and Training (Public Elementary Education (Pre-university), Technical Education and Training, University or Higher Education”) in the mid-term plan (from 2017 to 2020) for SDS2030, we held three “Benkyo-kais” on the education policy/planning in a series for the MOE&TE and MOHE&SR starting in October 2016. The third “Benkyo-kai” was a joint one for the MOE&TE and MOHE&SR (December 14). 1) Date: December 14 2) No. of participants: 62 (MOPMAR: 12, MOE&TE: 20, MOHE&SR: 16, universities: 8, INP: 1, JICA Egypt: 4, others: 1) 3) Purpose and concept: Project implementation assessment taking the projects planned by the MOE&TE and MOHE&SR as examples 4) Main contents: (1) Opening speech: SDS2030 and the education-related mid-term plan (from 2017 to 2020) by the minister of MOPMAR (2) Keynote speech: (a) Competency-based dual system and curriculum reforms and in-service “teacher training” for the MOE&TE’s mid-term plan (2017 to 2020) by the Deputy Minister of MOE&TE, (b) Admission exams and pre-service “teacher training” and Scientific Technology Parks for the MOHE&SR’s MTP (2017 to 2020) by the Senior Assistant to the Minister of the MOHE&SR, (c) Planning and implementation methods in education’s MTP (2017 to 2020) by Dr. Naruo (3) During a group discussion, we conducted a project implementation assessment taking eight projects ((a) School Management, (b) Curriculum development, (c) Competency based on a dual system implementation, (d) Competency based on a curriculum reform, (e) Admission exams: the dynamic acceptance policies compatible with the capabilities of the student, (f) Pre-service teacher training (academic staff): the forming and constructing of distinctive teaching cadres, (g) Scientific Research: knowledge production, technology transfers and technology adaptation, to contribute to the economic and environmental development, and (h) Scientific Technology Parks (STPs)) as examples by applying the assessment tools, and presented the discussion results.

2017 The fourth education-related “Benkyo-kai” was held as described below:

28

February 1) Theme: Knowledge sharing during training courses in Japan (January 2017) “Education Policy and Planning” 2) Date & Time: Wednesday, February 22, 2017, from 9:30 to 16:00 3) Place: Al Masha Hotel 4) No. of participants: 97 (MOHE&SR: 29, MOE&TE: 38, MOPMAR: 15, others: 15 (E-Just, CAPMAS, INP, NGO, JICA, and private enterprises)), and 10 (student interns from the Department of Japanese Language and Literature, Cairo University) 5) Outputs: Knowledge sharing between 18 participants in the training courses in Japan, their colleagues, and the persons concerned; “Benkyo-kai”-style learning to achieve the above output; promotion of understanding of the elements of the mid- term plan for SDS2030 (policy, programs and businesses, and the investment/financial plan and implementation plan) 6) Main contents: First part: introduction of the “Benkyo-kai” method and opening speeches (read by the Minister of the Ministry of Higher Education and Scientific Research, by Deputy Minister Dr.Essam of the Ministry of Higher Education and Scientific Research, and by the Sector Head of MOPMAR Mohamed); Second part: reporting on each group’s theme by each leader of the eight groups (national educational administration, regional (prefectural, city) educational administration, school management (national and private universities), school management of vocational high schools/general high schools, school management of elementary schools, teacher training, curriculums, and education methods & scientific research); Third part: GAP analysis by the eight groups (Step 1: Discussion about the differences in education between Japan and Egypt, Step 2: Identification of the differences between the two countries, Step 3: Study of the causes of these differences). The contents of the group discussions were presented by the eight groups. In the fourth part, we pointed out as a future issue that only the investment/fiscal plan out of the four elements of the mid-term plan had been submitted to MOPMAR.

Of the 97 participants, 87 participants participated in the group discussion in the second part. Of these, 81 participants responded to the questionnaire. The number of respondents who were participants in the seven Benkyo-kais held in the past was 33 (41% of the respondents). The number of participants who wished that a Benkyo-kai would be held at their ministries and agencies, or at their organization, was 69 (85% of the respondents).

April The MOE&TE held a Benkyo-kai (BK-E5) within the ministry jointly with the Project Team as described below: 1) Date & Time: Thursday, April 20, from 10:30 to 12:30 2) Place: Meeting room on the 1st Floor of the MOE&TE (General Education in the annex) 3) Participants: General Education Planning Team (four members including two members who had participated in the training courses in Japan), Technical Planning Team (five members including two members who had participated in the training courses in Japan), and the Project Team (Dr. Naruo, Dr. Hisada, and 3 local staff members) 4) Theme: How to enhance the “Mid-term Plan” (Case study of the “Education” field) in collaboration with the MOE&TE (Ministry of Education and Technical Education) After Dr. Naruo’s presentation on the analysis framework for the MTP, the process for formulating the MTP, and the method of formulating “plans”, we answered questions.

29

Subsequently, the groups carried out a gap analysis of the methods and purpose, and discussed the proposal to develop and utilize the MTP. We translated the textbook (a handout for the training course in Japan (held in January 2017)) used at the fourth education-related Benkyo-kai (BK-E4) from English into Arabic, and continued to compile it.

May We helped the MOHE&SR hold a “Benkyo-kai (BK-E6)” to formulate an MTP to integrate the MTPs of the MOE&TE and the Ministry of Higher Education. The parties concerned in the MOHE&SR, as well as the persons in charge of the strategic planning unit of the national universities, and the officials in charge of technology of the MOE&TE attended the BK-E6, and they shared the experience of reviewing the results of the analysis of the MTPs of the MOHE&SR and the MOE&TE. The announced Benkyo-kai (BK-E6) within the MOHE&SR was held jointly with the Project Team as described below: 1) Date & time: Tuesday, May 23, from 9:30 to 12:30 2) Place: Conference Hall on the 3rd Floor of the MOHE&SR 3) Participants: MOHE&SR (30 persons including the Minister of the MOHE&SR and 4 participants in the training courses in Japan), universities (32 persons in charge of strategies and planning), science and technology-related institutes (4 persons), Ministry of Technical Education (1 person, who had participated in the training course in Japan), JICA’s Egypt Office (1 person), and the Project Team (Dr. Naruo, Dr. Hisada, and 3 local staff members) 4) Theme: Mid-term Plan (MTP) Execution Process with the MOHE&SR (Ministry of Higher Education and Scientific Research) At the beginning, Dr. Khaled Mostafa Kassam, Senior Assistant to the Minister of Higher Education and Scientific Research explained the theme and purpose of the Benkyo-kai. Dr. Khaled Abdel Ghaffar, Minister of Higher Education and Scientific Research gave a keynote speech. Subsequently, Dr. Naruo gave a keynote speech on “Education is fundamental for the country”. Mr. Khaled Mostafa Kassam, Assistant to the Minister of the MOH&SR (a participant in the training course in Japan) and Dr. Hama, General Manager of Planning Strategy Department of the MOE&TE (a participant in the training course in Japan) gave a presentation to share the knowledge of the framework used for analyzing the MTP, the process for formulating the MTP, and the method of formulating the “plans”. After that, we had a question and answer session on the “policy”, “project program”, “financing”, and the “project implementation/operation” during a group discussion between three panelists and participants, and a discussion was held by having all the participants make a statement in turn. (Note 1: The “Overview notes” indicate an “Internal working paper to study a mid- term plan for pre-university education” (General Education Office, MOE&TE), an “Internal working paper to study a mid-term plan for technical education” (Technical Education Office, MOE&TE), and an “Internal working paper to study a mid-term plan for higher education” (Higher Education Office, MOH&SR).) We translated from the textbook English into Arabic, and also compiled and printed the textbook (a handout for the training course in Japan (held in January 2017)) used at the fourth education-related Benkyo-kai (BK-E4).

July We helped MOPMAR to conduct a training course (BK-TOT) for those practitioners who would spread and put into practice the “Benkyo-kai” method that will strengthen the human affairs and personnel development functions of government bodies. 1) Date & Time: Tuesday, July 18 from 10:00 to 16:00

30

2) Place: Al Masha Hotel 3) No. of participants: 95 in total (MOPMAR: 15, other 28 ministries and agencies: 80), the Project Team (3 experts (Dr. Naruo, Dr. Hisada, and Mr. Maeda) and nine local staff members) 4) Theme: How to roll out human resource development measures for the policy making process

The Project Team held a “Benkyo-kai” seminar (BK seminar) for the participants in the 10 “Benkyo-kais” held during the Project period, in order to strengthen the policy formulations. 1) Date & Time: Wednesday, July 19, from 9:30 to 16:00 2) Place: Al Masha Hotel 3) No. of participants: 150 in total (MOPMAR, MOE&TE, MOHE&SR, and others), the Project Team (3 experts (Dr. Naruo, Dr. Hisada, and Mr. Maeda) and nine local staff members) 4) Theme: How to apply the Benkyo-kai (BK) method in the policy making process

2-2.Training in Japan (PDM: Activity 2-2) (Figure 4, 2-2.)

(1) The first training in Japan on NSDI (National Spatial Data Infrastructure)

(a) Overview of the outputs related to the first training in Japan on NSDI

After returning to Egypt, the participants in the training in Japan attended the workshop to share the knowledge about the training in Japan with persons involved. In addition, after returning to Egypt, some of CAPMAS (Central Agency for Public Mobilization and Statistics) members, who participated in the training in Japan, gave a presentation on training case studies of the training in Japan independently.

(b) Monthly activities related to the first training in Japan on NSDI

2015 We decided to deal with NSDI (National Spatial Data Infrastructure) as the theme of the first training in Japan, created a curriculum, made appointments with partner October organizations for conducting the training, and obtained lists of participants (for 8 out of 13).

November We obtained lists of all the participants (14) in the training in Japan on NSDI (National Spatial Data Infrastructure). We collected information on organization charts of the participants, and coordinated them with training sites in Japan. We agreed that we would conduct hands-on training on E-Views (empirical analysis tool using econometrics techniques, given by JICA in FY 2012) at the meeting with Dr. Nihal. We decided to conduct the training at the IT training room built with support of JICA in Phase 1. The training was scheduled to be conducted 10 times in total (twice per week for 5 weeks). First Assistant Dr. Nihal selected 11 expected participants. First Assistant Dr. Nihal selected 11 expected participants. Dr. Nihal asked the Faculty of Economics and Political Science, Cairo University for an instructor. We scheduled to

31

conduct the training around February because the university had a test period from December until around February.

December We held a pre-dispatch workshop for the training in Japan on NSDI (National Spatial Data Infrastructure) (14 participants) on December 27. We explained a series of processes of the training ((1) conducting a pre-dispatch workshop, (2) providing the training in Japan, (3) holding a knowledge sharing seminar after the training, (4) publishing a report on the training and seminar, (5) posting the publication on the website of the Project), and shared the operations that participants are in charge of and expectations for the training. Subsequently, we reported at the meeting with the minister that the training would be conducted from January 23 until February 5.

2016 Trainees (13) in the training in Japan on NSDI (National Spatial Data Infrastructure) arrived in Japan on January 24, and started the training on January 25. The leader of January the training (Assistant to the Minister of MOPMAR Mostafa) arrived in Japan on January 28, instructed by the minister of MOPMAR, to participate in Lectures 1-10 of the training.

February Trainees (13) in the training in Japan on NSDI (National Spatial Data Infrastructure) received training from January 25 until February 4 (arrived in Japan on January 24, and left Japan on February 5). As an output of the training, they learned knowledge of Japan and developed the basic concept (proposed) of "NSDI in Egypt". We agreed that we would hold a seminar to report on the outputs of the training in Japan on NSDI after they returned to Egypt.

March We held the seminar to report on the outputs of the training in Japan on NSDI after trainees (14 participants in first the training in Japan on NSDI (National Spatial Data Infrastructure)) returned to Egypt. The theme of the seminar was "Workshop/Seminar on 'Empowering Egypt 2030 strategy implementation: NSDI as a national integration catalyst for planning administration'". The seminar was held on March 27 from 10:00 through 16:00 at a meeting room on the 7th floor of INP (Institute of National Planning), an organization of MOPMAR. It was intended to form a consensus to empower Egypt development strategy implementation by 2030 (utilize NSDI as an integration/coordination function to strengthen national planning administration). About 85 participants participated from NSDI-related organizations. At this output report seminar, we bound the presentation slides of the outputs and abstract slides of lecture materials of the training in Japan into books, and distributed them to the participants in the seminar.

April We compiled a report on the discussion recorded at the seminar to report on the outputs of the first training in Japan (14 participants) (conducted on March 27 with 85 attendants). We bound the report to distribute it to the attendees and related organizations.

May We edited the report on the seminar to report on the outputs of the first training in Japan (14 participants) (conducted on March 27 with 85 attendants), and finished trial printing. We intended to bind the report to distribute it to the attendees and related organizations and post it on the website of the Project.

32

June We compiled materials used in the training in Japan on NSDI and at the follow-up seminar in Egypt to translate them into English and main parts into Arabic.

July We compiled materials used in the training in Japan on NSDI and at the follow-up seminar in Egypt, and requested Eng. Mostafa to make a final review of "National Spatial Data Infrastructure as National Integration in Egypt: Series 1 (English version)" and "National Spatial Data Infrastructure as National Integration in Egypt: Series 2 (Arabic version)".

August We encouraged a final review of "National Spatial Data Infrastructure as National Integration in Egypt: Series 1 (English version)" and "National Spatial Data Infrastructure as National Integration in Egypt: Series 2 (Arabic version)” by the Assistant to the Minister of MOPMAR Mostafa.

December We distributed the “National Spatial Data Infrastructure as National Integration in Egypt: Series 1 (English version)” and “National Spatial Data Infrastructure as National Integration in Egypt: Series 2 (Arabic version)” texts to the participants in the training course in Japan on NSDI and to the participants in the follow-up seminar after returning to Egypt.

(2) The second training in Japan on NPA (national planning administration)

(a) Overview of the outputs related to the second training in Japan on NPA

After returning to Egypt, the participants of the second training in Japan on NPA participated in the“Benkyo-kai” to further deepen the outputs of the training in Japan. Upon spontaneous request of the organizations which the participants in the training belong to (Ministry of Health and Population, MOPMAR, and the Ministry of Higher Education), we gave a lecture on "theory of leadership" and "education council" in Egypt as given in the training in Japan.

(b) Monthly activities related to the second training in Japan on NPA

2016 We discussed how to select participants in the second training in Japan "Training on planning administration (scheduled to be conducted from May 22 until June 4)" with March Minister Dr. Ashraf (March 1 and 15), and agreed to collect participant lists from related ministries and agencies by March 31. We intended to compile a participant list by March 24 (as of March 16), but changed it to March 23 due to the reorganization of the Cabinet (announced on March 23). We confirmed the contents of the training on planning administration, and the preliminary conditions of Egypt and Japan at the television conference with JICA (March 17).

April We developed and coordinated a curriculum of the second training in Japan, requested lectures to instructors, and translated textbooks. We confirmed the participants (13) in the

33

second training in Japan with Minister Dr. Ashraf, and made a list of participants. We compiled applications for the training.

May There were 13 expected participants in the second training in Japan "Training on planning administration (scheduled to be conducted from May 20 until June 4)", but four persons declined the participation by the pre-dispatch orientation (May 5). Those who declined occupy important posts such as deputy ministers and first assistant to the ministers. The Project team judged and accepted their reasons as urgent tasks in the ministers, agencies, or government. They hoped to participate in the workshop (seminar) after the training. Of 9 participants in the second training in Japan "Training on planning administration", 3 and 6 participants arrived in Japan on May 21 and 22, respectively (due to their flight reservations), and the training started on May 23. The training was composed of two parts. A participant (Assistant to the Minister of Higher Education) returned to Egypt on May 29 after completing Part 1 (planning administration). Eight participants in Part 2 (local administration planning and cultivation of human resources in planning administration) moved to Oita Prefecture on the second week (May 29) to continue the training. We reported on the details of the training in the monthly report of June. In the second training in Japan, Dr. Nagao, expert (vocational training) (former member of the Central Council for Education) gave a lecture on "ministries' councils" (discussed in advance on May 24) on May 25.

June Dr. Naruo and Assistant to the Minister of MOPMAR Mostafa, a participant, reported on the contents and outputs of the second training in Japan "Training on planning administration (conducted from May 20 until June 4)" to Minister Dr. Ashraf (June 21). We gave a lecture on "human resources policy (cultivation) in the second training in Japan "Training on planning administration, and visited a local government (Kamakura City). After the lecture on "Theory of leadership (in public policy implementation)", we discussed how participants can apply knowledge of Japan they had learned to planning administration in Egypt, and reported to JICA. Participants in the training understood the importance of leadership in public policy implementation, and requested Dr. Akira Nakamura (professor emeritus, Meiji University) to give a lecture on "Theory of leadership" at the follow-up seminar of the training. We compiled and submitted training completion reports (June 30).

July Upon request of the participants in the second training in Japan, Dr. Akira Nakamura, professor emeritus arrived in Egypt and gave a lecture on the training item "Theory of leadership (administrative officials)" for the director, head nurses, and head pharmacists of the hospital of the Ministry of Health and Population (about 180 persons) (July 14). - We held the follow-up workshop/seminar (Benkyo-kai zero “BK-0”)of the second training in Japan (July 16, attended by 17 persons (of which, 6 were participants in the training in Japan)), attended by Dr. Akira Nakamura, professor emeritus, JICA's Egypt Office, and 11 persons from the Project team). Dr. Akira Nakamura, professor emeritus gave a lecture on "Roles of public officials who contributed to Japan's economic development" for (about 50) officials of the Ministry of Planning, Monitoring and Administrative Reform at MOPMAR (July 17).

August We started translating English documents concerning "planning administration” in the second training in Japan into Arabic, and compiled “planning administration” textbooks.

34

2017 We translated the English materials about planning the administration for the second training course in Japan into Arabic and distributed them to the 139 staff members of April MOPMAR.

(3) The third training course in Japan: Formulation of the MTPs (mid-term plan) for the Ministry of Higher Education (MOHE&SR) and the Ministry of Education (MOE&TE)

(a) Overview of the outputs related to the formulation of the MTP for the third training course in Japan

We conducted the joint training course for the related three ministries (MOHE&SR, MOE&TE, and MOPMAR) on “Sharing of knowledge useful for formulating and implementing the mid-term plan for the education field in Egypt”. The outputs of this training have been reflected in the education-related mid- term plan (MTP). At the fourth education-related “Benkyo-kai” that took place after returning to Egypt, the participants shared the knowledge they had gained through the training with the colleagues at their ministries and agencies, as well as at the universities. The Assistant to the Minister of the MOHE&SR, who was a participant in this training course, held a “Benkyo-kai” to share the contents of the working paper for the results of the MTP evaluation analysis.

(b) Monthly activities related to the formulation of the MTP for the third training course in Japan

2016 As to the third training course in Japan and the training in third-party countries, we suggested to Minister Dr. Ashraf that they should set up a working team (for planning a April theme and curriculum, and for selecting the participants) (April 20).

May As to the third training course in Japan and the training in third-party countries, we sent Minister Dr. Ashraf a letter again to remind him of our suggestion about setting up a working team (for planning a theme and curriculum, and for selecting the participants) (May 20). We discussed setting up the working team with the Assistant to the Minister of MOPMAR Mostafa (May 22).

June As to the third training course in Japan (scheduled to be conducted in late September) and the training in third-party countries (scheduled to be conducted in December), we sent Minister Dr. Ashraf a third letter to remind him of our suggestion about setting up a working team (for planning a theme and curriculum, and for selecting the participants) (June 30).

July (In response to our third letter dated June 30) Minister Dr. Ashraf gave instructions to set up a working team for the third training course in Japan (July 12). The Project Team sent a request letter to the six persons indicated by the minister (key members: Deputy Minister Dr. Nihal, First Assistant Yasser, Assistant to the Minister of MOPMAR Mostafa) to set up the working team.

35

August Although we sent a request letter early in July to set up the working team for the third training course in Japan, there has been no movement on this issue.

September We created a curriculum for the third training course in Japan (tentative theme: “Formulation of the mid-term plans for the MOHE&SR and MOE&TE”) and had a meeting with the representatives of the organizations that wish to receive this training (Dr. Naruo, Mr. Maeda, and Dr. Nagao).

October As to the third training course in Japan (Theme: “Training in Japan for the Education Policy and Planning”), we asked the MOE&TE and MOHE&SR for their requests and created a curriculum. Upon receiving the outputs from the BK-E1 held on October 24, we reported to the Minister of MOPMAR that we would conduct the above third training course in Japan, and requested that he select four participants in charge of the compilation of the public investment budget for educational administration from his ministry.

November As to the third training course in Japan (Support theme: “Sharing of knowledge useful for formulating and implementing the mid-term plan for the education field in Egypt”), we created a curriculum based on the requests from the MOE&TE and the MOHE&SR. Upon receiving the outputs from the BK-E1 (October 24) and BK-E2 (November 8), we reported to the Minister of MOPMAR (November 23) that we would conduct the above third training course in Japan (from January 17 to 28, 2017). We reported that four persons from MOPMAR in charge of the compilation of the public investment budget for educational administration, 10 persons from the MOHE&SR including the Deputy Minister of the MOHE&SR, and five persons from the MOE&TE in charge of formulating the mid-term plan for SDS2030 had applied, and were approved by the minister.

December As to the third training course in Japan (Support theme: “Sharing of knowledge useful for formulating and implementing the mid-term plan for the education field in Egypt”), we put together 19 applications in total including 10 applicants from the MOHE&SR, five applicants from the MOE&TE, and four applicants from MOPMAR. We conducted a training seminar for the expected participants in the training course on the method of the project implementation assessment at the third “Benkyo-kai” (December 14). We also held an orientation meeting for the expected participants (December 26). 2017 January We conducted the third training course in Japan as described below: 1) Theme: Sharing of knowledge useful for formulating and implementing the mid- term plan for the education field in Egypt 2) Period: January 17 to January 29, 2017 (Period of the stay in Japan: January 18 to January 27, eight of the associated high officials left Japan on January 29 due to their flight schedules) 3) No. of participants: 18 in total, from the MOHE&SR (nine persons participated, but one declined the offer to participate), the MOE&TE (five), and MOPMAR (four) 4) Main organizations that were visited: Ministry of Education, Culture, Sports, Science and Technology; The Japan Society for the Promotion of Science; Graduate School of Education, Kyoto University; Faculty of Education, Osaka Ohtani University; University Policy Section, Culture and Sports Division, Kyoto Prefecture; Information Technology Education Center; Kyoto City Board of Education; Kyoto City Rakuo Elementary School; The Nissan Automobile

36

Technical College; Kyoto Prefectural Tanabe High School; Heian Jogakuin; Keihanna Culture Academic Association; Public Foundation of Kansai Research Institute; Advanced Telecommunications Research Institute International; Suntory World Research Center; International Institute for Advanced Studies; Osaka Seikei Gakuen; and the Embassy of Egypt in Japan 5) Outputs: We shared knowledge about educational administration, planning, and visited the educational sites in Japan that were useful for formulating the education- related mid-term plan (from 2017 to 2020) of Egypt. We confirmed again that we would hold a “Benkyo-kai” in Egypt on February 22 to reflect the knowledge that was gained through the training course in Japan in the education-related policies and plans. Participants in the training course suggested that a workshop should also be held (on February 8 or 15) to prepare for the above-mentioned “Benkyo-kai”, and it was decided that this workshop would be held in Cairo.

February to The activities conducted after returning from the third training course in Japan have May been mentioned in the above section “1-2 (3) Support for the formulation of the mid- term plan (MTP) (from 2017 to 2020) related to educational administration”.

3. Organizational development (strategic plan-making and policy unit) (PDM: Activity 2-4) (Figure 4, 3.)

(a) Overview of the outputs related to strategic plan-making and policy unit

We conducted training for members of the unit and shared knowledge.

(b) Monthly activities related to strategic plan-making and policy unit

2015 We started discussion on design of strategic plan-making and policy unit with the Counterparty (Assistant to the Minister of MOPMAR Mostafa). October

November As to the design of strategic plan-making and policy unit, we continued to support the Counterparty (Assistant to the Minister of MOPMAR Mostafa).

December As to the design of strategic plan-making and policy unit, we conducted training on public investment management (PIM) for Assistant to the Minister of MOPMAR Mostafa and his project members (14) on December 20.

4. Human resources development (PDM: Activity 2-4) (Figure 4, 4.)

4-1.Support for Result Base Management (RBM) (Figure 4, 4-1.)

(a) Overview of the outputs related to the support for RBM

37

Since the person in charge of RBM was transferred as an Assistant to the minister of the Ministry of Trade and Industry, the activities have been suspended. A member of RBM has been assigned to the Project manager of the Project by Assistant to the Minister of MOPMAR Mostafa, the Counterparty.

(b) Monthly activities related to the support for RBM

2015 We confirmed that Presidential Decree No. 122 extended the scope of Result Base Management (RBM) from organizational reform at MOPMAR to organizational reform at October all (33) ministers and preparation of the mid-term strategies, and discussed cooperation with the Project.

November We are checking how much the mid-term strategies for Result Base Management (RBM) project have been developed.

December We are checking how much the mid-term strategies for Result Base Management (RBM) project have been developed.

4-2.Cooperation with INP (Figure 4, 4-2.)

(a) Overview of the outputs related to cooperation with INP

We held a seminar jointly with short-term dispatched experts. We also held a follow-up seminar of the training in Japan on NSDI at the meeting facility of INP.

We attended the INP’s International Conference “Education for Sustainable Development in Egypt”. At the project session titled “Educational Administration and Planning in Japan”, Dr. Naruo gave a keynote speech on the history of education and educational systems in Japan.

(b) Monthly activities related to cooperation with INP

2015 We discussed cooperation on activities for cultivating human resources with INP (Institute of National Plan). October

December We continued to discuss cooperation with INP.

March We held a "Workshop for FILP and business innovation" jointly with INP (March 17). Dr. Tsuri, expert, Dr. Fujii, expert, and Dr. Naruo gave a presentation on "Japan's Fiscal Investment and Loan Program and housing", "Business Innovation", "Industrial Policy", respectively, and exchanged opinions.

38

2016 October INP requested that Dr. Naruo (October 26) give a keynote speech at the following international conference, and we accepted this request. 1) Theme: Education for Sustainable Development in Egypt 2) Period: May 6 to 8, 2017 3) Place: INP, Cairo

November We also invited the persons concerned in INP to the second “Benkyo-kai” on the education policy/planning (November 8), and three persons participated.

December We also invited the persons concerned in INP to the third “Benkyo-kai” on the education policy/planning (November 8), and one person participated.

2017 We continued to prepare for the project session titled “Educational Administration and Planning in Japan” conducted (May 8) at the INP’s International Conference “Education April for Sustainable Development in Egypt”, in Cairo on 6-8 May 2017.

May We attended the INP’s International Conference “Education for Sustainable Development in Egypt”, in Cairo on 6-8 May 2017. Dr. Naruo gave a keynote speech on “Japan’s experience in modernizing the education system” at the project session titled “Educational Administration and Planning in Japan” (May 8). Subsequently, Mr. Hidekazu Tanaka, Secretary of the Embassy of Japan in Egypt, gave a keynote speech on “Education in Japan - and overview and some key issues” followed by a question and answer session.

5. Other activities

(a) Monthly activities related to preparing reports

2015 We prepared a work plan in Japanese. October

2016 We prepared the Progress Report of the Project (Phase 2). We changed the date for the submission of the report from September 16 to October 7 in order to reflect the contents September of the SDS2030 Kickoff Meeting on August 2, 2016.

October We finished preparing the Progress Report of the Project (Phase 2), and submitted this to JICA on October 14 (meeting records dated October 7).

(b) Monthly activities related to the study of the constitution

Overview of major outputs: although we attempted from January to August to contact the parliament, we have not yet been able to meet the secretary-general of the parliament. We continue to make requests through multiple channels for contact with persons involved in the parliament, but need time because they are focusing on other activities. 39

2015 We continued to edit the study of the constitution of 2014 (Arabic version and English version of Series 2 "Ruling system" and Series 3 "Human rights"). October

November Study of the constitution of 2014: We reprinted 1000 books of the Arabic version and printed 300 books of the English version of Series 1 "Basic analysis of constitution". We put the Arabic version and English version of Series 2 "Ruling system" and Series 3 "Human rights" into test print, and continued to edit them.

December Study of the constitution of 2014: We reprinted 1000 books of the Arabic version and printed 300 books of the English version of Series 2 "Ruling system". We put the Arabic version and English version of Series 3 "Human rights" into test print, and completed the preparation for printing.

2017 We distributed 950 sets of the Study of the 2014 Constitution (Series 1 to 3) to political August parties, local governments’ councils, young peoples’ groups, regional NGOs, and universities studying the constitution via Dr. Talaat (Head of the General Federation of Non-Governmental Organizations), one of the authors of the series.

(c) Monthly activities related to exporting Japanese-style education

2015 With respect to President el-Sisi's visit to Japan, we cooperated in developing the matter of "Exporting Japanese-style education". ⇒We participated in the meeting at the office of the October President. Subsequently, we are continuing to cooperate with the JICA's Egypt Office and the embassy.

November With respect to President el-Sisi's visit to Japan, we continued to cooperate in developing the matter of "Exporting Japanese-style education".

December With respect to President el-Sisi's visit to Japan, we continued to cooperate in developing the matter of "Exporting Japanese-style education" with the JICA's Egypt Office and the Ministry of Technical Education and Vocational Training.

(d) Monthly activities related to handing over equipment

Overview of main outputs: The equipment of the IT training room was continuously used for SDS2030 follow-up activity meetings by Deputy Minister Dr. Nihal’s team and training for MOPMAR’s staff after installation.

2015 We began procedures for handing over the equipment for an IT training room, installed in October Phase 1.

November We followed up on the procedures for handing over the equipment for an IT training room, installed in Phase 1.

December We received the receipt for the equipment for an IT training room, installed in Phase 1.

40

(e) Monthly activities related to other training Overview of major outputs: We planned application (E-View) training for MOPMAR’s staff as the utilization of the IT equipment, jointly with Deputy Minister Dr. Nihal and Assistant to the Minister of MOPMAR Mostafa. Although Deputy Minister Dr. Nihal wanted to directly make arrangements for an external instructor, neither recommendations nor arrangements have yet been made.

2015 We agreed that we would conduct hands-on training on E-Views (empirical analysis tool using econometrics techniques, given by JICA in FY 2012) at the meeting with Dr. Nihal. November We decided to conduct the training at the IT training room built with support of JICA in Phase 1. The training was scheduled to be conducted 10 times in total (twice per week for 5 weeks). First Assistant Dr. Nihal selected 11 expected participants. First Assistant Dr. Nihal asked the Faculty of Economics and Political Science, Cairo University for an instructor. We scheduled to conduct the training around February because the university had a test period from December until around February.

December For the hands-on training on E-Views (empirical analysis tool using econometrics techniques, given by JICA in FY 2012), First Assistant Dr. Nihal had asked the Faculty of Economics and Political Science, Cairo University to arrange an instructor, but we agreed to postpone the period of the training to early in February because the university had a test period until late in January. In addition, we agreed to conduct the training by increasing the number of participants upon request of the Project team of Assistant to the Minister of MOPMAR Mostafa.

(f) Monthly activities related to RBF (Rockefeller Brothers Fund)

2015 The JICA Egypt Office is preparing for discussion on RBF (Rockefeller Brothers Fund)'s Phase 2 JICA/RBF scheme. November

December The JICA Egypt Office discussed RBF (Rockefeller Brothers Fund)'s Phase 2 JICA/RBF scheme.

(g) Monthly activities related to creating the website

2015 We started creating the website of the Project. December

2016 We translated the contents of the website of the Project in preparation from English into Arabic. January

February We edited the contents of the website of the Project in preparation.

41

March We opened the website of the Project (March 24). URL: http://www.egypt-japan-planning.com/en/

(h) Monthly activities related to the Suez Canal development meeting "Future Investments in Suez Canal Zone"

2016 (Dr. Naruo, expert, Dr. Hisada, expert, and other project managers, and local staff) participated in the Suez Canal development meeting "Future Investments in Suez Canal February Zone" (February 21). At the meeting organized by NGO "ECRA (Egyptian Credit & Risk Association)", Dr. Ahmed Darwish (chairman of Suez Canal Economic Zone) gave a speech. Key participants were members of ECRA, and persons from the government, universities and private sector business communities. The speaker explained the current conditions and prospects of the development of the Suez Canal area, and answered questions.

(i) Monthly activities related to public relations and information sharing activities

2016 We created leaflets of the Project outline (Arabic/English, A4 size, folded in three), and distributed them at seminars and places we visited. March

2017 JICA Project team made an introduction video about the BK method (approximately 10 minutes) based on the past four BKs related to education, and the training course in Japan March (held in January 2017), and we uploaded it to our project website. (URL: http://www.egypt-japan- planning.com/wpcontent/uploads/2017/03/BK_E4_video_medium.mp4)

(j) Monthly activities related to information on the reorganization of the Cabinet

2016 We collected information on the reorganization of the Cabinet (announced on March 23). March Minister Dr. Ashraf remains in office, and Dr. Nihal takes office as Deputy Minister of the Ministry of Planning. The reorganization changed ministers of 9 ministries and newly established a ministry called the "Ministry of Public Business Sector” (“responsible for state owned companies”)". Three deputy ministers take office in the Ministry of Finance. 2017 The new cabinet appointed the following new ministers and deputy ministers including February the Minister of MOPMAR.

42

Name of new ministers新大臣名 Name of the省名 minister Sahar Nasr Minister of investment and international cooperation Abdel-Moneim El-Banna Minister of agriculture Omar El-Khattab Arafa Minister of parliamentary affairs Ali El-Sayed Mosselhi Minister of supply and trade (a merger of two separate ministries) Mohamed Hesham Zein El-Abdein El-Sherif Minister of local development Hala Helmy El-Saeed Younis Minister of planning and administrative reform Khaled Atef Abdel-Ghaffar Minister of higher education and scientific research Tarek Galal Shawki Ahmed Shawk Minister of education Hesham Arafat Mahdi Ahmed Minister of transportation

Name of new新副大臣名 ministers Name of the省名 minister Mohamed Abdel-Tawab Deputy ‎minister of agriculture Mona Mehrez Deputy ‎minister of agriculture Safwat Abdel-Hamid Deputy ‎minister of agriculture Salah Abdel-Rahman Deputy minister of ‎planning.

(k) Monthly activities related to moving to the JICA team execution office

2016 1) The repair work of MOPMAR progressed and minister offices moved from the 9th floor April to the 1st floor. They intended to provide Room No. 9 on the 3rd floor as the JICA team execution office of the Project, but we are requesting to provide us a room large enough for all team members (3 experts and 4 local staff members) to work. We temporarily moved only our baggage from the 9th floor to Room No. 9 on the 3rd floor (April 20). 2) Until we are provided a room large enough for all team members to work by MOPMAR, we are continuing activities at the Project office (3-minute walk from MOPMAR) leased by the Project.

(l) Monthly activities related to holding JCC

2016 We confirmed with Assistant to the Minister of MOPMAR Mostafa, the Counterparty of the Project, who was staying in Japan to participate in the second training in Japan that we May would have a preparatory meeting for holding JCC (scheduled to be held on June 23) in Cairo on June 13 and June 20. We held (the 1st) JCC on June 23. The preparatory meeting was postponed from June 13 June to June 20, and subsequently postponed again to June 22 for Egypt side's reason.

Participants: Egypt side: (Minister Dr. Ashraf was absent.) Assistant to the Minister of MOPMAR Mostafa (project director), Ms. Dahlia (project manager), Mr. Heba (secretary to Eng. Mostafa), Japan side: (The secretary of the Japan Embassy was absent.), Mr. Ito, the Chief Representative, Mr. Konno, staff, Mr. Ahmed, staff of JICA, the JICA project team (Naruo, Hisada, Adriana, Maeda, Mohamed; honorifics omitted) Agenda: See the JCC report. Points checked and discussed: Based on R/D of the Project, Dr. Naruo explained the relation between the establishment of PC, development of EP, vision of SDS2030, and future activities in the framework of the Project, and confirmed their relationship. The JICA side asked for PC (SCPC) to be established early, and confirmed that they would continue to make efforts to establish it. Our activity report and future activity plans 43

based on PDM and OP were approved as drafted. (See the attached JCC minutes for details.)

(m) Activities to promote training with the “Benkyo-kai” method

2016 At the “Benkyo-kai” on the education policy/planning, we asked mainly 6 volunteer students (BK-E1) and 8 (BK-E2) from the Department of Japanese Language and November Literature, Faculty of Arts, at Cairo University to be reporters (comment recorders) during the group discussions. We made this attempt with the expectation that they would diffuse the (Japanese-style) “Benkyo-kai” from the policy and planning administration to the general administration, university education, and the industrial circles.

December At the third “Benkyo-kai”, there were eight comment recorders and an auditor.

3. Issues, solutions, and lessons in implementing and operating the Project 3.1 Organizing the preconditions for the Project

(1) Contents of the preconditions:

The roles of the JICA Project Team were to position the long-term plan (National Income Doubling Plan) jointly developed by MOPMAR and JICA in August 2012 as the MP, and to support the development of the EP for its concrete realization. In doing so, we intended to set up the PC and to hold discussions with the partners involved in the development plan (including those in private sectors, professionals, citizens’ groups, and regional representatives).

In summary, the following three items (Figure 9) are the preconditions.

1) To finalize the MP (National Income Doubling Plan)

2) To set up and operate the PC that will promote the development and execution of the EP

3) To develop and implement the EP

44

2012 2013 2014 2015 2016 2016 2017 2018 2019 2020 2021 2022 Master Plan: 10 year strategic framework (National Income Doubling Plan)

Guiding This is the framework of the RD (Record of Discussion) signed th Execution Plan Phase 1 on 15 April 2013. Execution (3 years: 2014-2017) Plans (EP) (Mid-term Prepare, Execution Plan Phase 2 Plan) Implement, (3 years: 2017-2020) Monitor, Recovery & Evaluate. Execution Plan Planning Phase 3 (2020~)

Committee (PC) 4

Figure 5 The project original proposal (Master Plan) (year 2012) to the Execution Plan (EP) and Planning Committee (PC)

(2) Changes to the preconditions in implementing the Project

1) Master Plan:

When the Project was launched in October 2014, the MP still existed. In February 2016, MOPMAR released SDS2030 as its long-term vision. Since then, the National Income Doubling Plan has not been regarded as the MP.

2) Planning Committee:

At the discussion between JICA and MOPMAR in September 2015 (the MM was signed on September 1, 2015), it was suggested that the existing council of the “Supreme Council of Urban Planning and Development” would play the roles and functions of the Planning Committee. Although we have followed this suggestion for over a year since then, the preconditions were not satisfied and the Planning Committee was not set up.

3) Execution Plan:

In August 2016, MOPMAR held a meeting on the execution of SDS2030 and summoned about 300 officials involved in the formulation of the plans from the ministries and agencies. At this meeting,

45

MOPMAR allocated 10 Pillars of SDS2030 to the ministries and agencies, and requested that the ministries and agencies formulate a mid-term plan for each allocated pillar..

(3) Causes of changes to the preconditions

1) Political/economic conditions

All of the above three preconditions for the Project changed because the Project period overlapped with a period of rapid changes in the political and economic conditions (Figure 10), including the revolution in 2011 (Arab Spring); the presidential election and the establishment of a new constitution in 2012; the political changes in 2013 during which President Morsi was pulled down from his position; the establishment of a new constitution and the presidential election in 2014; the parliamentary election in 2015; the request to the IMF for financial support due to the sluggish economic activities resulting from insufficient foreign currency reserves, a change to the floating exchange rate system, and the subsequent slump in the value of the Egyptian currency in 2016.

2) Issues concerning the human resources within MOPMAR

Just after the revolution in January 2011, Minister Abou el-Naga (then) of the Ministry of International Cooperation served concurrently as the Minister of Planning, and started organizational reforms and the development of the human resources in the Ministry of Planning. However, some cabinet members including Minister Abou el-Naga were changed under the new President Morsi’s administration, which left the organizational reforms only half completed.

3) Change in the MOPMAR’s organizational structure

The Ministry of Planning was changed from MOPIC to MOPMAR, and extended the scope of its services to the former MSAD in charge of reforming the administrative organization.

46

2011 2012 2013 2014 2015 2016 2017 Start of technical cooperation Apr Aug Apr Oct 2014 Sep 2017 2011 2013 Beginning 2012 Discontinuation JICA JICA planning support (A year and a half) Phase1 Phase2

Japan R Japan Japan Japan 本 本 本Japan 本 A1 D RBM/ 本 邦 邦 邦 邦 邦 Continued to send experts UNDP ??? June Modify Governed by Dr. Nihal/ USAID

Planning administrationPlanning Changed to 2012 Feb 2016 MP MP SDS2030 preparation SDS SDS2030 Mid-term Plan 2030 MTP No actual MP incl. MOPincl. 5 year Plan/ annual EP Plans encircled by dotted plan for public Stimul Additional public 5 year Gov. investment of EGP 22B lines are either incomplete us pkg strategy Prog Investment were divided into two or in preparation. (public investment phases. Economy Summit budget document) 2YP 2YP Reform Reconstruction program 2-year mid-term The 6th 5-year plan ended Held by the Plan(WEF) ( budget plan IMF) in June 2012. NEC Rockefeller Preparation for WEF July Foundation Preparation for IMF negotiations Cabinet 2 persons Ganzuri Candir 2013 Beblawi Mahlab Ismail Externalfactor Revolution 2nd Revolution Parliamentary First Original schedule Second election Election voided Delayed by 1 year (by the constitutional court) Dec 2015 Establishment of 2012 Constitution 2014 Constitution a constitution 2014 Constitution First Second Presidential President SiSi election Morcy Mansuri Ruled temporarily by the military (Brotherhood government) Temporary president

Figure 6 The history of the project and the environment surrounding it (from year 2011 to year 2016)

(4) Project Team’s response to the changes in the preconditions

The options that could be taken when the preconditions for the Project were not satisfied were classified into the following three:

Idea 1: To discontinue the Project at that point

Idea 2: To continuously approach MOPMAR

Idea 3: To work on the development of the planning administration human resources required in Egypt in view of the Overall Goal.

We should have decided to discontinue the Project when the MM was concluded (September 2015), as the PC had still not been set up a year after the technical cooperation was started, when SDS2030 was released as the MP in place of the National Income Doubling Plan (in February 2016), and when MOPMAR decided not to develop the EP on their own and instead allocated the mid-term plan formulation tasks to the other ministries and agencies (in August 2016).

47

We continuously supported MOPMAR after the MM was concluded in September 2015 based on the promise of the Minister of MOPMAR that he would set up the PC (a stance central to Idea 2). However, we determined that the development of the planning administration for human resources targeted only at MOPMAR would be difficult, as there was no progress in the establishment of the PC as of August 2016.

In the process of changing the preconditions, we took the options of suggesting or taking measures to recover from the changes based on the fundamental principles of the RD.

The followings are the measures that we took, in chronological order:

Phase 1 (September 2014 - August 2015): Time to organize the Egyptian government’s requests

Phase 2 (September 2015 – September 2017): Implementation period

(September 2015 – August 2016): Continuous support for MOPMAR by implementing Idea 2.

(September 2016 – August 2017): Changed the focus of our support to the other ministries and agencies by implementing Idea 3.

(5) Outputs of the measures taken by the Project Team

Considering the above, the aim of the measures taken by the Project Team was to “ultimately develop a more efficient scheme for the Overall Goal without changing the Overall Goal, and to extend our practical support further beyond MOPMAR by utilizing the BK method efficiently, while continuously trying to involve MOPMAR, and without ignoring it”.

It was decided that we could support the development of the planning administration for human resources by making flexible efforts in accordance with the changes in the situations based on the above policy: We held BKs for the other ministries and agencies, and distributed textbooks. On the other hand, there was room for considering the other options, including the discontinuation of the Project, so we needed to consider these options in view of the outputs of the Project.

3.2 Issues, solutions, and lessons for the outputs of the Project (first half of Phase 2: October 2015 – September 2016)

In view of the above, we would like to report in order on the Output 1 (Figure 4, 2-1) and Output 2 (Figure 4, 2-2) in terms of the issues, solutions, and lessons resulting from implementing the Project, based on the Operation Flows of the Project (Figure 4).

48

1. Output 1: Activities for developing the Execution Plan

1-1.Issues for establishing the PC (Figure 4, 1-1.)

Minister Dr. Ashraf of MOPMAR promised in August 2015 to change the name of the current "Supreme Council of Urban Planning and Development" to "Supreme Council of Planning and Development" and to set up PC functions as a MOPMAR-led council; however, a year has passed, and there is no finalization of setting up the PC. It is appropriate to think that MOPMAR currently needs to work on implementing the deliberative planning administration. (See figure 5).

(a) Solution for establishing the PC

In March 2016, we revised the definition document for the PC, and presented it to the minister and Deputy Minister Dr. Nihal. After that, also, we confirmed the status of the establishment of the Supreme Council of Planning and Development in every meeting with the minister.

(b) Lessons for establishing the PC

The planning administration that MOPMAR is promoting has become conducted in a “delegation manner"4 rather than in a“deliberative manner”, and plans that it formulates has become “decentralized” rather than “integrated”, the time of which coincides with the time when Deputy Minister Dr. Nihal has come to the MOPMAR as Economic Assistant in August 2013 (Fig. 5). After that, as Deputy Minister Dr. Nihal has been promoted to undersecretary, first undersecretary, and deputy minister, she has steadily assumed control in the ministry and moved MOPMAR away from its goals to a decentralized plan by delegation manner planning administration.

4 (Delegation Manner) is the way of announcing plans or policies suddenly, without releasing its detailed deliberation or review process, and those plans or policies are decided by some staff from the ministry. At that time, senior officials of the government attend the deliberation council, broadcast it through media such as TV, and make the announced content to an established fact. Sustainable Development Strategy 2030 which was released on 24 February 2016, and Sustainable Development Strategy 2030 implementation plan which was released on 2 August 2016 are examples for that.

49

Original target

Deliberative 2011-2012 Egypt planning JICARD Target of technical Master Plan PC/EP administration ( cooperation/support0 2013/4) (2014/10-2017/9) National planning administration MP-PC-EP through the Planning Committee

2013/7: Egypt's military collapsed Morsi's administration.

support? 2013/8-: Interim administration Possible Possible to Present 2014/1: The new constitution was promulgated. situation of 2014/4: Presidential election (President Sisi) MOP 2015/3: Egypt Economic Development Conf. 2015/12: General election of the parliament 2015-2016 Egypt 2016/1: Parliament was inaugurated. Delegation 2016/2: SDS2030 was unveiled. SDS2030, Government manner 2016/3: The Government Program was submitted to the Program, etc. parliament. planning Planning administration 2016/8: Economic Reform Program (supported by the IMF) administration

Decentralized plans Integrated plans

Figure 7 Positioning of JICA's technical cooperation and changes in MOPMAR planning administration's trends

1-2. Execution Plan (EP) (Figure 4, 1-2.)

(a) Issues for developing the EP5

The EP (Execution Plan) was supposed to be developed by the PC, and was not supposed to be prepared by the JICA Team alone. However, MOPMAR did not set up the PC during the Project period.

(b) Solution for developing the EP

We started preparing Policy Paper (PP), the prototype for the EP, at the Project in November 2015, and shared it with the sector of MOPMAR in charge in December 2015. We provided and explained it to MOPMAR as a reference for development of individual public investment plans based on policies.

(c) Lessons for developing the EP

The EP-formulating scheme that depends on the establishment of the PC assumes MOPMAR’s deliberative planning administration. As more than a year has already passed since the Minster decided

5 As shown in Figure 8 of Chapter 4, JICA’s R/D model is an integrated one, where it supports the formation of the PC and the PC formulates EP, while the SDS2030 model is a decentralized one, where the Ministerial Committee led by the president asks the Technical Secretariat led by the MOPMAR minister to formulate decentralized mid-term plan for each of ten axes in SDS2030 with assigned leaders.

50

to establish the PC, probably we should recognize that no progress has been done. It may be realistic to think that MOPMAR needs more time to implement the deliberative planning administration.

1. Output 2: Restructuring of the organizational framework of MOPMAR and support for enhancing the capacity of MOPMAR’s staff (training in Japan) (Figure 4, 2-2.)

(a) Issues for the training

We conducted training twice in Japan (training on NSDI and training on national planning administration). MOPMAR suggested the theme of the training only, without deep involvement for training needs and content of curriculums.

(b) Solution for the training

We planned to conduct the training in Japan in the following order: The 1st training on NSDI, the 2nd training on E-government, and the 3rd training on national planning administration. We moved up and conducted “Training in national planning administration" as the second training in Japan (from May 22 until June 4, 2016) for ministries and agencies' top officials who are expected members of the PC when it is set up6 , and held a follow-up workshop after they returned to Egypt (July 16).

(c) Lessons for the training

As we opened training opportunities to human resources for not only MOPMAR but also other ministries and agencies, we were able to expand our network to these ministries and agencies, and to contribute to nurturing a wide range of human resources involved in planning administration.

2. How to implement the Project in the future considering the lessons that have been learned

Although two years have already passed since the Minister of MOPMAR made his decision in August 2015, the PC has not yet been established. Also, on August 2, 2016, the Introduction Plan for SDS2030 was suddenly announced. In the Introduction Plan, the person responsible for each pillar (a Director-level Official of a specific ministry or agency) formulated a mid-term plan (2017-2020).

6 This was aimed at nurturing human resources that will help Egypt’s planning administration in the future. As a result, we were able to build a network with other ministries and agencies, achieving significant outputs in terms of human resource development.

51

In the SDS2030 introduction meeting on August 2, MOPMAR allocated the tasks of the mid-term plan formulation to the other ministries and agencies. As MOPMAR’s role has changed in that regard, the JICA Team should determine what is now required in order to achieve the objectives of the RD. So far, we have been focusing our support mainly on MOPMAR, but will need to shift this to the planning sections of the ministries and agencies where the planning work will be carried out.

One hypothesis could be that “even if the PC/EP in Output 1 do(es) not function, it is possible for us to contribute to the improving of Egypt’s planning administration (the Project’s Overall Goal) through activities aimed at the nurturing of the human resources and organizations in Output 2, and in collaboration with the individual ministries and agencies”. We have already attempted to share knowledge on the policy and planning formulation with 15 or more ministries, agencies, and other governmental organizations through the past four “Benkyo-kais”. Therefore, we will be able to make further significant contributions to the Egyptian government by continuing to proactively use this “Benkyo-kai” scheme.

As we opened training opportunities to human resources for not only MOPMAR but also other ministries and agencies, we were able to expand our network to these ministries and agencies, and to contribute to nurturing a wide range of human resources involved in planning administration.

JICA project working schema (From Oct 2016~Sep 2017) RD: Project's overall goal The process of the national development planning and implementation according to national priorities is improved.(計画行政プロセスが改善していくこと)(improvement of planning administration) 計画行政全般に対する Mid term plan Tend政策形成・計画策定に to directly participate in 寄与度が、著しく減退l (2017-2020) creation直接的に関与する傾向 of policies and plans formulation策定業務 MOPMAR計画省((MinistryMOPMAR) of Planning) 各省庁のPlanning unit inPlanning ministries, agencies Unit

Achievement成果1: 1:PC/EP PC/EP関連 matters Reconsider if the 状況が好転す situation 各省庁で計画行政に関わOrganizations and human resources PromotingSDS2030等の推進: SDS2030 and others: れば、再検討improves (most are contract workers or transfers JICAJICAプロジェ リソースHuman involvedる組織、人材 in planning admin Dr.from Nihal INP) Team Project Team resources投入 (大半が契約社員かINPからの出向社員) クトチーム in ministries and agencies (財務省、地域開発省、高等教育省、 Public investment plan (Ministry of: Finance, Local Development, Higher Education電力省、保健・人口省、貿易産業省、, Electricity, Health & Population, Trade formulation department 公共投資計画策定部門 &運輸省、投資省、住宅・都市開発省、 Industry, Transportation, Investment, Housing (all are MOPMAR employees) (全員、計画省職員) & Urban Development,観光省、農業省 Tourism,、、、 Agriculture…) )

Support計画行政支援活動 for planning admin. 計画省側の受け入れ態勢に応じて、Take necessary measures according (Mid(Mid term term plan, plan etc.)等) 必要な措置をとる。to MOPMAR’s readiness to accept BK (study group), Training in Japan, Training in BK(勉強会)、本邦研修、第3国研修、third-party countries Achievement 2: organization成果2:組織・人材育成関連 and human resource development

Figure 8 Support from MOPMAR for the planning unit of each ministry

(Issues, solutions, and lessons in operating work)

The operation system of the Project is as shown on the following figure, assumed in "5.1. JICA project team’s operation execution system" (pp.24-27) of "The Work plan (Phase 2)". 52

Concept of operations system for technical cooperation (structure for technical Divide roles as a Egypt side JICA side cooperation/support) team to cover three functions of R/D. The Minister JICA Egypt office (MOP) MSAD Appoint a. Overall/economic (1) Structure policy of long-term experts MOP’s CP (Counterpart) C-1. Assistance in b. System C-2. Development of HR, operations adjustment Cooperate in operations adjustment operations establishment and system establishment Cooperate c. Training/operations adjustment

The plan (Approx. 700 persons)

Japan’s support system (Support for techniques, operations

Cooperate Support management, safety management) Support

Ministries & agencies, Department Europe and East Middle JICA organizations related to planning (2) Short-term experts by theme (Three to four themes are planned.)

Field support system locally Cooperate Productive (3) Local staff: administrative management (full-time: 1), work assistant (full-time: 3). Utilize experts in local staff is "policy analysis, economic analysis, project analysis, IT technology, political/economic information the key. analysis" on site as necessary.

Figure 9 Concept of operation system for technical cooperation

Issues, solutions, and lessons for the operation system are reported as follows:

(1) Counterpart (CP)

(a) Issues for the Counterpart

The Assistant to the Minister of MOPMAR Mostafa, the Counterpart (CP), was seen to take a positive stance on the collaboration with JICA at the beginning of the Project when he was appointed as the CP. The new Deputy Minister Dr. Saleh has been playing his role as the Project’s CP since March 2017.

(b) Solution for the Counterpart

JICA Project provided three opportunities for training in Japan to the First Assistant of the Minister of MOPMAR , Eng.Mostafa, and also Ms. Dalia, the Project Manager. JICA Project had also responded to the regular meeting proposal and the requests of providing various information.

We do not think it was wrong that we kept a distance from Deputy Minister Dr. Nihal and regarded Mr. Mostafa as our CP, but Eng. Mostafa actually could not function as our CP. We had no option but to

53

continuously operate the Project by utilizing a direct relationship of mutual trust with Minister Dr. Ashraf and his networks.

(2) Project Manager (PM)

(a) Issues for the Project Manager

Ms. Dalia who was nominated as Project Manager (November 2015) began working in October 2015 as a team member of Assistant to the Minister of MOPMAR Mostafa, who is the project's Counterpart. She was a consultant at MOPMAR's organizational reform at the Results-based management project. Because she was an outsider of MOPMAR, she does not have a social network at MOPMAR. Also, as of August 2016, she was involved partly to work in Mr. Mostafa's team, as she started working in another organization7.

(b) Solution for the Project Manager

Since Ms. Dalia was nominated as a project manager of this project, she started attending the project morning meetings and promoted understanding of this project. She also participated in the 2nd National Planning Administrative Training as Project Management to promote understanding of planning administration in Japan.

(c) Lessons for the Project Manager

As the role of Assistant to the Minister of MOPMAR Eng. Mostafa changed, and Ms. Dalia, the Project Manager, started working with other departments, which caused some difficulty of relationship between JICA team and MOPMAR. As the power relations within the ministry and the organizational direction changed, the project management work became more difficult. So, in order to understand the relationship of power within the province, the personnel matters are involved, and it is difficult to grasp it accurately.

(3) MOPMAR project execution office

(a) Issues

The execution office of the Project was on the 9th floor, the same floor as the minister's execution office. The repair work of MOPMAR's building progressed, and we were provided with Room No. 9 on the 3rd floor in April 2016. The new execution office has space for two large desks only and is not large enough for four experts and three Egyptian staff members to work. We are asking MOPMAR to provide with a room large enough for the experts and staff of the Project to work, but we are not sure when we will be given the room.

8When asking Mr. Mostafa directly for this situation, he seemed to avoid giving a clear answer: "Because it is Egypt's government personal matter..." Any further inquiries in this issue would be taken as a political matter within the organization, so it is necessary to take careful measures.

54

(b) Solution

We are using the newly provided Room No. 9 on the 3rd floor as the Project's liaison office (Dr. Naruo's execution office), and full-time staff work regularly on a rotation basis. Other experts work in a room of a private office, which is a five-minute walk away from MOPMAR.

(c) Lessons

The repair work in MOPMAR's building started in around November 2014, and it took around 18 months to repair the 1st to 6th floors of the main building. The repair work on the 7th to 11th floors and the annex was not completed by the time that the Project ended. We could promote the activities without delaying them by having a project office in a private apartment near MOPMAR, as we cannot expect to be provided with an additional office by the end of September 2017 when the Project ends.

3.3 Comprehensive issues, solutions, and lessons learned from implementing the Project (second half of Phase 2: October 2016 to August 2017)

The support activities performed by JICA’s projects before this technical cooperation was started are as follows (Figure 10):

2011 2012 2013 2014 2015 2016 2017

Master Plan Support by specific Technical Cooperation Development subject (Capacity Building, JICA Team in Economic Policy, Planning) (From Oct 2014 to Sep 2017) MOPMAR April 15th Support for Master Plan R/D Main activity SDS2030 Education Pillars “National (Feb 2016) Income Mid-Term Doubling Plan” Policy Plan (2017- EP 2020) (Execution Paper plan) 1.Training Course 1 2 3 4 5 Education in Japan (5 times) Planning Planning System NSDI National Policy & (MOP grand design) Planning Planning system Administration JICA Seminar for Japanese Experience N NSDI workshop 2. Seminar & S Training Course for 1. New Planning Concept T T Policy Study 1~3 for Training Course 2. Industrial Policy MOPMAR new employee MOPMAR Employee In Egypt (10 +) 3. National Land development S National Account seminar Finance system & Energy E E 3. Short Term NA Transport Expert T T Expert Dispatched National Account Industrial Policy Expert I I Improvement team from Japan (4 experts) Education Expert E E 4. BK (Benkyo-Kai) Public Policy 0 E1 BK: Japanese-style Unique FILP & Energy 1 E2 Education Japanese-style & Fruitful workshop Marine Transport 2 E3 Series 1~4 Special Workshop (8 times BK) Industrial Policy 3 E4 1. Text book Constituti NSDI Education 5.Publications for for New -on study National 7 Policy & Planning (30 books) account employee Book1-3 NPA MTP

Figure 10 This is the basic concept of the JICA projects when the R/D was signed, and the background of the changes that took place after August 2, 2016

55

(1) MOPMAR’s situations and problems

During the reorganization of the Cabinet in February 2017, Dr. Hala Al-Saeed, the Dean of the Faculty of Economics and Political Science at Cairo University, and Dr. Saleh Abdel Rahman, an Associate Professor in the faculty, were appointed as the new Minister and Deputy Minister, respectively.

As soon as Dr. Hala was inaugurated as the new Minister, we held a meeting on March 7, 2017, where we asked her to assign Deputy Minister Dr. Saleh to be responsible for the preparations for holding the BK- P1 (first “Benkyo-kai” on the planning administration) proposed by the JICA Team. “Be sure to spare at least an hour a day to discuss this issue with the JICA Team” was our requirement at that time. Nonetheless, we did not have opportunities for regular meetings with the CP of MOPMAR, which delayed our operations.

Our Project’s CP organization is MOPMAR, but its function of promoting the planning administration has been limited. Ministries including the MOF (Ministry of Finance), CB (Central Bank of Egypt), and the MOTI (Ministry of Trade and Industry) have the function of planning the country’s economic policies, while MOPMAR only has a team that develops the NA (National Accounts).

MOPMAR formulates a public investment budget plan. However, the ministry only examines the budgetary items (in the projects and programs), and does not discuss the policies.

(2) Status and issues in the Project-related field

The Project Team decided in August 2016 to shift our focus of planning to provide support to the ministries and agencies in charge of formulating the mid-term plan.

SDS2030 consists of 10 pillars. JICA has supported the Ministry of Education and Technical Education and the Ministry of Higher Education and Scientific Research by focusing mainly on Pillar 3 (Technology) and 7 (Education).

From August 2016, the Project Team helped hold “Benkyo-kais” (Benkyo-kai in education; hereinafter “BK-E”) for the education budget compilation teams of the MOE&TE, MOHE&SR, and the MOPMAR to strengthen the capacity of the teams involved in formulating educational administration plans. We held four “Benkyo-kais” (BK-E1 to BK-E4) for about 100 persons, and conducted the joint training courses in Japan for the above three ministries in January 2017. In addition, as follow-up Benkyo-kais, we helped the MOE&TE and MOHE&SR hold the BK-E, and BK-E5 and BK-E6 respectively, even after April 2017.

56

Technical cooperation started in Oct 2014 Current situation as of Mar 2017 (Original scope of the work) shifted MOPMAR National Income Doubling Plan MP (Strategic Framework ~2022) SDS2030

Aug 2nd 2016 Not yet Shift Ministerial Supreme Council PC: Planning ??? Committee of Planning & JICA PC Committee Development Technical Team Secretariat

Execution Shift P-1 P-2 P-3 P-7 P-10 EP Plan (EP) MTP MTP MTP MTP MTP Execute JICA Team Sep 2016 MOHE&SR MOE&TE Support

Education BK-E1,E2,E3,E4 & Training MTP 6 Courses in Japan

Figure 11 Structural changes of the "roles of MOPMAR" before and after August 2, 2016

An integrated national planning administration was the initial goal. However, as the planning administration in Egypt started becoming decentralized, we endeavored to help the two education-related ministries develop the human resources in the planning administration and to accumulate knowledge in Egypt.

(3) Efforts related to the efficiency, effectiveness, impact, appropriateness, and sustainability of the Project

1) Efficiency

We have been turning our resources to the Overall Goal of the “Improvement of the planning administration in Egypt” in the pursuit of a desirable planning administration in Egypt.

This policy change has enabled us to provide our expertise in planning administrations to many of the officials within the Egyptian government that are involved in the planning administration directly or indirectly, thus preventing the Project’s efforts from being futile.

Through the Project, we have published 43 books on policies, planning, techniques, and knowledge, thereby leaving valuable assets for the future use of the parties involved and the government agencies.

57

2) Effectiveness

We aimed at achieving the Overall Goal and focused on the “Improvement of the planning administration in Egypt” without abandoning the Project.

3) Impact

We think the Project has had a limited impact on MOPMAR. Even though the CP assigned by MOPMAR lost its priority status, we persistently cultivated and persuaded a practical CP in order to promote the Project, and we maintained the relationship with MOPMAR until the Project ended, developed human resources, and provided expertise in planning administrations.

Beyond the organization of MOPMAR, we also planned and conducted the training courses in Japan for the NPA (National Planning Administration), and we helped seven ministries and agencies in addition to MOPMAR, including the Ministry of Finance, the Ministry of Local Development, the MOHE&SR, the Ministry of Electricity, the Ministry of Health and Population, and the National Center for Planning State Land Uses to improve their methods for a planning administration.

Furthermore, we provided expertise in policies, planning, and techniques to the ministries and agencies other than MOPMAR, as well as to government agencies, universities, research institutes, private enterprises, economic organizations, and citizens’ groups through various seminars and Benkyo-kais, and helped them to improve their methods of policymaking.

Technical support MOPMAR 1. Capacity building Main support 2. Organization reforms Planning 1. Planning Committee 3. MOPMAR grand design 2. Execution Plan process 4. Policy analysis JICA Team 5. Planning process

National NPA Scientific Policy NSDI (National Planning Education Accounts Administration) Research Analysis CAPMAS CAPMAS MOF Ministry of Higher Ministry of Ministry of Education & SR Education & TE Transport Ministry of Council for Research Ministry of Higher Ministry of Industry INP Ministry of Electricity Communication & Center & Institutes Education & SR & Trade Ministry of Local Information National Center National MOF Technology Development STRA-City Investment Bank Ministry of Higher for Education Egyptian Survey Education Ministry of Tourism Central Bank Universities EJUST Authority Ministry of Health GOPP & Population Around 20 ministries and National Center for GAFI Planning State land 8 public agencies. Use IDSC Figure 12. Project support scheme (bird's-eye view)

58

4) Appropriateness

After the revolution in 2011, JICA immediately supported the planning administration, and provided our know-how on the planning administrations in Japan during the period of postwar rehabilitation and rapid economic growth. As a result, Egypt’s Ministry of Planning (MOPIC at that time) followed Japan’s National Income Doubling Plan to develop the National Income Doubling Plan in August 2012, the first integrated plan after the revolution, which was approved by the Cabinet.

Subsequently, President Morsi was elected in the presidential election. The new cabinet was established and a new constitution was established, but President Morsi was removed from his position due to the political changes that occurred in July 2013. Following this, many things happened in rapid succession, including the establishment of temporary administration, another presidential election, the establishment of another new constitution, dissolution of the parliament, and a general election.

The RD on technical cooperation was signed in these days of rapid changes, but the Project was postponed for over a year and a half, and only started in October 2014.

Because of the significant changes that have taken place in the external environment, the framework for the Project set in the original R/D cannot be said to be necessarily appropriate for the Egyptian government’s current needs or policies. Therefore, we need to deliberately consider and evaluate its appropriateness.

On the other hand, it will still take time until the confusion following the revolution calms down and the national policy gets on the right track. At present, it is difficult to evaluate the appropriateness of the Project based on the current unstable political situation. Nonetheless, our expertise in planning administrations has been transferred to MOPMAR, the other ministries and agencies, government agencies, universities, and private groups through the Project, so it may be appraised from a long-term perspective that we have partially responded to the target group’s potential needs.

5) Sustainability

In the future, the planning administration in Egypt may become decentralized. If so, each ministry and agency will need to have the ability to formulate and implement plans. Through this Project, we have actively helped the other ministries and agencies, universities, research institutes, and private groups to improve their methods of planning administration while also supporting MOPMAR’s planning administration.

In particular, from August 2016, we intensively helped the planning sections of the MOE&TE and the MOHE&SR in the formulation of the 2017-2020 mid-term plan. We developed the BK (Benkyo-Kai) method, and held BKs on public policies, transport policies, industrial policies, FILP/energy policies, and education policies/planning, while also spreading and promoting the BK method.

59

Just sharing the knowledge of formulating policies or plans is likely to have a transient effect. We cannot ignore this possibility, especially when the country’s politics remains unstable after the revolution.

Nonetheless, what is important for the autonomous development of Egypt is not only to share our knowledge and expertise in a specific field, but also to find a way for them to gain such knowledge and expertise on their own. We are certain that acquiring this ability will lead to their autonomous development.

Based on this belief, during the Project we transferred our knowledge and expertise to the Egyptian officials using the method called BK. We also compiled and translated such knowledge and expertise into Arabic in order to disseminate and spread it to more people, and we published a total 43 books. In addition, we posted these on the Project’s website so that this information can be easily accessed or downloaded.

Transferring our knowledge and expertise into printed publications was a very tough task, but we employed specialist staff and made strong efforts so that the publications would be useful for the establishment of the planning administration in Egypt and could be used as intellectual property in their future.

(4) Lessons and proposals when cooperating in similar projects or similar fields in the future

There has not been any agency in charge of the planning administration in Japan since the Economic Planning Agency was dissolved in 2001. Therefore, it can be said that the planning administration in Japan completed its role 70 years after the Second World War. However, a properly working planning administration is one of indispensable administration functions in many developing countries. For this reason, the need for providing support to planning administrations like this Project will increasingly grow as one of JICA’s cooperation themes in the future.

However, the personnel involved in planning administrations that study fields such as the economy, coordinate policies, and formulate plans are scattered and have grown older in Japan since the Economic Planning Agency was dissolved. Consequently, it is difficult to find anyone among JICA consultants who can instruct people in the area of planning administration. For this reason, it will be difficult for JICA to send personnel who can meet to the expectations in this area, even if the destination countries show their need for instruction on planning administrations.

In addition, we need to be greatly determined when supporting the planning administration in a time of political instability, such as after the revolution that took place during this Project. When the counterpart’s government changes its way of accepting us, the environment for implementing the Project and the degree of difficulty will change drastically. We must therefore be determined to adapt to the changes and secure the necessary systems (a consulting company and the JICA Team) persistently.

60

A future issue in the planning administration field is to improve the abilities of local governments in the methods of planning administration. Accordingly, nurturing the human resources in the local governments is an urgent issue.

Speaking of planning administration, the central government’s planning administration has almost disappeared in Japan, but the functions of the planning administration have instead been developing in the country’s local governments (prefectures, municipalities). The history of the local governments in Japan is not as long as that in the US and Europe, but they have been making efforts to develop since the 1980s. Therefore, the Local Autonomy College and the local governments in Japan have accumulated expertise in the system design of this field and in curriculums for human resource development, and many personnel who are capable of supporting the local governments in developing countries could be likely to be produced. It is expected that Japan will be able to give support meeting to address the future needs in the administrative reform field.

61

4. Proposals to achieve the Overall Goal 4.1 Overall Goal

“The improvement of the process of the planning and implementation of the national development according to the national priorities.”

4.2 Proposals to achieve the Overall Goal

(1) The government should take the initiative in promoting the BK method (MOPMAR, the Cabinet Office, or the office of the president).

Regarding the items that countries accepting our assistance will need to address in the future to improve the autonomous development of similar projects, they should consider, analyze, and rack their brains by utilizing the BK method. The 43 publications prepared by the Project Team are treasure houses of knowledge for policies, planning, and techniques, and can be considered as valuable Egyptian intellectual property. It is important to try to utilize, learn humbly, and deepen the understanding of these books through the BK method.

The BK method is a method that has proven to be effective in policy discussions in Egypt, and can be an effective tool in formulating policies with professionals and stakeholders inside and outside the government. In addition, it is expected to be an effective method for planning or discussing strategies in universities or in private sectors other than the government.

We have already held more than 10 BKs, and those BKs have been penetrated mainly into the education-related ministries and agencies. It is worth considering efforts to develop this movement into a social movement.

The establishment of a planning administration requires the process of setting up and sharing the objectives of a number of plans. BKs are likely to take hold in Egypt as an effective method in the country’s policy formations.

(2) The BKs and the 43 books containing know-how should be held within the government with the participation of private sectors.

The seminars, trainings, visits, and BKs conducted through this technical cooperation have produced a variety of expert knowledge in the fields of planning administration and policy formations. We have successfully published 43 books related to this expertise.

These books are written in English or Arabic, and each book can be viewed as a valuable asset and as worthy knowledge for Egypt’s future.

62

The books have already been provided to the related organizations including MOPMAR and INP. We think it is also necessary to provide them to Egyptian government agencies, local governments, universities, and research institutes in order to spread this expertise further.

(3) The Minister should establish the PC under his direct control to develop the planning administration policies.

Unfortunately, MOPMAR could not establish the PC during the Project period. Nonetheless, a cross- ministry and agency policy council like the PC will be indispensable for Egypt in the future. Even the postwar planning administration in Japan, the Economic Planning Agency, supported the Economic Council, but the Economic Council also consulted the prime minister and submitted plans.

Egypt is flooded with more than 30 ministries and agencies, and the roles and responsibilities of those ministries and agencies are not necessarily clear. We think it is necessary to establish an organization like the PC, in which the prime minister can take the initiative to discuss cross-ministry and agency policy issues and to make proposals under the situation existing with such a government. Therefore, finding a way to suggest the establishment of the PC to the Cabinet Office or the Executive Office of the President rather than MOPMAR will be a future issue.

(4) The government should develop the new Planning Law through the PC.

They started considering the new Planning Law more than three years ago.

Collecting opinions broadly and deliberating sufficiently are necessary actions, because the new Planning Law will be the first revision since 1973. Considerations conducted through an organization like the PC will be required.

(5) The government should draft a basic design for the administrative organizations including MOPMAR.

The Egyptian government is currently packed with 33 ministries and agencies. To make prompt decisions or to make comprehensive judgments, the reorganization, elimination, and consolidation of these ministries and agencies is an indispensable development. The MSAD (Ministry of State Administrative Development), an organization under MOPMAR, is responsible for such administrative reforms.

63

We have already provided the Deputy Minister with the materials8 on Japan’s experience of an administrative reform, so the Egyptian government can hold Benkyo-kais using Japan’s materials if they make the effort to establish a consideration team. Providing the knowledge of Japan to promote an administrative reform will be an indispensable factor for building a planning administration system for Egypt in the future.

(6) The government should create an “Egypt’s Policy Map”, check the positions of the existing policies, and steer the policies as urgent issues.

The ministries and agencies are currently making various efforts under the instructions of President el- Sisi. Egypt’s political system is a presidential government, so the ministers need not undergo the baptism of an election. For this reason, they tend to work according to the instructions of the Prime Minister and the President, as their superiors.

The ministers respond to the instructions of their superiors quickly and tend to conduct political activities directly, rather than cooperating with other ministries and agencies. In an organization where decisions are made under such a vertically divided system, the development of a cross-ministry and agency policy- related matrix will be an effective solution. In other words, creating an “Egypt’s Policy Map” that can provide an overview of the influential connections between policies is required.

Such a comprehensive policy design tool is required so that the planning administration system can function.

8 The author and the title of the reference book on Japan’s administrative reform: Masajima, Toshiyuki (2006) Administrative Reform in Japan, The Institute of Administrative Management, Tokyo

64

5. Attachments 5.1. PDM (latest edition, background of changes) 5.2. Operation Flow Chart 5.3. Records of the Dispatched Experts (Personnel Plan) (September 2017) 5.4. Records of the Accepted Trainees 5.4.1 Final Report on the First Training Course in Japan for “NSDI” 5.4.2 Final Report on the Second Training Course in Japan for “Planning Administration” 5.4.3 Final Report on the Third Training Course in Japan for “Education/Planning Administration” 5.5. Records of the Training Courses and Seminars 5.6. Records of the Purchased Equipment (Equipment Management List) 5.7. JCC Minutes 5.7.1 JCC Minutes of the Meeting 5.7.2 JCC Minutes of the PDM and PO Meeting 5.8. Records of Other Activities 5.8.1 PROJECT Publication List 5.8.2 JICA Project report to the Minister (In the past “June 2011~Feb 2017” and in the future “until Sep 2017”) 5.8.3 Three layers of Planning (Institution, Policy and Operation system)

65 Attachment:5-1

1/12 Attachment:5-1

2/12 Attachment:5-1

3/12 Attachment:5-1

4/12 Attachment:5-1

5/12 Attachment:5-1

6/12 Attachment:5-1

7/12 Attachment:5-1

8/12 Attachment:5-1

9/12 Attachment:5-1

10/12 Attachment:5-1

11/12 Attachment:5-1

12/12 Project's work flow Project Title: "Sharing knowledge on Development and Implementation of Execution Plans"(Phase 2) FY 2015/16 FY 2016/17 FY 2017 Activities Output Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep 1-1 Planning Committee (PC) (PDM: Activity 1-1 to 1-2) Plan 1-1-1 Functional design (PDM: Activity 1-1) Active

Operation (EP preparation, coordination Plan 1-1-2 within the government, M&E) (PDM: Activity 1-2) Active

Monitoring and Evaluation of Plan 1-1-3 Planning Committee Active

1-2 Execution Plan (EP) (PDM: Activity 1-3 to 1-4) Exaction Plan Preparation Plan 1-2-1 (MOPMAR) Active SDS2030 SDS2030 SDS2030 SDS2030 SDS2030 SDS2030 Mid-term Plan Mid-term Plan Mid-term Plan Plan 1-2-2 Exaction Plan making Attachment:5-2 Active Benkyo-kai Benkyo-kai Benkyo-kai Benkyo-kai Mid-term Plan Mid-term Plan Mid-term Plan Benkyo-kai Feedback Exaction Plan approval by the Plan Strategy Egypt's Vision 2030 (SDS 2030). 1-2-3 cabinet Active 1/1 Implementation (Policy integration, Plan 1-2-4 Feedback, M&E) (PDM: Activity 1-4) Active Mid-term Plan Feedback Exaction Plan Monitoring and Plan 1-2-5 evaluation Active Output 1: Development of national execution plans in compliance with Sustainable Development 2-1 Knowledge sharing (PDM: Activity 2-1~2-3) Plan Short-term experts on policy セミナ等 セミナ等 セミナ等 セミナ等 セミナ等 セミナ等 セミナ等 セミナ等 2-1-1 formulation (PDM: Activity 2-2) Active Benkyo-kai Benkyo-kai Benkyo-kai Benkyo-kai Benkyo-kai Benkyo-kai Benkyo-kai Report translation Report translation Report translation BK preparation Benkyo-kai Feedback Plan 派遣前ワークショップ、本邦研修、知見共有セミナー、報告書出版、ホームページに報告書公開 派遣前ワークショップ、本邦研修、知見共有セミナー、報告書出版、ホームページに報告書公開 派遣前ワークショップ、本邦研修、知見共有セミナー、報告書出版、ホームページに報告書公開 2-1-2 Training in Japan (PDM: Activity 2-2) Active ワークショップ実施 本邦研修 セミナー 本邦研修 フォローアップ準備 フォローワークショップ 本邦研修準備 本邦研修準備 本邦研修準備 本邦研修 Text translation Text translation Print & distribution Print & distribution Benkyo-kai Feedback Plan 派遣前ワークショップ、第3国研修、知見共有セミナー、報告書出版、ホームページに報告書公開 2-1-3 Training in third-party countries (PDM: Activity 2-3) Active

2-2 Organizational development (Strategic Planning and Policy Unit) (PDM: Activity 2-4) Plan 2-2-1 Functional design Active

Operation as newly integrated Plan 2-2-2 organization Active

2-3 Human resources development (PDM: Activity 2-4) Plan 2-3-1 Support for RBM Active MoP Reform MoP Reform

MoPMAR staff is strengthened to develop and implement execution plans. Plan 2-3-2 Support for INP Active

Output 2: The organizational framework of MoPMAR is streamlined, and the capacity of Benkyo-kai Benkyo-kai Benkyo-kai Benkyo-kai Benkyo-kai Benkyo-kai Benkyo-kai Prepare conference Prepare conference Benkyo-kai Feedback *1: Output 1: Development of national execution plans in compliance with Sustainable Development Strategy Egypt's Vision 2030 (SDS 2030).(PDM) *2: Output 2: The organizational framework of MoPMAR is streamlined, and the capacity of MoPMAR staff is strengthened to develop and implement execution plans. (PDM) Performance table of experts Project's Name Sharing Knowledge on Development and Implementation of Execution Plans Project (Phase 2) FY 2015/16 FY 2016/17 Duties in charge Name October November December January February March April May June July August September

Economic Policy / 2/1 (111days) 5/21 1 Shinji NARUO 10/20 (24days) 11/30 (30days) 12/291/27 (4days) 1/30 2/7 (32days) 3/9 3/24 (31days) 4/23 6/6 (98days) 9/11 Chief Advisor

2 Shinichiro HISADA 10/22 (77days) 1/6 2/6 (41days) 3/17 4/9 (43days) 5/21 6/11 (93days) 9/119/25 (97days) TrainingInstitution & Administrative Building management Adriana 3 10/20 (61days) (11/18-19 private off) 12/21 1/23 (70days) 4/1 5/3 (79days) (6/1-2 private off) 7/22 8/21 (67days) (9/14-15 private off) 10 (Institution Building support) ZELMER Training & Administrative 1 4 Hiroshi MAEDA 3/13 (30days) 4/11 6/17 (32days) 7/18 8/22 (21days) 9/11 management (2)

Training & Administrative Attachment:5-3 E 5 Naoyoshi SASAKI management (3) g y 6 MasaoTSURI 3/10 (14days) 3/23 8/27 (11 days) 9/6 Energy Policy Expert p 3/10 (14days) 3/23 1/2 t 7 Shinji NARUO Industrial Policy Expert 2/26 (15days) 3/11 8 Daiji FUJII 3/10 (14days) 3/23 8/27 (12 days) 9/7 Industrial Policy Expert (2)

9 Takayuki TSUMORI 7/16 (7days) 7/22 8/27 (12 days) 9/7 Industrial Policy Expert 10 Hiromi NAGAO 2/12 (11days) 2/22 6/30 (7days) 7/6 Vocational Policy Expert 0.8MM 0.8MM

Economic Policy / 4/28 (23days) 6/3 1 Shinji NARUO 11/13 (10days)11/28 1/25 (2days) 1/26 ; 2/1(5days) 2/5 4/28 (23days) 6/3 9/15 (10days) 9/30 Chief Advisor 2 2 Shinichiro HISADA 1/24 (10days) 2/5 5/22 (10days) 6/3 Institution Building Training & Administrative management Adriana J 3 (Institution Building support) ZELMER a Training & Administrative p 4 Hiroshi MAEDA 10/20 (10days)11/3 1/24 (10days) 2/5 5/9 (20days) 6/3 9/15 (10days) 9/30 management (2) a n 5 Takayuki TSUMORI 8/8 (2days) 8/9 Industrial Policy Expert 6 Hiromi NAGAO 5/24 (2days) 5/25 7/20 (2days) 7/21 9/29 (2days) 9/30 Vocational Policy Expert Project's Name Sharing Knowledge on Development and Implementation of Execution Plans Project (Phase 2) FY 2016/17 FY 2017 Total Total Duties in charge Name October November 12 1 2 3 4 5 6 7 8 9 (days) (months) Records Records Economic Policy / 2/1 (38days) 3/10 8/18 (16days) 9/2 1 Shinji NARUO 10/16 (65days) (11/15-22 private off) 12/27 2/1 (38days) 3/10 4/11 (20days) 4/30 5/7 (19days) 5/25 7/3 (31days) 8/2 8/18 (16days) 9/2 408 13.60 Chief Advisor

2 Shinichiro HISADA9/25 (97days) 12/30 1/30 (89days) 4/28 5/7 (21days) 5/27 7/1 (64days) 9/2 525 17.50 TrainingInstitution & Administrative Building management Adriana 3 15 private off) 10/28 12/3 (31days) (12/28-29 private off) 1/41/25 (37days) 3/2 , 3/3 (18days) 3/20 345 11.50 (Institution Building support) ZELMER Training & Administrative 7/8 (15days) 7/22 1 4 Hiroshi MAEDA 10/14 (30days) 11/12 2/11 (37days) 3/19 7/8 (15days) 7/22 165 5.50 management (2)

Training & Administrative Attachment:5-3 E 5 Naoyoshi SASAKI 0 0.00 management (3) g y 6 MasaoTSURI 25 0.83 Energy Policy Expert p

2/2 t 7 Shinji NARUO 14 0.47 Industrial Policy Expert 8 Daiji FUJII 26 0.87 Industrial Policy Expert (2)

9 Takayuki TSUMORI 19 0.63 Industrial Policy Expert 10 Hiromi NAGAO 18 0.60 Vocational Policy Expert Egypt 1545 51.50 0.8MTotal

Economic Policy / 6/5 (18days) 6/28 1 Shinji NARUO9/30 1/10 (18days) 1/31 6/5 (14days) 6/28 82 4.10 Chief Advisor 2 2 Shinichiro HISADA 1/18 (10days) 1/27 6/7 (10days) 6/20 40 2.00 Institution Building Training & Administrative management Adriana J 3 0 0.00 (Institution Building support) ZELMER a Training & Administrative p 4 Hiroshi MAEDA9/30 1/18 (10days) 1/27 60 3.00 management (2) a n 5 Takayuki TSUMORI 2 0.10 Industrial Policy Expert 6 Hiromi NAGAO(2days) 9/30 1/19 (6days) 1/26 6 0.30 Vocational Policy Expert Japan 190 9.50 Total Attachment:5-4-1

Tentative Schedule for NSDI Training in Japan

Course Name : Training on NSDI for Development Planning Period : 23/JAN/2016 - 5/FEB/2016

Lecturer Langu Date Time Contents Transportation Place Stay Name Organization / Company age 23/Jan (Sat) 13:45 ~ 19:15 Cairo - Abu Dhabi

(*1)Tokyo 24/Jan (Sun) 22:10 ~ 13:15 Abu Dhabi - Narita (Tokyo) Green Palace

Ms. Shinozaki Coordinator 10:00 ~ 11:30 JICA's Briefing E JICA's bus TIC Ms. Naganawa Coordinator

11:30 12:30 Introduction, Course Guidance Mr. Maeda JICA Project E TIC

12:30 ~ 13:30 Lunch TIC

Ms. Nishiyama Tokyo Workshop(1):How to utilize collected (Dr. Naruo, VSOC / JAICAF 25/Jan (Mon) 13:30 ~ 14:30 E TIC Green information Dr. Hisada, (JICA experts) Palace Mr. Maeda)

15:00 ~ 16:50 JAPAN's NSDI, Its History and Overview Mr. Yamada Kokusai Kogyo Co. Ltd. E TIC

Dr. Naruo JICA Project Dr. Hisada JICA Project 17:00 ~ 19:00 Welcome Party E TIC Mr. Sasaki VSOC, LTD. etc. Japan Aerospace 10:00 ~ 11:00 Outline of GNSS Mr. Hisano Exploration Agency J JICA's bus TBIC (JAXA) Tokyo 26/Jan (Tue) Green 12:00 ~ 13:30 Lunch TBIC Palace 15:00 ~ 16:30 Visit JAXA Tsukuba Space Center J JICA's bus JAXA

Geospatial Information 9:30 ~ 9:45 Guidance Mr. Shirai J JICA's bus GSI Authority of Japan (GSI)

Basic Act on the Advancement of 9:50 ~ 10:50 Utilizing Geospatial Information and Mr. Kushida GSI J GSI Promotion Measures Tokyo Introduction to the Fundamental 27/Jan (Wed) 11:00 ~ 12:00 Mr. Watanabe GSI J GSI Green Geospatial Data Palace 12:00 ~ 13:00 Lunch Geospatial Information Access via Web 13:10 ~ 14:10 Mr. Kojima GSI J GSI Technologies

14:30 ~ 15:30 Visit Science Museum of Map and Survey J GSI

National Institute of Geospatial Big Data and G Space Information and 10:00 ~ 12:00 Mr. Nagaya J JICA's bus NICT Platform Communication Technology (NICT) Tokyo 28/Jan (Thu) 12:30 ~ 13:30 Lunch TIC Green Ms. Nishiyama Palace Workshop: (Dr. Naruo, VSOC / JAICAF 13:30 ~ 16:30 Comparing current situation of NSDI E TIC Dr. Hisada, (JICA experts) between Egypt and Japan Mr. Maeda)

10:00 ~ 12:00 Introduction of Activity of PASCO Mr. Ishizuka PASCO E JICA's bus TIC Tokyo 29/Jan (Fri) 12:00 ~ 14:00 Lunch・(*2)Praying TIC Green Palace Urayasu City 15:30 ~ 17:00 Activity of Urayasu City on GIS Mr. Kuwashima Urayasu City Office J Office

~ Holiday Tokyo 30/Jan (Sat) Green ~ Palace

~ Holiday Tokyo 31/Jan (Sun) Green ~ Palace

Introduction of Japanese NSDI Tokyo Green 10:00 ~ 12:00 Mr. Yamada Kokusai Kogyo Co. Ltd. E development Palace

Embassy of Tokyo Courtesy visit to Embassy of Egypt in 1/Feb (Mon) 12:00 ~ 13:00 Egypt in Green Japan Japan Palace

IBM Japan 13:00 ~ 14:30 Introduction of Activity of IBM Japan Mr. Oohashi IBM Japan J JICA's bus Tokyo Office

1/2 1/3 Attachment:5-4-1

Lecturer Langu Date Time Contents Transportation Place Stay Name Organization / Company age

Ministry of Land, Information from Ministry of Land, JICA HQs 10:00 ~ 12:00 Mr. Kasama Infrastructure, Transport J Walk Infrastructure, Transport and Tourism Room 110 and Tourism (MLIT) Tokyo 2/Feb (Tue) 12:00 ~ 14:00 Lunch TBD Green Palace JICA Ministry of Internal 14:00 ~ 16:00 G-space x ICT projects in Japan J Ichigaya Affairs and Communication Office / MIC

Ms. Nishiyama Workshop (3): Development of Action VSOC / JAICAF 9:30 ~ 12:00 (Dr. Naruo, E JICA's bus TIC Plan on Egyptian NSDI (JICA experts) Dr. Hisada) Tokyo 3/Feb (Wed) 12:00 ~ 13:00 Lunch TIC Green Palace Ms. Nishiyama Workshop(4): Preparation of Training VSOC / JAICAF 13:00 ~ 17:00 (Dr. Naruo, E TIC Report (JICA experts) Dr. Hisada)

Dr. Naruo, Dr. Hisada, Mr. VSOC / JAICAF 10:30 ~ 11:15 Preparation of Final Presentation E JICA's bus TIC (*4) Maeda, (JICA experts) Ms. Nishiyama Mr. Mori JICA Middle East and 11:30 ~ 12:30 Presentation of Training Report Mr. Ono Europe Dept., Middle East E TIC Ms. Shibata Div. 1 4/Feb (Thu) Mr. Mori JICA Middle East and 12:30 ~ 12:45 Certification Ceremony Mr. Ono Europe Dept., Middle East TIC Ms. Shibata Div. 1 13:00 ~ 13:45 Farewell Lunch TIC 17:00 ~ Leave for Narita airport 21:20 ~ Departure from Narita airport

~ 5:10 Abu Dhabi 5/Feb (Fri) 9:55 ~ 12:15 Abu Dhabi - Cairo

Note: (*1) Rooms for training participants are basically non-smoking rooms. (*2) There is a masjid(mosque) named Tokyo Camii near TIC. URL: http://www.tokyocamii.org/about/welcome (*3) Lunch or dinner at TIC or TBIC, halal food is available. (*4) You are requested to check out of the hotel and bring all your belongings to TIC since you will leave for Narita airport from TIC.

Recommendation: You would be better to have your business card to exchange your official information.

Abbreviationn: JICA Japan International Cooperation Agency JICA HQs JICA Head Quarters TIC JICA Tokyo International Center TBIC JICA Tsukuba International Center MIC Ministry of Internal Affairs and Communication NICT National Institute of Communication Technology GSI Geospatial Information Authority of Japan VSOC Vision and Spirits for Overseas Cooperation JAICAF Japan Association for International Collaboration of Agriculture and Forestry

2/2 2/3 Attachment:5-4-1

Training on NSDI for development planning, training participant list as of 2016/1/12

No. Ministry/Organization Name Title Department Position

Ministry of Planning, Monitoring Assistant to H.E Minister Mostafa Mahmoud Elsayed P1 and Administrative Reform Eng. IT Department of Planning, Monitoring and Ghaly (MOPMAR) Administrative Reform

Ministry of Planning, Monitoring Ahmed Emad Mohamed Strategic Planning and P2 and Administrative Reform Mr. GIS Specialist Esmail Policy Division (MOPMAR)

Ministry of Planning, Monitoring Megahed Hassan Mohamed Strategic Planning and P3 and Administrative Reform Mr. GIS Specialist Hassan Policy Division (MOPMAR)

Ministry of Planning, Monitoring Ahmed Helmy Nabil Helmy Strategic Planning and P4 and Administrative Reform Eng. Urban Planning Specialist Mohamed Mansour Policy Division (MOPMAR)

Ministry of Planning, Monitoring P5 and Administrative Reform Mohamed Tarek Said Ibrahim Mr. Information Center Software Developer (MOPMAR) Technical Support and Central Agency for Public Abdelhalim Ibrahim Mohamed Development / Geographical P6 Mobilization and Statistics Mr. GIS Developer Abdelaziz Information System (CAPMAS) Department Central Agency for Public Ahmed Kamal Abdelaziz Advisor of CAPMAS P7 Mobilization and Statistics Mr. CAPMAS President Office Ibrahim Elsaid President (CAPMAS) Information Technology Central Agency for Public Amal Mohamed Ahmed Center / Geographical P8 Mobilization and Statistics Eng. Senior GIS Engineer Elsharnoby Information System (CAPMAS) Department Central Agency for Public Mennatallah Anwar Ahmed Geographical Information P9 Mobilization and Statistics Eng. Senior GIS Developer Mohamed Hashim System Department (CAPMAS) Information Technology Central Agency for Public Cector / Gneral Nahla Seddik Mohammed P10 Mobilization and Statistics Eng. Administration of GIS Unit Director Saleh (CAPMAS) Geographical Information System Information and Ministry of Communications & Tamer Mahmoud Abdalla P11 Dr. Communications Technology ICT Integration Specialist Information Technology (MCIT) Abounema Department

Information and Ministry of Communications & Wael Mohamed Ahmed P12 Dr. Communications Technology ICT Integration Specialist Information Technology (MCIT) Hendawy Department

National Mapping Head of National Mapping P13 Egyptian Survey Authority (ESA) Khaled Sayed Amin Ramadan Eng. Department Department

Alaaeldin Saleh Mohamed Cadaster Department for Head of Central P14 Egyptian Survey Authority (ESA) Dr. Salem Registration by Title Administration of Cadester

3/3 Attachment:5-4-2 as of 21/May/2016 Tentative Schedule for NPA Training in Japan

Course Name : Training on National Planning Administration Period : 21/May/2016 - 3/Jun/2016

1. To increase capacity of policy development and planning through sharing knowledge of Japanese policy making, legislation process, planning process, budget making process and project evaluation. 2. To understand planning administration through sharing knowledge of planning administration Purpose executed by Japanese local government. 3. To visit industrial zone and study a scheme of "public - private partnership", PPP, as an efficient measure for social economic development

Date Time Contents Stay

Departure from Cairo: 20/May (Fri) Group ③ time:14:10 flight:EY654 Group ④ time:18:40 flight:EK924 Departure from Cairo: Group ① & ② time:14:10 flight:EY654 Excel Hotel Tokyu, 21/May (Sat) Arrival at Narita Airport: Akasaka, Tokyo (Excel Group ③ time:13:15 flight:EY878 Hotel) Group ④ time:17:35 flight:EK318 Tel: +81-3-3580-2311 Arrival at Narita Airport: 22/May (Sun) Group ① & ② time:13:15 flight:EY878 Excel Hotel (Tokyo)

Meeting with Mr. Shinichi YAMANAKA (Director General, Europe 9:30 and Middle East Department, JICA HQs) 10:00 Briefing 23/May (Mon) Excel Hotel (Tokyo) 11:45 Introduction, Course Guidance 12:30 Welcome lunch 14:00 Workshop:Information sharing Public policy in Japan (Lecturer: Dr. Akira Nakamura, Meiji 10:00 Univ.) Courtesy visit to Embassy of Egypt in Japan 24/May (Tue) 12:30 Excel Hotel (Tokyo) (Lunch) Policy formation process (Lecturer: Dr. Akira Nakamura, Meiji 15:00 Univ.) Budget making process (Lecturer: Dr. Hideaki Tanaka, Graduate 10:00 School, Meiji Univ. )

25/May (Wed) 12:00 Lunch break Excel Hotel (Tokyo) Councils in Japan ("Shingi-kai") (Lecturer: Dr. Hiromi Nagao, 14:00 Head of Wilmina Archives & Research Center, Osaka Jogakuin Univ.) Legislative process (Dr. Hideo Fukui, National Graduate 10:00 Institute for Policy Studies) 26/May (Thu) 12:00 Lunch break Excel Hotel (Tokyo) Planning administration in local government (Dr. Akio Kamiko, 14:30 Ritsumeikan Univ.) Policy evaluation (Mr. Shojiro Yoshikai, Director, Ministry of 10:00 Internal Affairs and Communications) 12:00 Lunch break 27/May (Fri) Excel Hotel (Tokyo) Comprehensive national development plan (Dr. Shinji Naruo, 14:00 Project Leader of JICA MOP Project) 15:15 Workshop: What you learned in this week Holiday 28/May (Sat) Group ① (Dr. Khaled Moustafa Kassem Ramadan) leaves from Excel Hotel (Tokyo) Japan. time:21:20 flight:EY871

1 / 2 1/3 Attachment:5-4-2

Date Time Contents Stay

REMBRANDT HOTEL OITA (Oita 29/May (Sun) Move from the Hotel to Haneda Airport (Fly to Oita prefecture) 13:00 Pref.) (SR93/ANA3793, code share) Tel: +81-97-545-1040 9:30 Courtesy call for Deputy Governor, Oita Prefecture 10:00 Regional development I 11:00 Regional development II REMBRANDT HOTEL OITA (Oita 30/May (Mon) 12:00 Lunch break Pref.) Site visit in Oita prefecture I (Oita Production Base, Nippon 14:00 Steel & Sumitomo Metal Corporation)

Site visit in Oita prefecture II (Mr. Yoshinori Shirasaka, 10:00 representative, JR Kyushu Farm Ltd. Oita Farm) 13:00 Lunch break (short break) 31/May (Tue) (tentative) local development by local entity (Prof. Koichi 13:30 Miyoshi, Representative of Institute for Community Design) Site visit in Oita prefecture III (Station of the village 16:30 Musashi) 18:20 Return to Tokyo by air (ANA800) Excel Hotel (Tokyo) Human resource training in policy making (Dr. Takahiro Suzuki, 9:00 Graduate school, Josai Kokusai Univ.) 1/Jun (Wed) 11:00 Lunch break Excel Hotel (Tokyo) 12:00 Move to Kamakura City by road 14:00 Visit Kamakura City Office 10:00 Workshop: What you learned in this training 2/Jun (Thu) 12:00 Lunch break Excel Hotel (Tokyo) 14:00 Workshop: Lap up dialogue 10:30 Final report to JICA, Closing 11:40 Farewel lunch 3/Jun (Fri) Departure from Narita Airport: Group ② & ③ time:21:20 flight:EY871 Group ④ time:22:00 flight:EK319 Arrival at Cairo Airport: 4/Jun (Sat) Group ② & ③ time:12:30 flight:EY653 Group ④ time:10:05 flight:EK927

Group ①: ・(P9) Dr. Khaled Moustafa (One week attendee, business class, departure from Cairo on May 21 (Sat), Kassem Ramadan then arrival at Cairo on May 29 (Sun), via Abu Dhabi)

・(P3) Mr. Mostafa Shereen Farouk Mohamed Qotbi (Economy) ・(P4) Ms. Dalia Wagih Naguib Group ②: Abadir (Economy) (Two weeks attendee, business or economy class, departure on May 21 ・(P5) Dr. Khaled Mohamed (Sat), then arrival on June 4 (Sat), via Abu Dhabi) Ibrahim Mohamed Nofal Flights (Buisiness) schedule ・(P7) Mr. Ahmed Mohamed grouping: AbdelMenim Ahmed (Buisiness)

・(P2) Eng. Mostafa Mahmoud Group ③ Two weeks attendee, business class, departure on May 20 (Fri), ElSayed Ghaly then arrival on June 4 (Sat), via Abu Dhabi ・(P10) Dr. Mohamed Moussa Ali Omran

・(P11) Dr. Hashem Kamel Group ④: Mahmoud Ali (Two weeks attendee, business class, departure on May 20 (Fri), then ・(P13) Eng. Ahmed Hesham arrival on June 4 (Sat), via Dubai) SalahElDin Ahmed Fadel

2 / 2 2/3 Attachment:5-4-2

Participants List of National Planning Administration Training in Japan as of 2016/5/18 Code Ministry/ No. Name Title Department Position Remarks Organization

Ministry of Planning, Monitoring & Mostafa Mahmoud ElSayed Assistant to the 1 P2 Eng. IT Department Administrative Reform Ghaly Minister (MOPMAR) Ministry of Planning, Monitoring & Mostafa Shereen Farouk Senior Economic 2 P3 Mr. Minister's office Administrative Reform Mohamed Qotbi Researcher (MOPMAR) Ministry of Planning, Project Manager for Monitoring & Strategic Planning 3 P4 Dalia Wagih Naguib Abadir Ms. JICA MOPMAR Administrative Reform and Policy Division Project (MOPMAR)

Technical and Khaled Mohamed Ibrahim 4 P5 Ministry of Finance Dr. Administrative Deputy Minister Mohamed Nofal Reform

Ministry of Local Ahmed Mohamed Secretary General of 5 P7 Mr. Development AbdelMenim Ahmed the Ministry

Senior Assistant Ministry of Higher Khaled Moustafa Kassem Minister for Higher leave on 28th 6 P9 Education and Scientific Dr. Strategic Plan Ramadan Education and May. Research Scientific Research First Undersecretary Research, Planning of State for Ministry of Electricity and Mohamed Moussa Ali Dr. / 7 P10 and Authorities' Research, Planning Renewable Energy Omran Eng. Follow Up and Authorities' Follow Up

Deputy Manager of Ministry of Health and Hashem Kamel Mahmoud 8 P11 Dr. Leadership Specialized Medical Population Ali Centers

National Center for National Center for Planning State Land Uses Ahmed Hesham SalahElDin Director (Head) of 9 P13 Eng. Planning State Land (The Cabinet of Ahmed Fadel NCPSLU Uses Ministers)

3/3 Schedule of "Education Policy and Planning" Course for the Arab Republic of Egypt Duration: January 18, 2017 to January 27, 2017

(Legend): TIC: Tokyo International Center, JICA Tokyo SR: Seminar Room MEXT: Ministry of Education, Culture, Sports, Science and Technology (Lec): Lecture, (Obs): Observation, (Disc): Discussion (The Schedule is subject to change. As of January 17, 2017) Date Time Place/Venue Program/Activity Lecturer/Person in Charge/Organizer Accomodation

AKASAKA EXCEL HOTEL TOKYU Jan. 18 Wed Arrival in Japan Tel: 03-3580-2311 in Akasaka, Chiyoda city, Tokyo

⇒Get on JICA bus⇒JICA Tokyo/Tokyo International Center (TIC) Jan. 19 Thu 9:00 a.m. Gather in Hotel Lobby * Breakfast is Included.

10:00 - 11:30 TIC SR 201 (Lobby Floor) JICA Registration and Briefing Staff in charge, JICA Breakfast is served at "Akasaka Square Dining on the 3rd Floor. 11:30 - 12:30 ditto Program Orientation Dr. HISADA 6:00 ~ 10:00 a.m./ Buffet style

Lunch on your own at the Cafeteria of TIC

13:50 Leave TIC by JICA bus ⇒ Ministry of Education, Culture, Sports, Science and Technology (MEXT) Attachment:5-4-3

Mr. KOMATAU, Deputy Mnister of Education, 14:30 - 14:55 MEXT Greeting Culture, Sports, Science and Technology * Wi-Fi and Internet access with cable Mr. SASAI, Director for International Affairs, (Education Policy and Science and Technology Policy) is available for free. 1/6 15:00 - 15:45 ditto (Lec) Bureau of Science, Technology and Innovation, Science, Technology and Innovation Policy In Japan Cabinet Office * A plug adapter can be borrowed at Elementary and Secondary Education in Japan Mr. KITANO, Deputy Director, Elementary and the Bell Desk, and a smartphone 15:50 - 16:35 ditto (Lec) (Development in Post-war Times) Secondary Education Bureau, MEXT charger at the Front Desk. Mr. TANAKA, Senior Specialist, Lifelong Learning 16:40 - 17:25 ditto (Lec) The Basic Plan for the Promotion of Education Bureau, MEXT approx.18:00 by JICA bus ⇒ Back to Hotel

Jan. 20 Fri 9:20 Gather in the Hotel Lobby ⇒Get on JICA bus⇒Kousaikaikan Hall/Venue of the lectures * Please Take the Textbooks of Yesterday. * A "Seven-Eleven", convenience store, is located on the 1st floor. Meeting Room Human Resource Development for Japanese Education Dr. SUZUKI, Advisor of MEXT, Professor of the Open 24 hours, No Holiday. 10:00 - 11:00 (Lec) of Kousaikaikan (4th floor) Policy and Science & Technology University of Tokyo and Keio University Food and daily necessity is available.

Dr. NAGAO, Director of Education Research Workshop for Japanese Education Policy and Science and 11:00 - 12:00 ditto Center, OSAKA JOGAKUIN UNIVERSITY Technology (Former Member of Central Coucil for Eduation)

Walk to Lunch place⇒ Lunch ⇒ 12:00 - 13:30 Yotsuya area Walk to Japan Society for the Promotion of Science (JSPS)

Promotion of Education, Research, Science and Dr. ANZAI, President of Japan Society for the 13:30 - 15:30 JSPS (Lec) Technology in Japan Promotion of Science (JSPS)

Branch of SMBC Bank Withdraw JICA's Allowance Ms. Marumo & Ms. Nozaki

approx.16:00 by JICA bus Back to Hotel

1 Date Time Place/Venue Program/Activity Lecturer/Person in Charge/Organizer Accomodation

Jan. 21 Sat Check Out Hotel at 9:50 a.m. HOTEL NEW HANKYU KYOTO Tel: 075-343-5300 in Kyoto city, Kyoto prefecture 10:00 Leave Hotel by JICA bus ⇒ Go to Tokyo station Ms. Marumo & Ms. Nozaki

*Kyoto was the old capital of Japan for more than 11:30 Leave Tokyo station by Shinkansen/Bullet Train "NOZOMI #29" * Breakfast is included. 1000 years till Tokyo became the capital in 1868. * Kyoto is the most famous and popular tourist * Buy lunch at a convenience store inside the station destination in Japan, located about 500km west of Eat lunch in the train Tokyo. * Breakfast is served at Restaurant * Temperature in Kyoto this time is expected to be "BOULEVARD" on the 1st Floor. Arrive at Kyoto station ⇒ Walk to the Hotel, located in front of JR Kyoto station (KarasumaChuo ℃ ℃ 7:00 ~ 10:00 a.m./ Buffet style 13:50 High: 7 ~ 10 , Low: - 1 ~ 2 Exit) Population: 1.47million in Kyoto city, approx.14:00 Check In Hotel Hotel New Hankyu Kyoto * Wi-Fi and Internet access with cable 2.54million in Kyoto prefecture. is available for free. Jan. 22 Sun * You are advised to go for breakfast as early as 7:00am. The venue is expected to be very crowded with many guests in this season. * A smartphone charger is equipped . A plug adapter can be in every room Attachment:5-4-3 Leave Hotel ⇒Walk to Pick Up Place of Sightseeing Tour Ms. Marumo & Ms. Nozaki 7:50 also borrowed at the Front Desk.

8:25 Get on Kyoto Morning Tour (Visit Kinkakuji Temple, Nijo Castle and Kitano Tenmangu Shrine) *A Humidifier can be borrowed at the Front Desk.

2/6 12:40 - 13:00 End of the Tour Ms. Marumo & Ms. Nozaki

Dr. NARUO, Dr. HISADA, Mr. MAEDA, Ms. 15:00 - 16:00 Workshop for Kyoto program (The venue ot be Informed in the hotel) NISHIYAMA Jan. 23 Mon 8:30 Gather in the Hotel Lobby ⇒Get on a chartered bus⇒Kyoto University (Yoshida Campus) detto Kyoto Univrsity Dr. TAKAMI, 9:30 - 12:00 (National University) Dean, Faculty of Education, Kyouto University (Lec) Japanese Educational Administration Dr. MATSUMOTO, President of RIKEN (Institute of Physical and Chemical Research )

Lunch at the University Cafeteria in the Campus

13:15 Move to Osaka by bus ⇒Get on a bus and move to the venue in the afternoon in Osaka

Osaka Ohtani University Dr. KAINUMA, Faculty of Education, 15:30 - 17:30 (Lec) Teacher Training Shigakudai Campus, Osaka Ohtani University

approx. 19:00 Osaka ⇒Kyoto by bus Back to Hotel

2 Date Time Place/Venue Program/Activity Lecturer/Person in Charge/Organizer Accomodation

Group A Mr. TAREK MOHAMED ABDELAZIZ MOHAMED, Dr. NOUR HENRY NOUR DOUS, Dr. HAMA ABDELRAHMAN SHEHATA MANSOUR, Mr. SAMIR RAGAB with Dr. HISADA, Mr. BASYOUNY HEGAZY, Dr. HANAN MOHAMED RABIE MAHMOUD ABDELKHALEK, Mr. MOHAMED FARID ABDELFATTAH ELMORSHEDY, Mrs. HEBA HOTEL NEW HANKYU KYOTO MAEDA, Ms. N0ZAKI MOHAMED ABDELMONIEM MANSOUR, Dr. YOUSSEF ABOUELFADL MOHAMED MOSTAFA, Ms. HEND GALAL AHMED MOHAMED GELGEL Tel: 075-343-5300 Jan. 24 Tue in Kyoto city, Kyoto prefecture 8:40 Gather in Hotel Lobby Get on a bus ⇒ Kyoto Prefectural Government Office

No. 1 Bldg., Kyoto Implementation System for Administration of Education Mr. OHOE, Div. of University Policy, Department of 9:30 - 10:30 (Lec) * Breakfast is included. Prefectural Government Policy Culture & Sports, Kyoto Prefectural Government

No. 3 Bldg., Kyoto Prefectural Implementation System for Administration of Education Mr. SHIMOMURA, General Planning Division, 11:00 - 12:30 (Lec) Board of Education Policy Kyoto Prefectural Board of Education Lunch at the Cafeteria of the Kyoto Pref. Gov. Office

13:40 Leave Pref. Gov. by bus ⇒ Kyoto Prefectural Information Technology Education Center

Kyoto Pref. Info. Tech. Implementation System for Administration of Education Mr. FURUICHI, Director, Kyoto Prefectural 14:30 - 16:30 (Lec) Education Center Policy Information Technology Education Center

17:00 Back to the Hotel by bus Attachment:5-4-3 Jan. 25 Wed 9:20 Leave Hotel by Bus ⇒ Kyoto City Board of Education 4th Floor, Implementation System for Administration of Education Mr. YASUMURA, Div. of School Supervision, Kyoto 10:00 - 12:00 (Lec) Kyoto City Hall Policy (Kyoto City Borad of Education ) City Board of Education

3/6 City Hall ⇒ Kyoto Univ. Lunch at the Cafeteria of Kyoto University 〃 13:05 Leave Kyoto Univ. by bus ⇒ Kyoto City Rakuo Elementary School

13:30 - 15:30 Rakuo Elementary School (Obs) Kyoto City Rakuo Elementary School (Public School)

16:00 Back to Hotel by bus

Jan. 26 Thu Check Out Hotel at 8:30 * Take all of your belongins with you. AKASAKA EXCEL HOTEL TOKYU Tel: 03-3580-2311 * Please 8:40 Lv. Hotel by bus ⇒Nissan Automobile Technical College in Kyoto in Akasaka, Chiyoda city, Tokyo prepare your lunch before Kumiyama Town, Nissan Automobile Technical College in Kyoto Mr. IMANISHI, President of Nissan Automobile leaving the 9:30 - 12:00 (Obs) * Breakfast is included. Kyoto Prefecture (Vocational Training) Technical College hotel. 12:00 - 13:00 NISSAN Lunch at NISSAN

13:15 Leave Nissan by bus ⇒ Kyoto Prefectural Tanabe High School

Tanabe High School Kyoto Prefectural Tanabe High School 14:00 - 16:00 (Obs) Mr. TSUBATA, Principal, Tanabe High School in Kyotanabe City, Kyoto (Public High School for Vocational Education)

16:10 Leave School by bus ⇒Kyoto Station

18:05 Leave Kyoto Station by Shinkansen/Bullet train "NOZOMI #248"

20:23 Arrive at Tokyo station / Get on JICA bus

21:10 Check in AKASAKA EXCEL HOTEL TOKYU 3 Date Time Place/Venue Program/Activity Lecturer/Person in Charge/Organizer Accomodation Group B Prof. ESSAM KHAMIS KHAMIS IBRAHIM ELHANASH, Prof. KHALED MOUSTAFA KASSEM RAMADAN, Prof. YASSER REFAAT ABDELFATTAH MOHAMED, with Dr. NARUO, Dr. NAGAO, Prof. ABDALLA ELSAYED ELSAYED AHMED ASKER, Prof. ABDELHADY BASHIR ABDELHADY KASHYOUT, Prof. SAID ABDELAZIZ ALI OSSMAN, HOTEL NEW HANKYU KYOTO Ms. NISHIYAMA, Ms. Prof. NABIL HASSAN MOSTAFA HASSAN, Dr. NOURAN ABDELHAMID IBRAHIM ABDELGAWWAD, Dr. REEM ALI MOHAMED MOHAMED DERBALA Tel: 075-343-5300 MARUMO in Kyoto city, Kyoto prefecture Jan. 24 Tue 9:10 Gather in the Hotel Lobby Get on a bus ⇒ Kyoto University Kyoto Univrsity Dr. YAMAOKA, President of Heian Jogakuin 10:00 - 12:00 (Lec) School Management (University reform) * Breakfast is included. (National University) University Lunch in the Cafeteria of the University Kyoto Univrsity Dr. TAKAMI, Dean, Faculty of Education, Kyoto 13:30 - 16:00 (Lec) School Management (National Universities) (National University) University

approx. 16:40 Back to Hotel by bus

Jan. 25 Wed 9:20 Gather in the Hotel Lobby Get on a bus ⇒ Kansai Science City (Keihanna Science City) Keihanna Plaza Mr. TAKAHASHI, Deputy President, 〃 10:30 - 12:00 Meeting Room "Volga" 5th (Lec) Outline of Kansai Science City (Keihanna Science City) Keihanna Culture & Science Association floor Mr. Hiroshi SETO, Managing Director, Public Foundation of Kansai Research Institute 12:00 - 13:30 Restaurant "Le Seine" Lunch at the restaurant in Keihanna Plaza Attachment:5-4-3

Keihanna City ATR/ Advanced Telecommunication Research Institute Mr. TAKAHASHI, Deputy President, 14:00 - 15:00 (Obs) (Seika Nishikizu Area) International Keihanna Culture & Science Association 4/6 15:30 - 16:30 ditto (Obs) Suntory World Research Center ditto

17:00 - 18:00 ditto International Institute for Advanced Studies Tourig Seika Nishikizu Area of Keihanna City by bus including 18:00 - 18:30 ditto ditto International Institute for Advance Studies

approx. 19:30 ditto Back to Hotel by bus

Jan. 26 Thu Check Out Hotel at 8:30 * Take all of your belongins with you. AKASAKA EXCEL HOTEL TOKYU * Please Tel: 03-3580-2311 8:40 Lv. Hotel by bus ⇒Nissan Automobile Technical College in Kyoto prepare your in Akasaka, Chiyoda city, Tokyo lunch before Kumiyama Twon, Nissan Automobile Technical College in Kyoto Mr. IMANISHI, President of Nissan Automobile leaving the 9:30 - 12:00 (Obs) * Breakfast is Included. Kyoto Prefecture (Vocational Training) Technical College hotel. 12:10 Leave Nissan by bus Eat Lunch in the bus ⇒ Osaka Seikei University

(Lec & Mr. ISHII President of Dept., Osaka Seikei Gakuen 14:00 - 16:00 Osaka Seikei University School Management (Private Universities) Obs) (Incorporated School) 16:10 Leave School by bus ⇒ShinOsaka Station

17:50 Leave ShinOsaka Station by Shinkansen/Bullet train "NOZOM I#248"

20:23 Arrive at Tokyo station / Get on JICA bus

21:10 Check in AKASAKA EXCEL HOTEL TOKYU

4 Date Time Place/Venue Program/Activity Lecturer/Person in Charge/Organizer Accomodation

10 Participants are requested to check out the Jan. 27 Fri hotel this morning (* See the Members of Friday * Take all of your belongins with you to TIC. AKASAKA EXCEL HOTEL TOKYU Night Departure Group below) Tel: 03-3580-2311 in Akasaka, Chiyoda city, Tokyo 8:00 Gather in the Hotel Lobby Get on JICA Buses⇒ JICA Tokyo/TIC * Breakfast is Included. 9:00 - 11:15 TIC SR 201 (Lobby Floor) Fill In JICA Questionnaire

ditto (Disc) Wrap Up Discussion of the Program Ms. NISHIYAMA

Final Presentation Mr. OGAWA, Middle East and Europe Department, 11:15 - 12:00 ditto Closing Ceremony (JICA Certificate to be Awarded) JICA

12:00 - 12:45 TIC SR ( TIC Dining Room) Farewell Lunch

10 Participants Free Time 12:45 ~16:00 (Friday Night * A Mosque is located 15 min. walk from TIC. Departure Attachment:5-4-3

8 Participants who remain in Tokyo one more night will vist the 8 Participants TIC⇒ Egyptian Embassy 15:00 Embassy of Egypt by JICA Bus (Saturday (*See the Members of Saturday Departure Group Below)

5/6 Departure Group) 15:00~ Egyption Embassy Courtesy Call Mr. FUSE, JICA

Friday Night Departure 17:00 Leave TIC for the Airport Picked Up by Travel Agent in TIC Lobby Group

Jan. 27 Sat 9:30 Hotel check out Departure from Japan (8 Participants) 8 Participants Leave HOTEL for the Airport Picked Up by Travel Agent at Lobby of HOTEL (Saturday 10:00 Departure Check in at the NARITA Group) airport

* When the shceduled time is changed, you will be informed by your coordinators.

* Staff to Accomany the Program in Japan: JICA Project Staff: Dr. Shinji NARUO, Dr. Hiromi NAGAO, Dr. Shinichiro HISADA, Mr. Hitoshi MAEDA, Mr. Naoyoshi SASAKI, Ms. Akiyo NISHIYAMA JICA Training Coordinators: Ms. Yuko MARUMO, Ms. Miyuki NOZAKI

Friday Night Departure Group (10 Participants): Dr. NOURAN ABDELHAMID IBRAHIM ABDELGAWWAD, Dr. REEM ALI MOHAMED MOHAMED DERBALA, Mr. TAREK MOHAMED ABDELAZIZ MOHAMED, Dr. NOUR HENRY NOUR DOUS, Dr. HAMA ABDELRAHMAN SHEHATA MANSOUR, Mr. SAMIR RAGAB BASYOUNY HEGAZY, Dr. HANAN MOHAMED RABIE MAHMOUD ABDELKHALEK, Mrs. HEBA MOHAMED ABDELMONIEM MANSOUR, Dr. YOUSSEF ABOUELFADL MOHAMED MOSTAFA, Ms. HEND GALAL AHMED MOHAMED GELGEL

Saturday Departure Group (8 Participants): Prof. ESSAM KHAMIS KHAMIS IBRAHIM ELHANASH, Prof.KHALED MOUSTAFA KASSEM RAMADAN, Prof. YASSER REFAAT ABDELFATTAH MOHAMED, Prof. ABDALLA ELSAYED ELSAYED AHMED ASKER, Prof. ABDELHADY BASHIR ABDELHADY KASHYOUT, Prof. SAID ABDELAZIZ ALI OSSMAN, Prof. NABIL HASSAN MOSTAFA HASSAN, Mr. MOHAMED FARID ABDELFATTAH ELMORSHEDY 5 Attachment:5-4-3 Participant List of Training on Education Policy and Planning as of 14 January 2017

No. Ministry / Organization Name Title Department Position A/B

Deputy Minister of Higher Ministry of Higher Education and ESSAM KHAMIS KHAMIS Ministry of Higher Education Prof. Education and Scientific 1 Scientific Reseach IBRAHIM ELHANASH and Scientific Research Research

Senior Assistant Minister for Ministry of Higher Education and KHALED MOUSTAFA KASSEM Prof. Strategic Plan Higher Education and Scientific 2 Scientific Reseach RAMADAN Research

Council for Research centers YASSER REFAAT Prof. Secretary General 3 and institutes ABDELFATTAH MOHAMED

ABDALLA ELSAYED ELSAYED Sector of Society Serves and Zagazig University Prof. Vice president 4 AHMED ASKER Environment Development Group Group B City of Scientific Research and ABDELHADY BASHIR Technological Applications Prof. Investment Zone CEO 5 ABDELHADY KASHYOUT (STRA - City)

Professor of Economics and Faculty of Commerce, SAID ABDELAZIZ ALI OSSMAN Prof. Public Finance Public Finance / Ex-Governer of 6 Alexandria University, Egypt El-Sharkia Governorate

Ministry of Higher Education and NABIL HASSAN MOSTAFA Prof. Project Management Unit Manager 7 Scientific Reseach HASSAN

Ministry of Higher Education and NOURAN ABDELHAMID Studies and Research Unit - Dr. Executive Manager 8 Scientific Reseach IBRAHIM ABDELGAWWAD Higher Education Observatory

Ministry of Higher Education and REEM ALI MOHAMED Dr. Strategic Planning Unit Director 9 Scientific Reseach MOHAMED DERBALA

Ministry of Education and TAREK MOHAMED ABDELAZIZ Minister's Tech. Office - Mr. Head of Department 10 Technical Education MOHAMED Policy and Planning Unit

Ministry of Education and Policy Strategy Planning Unit Chief Specialists (PSPU), NOUR HENRY NOUR DOUS Dr. 11 Technical Education (PSPU), Ministet's Office Minister's Office

Ministry of Education and HAMA ABDELRAHMAN Planning and Projects General Manager of Planning and Dr. 12 Technical Education SHEHATA MANSOUR Department projects department

Ministry of Education and SAMIR RAGAB BASYOUNY Mr. Technical Education Sector Curriculum Expert 13 Technical Education HEGAZY Group Group A National Center for Educational HANAN MOHAMED RABIE Curriculum Development Dr. Associate Professor 14 Research and Development MAHMOUD ABDELKHALEK Research

Ministry of Planning, Monitoring MOHAMED FARID Human and Social Head of Human and Social Mr. 15 and Administrative Reform ABDELFATTAH ELMORSHEDY Development Sector Development Sector

Manager for General and Ministry of Planning, Monitoring HEBA MOHAMED Human and Social Mrs. Vocational Education 16 and Administrative Reform ABDELMONIEM MANSOUR Development Sector Department

Ministry of Planning, Monitoring YOUSSEF ABOUELFADL Human and Social Dr. Manager for Higher Education 17 and Administrative Reform MOHAMED MOSTAFA Development Department

Ministry of Planning, Monitoring HEND GALAL AHMED Educational Excellence Project Ms. Advisory Board 18 and Administrative Reform MOHAMED GELGEL Manager

6/6 Attachment:5-5

Sharing knowledge on Development and Implementation of Execution Plans Project in Egypt Outputs of the project from September 2014 to July 2017

A. Training in Japan No Title Duration Participants Place 27 Feb. 2015 1 Sharing knowledge on development and implementation of execution plans 3 Tokyo to 8 Mar. 2015 Training on NSDI (National Spatial Data Infrastructure) for development 24 Jan. 2016 Tokyo and Urayasu- 2 14 planning to 4 Feb. 2016 city Tokyo, Oita- 23 May 2016 3 Training on National Planning Administration 9 prefecture, to 3 Jun. 2016 Kamakura-city 17 Jan 2017 to Tokyo, Kyoto & 4 Training in Japan for Education Policy and planning 18 29 Jan 2017 Osaka prefectures B. Third Country Training No Title Duration Participants Place 21 Dec. 2014 1 Arab Monetary Fund / JICA Cooperation Seminar on "National Account" to 24 Dec. 3 Abu Dhabi 2014 C. Local training (Follow up for the Training in Japan and Third country Training) No Title Duration Participants Place 1 National Account Expert Seminar 15-Feb-2015 56 Sonesta Hotel Workshop/Seminar on Institute of National 2 “Empowering Egypt 2030 strategy implementation: 27-Mar-2016 77 Planning, Cairo NSDI as a national integration catalyst for planning administration” D. Benkyo-Kai (BK), A unique and fruitful Japanese style workshop (Twelve times BK referres to the attached table.) No Title Duration Participants Place (Twelve times BK referrer to the attached table.) 665 (Twelve times BK participants are 665)

E. Seminar for MOPMAR's staff No Title Duration Participants Place Workshop for Japanese FILP and Housing by Prof. Tsuri, Business innovation 1 17-Mar-2016 20 INP by Prof. Fujii, and Industrial Policy by Dr. Naruo Role of civil servants played in Japan's economic development by Prof. Ministry of Higher 2 17-Jul-2016 50 Nakamura Education Agglomeration of Logistics Functions and Economic Development in Egypt by 3 29-Aug-2016 3 MOPMAR Prof. Tsumori Semi Hierarchical Inter-Organizational Arrangements and it’s Adaptive 4 31-Aug-2016 17 INP Rationality under Highly Uncertain Business Environment by Prof. Fujii FILP for Housing and Energy: Application of Japan’s Economic Policy on 5 5-Sep-2016 20 MOPMAR Egypt by Prof. Tsuri F. Seminar for other Ministries No Title Duration Participants Place Ministry of Higher 1 Japanese Educational Shinigi-kai by Prof. Nagao 3-Jul-2016 15 Education and Scientific Research Ministry of Health 2 Leadership and Public Trust in Government by Prof. Nakamura 14-Jul-2016 180 and Population G. Field trip and study for staff of MOPMAR No Title Duration Participants Place Visiting to the Egypt-Japan University for Science and Technology(E-JUST) 1 6-Dec-2015 4 Alexandria with Dr. Naruo and 3 of IT Dept. staff Visiting to the Egypt-Japan University for Science and Technology(E-JUST) 2 18-Feb-2016 4 Alexandria with Prof. Nagao Visiting to Arab Academy for Science, Technology and Maritime Transport 3 18-Jul-2016 3 Alexandria with Prof. Tsumori 4 Visiting to the Suez Canal Authority in Ismailia with Prof. Tsumori 20-Jul-2016 6 Ismailia 5 Visiting Port Said Authority with Prof. Tsumori 1-Sep-2016 7 Port Said Visiting New Borg el-Arabcity (Industrial Park) and Egypt-Japan University 6 1-Sep-2016 8 Borg el Arab for Science and Technology(E-JUST) Prof. Tsuri and Prof. Fujii 7 Alexandria Port Authority Prof. Tsumori, Prof. Tsuri and Prof. Fujii 2-Sep-2016 6 Alexandria

1/2 As of July 22nd 2017 BK (Benkyo-Kai: Japanese Style Workshop) rollout in Egypt Date / Venue Theme / Opening speech / Key note speech Participant Group discussion topics Number of Participant July 16th BK-Public Policy, Planning and implementation MOPMAR, Ministry of Finance, Ministry of Lical Development, Ministry of What is the learning from NPA training course? 1st 2016 / Al- Prof. Nakamura from Japan Higher Education, Ministry of Electricity, Ministry of Health and Ppulation, 26 Masah Hotel National Center for Planning State Land Use. Aug 30th BK-1 FILP (Fiscal policy and Investment program) MOPMAR, Ministry of finance, Ministry of Electricity, GOPP, IDSC, INP, FILP in Egypt 2016 / Al- for housing and Energy sector. Ain-Sham Univ, Cairo Univ, GAFI, NIB 1. Financial mechanism 2nd Masah Hotel Prof. Tsumori from Japan 2. Financial management 30 Mr. Ahmaed El-Sayyad, COO, National Investment Bank 3. Investment management Sep 3rd 2016 BK-2 Maritime transport MOPMAR, Suez Canal Authority, INP, CAPMAS, Alexandria Port authority, Suez Canal industrial zone, Industrial zone 3rd / Prof. Tsumori from japan General Authority of Suez Canal Economic Zone, Ministry of Transport, Port development, International logistic trend, 26 Al-Masah Dr. Hatem Abd El-Gawad, Suez Canal Authority Said Univ, Arab Academy for Science Technology & Marintime, Competitiveness in global marintime. SepHotel 5th 2016 BK-3 Industrial Policy MOPMAR, Ministry of Tourism, Ministry of Electricity, Federation of Who is the major key player to make it better 4th / Prof. Fujii from Japan Egyptian Industry, Kaizen Center, Ministry of Communication and for Egyptian national economy? 33 Al-Masah Mr. Sekiguchi, Nissan Motor Egypt, Mr.Ikeda, JETRO Information Technology, INP, Center for Political & Strategic Industry, OctHotel 24th 2016 BK-E1: Education system and Industry's needs MinistryNissan, JETRO,,, of Education & Vocational Education A. Quality of Education, B. School mnagement / Al-Masah Dr.Ahmed Geyoushy, Deputy Minister of MOE&VE Ministry of Higher Education & SR, system, C. Social and industrial needs, D. 5th Hotel Mr.Tarek El-Aziz, Head of Strategic Planning Unit, MOE&VE, Dr. MOPMAR, INP, Giz, Ministry of Manpower, National Center for Developing Education infrastructure, E. Teacher's quality, 52 Gamal Megahed, Deputy Genera Technical dept, Ezz Steel HR, NGO, Industry, F. Education industry Nov 8th 2016 BK-E2: Higher Education and SR policy & implementation Ministry of Higher Education & SR, Ministry of Education & Vocational Review 11 critical path and strategic issues & / Dr.Ashraf El-Shihy, Minister of MOHE&SR Education, Cairo univ, Ain Sham Univ, INP, Alexandrian univ, Beni Seweif objectives. Then, deepen the analysis for root 6th Al-Masah Dr. Khaled Kassem, MOHE&SR, Minister's senior assistant to the univ, El-Arish univ, Fayoum univ, Helwan univ, Mansour univ, Menia univ, causes behind the problem on the surface. 66 Attachment:5-5 Hotel Minister South vally univ, Tanta univ, Zigazig univ, National institutes, industry, Dec 14th BK-E3:Dr. Ayman Education Fathy, Senior project Manager implementation in Quality with , Ezz SDS2030 Steel Integration of BK-E1 and 2. 8 critical education Project review from "Pre- 2016 / Al- Dr. Ashraf Alaby, Minister of MOPMAR Invite from MOE&VE, MOHE&SR, MOPMAR, INP as above BK-E1 and 2. education strategy 2030, STI-2030, NSHED- 2/2 7th Masah Hotel Dr.Ahmed Geyoushy, Deputy Minister of MOE&VE, 2030 and SDS2030. 62 Dr. Khaled Kassem, MOHE&SR, Minister's senior advisor Jan 17th ~ Jan 4th Training course in Japan Ministry of Education & Vocational Education Coordinated by Mr. Maeda, Ms. Nishiyama of 28th 2017 Education Policy and Planning Ministry of Higher Education & SR, MOPMAR JICA team Feb 22nd BK-E4: Learning from Japanese Education system MOE&TE, MOHE&SR, MOPMAR, other education expert 2017 / Al- Prof. Essam Khames, deputy Minister (MOHE&SR) (Group 1) Administration Central Government, Prof. Khaled Kassem (MOHE&SR), (Group 2) Administration Local Masah Mr. Mohamed Farid (MOPMAR) Governments (Prefecture and Municipality), Prof. Said Ossman (MOHE&SR), (Group 3) School management (National & 8th Dr. Shinji NARUO (JICA Expert), Minister's advisor (MOPMAR) Private University), Prof. Abdalla Askar, (MOHE&SR), (Group 4) School management (Vocational & High School), Dr. Nouran 97 Abdelhamid (MOHE&SR), (Group 5) School management (Elementary School), Mrs. Heba Mohamed (MOPMAR), (Group 6) Teacher Pre-training, Dr. Reem Derbala (MOHE&SR), (Group 7) Curriculum Teaching Method (Elementary & High School), Dr. Hanan Mohamed (MOE&TE) April 20th BK-E5: MOE&TE's Mid term plan (GroupMOE&TE 8) andScientific JICA teamResearch, Prof. Essam Khamis (MOHE&SR) How to execute MTP 9th 2017 Mr.Tarek El-Aziz, Head of Strategic Planning Unit, MOE&TE organized it, and JICA team supported it. 9 / MoE&TE Dr.Hama, Technical Education May 23rd BK-E6; MOHE&SR's Mid-term plan MOHE&SR, University, education expert and JICA team How to execute MTP 10th2017 Dr. Khaled Abdeled Ghaffar, Minister of MOHE&SR MOHE&SR organized it, and JICA team supported it. 67 / MoHE&SR Dr. Shinji NARUO (JICA Expert), Minister's advisor (MOPMAR) July 18th BK-TOT: Training for Trainer of BK in Egypt HR development & Training expert from 30 ministries BK concept paper developmet 2017 Dr. Saleh Abdelrahman, Deputy Minister of MOPMAR MOPMAR organized it, and JICA team supported it. 1. Scope of BK / Al-Masah Dr. Tarek el Hosary, MSAD (Participant) 2. Key topics definition 11th Ministry of Agriculture, Ministry of Antiquites, M of Civil Aviation, M of 3. Key presentation (Title) 86 Communication, M of Education, M of Higher Education, M of Finance, M of 4. Participant? Housing, M of Industry and Traiding, M of International cooperation, M of,,,, 5. Expected result of the BK July 19th BK Semirar: BK roll out facilitation for past BK participant JICA team Invited the person who participated BK in the past. BK concept paper developmet 2017 Prof. Essam Khames (MOHE&SR) (Participant) What is BK? 12th/ Al-Masah Dr. Khaled Kassem, MOHE&SR, Minister's senior assistant to the Government officials, public sector, How to apply BK in Egypt? 111 Minister Professor, Engineer, Business person, Banker, Design concept paper (1~5). HR development expert, Total 665 Attachment:5-6

Sharing knowledge on development and implementation of execution plans, MOPMAR-JICA

List of equipment

Year of No. Descriptions (Manufacture, Models) Serial No. Quantity purchased Notebook Computer 1 DWCGR32 October 25, 2015 1 Dell Inspiron 5558 Notebook Computer 2 C1NFR32 October 25, 2015 1 Dell Inspiron 5558 Notebook Computer 3 JG6GR32 October 25, 2015 1 Dell Inspiron 5558 Notebook Computer 4 70DRG32 October 25, 2015 1 Dell Inspiron 5558 Notebook Computer 5 6R3HR32 October 25, 2015 1 Dell Inspiron 5558

1/1 Attachment:5-7-1

Minuets of Meeting

 Name of Meeting: First Joint Coordination Committee (JCC) for Project on Sharing knowledge on Development and Implementation of Execution Plans  Date & Time : June 23, 2016 (Thursday), 14:00 ~ 15:30  Venue : Minister's Meeting Room, on 1th floor, MOPMAR  Attendees: No Ministry / Organization Name Position 1. MOPMAR Eng. Mostafa Ghaly Assistant to the Minister Project Manager for JICA 2. ditto Ms. Dalia Abadir MOPMAR Project Assistant to Eng. Mostafa 3. ditto Ms. Heba Rezk Ghaly 4. JICA Egypt Office Mr.Teruyuki Ito Chief Representative 5 ditto Mr. Takatsugu Konno Representative 6 ditto Mr.Mohamed Adam Program Officer 7 JICA MOPMAR Project Dr.Shinji Naruo Project Leader / JICA Expert 8 ditto Dr. Shinichiro Hisada JICA Expert 9 ditto Ms. Adriana Zelmer JICA Expert 10 ditto Mr. Hiroshi Maeda JICA Expert 11 ditto Dr. Mohamed Al Araby JICA Project Analyst  Agenda : 1. Opening remarks by the representative of MOPMAR 2. To monitor and evaluate progress of the project by the Project Director 3. To review and approve the Plan of Operation by JCC 4. To exchange views on major implementation issues of the project chaired by the Project Director and Chief Advisor of the JICA project 5. Closing remarks by the representative of JICA Egypt

 Attachments: 1. Project Design Matrix 2. Plan of Operation 3. 2-1: Basic Framework of the project (New approach) 4. 2-2: Project’s activity (Holistic view) 5. 3-1: Working formation among SDS2030, EP and PC 6. 4-1: Benkyou-Kai (BK) - June, July, August and September 2016)

1

1/4 Attachment:5-7-1

Minuets :

1. Opening remarks by the representative of MOPMAR:

Eng. Mostafa Ghaly (MOPMAR ): - Eng. Mostafa addressed the opening remarks, on behalf of H.E. Dr. Ashuraf the Minister of Planning, Monitoring and Administrative Reform, for the first Joint Coordination Committee (hereafter JCC) of the project of Sharing knowledge on Development and Implementation of Execution Plans (hereafter Project).

2. To monitor and evaluate progress of the project by the Project Director:

- Eng. Mostafa, as the Project Director, presented results of monitoring and evaluation of the Project Design Matrix (hereinafter PDM) and Plan of Operation (hereinafter PO), a period between October 25, 2015 and May 31, 2016, and JCC members raised following comments. Then finally it was approved by the JCC attendees. Comment by: Eng. Mostafa (MOPMAR): - The core activity of Project is to support to set up planning committee (hereinafter PC). Then Project supports to prepare execution plan (hereinafter EP) by PC and to get approval by the responsible government authority. - MOPMAR and Project agreed to utilize “Supreme council of Planning and Urban Development (hereinafter SCPUD)” as same function as PC, once it will be renamed to “Supreme council of Planning and Development (hereinafter SCPD)”. - MOPMAR submitted a request to the Cabinet Office to rename SCPUD to SCPD in August 2015. However, MOPMAR is still waiting for an approval of renaming to SCUD and it is not sure when it will be done by the Cabinet Office due to current political situation. - We want to assert more on the activities of "Capacity Building" of our (public servants’) human capital, in following fields: Education, Health, and National Planning. - We need also above-mentioned field of the Japanese experts to dispatch to our country in the near further, it would be very useful for human capital transformation (human resource capacity building).

2

2/4 Attachment:5-7-1

Dr. Naruo (Project expert): - Original framework of Record of Discussion (hereinafter RD) is based on two key elements: PC and EP. MOPMAR is responsible to set up PC. The role of PC is to prepare an EP. The role of Project is to support the formulation and implementation of PC in order to prepare EP. Without having PC, it is impossible to prepare EP. In august 2015, the Minister of MOPMAR, Dr. Ashraf, offered JICA to change the name of "Supreme Council for Planning and Urban Development" to be "Supreme Council for Planning and Development". However it has not been approved by the Cabinet Office yet. - Currently there are two possible options for establishing PC: 1. Cabinet office would approve the request of MOPMAR and then it would enable "Supreme Council for Planning and Development". 2. Dr. Nihal has been working for an approval of new planning law. If it would be approved by Parliament, then the "Supreme Council for planning and Sustainable Development" will be established, then such a new council would function as PC. - JICA and MOPMAR agreed to make some modification to PDM and PO in September 1st of 2015. The main point of amendment was to acknowledge SDS2030 future vision (hereinafter SDS2030) as the long term economic development strategy and EP would be based on it. - PC has not officially been renamed or formed yet, in this circumstance Project asked the minister of MOPMAR to organize “Preparatory PC ” and facilitated it for three times, so far.

3. To review and approve the Plan of Operation by JCC:

Original PDM and PO, duration from June 1st 2016 to September 30th 2017, are proposed for discussion by JCC attendees. Those were finally approved by the JCC. Comment by: Dr. Naruo (Project): - Dr. Naruo elaborated on relationship between frameworks of SDS2030 and Project how to apply existing issues. - Attachment 3-1 shows a basic framework of Project after SDS2030 was officially announced in February 2016. Attachment 3-1 describes as follow. 3

3/4 Attachment:5-7-1

- SDS2030 as the strategy / vision level, is contained ten (10) pillars. Those each one of pillar drilling down to separate “mid-term plan”. Then, in order to implement annual budget, public investment, projects and programs, those mid-term plan navigate to short-term plan as of operation layer. - Project modifies (adjusts) from original designs to PC (SCPD) has a function of facilitating to drilling down from each pillars as well as developing to EP, which has a function of extracting and integrating policies from ten of mid-term plan, which are drilling down from pillars. Then EP would navigate to the annual short term plan. - The working formation among SDS2030, EP and PC would be discussed further details functions with Dr. Nihal. Mr. Konno (JICA Egypt Office): - What is a role of the MOPMAR in PC? Eng. Mostafa (MOPMAR): - The role of MOPMAR is to mobilize the PC process, to set general direction, to check individual plans designed by the other ministries, coordination of ministries, monitoring and assessment of executed projects and programs, and activation of the government program - In addition, we want to focus on capacity building issues in recent circumstances. We think human development, or human capital transformation, is more important issue.

4. To exchange views on major implementation issues of the project

chaired by the Project Director and Chief Advisor of the JICA project : - In coming three month (June, July, August and September 2016)Project proposed that BENKYO-KAI (learning and studying together method) is organizing for the following up of the National Planning Administration training course and subjects of short-term experts (Energy, Industry, transportation and education). (Attachment 4-1)

5. Closing remarks by the representative of JICA Egypt (Mr. Ito): - Mr. Ito expressed his enthusiasm to cooperation in between JICA and MOPMAR. - He emphasized on acceleration of efforts from both sides MOPMAR and Project to achieve what had been agreed on according to PDM and PO. 4

4/4 添付資料: 5.7.2JCC PDM & PO

Project Design Matrix 別添5:(1) Project Title: "Sharing knowledge on Development and Implementation of Execution Plans" Version One Implementing Agency: Ministry of Planning, Monitoring and Administrative Reform (MoPMAR) Date (up date) June 23, 2016 Target Group: Staff of MoPMAR Period of Project: October 2014 to September 2017 Project Site: Cairo and other Regions Narrative Summary Objectively Verifiable Indicators Means of Verification Important Assumption Achievement Remarks Overall Goal (Status of Verification) The process of the national 1) The national development plans 1) EP 1) Policy Paper (as a development planning and (SDS-2030 (Master Plan), Execution foundation of EP) was implementation according to national Plan(hereafter, EP) and Annual developed by JICA team priorities is improved. Investment Plans) are regularly and on January 2016 and timely developed and implemented. shared with sectors of 2) National mega projects are MOPMAR are implemented according to the national concerned. development plans. 2) Annual investment plans 2) Annual Socio Economic Development Plan 2015/16 was made in Arabic by MOPMAR. Then JICA team translated it in English and distributed to the international organizations.

Project Purpose National development plans are 1) EP is formulated through the 1)EP The policy of Egyptian 1) As same as 1) EP developed and implemented according coordination with Egyptian government to reform the national "Overrall Goal" to national priorities as decided by development partners. development planning and MOPMAR in cooperation with the 2) The annual investment plans are implementation process is going 2) Annual investment plans 2) As same as 2) Egyptian development partners. produced by MOPMAR based on the to sustain. Annual investment execution plan and followed up every plans EP "Overrall year. Goal" 3) Records of meetings by the 3) Preparatory meeting planning committee or its report of the PC was held three times, on 27 Dec. 2015, 7 Apr. 2016, and 22 Apr. 2016.

Outputs (Status of Verification) 1. Execution plan is developed in 1) Roles of the planning committee 1) Planning Committee meeting 1) The staff and budget necessary 1) Policy Paper (as a 1) Planning Committee compliance with Sustainable (hereafter, PC) are defined. records for the development and foundation of EP) was meeting records: As Development Strategy Egypt's Vision 2) PC is set up by MOPMAR and / or implementation of the execution developed by JICA team same as 3) Records of 2030 (hereafter, SDS 2030). other responsible ministries. plans are allocated in MOPMAR on January 2016 and meetings by the 3) EP is prepared with reference of the and in other stakeholders. shared with sectors of planning committee or SDS 2030. 2) Majority of the staff trained by MOPMAR are its report "Project 4) EP's monitoring reports are the project will continue to serve. concerned. Purpose" produced. 2) Execution plan 3) MOPMAR and / or other 2) As same as 1) EP responsible ministries commits "Overrall Goal" and takes the leading role to set 3) Manuals for EP's development PC. 3) As same as 1) EP and its implementation 4) MOPMAR (and other "Overrall Goal" responsible ministries) commits 4) EP's monitoring reports and takes the leading role to plan 4) NA and to implement EP. 2. The organizational framework of 1) Staff‘s knowledge and capacity for 1) Project activities reports 1) Mid-term project MOPMAR is streamlined, and the developing and implementing of EP report is scheduled to capacity of MOPMAR staff is are improved. make by the end of strengthened to develop and implement 2) Staff‘s knowledge and capacity for September 2016. execution plan. Project Management Infrastructure System(hereafter,PROMIS), are 2) Reports of seminars or trainings 2-1) NSDI training improved. in Japan and 3rd country, course was held from 3) Strategic Planning and Policy questionnaire surveys at the end of 23 Jan. to 6 Feb. 2016. Division of MOPMAR is established seminars and trainings and functionalized. 2-2) NPA training course was held from 21 May to 4 Jun. 2016. 3) Reports of local seminars or 3) NSDI’s local workshops workshop was held on 27 Mar. 2016. The report will be published by the end of June 2016.

Inputs Activities Pre-Conditions The Japanese Side The Egyptian Side 1. Support to set up PC for 1. Experts 1. Assign Project Director, Project Organizational reform or development and implementation of EP. 1) Long-Term Experts (Economic Manager. personnel reshufflings inside of (In case that "Supreme Council of Policy/Chief Advisor, Institution MOPMAR by the election etc., Urban Planning and Development" building, Training & Administrative 2.Assign members to Joint which may influence the Project covers the function of PC, the Project management) Coordinating Committee and hold it operation, does not take place. will technically support its operation.) 2) 3 to 4 Short-Term Experts per year annually in order to facilitate (Energy policy, Transportation Policy, organizationtional coordination. Industrial policy, Vocational training etc.) 3. Assign participants for trainings * The exact specialization will be and seminars and project 1-1. Support to study role of PC. determined according to Project supporting staff. progress. 1-2. Support to formulate PC and 4. Project office and facilities. secretariat which manages its 2. Trainings in Japan (15trainees x operation, and to make its manuals and 3times =45 trainees) (NSDI, e- 5. Assign appropriate members for operational rules. Government, policy making process formulating PC. and planning process, others if necessary.) 6. Assign staffs to plan and 1-3. Support to prepare EP by * The exact topics for trainings will be implement EP. MOPMAR / PC and to get approval by determined according to Project responsible authority. progress. 7.Necessary running expenses 1-4. Support to implement EP and to (salary of Egyptian counterparts, make monitoring reports of EP by PC. 3. Local experience sharing trainings, internal transportation cost) for the seminars and workshops. implementation of the Project. 2. Support to streamline organizational framework and capacity building of 4. Trainings in 3rd country (5trainees x MOPMAR to plan and implement EP. 2 times =10trainees) (industry policy and policy making process) 2-1. Hold seminars or workshops of knowledge sharing for policy making 5. Local cost necessary for the Project with Japanese short term experts in implementation Egypt. 2-2. Hold trainings in Japan, pre-training workshops and post-training seminars.

2-3. Hold trainings in 3rd country, pre- training workshops, post-training seminars.

2-4. Support to set up Strategic Planning & Policy Division of MOPMAR by supporting study of its role and its formulation.

1/2 添付資料: 5.7.2JCC PDM & PO

Plan of Operation Version Two 別添5:(2) Date June 23, 2016 Monitoring Year 1st Year (Oct. '15-Sep. '16) 2nd Year (Oct.'16-Sep.'17) Inputs Remarks Issue Solution 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 Expert 1. Economic Policy / 1 Plan Chief Advisor Actual Plan 2. Institution Building 2 Actual 3. Training & Administrative management 3 Plan (Institution Building support) Actual Due to “Egypt – Japan Plan education package Vocational Policy Expert 4. Training & Administrative management 4 Actual program”, a necessity was dispatched earlier was arisen for following than schedule. Plan 0.5 0.5 5. Energy Policy Expert 5 up the program. Actual Plan 0.5 0.5 6. Industrial Policy Expert 6 Actual Plan 0.5 0.5 7. Transport Policy Expert 7 Actual Plan 0.5 0.5 8. Vocational Policy Expert 8 Actual Equipment Plan Actual Training in Japan 1. Policy making process and planning process with 1 2 3 4 Plan National Planning Capacity building for Administration training focus on National Spatial Data Infrastructure (NSDI) Actual actual working members course in Japan was 2. Policy making process and planning process with 1 2 3 4 Plan of the Planning conducted earlier than focus on e-Government Actual Committee. e-government training 3. Policy making process and planning process with 1 2 3 4 Plan course. focus on Planning system / administration Actual In-country/Third country Training Post NSDI’s training 1. Local experience sharing trainings, workshops and 1 2 3 5 6 7 8 Plan Following up of NSDI’s course in Japan was seminars Actual training course in Japan. held on March 27, 2016. 2. 3rd country trainings on Industrial Policy and Policy 1 2 3 Plan Making Process Actual

Activities Year 1st Year (Oct. '15-Sep. '16) 2nd Year (Oct.'16-Sep.'17) Responsible Organization Issue & Achievements Sub-Activities 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 Japan Egypt Countermeasures Output 1: Development of national execution plans in compliance with Sustainable Development Strategy Egypt's Vision 2030 (SDS 2030). 1. Support to set up PC for development and Plan implementation of EP. (In case that "Supreme Council of Urban Planning and Development" Actual covers the function of PC, the Project will technically support its operation.)

1-1. Support to study role of PC. 1 2 3 Plan Grand Design of PC was To be approved by the ✓ developed by JICA team. government. Actual 1-2. Support to formulate PC and secretariat 1 2 3 Plan Two times preparatory To be officially approved PC meeting were held. for renaming the SCPD which manages its operation, and to make its ✓ ✓ Actual from SC”U”PD. manuals and operational rules. 1-3. Support to prepare EP by MOPMAR / PC 1 2 3 Plan Developed the Policy To be made for EP and ✓ Paper (foundation of EP) approved by government. and to get approval by responsible authority. and shared with Actual concerning officials.

1-4. Support to implement EP and to make 1 2 3 Plan monitoring reports of EP by PC. Actual

Output 2: The organizational framework of MoPMAR is streamlined, and the capacity of MoPMAR staff is strengthened to develop and implement execution plans. 2. Support to streamline organizational Plan framework and capacity building of MOPMAR to plan and implement EP. Actual

2-1. Hold seminars or workshops of knowledge 1 2 3 5 6 7 8 Plan To strength Policy Two subjects (energy ✓ ✓ development of energy and industry policy) of sharing for policy making with Japanese short and industry workshop were held at term experts in Egypt. Actual INP on March 17, 2016.

2-2. Hold trainings in Japan, pre-training 1 2 3 4 Plan To aware purpose of Held two times pre- ✓ ✓ NSDI and NPA training training workshop for workshops and post-training seminars. course and to share NSDI and NPA and experience of the NSDI post-training workshop Actual training in Japan. for NSDI was held on March 27, 2016. 2-3. Hold trainings in 3rd country, pre-training 1 2 3 4 Plan workshops, post-training seminars. Actual

2-4. Support to set up Strategic Planning & 1 2 Plan To be strengthen To advice and lecture ✓ ✓ concept of role and for the role and its Policy Division of MOPMAR by supporting responsible of the formulation. study of its role and its formulation. Actual Strategic Planning & Policy Division.

Plan Duration / Phasing Actual

Year 1st Year (Oct. '15-Sep. '16) 2nd Year (Oct.'16-Sep.'17) Monitoring Plan Remarks Issue Solution 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 Monitoring Plan To prepare and organize Held preparation meeting Joint Coordination Committee Actual JCC of JCC To monitor project's Plan Conducted joint progress and review monitoring while 1st JCC Submission of Monitoring Sheet annual operation plan preparation. Actual 2016/17 Plan Monitoring Mission from Japan Actual Reports/Documents Plan Project Progress Report Actual Plan Project Completion Report Actual Public Relations Plan To extend and share To develop and launch Actual knowledge of activities the web-site. Plan Actual

2/2 Attachment:5-8-1

JICA project output list (Sharing Knowledge on Development and Implementation of "Execution Plans)" Category No. Title of the book Year Language 1 National Account 40 Capacity Building of Egypt National Accounts department 2012 E 39 NA expert seminar (All the NA stakeholder meeting) 2015 A 2 HR development 43 Training course for newly-hired Personnel in MOP 2014 A (Capacity 37 Woekshop for Public Policy and Planning (English) 2011 E Building) 38 Woekshop for Public Policy and Planning (Arabic) 2011 A 3 Planning system National Income Doubling Plan; Strategic Framework for 35 E 1)Master Plan Economic and Social Development Plan until 2022 2012 2)Execution Plan 36 Strategic Framework for Economic and Social Development A 3)Annual Public Plan until 2022 (Arabic original version) 2012 investment Plan 41 1st Draft od Execution Plan (E & A) 2017 E/A 7 Socio-Economic Development Plan 2015/16 (English translation) 2015 E 10 SDS2030 (English Translation & Editing) 2016 E 8 "Public Investment (PI)" Polocy paper 2016 E/A 4 NSDI 9 NSDI Integration Seminar handout 2016 E (National Spatial 12 Book1:NSDI: Textbook NSDI Workshop of training presentation course in inJapan Egypt, S1 (E) 2016 E Data Infrastructure) 13 Book2: Textbook of training course in Japan 2016 A 5 BK design 18 BK-Story book (Japanese concept of a Workshop)-E 2016 E (Benkyo-Kai) 19 BK-Story book (Japanese concept of a Workshop)-A 2016 A Japanese style 24 BK-Know how book (Quick referance)-E 2017 E creative workshop 25 BK-Know how book (Quick referance)-A 2017 A 6 BK-0 NPA 11 NPA follow up seminar handout (Benkyo-Kai) 2016 E (National Planning 14 NPA Policy & Planning textbook (Series1-General)-E 2016 E Administration) 15 NPA Policy & Planning textbook (Series1-General)-A 2016 A 7 BK1~3 3 policy 16 BK-Handout (FILP, Energy, Transport, Industry)-E 2016 E 1) FILP for Energy 17 BK-Handout (FILP, Energy, Transport, Industry)-A 2016 A 2) Transport policy 20 NPA Specific Policy (FILP,Transport, Industry)-E 2017 E 3) Industry Policy 21 NPA Specific Policy (FILP,Transport, Industry)-A 2017 A 8 BK-E1~4 26 Benkyo-Kai Education Series (E1~E4)-English 2017 E Education Policy 27 EducationBenkyo-Kai Policy Education & Planning Series Training (E1~E4)-Arabic Text book in Japan - 2017 A and Planning 22 EducationE Policy & Planning Training Text book in Japan - 2017 E 23 A 2017 A 9 BK-E5,6 34 MTP (2017-20) Toward "Integrated Education Plan 2017 E/A Education Mid- 28 Overview note (MTP-Pre University) 2017 E Term Plan 29 Overview note (MTP-Technical Education) 2017 E 30 Overview note (MTP-Higher Education) 2017 E 10 MTP Calender 33 Mid-Term Plan (2017-2020 3 years Calendar) 2017 E 11 Policy design Book for "Policy related paper proposed by JICA team" in 42 E the past (~March 2017) 2017

12 Constitution in 1 Series1 Plain Constitution (Article 1~247)- English 2015 E Your Hand 2 Series1 Plain Constitution (Article 1~247)- Arabic 2015 A (Joint study with 3 Series2 Ruling System and Governance (101~247)-E 2015 E Dr.Talaat) 4 Series2 Ruling System and Governance (101~247)-A 2015 A 5 Series3 National People, Right, Duty and Society (1~100)-E 2015 E 6 Series3 National People, Right, Duty and Society (1~100)-A 2015 A

1/1 Attachment:5-8-2

“Sharing Knowledge on Development and Implementation of Execution Plans”

JICA project report to the Minister (In the past “June 2011~Feb 2017” & Future “ till Sep 2017”)

March 7th 2017 JICA Planning Expert Minister’s Advisor S. NARUO

Table of contents (3 topics) A. History (Past): Page 3 Briefing “JICA support activity to MOPMAR” (June 2011~Feb 2017)

B. Current Situation (Now): Page 12 Three themes in Planning System in Egypt

C. Future proposal: Page 17 Proposing 3 options (April 2017~Sep 2017) Reference: 1. Egypt planning system (SDS2030, Government Program) Page 24 2. How to make Mid-Term Plan. Page 34

1/26 1 Attachment:5-8-2

A. History (Past): Briefing “JICA support activity to MOPMAR” (June 2011~Feb 2017) B. Current situation (Now): Three themes in Planning System in Egypt C. Future proposal: Proposing 3 options (April 2017~Sep 2017) Reference: 1. Egypt planning system (SDS2030, Government Program) 2. How to make Mid-Term Plan.

JICA original proposal: From Master Plan to EP / PC model. 2012 2013 2014 2015 2016 2016 2017 2018 2019 2020 2021 2022 Master Plan: 10 year strategic framework (National Income Doubling Plan)

Guiding This is the framework of RD (Record of Discussion) signed th Execution Plan Phase 1 at 15 April 2013. Execution (3 years: 2014-2017) Plans (EP) (Mid-term Prepare, Execution Plan Phase 2 Plan) Implement, (3 years: 2017-2020) Monitor, Recovery & Evaluate. Execution Plan Planning Phase 3 (2020~) committee (PC)

2/26 2 Attachment:5-8-2

Original Basic design for Planning Committee (PC) Responsible to coordinate Prime Minister Nominate Report Minister of Chief of Committee All the line Instruction Planning ministries Organize MOP (Ministry of cooperate to Planning Committee (PC) Planning) support PC (Member; 20 well-informed person, term; 2 years) the administration of committee. Review and study reports 4th Sub-committee 1st Sub-committee 2nd Sub-committee 3rd Sub-committee National policy Institution design Planning system Plan Execution review 1. Planning law 1. National plan 1. National 1. Energy policy Mega-Project Review and guide 1) Long term plan SNAP (Strategic National 2. Food security New planning law. 2) Mid term plan Mega Project) support 3) Annual plan 3. Employment 2. Related law 2. Regional project system 2. Regional plan Review the environment 1) Project promotion 4.Social safety of planning institution. 3. Industry plan 2) Project monitoring net (Poverty) 3) Recovery 4. Investment plan 5. National 4) Evaluation 1) Public investment urgent issues 2) PPP investment

Project current situation (Mar 2017) Technical cooperation started at Oct 2014 Current situation as of Mar 2017 (Original scope of work) shifted MOPMAR National Income Doubling Plan MP (Strategic Framework ~2022) SDS2030

Aug 2nd 2016 Not yet Shift Ministerial Supreme council PC: Planning ??? committee of Planning & JICA PC Committee Development Technical team secretariat

Execution Shift P-1 P-2 P-3 P-7 P-10 EP Plan (EP) MTP MTP MTP MTP MTP Execute JICA team Sep 2016 MOHE&SR MOE&TE Support

Education BK-E1,E2,E3,E4 & Training MTP course in Japan

3/26 3 Attachment:5-8-2

History of JICA support to MOP 2011 2012 2013 2014 2015 2016 2017

Master Plan Support by specific Technical Cooperation Development subject (Capacity building, JICA team in Economic Policy, Planning) (From Oct 2014 to Sep 2017) MOPMAR April 15th Support for Master Plan R/D Main activity SDS2030 Education pillar “National (Feb 2016) Income Mid-Term Doubling Plan” Policy Plan (2017- EP 2020) (Execution Paper plan) 1.Training course 1 2 3 4 5 Education in Japan (5 times) Planning Planning System NSDI National Policy & (MOP grand design) Planning Planning system Administration JICA seminar for Japanese Experience N NSDI workshop 2. Seminar & S Training course for 1. New planning concept T T Policy study 1~3 for Training course 2. Industrial Policy MOPMAR new employee MOPMAR Employee In Egypt (10 +) 3. National Land development S National Account seminar Finance system & Energy E E 3. Short term NA Transport Expert T T expert dispatch National Account Industrial Policy Expert I I Improvement team From Japan (4 experts) Education Expert E E 4. BK (Benkyo-Kai) Public policy 0 E1 BK: Japanese style Unique FILP & Energy 1 E2 Education Japanese style & Fruitful workshop Marine Transport 2 E3 Series 1~4 Special workshop (8 times BK) Industrial policy 3 E4 1. Text book Constituti NSDI Education 5.Publications for National for New -on study Policy & Planning (30 books) account employee Book1-3 NPA MTP

JICA team’s Support schema – 1 (Total picture) Technical support MOPMAR 1. Capacity building Main support 2. Organization reform 1. Planning Committee Planning 3. MOP grand design 2. Execution Plan process 4. Policy analysis JICA team 5. Planning process

National NPA Scientific Policy NSDI (National Planning Education Accounts Administration) Research analysis CAPMAS CAPMAS MOF Ministry of Higher Ministry of Ministry of Education & SR Education & TE Transport Ministry of Council for Research Ministry of Higher Ministry of Industry INP Ministry of Electricity Communication & Center & Institutes Education & SR & Trade Ministry of Local Information National Center National MOF Technology Development STRA-City Investment Bank Ministry of Higher for Education Egyptian Survey education Ministry of Tourism Central Bank Universities EJUST authority Ministry of Health GOPP & Population Around 20 ministries and National Center for GAFI Planning State land public agencies. use IDSC

4/26 4 Attachment:5-8-2

JICA team’s Support schema – 2 (In MOPMAR) Eng. The Minister Project Mostafa (3) team (86staff) (53staff) (94staff) (312staff) (98staff) (56staff) Regional Minister’s Planning Infrastructure Social/life HR sector sector sector office sector Roll out to all sectors Information Training NA decision support Energy Education Upper Egypt Rolltosectorsall out Parliament, Administrati Plan prep Population, on, Finance ministries Housing Labor force Cairo, Lower A. Economic Plan Agriculture, Monitoring Service Monitoring Water research & Analysis function Funding Transport C. Public investment IT training B. Policy room (Infra, Human/ Social making Industry, sectors & Regional) Trade function Support D. Planning function (Planning sector, Cooperate Mr. Mohamed Farid (2) JICA team Minister’s office) Dr. Hazem Fahmy (1) To be developed. Other 40 staff ,,,,, Training course, seminar, workshop,,, Training course in Japan more than 30% of MOP employee have learned.

JICA team’s Support schema – 3 (MOPMAR Group)

Minister Dr. Hala

Manage & Integrate Government Research Public investment system institute

INP Organization MOP (Ministry of (Institute of CAOA MSAD NIB CAPMAS Planning) National Function Planning)

Public Public Investment 1. Public Investment Investment (Disbursement & management Dr.Shereen El ) Planning Sabagh learned 2. Economic research in JICA training. (Economic research & Research & Policy making function) Consulting & & analysis ⇒To be developed??? Policy analysis 3. Human Resource Training for Training for Training & Training & public servant public servant Development (Training) Education Education 4. National Account & National Account & Statistics & economic statistics Economic information Information analysis analysis 5. Government systemGovernment Government Reform system system reform reform

5/26 5 Attachment:5-8-2

JICA / MOPMAR Project Main Publication List PUBLICATION title Contents Language NO. Published English version 1 CONSTITUTION Series 1-3 - (Plain Constitution)Nov 2015 Presents a general explanation of every article from the Egyptian Arabic version Constitution 2 ANNUAL PLAN-Englis translation March 2015 MOPMAR Public investment English version English version 3 POLICY PAPER (For Mid-term plan) Feb 2016 Policy analysis for EP Arabic version 4 NSDI Seminar Handout March 2016 1st Training in Japan, follow up English version English version 5 NSDI Training in Japan Series1 & 2 July 2016 1st Training in Japan presentations materials, Edited Arabic version 6 SDS 2030-English version Editing April 2016 SDS2030 Editing & Translation English version 7 NPA Benkyo-Kai Seminar Handout July 2016 2nd Training in Japan, follow up English version English version 8 NPA Policy Text Book (General policy) Sept 2016 2nd Training in Japan presentations. Policy making & Plan Arabic version English version 9 Economic policy discussion BK - 1, 2, 3 Oct 2016 Dai-Benkyo-Kai on FILP on Energy and Housing, Arabic version English version 10 BK Story Book Dec 2016 BK Framework and Story Arabic version 11 BK Know How Book Feb 2017 How to prepare BK, and the execution. English version English version 12 Education Training Course Feb 2017 3rd Training in Japan presentations, Edited Arabic version English version 13 Mid-term Plan - EDUCATION Feb 2017 Study and analysis for Mid term Plan of Edication Arabic version English version 14 BK E1-4 Session 1 (Key Note presentation)March 2017 Summarize BK-E1~4 as integrated book Arabic version English version 15 BK E1-4 Session 2 (Group Discussion) March 2017 Summarize BK-E1~4 as integrated book Arabic version to be published English version 16 Planning administration: Plan to implement Integrated Planning administration: Textbook Arabic version soon English version to be published The final reports on FILP on Energy and Housing, 17 NPA Policy Text Book (Specific policy) soon Arabic version P1 National Income doubling Plan July 2012 Prepared before Technical cooperation starting Arabic P2 National Account Knowledge transfer Mar 2012 Prepared before Technical cooperation starting English P3 New Employee training course book Mar 2014 Prepared before Technical cooperation starting Arabic/English

A. History (Past): Briefing “JICA support activity to MOPMAR” (June 2011~Feb 2017) B. Current situation (Now): Three themes in Planning System in Egypt C. Future proposal: Proposing 3 options (April 2017~Sep 2017) Reference: 1. Egypt planning system (SDS2030, Government Program) 2. How to make Mid-Term Plan.

6/26 6 Attachment:5-8-2

3 important findings in Egypt planning 1. Planning process (Consensus building) The plan should have established process to make it. If not, nobody can prepare the precise plan.

2. Plan Structure (Standardized model) The plan should have common framework. If not, nobody understands the plan.

3. Plan’s binding power (Enforcing others to do) The Plan should have the power to force someone to obey it. If nobody cares for the plan, it is just a paper.

1. Planning process (Consensus building) The plan should have established process to make it. If not, nobody understands the plan. Plan preparation Plan Implementation ‘Execution) Prepared by who? End of Egypt Internal process Planning Planning Lack of transparency. PLAN Lack of participation. Start to discuss how process Lack of consensus. to implement Implementation Lack of ,,,,,,, Phase Under the coordination of Planning End of committee, all the stakeholder Planning participate the process. So, at the It is ready Japanese end of preparation, it is ready to PLAN Planning implement the plan. to implement. process Prepare Planning (EPA) EPA Economic committee Planning Monitoring Agency Promote Shift to execution Execution process

7/26 7 Attachment:5-8-2

2. Plan Structure (Standardized model) The plan should have common framework. If not, nobody understands the plan. The common framework of the plan

Responsible 1.Policy organization: Responsible Analysis Planning dept. organization: Investment Operation dept. plan MOPMAR 2.Project, Plan Program Core design 3.Financial design plan Expense MOF Responsible budget organization: Responsible 4.Implementation Budget dept. organization: plan None. 1. Policy analysis: Missing or weak. 2. Project / Program design: Not designed well. Fragmented. No link to financial plan & Policy. 3. Financial plan: Isolated. No link with 1 and 2. 4. Implementation Plan: Missing

3. Plan’s binding power (Forcing others to do) The Plan should have the power to force someone to obey it. If nobody cares for the plan, it is just a paper. Leading & Guiding No binding power Respected as Guideline power A B C Many plans in Egypt

Weak Evolution Medium Strong plan is necessary Plan Plan

1. It is the internal 1. It is public paper. 1. It is public paper. work paper. 2. Instruction (Standard) 2. Authorized at Parliament 2. Reference only. 3. To be adopted by all 3. Everybody respect it. 3. No power to stakeholder. 4. It has power to enforce enforce others. 4. Medium power to others 4. Easy to ignore. others

8/26 8 Attachment:5-8-2

A. History (Past): Briefing “JICA support activity to MOPMAR” (June 2011~Feb 2017) B. Current situation (Now): Three themes in Planning System in Egypt C. Future proposal: Proposing 3 options (April 2017~Sep 2017)

Reference: 1. Egypt planning system (SDS2030, Government Program) 2. How to make Mid-Term Plan.

Proposing 3 options to work for

1. Cross-functional planning approach by BK ⇒Topics: Common planning platform in Egypt 2.Bottom up planning approach by BK ⇒Topics: Local government System and Planning 3.Integrated planning approach by BK ⇒Topics: How to develop “Policy plan” in MOPMAR.

9/26 9 Attachment:5-8-2

1. Cross-functional planning approach BK Topics: Common planning platform in Egypt NPA Reference INP MOPMAR book Invite “planning manager” facilitate Study 1: in each ministry. Basic design of Planning Ministry 1 (MTP model) BK: Knowledge sharing & Study 2: Ministry 2 Group discussion ~~~ Planning process (How to make Plan) Output Ministry 33 Study 3: Egypt Planning Plan execution framework (Proposal)

1. MOPMAR organizes this BK with all other ministries in April 2017. 2. JICA team support to coordinate BK and provide necessary discussion material. 3. Expected result is to make a draft of “Egypt Planning Framework (Proposal)”. 4. BK is the trigger to start the cross-functional planning.

2. Bottom up planning approach by BK Topics: Local government System and Planning MOPMAR

Nominated INP 8 Regional managers Study 1: ministry Local government R2 R4 R6 R8 system in Japan MOHE&SR R1 R3 R5 R7 BK: Knowledge sharing & Study 2: MOE&TE Group discussion G3 G27 Planning of Local G1 G4 G24 G26 G2 G25 government in Japan ??? G5 G,,, Study 3: Academy of 27 Governors Local Autonomy Leadership MOLD college in Japan (Local development) 1. MOPMAR organize this BK with MOLD (Ministry of local Development) in April 2017. 2. JICA team support to coordinate BK and provide Japanese experience and knowledge. 3. Expected result is to facilitate collaboration for regional development. 4. BK is the trigger to link the stakeholder for Regional planning and development.

10/26 10 Attachment:5-8-2

3. Integrated planning approach by BK Topics: How to develop “Policy plan” in MOPMAR. MOPMAR Gather & All the ministries have develop submitted to MOPMAR. Master MTP Public investment Plan 2017-20 Submitted plan preparation. in Feb 2017 Each ministry BK for this draft. Parliament review and authorize Public National in May~June. investment MTP Consider National matching paper plan (Budget) (2017-20) Public investment SDS2030, Policy integration. Book (1000 Annual 3 years Government Investment Investment Strategic approach. Program, pages) plan plan etc Socio-Economic Development Plan (2017/18) Budget Plan Policy Plan

Pre-conditions for Option 1

1. The Minister of MOPMAR invites the ministries. ⇒The minister decides to chose the ministries.

2. The Minister assigns reliable manager to work with JICA team. ⇒Newly assigned deputy minister?

3. The BK schedule will be in April ⇒Recommended at 22nd April 2017 (Saturday)

11/26 11 Attachment:5-8-2

Reference: 1. Egypt planning system ⇒SDS2030, Government Program

2. How to make Mid-Term Plan. ⇒Case study of “Education” field ⇒Collaboration with MOE&TE and MOHE&SR

1. Egypt planning system (SDS2030, Government Program)

Mar 7th 2017

JICA Planning support team Dr. S. Naruo

12/26 12 Attachment:5-8-2

Egypt planning (2016~) There is no plan, but strategy, vision and program.

Published Prepared by Background Period Structure A. 2016. Feb MOPMAR 2016~2030 10 pillars SDS2030 (400 (Logic (15 years) (Consisted Egypt future pages) supported by Need to publish Phase1: by many KPI, vision USAID?) Long term ~2020 objectives, Master plan. Phase2: challenges, ~2030 programs ,,,) B. 2016. Cabinet office Submitted to the 2016~2018 Status qua, Government March Parliament. (2-year) Challenges Action (200 Not, clearly and program pages) defined in 7 axis. the program.

A. SDS2030 Matrix analysis for Dimensions and Pillars-SDS 2030 Functional analysis (By JICA team) 2. Mechanism 1. Development 3. Commitment Restructuring (Proactive actions to (Promise and gurantee (Reconstruct and achieve the target) for the people) innovate mechanism) 3. Knowledge, Innovation and Scientific Research A: Economic 1. Economic Development 4. Transparency and 2. Energy Dimension Efficiency of Governmental Institutions

5. Social Justice B: Social 7. Education and Training 6. Health Dimension 8. Culture

SDS2030's category C: Environmental 10. Urban Development 9. Environment Dimension

13/26 13 Attachment:5-8-2

Statistic analysis for Sustainable Development Strategy Economic Dimencion Social Dimension Environmental Dimension Pillar 3 Pillar 4 Pillar 7 Pillar 1 Knowledge, Transperanc Pillar 10 Pillar 5 Education Economic Pillar 2 Innovation y and Pillar 6 Pillar 8 Pillar 9 Urban Social & Training Total Developmen Energy and Efficiency of Health Culture Environment Developmen Justice (Page 171- t Scientific Governmrnt t 216) Research Institution 1 Objectices 9 6 3 3 3 3 9 3 4 3 46

Challenges (Policies, 2 274 Prioritized 32 28 8 18 12 20 79 12 32 33 target)

3 Programs and 174 Projects 78 9 5 10 6 8 26 8 13 11

KPI (Key 4 252 Performance 32 14 37 13 27 20 45 29 19 16 Indicater) Management Valuable 119 43 16 31 21 31 114 23 49 47 494 from 1 to 3

SDS2030 model

Basic Policy model Measurements

Current Ends Means issues (Goals) Policy means Current Themes Policy Goals

Achievement Ends (Goal)

Current KPI Situation (2020 & Analysis 2030)

CSA Timeframe 1st Phase 2nd Phase 3rd Phase 2020 2025 2016 2030 Now Future

14/26 14 Attachment:5-8-2

B. Government action program 2016 (2016-18: 2 year ) 2nd . 12 challenges st 1 . 7 Axis (Current situation) Egypt Future (Strategic policy and measures) Axis1 Preserving the Egyptian national security (National security)

Axis 2 Deepening and enhancing the democratic structure (Political system reform))

Axis3 Government vision and economic program (Economic policy)

Social equity and citizens services (1. Housing, 2. Health, 3. Education, 4.Youth & Axis 4 Sports, 5. Culture, 6. Local development, 7. Environment, 8. Transport, 9. Religious) Sectoral development (1. Industry, 2. Trade, 3. Mining & Energy, 4. Electricity & Axis5 Reusable energy, 5. Agriculture, Fishery and Forest, 6. Water resource, 7. IT, 8.Tourism, 9. Transport, 10. Civil Aviation ) Administrative reform and further mechanisms of transparency and integrity. Axis 6

Axis7 Leading role on the Arab and African levels and boosting such role on the international level (Diplomacy and International relation)

We are serious about the reform process on all political, economic, social, environmental and administrative levels, and will cooperate, coordinate and work closely with the Parliament First to achieve our goal. Problems and challenges are huge and enormous, however, we are persistent to follow the true scientific method in facing such challenges and problems. Second We will have to take many hard and tough decisions that used to be postponed for long times bringing us to the status quo. It is inevitable now to take such decisions to step towards Third better future. Our goals and programs are clear and definite. They are easy to follow up and evaluate the progress in achievements in a way enhancing the values of governance, transparency and Fourth accountability. Citizen's satisfaction is our focus of interest. So, the issues concerning people (education, health, housing, etc.) are top priorities. Fifth Any economic action will be accompanied by a social protection program to protect, as possible, the poor and people of limited income. The social program will not be implemented Sixth except when the fund resources are available for it to ensure its sustainability and its ongoing benefits. Seventh Corruption is intolerable and we will work hand in hand with your reverend assembly and all regulatory authorities to combat all forms of corruption. We will work with the private sector, treat bureaucracy, and rebuild the administrative body in the country on the fundamentals of competency, integrity and efficiency. Eighth 3rd . Basic idea (The People need to understand in order to achieve good future)

7 axis as strategy

Axis 1 Preserving the Egyptian national security (National security)

Axis 2 Deepening and enhancing the democratic structure (Political system reform)

Government vision and economic program (Economic policy) Axis 3 Vision, goal, fundamental policy, economic infrastructure, institution development & 12 National mega project.

Social equity and citizens services (1. Housing, 2. Health, 3. Education, 4.Youth & Axis 4 Sports, 5. Culture, 6. Local development, 7. Environment, 8. Transport, 9. Religious)

Sectoral development (1. Industry, 2. Trade, 3. Mining & Energy, 4. Electricity & Axis 5 Reusable energy, 5. Agriculture, Fishery and Forest, 6. Water resource, 7. IT, 8.Tourism, 9. Transport, 10. Civil Aviation )

Administrative reform and further mechanisms of transparency and integrity. Axis 6

Axis 7 Leading role on the Arab and African levels and boosting such role on the international level (Diplomacy and International relation)

15/26 15 Attachment:5-8-2

12 Key challenges

8 basic ideas First We are serious about the reform process on all political, economic, social, environmental and administrative levels, and will cooperate, coordinate and work closely with the Parliament to achieve our goal. Second Problems and challenges are huge and enormous, however, we are persistent to follow the true scientific method in facing such challenges and problems. Third We will have to take many hard and tough decisions that used to be postponed for long times bringing us to the status quo. It is inevitable now to take such decisions to step towards better future. Fourth Our goals and programs are clear and definite. They are easy to follow up and evaluate the progress in achievements in a way enhancing the values of governance, transparency and accountability. Fifth Citizen's satisfaction is our focus of interest. So, the issues concerning people (education, health, housing, etc.) are top priorities. Sixth Any economic action will be accompanied by a social protection program to protect, as possible, the poor and people of limited income. The social program will not be implemented except when the fund resources are available for it to ensure its sustainability and its ongoing benefits.

Seventh Corruption is intolerable and we will work hand in hand with your reverend assembly and all regulatory authorities to combat all forms of corruption. Eighth We will work with the private sector, treat bureaucracy, and rebuild the administrative body in the country on the fundamentals of competency, integrity and efficiency.

16/26 16 Attachment:5-8-2

3 layer model GAP analysis in MOP in planning Current situation To be model A.Institution 1. Planning law 70, 1973 1. New Planning law under the constitution 2014. level 2. Planning committee activate (Law, Decision,,,) (Supreme council of Planning and Development)

1. SDS2030 (Egypt vision) 1. The Integrated Master Plan 2. Execution Plan (Mid term plan) 2. Government action B. Planning on 1) Policy program (2016-18) Policy level 2) Project / Program 3. Egypt Economic Reform 3) Finance plan (Policy design) Program 4) Implementation plan Public 1. Public investment plan Investment Under Chapter 6 of Financial Plan (MOP) International Integrate C. Planning on law. Cooperation Budget level 2. Annual Socio-economic planning (MOIC) (Public investment) Plan Public Expense In State Budget (MOF)

2. How to make “Mid-Term Plan”

(Case study of “Education” field) Collaboration with MOE&TE and MOE&TE

Dr. Shinji NARUO JICA Planning Expert Minister’s advisor (MOPMAR)

17/26 17 Attachment:5-8-2

Table of contents

1. Planning process for MTP (Input / output) 1-1. Planning process in MOE&TE 1.2. Analysis and editing for Education MTP 1-3. Basic framework of MTP

2. MTP table of contents (Basic framework) 2-1. MTP (Table of contents ); 1. Policy paper 2. Project / Program Design

3. How to make “Plan” (Analysis and modeling approach) 3-1. Goal of Education 3-2.Planning system model 3-3. Simplified Planning model. 3-4. Analysis flow for Plan paper

4. Next step (MTP Know-how sharing)

1. Planning process for MTP (Input / output)

1-1. Planning process in MOE&TE 1.2. Analysis and editing for Education MTP 1-3. Basic framework of MTP

18/26 18 Attachment:5-8-2

1-1. Mid Term Plan Planning process in MOE&VE.

Community SDGs (UN) Schools Strategic Plan 17 goals 169 targets for Pre- 230 indicator Mid-Term University Implementation Plan 2017-2020 Education 2014-2030 10 principles of project implementation Project, SDS2030 (MOPMAR) Program 10 pillers 46 objectives 274 challenges 174 projects/programs 252 KPI

1-2.Analysis and editing approach for Education MTP

MOPMAR announced (Feb 2016) It will be published by SDS2030 MOPMAR Analysis SDS2030 Education after parliament approval (MOPMAR) analysis paper In May 2017. Public Investment Plan Cabinet⇒ Parliament (March 2016) (Annual & Midterm) Government (MOPMAR, May Education analysis 2017) program Analysis paper 2016~18

Strategy 2014~30 1.Policy (Book1) MOE & VE internal paper Document. Phase1 Investment (2014~17) MTP account (Book2) 2.Project, Program Core design 3. Financial NSHED design plan MOE&TE internal Expense account Document. 4.Implementation STI2030 plan

19/26 19 Attachment:5-8-2

1-3. Basic framework of MTP

1.Policy paper

2.Project, MTP Core design Program 3. Financial design plan

4.Implementation plan

2. MTP table of contents (Basic framework)

2-1. MTP (Table of contents ); 1. Policy paper 2. Project / Program Design

20/26 20 Attachment:5-8-2

2-1. MTP (Table of contents) 1.Policy paper: Basic policy and planning

1-1. Current situation and themes We can define them through policy discussion. 1-1-1. Current situation (Problems and causes) 1-1-2. Themes (Categorized issues to be solved) 1-2. Necessary policies to solve the themes We can design Education system. 1-2-1. Education policy model 1-2-2. Table of theme 1-3. Goal setting We must show expected achievement (Effects) in 3 years later. 1-3-1. Social contribution 1-3-2. Economic contribution 1-4. Total picture of education system and model to be achieved. 1-4-1. Education stakeholder analysis

2-2. Project / Program design paper

2-1. Project / Program design All Project / Program must link with the goals, and then need to consider as follows. 2-1-1. Necessary formation in the ministry 2-1-2. Necessary cooperation with other ministry 2-1-3. Necessary partnership with private sector: PPP, NGO 2-1-4. Necessary cooperation in the regional social community 2-1-5. Necessary collaboration schema with donor 2-2. Financial requirements & Planning: 2-2-1. Government investment - School construction, new facility, project & program cost to be reserved. 2-2-2. Budget for new teacher 2-3. CSF(Critical Success Factor): The requirement out of finance 2-3-1. Change of teacher’s mind set 2-3-2. Establish mutual trust between school and community: 2-3-3. Collaboration with industry 2-3-4. Management system redesign in school, public institute 2-3-5. Legislation and proper process to execute the law

21/26 21 Attachment:5-8-2

3. How to make “Plan” (Analysis and modeling approach)

3-1. Goal of Education 3-2. Planning system model 3-3. Simplified Planning model. 3-4. Analysis flow for Plan paper

Goal of Education Quality of 1. HR for industry & government Education 2. Quality of People’s Life 3. Stable society (Social quality)

Ultimate Goal Improve the quality of Education

Expand the capacity of Education

Current situation Capacity of Education

Everybody agree this model.

22/26 22 Attachment:5-8-2

3-2. Planning system model 1. HR for industry & government 2. Quality of People’s Life Ultimate goal Ultimate 3. Stable society (Social quality) goal Enable Capacity of Quality of Goals Education Education

objective objective objective objective objective objective objective ~~~ Objective 1 2 3 4 5 6 15~

Theme Theme Theme Theme Theme Theme Theme Issues, or or ~~~ or or or or or Challenges, Challenge Challenge Challenge Challenge Challenge Challenge Challenge problem, group 1 group 2 group 3 group 4 group 5 group 6 group 15~ actions

Project / Project / Project / Project / Project / Project / Project / Project / Project / Project, Program Program Program Program Program Program Program Program ~~~ Program Program 1 2 3 4 5 6 7 8 30

Finance mechanism

Public investment (MOPMAR), International cooperation (MOIC), Expense for the Financial project (MOF), Private sector’s investment, PPP, other finance source system

3-3.Simplified Planning model (Ex: Education) Ultimate goal Ultimate goal (HR, Quality Life & Society) (Result of good 1. Policy Education) analysis Enable Goals paper Capacity of Quality of Education Education (Education)

Enable Objective 2. Project / objectives (Target to achieve) Program Theme Themes or challenges Design or (Issues, challenges, Challenge problem, actions To be solved) Enable Projects / Programs Projects / Programs (Measures: Action to 3. Financial solve the issues) Plan Enable Public investment (MOPMAR), International cooperation (MOIC), Expense for the project Financial system (MOF), Private sector’s investment, PPP, (Financing for other finance source projects / programs)

23/26 23 Attachment:5-8-2

3-4. Analysis flow for Plan paper

1. HR for industry & government Ultimate goal 2. Quality of People’s Life (Result of good 3. Stable society (Social quality) Education) Enable Capacity development Goals Quality improvement (Education) 2 4 6 8 10 12 Objective 1 3 5 7 9 11 ----- (Target to achieve) I I I C C C I Themes or challenges I P P P C (Issues, challenges, P C Analyze,O I classify, Oand map Ito objectives.O P O C I C I O problem, actions P O C P C P O O P O To be solved) P/P P/P P/P P/P P/P Projects / Programs (Measures: Action to P/P P/P P/P P/P solve the issues) P/P P/P P/P Public State International Financial system PPP investment budget cooperation (Financing for (?) (MOPMAR) (MOF) (MOIC) projects / programs)

4. Next step (MTP Know-how sharing)

4-1. Next step (MTP Know-how sharing) 4-2. Sharing Basic Framework of Planning in Egypt 4-3. Implementation of “Planning process learning”

24/26 24 Attachment:5-8-2

4-1. Next step MTP (Mid- term Plan) know-how sharing

Target ministry “Planning” Know-how transfer (To be defined) Ministry of Finance MOPMAR Ministry of MTP Know-how (Support by Electricity paper JICA team) (How to make a Ministry of plan) Health Ministry of Local Joint work Development Ministry of Education &TE Ministry of Transport Ministry of Higher Education &SR Ministry of ,,,,,,,,,,,,

4-2. Sharing Basic framework of Planning in Egypt 1.Policy paper

2.Project, Planning Program Core design 3. Financial design plan

4.Implementation plan

Cabinet MOPMAR office MOIIC MOF MOT MOLD MOHE&SE MOE&TE MOE MOH&UC MOY&S MOE&RE MOCI MOI&T MOM MOA MOWR MOP All others need planning

25/26 25 Attachment:5-8-2

4-3. Implementation of “Planning process learning” Starting from Education for social prosperity BK Start in (All ministries) Revisit Each ministry For improvement 1. Goal & 4. Harmonize the Objective design planning mechanism Deepen the discussion Think & Act Integration Verification 2. Project & 3. Develop feasible Program design & finance plan Mapping P/P to objectives. Feasibility Verify financial feasibility of the project & program.

26/26 26 3 layer of Planning Institution- Policy - Operation 2015.08.31 National development system MOPMAR(Planning Function)'s Grand design (Role & Responsibility Model) Layer Work field CSA (Step1) To be model (Step2) Doable model(Step4) A Institution Layer (Law, Decree, Regulation, convention , rule) 9 articles in the Constitution refers A-1. Constitution The constitution 2014 has to "Planning". It is necessary to Same as "To be model" level been enacted in Jan 2014. review the requirements. Institutio Need to design "The System of After general election, new cabinet shall submit A-2. Law/Decree Planning administration in Egypt", "New Planning Law"to the parliament. n system Planning Law No. 70, 1973 level and then draft "New Planning Law". B Policy Layer (State Policy design) JICA Collaborates underlined parts mainly. Constitution Article 167 requires the governemnt to prepare The After general election in Nov,Dec 2015, new Attachment:5-8-3 B-1. State policy Not yet General Policy of the State. cabinet start to develop it with the President. ⇒Need to study the constitutional Then, submit it to the parliament.

1/1 requirements of Article 167. 1. Constitution Article 167 requires 1. Planning committee (Suprem Council of The General Plan of the State. Planning and Development) Policy 2. Strategic Planning and Policy Division system 2. Planning system (Egypt model) 3. Macro Economic Unit (New Function) B-2. Strategy 1. SDS2030 1) Long term Plan (10 years longer) Need to restructure the organization in order to (To be announced soon). 2) Middle term Plan (3-5 years) implement 1,2 and 3 as above. 3) Short term Plan (This can be Linkage caregorized under C-1: Budget plan). 1. SDS2030 (Long term vision) between 2. Execution Plan (Mid-term plan) Policy and C Budget Layer (National budget, public investment) Integrated Investment 1. Socio-economic systematic Review and Analyse PIM. by development plan (Annual) 1. Business process design view. indicater C-1. Budget plan 2. Public investment Plan 2. Information Technology view (Chapter 6) New integrated concept "Public 3. Total investment view. Investment C-2. Project / Program 233 employee are working Investment management (PIM)" 4. Social impact view (Benefit) system for "Public investment". that Mr. Mostafa proposed. 5. Cost vs. Effect view implementation 6. Schedule & timing view C-3. IT infrastructure Promise system 7. Collaboration schema (WB or others?)