Government of

OUTCOME BUDGET 2014-15

Rural Development Department

Sl. Page No. No. CONTENTS

1. EXECUTIVE SUMMARY I-VII

2. CHAPTER-I Introduction 1-15

CHAPTER-II Outcome Budget, 2014-15 3. 16-119 Statement (Plan & Non- Plan)

CHAPTER-III Reform Measures & 4. Policy Initiatives 120-122

CHAPTER-IV Past performance of 5. programmes and schemes 123-129

6. CHAPTER- V Financial Review 130-137

7. CHAPTER-VI Gender and SC/ST 138 Budgeting

EXECUTIVE SUMMARY

The Outcome Budget of Rural Development Department broadly indicates physical dimensions of the financial outlays reflecting the expected intermediate output. The Outcome Budget is a tool to monitor not just the immediate physical "outputs" that are more readily measurable but also the "outcomes" which are the end objectives.

2. The Outcome Budget 2014-15 broadly consists of the following chapters:

 Chapter-I: Brief introduction of the functions, organizational set up, list of major programmes/schemes implemented by the Department, its mandate, goals and policy frame work.

 Chapter-II: Tabular format(s)/statements indicating the details of financial outlays, projected physical outputs and projected outcomes for 2014-15 under Plan and Non-Plan.

 Chapter-III: The details of reform measures and policy initiatives taken by

the Department during the course of the year.

 Chapter-IV: Write-up on the past performance of the year 2012-13 and 2013-14 (up to March-2014)

 Chapter-V: Actuals of the year preceding the previous year, Budget Estimates and Revised Estimates of the previous year, Budget Estimates of the Current Financial year.

 Chapter-VI: Highlights of the outlays provided for the schemes benefiting Women, ST and SC groups along with the corresponding physical output.

Outcome Budget; DoRD for 2014-15 Page I

Monitoring Mechanism of Rural Development department

The establishment of the Millennium Development Goals has significantly reinforced the concerns about non-income poverty. With the paradigm shift in economic development from growth to broadly defined “development,” the concept of rural development has begun to be used in a broad sense. The concept now encompasses “concerns that go well beyond improvement in growth, income and output. Connectivity – physical like roads, water and sanitation services to our people in rural areas is not an administration but a mission.

Road transport is vital for the economic development and social integration of the country. Easy accessibility, flexibility of operations, door-to-door service and reliability have earned road transport an increasingly higher share of both passenger and freight traffic vis-à-vis other transport modes. Transport sector accounts for a share of 6.4 percent in ’s Gross Domestic Product (GDP). The Road Transport Sector has grown significantly during the past five decades. Road Transport has deep linkages with the rest of the economy and a strong multiplier effect. Transport is essentially a derived demand depending upon the size and structure of the economy and the demographic profile of the population. Greater the share of commodity- producing sectors like agriculture and manufacturing, higher is the demand for transport. Orissa’s surge in growth and expansion in public spending in the past decade has created new possibilities for its social protection system. Social protection strategy must aim at mitigating water poverty in rural areas. The Government is firmly committed to the goal of providing safe drinking water and sanitation facilities to the entire population of the State. The Government is equally committed to the objective of ensuring source and system sustainability. Despite the efforts put forth in the past, there is a growing concern over the widening gap between the expectations of the people and the achievements. Paucity of funds, over-exploitation of water resources, degradation of water recharge structures, competing demand on the available water resources, depleting water availability due to continuous failure of monsoon are some of the factors that cause concern on the supply front.

There is an inbuilt monitoring mechanism in the guidelines of each scheme of the Department so as to ensure that the objectives are achieved by their implementation.

The Deptt. have 13 Sections. Two sections namely (1) Budget and (2) PMGSYare headed by a F.A-cum-Addl. Secretary, seven sections like (1) RWS&S (Field

Outcome Budget; DoRD for 2014-15 Page II

Establishment) (2) RWS&S (Scheme) (3) Bill and Cash (4) Office Establishment (5) Coordination (6) RTI/PMU and (7) DAK Section are being managed by one Additional Secretary, 2 sections namely (1) RW (Establishment) and (2) RW (Scheme) are being managed by one Joint Secretary, Computer Cell is being look after by Deputy secretary. Legal Cell is headed by Law Officer. That apart, there are two Under Secretaries and one AFA-cum-Under Secretary to assist FA-cum-AS and Addl. Secretaries in discharging the official duties.

The Department has a huge field formation with 2 EICs, 6 Chief Engineers at Heads of Dept. level (1 EIC and 3 Chief Engineers in Rural Works Organization, 1 EIC and 3 Chief Engineers in Rural Water Supply and Sanitation Organization), 23 circles headed by S.Es at Circle level (15-RW + 8 - RWS&S) and 89 Divisions headed by Executive Engineers at District level ( 53-RW and 36-RWS&S) and 404 Sub-Divisions headed by Asst. Executive Engineers (AEE) at Sub-Division level, 628 Sections headed by AEs & JEs who are looking after the functioning of this Department. This is in addition to 314 JEs recently engaged for O&M and sanitation work in each Panchayat Samiti. There are two Agencies namely (i) Odisha State Rural Road Agency (OSRRA)- chaired by Hon'ble Minister RD, to monitor the PMGSY works and (ii) Odisha State Water & Sanitation Mission (OSWSM)- chaired by the , to monitor/execute the Nirmal Bharat Abhiyan (previously known as Total Sanitation Campaign (TSC) programme). Apart from continuous monitoring through periodical progress reports received from the Districts depicting both the financial and physical progress of the programmes, the Department also emphasizes on E-Governance. Emphasis is being given on both quality and quantity of physical progress. For effective monitoring of quality of works for non-PMGSY works Third Party Quality Monitoring System is being established. Project Monitoring Units are being set up for monitoring the physical progress of works of both RWS&S and RW organisations. To monitor the physical progress of each project, provision has been made in WAMIS for uploading the geo-tagged photographs of works. This system will facilitate the high level officers to monitor both the physical as well as financial progress of projects.

Furnishing of statement of expenditure, Utilization Certificates, Audited Accounts and other requisite reports are submitted for the release of subsequent installments.

Outcome Budget; DoRD for 2014-15 Page III

The officer dealing with the implementation of the programmes visits regularly the site to ensure that the programmes are being implemented satisfactorily.

Officers visit their assigned districts at regular intervals and the important observations of such teams are shared with the Department advising them to take appropriate corrective measures, wherever shortcomings are noticed.

A Performance Review Committee under the chairmanship of Principal Secretary reviews the performance of various programmes being implemented by the districts and recommends corrective action wherever found necessary.

With a view to fulfilling the objective of ensuring quality in implementation, particularly in the context of large public funds being spent under all the programmes of the Department the Monitoring Committees are constituted.

Regular monthly review meetings are held through Gramsat and Video conferencing and along with this constant feedback and suggestions are taken and incorporated for the proper implementation of the programmes.

Work Plan for DoRD for the Financial Year 2013-14 was prepared with due consultation of all stake holders. The work plan was drawn up taking into account the annual budget provisions and past performance of respective areas of work. The Chief Engineers were asked to draw up similar month wise and head of expenditure wise financial and physical plans for all the divisions to enable field functionaries to appreciate the purpose and benefit of Results Framework Approach. Evaluation has been made basing on the scheme-wise weightage provided to physical targets. It is found that during the financial year 2013-14, the achievement was about 93%. The RFD for the year 2014-15 is also prepared and submitted to P&C Department.

Public Information System

Information, Education and Communication (IEC) plays a vital role in creating awareness, mobilizing people and making the development participatory through advocacy and by transferring knowledge, skills and techniques to the people. Moreover, IEC plays two most important roles – informative and persuasive and as such is crucial for bringing about requisite social mobilization and facilitating participatory development.

The following strategy that has been adopted by the Department would be continued to ensure maximum benefits out of the programmes of the Department.

Outcome Budget; DoRD for 2014-15 Page IV

Odisha Right To Public Services Act 2012 – Repair of Handpump

Delivery of important services in a time bound manner is the hallmark of Good Governance. has time and again initiated steps for improving the service delivery to its citizen. Keeping with the ethos of a Welfare State, Government of Odisha has passed a landmark legislation "Odisha Right to Public Services Act, 2012" that guarantees the delivery of public services in a time bound manner. With the passing of Right to Public Services Act, Government of Odisha has taken another strong step to bring efficiency, accountability and transparency in delivery of the public services. Time period of services (Repair of Hand Pump Tubewells) has been prescribed as detailed below: (i) 7 days of Minor Repair (ii) 14 days of Major Repair(except replacement) (iii) 28 days for replacement.

 Designated Officer .. Junior Engineer-II, RWSS  Appellate Authority .. Assistant Engineer, RWSS  Revisional Authority .. Block Development Officer.

All the Tubewells belonging to RWSS organisation are being painted in number Any person who wants to repair the tubewells may apply to the Designated Officer (DO) by giving the details of tubewell in a plain paper along with his address, and DO shall repair the said tubewell within 7 days.

APPEAL : Any person whose application is rejected or not provided the service within given time limit may within 30 days from the date of receipt of order of rejection of expiry of given time limit prefer an appeal before the Appellate Authority. Appellate Authority may within a period of 30 days from the date of filing of appeal by order, direct the Designated Officer to provide the service within the time limit mentioned in the order.

REVISION: Any person aggrieved by the order of Appellate Authority or in case of non-disposal of the appeal in time may within 30 days from the date of that order, prefer a revision. Revision with 30 days.

Revisional Authority may impose penalty within the designated officer appellate authority and the subordinate staff `5000/ or `250/ per each day of delay shall be

Outcome Budget; DoRD for 2014-15 Page V proportioned to be decided by the revisional authority. Public holidays shall not be included in the given time limit. This is an act of the Government to provide service within the given time.

Sanjog Initiative

Sanitation is essential to ensure a better quality of life among all sections of people in rural and urban areas. 80% of common diseases are caused by lack of sanitation and personal hygiene practices. Total Sanitation Campaign (TSC) does not limit itself to safe disposal of human excreta; it forms a comprehensive concept that includes safe disposal of solid and liquid waste, food hygiene, domestic and personal hygiene. TSC in Odisha is being implemented in all the 30 districts of the State. The Programme is “community-led” and “people-centered” with increased stress on awareness creation and demand generation from people for sanitary facilities in households, schools, anganwadis centers for cleaner environment. The present Operational Guidelines and booklet on Technology Options are developed to guide district as well as field functionaries and core team members in smooth implementation of the TSC programme. This is necessary because of low coverage of IHL construction and less involvement of Panchayati Raj Institutions specifically Gram Panchayats in the program.

The Sarpanch will monitor the progress of the household, school and anganwadi sanitation in the GP. He /she will be supported by a team of AWWs, ASHA, SEM and village motivators to make household visits, and assess the participation of the households, installation of complete and usable toilets, technologically appropriate and fitted correctly to ensure best benefits to the community. An appropriate superstructure should also be done to render the toilet usable immediately. The completed toilets will be verified by a two member team consisting of SEM and AWW, AWW and ASHA or the SEM and ASHA. The implementing agency, SHGs, the AWWs, ASHA, and Sarpanch will continue to advocate the use of toilets after the installation is complete.

They should also emphasize the importance of other associated hygiene practices, hand washing with soap after defecation and before handling food, safe disposal of child fecal, safe disposal of waste water and solid waste, cleanliness around hand pumps, clean tube well platforms etc. Nirmal Gram Puraskar has been awarded to 236 Gram Panchayats for achieving total sanitation and open defecation free environment by HE Outcome Budget; DoRD for 2014-15 Page VI

E-initiatives

Efficiency of delivery is increasingly becoming the focus of governmental programmes. This is both on account of an explicit recognition of sub-optimal achievements in reaching the targeted beneficiaries in many of the schemes as well as in curbing wasteful expenditure. Realizing this, new tools, particularly application of modern technology are being resorted to in achieving governance and delivery efficiency.

As per section 4 of Right to Information Act, 2005 every public authority shall maintain all its records duly catalogued and indexed in a manner and the form which facilitates the right to information under this Act and ensure that all records that are appropriate to be computerized are, within a reasonable time and subject to availability of resources, computerized and connected through a network all over the country on different systems so that access to such records is facilitated. The Act U/S 4-4 further says that all materials shall be disseminated taking into consideration the cost effectiveness, local language and the most effective method of communication in that local area and the information should be easily accessible, to the extent possible in electronic format with the Central Public Information Officer or State Public Information Officer, as the case may be, available free or at such cost of the medium or the print cost price as may be prescribed.

The e-initiatives of RD department were meant to answer the above need and convert this threat into an opportunity to automate the processes that can be done so using latest technology platforms. E-Dispatch, iOTMS, e-Procurement, LMS, OMMAS, IMIS, WAMIS and OSWAS were major steps, taken. In addition to the above the website of RD Department are maintained and updated regularly.

Road Ahead

Rural Development Department is in charge of construction and maintenance of rural roads and water supply. We have got plan to connect habitations with population 250 and above in 18 IAP districts and habitations with population 500 and above in plain areas and 250 and above in scheduled area for balance 12 Non IAP districts in a phased manner. Till 31.03.2014, 7308 habitations above 250 populations have been provided connectivity under PMGSY. During 2013-14, approx. 500 habitations are going to be provided with all-weather connectivity. Out of such habitations, connectivity has been provided to 418 unconnected habitations till end of

Outcome Budget; DoRD for 2014-15 Page VII

December 2012. Similarly we have less than 2% rural house hold with tap-water in their household. 74 lakh rural households require 3-taps (kitchen, bathroom and toilet) in their households to enjoy water security at household level. Sanitation coverage among BPL is encouraging but the same among APL is not so. This may require more intensive and extensive IEC campaign for times ahead.

Outcome Budget; DoRD for 2014-15 Page VIII

CHAPTER-I

INTRODUCTION

The concept of rural development has changed significantly during the last 3 decades. Until the 1970s, rural development was synonymous with agricultural development and, hence, focused on increasing agricultural production. This focus seems to have been driven primarily by the interests of industrialization to extract surpluses from the agriculture sector to reinforce industrialization. Four major factors appear to have influenced the change: increased concerns about the persistent and deepening of rural poverty; changing views on the meaning of the concept of development itself; emergence of a more diversified rural economy in which rural non-farm enterprises play an increasingly important role; and increased recognition of the importance of reducing the non-income dimensions of poverty to achieve sustainable improvements in the socio-economic well-being of the poor.

The establishment of the Millennium Development Goals has significantly reinforced the concerns about non-income poverty. With the paradigm shifts in economic development from growth to broadly defined “development,” the concept of rural development has begun to be used in a broader sense. The concept now encompasses “concerns that go well beyond improvements in growth, income, and output. The concerns include an assessment of changes in the quality of life, broadly defined to include improvement in health and nutrition, education, environmentally safe living conditions, and reduction in gender and income inequalities.”Today there seems to be a universal consensus that the ultimate objective of rural development is to improve the quality of life of rural people. This makes it essential to go beyond the income-related factors such as prices, production, and productivity to a range of non-income factors that influence quality of life and hence inclusiveness. Inclusive rural development is a more specific concept than the concept of rural development.

Rural upliftment requires strong commitment, patience and perseverance. It is a challenging but interesting task. The Govt. can not by itself provide the required services/comforts without the cooperation of the all stake-holde` Physical connectivity like construction of roads and bridges and providing adequate safe drinking water as well as sanitation services to our rural population is indeed a mission and not a mere administrative function. With this concept, R.D. Department was created on 1st July, 1990 to look after sectors like construction of rural roads, buildings construction & maintenance of rural water

Outcome Budget: DoRD for 2014-15 Page 1 supply projects and implementation of sanitation programmes to enhance the quality of life of rural population of the State.

Work Plan for DoRD for the Financial Year 2014-15 is prepared with due consultation of all stake holders.The work plan was drawn up taking into account the annual budget provisions and past performance in respective areas of work. The Chief Engineers were asked to draw up similar month wise and head-wise financial and physical plans for all the divisions to enable field functionaries to appreciate the purpose and benefit of Results Framework Approach. We propose to continue this in current financial year.

The Rural Development Department in its present form consists of two organisations namely (i) Rural Works (R.W.) (ii) Rural Water Supply & Sanitation (RWS&S). Organisational Setup:

The Deptt. have 13 Sections. Two sections namely (1) Budget and (2) PMGSYare headed by a F.A-cum-Addl. Secretary, seven sections like (1) RWS&S (Field Establishment) (2) RWS&S (Scheme) (3) Bill and Cash (4) Office Establishment (5) Coordination (6) RTI/PMU and (7) DAK Section are being managed by one Additional Secretary, 2 sections namely (1) RW (Establishment) and (2) RW (Scheme) are being managed by one Joint Secretary, Computer Cell is being look after by Deputy secretary. Legal Cell is headed by Law Officer. That apart, there are two Under Secretaries and one AFA-cum-Under Secretary to assist FA-cum-AS and Addl. Secretaries in discharging the official duties.

The Department has a huge field formation with 2 EICs, 6 Chief Engineers at Heads of Dept. level (1 EIC and 3 Chief Engineers in Rural Works Organization, 1 EIC and 3 Chief Engineers in Rural Water Supply and Sanitation Organization), 23 circles headed by S.Es at Circle level (15-RW + 8 - RWS&S) and 89 Divisions headed by Executive Engineers at District level ( 53-RW and 36-RWS&S) and 404 Sub-Divisions headed by Asst. Executive Engineers (AEE) at Sub-Division level, 628 Sections headed by AEs & JEs who are looking after the functioning of this Department. This is in addition to 314 JEs recently engaged for O&M and sanitation work in each Panchayat Samiti. There are two Agencies namely (i) Odisha State Rural Road Agency (OSRRA) to monitor the PMGSY works and (ii)Odisha State Water & Sanitation Mission (OSWSM) to monitor/execute the Nirmal Bharat Abiyan (NBA) programme.

Principal Secretary is the Chief Executive Officer to monitor the work of the Department.

Outcome Budget: DoRD for 2014-15 Page 2

ORGANISATIONAL STRUCTURE

SECRETARIAT ESTABLISHMENT

PRINCIPAL SECRETARY

ADDITIONAL SECRETARY Joint FINANCIAL Secretary ADVISOR - cum - ADDITIONAL SECRETARY Deputy Secretary Under AFA-CUM-UNDER Under Secretary Secretary SECRETARY (1) Bill and Cash (1) RWS&S (1) Office (1) RW (Field 1. Budget Section (2) Coordination (Field Est.) Establishment Est.) (Audit Report, compliance (2) RWS&S (2) RTI/IMU (2) RW to SVP Report, Inspection (Scheme) (Scheme) Report, Efficiency Audit (3) Legal Cell Report) (4) Computer 2.PMGSY Cell (5) DAK Section

Outcome Budget: DoRD for 2014-15 Page 3

RURAL WORKS ORGANISATION

ENGINEER-IN-CHIEF (Planning, Budget, Accounts,Improvement & maintenance of RD Roads (Non-Plan), PMGSY and Establishment)

1. CHIEF ENGINEER, RW-I 2. CHIEF ENGINEER, RW-II 3. CHIEF ENGINEER, RW-III (Construction & Maintenance (ADB assisted PMGSY works, MMSY, Development of (Roads and Bridges funded by NABARD, Buildings, BSY, CWA, Bailey Bridges, Rural Road Connectivity, Quality Monitoring of improvement of RD roads under Plan Assembly maters) PMGSY & NON-PMGSY, PMU and training) Scheme, ACA, SCA for KBK districts and Rural Roads under 37114-Public works) CIRCLES DIVISIONS CIRCLES DIVISIONS CIRCLES DIVISIONS CIRCLES DIVISIONS CIRCLES DIVISIONS 1.SE, 1. 4. S.E. 1. KEONJHAR 7. SE, 1. 10. S.E., 1. SUNDARGARH-I 13. S.E RW 1.-I RW CIRCLE, 2. NORTH EASTERN 2. KEONJHAR-II RW CIRCLE, 2. RW CIRCLE, 2. CIRCLE, 2.KENDRAPARA-II ANGUL 3. KAMAKHYA CIRCLE, 3. BHAWANIPATNA 3. DHARMAGARH SUNDARGARH 3. KENDRAPARA NAGAR KEONJHAR 4.KESHINGA 5. KHARIRAR

2.SE. 1. 5. S.E. RW CIRCLE, 1. 8. S.E., 1. -I 11. SE, 1. BOLANGIR 14. S.E. 1. ELECTRICAL RW CENTRAL 2. BARIPADA 2. RW CIRCLE, 2. GANJAM-II RW CIRCLE, 2. TITILAGARH ELECTRICAL, BBSR CIRCLE, BBSR 3. -I 3. 3.GAJAPATI BOLANGIR 3.SONEPUR CIRCLE, BBSR 4. NAYAGARH-II 4. 4. 5. NIMAPARA 5. 2. MECHANICAL 6. BBSR 7. 8. BALIGUDA 3.SE., 1. -I 6. S.E. 1. 9. SE, 1. 12. SE, 1.-I 15. S.E. 1. PH, BBSR RW CIRLCE, 2. BALASORE-II RW CIRCLE, 2. -I RW CIRCLE, 2. DEOGARH RW CIRCLE, 2.CUTTACK-II RW P.H. CIRCLE, BALASORE 3. 3. MALKANGIRI-II SAMBALPUR 3. CUTTACK 3. -I BBSR 4. -I 4.-I 4. 4. JAJPUR-II 5. BHADRAK -II 5.NABARANGPUR-II 5. 6. 7. SUNABEDA 8. 9.

Outcome Budget: DoRD for 2014-15 Page 4

RURAL WATER SUPPLY & SANITATION ORGANISATION

EIC and CHIEF ENGINEER-I CHIEF ENGINEER-II CHIEF ENGINEER-III (NRDWP-except PWS Scheme, (NBA, WSSO, OSWSM, water quality, water (NRDWP-PWS Scheme, Deposit Works) Establishment, Capacity Building, Budget, testing laboratories) RIDF, installation, repair & maintenance of spot sources, Deptt. rigs.) 1. S.E. 2. S.E. 3. S.E. 4. S.E. 5. S.E. 6. SE 7. SE 8. SE BHUBANESWAR CUTTACK SAMBALPUR BERHAMPUR KORAPUT PLANNING BOLANGIR BALASORE MONITORING, DESIGN & INVESTIGATION, BBSR

DIVISION DIVISION DIVISION DIVISION DIVISION DIVISIONS DIVISIONS DIVISIONS 1. PURI 1. CUTTACK 1. SAMBALPUR 1. BERHAMPUR 1. KORAPUT 1. MECH., BBSR 2. Khurda 2. KENDRAPARA 2. BARGARH 2. BHANJANAGAR 2. NAWARANGPUR 1. BOLANGIR 1. BALASORE 3. NAYAGARH 3. JAJPUR 3. JHARSUGUDA 3. GAJAPATI 3. MALKANAGIRI 2. MECH., 2. NUAPADA 2. BARIPADA 4. DHENKANAL 4. JAGATSINGHPUR 4. SUNDARGARH 4. KANDHAMAL 4.RAYAGADA SAMBALPUR 3. BHAWANIPATNA 3. RAIRANJGPUR 5. ANGUL at 5. ATHAGARAH 5. ROURKELA 4. SONEPUR 4.KEONJHAR 6. DEOGARH 5. BOUDH 5.BHADRAK 6. PROJ. 6.ANANDPAUR DIVISION

Outcome Budget: DoRD for 2014-15 Page 5

Funding The activities of the DoRD are supported by financial outlays in the Plan and Non-Plan Budget of the State Govt.Besides the grants received from the Central Govt through Ministry of Rural Development for implementation of National Rural Drinking Water project on the sharing basis 50:50 in Coverage,Operation & Maintainence and Water Quality programme.Further Govt. of India have provided 100% funds for implementation of Pradhan Mantri Gram Sadak Yojana for construction of all-weather connectivity to all unconnected habitations in rural area of the State having more than or equal to The existing PMGSY scheme aims for providing connectivity to the unconnected habitations of500 + population in general area and 250 + population in 18 IAP districts & upto 100+ population in 38 LWE blocks. The funds were previously released by the Govt. of India under PMGSYand NRDWPnot routed through state Govt. Budget and the same is directly released to the implementing agency i.e.OSRRA(Odisha State Rural Road Agency). This year the Govt. of India has decided to root the fund under State Plan of the State Govt. In order to address the Rural Sanitation needs through community empowerment, the centrally sponsored “Nirmal Bharat Abhiyan"(NBA) previously known as "Total Sanitation Campaign"(TSC) is being implemented in all the 30 districts of the State. Government of India directly releases funds to the Odisha State Water & Sanitation Mission (OSWSM)without being routed through State Govt. budget and the State Govt. releases funds as matching state share to the missions after making appropriate provision in the state budget. The entire operation under this campaign is being looked after by the OSWSM of RD Department and the District Water and Sanitation Missions. The Demand as reported in iOTMS is as follows: (` in TRS)

Scheme Chart of Account Budget 2014-15 1. NRDWP 28-2215-01-102-2477-37285 2644680 28-2215-01-789-2477-37285 749326 28-2215-01-796-2477-37285 1013794 SUB- TOTAL 4407800 2. NBA 28-2215-02-105-2940-41417-918 600000 28-2215-02-789-2940-41417-918 170000 28-2215-02-796-2940-41417-918 230000 SUB -TOTAL 1000000 3. Off.BUILDINGS 28-4059-01-051-2148-37114 108000 28-4059-01-789-2148-37114 30600 28-4059-01-796-2148-37114 41400 SUB -TOTAL 180000

Outcome Budget: DoRD for 2014-15 Page 6

4. RES. BUILDINGS 28-4216-01-106-2148-37114 108000 28-4216-01-789-2148-37114 30600 28-4216-01-796-2148-37114 41400 SUB -TOTAL 180000 5. Rural Water Supply 28-4215-01-102-0007-37182 300000 28-4215-01-789-0007-37182 85000 28-4215-01-796-0007-37182 115000 SUB -TOTAL 500000 6. RIDF 28-4215-01-102-2161-37182 60000 28-4215-01-789-2161-37182 17000 28-4215-01-796-2161-37182 23000 SUB- TOTAL 100000 Completion of 7. incomp. R&B 28-5054-04-800-1230-37158 420000 28-5054-80-789-1230-37158 119000 28-5054-80-796-1230-37158 161000 SUB- TOTAL 700000 8. INCENTIVE 28-5054-04-800-1230-78218 5000 Imp. of existing RD 9. ROAD 28-5054-04-800-1230-37247 342000 28-5054-80-789-1230-37247 96900 28-5054-80-796-1230-37247 131100 SUB- TOTAL 570000 10. B S Y 28-5054-04-800-1230-37257 978000 28-5054-80-789-1230-37257 277100 28-5054-80-796-1230-37257 374900 SUB -TOTAL 1630000 Dev. of Rural Road 11. Connectivity 28-5054-04-800-1230-37287 6000 28-5054-80-789-1230-37287 1700 28-5054-80-796-1230-37287 2300 SUB -TOTAL 10000 12. One time ACA 28-5054-04-800-2006-37107 420000 28-5054-80-789-2006-37107 119000 28-5054-80-796-2006-37107 161000 SUB- TOTAL 700000 CAPACITY 13. BUILDING 28-5054-04-800-2604-37180 80000 14. PMGSY 28-5054-04-337-1077-37114 18000001 15. RIDF 28-5054-04-789-2161-37107 697000 28-5054-04-796-2161-37107 943000 28-5054-04-800-2161-37107 2460000 SUB -TOTAL 4100000

Outcome Budget: DoRD for 2014-15 Page 7

16. MMSY 28-5054-04-789-2161-37286-119 255000 28-5054-04-796-2161-37286-119 345000 28-5054-04-800-2161-37286-119 900000 SUB- TOTAL 1500000 17. CWA 28-5054-04-789-0906-37107 48280 28-5054-04-796-0906-37107 65320 28-5054-04-800-0906-37107 170400 SUB- TOTAL 284000 18. SCA for KBK 28-5054-04-789-2526-37107 144500 28-5054-04-796-2526-37107 195500 28-5054-04-800-2526-37107 510000 SUB -TOTAL 850000 19. LAND ACQ 28-5054-04-800-2373-37105 5000 20. DECRETAL DUES 28-5054-04-800-2373-14001 5000 28-5054-04-101-1230-37281 264000 21. Construction of Bailey 28-5054-04-789-1230-37281 74800 Bridges 28-5054-04-796-1230-37281 101200

The details are as follows:

A. STATE PLAN

(i) R.W Organisation

A total outlay of `291290.01 lakh has been proposed under the roads & bridge sector/building sector of Rural Works Organisation Schemes to be implemented as follows.

1) Construction ofNon-Residential Buildings of R.W. Organisation. (`1300.00 lakh) A sum of `1300.00 lakh has been proposed for the year 2014-15 for construction of office building for different office of Rural Development Department.

2) Construction of Residential Buildings of R.W. Organisation (`1200.00lakh) A sum of `1200.00 lakhs has been proposed for construction of residential building under Rural Development Department for the year 2014-15.

3) Rural Roads and Bridges (NABARD Assisted Project) (`41000.00 lakh) A sum of `41000.00 lakh has been proposed in the year 2014-15 for completion of 46 bridges & 13 roads under NABARD scheme.

4) Road Works (PMGSY) (`180000.01 lakh) A sum of `180000.01 lakhs has been proposed for construction of roads & bridges. There is a Central Share of Rs.170000.00 lakh under the above scheme & State’s share of Rs.10000.00 lakh towards State share of construction of bridges, tender premium & labour escalation etc. for the year 2014-15.

5) CWA (Constituency Wise Allotment) (`2840.00 lakh) `20.00 lakh has been provided for each Assembly constituency (except five urban constituencies) in the budget for the year 2014-15 for improvement of Rural Roads.

Outcome Budget: DoRD for 2014-15 Page 8

6) Completion of incomplete roads & bridges under different tranches of R.I.D.F & Other Schemes. (`7000.00 lakh) A sum of `7000.00 lakh has been proposed for completion of incomplete roads and bridges under different trenches of RIDF & other schemes for the year 2014-15.

7) Capacity Building(Resource & Infrastructure Development) (`800.00 lakh) A sum of`800.00 lakh has been proposed under capacity building for Survey Expenses,Survey Equipment, Tech. Training,Consultancy charges-PMU & Quality Monitoring important roads, bridges & building projects, DPR preparation, Computerisation of offices, WAMIS,GIS exposure visit inside/outside country etc.for the year 2014-15. 8) Land acquisition charges (`50.00 lakh) A sum of `50.00 lakh has been proposed for the year 2014-15 towards land acquisition for different rural roads and bridges.

9) Decretal dues (`50.00 lakh) After settlement of the court cases, Govt. needs to pay decretal dues as and when necessary Provision of `50.00 lakh has been proposed for the year 2014-15. 10) Biju Setu Yojana (`16300.00 lakh) `16300.00 lakh has been proposed for construction of bridges on rural roads under Biju Setu Yojana during 2014-15. 11) One time ACA. (`7000.00 lakh) There is a budget provision of `7000.00 lakh during 2014-15 for improvement of RD roads connecting important tourist places and economic importance. 12) Improvement of existing RD roads. (`5700.00 lakh) There is a provision of `5700.00 lakhs for improvement of existing R.D. Roads. during 2014-15. 13) Incentive for early completion of Major Projects. (`50.00 lakh) There is a proposal of of `50.00 lakhs towards incentive to contractors for early completion of Major Projects during 2014-15. 14) Special Programme for KBK dist. (SCA). (`8500.00 lakh) There is a proposal of `8500.00 lakhs for improvement of road in KBK dist during 2014-15. 15) Construction of Bailey Bridges. (`4400.00 lakh) There is a proposal of of `4400.00 lakhs for construction of 103 nos of Bailey Bridges in inaccessible areas IAP districts during 2014-15. 16) Mukhya Mantri Sadak Yojana. (`15000.00 lakh) There is a proposal of `15000.00 lakhs for improvement of important RD roads during 2014-15. This is new scheme introduced for construction/improvement of rural roads. The modalities of the scheme is being finalized. 17) Development of Rural road connectivity. (`100.00 lakh) There is a proposal of `100.00 lakhs for development of rural road connectivity during 2014-15.This is new scheme introduced for construction/improvement of rural roads. The modalities of the scheme is being finalized

Outcome Budget: DoRD for 2014-15 Page 9

(ii) Rural Water Supply The availability of safe drinking water is an important role in the health and wellbeing of the people. Rural Development Department is the nodal department for providing safe drinking water in rural population.

1. NRDWP (SP: `44078.00 lakh) The rural water supply and sanitation organisation is functioning under the Rural Development Department primarily aims at providing safe drinking water to the rural people of the state. From the year 2009-10, rural water supply is carried out as per the new guideline of GOI i.e. National Rural Drinking Water Programme (NRDWP). The goal of the programme is to provide every rural person with adequate water for drinking, cooking and other domestic basic needs on a sustainable basis. There is a paradigm shift in coverage from habitation to household. To meet the emerging challenges in the rural drinking water sector relating to availability of sustainable and qualitative drinking water supply, the components covered under the program are NRDWP-Coverage, Sustainability, Water quality, operation & maintenance and Support activities. The proposed fund includes provision to address water quality related issues in the fluoride affected districts particularly Nuapada. To meet the above needs, an amount of Rs.44078.00 lakhs under State Plan in the Budget for the year 2014-15 is available against anticipated GoI allocation of Rs.22000.00. Target has been fixed to take up 2845 PWS schemes (2296 PWS under coverage, 549 PWS under water quality) and 30000 spot sources under coverage during the year-2014-15. 2. Capacity Building: (SP: `700.00 lakh) An amount of Rs.700.00 lakh is available in the Budget for capacity building. The scope of the works include survey & investigation, Source finding and preparation of detailed project reports for new rural PWS Schemes, Procurement of Survey Equipments, training, Exposure visit inside and outside India, consultancy charges, PMU establishment charges, quality monitoring, computerisation, WAMIS & GIS etc. 3. Construction of Non-residencital Buildings of RWSS Org. (SP: `500.00 lakh) A sum of Rs.500.00 lakh is available for the year 2014-15 for construction of newly created Non-Residential Buildings of RWSS Organisation and Govt residential buildings for RWSS staffs. 4. Construction of Residencital Buildings of RWSS Org. (SP: `600.00 lakh) A sum of Rs.600.00 lakh is available for the year 2014-15 for construction of newly created Residential Buildings of RWSS Organisation and Govt residential buildings for RWSS staffs. 5. Rural Water Supply (SP: `5000.00 lakh) A sum of Rs.5000.00Lakh has been allocated under state Plan to cover PWS projects as well as spot sources in villages and habitations where it is not possible to cover those locations under NRDWP. State specific projects can be taken up to meet the demand of public on priority basis. 6. RIDF: (SP: Rs.1000.00 lakh) As a long term sustainable measure, to mitigate the presence of Fluoride and Chloride in drinking water in the district of Nuapada and Puri , 7 Number of PWS projects taking reservoirs / rivers as drinking water sources in and one Mega PWS Scheme in have been proposed under RIDF assistance . Similarly 2 numbers of Aug. Schemes in Bolangir district are also proposed under RIDF. Hence total ten numbers of schemes are under RIDF assistance at an estimated cost of Rs.200.22Crores.

Outcome Budget: DoRD for 2014-15 Page 10

The work for PWS to 59 villages of Bramhagiri Block in the district of Puri has already been started while seven schemes in Nuapada district are under process for preparation of DPR (iii) Rural Sanitation. S.S.`4000.00 lakh C.S.`6000.00 lakh In order to address the rural sanitation needs through community empowerment, the centrally sponsored Nrmal Bharat Abhiyan (NBA) previously known as Total Sanitation Campaign(TSC) is being implemented in all the 30 districts of the State. The entire operation under this campaign is being looked after by “Orissa State Water & Sanitation Mission (OSWSM)” of RD Department and the District Water and Sanitation Missions (DWSMs). In the Annual Plan for the year 2014-15an amount of`6000.00 lakh towards Central share and `4000.00 lakh has been proposed as State Share. B. NON- PLAN (I) RURAL WORKS ORGANISATON:

A total outlay amounting to `101209.70 lakh has been proposed under Non-Plan grant in Rural Works Organization during 2014-15. Finance Commission Award Under 13th Finance Commission Award, provision of `4376.57 lakh for PMGSY roads and `9237.87lakh for R.D. roads has been provided for maintenance of R.D. roads and 5 year completed PMGSY roads respectively. Maintenance of Roads and Bridges: `47880.21 lakh has been proposed for repair, maintenance, improvement, widening of R.D. roads and bridges during 2014-15.

Maintenance of Rural Buildings: `23677.66 lakh has been proposed during 2014-15 maintenance of residential and non-residential buildings including `3400.00 lakh for maintenance of 30 years old and `100.00 lakh for maintenance of 50 years old High School Buildings borne in the books of R.D. Department.

(II) RURAL WATER SUPPLY AND SANITATION:  Office Building - Maintenance of Water Supply and Sanitary installations - ` 510.87 Lakh  Direction and Administration - ` 4567.18 lakh  Machinery and Equipment - ` 1222.89 lakh  RWSS M & R, WagesWork Charged Salaries etc. - ` 5133.18 lakh  Suspense - ` 0.01 lakh  Other Expenses - ` 5.25 lakh  Sanitary Technitians' Training - ` 7.30 lakh  Res. Bld.- Maintenance of Water Supply and Sanitary installations - ` 309.55 Lakh  Apprenticeship Taining - ` 9.00 lakh Total - `11765.23 lakh

(III)SECRETARIAT ESTABLISHMENT - `582.23LAKH

Outcome Budget: DoRD for 2014-15 Page 11

2. RURAL DRINKING WATER SUPPLY (R.W.S & S Organization)

The role of drinking water for individual's survival, reducing illness, enhancing economic growth and improving peoples’ quality of life has acquired prominence in the process of the development agenda in recent years. The 10th Plan accorded topmost priority to provisionof stipulated quantity of safe drinking water to "Not Covered" (NC) habitations, followed by coverage of “Partially Covered” (PC) and the quality affected habitations (having contaminated water). In previous years, the habitations were mostly covered by installation of hand pump tube wells and sanitary wells. But it is found that these sources do not attend to the desired level of sustainability. Hence it is decided that desired goal can be achieved by providing water to rural habitations through Piped Water Supply (PWS) schemes. The State Government has a clear mandate to cover all uncovered rural habitations and Government & Government aided schools. As on 31.3.14, there are 1, 57,296 habitations (102110-FC+48466-PC+6564-WQ) have been provided with drinking water facility through 3,80,469 spot sources (hand pump Tube Well and Sanitary Wells) and 9458 Piped Water Supply projects commissioned in the State.

National Rural Drinking Water Programme

National Rural Drinking Water Programme (NRDWP) is being implemented w.e.f. 1.4.2009. Under this programme, provision of drinking water supply to the rural population is made through hand pump tube wells and piped water supply schemes. As per the new guidelines under NRDWP, there has been a shift in approach of coverage which aims at household level water security. The State Government provides a matching share of Central Assistance released for implementation of NRDWP scheme. Under the modified NRDWP programme, the drinking water supply projects are implemented with the following broad components:

 Coverage - Priority has been given to provide safe drinking water to "Not 47% Covered (NC)" habitations followed by coverage of "Partially Covered (PC)" habitations. (matching share 50:50)  Water Quality To provide safe alternative sources of drinking water supply in - 20% quality affected habitations except for capital investment priority has been given for Fluoride affected habitations followed by Iron & salinity problems. (Matching share - 50:50)  Sustainability To encourage community participation for sustainability of water (Swajaladhara supply sources and systems, these schemes are implemented in mode) - 10% broad Swajaladhara principle. (No matching share is required from State but contribution from village community is the essence.)

Outcome Budget: DoRD for 2014-15 Page 12

 Support Communication and capacity development (CCDU), activities - Management Information System (MIS) and Computerisation are 5% to be taken up on priority.

 Water quality Services of Asha, Angawandi workers, School Teachers, GP Monitoring & members, Social workers etc. will continue to be utilized for Surveillance – Surveillance programme. Monitoring is to be done by entering 3% the test result of all sources tested by the Labs. The habitation and household data must be collected by two village level members i.e. VWSC members selected in the Gram Sabha and fully accountable to the Panchayat. They will also authenticate the test results of field test kits used in the village.

 Operation and Government of India has provided 15% of funds to the State Maintenance - Govt. for operation and maintenance of existing rural water 15% supply system. (matching State share - 50:50)

Rural Water Quality Monitoring and Surveillance

Govt. has made significant interventions to improve the availability of drinking water in rural areas. Activities relating to water quality were limited to testing of water sources at the time of commissioning the PWS projects and provision of alternative water supply through sub-mission projects for areas where occurrence of Fluoride, salinity and Iron in ground water is beyond the permissible limit. The above programme would be implemented at three levels consisting of the State level, District level and grass root level.

 Water Quality Problem Mitigation

 As a long term sustainable measure 21 PWS projects taking reservoir / river as drinking water sources have been proposed at an estimated cost of `265.09 Crores.Now 21 Schemes have been reduced to 16covering equal number of habitations as before due to merger of several schemes by adopting gravity flow wherever possible.  Out of the above, 4 Projects ( Nuamalpada, Amodi, Koligaon, and Thelkodungri), at an estimated cost of `20.32 Crores are taken up under NRDWP.  Out of the above, the Nuamalapada and Amodi PWS Projects sanctioned are under progress. For Koligaon & Thelkodungri, sources have been completed and tender for balance work is in process.  Out of remaining 12 projects, the following 6 projects (Pipalchandi, Patara, Khalipani, Ichhapur, Krishan, and Dharanimal & Palasad) at an approximate cost of `178.02 Crores are proposed to be taken up in phased manner with assistance of RIDF (NABARD) for which action is being taken for preparation of DPR.  Tender for consultancy service for balance 6 projects such as (1) Gudvella,Ranipur Chandel,Dhanksar & Bhaludunguri, (2) Kusumjore (3) Khalna,(4) Chota darlipada (5) Litiguda (6) Bergaon are under progress so as to prepare DPR.

Outcome Budget: DoRD for 2014-15 Page 13

3. ODISHA STATE WATER & SANITATION MISSION (OSWSM)

Nirmal Bharat Abhiyan (NBA)

Total Sanitation Campaign (TSC) was launched as a Millennium Development Goal by Govt. of India in December 1999. The campaign views the sanitation problem holistically and looks at important tools and approaches that create demand for sanitation. It is an initiative to eradicate the age old practice of open defecation in country side. Encouraged by the success of Nirmal Gram Puraskar in different parts of the Country, Govt. of India has renamed TSC as Nirmal Bharat Abhiyan (NBA) with effect from 1st April, 2012. This initiative is unique for its vision of comprehensive sanitation coverage of entire rural community, all rural schools, anganwadies and public institutions through saturation approach latest by 2022 or earlier. The benefit under NBA is extended to IAPL (Identified APLs) covering all SC/STs, small and marginal farmers, landless labourers with homestead land, differently abled and women headed households along with all BPL households.

The unit cost of household toilets has been increased from `625/- (1999) to `5500/- (2012-13) out of which Government of India provides `3200/- towards its share along with state matching share of `1400/-. The beneficiary contribution for IHL is `900/- in shape of cash/kind/labour.IHHL construction cost under NBA has been raised to `10000/- in convergence with MGNREGS under which `4500/- is available through convergence with Panchayati Raj Department. The unit cost of toilets in Anganwadi Centre has also been revised from `5000/- to `8000/- (`5600/- GoI + `2400/- GoO) and School toilet from `20000/- to `35000/- (`24500/- GoI + `10500/- GoO) w.e.f. June 2010.

Objective:

 To Improve general quality of life in the rural areas by improving health & hygiene, ensuring economic development and over all environmental sanitation enhancing individual & collective self esteem and restoration human dignity.  Women and children are the key stakeholders of the programme integrating the entire village for development through active participation of each and every family in promotion of sanitation.  Involvement of PR Institutions in promotion of sustainable sanitation facilities is the focal point.  School and AWC toilets are an integral part of NBA expected to be completed by March 2013.

Outcome Budget: DoRD for 2014-15 Page 14

 Community managed environmental sanitation with solid & liquid waste management.

Rural Sanitation & Funding:

In order to address the Rural Sanitary needs through community empowerment, the centrally sponsored “Nirmal Bharat Abhiyan” (NBA) is being implemented in all the 30 districts of the State. Government of India directly releases funds to the State Mission without being routed through State Budget and the State Government releases funds as Matching State Share to the District Water & Sanitation Missions after making appropriate provision in the State Budget. This year the Govt. of India has decided to root the fund under State Plan of the State Govt. The entire operation under this campaign is being looked after by “Odisha State Water & Sanitation Mission” (OSWSM) of R.D. Department and the “District Water & Sanitation Missions” (DWSMs). State Government has made a budget provision of `5599.00 lakh towards matching State Share for the year 2013-14. In the Annual Plan for the year 2014-15 an amount of `4000.00 lakh has been proposed as Matching State Share.

Nirmal Gram Puraskar

In order to achieve desirable impact in disease prevention as well as for ensuring minimum standard of living to the entire rural population, it is essential that every household in any particular area has access to sanitation facilities and also to adopt hygienic practices. To promote such full coverage as well as to ensure total stoppage of the practice of open defecation and to maintain cleanliness, the Govt. of India have launched the Nirmal Gram Puraskar (NGP) from October, 2003. The NGP is awarded to Gram Panchayat, Block and Districts where there is no open defecation, access of toilets in all households as well as institutions like Schools, Anganwadi centers etc. So far 284 Gram Panchayats of the State have been bestowed with Nirmal Gram Puraskar at national level. During the year 2013 State has submitted proposals of 32 G.Ps to GoI with recommendation for consideration of NGP Award.

Outcome Budget: DoRD for 2014-15 Page 15

CHAPTER-II

Outcome Budget for 2014-15

The exercise is primarily meant for converting financial outlays into measurable and monitorable outcome. It is a performance measurement tool that helps in better service delivery, decision making, evaluating programme performance and results and improving programme effectiveness.

The Outcome Budget is also aimed at changing the outlook of the agencies entrusted with the responsibility of programme execution and implementation. The idea is to make the programme implementing agencies more result oriented by shifting the focus from “Outlays” to “Outcomes”.

It is a performance measurement tool that helps in better service delivery, decision– making, evaluating programme performance and results, communicating programme goals and improving program effectiveness.

The scheme-wise details, wherever necessary of the Outcome Budget for 2014-15 are indicated in the attached statement.

Outcome Budget: DoRD for 2014-15 Page 16

Success Story

Koraput village sets hygiene example ------Satyanarayan Pattnaik, TNN | 2013-03-02 KORAPUT: Marking a social success for others to emulate, a village in has become totally free of open defecation with each of its 45 families constructing toilets in their homes.Since the past two years, around 220 tribal villagers of the non-descript Bondaguda village under Similiguda block in the district have been using toilets after the village committee banned open defecation. "All the 45 Kandh families have toilets of their own now. There is strict prohibition of open defecation in the village," said Naranga Pujari, president of Bondaguda Mahila Mandal

Nestled at the foothills of hill with numerous streams nourishing its lush farmlands, the village situated at a distance of about 45 km from here, has shown a marked decrease in the incidence of diseases since open defecation stopped. "Since we started using toilets not a single case of diarrhoea or malaria has been reported at our village," said Juruko Pujari, a village woman.

However, it was not easy to inculcate the toilet culture in the village. It took a series of awareness camps organized by the district administration at the village to make the villagers conscious about the ill-effects of defecating in the open.

"Initially, the tribals were reluctant to construct toilets at their homes but when they were made to realize through steet plays and posters how they were suffering from various diseases like diarrhoea and malaria due to defecating in the open, their mindset gradually changed," said Debasish Patnaik, coordinator of district water and sanitary mission.The tribals were provided training in constructing toilets and ` 2,200 was given by the administration to each of the 31 BPL families of the village to built toilets. "As the rest of the 14 families at our village don't have BPL cards, they were not provided with the fund for constructing toilets. So we pooled all the fund of the 31 families and donated our labour to ensure that all the 45 families get a toilet from the fund meant for 31 families," said Pujari.

The villagers are now motivating people in neighbouring villages of Jhimitiguda, Pipalguda and Dalaiguda to use toilets too. "Bondaguda is the first village of the district which has been declared 'open defecation free'. It has set an example for others to follow. Now we aim to make the entire Similiguda block 'open defecation free' in the next few months," said Koraput collector Sachin Jadhav.The village also boasts of another reform by restricting consumption of liquor to only Fridays and special occasions like pujas and marriages. "The villagers are allowed to consume liquor only on Friday as the haat (weekly market) sits on that day. Moreover, villagers are not allowed to create nuisance after consuming liquor. If anyone is found consuming liquor on any other day and creating disturbance at the village, a fine of `50 is imposed on him," said Sanjeev Sekhar Pujari, a villager. "We have also restricted the use of cigarettes, bidis and chewing tobacco at the village," he added.

Continuing on the progressive path, the villagers have started yet another praiseworthy practice of collecting `5 each month, which go towards creating a common fund pool to be used in times of emergency like taking a patient to the hospital, purchasing medicines, etc. "A village meeting is held once a month, attended by at least one member from each family. All community decisions are taken at the meeting," said Kosai Pujari, another villager.

Outcome Budget: DoRD for 2014-15 Page 17

STATE PLAN (2014-15)

Rural Water Supply & Sanitation ` in TRS Name of the Sl. Financial Outlay Broad Quantifiable/Deliverable Processes/ Remarks/Ris Schemes/Pr Project Outcome No objective Physical Outputs Timelines k Factors ogramme 1 2 3 4 5 6 7 8 National 2200000-State Share Rural Availability of safe drinking Availability of of NRDWP, Drinking water / Coverage of 11000 potential 100000 – RIDF – Providing safe Supply of potable drinking Water rural habitations, through Source with 1 Rural Water Supply drinking water water to the rural population of 12 months Programme 30000 spot sources & 1300 quality water, to rural public the State. (NRDWP) PWS Schemes & 1000 Solar electricity and 2207800–(Anticipated and Sate Powered PWS Schemes Govt. land. Central Share) Plan Providing safe Rural Water Supply of potable drinking drinking 2 Supply 500000 water to the rural population of 12 months water to rural the State. public Survey & Investigation Provide training to Officials, State Plan – Development work including Source establishment of PMUs, 3 Capacity 70000 human finding of 1254 PWS Technological advancement, 12 months Building resources schemes proposed to be survey expences, preparation taken up in 2014-15 of DPRs Better Construction and completion State Plan – Construction of new and working of Departmental Office Building ongoing office/res. bld for conditions Building and Residential 4 Programme 110000 RWSS organisation. And 12 months and living Building (Including `1.00 (Both Res. & instalment of PH infrastrucutre condition for crore for Improvement of Non-Res) in RWS&S buildings. the officials. IGTC Palasuni) 2980000 (State Plan) 2980000 Total Social 2207800 (NRDWP- (State Plan) Services Central Share) 2207800 Sector (NRDWP-Central Share)

Outcome Budget: DoRD for 2014-15 Page 18

STATE PLAN (2014-15) RURAL WORKS ORGANISATION(` in TRS) Broad objective Quantifiable/ Processes/ Sl. Name of the Schemes/ Financial Remarks/Risk Deliverable Project Outcome Timelines No Programme Outlay Factors Physical Outputs 1 2 3 4 5 6 7 8

Construction of new Better working Construction of Non- 228 new Res. and ongoing office condition and living Residential and Residential Buildings and Availability of Land, building and condition for the 1 buildings of R.D. 250000 114 Non-Res. 12 months Non response residential buildings officials working in Department Buildings. tenders of Rural R.D. Rural Works

Department Organizations. Survey Expenses,Survey Equipment, Tech. Training,Consultancy Survey and charges-PMU & Quality investigation & Capacity Building Monitoring important conducting (Resources & Infrastructure roads, bridges & technical seminars, 2 80000 building, DPR Not quantifiable 12months - Development) preparation, workshops, Computerisation of procurement of offices, WAMIS,GIS modern survey exposure visit equipments inside/outside country etc. Improve critical 12 months Minimum Needs All-weather roads to Rural roads in 142 The proposals are roads in the rural Implemented through Programme-Constituency- rural habitations in Assembly furnished by Hon'ble 3 284000 area for better Chief Engineer RW-I Wise allocation (CWA) 142 constituencies of Constituency in the MLAs, connectivity to the and field the State. State rural habitations functionaries. Construction of Bridges Through tender. Land acquisition Construction of Completion of149 To improve rural 4 under Biju Setu Yojana 1630000 9 months to difficult site in bridges on rural roads bridges connectivity 30 months certain parts Improvement of existing To improve rural Completion of 42 Improvement of 5 570000 12 months R.D roads connectivity nos of RD roads riding quality Outcome Budget: DoRD for 2014-15 Page 19

Broad objective Quantifiable/ Processes/ Timelines Sl. Name of the Schemes/ Financial Remarks/Risk Deliverable Project Outcome No Programme Outlay Factors Physical Outputs 1 2 3 4 5 6 7 8 Completion of incomplete 12 months Time consuming roads & bridges under Completion of Implemented through To Improve rural tender process. 6 different tranches of RIDF 700000 incomplete roads and 100 km. roads Chief Engineer RW-I connectivity & other schemes bridges and field

functionaries. Limited no. of To improve rural Rural Infrastructure Completion of 46 Bridge contractors To Improve road connectivity 11 months to 7 Development Fund 4100000 Bridges &13 road in the State, & infrastructure 30 months projects delay in land

acquisition. Construction of PMGSY Roads & To implement Bridges,State share Construction of PMGSY Schemes Large number of non Road Work (PMGSY) 8 18000001 for constn of 4500 kms of roads in the Sate for - response tender

bridges,Tender & bridges better rural Premimum, Labour connectivity. Escalationetc. To improve rural One time ACA roads having tourism Completion of 40 Improving riding 9 700000 12 months - and economic nos of road projects. quality of roads importance Completion of projects ahead of - Incentive to the Contractors Timely completion of 10 5000 - scheduled time to - projects prevent time and cost over run. To clear the liability - of contractors as per Payment of decretal dues 12 5000 Court disposal - - -

Outcome Budget: DoRD for 2014-15 Page 20

Broad objective Quantifiable/ Processes/ Timelines Sl. Name of the Schemes/ Financial Remarks/Risk Deliverable Project Outcome No Programme Outlay Factors Physical Outputs 1 2 3 4 5 6 7 8 To facilitate acquisition of Land acquisition charges Completion of - 13 5000 - private land - projects in time required for road & bridge projects

Special Programme for Impvt. of Rural Completion of 90 Improving riding 14 850000 KBK dists. Roads in KBK dist. nos of roads quality of roads 12 months

New scheme Mukhya Mantri Sadak Impvt. of important ------introduced& the 15 1500000 Yojana Rural Roads modalities of the scheme are being finalized. New scheme introduced& the Development of rural Development of 16 10000 - - - modalities of the road connectivity rural roads scheme are being finalized. - Construction of To improve rural Completion of 54 Construction of Bailey bailey bridges connectivity. 17 440000 nos of Bailey - Bridges inaccessible area of bridges IAP dist.

Outcome Budget: DoRD for 2014-15 Page 21

Work list under D.No.28-4059-COL on Public works-SP-DS-01-Office buildings-051-Constn/789-SCP for SC/796-TASP-2148-Constn of buildings of R.D.Deptt.-37114-Public worksfor the year 2014-15

Sl. Name of Scheme / Project / Work District in Financial No. which outlay implemented (in TRS) (including Normal,SCP & TASP) 1 2 3 4 051-Construction 1 J.E. R.W. Section-II Office building at Angul Angul 489 2 J.E. R.W.( P.H) Office building at Angul Angul 368 3 R.W. Rest shed at Boinda Angul 35 4 R.W. Circle office building, Balasore Balasore 50 5 R.W.S.S. Section office at Simulia Balasore 310 6 R.W. Section-II at Khaira Balasore 57 7 R.W. Rest shed at Bhogarai Balasore 468 Construction of R.W. Section office-II at 8 Bargarh 500 Bheden Construction of R.W. Section office-II at 9 Bargarh 500 Barpalli 10 Renovation of R.W. Division office at Bargarh Bargarh 700 11 Constn. of R.W. (P.H.) Section, Bargarh Bargarh 15 Constn. of R.W.Sub Division office-II at 12 Bargarh 320 Bargarh 13 Section -II at Barapali Bargarh 300 14 R.W. Sub division-I office at Baragarh Bargarh 13 15 Constn. of R.W. Section-I office at Bargarh Bargarh 14 16 Constn. of R.W. Section-II office at Bargarh Bargarh 20 17 Renovation of division office Padampur Bargarh 360 Renovation of R.W. Division office at 18 Bargarh 1200 Padampur 19 Constn. of R.W. Section office I & II at Bijapur Bargarh 1200 Constn. of R.W. Sub Division office at 20 Bargarh 700 Padampur 21 R.W. Section Office, Bodak, Tihidi Bhadrak 360 22 R.W. Section office at Pirahat Bhadrak 150 R.W. Sub-Division & Section office at Bonth 23 Bhadrak 100 (Renovation work) 24 R.W. Sub Division, Bhadrak Bhadrak 30 25 R.W. Section office, Tihidi Bhadrak 30 26 R.W. Section office at Dhusuri Bhadrak 407 27 R.W. Section Office at Asurali Bhadrak 195 Renovation of R.W. Division office, 28 Bhadrak 122 Bhadrak-II Outcome Budget: DoRD for 2014-15 Page 22

Renovation of R.W. Sub-Division office, 29 Bhadrak 198 Bhandaripokhari Renovation of R.W. Section office, 30 Bhadrak 185 Bhandaripokhari 31 Construction of R.W. Section Office at Saintala Bolangir 500 Conference hall at R.W. Division office, 32 Bolangir 700 Bolangir 33 Renovation of R.W. Sub-Division, Saintala Bolangir 600 34 Renovation of R.W. Sub-Division, Patnagarh Bolangir 600 35 Renovation of R.W. Division office at Bolangir 621 36 Renovation of R.W. Circle office at Balangir Bolangir 424 Renovation of R.W. Sub Division office at 37 Bolangir 550 Titilagarh 38 Const. Of R.W. Section office at Bangomunda Bolangir 310 Renovation of R.W. Sub Division office 39 Bolangir 118 building at Kantabhanji 40 R.W.S.S. Sub-Division office at Bolangir 190 Extension & renovation of R.W. Section 41 Boudh 400 office,Charichhaka Renovation to old R.W. Sub-Division & 42 Boudh 500 Section office at Boudh Renovation to R.W. Division Office at Boudh 43 Boudh 700 (Conference hall) J.E. R.W. Section Office building at 44 Boudh 522 Manmunda-II 45 R.W.S.S. Sub-Division office at Boudh Boudh 269 46 Renovation of R.W. Section office, Odaspur Cuttack 500 47 Conference hall at R.W. S.E. office, Cuttack Cuttack 700 Constn. of R.W.Section office building at 48 Cuttack 500 Kishannagar 49 Construction of laboratory hall at Cuttack Cuttack 600 50 Constn. of R.W. (P.H.) Sub-Division, Cuttack Cuttack 600 51 Constn. of R.W. (P.H.) Section, Cuttack Cuttack 500 Constn. of Cycle stand at R.W. Division office, 52 Cuttack 200 Cuttack 53 R.W. Elect. Sub -Division office, Cuttack Cuttack 500 54 R.W. Elect. Section office, Cuttack Cuttack 350 55 R.W. Section Office Nemalo Cuttack 200 56 R.W. Section Office Salipur-II Cuttack 460 57 R.W. Circle office at Cuttack Cuttack 400 58 R.W. Section office at Krishnanagar Cuttack 270 59 Construction of R.W. Section at Kalapathar Cuttack 500 60 Construction of R.W. Section at Kanpur Cuttack 500 61 Construction of R.W. Section at Baranga Cuttack 500 62 Construction of R.W. Section at Gurudijhatia Cuttack 500 Extension of R.W. Division office building, 63 Cuttack 1000 Cuttack-II

Outcome Budget: DoRD for 2014-15 Page 23

Extension & renovation of R.W. Sub Division 64 Deogarh 700 office, Deogarh R.W. Section -II office at , 65 Dhenkanal 100 Mahaviroad 66 R.W.Section office at Mohana Gajapati 252 67 R.W.Section-II office at R.Udayagi Gajapati 63 68 R.W. Section office at Jeerango Gajapati 389 69 R.W.S.S. Section office at Mohana Gajapati 358 70 R.W. Section office at Gumma Gajapati 171 71 R.W. Section office at Khandava Gajapati 262 72 R.W.Division office at Bhanjanagar Ganjam 1100 73 R.W.Sub-Division office at Bellaguntha Ganjam 700 74 R.W. Section office at Ganjam 210 75 R.W. Rest shed at Bhanjanagar Ganjam 202 76 R.W. Rest shed at Soroda Ganjam 147 77 R.W. Section office at Beguniapada Ganjam 83 Renovation of R.W. Sub-Division office at 78 Ganjam 700 Hinjili R.W. Division-II Ganjam & Circle office at 79 Ganjam 244 Berhampur (Renovation) 80 R.W.S.S. Section office at Sanakhemundi Ganjam 290 81 R.W. Section office at Gopalpur Ganjam 200 Construction of R.W. Section office at 82 Jagatsinghpur 600 Naugaon Constn. of R.W. Section office at Balikuda 83 Jagatsinghpur 600 (Extension) 84 R.W. Section office at Manijanga Jagatsinghpur 407 85 R.W. Sub Division office at Jagatsinghpur Jagatsinghpur 316 86 R.W.S.S. Division office at Jagatsinghpur Jagatsinghpur 1135 87 R.W. Section office at Paradeepgarh Jagatsinghpur 26 88 R.W. Division office at Jajpur Jajpur 700 89 R.W. Sub-Division office Jajpur Jajpur 100 90 R.W. Section Office-I & II at Jajpur Jajpur 134 91 R.W. Rest shed at Jharsuguda Jharsuguda 218 92 R.W. Section, Jharsuguda Jharsuguda 34 Construction of R.W. Circle office at 93 Kalahandi 1200 Bhawanipatna 94 R.W. Section Office building at Junagarh Kalahandi 233 R.W. Division office at Bhawanipatna 95 Kalahandi 450 (Improvement & Extension) 96 RW (PH) Section, Bhawanipatna Kalahandi 72 97 R.W. Section Office building at Kalahandi 326 98 R.W. Section - I & II at Bhawanipatna Kalahandi 200 99 R.W.S.S. Section office at Bhawanipatna Kalahandi 89 100 R.W.S.S. Division office at Bhawanipatna Kalahandi 215 101 R.W. Sub Division at Bhawanipatna Kalahandi 119

Outcome Budget: DoRD for 2014-15 Page 24

102 Renovation of R.W. Section office, Kalahandi 600 Extension & renovation of R.W. Sub Division 103 Kalahandi 700 office, Dharmagarh 104 Constn. of R.W. Rest shed at Jaipatna Kalahandi 400 105 Constn. of R.W. Rest shed at Dharmagarh Kalahandi 400 106 Rural Works Division Office at Balliguda Kandhamal 1200 107 Sub-Division office at Kotagarh Kandhamal 700 108 Sub-Division office at Daringibadi Kandhamal 700 109 Constn. of R.W. (P.H.) Sub-Division, Phulbani Kandhamal 700 Construction of R.W. Section office-II, 110 Kendrapara 600 Mahakalpara 111 Construction of R.W. Section office, Ramnagar Kendrapara 600 112 R.W. (PH) Section, Kendrapara-I Kendrapara 216 113 R.W. Section office at Indupur Kendrapara 67 114 R.W. Section Office at Panapentha Kendrapara 226 115 R.W.S.S. Section office at Pattamundei Kendrapara 50 116 Constn. of R.W. (P.H.) Sub-Division, Keonjhar Keonjhar 700 117 Constn. of R.W. (P.H.) Section, Keonjhar Keonjhar 600 118 R.W. Section office, Keonjhar 600 Extension & renovation of R.W. Sub Division 119 Keonjhar 700 office, Constn. of office of Rural 120 Works,Bhubaneswar,Unit- 900 IV,Madhusudannagar Improvement to R.W. Sub-Division office at 121 Khordha 600 Khordha 122 Constn. of R.W. Section-II, Balipatna Khordha 500 Constn. of 4th floor & 5th floor of R.W. 123 Khordha 1800 Division office, Chandrasekharpur, BBSR Constn. of 2nd floor of R.W. Sub-Division-I at 124 Khordha 900 Unit-IX, Bhubaneswar Extension & renovation of R.W. Sub Division 125 Khordha 700 office, Khordha Extension & renovation of R.W. Section office, 126 Khordha 600 Additional floor of E.I.C. Office at Unit- 127 Khordha 800 IV,Madhusudannagar,Bhubaneswar Provision of lift of R.W. Division office at 128 Khordha 750 Chandrashekarpur,Bhubaneswar 129 Renovation of R.W.S.E. Office, Bhubaneswar Khordha 700 Bhubaneswar R.W. Division office at C.S.Pur 130 Khordha 812 (Extension & Renovation) External electrification for C.E. office at Unit- 131 Khordha 450 IV, BBSR 132 R.W. Section Office building at Nayagarh 502 Construction of R.W. Division office at 133 Nayagarh 1100 Nayagarh-II

Outcome Budget: DoRD for 2014-15 Page 25

Construction of R.W. Sub-Division office 134 Nayagarh 750 building at Khandapada Construction of R.W. Sub-Division office 135 Nayagarh 750 building at Ranapur Construction of R.W. Sub-Division office 136 Nayagarh 750 building at Nuagaon Constn. of Conference hall of R.W. Division, 137 Nayagarh 600 Nayagarh 138 R.W. Section Office building at Puri 230 139 R.W. Section Office building at Bangurigaon Puri 214 Renovation of R.W. existing building at 140 Puri 700 Kakatpur 141 Construction of R.W. Division office at Khariar Puri 1400 142 RW (PH) Section, Puri Puri 35 143 R.W. Section office at Satapada Puri 214 144 R.W. Section office at Nuapada Puri 144 145 R.W. Circle office,Building at Sambalpur Sambalpur 382 Const. Of Conference Hall of S.E. Office 146 Sambalpur 750 Sambalpur Constn. Of Section office building at 147 Sambalpur 317 Kesaibahal 148 Constn. Of Section office building at Sambalpur 513 Renovation of division office building at 149 Sambalpur 1300 Sambalpur 150 Construction of R.W. Division office at Sambalpur 1200 151 R.W. Section office at Subarnapur 229 152 R.W. Section-II Ullunda Subarnapur 295 153 R.W.S.S. Section office at Tarava Subarnapur 146 154 R.W.S.S. Section office at Ulunda Subarnapur 211 155 R.W.S.S. Section office at B.M. Pur Subarnapur 249 156 R.W.S.S. Section office at Binika Subarnapur 140 157 R.W.S.S. Section office at Dunguripali Subarnapur 135 158 Construction of R.W. Section office Tarva-II Subarnapur 600 159 Renovation of R.W. Division office, Sonepur Subarnapur 800 160 Renovation of R.W. Sub Division office, B.M. Pur Subarnapur 700 161 Constn. of Circle office bulding at Sundargarh Sundargarh 250 162 R.W.S.S. Section office at Badagaon Sundargarh 25 163 R.W.S.S. Section office at Sundargarh Sundargarh 70 164 R.W. Section-II office at Bargaon Sundargarh 45 165 Consnt. Of Conference hall at Sundargarh Sundargarh 600 166 Const. Of R.W. Section office at Gurundia Sundargarh 147 167 Const. Of R.W. Section office at Sundargarh 147 168 Lump Provision for Ongoing Buildings 1964 Completion of incomplete Buildings (Lump 169 1600 Provision) Total : 78000

Outcome Budget: DoRD for 2014-15 Page 26

789-SCP for SC Renovation of R.W. Sub-Division office at 1 Bolangir 700 Tureikela Construction of R.W. Seciton office at 2 Bolangir 600 Tureikela-I & II Construction of R.W. Seciton office at 3 Bolangir 600 Muribahal Extension & renovation of R.W.Division 4 Bolangir 800 office, Titilagarh 5 R.W.S.S. Sub-Division office at Boudh Boudh 85 R.W. Section -II office at Kamakhyanagar, 6 Dhenkanal 40 Mahaviroad 7 R.W.Section office at Mohana Gajapati 123 R.W. Division office Gajapati at 8 Gajapati 214 (Renovation) 9 R.W. Section office at Jeerango Gajapati 215 10 R.W.S.S. Section office at Mohana Gajapati 194 11 R.W. Section office at Gumma Gajapati 150 12 R.W. Section office at Khandava Gajapati 71 13 R.W.S.S. Section office at Sanakhemundi Ganjam 50 Construction of R.W. Division office at 14 Kalahandi 1300 Construction of R.W. Sub-Division office at 15 Kalahandi 750 Junagarh Construction of R.W. Sub-Division office at 16 Kalahandi 750 Construction of R.W. Sub-Division office at M. 17 Kalahandi 750 Rampur 18 Construction of R.W. Section office at M. Rampur Kalahandi 600 19 R.W. Section Office building at Kalahandi 50 20 R.W. Section Office building at Kalahandi 436 21 R.W. Section Office building at Kalahandi 270 R.W. Division office at Dharmagarh 22 Kalahandi 564 (Improvement & Extension) 23 R.W. Section Office building at Kalahandi 219 24 R.W. Section office at Tumudibandha Kandhamal 222 25 R.W.Section office at Bamunigaon Kandhamal 362 R.W. Sub Division office at Baliguda 26 Kandhamal 247 (Improvement & Renovation) R.W. Section office at Baliguda (Improvement 27 Kandhamal 325 & Extension) 28 R.W. section office at G.Udayagiri Kandhamal 250 29 R.W. Section Office at Bhanda Keonjhar 48 30 R.W. section office at Joda Keonjhar 259 31 R.W. Section office-II at Dasmantpur Koraput 234 Constn. of R.W. (P.H.) Sub-Division, 32 Koraput 700 Sunabeda

Outcome Budget: DoRD for 2014-15 Page 27

Constn. of Conference hall of R.W. Division, 33 Koraput 850 Sunabeda Renovation & extension of R.W. Division, 34 Koraput 850 Sunabeda Renovation & extension of R.W. Sub Division 35 Koraput 700 office, Laxmipur 36 Constn. of R.W. Section office at Narayanpatna Koraput 650 37 Constn. of R.W. Section office at Semeliguda Koraput 650 Constn. of R.W. Laboratory building at 38 Koraput 700 Sunabeda 39 R.W.S.S. Section office at Malkangiri Malkangiri 169 40 R.W. Section office-I at Malkangiri 297 R.W. Sub- Division, Office Building at 41 Malkangiri 400 Kalimela R.W. Section Office building Kalimela-II at 42 Malkangiri 300 Mottu R.W. Section office building Kalimela-I at 43 Malkangiri 300 Kalimela 44 R.W. Section offfice Building Podia at Podia Malkangiri 354 R.W. Section Office building Korukonda at 45 Malkangiri 332 Korukonda R.W. Section Office building at 46 Malkangiri 365 Balimela 47 R.W. Section Office building at Chitrakonda Malkangiri 345 48 R.W. Section office at Khariar Nuapada 50 49 R.W.S.S. Section office at Ulunda Subarnapur 50 50 R.W. (PH) Section at Sundargarh Sundargarh 60 Constn. of R.W. (P.H.) Sub-Division, 51 Sundargarh 700 Sundargarh 52 Constn. of R.W. (P.H.) Section, Sundargarh Sundargarh 600 Constn. of conference hall at R.W. Division, 53 Sundargarh 600 Rourkela 54 Constn. of R.W. Section office at Lathikata Sundargarh 600 Total : 22100 796-TASP 1 R.W. Section Office building at Junagarh Kalahandi 169 2 R.W. Section - I & II at Bhawanipatna Kalahandi 146 3 R.W. Section Office building at Ampani Kalahandi 222 R.W. Section office at Baliguda (Improvement 4 Kandhamal 105 & Extension) 5 R.W. section office at Chakapada Kandhamal 100 6 R.W. section office at Tikabali Kandhamal 227 7 R.W. section office at Turumunga Keonjhar 244 8 R.W. Section office at Keonjhar-II at Dhurpada Keonjhar 350 9 R.W. Circle office at Keonjhar Keonjhar 131 10 R.W. Section office at Banspal Keonjhar 200 11 R.W. Sub Division office at Saharpada Keonjhar 50

Outcome Budget: DoRD for 2014-15 Page 28

12 R.W. Section office-I & II at Jhumpura Keonjhar 60 13 R.W. Section office at Ukhunda Keonjhar 75 14 R.W. Section Office at Bhanda Keonjhar 75 Construction of R.W. Division office at 15 Koraput 1300 Jeypore R.W. Sub Division office at Lamtaput 16 Koraput 110 (Renovation & Extension) 17 R.W. Section office-II at Dasmantpur Koraput 198 Construction of R.W. Sub-Division office at 18 Koraput 700 Construction of R.W. Section office-III at 19 Koraput 600 Kotpad Construction of R.W. Section office-III at 20 Koraput 600 Boriguma Construction of R.W. Sub-Division office at 21 Koraput 700 Boipariguda Construction of R.W. Section office-III at 22 Koraput 600 Boipariguda Construction of R.W.Sub-Division office at 23 Koraput 700 Dasmantapur Construction of R.W. Section office-III at 24 Koraput 600 Dasmantapur Construction of R.W. Section office-II at 25 Malkangiri 600 Mathili Construction of R.W. Section office building at 26 Mayurbhanj 600 Baripada Extension & renovation of R.W. Division 27 Mayurbhanj 1100 office, Baripada R.W. Section-I & II Office building at 28 Mayurbhanj 611 Kaptipada 29 R.W. Section Office building at SamaKhunta Mayurbhanj 114 30 R.W. Section-II Office building at Khunta Mayurbhanj 100 31 R.W. Section Office-II building at Sarat Mayurbhanj 251 32 R.W. section office,Building at -II Mayurbhanj 366 33 R.W. Circle office,Building at Baripada Mayurbhanj 1000 34 R.W. Section office building at Chitrada Mayurbhanj 150 35 R.W. (PH) Section office, Baripada Mayurbhanj 30 Construction of Laboratory room at R.W. 36 Mayurbhanj 600 Division, Karanjia Construction of R.W. Section office-II at 37 Mayurbhanj 600 Jasipur Construction of R.W. Section office-II at 38 Mayurbhanj 600 Karanjia Construction of R.W. Section office-II at 39 Mayurbhanj 600 Raruan Renovation of R.W.Division office at Karanjia 40 Mayurbhanj 1200 including garage 41 R.W. Section office at Thakuramunda Mayurbhanj 60

Outcome Budget: DoRD for 2014-15 Page 29

42 R.W. Section office at Mayurbhanj 50 43 R.W. Section Office at Badampahar Mayurbhanj 30 44 R.W. Section Office at Jamda Mayurbhanj 130 45 R.W. Section Office at Tiring Mayurbhanj 582 Renovation of R.W. Store Building at 46 Nabarangapur 550 Nabarangapur 47 R.W. Section office building at Tentulikhunti Nabarangapur 300 48 Section office building Maidalpur Nabarangapur 430 49 Section office building Kosagumunda-II Nabarangapur 280 50 R.W. Section office at Jharigam Nabarangapur 197 51 R.W. Section office-I & II at Nabarangapur 121 52 R.W. Section office-I & II at Chandahandi Nabarangapur 413 53 Section office building at Dhodra Nabarangapur 325 54 R.W. Section office building at Deobandha Nabarangapur 300 55 Section- I,II & III office building at Raighar Nabarangapur 582 56 R.W. Section office building at Chandrapur Rayagada 400 57 R.W. Section office at Kasipur Rayagada 48 58 R.W. Section office at Gumuda Rayagada 92 59 R.W. Section office at Gudari Rayagada 221 60 R.W. Section office at Rayagada 304 61 Section office at Bisam Cuttack Rayagada 251 62 R.W. Section office at K.Singhpur Rayagada 150 Construction of R.W.Division office at 63 Rayagada 1300 Gunupur Construction of R.W. Sub-Division office at 64 Rayagada 700 Padmapur Construction of R.W. Sub-Division office at 65 Rayagada 700 Ramanguda Construction of R.W. Section office-II at 66 Rayagada 600 Gunpur 67 Construction of R.W. Section office at Durgi Rayagada 600 Extension of R.W. Sub Division Office at 68 Rayagada 600 Gunupur Construction of R.W. Sub-Division office-II at 69 Rayagada 700 Rayagada Construction of R.W. Section office-III at 70 Rayagada 600 Rayagada Construction of R.W. Section office-IV at 71 Rayagada 600 Rayagada (Kolanara) Renovation of R.W. Division office at 72 Rayagada 900 Rayagada Total : 29900 Grand Total : 130000 The work / Scheme / Project wise allocation is tentative & may be varied N.B.: in keeping with the progress of work during the course of the financial year.

Outcome Budget: DoRD for 2014-15 Page 30

Work list under D.No.28-4216-COL on Houshing-SP-DS-01-GRB-106- GPA/789-SCP for SC/796-TASP-2148-Constn of buildings of R.D.Deptt.- 37114-Public worksfor the year 2014-15

Sl.No. Name of Scheme / Project / Work District in Financial which outlay implemented (in TRS) (including Normal,SCP & TASP) 1 2 3 4 106-General Construction of 2 nos. 'E' type Qtrs. at R.W. Division, Angul 400 1 Angul Construction of 2 nos. 'F' type Qtrs. for Staff at R.W. Angul 250 2 Division, Angul Construction of 2 nos. 'F' type Qtrs. for Staff at R.W. Angul 250 3 Circle, Angul 4 Construction of 'E' type Qtrs. at Athamallik Angul 200 5 Construction of 'F' type Qtrs. at Kishorenagar Angul 200 6 Construction of 'F' type Qtrs. at Athamallik Angul 200 2 "E" type quarter for J.E., Mechanical & Estimator at Angul 174 7 Angul Constn. of 'D' type Qtrs. for A.E.R.W.(P.H.) Sub-Division, 300 Balasore 8 Balasore Constn. of 1 No. 'F' type Qtrs. for Electrical Staff at R.W. 200 Balasore 9 Division, Balasore-I Constn of 1 No. ‘E’ Type qtr. For Rural Works (PH) Sub- 122 Balasore 10 Divn & Section,Balasore 11 'D' type Qtr. for A.E.R.W. Sub-Division, Basta Balasore 190 12 E' type Qrt. for J.E. R.W.Section -II Balasore 357 13 C' type Qrt. for E.E. R.W.Division-II Balasore Balasore 950 14 E type Qtrs. for J.E. R.W. Section, Oupada Balasore 73 15 E type Qtrs. for J.E. R.W. Section, Basta Balasore 73 16 E type Qtr. for J.E R.W. Section Markona Balasore 50 17 'D' type Qtr. for A.E.R.W. Sub-Division, Soro Balasore 102 18 E type Qtr. for J.E R.W. Section Soro Balasore 102 Construction of 'D' type Qtrs. for D.A.O. of R.W. 300 Balasore 19 Division, Jaleswar Construction of 'E' type Qtrs. for J.E. R.W. Division, 250 Balasore 20 Jaleswar 21 Constn. of twin 'F' type Qtrs. at Jaleswar Balasore 300 22 J.E. Quarter (E type) R.W.Section-II, Baliapal Balasore 147 23 D' type Qrt. of R.W.Sub Division Jaleswar (Rajghat) Balasore 441 24 'D' type Qtr. at Bhogarai Balasore 92 25 1 No. "E" type Qtr at Bargarh 295 26 Constn. of 1 No. E type Qtr. at Bheden Bargarh 114 27 Constn. of E type Qtr. at Ambabhona Bargarh 372 28 Constn. of E type Qtr. at Sohela Bargarh 295

Outcome Budget: DoRD for 2014-15 Page 31

29 2 Nos. "F" type Qrt. At Baragarh Bargarh 685 Construction of 'E' type Qtrs. for J.E. at Bheden-II at 200 Bargarh 30 Bheden Construction of 'E' type Qtrs. for J.E. at Barpalli-II at 200 Bargarh 31 Barpalli 32 Constn.of 2 Nos.'F' type Qtrs. at R.W. Division, Bargarh Bargarh 300 33 Constn. of 1 No. 'E' type Qtrs. for P.H. at Bargarh Bargarh 150 34 Twin "E" type Qtr at Bijepur Bargarh 249 35 Const. Of Twin 'E' type Qrt. At Division office, Padampur Bargarh 420 36 Construction of twin 'E' type Qtrs. at Padampur Bargarh 500 37 Construction of 2 nos. 'F' type Qtrs. at Bijepur Bargarh 300 Constn. of 2 Nos. 'F' type Qtrs. for Electrical Staff at R.W. Bargarh 300 38 Division, Padampur 39 Twin E- Type Qtr. at R.W.Division Bhadrak Bhadrak 114 40 1 no. C Type Qtr. For EE at R.W.Division Bhadrak Bhadrak 99 41 D- Type Qtr at R.W.Sub-Division,Tihidi (For A.E.) Bhadrak 154 42 Twin E Type Qtr. at R.W.Section Tihidi (For J.E.) Bhadrak 118 43 'E' type Qrt. of R.W.Section at Bhadrak Bhadrak 150 44 'D' type Qtr. of R.W. Sub Division at Bhadrak Bhadrak 915 45 D type Qtrs. for R.W. Sub-Division, Dhamnagar (for A.E.) Bhadrak 103 46 Twin 'F' type Qtrs. R.W. Division, Bhadrak Bhadrak 87 Constn of 2 Nos.'E' type Qtrs. for J.E. R.W. Section, 400 Bhadrak 47 -I (Block-2) Construction of 'E' type Qtrs. for J.E. R.W. Section, 200 Bhadrak 48 Chandbali Constn. of 1 No. 'F' type Qtrs. for Electrical Staff at R.W. 200 Bhadrak 49 Division, Bhadrak-II 50 E Type Qtr. at R. W.Section Asurali (For J.E.) Bhadrak 185 51 E Type Qtr. at R.W.Section Dhusuri (For J.E.) Bhadrak 235 52 E type Qtrs. for J.E. R.W. P.H. Section, Bolangir Bolangir 350 53 F type Qtr. for Elect. Staff of R.W. Division, Bolangir Bolangir 350 54 D type qtr. for A.E. RW (PH) Sub-Division, Bolangir Bolangir 800 Const. Of D type Qrt. For R.W. Sub Division office at Bolangir 90 55 Saintala 56 D type Qrt. for DAO of R.W. Division, Bolangir Bolangir 490 57 D type qtr at Titilagarh Bolangir 200 58 E type qtr at Bangomunda Bolangir 14 59 E type qtr at Tureikela Bolangir 60 60 Twin F type Qtr. at R.W. Sub Division, Kantabanji Bolangir 101 Construction of 'D' type Qtrs. for D.A.O-I of R.W Boudh 300 61 Division, Boudh Construction of 'E' type Qtrs. for J.E Estimator of R.W Boudh 200 62 Division, Boudh 63 Constn. of 1 No. 'F' type Qtrs. at R.W. Division, Boudh Boudh 150 Constn. of 1 No. E type Qtrs. for J.E.R.W. Section-II Boudh 200 64 Purunakatak at Charichhak ‘E’ type quarter for Junior Engineer, R.W.Section, Boudh 249 65 Boudh-II

Outcome Budget: DoRD for 2014-15 Page 32

66 "F" type quarter for Peon at Boudh Boudh 182 67 Construction of 'E' type Qtrs.at R.W.Section, Kishannagar Cuttack 200 68 Construction of 'F' type Qtrs. at R.W. Section, Niali Cuttack 150 Constn of 'E' type Qtrs. at REO Colony (3rd floor) at Cuttack 400 69 Cuttack, Block-I (2 Nos.) Consn of 'E' type Qtrs. at REO Colony (triple storied) at Cuttack 1200 70 Cuttack,Block-2(6 Nos.) Construction of 'F' type Qtrs. at REO Colony (3rd floor) at Cuttack 300 71 Cuttack, (2 Nos.) Constn. of twin 'E' type Qtrs. (1st floor, 2nd floor) in REO Cuttack 350 72 Colony, Cuttack 73 Construction of 'E' type Qtrs. at R.W. Section, Cuttack 200 Construction of twin 'F' type Qtrs. at R.W. Section, Cuttack 300 74 75 Construction of 'E' type Qtrs. at Niali Cuttack 200 76 Construction of 'F' type Qtrs.at R.W. Section,Choudwar Cuttack 150 77 Twin E type Qtr. R.W. Circle, Cuttack Cuttack 800 78 Twin F type Qtr. R.W. Circle, Cuttack Cuttack 500 79 C Type Qtr. for S.E. at R.W. Circle, Cuttack Cuttack 200 80 Construction of 'E' type Qtrs. at Kanpur Cuttack 200 Construction of twin 'F' type Qtrs. at R.W. Sub division, Cuttack 300 81 Baramba Construction of 1 no.'E' type Qtrs.R.W. Section office at Cuttack 200 82 Baranga Construction of 1 no.'F' type Qtrs.R.W. Section office at Cuttack 150 83 Baranga Construction of twin 'F' type Qtrs. at R.W. Section, Cuttack 300 84 Gurudijhatia 85 Construction of 'E' type Qtrs.R.W. Section at Tigiria Cuttack 200 86 Construction of 'E' type Qtrs. at Kalapathar Cuttack 200 87 Construction of 'F' type Qtrs. at Kalapathar Cuttack 150 88 Construction of 'F' type Qtrs. at Kanpur Cuttack 150 89 Construction of 'E' type Qtrs. at Gurudijhatia Cuttack 200 90 1 no. 'F' type Qrt. At Reamal Deogarh 116 91 Construction of 2 nos. 'E' type Qtrs. at Mahisapat Dhenkanal 400 92 Construction of 'D' type Qtrs. at Hindol Dhenkanal 300 93 Construction of 'F' type Qtrs. at Hindol Dhenkanal 150 94 Construction of 'E' type Qtrs. for J.E.R.W. Section Hindol Dhenkanal 200 Construction of 'E' type Qtrs. for J.E.R.W. Section Dhenkanal 200 95 Maidharpur Constn. of 2 Nos. 'F' type Qtrs. at R.W. Division, Dhenkanal 346 96 Mahisapat 97 Constn.of 1 no. 'F' type Qtrs. at Joranda Dhenkanal 150 98 "E" type quarter at Odapada Dhenkanal 142 99 "E" type quarter at Hindol Dhenkanal 176 100 "E" type quarter at Rasol Dhenkanal 63 101 Construction of 2 nos.'E' type Qtrs. at Kamakshyanagar Dhenkanal 400 Constn. of 2 Nos. 'F' type Qtrs.at R.W. Division, Dhenkanal 346 102 Dhenkanal-II Outcome Budget: DoRD for 2014-15 Page 33

103 E type Qrs of J.E. Kamakhyanagar Section-II, Mahaviroad Dhenkanal 282 104 "F" type quarter of R.W. Sub-Division at Parjang Dhenkanal 31 105 "F" type quarter for R.W. Rest shed at Mahabirod Dhenkanal 316 106 D type Qtrs. for A.E. Parjang Dhenkanal 23 107 E type Qtrs. for J.E. Parjang Dhenkanal 71 108 J.E. Qtr. At Kashinagar (E type) Gajapati 30 109 ‘E’ type quarter for J.E., R.W.Section, Jeerango Gajapati 350 110 ‘E’ type quarter for J.E., R.W.Section, Mohana Gajapati 300 111 ‘F’ type staff quarter for R.W.Section, Mohana Gajapati 250 112 'D' type Qtr. for DAO at Paralakhemundi Gajapati 102 113 Two nos. of 'F' type staff Qtr at Ganjam 300 114 E' Type Qtr for J.E., R.W.Section Bellaguntha Ganjam 200 115 Constn. of 'D' type Qtrs. for SDO at Bellaguntha Ganjam 350 116 Constn. of 'D' Staff Qtr at Bhanajnagar(1No.) Ganjam 350 117 Constn.of 'F' Type Staff Qtr at Bhanjanagar (4 Nos.) Ganjam 600 118 Constn. of 'C' type Qtrs. for E.E. at Bhanajnagar Ganjam 500 119 J.E. Qtr. At Polsara (E type) Ganjam 150 ‘E’ type quarter for Junior Engineer, R.W.Section, Ganjam 129 120 Purusotampur 121 Constn.of 'D' Type Qtr. for A.E.R.W.Khallikoe Ganjam 300 Constn.of 'E' Type Qtr. for J.E.R.W.Section at Ganjam 250 122 Kukudakhandi 123 Constn.of 'D' Type Qtr. for A.E.R.W.Hinjili Ganjam 300 124 Constn. of 1 No. 'E' type Qtrs. at Hinjili Ganjam 250 125 Twin E type Qtr. for R.W. Circle, Berhampur Ganjam 468 126 Twin F type Qtr. for R.W. Circle, Berhampur Ganjam 564 127 E type Qtr. for J.E. R.W. Section, Nuapada Ganjam 354 128 E type Qtr. for J.E. R.W. Section, Beguniapada Ganjam 129 ‘D’ type quarter for Assistant Engineer, R.W.Sub- Ganjam 275 129 Division, Berhampur ‘E’ type quarter for Junior Engineer, R.W.Section, Ganjam 202 130 Gopalpur ‘E’ type quarter for Junior Engineer, R.W.Section, Ganjam 251 131 Sanakhemundi ‘E’ type quarter for Junior Engineer, R.W.Section, Ganjam 338 132 Sheragada. ‘E’ type quarter for Junior Engineer, R.W.Section, Ganjam 422 133 Ganjam. 134 E type Qtr. at Ganjam 60 135 E type Qtr. for J.E. at Ganjam 423 136 R.W.S.S. E type Qtrs for the staffs, Berhampur Ganjam 170 137 Construction of 2 nos.'D' type Qtrs. at Jagatsinghpur Jagatsinghpur 600 138 Construction of 4 nos.'E' type Qtrs. at Jagatsinghpur Jagatsinghpur 540 139 Construction of 1 No. 'C' type Qtrs. at Jagatsinghpur Jagatsinghpur 450 140 Construction of 1 no. 'E' type Qtrs. at Naugaon Jagatsinghpur 250 141 Constn. Of 4 nos. 'F' type Qtrs. at Jagatsinghpur Jagatsinghpur 600 142 Constn. of 1 No. 'E' type Qtrs. at Paradeepgarh Jagatsinghpur 250

Outcome Budget: DoRD for 2014-15 Page 34

143 Constn. of 'C' type Qtrs. for E.E.R.W. Division, Jajapur Jajpur 450 144 Constn. of 'D' type Qtrs. for DAO, R.W. Division, Jajapur Jajpur 300 145 Constn. of 'E' type Qtrs. for J.E., R.W. Section Tamaka Jajpur 250 146 Constn. of 2 Nos. 'E' type Qtrs. at Jajpur Jajpur 500 147 Constn. of 'E' type Qtrs. at Binjharpur Jajpur 250 148 Constn. of 'F' type Qtrs. at Binjharpur Jajpur 150 149 Construction of 'E' type Qtrs.for JE at Kuakhia Jajpur 250 150 Constn. of twin 'F' type Qtrs.for Class-IV at Kuakhia Jajpur 150 151 2 Nos. Twin F type Qtrs. at Jajpur 290 152 E.E. Qtr. At Jharsuguda Jharsuguda 170 153 2 Nos. E type Qtrs. For J.Es Jharsuguda Jharsuguda 331 154 Twin "F" type Qtr at Jharsuguda Jharsuguda 207 155 DAO Qtrs. at Jharsuguda Jharsuguda 48 156 E type Qtrs. at R.W. Division, Jharsuguda Jharsuguda 87 157 2 Nos. E type Qtr. at Laikera Jharsuguda 45 158 "E" type Qtr at Th. Rampur Kalahandi 69 159 Twin E type Qtr. for R.W Circle, Bhawanipatna Kalahandi 100 160 "E" type quarter at Junagarh Kalahandi 50 D type Qtr. for R.W. Sub Division office Mukhiguda at Kalahandi 80 161 Jaipatna 162 Constn.of 'E' type Qtrs.for J.E.R.W. Section,Golamunda Kalahandi 150 Constn. of 'E' type Qtrs. for J.E. R.W. Section, Kalahandi 150 163 Kusumkhunti 164 ‘E’ type quarter for J.E., R.W.Section-II Tikabali Kandhamal 240 Twin ‘F’ type quarter for Peon at R.W.Sub-Division, 150 Kandhamal 165 Balliguda 166 Construction of 'C' type Qtrs. for E.E. at Balliguda Kandhamal 450 167 Construction of 'D' type Qtrs. for D.A.O at Balliguda Kandhamal 300 168 Construction of 'D' type Quarters at Kotagarh Kandhamal 300 169 Constn. of 'E' type Qtrs. at Phulbani Kandhamal 250 Constn. of 1 No. 'F' type Qtrs. for Electrical Staff at R.W. 150 Kandhamal 170 Division, Phulbani 171 Constn. of twin 'F' type Qtrs. at Baliguda Kandhamal 300 172 Constn. of 'F' type Qtrs. at Kotpad Kandhamal 150 Construction of 'E' type Qtrs. for J.E. R.W. Section, Kendrapara 250 173 Derabish Construction of 'E' type Qtrs. for J.E. R.W. Section, Kendrapara 250 174 Mahakalpara 175 Constn. of twin 'F' type Qtrs. at Kendrapara-I Kendrapara 300 Construction of 'E' type Qtrs. for J.E. R.W. Section-II, Kendrapara 250 176 Rajkanika Construction of 'D' type Qtrs. for R.W. Sub-Division, Kendrapara 300 177 Rajkanika 178 Construction of 'E' type Qtrs. for J.E. at Aul Section-II Kendrapara 250 179 Constn. of 'E' type Qtrs. at Panapentha Kendrapara 250 180 D type Qtr. for E.E. at Anandapur Keonjhar 25 181 E type Qtr. for J.E. at Hatadihi Keonjhar 191

Outcome Budget: DoRD for 2014-15 Page 35

182 D type Qtr. for A.E. at Saharpada Keonjhar 91 183 Twin E type Qtr. for R.W. Circle, Keonjhar Keonjhar 406 184 Twin F type Qtr. for R.W. Circle, Keonjhar Keonjhar 500 185 E type Qtrs. for J.E. R.W. Section-II, Keonjhar Keonjhar 250 Twin 'E' type Qtrs. for J.E. Estimator of R.W. Division, Keonjhar 500 186 Keonjhar Consnt. of 2 nos. 'E' type Qtrs. for J.E. R.W. Section, Keonjhar 350 187 Keonjhar 188 2 Nos. E type Qtr. At Jhumpura Keonjhar 102 189 E type Qtr. R.W. Sub Division, Telkoi-I Keonjhar 86 190 F type Qtr. at Keonjhar 38 191 E type Qtr. at Banspal Keonjhar 72 192 Constn. of 2 nos. 'F' type Qtrs. at Balianta Khordha 300 193 Constn. of 1 no. 'D' type Qtrs. at Balipatna Khordha 300 194 Constn. of 1 no. 'D' type Qtrs. at Balianta Khordha 300 195 Constn. of 2 nos. 'F' type Qtrs. at Tangi Khordha 300 196 Constn. of 2 nos. 'F' type Qtrs. at Balugaon Khordha 300 197 Constn. of 2 nos. 'F' type Qtrs. at Balipatna Khordha 300 198 Constn. of 2 nos. 'F' type Qtrs. at Khordha 300 Constn. of 'E' type Qtrs. for J.E.R.W.(P.H.) Section, 200 Khordha 199 Bhubaneswar Constn.of 1 No.'F' type Qtrs. for Electrical Staff at 200 Khordha 200 R.W.Division,Bhubaneswar 201 Constn. of 2 nos. 'F' type Qtrs. at Khordha Khordha 300 202 Constn. of 2 nos. 'F' type Qtrs. at Nirakarpur Khordha 300 203 D type qtr. for A.E. RW (PH) Sub-Division, Bhubaneswar Khordha 236 204 Twin 'F' type Qrt. At R.W. Sub division Khurda Khordha 80 205 D type Qtr. for DAO R.W. Division, Koraput Koraput 88 206 2 "E" type quarter for JE(Clerical) staff at Koraput Koraput 100 207 J.E. (E type) Qtr. at Kotpad Koraput 67 208 E type Qtr. for J.E. at Badhugaon Koraput 181 Constn. of 2 Nos. 'F' type Qtrs. at R.W. Division, Koraput 300 209 Sunabeda 210 Constn. of E type Qtrs. for R.W. J.E. at Semeliguda Koraput 250 211 Constn. of E type Qtrs. for R.W. J.E. at Narayanpatna Koraput 250 212 Constn. of E type Qtrs. at Laxmipur Koraput 250 213 Construction 'D' type Qtrs. of R.W. Division-II, Nayagarh Nayagarh 300 Construction 'E' type Qtrs. (2 Nos.) of R.W. Division-II, 500 Nayagarh 214 Nayagarh Construction 'F' type Qtrs. (2 Nos.) for R.W. Division, 400 Nayagarh 215 Nayagarh 216 Construction of 1 No.'C' type Qtrs. for E.E.at Khariar Nuapada 450 Construction of 2 Nos. 'D' type Qtrs. for A.E. & Estimator 600 Nuapada 217 at Khariar Construction of 2 Nos. 'E' type Qtrs. for J.E. & Staff at 500 Nuapada 218 Khariar 219 Construction of 2 Nos. 'F' type Qtrs. for Staff at Nuapada Nuapada 300 220 Construction of 'D' type Qtrs. for A.E. at Nimapara Puri 300 Outcome Budget: DoRD for 2014-15 Page 36

Constn. of 2 Nos. 'E' type Qtrs. for Staff of R.W. Division, Puri 500 221 Puri Constn. of 2 Nos. 'F' type Qtrs. for Staff of R.W. Division, Puri 300 222 Puri Constn. of 2 Nos. F type Qtrs. of R.W Sub Division, Sambalpur 285 223 Rairakhol 224 E type Qtr. at Kuchinda Sambalpur 72 225 Construction of 1 no. 'E' type Qtrs. at Keseibahal Sambalpur 250 226 Construction of 1 no. 'F' type Qtrs. at Bamara Sambalpur 150 227 Construction of 1 no. 'E' type Qtrs. at Bhojpur Sambalpur 250 228 Construction of 1 no. 'E' type Qtrs. at Jujumura Sambalpur 250 229 Construction of 1 no. 'C' type Qtrs. at Kuchinda Sambalpur 450 230 Constn. of 1 No. 'F' type Qtrs. at Dhama Sambalpur 150 231 Constn. of 1 No. 'E' type Qtrs. at Dhama Sambalpur 250 232 Constn. of 1 No. 'F' type Qtrs. at Jamankira Sambalpur 150 233 Constn. of 1 No. 'F' type Qtrs. at Bamra Sambalpur 150 234 E' type Jr. Engineer R.W. Section Dunguripali Subarnapur 300 235 D type Qtr. for A.E.R.W. Division (Estimator) Sonepur Subarnapur 400 236 E' type Jr. Engineer R.W. Section Binika Subarnapur 129 237 E' type Jr. Engineer R.W. Section-II Tarva Subarnapur 162 238 E' type Class III Staff Qtr. at Sonepur Subarnapur 240 239 F' type Class IV Staff Qtr. at Sonepur Subarnapur 200 240 F' type Qrt 2 nos for Class-IV at Sonepur Subarnapur 350 241 E type 1 No. for Class-III staff at Sonepur Subarnapur 210 242 Construction of 'D' type Qtrs. for A.E. B.Mpur Subarnapur 300 Construction of 4 Nos. 'E' type Staff Qtrs. for Clerical at Subarnapur 1000 243 Sonepur 244 Constn. of 2 Nos. 'F' type Qtrs.at R.W.Division, Sonepur Subarnapur 300 245 Constn. of 'C' type Qtrs. at Sonepur Subarnapur 450 Constn. of 'E' type Qtrs. for J.E.R.W.(P.H.) Section, Sundargarh 250 246 Sundargarh Constn.of 1 No.'F' type Qtrs.for Electrical Staff at R.W. Sundargarh 170 247 Division,Sundargarh-I 248 Construction of 1 no. 'C' type Qtrs. at Sundargarh Sundargarh 450 249 Constn. Of 4 nos. 'E' type Qtrs. for J.E. at Sundargarh Sundargarh 1000 250 Constn. of 1 no. 'D' type Qtrs. at Lefripada Sundargarh 300 251 Constn. of 1 no. 'E' type Qtrs. at Lefripada Sundargarh 175 252 Constn. of 1 no. 'E' type Qtrs. at Himgiri Sundargarh 175 253 Constn. of 2 nos. 'E' type Qtrs. at Bargaon Sundargarh 350 254 Twin "D" type Qtr at Rourkela Sundargarh 871 255 Twin "E" type Qtr at Rourkela Sundargarh 852 256 Twin "F" type Qtr at Rourkela Sundargarh 763 Constn. of Twin 'E' type Qtrs. at R.W. Colony, Sundargarh 500 257 (1st Floor) Constn. of 2 Nos. 'F' type Qtrs. at R.W. Division, Sundargarh 348 258 Sundargarh-II 259 Constn. of twin 'D' type Qtrs. at Panposh Sundargarh 600

Outcome Budget: DoRD for 2014-15 Page 37

260 Constn. of 'D' type Qtrs. at Kuanrmunda Sundargarh 300 Total : 72000 789-SCP for SC Constn. of 'D' type Qtrs. for A.E.R.W.(P.H.) Sub-Division, Bolangir 300 1 Bolangir Constn. of 'E' type Qtrs. for J.E.R.W.(P.H.) Section, Bolangir 250 2 Bolangir 3 Constn. of 1 No. 'F' type Qtrs.at R.W. Division, Bolangir Bolangir 150 4 Constn. of twin 'F' type Qtrs. at R.W. Circle, Bolangir Bolangir 300 Constn. of 'D' type Qtrs. for P.A. to S.E. R.W. Circle, Bolangir 300 5 Bolangir Constn. of 'E' type Qtrs. at Harisankar (Khaprakhole Bolangir 250 6 Section-II) Renovation of 'D' type Qtrs. for A.E.R.W. Sub Division, Bolangir 200 7 Patnagarh 8 Constn. of twin 'E' type Qtrs. at R.W. Circle, Bolangir Bolangir 500 9 Constn. of 'E' type Qtrs. at Gudvella Bolangir 250 10 Construction of 'D' type (2 Nos.) Qtrs. at Titilagarh Bolangir 500 11 Construction of 'D' type Qtrs. at Tureikela Bolangir 300 12 Construction of Twin 'E' type Qtrs. at Tureikela Bolangir 500 13 Construction of 2 Nos. 'F' type Qtrs. at Titilagarh Bolangir 300 14 Construction of 'E' type Qtrs. at Muribahal Bolangir 250 Cosntn. of 2 Nos. twin 'E' type Qtrs. R.W. Section-I & II, 500 Bolangir 15 Titilagarh 16 ‘E’ type quarter for J.E., R.W.Section, Jeerango Gajapati 98 17 ‘E’ type quarter for J.E., R.W.Section, Mohana Gajapati 143 18 ‘E’ type quarter for J.E., R.W.Section, Gumma Gajapati 89 19 ‘F’ type staff quarter for R.W.Section, Mohana Gajapati 64 20 Construction of 1 No. 'C' type Qtrs. for E.E. at Kesinga Kalahandi 400 Construction of 2 Nos. 'E' type Qtrs. for J.E. & Staff at Kalahandi 500 21 Kesinga 22 Construction of 2 Nos. 'F' type Qtrs. for Staff at Kesinga Kalahandi 300 23 Constn.of twin 'E' type Qtrs.for J.E.R.W., Bhawanipatna Kalahandi 500 Constn. of 2 Nos. 'F' type Qtrs. for R.W. Division, Kalahandi 300 24 Bhawanipatna 25 Constn. of 2 nos. 'D' type Qtrs. at Kesinga Kalahandi 600 26 Constn. of 2 nos. 'D' type Qtrs. at Khariar Kalahandi 600 27 Constn. of 2 nos. 'E' type Qtrs. at Khariar Kalahandi 500 28 C type Qtr. For S.E. Bhawanipatna Kalahandi 150 29 C type Qtr. for EE at Bhawanipatna Kalahandi 523 30 "E" type Qtr at Th. Rampur Kalahandi 254 31 Twin E type Qtr. for R.W Circle, Bhawanipatna Kalahandi 150 32 E type Qtr. at Karlamunda Kalahandi 200 33 "E" type quarter at Junagarh Kalahandi 172 34 Construction of 2 nos. 'E' type Qtrs. at Dharmagarh Kalahandi 500 35 Construction of 'E' type Qtrs. for J.E.R.W. Section, Ampani Kalahandi 250 Construction of 'E' type Qtrs. for J.E.R.W. Section, Kalahandi 250 36 Mukhiguda at Jaipatna

Outcome Budget: DoRD for 2014-15 Page 38

37 Twin "D" type Qtr at R.W. Division, Dharmagarh Kalahandi 111 38 1 No. "C" type for E.E. at R.W. Division, Dharmagarh Kalahandi 192 39 Twin "E" type Qtr at Dharmagarh Kalahandi 111 40 2 Nos. "F" type class-III staff Qrt. At Dharmagarh Kalahandi 128 Construction of 2 Nos. 'F' type Qtrs. for Class-III staff at 300 Kalahandi 41 Dharmagarh Constn. of 1 No. 'F' type Qtrs. at R.W. Division, 150 Kalahandi 42 Dharmagarh 43 Construction of 'C' type Qtrs. for E.E. at Dharmagarh Kalahandi 450 44 ‘E’ type quarter for J.E., R.W.Section-II Tikabali Kandhamal 148 45 D type Qtr. for A.E. at Saharpada Keonjhar 138 46 2 nos "F" quarter for staff at Keonjhar (Dhurupada) Keonjhar 150 47 E type Qtrs. for J.E. R.W. Section, Turumunga Keonjhar 250 48 Constn.of 2 Nos.'F' type Qtrs. R.W. Division, Keonjhar-I Keonjhar 400 Constn. of 2 nos. 'E' type Qtrs. of S.E. R.W. Circle, 500 Keonjhar 49 Keonjhar 50 E type Qtrs. 1 No. for R.W. Section, Janghira Keonjhar 250 51 2 Nos. E type Qtr. At Jhumpura Keonjhar 30 52 "E" type qtr at Banspal Keonjhar 107 53 E type Qtrs. 1 No. for R.W. Section-II. Kaliahata Keonjhar 250 54 Constn. Of 'E' type Qtrs. for R.W. Section, Bhanda Keonjhar 250 55 Constn. of 'F' type Qtrs. at Jhumpura Keonjhar 200 Constn. of 1 No. 'F' type Qtrs. for Electrical Staff at R.W. Koraput 200 56 Division, Koraput 57 A.E. qtr (D type) at Govindpalli Malkangiri 200 58 Twin "E" type staff qtr at Malkanagiri Malkangiri 250 59 E type Qtr. for J.E. at Mathili-I Malkangiri 167 60 2 nos. "E" type quarter for J.E at Malkangiri Malkangiri 300 61 "D" type quarter for DAO at Malkangiri Malkangiri 210 62 F' type Peon Qrt. For R.W. Divi-II ,Malkanagiri Malkangiri 150 63 "E" type Clerical Qtr. for R.W. Division-II, Malkangiri Malkangiri 250 64 E type qtr for J.E. at Tentulikhunti Nabarangapur 210 65 "E" type quarter for J.E at Dabugam-I Nabarangapur 300 66 "E" type quarter for J.E at Maidalpur Nabarangapur 300 67 C type Qtr. for E.E. R.W. Division-II, Nabarangpur Nabarangapur 146 68 E type Qtr. for J.E. R.W. Section, Jharigam Nabarangapur 64 Twin E type Qtrs. for J.E.'s of R.W. Sub-Division, 210 Nabarangapur 69 Chandahandi 70 Two nos. of "E" type quarter for J.E at Raighar Nabarangapur 400 71 "E" type Qtr. of Section office at Deobandha Nabarangapur 300 72 Twin "E" type Qtr at Nuapada for J.E Nuapada 113 73 Twin "F" type Qtr at Nuapada for Clerical Staff Nuapada 107 74 "E" type quarter for J.E Section at Nuapada Nuapada 131 75 E type Staff Qtrs. at Nuapada Nuapada 137 Constn. of 2 Nos. F type Qtrs. of R.W Sub Division, 143 Sambalpur 76 Rairakhol 77 E' type Jr. Engineer R.W. Section Dunguripali Subarnapur 99 Outcome Budget: DoRD for 2014-15 Page 39

78 E' type Jr. Engineer R.W. Section-II Tarva Subarnapur 108 79 E' type Class III Staff Qtr. at Sonepur Subarnapur 99 80 E type Qtr. for R.W. Section, Koira Sundargarh 149 81 E type Qtr. for R.W. Section, Gurundia Sundargarh 149 Total : 20400 796-TASP 1 E type Qtr. at Karlamunda Kalahandi 150 2 Twin "D" type Qtr at R.W. Division, Dharmagarh Kalahandi 600 3 1 No. "C" type for E.E. at R.W. Division, Dharmagarh Kalahandi 800 4 Twin "E" type Qtr at Dharmagarh Kalahandi 450 D type Qtr. for R.W. Sub Division office Mukhiguda at Kalahandi 181 5 Jaipatna 6 E type Qtr. for J.E. R.W. Section, Kalahandi 342 7 2 Nos. "F" type class-III staff Qrt. At Dharmagarh Kalahandi 360 8 D type Qtr. At Telkoi Keonjhar 141 9 "D" type Qtr. for R.W. Sub-Division at Jhumpura Keonjhar 65 10 "F" type Qutr. R.W.Sub division,Telkoei Keonjhar 193 11 A.E. qtr (D type) at Lamtaput Koraput 145 12 A.E. qtr (D type) at Jeypore Koraput 141 13 D type Qtr. for DAO R.W. Division, Koraput Koraput 248 Koraput 305 14 2 nos."E" type quarter for JE(Clerical) staff at Koraput Construction of 'D' type Qtrs. for D.A.O. Jeypore Koraput 300 15 16 Construction of 'D' type Qtrs. for A.E. Kotpad Koraput 300 17 Construction of 'E' type Qtrs. for J.E. Kotpad-III Koraput 250 18 Constn. of 1 No. 'E' type Qtrs. Boipariguda Koraput 250 19 Construction of 'D' type Qtrs. for A.E. Boipariguda Koraput 300 20 Construction of 'D' type Qtrs. for A.E. Dasmantapur Koraput 300 21 Construction of 'E' type Qtrs.for J.E.Dasmantapur-III Koraput 250 22 Constn. of 1 no. 'E' type Qtrs. at Koraput 250 23 Construction of 'E' type Qtrs. for J.E. Mathili-II Malkangiri 250 24 Construction of 'C' type Qtrs. for E.E. Mlakangiri-I Malkangiri 450 Construction of 'D' type Qtrs. for A.E. Estimator at Malkangiri 300 25 Malkangiri-I Constn. of 2 Nos. 'F' type Qtrs. at R.W. Division, Malkangiri 300 26 Malkangiri-I 27 Construction of twin 'E' type Qtrs. for Staff at Malkangiri-II Malkangiri 500 28 Construction of twin 'D' type Qtrs. for Staff at Malkangiri-II Malkangiri 600 29 Construction of 'C' type Qtrs.for E.E. at Malkangiri-II Malkangiri 450 Construction of twin 'E' type Qtrs. R.W. Division, 500 Mayurbhanj 30 Baripada Construction of 'D' type Qtrs. for P.A. of S.E.R.W. Circle, 300 Mayurbhanj 31 Baripada Construction of twin 'F' type Qtrs. for S.E.R.W. Circle, 300 Mayurbhanj 32 Baripada Construction of 'E' type Qtrs. for J.E.R.W. Section, 250 Mayurbhanj 33 Samakhunta

Outcome Budget: DoRD for 2014-15 Page 40

Construction of 'F' type Qtrs. for Staff R.W. Section, 150 Mayurbhanj 34 Samakhunta Construction of 'F' type Qtrs. for Staff R.W. Section, 150 Mayurbhanj 35 Construction of 'D' type Qtrs. for A.E.R.W. Sub-Division, 300 Mayurbhanj 36 Betnoti Construction of 'F' type Qtrs. for Staff R.W. Sub-Division, 150 Mayurbhanj 37 Betnoti Construction of 'E' type Qtrs. for J.E.R.W. Section, 250 Mayurbhanj 38 Betnoti-II Construction of 'E' type Qtrs. for J.E.R.W. Section, 250 Mayurbhanj 39 Baisinga Construction of 'E' type Qtrs. for J.E.R.W. Section, 250 Mayurbhanj 40 Kaptipada-II Construction of 'F' type Qtrs. for Staff of R.W. Section, 150 Mayurbhanj 41 Kaptipada-II 42 Construction of 'E' type Qtrs. for J.E.R.W. Section, Sarat Mayurbhanj 250 43 Constn. of 2 Nos. 'E' type Qtrs. at Baripada (Block-2) Mayurbhanj 500 44 E type Qtr. for R.W.Section, Kaptipada-I Mayurbhanj 427 45 E type Qtr. for J.E. R.W.Section, Chitroda Mayurbhanj 300 46 E type Qtr. for J.E. R.W.Section, Kuliana Mayurbhanj 265 47 E type Qtr. for J.E. R.W.Section, -II Sarat Mayurbhanj 15 48 Twin E- Type Qtr. For J.E. R.W. Section at Khunta Mayurbhanj 700 49 S.E. Qtr. At Baripada(C type) Mayurbhanj 1200 50 2 Nos. F type Qtrs. at R.W. Sub Division, Udala Mayurbhanj 600 51 2 Nos. F type Qtrs. for Staff at S.E. office at Baripada Mayurbhanj 200 Construction of 2 Nos. 'F' type Qtrs. for Staff of R.W. Mayurbhanj 300 52 Division, Karanjia Construction of 'E' type Qtrs. for J.E.R.W. Section-II, Mayurbhanj 250 53 Raruan Construction of 'E' type Qtrs. for J.E.R.W. Section, Mayurbhanj 250 54 55 Construction of 'D' type Qtrs. for DAO at Karanjia Mayurbhanj 300 56 Constn.of 2 Nos.'E' type Qtrs. at R.W. Division, Karanjia Mayurbhanj 500 57 Constn. of 'E' type Qtrs. at Jasipur Mayurbhanj 250 58 Twin E type Qtr for J.E. at Karanjia Mayurbhanj 31 59 E type Qtr for J.E. at Jashipur Mayurbhanj 45 60 2 nos. "F" type quarter at Sub-Division Mayurbhanj 350 Construction of 3 Nos. 'E' type Qtrs. for Staff at R.W. 650 Mayurbhanj 61 Division, Rairangpur Construction of 'D' type Qtrs. for Staff at R.W. Division, 300 Mayurbhanj 62 Rairangpur 63 Constn. of twin 'E' type Qtrs. at Nabarangapur Nabarangapur 500 64 Constn. of twin 'F' type Qtrs. at Nabarangapur Nabarangapur 300 Construction of twin 'E' type Qtrs. for staff at Division-II, Nabarangapur 500 65 Umerkote Constn. of 2 Nos. 'F' type Qtrs.at R.W. Division, Nabarangapur 300 66 Nabarangapur-II 67 Construction 'D' type Qtrs. at Umerkote Nabarangapur 300 68 Constn. of twin 'E' type Qtrs. at Raighar Nabarangapur 500 Outcome Budget: DoRD for 2014-15 Page 41

69 Twin "E" type Qtr at Nuapada for J.E Nuapada 100 70 Twin "F" type Qtr at Nuapada for Clerical Staff Nuapada 90 150 71 D type Qtr. for A.E.R.W. Sub-Division Gunupur Rayagada 150 72 D type Qtr. for A.E.R.W. Sub-Division Rayagada Rayagada 258 73 E type Qtr. for A.E.R.W. Sub-Division B.Cuttack Rayagada 74 D type Qtr. for D.A.O.R.W. Division Rayagada Rayagada 150 75 Twin D type Qtrs. for Estimator at Division Rayagada Rayagada 300 76 E type Qtr. R.W.Division Rayagada for Staff Rayagada 200 77 E type Qtr. for J.E. at Sub-Division Kasipur Rayagada 150 78 Twin "F" type quarter for Staff at Gunupur Rayagada 200 79 F type Qtr. for Staff at Padmapur Rayagada 150 80 Twin "E" type quarter for J.E. at Gunupur Rayagada 150 81 Construction of 'D' type Qtrs. for D.A.O. Gunpur Rayagada 300 82 Construction of 'E' type Qtrs. for J.E.R.W. Section, Durgi Rayagada 250 Construction of twin 'F' type Qtrs. for Staff R.W. Division, Rayagada 300 83 Gunpur 84 Construction of 'D' type Qtrs. for A.E. at Rayagada-II Rayagada 300 85 Construction of 'E' type Qtrs. for J.E. at Rayagada-III Rayagada 250 Construction of 'E' type Qtrs. for J.E. at Rayagada-IV Rayagada 250 86 (Kolnara) 87 Construction of 'C' type Qtrs. for E.E. at Rayagada Rayagada 450 88 Constn. of 2 nos. 'F' type Qtrs. at R.W. Division, Rayagada Rayagada 300 89 Constn. of 'D' type Qtrs. at Ramanguda Rayagada 300 90 Constn. of 'E' type Qtrs. at Gunupur Rayagada 250 91 Constn. of 'D' type Qtrs. at Padampur Rayagada 300 92 E type Qtr. at Lahunipada Sundargarh 48 Total : 27600 Grand Total 120000 The work / Scheme / Project wise allocation is tentative & may be varied in keeping with N.B.: the progress of work during the course of the financial year.

Outcome Budget: DoRD for 2014-15 Page 42

Work list under D.No -28-5054-COL on R&B-SP-DS-04-DOR-789-SCP SC/796-TASP /800-OE-2161-RIDF-37107 Major work for the year 2014-15 Sl.No. Name of the Scheme / Project / Work District which Financial implemented outlay (in TRS) (including Normal, SCP & TASP) 1 2 3 4 80-General-789-SCP-SC H.L. bridge over Chilanti nallah at 7th km. on Rengali- 1 Angul 1 Kuluma via Nailu road H.L. bridge over Chilanti nallah at 8th km. on Bajrakote- 2 Angul 1 Baliposi road 4 x 9.77m. H.L. bridge over Khairasahi nallah at 1st KM on 3 Angul 1 Thakurgarh-Kantapal road HL. Bridge over river Gangahar nallah at 6th km. on 4 Balasore 15000 -Palsia road 5 Bridge over Budhabalanga on Ambulkuda-Gandara road Balasore 5000 6 Bridge over Budhabalanga on Kasimpur-Haldia road Balasore 5000 7 Silda Mahadev Temple to Padabadagaon Rly gate road Balasore 8000 Kasafal Chandanpalihari Chhak to Nuakundi via Sahu 8 Balasore 5000 Chhak project 9 Talakurunia to Arhua bad via -Dolpur Balasore 5000 10 Anantapur to Bakeswarpur via Patimunda & Palapur Balasore 2500 Benuda- Nimapouhari to Kulida PMGSY road via Darhha 11 Balasore 500 Patrasahi road Mahagah PMGSY road to Kuliha via Kiagadia Kalyanpur 12 Balasore 3000 Kaisa & Karihandu road 13 Bada Mahisahi Chhak to S.R. College Road Balasore 5300 H.L. bridge over Jhainjore at 2nd km. on Kadobahal- 14 Baragarh 2 Jhilminda road 5 x 30.63m. Bridge over river Jeera at 10th km. on PWD road-Kusanpur- 15 Bargarh 25000 Baramkela road 16 Bridge over Jhainjore on Tope Pithapotala road Bargarh 20000 Bridge over river Jeera on RD road-Launsara via Malipali 17 Bargarh 20000 road H.L. bridge over river Genguti at 10/10 km. on 18 Bhadrak 10000 Mangarajpur-Kampada-Iswarpur road 2x 0.63m. HL Bridge over river Mantei at 4.800 km. on BC road to 19 Bhadrak 15000 Bahabalapur with approaches H.L. bridge over river Reba near Patuli on Bhandaripokhari- 20 Bhadrak 1 Patuli road alongwith long approach 21 Manjuri Gobindapur Road (Phylin) Bhadrak 4143 22 Hatapada Senyata road Bhadrak 500 23 Tailu to Mahagupur via Gotsira Bhadrak 10000

Outcome Budget: DoRD for 2014-15 Page 43

H.L. bridge over Laxmipur nallah at 21st km. on Boudh- 24 Boudh 5755 Dhialpur road 3 x 25.35m H.L. bridge over river Bagh at 25th km. on Manmunda- 25 Boudh 15000 Sagada road 3 nos of bridge over Local Nahhal including approach on 26 Boudh 20000 PGBM road H.L. bridge over Kapakhai nallah on 2nd km. on 27 Boudh 500 Baghiapada-Birigada road Bridge over Karadakatha nallah on Kusanga-Mahalikpada- 28 Boudh 15000 Talagaon road. Bridge over Meherruni nallah at 10th KM on - 29 Boudh 1 Lamsori road. Bridge over Ghesali nallah on Agalpur-Nuagaon-via 30 Bolangir 1 Mahakhanda road. Bridge over Tendiapali nallah at 13th KM on Sonepur PWD 31 Bolangir 1 road to Tendipali H.L. bridge over river Kathjodi near Kaijanga at 18th km. on 32 Cuttack 2000 Jhinkiria-Bentaka-Chanduli road 21x30.63m 33 Telengapentha-Sainda road (0/0 - 4/0 km.) Cuttack 1 34 Panimando to Ratilo road Cuttack 15000 35 Majhikandei- Bilasuni Cuttack 30000 36 Karilo Panchgochia road Cuttack 20000 37 R.D. road to Oringabandi via Dandapadia Talupadia road Cuttack 10000 38 Dhaipur Kaitha Chhak to Kantol PWD road Cuttack 10000 Bridge over Lunibandha nallah at 8th KM on Bidharpur- 39 Dhenkanal 1 Joranda -Kaluria road Bridge over Kalabila nallah at 2nd KM on Kadua- 40 Dhenkanal 1 Bhagirathipur road 41 Golabandha-Buguda road (8.10 km.) Ganjam 1 Talasakara Antarpada Road ( Sankula to Manibandha to 42 Ganjam 1 Pdpur Sasan from 0/0 to 2/100 km ) Surangi-Nuapada via Rajapur-Pitigovindapur and Subalya 43 Ganjam 10000 (0/0 to 15/6 km.) 44 Jarada-Sunakhala via Ghati Mukundapur (0/8 km.) Ganjam 5000 45 Khandadeuli via Nimisola Ganjam 15000 46 Bridge over river Bahuda on Sonepur to Patisonepur road Ganjam 60000 H.L. bridge over Kharikhari nallah at 5th km. on 47 Ganjam 30000 Santoshpur-Umari-Barpali road R.D. road Kudutei to Samaabandha via Badakhanda 48 Ganjam 10000 Tulasipalli & Narayanpalli road 49 Dholpita Domuhani road Ganjam 4000 50 Chopra to Nada road Ganjam 3000 51 Purushottampur-Bhimpur via Kulasingh road Ganjam 1 52 Sikharpur-Sahapur road Ganjam 1 53 Kaleswar-Pandia- road Ganjam 1

Outcome Budget: DoRD for 2014-15 Page 44

54 9th Distribution Embankment road Ganjam 1 H.L. bridge over river Devi on Devidola connecting to Gada 55 Jagatsinghpur 39214 village 56 Dhanipur Mandasahi Bhokanji road. Jagatsinghpur 12000 57 Chasikhanda-Gelpur road (7.80 km.) Jagatsinghpur 1 Bridge over river Devi at 3 Km on Bhokanji-Mundilo road 58 Jagatsinghpur 10000 (600m) 59 Bridge over Hansua on Alana - Rankei road Jagatsinghpur 10000 60 Tandikula to Champahat Jagatsinghpur 15000 61 Rahama Pandua ( R&B) road Purudi via Napanga Jagatsinghpur 15000 62 Bridge over river Hansua on Katra-Kutilo road Jagatsinghpur 1 63 Kamarpada-Gadama road Jagatsinghpur 1 H.L. bridge over river Nuanai at 2nd km. on Bari- 64 Jajpur 10000 Binjharpur road S.B. over Benga nallah at 8th km. on B.C.J. High School- 65 Jajpur 1 Badakunal-Naragochha road 4x10.77m 66 Sasanpada Sayedpur road Jajpur 5000 Bridge over Tenta nallah on Kapila Barapada Chilapadia via 67 Jajpur 15000 Nagapura road 68 Bridge over Tenta nallah on Sayedpur-Sanpada road Jajpur 1 NH5 to Kolha via Haridaspur Railway station from 0/750 69 Jajpur 1500 km to 9.00 km 70 R & B road to Budha Kendua Jajpur 30000 71 N.H.5 to Sidhipur Jajpur 7000 72 Sukinda Duburi mundapandu road Jajpur 5000 73 Kabatabandha-Rekhideipur road Jajpur 1 74 NH 200 to Hatibari road Jajpur 1 75 Bridge over river Udanti on PWD road-Kanduljore road Kalahandi 35000 H.L. bridge over river Udanti at 2nd km. on Udsurang- 76 Kalahandi 4459 Kuhura road 7 x 30.63m H.L.bridge over river Salki at 2nd. Km. on Kainjhar- 77 Kandhamal 1 Gutingia via-Katadi road 3x 30.63 m 78 Gochhapada-Balandapada-Malikikud road 14 km. Kandhamal 3500 79 Pasina Linepada road Kandhamal 6000 80 Bridge over river Gobari on Pehenta-Pesta road Kendrapara 3000 81 Ayeba Nembura road Kendrapara 13100 S.B. over Lamtaguda nallah at 3rd. km. on Kumarput 82 Malkanagiri 1 Mathili road 3x8.77 m 83 Khariar- Dumerjhor Nuapada 8000 Box cell bridge over river Kadua at 8th km. on Roulpatana- 84 Puri 1 Dhantri-Panichhatra road 6 x 8m x 3.91 H.L. bridge over Tangarjore nallah at 4th km. on Garposh- 85 Sambalpur 10000 Nuapali road 3 x 25.35 m H.L. Bridge over over Kularijore nallah at 2nd K.M. on 86 Sambalpur 1 Bhaliapali- Dalbi road 2x 24.75 m

Outcome Budget: DoRD for 2014-15 Page 45

H.L. bridge over Harada nallah on PWD road-Themra 87 Sambalpur 1 (extension to NH 6) Bridge over Murmuri nallah at 18th KM on MDR 39 to 88 Sonepur 1 Asuragarh road Total : 697000 80-General-796-TASP 1 Joranda Vegibola road Dhenkanal 24000 2 Tilapada Nathua Chuli road Dhenkanal 8000 3 Chandar Ektali road Dhenkanal 7000 Bridge over Bousjore nallah at 3rd KM on Taranga-Tuhilmal 4 Deogarh 1 road 5 NH6 to Rengalbeda via Gohira road Deogarh 1 6 Saida-Purunapani road Deogarh 1 Bridge over Jamudihi nallah at 13th km. on Chandragiri- 7 Gajapati 400 Antarabat-Chudangapur road 8 Gorabandha Kichling Kainpur road Gajapati 1500 9 Birikote Guluba Road Gajapati 1500 10 Jhadabhaumi-Kadapada Ganjam 5000 11 Kulangi K Banpur via Budhanta Ganjam 10000 12 Moritana Chilikhana Ganjam 5000 13 Balia Aladigaon road Ganjam 5000 Locha padi PWD road to Saktinagar via Lamanagar 14 Ganjam 500 Merisahi Badasahi rd 15 Mahulipala- Boripadar raod Ganjam 500 16 Jakari PWD road to Komaradi raod Ganjam 500 17 Paresnar pur Kutepur road Jajpur 5000 18 Achutapur- Badabarisahi road Jajpur 25000 Bridge over Kukerma nallah on Laikera-Sahaspur-Bamra 19 Jharsuguda 1 road 20 Laikera-Sahaspur-Bamara road Jharsuguda 1 21 Sashapur - Malidihi Road Jharsuguda 10000 S.B. over Perencho nallah at 5th km. alongwith Talapada- 22 Kalahandi 1 Barbandha road (0/0 to 12.00 km) Bridge over Ambaguda nallah on -Bijepur road 23 Kalahandi 5000 (30m) Bridge over river Mudra on Gambhariguda-Chikili road 24 Kalahandi 15000 (100m) Bridge over river Udanti (Tel) on Dokripada-Atigaon road 25 Kalahandi 100 (150m) 26 Bijepur road (27/0 to 38/0 Km.) Kalahandi 12500 H.L. bridge over river Khadaga on Baliguda-Katikia- 27 Kandhamal 1 Sindhigam road 4x30.63 m 28 Tikabali-Chakapada-Nediguda-Badangi road Kandhamal 1

Outcome Budget: DoRD for 2014-15 Page 46

29 Bataguda Rutungia via Pusungia road. Kandhamal 100 30 Raikia-Simanbadi road 4 km. Kandhamal 1 31 Daringabadi-Partmaha road (0 to 7 km.) Kandhamal 8000 32 Baliguda-Budaguda road Kandhamal 10000 33 Raikia Badajahari road Kandhamal 500 34 Masaripada-Kelapada-Sadingia-Balandapada road Kandhamal 1 35 Benabandha Kendrapara 7500 36 Nayadia ghat to Singhayada via krushnadaspur Kendrapara 4000 37 Gobindpur Thakur patna road Kendrapara 4000 H.L. Bridge over over river Kusei at 16th K.M. on 38 Keonjhar 10000 Harichandanapur- Daitary road 2 x 21.75m H.L. bridge over river Baitarani at 6th km. on Childa- 39 Keonjhar 5000 Rajnagar road Bridge over Ghagara nallah on Khadipala Kathakata road 40 Keonjhar 10300 (60 m) Bridge over Ghagara nallah on Anandapur-Goyalmunda 41 Keonjhar 1 road Bridge over river Musala at 12th km. on Ghatagaon- 42 Keonjhar 2000 Harichandanpur road (150m) Bridge over river Sunder Gouduni nallah on Arsala- 43 Keonjhar 2973 Chauthia road (40m) 44 Mangalpur-Bhimkund Road (10 to 15 Km.) Keonjhar 2500 45 Bridge over river Baitarani on Uchabali-Uttarposi road Keonjhar 10000 46 Bridge over Bhaluka nallah on Karanjia-Remuli road Keonjhar 20000 H.L. bridge over river Samakai nallah at 16th km Telkoi- 47 Keonjhar 2299 Madhusudanpur-Talapada road ( 1x30.63 m) H.L. bridge over river Baitarani at 1st km. on Jamudalaka- 48 Keonjhar 5635 Kankadapata-Kutraposi-Champua road 49 Batipal Talakanendi road Keonjhar 4000 50 jakara road Khurda 1500 51 Bolagada Dalei sahi road Khurda 1500 52 Biribandha Retanga road Khurda 1500 H.L. bridge over river Deogarh & Muran at 8th & 10th km. 53 Koraput 5000 on Dasmantapur-Lulla road 2 x 24.75m & 4 x 30.63m H.L. bridge over river Telingiri at 4th km. on Mundaguda- 54 Koraput 10000 Somilaguda-Nakulguda road 4 x 30.63m H.L. bridge over river Kurla at 4th km. on Kundra-Lima 55 Koraput 100 road 56 Bridge over river Kolab on Ramgiri-Raniguda road Koraput 12500 57 Koraput Mahadeiput-Panasaput ( 8.9 Km) Koraput 30560 58 Kotpad- Chirmandi ghat (5.8 km) Koraput 19241 59 Bridge over Beda nallah at 5th KM on Subei-Kunduli road Koraput 1

Outcome Budget: DoRD for 2014-15 Page 47

Bridge over Bhitarli nallah at 2nd KM on Nandapur- 60 Koraput 1 Sarabati road Bridge over Tamasa nallah on MV 5 - MV44 via MV1 & 61 Malkanagiri 442 MV4 at 3rd km. H.L. bridge over river Kalo at 4th km. on Kaptipada- 62 Mayurbhanj 15000 Podadiha road S.B. over river Kushabhadra at 3rd km. on Kaptipada- 63 Mayurbhanj 14000 Padadiha via Kulialam-Sanadei 64 Bridge over Budhabalanga on Khuntapal-Darkhuli road Mayurbhanj 20000 Bridge over river Jambhira on Kendudiha-Bhairangi-Ektaili 65 Mayurbhanj 30000 road H.L. bridge over Budhabalanga at 3rd km. on 66 Mayurbhanj 30000 Golamundakata-Kanchhinda road 67 Kadadihi-Mikdih-Thakumapatna road Mayurbhanj 25000 68 Jharpokharia-Sankhabhanga road Mayurbhanj 25000 Bridge over Ektali Nallah at 7.2 km. on Bisoi-Mahubhandar 69 Mayurbhanj 100 road (45m) Bridge over Budhi Nallah at 4.59 km. on Rasamtala 70 Mayurbhanj 100 Hatibari road (80m) Bridge over Balisutra Nallah at 2nd km. on Jamada-Hensda 71 Mayurbhanj 100 road (45 m) 72 Betnoti-Dahikoti-Merda Road (9.910 km) Mayurbhanj 100 S.B. over river Kanhu at 12th km. on Jamda- Hensada road 73 Mayurbhanj 100 13x10.77m 74 Vegidiha to Surat road Mayurbhanj 20000 75 Jaldiha to Sadheikala Mayurbhanj 10000 76 Gorumahisiani to Chandipahandi Mayurbhanj 5000 77 Baghia Tanpur to Barakati Mayurbhanj 7000 78 HL Bridge over river Sono Jeypur-Biaradihi-Debagaon road Mayurbhanj 1 Bridge over river Tentua ta 3rd KM on Anlabeni-Baunsanali 79 Mayurbhanj 1 road H.L.Bridge over river Indrabati at 8th km. on Rajoda- Benia 80 Nabarangapur 5000 Nadighat road 9 x 30.63m H.L. bridge over river Bhaskel at 2nd km. on RD road- 81 Nabarangapur 1 Ghodakhunatia road 7x30.63 S.B.over Udayapur nallah at 3rd km. on Pourabela-II to 82 Nabarangapur 1 Udayapur road ( 4x10.77 m ) Bridge over Local nallah at 1 km. on Badaolama-Gogegaon 83 Nabarangapur 1 road 84 Bridge over Turi nallah on Nabarangapur-Ambadola road. Nabarangapur 15000 Bridge over Chitrangi nallah at 15th KM on Jharigaon- 85 Nabarangapur 1 Dhamanguda road Bridge over Amrali nallah at 7th KM on Jharigaon- 86 Nabarangapur 1 Dhamanguda road

Outcome Budget: DoRD for 2014-15 Page 48

Bridge over Angi on B.M. Semla leading to Dabugaon road 87 Nabarangpur 20000 (200m) PL road to Kumuli, Chattibeda, Bharsundi to PL road. (18 88 Nabarangpur 23000 Km) 89 Bridge over river Tel on Octasil-Nagalsis road Nabarangpur 100 90 Bhogar Tendabadi rod Nayagarh 1000 91 Jamujhari to Golapokhari road Nayagarh 1000 H.L. bridge over river Sunder at 1st km. on Komana-Bhela 92 Nuapada 1 road 93 Bridge over river Sunder on Kutribahal-Kumutimunda road Nuapada 2180 94 Gorual to Balipada Sandhapur road Puri 3000 95 Danda Mukunda pur to Delanghat road Puri 4500 96 NH 203 to Basudevpur via Dubu Duba Puri 7000 97 Charichhak Top road to Temple Chhak Puri 5000 98 Ottar Balikanda to Silei road Puri 1000 Approach road to Bridge over river Daya on Kalyanpur- 99 Puri 1000 Mandarabasta Road H.L. bridge over river Bansadhara on Dangosorada- 100 Rayagada 3000 Piskapanga road 4x30.63 m H.L. bridge over river Nagavali at 2nd k.m. on Jimidipeta- 101 Rayagada 1106 Pipalguda road 4 x 30.63m H.L. bridge over river Nagabali on Kotapeta-K.Malegaon 102 Rayagada 20000 road H.L. bridge over river Jhajabati at 1st km. on near Serikana 103 on PWD road-Malipada-Tadama road alongwith long Rayagada 8000 approach. H.L. bridge over river Nagavali at 4th km. on Antamada- 104 Rayagada 10000 Denduli- road H.L. bridge over Phalphalia nallah at 50th km. on Padmapur- 105 Rayagada 100 Gudari-Raibiji road S.B. over Haduguda nallah at 1st km. on PWD road- 106 Rayagada 8000 Haduguda 107 Bridge over Bansadhara on Naira-Bainaguda road (350m) Rayagada 20000 108 Jimidipeta -Champikota road (11.25 km) Rayagada 2700 Bridge over river Nagabali on Rayagada-Baisingi via 109 Rayagada 20000 Chekaguda road 110 Junadihi- road Sambalpur 30000 Bridge over at 7th km. on Charpali-Tulundikud- 111 Sambalpur 100 Gunderpur road H.L. bridge over river Tulub at 12th km. on Bhojapur- 112 Sambalpur 1 Jaminkera road 1 x 30m.+2 x 20m. H.L. bridge over Surubalijore nallah at 1st km. on Tribenipur 113 Sambalpur 1 Chhaka-Badkhola via Bharatpur road. Bridge over Kardapal Nallath at 13th km. on Padabalanda - 114 Sambalpur 100 Badmal road (60m)

Outcome Budget: DoRD for 2014-15 Page 49

115 Bridge over Maltijore nallah on Padiabahal Tampergarh road Sambalpur 15000 Bridge over Champali nallah at 10th KM on PWD road to 116 Sambalpur 500 Rail road H.L. bridge over river Mahanadi at 6th km. on Sambalpur- 117 Sonepur to Chadheipanka-Binka road 24 x41.50+2 x Sonepur 60139 30.64m HL bridge over river Ichha at 8th km on Mahulpali Surda 118 Sundaragarh 10000 Road Bridge over Safei on Bargaon Bhoipali Kureiboga road 119 Sundargarh 20000 (120m) Bridge over Basundhara Nallah at 7th km. on Duduka- 120 Sundargarh 100 Barapali via Kuisara road (60m) 121 Pandrisila road Sundargarh 15000 122 Rungaon Sahajbahal road Sundargarh 1000 Bridge over Rukuda(Lima nallah) on RD road to 123 800 Bhadimarah road (45m) 124 Dalakudar road Sundergarh 24400 125 Bridge over Brahmani nallah on Lathikata Timjore road Sundergarh 50000 S.B. over Chandiposh Nallah on Dumerjore-Kuarmunda Via 126 Sundergarh 1 Jagdishpur road 9x10.77mtr H.L.bridge over river Safei at 2nd km. on Talsara-Bijadihi 127 Sundergarh 1 road 6x30.63 Total : 943000 04-Dist & Other Roads -800-Other Expr. H.L.bridge over Lingara nallah at 3/00 km. on Jarapada- 1 Angul 300 Purunakote rd Bridge over Hatigenja nallah at 16.20 km. on Sanahula-Paikasahi- 2 Angul 1 Kantapada road 3x25.35 m 3 Bridge over Aunli on Bagedia Sarpa road (150m) Angul 200 4 Somanathpur Ankula Gopinathpur Road (5.520 Km) Angul 20000 5 Jharbeda Jambua Road (8.0 Km) Angul 20516 6 Boinda Makarmunda Road Angul 15945 Bridge over Local nallah at 1st km. on Gopinathapur-Mandarpur 7 Balasore 1 road Bridge over Local & Genguti Nallah at 4.5 Km & 5.6 km. on 8 Balasore 5000 N.H.5 to Mulising (15m & 25m) Bridge over Chetei Nallah-I&II at 0.4 & 0.03 km.on Bayanighat- 9 Mohagab Via-Ramchandrapur Madhupur,Kusuti road Balasore 1000 (30m&30m) 10 Bridge over river Sono on Sajanagarh-Ajodhya-Tindesh road Balasore 40000 H.L. bridge over on O.T. road to Chansla. 12 11 Balasore 49649 x 30m. Bridge over Chitei nallah with approach road at 7.7 km on 12 Balasore 11987 Baharda-Bhutentuli-Laxmipatna road

Outcome Budget: DoRD for 2014-15 Page 50

H.L. Bridge over over river Ranj at 5th K.M. on Kainsir- 13 Baragarh 1 Patkulunda road 5x30.63 H.L. bridge over river Kuliarijore nallah at 1.30 km. on Kaisira- 14 Bargarh 5459 Urduna via Beherapali road H.L. Bridge over over river Ong at 2nd km. on P.W.D.road to 15 Bargarh 1 Munikela road 5x25.35 Bridge over Hirapur nallah at 1 km. on Paikamal-Jhadabandha 16 Bargarh 1 road Bridge over Badmal Nallah-I&II at 14.1 & 14.375 Km on 17 Bargarh 10000 Ambabhona-Dunguri road (25m & 20m) 18 Bhatli-Nuagarh-Sulsulia road Bargarh 25000 19 Bridge over river Ranj on Barguda to Bhatigaon road Bargarh 20000 20 Bridge over Kumudi nallah on Kansar-Darliguda Padmapur road Bargarh 25000 21 Dolasahi Guamal Tihidi road from 0/0 km. to 3/700 km Bhadrak 4896 H.L. bridge over Mantei at 7.80 km. on BC road-Matiasahi road 22 (Missing Link on Saya-Nandakandarpa PMGSY road OR-04- Bhadrak 4000 109) H.L. bridge over river Reba at 4th km. on Jhatiasahi-Mangalpur 23 Bhadrak 1 road 2 x 25.35m 24 Manjuri-Govindapur Road.(RIDF) Bhadrak 5000 Bridge over Baitarani connecting R.D.Road to Balipatna and 25 Bhadrak 30000 Ahias Kamalpur road (300m) Bridge over Palasahi & Chingadanashi nallah at 2nd Km & 5th 26 km. on Doharasahi-Paramandapur via-Chingadanashi Palasahi rd Bhadrak 1 (32m & 21m) Bridge over river Kapali at 0.7 Km on RD Road to CS Nandoor 27 Bhadrak 5000 (50m) 28 Ganijanga-Ramakrishnapur Bhadrak 14938 29 Bridge over Kandia at 4th km. on Dhusuri-Nadigaon road Bhadrak 8904 30 H.L. bridge over Lanth on Ampali-Belagaon road 11x30.63m Bolangir 1000 31 Bridge over Katangi nallah on Khaprakhol-Juria road 9 x 10.77m Bolangir 100 H.L.bridge over river Sonegarh at 1st km. on Bandhapada-Tepren 32 Bolangir 5000 road 33 H.L. bridge over Sonegarha at 2nd km. on Kuthurla-Silekani road Bolangir 15000 34 Bridge over river Lanth on Mandal-Madhyapur road Bolangir 15000 35 Salepali (PWD) road to Babejuri via Chakamal Bolangir 37657 S.B. over river Nuapali nallah at 10th km on Deogaon-Nuapalli 36 Bolangir 1 road( Jarasingh Athagaon) S.B. over Mayabati at 1st. Km. on Sarmuhana-Sunamudi road 4 37 Bolangir 1 x 30m. H.L. bridge over river Rahul at 1st km. near Gudvella on 38 Bolangir 1 Gudvella-Jammut road 5 x 30.63m. H.L. bridge over river Baurijore nallah at 10th km. near 39 Bolangir 1 Kudasingha on Singhkhaman-Kudasingh road S.B. over Lanth at 3rd km. on PWD road-Pallimal road 9 x 40 Bolangir 1 10.77m. Outcome Budget: DoRD for 2014-15 Page 51

S.B. over Ichhapada nallah at 0.500 km. on PWD road-Ichhapra 41 Bolangir 1 road 42 S.B. over Sakam nallah at 2nd km. on Fasad-Fatabahal road Bolangir 1 Bridge over Satabahani nallah on Titilagarh Muribahala road 43 Bolangir 10000 (40m) Bridge over Ghagarajore nallah at 3td km. on Turekela to 44 Bolangir 1000 Badabanki road (50m) 45 Rajendra Chhaka-NH 201 via Women's College road Bolangir 10000 46 Bridge over Suktel on Bagmud-Hirli to Luhasingha road Bolangir 25000 H.L. bridge over river Tel at 14th km. on Titilagarh-Lutharbandha 47 Bolangir 95106 road 48 H.L. bridge over river Tel at 2.50 km. on Tarava-Kantamal road Boudh 70000 49 Chahapada-Kanpur road (3.795 - 9.60 km.) Cuttack 2000 Bridge over Gobari Drainage cut at 1.250 km. on - 50 Cuttack 1600 Haribhaktapur road 5 x 8.77m. 51 Godibandha Dasrathipur road Cuttack 20000 H.L.bridge over river Birupa at 2nd km. near Jasarajpur on 52 Cuttack 1 Bheda-Anandabazar road.11x30.63m 53 Bridge over Gobari on Baradiha-Jaleswarpur road (80m) Cuttack 20000 Bridge over River Badagenguti at 2nd Km on Basudevpur 54 Cuttack 40000 Madhupur Jayapur Via-Dobandia road (300m) 55 Alarpur - Kateni road (4.07 km) Cuttack 15000 56 Katikata - Tilanga Cuttack 15000 57 Sauri Ramaswar Cuttack 20000 58 Bridge over Sedhua nallah on Khurunti Khalarda road Cuttack 70000 59 Bridge over Sapua nallah on Katakisahi-Balisahi road Cuttack 20000 60 Bridge over Teljdi nallah on Patsundarpur-Mahura road Cuttack 1 61 S.B. over Badajore nallah at 2nd km. on Tarava-Sankulai road Dhenkanal 3269 S.B. over Kuanria nallah at 9th km. Pingua-Laulai road alongwith 62 Dhenkanal 1 6 km. approach road 63 Bridge over Badajore nallah on Kalapani Banasingh road (45m) Dhenkanal 1788 64 Bridge over Lingara nallah on Nuagaon-Kankalu road Dhenkanal 34180 S.B. over Pandra nallah at 12th km. on Anantapur-Balibo- 65 Dhenkanal 1 Mahulpal road 66 Bridge over river Ramial on Hatuary-Jagannathpur road Dhenkanal 30000 67 Bridge over river Ramial on Khatakhura-Bhairipur road Dhenkanal 30000 Bridge over Benga nallah at 5th KM on Bhapur-Abhimanpur 68 Dhenkanal 1 road H.L. bridge over river Mahendratanaya at 3/80 km. on Gosani- 69 Gajapati 5000 Gurandi-Lingipur-Upalada road. 4 x 30.63m H.L. bridge over Kharkhari nallah at 2nd km. on Sama-Phasipada 70 Ganjam 1 road 2 x 30.63m. 71 Badamahuri-Samantaratnapalli via Bauribagadia road (6.90 km.) Ganjam 800 72 Khajapalli-Satanalla via Kalimeghi Beruanbadi road (8.43 km.) Ganjam 1

Outcome Budget: DoRD for 2014-15 Page 52

S.B. over Bantadhara nallah at 19th km. on Belaguntha-Gereda- 73 Ganjam 1 Lembhei road 74 Sheragada-Kumarpani Karadakara road (0/0 to 7.80 km.) Ganjam 500 S.B.over river Bodanadi at 2nd km. on PWD Road to Malingi via 75 Ganjam 1 Routi road (6x10.77 mtr ) S.B.over Banta nallah at 3rd km. on Gereda-Khetamundali road 76 Ganjam 1 (6x10.77 mtr ) HL Bridge over river Baghua at 2nd km on PWD road to 77 Ganjam 1 Bhagabanpur road 3 x 30.63m Bridge over Bada Nallah at 5.1 km. on NH-217 (NH-59) to 78 Ganjam 100 Surekhadeipur road (45m) H.L. bridge over river Bahuda connected to village Parsambha 79 Ganjam 100 (Chikiti block) to Badabaranga, Andra pradesh Chandrapur Sasan H.L. bridge over river Bahuda connected to village Jagannathpur- 80 Ganjam 100 Turibodi (Patrapur block) H.L. bridge over river Bahuda connected to village Pandri 81 Ganjam 100 (Chikiti block) to Chaitanya Chandrapur sasan Bridge over Local Nallah at 0.8,0.9 & 1.2 Km on PWD road- 82 Ganjam 100 Kusapada,Potanda Via,Kamapadia,Kedarpur (8m,24m&16m) 83 Chakundapalli-Dhumakumpa Road (6KM) Ganjam 40144 84 Mardamekha road (5 km.) Ganjam 1 Talasakar-Antarapada road from Pump House-Sakaleswar Pitha- 85 Ganjam 31451 P.D.Pur Sasan Chhaka & Sanakulai 86 Approch road to JN Sagar MIP Polsara via JN Pur Ganjam 20000 87 Janivilli road Ganjam 14000 88 Bridge over Kokolaba nallah on Manapur-Tarasingi road Ganjam 25000 89 Bridge over Jarau nallah at 21st Km on Badgada - Mohana road. Ganjam 5000 90 Bridge over Jarau nallah at 31st Km on Badgada - Mohana road. Ganjam 8000 Bridge over river Baghua on Mandar-Bellagam Via. Sodaka - 91 Ganjam 30000 Budhesuni road 92 Sikiri MDR 64-P.Ramchandrapur Ganjam 20000 Berhampur Medical Chhaka-G.Jagannathpur via Bhabinipur road 93 Ganjam 25000 (5.30 km.) 94 Darubhadra-Gandala via Maruapali road Ganjam 25000 PWD road to Gokarnapur PWD road via Jakarpali, 95 Ganjam 10000 Sanaboreda, Bada Barada, Kankeri S.B. over Kokolaba nallah near Manapur at 20th km. on 96 Ganjam 23237 Belaguntha-Gereda-Lambee road 97 Gundurisahi-Gayaganda road Ganjam 25598 H.L. bridge over river Badanadi at 10th km. on Dholpita- 98 Ganjam 1 Domuhani road 3 x 30.63m H.L. bridge over river Padma at 7th km. on Baradi-Lokamari- 99 Ganjam 25461 road 3 x 30.63m H.L. bridge over Loharakhandi nallah at 4th km. on SH 7 - 100 Ganjam 32700 Badakodanda road

Outcome Budget: DoRD for 2014-15 Page 53

101 Raipali to Gopinathpur road (7 km.) Ganjam 12307 H.L. bridge over Rushikulya connecting NH 217- Jagadei-Jahad 102 Ganjam 45000 road 103 Kendupadar-Pailipada road Ganjam 35000 104 H.L. bridge over river Rushikulya on Talhara-Vetasingi road Ganjam 60000 R.Subani to Haripur via Jhatipadara Khuntapali from 0 km to 16 105 Ganjam 100 km H.L. bridge over Rangei nallah with approach road on 106 Ganjam 20000 Mandarajpur-Ekasingi road H.L. bridge over Nandini nallah at 3/6 km. on NH 36- 107 Ganjam 20000 Krushnachhai via Seranguda road 108 Chaittanyapada-Dayapali via Godarapali & Drubandha Ganjam 30000 109 Dharampur-Gopalpur chhaka via Venkatrapur-New Boxpalli road Ganjam 15000 110 Khajipalli-Kanchuru via Mohanpali road Ganjam 9500 111 Punarkhundi to Sasan Ambagaon via saru Ganjam 20000 112 PWD road ( Harina )to Pudomari Ganjam 24000 H.L. bridge over river Bahuda at 1st km. on K.Nuagaon-BSNL 113 Ganjam 1 Pur road 114 Hinjili-Khirida road (0/0 to 2.65 km.) Ganjam 600 115 Gandala-Sadasivpur-Chandipadar road (0/0 to 4.80 km.) Ganjam 600 Buguda, PWD road to Ganjam Border Via- Chirikipada 116 Ganjam 336 & Maa singhasini Pitha 117 Nuapada Kabulpur road Jagatsinghpur 13000 Expressway Kaijhar Chhaka to Ostapal Bramhanipal road from 118 Jajpur 9000 0/0 Km to 6/300 Km 119 H.L. bridge over Balungapatia at 4th km. on Bari-Binjharpur road Jajpur 35000 120 H.L.bridge over river Budha at 5th km. on RD road-Uasahi road Jajpur 40000 Bridge over Kharastrota on Maheswarpur-Jahalaghata road 121 Jajpur 50000 (550m) H.L. bridge at Namitikiri over HLC Range-II at 9th km. & 122 Jamuna nallah at 7th km. on Ankula-Panikoili road 2 x 25.35m & Jajpur 1000 4 x 30.63m HL Bridge over river Baitarani at 8th km on Barundei- 123 Jajpur 1 Mathurapur road 24 x 30.63m Bridge over Ganda Nallah at 2nd km. on Gobardhanpur Ostapla 124 Jajpur 5000 road (30m) Bridge over river Birupa at 3rd km. on Bahujanga to 125 Jajpur 5000 Dhaudiapada road (150m) 126 Malaanandapur to Adanga Bridge (6.33Km) Jajpur 15000 127 NH-5 to Sunguda via Khosalpur Jajpur 20000 128 Duburi Expressway to Patapur via Nakadei and Sorisiapada Jajpur 5000 129 Bridge over Ganda nallah on RD road-Baghabindha road Jajpur 25000 H.L. bridge over river Badagenguti near Biramalpur at 3rd km. on 130 Jajpur 30000 Udayagiri-Majhipada road 131 H.L. bridge over Keluo on Udaya nagar Kadampal road Jajpur 30000

Outcome Budget: DoRD for 2014-15 Page 54

132 Bridge over river Utei on Karlamunda-Joradobra road Kalahandi 40000 133 Bridge over Perenchu nallah on Bhanpur-Upher road Kalahandi 28000 Bridge over river Sandul at Bramhanighat on Balipada- 134 Kalahandi 24696 Ghodapokhari road 135 Bridge over river Mudra on Chiliguda-Phupgaon road Kalahandi 20000 136 Bridge over river Kamal on Badakutru-Sankutru road Kalahandi 25000 Bridge over Digiripada nallah at 9th km. on Nuagaon-Kudutuli- 137 Kandhamal 3000 Sainipada rd Bridge over Brahmani drainage cut at 8th km. on Dobandha- 138 Kendrapara 8000 Ghagara road 139 Narayanpur to Ajgarpatia Kendrapara 100 Bridge over Peta on Singhpur Rajkanika (R&B)road-Hatasahi 140 Kendrapara 500 via-Agaada Gahampal Batapada 141 H.L. bridge over river Kani at Kalamada on RD road-Padanipal Kendrapara 100 H.L. bridge over river Kharasrota at 2nd km. on Nuabazar- 142 Kendrapara 100 Balitaraghat road 143 H.L. bridge over Babar Creek at 13th km. on Orat-Badhi road Kendrapara 8000 H.L. bridge over Guptagiri nallah at 4th km. on Gojabandha- 144 Kendrapara 1 Ramnagar road 2x30.63m H.L. bridge over river Birupa at Benipur-Kampagarh on 145 Kendrapara 1 Laxminarayanpur-Balikuda road 146 Bridge over Khola nallah on Haranasi-Barakolikhala road (35m) Kendrapara 20000 147 Gurujanga - Kajalaganda road Khurda 18938 148 Gayabandha- Olasingh road Khurda 20000 149 Bridge over river Dhanua on Madhuban Darada road Khurda 20000 H.L. bridge over Dhanua at 5th km. on Narada-Dalaksati-Rajas rd 150 Khurda 1 3x30.63m S.B. over river Malaguni (Mandakini) & river Khatial on 151 Khurda 1 Kaipadar-Siko-Gadamantri road alongwith long approach S.B. over Chatura (Bangiri) nallah at 3rd km. on Brahmagiri-Atri 152 Khurda 1 road H.L. bridge over Kusabhadra at 14/990 km. connecting Sisu 153 Khurda 1000 Ananata Pitha-Jayadev Pitha 154 Hantuada-Dhumala road Khurda 1 155 Impvt. to NH 203 to Gangotri nagar Lane-I to Lane -III BBSR Khurda 100 H.L. bridge over river Dahuka at 4th km. on Tulasipur- 156 Nayagarh 30000 Khadugaon rd ( 4x30.63 mtr on well foundation ) H.L. bridge over river Kusumi at 5th km. on Kadalibandha- 157 Nayagarh 20000 Gunthasahi road 158 Bridge over river Kuanria on PWD road-Dwarigaon road Nayagarh 9000 Bridge over Dahuka nallah at 3.90 km. on Krushnaprasad- 159 Nayagarh 12000 Anlamada road H.L. bridge over Lunijhar nallah at 2nd km. on - 160 Nayagarh 30000 Khedapada road 161 Nuagaon-Naitalia road Nayagarh 20000

Outcome Budget: DoRD for 2014-15 Page 55

162 H.L. bridge over Dahuka nallah at 1st km. on PWD road-Gateri Nayagarh 17500 H.L. bridge over river Brutanga at 10th km. on Andarikote- 163 Nayagarh 1 Ghugudupada road 3 x 30.63m 164 Bridge over Kusumi on Magarbandha - Gunduribadi road Nayagarh 30000 H.L. bridge over Dhanua Nalla near Boitabhanga on Subarnapur- 165 17000 Gabakunda road 3x 24.75 m 166 Dighalo Chhaka-Terundia via Musunupur road. Nimapada 3000 167 Bridge over Dhanua nallah on Bamanal-Balanga via-Baku road. Nimapara 25000 HL bridge over river Sunder at 5th km. on Khariar Dumerjore 168 Nuapada 1 road 5 x 30.63m. 169 Nuapada-Kuliabandha road 17.57 km. Nuapada 1 170 Bridge over river Dahanapali on Kulekela-Dahanapali road Nuapada 100 HL Bridge over river Balighai nallah I & II at 13/900 km & 171 Puri 23800 14/300 Km on Jankia-Kanasa road H.L. bridge over river Daya at 6th km. near Birakesarpur on 172 Puri 15000 Mandarbasta-Trilochanpur-Kalyanpur road 173 Mandarbasta - Kalyanpur road Puri 20000 174 Bridge over Ratnachira on Siruli Karamala road Puri 100 Bridge over river Bhargavi on Balikera-Tinikudi near 175 Puri 100 Rahadamala road H.L. bridge over Uttali nallah at 1st. Km. on Lachhipur- 176 Sonepur 3500 Kutasinga road 5x 30.63 mtr 177 H.L. bridge over river Suktel at 1st km. on Pua-Deulapadar road Sonepur 38000 H.L. bridge over river Nibruti at 1st km. on Ghatkaintara- 178 Sonepur 35000 Maradiguchha road Total : 2460000 Grand Total 4100000

The work / Scheme / Project wise allocation is tentative & may be varied in keeping with N.B : the progress of work during the course of the financial year.

PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY) PMGSY programme a Govt. of India sponsored scheme aims at providing all-weather connectivity to all unconnected habitations in rural areas of the State upto population 250 and above in 18 IAP districts & 500 and above for 12 Non-IAP districts as per present norms. Accordingly, GoI has so far sanctioned projects worth `17814.25 crore for construction of 11649 nos of roads with a length of 45190.14 Km. in different phases with construction of 275 missing link bridges on PMGSY roads for providing connectivity to 16395 habitations. Till end of March’14 `11351.39crore has been incurred for construction of 28545.14 Km. of roads including 95 missing link bridges for providing connectivity to 9777 habitations. During the year 2013-14 `1615.57 crore has been incurred by constructing 3063.22 km. of roads for providing connectivity to 1004 no. of habitations. During the year 2014-15 it has been programmed to utilize `1800.00 crore for construction of roads of 4500 km. and bridges under the scheme. Out of such utilization `1700.00 crore will be received from MoRD, GoI and balance of Rs.100.00 crore lakhs will

Outcome Budget: DoRD for 2014-15 Page 56 be provided by the State towards construction of bridges, tender premium & labour escalation. Outcome budget for the year 2014-15 under PMGSY programme

Sl. No. Name of the No. of road on- No. of bridges on- Expenditure District going/ to be going/ to be to be made takenup. takenup. during 2014-15

1 2 3 4 5 1 Angul 88 8 2 Balasore 262 4 3 Baragarh 180 - 4 Bhadrak 148 6 5 Bolangir 236 3 6 Boudh 33 2 7 Cuttack 161 6 8 Deogarh 65 - 9 Dhenkanal 95 1 10 Gajapati 172 4 11 Ganjam 256 9 12 Jagatsinghpur 77 1 13 Jajpur 127 10 14 Jharsuguda 29 - 15 Kalahandi 235 15 Rs.1800 Cr.* 16 Kendrapara 110 6 17 Keonjhar 262 13 18 Khurda 96 4 19 Koraput 206 5 20 Malkangiri 209 6 21 Mayurbhanj 269 16 22 Nawarangpur 129 4 23 Nayagarh 137 5 24 Nuapada 116 1 25 Phulbani 111 9 26 Puri 269 7 27 Rayagada 203 10 28 Sambalpur 132 9 29 Sonepur 130 3 30 Sundergarh 214 12 Total : 4757 179 * NB: Rs 1800.00 Crore includes roads , bridges , labour escalation ( Rs 50.00 Crore ) , tender premium of bridges ( Rs 23.38 Crore ) , State share of bridges ( Rs 100.00 Crore )

Outcome Budget: DoRD for 2014-15 Page 57

Work list under D.No.28-5054-COL on R&B-SP-SS-04-DOR/80-General- 800-OE/789-SCP for SC/796-TASP-1230-rural roads-37257-Biju Setu Yojana for the year 2014-15 Sl. Name of the Scheme / Project / Work District which Financial No. implemented outlay (in TRS) (including Normal,SCP & TASP) 1 2 3 4

04-DOR-800-Other Expr. 1 Bridge over Sanjamara Nallah on Raniakata-Sanjamara Road Angul 6500 2 Bridge over Himtira Nallah on Himtira-Sanjamura Road Angul 4000 3 Bridge over Samakoi Nallah on Injidi-Alluri Road Angul 4000 Bridge over Ulani Nallah at 4th km on Derenga-Ghantianali 4 Angul 9000 Road Bridge over Nandira Nallah at 5th km on Sathapada- 5 Angul 9000 Lingrakata Road 6 Bridge over river Bauli on Khalgoan Talgarh Road Angul 3000 Bridge over Angapada Nallah on Urukula Serenda-Khamara 7 Angul 5000 Angapada Road 8 Bridge over Katrapali Nallah on Kantrapali-Naktideol Road Angul 7000 9 Bridge over Naktideol Nallah on Kantrapali-Naktideol Road Angul 7500 Bridge over Bauli Nallah at 2.700th KM on Sankhapur 10 Angul 2 Kaleipada Road Bridge over Nadaka Nallah at 3.700 KM on Sankhapur 11 Angul 2 Kaleipada Road Bridge over Rukuna Nallah at 0.750th KM on Kaleipada 12 Angul 2 Maranda Road Bridge over Kumbharia Nallah at 2nd KM on Chhendipada 13 Angul 2 Chhandipada(J) Road Bridge over Ghodadian nallah on Kumursingha- 14 Angul 2 Inkarbandha-Pondapur road H.L. bridge over Badajora Nallah at 2nd Km on Kurumtap- 15 Angul 2 Gundurikhali- Similia road S.B. over Balasingha Nallah at 5th Km on Kumursingha- 16 Angul 2 Inkarbandha- Pondapur Road H.L. bridge over river Oreda Jore at 6/500 Km on Tusara- 17 Angul 2 Oreda-Kadaligarh road H.L. bridge over Aunli Nallah at 2nd km on Magarmuhan to 18 Angul 2 Hansala via-Sandhamunda road H.L. bridge over Lingara Nallah at 3rd km on Khandahata- 19 Angul 2 Angarabandha-Barasingha road H.L. bridge over river Badjura Nalla on the road from 20 Angul 2 Podapada to Govindpur 21 Bridge over Coast Canal on Tiakhia Gopinathpur Balasore 1000

Outcome Budget: DoRD for 2014-15 Page 58

Bridge over Ghagara Nallah at 3rd Km. on R.D. Road 22 Balasore 7000 (Tarini Chhack) to Malyani Via Kharadia Bridge over Kamala Nallah at 10th Km. on Bhalukasuni 23 Balasore 4000 Matiali Road Bridge over Prasanna Nallah at 1/100 Km. on Durgadevi 24 Balasore 8533 R.D. Road to Gududa Road 25 Bridge over river Jalaka on Badadhanadi to Koilisahi Road Balasore 2 Bridge over Dubdubi nallah on Lumnakhundi Kasafal 26 Balasore 2 Ghamagadia Via Sahu Chhak Ferry Ghat road Bridge over Penjwara Nallah on Nalabhar to Sarthamuhan 27 Balasore 2 Road 28 Bridge over Baharda on Baliapala -Ghungi road Balasore 2 Bridge over Palpala Nallah at 1.900 KM on Langeswar PWD 29 Balasore 2 Road at Balipati to Irda Road Bridge over Baunsamukha Nallah at 0.260 KM on NH-60 30 Balasore 2 (Gandhichhak) to Sadanandapur Road Bridge over Sindhua Nallah at 1.600 KM on Ajodhya 31 Balasore 2 Baliapal Road 32 Bridge over Kudia nallah on PWD road to Basuchakari road Balasore 2 H.L. bridge over Sagakhanallah on P.W.D. Road to 33 Balasore 2 Bankisahi H.L. bridge over Bankatira nallah on NH-5 to Ambulakuda 34 Balasore 2 road Bridge over Chhapulia (Chikidi) Nallah on N.H.5 to 35 Balasore 500 Mulising road (4 x 8.77m) Bridge over Kanchudi Nallah at 8th Km. on Godipokhari to 36 Balasore 1500 Andrei road (3 x 8.77m ) Bridge over river Kansabansa Nallah on Agnipur- Amaria 37 Balasore 5000 road (3 span of 8.77m each) Bridge over Begunia nallah at 7th KM on Ojhapokhari- 38 Balasore 2 Saradanga road Bridge over Andia nallah at 0/550 KM on Kalikapur- 39 Balasore 2 Chhotkanpur road Bridge over Andia Nallah at 1.000 Km. on Uttarpada- 40 Balasore 10745 Namkana Road. Bridge over Hanskura Nallah at 3rd km. on Anirudha Chhak 41 Balasore 1000 to Chaulti Via- Kalsimuli road S.B. over Khalajodi Nallah at 11th km. on Nahara Balim to 42 Balasore 1000 Border road Bridge over Chiteinallah on Batagram Chitrarekha Pond- 43 Balasore 7019 Putina Via- Chakaisab & Naradiha U.P. School Bridge over Chitei nallah (Near Nilipura village ) at 7th KM 44 Balasore 2 on Baharda-Bhuatentuli & Nilipura via Chirkul road Bridge over Subarnarekha river at 14th Km on Raibania O.T. 45 Balasore 2 road H.L. Bridge over Gobara Nallah at 1.5 km on Salsanda to 46 Balasore 2 Palsankasids road H.L. Bridge over Birlkiti nallah at 5.28 km on Kirtania to 47 Balasore 2 Basudevpur road H.L. bridge over river Koliari Jore connecting Haladipalli to 48 Baragarh 2 tunda Outcome Budget: DoRD for 2014-15 Page 59

49 Bridg over Jeera river on Ruhunia to Khuntpali Baragarh 2 50 Bridge over Jeera river on Jamdol to Dubenapali Baragarh 2 Bridge over river Ong on PWD road at Manlpada, to 51 Bolangir Border via Dharol, Malpada, Chhindeikela, Baragarh 2 Patraguda, Temrimal, Menkamunda road Bridge over Kapati Nallah on R.D. road at Sargul chhak- 52 Baragarh 2 Kapati Chhatishgarh border via- Bhainsadarah Const. of Bridge over river ONG from Lakhmara to 53 Baragarh 2 Chardapali, Chhattishgarh Border at Ch..0/400Km Bridge over river Ong on PWD road to Brahmandihi via 54 Baragarh 6000 Koknara road Bridge over river Uttali on Talpadar-Bijepur via Sanbaunsen, 55 Baragarh 7000 Barguda, Bandupali road 56 Bridge over river Uttali on Patharla-Tuhilamal road Baragarh 4500 57 Bridge over Baitali Nallah on Baitali-Adapani road Baragarh 6500 Bridge over Kukuri Nallah on Tumuripani-Nityanandpur 58 Baragarh 6000 road 59 Bridge over Jhitiki Nallah on Mandosil- Amethi road Baragarh 5000 Bridge over at 3rd km. on SH13-Jamsesh- 60 Baragarh 2 Chindukela road Bridge over Pathurimunda Nallah on NH6 to Bhoipura 61 Bargarh 2376 PMGSY road 62 Bridge over Banjari nallah on Gudesira NH6 via Saiyan road Bargarh 7870 63 Bridge over Kuliarijore on Nuagarh-Urduna via Hatisar road Bargarh 9500 64 Bridge over Pandakipalli Nallah on Loharachoti Machimora Bargarh 6000 Bridge over Burogarh Nallah at 2.7 Km on phulapali 65 Bargarh 4000 Bandhapali road Bridge over Arjunda nallah on Thuapalli-Arjunda PMGSY 66 Bargarh 2 road Bridge over Salandi River at 5.200 km on B.C. Road to 67 Bhadrak 10000 Nuabandha Road(70 m) Bridge Over Khandia Nallah at 1.500 km on PWD Road to 68 Bhadrak 700 Goramati Road (35 m) Bridge over River Dhala on Natiapal to Padmapur Birasa 69 Bhadrak 500 PWD Road via Mathurapur Bridge Over Chhelia Nallah at 14th km on B.C. Road to 70 Bhadrak 6000 Taladumuka Road (40 m) Bridge over Nalia Nallah at 0.400 km on T5 to Langudi 71 Bhadrak 2 Road (50m) 72 Bridge over river Sanakapali on Aluti Ramapur road Bhadrak 6400 Bridge over River Dhala Nallah at 3/10 K.M. on Bounsbag 73 Bhadrak 4000 to Sanandapur Road Bridge over River Kapali Nallah at 2/00 K.M. on 74 Bhadrak 4000 Balabhadrapur Ultanga Road 75 Bridge over River Salandi on Charigaon Chakrapadhi Road Bhadrak 4000 Bridge over River Sanaseulia jore on R.D Road to Hansapat 76 Bhadrak 5000 Road Bridge over River Sanakapali on Ramakrushnapur- 77 Bhadrak 2 Kenduapada Road Bridge over Salandi on L54 to Deulipal (Pkg No. OR-04- 78 Bhadrak 2 222) at 2.40 K.M

Outcome Budget: DoRD for 2014-15 Page 60

H.L. Bridge over Salndi river at 1st K.M. On P.W.D road to 79 Bhadrak 2 Srirampur H.L.Bridge over Nua Mantei river at 3rd km on 80 Bhadrak 2 Nischintapur-Padmapur Birasa PWD road via Madhupur S.B over Janta Mahara nallah on Dhamnagar to Falapur 81 Bhadrak 5000 Road 82 Bridge over River Reba on Manjuri to Gobindpur Road. Bhadrak 704 Bridge over Hasnabad Nallah at 3.40 KM. on RD Road to 83 Bhadrak 1614 Pangata Road Bridge over River Genguti at 1st KM. on Biroli-Sathagaon 84 Bhadrak 56 Road S.B Bridge over River Gamei on Brahmanogaon to 85 Bhadrak 5000 Pandasunighat Road. Bridge over River Kochila at 1.800 KM on PWD Road to 86 Bhadrak 2 Astak Road Bridge over Kapali Nallah at 5.500 KM on Jhatiasahi 87 Bhadrak 2 Mangalapur Road 88 Bridge over Galia nallah on B.C.Road (Kuansar) to Chardhia Bhadrak 2 89 Bridge over river Salandi on Motto-Aradi road Bhadrak 2 Bridge over Sarta nallah at 2.200Km on Biroli Sathagaon 90 Bhadrak 2 Road H.L. Bridge over Dhanantori Nallah on R.D. Road to Jaguali 91 Bhadrak 2 Chhanda road SB over Bourijore nallah on Nuapada Sahajbahal road under 92 Bolangir 8000 BSY(Span-6x10.77mtr) SB over Dhanpur nallah at 8th Km on Jamut Dhanpur road 93 Bolangir 9101 under BSY(Span-6x10.77mtr) SB over Kusangi nallah at 5th Km on Hirapur Keutipali 94 Bolangir 8000 road under BSY(Span-6x10.77mtr) Bridge over Kultapada nallah on PWD road to Kultapada via 95 Bolangir 7204 Kumuria Khairguda road.(4x8.77m) 96 Bridge over Suktel on Tamia Mudalsar road. Bolangir 10300 97 SB over Suktel nallah on Patrapali Baliabhata road. Bolangir 3000 98 Bridge over Luhurapali Nallah on Luisingha Badibahal road Bolangir 2 Bridge over Amaghat nallah on Ramachandrapur- 99 Bolangir 2 Ghatuldunguri road H.L. bridge over Suktel nallah on Kubrimahul PMGSY road 100 Bolangir 2 to Barghati road H.L. bridge over Jamjore nallah on Dalapali PWD road to 101 Bolangir 2 Khuntsamalie S.B.over Nehera Nallaha at 11 th K.M. on Bhatipada-Lebda 102 Bolangir 4000 road 103 Bridge over Tangjore nallah on Sindhekela Themra road Bolangir 5000 104 Bridge over Bagbahal nallah on PWD road to Bhuslad road Bolangir 4544 Bridge over Tentulikhunti nallah on Haldi Muribahal via 105 Bolangir 2 Tentulikhunti road H.L. bridge over Suapada nallah on Suapada to Dumerbahal 106 Bolangir 2 P.R. Deptt. road Bridge over local nallah on Similijhore - Ambagaon via N. 107 Boudh 6000 Prasad Road at 10th Km

Outcome Budget: DoRD for 2014-15 Page 61

Bridge over local nallah on Similijhore - Narayanprasad - 108 Boudh 2 Dedhenimal -Ambagaon Road 109 Bridge over local nallah on Baragaon - Kunasila road Boudh 5000 Bridge over Local Nallah ( 3 Nos) on Dahya - Talpadar - 110 Boudh 10000 Sagada Road Bridge over Local Nallah at 0/900 Km on Sainipada - 111 Boudh 3000 Sundhipadar Road Bridge over Badajhar Nallah at 0/240 Km on Purumunda- 112 Boudh 3000 Turuguda- Sagada Road Bridge over Sankulai nallah on RD road to MSG to 113 Boudh 3000 Purunapalli road Bridge over Nenon Nallah at 3rd Km on R.D. Road - 114 Boudh 2 Karadapadar via Pabulipada Barakoda road. Bridge over Sakusinga Nallah at 4th Km and Kusuma nallah 115 Boudh 2 at 5th. km on Dhalpur-Kharasankulei. Bridge over Bankamunda Nallah at 3rd Km and 116 Boudh 2 Kukupetswar Nallah at 5th km on R.D. road-Khandahata 117 Bridge over Local Nallah at 1st Km on Boudh Dhalpur road. Boudh 2 Bridge over River Mahanadi on Boudh Dhalpur R.D. road to 118 Boudh 2 Marjakuda road Bridge over Local Nallah at 7th Km on Rugudikanapada- 119 Boudh 2 Rd road. Bridge over Local Nallah at 6th Km on PWD road to 120 Boudh 2 Tundumal via Ratakhandi. Bridge over Local Nallah at 7th Km & 13th. Km on 121 Boudh 2 Similijhar Narayan Prasad road H.L. bridge over river Khadanga from Khunti Gura to 122 Boudh 2 Jamuta Bridge on Kendrapara Canal at 4th Km. on Nandol Tentol 123 Cuttacak 2 Road Bridge over River Prachi at 1st Km. on Adaspur Kasarada 124 Cuttacak 2 Road to Banamalipur H.L.bridge over Dead Paika at Raghunathpur on Hanuman 125 Cuttacak 2 Mandir Chhak-Kalarabanka via-Neutiakana road 126 H.L. bridge over river Kandal from Pahanga to Kalakha Cuttacak 2 H.L. bridge over Local nallah at on Singhala 127 Cuttacak 2 to Purusottampur road Bridge over Jhaarana Nallah on Nuataila- Bangirisinga road 128 Cuttacak 2 at 3.00km Bridge over Chatara nallah on Dhobani Nallah Karada Road 129 Cuttacak 2 at 0/500 Km. Bridge over Pokhara Nallah on Sunapal Mangarajpur road at 130 Cuttacak 2 3/800 Km. Bridge over Khajuripada Nallah at 15/00 Km. on 131 Cuttacak 2 Ramachadrapur- Kalapathar Road Bridge over Local Nallah at 13th Km. on Damapada Haladia 132 Cuttacak 2 Road. 133 H.L. bridge over Siaria nallah on Deuli Bisambarpur road Cuttacak 2 H.L. bridge over Balichaturi nallah on R.D. Road to 134 Cuttacak 2 Berhampura 135 H.L. bridge over Nuabandha nallah on Mahuladhipa to Cuttacak 2

Outcome Budget: DoRD for 2014-15 Page 62

Paikara road Bridge over Kandal river at 3rd Km on Patasundarpur- 136 Cuttacak 13000 Badamulei road 137 Bridge over Junia nallah on Kalipoi- Balipahad road Cuttacak 2 138 Bridge over Jahalnai on Chapada-Kanpur road Cuttacak 2 Bridge over High Level Canal on Sanachancho Badachancho 139 Cuttacak 5000 Road. Bridge over Taladanda Canal on Alarpur Sidheswarpur 140 Cuttacak 3000 Road. 141 Bridge over Sukanai on Triveniswar Mouda Road. Cuttacak 5000 Bridge over Mendhakhai Jora on NH-5 to Champapur 142 Cuttacak 3000 Anandabazar Road. Bridge over Chindanala river at 3rd km on Patrakana village 143 Cuttacak 8000 Road. 144 Bridge over Ganda Nallah on Agrahat Bisinahakani Road. Cuttacak 4000 145 Bridge over Kendrapada Canal at Salipur PHC road. Cuttacak 4000 S.B. over Gobari on Chahapada Kanpur Road at Jankoti of 146 Cuttacak 6000 Rs.276.00 lakhs. S.B. over Gobari on Badheichhanda Manitri Road of 147 Cuttacak 7000 Rs.290.00 lakhs. S.B. over Benga & Sapua at 0/825 Km. & 1/305 Km. on 148 Cuttacak 8000 Achalakota Village to Old Cuttack & Sambalapur Road S.B. over River Sapua at 5/900 Km. on Jenapada 149 Cuttacak 5000 Arakhapatana Road 150 S.B. over Khaira nallah at 1st K.m on Ichhapur Jhajia road. Cuttacak 4000 151 Bridge over Chandipur nallah on Chandipur Rajib road. Cuttacak 7500 152 HL Bridge over Dhania nallah on Mitikapur Hatibari road Cuttacak 4000 Bridge over Puri main Cenal on Ratagarh Godisahi 153 Cuttacak 2500 Road(6x10.77 mtr) 154 SB over river Finga on KaraKamal to Udayapur-Dal road. Cuttacak 5000 SB over river Lesma on Danda padia-Ostapur-Santanibati 155 Cuttacak 4500 road S.B. over Beluam Nallah at 4th Km on Tikilipada-Sodo road 156 Deogarh 3000 (5x10.77m) S.B. over Maajhia Nallah on Tusula Phulpathar Road 157 Deogarh 4000 (4x10.77m) Bridge over Lambodara Nallah at 1st Km on Jharasahi to 158 Deogarh 2000 Ardabahal Road Bridge over Baliapita nallah at 3rd KM on RD road to 159 Deogarh 2 Kalanda road 160 Bridge over Jautak nallah on Surubali -Madalia road Deogarh 2 161 Bridge over Matuali nallah on Chheplipali Subarnapali Road Deogarh 2 Bridge over Daunri Nallah at 1st Km on Santhapur-Raitala 162 Dhenkanal 9500 road (Zero Base 2014-15) S.B over Analei nallah at 1st km on Chandpur Gurujaguli 163 Dhenkanal 3500 road (Zero base 2013-14) 164 Bridge over Damasal nallah on NH-200 to patapur road Dhenkanal 8000 165 S.B over Batajanla nallah on Gelhikateni Saranga Road Dhenkanal 3000 Bridge over Gotiadandi nallah at 2/0 km on Roda Renthapat 166 Dhenkanal 1000 Road

Outcome Budget: DoRD for 2014-15 Page 63

H.L. bridge over Badajore nallah at 1st km on on P.W.D. 167 road (Paribesha Vihar) to Tipeijharana via Madarangamunda Dhenkanal 2 road H.L. bridge over Badajore nallah on Govindpur -Hundisahi 168 Dhenkanal 2 P.R.Road HL Bridge over Mahendratanaya river Bagasala 169 Gajapati 3500 road at 5.4 Km of PWD road to Bagasala Agarkhandi road. 170 Bridge on Padmapur Jeeba RD road at 0/750Km Gajapati 2 Bridge on Kokolaba Nallaha at 14/0Km. on Gundrisahi 171 Ganjam 2 Gayaganda Road SB over Loharakhandi at 4/9 Km of Bhanjanagar PWD 172 Ganjam 15000 Road to Bhaliakhai PWD Road via Gamundi 173 Bridge over Jamakunda Nallah on Bhetanai - Badagada road Ganjam 2 Bridge over Renguti Nallah on Kodala - Renguti - Somma - 174 Ganjam 2 Achuli Jn. Road Bridge over Sandhi Nallah at 5th Km. of PWD Road to 175 Bhagabanpur (Box cell 3 x 8M x 4M at 1st Km & 2 x 8M x Ganjam 2 4M at 2nd Km.) Bridge over Rushikulya Tributarty on Ranjhalli - Hundata - 176 Ganjam 1990 Hottapur Road H.L. Bridge over Loharakhandi at 2nd K.M. of Bahadapadar 177 - Nandinipalli via Gurabadi - Chadheyapalli road (3 X Ganjam 1580 25.35) Box Cell Bridge over Kothia Nallah on MDR-62( NH-217)- 178 Ganjam 1060 Ghasibilli road Bridge over Kokalaba Nallah at 1/3 Km on Jadadhara - 179 Ganjam 2 Masabadi Road Bridge over Kokalaba Nallah on Gayaganda - Nabagochha 180 Ganjam 2 Road Box cell Bridge over Kadamba Nallah on Kodala - 181 Ganjam 7000 Mardamekha- Ghodapada Road Bridge over Sitamba Nallah at 10/650 Km on Janivilli - 182 Ganjam 2 Sorada - Badagada Road Bridge over Satrusola Nallah at 6th K.M. of Katakala- 183 Ganjam 2 Bhamasiali Road 184 S.B. over Sara Nallah on K.Barapur - Ustia Road Ganjam 2 S.B. Bridge over Boda Nadi at 2nd K.M. of Adheigam - 185 Ganjam 2 Nimapadar road Box Cell Bridge over Gahanju Nallah at 8/150 KM on 186 Ganjam 9000 Babanapur-Maharajpur Road SB over Sana nadi at 1/5 KM on PWD Road to Rangameru 187 Ganjam 7000 Road Box cell Bridge over Boda nadi at 2nd Km on J.N.Prasad- 188 Ganjam 6000 -Alsu Road H.L. Bridge over Rushikulya at 3/8 KM on NH-217 to 189 Ganjam 2 Genja via B.Kotibadi SB over Kaliamba Nallaha at 3rd Km on Binchana 190 Ganjam 7000 Badaborsingi Road Bridge over Rutray nallah at 2nd KM on SH17 -Chhanameri 191 Ganjam 2 (Nuasahi ) road H.L. bridge over Badanadi at 1st. Km on Turumu - 192 Ganjam 2 Berhambadi road

Outcome Budget: DoRD for 2014-15 Page 64

H.L. bridge over Badanadi at 1st. Km on Kulada - 193 Ganjam 2 Dhananjaypur Sasan road H.L. bridge over Local nallah on Jholori to Manikpur road, 194 Gorumatia nallah on Mala tentulia to Khajuria road & Ganjam 2 Pokosunga nallah on Bhabarada to Gopiapalli road H.L. bridge over Chatura Nallah on RD road to Ranigaon via Baragaon road, Baragaon to Gothiali road,Jayamangala 195 Ganjam 2 nallah on RD road to Kusapur road & Sunathara to Mahanandapur road Bridge over Local Nallah (Patharabandha) at 3rd Km on 196 Ganjam 3000 Sasanpadar Mantridi road Bridge over Local Nallah on Sikharpur Sahapur (Khajapalli) 197 Ganjam 4000 road Bridge over Local Nallah on Chaitanapada to Dayapali Via: 198 Ganjam 2500 Godarapalli 199 Bridge over Sagadia Nallah on Sundarpur Duanpalli road Ganjam 3500 200 Bridge over Salt canal on NH-5 to Gokharakuda road Ganjam 2500 Bridge over Makhana Nallah at 3/244 Km on Sorala to 201 Ganjam 5000 Sunapur Via: Krupanidhi Pentho road Bridge over Sulia Nallah on Moulabhanja to Khuludi 202 Ganjam 5000 Nuagada road Bridge over Sulia Nallah on PWD road to Harina to 203 Ganjam 4000 Podamari 204 Bridge over river Bahuda on Sanakelajhali Dauni road Ganjam 2 Bridge over Nandini Nallah at 2nd Km on Kurula chhaka to 205 Ganjam 2 Gothagam via Mahurikana road Bridge over Local Nallah or Kaliaballi Chaka to 206 Ganjam 2500 Madhabapur Bridge over Dengapara Nallah at 3/500 Km & Khari Nallah 207 Ganjam 4000 at 4/600 Km on Bhismagiri RD road to Baramunduli road Bridge over Badabandha Nallah on Burukudi to Phulta 208 Ganjam 5000 Dumudumi road Bridge over Tota Nallah at 2nd Km Turuburai 209 Ganjam 5000 M.Jaganathapur road 210 Bridge over Local Nallah on 1st Km Khirida to Hadachira Ganjam 2000 Bridge over Local nallah on Dengapadar Indirabbas to 211 Ganjam 2 Rohigam road. Bridge over Raoutray Nallah at 4/00 Km on Podamari 212 Ganjam 2 Borigaon road H.L. bridge over Padmatala nallah at 0/5 km on Chiripadi to 213 Gudiapadar road & Iskapada nallah at 1/5 Km on Ganjam 2 Madarajpur-Dankalpada road 214 H.L. bridge over Local nallah Sindurapur - Duanapali road Ganjam 2 H.L. bridge over Nandini nallah Raktapata to Gambhariguda 215 Ganjam 2 road H.L. bridge over Rusikulya Canal at 4th Km on Bhaliajholo 216 Ganjam 2 PWD road to Erenda PWD road via Patharapunji road H.L. bridge over Ramanadi at 9/3 km on Dengaosta PWD 217 Ganjam 2 road to Kaithakhandi via N.K.Pintha. 4500 218 Bridge over Hansua (Ratanjodi) on Kaijanga Parabil Road Jagatsinghpur

Outcome Budget: DoRD for 2014-15 Page 65

Bridge over river Potanai Pokamul Devi Right Canal 219 Jagatsinghpur 10000 Embankment Bridge over river Divi near Dahanikhia on Machhagaon 220 Jagatsinghpur 16400 Asilo road Bridge over river Jatadhari near Baliamara on Manapur 221 Jagatsinghpur 5000 Kandha road to Gadakujnga via Bhuinpal Bridge over river Adsanga Nallah Erasama Pokhariapada 222 Jagatsinghpur 3000 Road Bridge over river Brudhanallah on Rahama Sariki 223 Jagatsinghpur 3000 Nuapokhari Rosd 224 Bridge over river Hansua on Kaijanga Parabili road Jagatsinghpur 3000 Bridge over Gobari on Biribati - Alipingal road connecting 225 Jagatsinghpur 2 to Patasara road. Bridge over river Madhapur Safei (Hansua) at 4th Km on 226 Jagatsinghpur 2 Sampur Nuapada Road . 227 H.L. bridge on Bansa to Salijanga road Jagatsinghpur 2 228 H.L. bridge on Borikina-Sumuda road at Balisahi Jagatsinghpur 2 Bridge over Kaninallaha at 0.35km on Ahiyas Kamalpur 229 Jajpur 5000 road for 2011-12 230 Bridge over Chingudianallah on Bari Binjharpur road Jajpur 3000 Bridge over Kusi nallah on GP Jajpur block via 231 Jajpur 4000 Beleswar road 232 Bridge over Jamuna nallah on Beruda to Jalahara road Jajpur 7500 233 Bridge over Kaliapani nallah on Ranapur Odapada road Jajpur 5000 234 Bridge over Kantapal nallah on Sukinda Kuhika road Jajpur 1700 235 Bridge over Ordapal nallah on TISCO gate to Deogaon road Jajpur 3000 Bridge over river Bramhani near Chandanpur on Golakunda 236 Jajpur 10000 Indupur road 237 Bridge over Kani Nallah on Baulanga Patri Kamalpur road Jajpur 4000 Bridge over Kaliapola nallah on Kadamachhaka to 238 Jajpur 4000 Godarapal nallah 239 Bridge over Pandara nallah on Bambilo Kuhika road Jajpur 6092 Bridge on River Sankhua at 6th Km.on Mangalpur Dandisahi 240 Jajpur 2 road Bridge over Sankhua nallah at 3rd Km. on Boulanga 241 Jajpur 2 Akhusahi road Bridge over Mainsipahara Nallah at 7th Km. on TISCO gate 242 Jajpur 2 to Deogaon road Bridge over Dudhei nallah at 0.3 Km on Sujanpur- Rudrapur 243 Jajpur 2 road. 2 nos H.L. bridges over river Brahamni on Jhalpada 244 Jajpur 2 Brahamabrada G.P. Routarpur G.P, Samantrapur G.P 245 H.L. bridge over river Budha on Champa - Chanda road Jajpur 2 246 Bridge over Dappa Nallah on Haripur to Karjanga road Jajpur 4000 Bridge over Rasuna Nallah on Narasinghpur Sikchilabag 247 Jajpur 500 Rasuna road 248 Bridge over Kelua Nallah on Talua Musatikiri road Jajpur 3000 Bridge over river Sanagenguti at 3rd km. on N.H-5 to 249 Jajpur 5000 Sakuntalapur 250 Bridge over Anjiara Nallah on N.H-5 to Balangia road Jajpur 6000

Outcome Budget: DoRD for 2014-15 Page 66

Bridge over River Sanagenguti at 3rd KM on NH-5 251 Jajpur 4000 Sukadeipur to Dihakaranda 252 Bridge over river Sagadia on Chakrada to Sundaria road Jajpur 2 253 Bridge over Charbatia nallah on Haridaspur to Kolha road Jajpur 2 Bridge over Local Nallah at 1/470 Km.on NH5 to 254 Jajpur 2 Sankuntalpur Bridge over Gudipania Nallah at 3/500 Km.on Haripur to 255 Jajpur 2 Karajanga road Bridge over river Dappa at 1/500Km.on Chandipur to 256 Jajpur 2 Kolathala road Bridge over river Kuanria at 6/000 Km. on Rahadpur to 257 Jajpur 2 Kampalu road H.L. bridge over Rahasola Nallah on the Nuasunguda 258 Jajpur 2 Khetrapal road at 0.50 km 259 H.L. bridge over river Kelua from arabal to Rambhapur road. Jajpur 2 Bridge Over Gudigaon Nallah on Patrapali - Gudigaon 260 Jharsuguda 2 PMGSY Road. 261 Bridge over Local Nallah on Perifery - Sunary Road. Jharsuguda 4200 262 H.L. bridge over river Bheden Hirma to Malda road Jharsuguda 2 S.B.over Bhatrajore Nallah at 1/0Km on Kupagaon to 263 Kalahandi 10000 Paduapada Road 264 Bridge over local nallah on PWD road to Siripur road Kalahandi 2 Bridge over Kukudi nallah at 13th km. on Badakarkote- 265 Kalahandi 2 Badapujariguda road Bridge over Nuapada nallah at 16th km. on Badakarlakote- 266 Kalahandi 2 Badapujariguda road 267 Bridge over river Sandul on Balipada-Lupra road Kalahandi 2 268 Bridge over Kumbherjori nallah on R.D. road to Ranipanga Kandhamal 1500 S.B. over Budhajore nallah at 10th Km on Chakapada 269 Kandhamal 3601 Archangi road. 270 HL bridge over Damdei nallah on Barakhama Sitapadi road Kandhamal 2000 Bridge over Badabanga nallah at 16th Km on Raikia 271 Kandhamal 2000 Simanbadi road. 272 Bridge over river Birupa at 1st KM on Chhoti-Mugabari road Kendrapada 2 Bridge over Gobari dead channel on Bagadia Dasipur 273 Kendrapara 2 PMGSY Road H.L. bridge over Ashrunkhala Nallah at Mantei on Nuapada 274 Kendrapara 2 Antei R.D. Road to Manikpur Batira R.D. Road H.L. bridge over Gobari on Khairbad Allijanga to Chakada 275 Kendrapara 2 Baranga Nagapura P.R. road Bridge over Seuladanda Nallah at 3rd Km.on Chandigadi- 276 Kendrapara 2 Mahasahani road Bridge over Kolathia Nallah at 3rd Km on Penthapal Balikira 277 Kendrapara 2 road HL Bridge over river Baitarani at 7th Km.on Pegarapada 278 Kendrapara 2 Manpur road H.L. bridge over Kharasrota Sakha Nallah on Habalaganda 279 Kendrapara 2 Patna Chhal to Boulajodidia roat at 1st km 280 H.L. bridge over river Patsala at Gupti-Jhunus nagar Kendrapara 2 281 Bridge over river Gobari on Kupuni to Gandakhia road Kendrapara 10000

Outcome Budget: DoRD for 2014-15 Page 67

(1span of 30.63mtr.) Bridge over Sarumuhin Nallah on Adoi to Sarumuhin road 282 Kendrapara 5000 (1span of 25.35mtr.) Bridge over Tantiapal Nallah on Gunthi-Tantiapal road 283 Kendrapara 5000 (1span of 25.35mtr.) Bridge over Ambura Nallah on Belarpur High School to 284 Kendrapara 7000 Laxmanjew Temple Office road. (3span of 10.77mtr.) Bridge over Machha Bandha Nallah on Gobara Chhak to - 285 Kendrapara 3000 Chaulia - Bamara road. (Boxcell 4span of 6.14mtr.) 286 Bridge over Kharianga dead river on Podal to Jamdhar road. Kendrapara 3000 287 Bridge over Patanallah on Manikpur Batira road. Kendrapara 2 Bridge over Chandal Patanallah Nallah on Cuttack 288 R & B Road (Ramachandi Thakurani) to R & B Kendrapara 6000 road. HL Bridge over river Brahmani Creek on Angadaghat to 289 Kendrapara 10000 Nangadaghat road (span of 30.63 mtr) HL Bridge over river Brahmani Creek on Kerdagarha to 290 Kendrapara 4000 Chandan pur road (1 span of 25.35mt) Bridge over Peta nallah at 5th km on Domunda to Kanpur 291 Kendrapara 500 road Bridge over Luna nallah on Duhudipur to Badamohanpur 292 Kendrapara 7000 road Bridge over Sarajori Nallah on Govindpur Thakurpatana 293 Kendrapara 4000 road 294 Bridge over river Gobari on Nagespur to Derabish road Kendrapara 2 295 Bridge over Aradei Nallah on Karanjia-Remuli road Keonjhar 12000 Gop Branch Canal at 4.660 Km on Athantar to Nuagaon ( up 296 Khurdha 2 to Banamalipur) road 297 Bridge over Barabatia nallah on Prataprudrapur Kenduli road Khurdha 1570 Bridge over Kanheidanda nallah on Malipada-Hadapada 298 Khurdha 3092 road 299 Bridge over Hada nallah on - Dhalapathar road Khurdha 1430 300 Bridge over Balia nallah on RD road Parabola-Nimuna road Khurdha 2 301 Bridge over Hada nallah on Nayapatna - Belapadar road Khurdha 5000 Bridge over Mahujhara nallah (Kusumi nallah) on N.H.5 to 302 Khurdha 7000 Pariorada Via Orada road 303 Bridge over river Prachi on Ramachandrapur Chitalpur road Khurdha 4000 Bridge over river Gangua Nallah on N.H.203 to 304 Khurdha 7000 Mohavirnagar road Bridge over Daya Canal on Nandankanan to Kendupatna via 305 Khurdha 5000 Padasahi road at 1/300 Km Bridge over river Kansari at 1st Km of N.H.5 (Bankiapalli) 306 Khurdha 4000 to Lambodarpur road 307 Bridge over river Hada on PWD road to Asanapali Khurdha 4000 Bridge over river Kusumi (Mahujharanallah) at 1st Km on 308 Khurdha 5600 Singarama to Panasapur. H.L. bridge over river Kushabhadra on Jhinkiridihi to 309 Khurdha 2 Pratapnagar road. 310 H.L. bridge over Gangua nallah on Bikipur to Kuha road. Khurdha 2 311 H.L. bridge over Satasankha nallah on NH-5 to Phulagarada Khurdha 2

Outcome Budget: DoRD for 2014-15 Page 68

road 312 H.L. bridge over Prachi on Bhanara to Kudapatna road. Khurdha 2 H.L. bridge over river Malaguni on Nirakarpur to Talapada 313 Khurdha 2 road H.L. bridge over Local nallah on on 314 Khurdha 2 Panchupalli village road H.L. bridge over river Hadanala from Bankoi to Binodpada 315 Khurdha 2 via Kanteilo of Block. Bridge over Raju Shankar Nallah at 2nd km on Pukali 316 Koraput 5000 Sambai Road 317 Bridge over Sim Nallah on Simdiha Boring road. Mayurbhanj 10000 H.L. Bridge over river Duanto on Panchrida-Rohibanka- 318 Nayagarh 9000 Banthapur Road 319 H.L. Bridge over local Nallah on Sulia-Kantilo Road Nayagarh 5000 320 H.L. Bridge over river Kusumi on Mardarajpur-Bodasa Road Nayagarh 7000 H.L. Bridge over river Malaguni on Natim-Mayurjhalia 321 Nayagarh 7000 Road Bridge over Brutanga river on Banigochha to Dasanipada 322 Nayagarh 5000 Road 323 Bridge over river Kusumi on Bhadikila-Ostia Road Nayagarh 7000 324 Bridge over Lunijhar nallah on Itamati-Balikudia Road Nayagarh 500 325 Bridge over river Kusumi on Angisingi-Dhusuma Road Nayagarh 500 326 Bridge over river Kusumi on Khandapada-Banamalipur road Nayagarh 2 Bridge over Nagajhar nallah on 4th Km of Godipada 327 Nayagarh 2 Kakalaipalli road H.L. bridge over river Duanto on Sanagorada to Bhaliadihi 328 Nayagarh 2 via. Bilagorada road 329 H.L. bridge over river Sulia on Udayapur Pallisasana road Nayagarh 2 330 Bridge over river Duanto on Nandighar-Laudaput road Nayagarh 2 Bridge over local nallah (2nos ) on Banthapur-Rohibanka 331 Nayagarh 2 road S.B. over Local (Dhobenjore) Nallah at 2 Km on Sindursil- 332 Nuapada 9000 Talakot Road S.B. over Kusumtala Nallah at 1st Km Budhikomna- 333 Nuapada 11500 Dhumabhata Road S.B over Kadua Branch Canel on Sukapokhari Santrash Via 334 Puri 6000 Kajalapatia road H.L. Bridge over River Kadua on Palabasta Tellkud road 335 Puri 10000 under Biju Setu Yojana H.L.Bridge over River Prachi on Somanathpur Tavagorada 336 Puri 10000 road under Biju Setu Yojana. H.L. Bridge over River Devi at 0.00 Km on Talada - 337 Puri 19079 Dihakarada road H.L. bridge over river Kushabhadra on Dalanai 338 Puri 2 Balikapileswar road H.L.bridge over river Makara on Badakharad- Badal road at 339 Puri 10000 5.7 Km road. H.L. bridge over river Bhargavi at 4th Km. on 340 Puri 10000 Biswanathpur- Panibhandar - B.Gadadharpur.

Outcome Budget: DoRD for 2014-15 Page 69

Box Cell Bridge over Local Drainagecut at 1/00 Km. on 341 Puri 2 Dandamakundapur Delanghat road 342 Bridge over Dhanua on Sanapalli Podapada Road Puri 2000 Bridge over Ratnachira on N.H 203 to 343 Puri 2000 Biraramachandrapur(Kadua-) Road Bridge Over river Luna on Dandamakundapur to Delanghat 344 Puri 2 Road 345 Bridge over river Dhanua on Nalihana- Gaindol Road Puri 2 H.L. bridge over local nallah at 1st Km on Maligaon 346 Puri 2 Singhberhampur road 347 H.L. bridge over local nallah on Brahmanpada Atheisa road Puri 2 H.L. bridge over river Bhargavi on NH-203 TO Kanchi 348 Puri 2 Bridge approach road H.L. bridge over river Luna on Nikhila Govindpur 349 Puri 2 Majhipaida 350 Bridge over local nallah on Khirisahi -Berhampur road Puri 2 351 Bridge over Surubali Nallah on Podabalanda Badmal Road Sambalpur 4500 S.Bridge over Murmuri nallah at 7th km on Davla 352 Sonepur 5000 Akhidadar road ( 5 x10.77 Mtr) Bridge over Dahukbed nallah on Cherupali Mahada road ( 353 Sonepur 1600 3x8.77 Mtr) Bridge over Chouki & Panikhai nallah at 9/7 km & 10/200 354 Sonepur 4000 KM on MDR 39 to Nandanmal road (6x10.77 m) Bridge over river Tel at 4th km. on Hardakhole- Baidyanath 355 Sonepur 2 road H.L. bridge over Local Nallah at 1st km on Bandhapali- 356 Sonepur 2 Jhulpiapali road H.L. bridge over Lamloi nallah at 2nd km on Lamloi to 357 Sundargarh 2 Luhakhan road Total: 978000

80-General-789-SCP for SC Bridge over Singada Nallah on Kuskila Kosala via Barpada 1 Angul 3000 Chankundapal Road 2 Bridge on Nandira Nallah on Angul Kalamchhuin Road Angul 5500 Bridge over Singada Nallah on Badatribida-Chandrabil- 3 Angul 1000 Soloda Road H.L. bridge on Singada Nallah at 1st Km on Baghabaspur- 4 Angul 2 Ranjagoda Road Bridge over Khaparapada Nallah at 6.800 Km. on R.D.road 5 Balasore 3500 to Sankarpada Via- Bagada, Alda Road. Bridge over Chhapulia Nallah at 0.722 Km. on Kuruda to 6 Balasore 5000 Ainiri road Constn. of bridge over Reba Nallah at 8th Km. on Bariha to 7 Balasore 5000 Nuabaj road 8 Bridge over Chikiti nallah on PWD road-Thalabartana road Balasore 2 Bridge over Local Nallah at 1st km. & 2nd. km. (3 nos) on 9 Balasore 2 R.D road to Balarampur road Bridge over Local Nallah at 2nd km. on Khaira to Oupada 10 Balasore 2 Via- Kukudia road

Outcome Budget: DoRD for 2014-15 Page 70

H.L. Bridge over Kansabansa Nallah on Brahmana Sabira to 11 Balasore 2 Patuli H.L. Bridge over Coast canal at 2nd km on Kulhadnada to 12 Balasore 2 Badatalapada road. Bridge over Ghagara nallah connecting Kesura-Ringpur 13 Balasore 2 road H.L. bridge over river Rancha Nadi on Kumbhari G.P. To 14 Baragarh 2 Patakulunda G.P. Bridge over Kharmunda Jore on Kalangapali to main canal 15 Bargarh 3000 road 16 Bridge over Matuali jore on Lastala Dangarla road Bargarh 4000 Bridge over Salandi River at 2.100 km on PWD Road to 17 Bhadrak 2000 Bentala Road(55 m) Bridge over Hansdia Nallah on Shyamsundarpur Upper 18 Bhadrak 5000 Dumka to taladumka road Bridge over River Kochila at 1.42 KM. on RD Road to 19 Bhadrak 7400 Balipatana road. Bridge over Kapali on RD Road to Khaparapada at Chainage 20 Bhadrak 4000 0/900Km Bridge over river Barakolimahara at Chiainage 3/100 Km on 21 Bhadrak 2 Dhamangar Falapur road Bridge over river Biruan Mahara at Chiainage 3.500 Km on 22 Bhadrak 2 Dhamangar Falapur road H.L. bridge over river Baitarani at Hasanabad-Pallhasahi 23 Bhadrak 2 uner Hasanabad G.P. H.L. Bridge over Chhatra jore nallah on Karanjamal to 24 Bhadrak 2 Bhuansul road Bridge over Nibrutijore on Jaljodipali to Kulegarh 25 Bolangir 5000 road.(Span-8x10.77mtr)open 26 Bridge over Chinched nallah on PWD road to Chinched road Bolangir 2 Bridge over Kusangi nallah on Bolangir-Chandanabhati 27 Bolangir 2 road H.L. bridge over Lanth on Badimunda PMGSY road to 28 Bolangir 2 Saintala 29 H.L. bridge over Kasangijore on Pandrani to Manhira Bolangir 2 30 Bridge over Kusasinga Nallah on R.D Road Boudh 2500 31 Bridge over Kutijhar Nallah on Bukasinga to Kutijhar Road Boudh 2500 Bridge over Somapaju nallah at 7/100 KM on Baghiapada- 32 Boudh 2 Somapaju-Panisal road Bridge over Somapaju nallah at 8/100 Km on Baghiapada- 33 Boudh 3000 Somapaju-Panisal road. Bridge over Local Nallah at 15th on Baghiapada- Sagada 34 Boudh 2 road Bridge over Local Nallah at 3rd Km and at 4th Km on 35 Boudh 2 Narayan Prasad Landapalli road. Bridge over river Salki on PWD road to Olanda -Kamira 36 Boudh 2 road. Bridge over Arkhei Nallah at 4th Km on S.H to Jadagola 37 Deogarh 2000 road (8x10.77m) Bridge over Siaria nallah at 2nd KM on Basantapur- 38 Deogarh 2 Gundiapali road

Outcome Budget: DoRD for 2014-15 Page 71

Bridge over Lingara Nallah on Khajuriakata-Sanjapada R.D 39 Dhenkanal 400 road to Rakala P.S road S.B over Andhari Nallah at 5th Km on Santhapur-Marthapur 40 Dhenkanal 2000 road Bridge over Bhagiagoda Nallah at 3rd km. on Nadhar- 41 Dhenkanal 7500 Ramachandi road H.L. bridge over Kantei Nallah on Balsar to Sudhakantamila 42 Dhenkanal 2 P.R.road 43 H.L. bridge over Rigidi nallah on Badkalakote to Rigidi road Gajapati 2 Bridge over Angu Nallah on Sunathara - Angu - Hindula 44 Ganjam 300 Road Bridge over Swapenaswar Nallah at 5th K.M. of Sadara - 45 Ganjam 2 Golapada road (SB 4 X 10.77) Box cell Bridge over Natchuni Nallah at 2nd K.M. of 46 Budurungu R.D. Road to Chellakhai PWD Road vide Ganjam 2 Sisunda Charichhaka road (Box cell 3 x 8m x 4 M) SB over Loharkhandi Nallah at 3/6 Km on Mujagada to 47 Ganjam 4000 Rambhapalli Road SB (5 x 10.77 M) HL Bridge over Baghua at 3/4Km on Polosara Bartini via 48 Ganjam 7500 Belaqgam Dimiria Road . (HL:4 x 30.63M) SB over Kaliamba Nallaha at 3/3 Km on Nunipada to 49 Ganjam 7500 Sanadodanga Road (SB (6 x 10.77 M) Bridge over Kharkhari Nallah on Badarampalli Bilaspur 50 Ganjam 6000 Road Road H.L. bridge over river Padma on Madhabapur-Dhanapur 51 Ganjam 2 road Bridge over Bandhaghatnallah on Kirtipur Hatipada 52 Ganjam 5000 Golabandha road Bridge over Kela Nallah Erasama Champahat via 53 Jagatsinghpur 3000 Kothinimol Bridge over river Biluakhai on Dhanipur-Gelapur road via 54 Jagatsinghpur 11400 Kantilo Well foundation Span 10 x 30.63 mtr Bridge over river Alaka at 7th Km. on Salijanga PMGSY 55 road Khaleri via-Agarpur, Alijanga, Tanduani and Godida Jagatsinghpur 2 road 56 Bridge over Canal at 0/00 Km on Dhanipur - Kantilo Road. Jagatsinghpur 2 57 H.L. bridge on Deulisahihat to Dhaulikuda road Jagatsinghpur 2 58 H.L. bridge on Hansra to Kalikuda road Jagatsinghpur 2 Bridge over Dudheinalla on MDR 14 to Dihasahi road for 59 Jajpur 6500 2011-12 60 Bridge over Banapur nallah on Bari Binjharpur road Jajpur 2500 61 Bridge over Adan nallah on 10th km on Bari Binjharpur road Jajpur 3000 62 Bridge over local nallah at 8th km on Bari Binjharpur road Jajpur 3000 Bridge over Safai at 4.400 KM on Katia Ahiyas Bainsipan 63 Jajpur 2 Raod Bridge on River Kharasrota at 0.00 Km. on Kamalpurghat to 64 Jajpur 2 Dhaudibandhaghat 65 Bridge over Kharasrota at 3rd Km. on Mainda Ghantiali road Jajpur 2 Bridge over Gadagadi nallath at 2.15 Km and Nuamahara 66 Jajpur 2 nallah at 5.10 Km on BCJ High School to Badakuanla road.

Outcome Budget: DoRD for 2014-15 Page 72

H.L. bridge over Jamuna nallaha on R.D. Road to 67 Jajpur 2 Ghanashyampur Sasan road. H.L. bridge over Ganda nallaha on R.D. Road (Mulasara) to 68 Jajpur 2 Olala road. H.L. bridge over Katha nallaha & Gadabandha nallaha on 69 Jajpur 2 Gadabandha to Jundupur road 70 Bridge over Kuanria Nallah on Taranjia to Parikheta road Jajpur 4000 Bridge over Kainbila Nallah at 4th KM on NH-5 to 71 Jajpur 4000 Kantigadia via Sidhipur Road Bridge over Gohira Tikira Nallah at 0.5 KM on 72 Jajpur 800 Kabatabandha Rekhideipur Road Bridge over River Badagenguti at 11th KM on Nuahata to 73 Jajpur 10000 Khadianga Road Bridge over Baunsa -Anta nallah on RD road to Panturi 74 Jajpur 2 Road Bridge over Hatianallah on Ramachipidihi to Routbahal 75 Jharsuguda 10000 Road. 76 Bridge over Bungaberna Nallah on Deopan Bhimjore Road. Jharsuguda 10000 H.L. bridge over river Saraswati nallah on 1st km of NH 49 77 Jharsuguda 2 to Betajharam H.L Bridge over Rahul River on PWD Road to Benaguda 78 Kalahandi 1000 Road 79 H.L Bridge over Udanti River on Artal to Dumeria Road Kalahandi 20000 S.B.over Local Nallah (Turupi ) at 7/0 Km on 80 Kalahandi 7400 Maddingpadar - Singhjharan Road Minor Bridge over Bijepur nallah on Biswanathapur-Bijepur 81 Kalahandi 2 road at 37/300 KM Bridge over Lakhabahali Nallah at 24 km. on Biswanathpur- 82 Kalahandi 2 Bijepur Road Bridge over Local Nallah at 17th km on Biswanathpur- 83 Kalahandi 2 Bijepur Road H.L. bridge over river Mangalijore nallah on Jogipala to 84 Kalahandi 2 Sahajpati H.L. bridge over river Pipal nallah on Kamthana to 85 Kalahandi 2 Ghusurigudi Bridge over Kutrasingi nallah on SH-1 to Pankua Nuagaon 86 Kandhamal 2 road 87 Box cell bridge on Subarnagiri Budaguda road Kandhamal 800 H.L. bridge over Local nallah on Taladandikia-Akapratha 88 Kandhamal 2 road. H.L Bridge over river Gobari on Raghudeipur - Raitundi 89 Kendrapara 7400 road (2span of 30.63mtr.) 90 Bridge over Hansua Creek on Baunsanali road Kendrapara 3000 Bridge over Remal river on keshdurapal- Brahmanipal Road 91 Keonjhar 2 at R.D 14/800 km Bridge over Local Nallah on Santoshpur- Singnali Road, 92 Keonjhar 2 (Pkg No. OR-17-284) at R.D.4/600 km 93 Bridge over on Ambo-Batto Road Keonjhar 2 Bridge over Baunsa Nallah at 3rd Km on Banapur Ayatpur 94 Khurdha 2 road in the Dist. of Khurda. Bridge over Daya West Branch Canal on Nandankanan to 95 Khurdha 1000 Jaripatna Via Injana road

Outcome Budget: DoRD for 2014-15 Page 73

H.L. bridge over Kenduguda nallah at 2nd km on 96 Malkangiri 2 Kenduguda Darkajodi road Bridge over river Poteru on Old Chitapari -Balimela 97 Malkangiri 2 township road Bridge over Potteru Nallah at 23rd km on Podia to Pusuguda 98 Malkangiri 2 road Bridge over river Turi at Ist Km on Kodinga Chatthandi 99 Nabarangapur 6500 Road H.L. Bridge over river Kusumi on Baghuapalli-Boragaon 100 Nayagarh 10000 Road 101 H.L. Bridge over river Dahuka on Hatadwar-Dhenkena Road Nayagarh 7000 H.L. bridge over river Kuanria on Sardhapur-Dholamara 102 Nayagarh 2 road. S.B. over Gurmajore Nallah at 1st Km on Tikrapada-Reng 103 Nuapada 9000 Road Bridge over Mugei Nallah on Ganeswarpur -Andhera- 104 Puri 3600 Ichhapur road at R.S.-4.95 KM Bridge over Balia Chatara Nallah at 0.50 km on Barimendei 105 Puri 5000 Sairi road 106 Bridge over Local Nallah on Parakena-Padmapur road Puri 2000 H.L. bridge over river Kadua on Mandupada Chitra to 107 Puri 2 Gorual Panchana road 108 Bridge over river Bhargabi on RD road to Bindheibasta. Puri 2 109 Bridge over Basupali Nallah on Basupali Laumal Road Sambalpur 8500 110 Bridge over Porpetta Nallah on Anladhipa Baliturei Road Sambalpur 6500 111 Bridge over Ranjan nallah on Goudpali Saplat road Sambalpur 2 S.Bridge over Cherupali nallah at 2nd km on Cherupali 112 Sonepur 2502 Agalpur road ( 3x10.77 Mtr) Bridge over Hariharjore at 3rd km on Mendhamal Barjhola 113 Sonepur 3982 road (13x10.77) H.L. bridge over Chouki Jore on Jamchhapur-Bhramarapali 114 Sonepur 2 road Total: 277100 80-General-796-TASP 1 Bridge over river Ong on Jamala Khuntpali road Bargarh 2 2 Bridge over River Nalia on PWD Road to Bhatpur Bhadrak 2000 Bridge over Hinjuli Nallah at 8th Km on NH 200 to Gadamal 3 Deogarh 1000 Road (6x10.77m) Bridge over Baliapita nallah at 1st KM on Suguda- 4 Deogarh 2 Gunduriposi road Bridge over local nallah on Hadubhangi-Gaiba-Gumma road 5 Gajapati 400 (1 span of 8.77 C/C ) Steel Bridge over Kamalpadar nallah on Kamalpadar 6 Gajapati 2 Kendupadar road (Span 1x59.872 m) Box cell Bridge over Loba nallah on Anukurada-Labaguda 7 Gajapati 1000 road (2 x 8x 5 Mtr) 8 Box Cell Bridge at 7/500 KM on Odasingi-Kinchilingi road Gajapati 2 9 Bridge on R.Udayagiri Sambalpur road at 2/260 Km Gajapati 2 Bridge over local nallah at 0/0 Km on Nuagada Keradanga 10 Gajapati 2 road

Outcome Budget: DoRD for 2014-15 Page 74

Bridge over Bariabandha nallah at 16th. Km on Chandragiri- 11 Gajapati 2 Antaraba-Chudangapur road H.L. bridge over Mahendratanaya river on Laxmipur to 12 Gajapati 2 Kinada PR road Bridge over Kalijharan nallah on Bhusenpali to Indarpada 13 Jharsuguda 3000 Road 14 Bridge over Pipal Nallah on PWD Road to Bhikajharan Road Kalahandi 3000 15 Bridge over River Hati Talmala Bainriguda Road Kalahandi 4000 16 H.L Bridge over Sandul River on Balipada - Rupra Road Kalahandi 4000 S.B.over Kataki Nallah on Bhurtigarh - Kadamguda junction 17 Kalahandi 5000 Road S.B.over Local Nallah Tajabaju Nallah at 4/0 Km on 18 Kalahandi 4000 Pajibahal - Mohangiri Road S.B.over Perenchu Nallah at 9/750Km on Tulapada - Panga 19 Kalahandi 5000 Road 20 S.B over Bhatrajore at 2/00Km on Karlabeda to Kulihari Road Kalahandi 3000 21 Bridge over river Andrajore on Pipalbhadi-Kutingpadar road Kalahandi 2 H.L. bridge over river Ret on Bachaka Chhak to Kankutru ( 22 Kalahandi 2 Kankutru G.P) H.L. bridge over river Khapaar Nallah on Kulihari to 23 Kalahandi 2 Budhidar via Brahmaniguda Bridge over Local Nallah (Haridajore) on Kenduguda 24 Kalahandi 5500 Sariguda Road. Bridge over Jampada Nallah on Kalampur -Dulkibandh 25 Kalahandi 11501 Road. 26 Bridge over Local Nallah on Kalampur -Mandal Road. Kalahandi 5000 27 Bridge over Mudra on Gambhariguda-Chikili Road Kalahandi 2400 H.L. bridge over river Hati on Patrabasa - Badkutru G.P. 28 Kalahandi 3002 Road 29 Bridge over Gadadi nallah on Raikia Simanbadi at 19th Km Kandhamal 1000 Bridge over Gandharaguda nallah at 8/6th km.on Subarnagiri 30 Kandhamal 2 Budaguda road. Bridge over Local nallah at 4th Km on Sombapadar Nuagaon 31 Kandhamal 3000 road. SB over Baibali nallah at 1st Km on Indragada to Baibali 32 Kandhamal 8188 road 33 Bridge over Local nallah on Temangi Sadingia road Kandhamal 3000 Bridge over local nallah at 3/480 Km on Pakangaon 34 Kandhamal 2 Balaskumpa Dutimendi Kerandimaska road Bridge over Gadagadi nallah , Mankadachua nallah ,Lahabadi nallah,Kusupani nallah & Sirsingi nallahat 35 Kandhamal 2 9/060Km ,6/760Km.11/280Km,12/630Km & 13/150Km on Pasara Linepada road Bridge over local nallah at 2nd Km of Parampanga 36 Kandhamal 2 Gugurumaha road 37 H.L. bridge over Raula to Tumudibandha-Sirala road Kandhamal 2 H.L. bridge over local nallah at 1st Km on PWD road to 38 Kandhamal 2 Bakingia road 39 Bridge over Dhenka Nallah on Bancho-Panchagochhia road. Keonjhar 4000 40 Bridge over Kusei on Daradipal-Jalasuan road. Keonjhar 1000

Outcome Budget: DoRD for 2014-15 Page 75

Bridge over Ghagara nallah at 11.4 Km. of Dadhibamanpur- 41 Keonjhar 2000 Tartara-Kantipal road. 42 Bridge over Kusei-Salapada-Sarei-Madanpur road. Keonjhar 418 43 Bridge over Sendhei on Bhandaridiha to Toranipal road. Keonjhar 1502 Bridge over Bahutia Nallah on Badakhamandra-Mishramala 44 Keonjhar 2 Road at R.D. 4/648 km Bridge over Aradei River on Raisuan-Sahadapur road at 3rd. 45 Keonjhar 2 km Bridge over Sita Nallah at 5th km & Kasia Nallah at 7th. km 46 Keonjhar 2 on P.W.D.-Bhimkunda road H.L.Bridge over Machhakandana on N.H.-215 to 47 Keonjhar 2 Ambuapada via Valiadiha 48 H.L.Bridge over Neulijodi nallah Putugaon to Chemna road Keonjhar 2 49 H.L.Bridge over Sita nallah on Kashibeda to Baghaghar road Keonjhar 2 50 Bridge over Tel on Saharpada-Machhagarh road Keonjhar 7000 Bridge over Kasia nallah at 9th KM on PWD road - 51 Keonjhar 2 Kumudabahal road. Bridge over Kachhimajodi Nallah at 0.775 Km. on 52 Keonjhar 2000 Khajuridiha Beghna road. Bridge over Local (Aradei) Nallah at 2nd Km. on Jamudiha- 53 Keonjhar 1000 Bistapal road. Bridge over Kukurkata Nallah on Ghatagaon to 54 Keonjhar 2 Chinamaliposhi road. 55 Bridge over Aradei on NH-215-Silisuan Via-Bishnupur road. Keonjhar 5000 56 Bridge over Tigiria Nallah on Nudurpada-Kaliahata road Keonjhar 5000 Bridge over Handibhanga nallah on Kalimati-Handibhanga 57 Keonjhar 1000 road. 58 Bridge over Purujoda nallah on Telkoi-Akula road. Keonjhar 2000 Bridge over Kuladhankuni nallah at 28th Km. on 59 Keonjhar 1000 Nudurpada-Kaliahata road. 60 Bridge over Karrow on Lasarda to Dhanurjay road. Keonjhar 4000 Bridge over Aradei on Kalikaprasad-Urti via Gambharia 61 Keonjhar 4000 road. 62 Bridge over Goda nallah on Gumura-Amlaniguda road. Keonjhar 2 63 Bridge over Batanai on Raisuan to Samakuda road. Keonjhar 2 Bridge over Samantamundi nallah on Nudhurpada to 64 Keonjhar 2 Kaliahata road. H.L.Bridge over river Baitarani at 1.50km on Patua Kandra- 65 Keonjhar 2 Basantapur road 66 H.L.Bridge over Katrajodi Nallah on Telkoi-Kaliahata road Keonjhar 2 Bridge over river Kusei on Irrigation embankment 67 Keonjhar 2 connecting PMGSY road Bridge over river Samarsinga nallah at 21st KM on 68 Keonjhar 2 Pithagola to Telkoi road Bridge over Baghira nallah at 3/800 KM on Sunapentha to 69 Keonjhar 2 Gopinathpur road Bridge over Bonda nallah on Badabandhapada - 70 Keonjhar 2 Nahuraniposi via Gudadhia road Bridge over river Remal at 5th KM on Harichandanpur- 71 Keonjhar 2 Daitary road

Outcome Budget: DoRD for 2014-15 Page 76

Bridge over Biriguda Nallah on Jeypore-Balia-Boipariguda 72 Koraput 20 Road (3.00 x 8.77mtr.) Bridge over Brahmanajodi Nallah on Jamakanadi- 73 Koraput 2000 Bhejahandi Road (4.00 x 10.77) Bridge over Local Nallah on at 11th Km on Dasmantapur- 74 Koraput 5000 Murkar Road (4.00 x 10.77mtr.) Bridge over Putra Nallah on at 3/900 Km on Bada Kaudi to 75 Koraput 3000 Sana Kaudi Road (5 x 10.77) Bridge over Putra Nallah on Solpa-Dharanahandi - 76 Koraput 3000 Khairimundi-Hadia Road (12x10.77m) 77 Bridge over Kurlu River on Jamakanadi-Bhejahandi Road Koraput 2000 78 Bridge over Local Nallah on Murkar-Autodora Road Koraput 3000 Bridge over Local Nallah at 1st km on Umbel to Paliva 79 Koraput 1000 Road Bridge over Local Nallah on Mattamput P.W.D. Road to 80 Koraput 1000 Udapada Road. (2 x 30.63mtr.) Bridge over river Kolab on Murtahandi-Ghodaghat- 81 Koraput 2 Gupteswar road 82 Bridge over Local nallah on Admunda-Lulla road Koraput 2 Bridge over Putra nallah on Ambaguda-Hadia -Putra -Telia - 83 Koraput 2 Jamunda road 84 Bridge over Sobhaput nallah on Hataguda-Pantalung road Koraput 2 Bridge over Sindhigaon nallah on Ambaguda-Hadia-Putra- 85 Koraput 2 Telia-Jamunda road. H.L. bridge over Teluguri River at 3rd km on Nuagam- 86 Koraput 2 Narigam road H.L. bridge over Porli nallah at 1/700 km on Porli-Nandarla 87 Koraput 2 road H.L. bridge over Kurli Nallah at 4th km on Kenduguda 88 Koraput 2 Baligam road under Boipariguda Block Bridge over Hanjaraguda nallah on Hanjaraguda 89 Koraput 2500 road (P.S Road) 2 spans of 30.63mtr 90 Bridge over Champi Nallah on Champi Godagade road Koraput 2500 91 Bridge over local nallah on Dolaguda Mantriput Road Koraput 3000 92 H.L. bridge over Local nallah on Kadamguda to Phuldoba Koraput 2 93 H.L. bridge over Local nallah on Khalkona to Baghmari Koraput 2 94 Bridge over Madakapadar Nallah on PWD Road-Disariguda Malakangiri 5000 Bridge over Ambaguda Nallah on Amlabhatta-Ambaguda 95 Malakangiri 6000 Road Bridge over Padmapur Nallaha on Pedakonda Sindhrimal 96 Malakangiri 4000 Road 97 Bridge over Boilapari Nallaha on Goudaguda Tamasa Road Malakangiri 5500 Bridge over Local Nallaha on Kukuguda- Biralaxmanpur 98 Malakangiri 3500 Road Bridge Over Tamasa Nallah at 3rd Km on Korukonda to 99 Malakangiri 3000 Kotapalli Road 100 Bridge over river Deo at 3rd Km.on Udala-Amadiha road. Mayurbhanj 4000 Bridge over river Baunsa Nallah on NH-5 Chhurunia- 101 Mayurbhanj 3000 Mantapal road. Outcome Budget: DoRD for 2014-15 Page 77

102 Bridge over river on Gangahar on Deuli-Balichilima road. Mayurbhanj 5000 103 Bridge over Madhabi Nallah on Naupal-Rout Sahi road. Mayurbhanj 2000 104 Bridge over Dudhiasole Nallah on Jaibilla-Dudhiasole road. Mayurbhanj 3000 Bridge over Jambhira nallah on Gadia-Bharbadi-Kendudiha 105 Mayurbhanj 2000 road 106 Bridge over river Deo on Kundabai-Manikpur road. Mayurbhanj 5000 107 Bridge over Tangna on Udala-Mouda Pahanda Sasan road. Mayurbhanj 500 108 Bridge over Arikul Nallah on Mahibasa-Agnikumari road Mayurbhanj 3000 Bridge over Baunsha Nallah on N.H.-5 Dahria via Kathapal 109 Mayurbhanj 2000 road. 110 Bridge over Siltia Nallah on Dumurdiha-Nodhana Road. Mayurbhanj 2000 Bridge over Katra Nallah on N.H-5 Kuliana to 111 Mayurbhanj 2000 Jagannathkhunta Road. Bridge over Chhakakhala nallah on kalajhinei-Kuabuda 112 Mayurbhanj 1000 road. 113 Bridge over River Jarali on Station Bazar to Baghara Road. Mayurbhanj 2000 Bridge over River Nalua on S.H-19 to Nalua-Karkachia 114 Mayurbhanj 1000 Road. 115 Bridge over River Kalapani Nallah on Khunta-Bholagadia Road. Mayurbhanj 2000 Bridge over Brahmanmara nallah on Kosta-Kaduani- 116 Mayurbhanj 2000 Nuajhalia road. Bridge over Handibhanga nallah on Suliapada- 117 Mayurbhanj 4000 Chaksuliapada road. Bridge over Gabadiha Kuchila Nallah on Jharpokharia- 118 Mayurbhanj 1000 Sankhabhanga Road. 119 Bridge over Panijia Nallah on Saraskona-Dighi Road Mayurbhanj 1000 Bridge over Rajabandha nallah on Jharpokharia- 120 Mayurbhanj 2000 Sankhabhanga road. 121 Bridge over Kanthala Nallah on Jamdiha-Badkhaman road. Mayurbhanj 2000 Bridge over Panpik Nallah on Nachhipur-Kulialam Sandhei 122 Mayurbhanj 2000 Road at 5th Km. Bridge over River Kalo on Nachhipur-Kulialam Sandhei 123 Mayurbhanj 2000 Road at 5th Km. Bridge over River Jambhira on Kanimahuli-Jambhirapal 124 Mayurbhanj 3000 Road at 2nd Km. 125 Bridge over Seula Nallah at 5th km on Betnoti-Manatri Road Mayurbhanj 2 Bridge over Mendhamundia Nallah at 13th km on Maitrapur- 126 Mayurbhanj 2 kuliana Road Bridge over chepti Nallah at 14th on Maitrapur-kuliana 127 Mayurbhanj 2 Road 128 Bridge over Chuhagi Nallah at 5th km on Panasia-anla Road Mayurbhanj 2 Bridge over Dariakundi Nallah at 8th km on N.H-5 129 Mayurbhanj 2 Bishrampur-patalipura Road Bridge over Badjod Nallah at 4th km on paunsia- patrapada- 130 Mayurbhanj 2 silaghaty Road 131 S.B over Chitat Nallah at 3rd km on N.H-5 to Jhinei Road Mayurbhanj 2 Bridge over ltajodi Nallah at 2nd km on Samakhunta- 132 Mayurbhanj 2 Ambaduvi Road 133 Bridge over Palpala Nallah on Padaastia to Lulung Road Mayurbhanj 2 Bridge over Sukhilakatra Nallah at 28th km on Jharpokharia- 134 Mayurbhanj 2 Sankhabhanga Road Outcome Budget: DoRD for 2014-15 Page 78

Bridge over Local Nallah at 1st km on Gandipani- 135 Mayurbhanj 2 Nabinmundhakata- pahadour Road Bridge over Kuchila Nallah. (Kuldiha Chhak) at 8th km on 136 Mayurbhanj 2 Jharpokharia- Sankhabhanga Road S.B over river Hadagada at 22nd km on Kaptipada Sarat 137 Mayurbhanj 2 Road Bridge over river Sono at 4th Km on Udala Teldehudi- 138 Mayurbhanj 2 Dimagadia R.D. Road Bridge over Ranaposi Nallah at 0/400 th km on Kaptipada- 139 Mayurbhanj 2 Chuinposi Road H.L. bridge over river Katra at 1st km on Upperbeda- 140 Mayurbhanj 2 Ambadiha road H.L. bridge over river Gangahar & Arikul Junction at 9th 141 km on PWD road to Gendagadia via Bhandagaon-Sinduria Mayurbhanj 2 road H.L. bridge over river Budhabalanga at 1st km on Bartana- 142 Mayurbhanj 2 Nischintapur road H.L. bridge over river Jambhira on Musamari-Sanmandia 143 Mayurbhanj 2 road at 4th km H.L. bridge over river Arikul Nallah on Tadiki-Kusagadia- 144 Mayurbhanj 2 Raigadi-Salbani road H.L. bridge over river Budhabalanga at 3rd km on 145 Mayurbhanj 2 Itamundia to Paikabasa road 146 Bridge over Gobarjoda Nallah on Jarka-Jamunalia road. Mayurbhanj 1500 Bridge over Fulcomp Nallah on Fulcomp to Panpataria road. 147 Mayurbhanj 1500 (Balance Work) 148 Bridge over Salandi on Jamda to Bagdafa road. Mayurbhanj 4000 149 Bridge over Local Nallah Dolaposi Naibhanga road. Mayurbhanj 600 150 Bridge over Local Nallah Hatabhadra-Kusumi road. Mayurbhanj 2 151 Bridge over Chautia nallah on Tingria-Purunia road. Mayurbhanj 1500 152 Bridge over Chautia Nallah on Raruan Naksara Road. Mayurbhanj 1500 153 Bridge over Jamuti Nallah on Raruan Naksara Road. Mayurbhanj 2000 154 Bridge over Local Nallah on Parabeda Panpatria road. Mayurbhanj 2000 Bridge over Local nallah at 2.01Km on Jamunalia- 155 Mayurbhanj 2000 Kasiabeda road. Bridge over Local Nallah at 2.275 km. 3.12 Km., 5.0 Km. on 156 Mayurbhanj 5000 Sunaposi-Bisipur-Baliposi road. 157 Bridge over local nallah on Bisipur approach road. Mayurbhanj 5000 158 Bridge over local nallah on Tato-Pichuli-Jhatiali road. Mayurbhanj 2000 Bridge over Budhi nallah at 2.5 Km. on Salarpada-Panaspal 159 Mayurbhanj 2000 road. Bridge over Baunsadiha nallah on Bharandia-Baunsadiha 160 Mayurbhanj 2000 road. Bridge over Sankarei Nallah on Shyamsundarpur- 161 Mayurbhanj 2000 Pursoattampur Road. 162 Bridge over SIM River on Talapada to Road Mayurbhanj 2 163 Bridge over Nitei Nallah on Mangod to Nitei Road Mayurbhanj 2 164 Bridge over Naujore nallah on Badada to Kusumi Road Mayurbhanj 51 2 165 Bridge over Joka Nallah on Jaldiha Masinabilla Road Mayurbhanj

Outcome Budget: DoRD for 2014-15 Page 79

Bridge over Dapani Nallah on Salabani Chhak to Taradapal 166 Mayurbhanj 2 Road at 3.90 km Bridge over Kulgidihi Nallah on Bisoi Mohubhandar Road at 167 Mayurbhanj 2 8.00 km Bridge over Asana Nallha on Kasipani Approach Road at 168 Mayurbhanj 2 1.45 km Bridge over Local Nallah on Dhobadiha Jamuriposi Road at 169 Mayurbhanj 2 0.90 km Bridge over Jhadgosda Nallah on Tangia- Deuli- Jhadgosda 170 Mayurbhanj 2 Road at 3.00 km Bridge over Dhodibahali Nallah on Satkosia Nada Road at 171 Mayurbhanj 2 8.70 km H.L.Bridge over Kanta Khairi nalla at 3rd km on RD road to 172 Mayurbhanj 2 Deuli H.L.Bridge over Salandi at 2nd Km Nuagoan to Mulapal 173 Mayurbhanj 2 road 174 Bridge over Local Nallah on Jhardihi-Badkedam road. Mayurbhanj 2 175 Bridge over Chapal nallah on Jampani-Kuleisila road. Mayurbhanj 2 176 Bridge over river Bankabal on Bankati Bharandia road Mayurbhanj 4200 177 Bridge over river Khadakhai on Kumudasole Jonti road Mayurbhanj 4000 Bridge over local nallah at Lipighutu on Jamda-Rangamatia- 178 Mayurbhanj 2000 Ulidihi road. H.L. bridge over Chhamdadihi Nallah on Kuleisila to 179 Mayurbhanj 2 Udayapur road Bridge over Panditguda Nallah at 3rd KM on Dabugam to 180 Nabarangapur 2 Maidalpur Road Bridge over Bangiri Nallah on Nanda Dahana via Ekamba 181 Nabarangapur 1000 road 182 Bridge over Local Nallah Sanoloma to Chelipetha Road Nabarangapur 2500 Bridge over Mokiya Nallah on Mokiya to Sindhikaguda 183 Nabarangapur 1200 Road SB Over Phatojodi Nallah at 10th KM on Chikili Phatakote 184 Nabarangapur 3500 Road Bridge over Gunighat Nallah at 9th Km on Podalguda to 185 Nabarangapur 3000 Patraput Road 186 Bridge over Bellari Nallah on Junapani to Koilari Road Nabarangapur 3000 187 H.L. bridge over river Turi on Bhatrasiuni - Bhatrasirsi road Nabarangapur 2 H.L. bridge over river Angi at 2nd Km on Badagumuda to 188 Nabarangapur 2 Kottagam road Bridge Over River Bhaskel at 2nd Km. on Dhodra to 189 Nawarangapur 3000 Telkonadi Road Bridge over Kurubella Nallah at 13th K.M. of PL Road to 190 Nawarangapur 2000 Dumurimunda Road H.L. Bridge over Bhandari Nallah on Sardhapur to Motigaon 191 Nawarangapur 2 Road 192 Bridge over river Bhaskel on Umerkote-Badabasini road Nawarangapur 2 H.L. bridge over Tumuda Nallah at 2nd km of Pakhanaguda 193 Nawarangapur 2 Jn. To Simuda H.L. bridge over Chitrangi Nallah at 1st Km of Mahuli to 194 Nawarangapur 2 Khutuguda 195 Bridge over local Nallah on Nuagaon-Naitaila Road Nayagarh 1500

Outcome Budget: DoRD for 2014-15 Page 80

196 H.L. bridge over local nallah on NH-224 to Raita - Odasara Nayagarh 2 H.L.Bridge over River Sananadi at 2nd Km near Baghiharan 197 Nuapada 2000 on Tukla Plasakhanda Road 198 Box Cell Bridge on Nuapada-Kuliabandha Road Nuapada 2 H.L. bridge over Jonk at 1st Km Bhalwsar to C.G. Boarder 199 Nuapada 2 (REWA) road 200 H.L. bridge over River Udanti on Kopia to Hatibandha road Nuapada 2 Bridge over kanijodi nallah on B.Cuttack-Kutraguda road.(6 201 Rayagada 2500 x 10.77mtr) Bridge over karanja nallah on Kutraguda-Jagadalpur- 202 Rayagada 2500 Anbodala. (5x 10.77mtr) Bridge over kamper Nallah at 1st km on PWD Road to 203 Rayagada 1500 Kamper ( 4x 9.77mtr) Bridge over river Sananai at 6th km on Khaira-Jhumpapur- 204 Rayagada 3000 Phulphuti road. ( 5 x 30.63mtr) Bridge over local nallah on Telengapadar-Dangasorada- 205 Rayagada 1500 Chandrapur road.(Steel Decking Span 21.392m) Bridge over local nallah on Munikhol-Sakata road. (Steel 206 Rayagada 1500 Decking Span 39.624mt) Bridge over local nallah at 1st km on K.Dhamini-Bethiapada 207 Rayagada 1500 road. (Steel Decking Span 39.680mt) Bridge over local nallah at 12th km on Ambodala- 208 Rayagada 1500 Dharanimaska road (Steel Decking Span 39.680m) Bridge over Karanja Nallah on Jagadalpur-Janaballi road ( 209 Rayagada 1000 6 Spans of 10.77mtr) Bridge over local nallah 3rd km on Naira-Bainaguda road ( 210 Rayagada 1000 1 Span of 8.77 mtr) Bridge over local nallah on Gudari-Dhepaguda-Karlaghati 211 Rayagada 1500 road. (Steel Decking Span 21.39mt) Bridge over local nallah at 4th km on Kulusingi-Engaraba 212 Rayagada 1500 road.( 6 Spans of 10.77mtr) Bridge over local nallah at 3rd km on Putasingi-Sagada road. 213 Rayagada 1500 (Steel Decking Span 39.68mt) HL Bridge over river Jhanjabati at 1st km on P.W.D. Road 214 Rayagada 2962 to Halwa.( 3 Spans of 30.63mtr) Bridge over Polama Nallah at 1st KM on Rekahlaguda 215 Rayagada 2 Papikona Road Bridge over Ambabadi nallah on Chalkamba-Bhimpur 216 Rayagada 2 Titimiri Road. Bridge over Local nallah on Kasipur-Mandibisi-Sikarpai 217 Rayagada 2 road Bridge over Baldia nallah at 1/200 KM on Sikarpai to 218 Rayagada 2 Seriguma road H.L. bridge over Jhanjabati river on PWD road to Bhatakhal 219 Rayagada 2 road H.L. bridge over Dimiriguda nallah on Dimiriguda to 220 Rayagada 2 Kalahandi border road H.L. bridge over Gulusunda nallah on Ghotona to 221 Rayagada 2 Gulusunda road

Outcome Budget: DoRD for 2014-15 Page 81

Bridge over Nuaburda Nallah on Falsabahal Padhanpali 222 Sambalpur 2000 Road 223 Bridge over Bausen Nallah on Salad Thutikatarbaga Road Sambalpur 2500 Bridge over Bhalijore Nallah on Padiabahal Tampergarh 224 Sambalpur 2500 Road Bridge over Badkhol Nallah on Tribanpur Chhak to Badkhol 225 Sambalpur 2000 Road 226 Bridge over Budhakata Nallah on Batgaon Salebhata Road Sambalpur 2000 227 Bridge over Local Nallah on Charmal Khasua Road Sambalpur 2000 Bridge over Sialjore Nallah on Tamperkela Orampada 228 Sambalpur 2000 Rengalpali Road 229 Bridge over Maltijore Nallah on Padiabahal-Panposi Road Sambalpur 2 Bridge over Barhiasahi nallah on Charmal Khasua road at 230 Sambalpur 2 4.40 Km Bridge over Local Nallah at 9/05 km on Charmal Khasua 231 Sambalpur 2 road Bridge over Amjhuri Nallah on Batagaon Salebhata road at 232 Sambalpur 2 8.850 km Bridge over Haradjore nallah at 4th km on Sadasinga to 233 Sambalpur 2 Nuapali road H.L. bridge over Kerandijore nallah at 0.400 km on SH- 24 234 Sambalpur 2 (Raikhol) to Purunagarh road H.L. Bridge over Veden nallah at 3rd km on Kuchinda to 235 Sambalpur 2 Satkama Bridge over Nibrutijore on Sargaj Jurabandh road(7x10.77 236 Sonepur 3000 Mtr) Bridge over Amrudi Nallah on Gopana-Hatikucha Road ( 237 Sundargarh 300 5x10.77 Span ) 238 Bridge over Propetta Nallah at Kello Road ( 4x10.77 Span ) Sundargarh 400 Bridge over Laba Nallah at 7.23 on Jamudihi- Chordhara 239 Sundargarh 2500 Road ( 4x10.77 Span ) Bridge over Turturi Nallah at 0.350 Km Lathikata -Girjatola 240 Sundargarh 200 ( 3x10.77 Span ) 241 Bridge over Chhinda Nallah on Sahajbahal Kulmindra Road Sundargarh 2 242 Bridge over Bagdiha Nallah on KBK Waterfall Road Sundargarh 2000 243 Bridge over Chandri Nallah of Tainsar-Musapali Road Sundargarh 2000 244 Bridge over Suidihi Nallah on Dalakudar-Kankusuan Nallah Sundargarh 3800 245 Bridge over Dalposh Nallah on Jhirpani - Dalposh Road Sundargarh 1500 246 Bridge over Jamsara nallah on Bandhamunda-Jhiripani road Sundargarh 2 Bridge over Kacheru nallah at 4th km on Kuarmunda 247 Sundargarh 2 Kacharu Road Bridge over Local nallah at 3/400 km on Kumakela Chandra 248 Sundargarh 2 Road Bridge over Mundajore nallah at 2/000 km on Dilkudar- 249 Sundargarh 2 Bardhanmunda Road Bridge over samtha nallah on Jareikela Kopsingha Road at 250 Sundargarh 2 0/500 km Bridge over river Brahmani at 0/500 km on Bonei Jangara 251 Sundargarh 2 Road Sanbondajore nallah at 2nd km.of Subdega-Damkuda road 252 Sundargarh 2 (3.1km) (5 x10.77 mtr)

Outcome Budget: DoRD for 2014-15 Page 82

Bridge over Kenti Nallah on Khatkurbahal Amgova road. (5 253 Sundargarh 2000 spans of 10.77 mtr) Bridge over Ahida Nallah on Kanika Julumbahal road (4 254 Sundargarh 2000 spans of 10.77 mtr) . Bridge over Tambu Nallah at 6th Km on Jouramunda 255 Sundargarh 2000 Tarkera road. Bridge over Safei Nallah at 3 rd Km. on Deuli-Bhalugard 256 Sundargarh 6000 road. 257 Bridge over river Safei on Sulei-Kantapali-Kinjirma road. Sundargarh 3000 Bridge over Hutupani Nallah on 8th Km on Rouldega to 258 Sundargarh 2 Tangargaon road. Bridge over Kukuda Nallah at 1 st K.m. on PWD road to 259 Sundargarh 2000 Dhaniapunji. Bridge over Thinthin Nallah at 3rd Km on Nuadihi 260 Sundargarh 2000 Pandiapali road. 261 Bridge over Satabari Nallah on Kurumkel Deogaon road. Sundargarh 2 Bridge over Local nallah at 9th. Km on Sundargarh- 262 Sundargarh 2 Gadiajore Road Bridge over Kudaboga nallah on PWD road to Kudaboga 263 Sundargarh 2 Road Bridge over Tambu nallah at 7th Km on Sanbarsa-Tarkera 264 Sundargarh 2 Road Bridge over Kharkhari nallah at 3rd. Km on Jampali- 265 Sundargarh 2 Kukuda-Bheluadihi Road Bridge over Sathi nallah at 5th. Km on Sahajbahal-Rungaon 266 Sundargarh 2 Road Bridge over Balijore nallah at 5th. Km on Dumebahal- 267 Sundargarh 2 Telijore Road 268 Bridge over river IB at 7th. Km on Subdega-Rajpur Road Sundargarh 2 H.L. bridge over Iccha nallah on Surguda to Dalkijharan via 269 Sundargarh 2 Bargamal road 270 H.L. bridge over River Safei in Medha to Jarmal road Sundargarh 2 271 H.L. bridge over Deo at 1st km on Khuntgaon Lankoi road Sundargarh 2 H.L.bridge over Budhikudar nallah at 2nd km on R.D.road- 272 Sundargarh 2 Potobeda rd H.L.bridge over Sapiata nallah at 1st km on Jamdhar- 273 Sundargarh 2 Dharaniprasad rd Total: 374900 Grand 1630000 Total: N.B The work /Scheme/ Project wise allocation is tentative & may be varied in keeping with the progress of work during the course of the financioal year.

Outcome Budget: DoRD for 2014-15 Page 83

Work list under D.No.28-5054-COL on R&B-SP-SS-04-DOR/80-General- 800-OE/789-SCP for SC/796-TASP-2006-One Time ACA-37107-Major works for the year 2014-15

Sl. Name of the Scheme / Project / Work District which Financial outlay No. implemented (in TRS) (including Normal, SCP & TASP) 1 2 3 4 800-Other Expr.

1 PWD road to road Angul 2900 2 Bagdia Gadamandal Patrapada Road Angul 1007 3 Saragaon Padmapur bankeswar Bardhanpur to Salt road Balasore 14088 4 Improvement to Jirtal to Shamsundurpur Road. Balasore 9700 5 PWD road to Mahisasuri via Manatri Balasore 1 6 Baliapal Choukukh (Dagara Sea Beach road) Balasore 1 7 Papanga Colony to Papanga village road Bargarh 1 8 Improvement to Bargarh Bheden Canal Road ( Bargarh 9400 Chhack) 9 Improvement to Ambabhona- Ruchida road. Bargarh 19500 10 Ganiapali-Kundakhai via Madamada road (Ganiapali to Bargarh 2000 Charichhak road) 11 Improvement to R.D Road from to Nrusinghnath Bargarh 5000 12 Kuliana Digarstia road Mayurbhanj 8183 13 Madhab to Binishpur road Cuttack 1 14 Jenapada Arakhapatna Cuttack 4500 15 Impvt to Olaba to Deondarjhara Cuttack 9200 16 Improvement to RD road to Ramanath Temple Cuttack 9200 17 Improvement to R.D.Road to Ganeshkhol Dhenkanal 6400 18 Bidharpur Joranda road Dhenkanal 1 19 NH 23 to Anatasayan Dhenkanal 1874 20 Improvement to NH 217 to karanje temple Road Ganjam 6100 21 Improvement to Sorada Kantipalli PWD road (ODR) to Ganjam 15000 Panchanan Temple 22 Improvement to Budhamba-Polosara PWD road (MDR- Ganjam 8025 72) to Marda Temple 23 Taratarini Ring road Ganjam 21000 24 Buguda to Budhakhole Hill top road Ganjam 331 25 Sasanapadar to Mantridi road Ganjam 1 26 PWD road to Kuansha Mangala road Jajpur 10600 27 Improvement to Chandimandir to Mahabinayak via Jajpur 20000 Darpani Road 28 Khadagpur to Charinangala Alasahi Ambasouri via Jajpur 10000 kalashree Gajendrapur road

Outcome Budget: DoRD for 2014-15 Page 84

29 Udayagiri Majhipada R.D road to P.W.D. road via Jajpur 11900 Talachandia road 30 Bhatangpadar (R.D. Road) Kalahandi 10000 to Rabandhar 31 Khajurpada Turkel via Kikia road Kalahandi 2200 32 Hatadihi Podasingidi road Keonjhar 9419 33 Katrabeda - Sitabinjhi Road Keonjhar 6110 34 Kasapada to Vimkund Keonjhar 9200 35 PWD road to Khandadhar Keonjhar 5500 36 Simor-Banki-Malipadar Road Khurda 1 37 Nirakarapur Bhusandapur road Khurda 14100 38 Banamalipur Jaydevpitha via Poijhari road Khurda 900 39 Pithabata to Sitakund Road Mayurbhanj 3300 40 Nachhipur Kulialam Sandhei road Mayurbhanj 13713 41 Improvement to Dahana to Jagannathpur Road Nawarangapur 5000 42 B.M. Semla to P S. leading Dabugaon road Nawarangapur 14600 43 Dabugaon to Kelia road Nawarangapur 5800 44 Sulia Kantilo road Nayagarh 1 45 Impvt. To Gotisahi to road Nayagarh 19100 46 Darpada - Road (Ambarpur to Odagaon Nayagarh 1140 portion) 47 Sanagarh Baunsagarh road Nayagarh 1 48 Gotma Bhainsmundi road Nuapada 1 49 B.Cuttack to via Badamotokabadi Rayagada 15000 50 RD road to Rayagada 5000 51 Gudari to Raibiji road Rayagada 10000 52 Sakata Ambodhani Rayagada 10000 53 Improvement to Kuntura to Gudguda Sambalpur 18000 54 Improvement to MDR 31 to Majhapara to Madheswar Sundargarh 10000 Temple temple Road 55 Improvement to Mohipani- Jareikela- Up to Kundaposh Sundargarh 15000 road 56 Impvt, to Road and C.D. work of PWD road to Chatri Sundargarh 5000 Hill road under ACA in the Dist of Sundergarh 57 Dalgaon Tilia road Jharsuguda 6000 420000 Total : 789 -SCP-SC 1 Mangarajpur to Kampada road (Upper Dumka to Bhadrak 12500 Taladumka portion) 2 Nalabanka to Nualunabandha via Gothadia Bhadrak 4400 3 Improvement to Malikunda to Baidynath road Sonepur 13000 4 Improvement Mundpadar to Jharial road Bolangir 2700 5 N.H.-5 to Bhalukhiai (via Deuli Hilltttop & kumari Jajpur 10000 village(link Gokarneswar Temple) road 6 Gaineilo Bridge to Tanra Jagatsinghpur 17800 7 Nuapada to Chhapada via Ganello Jagatsinghpur 4983 8 Sahadabedi PMGSY road to Siali Via- Mathasahi Jagatsinghpur 10000 Kalavedi Road Outcome Budget: DoRD for 2014-15 Page 85

9 Impvt. to PWD Road (Gopalpur Chhak) to Nasik via Jagatsinghpur 10000 pitting binala kutia 10 Kujanga Balitutha road Jagatsinghpur 2500 11 Sukala Mahakalapada road Jajpur 1500 12 Barabati Rasulpur road Jajpur 12000 13 Cuttack Chandabali R&B road (Ramachandi Thakurani) Kendrapara 5800 to R&B Ganeshpur road via Ishandia Kendrapara canal near Sorisia connected to Gahanaga Narasinghpur RD road Danpur GP Office, Society Office Paniola 14 Kusumi Badbahal gudguda road Sambalpur 1 15 Improvement to to Chandilpat Road Sonepur 8000 16 Papakhaya Charda road Sonepur 3816 Total : 119000 796-TASP

1 Ramchandrapur to Ghatuldungri road Bolangir 1 2 Sindheikela - Themra road Bolangir 1 3 Odasingi Kinchilingi road Gajapati 13668 4 PWD Road to Kadal Asurgarh via- Nunpur Kalahandi 18400 5 R.D Road to Mardiguda Kalahandi 10600 6 Siletpada to Kusurla Kalahandi 6400 7 R.D Road to Hello point Kalahandi 3000 8 Badel Attenda road Koraput 1200 9 Shyamsundarpur - Dhabanisol Road Mayurbhanj 4870 10 MDR 45 to Simla Siva Temple Mayurbhanj 4000 11 Kendujuani to Bhimkund Road Mayurbhanj 17892 12 RD Road to Nedam Dam Mayurbhanj 10000 13 Mahiskudar to Suleipat Dam Site Mayurbhanj 15400 14 Samardafa - Kuldiha Road Mayurbhanj 4503 15 PMGSY Road (Amsena) to Saliha upto Patparpali via Nuapada 10000 Thelkobeda, Mahattamtora 16 Baloda chhak to Biromal with a link to Darlinuapada Nuapada 10100 17 PWD Road (Dunguripali) to Budhikomna Nuapada 3700 18 PMGSY Road (Bangomunda) to Bondkimahal Nuapada 12200 19 Kadodihi Budhabhuin Khandadhar road Sundargarh 1065 20 Khandadera to Suleipat Road Sundargarh 4000 21 Halda-Rairangpurgarh Road Sundargarh 6000 22 to Ghogar Sundargarh 4000 Total : 161000 Grand Total : 700000

The work / Scheme / Project wise allocation is tentative & may be varied in keeping with N.B.: the progress of work during the course of the financial year.

Outcome Budget: DoRD for 2014-15 Page 86

Work list under D.No.28-5054-COL on R&B-SP-SS-04-DOR/80-General- 800-OE/789-SCP for SC/796-TASP-1230-rural roads-37247-Impvt of Existing RD roads for the year 2014-15 Sl Name of the Works District in Financial No which Outlay Implemented. (In Trs) (Including Normal SCP,& TASP) 1 2 3 4 04-Dist & Other roads-800 other Expr 1 Badatiribida Kaniha road Angul 463 2 Basta Bazar to Kusudiha Road Balasore 982 3 Dandi to Kusida via Dunda Road Balasore 1000 4 N.H. 5 to Taharpur road Balasore 6000 5 Mahatipur to Golia road Balasore 2500 6 NH-5 to Podagaon road Balasore 2000 7 Benuda to Kalyanpur Balasore 7000 8 Bargarh Bheden Canal Road Bargarh 1 9 Attabira Paharsirgida Road Bargarh 5000 10 Padampur-Gaisilet road Bargarh 4341 11 Petuapalli to Saipai Road Bargarh 1 12 Kuleipada to Khatuapatana via Champasahi Parida Road Bhadrak 6000 13 Bijepur to Luthurbandh Road Bolangir 1 14 Karanjakata- Kitangapada Road via Tilkup Boudh 9000 15 Jhinkiria Bentakar Chanduli Road Cuttack 45000 16 Chhagaon level crossing to Gobara Road Cuttack 4000 17 Nukhapada Riverghat Via-Dhanipur Road. Cuttack 10000 18 Banki-baideswar-Kalapathar Road Cuttack 8000 19 Chhatabar Khilei Road Deogarh 5000 20 Nihalprasad-Laulai road Dhenkanal 2859 21 Baunsapokhari-Kantamila road Dhenkanal 3743 22 Bahalunda-Illirisingha Dhenkanal 3884 23 Khatakhura Bhairipur Road Dhenkanal 4000 24 Belaguntha Gereda Lembhei Road Ganjam 15047 25 Bhutasarasingi Mathasarasingi Road Ganjam 1 26 PWD road to Paitagaon via Dadaralunda village Ganjam 8000 27 PWD Road to Kanabindha via Bnjarasahi and Ganjam 6000 Darpangia Road (0/0 to 2/0 Km) 28 Kamasaragada Chhaka to PWD Road via Jhadasi Ganjam 5000 29 Karapalli Golabandha road Ganjam 6000 30 Dharmpur Chakka to Khandadeuli Talapur Ganjam Gokanameripalli touching to Podamari Road . (0/0 Km to 8000 7/700 Km) 31 Barada Chhaka to NH 215 via Taharpur, Saintara road Jajpur 8000 32 Gadamadhupur Dankari Turanga road Jajpur 15000

Outcome Budget: DoRD for 2014-15 Page 87

33 Sergarh - Barbandha Road Kalahandi 2288 34 Bhanpur Upher Kalahandi 1 35 Moter to Lagugaon Road Kalahandi 2000 36 Gobara Chhak to Bamara via- Diminia Chaulia Kendrapara 10000 37 Manoharpur Pithagola Road Keonjhar 1000 38 Bidyadharpur to Kanpur via Soso Road Keonjhar 10000 39 Nandabar to Atta Road Keonjhar 10000 40 Bancho Panchagochhia Road Keonjhar 5000 41 Raisuan Sahadapur Road Keonjhar 6000 42 Naradapur to Jodipada Road Keonjhar 1 43 Dayawest Branch Canal road from Padasahi Chhak to Khurda 23334 Bhatapada road 44 N.H. 203 to Gangotri Nagar (Ln-I & II) Khurda 6224 45 Banapur main canal road to Antarakiari via Kosarada Khurda 9999 road 46 Bhagabati Temple to Bhuskapada Khurda 5000 47 Subai Bhairaguda road Koraput 1883 48 Chitroda-Gadigaon road. Mayurabhanj 1502 49 Purunia Chhaka to Jhipabandha. Mayurabhanj 5000 50 Tarana to Bhitarmada road. Mayurabhanj 3941 51 Purosottampur Notar Road (From 6/0 Km to 10 Km) Nayagarh 1 52 Rajsunkhala-Surkrabedi Road Nayagarh 13000 53 Paraskhole to Jamdharah Road Nuapada 1 54 Kushubhadra bridge to Andhere GP office road via Puri Benipur Madhagadia Ichhapur Adangasahi Alichar and 2000 Badamath road 55 Sailo Niali road Puri 10000 56 Approach road to Beleswar Temple Puri 3000 57 Kakatpur road Puri 4000 58 Puri Arakhakuda Road Puri 1 59 R.D.Road (Chotapur) to Haridasa via Rampur Bhoi Sahi, Puri 1 Bhubanpati adhaghai, Kusubenti road 60 Paika Sahi to Sankarpur Temple via Parbatipur Road Puri 4500 Samanga G.P Road 61 Teisipur to Pidhapatna Road Puri 500 Total : 342000 80 -General-789-SCP-SC 1 Ganijang Manguli Chhaka via Ambagadia to Gopalpur 5000 Bhadrak Road Kanapada RD road to Mukundpur Nigadi via Gudupal Bhadrak 7145 2 road 3 PWD road to Poda Pada Via Ganjamal road Bhadrak 4000 4 Dhamara Road to Lunabandha via Budhi Chhak road Bhadrak 2839 5 Bedpur-Padhani road Bhadrak 1712 6 Andola to Kuali RD Road via Chhatrapada Bhadrak 10000 7 BC rod to Kuansar Bhadrak 5000 8 Bohira to Dumuduma road Boudh 500 Outcome Budget: DoRD for 2014-15 Page 88

9 Mankadchuan PWD road to MSG Project road via Boudh 4466 Jogendrapur road 10 Tirtol Kolar Road Jagatsinghpur 20000 11 NH to Siju via Katakula & Chunabelari Road Jagatsinghpur 12000 12 Pingala Hatibari Road Jajpur 1 13 Narayanapur-Ajagarapatia Road Kendrapara 7481 14 Aul - Bhuin Pur Road Kendrapara 1 15 Batagaon Salebhata RD Road Sambalpur 3000 16 Charmal Khasua road Sambalpur 5000 17 Narayanpur to Mukundapur Road Sonepur 2000 Putupali chowk to Kapasira via: Jagannathpali (1/5 to Sonepur 1755 18 7/5km) 19 Ainlachhat PWD road to Krushnapur via: Jaunra Bhaunra Sonepur 5000 Sujia Total : 96900 80- General -796- TASP 1 Mohana to Badagada road Gajapati 8000 2 Raikia Manikeswar Karada road Kandhamal 7000 3 Phiringia Nuapadar road Kandhamal 6000 4 Indragada Sahajkhol road Kandhamal 13116 5 Pakanguma Balaskumapa Dutimundi Karandimaska road Kandhamal 5950 6 B.Singpur-Gujuniguda-Cheptemba Road. Koraput 5401 7 to Pedakonda Road Malkangiri 10000 8 Malkangiri to Chatishgarh Border via Challnguda Road Malkangiri 29884 9 Kostha-Mahabilla road. Mayurabhanj 558 10 Bankati to Khgandadera Road Mayurabhanj 1 11 Bariguda to Mokiya Road Nabarangpur 7959 12 Dabugaon to Kelia Nabarangpur 5000 13 Jharigam to Dhamnaguda Road Nawarangpur 7000 14 Umerkote to Maligaon Road Nawarangpur 7000 15 Jeeraguda to Podaguda Road Nawarangpur 2000 16 Padmapur-Gudari-Raibiji road (52km) from 0/00 to Rayagada 2229 12/00km 17 Naira-Bainaguda road Rayagada 6000 18 Chatikona to Kurli road Rayagada 4000 19 Tuniapali Balia Road Sundargarh 1 20 Bargaon Sahajbahal Runugaon Road Sundargarh 1 21 Sundargarh to Gandiajore Sundargarh 4000 Total : 131100 Grand Total 570000 The work / Scheme / Project wise allocation is tentative & may be varied in keeping N.B with the progress of work during the course of the financial year.

Outcome Budget: DoRD for 2014-15 Page 89

Work list under D.No.28-5054-COL-on R&B-SP-SS-04-DOR/80-General- 800-OE/789-SCPSC/796-TASP-1230-rural road-37158-completion of incomplete roads & bridges under different tranches of RIDF & other schemes for the year 2014-15 (Plan)

Financial outlay District in which (in TRS) Sl.No. Name of Scheme/ Project/work implemented (including Normal, SCP & TASP) 1 2 3 4 04-Dist & Other roads - 800 - other 1 Bagedia Sarapal road Angul 1225 2 Kukurpeta Takua via Brahmanbil road Angul 3427 3 Bhagarathipur to Durgapur road Angul 698 4 Seepur to Podagarh road Angul 1826 5 Pabitranagar to Deragola road Angul 423 6 Bridge over Andhari nallah at 5th km. on Nimirebeda- Angul 2000 Andhari road (40 m) 7 Kumurisingha Inkarbandha Pondapur road Angul 2000 8 Salandi Bandha to PWD road via-Tumbapadi-Belagadia Bhadrak 960 road (0/0 to 1/4 Km.) 9 Tunda-Radhanagar road Bhadrak 1603 10 Padiapada to Nilok via-Gharpada road Bhadrak 1468 11 R.D. road to Kabirpur Bhadrak 2561 12 Barikpur Banth road to Pachhatira chhak to Bhadrak 5327 Raghunathpur 13 Pirahat-Charbatia R.D.road to Kabirpur road. Bhadrak 944 14 Salandi bandha to PWD road via Tumbapadi Bhadrak 1571 Belagadhia road. (2/0 to 3/600 Km.) 15 R.D. road to Guptaganga via Ramanuja Vidyapitha & Bhadrak 1456 Biranchi Mandira road. 16 Construction of bridge over Kundi nallah on B.C. Road Bhadrak 3438 to Guptaganga road 17 Bhaunria to Nahanga road Cuttack 2151 18 Anantapur to Mahidharapada road Cuttack 5169 19 Harachandi Malahat road Cuttack 716 20 Umar Sukarpada via Haladharpur road Cuttack 1278 21 N.H.-5 to Itua Via Tantira road Cuttack 5096 22 Chahapada to Kanpur road Cuttack 2745 23 N.H.-5 to Champapur Anandbazar via Govindpur road Cuttack 1750 24 N.H - 55 to Gopalpur Via Laxminarayanpur Road Cuttack 3332

Outcome Budget: DoRD for 2014-15 Page 90

25 Padmapur Venterinary to Pirabazar via Karasahi Road Cuttack 1817 26 Badapada village to Bandalo via Chalikhia Road Cuttack 5419 27 Baradia Jaleswarpur Road Cuttack 5052 28 Kujibara PMGSY Road to OTM Colony Via Cuttack 3921 Jajabhairabi Road 29 Mangarajpur R.D Road to Badasamantarapur via Cuttack 5474 Bhaghadhara Raghunathprasad Road 30 Agrahat Bisinahakani Road Cuttack 836 31 Rajabati Ambilijhari Road Cuttack 3897 32 Old C.S Road to Indranipatna Road Cuttack 537 33 Palasudha Valiakana road Cuttack 2489 34 Tikira Jagannathpur Road Cuttack 1391 35 Naliamuhan Satyabhamapur Road Cuttack 2100 36 Chintamanipur Mania Road Cuttack 300 37 Adaspur Kasarda Sithalo Bachhasailo Road Cuttack 1000 38 Salei Baharana Road Cuttack 1000 39 Aradia School to Anantapur Road from 0.814 km. to Cuttack 4500 4.900 km. 40 Regeda Sanagaon road Cuttack 496 41 Ghodabar-Gholapur road Cuttack 3677 42 Singhanathpur-Durgapur road Cuttack 3200 43 Nukhapada Upperkata road Cuttack 420 44 Old C.S road to C.S prasad Dhenkanal 265 45 Santhpur-Marthapur road Dhenkanal 235 46 Raitola to Bajuria-Ambabahali road Dhenkanal 542 47 Nilakanthapur to Arachua via village karagola Dhenkanal 2153 48 Mathatentulia to Sorisiapada road via Anandapur, Dhenkanal 7757 Arachua, Nilakanthapur, Jambu, Mundamari, Mahisakada, Padhantangara, Simikia. 49 Khankar-Thakurpal- Kaluria road Dhenkanal 2220 50 Baishnababandha-Jharbandha road Dhenkanal 3575 51 Khajuriakata-Sanjapada road Dhenkanal 282 52 Pingua-Laulai road Dhenkanal 1828 53 Khatakhura Bharipur road Dhenkanal 9543 54 Soagr Baruan road Dhenkanal 3999 55 Kadua Bhagirathipur road Dhenkanal 1903 56 Haladikundi Makauakateni road Dhenkanal 2401 57 Mahabirod Talcher Border road Dhenkanal 4186 58 Garpalasuni petraghati road Dhenkanal 3349 59 Hatuary Jaganathpur road Dhenkanal 2466 60 B.D.Pur to Adheigam via Khamarapalli Road. Ganjam 2770

Outcome Budget: DoRD for 2014-15 Page 91

61 PWD road to Bhagabanpur Road Ganjam 3446 62 Singipur to Munigadi via Banthapalli Ganjam 871 63 N.H.217 to Dhaugam Road Ganjam 492 64 Kodala Phasi extended to Billipada, Phasipada, Bhadua Ganjam 1396 Road 65 Construction of H.L. Bridge ovr River Bada nadi on Ganjam 2600 Nahada Gahangu Road 66 Construction of approach road of Kharakhari Bridge on Ganjam 240 somma Phasipada Road 67 Puruosttampur Ranigam Sikula Arakhapur Rishipur Ganjam 10083 Road 68 Khandabnadha Maguriapalli Road (0/0 to 3/8Km) Ganjam 3749 69 A.Laxmanpalli Debabhumi Road Ganjam 4879 70 Dhunkapada Kendubadi Kanachai Golamundala Road Ganjam 3000 71 Badgada Mohana Road Ganjam 13751 72 Purushotampur via Govindapur Nauli Laxmipur Road Ganjam 632 73 Sindarapur Duanapalli road (3/0 to 5/345 Km.) Ganjam 1579 74 Sindurapur Duanapalli road (1/850 to 4/100 Km.) Ganjam 3678 75 Kaithakhandi PWD road to Kamalapur Via: Gaida, Ganjam 574 Ghanasingi & Birapatana road (1/692-1/850 & 3/300- 7/200) KM 76 Digapahandi PWD to Kusapada Patanda Ganjam 454 Via: Kamapadia,Kedarpur (1/483-2/00 Km) 77 Nagardhia Jn. To Hugulapatta Balajipalli (Part) 2/5 to Ganjam 591 5/0 (1/550-2/500)Km 78 Salabana Khasua Khajapalli road 0/0 to 2/6 Km. Ganjam 1559 79 Salabana Khasua Khajapalli road (2/6 to 7/6 Km.) Ganjam 1579 80 Santho Sirelo road (3/165 to 3/965 Km.) Jagatsinghpur 859 81 Borikina Osakana road Jagatsinghpur 750 82 Machhagaon to Sukinda road Jagatsinghpur 821 83 Sariki Gorada Dhunpur Road Jagatsinghpur 1041 84 Sampur to Nuapada road Jagatsinghpur 1462 85 Santho Haripa Road Jagatsinghpur 2140 86 Gualipur Khardasahi road Jagatsinghpur 1629 87 Bridge over Hansua Drainage Cut on Badilo Champahat Jagatsinghpur 7500 Road 88 Naugaon Dabar via Dahipal Road Jagatsinghpur 1900 89 Santho Sireilo Road (0/531 to 1/822 Km.) Jagatsinghpur 1600 90 Dhanipur - Kantilo Road Jagatsinghpur 2100 91 Kamasasan Nuagaon road. Jagatsinghpur 2594 92 NH 5 to Khandarpur road Jajpur 820 93 Karda Gopinathpur to Vat Solpata road via Bhakandari , Jajpur 1888 Baghanata and Rangaranga road 94 Badabiruhan GP office to NH 215 Jajpur 767 95 3A Embankment to road Jajpur 1868 96 Tarakota to Purbakota road Jajpur 646

Outcome Budget: DoRD for 2014-15 Page 92

97 Mulari to Nahaka road Jajpur 763 98 Mahuriachua to Sridheswar via Mansinghat and Hirapur Jajpur 2704 road 99 Rahasoi to Kodeibati road Jajpur 3101 100 Bijipur to Kapasi road Jajpur 1609 101 HLBridge over River Kharasrota on Bari-Binjharpur Jajpur 6000 Road 102 Katikata Kuanpur road Jajpur 5000 103 RD road to Jamuna culvert via Samsarpur Baniagadia Jajpur 4500 road 104 Kadei chhak to Nuasasan via Khaira road Jajpur 5366 105 Rajpur Ghat to Barapada via Talua Baniari road Jajpur 7432 106 Kharanasi to Barakoliakhola road Kendrapara 4356 107 Belarpur High School to Laxmanjew Temple Kusiapal Kendrapara 1609 via Kurujanga G.P Office road 108 Dianapatana to Bilabalarampur via Kendrapara 425 Ambrutamanipatana-Aitipur 109 Podal Jamadhar road Kendrapara 1838 110 Birijanga to Puruna Gopinathapur road Kendrapara 460 111 Laxminarayanpur to Satabatia road Kendrapara 1373 112 Balisahi to Teheda School via Harianka Medical Kendrapara 2300 Janabarimula School Chhaka road 113 Singhpur Rajkanika (R&B) road to Hatsahi road via Kendrapara 1559 Agapada Gahanpal, Batrapada 114 Talachua Ahirajpur Kendrapara 8897 115 Pegarapada Manpur Kendrapara 402 116 Madhapur-Dhanchangeda Road Nayagarh 8412 117 Dahalpada to Bhandaridanda via Dihapada road Puri 3227 118 Brahmanapada to Atheisa road Puri 1576 119 Sahupada Irrigation Embankment to Nilakanthapur Puri 5926 120 Ratapada Goradapedi Road. Puri 900 121 Malud Berhampura Road Puri 4600 122 Construction of bridge on left & right approach of the Puri 9043 bridge over Dhanua at 3rd Km. on Sanapali - Padapada road 123 Nagabasta chhak to Alanda via Arila, Talantala road Puri 8706 124 MD Road to Gop Konark road Puri 4636 125 Domundi chhak to Bharagol road Puri 5583 126 Talaandia Chhak to Chanarpada via Seulasahi Puri 8423 127 Charichhaka-Gop Tampalo Chhaka to Jhampulakuda Puri 4500 Via Terundia From R/D- 5/180Km to 7/700Km 128 M.D road to Gop-Konark road(Link approach to Puri 2246 Balikapileswar) 0/00Km to 1/260Km 129 Tulundi Kud-Gunderpur road Sambalpur 3631 130 Sankarma Gambharikata road Sambalpur 689 131 Bhimkhoj Chhamunda road Sambalpur 5826

Outcome Budget: DoRD for 2014-15 Page 93

132 PWD road to Bansara road Sambalpur 250 133 Salad to Thuti katarbaga road Sambalpur 415 134 Bhaliapali Dalbi Kulerjore Road Sambalpur 1250 135 Hatibari Kulsar Road Sambalpur 4100 136 NH42 to Dakra via Basiapada Road Sambalpur 4300 137 Falsabahal Padhanpali road Sambalpur 1280 138 Badmal Gundruchuan road Sambalpur 1500 139 Lad Fashimal road Sambalpur 12850 140 Lad Chandinimal Road Sambalpur 3850 141 Gochhara Langbahal Road Sambalpur 1800 142 Bhojpur Tihadipali Road Sambalpur 2000 143 Bamra Garposh PWD Road Kutarimal Sambalpur 6900 144 MDR 31 to Jarabaga Road via Nuadihi Sambalpur 5000 145 Chhatiposh Belmunda Road Sambalpur 1185 Total : 420000

80- General 789-SCP- SC 1 Oupada (Station Sahi) to Khuntadiha Patna raod Balasore 466 2 N.H - 60 to Mandarada Via Jhinjpura road Balasore 2319 3 Ada Anandapur via Mahammedpur road Balasore 708 4 Maitapur Abjana road Balasore 430 5 NH 5 to Sanpatpur road Balasore 1102 6 PWD road to Kesharipur road Balasore 2544 7 NH 5 Mulisingi road Balasore 883 8 PWD road to Khunta via Atapur road Balasore 973 9 NH 5 to Talakurunia road Balasore 3083 10 PWD road to Aruha Via Thalabartana road Balasore 1951 11 NH 5 to Bajipur road Balasore 1318 12 NH 5 to Patharapentha road Balasore 4871 13 Belda Gandua via Rafayatpur road Balasore 756 14 Thana chhak Deula PWD road to Baghrukhi Manisha Balasore 2099 Pokhari Via chhaka ,Gobardhanpur, Ghantilodi road 15 Bhograi PWD road at Sultanpur GP Office to Gabagaon Balasore 1022 irrigation bandha (Bhua Bandha) Via Allalbindha road 16 Langeswar Kasafal via Bolang road Balasore 1404 17 Bad Mahisadi Dumi Chhak Road Balasore 1886 18 Kamarda Market to W.B.border Via Khairda road Balasore 2375 19 Bayani ghat to Mohagob raod Balasore 5952 20 Jaladha Balipokhari PMGSY road to Kamarda Baliapal Balasore 2732 PWD road 21 Aitapali Talmunda road Jharsuguda 2492 22 Rengalbeda Kuarmal Jammal road Jharsuguda 716

Outcome Budget: DoRD for 2014-15 Page 94

23 Bagdihi to Barpan road Jharsuguda 489 24 Sulehi Bhaura Road Jharsuguda 955 25 Kumbhari Hirma Road Jharsuguda 843 26 Perifery Sunary Road Jharsuguda 1355 27 R.K.B.H Road Keonjhar 3501 28 Telkoi to Kaliahata road Keonjhar 3180 29 Telkoi Akul Balijodi Benamunda road Keonjhar 556 30 Anseikala Jamukundia road Keonjhar 518 31 Jhargaon Bhuyanroida Keonjhar 632 32 Basudevpur Dhobakuchuda road Keonjhar 483 33 Chimila Satahalia road Keonjhar 450 34 Telkoi- Balijodi- Benamunda Road. Keonjhar 4292 35 Mareigaon to Dhenka road Keonjhar 488 36 Gopalpur to Bahia road Keonjhar 675 37 Hatadihi to Samana road Keonjhar 1917 38 Baranga Jabinpur road Keonjhar 417 39 Tikarpada River embankment to Gangua embankment Khurda 2084 through Harijan Sahi road 40 Chandua to Sunaria road Mayurbhanj 335 41 Gandipani Nabinmundhakata Pahadpur road Mayurbhanj 694 42 Harisole Samadihi road Mayurbhanj 754 43 NH 5 to Budhikhamari Jamdapal road Mayurbhanj 577 44 Deulia Patisari Balichilima road Mayurbhanj 1155 45 Sarumula Khunta Balasore Border road Mayurbhanj 993 46 Brundabanchandrapur Athapada road Mayurbhanj 1084 47 Gendagadia Salachua road Mayurbhanj 266 48 Telibilla-Janudahi-Balidiha Road. Mayurbhanj 1598 49 Paktia-Chadheigan Road. Mayurbhanj 2451 50 Haladia Kusunpur via Sunaposi Ghagi road Mayurbhanj 1183 51 Dolaposi Naibhanga road Mayurbhanj 2114 52 Baneikela Purunapani road Mayurbhanj 2076 53 Bakla Tangabilla Road Mayurbhanj 4020 54 Sunaposi- Baliposi- Bishipur Road Mayurbhanj 3472 55 Bisoi - Mahubhandar road. Mayurbhanj 1252 56 Haldia Kasia Road. Mayurbhanj 7852 57 N.H-6- Hatichhad Road. Mayurbhanj 3808 58 Tentla Jamda Road. Mayurbhanj 699 59 Guhaldangri Suriyagoda Road. Mayurbhanj 2737 60 Sankaranda to Sankarada Adivasi road Nabarangpur 377 61 Malgam to Kalahandi Border road Nabarangpur 1991

Outcome Budget: DoRD for 2014-15 Page 95

62 KP-III to KP Advasi raod Nabarangpur 705 63 Badgaon to Sabra. Sundargarh 2712 64 Menmena to Rampur Sundargarh 4006 65 Mahuldiha- Talbahali Road Sundargarh 86 66 Kendudihi-Kenapali Sundargarh 2024 67 Tuniapali-Balia Road Sundargarh 178 68 Kumakela-Chandrapur Metalled road Sundargarh 154 69 Jhinkinali-Angul Road Sundargarh 974 70 Bhanjapali-Kalamanga Road Sundargarh 1756 Total : 119000 80- General- 796 - TASP 1 Ambabhona to Dunguri road Bargarh 720 2 PWD road to Dalbi via Kultatikra Gandhitikira road Bargarh 1954 3 NH 6 to Chakuli village road Bargarh 299 4 Silet to Janged road Bargarh 1128 5 Main Canal to Amjore via Tangarpali road Bargarh 904 6 PWD road to Dabka road Bargarh 305 7 Luhurachati Machimura Bargarh 7300 8 Sargul Bhaisadarha road Bargarh 2030 9 RD road at Baitali to Adapani chhowk via Turla and Bargarh 459 road 10 PWD road at Mandosil to Balangir Border via Dharol Bargarh 609 Malpada Chhindeikela, Patraguda Temrimal Menkamunda road 11 Ghanteswari Buden Palsada road Bargarh 1038 12 PWD road to Rebedega via Nuapali road Bargarh 300 13 Bandalo PMGSY road to Jhutana Bhadrak 2018 14 Barikpur Daipur Asurali road Bhadrak 1288 15 Brahmanigaon to Pandasunighat road Bhadrak 1677 16 Loisingha Badibahal road Bolangir 1232 17 Hirapur Keutipali road Bolangir 402 18 Tamia Chhak to Baneimunda via Daldali road Bolangir 487 19 Telibandha Budhipadar road Boudh 2688 20 Sanabutupali to Panthei road Boudh 1385 21 Purumunda turuguda Sagada road Boudh 3731 22 PWD road to Tundumal via Ratakhandi Boudh 2522 23 Sainipada Sundhipadar raod Boudh 2599 24 Constn. Of H.L over Salki nallah at 1st Km on Boudh 9088 Baghiapada Sagada road 25 Telibandha Barapuduga road Boudh 2556 26 Baghiabahal Sanjamunda Lambsory Mundapada road Boudh 3253 27 Tikilipada to Sodo Road Deogarh 5790

Outcome Budget: DoRD for 2014-15 Page 96

28 Tinkibir-Rengalbeda Road Deogarh 1069 29 Bridge over river Tikira on Kundheigola-Nuapada road Deogarh 2279 30 PWD road to Karchabadi Gajapati 228 31 Jagannathpur Kankorada Gajapati 667 32 Kasinagar Sukarnpeta Gajapati 598 33 Kidigam to Kartum Gajapati 421 34 Labarasingi Jeerango Gajapati 943 35 Sidhamadango to Ch.Laxmipur Gajapati 385 36 Brundabahal Daspur Nandol road Kalahandi 560 37 Tulapada Panga road Kalahandi 1189 38 NH 201 to Bhatrajore road Kalahandi 539 39 Constn.of HL Bridge over river Tel at 17th km on Kalahandi 15007 Brundabahal Daspur Nandol road 40 Kotagarh Srirampur Gadapur road Kandhamal 1634 (Daringibadi block) (7/0 to 10/500 Km.) 41 Dadaki Lambrojhari road Kandhamal 1870 42 Srirampur Gadapur Kandhamal 7689 43 Chakapada to Badala road Kandhamal 478 44 Kotagarh Srirampur Gadapur road (7/0 to 11/035 Km.) Kandhamal 3000 45 Daringibadi Partamaha road Kandhamal 4000 46 TCNB road Kandhamal 2000 47 Lankagarh Jhiripani road Kandhamal 2000 48 Subarnagiri Budaguda road Kandhamal 2000 49 Constn.of HL bridge over Kudutuli nallah on Nuagaon Kandhamal 2000 Kudutuli Sainipada road 50 MKSB road from 22/0 to 28/0Km. Kandhamal 1500 51 Constn.of bridge over Mundarigaon nallah at 8th Km.on Kandhamal 300 Nuagaon Kudutuli Sainipada road 52 Solpa to Dharnahandi Koraput 617 53 Jamakahandi Bhejahandi road Koraput 249 54 RSC-17 to RSC-12 Road. Malkangiri 2114 55 Kosagumuda to Kantasariguda road Nabarangpur 2098 56 Jatabal to Nuakote road Nabarangpur 368 57 SB over Local Nallah at I st Km on Kottagam Attigam Nabarangpur 1173 Road 58 Rayagada to Baisingi road via Chekaguda. Rayagada 4278 59 PWD road to Soroda via Sundaramati Rayagada 2448 60 Hanumanthapur to Uapuchi. Rayagada 2325 61 Sargipali Balichuan road Sundargarh 616 62 Darlipali Raidihi road Sundargarh 1876 63 Telijore ferryghat to Bandhabahal raod Sundargarh 1796 64 Podmundi Bijadihi road Sundargarh 3139

Outcome Budget: DoRD for 2014-15 Page 97

65 Raidihi Aunabahal road Sundargarh 3288 66 Sagbahal to Tilia road Sundargarh 1570 67 Rouldega to Tangargaon road Sundargarh 6579 68 Darlipali to Ghantimal Sundargarh 658 69 Darlipali Raiboga road Sundargarh 1890 70 Khatkurbahal to Amgova road Sundargarh 500 71 Hemgir Bileimunda road Sundargarh 5000 72 Sundargarh Gadiajore road Sundargarh 8300 Total : 161000 Grand Total 700000 The work / Scheme / Project wise allocation is tentative & may be varied in keeping N.B.: with the progress of work during the course of the financial year.

Outcome Budget: DoRD for 2014-15 Page 98

Work list under D.no.28-5054-Colon Roads & Bridges-SP-DS-04-DOR- 2526-SCA for special programme foe KBK district-789-SCP S.C/796 TASP/800- OE-37107-Major works for the year 2014-15

Sl. Name of the Scheme / Project / Work District which Financial outlay No. implemented (in TRS) (including Normal,SCP & TASP) 1 2 3 4 80-General-789-SCP-SC 1 Bhoipali to Sadhupali road Bolangir 4500 2 PWD road to Nuniadhiba road Bolangir 4500 3 Luthorbandha to Majhipada road Bolangir 2500 4 Brahmani to Bahaduki road Bolangir 2000 5 Baldas road to Mangulipara road Bolangir 2000 6 L-37 to Rangabahali Bolangir 1000 7 Biswanathpur- Bijepur Road (Phase-II) Kalahandi 3400 8 Bijepur - Kalyansinghpur Road Kalahandi 1459 9 Brahmaniguda to Budhidar Road Kalahandi 2808 10 Madding to Singhjharan Road Kalahandi 2000 11 Kesinga to Joradobra Road (Phase-I) Kalahandi 2478 12 – Tusura via Gajabahal Road Kalahandi 1944 13 Siripali – Barbandha Road Kalahandi 1204 14 Biswanathpur – Bijepur Road (Phase-I) Kalahandi 2662 15 Bandhapari to Lanjigarh Road Kalahandi 1330 16 Tulapada - Panga Road Kalahandi 1785 17 Kesinga - Joradobra Road (Phase-II) Kalahandi 1674 18 Karlamunda - Teresinga Road Kalahandi 2476 19 Rishida - Pourkela Road Kalahandi 1271 20 Hati Bridge to Attigaon Road Kalahandi 1 21 N.H-201 to Bhatrajore Road Kalahandi 1470 22 Maddingpadar - Singhjharan Road Kalahandi 810 23 Gulujuba to Habaspur road Kalahandi 1619 24 PWD Road to Khetupada Kalahandi 5000 25 Kusurpada to Singjharam Kalahandi 3000 26 Darlipada to Nuapada (Pujaharipada-II) Kalahandi 5000 27 Nuagam to Kumudaguda Koraput 6500 28 M.D.R. to Muliaput Koraput 6500 29 Mundiguda to Doraguda Koraput 3000 30 Pradhaniput to Sundhiguda Koraput 5000 31 P.Khudi to K.Khudi Koraput 2500

Outcome Budget: DoRD for 2014-15 Page 99

Govdindapalli to High School Road (Constn. of 32 Malkangiri 1 Bituminous Macadam) JM Road to Katrimajhiguda Road (Constn. of 33 Malkangiri 44 Bituminous Macadam) MM Road to BM Road (Constn. of Bituminous 34 Malkangiri 3037 Macadam) 35 RD Road to Nuaguda Malkangiri 4000 36 Old MM Road Malkangiri 592 37 MM Road to MPV-83 Malkangiri 2025 38 Malkangiri to MV.27 Road Malkangiri 245 Canal Bank to MV-49 (Constn. of Bituminous 39 Malkangiri 1071 Macadam) Link Road from MV-15 to MV-46 via Singarajkonda 40 Malkangiri 5000 (Constn. of Bituminous Macadam) 41 BM Road to MV-32 (Constn. of Bituminous Macadam) Malkangiri 2594 42 Venketapalam to Panimetla Malkangiri 4500 43 Ambagaon to Bhaludangri Road Nabarangpur 4500 44 Saruguda to Bairagipadar Road Nabarangpur 4000 45 Kumujhar to Purniguda Road Nabarangpur 5000 46 Hirapur to Nagjodi Nabarangpur 5000 47 Mendatal to Chacharajharan Nuapada 6000 48 Saipala to Santoshpada Nuapada 3000 49 Algingiguda to Pradhaniguda Rayagada 5000 50 Bahirkhaman to Bandhapali Subarnapur 4000 51 Kamsara Balikhamar to Basasankar Subarnapur 1500 Total : 144500 80-General-796-TASP 1 Chikalbahal to Bankira road Bolangir 4000 2 Gambhariguda to Raxibhata road Bolangir 7000 3 PWD road to Damnimal road Bolangir 2500 4 Manigaon to Nanajore Bolangir 3000 5 MDR 40 to Suhagpur road Bolangir 4000 6 Talgaj RD road to Kundeigad road Bolangir 2000 7 RD road to Dhursamunda road Bolangir 4000 8 Pipalbandha to Jenapada road Bolangir 3000 9 R.D. to Amthaguda Kalahandi 4000 10 Patrabasa- Jhulenbar Kalahandi 6000 11 Lakhabahahali to Sialjore Kalahandi 4000 12 P S Road to Tendapani Via Mimiri Kalahandi 4000 13 Jagannathpur to Padmapur Koraput 5000 14 Machara to Khaparaput Koraput 5000 15 R.D. Road to Podapadar Koraput 6000 16 P.W.D. Road to Brahmanaguda Koraput 5000

Outcome Budget: DoRD for 2014-15 Page 100

17 R.D. Road (PMGSY) to Sorisapadar Koraput 3000 18 PWD Road Raisil Koraput 7000 19 NH-43 to Chikalmari via Gangarajpur Koraput 6000 20 Sindhiguda to Chitapari Malkangiri 4500 21 Chichibai to Bandhakona Road Nabarangpur 4500 22 RD road Jn to Bagniguda Road Nabarangpur 4500 23 Hardoli to Budaguda Road Nabarangpur 5000 24 Gopiguda to Chhotaguda Road Nabarangpur 4000 25 Podulguda to Patraput road Nabarangpur 3871 26 Dabugam to Maidalpur road Nabarangpur 3818 27 Kosagumuda to Kontasariguda road Nabarangpur 2295 28 Kosagumuda to MP Border road Nabarangpur 1592 29 Nandahandi Dahana via Ekamba Nabarangpur 5000 30 Dabugaon to Maidalpur Nabarangpur 2200 31 Jatabal to Nukote road Nabarangpur 2800 Kondagam Road to Sankarada Silati (2/500 to 4/500 32 Nabarangpur 1777 Km) Silati to Rajpur Via, Benora Road from 2/00 to 4/200 33 Nabarangpur 2922 Km Kondagam Road to Sankarada Silati (6/500 to 8/700 34 Nabarangpur 4945 Km.) Silati to Rajpur Via, Benora Road ( 0/00 Km to 2/00 35 Nabarangpur 1985 Km ) 36 Bharsundi DP to Bharsundi Adivasi Nabarangpur 1 37 Phupugam to Dengaguda road Nabarangpur 3000 38 Malgam to Kuamba Nabarangpur 2000 39 Motigam to Dhepaguda Nabarangpur 4500 40 Lakhna Thakpali Road to Rohinipadar Nuapada 4000 41 Brahamaniguda to Kuliharibahal Nuapada 5000 42 Naira-Bainaguda road Rayagada 453 43 Majhiguda-Jaganathapur Rayagada 290 44 Kolnara-Munisingi-Khedapada Rayagada 782 45 Rayagada to Baisingi via Chekaguda Rayagada 2938 46 Hatamuniguda- Nirgundi Rayagada 553 47 Telengapadar-Sardhapur Rayagada 2086 48 PWD Road to Royalpadar Biripadar Rayagada 2475 49 Kereda Bilesu road Rayagada 84 50 Kolnara Munisingi Khedapada Rayagada 1365 51 Jimidipeda Pipalguda road Rayagada 2 52 B.Cuttack Dukum road Rayagada 400 53 Jimidipeta Champikota road Rayagada 2 54 PWD Road to Ghodabadi Rayagada 4864 55 Dangasorada to Nauduguda Rayagada 5000

Outcome Budget: DoRD for 2014-15 Page 101

56 Jujistipur chowk to Basudevpur Subarnapur 4000 57 BARD road to Bajikhol Subarnapur 4500 58 NK RD road to Chuhanpali Subarnapur 2500 59 PWD road to Krushnapali Subarnapur 4500 Total : 195500 04-Dist & Other roads-800-Other Expr. 1 Mahimunda Talpalli road Bolangir 500 2 Jarasingha Salepali via Baddunguri road Bolangir 1680 3 PWD road to Kultapada via Khairguda, Kumuria Bolangir 1340 4 Loisingha Badibahal road Bolangir 2000 5 Ghungi Dunguripali road Bolangir 1500 6 Duduka Kutasingha via Rampur Bakti road Bolangir 3000 7 Patnagarh PWD road to Dunguripali road Bolangir 2000 8 Batharla Gohirmunda road Bolangir 2800 9 Jogimunda Dhandadadar road Bolangir 3000 10 Kansapala Matikhai road Bolangir 1700 11 Mandal Madhyapur via Kenkeba road Bolangir 1300 Patnagarh Kantabanji PWD road to Patnagarh 12 Bolangir 1500 Tikrapada PWD road 13 Rengali Lathore via Udenbandha road Bolangir 1 14 Nandupala Turla Jhankarpali road Bolangir 1 15 Agalpur Nagaon via Mahakhanda road Bolangir 1 16 Duduka Kutasingha via Rampur road Bolangir 1503 17 Jarasingha to Kuliabahal via Baddunguripali Bolangir 1 18 Kudasingha to Siris road Bolangir 6000 19 Amthimunda chhok to Karnapali road Bolangir 5000 20 Ingsa to Nagraj road Bolangir 5000 21 Bhadra Badipara RD road to Dedhel road Bolangir 6000 22 Barlapali to Sargipali road Bolangir 4000 23 Jharphatamunda to Satchun road Bolangir 5000 24 PWD road to Khiarpali via Bagalabandh Bolangir 5000 25 L95 to Gailmara Bolangir 6000 26 Badtika to Ghunatipali road Bolangir 5000 27 Belgaon Ampali RD road to Deuli road Bolangir 4000 28 Saintala Block Boarder to Gudvella Block Boarder Bolangir 6000 29 NH 201 to Ghuchinerpali road Bolangir 6000 30 Maharapadar Kandarbhata Bolangir 6000 Haldi to Muribahal road (from 0/5 to 2/10, 3/0 to 3/50 31 Bolangir 828 & 3/80 to 7/50Km) 32 Sireikela to Goudtola road (from 26/715 to 28/000Km) Bolangir 559 Nunhad to Tureikela road (from 10/650 to 11/400 & 33 Bolangir 2321 13/000 to 14/000Km)

Outcome Budget: DoRD for 2014-15 Page 102

34 PWD road to Bhuslad Bolangir 127 35 Haldi – Muribahal road Bolangir 2178 36 Sireikela to Goudtola road Bolangir 799 37 Bhatipada to Lebda RD road Bolangir 1 38 PWD road to Lebda RD road Bolangir 1 39 PWD road to Lebda RD road Bolangir 1 40 Kantabanji Tureikela via Kuibahal Bolangir 1 41 Kantabanji to Chatuanka Bolangir 1 42 Malkasira to Themra Bolangir 1 43 Dhumamal to Kharjuri Bolangir 4000 44 Burdipara to Kumbhipada road Bolangir 4000 45 Rigdol Lutherbandh RD road to Ghisirmal Bolangir 2500 46 PWD road to Bijmal Bolangir 4000 47 PWD road to Bagbel road Bolangir 4500 48 NH 217 to Paraskuni road Bolangir 3000 49 Sireikella Goudtola RD road to Khalipara road Bolangir 4000 50 Kapilabhata to Malpada road Bolangir 5000 51 R.D. Road to Sarlanji Kalahandi 6000 52 NH201 to Suruguda Kalahandi 8000 53 Rahul bridge to Sargipada Kalahandi 7000 54 PWD Road to Gundri Kalahandi 6000 55 R.D. Road to Kanagaon Kalahandi 4000 56 RD Road to Chokobahali Kalahandi 5000 57 R.D Road to Kutenpadar Kalahandi 5000 58 Dongriguda to Kasibahal Kalahandi 1 59 Kenduguda Sargiguda (Phase-I) Kalahandi 1 60 to Farang Kalahandi 1 61 Kegaon to Badcherigaon (Phase-I) Kalahandi 1 62 Dhanarpur to Khuntia Kalahandi 3000 63 Ladugaon to Mahajanguda Kalahandi 1 64 Dharmagarh to Ampani Kalahandi 1 65 Dharamgarh to Charbahal Kalahandi 1 66 Dahagaon to sargiguda Kalahandi 1 67 Dongriguda to Kasibahal Kalahandi 1 68 Kenduguda Sargiguda (Phase-II) Kalahandi 1 69 Kegaon to Badcherigaon (Phase-II) Kalahandi 6833 70 RD Road to Latabanji Kalahandi 6000 71 Kotagaon to Bindhaniguda Kalahandi 6000 72 Rd Road to Hernapada Kalahandi 6000 73 NH-201 Ampani to Kuturu Kalahandi 6000 74 jaipatana to Chhatapadar (Nuapada) Kalahandi 4000

Outcome Budget: DoRD for 2014-15 Page 103

75 Hardali Nuagaon raod Koraput 1805 76 Jeypore Gheuri Phampuni road Koraput 3563 77 Umuri Chapar road Koraput 1314 78 Padwa Underguda road Koraput 600 79 Ambaguda Hadia Putra Telia Jamunda Koraput 4188 80 Guneipada Godihanjar Kitchabeda Jallaput Koraput 2702 81 Deoghati Bogeipadar Koraput 1638 82 Hardali Nuagaon raod Koraput 1891 83 Badel to Sukriput Koraput 4200 84 Kosagua to Dahadapalla Koraput 6000 85 P.W.D road to Malidambaput Koraput 3000 86 Umbel to Koraput 6000 87 P.W.D. Road Tarliput Koraput 3000 88 PWD Road to Machapadar Koraput 6000 89 Gotijodi to Gajuguda Malkangiri 5000 90 Meka to Dauduguda Malkangiri 4000 91 GB Road to Talagudaput Malkangiri 5000 92 MV-86 to Padmapur Malkangiri 2500 93 Mathili Kaliaguda Road Malkangiri 2 94 MV.2 to MV.1 Road Malkangiri 2673 95 Malkangiri to MV.27 Road Malkangiri 1531 96 MM Road to Zonal Hospital Road Malkangiri 1 97 MV-31 to Palmeta Road Malkangiri 4000 98 BM road to Mahulput Malkangiri 5000 99 RD Road to Mashaguda Malkangiri 5000 100 MV-107 to MPV-63 Road Malkangiri 5000 101 Umuri Jn (T-0905) to Kandhaguda Road Nabarangpur 3000 102 Mendra to Tapaguda Road Nabarangpur 6000 103 B. Debtaguda to Podapala Road Nabarangpur 6000 104 Bharanpur jn (T-0907) to Bhimaguda Road Nabarangpur 1500 105 Gharachapara jn to Bijilipara Nabarangpur 6000 106 Sana Temera to Mundkhaguda road Nabarangpur 7000 107 PL road to Landibeda Nabarangpur 7000 108 Tohra to Keripadar Nabarangpur 7000 109 Nirundi to Dabriguda road Nabarangpur 7000 110 Chalanpara to Handikadara Nabarangpur 7000 111 Paraskhol to Jamdarha Road Nuapada 1804 112 Nuapada to Kuliabandha Road Nuapada 1483 113 Sialati to Kotenchuan Road Nuapada 1483

Outcome Budget: DoRD for 2014-15 Page 104

114 Komna to Bhella Road Nuapada 1882 115 Gandabahali to Liad Road Nuapada 378 116 Budhapada to Lanji Road Nuapada 564 117 Damjhar to Karlakote Road Nuapada 1860 118 PWD road to Latkanpada road Nuapada 4000 119 Hatibandha to Bharuamunda rod Nuapada 3000 120 Karangamal to Boden via Kerapadar Nuapada 3000 121 Lakhna Thakpali Road to Tankapani Nuapada 4500 122 PS Road to Haldikhol Nuapada 8000 123 SH-3 to Padampuri Nuapada 8000 124 Sialati to Tengnabasa via Sunarital Nuapada 8000 125 SH-3 Saipala to Gundrijhar Nuapada 4000 126 Kandetara to Bharuamunda Nuapada 7000 127 Butingi Jn. To Alamguda Rayagada 8000 128 132 KVLine Road to Patuguda Rayagada 7000 129 PS Road to Sikajhila Rayagada 5000 130 RD Road to Chiligudi Rayagada 9000 131 Kamsara to Chavata Singhari Via Khaivadi road Subarnapur 2000 132 Cherupali to Agalpur road Subarnapur 100 133 Narayanpur High School Chowk to Teleimal road Subarnapur 1400 134 Binika to Papakhaya road Subarnapur 1500 135 Mundaghat Jalai upto Rathpur Subarnapur 100 136 PWD road to Ainlachat to Krushnapur via Sulia Subarnapur 100 137 Cherupali Agalpur road (10/2 to 12/0 km.) Subarnapur 100 138 Kamasara Surda Subarnapur 1000 139 NH 224 to Janmura via Patabhadi Subarnapur 150 140 Daval Akhidadar Subarnapur 100 141 Mursundi Subalaya Via Khandahata Subarnapur 2800 142 Naikpara Kapasira Subarnapur 100 143 Padhanpali to Silijuri Subarnapur 4000 144 Lakhani chowck to Teleimal Subarnapur 5000 145 B.A.RD road to Purusotampur Subarnapur 4000 146 RD road to Indiranagar(Balance length) Subarnapur 5000 147 Pankel to Jogipara Subarnapur 3000 148 Kamsara Balikhamar to Kulthiapadar Subarnapur 5000 149 RD road to Fakirmunda Subarnapur 5000 150 Khuntulapali to Kulhapara (Balance length) Subarnapur 5000 151 PWD road (Gumurdala )to Nachipadar Subarnapur 5000 152 Kartang to Gariapali Subarnapur 5000

Outcome Budget: DoRD for 2014-15 Page 105

153 RD road to Indiranagar Subarnapur 4000 154 T.L.RD road to Pipilipali Subarnapur 4000 155 Khuntulapali to Kulhapara Subarnapur 6000 Total : 510000 Grand Total 850000 N.B The work / Scheme / Project wise allocation is tentative & may be varied in keeping : with the progress of work during the course of the financial year.

Outcome Budget: DoRD for 2014-15 Page 106

Work list under D.no.28-5054-COL on Roads & Bridges-SP-DS-04-DOR-1230 Rural roads-789-SCP SC/796-TASP/800-OE-37281-Constn of Bailey bridges for the year 2014-15 Sl. Name of project District in Financial No. which outlay implemented in TRs including General, SCP & TASP 101-Bridges Kendili - Laktiguda road, G.P.-Bethiapada, Block- Bissam 1 Rayagada 4305 Cuttack Putupadar - Bhatapur road, G.P.-Bhatapur, Block-Bissam 2 Rayagada 5463 Cuttack 3 Paridi - Marama road,G.P.-Moroma, Block- Gunpur Rayagada 5658 Panchapadava - Goudapadar rroad, , G.P.-Pendili, Block- 4 Rayagada 11789 Gudari. 5 Thurudi - Luhamunda road,G.P.-Pendili, Block- Gudari. Rayagada 13267 Khamariguda- Dakorama road, G.P.-Tembaguda, Block- 6 Rayagada 7406 Padmpur. Kopadango- Bada Erukubadi road, G.P.-Bada Erukubadi, 7 Rayagada 8911 Block- Rayagada. 8 Balput - Banikona road, G.P.-Baising, Block- Rayagada Rayagada 3718 9 B.K.Padar - Arabi road, G.P.-Karagudi Rayagada 9147 Raghunathpur- Majhiguda road, G.P.-Majhiguda, Block- 10 Rayagada 8566 K.Singhpur. 11 Karapa - Landabali road, G.P.-Karapara, Block- K.Singhpur Rayagada 3213 12 Kalakani - Kumbharasila road, G.P.-Kashipur, Block- Kashipur. Rayagada 5518 13 Lekapai-Champia road, G.P.-kolnara, Block- kolnara. Rayagada 7977 14 Balungi -Kumbhikota road, G.P-Kumbhikota, Block- Rayagada. Rayagada 19301 15 Mirabali -Rachapaka road, G.P.-Mirabali, Block- Rayagada. Rayagada 3409 16 Rengalpadu -Mirabali road,G.P.-Mirabali, Block- Rayagada. Rayagada 4987 17 Pipalguda- Uapaka road, G.P.-Pipalguda, Block- Rayagada. Rayagada 8664 18 Didwa -Kornaopadu road, G.P.-Poloma, Block- K.Sinpur Rayagada 8949 Dibalpadu - Pujariguda road, G.P- Pujariguda, Block- 19 Rayagada 3956 K.Singpur. Dimiribadi -Pujariguda road, G.P.- Pujariguda, Block- 20 Rayagada 8593 K.Singpur. 21 Balipur - Karadang road, G.P.- Seriguma, Block- K.Singpur. Rayagada 7855 22 R.D. Road - Delibadi road, G.P.- Sikarapai, Block- K.Singpur. Rayagada 17975 Hasku - Bada Erukubadi road, G.P.-Bada Erukubadi, Block- 23 Rayagada 6235 Rayagada. 24 Boriguda -Singari road, G.P.- Sikarapai, Block- K.Singpur. Rayagada 20412 25 Khambaribhatta - Singari road,G.P.- Singari, Block- K.Singpur. Rayagada 18325 26 Paduguda - Singari road, G.P.- Singari, Block- K.Singpur Rayagada 19598 27 Palakhaman - Singari road,G.P.- Singari, Block- K.Singpur Rayagada 17645 28 Palligaon- Sarati road,G.P.- Sunakhandi, Block- K.Singpur Rayagada 3116 29 Godelpas-Manusgaon GP-Manusgaon, Block-Kasipur Rayagada 1

Outcome Budget: DoRD for 2014-15 Page 107

30 Kumbharsila-Ratapadar GP-Kashipur, Block-Kasipur Rayagada 1 31 Kabatsil-Gumudisupel GP-Manusgaon, Block-Kasipur Rayagada 1 Ladiguda-Parkakupakhal/Kundipari, (1) GP-Kudipari, Block- 32 Rayagada 1 Kasipur Ladiguda-Parkakupakhal/Kundipari, (2) GP-Kudipari, Block- 33 Rayagada 1 Kasipur 34 Kantrabali-Kamalabadi GP-Muniguda, Block-B.Cuttack Rayagada 1 35 Sutaruruni-Sakata GP-Mlmiguda, Block-B.Cuttack Rayagada 1 36 Tobhapedar-Kauguda GP-Muniguda, Block-B.Cuttack Rayagada 1 37 Tulusipadar-Badadahikhal GP-Muniguda, Block-B.Cuttack Rayagada 1 38 Dumriguda-Khedapada GP-Khedapada, Block-Kolnara Rayagada 1 39 Halam-Kaju GP-Kariaghati, Block-Gudari Rayagada 1 40 Kandapendili-Gurutha GP-Khariguda, Block-Gudari Rayagada 1 Bridge at Antapali, Kukudapli, , G.P.-Batemura, Block- 41 Sambalpur 1 42 Bridge over Kalpa nallah, G.P.-Nuabarangamal, Block-Jujumura Sambalpur 1 Bridge on Luhapank to Gadmunda, G.P.-Luhapank, Block- 43 Sambalpur 1 Rairakhol Bridge at Kandhel on Sadhudahali road Dhauragodh, G.P.- 44 Sambalpur 1 Salebhata, Block-Naktideul Bridge at Cuttack nallah on Badmal to Brahmani road, G.P.- 45 Sambalpur 1 Ghosaramal, Block-Naktideul Bridge over Deogaon river at Fasimal, G.P.-Fasimal, Block- 46 Sambalpur 1 Jamankira Bridge at Betghar to Kusumkhol, G.P.-Luhapank, Block- 47 Sambalpur 1 Jamankira 48 Bridge at Pitha nallah, G.P.-Luhapank, Block-Rairakhol Sambalpur 1 49 Bridge at Kendukupali nallah, G.P.-Luhapank, Block-Rairakhol Sambalpur 1 50 Bridge at Betghat to Kosali, G.P.-Luhapank, Block-Rairakhol Sambalpur 1 Bridge at Bijaguda to Damagaon, G.P.-Kenadhipa, Block- 51 Sambalpur 1 Jamankira 52 Bridge at Fulchangudi , G.P.-Kenadhipa, Block-Jamankira Sambalpur 1 53 Bridge at Bamandagarh, G.P.-Dimirimunda, Block-Jamankira Sambalpur 1 Bridge at Tileising nallah on Landimal to Dhatukimal road, G.P.- 54 Sambalpur 1 Ghosaramal, Block-Naktideul Bridge over Ranja nallahon Mura to Kanibandhali, G.P.- 55 Sambalpur 1 Nuatihura, Block-Maneswar 56 Bridge over Mahulpali nallah , G.P.-Tabla, Block-Maneswar Sambalpur 1 57 Bridge over Ahida nallah on Barbahali to Daghora station road Sundargarh 1 58 Bridge over Local nallah on Kankutura to Latakhandi road Sundargarh 1 59 Bridge over Local nallah on Bhograkachhar to Latapali road Sundargarh 1 Bridge over Karo nallah on Rengalbeda to Kalta road under 60 Sundargarh 1 Koida G.P. 61 Bridge over Kuradhi nallah at Nuatantra under Dengula G.P. Sundargarh 1 62 Bridge over Kuradhi nallah at Gaganposh under Chordhara G.P. Sundargarh 1 Bridge over Khatma nallah on Kadamtoli to Khatma road under 63 Sundargarh 1 Purunapani G.P. Bridge over Kilbaga nallah on Kansar to Jharbandha road under 64 Sundargarh 1 Kundeidiha G.P.

Outcome Budget: DoRD for 2014-15 Page 108

Bridge over Samsara nallah on Jharposh to Jalei road under 65 Sundargarh 1 Kundeidiha G.P. Bridge over Badajora nallah on Kadabira to Ulundujham road 66 Sundargarh 1 under Sole G.P. Bridge over Local nallah on Kucheita to Kusumtola road under 67 Sundargarh 1 Kucheita G.P. Bridge over Tetrabahal nallah on Tetrabahal to Linetoli road 68 Sundargarh 1 under Undali G.P. Bridge over Sundar nallah on Ratakhandi to Surli road under 69 Sundargarh 1 Kukundubahal G.P. Bridge over Sundar nallah on Kukundubahal to Nandatoli road 70 Sundargarh 1 under Kukundubahal G.P. Total : 264000 789-SCP for SC 1 Anukundaguda - Jeeba, G.P.- Gumma, Block- Gumma. Gajapati 9891 2 Anukundaguda - Radhakantpur , G.P.- Gumma, Block- Gumma. Gajapati 10538 3 Padursingh-Sulsulada , G.P.- Gumma, Block- Gumma. Gajapati 9712 4 Analaguda -Mohana , G.P.- Mohana, Block- Mohana. Gajapati 17023 5 Balipanka - Chandiput , G.P.- Mohana, Block- Mohana. Gajapati 6849 6 Hundipadar - Pinkidi , G.P.- Mohana, Block- Mohana. Gajapati 7610 7 Binjiri - Deopur Road, G.P.- Gosani, Block- Gosani. Gajapati 8302 8 Ramchandrapur - Luhagudi , G.P.- Mohana, Block- Mohana. Gajapati 4866 9 B.K.ltamana to Labs GP-Dambosara, Block-Gunupur Rayagada 1 10 Elrnanguda-Bada Barida GP-Golholpadar, Block-Gunupur Rayagada 1 11 Buvalkul-Anjarbaising GP-Kulusing, Block-Gunupur Rayagada 1 12 Kadasi-Ajingtal GP-Kulusing, Block-Gunupur Rayagada 1 13 Saisingi-Gudi GP-Kutusing, Block-Gunupur Rayagada 1 14 Plolour Nalls-Borel GP-Puttasing, Block-Gunupur Rayagada 1 15 Oreepul-Rayalpadu GP-Sagada, Block-Gunupur Rayagada 1 16 Kimjhola- Deriguda, GP-Deriwun, Block-Padmapur Rayagada 1 17 lswarguda-Bahpanga GP-Kadama, Block-Padmapur Rayagada 1 Total : 74800 796-TASP 1 Majhiguda -Kusumi road, G.P.- Chitra, Block- Kotpad. Koraput 6147 2 Raikundra - Kenduguda road, G.P.- Kundra, Block- Kundra. Koraput 5201 P.Mundiguda - Bhusangaguda road,G.P.- Kusumi, Block- 3 Koraput Kotpad. 1419 Basuaput - Purimunda road, G.P.- Dasamantpur, Block- 4 Koraput Dasamantpur. 4728 Dasamantpur-angipur road,G.P.- Dasamantpur, Block- 5 Koraput Dasamantpur. 7093 Girligumma -Duarsuni road,G.P.- Dasamantpur, Block- 6 Koraput Dasamantpur. 8511 Kiramba - Jamuru road,G.P.- Dasamantpur, Block- 7 Koraput Dasamantpur. 7093 Tamaksil -Tamaksil road, G.P.- Dasamantpur, Block- 8 Koraput Dasamantpur. 7093 9 Gadikhal- Kalijhola road,G.P.- Laxmipur, Block- Laxmipur. Koraput 6620

Outcome Budget: DoRD for 2014-15 Page 109

10 Kedupati - Bagmari road,G.P.- Laxmipur, Block- Laxmipur. Koraput 9457 11 Odiapentha - Bisampur road, G.P.- Laxmipur, Block- Laxmipur. Koraput 9457 12 Girliput - Jogiput road, G.P.- Nandapur, Block- Nandapur Koraput 9457 13 Sipurijholla - Kugum road, G.P.- Nandapur, Block- Nandapur Koraput 6620 14 Tema - Kirajholla road, G.P.- Pottangi, Block- Pottangi. Koraput 5674 Hataguda - Gadikhamara road,G.P.- Similiguda, Block- 15 Koraput Similiguda 6618 16 Kutradhar-Chakunde GP-M.K.Rai, Block-Padmapur Rayagada 1 17 Sriramnagar-Binishpur GP-Pujariguda, Block-K.Singpur Rayagada 1 18 Kodingiguda-Haula GP-Haula, Block-Rayagada Rayagada 1 19 Tala Sankesu-Haula GP-Haula, Block-Rayagada Rayagada 1 20 Mautiguda-Jamedaipentha GP-Jamedaipentha, Block-Rayagada Rayagada 1 21 Mardipuda-Kumbhikota GP-Kumbhikota, Block-Rayagada Rayagada 1 22 Badamanadhar-Kutuli GP-Kutuli, Block-Rayagada Rayagada 1 23 Gumjiguda-Adajor GP-Adajor, Block-Kasipur Rayagada 1 24 Kisankedi-Adajor GP-Adajor, Block-Kasipur Rayagada 1 Ladiguda-Palkakupachal/Jogipartunda, (1) GP-Jogiparitunda, 25 Rayagada Block-Kasipur 1 Ladiguda-Palkakupachal/Jogipartunda, (2) GP-Jogiparitunda, 26 Rayagada Block-Kasipur 1 27 Mandibisi-Katagaon GP-Mandibisi, Block-Kasipur Rayagada 1 Total : 101200 Grand Total 440000 The work / Scheme / Project wise allocation is tentative & may be varied in keeping with N.B.: the progress of work during the course of the financial year.

Outcome Budget: DoRD for 2014-15 Page 110

STATE PLAN (2014-15)

Rural Water Supply & Sanitation ` in TRS Name of the Sl. Financial Outlay Broad Quantifiable/Deliverable Processes/ Remarks/Ris Schemes/Pr Project Outcome No objective Physical Outputs Timelines k Factors ogramme 1 2 3 4 5 6 7 8 National 2200000-State Share Rural Availability of safe drinking Availability of of NRDWP, Provide safe drinking water by Drinking water / Coverage of 11000 potential 100000 – RIDF – Providing safe installing PWS/TWs/SWs. Water rural habitations, through Source with 1 Rural Water Supply drinking water Coverage of Habitations, 12 months Programme 30000 spot sources & 1300 quality water, to rural public provide safe drinking in (NRDWP) PWS Schemes & 1000 Solar electricity and 2207800–(Anticipated quality affected areas. and Sate Powered PWS Schemes Govt. land. Central Share) Plan Rural Water Providing safe Provision of drinking water 2 Supply 500000 drinking water where coverage through 12 months to rural public NRDWP is not possible Survey & Investigation State Plan – work including Source Establishment of PMU, 3 Capacity 70000 finding of 1254 PWS enhance quality of service, 12 months Building schemes proposed to be training of personnel etc. taken up in 2014-15 Construction and completion of Departmental Office State Plan – Construction of Building and Residential 4 Building 110000 Official/Residential buildings 12 months Building (Including `1.00 Programme of RWS&S Organisation crore for Improvement of IGTC Palasuni) 2980000 (State Plan) 2980000 Total Social 2207800 (NRDWP- (State Plan) Services Central Share) 2207800 Sector (NRDWP-Central Share)

Ooutcome Budget : DoRD for 2014-15 Page 111

NON PLAN (2014-15) Sl. Name of the Financial Broad objective of the Quantifiable/D Project Outcome Processes/ Remarks/Risk No. Schemes/Programme Outlay/ Non- Scheme eliverable Timelines Factors Salary Physical with Budget Head (Deliverable Outputs outputs) 1 2 3 4 5 6 7 8 RURAL WORKS ORGANISATION 2059-Repair, Maintenance Improve the working 12 months Physical output could not Can not be Maintenance of Office of Non-Residential condition of officials in be quantified as these are 1 15027.04 assessed being Buildings in Rural Building Rural areas. operation and maintenance repair work Areas works. i. To maintain approx. 12 months - 2059-Repair and 1025 old High School

renovation of old Govt. & College Buildings Improvement of Can not be High School and College which are 30 years 2 (i) 3400.00 Educational infrastructure assessed being Buildings ii. Maintenance of E.I. (ii) 100.00 repair work (i) 21159-above 30 years & PH works of 506

(ii) 21145-above 50 years nos. of High School Buildings 2216-Repair and Improvement of living 12 months Physical output could not Can not be Maintenance of maintenance of Residential condition of officials be quantified as these are 3 5150.62 assessed being Government buildings working in rural areas. operation and maintenance repair work Residential Buildings works. Physical output could not Can not be 3054-Repair and be quantified as these are Up keeping the rural road assessed being Maintenance of Rural 4 Maintenance of Rural 47880.21 12 months operation and maintenance infrastructure repair nature of Roads and Bridges. Roads and Bridges works. work

3054-2582-Maintenance of Repair & Maintenance 12 months - Up keeping the rural road 5. roads & bridges under 13th 13614.44 2289 Km. of RD & PMGSY roads infrastructure FC Award & CD works 12 months Physical output could not Can not be Maintenance of 3054-1230-198-Grant –in- Up keeping the rural road be quantified as these are 6 4800.00 assessed being PMGSY Roads. Aid General (Non-salary) infrastructure operation and maintenance repair work works. TOTAL 89972.31

Ooutcome Budget : DoRD for 2014-15 Page 112

NON PLAN (2014-15) Rural Water Supply & Sanitation Sl. Name of the Financial Quantifiable/Deliverable Financial Remarks/Risk Factors No. Schemes/Programme with Outlay/ Non- Physical Outputs Target Budget Head Salary (Deliverable outputs) (Provisional) 1 2 3 4 5 6 28-2059 Maintenance Ext W/S & S/I Physical output could not be quantified 1 Repair, Maintenance of Non- 50600 of Govt Office Buildings in 50600 as these are operation and maintenance Residential Building Rural Areas works. 28-2216 Maintenance Ext W/S & S/I Physical output could not be quantified 2 Repair and maintenance of 33420 of Govt residential Buildings 33420 as these are operation and maintenance Residential buildings in Rural Areas works. 28-2215 Physical output could not be quantified Repair and maintenance a Repair and Carriage as these are for maintenance and nd POL for running of 3 Machinery & Equipment 5500 5500 running of vehicles. Machinery & Equipment including Vehicles and Rigs including Vehicles and Rigs of RWSS 28-2215 Physical output could not be quantified Maintenance and upkeep of Repair and maintenance of as these are operation and maintenance existing 316281 Spot 4 Rural Water Supply System 251291 251291 works. Sources, 7693 rural piped including tube well and water supply schemes. sanitary wells Total 340811 340811

Ooutcome Budget : DoRD for 2014-15 Page 113

ABSTRACT STATE PLAN ` in TRS) Sl No Name of the Scheme / Programme Financial Outlay (Provisional) Physical Outputs / Number of Beneficiaries 1 National Rural Drinking Water Programme 2200000-State Share of NRDWP, (NRDWP) 10,00,00 – RIDF – Rural Water Supply 2207800–(Anticipated Central Share) 2 Rural Water Supply 500000 3 State Plan – Capacity Building 70000 4 State Plan – Building Programme 110000 Total Social Services Sector 2980000 (State Plan) 2207800 (NRDWP-Central Share)

NON PLAN 1 Repair, Maintenance of Non- Residential Building 50600 2 Repair and maintenance of Residential buildings 33420 3 Repair and Carriage Machinery & Equipment 5500 including Vehicles and Rigs of RWSS 4 Repair and maintenance of Rural Water Supply 251291 System including tube well and sanitary wells

Ooutcome Budget : DoRD for 2014-15 Page 114

DISTRICT WISE PWS SCHEMES TO BE TAKEN UP DURING 2014-15

Sl. District Division No of No of New Total No of No. Ongoing PWS PWS Scheme PWS Scheme Scheme

Cov WQ Cov WQ Cov WQ 1 Angul Angul 79 9 22 10 101 19 2 Balangir Balangir 117 19 39 17 156 36 3 Balasore Balasore 76 19 34 14 110 33 4 Bargarh Bargarh 77 21 34 14 111 35 5 Bhadrak Bhadrak 57 28 20 8 77 36 6 Boudh Boudh 23 9 8 4 31 13 7 Cuttack Cuttack 63 34 39 17 102 51 8 Deogarh Deogarh 16 2 8 4 24 6 9 Dhenkanal Dhenkanal 94 9 22 10 116 19 10 Gajapati Gajapati 35 1 20 8 55 9 11 Ganjam Berhampur 113 10 29 13 142 23 Bhanjanagar 109 19 31 13 140 32 12 Jagatsinghpur Jagatsinghpur 37 13 22 10 59 23 13 Jajpur Jajpur 92 21 28 12 120 33 14 Jharsuguda Jharsuguda 36 4 14 6 50 10 15 Kalahandi Kalahandi 126 18 36 16 162 34 16 Kandhamal Phulbani 114 20 34 14 148 34 17 Kendrapara Kendrapara 76 28 25 11 101 39 18 Keonjhar Keonjhar 140 39 36 16 176 55 19 Khurda Bhubaneswar 63 4 28 12 91 16 20 Koraput Koraput 56 36 39 17 95 53 21 Malkangiri Malkangiri 29 29 20 8 49 37 22 Mayurbhanj Baripada 119 31 39 17 158 48 Rairangpur 70 18 34 14 104 32 23 Nabarangpur Nabarangpur 85 16 28 12 113 28 24 Nayagarh Nayagarh 38 9 22 10 60 19 25 Nuapada Khariar 0 4 0 0 0 4 Nuapada 42 12 14 6 56 18 26 Puri Puri 111 3 31 13 142 16 27 Rayagada Rayagada 59 18 31 13 90 31 28 Sambalpur Sambalpur 56 13 25 11 81 24 29 Subarnapur Sonepur 36 4 17 7 53 11 30 Sundargarh Rourkela 42 30 22 10 64 40 Sundargarh 65 8 25 11 90 19 TOTAL 2351 558 880 374 3231 932

Ooutcome Budget : DoRD for 2014-15 Page 115

DISTRICT WISE INSTALLATION OF SPOT SOURCES TO BE TAKEN UP DURING 2014-15 Sl. No. District Division No of Spot Sources 1 Angul Angul 1000 2 Balangir Balangir 1000 3 Balasore Balasore 1000 4 Bargarh Bargarh 1000 5 Bhadrak Bhadrak 1000 6 Boudh Boudh 1000 7 Cuttack Cuttack 1000 8 Deogarh Deogarh 1000 9 Dhenkanal Dhenkanal 1000 10 Gajapati Gajapati 1000 11 Ganjam Berhampur 500 Bhanjanagar 500 12 Jagatsinghpur Jagatsinghpur 1000 13 Jajpur Jajpur 1000 14 Jharsuguda Jharsuguda 1000 15 Kalahandi Kalahandi 1000 16 Kandhamal Phulbani 1000 17 Kendrapara Kendrapara 1000 18 Keonjhar Keonjhar 1000 19 Khurda Bhubaneswar 1000 20 Koraput Koraput 1000 21 Malkangiri Malkangiri 1000 22 Mayurbhanj Baripada 500 Rairangpur 500 23 Nabarangpur Nabarangpur 1000 24 Nayagarh Nayagarh 1000 25 Nuapada Khariar 0 Nuapada 1000 26 Puri Puri 1000 27 Rayagada Rayagada 1000 28 Sambalpur Sambalpur 1000 29 Subarnapur Sonepur 1000 30 Sundargarh Rourkela 500 Sundargarh 500 TOTAL 30000

Ooutcome Budget : DoRD for 2014-15 Page 116

BUDGETARY PROVISION FOR 2014-15 Sl. No. Name of work Ch. Head No of Budgetary Prov. Schemes 2014-15 in Crore 1 2 3 4 5 1. Piped Water Supply Coverage 3231 62.17 Scheme Water Quality 932 88.30 2. Installation of Spot Coverage 30000 145.33 Sources(TW/SW) 3. Sustainability Sustainability 44.15 Structures 4. Operation & O&M 66.21 Maintenance of PWS & Spot Sources

Ooutcome Budget : DoRD for 2014-15 Page 117

RESIDENTIAL BUILDINGS

Name of the Nos.of Budget Provision Sl.No. Remarks Division Building (Rs. In lakhs )

1 2 3 4 5 1 Angul 11 135.70 2 Balasore 1 6.20

3 Baripada 5 42.60

4 Bhadrak 2 30.40 5 Dhenkanal 6 60.00 6 Jagatsinghpur 6 62.20 7 Jharsuguda 10 79.50 8 Malkangiri 3 40.60 9 Koraput 3 31.50 10 Rairangpur 14 76.90 11 Sambalpur 3 22.60 12 Sonepur 2 11.80

TOTAL : 66 600.00

Ooutcome Budget : DoRD for 2014-15 Page 118

NON-RESIDENTIAL BUILDINGS

Sl.No. Name of the Nos.of Budget Provision Remarks Division Building (Rs. In lakhs )

1 2 3 5

1 Balasore 5 63.00

2 Baripada 4 37.40

3 Bhubaneswar 1 75.00

4 Bhadrak 7 41.00

5 Bolangir 1 50.00

6 Cuttack 2 93.50

7 Dhenkanal 2 4.30

8 Jharsuguda 3 34.20

9 Rairangpur 6 18.70

10 Rourkela 1 23.00

11 Kalahandi 1 9.60

12 Sambalpur 4 50.30

TOTAL : 37 500

Ooutcome Budget : DoRD for 2014-15 Page 119

CHAPTER-III Reform Measures and Policy Initiatives

R.D. Department has taken many e-initiatives to monitor and maintain transparency in the works being implemented by the Department. The provision of basic public services being provided through electronic mode are: (I) Website: The information relating to R.D. Department is being uploaded to the State Govt. website i.e. http://www.rdodisha.in/index.htm. The website of the department acts as an index of all activities relating to R.D. Department. Further, links have been provided to all other e-activities undertaken by this Department. The information on Pradhan Mantri Gram Sadak Yojana (PMGSY), Drinking Water Supply and Nirmal Bharat Abhiyan (NBA) is being monitored online. The letters dispatched through e-Dispatch by the Department are also being webhosted. The information coming under Right to Information Act is also being updated and available in the Department website. (ii) e-Desptch: Starting from the R.D. Department at Secretariat, an electronic integrated platform for dispatching letters is in use up to Division level since 2009. All letters are web-hosted for public view for transparency, quick transmission and easy access. (iii) Integrated Management Information System (IMIS): A web-based system (http://indiawater.gov.in/imisweb/) for management & monitoring of drinking water supply system has come into force with effect from 1st April, 2009. Officials as well as public can know every detail of drinking water sources available in their habitation, the cost of the project, year of installation etc. (iv) Online Monitoring and Management of Accounts System (OMMAS): To make it transparent and proper monitoring of both physical and financial progress,of PMGSY work, C-DAC, Govt. of India have developed a web-based software for online monitoring and management namely OMMAS. The URL of OMMAS site is http://www.pmgsy.org/. By accessing this site, the public can see the details of roads taken up under PMGSY, it's executing agency, the cost of the roads, the length of roads and it's physical & financial progress. (v) Nirmal Bharat Abhiyan (NBA): The information on NBA is also being monitored online. The URL of the NBA website is http://tsc.gov.in/tsc/NBA/NBAHome.aspx. The details of Individual Household Latrines, Anganwadi Toilets, Village Sanitary Complex constructed under TSC are available in the website. OSWSM has its own website as http://oswsm.com (vi) Integrated Grievance Redressal System (IGRS): An IGRS named as Sanjog Helpline (www.sanjoghelpline.in) is an IT solution which informs about the grievance of a common man to the right authority in real time via SMS, email & FAX. A toll-free number i.e. 155335/18003456770 has been provided for the public to register their complaints. IGRS is activated and operated towards the goal for smooth redressal of public

Ooutcome Budget : DoRD for 2014-15 Page 120 grievances on Rural Water Supply and Sanitation (RWSS) and Pradhan Mantri Gram Sadak Yojana (PMGSY). (vii) e-Procurement: It is carrying out traditional tendering process in an electronic form (through internet). It connects the procuring organization with the bidders through electronic exchange of tende` It is a management and reform program in the procurement field. e-Procurement and iOTMS is done with a software application that includes features for supplier management and complex auctions. Here in the electronic tendering process both the Govt. and the contractors will be benefited. (viii) WAMIS: Works and Accounting Management Information System (WAMIS), a web-based software, is being developed by C-DAC, Pune. It is a Division Automation System integrated with MIS features. WAMIS has 5 modules such as : 1) Accounting Management System (AMS) 2) Works Management System (WMS) 3) Budget Management System (BMS), 4) Billing Module, and 5) Integration with AG for online submission of Monthly Accounts. By using this software Divisions are generating their Monthly Accounts and started submitting these to AG. Not only R.D. Deptt, but also all engineering departments of the State like, Works, Water Resources and H&UD Departments are now using WAMIS. (ix) CPSMS Central Plan Scheme Monitoring System, an web application for online management information and decision support system for the Plan Schemes of Government of India has been in use in the Department. The Central Sponsored Schemes like PMGSY, NRDWP and TSC have been registered in this system. (x) OSWAS Odisha State Workflow Automation System, an e-fileing system has been implemented in Rural Development Department since January, 2012. Now all files are being processed through OSWAS, which not only eases the movement of files but also tracking of Daks and files has become much easier. This makes the Department a Less Paper Office. (x) e-NIRMAN AnOnline Project Monitoring system (e-Nirman) is being used by the Department since December, 2011 o track and trace the Physical and financial progress of different projects undertaken under different important schemes like BSY, NABARD assisted projects etc.. The online application has the facility to integrate all construction activities like forecasting, tender processing, bill processing of different works like Roads, Buildings and Bridges. The application is assesible through http://www.rdodisha.in/e-Nirman.asp.  New schemes introduced. From the year 2007-08 the State Govt. have provided funds under major head-5054 under State Plan for grant to Odisha State Rural Road Agency (OSRRA) towards high tender premium and construction of bridge beyond 50 mtr for PMGSY work and under major head-3054 under

Ooutcome Budget : DoRD for 2014-15 Page 121

Non-Plan sector towards routine maintenance of the PMGSY work which have already been completed earlier. Earlier, this Department have executed PWS, Tube Well & Sanitary wells for providing safe drinking water to the rural habitation under ARWSP scheme which is subsequently GoI change by giving re-name as NRDWP by the GoI.  Change in internal processes of the Department in relation to administration of the scheme. No internal processes of the Department in relation to administration of the scheme have been changed.  Change of financing pattern and Fund flow mechanism. Only in NRDWP scheme GoI have provided funds to the implementing agency directly (i.e. CE, RWS&S) through Bank Account and the State Govt. is also provided state matching contribution to the implementing agency through Administrative Department. The Administrative Department draws the state matching share and deposits in the bank account of implementing agency.  Policy reform if any The R.D. Department has executed the PWS, Tube Well & Sanitary Wells for providing safe drinking water to rural habitation. After execution of the project the same has been transferred to Gram Panchayats for maintenance of projects. Now dedicated JEs have been posted in each block for O&M and sanitation work. We propose to go for EPC based procurement and slowly go for zero stock & store. PMGSY programme aims at providing all weather connectivity to all unconnected habitation in the rural areas of the State having more than of equal to 1000 habitations in plain areas and 500 or more in schedule area which has been relaxed by GoI from 500 to 250 habitations for selection of PMGSY road projects in such areas.  Internal Audit of PMGSY works Works and accounts of PMGSY works are normally audited by A.G. & empanelled Chartered Accountant firms as statutory audit. In order to ensure both accuracy in accounts and efficiency in the operation of financing of State agencies, MoRD in GoI has decided to make internal audit of SRRDAs and PIUs under PMGSY mandatory SRRDA will appoint internal auditors as a management aid to ensure the true and fair record of account. Accordingly, internal audit of PMGSY work in the State is being operationalised by OSRRA with effect from 2012-13 for which a Steering Committee is constituted at Govt. level. Internal audit is to be conducted half yearly basis. The audit report will be uploaded in OMMAS site.

 Change in the composition of beneficiaries, if any Not required.

Ooutcome Budget : DoRD for 2014-15 Page 122

CHAPTER-IV Past performance of programmes and schemes

The performance of DoRD at a glance is as follow

Statement of Expenditure – 2013-14 State Plan (` in TRS)

Budget Provision Expenditure upto C.O. Budget 2014-15 2013-14 March’2014

EIC,RW 7729604 7416584 28879001 CERW-I 225000 212094 250000 RWSS 2600000 2896734 5187800 (Reappropriated) OSWSM 559900 0 1000000 Total 11114504 10525412 35316801

Non-Plan

` in TRS

Budget Provision Expenditure upto C.O. Budget 2014-15 2013-14 March’2014

EIC,RW 6452974 6175625 7674406 CERW-I 2130884 2091187 2446564 RWSS 1176128 1061450 1298396 Sectt. Estt. 48721 36108 58223 TOTAL 9808707 9364370 11477589

Ooutcome Budget : DoRD for 2014-15 Page 123

(` in TRS) CHAPTER – IV Past Performance of programmes and schemes

RURAL WORKS Target for 2012-13 Achievement till 3/2013 Remarks Total Budget Sl. Expenditure Scheme (State Plan) Provision 2012- Roads Bridge/ Roads Bridge/ No. till 3/2013 13 (Nos./Km.) Buildings (Nos./Km) Buildings (in nos) (in nos) NABARD assisted RIDF Scheme for 1 1950003 1846923 8; 33 4 24 constn. of Roads and Bridges Completion of Incomplete roads and 2 274903 274000 28 15 24 12 bridges 3 Constituency-wise Allotment 284000 280669 4 PMGSY Bridges (RIDF Missing Link) 350000 350000 17 21 5 Biju Setu Yojana 1400001 1357809 50 47 6 Impvt. To existing RD roads 800001 628793 67/649.13 20 7 Special Programme for KBK 218100 155695 58/113.34 6 8 One Time ACA 500000 277853 55/406.26 19 9 Construction of R.D. Department Buildings 225000 206716 215 172 Scheme (Non-Plan) Repair and Maintenance of Non Residential Operation & 10 1160910 1155220 2850 Buildings maintenance Repair of 50 years old Govt. School Operation & 11 100000 101955 506 Buildings maintenance Operation & 12 Repair of 30 years School Building 150000 150000 750 maintenance Repair and maintenance of Residential Operation & 13 389450 374062 1430 Buildings maintenance Operation & 14 Repair and maintenance of Rural Roads 4543380 4531648 3776 km. maintenance Grant to OSRRA (PMGSY Road Operation & 15 400000 400000 maintenance which 5 years of completion) maintenance

Ooutcome Budget : DoRD for 2014-15 Page 124

RURAL WORKS (` in TRS) Target for 2013-14 Achievement till 3/2014 Remarks Total Budget Sl. Expenditure Scheme (State Plan) Provision Roads Bridge/ Roads Bridge/ No. till 3/2014 2013-14 (Nos./Km.) Buildings (Nos.) Buildings (in nos) (in nos) NABARD assisted RIDF Scheme for 1 2100000 2075240 3 35 2 26 constn. of Roads and Bridges Completion of Incomplete roads and 2 490000 450999 151 19 48 8 bridges 3 Constituency-wise Allotment 284000 280088 4 PMGSY Bridges (RIDF Missing Link) 1 Nil 34 31 5 Biju Setu Yojana 1750000 1721850 125 107 6 Impvt. To existing RD roads 781700 772423 87 12 7 Special Programme for KBK 475904 358626 64 32 8 One Time ACA 774900 708575 55 10 9 Constn of Bailey Bridges 275100 268024 10 Construction of R.D. Department Buildings 225000 212094 345 264 Scheme (Non-Plan) Repair and Maintenance of Non Residential Operation & 11 1311047 1300118 3001 Buildings maintenance Repair of 30 years old Govt. School 12 280000 280000 -do- 750 Buildings 13 Repair of 50 years School Building 20000 19999 -do- 506 Repair and maintenance of Residential 14 447731 435787 -do- 1042 Buildings 15 Repair and maintenance of Rural Roads 5196888 5011471 -do- 4176 km. Grant to OSRRA (PMGSY Road 16 414000 414000 -do- 2135 nos maintenance which 5 years of completion)

Ooutcome Budget : DoRD for 2014-15 Page 125

RURAL WATER SUPPLY AND SANITATION ORGANISATION

STATE PLAN (` in TRS)

Financial Expenditure up Sl Flow to Flow to Physical Achievement Name of the Scheme / Programme outlay Physical Target 2012-13 to January 2014 Remarks No SCSP TASP up to December, 2012 2012-13 (State Plan)

1 2 3 4 5 6 7 8 9 Coverage Activity- 800 Coverage Activity- 169 Water Quality - 250 Water Quality - 37 PWSSchemes PWSSchemes 1 Coverage Activity 2959900 692390 723910 1791882 Sustainability- 251 Sustainability- 104 PWSSchemes PWSSchemes Spot Sources- 32630 Nos Spot Sources- 19769 Nos Grand Total 2959900 692390 723910 1791882

CSP - NRDWP Completion of balance 100% funded by 3 Jalmani 6935 - - - - work under Jalamani GOI Procurement of 100% funded by 4 MIS and Computerisation 847 Computers and - - GOI peripherals 7782 0 0 -

NON PLAN Maintenance Ext W/S & 5 Office Building - M/R 51087 S/I of Govt Office 24292 Buildings in Rural Areas Repair and maintenance and POL for running of 6 M & E 122288 99505 Machinery & Equipment including Vehicles and Rigs

Ooutcome Budget : DoRD for 2014-15 Page 126

Maintenance and upkeep of existing 7 M/R of Rural Water Supply 513318 316281 Spot Sources, 331826 7693rural piped water supply schemes Payment of Decretal 8 Decretal Dues 525 - dues to staff Maintenance Ext W/S & S/I of Govt Office 9 Residential Building - M/R 90355 13299 Buildings in Rural Areas Salaries & Allowances 10 Direction & Administration 457448 359590 of Staff 11 Others 901 538 Total 1176523 829050

Ooutcome Budget : DoRD for 2014-15 Page 127

RURAL WATER SUPPLY AND SANITATION ORGANISATION

STATE PLAN (` in TRS)

Financial Expenditure up Sl Flow to Flow to Physical Achievement Name of the Scheme / Programme outlay Physical Target 2013-14 to March Remarks No SCSP TASP up to March 2014 2013-14 2014(State Plan)

1 2 3 4 5 6 7 8 9 Coverage Activity- 380 Coverage Activity- 380 & Water Quality - 107 & Water Quality - 107 PWSSchemes PWSSchemes Solar Powered PWS in Solar Powered PWS in 1 Coverage Activity 2959900 692390 723910 2505994 IAP District- 130 IAP District- 130 Sustainability PWS-84 Sustainability PWS-84 Deposit PWS-373 Deposit PWS-373 PWSSchemes Spot Sources- 30000 Nos Spot Sources- 30326 Nos Grand Total 2959900 692390 723910 2505994

CSP - NRDWP Completion of balance 100% funded by 3 Jalmani 6935 - - - - work under Jalamani GOI Procurement of 100% funded by 4 MIS and Computerisation 847 Computers and 291 - GOI peripherals 7782 0 0 291

NON PLAN Maintenance Ext W/S & 5 Office Building - M/R 51087 S/I of Govt Office 24292 Buildings in Rural Areas Repair and maintenance and POL for running of 6 M & E 122289 99505 Machinery & Equipment including Vehicles and Rigs

Ooutcome Budget : DoRD for 2014-15 Page 128

Maintenance and upkeep of existing 7 M/R of Rural Water Supply 513318 316281 Spot Sources, 331826 7693rural piped water supply schemes Payment of Decretal dues 8 Decretal Dues 525 - to staff Maintenance Ext W/S & S/I of Govt Office 9 Residential Building - M/R 30955 13299 Buildings in Rural Areas Salaries & Allowances of 10 Direction & Administration 457448 359599 Staff 11 Others 901 538 Total 1176523 829050

Ooutcome Budget : DoRD for 2014-15 Page 129

CHAPTER – V TABLE – C FINANCIAL REVIEW (CSP - NRDWP)

RURAL DEVELOPMENT DEPARTMENT (`in TRS)

RURAL WATER SUPPLY &SANITATION ORGANISATION 2012-13 BE RE BE SlNo Name of the Scheme (Actuals) 2013-14 2013-14 2014-15 1 2 3 4 5 6 1 MIS Computerisation – OE-OC 161 - 847 - 2 Jalamani 2562 - 6935 -

3 NRDWP (Outside Budget) 2477106 3150481 3150481 -

Grand Total 2479829 3150481 3158263 -

CHAPTER – V TABLE – D FINANCIAL REVIEW (STATE PLAN) RURAL DEVELOPMENT DEPARTMENT (`in TRS) RURAL WATER SUPPLY & SANITATION ORGANISATION 2012-13 BE RE BE SlNo Name of the Scheme (Actuals) 2013-14 2013-14 2014-15 1 2 3 4 5 1 4059-Office Building - 30000 30000 50000 2 4216 – Residential Building - 10000 10000 60000 3 2215 – ME – R/C - 10000 10000 - 4 2215 – Survey & Investigation - 50000 50000 70000 5 State Share of NRDWP 2040192 2400000 2959900 2200000 6 Central Share of NRDWP - - - 2207800 7 Rural Water Supply - - - 500000 8 RIDF – Rural PWS schemes - 100000 100000 100000 G Total 2040192 2600000 3159900 5187800

Ooutcome Budget : DoRD for 2014-15 Page 130

CHAPTER – V TABLE – E FINANCIAL REVIEW ( NON-PLAN) RURAL DEVELOPMENT DEPARTMENT (`in TRS) RURAL WATER SUPPLY & SANITATION ORGANISATION

RWS & S ORGANISATION

2012-13 BE RE BE Sl No Name of the Scheme (Actuals) 2013-14 2013-14 2014-15 1 2 3 6 2059 MR to Govt Office 1 42736 50692 51087 56587 Bldg 2 2215 – Dir & Admn 399494 440661 456718 505543 2215 – Machinery and 3 101981 122288 122289 131795 Equipment 2215 Maintenance and 4 391348 506958 513318 566546 Repair 5 Decretal Dues - 525 525 550 5 2215 - Suspense - 1 1 1 6 2215 Sanitary Tech Estt 387 730 730 863

7 2216 – MR to Res Bldg 24992 30955 30955 35510

2230-Labour & 8 830 800 900 1000 Employment - Stipend

Grand Total 961768 1153610 1176523 1298395

Ooutcome Budget : DoRD for 2014-15 Page 131

State Budget - State Plan (Outcome Budget 2014-15) (` In TRS) Sl Name of the Objective/ OUTLAY 2014-15 Quantifiable/Deli Projected Process/Timeliness Remarks/Risk Schemes/Pro Outcome verable Physical outcome Factors grammes Outputs 1 2 3 4(i) 4 (ii) 4(iii) 5 6 7 8 Non- Plan Complementary Plan Budget Extra-Budgetary Budget Resources 1 Nirmal Bharat Improve - 40,00,00 - 700000 numbers of To create an Participatory Abhiyan quality of life (State Individual open approach and in Rural Share of Household Latrines defecation completion by March Odisha CSP) free country 2022 as one of the through better side where Millennium Sanitation & Solid and Development Goals Water Supply Liquid implemented through Waste is 30 DWSMs under disposed of OSWSM an used for better livelihood

Ooutcome Budget : DoRD for 2014-15 Page 132

PEFORMANCE OF OUTCOME BUDGET 2013-14 (` In TRS) Sl Name of the Budget Physical target/works Actual expenditure for Physical achievement on each scheme/work under Programme Provision proposed to be each scheme/works Normal, TASP and SCSP 2012-13 executed in 2013-14 upto March 2014 IHHL School AWC toilets 1 Nirmal 25,00,00 IHL 900000 604,57 Total 33759 373 45 Bharat School 1471 TASP 7471 Abhiyan AWC 1840 SCSP 5570

PEFORMANCE OF OUTCOME BUDGET 2012-13 (` In TRS) Sl Name of the Budget Physical target/works Actual expenditure for Physical achievement on each scheme/work under Programme Provision proposed to be each scheme/works Normal, TASP and SCSP 2012-13 executed in 2012-13 IHHL School AWC toilets 1 Nirmal 25,00,00 IHL 1203061 17,21,48 Total 118318 1138 956 Bharat School 1479 TASP 26183 Abhiyan AWC 1183 SCSP 19522

Ooutcome Budget : DoRD for 2014-15 Page 133

CHAPTER-V Financial Review In this chapter actual of the Financial Year 2012-13, Budget Estimates and Revised Estimates for the year 2013-14 and shown Budget Estimates for the year 2014-15 are detailed in tabular form for better assessment of Financial Outlay and review of schemes implemented through R.D. Department.

(State Plan) RURAL WORKS ORGANISATION (` In TRS) Actual Proposal Sl. Head of B.E RE Name of the Scheme Expenditure for No Account 2013-14 2013-14 2012-13 2014 - 15 1 2 3 4 5 6 7 Construction of RD Deptt. Buildings(Non 1 4059-2148 104847 125000 125000 130000 Residential) Construction of RD Deptt. Buildings 2 4216-2148 101869 100000 100000 120000 (Residential) 3 5054-1230 Completion of Incomplete Roads & Bridges 274000 670000 490000 700000 4 5054-2161 RIDF (NABARD) 1846923 2100000 2100000 4100000 5 5054-0906 CWA 280669 284000 284000 284000 6 5054-1077 Tender Premium 550000 400000 747300 - Grant to OSRRA for completion of bridges on 7 5054-1077 350000 1 1 - PMGSY roads 8 5054-1077 Road works (PMGSY) - 18000001 9 5054-1077 PMGSY Labour Escalation - 25000 - 10 5054-2373 Survey Expenses 42016 40000 20000 - 11 5054-2373 Technical Training 2500 5000 1500 - 12 5054-2373 Land Acquisition Charges 544 7999 1899 5000 13 5054-2373 Survey Equipement 4152 3000 300 -

Ooutcome Budget : DoRD for 2014-15 Page 134

14 5054-2373 Decreetal Dues 1941 32000 32000 5000 15 5054-1230 Incentives to Contractor - 5000 - 5000 16 5054-1230 Impvt. To existing R.D Roads 628793 1200000 781700 570000 17 5054-1230 Construction of Bailey Bridges - - 275100 440000 18 5054-1230 Biju Setu Yojana 1357809 1500000 1750000 1630000 19 5054-2526 SCA for Special Programme for KBK dist. 155695 218100 475904 850000 20 5054-1230 One time ACA 277853 706700 744900 700000 Capacity Building (Resource & Infrastructure 21 5054-1230 - - 80000 Development) 22 5054-2161 Mukhya Mantri Sadak Yojana - - 1500000

23 5054-1230 Development of Rural Road Connectvity - - 10000 Total 5979611 7396800 7954604 29129001

Ooutcome Budget : DoRD for 2014-15 Page 135

TABLE-B Non-Plan

RURAL WORKS ORGANISATION (` In TRS) Actual Sl. Head of B.E RE Proposal for Name of the Scheme Expenditure No Account 2013-14 2013-14 2014-15 2012-13 1 2 3 4 5 6 7 1 2059 Salaries (Direction & Administration) 498105 582815 582816 788561

2 2059 M&E repair & carriage 15164 17433 17433 10000

3 2059 Work Charged/Wages Salaries (M&E) 36315 50962 50963 51683 4 2059 New Supply 0 1 1 500 5 3054 Maintenance Works 910130 1001888 1001888 1200000 6 3054 Maintenance of Critical Roads 228937 300000 300000 350000 Improvement / Widening & Completion of Roads, 7 3054 229425 300000 300000 350000 Bridges & nallahs 8 3054 Maintenance of Roads constructed under plan schemes 419799 483000 483000 560000

9 3054 Special Repair to Roads & Bridges 111348 150000 150000 180000

10 3054 Periodical Maintenance 114608 150000 150000 180000

11 3054 Maintenance of Roads & Bridges 1601007 1782000 1782000 1968021

12 3054 13th F.C Award (Road) 916394 1030000 1030000 1361444

Ooutcome Budget : DoRD for 2014-15 Page 136

13 3054 Grant to OSRRA 400000 414000 414000 0 14 3054 Grant-in-Aid-Genral(Non Salary) 480000 15 3054 Work Charged/Wages Salaries 142191 189272 189273 192397 16 2230 Labour & Employment 1597 1400 1600 1800

17 2059 Maintenance of Non Residential Building 1155220 1311047 1311047 1502704 18 2059 Maintenance of 30 years old school Building 150000 280000 280000 340000 19 2059 50 yrs School Building 101995 20000 20000 10000 Wages /Work Charged Salaries 20 2059 34304 49867 53803 60496 (Non Res Buildings) 21 2216 Maintenance of Residential Buildings 374062 447731 447731 515062

22 2216 Municipality Tax 23 150 150 150

Wages /Work Charged Salaries 23 2216 11855 17067 17067 18152 (Residential Buildings)

Total 7452479 8578633 8582772 10120970

Ooutcome Budget : DoRD for 2014-15 Page 137

CHAPTER-VI Gender and SC/ST Budgeting

As per the Plan ceiling furnished by the P&C Department, during the financial year 2014-15, the provision made under Transport Sector Schemes having General,TASP & SCP-SC components (rural roads and bridges) is `1078.40 crore out of which TASP provision is `248.03 crore and `183.33 crore for SCSP component for implementation of schemes in scheduled areas. Accordingly, the Department has formulated project list for construction of the roads and bridges in the scheduled areas to provide good all-weather roads. (` in TRS) Sector Major Resource Head Proposed Outlay/Plan Ceiling of Annual Plan 2014-15 Head/Minor District State Total TASP SCSP Head of Sector Sector out of out of Development Total Total Transport 1.Rural RIDF 4100000 - 4100000 943000 697000 Roads & Bridges (5054- 2161-37107) Social 2. Water Supply SS of CSP 4407800 4407800 1013794 749326 Service & Sanitation RIDF 100000 100000 a) Rural Water Others 680000 680000 156400 115600 Supply (b) Rural SS of CSP 250000 250000 55330 41330 Sanitation Transort (5054-0906- Others (CWA) 284000 - 284000 65320 48280 37107) Non-Res 4059-2148- Others 130000 - 130000 29900 22100 Building 37114 Res. Building 4216-2148- Others 120000 - 120000 27600 20400 37114 Transport 5054-1230- Completion of 700000 700000 161000 119000 37158 incomplete Roads & bridges under RIDF Transport 5054-1230- Improvement of 570000 570000 131100 96900 37247 existing RD roads Transport 5054-1230- Biju Setu Yojana 1630000 1630000 374900 277100 37257 Transport 5054-2006- One time ACA 700000 700000 161000 119000 37107 Transport 5054-2526- SCA for KBK 850000 850000 195500 144500 37107 Transport 5054-2161- Others (Mukhya 1500000 1500000 345000 255000 37286 Mantri Sadak Yojana) Transport 5054-1230- Others (Bailey 440000 440000 101200 74800 37281 Bridges) Transport 5054-1230- Others 10000 10000 2300 1700 37287 (Development of rural road connectivity)

Ooutcome Budget : DoRD for 2014-15 Page 138

Hon'ble CM inaguarat es a bridge

WAMIS

Ooutcome Budget : DoRD for 2014-15 Page 139