EIS 1791
Environmental impact statement: proposed Wallerawang
Qu:ry pi PRiMARY 1S1RIES
/J66863 ~- C) (/0 sil, I
SITE G 04 L P 'fV Li14U TEl)
I I
I I I PROPOSED WALLERAWANG QUARRY
Pacri'llt ENVIRONMENTAL Report 01/206.1 November 2001 Sitegoal Pty Ltd
ENVIRONMENTAL IMPACT STATEMENT
PROPOSED WALLERAWANG QUARRY
Prepared for: Prepared by:
Sitegoal Pty Ltd Pacrim Environmental Pty Ltd 191 Main Street 2/120 Darby Street LITHGOW NSW 2790 NEWCASTLE NSW 2300
Telephone: (02) 6352 3377 Telephone: (02) 4926 5166 Facsimile: (02) 6352 3661 Facsimile: (02) 4926 5125 Email: [email protected]
Report 01/206.1 November 2001 vJ I
Submission of I environmental impact statement (EIS) prepared under the Environmental Planning and I Assessment Act 1994
I EIS prepared by name K. Wayne Perry
I qualifications BSc BArch F.AusIMM, M.EIA, CPEnv
address Unit 2, 120 Darby Street I NEWCASTLE NSW 2300
in respect of I development application Proposed Wallerawang Quarry I applicant name Sitegoal Pty Limited applicant address 191 Main Street Lithgow NSW 2790
I land to be developed Off Great Western Highway, Wallerawang
lot n°. DP/MPS. vol/fol etc Lot 6, DP 872230 and Part SF 707 I proposed development
environmental impact I statement an environmental impact statement (EIS) is attached.
certificate 1 I certify that I have prepared the contents of this Statement and to the best of my knowledge it is in accordance with Clauses 72 and 73 of the Environmental I Planning and Assessment Regulation 2000; it contains all available information that is relevant to the environmental assessment of the development to which the I statement relates; and it is true in all material particulars and does not, by its I presentation or omission of information, materially mislead. signature I name K. Wayne Perry date /3 I't12001 I I TABLE OF CONTENTS I Page N°
GLOSSARY OF TERMS & ABBREVIATIONS ...... vii I EXECUTIVE SUMMARY ...... ix i.INTRODUCTION...... 1
I 1.1 Background ...... 1 1 1.2 Location and Land Details...... 1 1.3 Company Profile ...... 2 I 1.4 Approvals Required...... 2 1.5 Project Objective and Basis of Impact Assessment ...... 3 1 1.6 Key Environmental Issues ...... 3
2. REGIONAL CONTEXT ...... 5
2.1 Regional Geology ...... 5 1 2.2 FutureDemand ...... 5 2.3 Markets ...... 5 1 2.4 Adjacent Resources ...... 6 3. PROPOSED DEVELOPMENT ...... 7 I 3.1 Reserves and Rationale for Development ...... 7 3.2 Quany Planning ...... 7
1 3.3 Mining Equipment ...... 10 1 3.4 Drill and Blast Design...... 11 3.5 Crushing and Stockpiling...... 12 3.5.1 Crushing ...... 12 I 3.5.2 Stockpiling ...... 13
3.6 Site Development ...... 14
1 3.7 Hours of Operation, Duration and Workforce ...... 14 1 3.8 Transport ...... 14 3.9 Energy Usage ...... 15 1 3.10 Community and Statutoiy Consultation ...... 15
Environmental Impact Statement - Wallerawang Quartzite Quarry Pacrirn Environmental
I II
3.11 Cleaner Production .17
4. ENVIRONMENTAL MANAGEMENT ...... 18
4.1 Water Management and Erosion Control ...... 18 4.1.1 Objectives...... 18 4.1.2 Water Usage ...... 18 4.1.3 Existing Water Resources ...... 19 4.1.4 Water Management Strategy...... 19
4.2 Air Quality Management ...... 21
4.3 Noise, Blast and Vibration Management ...... 21 4.3.1 Objectives...... 21 4.3.2 Noise Management Program...... 22
4.4 Hydrocarbons, Chemicals and Waste Management ...... 22
4.5 Site Rehabilitation ...... 24 4.5.1 Objectives ...... 24 4.5.2 Vegetation Management ...... 24 4.5.3 Topsoil Management ...... 24 4.5.4 Materials Available for Rehabilitation and Posi Extractive Land Use...... 24 4.5.5 Surface Shaping and Revegetation...... 25
4.6 Bush Fire Management ...... 26
4.7 Transport ...... 27
5 EXISTING ENVIRONMENT AND IMPACT ASSESSMENT...... 28
5.1 Physiography ...... 28 5.1.1 Existing Environment ...... 28 5.1.2 Impact Assessment ...... 28
5.2 Soils ...... 29 5.2.1 Existing Environment ...... 29 5.2.2 Impact Assessment...... 30
5.3 Land Capability ...... 30 5.3.1 Existing Environment ...... 30 5.3.2 Impact Assessment ...... 31
5.4 Archaeology ...... 31 5.4.1 Existing Environment ...... 31 5.4.2 Impact Assessment ...... 32
5.5 Flora and Fauna ...... 32 5.5.1 Existing Flora ...... 32 5.5.2 Existing Fauna ...... 33 5.5.3 Impact Assessment ...... 34
Environmental Impact Statement - W1erawang Quzite Quy Pacrim Enviroental I
5.6 Hydrology and Water Quality ...... 34 5.6.1 Existing Environment ...... 35 I 5.6.2 Impact Assessment ...... 35 5.7 Climate and Air Quality ...... 37 I 5.7.1 Existing Climate ...... 37 5.7.2 Existing Dust Levels ...... 38 5.7.3 Quartzite Dust and Human Health...... 39 1 5.7.4 Impact Assessment...... 39 5.8 Operational and Traffic Noise ...... 41 1 5.8.1 Noise Terminology ...... 42 5.8.2 Existing Environment...... 42 5.8.3 Operational and Road Traffic Noise Goals ...... 42 1 5.8.4 Impact Assessment...... 44 5.9 Vibration and Blasting...... 46 I 5.9.1 Vibration and Blast Terminology...... 46 5.9.2 Existing Environment...... 47 5.9.3 Vibration and Blasting Assessment Goals...... 47 I 5.9.4 Impact Assessment ...... 47 5.10 Visual Environment ...... 48 1 5.10.1 Existing Environment ...... 48 5.10.2 Impact Assessment ...... 49 I 5.11 Recreation ...... 50 5.11.1 Existing Environment ...... 50 I 5.11.2 Impact Assessment ...... 51 5.12 Land Use, Tenure and Services ...... 51 5.12.1 Existing Environment ...... 51 1 5.12.2 Impact Assessment ...... 52 5.13 Planning and Zoning ...... 53 I 5.13.1 Existing Environment ...... 53 5.13.2 Impact Assessment ...... 54 I 5.14 Transport ...... 55 5.14.1 Existing Environment ...... 55 1 5.14.2 Impact Assessment ...... 56 5.15 Socio-Economics ...... 58 5.15.1 Existing Environment ...... 58 I 5.15.2 Impact Assessment ...... 58 5.16 Hazard Analysis ...... 58 I 5.17 Ecologically Sustainable Development ...... 60 1 5.18 Cumulative Impacts ...... 61
Environmental Impact Statement - Wallerawang Quartzite Quarry Pacrim Environmental I
lv
6 PROJECT JUSTIFICATION AND ALTERNATIVES .63 6.1 Project Justification ...... 63
6.2 Consideration of Alternatives ...... 64 6.2.1 Not Proceeding...... 64 6.2.2 Alternative Quarry Areas...... 64 6.2.3 Alternative Quarrying Methods...... 64 6.2.4 Alternative Access Modes and Routes ...... 64 6.2.5 Alternative Waste and Water Management Practices...... 65 6.2.6 Final Landform Options...... 65 6.2.7 Alternative Product Transport Option...... 65 REFERENCES ...... 67
APPENDICES Appendix 1 Correspondence with Government Authorities and Results from Community Consultation Appendix 2 Transportation Study Appendix 3 Water Management Appendix 4 Statement of Effect on Threatened Flora and Fauna Appendix 5 Site Stability Analysis Appendix 6 Soil Survey Appendix 7 Archaeological Assessment Appendix 8 Air Quality Assessment Appendix 9 Acoustical Assessment Appendix 10 Study Team
After Page N° FIGURES
Figure1.1 Location...... 2 Figure 1.2 Site Context Plan...... 2
Figure 2.1 Resource Evaluation...... 6
Figure 3.1 Borehole Logs Holes 001 and 002 ...... 8 Figure 3.2 Borehole Logs Holes 004 and 005 ...... 8 Figure 3.3 Geological Cross Section...... 8 Figure 3.4 Quarry Development - Stage 1 Trench...... 10 Figure 3.5 Quarry Development - Stage 1 Floor...... 10 Figure 3.6 Quarry Development - Stage 2 Trench...... 10 Figure 3.7 Quarry Development - Stage 2 Floor...... 10 Figure 3.8 Quarry Development - Stage 3 Floor...... 10 Figure 3.9 Cross Sections...... 10 Figure 3.10 Surface Facilities ...... 12
Environmental Impact Statement - Wallerawang Quartzite Quarry Pacrirn Environmental OA I
Figure 4.1 Proposed Irrigation Network .20
I Figure 4.2 Site Drainage Layout -Stage 1...... 20
Figure 4.3 Site Drainage Layout -Stage 2 and 3...... 20 Figure 4.4 Rehabilitation Plan...... 26 I Figure 4.5 Final Landform...... 26 ill ! F I Figure 5.1 Soil Classification and Topsoil Stripping Plan...... 30 Figure 5.2 Land Capability and Slope Class Plan...... 30 Figure 5.3 Wind Roses Mt Piper Power Station...... 38
Figure 5.4 Scenario 1 -Predicted Maximum 24 hour Average Ground Level PM10 Concentrations (ug/m3) ...... 40 Figure 5.5 Scenario 1 Predicted Maximum 24 hour Average Ground Level FA PM10 Concentrations (ug/m3) ...... 40 Figure 5.6 Scenario 1 Predicted Annual Average Ground Level TSP I Concentrations (uglm3) ...... 40 Figure 5.7 Scenario 1 -Predicted Annual Average Deposition Rates (g/m2/month)4o
Figure 5.8 Scenario 3 -Predicted Maximum 24 hour Average Ground Level PM10 I Concentrations (ug/m3) ...... 40
Figure 5.9 Scenario 3 -Predicted Annual Average Ground Level PM10 Concentrations (ug/m3) ...... 40
1 Figure 5.10 Scenario 3 -Predicted Annual Average Ground Level TSP Concentrations (ug/m3) ...... 40
Figure 5.11 Scenario 3 -Predicted Annual Average Deposition Rates (g/m2/month)40 I Figure 5.12 Scenario 3 Predicted Annual Average Ground Level PM7 Silica Concentrations (ug/m3) ...... 42 n Figure 5.13 Predicted Noise Levels for Initial Trench, Stage 1 (Years 1-2)...... 46 Figure 5.14 Predicted Noise Levels at Completion of Stage 1 (Years 1-2)...... 46 Figure 5.15 Predicted Noise Levels for Initial Trench, Stage 2 (Years 3-4 )...... 46 Figure 5.16 Predicted Noise Levels at Completion of Stage 2 (Years 4-15)...... 46 Figure 5.17 Land Use and Zoning...... 48 Figure 5.18 Adjacent Land Subdivisions and Residences ...... 52 I Figure 5.19 Estimated Hourly Truck Movements Associated with the Proposed I Quarry Development (500,000tpa)...... 57 PLATES
Plate 1 Aerial Photograph (1998) and Monitoring Locations...... 2 Plate 2 Existing View from the Rocky Waterhole...... 50 Li Plate 3 View to Quarry from the Rocky Waterhole...... 50 Plate 4 Existing View from the Coxs River Bridge...... 50 ~1 Plate 5 View to Quarry from the Coxs River Bridge...... 50 Plate 6 Existing View from the Wallerawang Primary School...... 50 Plate 7 View to Quarry from the Wallerawang Primary School...... 50 F1 Plate 8 Existing View from the Great Western Highway...... 50
Environmental Impact Statement - Wallerawang Quartzite Quarry Pacrim Environmental vi
Plate 9 View to Quarry from the Great Western Highway...... 50 Plate 10 View to Rehabilitated Quarry from the Great Western Highway...... 50
TABLES
Table 1.1 Key Environmental Issues...... 4 Table 3.1 Quarry Planning Constraints and Management Safeguards...... 8 Table 3.2 Proposed Equipment ...... 11 Table 4.1 Preliminary Rehabilitation Schedule...... 26 Table 5.1 Distribution of Slope Classes ...... 28 Table 5.2 Soil Volumes ...... 30 Table 5.3 Summary of Upstream Water Quality...... 35 Table 5.4 Source of Meteorological Data...... 37 Table 5.5 Climatic Summary...... 38 Table 5.6 Summary of Dust Deposition Data Collected at Wallerawang...... 38 Table 5.7 Air Quality Standards/Goals for Particulate Matter Concentrations ...... 40 Table 5.8 Ambient Noise Measurements at Three Monitoring Locations...... 42 Table 5.9 Daytime Operational Noise Goals (dB(A))...... 44 Table 5.10 Assessment Goals for Blasting ...... 47 Table 5.11 Reference Points for Visual Impact Assessment...... 49 Table 5.12 Nearest Residents ...... 52 Table 5.13 Existing Traffic Volumes...... 55 Table 5.14 Predicted Truck Traffic Volumes...... 57 Table 5.15 Hazard Analysis for Proposed Quarry Activities...... 59
Environmental Impact Statement - Wallerawang Quartzite Quarry Pacrim Environmental VII I GLOSSARY OF TERMS AND ABBREVIATIONS
I o Degrees Degrees Celsius I % Percent .Ls/cm Microsiemens per centimetre. A measure of conductivity Micron (1x106 metres) I pg Microgram igIm3 Microgram per cubic metre I AADT Annualised Average Daily Traffic ABS Australian Bureau of Statistics Li AF[1) Australian Height Datum ANFO Ammonium Nitrate Fuel Oil explosive I ANZECC Australian and New Zealand Environment Conservation Council AS Australian Standards AWTS Aerated Wastewater Treatment System I BOM Bureau of Meteorology cm Centimetres 1 CO2 Carbon Dioxide c13 Decibels - a measure of noise I dB(A) Decibels (A weighted scale) dB(Lin) Noise as pressure fluctuations in air measured in decibels I DLWC Department of Land and Water Conservation (NSW) DMR Department of Mineral Resources (NSW) DUAP Department of Urban Affairs and Planning (NSW) I EC Electrical Conductivity (salinity) ElS Environmental Impact Statement I EL Exploration Licence ENM Environmental Noise Computer Model I EPA Environment Protection Authority (NSW) EP&A Act Environmental Planning and Assessment Act, 1994 I ESD Ecologically Sustainable Development g/m2/month Grams per square metre per month ha Hectares I hr Hour km Kilometres I kmlh Kilometres per hour kV kilovolt I L Litre LAeq Average noise energy during monitoring period
[1 Environmental Impact Statement - Wallerawang Quartzite Quarry Pacrim Environmental vili I LAOO Average noise energy 90% monitoring period I L10 Noise level exceeded 10% of the monitoring period
L90 Noise level exceeded 90% of the monitoring period lid Litres per day litres/m2lhr litres per square metre per hour M Million ML Million litres (megalitre) mg/L milligrams per litre I m metres mIs metres per second I m2 Square metres m3 Cubic metres mm millimetres mmls millimetres per second MSDS Material Safety Data Sheet I Mt Million tonnes (megatonne) Mtpa Million tonnes per annum (year) I N North NFR Non Filterable Residue NHMRC National Health and Medical Research Council NPWS National Parks and Wildlife Service (NSW) PFM Planning Focus Meeting pH Units of acidity/alkalinity PM7 Particulate matter less than 7 microns diameter I PM10 Particulate matter less than 10 microns diameter POEO Act Protection of the Environment Operations Act 1997 1 PPV Peak Particle Velocity Pty Ltd Proprietary Limited REP Regional Environmental Plan RTA Roads and Traffic Authority (NSW) S South SCA Sydney Catchment Authority (NSW) SCS Soil Conservation Service (NSW) I SE South East SEPP State Environmental Planning Policy I SiO2 Silica SOE Statement of Effects t tonne tpa Tonnes per annum (year) TSP Total Suspended Particulates WBM Consultants, WBM Oceanics Australia Environmental Impact Statement - Wallerawang Quartzite Quany Pacrim Environmental I lx I EXECUTIVE SUMMARY I I BACKGROUND It is proposed to develop a hardrock quarry at a location approximately 2.5km southeast of I Wallerawang. The quarry site is located south of the Great Western Highway and to the west of the Coxs River. The quarry will be developed by Sitegoal Pty. Ltd., a Lithgow-based I Company, who have held an exploration licence (EL4473) over the site since 1993.
[I] THE PROJECT
F1 The quarry will comprise a total disturbed area of approximately 1 lha and produce quartzite and rock aggregate material for use in the Wallerawang, Lithgow, Blue Mountains and I Sydney regions. The quarry will produce approximately 3.5Mt of product material over the I initial approval period of 20 years, with an estimated value of $77M. The quarry site will be developed in three stages and quarry material will be won using a I combination of drilling, blasting and rock breaking operations. Quarry product will be crushed and stockpiled on-site using either a mobile crushing plant or a fixed crushing plant, I dependent upon contractor and product requirements. Overburden material will be stockpiled I on-site for either sale or use in the rehabilitation of the quarry. I It is envisaged that production will vary between 125,000tpa and 500,000tpa depending on market demand. The proposed Wallerawang Industrial Park adjacent to the existing power I station, would provide an estimated product requirement of 500,000tpa for at least two years. At this maximum production rate, an estimated 80 loads or 160 heavy vehicle movements will I be generated by the project each day. At the lower production rate, vehicle movements are expected to be approximately 40 per day or 20 loads per day. Safe access and egress to the I site will be facilitated by the construction of a new intersection approximately SOOm west of Barton Ave. I The quarry will generally operate between the hours of 7.00am and 500pm Monday to Friday I unless market demand necessitates additional production on a Saturday. To satisfy Sydney I Environmental Impact Statement - Wallerawang Quartzite Quarry Pacrim Environmental pi market requirements, there will be a need to dispatch trucks in the early hours of the morning. Saturday operations will include plant maintenance and loading of quarry product. It is anticipated that two to four permanent staff will be employed on site, supplemented by contract truck, dozer and excavator drivers.
PREPARATION OF THE EIS
This document has been prepared in accordance with the requirements of the Environmental Planning and Assessment Act and Regulation. It takes into account comments from the public consultation process and the requirements of relevant statutory authorities.
Approval is sought for a production level of up to 500,000tpa. The proposal is deemed to be a State Significant Development, exceeding the 200,000tpa extraction rate listed in the Schedule to the EP&A Act Declaration, dated 3 August 1999.
A Planning Focus Meeting was held with relevant authorities and consultation with the community has been on-going via information brochures, face to face contact and an on site community briefing. Issues raised by the community and Statutory Authorities have been addressed in the EIS.
ENVIRONMENTAL ASSESSMENT
Archaeology. Site investigations located an aboriginal archaeological site within the area proposed for topsoil storage. Modification of the project layout resulted in the relocation of this proposed stockpile site. Protection of the site will occur through fencing the area to exclude access and by notifying employees of the significance of the site through an induction program. A management plan will be prepared.
Flora and Fauna. The quarry site is predominantly sub-alpine Eucalypt woodland. Canopy cover is generally continuous across the site, while understorey development is limited. No species of threatened flora were identified or are known to occur on or near the quarry site.
Environmental Impact Statement - Wallerawang Quartzite Quarry Pacrim Environmental xl I One species of threatened fauna (Yellow-bellied Sheathtail-bat) was identified as occurring I on the site. Two other threatened species (Koala and Bathurst Copper butterfly) are recorded in the NPWS database as occurring within a 10km radius of the site. Consideration of the site I under SEPP 44 (Core Koala habitat) determined that although sufficient koala feed tree species existed on the site, there was no evidence of koala habitation in the area proposed for I quarry development. I It was concluded that due to the abundance of similar habitat both locally and regionally, the quarry development will not affect local populations of threatened species that potentially use I the site. Upon completion of quarry activities, the site will be returned to a floristic structure commensurate with the surrounding area. I Surface and Ground Water. I The natural hydrology of the site will be altered during quarry development. Water from undisturbed areas will be diverted around the site and discharged to the Coxs River. Water I from disturbed areas will be captured, transported and stored in a series of water management structures constructed on the site. A 7.7ML water management dam will provide the major I storage facility on the site. Water re-use and efficiency will be maximised by using water stored in the water management dam for the majority of on-site water requirements, I predominantly for dust suppression purposes. An irrigation component is included in the water management design to ensure adequate storage is available on site for the majority of I storm events.
I The quarry development will operate as a zero discharge site under the majority of climatic conditions. During extreme rainfall events it may be necessary to discharge water from I disturbed areas of the site. On these occasions, dilution with runoff from the surrounding I catchment areas will minimise surface water impacts. Due to the fractured nature of the rock and the inability to intersect the groundwater table I during drilling operations at the site, groundwater impacts are considered unlikely to occur as I a result of the project. I I Enviromriental Impact Statement - Wallerawang Quartzite Quarry Pacrim Environmental xii
Air Quality. Modelling of likely dust emissions resulting from the quarry was undertaken for a range of production levels. Results indicate that nuisance and health related dust impacts would be negligible at all production levels and under all wind conditions.
Operational safeguards will include watering of haul roads and machinery manoeuvring areas, keeping stockpiles in a dampened state, a wheel wash facility, sealing of the access road from the wheel wash to the Great Western Highway and the covering of all loads.
In the event that excessive dust generation occurs during adverse wind conditions, activities will be modified or ceased during the period. However, the retention of extensive tree cover around the entire site should minimise this occurrence by sheltering the site from unfavourable winds.
Noise. Modelling of predicted noise levels for potential receptors in the vicinity of the quarry site indicates that under calm atmospheric conditions, all noise assessment goals will be complied with. During adverse conditions (winds and a temperature inversion) noise assessment goals may be exceeded at some receptor locations.
Operational safeguards have been incorporated to reduce the risk of noise impacts upon the receiving environment. These include restricting or ceasing quarry activity during adverse weather conditions, retaining a 6-8m highwall at the northern end of the quarry to act as a noise buffer and retaining extensive tree cover around the entire quarry site.
Periodic noise monitoring will be undertaken throughout the life of the project to ensure that noise criteria are being complied with. Wind speed and weather conditions will be monitored at a permanent exposed location to allow operational modifications to be considered.
Blasting and Vibration. Modelling indicates that the prescribed allowable level of blast noise will not be exceeded at any time during quarry operations. Due to the potential for flyrock, it may be necessary to close the Great Western Highway for short periods during blasting operations. Blasting is
Environmental Impact Statement - Wallerawang Quartzite Quarry Pacrim Environmental I expected to occur once every two weeks at the maximum production level reducing to once I every two months at the lower production levels. I The quarry site is located adjacent to an existing electricity supply pylon, and therefore blasting will be designed to ensure that vibration levels do not exceed 25millimetres per I second, as required by Transgrid. Vibration monitoring will be undertaken at the base of the pylon. 1 Two operational measures have been included to reduce blast vibration and over-pressure [1 impacts. A small diameter (89mm) drill hole will be used in conjunction with the 'Nonelt initiation system. This system allows for individual in-hole delays and prevents the effects of I a single large blast.
I Visual. Quarry operations will not be visible from the majority of public viewing locations identified. I View modification at these sites will occur as subtle changes to the current ridgeline profile. Trees occurring in the foreground are likely to obscure the majority of views to quarry I activities.
I Views of the eastern quarry highwall are likely from the elevated western approaches of the Great Western Highway. However, views from this location will predominantly occur from I eastbound road traffic, travelling at the nominal speed of 110km/h. Rehabilitation east of the Stage 2 trench will commence in Year 3 of the quarry program and will soften this outlook I considerably.
I Site Rehabilitation. Stabilisation works will commence concurrently with development of the quarry. Quarry I benches will be revegetated as soon as practicable using a range of endemic trees and shrubs. Upon completion of quarry activities, the void space, access road and surface facilities areas I will be ripped, and seeded/planted with a range of endemic tree, plant and grass species.
I The final void will comprise a gently sloping floor (4%) surrounded by steeper side slopes I (approximately 50 degrees), not inconsistent with existing slopes in the area.