Appendix A – Footway and Carriageway Improvement Schemes
The delivery of these schemes is weather dependent; should it prove not possible to carry out these works on the planned dates, new dates will be arranged and the residents will be informed by a letter drop to their homes.
Machine Resurfacing – Contact Officer Mr Byron Lovell
Road Name Parish Extent of Works Current Status
From the junction with Royal Tunbridge nd Camden Road Calverley Road to the Programmed 2 Wells junction with Albion Road. October 2017
Royal Tunbridge th A26 London Road Junction with Church Road Programmed 24 Wells October 2017
Footway Improvement - Contact Officer Mr Neil Tree
Road Name Parish Extent of Works Current Status
From Outside number 32 Programmed for Sychem Place Capel for the remaining length. November 2017. (Footway Protection). From the junction with Maidstone Road to the Badsell Road Paddock Wood layby adjacent to Completed. The Goldings. (Footway Protection). Entire length Programmed for Allan Close Rusthall (Footway Protection) November 2017.
Surface Treatments – Contact Officer Mr Jonathan Dean
Micro Surfacing
Road Name Parish Extent of Works Current Status
A262 Cranbrook / Hammerhill Farm to Neave Completed Biddenden Road Frittenden
Babbs Lane to South Cranbrook Road Benenden Completed Lodge Constitutional Hill Road to the junction with A26 Southborough Pennington Road. (St Completed London Road Andrews Park to Harland Way) A26 Vale Road to the junction Tunbridge Wells Completed London Road with Mount Ephraim. A26 Harland Way to Bidborough Southborough Completed London Road Ridge (linked to Ops P1) Top of "S" bends. Extend micro either side of bends B2160 Matfield and micro top bend. Extend Completed Gedges Hill to join with Chantlers Hill (Extra 350Lm) Barn Store to previous B2086 micro joint (outside Cranbrook Completed Benenden Road Swattenden Cottages) near Tilsden Lane B2079 Peasley Lane to Goudhurst Goudhurst Completed Bedgebury Road crossroads
B2086 Tilsden Lane through dip Cranbrook Completed Cranbrook Road up to Binan Cottage
Hollybank to Brenchley Crook Road Brenchley Completed Road
B2160 Coppers Lane to Chestnut Matfield Completed Maidstone Road Lane
Hartleys Farm Shop to Swattenden Lane Cranbrook Completed A229
B2084 End of SD "UPPER LAWN" Goudhurst Completed Chequers Road to B2079 North Road
A264 Ashurst "s" bends From Stone Ness Completed Ashurst Road Stone Ness to Stone Cross
Programmed for 18th Coach Road Rusthall Whole Road October 2017 for 2 days From junction with Rusthall Programmed for 19th Lower Green Road Rusthall Road to Junction with October 2017 for 2 Cranwell Road days
Surface Dressing
Road Name Parish Extent of Works Current Status
Slip Mill Road Hawkhurst A268 to Lightfoot Green Completed