AIR QUALITY AND GREENHOUSE GAS ANALYSIS FOR THE MARIPOSA BIOMASS PROJECT

Prepared for: Mariposa County Resource Conservation District

Prepared by: TSS Consultants Sacramento, California

November 23, 2017

MARIPOSA BIOMASS PROJECT AIR QUALITY and GREENHOUSE GAS EMISSIONS

Introduction

The potential air emissions of the proposed 2.4-MW net (2.7 MW gross) woody biomass to electricity facility are presented and discussed below for the purposes of supplying the Mariposa County Planning Department and the Mariposa County Air Pollution Control District with background information and data for their respective CEQA review of the Mariposa Biomass Project.

TSS Consultants (TSS) of Sacramento, CA was retained by the Mariposa County Resource Conservation District to prepare the following analyses.

Air Quality

Projected Emissions – Stationary Sources

The proposed bioenergy facility will utilize approximately 12,000 bone dry tons (BDT) of woody biomass waste per year. Total electrical production will be 2.7 MW gross, with 2.4 MW net transmitted to the grid. As the proposed project will sell electrical power to Pacific Gas & Electric under the California Bioenergy Market Adjustment Tariff (BioMAT) Category 3, 80% of the woody biomass waste will originate from forest sources, much of which would have been otherwise piled and burned.

The facility is planned to operate 24/7, however given there will be scheduled and unscheduled maintenance requirements for the equipment it is anticipated that the bioenergy facility will likely only operate approximately 330 days per year.

The proposed facility will utilize the Cortus Energy WoodRoll woody biomass gasification to electricity technology (see Figure 1 below) The facility includes a fuel drier, which removes moisture from the fuel before it enters the pyrolizer. Char produced by the pyrolizer is indirectly heated using the gases generated in the pyrolysis process and mixed with steam to produce a low nitrogen . The syngas is to be combusted in two GE Jenbacher, type 6 generators to produce electricity (see Appendix A for engine specifications). The engines are equipped with SCRs for NOx control and CO catalysts for increased CO emission reduction. Particulate Matter will be controlled by filters (syngas filter and pyrolysis gas exhaust filter). The exhaust gas from the two engines as well as the exhaust from the fuel drier is ducted to one common stack. The facility also includes a flare to burn excess fuel during startup, shutdown and emergency upset conditions.

TSS Consultants 1 November 2017

Figure 1 – Cortus Energy WoodRoll Facility General Schematic

TSS Consultants 2 November 2017

A summary table of stationary emissions is presented below in Table 1. Total emissions are presented in tons per year (TPY) based on 8,760 annual hours. Table 1. Stationary Source Emission Estimates Major MC Total Source APCD for and IC Engine* WoodRoll** Flare*** CEQA 2.4 ERC Thres- MW Thres- hold hold Emission Total Emission Total Emission Total

Factor Emissions Factor Emissions Factor Emissions

(lb/hr) TPY (lb/hr) TPY (lb/hr) TPY TPY TPY TPY VOC 1.12 4.90 0.05 0.20 0.003 0.002 5.80 100 100 NOx 1.67 7.30 0.71 3.10 0.133 0.100 11.93 100 100 CO 5.55 24.30 0.07 0.30 0.027 0.020 27.96 100 100 PM10 0.23 1.00 0.07 0.30 0.000 0.000 1.48 100 100 PM2.5 0.23 1.00 0.07 0.30 0.000 0.000 1.48 100 100 SOx 0.43 1.90 0.48 2.10 0.000 0.000 4.55 100 100

*- IC Engine emission factors from Manufacturer's (GE Jenbacher specifications w/SCR control device and catalytic converter ** - WoodRoll emissions factors based on measurements conducted by Cortus Energy

*** - Emergency/standby flare emissions factors from Cortus Energy based on ordinary LPG/Propane burner

The thresholds of significance presented in the table above are taken Table 4 below.

CalEEMod Modeling for Project Emissions

Emissions modeling for this project was performed using California Emission Estimator Model (CalEEMod) Version 2016.3.1. Project specific data was applied when available and remaining data was populated with Mariposa County APCD default data. Construction is not expected to occur during every day during the construction schedule, therefore, two model runs were performed, one with the actual as expected construction schedule for the worst-case daily emissions and one model containing a condensed single year construction schedule to represent the worst-case annual emissions. A condensed construction schedule was used to more accurately calculate annual emissions by basing the construction schedule on the number of working days. For example, if a construction phase was expected to range three months and only have 20 days of construction activity, it would be modeled in the condensed schedule version as a single month to account for a total of 20 working days instead of the CalEEMod auto calculated 60 days.

TSS Consultants 3 November 2017

Project Emissions - Construction

The construction of the bioenergy facility will include the erection of an enclosed warehouse-type building, road construction, and site grading. There is expected to be no demolition of buildings or related structures as none currently exist onsite.

Project construction is assumed by the developer to take 9 months with approximately 2.4 acres of disturbed ground area. Grading/site preparation will utilize 1 each heavy wheel loader, hydraulic excavator, grader, material handling crane, and dump truck. Table 2 presents the maximum daily and annual construction emissions.

Table 2. Construction Emissions Estimates

Maximum Controlled Maximum Pollutant Daily Emissions Controlled Annual (lb/day) Emissions (tons) VOC 15.79 0.61 NOx 45.34 1.22 CO 99.01 2.38 SOx 0.16 0.004

PM10 10.77 0.27

PM2.5 4.21 0.11 1 CO2e 15,900 360.54 1 Annual CO2e is in metric tons per year. These results of the CalEEMod modeling are found in Appendix B. Daily emissions from Section 2.1 of Daily Emissions Modeling Spreadsheet and Annual emissions from Section 2.1 of Annual Emissions Modeling Spreadsheet.

Project Emissions – Mobile and Temporary Sources

Mobile emission sources for the proposed bioenergy facility operation include truck activity (for chip delivery), loader activity (to move onsite biomass), employee commute trips, biomass hauling, and ash hauling. The front loader will operate onsite moving biomass from the storage windrows to the dryer’s feedstock hopper and stacking the storage windrows during and after feedstock delivery. Truck activity will follow the all- weather access roads onsite to reach the storage windrows. The scale is onsite and immediately adjacent to the bioenergy facility.

The following CalEEMod inputs were used to estimate the operational mobile source emissions. • 10 full-time employees with 10 round trips for a per day commute at an average 60 miles round trip; • 12 additional jobs for recovering biomass with 12 round trips per day at an average 60 miles round trip

TSS Consultants 4 November 2017

• Woody biomass fuel vehicles (i.e. chip vans) with a haul capacity of 12.5 BDT per load with 960 loads annually for 12,000 BDT of delivered biomass. Assume average 60 mile round-trip for feedstock acquisition: • Ash removal, 650 tons per year (one 12.5 ton truckload per week), assume 2 mile round trip to nearby Mariposa County Landfill and Recycling Center.

The result of the operational mobile and temporary source emissions are presented in Table 3.

Table 3. Operational Mobile and Temporary Source Emission Estimates Pollutant Maximum Controlled Maximum Controlled Daily Emissions Annual Emissions (lb/day) (tons) VOC 3.03 0.48 NOx 19.30 3.00 CO 43.11 6.89 SOx 0.07 0.01 PM10 5.77 0.91 PM2.5 2.05 0.32 * CO2e 7,112 1054.57 * Annual CO2e is in metric tons per year.

These results of the CalEEMod modeling are found in Appendix B. Daily emissions from Section 4.1 of Daily Emissions Modeling Spreadsheet and Annual emissions from Section 4.1 of Annual Emissions Modeling Spreadsheet.

MCAPCD Significance Thresholds and Potential to Emit

The MCAPCD has not formally adopted thresholds of significant impact for the purposes of CEQA review. Thresholds of potential significant impact were nonetheless identified in the 2006 Final Environmental Impact Report prepared for the Mariposa County General Plan. In Table 4.8-1 of the Final EIR1, the emissions in excess of 100 TPY of any criteria air contaminant would be the threshold for significant impact. In addition, the values listed in Table 4 were further confirmed by the MCAPCD2.

Table 4. MCAPCD Significance Thresholds Project VOC NOx CO SOx PM10 PM2.5 Phase (ROG) Operational 100 TPY 100 TPY 100 TPY 100 TPY 100 TPY 100 TPY Construction 100 TPY 100 TPY 100 TPY 100 TPY 100 TPY 100 TPY

1 http://ca-mariposacounty.civicplus.com/DocumentCenter/Home/View/3113 2 Personal Communication with David L. Conway, MCAPCD, September 30, 2017 TSS Consultants 5 November 2017

Pre-Project Potential to Emit

The potential to emit before the implementation of the proposed project is from the disposal method of the sustainably sourced forest woody biomass feedstock. Emissions factors for biomass feedstock fated to the pile and burn scenario are based on a study by the National Renewable Energy Laboratory (NREL)3. These emission factors are verified in a technical paper by the Placer County Air Pollution Control District in 20114. The results of these studies are shown in Table 5 include the emissions from processing and transportation of the woody biomass feedstock

Table 5. Pile and Burn Emission Factors Pollutant EF (lb/thousand BDT) VOC 24,000 NOx 2,500 CO 150,000 SOx 150 PM10 15,000

Net Potential to Emit

The factors in Table 5 are then utilized in Table 6 (along with results in Tables 1 and 3) below to determine the emissions from the standard practice of pile and burn of the woody biomass waste in the forest, which release uncontrolled emissions. The amount of forest-sourced woody biomass to be used (no less than 80% of the annual 12,000 BDT as required by BioMAT) and assuming 60% of that material would have been piled and burned is then calculated and compared to the operational and construction emissions in Tables 1, 2, and 3. The difference between the pile and burn and the operational/construction emissions can then be compared to the MCAPCD thresholds of significance (Table 4).

The net emissions based on the project represent the difference between the pre- project potential to emit and the project’s potential to emit, as shown in Table 6.

3 Adapted from Table 3 - Emissions from Biomass Power Plants in "The Value of the Benefits of U.S. Biomass Power" National Renewable Energy Lab, November 1999 (http://www.nrel.gov/docs/fy00osti/27541.pdf) 4 “Emissions Reductions from Woody Biomass Waste for Energy as an Alternative to Open Burning” Journal of Air & Waste Management 61:63-68. January 2011 TSS Consultants 6 November 2017

Table 6. Net Operational Emissions from Proposed Project

Amount Estimated Percentage of fuel Emission Operational Amount MCAPCD Amount Percentage controlled of fuel diverted factor for TPY for emissions of net Thresholds of fuel per forest emission Pollutant diverted from pile pile and pile and in TPY emissions of year in sourced in TPY from pile and burn in burn (from Table produced Significance BDT fuel (from and burn burning in lb/BDT 3) in TPY in TPY* Table 1) BDT NOx 12,000 80% 60.0% 5,760 7 20.16 11.93 3 -5.23 100 PM10 12,000 80% 60.0% 5,760 15 43.20 1.48 0.91 -40.81 100 VOC 12,000 80% 60.0% 5,760 24 69.12 5.8 0.48 -62.84 100 CO 12,000 80% 60.0% 5,760 150 432.00 27.96 6.89 -397.15 100 SOx 12,000 80% 60.0% 5,760 0.15 0.43 4.55 0.01 4.13 100 1 Table 1 presents the stationary emissions from the proposed project. 2 Table 3 presents the total operational emissions analyzed in its CalEEMod output from the proposed project.

TSS Consultants 7 November 2017 As can be seen in Table 6 above, the differentials between pile and burn emissions and the emissions from operations and construction are considerable, and place all the net emissions significantly below the MCAPCD significance thresholds.

It should be noted that this net emissions analysis does not exempt the facility from acquiring an Authority to Construct permit in which the diversion of the emissions from pile and burn will not be considered.

Calculation of the Pile and Burn Diversion Rate

In August 2015 TSS completed a biomass feedstock availability analysis for the Mariposa Biomass project, on behalf of the Mariposa County Fire Safe Council5. Analysis and information in that analysis served as a basis for the diversion rate determination

Optimized Feedstock Blend

The August 2015 feedstock supply availability analysis report included an optimized feedstock blend forecast: Table 7: Optimized Feedstock Blend

Volume Percent Of Source (BDT/Yr) Total Forest 12,800 80% Urban 2,400 15% Agriculture 800 5% TOTALS 16,000 100%

Feedstock Procurement Forecast

It is TSS understanding that the Mariposa Biomass facility is expected to enter commercial service Q2 2020. Table 8 is a fuel procurement forecast by fuel type for the facility’s initial year of commercial operation (Q2 2020 to Q2 2021). Table 8:Year One Feedstock Procurement Forecast Volume Fuel Type (BDT/Yr) Usual Fate Timber Harvest Residuals 6,800 Open Burn 40% Open Burn/60% Hazardous Fuels Removal 6,400 chip/scatter Total Forest 13,200

5 http://tssconsultants.com/wp-content/uploads/2015/10/MSFSC-Feedstock-Avail-Analysis-Report- 20150827_final.pdf TSS Consultants 8 November 2017

Volume Fuel Type (BDT/Yr) Usual Fate Ag Fuel - Orchard Removal 600 Open Burn Urban Wood Waste 2,200 Landfill Total Feedstock Procured 16,000 Volume Diverted Away From Open Burn 9,960 Percent Diverted From Open Burn 62%

TSS conducted interviews with foresters that are familiar with forest practices in the Mariposa/Madera County region in order to generate this feedstock forecast. Information provided by these local foresters included:

• Historic timber harvest residual disposal methods. • Current fuels treatment methodologies and disposal options. • Planned tree mortality mitigation plans.

In addition, TSS utilized past experience as a forester6 and fuel procurement manager, and knowledge of current forest and agricultural management practices to generate this forecast.

To increase the conservative nature of the emissions analysis, a diversion rate of 60% was used in Table 6

Health Risk Assessment Dispersion Model Selection The health risk assessment (HRA) modeling for the project operations was conducted using the California Air Resources Board (ARB) Hotspots Analysis Reporting Program Version 2 (HARP 2) and the state-approved air dispersion modeling program AERMOD based on guidance and data from the California Office of Environmental Health Hazard Assessment (OEHHA) guidelines (OEHHA, 2015). The technical options selected for dispersion modeling include: • Regulatory default control options • Rural dispersion mode • Receptor elevations and controlling hill heights obtained from AERMAP (version 11103 or most recent) output

6 Tad Mason, California Registered Professional Forester, #2156, issued 1982 TSS Consultants 9 November 2017

Source Characterization

The facility sources including two syngas-fueled internal combustion engines and the Wood Roll process are vented through a single common facility stack and were therefore modeled as a single point source. Emissions for each source were combined with the exhaust parameters obtained from manufacturer data. A table of the facility stack parameters is presented in Table 9 below and emissions are presented in Appendix C.

Table 9. Modeling Parameters Stack Height (m) 18.29 Stack Diameter (m)* 1.0 Exhaust Gas Flow Rate (m3/hr)** 17,145.4 Exhaust Velocity (m/sec) 6.06 Exhaust Temperature (deg. C)*** 220 * Stack diameter represents the inner diameter of the facility stack. ** Exhaust gas flow rate represents the manufacturer supplied flow rate multiplied by two to account for both engines exhausting through a common stack. ***Exhaust temperature accounts for heat recovery processes from exhaust stream resulting in a lower exhaust temperature.

Meteorological Data

Preprocessed meteorological data for input into AERMOD was obtained from the San Joaquin Valley Air Pollution Control District website for the Madera station (Station ID: 93242) located approximately 36 miles south of the site. This meteorological data site was selected as representative due to the following reasons: proximity to the proposed project, similar local land cover area to the proposed project area, and minimal terrain between the proposed project and selected meteorological station.

Receptor Selection

The receptor grid modeled in this risk analysis includes fence line receptors, sensitive receptors, census centroid receptors, and gridded receptors. The receptors were spaced to provide sufficient estimation of the maximum concentrations and elevations were based on the AERMAP model run output. The receptor spacing is as follows:

• 50-meter spacing along the fence line • 50-meter spacing from the fence line to 1,000 meters beyond the fence line • 200-meter spacing from 1,000 meters to 5,000 meters beyond the fence line TSS Consultants 10 November 2017

In total, cancer and non-cancer risks were evaluated at 5,402 receptors. The receptor breakdown is as follows:

• Receptors 1 through 5,337: Gridded Receptors • Receptors 5,338 through 5,400: Census Receptors • Receptors 5,401 through 5,402: Sensitive Receptors

Figure 2 shows the receptor grid showing the receptor grid spacing overlaid on an aerial map. Census receptors within the modeling domain were extracted directly from HARP2 and are based on 2010 census data. Sensitive receptors include schools (kindergarten through 12th grade), day care centers, nursing homes, retirement homes, health clinics, and hospitals.

TSS Consultants 11 November 2017

Figure 2 – AERMOD Grid

TSS Consultants 12 November 2017

Health Risk Modeling Carcinogenic

The point of maximum impact (PMI), maximally exposed individual residence (MEIR) excess cancer risks were evaluated using the 30-year exposure duration scenario. The maximally exposed individual worker (MEIW) cancer risk was evaluated using the 25-year exposure duration as recommended in the OEHHA Guidelines7. Based on the Risk Management Guidance for Stationary Sources of Air Toxics8, the Derived (Adjusted) Method in HARP 2 was used for the excess cancer risk assessment, which uses the 95th percentile breathing rate from the 3rd trimester to 2 years and the 80th percentile inhalation rate from 2 years to 70 years for MEIR excess cancer risk assessments. The 30-year and 25-year exposure durations for the MEIR and MEIW were obtained from the OEHHA Guidelines.

Excess cancer risks were evaluated based on the annual toxic emissions impacts at ground level, inhalation cancer potency, oral slope factor, frequency and duration of exposure at the receptor, and breathing rate of the exposed persons. The MEIW incremental cancer risk was conservatively assumed to occur at the maximum impacts receptor in the modeling domain to account for new industrial activities potential to occur anywhere within the modeling area.

Non-Carcinogenic

The PMI, MEIR, MEIW and maximum sensitive receptor non-carcinogenic acute and chronic health effects were evaluated using the default OEHHA input assumptions. The health index is obtained by dividing the calculated increase acute and chronic risk by the acute and chronic RELs. Chronic toxicity is defined as adverse health effects from prolonged chemical exposure, caused by chemicals accumulating in the body. Acute toxicity is defined as adverse health effects caused by a brief chemical exposure of no more than 24 hours. To assess chronic and acute non-cancer exposures, annual and 1-hour toxic air contaminant ground-level impacts are compared with the reference exposure levels (REL) developed by OEHHA to assess the chronic or acute hazard index.

7 Office of Environmental Health Hazard Assessment (OEHHA), 2015. Air Toxics Hot Spots Program Risk Assessment Guidelines, The Air Toxics Hot Spots Program Guidance Manual for Preparation of Health Risk Assessments. Director, Office of Environmental Health Hazard Assessment, California Environmental Protection Agency, George V. Alexeeff, Ph.D. February 2015. 8 California Air Resources Board (ARB), 2015. Risk Management Guidance for Stationary Sources of Air Toxics. California Air Pollution Control Officers Association. July 2015.

TSS Consultants 13 November 2017

HARP Options

The most recent version of HARP 2 (Version 17052), with the revised unit risk and cancer potency values, version 17228, was used for this analysis. The updated sensitivity factors were applied in accordance with the current regulatory guidance (ARB, 2015).

The deposition rate modeled in HARP 2 was set to 0.02 meters per second because the facility sources are considered controlled. In addition to inhalation exposure, the HRA assesses potential health impacts related to exposure from farm produce, mother’s milk, dermal absorption (mixed climate), and soil ingestion as required by OEHHA guidelines.

Exposure Pathways

For this analysis, the following applicable exposure pathways in Table 10 were included for each risk scenario: Table 10. Exposure Pathways Risk Analysis Modeled Exposure Intake Rate Percentile Pathways Acute/8-Hour Inhalation OEHHA Derived Method Inhalation Soil Ingestion Non-Cancer Chronic Dermal Absorption OEHHA Derived Method Mother's Milk Farm Produce Inhalation Soil Ingestion RMP using the Derived Cancer Dermal Absorption Methodology Mother's Milk Farm Produce

The OEHHA Derived Method for non-cancer chronic assessments uses the 95th percentile (High End) values for calculation for the inhalation pathway and the next two risk driving pathways while the remaining exposure pathways will use the 65th percentile values (Mean). The RMP using the Derived Methodology uses the 95th percentile values for all inhalation risk calculations.

Health Risk Assessment Results

Table 11 presents the results of the HRA based on the modeling and risk assessment methodology presented above. As noted above, the MEIW results are based on the impact results at the PMI, assuming workers are exposed only during work hours. This is the reason for the difference between the PMI and MEIW excess cancer risks. Figure 3 shows the location of the excess cancer risk and acute and chronic hazard index for the PMI, MEIR, and MEIW. TSS Consultants 14 November 2017

Figure 3 – HARP Impacts

TSS Consultants 15 November 2017

Table 11. Mariposa Biomass Health Risk Assessment Results Risk Impacts Value Rec UTM*-X UTM*-Y Number Cancer Risk at PMI (per million) 21.7 274 233850 4155050 Cancer Risk at MEIR (per million) 2.4 1754 234550 4155150 Cancer Risk at Sensitive (per million) 0.4 5402 237913 4153246 Cancer Risk at MEIW (per million) 1.8 274 233850 4155050 Chronic Risk at PMI 0.079 274 233850 4155050 Chronic Risk at MEIR 0.009 1754 234550 4155150 Chronic Risk at Sensitive 0.001 5402 237913 4153246 Chronic Risk at MEIW 0.079 274 233850 4155050 Acute Risk at PMI 0.278 1754 234550 4155150 Acute Risk at MEIR 0.278 1754 234550 4155150 Acute Risk at Sensitive 0.019 5402 237913 4153246 Acute Risk at MEIW 0.278 1754 234550 4155150

The exhaust stack height was developed to balance aviation safety concerns with air quality/public health impacts. Reducing the exhaust stack height from the proposed 60 feet would result in higher air dispersion modeled ground-level impacts due to a lower release height. In addition, lowering the exhaust stack height could result in building-induced downwash of the exhaust plume, which is caused by building or structures wake effect resulting in a downward trajectory winds in the project area. This downward wind trajectory causes the exhaust plume to also be directed downward, resulting in less plume dispersion and higher modeled ground-level concentrations.

Long Term and Cumulative Impacts

With the project emissions below the MCAPCD thresholds of significant impacts, potential long-term impacts are also insignificant.

Regarding potential cumulative air quality impacts, one of the principal air quality impacts in the region is the pile and burning of woody biomass waste from forest management operations. Per the calculations in Table 6, the proposed bioenergy project actually reduces cumulative impacts

Odors

The proposed project is not considered a major source of odor emissions. The project could introduce new odor sources in the project area such as from anaerobic activity in the storage piles of biomass feedstock, and additional diesel

TSS Consultants 16 November 2017

vehicle emissions. However, such odor sources at the site are not expected to impact adjacent land uses, as project operations would include measures to avoid anaerobic activity in the storage piles. Plus, the nearest sensitive receptors (residences) are over 1,000 feet to the northeast.

TSS Consultants 17 November 2017

Greenhouse Gas Emissions

CalEEMod was also used to assess the project construction greenhouse gas (GHG) emissions. Table 12 presents the results of the construction GHG assessment. The CalEEMod results are found in Appendix B. Table 12. Construction GHG Maximum Controlled Annual Pollutant Emissions (metric tons) Carbon Dioxide-Equivalent 360.54

CalEEMod was also used to assess the project operational mobile and temporary source greenhouse gas (GHG) emissions. Table 13 presents the results of the operational mobile GHG assessment. Table 13. Mobile GHG Emissions Maximum Controlled Annual Pollutant Emissions (metric tons) Carbon Dioxide-Equivalent 1,054.57

Using the above CalEEMOD data and calculated GHG emissions from the combustion of 12,000 BDT annually by the proposed facility and from the 60% reduction of open burning of the woody biomass waste, the following Table 14 results in the total GHG burden of the bioenergy facility. Table 14. Total Facility GHG Burden Projected GHG Emissions Emission Source (CO2e in metric tons per year) 360.54 Construction Emissions 12 MT/year9 Project Emissions 20,760 MT/year10 Mobile Operations 1054.57 MT/year Reduced Open Pile Burning (-12,456) MT/year11 TOTAL 9,370.57MT/year

Regarding the total GHG emissions whether it be the total gross GHG emissions (21,826.57 MT/year) or the net GHG emissions after considering the offset of GHG from reduced open pile burning (9,370.57 MT/year), it should be noted that

9 Amortized over 30 years 10 Uses a CO2e emission factor of 1.73 tons CO2 per dry ton of biomass. From “Biomass Waste for Energy Project Reporting Protocol” January 2013. Prepared by the Placer County Air Pollution Control District. Calculate 80% of 12,000 annual BDT times 60% diversion from open burning. 11 Ibid

TSS Consultants 18 November 2017

the MCAPCD does not have a GHG emissions significant impact threshold value. The California Air Resources Board (CARB) has used 25,000 metric tons/year as a reporting threshold for the cap and trade program, but was not specifically established as a CEQA threshold for GHGs. However, in the report titled: CEQA and Climate Change: Evaluating and Addressing Greenhouse Gas Emissions from Projects Subject to the California Environmental Quality Act12, the California Air Pollution Control Officers Association (CAPCOA) identifies the 25,000 metric ton threshold, as used by CARB for their reporting threshold, as a potential and appropriate non-zero GHG threshold for use in a CEQA document (see pages 44-45 of the above-referenced 2008 report13).

Additionally, the U.S. EPA regulations for reporting of GHG emissions set a 25,000 metric ton threshold for large emission sources and the European Union has provided for “small installations” with emissions under 25,000 metric tons to be exempted from its Emissions Trading Scheme; notably, biomass emissions are excluded from this calculation.

In summary, a 25,000 metric ton threshold has been determined in several state, federal, and international rulemaking processes to represent a significant level of emissions with respect to cumulative contributions to global climate change. Given the research and resources that went into the development of the GHG Mandatory Reporting Rule and cap and trade programs adopted by CARB, the U.S. EPA GHG reporting rule, and the fact that the 25,000 metric ton threshold would capture approximately 94 percent of GHG emissions associated with stationary sources in California (CAPCOA, page 44), this level could be used as the significant impact threshold for GHGs in the MCAPCD

Therefore, if the proposed project generates 25,000 metric tons of CO2e or greater in a year, it would be considered to have a significant and cumulatively considerable impact on the environment. If the proposed project would generate

less than 25,000 metric tons of CO2e per year, it would be considered a less than significant and less than cumulatively considerable impact related to climate change and GHGs. In order to determine if the proposed project would conflict with an applicable plan, policy, or regulation adopted for the purpose of reducing the emissions of GHGs, the proposed project is compared to the most applicable and relevant state-level regulations adopted to reduce GHG levels.

It must be noted that Table 14 calculates the GHG emissions without considering the carbon neutrality of woody biomass. Woody biomass combustion for the production of electricity is considered to be carbon neutral by state, federal and international agencies. CO2e emissions related to the burning of woody biomass has been exempted from the California Cap and Trade program for this reason and, as such, it is reasonable to consider the calculation of total emissions as

12 http://www.capcoa.org/wp-content/uploads/2012/03/CAPCOA-White-Paper.pdf 13 Ibid

TSS Consultants 19 November 2017

potentially carbon neutral when determining the project’s environmental impacts. If the project emissions in Table 9, i.e., the GHG emissions from the combustion of woody biomass, is considered zero, then the GHG burden of the proposed project is 1,067 MT/year.

TSS Consultants 20 November 2017

APPENDIX A

GE Jenbacher Syngas Engine Specifications

Technical Description

Cogeneration Unit JMS 616 GS-S.L

Cortus Energy JMS 616 F70, 480V, Syngas 7 Syngas Gas Composition*: CO: 34%, H2: 54%, CH4: 2.0%, CO2: 10% The ratings in the specification are valid for full load operation at a site installation of 0 ft (0 m) and an air intake temperature of T1 < 95F (35C). At T1 > 95 F (35C), an output derating 1.1%/F (2%/C) will occur.

Electrical output 1381 kWe

Thermal output 6090 Mbtu/hr

Emission values NOx < 1.1 g/bhp.hr (NO2)

31.01.2017/HT(P (5015) TS JMS 616 F70 480V 31 January 2017 Cortus Energy us.docx Copyright ©(rg) 1/43

0.01 Technical Data (at module) ______4 Main dimensions and weights (at module)(with gearbox) 5 Connections 5 Output / fuel consumption 5 0.02 Technical data of engine ______6 Thermal energy balance 6 Exhaust gas data 6 Combustion air data 6 Sound pressure level 7 Sound power level 7 0.02.01 Technical data of gearbox ______7 0.03 Technical data of generator ______8 Reactance and time constants (saturated) 8 0.04 Technical data of heat recovery ______9 General data - Hot water circuit 9 General data - Cooling water circuit 9 Exhaust gas heat exchanger (By Others) 9 Guaranteed Thermal Output (10 bar) connection variant H ______10 Expected Thermal Output (11.5 bar) connection variant H ______11 0.10 Technical parameters______12 0.11 Additional Technical parameters ______14 1.00 Scope of supply - Module ______15 1.01 Spark ignited gas engine ______15 1.01.01 Engine design ______16 1.01.02 Additional equipment for the engine (spares for commissioning) ______17 1.01.03 Engine accessories ______18 1.01.04 Standard tools (per installation)______18 1.02 Generator-Low Voltage ______19 1.03 Module Accessories ______22 1.03.01 Engine jacket water system ______24 1.03.02 Automatic lube oil replenishing system incl. extension tank ______24 1.04 Heat recovery ______25 1.05 Gas train (special gas) ______26 1.05.01 Nitrogen flushing ______27 1.07 Painting ______27

31.01.2017/HT(P (5015) TS JMS 616 F70 480V 31 January 2017 Cortus Energy us.docx Copyright ©(rg) 2/43

1.11 Engine generator control panel – DIA.NE XT ______28 1.11.02 Remote information via Modbus RTU ______33 1.11.03 Remote Data-Transfer with DIA.NE XT - HERMES ______33 1.20.03 Starting system ______36 1.20.05 Electric jacket water preheating ______36 1.20.08 Flexible connections ______37 2.00 Electrical equipment ______37 2.02 Grid monitoring device ______37 3.03 Exhaust Gas Pressure Relief Valve ______39 3.70 Control Strategy and Options ______39 4.00 Delivery, installation and commissioning ______40 4.01 Carriage 40 4.02 Unloading 40 4.03 Assembly and installation 40 4.04 Storage 40 4.05 Start-up and commissioning 40 4.06 Trial run 40 4.07 Emission measurement (exhaust gas analyser) 40 5.01 Limits of delivery ______41 5.02 Factory tests and inspections ______42 5.02.01 Engine tests 42 5.02.02 Generator tests 42 5.02.03 Module tests 42 5.03 Documentation ______43

31.01.2017/HT(P (5015) TS JMS 616 F70 480V 31 January 2017 Cortus Energy us.docx Copyright ©(rg) 3/43

0.01 Technical Data (at module)

Data at: Full Part Load load Fuel gas LHV BTU/scft 291 Guarantee Expected 50%

Energy input MBTU/hr [2] 12,060 13,614 7,640 Gas volume scfhr *) 41,443 46,783 26,254 Mechanical output bhp [1] 1,675 1,924 962 Electrical output kW el. [4] 1,195 1,381 681 Recoverable thermal output ~ 1st stage MBTU/hr 1,006 1,275 233 ~ Lube oil (with gearbox) MBTU/hr 1,174 1,297 921 ~ Jacket water MBTU/hr 1,075 1,201 805 ~ Exhaust gas cooled to 356 °F MBTU/hr 2,201 2,317 1,641 Total recoverable thermal output MBTU/hr [5] 5,457 6,090 3,600

Heat to be dissipated ~ Intercooler 2nd stage MBTU/hr [9] 370 418 235 ~ Lube oil (with gearbox) MBTU/hr ~ ~ ~ ~ Surface heat ca. MBTU/hr [7] 705 756 ~

Spec. fuel consumption of engine electric BTU/kWel.hr [2] 10,095 9,860 11,215 Spec. fuel consumption of engine BTU/bhp.hr [2] 7,201 7,076 7,942 Lube oil consumption ca. gal/hr [3] 0.28 0.28 ~ Electrical efficiency % 33.8% 34.6% 30.4% Thermal efficiency % 45.3% 44.7% 47.1% Total efficiency % [6] 79.1% 79.3% 77.5%

Hot water circuit: Forward temperature °F 194.0 194.0 179.3 Return temperature °F 158.0 158.0 158.0 Hot water flow rate GPM 339.8 379.2 379.2 *) approximate value for pipework dimensioning [_] Explanations: see 0.10 - Technical parameters

All heat data is based on standard conditions according to attachment 0.10. Deviations from the standard conditions can result in a change of values within the heat balance, and must be taken into consideration in the layout of the cooling circuit/equipment (intercooler; emergency cooling; ...). In the specifications in addition to the general tolerance of ±8 % on the thermal output a further reserve of +5 % is recommended for the dimensioning of the cooling requirements.

31.01.2017/HT(P (5015) TS JMS 616 F70 480V 31 January 2017 Cortus Energy us.docx Copyright ©(rg) 4/43

Main dimensions and weights (at module)(with gearbox) Length in ~ 400 Width in ~ 90 Height in ~ 110 Weight empty lbs ~ 63,040 Weight filled lbs ~ 65,250

Connections Hot water inlet and outlet [A/B] in/lbs 4''/145 Exhaust gas outlet [D] in/lbs 25''/145 Fuel Gas (at module) in/lbs 4''/145 Water drain ISO 228 G ½'' Condensate drain in/lbs 2''/145 Safety valve - jacket water ISO 228 in/lbs 2x1½''/2.5 Safety valve - hot water in/lbs 3''/145 Lube oil replenishing (pipe) in 1.1 Lube oil drain (pipe) in 1.1 Jacket water - filling (flex pipe) in 0.5 Intercooler water-Inlet/Outlet 1st stage in/lbs 4''/145 Intercooler water-Inlet/Outlet 2nd stage in/lbs 2½''/145

Output / fuel consumption ISO standard fuel stop power ICFN bhp 1,674 | 1,924 Mean effe. press. at stand. power and nom. speed psi 145 | 167 Fuel gas type Hydrogen gas Based on number | Min. methane number MN d) n.a. | n.a. Compression ratio Epsilon 10 | 11.3 Min./Max. fuel gas pressure at inlet to gas train psi 1.74 - 2.9 c) Allowed Fluctuation of fuel gas pressure % ± 10 Max. rate of gas pressure fluctuation psi/sec 0.145 Maximum Intercooler 2nd stage inlet water temperature °F 104 Spec. fuel consumption of engine BTU/bhp.hr 7,201 | 7,076 Specific lube oil consumption g/bhp.hr 0.37 Max. Oil temperature °F 176 Jacket-water temperature max. °F 203 Filling capacity lube oil (refill) gal ~ 171 c) Lower gas pressures upon inquiry d) based on methane number calculation software AVL 3.2

31.01.2017/HT(P (5015) TS JMS 616 F70 480V 31 January 2017 Cortus Energy us.docx Copyright ©(rg) 5/43

0.02 Technical data of engine

Manufacturer GE Jenbacher Engine type J 616 GS-F70 Working principle 4-Stroke Configuration V 60° No. of cylinders 20 Bore in 7.48 Stroke in 8.66 displacement cu.in 6,090 Nominal speed rpm 1,500 Mean piston speed in/s 433 Length in 193 Width in 74 Height in 99 Weight dry lbs 27,558 Weight filled lbs 29,762 Moment of inertia lbs-ft² 1541.76 Direction of rotation (from flywheel view) left Radio interference level to VDE 0875 N Starter motor output kW 20 Starter motor voltage V 24

Thermal energy balance Energy input MBTU/hr 12,060 | 13,614 Intercooler MBTU/hr 1,376 | 1,693 Lube oil (with gearbox) MBTU/hr 1,174 | 1,297 Jacket water MBTU/hr 1,075 | 1,201 Exhaust gas cooled to 356 °F MBTU/hr 2,201 | 2,317 Exhaust gas cooled to 212 °F MBTU/hr 2,973 | 3,204 Surface heat MBTU/hr 525 | 549

Exhaust gas data Exhaust gas temperature at full load °F [8] 752 | 721 Exhaust gas mass flow rate, wet lbs/hr 20,788 | 23,814 Exhaust gas mass flow rate, dry lbs/hr 19,274 | 22,106 Exhaust gas volume, wet scfhr 264,365 | 302,742 Exhaust gas volume, dry scfhr 234,231 | 268,735 Max.admissible exhaust back pressure after engine psi 0.725

Combustion air data Combustion air mass flow rate lbs/hr 19,418 | 22,269 Combustion air volume SCFM 4,012 | 4,600 Max. admissible pressure drop at air-intake filter psi 0.145

31.01.2017/HT(P (5015) TS JMS 616 F70 480V 31 January 2017 Cortus Energy us.docx Copyright ©(rg) 6/43

Sound pressure level Aggregate a) dB(A) re 20µPa 102 31,5 Hz dB 83 63 Hz dB 90 125 Hz dB 96 250 Hz dB 98 500 Hz dB 97 1000 Hz dB 95 2000 Hz dB 94 4000 Hz dB 94 8000 Hz dB 92 Exhaust gas b) dB(A) re 20µPa 119 31,5 Hz dB 109 63 Hz dB 119 125 Hz dB 128 250 Hz dB 117 500 Hz dB 115 1000 Hz dB 114 2000 Hz dB 111 4000 Hz dB 106 8000 Hz dB 91

Sound power level Aggregate dB(A) re 1pW 124 Measurement surface ft² 1,604 Exhaust gas dB(A) re 1pW 127 Measurement surface ft² 67.60 a) average sound pressure level on measurement surface in a distance of 1m (converted to free field) according to DIN 45635, precision class 3. b) average sound pressure level on measurement surface in a distance of 1m according to DIN 45635, precision class 2. The spectra are valid for aggregates up to bmep=319.083028 psi. (for higher bmep add safety margin of 1dB to all values per increase of 1 bar pressure). Engine tolerance ± 3 dB

0.02.01 Technical data of gearbox

Manufacturer EISENBEISS Type ~ Gearbox ratio 1:1.2 Efficiency % 99.51 Mass lbs 3,748

31.01.2017/HT(P (5015) TS JMS 616 F70 480V 31 January 2017 Cortus Energy us.docx Copyright ©(rg) 7/43

0.03 Technical data of generator

Manufacturer STAMFORD e) Type LVSI 804 R e) Type rating kVA 2,270 Driving power bhp 1,666 | 1,915 Ratings at p.f.= 1.0 kW 1,195 | 1,381 Ratings at p.f. = 0.8 kW 1,190 | 1,367 Rated output at p.f. = 0.8 kVA 1,487 | 1,709 Rated reactive power at p.f. = 0.8 kVAr 892 | 1,025 Rated current at p.f. = 0.8 A 1,789 | 2,055 Frequency Hz 60 Voltage V 480 Speed rpm 1,800 Permissible overspeed rpm 2,250 Power factor (lagging - leading) 0,8 - 1,0 Efficiency at p.f.= 1.0 % 96.1% | 96.7% Efficiency at p.f. = 0.8 % 95.7% | 95.8% Moment of inertia lbs-ft² 1774.12 Mass lbs 11,449 Radio interference level to EN 55011 Class A (EN 61000-6-4) N Ik'' Initial symmetrical short-circuit current kA 20.39 Is Peak current kA 51.90 Insulation class H Temperature (rise at driving power) F Maximum ambient temperature °F 104

Reactance and time constants (saturated) xd direct axis synchronous reactance p.u. 1.43 xd' direct axis transient reactance p.u. 0.11 xd'' direct axis sub transient reactance p.u. 0.09 x2 negative sequence reactance p.u. 0.12 Td'' sub transient reactance time constant ms 15 Ta Time constant direct-current ms 68 Tdo' open circuit field time constant s 3.95 e) GE Jenbacher reserves the right to change the generator supplier and the generator type. The contractual data of the generator may thereby change slightly. The contractual produced electrical power will not change.

31.01.2017/HT(P (5015) TS JMS 616 F70 480V 31 January 2017 Cortus Energy us.docx Copyright ©(rg) 8/43

0.04 Technical data of heat recovery

General data - Hot water circuit Total recoverable thermal output MBTU/hr 5,457 | 6,090 Return temperature °F 158.0 Forward temperature °F 194.0 Hot water flow rate GPM 339.8 | 379.2 Nominal pressure of hot water lbs 145 min. operating pressure psi 51.0 max. operating pressure psi 131.0 Pressure drop hot water circuit psi 21.76 Maximum Variation in return temperature °F +0/-21 Max. rate of return temperature fluctuation °F/min 18

General data - Cooling water circuit Heat to be dissipated MBTU/hr 370 | 418 Return temperature °F 104 Cooling water flow rate GPM 198 Nominal pressure of cooling water lbs 145 min. operating pressure psi 7.0 max. operating pressure psi 73.0 Loss of nominal pressure of cooling water psi ~ Maximum Variation in return temperature °F +0/-21 Max. rate of return temperature fluctuation °F/min 18

Exhaust gas heat exchanger (By Others) Type shell-and-tube

PRIMARY: Exhaust gas pressure drop approx psi 0.22 Exhaust gas connection in/lbs 25''/145

SECONDARY: Pressure drop hot water circuit psi 2.90 Hot water connection in/lbs 6''/145

The final pressure drop will be given after final order clarification and must be taken from the P&ID order documentation.

31.01.2017/HT(P (5015) TS JMS 616 F70 480V 31 January 2017 Cortus Energy us.docx Copyright ©(rg) 9/43

Guaranteed Thermal Output (10 bar) connection variant H

Expected Thermal Output (11.5 bar) connection variant H

0.10 Technical parameters

The following “Technical Instruction (TI) of GE JENBACHER” form an integral part of the contract and must be strictly observed:

TI 1100-0110 – Boundary Conditions for GE Jenbacher Gas Engines TI 1100-0111 – General Conditions – Operation and Maintenance TI 1100-0112 – Installation of GE Jenbacher Units

These Technical Instructions reference other guides and instructions which can be provided upon request. These instructions should be carefully reviewed by all personnel involved with the application, installation design, installation construction, and overall maintenance of any GE Jenbacher gas engine.

All data in the technical specification are based on engine full load (unless stated otherwise) at specified temperatures as well as the methane number and subject to technical development and modifications. For isolated operations, an output reduction may be applicable per the block load diagram. Before being able to provide exact output numbers, a detailed site load profile needs to be provided (motor starting curves, etc.).

All pressure indications are to be measured and read with pressure gauges (gauge).

(1) At nominal speed and standard reference conditions ICFN per DIN-ISO 3046 and DIN 6271, respectively (2) As detailed in DIN-ISO 3046 and DIN 6271, respectively, with a tolerance of + 5 %. Efficiency performance is based on a new unit (immediately upon commissioning). The effects of degradation during normal operation can be mitigated through regular service and maintenance work. (3) Average value between oil change intervals as per the maintenance schedule, without oil change amount (4) At p. f. = 1.0 as detailed in VDE 0530 REM / IEC 34.1 with relative tolerances, all direct driven pumps are included (5) Total output with a tolerance of +/- 8 % (6) As detailed in above parameters (1) through (5) (7) Only valid for engine and generator; module and peripheral equipment not considered (at p. f. = 0.8), (guiding value) (8) Exhaust temperature with a tolerance of +/- 8 % (9) Intercooler heat on: * standard conditions (Vxx) - If the design is done for air intake temperature > 30°C (86°F) w/o de-rating, the intercooler heat of the 1st stage need to be increased by 2%/K starting from 25°C (77°F). Deviations between 25 – 30°C (77 – 86°F) will be covered with the standard tolerance. * Hot Country application (Vxxx) - If the turbocharger design is done for air intake temperature > 40°C (104°F) w/o de-rating, the intercooler heat of the 1st stage need to be increased by 2%/K starting from 35°C (95°F). Deviations between 35 – 40°C (95 – 104°F) will be covered with the standard tolerance.

31.01.2017/HT(P (5015) TS JMS 616 F70 480V 31 January 2017 Cortus Energy us.docx Copyright ©(rg) 12/43

Definition of output  ISO-ICFN continuous rated power: The Net Break Power that the engine manufacturer declares an engine is capable of delivering continuously, at stated speed, between the normal maintenance intervals and overhauls as required by the manufacturer. Power determined under the operating conditions of the manufacturer’s test bench and adjusted to the standard reference conditions.   Standard reference conditions: Barometric pressure: 1000 mbar (14.5 psig) or 100m (328ft) above sea level Air temperature: 25°C (77°F) or 298 K Relative humidity: 30 %

 Volume values at standard conditions (fuel gas, combustion air, exhaust gas) Pressure: 1013.25 mbar (14.7 psig) Temperature: 0°C (32°F) or 273 K

Output adjustment for turbo charged engines The ratings in this specification are valid for an installation at an altitude 0ft (0m) and an air intake temperature T1 < 95F (35C). At T1 > 95F (35C), an output derating of 1.11%/F (2.0%/C) will occur.

Radio interference level The ignition system of the gas engines complies the radio interference levels of CISPR 12 and EN 55011 class B, (30-75 MHz, 75-400 MHz, 400-1000 MHz) and (30-230 MHz, 230-1000 MHz), respectively.

Parameters for the operation of GE Jenbacher gas engines

Maximum room temperature: 50°C (122°F) (T2) -> engine stop

If the actual methane number is lower than the specified, the knock control responds. First the ignition timing is changed at full rated power. Secondly the rated power is reduced. These functions are carried out by the engine management.

Operation of Voltage and frequency outside of stated limits for the generator as per IEC 60034-1 Zone A will result in a power de-rate up to and including tripping of the equipment.

31.01.2017/HT(P (5015) TS JMS 616 F70 480V 31 January 2017 Cortus Energy us.docx Copyright ©(rg) 13/43

The generator set fulfills ISO 8528-9 limits for mechanical vibrations.

If possible, railway trucks must not be used for transport (TI 1000-0046).

Parameters for the operation of control unit and the electrical equipment  Relative humidity: 50%  Maximum temperature: 40°C (104°F).  Altitude: < 6560ft (2000m) above the sea level.

The gas quantity indicated under technical data refers to standard conditions with the given calorific value. Actual volume flow (under operating conditions) must be considered for dimensioning of any the gas compressor and associated fuel system component. These elements will also be affected by:  Actual gas temperature (reference TI 1000-0300 for temperature limits)  Gas humidity (reference TI 1000-0300 for temperature limits)  Gas Pressure (page 5 of this specification)

0.11 Additional Technical parameters

 Idle load operation (without grid) with wood gas is not allowed.

 The engine room ventilation must be designed as a forced system (with intake fans), so that there is always a slight overpressure in the engine room. This ensures that any unburned exhaust gas will be forced out of the exhaust system and cannot leak back into the engine room.

 The engine room ventilation must be designed so that in case of leaks no ignitable amounts of gas can form.

 It must be insured that during any operational mode no ignitable gas mixture is evident at any of GE Jenbacher delivered components. See TA 1000-0110.  A emergency cut off valve that can be controlled by Jenbacher shall be installed outside of the engine room.

 The gas warning system must be designed according to the gas composition

 All persons in the immediate vicinity of the site must be equipped with a suitable wearable gas warning sensor. Relevant warning and security notification boards for CO, H2 and other poisonous and flammable gases/substances must be visible positioned and in a manner that informs and motivates personal correctly.

 The gas, according to TA 1000-0300 and at the given parameters (gas temperature < 50°C, gas pressure 105-200mbar) must be free of condensate and/or sublimates.

31.01.2017/HT(P (5015) TS JMS 616 F70 480V 31 January 2017 Cortus Energy us.docx Copyright ©(rg) 14/43

1.00 Scope of supply - Module

Design: The module is built as a compact package. The engine base is bolted to the gearbox/generator base. The Engine output shafting is connected through a coupling to a gearbox. A second coupling is then provided connecting the gearbox to the generator. To provide the best possible isolation from the transmission of vibrations, the engine rests on the engine base-frame by means of anti-vibration mounts. The remaining vibrations are eliminated by mounting the complete module (engine and gearbox/generator frames) on isolating pads (e.g. Sylomer). This, in principle, allows for placing of the module to be directly on any floor capable of carrying the static load. No special foundation is required. Prevention of sound conducted through solids has to be provided locally.

1.01 Spark ignited gas engine

Four-stroke, air/gas mixture turbocharged, aftercooled, with high performance ignition system and electronically controlled air/gas mixture system. The engine is equipped with the most advanced

LEANOX® LEAN-BURN COMBUSTION SYSTEM developed by GE JENBACHER.

31.01.2017/HT(P (5015) TS JMS 616 F70 480V 31 January 2017 Cortus Energy us.docx Copyright ©(rg) 15/43

1.01.01 Engine design

Engine block Single-piece crankcase and block made of special casting; crank case covers for engine inspection, welded steel oil pan.

Crankshaft and main bearings Drop-forged, precision ground, surface hardened, statically and dynamically balanced; main bearings (upper bearing shell: grooved bearing / lower bearing shell: sputter bearing) arranged between crank pins, drilled oil passages for forced-feed lubrication of connecting rods.

Vibration damper Maintenance free viscous damper

Flywheel With ring gear for starter motor and additionally screwed on.

Pistons Single-piece made of steel, with piston ring carrier and oil passages for cooling; piston rings made of high quality material, main combustion chamber specially designed for lean burn operation.

Connecting rods Drop-forged, heat-treated, big end diagonally split and toothed. Big end bearings (upper bearing shell: sputter bearing / lower bearing shell: sputter bearing) and bushing for piston pin.

Cylinder liner Chromium alloy gray cast iron, wet, individually replaceable.

Cylinder head Specially designed and developed for GE JENBACHER-lean burn engines with optimized fuel consumption and emissions; water cooled, made of special casting, individually replaceable; Valve seats and valve guides and sleeves individually replaceable; exhaust and inlet valve made of high quality material; Pre- chamber with check-valve.

Crankcase breather Connected to combustion air intake system

Valve train , with replaceable bushings, driven by through intermediate gears, valve lubrication by splash oil through rocker arms.

Combustion air/fuel gas system Motorized carburetor for automatic adjustment according fuel gas characteristic. Exhaust driven turbocharger, mixture manifold with bellows, water-cooled intercooler, throttle valve and distribution manifolds to cylinders.

31.01.2017/HT(P (5015) TS JMS 616 F70 480V 31 January 2017 Cortus Energy us.docx Copyright ©(rg) 16/43

Ignition system Most advanced, fully electronic high performance ignition system, external ignition control. MORIS: Automatically, cylinder selective registration and control of the current needed ignition voltage.

Lubricating system Gear-type lube oil pump to supply all moving parts with filtered lube oil, pressure control valve, pressure relief valve and full-flow filter cartridges. Cooling of the lube oil is arranged by a heat exchanger.

Engine cooling system Jacket water pump complete with distribution pipework and manifolds.

Exhaust system Turbocharger and exhaust manifold

Exhaust gas temperature measuring Thermocouple for each cylinder

Electric actuator For electronic speed and output control

Electronic speed monitoring for speed and output control By magnetic inductive pick up over ring gear on flywheel

Starter motor Engine mounted electric starter motor

1.01.02 Additional equipment for the engine (spares for commissioning)

The initial set of equipment with the essential spare parts for operation after commissioning is included in the scope of supply.

31.01.2017/HT(P (5015) TS JMS 616 F70 480V 31 January 2017 Cortus Energy us.docx Copyright ©(rg) 17/43

1.01.03 Engine accessories

Insulation of exhaust manifold: Insulation of exhaust manifold is easily installed and removed

Sensors at the engine:  Jacket water temperature sensor  Jacket water pressure sensor  Lube oil temperature sensor  Lube oil pressure sensor  Mixture temperature sensor  Charge pressure sensor  Minimum and maximum lube oil level switch  Exhaust gas thermocouple for each cylinder  Knock sensors  Gas mixer / gas dosing valve position reporting.

Actuator at the engine:  Actuator - throttle valve  Bypass-valve for turbocharger  Control of the gas mixer / gas dosing valve

1.01.04 Standard tools (per installation)

The tools required for carrying out the most important maintenance work are included in the scope of supply and delivered in a toolbox.

31.01.2017/HT(P (5015) TS JMS 616 F70 480V 31 January 2017 Cortus Energy us.docx Copyright ©(rg) 18/43

1.02 Generator-Low Voltage

The 2-bearing generator consists of the main generator (built as rotating field machine), the exciter machine (built as rotating armature machine) and the digital excitation system. The digital regulator is powered by an auxiliary winding at the main stator or a PMG system

Main components:  Enclosure of welded steel construction  Stator core consist of thin insulated electrical sheet metal with integrated cooling channels.  Stator winding with 2/3 Pitch  Rotor consists of shaft with shrunken laminated poles, Exciter rotor, PMG (depending on Type) and fan.  Damper cage  Excitation unit with rotating rectifier diodes and overvoltage protection  Dynamically balanced as per ISO 1940, Balance quality G2,5  Drive end bracket with re greaseable antifriction bearing  Non-drive end bracket with re grease antifriction bearing  Cooling IC01 - open ventilated, air entry at non-drive end, air outlet at the drive end side  Main terminal box includes main terminals for power cables  Regulator terminal box with auxiliary terminals for thermistor connection and regulator.  Anti-condensation heater  3 PT100 for winding temperature monitoring+3 PT100 Spare  2 PT100 for bearing temperature monitoring  Current transformer for protection and measuring in the star point xx/1A, 10P10 15VA, xx/1A, 1FS5, 15VA

Electrical data and features:  Standards: IEC 60034, EN 60034, VDE 0530, ISO 8528-3, ISO 8528-9  Voltage adjustment range: +/- 10 % of rated voltage (continuous)  Frequency: -6/+4% of rated frequency  Overload capacity: 10% for one hour within 6 hours, 50% for 30 seconds  Asymmetric load: max. 8% I2 continuous, in case of fault I2 x t=20  Altitude: < 1000m  Max permitted generator intake air temperature: 5°C - 40°C  Max. relative air humidity: 90%  Voltage curve THD Ph-Ph: <3% at idle operation and <3% at full load operation with linear symmetrical load  Generator suitable for parallel operating with the grid and other generators  Sustained short circuit current at 3-pole terminal short circuit: minimum 3 times rated current for 5 seconds.  Over speed test with 1.2 times of rated speed for 2 minutes according to IEC 60034

31.01.2017/HT(P (5015) TS JMS 616 F70 480V 31 January 2017 Cortus Energy us.docx Copyright ©(rg) 19/43

Digital Excitation system ABB Unitrol 1010 mounted within the AVR Terminal box with following features:

 Compact and robust Digital Excitation system for Continuous output current up to 10 A (20A Overload current 10s)  Fast AVR response combined with high excitation voltage improves the transient stability during LVRT events.  The system has free configurable measurement and analog or digital I/Os. The configuration is done via the local human machine interface or CMT1000  Power Terminals 3 phase excitation power input from PMG or auxiliary windings Auxiliary power input 24VDC  Excitation output  Measurement terminals: 3 phase machine voltage, 1 phase network voltage, 1 phase machine current  Analog I/Os: 2 outputs / 3 inputs (configurable), +10 V / -10 V  Digital I/O: 4 inputs only (configurable), 8 inputs / outputs (configurable)  Serial fieldbus: RS485 for Modbus RTU or VDC (Reactive power load sharing for up to 31 GEJ engines in island operation), CAN-Bus for dual channel communication  Regulator Control modes: Bump less transfer between all modes Automatic Voltage Regulator (AVR) accuracy 0,1% at 25°C ambient temperature Field Current Regulator (FCR) Power Factor Regulator (PF) Reactive Power Regulator (VAR)  Limiters: Keeping synchronous machines in a safe and stable operation area Excitation current limiter (UEL min / OEL max) PQ minimum limiter Machine current limiter V / Hz limiter Machine voltage limiter  Voltage matching during synchronization  Rotating diode monitoring  Dual channel / monitoring: Enables the dual channel operation based on self-diagnostics and setpoint follow up over CAN communication. As Option available  Power System Stabilizer (PSS) is available as option. Compliant with the standard IEEE 421.5-2005 2A / 2B, the PSS improves the stability of the generator over the highest possible operation range.  Computer representation for power system stability studies: ABB 3BHS354059 E01  Certifications: CE, cUL certification according UL 508c (compliant with CSA), DNV Class B,

31.01.2017/HT(P (5015) TS JMS 616 F70 480V 31 January 2017 Cortus Energy us.docx Copyright ©(rg) 20/43

 Commissioning and maintenance Tool CMT1000 (for trained commissioning/ maintenance personal)  With this tool the technician can setup all parameters and tune the PID to guarantee stable operation. The CMT1000 software allows an extensive supervision of the system, which helps the user to identify and locate problems during commissioning on site. The CMT1000 is connected to the target over USB or Ethernet port, where Ethernet connection allows remote access over 100 m.  Main window  Indication of access mode and device information.  Change of parameter is only possible in CONTROL access mode.  LED symbol indicates that all parameter are stored on none volatile memory.  Setpoint adjust window  Overview of all control modes, generator status, active limiters status and alarms.  Adjust set point and apply steps for tuning of the PID.  Oscilloscope  4 signals can be selected out of 20 recorded channels. The time resolution is 50 ms.Save files to your PC for further investigation.  Measurement  All measurements on one screen.

Routine Test Following routine tests will be carried out by the generator manufacturer  Measuring of the DC-resistance of stator and rotor windings  Check of the function of the fitted components (e.g. RTDs, space heater etc.)  Insulation resistance of the following components Stator winding, rotor winding Stator winding RTDs Bearing RTDs Space heater  No Load saturation characteristic (remanent voltage)  Stator voltage unbalance  Direction of rotation, phase sequence  High voltage test of the stator windings (2 x Unom. + 1000 V) and the rotor windings (min. 1500 V)

31.01.2017/HT(P (5015) TS JMS 616 F70 480V 31 January 2017 Cortus Energy us.docx Copyright ©(rg) 21/43

1.03 Module Accessories

Base frame Split Base Frame fabricated with welded structural steel. First frame to mount the engine, jacket water heat exchangers, pumps and engine auxiliaries, the second to mount the gearbox and generator.

Coupling #1 Engine to Gearbox coupling is provided. The coupling isolates the major sub-harmonics of engine alternating torque from gear box.

Coupling #2 Gearbox to Generator Coupling is provided. This coupling is designed with a torque limiter to couple gear box with alternator.

Coupling housings Provided for both Couplings

Anti-vibration mounts 2 sets of isolation, one is arranged between engine block assembly and base frame. The second is via insulating pads (SYLOMER) for placement between base frame and foundation, delivered loose.

Gear box: A Single-stage spur gear with overhead shaft and closed loop lube oil system, completely mounted on the gearbox/generator base frame. The lube oil heat exchanger is integrated with the warm/cooling water circuit. The gear transmission ratio is 1:1.2. Oil volume is approximately 52 gals (196 liters).

Exhaust gas connection A flanged connection is provided that collects the exhaust gas turbocharger output flows, includes flexible pipe connections (compensators) to compensate for heat expansions and vibrations.

Combustion air filter A Dry type air filter with replaceable filter cartridges is fitted. The assembly includes flexible connections to the fuel mixer/carburetor and service indicator.

Interface panel (M1 cabinet) Totally enclosed sheet steel cubicle with hinged doors, pre-wired to terminals, ready to operate. All Cable entry will be via bottom mounted cable gland plates.

Painting: RAL 7035

Protection: External NEMA 3 (IP 54), Internal IP 20 (protection against direct contact with live parts)

Cabinet design is according to IEC 439-1 (EN 60 439-1/1990) and DIN VDE 0660 part 500, respectively. Ambient temperature 41 - 104 °F (5 - 40 °C), Relative humidity 70%

31.01.2017/HT(P (5015) TS JMS 616 F70 480V 31 January 2017 Cortus Energy us.docx Copyright ©(rg) 22/43

Dimensions:  Height: 51 in - 82 in (1300 mm-2100 mm)  Width: 40 in - 47 in (1000 mm -1200 mm)  Depth: 16 in - 24 in (400 mm-600 mm)

Control Power Source: The starter batteries and the cabinet mounted battery chargers will provide the power source for this enclosure.

Interface Panel contents and control functions:  The cabinet houses the unit Battery Charger and primary 24VDC Control Power Distribution (breakers, fuses, and terminals) from the unit Batteries  Distributed PLC Input and Output cards, located in the cabinet, gather all Engine, Gearbox and Generator Control I/O. These cards transmit data via data bus interface to the central engine control of the module control panel located in the A1 cabinet. Data bus is via CAN and B&R Proprietary Data Highway (Data Cables provided by GE)  Speed monitoring relays for protection are provided.  Gas Train I/O Collection, including interface relays and terminals for gas train shutoff valves.  Transducer for generator functions, such as excitation voltage.  Door Mounted Emergency Stop Switch with associated Emergency Stop Loop interface relays.  Miscellaneous control relays, contacts, fuses, etc. for additional control valves, and auxiliaries.  Interface Terminal Strips

Skid Mounted 3 Phase Devices are Powered by 3 x 480/277 V, 60 Hz, 50 A

AC Power for engine mounted auxiliaries (heater, pumps, etc.) are routed through a separate J-box mounted on the side M1 cabinet (Box E1). This is done to maintain signal segregation (AC from control)

NOTE: Generator Current Transformer wiring is connected directly to the Generator and does NOT pass through the M1 cabinet.

Exhaust gas scavenging blower An exhaust gas scavenging blower is used to scavenge the remaining exhaust gas out of the exhaust gas pipe work, to prevent the appearance of deflagrations.

Function: Before each start scavenging by blower is done for app. 1 minute (except at black out – start)

Supervisions:  Scavenging air fan failure  Scavenging air flap failure

Consisting of:  Fan  Exhaust gas flap  Temperature switch  Compensator and pipe work

31.01.2017/HT(P (5015) TS JMS 616 F70 480V 31 January 2017 Cortus Energy us.docx Copyright ©(rg) 23/43

1.03.01 Engine jacket water system

Engine jacket water system Closed cooling circuit, consisting of:  Expansion tank  Filling device (check and pressure reducing valves, pressure gauge)  Safety valve(s)  Thermostatic valve  Required pipework on module  Vents and drains  Electrical jacket water pump, including check valve  Jacket water preheat device

1.03.02 Automatic lube oil replenishing system incl. extension tank

Automatic lube oil replenishing system: Includes float valve in lube oil feed line, including inspection glass. Electric monitoring system will be provided for engine shut-down at lube oil levels "MINIMUM" and "MAXIMUM". Solenoid valve in oil feed line is only activated during engine operation. Manual override of the solenoid valve, for filling procedure during oil changes is included.

Oil drain By set mounted cock

Oil sump extension tank (delivered loose) 79.3 gal To increase the time between oil changes

Pre-lubrication- and aftercooling oil pump: Mounted on the module base frame; it is used for pre-lubrication and aftercooling of the . Period of operation: Pre-lubrication: 1 minute both pumps Aftercooling: 15 minutes from engine stop only the 480/277 V pump Consisting of:  1 piece oil pump 1500 W, 480/277 V  1 piece oil pump 1500 W, 24 V  All necessary vents  Necessary pipework

31.01.2017/HT(P (5015) TS JMS 616 F70 480V 31 January 2017 Cortus Energy us.docx Copyright ©(rg) 24/43

1.04 Heat recovery

Engine-mounted intercooler and lube oil heat exchanger, jacket water heat exchanger mounted to the engine res. to the module base frame, complete with interconnecting pipe work. The exhaust gas heat exchanger is mounted to the heat recovery module. The insulation of heat exchangers and pipework is not included in GE Jenbacher scope of supply.

Heat exchanger - air/fuel mixture to warm water (intercooler) The engine-mounted intercooler is of two stage design. The first stage is integrated with the warm water circuit. The second stage requires low temperature water.

Heat exchanger - lube oil to warm water The heat recovery is done by a mounted heat exchanger which is integrated in the warm water circuit.

Heat exchanger - engine jacket water to warm water The plate-type heat exchanger is mounted to the module base frame, complete with interconnecting pipework, for recovery of engine jacket water.

31.01.2017/HT(P (5015) TS JMS 616 F70 480V 31 January 2017 Cortus Energy us.docx Copyright ©(rg) 25/43

1.05 Gas train (special gas)

Pre-assembled trains, delivered loose, for installation into gas pipework to the module. The gas train installation in the engine room must be designed so that the train is not cooled by the engine room ventilation as this can lead to the formation of condensate (insulation may be required). Heating of the gas train must be installed. Additional heating in the customers gas piping is recommended. Suitable plastic materials must be used in the gas train.

Consisting of:  Gas filter cartridge unit  Fine cartridge filter in welded configuration, width DN150/PN16, built on supports, with emptying connection DN50/PN16  Total height ca: 2000mm (required height for filter change ca 2600mm)  Filtermaterial: Polphyenylensulfide  Dust protection grade: > 2um 92%, 99% >5ym

Attention: the filter installed in the gas train is only a safety filter. The particle content in the fuel gas can lead to a quick pressure rise over the safety filter. Therefore correspondingly sized filters should be installed on site (not GEJ scope of supply) if required.

 Each of the gas trains consist of the following items:  Manual ball valve  Gas admission pressure regulator  Pressure gauge with push button valve, 0-500 mbar (0-7,25 psi)  Solenoid valves  Gas pressure switch (min.)  Leakage detector  Flame Arrestor  Gas pressure regulator  TEC JET  The gas train must be fitted with a heating system in order to avoid condensate formation -> customer scope of supply

The gas train complies with DIN - DVGW regulations and are equipped with CSA rated components, however final CSA approval of the gas trains will be at site by a site inspector. Maximum distance from main gas train outlet to gas entry on engine, including flexible connections, is 2 m (78 in).

31.01.2017/HT(P (5015) TS JMS 616 F70 480V 31 January 2017 Cortus Energy us.docx Copyright ©(rg) 26/43

1.05.01 Nitrogen flushing

For gases with a CO content greater than 5%vol Nitrogen flushing is required for safety reasons.

Function: After every engine stop or failed start (from a certain speed upwards) ,1.2 m3 of nitrogen will be injected directly into the gas train after the solenoid valves (flow direction engine) The engine sucks and/or pushes the nitrogen through the gas train, the engine and into the exhaust system, thus minimising the risk of CO residual gas in the engine. Before maintenance on the filter elements of the gas train, the appropriate section of the gas train must be manually flushed.

For the cartridge filter exchange it is possible to flush the filter manually

Scope of supply:

 N2 pressure reduction station  Ball valves  Solenoid valves  Software for the automatic flushing run  The N2 supply of 4 bar must be prepared on site

Flushing of the gas piping to the gas train is in the customers scope of supply.

1.07 Painting

 Quality: Oil resistant prime layer Synthetic resin varnish finishing coat

 Color: Engine: RAL 6018 (green) Base frame: RAL 6018 (green) Generator: RAL 6018 (green) Module interface panel: RAL 7035 (light grey) Control panel: RAL 7035 (light grey)

31.01.2017/HT(P (5015) TS JMS 616 F70 480V 31 January 2017 Cortus Energy us.docx Copyright ©(rg) 27/43

1.11 Engine generator control panel – DIA.NE XT

Dimensions:  Height: 87 in (2200 mm) [including 8 in (200 mm) pedestal]  Width: 40 in (1000 mm)  Depth: 24 in (600 mm)

Control supply voltage from starter and control panel batteries: 24V DC

Supply of power for auxiliaries from auxiliary power panel: 3 x 480/277 V, 60 Hz, xx A

Consisting of: DIA.NE XT 3 (Dialog Network new generation) motor management system

System elements visualization with central engine and module control

1) Visualization: Industrial control with 10.4“QVGA TFT color graphics display and 8 function keys. 10-key numeric keyboard for parameter input. Keys for START, STOP, Generator circuit breaker OPEN, Generator circuit breaker CLOSED/SELECTED, display selection keys and special functions. Interfaces:  Ethernet (twisted pair) for connection to DIA.NE WIN server  CAN-Bus: bus connection to the intelligent sensors and actuators  Data bus connection to the control in- and outputs Interfacing with the customer’s plant management according to GE JENBACHER list of options Protection class: IP 65 (front) Dimensions: W x H x D = approx. 8,4 x 10 x 3,75 in (212 x 255 x 95 mm)

A clear and functional graphic compilation of measured values is displayed on the screen. User prompts are by means of direct-acting display selection keys and function keys.

Main displays:  Electrical schematic  Oil and hydraulic schematic  Gas data  Engine controllers  Cylinder data  Exhaust gas data  Auxilliaries controllers  Spare screen for customer specific purposes  System display screens  Parameter manager  User setting  Alarm management

31.01.2017/HT(P (5015) TS JMS 616 F70 480V 31 January 2017 Cortus Energy us.docx Copyright ©(rg) 28/43

Recipe handling: Setting, display and storage of all module parameters

Alarm management: Efficient diagnostic instrumentation listing all active fault messages both tabular and chronologically, with the recorded time.

2) Central engine and module control: A real-time, modular industrial control system which handles all jobs for module and engine-side sequencing control (start preparation, start, stop, synchronizing, after-cooling, control of auxiliaries), as well as all control functions.

Control functions:  Speed control in no-load and isolated operation  Power output control in parallel operation system; job-specific with respect to internal and external set point values.  LEANOX control system for control of boost pressure; dependent upon the generator terminal power and the mixture temperature via the engine-driven air-gas mixer  Knocking control: adjustment of the ignition point, power output and (insofar as is locally possible) the mixture temperature in the event of detection of knocking.  Load sharing between several modules in isolated operation  Linear reduction of power output in the event of excessive mixture temperature and ignition failures

 Interface relays as per the interface list  Multi-transducer, to record the following electrically measured variables of the generator:  Phase current (with slave pointer)  Neutral conductor current  Voltages Ph/Ph and Ph/N  Active power (with slave pointer)  Reactive power  Apparent power  Power factor  Frequency An additional 0 - 20 mA output is produced for active power, as well as a pulse output for active power demand.

The following alternator supervisions are integrated with the multi-transducer (max. 8 functions simultaneous):  Overload/short-circuit [51], [50]  Over voltage [59]  Undervoltage [27]  Asymmetric voltage [64], [59N]  Unbalance current [46]  Failure Exitation [40]  Overfrequency [81>]  Underfrequency [81<]

31.01.2017/HT(P (5015) TS JMS 616 F70 480V 31 January 2017 Cortus Energy us.docx Copyright ©(rg) 29/43

 Lockable operation mode selector switch positions:  "OFF" No operation is possible, running set will shut down;  "MANUAL" Manual operation using (start, stop) is possible, unit is not available for fully automatic operation.  "AUTOMATIC" Fully automatic operation, according to remote demand signal:  Automatic start Fully automatic operation at full load  Stop with cooling down run for 1 minute Continuous operation of auxiliaries for 5 minutes after engine shutdown  Demand switch with the positions:  Demand OFF  Demand ON  Remote demand  Supply disconnecting device for auxiliaries with lockable circuit breaker

Shut-down functions with display:  Low lube oil pressure  Low lube oil level  High lube oil level  High lube oil temperature  Low jacket water pressure  High jacket water pressure  High jacket water temperature  Overspeed  Emergency stop/safety loop  Gas train failure  Start failure  Stop failure  Engine start blocked  Engine operation blocked  Misfiring  High mixture temperature  Measuring signal failure  Overload/output signal failure  Generator overload/short circuit  Generator over/undervoltage  Generator over/underfrequency  Generator asymmetric voltage  Generator unbalanced load  Generator reverse power  High generator winding temperature  Synchronising failure  Knocking failure

31.01.2017/HT(P (5015) TS JMS 616 F70 480V 31 January 2017 Cortus Energy us.docx Copyright ©(rg) 30/43

Warning functions with display:  Low jacket water temperature  CPU battery failure

Operational functions with display:  Ready to start  Operation (engine running)  Generator circuit breaker "CLOSED"

Remote signals: (volt free contacts) 1NO = 1 normally open 1NC = 1 normally closed 1 COC = 1 change over contact

 Ready for automatic start (to Master control) 1NO  Operation (engine runs) 1NO  Collective signal "shut down" 1NC  Collective signal "warning" 1NC

External (by others) provided command/status signals:  Engine demand (from Master control) 1NO

Single synchronizing Automatic With voltage balance

For automatic synchronizing of the module with the generator circuit breaker to the grid by PLC- technology, integrated within the module control panel.

Consisting of:  Lockable synchronizing mode selector switch, with positions "MANUAL - 0FF - AUTOMATIC"  AUTOMATIC: Automatic module synchronization, after synchronizing release from the control panel  MANUAL: Manual initiation of synchronizing by push button. Speed adjustment and closing of the circuit breaker is automatically controlled via microprocessor  OFF: Synchronization is disabled  Additional PLC hardware for the fully automatic synchronizing of each module, and monitoring of the "CIRCUIT BREAKER CLOSED" signal. Logic for monitoring of:  Non-logic breaker positions  Switch ”ON” trouble  Switch ”OFF” trouble

31.01.2017/HT(P (5015) TS JMS 616 F70 480V 31 January 2017 Cortus Energy us.docx Copyright ©(rg) 31/43

 Automatic synchronizing device to control the electronic speed governor adjustment, double voltmeter, double frequency meter and synchro-scope  Automatic voltage balancing  Luminous push button “GENERATOR CIRCUIT BREAKER OPEN / SELECT”  To indicate synchronizing mode  To indicate “Generator circuit breaker closed”  For manual synchronizing selection with the synchronizing mode selector switch in the MANUAL position  For manual closing of the generator circuit breaker to the voltage free bus bar (first connection) with synchronizing mode selector switch in the MANUAL position  Luminous push button “GENERATOR CIRCUIT BREAKER OPEN”  To indicate “Generator circuit breaker open”  To manually open the generator circuit breaker  Control switch  Required relays for control and monitoring  Voltage relay for monitoring of bus-bar voltage (only for island operation)

Operational indications for:  Generator circuit breaker CLOSED  Generator circuit breaker OPEN

Fault indications for:  Generator circuit breaker return signal fault  Generator circuit breaker closing fault  Generator circuit breaker opening fault

Remote signals (Volt free contacts)  Generator circuit breaker CLOSED 1 NO

The following reference and status signals must be provided by the switchgear supplier: Generator circuit breaker CLOSED 1 NO Generator circuit breaker OPEN 1 NO Generator circuit breaker READY TO CLOSE 1 NO Mains circuit breaker CLOSED 1 NO Mains circuit breaker OPEN 1 NO

 Mains voltage 3 x 480 V or 3x 110V/v3 – other measurement voltages available on request  Bus bar voltage 3 x 480 V or 3x 110V/v3 – other measurement voltages available on request  Generator voltage 3 x 480 V or 3x 110V/v3 – other measurement voltages available on request Voltage transformers in star point with minimum 50VA, Class 1

The following volt free interface-signals will be provided by GE Jenbacher to be incorporated in switchgear:  CLOSING/OPENING command for generator circuit breaker (permanent contact) 1 NO + 1 NC  Signal for circuit breaker undervoltage trip 1 NO

31.01.2017/HT(P (5015) TS JMS 616 F70 480V 31 January 2017 Cortus Energy us.docx Copyright ©(rg) 32/43

1.11.02 Remote information via Modbus RTU

Data transfer from the Jenbacher-engine control to customer's plant management system will be via a MODBUS-RTU-network (RS 485). The Jenbacher module control panel works as a SLAVE. The data transmission by the customer's MASTER shall be cyclical.

Transmitted data: Individual failure information, plant operating information, measuring values for generator power, oil pressure, oil temperature, jacket water pressure, jacket water temperature, cylinder and average exhaust gas temperatures.

GE Jenbacher limit of delivery: Interface connector at the PLC in the engine control panel.

1.11.03 Remote Data-Transfer with DIA.NE XT - HERMES

General HERMES is the remote data transfer solution for DIA.NE XT. HERMES is available via three connection methods and two applications.

Connections methods

1.) Modem Site - Customer connection via a Modem (analogue, ISDN, GSM).

Scope of supply  DIA.NE WIN – Server (Industrial PC without display, keyboard or mouse, built into the control panel, including operating system)  Modem (analogue, ISDN, GSM)

Customer Requirements  Modem (analogue, ISDN, GSM) in the customers PC  Public telephone connection with connection port for the DIA.NE WIN – Server (in the control panel) including over-voltage protection corresponding to the local telecommunication regulations.  Public telephone connection with connection port for the customer’s PC corresponding to the local telecommunication regulations.

2.) LAN Site - Customer connection via a local network.

Scope of supply  DIA.NE WIN – Server (Industrial PC without display, keyboard or mouse, built into the control panel, including operating system)  Ethernet – Network card (10/100 BASE T)

31.01.2017/HT(P (5015) TS JMS 616 F70 480V 31 January 2017 Cortus Energy us.docx Copyright ©(rg) 33/43

Customer Requirements  Ethernet – Network card (10/100 BASE T)  Ethernet – Cabling between the DIA.NE WIN – Server the customers PC.

3.) Internet Site – Customer connection via secure Internet access See comments under Technical instruction TI 2300 - 0006

Scope of Supply  DIA.NE WIN – Server (Industrial PC without display, keyboard or mouse, built into the control panel, including operating system)  Ethernet–Network card (10/100 BASE T)  Firewall–Appliance with connection feasibility to a customer network with a maximum of 10 Hosts (Installation and service by GE Jenbacher; during warranty period included, afterwards as a service package with costs) (built into the control panel)  Feature – service package (access monitoring, clock synchronization for server)

Customer Requirements  Broad band Internet access with at least two official IP addresses. Connection feasibility for the Firewall–Appliance to the Internet–Router via Ethernet (RJ45 Connector, Network Address Translation (NAT) is not permitted)

Applications

1.) DIA.NE WIN DIA.NE WIN is the Windows based „man-machine interface“ for GE Jenbacher gas engines. The system offers extensive facilities for commissioning, monitoring, servicing and analysis of the site. The option DIA.NE WIN extends the visualization of DIA.NE XT with respect to user friendliness, historical analysis and remote use. Several service stations can be independently operated in parallel. The system consists of a central PC (DIA.NE WIN – Server) which is built in to the control panel and one or more service stations (DIA.NE WIN – Clients). The system runs on a Microsoft Internet Explorer platform.

Function Service and monitoring, trend analysis, alarm management, parameter management, long-term data analysis, multi-user system, remote control, OPC (OLE for process control), print and export functions, operating data protocols, available in several languages.

Scope of supply  Software package DIA.NE WIN on the DIA.NE WIN – Server  DIA.NE WIN – Client License (Right to access of the user to the server on site) Customer requirements  Standard PC with keyboard, mouse and monitor (min. resolution 1024*768)  V supply for the customers’ PC  Operating system Windows 98, Windows NT, Windows 2000 or Windows XP  Microsoft Internet Explorer (min. Version 6.0) including Java support

31.01.2017/HT(P (5015) TS JMS 616 F70 480V 31 January 2017 Cortus Energy us.docx Copyright ©(rg) 34/43

2.) DIA.NE RMC DIA.NE RMC (Remote Message Control) is the automatic alarm system for DIA.NE XT. DIA.NE RMC can fully automatically transmit essential operational information from the DIA.NE XT Alarm Management to a remote station. The messages can be forwarded to an e-mail address, fax machine or mobile phone (SMS). Furthermore the stored messages can be visualized at the remote station. The system consists of a central PC (DIA.NE WIN – Server) which is built into the control panel and one or more customer remote stations.

Function Automatically transfer of messages to the customer via email, fax or SMS. Display and printing of the messages (also distributed via LAN). Automatically and manually transfer of messages, trend data and operating data protocols.

Scope of supply  Software package DIA.NE message on the DIA.NE WIN – Server  Software package DIA.NE control and DIA.NE report on the remote station Only for connection method “Internet”:  Firewall–Appliance for customer computer with connection feasibility to a customer network with a maximum of 10 Hosts (Installation and service by GE Jenbacher; during warranty period included, afterwards as a service package with costs)

Customer requirements  Standard PC with keyboard, mouse and monitor (min. resolution 1024*768)  V supply for the customers’ computer.  Operating system Windows 2000 (Professional and Server), Windows XP Professional or Windows Server 2003.  Internet connection (provider account) for the case that messages from the RMC should be forwarded to an email receiver (incl. SMS for mobiles and pagers). (Mobiles and pagers to be provided by the customer).  Customer fax software for message forwarding via fax Only for connection method “Internet”:  Broad band Internet access with at least two official IP addresses. Connection feasibility for the Firewall–Appliance to the Internet–Router via Ethernet (RJ45 Connector, Network Address Translation (NAT) is not permitted)

31.01.2017/HT(P (5015) TS JMS 616 F70 480V 31 January 2017 Cortus Energy us.docx Copyright ©(rg) 35/43

1.20.03 Starting system

Starter battery (is not included in GE Jenbacher scope): 4 piece 12 V Pb battery, 200 Ah (according to DIN 72311), complete with cover plate, terminals and acid tester.

Battery voltage monitoring: Monitoring by an under voltage relay.

Battery charging equipment: Capable for charging the starter battery with I/U characteristic and for the supply of all connected D.C. consumers. Charging device is mounted inside of the module interface panel or module control panel.

 General data:  Power supply 3 x 320 - 550 V, 47 - 63 Hz  max. power consumption 2120 W  Nominal D.C. voltage 24 V(+/-1%)  Voltage setting range 24V to 28,8V ( adjustable)  Nominal current (max.) 2 x 40 A  Dimensions ca. 10 x 5 x 5 inch (240 x 125 x 125 mm)  Degree of protection IP20 to IEC 529  Operating temperature 32 °F – 140 °F (0 °C - 60 °C)  Protection class 1  Humidity class 3K3, no condensation.  Natural air convection  Standards EN60950,EN50178 UL/cUL (UL508/CSA 22.2) Signalling: Green Led: Output voltage > 20,5V Yellow Led: Overload, Output Voltage < 20,5V Red Led: shutdown

Control accumulator:  Pb battery 24 VDC/18 Ah

1.20.05 Electric jacket water preheating

Installed in the jacket water cooling circuit, consisting of:  Heating elements  Water circulating pump

The jacket water temperature of a stopped engine is maintained between 133 °F (56°C) and 140°F (60°C), to allow for immediate loading after engine start.

31.01.2017/HT(P (5015) TS JMS 616 F70 480V 31 January 2017 Cortus Energy us.docx Copyright ©(rg) 36/43

1.20.08 Flexible connections

Following flexible connections per module are included in the GE Jenbacher -scope of supply:

No.Connection Unit Dimension Material

2 Warm water in-/outlet in/lbs 4''/145 Stainless steel 1 Exhaust gas outlet in/lbs 25''/145 Stainless steel 1 Fuel gas inlet in/lbs 6''/232 Stainless steel 2 Intercooler in-/outlet in/lbs 2½''/ Stainless steel 2 Lube oil connection in 1.1 Hose

Seals and flanges for all flexible connections are included.

2.00 Electrical equipment

Totally enclosed floor mounted sheet steel cubicle with front door wired to terminals. Ready to operate, with cable entry at bottom. Naturally ventilated.

Protection: IP 42 external, NEMA 12 IP 20 internal (protection against direct contact with live parts)

Design according to EN 61439-2 / IEC 61439-2 and ISO 8528-4. Ambient temperature 41 - 104 °F (5 - 40 °C), 70 % Relative humidity

Standard painting: Panel: RAL 7035 Pedestal: RAL 7020

2.02 Grid monitoring device

Standard without static Grid - 60Hz alternator

Function: The Grid monitoring device will provide for immediate disconnection of the generator from the grid in case of grid failures.

Consisting of:  High/low voltage monitoring  High/low frequency monitoring  Specially adjustable independent time for voltage and frequency monitoring  Vector jump monitoring or df/dt monitoring for immediate disconnection of the generator from the grid for example at short interruptions  Indication of all reference dimensions for normal operation and at the case of disturbance over LCD and LED

31.01.2017/HT(P (5015) TS JMS 616 F70 480V 31 January 2017 Cortus Energy us.docx Copyright ©(rg) 37/43

 Adjusting authority through password protection against adjusting of strangers

Scope of supply: Digital grid protection relay with storage of defect data, indication of reference dimensions as well as monitoring by itself.

Grid protection values:

Parameter Parameter limit Max time delay[s] Comments

59-61Hz Do work normal

f<[ANSI 81U] 59Hz 0,5 Load reduction with 10%/HZ below 59Hz!

f<<[ANSI 81U] 58.5Hz 0,1

f>[ANSI 81O] 61,5Hz 0,1 Load reduction with 30%/HZ above 61Hz!

U<[ANSI 27] 90% 1 Load reduction with 1%P /%U below 95%

U<<[ANSI 27] 80% 0,2 Load reduction with 1%P /%U below 95%

U>[ANSI 59] 110% 30 Load reduction with 1%P /%U above 105%

U>>[ANSI 59] 115% 0,2 Load reduction with 1% P/%U above 105%

Df/dt [ANSI 81R] 2Hz/s, 5 Periods Cos phi range:

Or Or 0,8ind (overexcited)

Vector shift 8° -3pol - 1

[ANSI 78]

31.01.2017/HT(P (5015) TS JMS 616 F70 480V 31 January 2017 Cortus Energy us.docx Copyright ©(rg) 38/43

3.03 Exhaust Gas Pressure Relief Valve

When the risk of backfires in the exhaust gas system exists (Fuel gas with H2 content) an single exhaust gas pressure relief valve (Hörbiger valve) must be installed. The exhaust gas can be released to atmosphere in case of a backfire. The pressure relief valve should be installed as close to the engine exhaust exit as possible. Scope of delivery:  1 piece Exhaust gas pressure relief valve (delivered loose)

3.70 Control Strategy and Options

Grid Parallel with KW Control – Real Power Load Control of the Generator set will be either via a 4-20mA input from the customer representing a unit KW load setpoint or a KW load setpoint entered on the Diane XT3 screen. Upon breaker closure, the unit will ramp to the setpoint at a maximum rate of (Rated Unit KW) / 180 seconds.

31.01.2017/HT(P (5015) TS JMS 616 F70 480V 31 January 2017 Cortus Energy us.docx Copyright ©(rg) 39/43

4.00 Delivery, installation and commissioning

4.01 Carriage According to contract.

4.02 Unloading Unloading, moving of equipment to point of installation, mounting and adjustment of delivered equipment on intended foundations is not included in GE Jenbacher scope of supply.

4.03 Assembly and installation Assembly and installation of all GE Jenbacher -components is not included in GE Jenbacher scope of supply.

4.04 Storage The customer is responsible for secure and appropriate storage of all delivered equipment.

4.05 Start-up and commissioning Start-up and commissioning with the GE Jenbacher start-up and commissioning checklist is not included. Plants with island operation require internet connection.

4.06 Trial run After start-up and commissioning, the plant will be tested in an 8-hour trial run. The operating personnel will be introduced simultaneously to basic operating procedures. Is not included in GE Jenbacher scope of supply.

4.07 Emission measurement (exhaust gas analyser) Emission measurement by GE Jenbacher personnel, to verify that the guaranteed toxic agent emissions have been achieved (costs for measurement by an independent agency will be an extra charge).

31.01.2017/HT(P (5015) TS JMS 616 F70 480V 31 January 2017 Cortus Energy us.docx Copyright ©(rg) 40/43

5.01 Limits of delivery

Electrical  Module:  At terminals of module interface panel  At terminals of generator terminal box (screwed glands to be provided locally)  Module control panel: At terminal strips  Auxiliaries: At terminals of equipment which is supplied separately

Warm water  At inlet and outlet flanges on module  At inlet and outlet flanges of the exhaust gas heat recovery system

Low temperature water At inlet and outlet flanges at module

Exhaust gas  At the exhaust gas exit of the engine  At inlet and outlet flanges of the exhaust gas heat recovery system

Combustion air The air filters are set mounted

Fuel gas  At inlet and outlet flanges of gas train  At inlet flange of gas pipework on module  At outlet flange of the pre-chamber gas train  At inlet flange of pre-chamber gas pipework on module  At connection for boost pressure compensation on module  At connection for boost pressure compensation on gas pressure regulator of the pre-chamber gas train

Lube oil At lube oil connections on module

Draining connections and pressure relief At module

Condensate At condensate drain on exhaust gas heat exchanger

Insulation Insulation of heat exchangers and pipe work is not included in our scope of supply and must be provided locally.

31.01.2017/HT(P (5015) TS JMS 616 F70 480V 31 January 2017 Cortus Energy us.docx Copyright ©(rg) 41/43

First filling The first filling of the plant, (lube oil, engine jacket water, anti-freeze, anti-corrosive agent, battery acid) is not included in our scope of supply.

The composition and quality of the used consumables are to be strictly monitored in accordance with the "Technical Instructions" of GE JENBACHER.

Suitable bellows and flexible connections must be provided locally for all connections. Cables from the module must be flexible.

5.02 Factory tests and inspections

The individual module components shall undergo the following tests and inspections:

5.02.01 Engine tests Carried out as combined Engine- and Module test according to DIN ISO 3046 at GE Jenbacher test bench. The following tests are made at 100%, 75% and 50% load, and the results are reported in a test certificate:  Engine output  Fuel consumption  Jacket water temperatures  Lube oil pressure  Lube oil temperatures  Boost pressure  Exhaust gas temperatures, for each cylinder

5.02.02 Generator tests Carried out on the premises of the generator supplier.

5.02.03 Module tests The engine will be tested with (methane number 94). The performance data achieved at the test bench may therefore vary from the data as defined in the technical specification due to differences in fuel gas quality. Carried out as combined Engine- and Module test commonly with module control panel at GE Jenbacher test bench, according to ISO 8528, DIN 6280. The following tests are made and the results are reported in a test certificate: Visual inspection of scope of supply per specifications.  Functional tests per technical specification of control system.  Starting in manual and automatic mode of operation  Power control in manual and automatic mode of operation  Function of all safety systems on module  Measurements at 100%, 75% and 50% load:  Frequency  Voltage  Current  Generator output

31.01.2017/HT(P (5015) TS JMS 616 F70 480V 31 January 2017 Cortus Energy us.docx Copyright ©(rg) 42/43

 Power factor  Fuel consumption  Lube oil pressure  Jacket water temperature  Boost pressure  Mixture temperature  Exhaust emission (NOx)

The module test for operating frequenzy 50 Hz and 6,3-6,6kV / 10,5kV-11kV will be carried out with the original generator, except it is not possible because of the delivery date. Then a test generator will be used for the module test. To prove characteristics of the above components, which are not tested on the test bench by GE JENBACHER, the manufacturers’ certificate will be provided.

5.03 Documentation

Preliminary documentation 60 days after receipt of a technically and commercially clarified order:  Module drawing 1)  Technical diagram 1)  Drawing of control panel 3)  List of electrical interfaces 2)  Technical specification of control system 2)  Technical drawing auxiliaries (if included in GE Jenbacher-limit of delivery) 1)

At delivery:  Wiring diagrams 3)  Cable list 3)

At start-up and commissioning (or on clients request):  Operating and maintenance manual 4)  Spare parts manual 4)  Operation report log 4)

31.01.2017/HT(P (5015) TS JMS 616 F70 480V 31 January 2017 Cortus Energy us.docx Copyright ©(rg) 43/43

APPENDIX B

CalEEMOD Modeling Results

CalEEMod Version: CalEEMod.2016.3.1 Page 1 of 31 Date: 10/22/2017 7:10 PM

Mariposa BioMass - Mariposa County APCD Air District, Winter

Mariposa BioMass Mariposa County APCD Air District, Winter

1.0 Project Characteristics

1.1 Land Usage

Land Uses Size Metric Lot Acreage Floor Surface Area Population

General Light Industry 15.00 1000sqft 0.34 15,000.00 0

Unrefrigerated Warehouse-No Rail 8.60 1000sqft 0.20 8,600.00 0

Other Asphalt Surfaces 31.10 1000sqft 0.71 31,100.00 0

Parking Lot 5.00 Space 0.05 2,000.00 0

1.2 Other Project Characteristics

Urbanization Urban Wind Speed (m/s) 2.2 Precipitation Freq (Days) 58

Climate Zone 1 Operational Year 2020

Utility Company Pacific Gas & Electric Company

CO2 Intensity 641.35 CH4 Intensity 0.029 N2O Intensity 0.006 (lb/MWhr) (lb/MWhr) (lb/MWhr)

1.3 User Entered Comments & Non-Default Data CalEEMod Version: CalEEMod.2016.3.1 Page 2 of 31 Date: 10/22/2017 7:10 PM

Mariposa BioMass - Mariposa County APCD Air District, Winter

Project Characteristics - CEC Climate Zone = Mariposa, Mariposa County. Start of Construction Date = Beginning of Site Prep. Land Use - General Light Indsutry Area = 1/3 of Project Area (46,100 ft2) Construction Phase - Total Number of Working Days will be less than CalEEMOD Projected Default based upon date range. Off-road Equipment - Dumper Truck = Off-Highway Truck (total 2 hours onsite) Off-road Equipment - Dumper Truck = Off-Highway Truck (2 hours onsite) Off-road Equipment - Dumper Truck = Off-Highway Truck (2 hours onsite) Off-road Equipment - Material Handling Crane = 10hr/day. Hydraulic Crane = 12hr/day. Off-road Equipment - Asphalt Truck = Off-Highway Truck (8 hours onsite total) Grading - Distrubance Area from Data Request (2.4 acres). Import material = Net Fill of 1,036 yd3. Trips and VMT - Values from Data Request (Dated 10/13/2017) Vehicle Trips - Other asphalt surface trip = ash removal. Informaiton from Data Request (dated 10/13/2017). Chip trucks and dump trucks combined for a value of 13. Area Coating - Energy Use - Solid Waste - biochar from the bioenergy facility will be sold as a part of the process and therefore is not considered waste. Operational Off-Road Equipment - Equipment Selection from similar project operations. Stationary Sources - User Defined - Stationary Sources - Process Boilers -

Table Name Column Name Default Value New Value

tblArchitecturalCoating EF_Parking 250.00 0.00

tblArchitecturalCoating PhaseName Architectural Coating Paving

tblAreaMitigation UseLowVOCPaintParkingValue 0 250

tblConstructionPhase NumDays 10.00 43.00

tblConstructionPhase NumDays 200.00 79.00

tblConstructionPhase NumDays 4.00 44.00

tblConstructionPhase NumDays 2.00 107.00

tblConstructionPhase NumDaysWeek 5.00 6.00 CalEEMod Version: CalEEMod.2016.3.1 Page 3 of 31 Date: 10/22/2017 7:10 PM

Mariposa BioMass - Mariposa County APCD Air District, Winter

tblConstructionPhase PhaseEndDate 10/10/2019 7/31/2019

tblConstructionPhase PhaseEndDate 9/12/2019 5/31/2019

tblConstructionPhase PhaseEndDate 12/6/2018 1/1/2019

tblConstructionPhase PhaseEndDate 11/30/2018 3/29/2019

tblConstructionPhase PhaseStartDate 9/27/2019 6/1/2019

tblConstructionPhase PhaseStartDate 12/7/2018 3/1/2019

tblConstructionPhase PhaseStartDate 12/1/2018 11/1/2018

tblConstructionPhase PhaseStartDate 11/29/2018 11/1/2018

tblGrading AcresOfGrading 1.50 2.40

tblGrading AcresOfGrading 1.00 2.40

tblGrading MaterialImported 0.00 1,036.00

tblOffRoadEquipment OffRoadEquipmentType Excavators

tblOffRoadEquipment OffRoadEquipmentType Welders

tblOffRoadEquipment OffRoadEquipmentType Rubber Tired Loaders

tblOffRoadEquipment OffRoadEquipmentType Plate Compactors

tblOffRoadEquipment OffRoadEquipmentType Off-Highway Trucks

tblOffRoadEquipment OffRoadEquipmentType Rubber Tired Loaders

tblOffRoadEquipment OffRoadEquipmentType Excavators

tblOffRoadEquipment OffRoadEquipmentType Generator Sets

tblOffRoadEquipment OffRoadEquipmentType Cement and Mortar Mixers

tblOffRoadEquipment OffRoadEquipmentType Pavers

tblOffRoadEquipment OffRoadEquipmentType Excavators

tblOffRoadEquipment OffRoadEquipmentType Cranes

tblOffRoadEquipment OffRoadEquipmentType Paving Equipment

tblOffRoadEquipment OffRoadEquipmentType Off-Highway Trucks

tblOffRoadEquipment OffRoadEquipmentType Rollers

tblOffRoadEquipment OffRoadEquipmentType Cranes CalEEMod Version: CalEEMod.2016.3.1 Page 4 of 31 Date: 10/22/2017 7:10 PM

Mariposa BioMass - Mariposa County APCD Air District, Winter

tblOffRoadEquipment OffRoadEquipmentType Rubber Tired Loaders

tblOffRoadEquipment OffRoadEquipmentType Graders

tblOffRoadEquipment OffRoadEquipmentType Off-Highway Trucks

tblOffRoadEquipment OffRoadEquipmentUnitAmount 0.00 1.00

tblOffRoadEquipment OffRoadEquipmentUnitAmount 0.00 1.00

tblOffRoadEquipment OffRoadEquipmentUnitAmount 0.00 1.00

tblOffRoadEquipment OffRoadEquipmentUnitAmount 0.00 1.00

tblOffRoadEquipment OffRoadEquipmentUnitAmount 0.00 1.00

tblOffRoadEquipment OffRoadEquipmentUnitAmount 0.00 1.00

tblOffRoadEquipment OffRoadEquipmentUnitAmount 0.00 1.00

tblOffRoadEquipment OffRoadEquipmentUnitAmount 0.00 1.00

tblOffRoadEquipment OffRoadEquipmentUnitAmount 0.00 1.00

tblOffRoadEquipment OffRoadEquipmentUnitAmount 0.00 1.00

tblOffRoadEquipment OffRoadEquipmentUnitAmount 0.00 1.00

tblOffRoadEquipment OffRoadEquipmentUnitAmount 0.00 1.00

tblOffRoadEquipment OffRoadEquipmentUnitAmount 0.00 1.00

tblOffRoadEquipment PhaseName Grading

tblOffRoadEquipment PhaseName Building Construction

tblOffRoadEquipment PhaseName Paving

tblOffRoadEquipment PhaseName Paving

tblOffRoadEquipment PhaseName Paving

tblOffRoadEquipment PhaseName Site Preparation

tblOffRoadEquipment PhaseName Building Construction

tblOffRoadEquipment PhaseName Building Construction

tblOffRoadEquipment PhaseName Paving

tblOffRoadEquipment PhaseName Paving

tblOffRoadEquipment PhaseName Site Preparation CalEEMod Version: CalEEMod.2016.3.1 Page 5 of 31 Date: 10/22/2017 7:10 PM

Mariposa BioMass - Mariposa County APCD Air District, Winter

tblOffRoadEquipment PhaseName Building Construction

tblOffRoadEquipment PhaseName Paving

tblOffRoadEquipment PhaseName Site Preparation

tblOffRoadEquipment PhaseName Paving

tblOffRoadEquipment PhaseName Building Construction

tblOffRoadEquipment PhaseName Grading

tblOffRoadEquipment PhaseName Grading

tblOffRoadEquipment PhaseName Grading

tblOnRoadDust PhaseName Architectural Coating Paving

tblOperationalOffRoadEquipment OperDaysPerYear 260.00 310.00

tblOperationalOffRoadEquipment OperDaysPerYear 260.00 310.00

tblOperationalOffRoadEquipment OperHoursPerDay 8.00 24.00

tblOperationalOffRoadEquipment OperHoursPerDay 8.00 24.00

tblOperationalOffRoadEquipment OperOffRoadEquipmentNumber 0.00 1.00

tblOperationalOffRoadEquipment OperOffRoadEquipmentNumber 0.00 1.00

tblProjectCharacteristics OperationalYear 2018 2020

tblSolidWaste SolidWasteGenerationRate 18.60 0.00

tblTripsAndVMT HaulingTripLength 20.00 30.00

tblTripsAndVMT HaulingTripLength 20.00 30.00

tblTripsAndVMT HaulingTripLength 20.00 30.00

tblTripsAndVMT HaulingTripLength 20.00 45.00

tblTripsAndVMT HaulingTripNumber 0.00 80.00

tblTripsAndVMT HaulingTripNumber 0.00 80.00

tblTripsAndVMT HaulingTripNumber 0.00 50.00

tblTripsAndVMT HaulingTripNumber 0.00 25.00

tblTripsAndVMT PhaseName Architectural Coating Paving

tblTripsAndVMT VendorTripLength 7.30 30.00 CalEEMod Version: CalEEMod.2016.3.1 Page 6 of 31 Date: 10/22/2017 7:10 PM

Mariposa BioMass - Mariposa County APCD Air District, Winter

tblTripsAndVMT VendorTripLength 7.30 30.00

tblTripsAndVMT VendorTripLength 7.30 30.00

tblTripsAndVMT VendorTripLength 7.30 30.00

tblTripsAndVMT VendorTripNumber 0.00 5.00

tblTripsAndVMT VendorTripNumber 0.00 5.00

tblTripsAndVMT VendorTripNumber 9.00 20.00

tblTripsAndVMT VendorTripNumber 0.00 2.00

tblTripsAndVMT WorkerTripLength 10.80 30.00

tblTripsAndVMT WorkerTripLength 10.80 30.00

tblTripsAndVMT WorkerTripLength 10.80 30.00

tblTripsAndVMT WorkerTripLength 10.80 30.00

tblTripsAndVMT WorkerTripNumber 8.00 55.00

tblTripsAndVMT WorkerTripNumber 8.00 55.00

tblTripsAndVMT WorkerTripNumber 24.00 294.00

tblTripsAndVMT WorkerTripNumber 13.00 0.00

tblTripsAndVMT WorkerTripNumber 5.00 24.00

tblVehicleTrips CC_TL 7.30 0.00

tblVehicleTrips CC_TL 7.30 2.00

tblVehicleTrips CC_TL 7.30 0.00

tblVehicleTrips CC_TL 7.30 25.00

tblVehicleTrips CC_TTP 28.00 0.00

tblVehicleTrips CC_TTP 0.00 100.00

tblVehicleTrips CC_TTP 0.00 100.00

tblVehicleTrips CNW_TL 7.30 0.00

tblVehicleTrips CNW_TL 7.30 0.00

tblVehicleTrips CNW_TL 7.30 0.00

tblVehicleTrips CNW_TL 7.30 0.00 CalEEMod Version: CalEEMod.2016.3.1 Page 7 of 31 Date: 10/22/2017 7:10 PM

Mariposa BioMass - Mariposa County APCD Air District, Winter

tblVehicleTrips CNW_TTP 13.00 0.00

tblVehicleTrips CNW_TTP 41.00 0.00

tblVehicleTrips CW_TL 9.50 0.00

tblVehicleTrips CW_TL 9.50 0.00

tblVehicleTrips CW_TL 9.50 0.00

tblVehicleTrips CW_TL 9.50 0.00

tblVehicleTrips CW_TTP 59.00 0.00

tblVehicleTrips CW_TTP 59.00 0.00

tblVehicleTrips DV_TP 5.00 0.00

tblVehicleTrips DV_TP 5.00 0.00

tblVehicleTrips HW_TL 0.00 30.00

tblVehicleTrips HW_TTP 0.00 100.00

tblVehicleTrips PB_TP 3.00 0.00

tblVehicleTrips PB_TP 3.00 0.00

tblVehicleTrips PR_TP 92.00 100.00

tblVehicleTrips PR_TP 0.00 100.00

tblVehicleTrips PR_TP 92.00 100.00

tblVehicleTrips ST_TR 1.32 6.00

tblVehicleTrips ST_TR 1.68 13.00

tblVehicleTrips SU_TR 0.68 6.00

tblVehicleTrips SU_TR 1.68 0.00

tblVehicleTrips WD_TR 6.97 8.00

tblVehicleTrips WD_TR 0.00 1.00

tblVehicleTrips WD_TR 1.68 13.00

2.0 Emissions Summary CalEEMod Version: CalEEMod.2016.3.1 Page 8 of 31 Date: 10/22/2017 7:10 PM

Mariposa BioMass - Mariposa County APCD Air District, Winter

2.1 Overall Construction (Maximum Daily Emission) Unmitigated Construction

ROG NOx CO SO2 Fugitive Exhaust PM10 Fugitive Exhaust PM2.5 Bio- CO2 NBio- CO2 Total CO2 CH4 N2O CO2e PM10 PM10 Total PM2.5 PM2.5 Total

Year lb/day lb/day

2018 6.7644 44.4474 43.8365 0.0834 3.4635 1.4042 4.8677 1.0562 1.2958 2.3520 0.0000 8,386.693 8,386.693 1.6720 0.0000 8,428.493 0 0 7

2019 15.7930 59.8769 99.0099 0.1597 8.8132 1.9536 10.7668 2.3759 1.8360 4.2119 0.0000 15,845.04 15,845.04 2.1907 0.0000 15,899.80 02 02 76

Maximum 15.7930 59.8769 99.0099 0.1597 8.8132 1.9536 10.7668 2.3759 1.8360 4.2119 0.0000 15,845.04 15,845.04 2.1907 0.0000 15,899.80 02 02 76

Mitigated Construction

ROG NOx CO SO2 Fugitive Exhaust PM10 Fugitive Exhaust PM2.5 Bio- CO2 NBio- CO2 Total CO2 CH4 N2O CO2e PM10 PM10 Total PM2.5 PM2.5 Total

Year lb/day lb/day

2018 6.7644 19.2329 43.8365 0.0834 3.4635 1.4042 4.8677 1.0562 1.2958 2.3520 0.0000 8,386.693 8,386.693 1.6720 0.0000 8,428.493 0 0 7

2019 15.7930 45.3419 99.0099 0.1597 8.8132 1.9536 10.7668 2.3759 1.8360 4.2119 0.0000 15,845.04 15,845.04 2.1907 0.0000 15,899.80 02 02 76

Maximum 15.7930 45.3419 99.0099 0.1597 8.8132 1.9536 10.7668 2.3759 1.8360 4.2119 0.0000 15,845.04 15,845.04 2.1907 0.0000 15,899.80 02 02 76

ROG NOx CO SO2 Fugitive Exhaust PM10 Fugitive Exhaust PM2.5 Bio- CO2 NBio-CO2 Total CO2 CH4 N20 CO2e PM10 PM10 Total PM2.5 PM2.5 Total

Percent 0.00 38.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Reduction CalEEMod Version: CalEEMod.2016.3.1 Page 9 of 31 Date: 10/22/2017 7:10 PM

Mariposa BioMass - Mariposa County APCD Air District, Winter

2.2 Overall Operational Unmitigated Operational

ROG NOx CO SO2 Fugitive Exhaust PM10 Fugitive Exhaust PM2.5 Bio- CO2 NBio- CO2 Total CO2 CH4 N2O CO2e PM10 PM10 Total PM2.5 PM2.5 Total

Category lb/day lb/day

Area 0.6735 6.0000e- 6.1300e- 0.0000 2.0000e- 2.0000e- 2.0000e- 2.0000e- 0.0131 0.0131 4.0000e- 0.0139 005 003 005 005 005 005 005

Energy 1.5600e- 0.0142 0.0120 9.0000e- 1.0800e- 1.0800e- 1.0800e- 1.0800e- 17.0669 17.0669 3.3000e- 3.1000e- 17.1683 003 005 003 003 003 003 004 004

Mobile 1.9704 9.0967 32.7421 0.0576 4.9922 0.0836 5.0758 1.3367 0.0786 1.4153 5,745.859 5,745.859 0.3928 5,755.679 1 1 6

Offroad 1.0602 10.2018 10.3699 0.0139 0.6892 0.6892 0.6341 0.6341 1,344.960 1,344.960 0.4350 1,355.835 5 5 2

Total 3.7056 19.3128 43.1300 0.0715 4.9922 0.7738 5.7661 1.3367 0.7137 2.0504 7,107.899 7,107.899 0.8282 3.1000e- 7,128.697 5 5 004 0 CalEEMod Version: CalEEMod.2016.3.1 Page 10 of 31 Date: 10/22/2017 7:10 PM

Mariposa BioMass - Mariposa County APCD Air District, Winter

2.2 Overall Operational Mitigated Operational

ROG NOx CO SO2 Fugitive Exhaust PM10 Fugitive Exhaust PM2.5 Bio- CO2 NBio- CO2 Total CO2 CH4 N2O CO2e PM10 PM10 Total PM2.5 PM2.5 Total

Category lb/day lb/day

Area 0.6735 6.0000e- 6.1300e- 0.0000 2.0000e- 2.0000e- 2.0000e- 2.0000e- 0.0131 0.0131 4.0000e- 0.0139 005 003 005 005 005 005 005

Energy 1.5600e- 0.0142 0.0120 9.0000e- 1.0800e- 1.0800e- 1.0800e- 1.0800e- 17.0669 17.0669 3.3000e- 3.1000e- 17.1683 003 005 003 003 003 003 004 004

Mobile 1.9704 9.0967 32.7421 0.0576 4.9922 0.0836 5.0758 1.3367 0.0786 1.4153 5,745.859 5,745.859 0.3928 5,755.679 1 1 6

Offroad 1.0602 10.2018 10.3699 0.0139 0.6892 0.6892 0.6341 0.6341 1,344.960 1,344.960 0.4350 1,355.835 5 5 2

Total 3.7056 19.3128 43.1300 0.0715 4.9922 0.7738 5.7661 1.3367 0.7137 2.0504 7,107.899 7,107.899 0.8282 3.1000e- 7,128.697 5 5 004 0

ROG NOx CO SO2 Fugitive Exhaust PM10 Fugitive Exhaust PM2.5 Bio- CO2 NBio-CO2 Total CO2 CH4 N20 CO2e PM10 PM10 Total PM2.5 PM2.5 Total

Percent 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Reduction

3.0 Construction Detail

Construction Phase

Phase Phase Name Phase Type Start Date End Date Num Days Num Days Phase Description Number Week

1 Site Preparation Site Preparation 11/1/2018 3/29/2019 5 107

2 Grading Grading 11/1/2018 1/1/2019 5 44

3 Building Construction Building Construction 3/1/2019 5/31/2019 6 79

4 Paving Paving 6/1/2019 7/31/2019 5 43 CalEEMod Version: CalEEMod.2016.3.1 Page 11 of 31 Date: 10/22/2017 7:10 PM

Mariposa BioMass - Mariposa County APCD Air District, Winter

Acres of Grading (Site Preparation Phase): 2.4

Acres of Grading (Grading Phase): 2.4

Acres of Paving: 0.76

Residential Indoor: 0; Residential Outdoor: 0; Non-Residential Indoor: 35,400; Non-Residential Outdoor: 11,800; Striped Parking Area: 1,986 (Architectural Coating – sqft)

OffRoad Equipment

Phase Name Offroad Equipment Type Amount Usage Hours Horse Power Load Factor

Grading Excavators 1 10.00 158 0.38

Paving Rubber Tired Loaders 1 10.00 203 0.36

Paving Plate Compactors 1 10.00 8 0.43

Paving Off-Highway Trucks 1 8.00 402 0.38

Building Construction Welders 1 10.00 46 0.45

Building Construction Generator Sets 1 10.00 84 0.74

Paving Cement and Mortar Mixers 1 10.00 9 0.56

Paving Pavers 1 10.00 130 0.42

Paving Paving Equipment 1 10.00 132 0.36

Site Preparation Rubber Tired Loaders 1 10.00 203 0.36

Site Preparation Excavators 1 10.00 158 0.38

Site Preparation Off-Highway Trucks 1 2.00 402 0.38

Paving Rollers 1 10.00 80 0.38

Building Construction Excavators 1 10.00 158 0.38

Building Construction Cranes 1 10.00 231 0.29

Building Construction Cranes 1 12.00 231 0.29

Grading Rubber Tired Loaders 1 10.00 203 0.36

Grading Graders 1 10.00 187 0.41

Grading Off-Highway Trucks 1 2.00 402 0.38 CalEEMod Version: CalEEMod.2016.3.1 Page 12 of 31 Date: 10/22/2017 7:10 PM

Mariposa BioMass - Mariposa County APCD Air District, Winter

Trips and VMT

Phase Name Offroad Equipment Worker Trip Vendor Trip Hauling Trip Worker Trip Vendor Trip Hauling Trip Worker Vehicle Vendor Hauling Count Number Number Number Length Length Length Class Vehicle Class Vehicle Class

Paving 1 24.00 2.00 25.00 30.00 30.00 45.00 LD_Mix HDT_Mix HHDT

Building Construction 7 294.00 20.00 50.00 30.00 30.00 30.00 LD_Mix HDT_Mix HHDT

Grading 3 55.00 5.00 80.00 30.00 30.00 30.00 LD_Mix HDT_Mix HHDT

Paving 5 0.00 0.00 0.00 10.80 7.30 20.00 LD_Mix HDT_Mix HHDT

Site Preparation 3 55.00 5.00 80.00 30.00 30.00 30.00 LD_Mix HDT_Mix HHDT

3.1 Mitigation Measures Construction

3.2 Site Preparation - 2018 Unmitigated Construction On-Site

ROG NOx CO SO2 Fugitive Exhaust PM10 Fugitive Exhaust PM2.5 Bio- CO2 NBio- CO2 Total CO2 CH4 N2O CO2e PM10 PM10 Total PM2.5 PM2.5 Total

Category lb/day lb/day

Fugitive Dust 0.1234 0.0000 0.1234 0.0569 0.0000 0.0569 0.0000 0.0000

Off-Road 1.0920 12.6073 7.3143 0.0176 0.4894 0.4894 0.4502 0.4502 1,767.963 1,767.963 0.5504 1,781.723 4 4 2

Total 1.0920 12.6073 7.3143 0.0176 0.1234 0.4894 0.6128 0.0569 0.4502 0.5071 1,767.963 1,767.963 0.5504 1,781.723 4 4 2 CalEEMod Version: CalEEMod.2016.3.1 Page 13 of 31 Date: 10/22/2017 7:10 PM

Mariposa BioMass - Mariposa County APCD Air District, Winter

3.2 Site Preparation - 2018 Unmitigated Construction Off-Site

ROG NOx CO SO2 Fugitive Exhaust PM10 Fugitive Exhaust PM2.5 Bio- CO2 NBio- CO2 Total CO2 CH4 N2O CO2e PM10 PM10 Total PM2.5 PM2.5 Total

Category lb/day lb/day

Hauling 0.0182 0.5601 0.1200 9.7000e- 0.0413 6.7400e- 0.0480 0.0106 6.4500e- 0.0171 101.1639 101.1639 3.3600e- 101.2478 004 003 003 003

Vendor 0.1450 2.6858 0.8547 5.2400e- 0.1374 0.0412 0.1786 0.0394 0.0394 0.0788 545.7708 545.7708 0.0177 546.2121 003

Worker 1.7890 1.5149 12.3467 0.0131 1.2541 0.0151 1.2692 0.3325 0.0140 0.3465 1,287.314 1,287.314 0.1319 1,290.611 6 6 2

Total 1.9523 4.7608 13.3213 0.0193 1.4327 0.0631 1.4958 0.3826 0.0598 0.4424 1,934.249 1,934.249 0.1529 1,938.071 3 3 1

Mitigated Construction On-Site

ROG NOx CO SO2 Fugitive Exhaust PM10 Fugitive Exhaust PM2.5 Bio- CO2 NBio- CO2 Total CO2 CH4 N2O CO2e PM10 PM10 Total PM2.5 PM2.5 Total

Category lb/day lb/day

Fugitive Dust 0.1234 0.0000 0.1234 0.0569 0.0000 0.0569 0.0000 0.0000

Off-Road 1.0920 7.3143 0.0176 0.4894 0.4894 0.4502 0.4502 0.0000 1,767.963 1,767.963 0.5504 1,781.723 4 4 2

Total 1.0920 7.3143 0.0176 0.1234 0.4894 0.6128 0.0569 0.4502 0.5071 0.0000 1,767.963 1,767.963 0.5504 1,781.723 4 4 2 CalEEMod Version: CalEEMod.2016.3.1 Page 14 of 31 Date: 10/22/2017 7:10 PM

Mariposa BioMass - Mariposa County APCD Air District, Winter

3.2 Site Preparation - 2018 Mitigated Construction Off-Site

ROG NOx CO SO2 Fugitive Exhaust PM10 Fugitive Exhaust PM2.5 Bio- CO2 NBio- CO2 Total CO2 CH4 N2O CO2e PM10 PM10 Total PM2.5 PM2.5 Total

Category lb/day lb/day

Hauling 0.0182 0.5601 0.1200 9.7000e- 0.0413 6.7400e- 0.0480 0.0106 6.4500e- 0.0171 101.1639 101.1639 3.3600e- 101.2478 004 003 003 003

Vendor 0.1450 2.6858 0.8547 5.2400e- 0.1374 0.0412 0.1786 0.0394 0.0394 0.0788 545.7708 545.7708 0.0177 546.2121 003

Worker 1.7890 1.5149 12.3467 0.0131 1.2541 0.0151 1.2692 0.3325 0.0140 0.3465 1,287.314 1,287.314 0.1319 1,290.611 6 6 2

Total 1.9523 4.7608 13.3213 0.0193 1.4327 0.0631 1.4958 0.3826 0.0598 0.4424 1,934.249 1,934.249 0.1529 1,938.071 3 3 1

3.2 Site Preparation - 2019 Unmitigated Construction On-Site

ROG NOx CO SO2 Fugitive Exhaust PM10 Fugitive Exhaust PM2.5 Bio- CO2 NBio- CO2 Total CO2 CH4 N2O CO2e PM10 PM10 Total PM2.5 PM2.5 Total

Category lb/day lb/day

Fugitive Dust 0.1234 0.0000 0.1234 0.0569 0.0000 0.0569 0.0000 0.0000

Off-Road 1.0019 11.1827 7.1767 0.0176 0.4293 0.4293 0.3950 0.3950 1,739.346 1,739.346 0.5503 1,753.104 8 8 6

Total 1.0019 11.1827 7.1767 0.0176 0.1234 0.4293 0.5527 0.0569 0.3950 0.4518 1,739.346 1,739.346 0.5503 1,753.104 8 8 6 CalEEMod Version: CalEEMod.2016.3.1 Page 15 of 31 Date: 10/22/2017 7:10 PM

Mariposa BioMass - Mariposa County APCD Air District, Winter

3.2 Site Preparation - 2019 Unmitigated Construction Off-Site

ROG NOx CO SO2 Fugitive Exhaust PM10 Fugitive Exhaust PM2.5 Bio- CO2 NBio- CO2 Total CO2 CH4 N2O CO2e PM10 PM10 Total PM2.5 PM2.5 Total

Category lb/day lb/day

Hauling 0.0143 0.5220 0.0939 9.6000e- 0.0292 4.6500e- 0.0338 7.6700e- 4.4500e- 0.0121 100.7143 100.7143 3.1500e- 100.7931 004 003 003 003 003

Vendor 0.1186 2.4746 0.6822 5.2200e- 0.1374 0.0311 0.1685 0.0394 0.0298 0.0692 543.8277 543.8277 0.0160 544.2288 003

Worker 1.6830 1.3763 11.1814 0.0127 1.2541 0.0144 1.2685 0.3325 0.0133 0.3458 1,253.292 1,253.292 0.1202 1,256.296 1 1 2

Total 1.8159 4.3729 11.9575 0.0189 1.4206 0.0502 1.4707 0.3796 0.0475 0.4271 1,897.834 1,897.834 0.1394 1,901.318 0 0 1

Mitigated Construction On-Site

ROG NOx CO SO2 Fugitive Exhaust PM10 Fugitive Exhaust PM2.5 Bio- CO2 NBio- CO2 Total CO2 CH4 N2O CO2e PM10 PM10 Total PM2.5 PM2.5 Total

Category lb/day lb/day

Fugitive Dust 0.1234 0.0000 0.1234 0.0569 0.0000 0.0569 0.0000 0.0000

Off-Road 1.0019 7.1767 0.0176 0.4293 0.4293 0.3950 0.3950 0.0000 1,739.346 1,739.346 0.5503 1,753.104 8 8 6

Total 1.0019 7.1767 0.0176 0.1234 0.4293 0.5527 0.0569 0.3950 0.4518 0.0000 1,739.346 1,739.346 0.5503 1,753.104 8 8 6 CalEEMod Version: CalEEMod.2016.3.1 Page 16 of 31 Date: 10/22/2017 7:10 PM

Mariposa BioMass - Mariposa County APCD Air District, Winter

3.2 Site Preparation - 2019 Mitigated Construction Off-Site

ROG NOx CO SO2 Fugitive Exhaust PM10 Fugitive Exhaust PM2.5 Bio- CO2 NBio- CO2 Total CO2 CH4 N2O CO2e PM10 PM10 Total PM2.5 PM2.5 Total

Category lb/day lb/day

Hauling 0.0143 0.5220 0.0939 9.6000e- 0.0292 4.6500e- 0.0338 7.6700e- 4.4500e- 0.0121 100.7143 100.7143 3.1500e- 100.7931 004 003 003 003 003

Vendor 0.1186 2.4746 0.6822 5.2200e- 0.1374 0.0311 0.1685 0.0394 0.0298 0.0692 543.8277 543.8277 0.0160 544.2288 003

Worker 1.6830 1.3763 11.1814 0.0127 1.2541 0.0144 1.2685 0.3325 0.0133 0.3458 1,253.292 1,253.292 0.1202 1,256.296 1 1 2

Total 1.8159 4.3729 11.9575 0.0189 1.4206 0.0502 1.4707 0.3796 0.0475 0.4271 1,897.834 1,897.834 0.1394 1,901.318 0 0 1

3.3 Grading - 2018 Unmitigated Construction On-Site

ROG NOx CO SO2 Fugitive Exhaust PM10 Fugitive Exhaust PM2.5 Bio- CO2 NBio- CO2 Total CO2 CH4 N2O CO2e PM10 PM10 Total PM2.5 PM2.5 Total

Category lb/day lb/day

Fugitive Dust 0.4684 0.0000 0.4684 0.2319 0.0000 0.2319 0.0000 0.0000

Off-Road 1.7417 21.5166 9.7077 0.0259 0.7790 0.7790 0.7167 0.7167 2,605.382 2,605.382 0.8111 2,625.659 6 6 9

Total 1.7417 21.5166 9.7077 0.0259 0.4684 0.7790 1.2475 0.2319 0.7167 0.9486 2,605.382 2,605.382 0.8111 2,625.659 6 6 9 CalEEMod Version: CalEEMod.2016.3.1 Page 17 of 31 Date: 10/22/2017 7:10 PM

Mariposa BioMass - Mariposa County APCD Air District, Winter

3.3 Grading - 2018 Unmitigated Construction Off-Site

ROG NOx CO SO2 Fugitive Exhaust PM10 Fugitive Exhaust PM2.5 Bio- CO2 NBio- CO2 Total CO2 CH4 N2O CO2e PM10 PM10 Total PM2.5 PM2.5 Total

Category lb/day lb/day

Hauling 0.0444 1.3620 0.2919 2.3500e- 0.0475 0.0164 0.0639 0.0129 0.0157 0.0286 246.0123 246.0123 8.1600e- 246.2163 003 003

Vendor 0.1450 2.6858 0.8547 5.2400e- 0.1374 0.0412 0.1786 0.0394 0.0394 0.0788 545.7708 545.7708 0.0177 546.2121 003

Worker 1.7890 1.5149 12.3467 0.0131 1.2541 0.0151 1.2692 0.3325 0.0140 0.3465 1,287.314 1,287.314 0.1319 1,290.611 6 6 2

Total 1.9784 5.5627 13.4932 0.0207 1.4390 0.0727 1.5117 0.3848 0.0691 0.4539 2,079.097 2,079.097 0.1577 2,083.039 7 7 6

Mitigated Construction On-Site

ROG NOx CO SO2 Fugitive Exhaust PM10 Fugitive Exhaust PM2.5 Bio- CO2 NBio- CO2 Total CO2 CH4 N2O CO2e PM10 PM10 Total PM2.5 PM2.5 Total

Category lb/day lb/day

Fugitive Dust 0.4684 0.0000 0.4684 0.2319 0.0000 0.2319 0.0000 0.0000

Off-Road 1.7417 8.9094 9.7077 0.0259 0.7790 0.7790 0.7167 0.7167 0.0000 2,605.382 2,605.382 0.8111 2,625.659 6 6 9

Total 1.7417 8.9094 9.7077 0.0259 0.4684 0.7790 1.2475 0.2319 0.7167 0.9486 0.0000 2,605.382 2,605.382 0.8111 2,625.659 6 6 9 CalEEMod Version: CalEEMod.2016.3.1 Page 18 of 31 Date: 10/22/2017 7:10 PM

Mariposa BioMass - Mariposa County APCD Air District, Winter

3.3 Grading - 2018 Mitigated Construction Off-Site

ROG NOx CO SO2 Fugitive Exhaust PM10 Fugitive Exhaust PM2.5 Bio- CO2 NBio- CO2 Total CO2 CH4 N2O CO2e PM10 PM10 Total PM2.5 PM2.5 Total

Category lb/day lb/day

Hauling 0.0444 1.3620 0.2919 2.3500e- 0.0475 0.0164 0.0639 0.0129 0.0157 0.0286 246.0123 246.0123 8.1600e- 246.2163 003 003

Vendor 0.1450 2.6858 0.8547 5.2400e- 0.1374 0.0412 0.1786 0.0394 0.0394 0.0788 545.7708 545.7708 0.0177 546.2121 003

Worker 1.7890 1.5149 12.3467 0.0131 1.2541 0.0151 1.2692 0.3325 0.0140 0.3465 1,287.314 1,287.314 0.1319 1,290.611 6 6 2

Total 1.9784 5.5627 13.4932 0.0207 1.4390 0.0727 1.5117 0.3848 0.0691 0.4539 2,079.097 2,079.097 0.1577 2,083.039 7 7 6

3.3 Grading - 2019 Unmitigated Construction On-Site

ROG NOx CO SO2 Fugitive Exhaust PM10 Fugitive Exhaust PM2.5 Bio- CO2 NBio- CO2 Total CO2 CH4 N2O CO2e PM10 PM10 Total PM2.5 PM2.5 Total

Category lb/day lb/day

Fugitive Dust 0.4684 0.0000 0.4684 0.2319 0.0000 0.2319 0.0000 0.0000

Off-Road 1.6103 19.4072 9.4742 0.0259 0.6933 0.6933 0.6378 0.6378 2,561.380 2,561.380 0.8104 2,581.640 7 7 6

Total 1.6103 19.4072 9.4742 0.0259 0.4684 0.6933 1.1617 0.2319 0.6378 0.8697 2,561.380 2,561.380 0.8104 2,581.640 7 7 6 CalEEMod Version: CalEEMod.2016.3.1 Page 19 of 31 Date: 10/22/2017 7:10 PM

Mariposa BioMass - Mariposa County APCD Air District, Winter

3.3 Grading - 2019 Unmitigated Construction Off-Site

ROG NOx CO SO2 Fugitive Exhaust PM10 Fugitive Exhaust PM2.5 Bio- CO2 NBio- CO2 Total CO2 CH4 N2O CO2e PM10 PM10 Total PM2.5 PM2.5 Total

Category lb/day lb/day

Hauling 0.0348 1.2695 0.2284 2.3400e- 1.5972 0.0113 1.6085 0.3933 0.0108 0.4041 244.9189 244.9189 7.6600e- 245.1105 003 003

Vendor 0.1186 2.4746 0.6822 5.2200e- 0.1374 0.0311 0.1685 0.0394 0.0298 0.0692 543.8277 543.8277 0.0160 544.2288 003

Worker 1.6830 1.3763 11.1814 0.0127 1.2541 0.0144 1.2685 0.3325 0.0133 0.3458 1,253.292 1,253.292 0.1202 1,256.296 1 1 2

Total 1.8363 5.1203 12.0920 0.0203 2.9886 0.0568 3.0454 0.7652 0.0539 0.8190 2,042.038 2,042.038 0.1439 2,045.635 6 6 5

Mitigated Construction On-Site

ROG NOx CO SO2 Fugitive Exhaust PM10 Fugitive Exhaust PM2.5 Bio- CO2 NBio- CO2 Total CO2 CH4 N2O CO2e PM10 PM10 Total PM2.5 PM2.5 Total

Category lb/day lb/day

Fugitive Dust 0.4684 0.0000 0.4684 0.2319 0.0000 0.2319 0.0000 0.0000

Off-Road 1.6103 8.2245 9.4742 0.0259 0.6933 0.6933 0.6378 0.6378 0.0000 2,561.380 2,561.380 0.8104 2,581.640 7 7 6

Total 1.6103 8.2245 9.4742 0.0259 0.4684 0.6933 1.1617 0.2319 0.6378 0.8697 0.0000 2,561.380 2,561.380 0.8104 2,581.640 7 7 6 CalEEMod Version: CalEEMod.2016.3.1 Page 20 of 31 Date: 10/22/2017 7:10 PM

Mariposa BioMass - Mariposa County APCD Air District, Winter

3.3 Grading - 2019 Mitigated Construction Off-Site

ROG NOx CO SO2 Fugitive Exhaust PM10 Fugitive Exhaust PM2.5 Bio- CO2 NBio- CO2 Total CO2 CH4 N2O CO2e PM10 PM10 Total PM2.5 PM2.5 Total

Category lb/day lb/day

Hauling 0.0348 1.2695 0.2284 2.3400e- 1.5972 0.0113 1.6085 0.3933 0.0108 0.4041 244.9189 244.9189 7.6600e- 245.1105 003 003

Vendor 0.1186 2.4746 0.6822 5.2200e- 0.1374 0.0311 0.1685 0.0394 0.0298 0.0692 543.8277 543.8277 0.0160 544.2288 003

Worker 1.6830 1.3763 11.1814 0.0127 1.2541 0.0144 1.2685 0.3325 0.0133 0.3458 1,253.292 1,253.292 0.1202 1,256.296 1 1 2

Total 1.8363 5.1203 12.0920 0.0203 2.9886 0.0568 3.0454 0.7652 0.0539 0.8190 2,042.038 2,042.038 0.1439 2,045.635 6 6 5

3.4 Building Construction - 2019 Unmitigated Construction On-Site

ROG NOx CO SO2 Fugitive Exhaust PM10 Fugitive Exhaust PM2.5 Bio- CO2 NBio- CO2 Total CO2 CH4 N2O CO2e PM10 PM10 Total PM2.5 PM2.5 Total

Category lb/day lb/day

Off-Road 2.7485 26.6243 17.2977 0.0337 1.2688 1.2688 1.1998 1.1998 3,247.876 3,247.876 0.7918 3,267.672 4 4 1

Total 2.7485 26.6243 17.2977 0.0337 1.2688 1.2688 1.1998 1.1998 3,247.876 3,247.876 0.7918 3,267.672 4 4 1 CalEEMod Version: CalEEMod.2016.3.1 Page 21 of 31 Date: 10/22/2017 7:10 PM

Mariposa BioMass - Mariposa County APCD Air District, Winter

3.4 Building Construction - 2019 Unmitigated Construction Off-Site

ROG NOx CO SO2 Fugitive Exhaust PM10 Fugitive Exhaust PM2.5 Bio- CO2 NBio- CO2 Total CO2 CH4 N2O CO2e PM10 PM10 Total PM2.5 PM2.5 Total

Category lb/day lb/day

Hauling 0.0121 0.4419 0.0795 8.1000e- 0.0163 3.9300e- 0.0202 4.4200e- 3.7600e- 8.1900e- 85.2566 85.2566 2.6700e- 85.3233 004 003 003 003 003 003

Vendor 0.4743 9.8985 2.7289 0.0209 0.5495 0.1245 0.6740 0.1576 0.1191 0.2767 2,175.310 2,175.310 0.0642 2,176.915 7 7 1

Worker 8.9965 7.3567 59.7696 0.0679 6.7036 0.0769 6.7804 1.7774 0.0709 1.8483 6,699.415 6,699.415 0.6424 6,715.474 7 7 5

Total 9.4829 17.6971 62.5780 0.0896 7.2693 0.2053 7.4746 1.9394 0.1937 2.1332 8,959.983 8,959.983 0.7092 8,977.712 0 0 8

Mitigated Construction On-Site

ROG NOx CO SO2 Fugitive Exhaust PM10 Fugitive Exhaust PM2.5 Bio- CO2 NBio- CO2 Total CO2 CH4 N2O CO2e PM10 PM10 Total PM2.5 PM2.5 Total

Category lb/day lb/day

Off-Road 2.7485 23.2719 17.2977 0.0337 1.2688 1.2688 1.1998 1.1998 0.0000 3,247.876 3,247.876 0.7918 3,267.672 4 4 1

Total 2.7485 23.2719 17.2977 0.0337 1.2688 1.2688 1.1998 1.1998 0.0000 3,247.876 3,247.876 0.7918 3,267.672 4 4 1 CalEEMod Version: CalEEMod.2016.3.1 Page 22 of 31 Date: 10/22/2017 7:10 PM

Mariposa BioMass - Mariposa County APCD Air District, Winter

3.4 Building Construction - 2019 Mitigated Construction Off-Site

ROG NOx CO SO2 Fugitive Exhaust PM10 Fugitive Exhaust PM2.5 Bio- CO2 NBio- CO2 Total CO2 CH4 N2O CO2e PM10 PM10 Total PM2.5 PM2.5 Total

Category lb/day lb/day

Hauling 0.0121 0.4419 0.0795 8.1000e- 0.0163 3.9300e- 0.0202 4.4200e- 3.7600e- 8.1900e- 85.2566 85.2566 2.6700e- 85.3233 004 003 003 003 003 003

Vendor 0.4743 9.8985 2.7289 0.0209 0.5495 0.1245 0.6740 0.1576 0.1191 0.2767 2,175.310 2,175.310 0.0642 2,176.915 7 7 1

Worker 8.9965 7.3567 59.7696 0.0679 6.7036 0.0769 6.7804 1.7774 0.0709 1.8483 6,699.415 6,699.415 0.6424 6,715.474 7 7 5

Total 9.4829 17.6971 62.5780 0.0896 7.2693 0.2053 7.4746 1.9394 0.1937 2.1332 8,959.983 8,959.983 0.7092 8,977.712 0 0 8

3.5 Paving - 2019 Unmitigated Construction On-Site

ROG NOx CO SO2 Fugitive Exhaust PM10 Fugitive Exhaust PM2.5 Bio- CO2 NBio- CO2 Total CO2 CH4 N2O CO2e PM10 PM10 Total PM2.5 PM2.5 Total

Category lb/day lb/day

Archit. Coating 12.7193 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000

Off-Road 2.2298 23.4079 15.7965 0.0366 1.0030 1.0030 0.9252 0.9252 3,580.774 3,580.774 1.1103 3,608.532 5 5 8

Paving 0.0463 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000

Total 14.9954 23.4079 15.7965 0.0366 1.0030 1.0030 0.9252 0.9252 3,580.774 3,580.774 1.1103 3,608.532 5 5 8 CalEEMod Version: CalEEMod.2016.3.1 Page 23 of 31 Date: 10/22/2017 7:10 PM

Mariposa BioMass - Mariposa County APCD Air District, Winter

3.5 Paving - 2019 Unmitigated Construction Off-Site

ROG NOx CO SO2 Fugitive Exhaust PM10 Fugitive Exhaust PM2.5 Bio- CO2 NBio- CO2 Total CO2 CH4 N2O CO2e PM10 PM10 Total PM2.5 PM2.5 Total

Category lb/day lb/day

Hauling 0.0157 0.5812 0.1013 1.1100e- 0.0397 5.3300e- 0.0450 0.0103 5.1000e- 0.0154 115.7099 115.7099 2.7300e- 115.7780 003 003 003 003

Vendor 0.0474 0.9899 0.2729 2.0900e- 0.0946 0.0125 0.1071 0.0255 0.0119 0.0374 217.5311 217.5311 6.4200e- 217.6915 003 003

Worker 0.7344 0.6006 4.8792 5.5400e- 1.0232 6.2700e- 1.0295 0.2619 5.7900e- 0.2677 546.8911 546.8911 0.0524 548.2020 003 003 003

Total 0.7976 2.1716 5.2533 8.7400e- 1.1575 0.0241 1.1815 0.2978 0.0228 0.3206 880.1320 880.1320 0.0616 881.6715 003

Mitigated Construction On-Site

ROG NOx CO SO2 Fugitive Exhaust PM10 Fugitive Exhaust PM2.5 Bio- CO2 NBio- CO2 Total CO2 CH4 N2O CO2e PM10 PM10 Total PM2.5 PM2.5 Total

Category lb/day lb/day

Archit. Coating 12.7193 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000

Off-Road 2.2298 9.8712 15.7965 0.0366 1.0030 1.0030 0.9252 0.9252 0.0000 3,580.774 3,580.774 1.1103 3,608.532 5 5 8

Paving 0.0463 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000

Total 14.9954 9.8712 15.7965 0.0366 1.0030 1.0030 0.9252 0.9252 0.0000 3,580.774 3,580.774 1.1103 3,608.532 5 5 8 CalEEMod Version: CalEEMod.2016.3.1 Page 24 of 31 Date: 10/22/2017 7:10 PM

Mariposa BioMass - Mariposa County APCD Air District, Winter

3.5 Paving - 2019 Mitigated Construction Off-Site

ROG NOx CO SO2 Fugitive Exhaust PM10 Fugitive Exhaust PM2.5 Bio- CO2 NBio- CO2 Total CO2 CH4 N2O CO2e PM10 PM10 Total PM2.5 PM2.5 Total

Category lb/day lb/day

Hauling 0.0157 0.5812 0.1013 1.1100e- 0.0397 5.3300e- 0.0450 0.0103 5.1000e- 0.0154 115.7099 115.7099 2.7300e- 115.7780 003 003 003 003

Vendor 0.0474 0.9899 0.2729 2.0900e- 0.0946 0.0125 0.1071 0.0255 0.0119 0.0374 217.5311 217.5311 6.4200e- 217.6915 003 003

Worker 0.7344 0.6006 4.8792 5.5400e- 1.0232 6.2700e- 1.0295 0.2619 5.7900e- 0.2677 546.8911 546.8911 0.0524 548.2020 003 003 003

Total 0.7976 2.1716 5.2533 8.7400e- 1.1575 0.0241 1.1815 0.2978 0.0228 0.3206 880.1320 880.1320 0.0616 881.6715 003

4.0 Operational Detail - Mobile

4.1 Mitigation Measures Mobile CalEEMod Version: CalEEMod.2016.3.1 Page 25 of 31 Date: 10/22/2017 7:10 PM

Mariposa BioMass - Mariposa County APCD Air District, Winter

ROG NOx CO SO2 Fugitive Exhaust PM10 Fugitive Exhaust PM2.5 Bio- CO2 NBio- CO2 Total CO2 CH4 N2O CO2e PM10 PM10 Total PM2.5 PM2.5 Total

Category lb/day lb/day

Mitigated 1.9704 9.0967 32.7421 0.0576 4.9922 0.0836 5.0758 1.3367 0.0786 1.4153 5,745.859 5,745.859 0.3928 5,755.679 1 1 6

Unmitigated 1.9704 9.0967 32.7421 0.0576 4.9922 0.0836 5.0758 1.3367 0.0786 1.4153 5,745.859 5,745.859 0.3928 5,755.679 1 1 6

4.2 Trip Summary Information

Average Daily Trip Rate Unmitigated Mitigated Land Use Weekday Saturday Sunday Annual VMT Annual VMT

General Light Industry 120.00 90.00 90.00 1,216,800 1,216,800 Other Asphalt Surfaces 31.10 0.00 0.00 16,172 16,172 Parking Lot 0.00 0.00 0.00 Unrefrigerated Warehouse-No Rail 111.80 111.80 0.00 872,040 872,040 Total 262.90 201.80 90.00 2,105,012 2,105,012

4.3 Trip Type Information

Miles Trip % Trip Purpose %

Land Use H-W or C-W H-S or C-C H-O or C-NW H-W or C-W H-S or C-C H-O or C-NW Primary Diverted Pass-by General Light Industry 0.00 0.00 0.00 0.00 0.00 0.00 100 0 0 Other Asphalt Surfaces 0.00 2.00 0.00 0.00 100.00 0.00 100 0 0 Parking Lot 0.00 0.00 0.00 0.00 0.00 0.00 0 0 0 Unrefrigerated Warehouse-No 0.00 25.00 0.00 0.00 100.00 0.00 100 0 0 Rail 4.4 Fleet Mix CalEEMod Version: CalEEMod.2016.3.1 Page 26 of 31 Date: 10/22/2017 7:10 PM

Mariposa BioMass - Mariposa County APCD Air District, Winter

Land Use LDA LDT1 LDT2 MDV LHD1 LHD2 MHD HHD OBUS UBUS MCY SBUS MH General Light Industry 0.509854 0.050310 0.198204 0.149339 0.051141 0.009120 0.011345 0.005705 0.002549 0.000960 0.006832 0.002182 0.002461

Unrefrigerated Warehouse-No 0.509854 0.050310 0.198204 0.149339 0.051141 0.009120 0.011345 0.005705 0.002549 0.000960 0.006832 0.002182 0.002461 Rail Other Asphalt Surfaces 0.509854 0.050310 0.198204 0.149339 0.051141 0.009120 0.011345 0.005705 0.002549 0.000960 0.006832 0.002182 0.002461

Parking Lot 0.509854 0.050310 0.198204 0.149339 0.051141 0.009120 0.011345 0.005705 0.002549 0.000960 0.006832 0.002182 0.002461

5.0 Energy Detail

Historical Energy Use: N

5.1 Mitigation Measures Energy

ROG NOx CO SO2 Fugitive Exhaust PM10 Fugitive Exhaust PM2.5 Bio- CO2 NBio- CO2 Total CO2 CH4 N2O CO2e PM10 PM10 Total PM2.5 PM2.5 Total

Category lb/day lb/day

NaturalGas 1.5600e- 0.0142 0.0120 9.0000e- 1.0800e- 1.0800e- 1.0800e- 1.0800e- 17.0669 17.0669 3.3000e- 3.1000e- 17.1683 Mitigated 003 005 003 003 003 003 004 004

NaturalGas 1.5600e- 0.0142 0.0120 9.0000e- 1.0800e- 1.0800e- 1.0800e- 1.0800e- 17.0669 17.0669 3.3000e- 3.1000e- 17.1683 Unmitigated 003 005 003 003 003 003 004 004 CalEEMod Version: CalEEMod.2016.3.1 Page 27 of 31 Date: 10/22/2017 7:10 PM

Mariposa BioMass - Mariposa County APCD Air District, Winter

5.2 Energy by Land Use - NaturalGas Unmitigated

NaturalGa ROG NOx CO SO2 Fugitive Exhaust PM10 Fugitive Exhaust PM2.5 Bio- CO2 NBio- CO2 Total CO2 CH4 N2O CO2e s Use PM10 PM10 Total PM2.5 PM2.5 Total

Land Use kBTU/yr lb/day lb/day

General Light 145.068 1.5600e- 0.0142 0.0120 9.0000e- 1.0800e- 1.0800e- 1.0800e- 1.0800e- 17.0669 17.0669 3.3000e- 3.1000e- 17.1683 Industry 003 005 003 003 003 003 004 004

Other Asphalt 0 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 Surfaces

Parking Lot 0 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000

Unrefrigerated 0 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 Warehouse-No Rail Total 1.5600e- 0.0142 0.0120 9.0000e- 1.0800e- 1.0800e- 1.0800e- 1.0800e- 17.0669 17.0669 3.3000e- 3.1000e- 17.1683 003 005 003 003 003 003 004 004 CalEEMod Version: CalEEMod.2016.3.1 Page 28 of 31 Date: 10/22/2017 7:10 PM

Mariposa BioMass - Mariposa County APCD Air District, Winter

5.2 Energy by Land Use - NaturalGas Mitigated

NaturalGa ROG NOx CO SO2 Fugitive Exhaust PM10 Fugitive Exhaust PM2.5 Bio- CO2 NBio- CO2 Total CO2 CH4 N2O CO2e s Use PM10 PM10 Total PM2.5 PM2.5 Total

Land Use kBTU/yr lb/day lb/day

General Light 0.145068 1.5600e- 0.0142 0.0120 9.0000e- 1.0800e- 1.0800e- 1.0800e- 1.0800e- 17.0669 17.0669 3.3000e- 3.1000e- 17.1683 Industry 003 005 003 003 003 003 004 004

Other Asphalt 0 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 Surfaces

Parking Lot 0 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000

Unrefrigerated 0 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 Warehouse-No Rail Total 1.5600e- 0.0142 0.0120 9.0000e- 1.0800e- 1.0800e- 1.0800e- 1.0800e- 17.0669 17.0669 3.3000e- 3.1000e- 17.1683 003 005 003 003 003 003 004 004

6.0 Area Detail

6.1 Mitigation Measures Area CalEEMod Version: CalEEMod.2016.3.1 Page 29 of 31 Date: 10/22/2017 7:10 PM

Mariposa BioMass - Mariposa County APCD Air District, Winter

ROG NOx CO SO2 Fugitive Exhaust PM10 Fugitive Exhaust PM2.5 Bio- CO2 NBio- CO2 Total CO2 CH4 N2O CO2e PM10 PM10 Total PM2.5 PM2.5 Total

Category lb/day lb/day

Mitigated 0.6735 6.0000e- 6.1300e- 0.0000 2.0000e- 2.0000e- 2.0000e- 2.0000e- 0.0131 0.0131 4.0000e- 0.0139 005 003 005 005 005 005 005

Unmitigated 0.6735 6.0000e- 6.1300e- 0.0000 2.0000e- 2.0000e- 2.0000e- 2.0000e- 0.0131 0.0131 4.0000e- 0.0139 005 003 005 005 005 005 005

6.2 Area by SubCategory Unmitigated

ROG NOx CO SO2 Fugitive Exhaust PM10 Fugitive Exhaust PM2.5 Bio- CO2 NBio- CO2 Total CO2 CH4 N2O CO2e PM10 PM10 Total PM2.5 PM2.5 Total

SubCategory lb/day lb/day

Architectural 0.1562 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 Coating

Consumer 0.5168 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 Products

Landscaping 5.8000e- 6.0000e- 6.1300e- 0.0000 2.0000e- 2.0000e- 2.0000e- 2.0000e- 0.0131 0.0131 4.0000e- 0.0139 004 005 003 005 005 005 005 005

Total 0.6735 6.0000e- 6.1300e- 0.0000 2.0000e- 2.0000e- 2.0000e- 2.0000e- 0.0131 0.0131 4.0000e- 0.0139 005 003 005 005 005 005 005 CalEEMod Version: CalEEMod.2016.3.1 Page 30 of 31 Date: 10/22/2017 7:10 PM

Mariposa BioMass - Mariposa County APCD Air District, Winter

6.2 Area by SubCategory Mitigated

ROG NOx CO SO2 Fugitive Exhaust PM10 Fugitive Exhaust PM2.5 Bio- CO2 NBio- CO2 Total CO2 CH4 N2O CO2e PM10 PM10 Total PM2.5 PM2.5 Total

SubCategory lb/day lb/day

Architectural 0.1562 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 Coating

Consumer 0.5168 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 Products

Landscaping 5.8000e- 6.0000e- 6.1300e- 0.0000 2.0000e- 2.0000e- 2.0000e- 2.0000e- 0.0131 0.0131 4.0000e- 0.0139 004 005 003 005 005 005 005 005

Total 0.6735 6.0000e- 6.1300e- 0.0000 2.0000e- 2.0000e- 2.0000e- 2.0000e- 0.0131 0.0131 4.0000e- 0.0139 005 003 005 005 005 005 005

7.0 Water Detail

7.1 Mitigation Measures Water

8.0 Waste Detail

8.1 Mitigation Measures Waste

9.0 Operational Offroad

Equipment Type Number Hours/Day Days/Year Horse Power Load Factor Fuel Type

Forklifts 1 24.00 310 89 0.20 Diesel

Tractors/Loaders/Backhoes 1 24.00 310 97 0.37 Diesel CalEEMod Version: CalEEMod.2016.3.1 Page 31 of 31 Date: 10/22/2017 7:10 PM

Mariposa BioMass - Mariposa County APCD Air District, Winter

UnMitigated/Mitigated

ROG NOx CO SO2 Fugitive Exhaust PM10 Fugitive Exhaust PM2.5 Bio- CO2 NBio- CO2 Total CO2 CH4 N2O CO2e PM10 PM10 Total PM2.5 PM2.5 Total

Equipment Type lb/day lb/day

Forklifts 0.4342 3.9120 3.5585 4.6000e- 0.2914 0.2914 0.2681 0.2681 446.3130 446.3130 0.1444 449.9216 003

Tractors/Loaders/ 0.6260 6.2898 6.8114 9.2800e- 0.3977 0.3977 0.3659 0.3659 898.6475 898.6475 0.2906 905.9136 Backhoes 003

Total 1.0602 10.2018 10.3699 0.0139 0.6892 0.6892 0.6341 0.6341 1,344.960 1,344.960 0.4350 1,355.835 5 5 2

10.0 Stationary Equipment

Fire Pumps and Emergency Generators

Equipment Type Number Hours/Day Hours/Year Horse Power Load Factor Fuel Type

Boilers

Equipment Type Number Heat Input/Day Heat Input/Year Boiler Rating Fuel Type

User Defined Equipment

Equipment Type Number

11.0 Vegetation CalEEMod Version: CalEEMod.2016.3.1 Page 1 of 34 Date: 10/22/2017 7:16 PM

Mariposa BioMass - Mariposa County APCD Air District, Annual

Mariposa BioMass Mariposa County APCD Air District, Annual

1.0 Project Characteristics

1.1 Land Usage

Land Uses Size Metric Lot Acreage Floor Surface Area Population

General Light Industry 15.00 1000sqft 0.34 15,000.00 0

Unrefrigerated Warehouse-No Rail 8.60 1000sqft 0.20 8,600.00 0

Other Asphalt Surfaces 31.10 1000sqft 0.71 31,100.00 0

Parking Lot 5.00 Space 0.05 2,000.00 0

1.2 Other Project Characteristics

Urbanization Urban Wind Speed (m/s) 2.2 Precipitation Freq (Days) 58

Climate Zone 1 Operational Year 2020

Utility Company Pacific Gas & Electric Company

CO2 Intensity 641.35 CH4 Intensity 0.029 N2O Intensity 0.006 (lb/MWhr) (lb/MWhr) (lb/MWhr)

1.3 User Entered Comments & Non-Default Data CalEEMod Version: CalEEMod.2016.3.1 Page 2 of 34 Date: 10/22/2017 7:16 PM

Mariposa BioMass - Mariposa County APCD Air District, Annual

Project Characteristics - CEC Climate Zone = Mariposa, Mariposa County. Start of Construction Date = Beginning of Site Prep. Land Use - General Light Indsutry Area = 1/3 of Project Area (46,100 ft2) Construction Phase - Reflects a condensed construction schedule to match the actual number of working days. Off-road Equipment - Dumper Truck = Off-Highway Truck (total 2 hours onsite) Off-road Equipment - Dumper Truck = Off-Highway Truck (2 hours onsite) Off-road Equipment - Dumper Truck = Off-Highway Truck (2 hours onsite) Off-road Equipment - Material Handling Crane = 10hr/day. Hydraulic Crane = 12hr/day. Off-road Equipment - Asphalt Truck = Off-Highway Truck (8 hours onsite total) Grading - Distrubance Area from Data Request (2.4 acres). Import material = Net Fill of 1,036 yd3. Trips and VMT - Values from Data Request (Dated 10/13/2017) Vehicle Trips - Other asphalt surface trip = ash removal. Informaiton from Data Request (dated 10/13/2017). Chip trucks and dump trucks combined for a value of 13. Area Coating - Energy Use - Solid Waste - biochar from the bioenergy facility will be sold as a part of the process and therefore is not considered waste. Operational Off-Road Equipment - Equipment Selection from similar project operations. Stationary Sources - User Defined - Stationary Sources - Process Boilers -

Table Name Column Name Default Value New Value

tblArchitecturalCoating EF_Parking 250.00 0.00

tblArchitecturalCoating PhaseName Architectural Coating Paving

tblAreaMitigation UseLowVOCPaintParkingValue 0 250

tblConstructionPhase NumDays 10.00 5.00

tblConstructionPhase NumDays 200.00 50.00

tblConstructionPhase NumDays 4.00 12.00

tblConstructionPhase NumDays 2.00 20.00

tblConstructionPhase NumDaysWeek 5.00 6.00 CalEEMod Version: CalEEMod.2016.3.1 Page 3 of 34 Date: 10/22/2017 7:16 PM

Mariposa BioMass - Mariposa County APCD Air District, Annual

tblConstructionPhase PhaseEndDate 10/10/2019 6/7/2019

tblConstructionPhase PhaseEndDate 9/12/2019 4/27/2019

tblConstructionPhase PhaseEndDate 12/6/2018 1/16/2019

tblConstructionPhase PhaseEndDate 11/30/2018 1/28/2019

tblConstructionPhase PhaseStartDate 9/27/2019 6/1/2019

tblConstructionPhase PhaseStartDate 12/7/2018 3/1/2019

tblConstructionPhase PhaseStartDate 12/1/2018 1/1/2019

tblConstructionPhase PhaseStartDate 11/29/2018 1/1/2019

tblGrading AcresOfGrading 1.50 2.40

tblGrading AcresOfGrading 1.00 2.40

tblGrading MaterialImported 0.00 1,036.00

tblOffRoadEquipment OffRoadEquipmentType Excavators

tblOffRoadEquipment OffRoadEquipmentType Welders

tblOffRoadEquipment OffRoadEquipmentType Rubber Tired Loaders

tblOffRoadEquipment OffRoadEquipmentType Plate Compactors

tblOffRoadEquipment OffRoadEquipmentType Off-Highway Trucks

tblOffRoadEquipment OffRoadEquipmentType Rubber Tired Loaders

tblOffRoadEquipment OffRoadEquipmentType Excavators

tblOffRoadEquipment OffRoadEquipmentType Generator Sets

tblOffRoadEquipment OffRoadEquipmentType Cement and Mortar Mixers

tblOffRoadEquipment OffRoadEquipmentType Pavers

tblOffRoadEquipment OffRoadEquipmentType Excavators

tblOffRoadEquipment OffRoadEquipmentType Cranes

tblOffRoadEquipment OffRoadEquipmentType Paving Equipment

tblOffRoadEquipment OffRoadEquipmentType Off-Highway Trucks

tblOffRoadEquipment OffRoadEquipmentType Rollers

tblOffRoadEquipment OffRoadEquipmentType Cranes CalEEMod Version: CalEEMod.2016.3.1 Page 4 of 34 Date: 10/22/2017 7:16 PM

Mariposa BioMass - Mariposa County APCD Air District, Annual

tblOffRoadEquipment OffRoadEquipmentType Rubber Tired Loaders

tblOffRoadEquipment OffRoadEquipmentType Graders

tblOffRoadEquipment OffRoadEquipmentType Off-Highway Trucks

tblOffRoadEquipment OffRoadEquipmentUnitAmount 0.00 1.00

tblOffRoadEquipment OffRoadEquipmentUnitAmount 0.00 1.00

tblOffRoadEquipment OffRoadEquipmentUnitAmount 0.00 1.00

tblOffRoadEquipment OffRoadEquipmentUnitAmount 0.00 1.00

tblOffRoadEquipment OffRoadEquipmentUnitAmount 0.00 1.00

tblOffRoadEquipment OffRoadEquipmentUnitAmount 0.00 1.00

tblOffRoadEquipment OffRoadEquipmentUnitAmount 0.00 1.00

tblOffRoadEquipment OffRoadEquipmentUnitAmount 0.00 1.00

tblOffRoadEquipment OffRoadEquipmentUnitAmount 0.00 1.00

tblOffRoadEquipment OffRoadEquipmentUnitAmount 0.00 1.00

tblOffRoadEquipment OffRoadEquipmentUnitAmount 0.00 1.00

tblOffRoadEquipment OffRoadEquipmentUnitAmount 0.00 1.00

tblOffRoadEquipment OffRoadEquipmentUnitAmount 0.00 1.00

tblOffRoadEquipment PhaseName Grading

tblOffRoadEquipment PhaseName Building Construction

tblOffRoadEquipment PhaseName Paving

tblOffRoadEquipment PhaseName Paving

tblOffRoadEquipment PhaseName Paving

tblOffRoadEquipment PhaseName Site Preparation

tblOffRoadEquipment PhaseName Building Construction

tblOffRoadEquipment PhaseName Building Construction

tblOffRoadEquipment PhaseName Paving

tblOffRoadEquipment PhaseName Paving

tblOffRoadEquipment PhaseName Site Preparation CalEEMod Version: CalEEMod.2016.3.1 Page 5 of 34 Date: 10/22/2017 7:16 PM

Mariposa BioMass - Mariposa County APCD Air District, Annual

tblOffRoadEquipment PhaseName Building Construction

tblOffRoadEquipment PhaseName Paving

tblOffRoadEquipment PhaseName Site Preparation

tblOffRoadEquipment PhaseName Paving

tblOffRoadEquipment PhaseName Building Construction

tblOffRoadEquipment PhaseName Grading

tblOffRoadEquipment PhaseName Grading

tblOffRoadEquipment PhaseName Grading

tblOnRoadDust PhaseName Architectural Coating Paving

tblOperationalOffRoadEquipment OperDaysPerYear 260.00 310.00

tblOperationalOffRoadEquipment OperDaysPerYear 260.00 310.00

tblOperationalOffRoadEquipment OperHoursPerDay 8.00 24.00

tblOperationalOffRoadEquipment OperHoursPerDay 8.00 24.00

tblOperationalOffRoadEquipment OperOffRoadEquipmentNumber 0.00 1.00

tblOperationalOffRoadEquipment OperOffRoadEquipmentNumber 0.00 1.00

tblProjectCharacteristics OperationalYear 2018 2020

tblSolidWaste SolidWasteGenerationRate 18.60 0.00

tblTripsAndVMT HaulingTripLength 20.00 30.00

tblTripsAndVMT HaulingTripLength 20.00 30.00

tblTripsAndVMT HaulingTripLength 20.00 30.00

tblTripsAndVMT HaulingTripLength 20.00 45.00

tblTripsAndVMT HaulingTripNumber 0.00 80.00

tblTripsAndVMT HaulingTripNumber 0.00 80.00

tblTripsAndVMT HaulingTripNumber 0.00 50.00

tblTripsAndVMT HaulingTripNumber 0.00 25.00

tblTripsAndVMT PhaseName Architectural Coating Paving

tblTripsAndVMT VendorTripLength 7.30 30.00 CalEEMod Version: CalEEMod.2016.3.1 Page 6 of 34 Date: 10/22/2017 7:16 PM

Mariposa BioMass - Mariposa County APCD Air District, Annual

tblTripsAndVMT VendorTripLength 7.30 30.00

tblTripsAndVMT VendorTripLength 7.30 30.00

tblTripsAndVMT VendorTripLength 7.30 30.00

tblTripsAndVMT VendorTripNumber 0.00 5.00

tblTripsAndVMT VendorTripNumber 0.00 5.00

tblTripsAndVMT VendorTripNumber 9.00 20.00

tblTripsAndVMT VendorTripNumber 0.00 2.00

tblTripsAndVMT WorkerTripLength 10.80 30.00

tblTripsAndVMT WorkerTripLength 10.80 30.00

tblTripsAndVMT WorkerTripLength 10.80 30.00

tblTripsAndVMT WorkerTripLength 10.80 30.00

tblTripsAndVMT WorkerTripNumber 8.00 55.00

tblTripsAndVMT WorkerTripNumber 8.00 55.00

tblTripsAndVMT WorkerTripNumber 24.00 294.00

tblTripsAndVMT WorkerTripNumber 13.00 0.00

tblTripsAndVMT WorkerTripNumber 5.00 24.00

tblVehicleTrips CC_TL 7.30 0.00

tblVehicleTrips CC_TL 7.30 2.00

tblVehicleTrips CC_TL 7.30 0.00

tblVehicleTrips CC_TL 7.30 25.00

tblVehicleTrips CC_TTP 28.00 0.00

tblVehicleTrips CC_TTP 0.00 100.00

tblVehicleTrips CC_TTP 0.00 100.00

tblVehicleTrips CNW_TL 7.30 0.00

tblVehicleTrips CNW_TL 7.30 0.00

tblVehicleTrips CNW_TL 7.30 0.00

tblVehicleTrips CNW_TL 7.30 0.00 CalEEMod Version: CalEEMod.2016.3.1 Page 7 of 34 Date: 10/22/2017 7:16 PM

Mariposa BioMass - Mariposa County APCD Air District, Annual

tblVehicleTrips CNW_TTP 13.00 0.00

tblVehicleTrips CNW_TTP 41.00 0.00

tblVehicleTrips CW_TL 9.50 0.00

tblVehicleTrips CW_TL 9.50 0.00

tblVehicleTrips CW_TL 9.50 0.00

tblVehicleTrips CW_TL 9.50 0.00

tblVehicleTrips CW_TTP 59.00 0.00

tblVehicleTrips CW_TTP 59.00 0.00

tblVehicleTrips DV_TP 5.00 0.00

tblVehicleTrips DV_TP 5.00 0.00

tblVehicleTrips HW_TL 0.00 30.00

tblVehicleTrips HW_TTP 0.00 100.00

tblVehicleTrips PB_TP 3.00 0.00

tblVehicleTrips PB_TP 3.00 0.00

tblVehicleTrips PR_TP 92.00 100.00

tblVehicleTrips PR_TP 0.00 100.00

tblVehicleTrips PR_TP 92.00 100.00

tblVehicleTrips ST_TR 1.32 6.00

tblVehicleTrips ST_TR 1.68 13.00

tblVehicleTrips SU_TR 0.68 6.00

tblVehicleTrips SU_TR 1.68 0.00

tblVehicleTrips WD_TR 6.97 8.00

tblVehicleTrips WD_TR 0.00 1.00

tblVehicleTrips WD_TR 1.68 13.00

2.0 Emissions Summary CalEEMod Version: CalEEMod.2016.3.1 Page 8 of 34 Date: 10/22/2017 7:16 PM

Mariposa BioMass - Mariposa County APCD Air District, Annual

2.1 Overall Construction Unmitigated Construction

ROG NOx CO SO2 Fugitive Exhaust PM10 Fugitive Exhaust PM2.5 Bio- CO2 NBio- CO2 Total CO2 CH4 N2O CO2e PM10 PM10 Total PM2.5 PM2.5 Total

Year tons/yr MT/yr

2019 0.6074 1.5145 2.3755 3.9900e- 0.2197 0.0492 0.2689 0.0624 0.0463 0.1087 0.0000 359.3252 359.3252 0.0484 0.0000 360.5362 003

Maximum 0.6074 1.5145 2.3755 3.9900e- 0.2197 0.0492 0.2689 0.0624 0.0463 0.1087 0.0000 359.3252 359.3252 0.0484 0.0000 360.5362 003

Mitigated Construction

ROG NOx CO SO2 Fugitive Exhaust PM10 Fugitive Exhaust PM2.5 Bio- CO2 NBio- CO2 Total CO2 CH4 N2O CO2e PM10 PM10 Total PM2.5 PM2.5 Total

Year tons/yr MT/yr

2019 0.6074 1.2180 2.3755 3.9900e- 0.2197 0.0492 0.2689 0.0624 0.0463 0.1087 0.0000 359.3251 359.3251 0.0484 0.0000 360.5361 003

Maximum 0.6074 1.2180 2.3755 3.9900e- 0.2197 0.0492 0.2689 0.0624 0.0463 0.1087 0.0000 359.3251 359.3251 0.0484 0.0000 360.5361 003

ROG NOx CO SO2 Fugitive Exhaust PM10 Fugitive Exhaust PM2.5 Bio- CO2 NBio-CO2 Total CO2 CH4 N20 CO2e PM10 PM10 Total PM2.5 PM2.5 Total

Percent 0.00 19.58 0.00 0.00 0.00 0.02 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Reduction CalEEMod Version: CalEEMod.2016.3.1 Page 9 of 34 Date: 10/22/2017 7:16 PM

Mariposa BioMass - Mariposa County APCD Air District, Annual

Quarter Start Date End Date Maximum Unmitigated ROG + NOX (tons/quarter) Maximum Mitigated ROG + NOX (tons/quarter)

1 11-1-2018 1-31-2019 0.3868 0.2111

2 2-1-2019 4-30-2019 1.3757 1.2924

3 5-1-2019 7-31-2019 0.3560 0.3222

Highest 1.3757 1.2924

2.2 Overall Operational Unmitigated Operational

ROG NOx CO SO2 Fugitive Exhaust PM10 Fugitive Exhaust PM2.5 Bio- CO2 NBio- CO2 Total CO2 CH4 N2O CO2e PM10 PM10 Total PM2.5 PM2.5 Total

Category tons/yr MT/yr

Area 0.1229 1.0000e- 5.5000e- 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 1.0700e- 1.0700e- 0.0000 0.0000 1.1400e- 005 004 003 003 003

Energy 2.9000e- 2.6000e- 2.1800e- 2.0000e- 2.0000e- 2.0000e- 2.0000e- 2.0000e- 0.0000 22.3632 22.3632 9.4000e- 2.3000e- 22.4566 004 003 003 005 004 004 004 004 004 004

Mobile 0.3197 1.4162 5.2809 9.5200e- 0.7861 0.0136 0.7997 0.2111 0.0128 0.2239 0.0000 862.4665 862.4665 0.0584 0.0000 863.9251 003

Offroad 0.1643 1.5813 1.6073 2.1500e- 0.1068 0.1068 0.0983 0.0983 0.0000 189.1198 189.1198 0.0612 0.0000 190.6489 003

Waste 0.0000 0.0000 0.0000 0.0000 1.6402 0.0000 1.6402 0.0969 0.0000 4.0634

Water 0.0000 0.0000 0.0000 0.0000 1.7314 8.5908 10.3222 0.1782 4.2800e- 16.0530 003

Total 0.6072 3.0001 6.8909 0.0117 0.7861 0.1206 0.9067 0.2111 0.1113 0.3223 3.3716 1,082.541 1,085.912 0.3956 4.5100e- 1,097.148 3 9 003 2 CalEEMod Version: CalEEMod.2016.3.1 Page 10 of 34 Date: 10/22/2017 7:16 PM

Mariposa BioMass - Mariposa County APCD Air District, Annual

2.2 Overall Operational Mitigated Operational

ROG NOx CO SO2 Fugitive Exhaust PM10 Fugitive Exhaust PM2.5 Bio- CO2 NBio- CO2 Total CO2 CH4 N2O CO2e PM10 PM10 Total PM2.5 PM2.5 Total

Category tons/yr MT/yr

Area 0.1229 1.0000e- 5.5000e- 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 1.0700e- 1.0700e- 0.0000 0.0000 1.1400e- 005 004 003 003 003

Energy 2.9000e- 2.6000e- 2.1800e- 2.0000e- 2.0000e- 2.0000e- 2.0000e- 2.0000e- 0.0000 22.3632 22.3632 9.4000e- 2.3000e- 22.4566 004 003 003 005 004 004 004 004 004 004

Mobile 0.3197 1.4162 5.2809 9.5200e- 0.7861 0.0136 0.7997 0.2111 0.0128 0.2239 0.0000 862.4665 862.4665 0.0584 0.0000 863.9251 003

Offroad 0.1643 1.5813 1.6073 2.1500e- 0.1068 0.1068 0.0983 0.0983 0.0000 189.1198 189.1198 0.0612 0.0000 190.6489 003

Waste 0.0000 0.0000 0.0000 0.0000 1.6402 0.0000 1.6402 0.0969 0.0000 4.0634

Water 0.0000 0.0000 0.0000 0.0000 1.7314 8.5908 10.3222 0.1782 4.2800e- 16.0530 003

Total 0.6072 3.0001 6.8909 0.0117 0.7861 0.1206 0.9067 0.2111 0.1113 0.3223 3.3716 1,082.541 1,085.912 0.3956 4.5100e- 1,097.148 3 9 003 2

ROG NOx CO SO2 Fugitive Exhaust PM10 Fugitive Exhaust PM2.5 Bio- CO2 NBio-CO2 Total CO2 CH4 N20 CO2e PM10 PM10 Total PM2.5 PM2.5 Total

Percent 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Reduction

3.0 Construction Detail

Construction Phase CalEEMod Version: CalEEMod.2016.3.1 Page 11 of 34 Date: 10/22/2017 7:16 PM

Mariposa BioMass - Mariposa County APCD Air District, Annual

Phase Phase Name Phase Type Start Date End Date Num Days Num Days Phase Description Number Week

1 Site Preparation Site Preparation 1/1/2019 1/28/2019 5 20

2 Grading Grading 1/1/2019 1/16/2019 5 12

3 Building Construction Building Construction 3/1/2019 4/27/2019 6 50

4 Paving Paving 6/1/2019 6/7/2019 5 5

Acres of Grading (Site Preparation Phase): 2.4

Acres of Grading (Grading Phase): 2.4

Acres of Paving: 0.76

Residential Indoor: 0; Residential Outdoor: 0; Non-Residential Indoor: 35,400; Non-Residential Outdoor: 11,800; Striped Parking Area: 1,986 (Architectural Coating – sqft)

OffRoad Equipment CalEEMod Version: CalEEMod.2016.3.1 Page 12 of 34 Date: 10/22/2017 7:16 PM

Mariposa BioMass - Mariposa County APCD Air District, Annual

Phase Name Offroad Equipment Type Amount Usage Hours Horse Power Load Factor

Grading Excavators 1 10.00 158 0.38

Paving Rubber Tired Loaders 1 10.00 203 0.36

Paving Plate Compactors 1 10.00 8 0.43

Paving Off-Highway Trucks 1 8.00 402 0.38

Building Construction Welders 1 10.00 46 0.45

Building Construction Generator Sets 1 10.00 84 0.74

Paving Cement and Mortar Mixers 1 10.00 9 0.56

Paving Pavers 1 10.00 130 0.42

Paving Paving Equipment 1 10.00 132 0.36

Site Preparation Rubber Tired Loaders 1 10.00 203 0.36

Site Preparation Excavators 1 10.00 158 0.38

Site Preparation Off-Highway Trucks 1 2.00 402 0.38

Paving Rollers 1 10.00 80 0.38

Building Construction Excavators 1 10.00 158 0.38

Building Construction Cranes 1 10.00 231 0.29

Building Construction Cranes 1 12.00 231 0.29

Grading Rubber Tired Loaders 1 10.00 203 0.36

Grading Graders 1 10.00 187 0.41

Grading Off-Highway Trucks 1 2.00 402 0.38

Trips and VMT CalEEMod Version: CalEEMod.2016.3.1 Page 13 of 34 Date: 10/22/2017 7:16 PM

Mariposa BioMass - Mariposa County APCD Air District, Annual

Phase Name Offroad Equipment Worker Trip Vendor Trip Hauling Trip Worker Trip Vendor Trip Hauling Trip Worker Vehicle Vendor Hauling Count Number Number Number Length Length Length Class Vehicle Class Vehicle Class

Paving 1 24.00 2.00 25.00 30.00 30.00 45.00 LD_Mix HDT_Mix HHDT

Building Construction 7 294.00 20.00 50.00 30.00 30.00 30.00 LD_Mix HDT_Mix HHDT

Grading 3 55.00 5.00 80.00 30.00 30.00 30.00 LD_Mix HDT_Mix HHDT

Paving 5 0.00 0.00 0.00 10.80 7.30 20.00 LD_Mix HDT_Mix HHDT

Site Preparation 3 55.00 5.00 80.00 30.00 30.00 30.00 LD_Mix HDT_Mix HHDT

3.1 Mitigation Measures Construction

3.2 Site Preparation - 2019 Unmitigated Construction On-Site

ROG NOx CO SO2 Fugitive Exhaust PM10 Fugitive Exhaust PM2.5 Bio- CO2 NBio- CO2 Total CO2 CH4 N2O CO2e PM10 PM10 Total PM2.5 PM2.5 Total

Category tons/yr MT/yr

Fugitive Dust 6.6000e- 0.0000 6.6000e- 3.0400e- 0.0000 3.0400e- 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 003 003 003 003

Off-Road 0.0100 0.1118 0.0718 1.8000e- 4.2900e- 4.2900e- 3.9500e- 3.9500e- 0.0000 15.7791 15.7791 4.9900e- 0.0000 15.9039 004 003 003 003 003 003

Total 0.0100 0.1118 0.0718 1.8000e- 6.6000e- 4.2900e- 0.0109 3.0400e- 3.9500e- 6.9900e- 0.0000 15.7791 15.7791 4.9900e- 0.0000 15.9039 004 003 003 003 003 003 003 CalEEMod Version: CalEEMod.2016.3.1 Page 14 of 34 Date: 10/22/2017 7:16 PM

Mariposa BioMass - Mariposa County APCD Air District, Annual

3.2 Site Preparation - 2019 Unmitigated Construction Off-Site

ROG NOx CO SO2 Fugitive Exhaust PM10 Fugitive Exhaust PM2.5 Bio- CO2 NBio- CO2 Total CO2 CH4 N2O CO2e PM10 PM10 Total PM2.5 PM2.5 Total

Category tons/yr MT/yr

Hauling 7.6000e- 0.0277 4.9100e- 5.0000e- 1.0000e- 2.5000e- 1.2400e- 2.7000e- 2.4000e- 5.1000e- 0.0000 4.9062 4.9062 1.4000e- 0.0000 4.9098 004 003 005 003 004 003 004 004 004 004

Vendor 1.1600e- 0.0245 6.7200e- 5.0000e- 1.3300e- 3.1000e- 1.6400e- 3.8000e- 3.0000e- 6.8000e- 0.0000 4.9453 4.9453 1.4000e- 0.0000 4.9488 003 003 005 003 004 003 004 004 004 004

Worker 0.0148 0.0126 0.1115 1.3000e- 0.0121 1.4000e- 0.0123 3.2200e- 1.3000e- 3.3500e- 0.0000 11.5986 11.5986 1.0900e- 0.0000 11.6259 004 004 003 004 003 003

Total 0.0167 0.0648 0.1232 2.3000e- 0.0144 7.0000e- 0.0151 3.8700e- 6.7000e- 4.5400e- 0.0000 21.4500 21.4500 1.3700e- 0.0000 21.4845 004 004 003 004 003 003

Mitigated Construction On-Site

ROG NOx CO SO2 Fugitive Exhaust PM10 Fugitive Exhaust PM2.5 Bio- CO2 NBio- CO2 Total CO2 CH4 N2O CO2e PM10 PM10 Total PM2.5 PM2.5 Total

Category tons/yr MT/yr

Fugitive Dust 6.6000e- 0.0000 6.6000e- 3.0400e- 0.0000 3.0400e- 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 003 003 003 003

Off-Road 0.0100 0.0718 1.8000e- 4.2900e- 4.2900e- 3.9500e- 3.9500e- 0.0000 15.7791 15.7791 4.9900e- 0.0000 15.9039 004 003 003 003 003 003

Total 0.0100 0.0718 1.8000e- 6.6000e- 4.2900e- 0.0109 3.0400e- 3.9500e- 6.9900e- 0.0000 15.7791 15.7791 4.9900e- 0.0000 15.9039 004 003 003 003 003 003 003 CalEEMod Version: CalEEMod.2016.3.1 Page 15 of 34 Date: 10/22/2017 7:16 PM

Mariposa BioMass - Mariposa County APCD Air District, Annual

3.2 Site Preparation - 2019 Mitigated Construction Off-Site

ROG NOx CO SO2 Fugitive Exhaust PM10 Fugitive Exhaust PM2.5 Bio- CO2 NBio- CO2 Total CO2 CH4 N2O CO2e PM10 PM10 Total PM2.5 PM2.5 Total

Category tons/yr MT/yr

Hauling 7.6000e- 0.0277 4.9100e- 5.0000e- 1.0000e- 2.5000e- 1.2400e- 2.7000e- 2.4000e- 5.1000e- 0.0000 4.9062 4.9062 1.4000e- 0.0000 4.9098 004 003 005 003 004 003 004 004 004 004

Vendor 1.1600e- 0.0245 6.7200e- 5.0000e- 1.3300e- 3.1000e- 1.6400e- 3.8000e- 3.0000e- 6.8000e- 0.0000 4.9453 4.9453 1.4000e- 0.0000 4.9488 003 003 005 003 004 003 004 004 004 004

Worker 0.0148 0.0126 0.1115 1.3000e- 0.0121 1.4000e- 0.0123 3.2200e- 1.3000e- 3.3500e- 0.0000 11.5986 11.5986 1.0900e- 0.0000 11.6259 004 004 003 004 003 003

Total 0.0167 0.0648 0.1232 2.3000e- 0.0144 7.0000e- 0.0151 3.8700e- 6.7000e- 4.5400e- 0.0000 21.4500 21.4500 1.3700e- 0.0000 21.4845 004 004 003 004 003 003

3.3 Grading - 2019 Unmitigated Construction On-Site

ROG NOx CO SO2 Fugitive Exhaust PM10 Fugitive Exhaust PM2.5 Bio- CO2 NBio- CO2 Total CO2 CH4 N2O CO2e PM10 PM10 Total PM2.5 PM2.5 Total

Category tons/yr MT/yr

Fugitive Dust 0.0103 0.0000 0.0103 5.1000e- 0.0000 5.1000e- 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 003 003

Off-Road 9.6600e- 0.1164 0.0569 1.6000e- 4.1600e- 4.1600e- 3.8300e- 3.8300e- 0.0000 13.9419 13.9419 4.4100e- 0.0000 14.0522 003 004 003 003 003 003 003

Total 9.6600e- 0.1164 0.0569 1.6000e- 0.0103 4.1600e- 0.0145 5.1000e- 3.8300e- 8.9300e- 0.0000 13.9419 13.9419 4.4100e- 0.0000 14.0522 003 004 003 003 003 003 003 CalEEMod Version: CalEEMod.2016.3.1 Page 16 of 34 Date: 10/22/2017 7:16 PM

Mariposa BioMass - Mariposa County APCD Air District, Annual

3.3 Grading - 2019 Unmitigated Construction Off-Site

ROG NOx CO SO2 Fugitive Exhaust PM10 Fugitive Exhaust PM2.5 Bio- CO2 NBio- CO2 Total CO2 CH4 N2O CO2e PM10 PM10 Total PM2.5 PM2.5 Total

Category tons/yr MT/yr

Hauling 7.6000e- 0.0277 4.9100e- 5.0000e- 1.0000e- 2.5000e- 1.2400e- 2.7000e- 2.4000e- 5.1000e- 0.0000 4.9062 4.9062 1.4000e- 0.0000 4.9098 004 003 005 003 004 003 004 004 004 004

Vendor 6.9000e- 0.0147 4.0300e- 3.0000e- 8.0000e- 1.9000e- 9.9000e- 2.3000e- 1.8000e- 4.1000e- 0.0000 2.9672 2.9672 8.0000e- 0.0000 2.9693 004 003 005 004 004 004 004 004 004 005

Worker 8.8800e- 7.5900e- 0.0669 8.0000e- 7.2600e- 9.0000e- 7.3500e- 1.9300e- 8.0000e- 2.0100e- 0.0000 6.9591 6.9591 6.6000e- 0.0000 6.9755 003 003 005 003 005 003 003 005 003 004

Total 0.0103 0.0500 0.0759 1.6000e- 9.0600e- 5.3000e- 9.5800e- 2.4300e- 5.0000e- 2.9300e- 0.0000 14.8325 14.8325 8.8000e- 0.0000 14.8546 004 003 004 003 003 004 003 004

Mitigated Construction On-Site

ROG NOx CO SO2 Fugitive Exhaust PM10 Fugitive Exhaust PM2.5 Bio- CO2 NBio- CO2 Total CO2 CH4 N2O CO2e PM10 PM10 Total PM2.5 PM2.5 Total

Category tons/yr MT/yr

Fugitive Dust 0.0103 0.0000 0.0103 5.1000e- 0.0000 5.1000e- 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 003 003

Off-Road 9.6600e- 0.0494 0.0569 1.6000e- 4.1600e- 4.1600e- 3.8300e- 3.8300e- 0.0000 13.9419 13.9419 4.4100e- 0.0000 14.0521 003 004 003 003 003 003 003

Total 9.6600e- 0.0494 0.0569 1.6000e- 0.0103 4.1600e- 0.0145 5.1000e- 3.8300e- 8.9300e- 0.0000 13.9419 13.9419 4.4100e- 0.0000 14.0521 003 004 003 003 003 003 003 CalEEMod Version: CalEEMod.2016.3.1 Page 17 of 34 Date: 10/22/2017 7:16 PM

Mariposa BioMass - Mariposa County APCD Air District, Annual

3.3 Grading - 2019 Mitigated Construction Off-Site

ROG NOx CO SO2 Fugitive Exhaust PM10 Fugitive Exhaust PM2.5 Bio- CO2 NBio- CO2 Total CO2 CH4 N2O CO2e PM10 PM10 Total PM2.5 PM2.5 Total

Category tons/yr MT/yr

Hauling 7.6000e- 0.0277 4.9100e- 5.0000e- 1.0000e- 2.5000e- 1.2400e- 2.7000e- 2.4000e- 5.1000e- 0.0000 4.9062 4.9062 1.4000e- 0.0000 4.9098 004 003 005 003 004 003 004 004 004 004

Vendor 6.9000e- 0.0147 4.0300e- 3.0000e- 8.0000e- 1.9000e- 9.9000e- 2.3000e- 1.8000e- 4.1000e- 0.0000 2.9672 2.9672 8.0000e- 0.0000 2.9693 004 003 005 004 004 004 004 004 004 005

Worker 8.8800e- 7.5900e- 0.0669 8.0000e- 7.2600e- 9.0000e- 7.3500e- 1.9300e- 8.0000e- 2.0100e- 0.0000 6.9591 6.9591 6.6000e- 0.0000 6.9755 003 003 005 003 005 003 003 005 003 004

Total 0.0103 0.0500 0.0759 1.6000e- 9.0600e- 5.3000e- 9.5800e- 2.4300e- 5.0000e- 2.9300e- 0.0000 14.8325 14.8325 8.8000e- 0.0000 14.8546 004 003 004 003 003 004 003 004

3.4 Building Construction - 2019 Unmitigated Construction On-Site

ROG NOx CO SO2 Fugitive Exhaust PM10 Fugitive Exhaust PM2.5 Bio- CO2 NBio- CO2 Total CO2 CH4 N2O CO2e PM10 PM10 Total PM2.5 PM2.5 Total

Category tons/yr MT/yr

Off-Road 0.0687 0.6656 0.4324 8.4000e- 0.0317 0.0317 0.0300 0.0300 0.0000 73.6606 73.6606 0.0180 0.0000 74.1096 004

Total 0.0687 0.6656 0.4324 8.4000e- 0.0317 0.0317 0.0300 0.0300 0.0000 73.6606 73.6606 0.0180 0.0000 74.1096 004 CalEEMod Version: CalEEMod.2016.3.1 Page 18 of 34 Date: 10/22/2017 7:16 PM

Mariposa BioMass - Mariposa County APCD Air District, Annual

3.4 Building Construction - 2019 Unmitigated Construction Off-Site

ROG NOx CO SO2 Fugitive Exhaust PM10 Fugitive Exhaust PM2.5 Bio- CO2 NBio- CO2 Total CO2 CH4 N2O CO2e PM10 PM10 Total PM2.5 PM2.5 Total

Category tons/yr MT/yr

Hauling 4.7000e- 0.0173 3.0700e- 3.0000e- 6.2000e- 1.5000e- 7.8000e- 1.7000e- 1.5000e- 3.2000e- 0.0000 3.0664 3.0664 9.0000e- 0.0000 3.0686 004 003 005 004 004 004 004 004 004 005

Vendor 0.0116 0.2449 0.0672 5.2000e- 0.0133 3.1000e- 0.0164 3.8400e- 2.9700e- 6.8100e- 0.0000 49.4525 49.4525 1.4100e- 0.0000 49.4878 004 003 003 003 003 003

Worker 0.1978 0.1690 1.4906 1.7300e- 0.1618 1.9200e- 0.1637 0.0430 1.7700e- 0.0448 0.0000 154.9989 154.9989 0.0146 0.0000 155.3642 003 003 003

Total 0.2099 0.4311 1.5609 2.2800e- 0.1758 5.1700e- 0.1809 0.0470 4.8900e- 0.0519 0.0000 207.5178 207.5178 0.0161 0.0000 207.9206 003 003 003

Mitigated Construction On-Site

ROG NOx CO SO2 Fugitive Exhaust PM10 Fugitive Exhaust PM2.5 Bio- CO2 NBio- CO2 Total CO2 CH4 N2O CO2e PM10 PM10 Total PM2.5 PM2.5 Total

Category tons/yr MT/yr

Off-Road 0.0687 0.5818 0.4324 8.4000e- 0.0317 0.0317 0.0300 0.0300 0.0000 73.6605 73.6605 0.0180 0.0000 74.1095 004

Total 0.0687 0.5818 0.4324 8.4000e- 0.0317 0.0317 0.0300 0.0300 0.0000 73.6605 73.6605 0.0180 0.0000 74.1095 004 CalEEMod Version: CalEEMod.2016.3.1 Page 19 of 34 Date: 10/22/2017 7:16 PM

Mariposa BioMass - Mariposa County APCD Air District, Annual

3.4 Building Construction - 2019 Mitigated Construction Off-Site

ROG NOx CO SO2 Fugitive Exhaust PM10 Fugitive Exhaust PM2.5 Bio- CO2 NBio- CO2 Total CO2 CH4 N2O CO2e PM10 PM10 Total PM2.5 PM2.5 Total

Category tons/yr MT/yr

Hauling 4.7000e- 0.0173 3.0700e- 3.0000e- 6.2000e- 1.5000e- 7.8000e- 1.7000e- 1.5000e- 3.2000e- 0.0000 3.0664 3.0664 9.0000e- 0.0000 3.0686 004 003 005 004 004 004 004 004 004 005

Vendor 0.0116 0.2449 0.0672 5.2000e- 0.0133 3.1000e- 0.0164 3.8400e- 2.9700e- 6.8100e- 0.0000 49.4525 49.4525 1.4100e- 0.0000 49.4878 004 003 003 003 003 003

Worker 0.1978 0.1690 1.4906 1.7300e- 0.1618 1.9200e- 0.1637 0.0430 1.7700e- 0.0448 0.0000 154.9989 154.9989 0.0146 0.0000 155.3642 003 003 003

Total 0.2099 0.4311 1.5609 2.2800e- 0.1758 5.1700e- 0.1809 0.0470 4.8900e- 0.0519 0.0000 207.5178 207.5178 0.0161 0.0000 207.9206 003 003 003

3.5 Paving - 2019 Unmitigated Construction On-Site

ROG NOx CO SO2 Fugitive Exhaust PM10 Fugitive Exhaust PM2.5 Bio- CO2 NBio- CO2 Total CO2 CH4 N2O CO2e PM10 PM10 Total PM2.5 PM2.5 Total

Category tons/yr MT/yr

Archit. Coating 0.2735 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000

Off-Road 5.5700e- 0.0585 0.0395 9.0000e- 2.5100e- 2.5100e- 2.3100e- 2.3100e- 0.0000 8.1211 8.1211 2.5200e- 0.0000 8.1840 003 005 003 003 003 003 003

Paving 1.0000e- 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 003

Total 0.2800 0.0585 0.0395 9.0000e- 2.5100e- 2.5100e- 2.3100e- 2.3100e- 0.0000 8.1211 8.1211 2.5200e- 0.0000 8.1840 005 003 003 003 003 003 CalEEMod Version: CalEEMod.2016.3.1 Page 20 of 34 Date: 10/22/2017 7:16 PM

Mariposa BioMass - Mariposa County APCD Air District, Annual

3.5 Paving - 2019 Unmitigated Construction Off-Site

ROG NOx CO SO2 Fugitive Exhaust PM10 Fugitive Exhaust PM2.5 Bio- CO2 NBio- CO2 Total CO2 CH4 N2O CO2e PM10 PM10 Total PM2.5 PM2.5 Total

Category tons/yr MT/yr

Hauling 3.4000e- 0.0124 2.1500e- 2.0000e- 8.2000e- 1.1000e- 9.4000e- 2.1000e- 1.1000e- 3.2000e- 0.0000 2.2625 2.2625 5.0000e- 0.0000 2.2638 004 003 005 004 004 004 004 004 004 005

Vendor 1.2000e- 2.4500e- 6.7000e- 1.0000e- 2.3000e- 3.0000e- 2.6000e- 6.0000e- 3.0000e- 9.0000e- 0.0000 0.4945 0.4945 1.0000e- 0.0000 0.4949 004 003 004 005 004 005 004 005 005 005 005

Worker 1.6100e- 1.3800e- 0.0122 1.0000e- 2.4600e- 2.0000e- 2.4800e- 6.3000e- 1.0000e- 6.5000e- 0.0000 1.2653 1.2653 1.2000e- 0.0000 1.2683 003 003 005 003 005 003 004 005 004 004

Total 2.0700e- 0.0162 0.0150 4.0000e- 3.5100e- 1.6000e- 3.6800e- 9.0000e- 1.5000e- 1.0600e- 0.0000 4.0223 4.0223 1.8000e- 0.0000 4.0269 003 005 003 004 003 004 004 003 004

Mitigated Construction On-Site

ROG NOx CO SO2 Fugitive Exhaust PM10 Fugitive Exhaust PM2.5 Bio- CO2 NBio- CO2 Total CO2 CH4 N2O CO2e PM10 PM10 Total PM2.5 PM2.5 Total

Category tons/yr MT/yr

Archit. Coating 0.2735 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000

Off-Road 5.5700e- 0.0247 0.0395 9.0000e- 2.5100e- 2.5100e- 2.3100e- 2.3100e- 0.0000 8.1211 8.1211 2.5200e- 0.0000 8.1840 003 005 003 003 003 003 003

Paving 1.0000e- 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 003

Total 0.2800 0.0247 0.0395 9.0000e- 2.5100e- 2.5100e- 2.3100e- 2.3100e- 0.0000 8.1211 8.1211 2.5200e- 0.0000 8.1840 005 003 003 003 003 003 CalEEMod Version: CalEEMod.2016.3.1 Page 21 of 34 Date: 10/22/2017 7:16 PM

Mariposa BioMass - Mariposa County APCD Air District, Annual

3.5 Paving - 2019 Mitigated Construction Off-Site

ROG NOx CO SO2 Fugitive Exhaust PM10 Fugitive Exhaust PM2.5 Bio- CO2 NBio- CO2 Total CO2 CH4 N2O CO2e PM10 PM10 Total PM2.5 PM2.5 Total

Category tons/yr MT/yr

Hauling 3.4000e- 0.0124 2.1500e- 2.0000e- 8.2000e- 1.1000e- 9.4000e- 2.1000e- 1.1000e- 3.2000e- 0.0000 2.2625 2.2625 5.0000e- 0.0000 2.2638 004 003 005 004 004 004 004 004 004 005

Vendor 1.2000e- 2.4500e- 6.7000e- 1.0000e- 2.3000e- 3.0000e- 2.6000e- 6.0000e- 3.0000e- 9.0000e- 0.0000 0.4945 0.4945 1.0000e- 0.0000 0.4949 004 003 004 005 004 005 004 005 005 005 005

Worker 1.6100e- 1.3800e- 0.0122 1.0000e- 2.4600e- 2.0000e- 2.4800e- 6.3000e- 1.0000e- 6.5000e- 0.0000 1.2653 1.2653 1.2000e- 0.0000 1.2683 003 003 005 003 005 003 004 005 004 004

Total 2.0700e- 0.0162 0.0150 4.0000e- 3.5100e- 1.6000e- 3.6800e- 9.0000e- 1.5000e- 1.0600e- 0.0000 4.0223 4.0223 1.8000e- 0.0000 4.0269 003 005 003 004 003 004 004 003 004

4.0 Operational Detail - Mobile

4.1 Mitigation Measures Mobile CalEEMod Version: CalEEMod.2016.3.1 Page 22 of 34 Date: 10/22/2017 7:16 PM

Mariposa BioMass - Mariposa County APCD Air District, Annual

ROG NOx CO SO2 Fugitive Exhaust PM10 Fugitive Exhaust PM2.5 Bio- CO2 NBio- CO2 Total CO2 CH4 N2O CO2e PM10 PM10 Total PM2.5 PM2.5 Total

Category tons/yr MT/yr

Mitigated 0.3197 1.4162 5.2809 9.5200e- 0.7861 0.0136 0.7997 0.2111 0.0128 0.2239 0.0000 862.4665 862.4665 0.0584 0.0000 863.9251 003

Unmitigated 0.3197 1.4162 5.2809 9.5200e- 0.7861 0.0136 0.7997 0.2111 0.0128 0.2239 0.0000 862.4665 862.4665 0.0584 0.0000 863.9251 003

4.2 Trip Summary Information

Average Daily Trip Rate Unmitigated Mitigated Land Use Weekday Saturday Sunday Annual VMT Annual VMT

General Light Industry 120.00 90.00 90.00 1,216,800 1,216,800 Other Asphalt Surfaces 31.10 0.00 0.00 16,172 16,172 Parking Lot 0.00 0.00 0.00 Unrefrigerated Warehouse-No Rail 111.80 111.80 0.00 872,040 872,040 Total 262.90 201.80 90.00 2,105,012 2,105,012

4.3 Trip Type Information

Miles Trip % Trip Purpose %

Land Use H-W or C-W H-S or C-C H-O or C-NW H-W or C-W H-S or C-C H-O or C-NW Primary Diverted Pass-by General Light Industry 0.00 0.00 0.00 0.00 0.00 0.00 100 0 0 Other Asphalt Surfaces 0.00 2.00 0.00 0.00 100.00 0.00 100 0 0 Parking Lot 0.00 0.00 0.00 0.00 0.00 0.00 0 0 0 Unrefrigerated Warehouse-No 0.00 25.00 0.00 0.00 100.00 0.00 100 0 0 Rail 4.4 Fleet Mix CalEEMod Version: CalEEMod.2016.3.1 Page 23 of 34 Date: 10/22/2017 7:16 PM

Mariposa BioMass - Mariposa County APCD Air District, Annual

Land Use LDA LDT1 LDT2 MDV LHD1 LHD2 MHD HHD OBUS UBUS MCY SBUS MH General Light Industry 0.509854 0.050310 0.198204 0.149339 0.051141 0.009120 0.011345 0.005705 0.002549 0.000960 0.006832 0.002182 0.002461

Unrefrigerated Warehouse-No 0.509854 0.050310 0.198204 0.149339 0.051141 0.009120 0.011345 0.005705 0.002549 0.000960 0.006832 0.002182 0.002461 Rail Other Asphalt Surfaces 0.509854 0.050310 0.198204 0.149339 0.051141 0.009120 0.011345 0.005705 0.002549 0.000960 0.006832 0.002182 0.002461

Parking Lot 0.509854 0.050310 0.198204 0.149339 0.051141 0.009120 0.011345 0.005705 0.002549 0.000960 0.006832 0.002182 0.002461

5.0 Energy Detail

Historical Energy Use: N

5.1 Mitigation Measures Energy

ROG NOx CO SO2 Fugitive Exhaust PM10 Fugitive Exhaust PM2.5 Bio- CO2 NBio- CO2 Total CO2 CH4 N2O CO2e PM10 PM10 Total PM2.5 PM2.5 Total

Category tons/yr MT/yr

Electricity 0.0000 0.0000 0.0000 0.0000 0.0000 19.5376 19.5376 8.8000e- 1.8000e- 19.6142 Mitigated 004 004

Electricity 0.0000 0.0000 0.0000 0.0000 0.0000 19.5376 19.5376 8.8000e- 1.8000e- 19.6142 Unmitigated 004 004

NaturalGas 2.9000e- 2.6000e- 2.1800e- 2.0000e- 2.0000e- 2.0000e- 2.0000e- 2.0000e- 0.0000 2.8256 2.8256 5.0000e- 5.0000e- 2.8424 Mitigated 004 003 003 005 004 004 004 004 005 005

NaturalGas 2.9000e- 2.6000e- 2.1800e- 2.0000e- 2.0000e- 2.0000e- 2.0000e- 2.0000e- 0.0000 2.8256 2.8256 5.0000e- 5.0000e- 2.8424 Unmitigated 004 003 003 005 004 004 004 004 005 005 CalEEMod Version: CalEEMod.2016.3.1 Page 24 of 34 Date: 10/22/2017 7:16 PM

Mariposa BioMass - Mariposa County APCD Air District, Annual

5.2 Energy by Land Use - NaturalGas Unmitigated

NaturalGa ROG NOx CO SO2 Fugitive Exhaust PM10 Fugitive Exhaust PM2.5 Bio- CO2 NBio- CO2 Total CO2 CH4 N2O CO2e s Use PM10 PM10 Total PM2.5 PM2.5 Total

Land Use kBTU/yr tons/yr MT/yr

General Light 52950 2.9000e- 2.6000e- 2.1800e- 2.0000e- 2.0000e- 2.0000e- 2.0000e- 2.0000e- 0.0000 2.8256 2.8256 5.0000e- 5.0000e- 2.8424 Industry 004 003 003 005 004 004 004 004 005 005

Other Asphalt 0 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 Surfaces

Parking Lot 0 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000

Unrefrigerated 0 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 Warehouse-No Rail Total 2.9000e- 2.6000e- 2.1800e- 2.0000e- 2.0000e- 2.0000e- 2.0000e- 2.0000e- 0.0000 2.8256 2.8256 5.0000e- 5.0000e- 2.8424 004 003 003 005 004 004 004 004 005 005 CalEEMod Version: CalEEMod.2016.3.1 Page 25 of 34 Date: 10/22/2017 7:16 PM

Mariposa BioMass - Mariposa County APCD Air District, Annual

5.2 Energy by Land Use - NaturalGas Mitigated

NaturalGa ROG NOx CO SO2 Fugitive Exhaust PM10 Fugitive Exhaust PM2.5 Bio- CO2 NBio- CO2 Total CO2 CH4 N2O CO2e s Use PM10 PM10 Total PM2.5 PM2.5 Total

Land Use kBTU/yr tons/yr MT/yr

General Light 52950 2.9000e- 2.6000e- 2.1800e- 2.0000e- 2.0000e- 2.0000e- 2.0000e- 2.0000e- 0.0000 2.8256 2.8256 5.0000e- 5.0000e- 2.8424 Industry 004 003 003 005 004 004 004 004 005 005

Other Asphalt 0 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 Surfaces

Parking Lot 0 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000

Unrefrigerated 0 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 Warehouse-No Rail Total 2.9000e- 2.6000e- 2.1800e- 2.0000e- 2.0000e- 2.0000e- 2.0000e- 2.0000e- 0.0000 2.8256 2.8256 5.0000e- 5.0000e- 2.8424 004 003 003 005 004 004 004 004 005 005 CalEEMod Version: CalEEMod.2016.3.1 Page 26 of 34 Date: 10/22/2017 7:16 PM

Mariposa BioMass - Mariposa County APCD Air District, Annual

5.3 Energy by Land Use - Electricity Unmitigated

Electricity Total CO2 CH4 N2O CO2e Use

Land Use kWh/yr MT/yr

General Light 65400 19.0256 8.6000e- 1.8000e- 19.1002 Industry 004 004

Other Asphalt 0 0.0000 0.0000 0.0000 0.0000 Surfaces

Parking Lot 1760 0.5120 2.0000e- 0.0000 0.5140 005

Unrefrigerated 0 0.0000 0.0000 0.0000 0.0000 Warehouse-No Rail Total 19.5376 8.8000e- 1.8000e- 19.6142 004 004 CalEEMod Version: CalEEMod.2016.3.1 Page 27 of 34 Date: 10/22/2017 7:16 PM

Mariposa BioMass - Mariposa County APCD Air District, Annual

5.3 Energy by Land Use - Electricity Mitigated

Electricity Total CO2 CH4 N2O CO2e Use

Land Use kWh/yr MT/yr

General Light 65400 19.0256 8.6000e- 1.8000e- 19.1002 Industry 004 004

Other Asphalt 0 0.0000 0.0000 0.0000 0.0000 Surfaces

Parking Lot 1760 0.5120 2.0000e- 0.0000 0.5140 005

Unrefrigerated 0 0.0000 0.0000 0.0000 0.0000 Warehouse-No Rail Total 19.5376 8.8000e- 1.8000e- 19.6142 004 004

6.0 Area Detail

6.1 Mitigation Measures Area CalEEMod Version: CalEEMod.2016.3.1 Page 28 of 34 Date: 10/22/2017 7:16 PM

Mariposa BioMass - Mariposa County APCD Air District, Annual

ROG NOx CO SO2 Fugitive Exhaust PM10 Fugitive Exhaust PM2.5 Bio- CO2 NBio- CO2 Total CO2 CH4 N2O CO2e PM10 PM10 Total PM2.5 PM2.5 Total

Category tons/yr MT/yr

Mitigated 0.1229 1.0000e- 5.5000e- 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 1.0700e- 1.0700e- 0.0000 0.0000 1.1400e- 005 004 003 003 003

Unmitigated 0.1229 1.0000e- 5.5000e- 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 1.0700e- 1.0700e- 0.0000 0.0000 1.1400e- 005 004 003 003 003

6.2 Area by SubCategory Unmitigated

ROG NOx CO SO2 Fugitive Exhaust PM10 Fugitive Exhaust PM2.5 Bio- CO2 NBio- CO2 Total CO2 CH4 N2O CO2e PM10 PM10 Total PM2.5 PM2.5 Total

SubCategory tons/yr MT/yr

Architectural 0.0285 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 Coating

Consumer 0.0943 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 Products

Landscaping 5.0000e- 1.0000e- 5.5000e- 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 1.0700e- 1.0700e- 0.0000 0.0000 1.1400e- 005 005 004 003 003 003

Total 0.1229 1.0000e- 5.5000e- 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 1.0700e- 1.0700e- 0.0000 0.0000 1.1400e- 005 004 003 003 003 CalEEMod Version: CalEEMod.2016.3.1 Page 29 of 34 Date: 10/22/2017 7:16 PM

Mariposa BioMass - Mariposa County APCD Air District, Annual

6.2 Area by SubCategory Mitigated

ROG NOx CO SO2 Fugitive Exhaust PM10 Fugitive Exhaust PM2.5 Bio- CO2 NBio- CO2 Total CO2 CH4 N2O CO2e PM10 PM10 Total PM2.5 PM2.5 Total

SubCategory tons/yr MT/yr

Architectural 0.0285 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 Coating

Consumer 0.0943 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 Products

Landscaping 5.0000e- 1.0000e- 5.5000e- 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 1.0700e- 1.0700e- 0.0000 0.0000 1.1400e- 005 005 004 003 003 003

Total 0.1229 1.0000e- 5.5000e- 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 1.0700e- 1.0700e- 0.0000 0.0000 1.1400e- 005 004 003 003 003

7.0 Water Detail

7.1 Mitigation Measures Water CalEEMod Version: CalEEMod.2016.3.1 Page 30 of 34 Date: 10/22/2017 7:16 PM

Mariposa BioMass - Mariposa County APCD Air District, Annual

Total CO2 CH4 N2O CO2e

Category MT/yr

Mitigated 10.3222 0.1782 4.2800e- 16.0530 003

Unmitigated 10.3222 0.1782 4.2800e- 16.0530 003

7.2 Water by Land Use Unmitigated

Indoor/Out Total CO2 CH4 N2O CO2e door Use

Land Use Mgal MT/yr

General Light 3.46875 / 6.5607 0.1133 2.7200e- 10.2032 Industry 0 003

Other Asphalt 0 / 0 0.0000 0.0000 0.0000 0.0000 Surfaces

Parking Lot 0 / 0 0.0000 0.0000 0.0000 0.0000

Unrefrigerated 1.98875 / 3.7615 0.0649 1.5600e- 5.8498 Warehouse-No 0 003 Rail Total 10.3222 0.1782 4.2800e- 16.0530 003 CalEEMod Version: CalEEMod.2016.3.1 Page 31 of 34 Date: 10/22/2017 7:16 PM

Mariposa BioMass - Mariposa County APCD Air District, Annual

7.2 Water by Land Use Mitigated

Indoor/Out Total CO2 CH4 N2O CO2e door Use

Land Use Mgal MT/yr

General Light 3.46875 / 6.5607 0.1133 2.7200e- 10.2032 Industry 0 003

Other Asphalt 0 / 0 0.0000 0.0000 0.0000 0.0000 Surfaces

Parking Lot 0 / 0 0.0000 0.0000 0.0000 0.0000

Unrefrigerated 1.98875 / 3.7615 0.0649 1.5600e- 5.8498 Warehouse-No 0 003 Rail Total 10.3222 0.1782 4.2800e- 16.0530 003

8.0 Waste Detail

8.1 Mitigation Measures Waste CalEEMod Version: CalEEMod.2016.3.1 Page 32 of 34 Date: 10/22/2017 7:16 PM

Mariposa BioMass - Mariposa County APCD Air District, Annual

Category/Year

Total CO2 CH4 N2O CO2e

MT/yr

Mitigated 1.6402 0.0969 0.0000 4.0634

Unmitigated 1.6402 0.0969 0.0000 4.0634

8.2 Waste by Land Use Unmitigated

Waste Total CO2 CH4 N2O CO2e Disposed

Land Use tons MT/yr

General Light 0 0.0000 0.0000 0.0000 0.0000 Industry

Other Asphalt 0 0.0000 0.0000 0.0000 0.0000 Surfaces

Parking Lot 0 0.0000 0.0000 0.0000 0.0000

Unrefrigerated 8.08 1.6402 0.0969 0.0000 4.0634 Warehouse-No Rail Total 1.6402 0.0969 0.0000 4.0634 CalEEMod Version: CalEEMod.2016.3.1 Page 33 of 34 Date: 10/22/2017 7:16 PM

Mariposa BioMass - Mariposa County APCD Air District, Annual

8.2 Waste by Land Use Mitigated

Waste Total CO2 CH4 N2O CO2e Disposed

Land Use tons MT/yr

General Light 0 0.0000 0.0000 0.0000 0.0000 Industry

Other Asphalt 0 0.0000 0.0000 0.0000 0.0000 Surfaces

Parking Lot 0 0.0000 0.0000 0.0000 0.0000

Unrefrigerated 8.08 1.6402 0.0969 0.0000 4.0634 Warehouse-No Rail Total 1.6402 0.0969 0.0000 4.0634

9.0 Operational Offroad

Equipment Type Number Hours/Day Days/Year Horse Power Load Factor Fuel Type

Forklifts 1 24.00 310 89 0.20 Diesel

Tractors/Loaders/Backhoes 1 24.00 310 97 0.37 Diesel CalEEMod Version: CalEEMod.2016.3.1 Page 34 of 34 Date: 10/22/2017 7:16 PM

Mariposa BioMass - Mariposa County APCD Air District, Annual

UnMitigated/Mitigated

ROG NOx CO SO2 Fugitive Exhaust PM10 Fugitive Exhaust PM2.5 Bio- CO2 NBio- CO2 Total CO2 CH4 N2O CO2e PM10 PM10 Total PM2.5 PM2.5 Total

Equipment Type tons/yr MT/yr

Forklifts 0.0673 0.6064 0.5516 7.1000e- 0.0452 0.0452 0.0416 0.0416 0.0000 62.7577 62.7577 0.0203 0.0000 63.2651 004

Tractors/Loaders/ 0.0970 0.9749 1.0558 1.4400e- 0.0617 0.0617 0.0567 0.0567 0.0000 126.3621 126.3621 0.0409 0.0000 127.3838 Backhoes 003

Total 0.1643 1.5813 1.6073 2.1500e- 0.1068 0.1068 0.0983 0.0983 0.0000 189.1198 189.1198 0.0612 0.0000 190.6489 003

10.0 Stationary Equipment

Fire Pumps and Emergency Generators

Equipment Type Number Hours/Day Hours/Year Horse Power Load Factor Fuel Type

Boilers

Equipment Type Number Heat Input/Day Heat Input/Year Boiler Rating Fuel Type

User Defined Equipment

Equipment Type Number

11.0 Vegetation

APPENDIX C

Health Risk Assessment Modeling Results

Mariposa Biomass Project Emissions Modeling November 2017

Plant Operational Parameters Hours of Operation per Day 24 Days of Operation per Year 310 Hours of Operation per Year 7440 Number of Engines 2

Engine Fuel Consumption Heat Input (Mbtu/hr) 13614 Heat Input (MMBtu/hr) 13.6 Heat Input (MMBtu/yr) 101288 Gas Volume Input (MMscf/hr) 0.0425 Gas Volume Input (MMscf/yr) 316 Note: Data taken from Engine Specification Sheet

WoodRoll System Fuel Consumption Heat Input (MMBtu/hr) 25.6 Heat Input (MMBtu/yr) 190464 Gas Volume Input (MMscf/hr) 0.0800 Gas Volume Input (MMscf/yr) 595

BioGas Heat Content Fuel Gas LHV (MMBtu/MMscf) 291 Fuel Gas HHV (MMBtu/MMscf) 320 Note: HHV is assumed to be 110% of the LHV

Emission Factor Per Engine WoodRoll System Total Emissions Substances CAS# lbs/MMscf lbs/hr tons/yr lbs/hr tons/yr lbs/hr tons/yr 1,3-Butadiene 106990 2.43E-02 1.03E-03 3.84E-03 1.94E-03 7.23E-03 4.01E-03 1.49E-02 1,4-Dioxane 123911 8.70E-03 3.70E-04 1.38E-03 6.96E-04 2.59E-03 1.44E-03 5.34E-03 Acetaldehyde 75070 6.24E-02 2.65E-03 9.87E-03 4.99E-03 1.86E-02 1.03E-02 3.83E-02 Acrolein 107028 1.42E-02 6.05E-04 2.25E-03 1.14E-03 4.23E-03 2.35E-03 8.73E-03 Benzene 71432 1.70E+00 7.22E-02 2.69E-01 1.36E-01 5.05E-01 2.80E-01 1.04E+00 Carbon tetrachloride 56235 4.44E-03 1.89E-04 7.02E-04 3.55E-04 1.32E-03 7.33E-04 2.73E-03 Chloroform 67663 8.82E-03 3.75E-04 1.40E-03 7.05E-04 2.62E-03 1.46E-03 5.41E-03 Ethylene dibromide 106934 4.36E-03 1.85E-04 6.89E-04 3.48E-04 1.30E-03 7.19E-04 2.67E-03 Ethylene dichloride 107062 4.42E-03 1.88E-04 6.99E-04 3.53E-04 1.31E-03 7.29E-04 2.71E-03 Formaldehyde 50000 1.80E+00 7.66E-02 2.85E-01 1.44E-01 5.36E-01 2.97E-01 1.11E+00 Methylchloroform 71556 8.88E-03 3.78E-04 1.40E-03 7.10E-04 2.64E-03 1.47E-03 5.45E-03 Methylene chloride 75092 8.76E-02 3.73E-03 1.39E-02 7.01E-03 2.61E-02 1.45E-02 5.38E-02 p-Dichlorobenzene 106467 4.28E-02 1.82E-03 6.78E-03 3.43E-03 1.27E-02 7.07E-03 2.63E-02 Perchloroethylene 127184 9.00E-03 3.83E-04 1.42E-03 7.20E-04 2.68E-03 1.49E-03 5.53E-03 Styrene 100425 3.31E-02 1.41E-03 5.24E-03 2.65E-03 9.85E-03 5.47E-03 2.03E-02 Toluene 108883 7.44E-01 3.16E-02 1.18E-01 5.95E-02 2.21E-01 1.23E-01 4.57E-01 Trichloroethylene 79016 8.76E-03 3.73E-04 1.39E-03 7.01E-04 2.61E-03 1.45E-03 5.38E-03 Vinyl Chloride 75014 1.14E-02 4.85E-04 1.80E-03 9.12E-04 3.39E-03 1.88E-03 7.00E-03 Vinylidene Chloride 75354 4.51E-03 1.92E-04 7.13E-04 3.60E-04 1.34E-03 7.44E-04 2.77E-03 Xylene 1330207 1.60E-01 6.81E-03 2.53E-02 1.28E-02 4.77E-02 2.64E-02 9.84E-02 Note: Emission factors from SJVAPCD Toxic Emission Factors for a digester gas-fired internal combustion engine with no VOC control. Mariposa BioMass Project Emissions November 2017

Engine 1 Modeling Parameters Stack Height (m) 18.288 Stack Outer Diameter (m) 1.4 Stack Inner Diameter (m) 1.0 Exhaust Gas Flow Rate (m3/hr) 17145.4 Exhaust Velocity (m/s) 6.06 Exhaust Temperature © 220

Note: Exhaust gas flow rate from Engine Specifications multiplied by two to account for two engines

Sensitive Receptor X Y John C. Fremont Healthcare District 236771 4154564 Mariposa Elementary School 237913 4153246 Mariposa Biomass Project Emissions Modeling Results November 2017

Risk Impacts Value Rec Number X Y Cancer Risk at PMI (per million) 21.7 274 233850 4155050 Cancer Risk at MEIR (per million) 2.4 1754 234550 4155150 Cancer Risk at Sensitive (per million) 0.4 5402 237913 4153246 Cancer Risk at MEIW (per million) 1.8 274 233850 4155050 Chronic Risk at PMI 0.079 274 233850 4155050 Chronic Risk at MEIR 0.009 1754 234550 4155150 Chronic Risk at Sensitive 0.001 5402 237913 4153246 Chronic Risk at MEIW 0.079 274 233850 4155050 Acute Risk at PMI 0.278 1754 234550 4155150 Acute Risk at MEIR 0.278 1754 234550 4155150 Acute Risk at Sensitive 0.019 5402 237913 4153246 Acute Risk at MEIW 0.278 1754 234550 4155150