Integrated Management of Agricultural Land Pollution (P153115) Procurement Plan

I. General

Public Disclosure Authorized 1. Bank’s approval Date of the procurement Plan Plan [original: June 27, 2017; 1st Revision: August 17, 2017; 2nd Revision: June 8, 2018; 3rd Revision: Aug. 10, 2018; 4th Revision: April 4, 2019; 5th Revision: December 20, 2019; 6th Revision: March 4, 2020; 7th Revision: March 30, 2020; 8th Revision: April 9, 2020; 9th Revision: May 21, 2020; 10th Update: June 5, 2020] 2. Date of General Procurement Notice: August 16, 2017 3. Period covered by this procurement plan: June 2020 to December 2020

II. Goods, Works, non-consulting services and Community participation in procurement under Component 1.

Public Disclosure Authorized 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Threshold Procurement Method Threshold US$ US$ ICB and LIB (Goods and Non- Greater than or equal to US$ 1. All Consulting Services ) 10 million NCB (Goods and Non-Consulting Greater than or equal to US$ Greater than or equal to 2. Services ) 0.5 million 2 million Greater than or equal to US$ 3. ICB (Works) All 40 million Greater than or equal to US$ Greater than or equal to 4. NCB (Works) 0.5 million 10 million

Public Disclosure Authorized Community participation in to be specified in the 5 No Threshold procurement operation manual

2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines.

3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: Detailed procedures for community participation are specified in operation manual.

4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project P153115 has been prepared by Hunan PPMO. Public Disclosure Authorized 5. Any Other Special Procurement Arrangements [including advance procurement and retroactive financing, if applicable]: None

6 Summary of the Procurement Packages planned during June 2020 to December 2020 . 1 2 3 4 5 6 7

Ref. Description Estimated Packages Domestic Review Comments No. Cost Preference by Bank US$ (yes/no) (Prior / thousand Post) Summary of the National Competitive Bidding (Works) Summary of the Shopping (Works) Summary of the National Competitive Bidding (Goods) Summary of the Shopping 82.08 2 Post (Goods) Summary of the Shopping (Non- Consultant Services) Cancellation (Works) Cancellation (Goods)

III. Selection of Consultants

1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants:

Selection Method Prior Review Threshold Comments 1. Competitive Methods (Firms) Greater than or equal to US$ 1,000,000 2. Single Source (Firms) Greater than or equal to US$ 1,000,000 3. Individual Greater than or equal to US$ 300,000

2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_500,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines.

3. Any Other Special Selection Arrangements [including advance procurement and retroactive financing, if applicable or delete if not applicable]: None

4. Consultancy Assignments with Selection Methods and Time Schedule

1 2 3 4 5 6

Estimated Review Description of Ref. No. Cost by Bank Assignment Packages Comments US$ (Prior / thousand Post) Summary of number of contracts that will be let under QCBS Summary of number of contracts that 85,075 1 IC will be let under other methods Cancellation PROCUREMENT : Hunan Integrated Management of Agricultural Land Pollution Project PLAN General Information

Country: China Bank’s Approval Date of the Original Procurement Plan: 2017-09-04 Revised Plan Date(s): (comma delineated, leave blank if none)2020-11-19 Project ID: P153115 GPN Date: 2017-08-16 Project Name: Hunan Integrated Management of Agricultural Land Pollution Project Loan / Credit No: IBRD / 87770, / Executing Agency(ies): Hunan Integrated Management of Agriculture PMO

WORKS Bid Evaluation Activity Reference No. / Procurement Estimated Actual Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalification High SEA/SH Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and Contract Description Component Review Type Method Document Amount Amount qualification Document / Signed Contract No. Approach Process (Y/N) Risk Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for Completion Type (US$) (US$) Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned

HNYDG001 / Construction Component 1: Under of drainage ditches, Demonstration of Risk- Request for Single Stage - One IBRD / 87770 Post Limited 495,870.00 0.00 Implementa 2017-09-15 2019-01-10 2017-11-10 2018-05-09 irrigation ditches, sand and based Agricultural Land Quotations Envelope tion gravel traps. Pollution Management.

HNYXG001 / Construction Component 1: of irrigation ditches, sand Demonstration of Risk- Request for Single Stage - One IBRD / 87770 Post Limited 347,610.00 0.00 Canceled 2017-09-15 2017-11-10 2018-05-09 and gravel traps, field based Agricultural Land Quotations Envelope roads. Pollution Management.

Component 1: HNYXG002 / Construction Demonstration of Risk- Request for Single Stage - One of drainage ditches, sand IBRD / 87770 Post Limited 171,190.00 0.00 Canceled 2017-09-15 2017-11-10 2018-05-09 based Agricultural Land Quotations Envelope and gravel traps. Pollution Management.

HNYXG003 / Construction of irrigation ditches, Component 1: drainage ditches, sand and Demonstration of Risk- Request for Single Stage - One IBRD / 87770 Post Limited 419,250.00 0.00 Canceled 2017-09-15 2017-11-10 2018-05-09 gravel traps, ecological based Agricultural Land Quotations Envelope interception ditches and Pollution Management. pumping stations.

Component 1: HNYXG004 / Construction Demonstration of Risk- Request for Single Stage - One of irrigation ditches, sand IBRD / 87770 Post Limited 60,150.00 0.00 Canceled 2017-09-15 2017-11-10 2018-05-09 based Agricultural Land Quotations Envelope and gravel traps. Pollution Management.

Component 1: HNYXG005 / Construction Demonstration of Risk- Request for Single Stage - One of irrigation ditches and IBRD / 87770 Post Limited 224,030.00 0.00 Canceled 2017-09-15 2017-11-10 2018-05-09 based Agricultural Land Quotations Envelope drainage ditches. Pollution Management.

Component 1: HNHYG001 / Construction Demonstration of Risk- Request for Single Stage - One of irrigation canals and IBRD / 87770 Post Limited 310,700.00 0.00 Canceled 2017-10-10 2017-12-05 2018-06-03 based Agricultural Land Quotations Envelope ditches Pollution Management.

Component 1: HNHYG002 / Construction Demonstration of Risk- Request for Single Stage - One of irrigation canals and IBRD / 87770 Post Limited 105,100.00 0.00 Canceled 2017-10-10 2017-12-05 2018-06-03 based Agricultural Land Quotations Envelope ditches. Pollution Management.

Component 1: HNHYG003 / Construction Demonstration of Risk- Request for Single Stage - One of irrigation canals and IBRD / 87770 Post Limited 154,210.00 0.00 Canceled 2017-10-10 2017-12-05 2018-06-03 based Agricultural Land Quotations Envelope ditches. Pollution Management.

Component 1: HNHYG004 / Construction Demonstration of Risk- Request for Single Stage - One of Sand and gravel traps IBRD / 87770 Post Limited 118,340.00 0.00 Canceled 2017-10-10 2017-12-05 2018-06-03 based Agricultural Land Quotations Envelope &Field roads. Pollution Management.

HNHNG001 / Construction Component 1: of irrigation system, gravel Demonstration of Risk- Single Stage - One or dirt road, Sediment IBRD / 87770 Post Request for Bids Open - National 1,048,810.00 0.00 Canceled 2019-03-01 2019-03-06 2019-04-17 2019-05-17 2019-06-21 2020-06-21 based Agricultural Land Envelope desilting and landfill in Pollution Management. .

Page 1 HNZFG001 / Construction Component 1: of irrigation system, gravel Under Demonstration of Risk- Request for Single Stage - One or dirt road, Sediment IBRD / 87770 Post Open - National 302,990.00 0.00 Implementa 2019-03-06 2019-05-01 2019-12-27 based Agricultural Land Quotations Envelope desilting and landfill in tion Pollution Management. .

HNZFG002 / Construction Component 1: of irrigation system, gravel Under Demonstration of Risk- Request for Single Stage - One or dirt road, Sediment IBRD / 87770 Post Open - National 320,930.00 0.00 Implementa 2019-03-06 2019-05-01 2019-12-27 based Agricultural Land Quotations Envelope desilting and landfill in tion Pollution Management. Zhongfang county.

HNLSTG001 / Construction Component 1: of irrigation system, gravel Demonstration of Risk- Single Stage - One or dirt road, Sediment IBRD / 87770 Post Request for Bids Open - National 888,370.00 0.00 Canceled 2019-03-01 2019-03-06 2019-04-17 2019-05-17 2019-06-21 2020-06-21 based Agricultural Land Envelope desilting and landfill in Pollution Management. Leng Shuitan county.

HNYSG001 / Construction Component 1: of irrigation system ,gravel Under Demonstration of Risk- Request for Single Stage - One or dirt road, sediment IBRD / 87770 Post Open - National 452,330.00 0.00 Implementa 2019-03-06 2019-05-01 2019-11-01 based Agricultural Land Quotations Envelope desilting and landfill in tion Pollution Management. .

Component 2: HNHYG004-1 / Under Strengthening Agricultural Request for Single Stage - One Reconstruction of heavy IBRD / 87770 Post Open - National 32,240.00 0.00 Implementa 2019-04-04 2019-05-30 2019-11-26 Environmental Monitoring Quotations Envelope metal detection laboratory. tion and Management.

HNHYG002-1 / Component 1: Construction of Irrigation Demonstration of Risk- Request for Single Stage - One IBRD / 87770 Post Open - National 123,000.00 0.00 Canceled 2019-03-06 2019-05-01 2020-05-01 system and gravel or dirt based Agricultural Land Quotations Envelope road in county. Pollution Management.

HNHYG003-1 / Component 1: Construction of Irrigation Demonstration of Risk- Request for Single Stage - One IBRD / 87770 Post Open - National 375,480.00 0.00 Canceled 2019-03-06 2019-05-01 2020-05-01 system and gravel or dirt based Agricultural Land Quotations Envelope road in . Pollution Management.

HNCLG001 / Construction Component 1: of irrigation system, gravel Under Demonstration of Risk- Request for Single Stage - One or dirt road, Sediment IBRD / 87770 Post Open - National 476,110.00 0.00 Implementa 2019-10-15 2019-12-10 2020-08-06 based Agricultural Land Quotations Envelope desilting and landfill in Cili tion Pollution Management. county.

HNCLG003 / Construction Component 1: of irrigation system, gravel Under Demonstration of Risk- Request for Single Stage - One or dirt road, Sediment IBRD / 87770 Post Open - National 333,760.00 0.00 Implementa 2019-10-15 2019-12-10 2020-08-06 based Agricultural Land Quotations Envelope desilting and landfill in Cili tion Pollution Management. county.

HNCLG004 / Construction Component 1: of irrigation system, gravel Under Demonstration of Risk- Request for Single Stage - One or dirt road, Sediment IBRD / 87770 Post Open - National 320,560.00 0.00 Implementa 2019-10-15 2019-12-10 2020-08-06 based Agricultural Land Quotations Envelope desilting and landfill in Cili tion Pollution Management. county.

HNCLG005 / Construction Component 1: of irrigation system, gravel Under Demonstration of Risk- Request for Single Stage - One or dirt road, Sediment IBRD / 87770 Post Open - National 90,710.00 0.00 Implementa 2019-10-15 2019-12-10 2020-08-06 based Agricultural Land Quotations Envelope desilting and landfill in Cili tion Pollution Management. county.

HNCLG002-1 / Component 1: Construction of irrigation Under Demonstration of Risk- Single Stage - One system, gravel or dirt road, IBRD / 87770 Post Request for Bids Open - National 653,460.00 0.00 Implementa 2019-10-10 2019-12-16 2019-10-15 2019-11-26 2020-01-10 2019-12-26 2020-01-10 2020-01-30 2020-09-26 based Agricultural Land Envelope Sediment desilting and tion Pollution Management. landfill in .

HNCLG002 / Construction Component 1: of irrigation system, gravel Demonstration of Risk- Request for Single Stage - One or dirt road, Sediment IBRD / 87770 Post Open - National 492,150.00 0.00 Canceled 2019-10-15 2019-12-10 2020-08-06 based Agricultural Land Quotations Envelope desilting and landfill in Cili Pollution Management. county.

HNBJG001-1 / Component 1: Construction of irrigation Under Demonstration of Risk- Request for Single Stage - One system ,gravel or dirt road, IBRD / 87770 Post Open - National 286,570.00 0.00 Implementa 2019-10-20 2019-12-15 2020-06-12 based Agricultural Land Quotations Envelope sediment desilting and tion Pollution Management. landfill in .

Page 2 HNBJG001 / Construction Component 1: of irrigation system ,gravel Demonstration of Risk- Single Stage - One or dirt road, sediment IBRD / 87770 Post Request for Bids Open - National 672,420.00 0.00 Canceled 2019-03-01 2019-03-06 2019-04-17 2019-05-17 2019-06-21 2019-12-21 based Agricultural Land Envelope desilting and landfill in Pollution Management. Baojing county .

HNQYG002 / Construction Component 1: Under of irrigation system and a Demonstration of Risk- Request for Single Stage - One IBRD / 87770 Post Limited 432,840.00 0.00 Implementa 2019-12-15 2020-02-09 2021-02-08 gravel or dirt road in based Agricultural Land Quotations Envelope tion county . Pollution Management.

HNQYG003 / Construction Component 1: Under of irrigation system and a Demonstration of Risk- Request for Single Stage - One IBRD / 87770 Post Limited 328,360.00 0.00 Implementa 2019-12-15 2020-02-09 2021-02-08 gravel or dirt road in based Agricultural Land Quotations Envelope tion Qiyang county . Pollution Management.

HNHNG002 / Construction Component 1: of irrigation system, gravel Under Demonstration of Risk- Request for Single Stage - One or dirt road, Sediment IBRD / 87770 Post Open - National 291,040.00 0.00 Implementa 2019-11-15 2020-04-26 2020-01-10 2020-07-08 based Agricultural Land Quotations Envelope desilting and landfill in tion Pollution Management. Hengnan county.

HNHYG001-1 / Construction of irrigation Component 1: Under system and gravel or dirt Demonstration of Risk- Single Stage - One IBRD / 87770 Post Request for Bids Open - National 880,000.00 0.00 Implementa 2019-03-01 2020-06-18 2019-03-06 2019-04-17 2020-07-23 2019-05-17 2020-07-23 2019-06-21 2020-06-21 road in Tai Yuan based Agricultural Land Envelope tion demostration area of Pollution Management. Hengyang county.

HNHYG002-2 / Component 1: Construction of irrigation Under Demonstration of Risk- Request for Single Stage - One system and gravel or dirt IBRD / 87770 Post Limited 344,780.00 0.00 Implementa 2019-12-06 2019-12-23 2020-01-31 2021-01-30 based Agricultural Land Quotations Envelope road in Xi Du demostration tion Pollution Management. area of Hengyang county.

HNHYG003-2 / Construction of irrigation Component 1: Under system and gravel or dirt Demonstration of Risk- Request for Single Stage - One IBRD / 87770 Post Limited 246,270.00 0.00 Implementa 2019-12-06 2019-12-23 2020-01-31 2021-01-30 road in Hong Shi based Agricultural Land Quotations Envelope tion demostration area of Pollution Management. Hengyang county.

HNQYG001 / Construction Component 1: Pending of irrigation system and a Demonstration of Risk- Request for Single Stage - One IBRD / 87770 Post Open - National 253,700.00 0.00 Implementa 2020-01-06 2020-03-02 2021-03-02 gravel or dirt road in based Agricultural Land Quotations Envelope tion Qiyang county . Pollution Management.

HNHNG003 / Construction Component 1: of irrigation system, gravel Under Demonstration of Risk- Request for Single Stage - One or dirt road, Sediment IBRD / 87770 Post Limited 388,060.00 0.00 Implementa 2020-01-04 2020-01-15 2020-02-29 2021-02-28 based Agricultural Land Quotations Envelope desilting and landfill in tion Pollution Management. Hengnan county.

HNHNG004 / Construction Component 1: of irrigation system, gravel Under Demonstration of Risk- Request for Single Stage - One or dirt road, Sediment IBRD / 87770 Post Limited 462,690.00 0.00 Implementa 2020-01-04 2020-04-15 2020-02-29 2021-02-28 based Agricultural Land Quotations Envelope desilting and landfill in tion Pollution Management. Hengnan county.

HNYZG001 / Construction Component 1: Pending of irrigation system and a Demonstration of Risk- Request for Single Stage - One IBRD / 87770 Post Limited 490,000.00 0.00 Implementa 2020-03-15 2020-05-10 2021-05-10 gravel or dirt road etc. in based Agricultural Land Quotations Envelope tion . Pollution Management.

HNYDG002 / Field Engineering Construction of Wentang Neighborhood Component 1: Pending Committee, Taiping Village, Demonstration of Risk- Request for Single Stage - One IBRD / 87770 Post Open - National 477,610.00 0.00 Implementa 2020-03-15 2020-05-10 2021-05-10 Heitan Village, based Agricultural Land Quotations Envelope tion Dingjiazhuang Village and Pollution Management. Bajiao Village in yongding county.

HNYDG003 / Field Component 1: Engineering Construction of Pending Demonstration of Risk- Request for Single Stage - One Changtan Village, Hongxing IBRD / 87770 Post Open - National 465,670.00 0.00 Implementa 2020-03-15 2020-05-10 2021-05-10 based Agricultural Land Quotations Envelope Village and Gaoping Village tion Pollution Management. in yongding county

Page 3 HNAHG001 / Construction Component 1: of irrigation system, gravel Pending Demonstration of Risk- Single Stage - One or dirt road, Sediment IBRD / 87770 Post Request for Bids Open - National 655,070.00 0.00 Implementa 2020-04-10 2020-04-15 2020-05-27 2020-06-26 2020-07-31 2021-07-31 based Agricultural Land Envelope desilting etc. in Anhua tion Pollution Management. county.

HNAHG002 / Construction Component 1: of irrigation system, gravel Pending Demonstration of Risk- Request for Single Stage - One or dirt road, Sediment IBRD / 87770 Post Limited 209,130.00 0.00 Implementa 2020-04-15 2020-06-10 2021-06-10 based Agricultural Land Quotations Envelope desilting etc. in Anhua tion Pollution Management. county.

HNAHG003 / Construction Component 1: of irrigation system, gravel Pending Demonstration of Risk- Request for Single Stage - One or dirt road, Sediment IBRD / 87770 Post Limited 200,600.00 0.00 Implementa 2020-04-15 2020-06-10 2021-06-10 based Agricultural Land Quotations Envelope desilting etc. in Anhua tion Pollution Management. county.

HNANG004 / Construction Component 1: of irrigation system, gravel Pending Demonstration of Risk- Request for Single Stage - One or dirt road, Sediment IBRD / 87770 Post Limited 228,130.00 0.00 Implementa 2020-04-15 2020-06-10 2021-06-10 based Agricultural Land Quotations Envelope desilting etc. in Anhua tion Pollution Management. county.

HNAHG005 / Construction Component 1: of irrigation system, gravel Pending Demonstration of Risk- Request for Single Stage - One or dirt road, Sediment IBRD / 87770 Post Limited 357,610.00 0.00 Implementa 2020-04-15 2020-06-10 2021-06-10 based Agricultural Land Quotations Envelope desilting etc. in Anhua tion Pollution Management. county.

HNQYG004 / Construction Component 1: Under of irrigation system and a Demonstration of Risk- Request for Single Stage - One IBRD / 87770 Post Limited 193,880.00 0.00 Implementa 2020-04-15 2020-06-10 2021-06-10 gravel or dirt road in based Agricultural Land Quotations Envelope tion Qiyang county . Pollution Management.

Component 1: HNLSTG002 / Construction Under Demonstration of Risk- Request for Single Stage - One of field engineering in IBRD / 87770 Post Limited 455,220.00 0.00 Implementa 2020-06-04 2020-09-15 2020-07-30 2021-01-26 based Agricultural Land Quotations Envelope Leng Shuitan county. tion Pollution Management.

HNXXHYG002 / Component 1: Construction of irrigation Under Demonstration of Risk- Request for Single Stage - One system, gravel or dirt road, IBRD / 87770 Post Open - National 368,510.00 0.00 Implementa 2020-09-15 2020-11-10 2021-05-09 based Agricultural Land Quotations Envelope Sediment desilting and tion Pollution Management. landfill in .

HNXXHYG001 / Component 1: Construction of irrigation Under Demonstration of Risk- Request for Single Stage - One system, gravel or dirt road, IBRD / 87770 Post Open - National 412,240.00 0.00 Implementa 2020-09-15 2020-11-10 2021-05-09 based Agricultural Land Quotations Envelope Sediment desilting and tion Pollution Management. landfill in Huayuan county.

HNXXHYG003 / Component 1: Pending Construction of field Demonstration of Risk- Request for Single Stage - One IBRD / 87770 Post Limited 497,310.00 0.00 Implementa 2020-09-15 2020-11-10 2021-05-09 engineering in huayuan based Agricultural Land Quotations Envelope tion county. Pollution Management.

Component 1: HNBJG002 / Construction Pending Demonstration of Risk- Request for Single Stage - One of field engineering in IBRD / 87770 Post Open - National 298,280.00 0.00 Implementa 2020-10-25 2020-12-20 2021-06-18 based Agricultural Land Quotations Envelope Baojing county. tion Pollution Management.

Component 1: HNLWG002 / Construction Pending Demonstration of Risk- Request for Single Stage - One of field engineering in lin IBRD / 87770 Post Open - National 434,300.00 0.00 Implementa 2020-11-05 2020-12-31 2021-12-31 based Agricultural Land Quotations Envelope wu county tion Pollution Management.

Component 1: HNLWG003 / Construction Pending Demonstration of Risk- Request for Single Stage - One of field engineering in lin IBRD / 87770 Post Open - National 338,300.00 0.00 Implementa 2020-11-05 2020-12-31 2021-12-31 based Agricultural Land Quotations Envelope wu county tion Pollution Management.

Component 1: HNLWG004 / Construction Pending Demonstration of Risk- Request for Single Stage - One of field engineering in lin IBRD / 87770 Post Open - National 308,000.00 0.00 Implementa 2020-11-05 2020-12-31 2021-12-31 based Agricultural Land Quotations Envelope wu county. tion Pollution Management.

Component 1: HNLWG001 / Construction Pending Demonstration of Risk- Request for Single Stage - One of field engineering in lin IBRD / 87770 Post Open - National 498,510.00 0.00 Implementa 2020-12-05 2021-01-30 2021-07-29 based Agricultural Land Quotations Envelope wu county tion Pollution Management.

Page 4 GOODS Bid Evaluation Activity Reference No. / Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and Description Component Review Type Method qualification Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual

HNH002 / Procurement of sampling inspection vehicles Component 2: to facilitate project Strengthening Agricultural Request for Single Stage - One / Post Limited 492,540.00 0.00 Canceled 2017-12-13 2018-02-07 2018-08-06 management and supervion Environmental Monitoring Quotations Envelope and sample transpotation in and Management. 15 project counties.

Component 1: HNHYH002 / Procurement Demonstration of Risk- Request for Single Stage - One of comprehensive pest and IBRD / 87770 Post Open - National 360,300.00 0.00 Canceled 2019-03-06 2019-05-01 2019-12-27 based Agricultural Land Quotations Envelope disease control equipment. Pollution Management.

HNH001 / Procurement of desktop computers , laptops , multi func printers , scanners, digital cameras , Component 2: Under DVs , projectors , GPS Strengthening Agricultural Request for Single Stage - One IBRD / 87770 Post Limited 149,250.00 0.00 Implementati 2019-03-06 2019-06-26 2019-05-01 2019-07-30 locators , projection screens Environmental Monitoring Quotations Envelope on and digital recorders , and Management. which aims to promote the management efficency and ability of PMO staffs

HNHYH001 / Procurement Component 2: Under of testing equipment for the Strengthening Agricultural Request for Single Stage - One IBRD / 87770 Post Open - National 303,300.00 0.00 Implementati 2019-04-04 2019-05-30 2019-11-26 Agricultural Bureau in Environmental Monitoring Quotations Envelope on Hengyang County. and Management.

HNH003 / Procurement of desktop computers , laptops , multi func printers , scanners, digital cameras , Component 2: Under DVs , projectors , GPS Strengthening Agricultural Request for Single Stage - One IBRD / 87770 Post Open - National 74,630.00 0.00 Implementati 2019-10-25 2019-12-20 2020-02-18 locators , etc. , which aims Environmental Monitoring Quotations Envelope on to promote the management and Management. efficency and ability of and Yizhang county PMO staffs.

HNYSH001 / Procurement Component 1: Under of comprehensive pest and Demonstration of Risk- Request for Single Stage - One IBRD / 87770 Post Open - National 119,400.00 0.00 Implementati 2020-03-15 2020-05-10 2020-10-31 disease control equipment in based Agricultural Land Quotations Envelope on Yongshun county. Pollution Management.

HNLWH001 / Procurement Component 1: Pending of integrated pest control Demonstration of Risk- Request for Single Stage - One IBRD / 87770 Post Limited 29,850.00 0.00 Implementati 2020-03-15 2020-05-10 2020-11-06 equipment for Linwu based Agricultural Land Quotations Envelope on county. Pollution Management.

HNHYH003 / Procurement Component 1: of comprehensive Under Demonstration of Risk- Single Stage - One agricultural pest and IBRD / 87770 Post Request for Bids Open - National 358,210.00 0.00 Implementati 2020-04-15 2020-09-11 2020-04-20 2020-06-01 2020-10-15 2020-07-01 2020-10-15 2020-08-05 2021-08-05 based Agricultural Land Envelope disease control equipment in on Pollution Management. Hengyang county .

HNAHH001 / Procurement Component 1: of comprehensive Pending Demonstration of Risk- Request for Single Stage - One agricultural pest and IBRD / 87770 Post Limited 141,790.00 0.00 Implementati 2020-04-20 2020-06-15 2021-06-15 based Agricultural Land Quotations Envelope disease control equipment in on Pollution Management. Anhua county .

HNQYH001 / Procurement Component 1: of comprehensive Under Demonstration of Risk- Request for Single Stage - One agricultural pest and IBRD / 87770 Post Limited 41,790.00 0.00 Implementati 2020-04-20 2020-05-28 2020-06-15 2021-06-15 based Agricultural Land Quotations Envelope disease control equipment in on Pollution Management. Qiyang county .

Component 2: HNQYH002 / Procurement Under Strengthening Agricultural Request for Single Stage - One of heavy metal detector in IBRD / 87770 Post Open - National 67,160.00 0.00 Implementati 2020-06-04 2020-07-30 2020-08-29 Environmental Monitoring Quotations Envelope Qiyang county. on and Management.

Page 5 Component 2: HNBJH001 / Procurement Under Strengthening Agricultural Request for Single Stage - One of heavy metal detector in IBRD / 87770 Post Open - National 67,160.00 0.00 Implementati 2020-06-04 2020-07-30 2020-08-29 Environmental Monitoring Quotations Envelope Baojing county. on and Management.

Component 2: HNXXHYH001 / Under Strengthening Agricultural Request for Single Stage - One Procurement of heavy metal IBRD / 87770 Post Limited 67,160.00 0.00 Implementati 2020-06-15 2020-07-03 2020-08-10 2020-09-09 Environmental Monitoring Quotations Envelope detector in Huayuan county. on and Management.

Component 1: Pending HNLWH002 / Procurement Demonstration of Risk- Request for IBRD / 87770 Post 14,920.00 0.00 Implementati 2020-06-15 2020-08-10 2020-09-09 of straw baler based Agricultural Land Quotations on Pollution Management.

HNYSH002 / Procurement Component 2: Pending of heavy metal rapid Strengthening Agricultural Request for Single Stage - One IBRD / 87770 Post Open - National 67,160.00 0.00 Implementati 2020-07-10 2020-09-04 2020-10-04 measuring instrument in Environmental Monitoring Quotations Envelope on Yongshun county . and Management.

Component 1: HNQYH003 / Procument of Under Demonstration of Risk- Request for Single Stage - One machine for straw baling in IBRD / 87770 Post Open - National 38,800.00 0.00 Implementati 2020-07-25 2020-09-19 2020-10-19 based Agricultural Land Quotations Envelope Qiyang county. on Pollution Management.

Component 1: HNCLH002 / Procument of Under Demonstration of Risk- Request for Single Stage - One machine for straw baling in IBRD / 87770 Post Open - National 26,870.00 0.00 Implementati 2020-07-25 2020-09-19 2020-10-19 based Agricultural Land Quotations Envelope Cili county. on Pollution Management.

Component 2: HNCLH001 / Procurement Under Strengthening Agricultural Request for Single Stage - One of heavy metal detector in IBRD / 87770 Post Open - National 67,160.00 0.00 Implementati 2020-07-25 2020-09-19 2020-10-19 Environmental Monitoring Quotations Envelope Cili county. on and Management.

HNAHH002 / Procurement Component 2: Pending of heavy metal detection Strengthening Agricultural Request for Single Stage - One IBRD / 87770 Post Open - National 398,210.00 0.00 Implementati 2020-07-25 2020-09-19 2021-03-18 laboratory instruments and Environmental Monitoring Quotations Envelope on equipment in Anhua county. and Management.

NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and Description Component Review Type Method qualification Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual

Component 1: HNYDFZ001 / Sampling Demonstration of Risk- Request for Single Stage - One from fields and detection of IBRD / 87770 Post Limited 28,940.00 0.00 Canceled 2017-09-15 2017-11-10 2018-05-09 based Agricultural Land Quotations Envelope the samples. Pollution Management.

HNYXFZ001 / Detection of agricultural products, Component 1: irrigation water, Demonstration of Risk- Request for Single Stage - One underground water, air, IBRD / 87770 Post Limited 13,490.00 0.00 Canceled 2017-09-15 2017-11-10 2018-05-09 based Agricultural Land Quotations Envelope sediment, organic fertilizer, Pollution Management. and pesticides for heavy matal determination.

HNHYFZ001 / detection of agricultural products, Component 1: irrigation water, Demonstration of Risk- Request for Single Stage - One underground water, air, IBRD / 87770 Post Limited 155,010.00 0.00 Canceled 2017-09-15 2017-11-10 2018-05-09 based Agricultural Land Quotations Envelope sediment, organic fertilizer, Pollution Management. and pesticides for heavy matal determination.

HNYDFZ002 / detection of agricultural products, Component 1: irrigation water, Demonstration of Risk- Request for Single Stage - One underground water, air, IBRD / 87770 Post Limited 92,250.00 0.00 Canceled 2017-09-15 2017-11-10 2018-05-09 based Agricultural Land Quotations Envelope sediment, organic fertilizer, Pollution Management. and pesticides for heavy matal determination

Page 6 HNYDFZ002-2-2 / Sampling of water, soil, Component 1: crops, sediments, agriculture Under Demonstration of Risk- Request for Single Stage - One inputs, atmosphere IBRD / 87770 Post Limited 121,190.00 0.00 Implementati 2018-03-10 2018-09-06 2018-05-05 2019-06-30 based Agricultural Land Quotations Envelope deposition, etc. in Yongding on Pollution Management. District and detection of the samples.

HNYXFZ001-2-2 / Sampling of water, soil, crops, Component 1: sediments,agriculture inputs, Demonstration of Risk- Request for Single Stage - One IBRD / 87770 Post Limited 36,790.00 0.00 Canceled 2018-03-10 2018-05-05 2019-06-30 atmosphere deposition, etc. based Agricultural Land Quotations Envelope in and Pollution Management. detection of the samples.

HNJSFZ001-2 / Sampling of water, soil, crops, Component 1: Pending sediments,agriculture inputs, Demonstration of Risk- Request for Single Stage - One IBRD / 87770 Post Limited 26,040.00 0.00 Implementati 2018-03-10 2018-05-05 2018-12-31 atmosphere deposition, etc. based Agricultural Land Quotations Envelope on in City and detection Pollution Management. of the samples.

HNYSFZ001-2 / Sampling of water, soil, crops, Component 1: Under sediments,agriculture inputs, Demonstration of Risk- Request for Single Stage - One IBRD / 87770 Post Limited 30,450.00 0.00 Implementati 2018-03-10 2018-08-15 2018-05-05 2018-12-31 atmosphere deposition, etc. based Agricultural Land Quotations Envelope on in Yongshun County and Pollution Management. detection of the samples.

HNBJFZ001-2 / Sampling of water, soil, crops, Component 1: Under sediments,agriculture inputs, Demonstration of Risk- Request for Single Stage - One IBRD / 87770 Post Limited 59,600.00 0.00 Implementati 2018-03-10 2018-08-24 2018-05-05 2018-12-31 atmosphere deposition, etc. based Agricultural Land Quotations Envelope on in Baojing County and Pollution Management. detection of the samples.

HNXXHYFZ001-2 / Sampling of water, soil, Component 1: crops, sediments,agriculture Under Demonstration of Risk- Request for Single Stage - One inputs, atmosphere IBRD / 87770 Post Limited 30,600.00 0.00 Implementati 2018-03-10 2018-08-24 2018-05-05 2018-12-31 based Agricultural Land Quotations Envelope deposition, etc. in Huayuan on Pollution Management. County and detection of the samples.

HNQYFZ001-2 / Sampling of water, soil, crops, Component 1: Under sediments,agriculture inputs, Demonstration of Risk- Request for Single Stage - One IBRD / 87770 Post Limited 24,330.00 0.00 Implementati 2018-03-10 2018-08-22 2018-05-05 2018-12-31 atmosphere deposition, etc. based Agricultural Land Quotations Envelope on in Qiyang County and Pollution Management. detection of the samples.

HNCLFZ001-2 / Sampling of water, soil, crops, Component 1: Under sediments,agriculture inputs, Demonstration of Risk- Request for Single Stage - One IBRD / 87770 Post Limited 31,940.00 0.00 Implementati 2018-03-10 2018-08-17 2018-05-05 2018-12-31 atmosphere deposition, etc. based Agricultural Land Quotations Envelope on in Cili County and detection Pollution Management. of the samples.

HNYZFZ001-2 / Sampling of water, soil, crops, Component 1: sediments,agriculture inputs, Demonstration of Risk- Request for Single Stage - One IBRD / 87770 Post Limited 20,150.00 0.00 Canceled 2018-03-10 2018-05-05 2018-12-31 atmosphere deposition, etc. based Agricultural Land Quotations Envelope in Yizhang County and Pollution Management. detection of the samples.

HNZFFZ001-2 / Sampling of water, soil, crops, Component 1: Under sediments,agriculture inputs, Demonstration of Risk- Request for Single Stage - One IBRD / 87770 Post Limited 44,160.00 0.00 Implementati 2018-03-10 2018-08-31 2018-05-05 2018-12-31 atmosphere deposition, etc. based Agricultural Land Quotations Envelope on in Zhongfang County and Pollution Management. detection of the samples.

HNAHFZ001-2 / Sampling of water, soil, crops, Component 1: sediments,agriculture inputs, Demonstration of Risk- Request for Single Stage - One IBRD / 87770 Post Limited 31,340.00 0.00 Canceled 2018-03-10 2018-05-05 2018-12-31 atmosphere deposition, etc. based Agricultural Land Quotations Envelope in Anhua County and Pollution Management. detection of the samples.

Page 7 HNLSTFZ001-2 / Sampling of water, soil, crops, Component 1: Pending sediments,agriculture inputs, Demonstration of Risk- Request for Single Stage - One IBRD / 87770 Post Limited 28,130.00 0.00 Implementati 2018-03-10 2018-05-05 2018-12-31 atmosphere deposition, etc. based Agricultural Land Quotations Envelope on in and Pollution Management. detection of the samples.

HNYDFZ003 / Sampling of water, soil, crops, Component 1: Under sediments, agriculture Demonstration of Risk- Request for Single Stage - One IBRD / 87770 Post Limited 356,270.00 0.00 Implementati 2019-03-06 2019-05-23 2019-05-01 2023-12-31 inputs, atmosphere based Agricultural Land Quotations Envelope on deposition, etc. in Yongding Pollution Management. District and detection of the samples.

HNQYFZ002 / Sampling of water, soil, crops, Component 1: Under sediments, agriculture Demonstration of Risk- Request for Single Stage - One IBRD / 87770 Post Limited 262,690.00 0.00 Implementati 2019-03-06 2019-03-10 2019-05-01 2023-12-31 inputs, atmosphere based Agricultural Land Quotations Envelope on deposition, etc. in Qiyang Pollution Management. county and detection of the samples.

HNLWFZ001-2 / Sampling of water, soil, crops, Component 1: Under sediments,agriculture inputs, Demonstration of Risk- Request for Single Stage - One IBRD / 87770 Post Limited 154,030.00 0.00 Implementati 2019-03-06 2019-04-22 2019-05-01 2023-12-31 atmosphere deposition, etc. based Agricultural Land Quotations Envelope on in and Pollution Management. detection of the samples.

HNZFFZ002 / Sampling of water, soil, crops, Component 1: Under sediments,agriculture inputs, Demonstration of Risk- Request for Single Stage - One IBRD / 87770 Post Limited 296,670.00 0.00 Implementati 2019-03-06 2019-04-23 2019-05-01 2023-12-31 atmosphere deposition, etc. based Agricultural Land Quotations Envelope on in Zhongfang County and Pollution Management. detection of the samples.

HNLSTFZ002 / Sampling of water, soil, crops, Component 1: sediments,agriculture inputs, Under Demonstration of Risk- Request for Single Stage - One atmosphere deposition, etc. IBRD / 87770 Post Limited 235,630.00 0.00 Implementati 2019-03-06 2019-05-27 2019-05-01 2023-12-31 based Agricultural Land Quotations Envelope in Leng Shuitan District on Pollution Management. and detection of the samples.

HNXXHYFZ002 / Sampling of water, soil, crops, Component 1: Under sediments,agriculture inputs, Demonstration of Risk- Request for Single Stage - One IBRD / 87770 Post Limited 262,120.00 0.00 Implementati 2019-03-06 2019-07-22 2019-05-01 2023-12-31 atmosphere deposition, etc. based Agricultural Land Quotations Envelope on in Huayuan County and Pollution Management. detection of the samples.

HNBJFZ002 / Sampling of water, soil, crops, Component 1: Under sediments,agriculture inputs, Demonstration of Risk- Request for Single Stage - One IBRD / 87770 Post Limited 248,540.00 0.00 Implementati 2019-03-06 2020-03-19 2019-05-01 2023-12-31 atmosphere deposition, etc. based Agricultural Land Quotations Envelope on in Baojing County and Pollution Management. detection of the samples.

HNYSFZ002 / Sampling of water, soil, crops, Component 1: Under sediments,agriculture inputs, Demonstration of Risk- Request for Single Stage - One IBRD / 87770 Post Limited 119,400.00 0.00 Implementati 2019-03-06 2019-04-08 2019-05-01 2023-12-31 atmosphere deposition, etc. based Agricultural Land Quotations Envelope on in Yongshun County and Pollution Management. detection of the samples.

HNHYFZ002 / Publicize the measures and effects of the project in Hengyang, so as to enhance the visibility Component 1: Under of the project and the value Demonstration of Risk- Request for Single Stage - One IBRD / 87770 Post Limited 74,630.00 0.00 Implementati 2019-03-06 2020-08-24 2019-05-01 2024-03-31 of agricultural products in based Agricultural Land Quotations Envelope on the project area, and Pollution Management. popularize the knowledge of heavy metal pollution control at the same time.

HNHNFZ001-2 / Sampling of water, soil, crops, Component 1: Under sediments,agriculture inputs, Demonstration of Risk- Request for Single Stage - One IBRD / 87770 Post Limited 477,610.00 0.00 Implementati 2019-03-06 2019-07-02 2019-05-01 2023-12-31 atmosphere deposition, etc. based Agricultural Land Quotations Envelope on in Hengnan County and Pollution Management. detection of the samples.

Page 8 HNCLFZ002 / Sampling of water, soil, crops, Component 1: Under sediments,agriculture inputs, Demonstration of Risk- Request for Single Stage - One IBRD / 87770 Post Limited 239,530.00 0.00 Implementati 2019-03-06 2019-04-02 2019-05-01 2023-12-31 atmosphere deposition, etc. based Agricultural Land Quotations Envelope on in Cili County and detection Pollution Management. of the samples.

HNHYFZ001-2-2 / Sampling of water, soil, Component 1: Under crops, sediments,agriculture Demonstration of Risk- Request for Single Stage - One IBRD / 87770 Post Limited 492,540.00 0.00 Implementati 2019-06-25 2019-06-27 2019-08-20 2024-04-20 inputs, atmosphere based Agricultural Land Quotations Envelope on deposition, etc. in Hengyang Pollution Management. County and detection of the samples.

HNLSTFZ003 / Hiring a third-party organization to train farmers and project managers in project Component 3: Capacity Under Request for Single Stage - One background, agronomic IBRD / 87770 Development and Post Open - National 262,610.00 0.00 Implementati 2019-10-25 2019-12-20 2023-12-31 Quotations Envelope measures, and integrated Knowledge Distribution. on pest ,disease control techniques, etc. in Leng Shuitan district.

HNQYFZ003 / Hiring a third-party organization to train farmers and project managers in project Component 3: Capacity Under Request for Single Stage - One background, agronomic IBRD / 87770 Development and Post Limited 280,600.00 0.00 Implementati 2019-10-25 2019-11-06 2019-12-20 2023-12-31 Quotations Envelope measures, and integrated Knowledge Distribution. on pest ,disease control techniques, etc. in Qiyang county.

HNYZFZ001 / Sampling of water, soil, crops, Component 1: Under sediments, agriculture Demonstration of Risk- Request for Single Stage - One IBRD / 87770 Post Limited 222,940.00 0.00 Implementati 2019-11-15 2020-03-06 2020-01-10 2023-12-31 inputs, atmosphere based Agricultural Land Quotations Envelope on deposition, etc. in Yi Zhang Pollution Management. County and detection of the samples.

HNXXHYFZ003 / Hiring a third-party organization to train farmers and project managers in project Component 3: Capacity Under Request for Single Stage - One background, agronomic IBRD / 87770 Development and Post Limited 134,330.00 0.00 Implementati 2020-01-04 2020-01-06 2020-02-29 2023-02-28 Quotations Envelope measures, and integrated Knowledge Distribution. on pest ,disease control techniques, etc. in HuaYuan county.

HNYSFZ003 / Hiring a third-party organization to train farmers and project managers in project Component 3: Capacity Under Request for Single Stage - One background, agronomic IBRD / 87770 Development and Post Limited 134,330.00 0.00 Implementati 2020-01-04 2020-01-03 2020-02-29 2023-02-28 Quotations Envelope measures, and integrated Knowledge Distribution. on pest ,disease control techniques, etc. in YongShun county.

HNJSFZ003 / Hiring a third-party organization to train farmers and project managers in project Component 3: Capacity Under Request for Single Stage - One background, agronomic IBRD / 87770 Development and Post Limited 134,330.00 0.00 Implementati 2020-01-04 2020-01-03 2020-02-29 2023-02-28 Quotations Envelope measures, and integrated Knowledge Distribution. on pest ,disease control techniques, etc. in JiShou city.

HNYZFZ002 / Hiring a third-party organization to train farmers and project managers in project Component 3: Capacity Under Request for Single Stage - One background, agronomic IBRD / 87770 Development and Post Open - National 179,100.00 0.00 Implementati 2020-03-15 2020-05-10 2023-12-31 Quotations Envelope measures, and integrated Knowledge Distribution. on pest ,disease control techniques, etc. in Yizhang county.

Page 9 HNJSFZ002 / Sampling of water, soil, crops, Component 1: Under sediments, agriculture Demonstration of Risk- Request for Single Stage - One IBRD / 87770 Post Limited 119,400.00 0.00 Implementati 2020-03-15 2020-05-15 2020-05-10 2023-12-31 inputs, atmosphere based Agricultural Land Quotations Envelope on deposition, etc. in Jishou Pollution Management. city and detection of the samples.

Component 3: Capacity Under HNLWFZ002 / Farmer Request for Single Stage - One IBRD / 87770 Development and Post Open - National 205,970.00 0.00 Implementati 2020-03-15 2020-05-10 2023-12-31 training in linwu county. Quotations Envelope Knowledge Distribution. on

HNAHFZ001 / Sampling of water, soil, crops, Component 1: Under sediments, agriculture Demonstration of Risk- Request for Single Stage - One IBRD / 87770 Post Limited 179,100.00 0.00 Implementati 2020-04-15 2020-07-09 2020-06-10 2023-12-31 inputs, atmosphere based Agricultural Land Quotations Envelope on deposition, etc. in Anhua Pollution Management. county and detection of the samples.

HNHNFZ002 / Training of Component 3: Capacity Under Farmers and Project Request for Single Stage - One IBRD / 87770 Development and Post Limited 186,570.00 0.00 Implementati 2020-04-15 2020-04-08 2020-06-10 2023-12-31 Managers in Hengnan Quotations Envelope Knowledge Distribution. on county.

HNHYFZ003 / Training of Component 3: Capacity Under Request for Single Stage - One farmers in Hengyang county IBRD / 87770 Development and Post Limited 210,820.00 0.00 Implementati 2020-06-04 2020-05-28 2020-07-30 2023-12-31 Quotations Envelope . Knowledge Distribution. on

Component 3: Capacity Under HNAHFZ002 / Training of Request for Single Stage - One IBRD / 87770 Development and Post Limited 246,490.00 0.00 Implementati 2020-06-04 2020-07-09 2020-07-30 2023-12-31 farmers in Anhua county. Quotations Envelope Knowledge Distribution. on

CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Interest Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual

Component 1: HNYXZ001 / Screening of Consultant Demonstration of Risk- low metal-accumulating IBRD / 87770 Post Qualification Open - National 44,790.00 0.00 Canceled 2017-09-20 2017-10-11 2017-11-24 2017-12-24 2018-01-28 2021-01-28 based Agricultural Land variety. Selection Pollution Management.

HNYDZ005 / Comparing Component 1: the differences of heavy Consultant Demonstration of Risk- metal uptaking between the IBRD / 87770 Post Qualification Open - National 15,650.00 0.00 Canceled 2017-09-20 2017-10-11 2017-11-24 2017-12-24 2018-01-28 2022-12-31 based Agricultural Land "with project"and"without Selection Pollution Management. project" situations

HNYDZ006 / Disseminate knowledge gained from demonstrations for Component 3: Capacity Consultant increasing awareness and IBRD / 87770 Development and Post Qualification Open - National 37,300.00 0.00 Canceled 2017-09-20 2017-10-11 2017-11-24 2017-12-24 2018-01-28 2022-12-31 building ability to make Knowledge Distribution. Selection informed choices among alternatives.

Component 4: Project Consultant HNYXZ002 / Project IBRD / 87770 Management and Post Qualification Open - National 74,650.00 0.00 Canceled 2017-09-20 2017-10-11 2017-11-24 2017-12-24 2018-01-28 2022-12-31 monitoring and evaluation. Monitoring and Evaluation Selection

Component 4: Project Consultant HNYXZ003 / Supervision IBRD / 87770 Management and Post Qualification Open - National 94,050.00 0.00 Canceled 2017-09-20 2017-10-11 2017-11-24 2017-12-24 2018-01-28 2022-12-31 of agronomic measures. Monitoring and Evaluation Selection

HNZ005 / Screening Component 1: experiment on simultaneous Consultant Demonstration of Risk- Under passivation agents for IBRD / 87770 Post Qualification Open - National 208,960.00 0.00 2018-06-10 2018-07-27 2018-07-01 2019-06-23 2018-08-14 2018-07-27 2018-09-13 2018-08-20 2018-10-18 2019-12-31 based Agricultural Land Implementation combined pollution of Selection Pollution Management. cadmium and arsenic.

HNZ008 / Conduction of annual environmental Component 4: Project Consultant assessment (produce one IBRD / 87770 Management and Post Qualification Open - National 283,580.00 0.00 Canceled 2018-11-10 2018-12-01 2019-01-14 2019-02-13 2019-03-20 2024-06-30 environmental assessment Monitoring and Evaluation Selection report every six months)

Page 10 HNHYZ001 / Screening Component 1: Consultant experiment of low cadmium Demonstration of Risk- Under IBRD / 87770 Post Qualification Open - National 98,510.00 0.00 2019-03-01 2019-07-14 2019-03-22 2019-05-05 2019-07-12 2019-06-04 2019-08-01 2019-07-09 2022-07-09 accumulation varieties in based Agricultural Land Implementation Selection Hengyang county. Pollution Management.

HNHYZ002 / Experiment on the effect of harvesting Component 1: Consultant at different maturity on Demonstration of Risk- Under IBRD / 87770 Post Qualification Open - National 44,300.00 0.00 2019-03-01 2019-06-25 2019-03-22 2019-05-05 2019-07-24 2019-06-04 2019-08-01 2019-07-09 2021-07-09 cadmium accumulation in based Agricultural Land Implementation Selection rice, to be conducted in Pollution Management. Hengyang county.

HNHYZ003 / Comparison of effects of agronomic Component 1: Consultant measures in different Demonstration of Risk- Under IBRD / 87770 Post Qualification Open - National 47,000.00 0.00 2019-03-01 2019-06-25 2019-03-22 2019-05-05 2019-07-24 2019-06-04 2019-08-01 2019-07-09 2023-12-31 regions and monitoring based Agricultural Land Implementation Selection experiment of soil cadmium Pollution Management. balance in Hengyang county.

Component 2: HNHYZ006 / Local policies Consultant Strengthening Agricultural Pending and standards development IBRD / 87770 Post Qualification Open - National 89,550.00 0.00 2019-03-01 2019-03-22 2019-05-05 2019-06-04 2019-07-09 2023-12-31 Environmental Monitoring Implementation in Hengyang county. Selection and Management.

Component 4: Project Consultant HNYDZ003 / Project IBRD / 87770 Management and Post Qualification Open - National 52,250.00 0.00 Canceled 2017-09-20 2017-10-11 2017-11-24 2017-12-24 2018-01-28 2022-12-31 monitoring and evaluation. Monitoring and Evaluation Selection

Component 4: Project Consultant HNYDZ007 / Supervision IBRD / 87770 Management and Post Qualification Open - National 189,650.00 0.00 Canceled 2017-09-20 2017-10-11 2017-11-24 2017-12-24 2018-01-28 2022-12-31 of agronomic measures. Monitoring and Evaluation Selection

HNQYZ001 / Screening Component 1: Consultant experiment of low cadmium Demonstration of Risk- Under IBRD / 87770 Post Qualification Open - National 98,510.00 0.00 2019-03-01 2019-03-22 2019-03-22 2019-05-05 2019-04-05 2019-06-04 2019-04-25 2019-07-09 2022-07-09 accumulation varieties in based Agricultural Land Implementation Selection Qiyang county. Pollution Management.

HNCLZ001 / Screening Component 1: Consultant experiment of low cadmium Demonstration of Risk- Under IBRD / 87770 Post Qualification Open - National 98,510.00 0.00 2019-03-01 2019-03-21 2019-03-22 2019-05-05 2019-04-29 2019-06-04 2019-05-06 2019-07-09 2022-07-09 accumulation varieties in based Agricultural Land Implementation Selection Cili county. Pollution Management.

HNHNZ001 / Screening Component 1: Consultant experiment of low cadmium Demonstration of Risk- Under IBRD / 87770 Post Qualification Open - National 98,510.00 0.00 2019-03-01 2019-03-28 2019-03-22 2020-04-27 2019-05-05 2019-04-04 2019-06-04 2019-04-10 2019-07-09 2022-07-09 accumulation varieties in based Agricultural Land Implementation Selection Hengnan county. Pollution Management.

HNZFZ001 / Screening Component 1: Consultant experiment of low cadmium Demonstration of Risk- Under IBRD / 87770 Post Qualification Open - National 98,510.00 0.00 2019-03-01 2019-04-10 2019-03-22 2019-05-05 2019-05-20 2019-06-04 2019-05-25 2019-07-09 2022-07-09 accumulation varieties in based Agricultural Land Implementation Selection Zhongfang county. Pollution Management.

HNLSTZ001 / Screening Component 1: Consultant experiment of low cadmium Demonstration of Risk- Under IBRD / 87770 Post Qualification Open - National 98,510.00 0.00 2019-03-01 2019-03-25 2019-03-22 2019-05-05 2019-06-04 2019-07-09 2022-07-09 accumulation varieties in based Agricultural Land Implementation Selection Lengshuitan district. Pollution Management.

HNXXHYZ001 / Screening Component 1: Consultant experiment of low cadmium Demonstration of Risk- Under IBRD / 87770 Post Qualification Open - National 98,510.00 0.00 2019-03-01 2019-03-25 2019-03-22 2019-05-05 2019-05-06 2019-06-04 2019-05-10 2019-07-09 2022-07-09 accumulation varieties in based Agricultural Land Implementation Selection Huayuan county. Pollution Management.

HNYSZ001 / Screening Component 1: Consultant experiment of low cadmium Demonstration of Risk- Under IBRD / 87770 Post Qualification Open - National 98,510.00 0.00 2019-03-01 2019-03-01 2019-03-22 2019-05-05 2019-04-28 2019-06-04 2019-04-29 2019-07-09 2022-07-09 accumulation varieties in based Agricultural Land Implementation Selection Yongshun county. Pollution Management.

HNZ001 / Development of a risk-based land management tool and use the tool to map all Component 2: farmland sat the county Strengthening Agricultural Quality Based Under and provincial levels to IBRD / 87770 Post Open - National 1,000,000.00 0.00 2019-03-10 2020-05-19 2019-03-31 2020-08-07 2019-05-14 2020-09-10 2019-06-11 2020-10-10 2019-07-11 2020-10-10 2019-08-10 2019-09-14 2022-09-14 Environmental Monitoring Selection Implementation classify areas with different and Management. risk levels, crops for different soil types and conditions, and identify risk management options.

Page 11 HNZ002 / Studies on sustainable financing models Component 2: Consultant and eco-compensation Strengthening Agricultural Under IBRD / 87770 Post Qualification Open - National 74,630.00 0.00 2019-03-17 2019-09-20 2019-03-27 2019-05-10 2020-09-10 2019-06-09 2019-07-14 2022-07-14 mechanisms for long-term Environmental Monitoring Implementation Selection agricultural land and Management. management.

HNZ003 / Establish a database of all relevant Component 2: Consultant information, and give early Strengthening Agricultural Under IBRD / 87770 Post Qualification Open - National 89,550.00 0.00 2019-03-17 2020-06-08 2019-04-07 2019-05-21 2020-09-10 2019-06-20 2019-07-25 2021-07-25 warning of possible risks to Environmental Monitoring Implementation Selection farmland and crops and Management. according to data changes.

HNZ004 / Monitoring the progress of project, finance, procurement and training.And summarize the situation of social tracking Component 4: Project Consultant monitoring, environmental IBRD / 87770 Management and Post Qualification Open - National 223,880.00 0.00 Canceled 2018-11-10 2018-12-01 2019-01-14 2019-02-13 2019-03-20 2024-06-30 tracking monitoring and Monitoring and Evaluation Selection project implementation effectiveness assessment (a report is produced every six months).

HNZ006 / Monitoring the Component 1: Consultant whole process of sampling Demonstration of Risk- Under IBRD / 87770 Post Qualification Open - National 268,660.00 0.00 2018-08-13 2019-08-28 2018-09-03 2018-10-17 2018-11-16 2018-12-21 2023-12-31 and detection of the based Agricultural Land Implementation Selection samples for quality control Pollution Management.

HNZ007 / Conduction of Social evaluation annually (tracking monitoring one Component 4: Project Consultant natural village per county Under IBRD / 87770 Management and Post Qualification Open - National 268,660.00 0.00 2019-03-02 2019-05-08 2019-03-23 2019-05-06 2019-06-05 2019-07-10 2023-12-31 and produce a social Implementation Monitoring and Evaluation Selection evaluation report each year) and dam safety assessment annually.

HNZ009 / Screening experiment on simultaneous Component 1: Consultant passivation agents for Demonstration of Risk- Under IBRD / 87770 Post Qualification Open - National 253,730.00 0.00 2019-03-05 2019-03-27 2019-03-26 2019-05-09 2019-06-08 2019-07-13 2021-07-13 combined pollution of based Agricultural Land Implementation Selection cadmium and arsenic for Pollution Management. the second time.

HNHYZ005 / Analysis and Component 1: Consultant evaluation of heavy metal Demonstration of Risk- Pending IBRD / 87770 Post Qualification Open - National 71,640.00 0.00 2019-03-05 2019-03-26 2019-05-09 2019-06-08 2019-07-13 2023-12-31 pollution data in Hengyang based Agricultural Land Implementation Selection county. Pollution Management.

Component 1: HNYDZ004 / Screening of Consultant Demonstration of Risk- Under low metal-accumulating IBRD / 87770 Post Qualification Open - National 98,510.00 0.00 2019-03-01 2019-04-01 2019-03-22 2019-05-05 2019-04-30 2019-06-04 2019-05-20 2019-07-09 2022-07-09 based Agricultural Land Implementation variety in Yongding district. Selection Pollution Management.

HNBJZ001 / Screening Component 1: Consultant experiment of low cadmium Demonstration of Risk- IBRD / 87770 Post Qualification Open - National 98,510.00 0.00 Canceled 2019-03-02 2019-03-23 2019-05-06 2019-06-05 2019-07-10 2022-07-10 accumulation varieties in based Agricultural Land Selection Baojing county. Pollution Management.

HNZ008-2 / Conduction of annual environmental Component 4: Project Quality And Cost- Open - Under assessment (produce one IBRD / 87770 Management and Post 343,280.00 0.00 2019-04-01 2019-05-19 2019-04-22 2019-05-19 2019-06-05 2019-07-16 2019-07-03 2019-08-19 2019-08-02 2019-08-19 2019-09-06 2019-08-20 2019-10-11 2023-12-31 Based Selection International Implementation environmental assessment Monitoring and Evaluation report every six months)

HNLSTZ002 / Hire a third Component 1: party to supervise the Consultant Demonstration of Risk- Under implementation of agronomic IBRD / 87770 Post Qualification Open - National 156,720.00 0.00 2019-04-01 2019-03-15 2019-04-22 2019-06-05 2019-07-05 2019-08-09 2023-12-31 based Agricultural Land Implementation measures in Leng Shuitan Selection Pollution Management. District.

HNQYZ003 / Hire a third Component 1: party to supervise the Consultant Demonstration of Risk- Under implementation of agronomic IBRD / 87770 Post Qualification Open - National 114,730.00 0.00 2019-03-25 2019-04-21 2019-04-15 2019-05-29 2019-04-30 2019-06-28 2019-05-30 2019-08-02 2023-12-31 based Agricultural Land Implementation measures in Qi Yang Selection Pollution Management. county.

Page 12 HNHNZ002 / Hire a third Component 1: party to supervise the Consultant Demonstration of Risk- Under implementation of agronomic IBRD / 87770 Post Qualification Open - National 231,690.00 0.00 2019-04-06 2019-05-05 2019-04-27 2019-06-10 2019-07-10 2019-08-14 2023-12-31 based Agricultural Land Implementation measures in Heng Nan Selection Pollution Management. county.

HNLWZ001 / Screening Component 1: Consultant experiment of low cadmium Demonstration of Risk- Under IBRD / 87770 Post Qualification Open - National 98,510.00 0.00 2019-04-10 2019-07-22 2019-05-01 2019-06-14 2019-07-14 2019-08-18 2022-08-18 accumulation varieties in based Agricultural Land Implementation Selection Lin Wu county. Pollution Management.

HNZ004-2 / Evaluation of Component 4: Project Quality And Cost- Open - Under the implementation effect of IBRD / 87770 Management and Post 522,390.00 0.00 2019-06-06 2019-06-26 2019-06-27 2019-07-09 2019-08-10 2019-08-09 2019-09-07 2019-10-16 2019-10-07 2019-10-16 2019-11-11 2019-12-16 2023-12-31 Based Selection International Implementation the project . Monitoring and Evaluation

HNXXHYZ002 / Hire a third party to provide Component 1: Consultant technical support for the Demonstration of Risk- Under IBRD / 87770 Post Qualification Open - National 44,780.00 0.00 2019-06-06 2019-12-02 2019-06-27 2019-08-10 2020-01-27 2019-09-09 2020-02-17 2019-10-14 2021-12-31 treatment of heavy metal based Agricultural Land Implementation Selection contaminated farmland in Pollution Management. Huayuan County.

HNYSZ002 / Hire a third party to provide technical Component 1: Consultant support for the treatment of Demonstration of Risk- Under IBRD / 87770 Post Qualification Open - National 44,780.00 0.00 2019-06-06 2019-12-02 2019-06-27 2019-08-10 2020-03-03 2019-09-09 2019-10-14 2021-12-31 heavy metal contaminated based Agricultural Land Implementation Selection farmland in Yongshun Pollution Management. County.

HNJSZ001 / Hire a third Component 1: party to provide technical Consultant Demonstration of Risk- Under support for the treatment of IBRD / 87770 Post Qualification Open - National 44,780.00 0.00 2019-06-06 2019-12-02 2019-06-27 2019-08-10 2020-01-29 2019-09-09 2020-02-25 2019-10-14 2021-12-31 based Agricultural Land Implementation heavy metal contaminated Selection Pollution Management. farmland in Jishou City.

HNHYZ007 / Hire a third Component 1: party to supervise the Consultant Demonstration of Risk- Under implementation of IBRD / 87770 Post Qualification Open - National 92,450.00 0.00 2019-06-06 2019-06-25 2019-06-27 2019-08-10 2020-07-24 2019-09-09 2019-08-01 2019-10-14 2023-12-31 based Agricultural Land Implementation agricultural measures in Selection Pollution Management. Hengyang County.

HNJSZ002 / Screening Component 1: Consultant experiment of low cadmium Demonstration of Risk- Under IBRD / 87770 Post Qualification Open - National 89,550.00 0.00 2019-12-30 2020-01-01 2020-01-20 2020-03-04 2020-01-29 2020-04-03 2020-02-28 2020-05-08 2023-05-09 accumulation varieties in based Agricultural Land Implementation Selection JiShou city. Pollution Management.

HNYSZ003 / Screening Component 1: Consultant experiment of low cadmium Demonstration of Risk- Under IBRD / 87770 Post Qualification Open - National 89,550.00 0.00 2019-12-30 2019-12-29 2020-01-20 2020-03-04 2020-03-03 2020-04-03 2020-05-08 2023-05-09 accumulation varieties in based Agricultural Land Implementation Selection YongShun county. Pollution Management.

HNXXHYZ003 / Screening Component 1: Consultant experiment of low cadmium Demonstration of Risk- Under IBRD / 87770 Post Qualification Open - National 89,550.00 0.00 2019-12-30 2019-04-01 2020-01-20 2020-03-04 2020-01-27 2020-04-03 2020-02-20 2020-05-08 2023-05-09 accumulation varieties in based Agricultural Land Implementation Selection HuaYuan county. Pollution Management.

HNYZZ001 / Screening Component 1: Consultant experiment of low cadmium Demonstration of Risk- Under IBRD / 87770 Post Qualification Open - National 104,480.00 0.00 2020-03-10 2020-03-05 2020-03-31 2020-05-14 2020-03-30 2020-06-13 2020-03-30 2020-07-18 2022-12-31 accumulation varieties in based Agricultural Land Implementation Selection Yizhang county. Pollution Management.

HNYZZ002 / Hire a third Component 1: Consultant party to supervise the Demonstration of Risk- Under IBRD / 87770 Post Qualification Open - National 111,940.00 0.00 2020-03-10 2020-03-06 2020-03-31 2020-05-14 2020-03-30 2020-06-13 2020-04-03 2020-07-18 2023-12-31 implementation of agronomic based Agricultural Land Implementation Selection measures in Yizhang Pollution Management. county.

HNLWZ003 / Hire a third Component 1: Consultant party to supervise the Demonstration of Risk- Pending IBRD / 87770 Post Qualification Open - National 74,630.00 0.00 2020-03-10 2020-03-31 2020-05-14 2020-06-13 2020-07-18 2023-12-31 implementation of agronomic based Agricultural Land Implementation Selection measures in Linwu county. Pollution Management.

HNAFZ001 / Screening Component 1: Consultant experiment of low cadmium Demonstration of Risk- Pending IBRD / 87770 Post Qualification Open - National 89,550.00 0.00 2020-05-30 2020-06-20 2020-08-03 2020-09-02 2020-10-07 2022-12-31 accumulation rice varieties based Agricultural Land Implementation Selection in Anhua county. Pollution Management.

HNZ010 / Conduct social Component 4: Project Consultant Pending evaluation of the new IBRD / 87770 Management and Post Qualification Open - National 30,000.00 0.00 2020-11-30 2020-12-21 2021-02-03 2021-03-05 2021-04-09 2021-10-06 Implementation project area. Monitoring and Evaluation Selection

Page 13 HNZ011 / Conduct Component 4: Project Consultant Pending environment assessment of IBRD / 87770 Management and Post Qualification Open - National 60,000.00 0.00 2020-11-30 2020-12-21 2021-02-03 2021-03-05 2021-04-09 2021-10-06 Implementation the new project area. Monitoring and Evaluation Selection

INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual

HNQYZ002 / Technical Component 1: guidance for district Individual Demonstration of Risk- Under treatment of cadmium - IBRD / 87770 Post Consultant Open 44,780.00 0.00 2019-03-01 2019-05-10 2019-04-19 2019-05-10 2019-06-14 2022-06-14 based Agricultural Land Implementation arsenic compound pollution Selection Pollution Management. project in Qiyang county.

HNCLZ002 / Technical Component 1: guidance for district Individual Demonstration of Risk- Under treatment of cadmium - IBRD / 87770 Post Consultant Open 44,780.00 0.00 2019-03-01 2019-07-20 2019-04-19 2019-06-14 2019-05-10 2019-06-24 2019-06-14 2022-06-14 based Agricultural Land Implementation arsenic compound pollution Selection Pollution Management. project in Cili county.

HNLWZ002 / Technical guidance for regional Component 1: Individual treatment of cadmium- Demonstration of Risk- Under IBRD / 87770 Post Consultant Open 89,550.00 0.00 2019-03-01 2019-06-15 2019-04-19 2020-04-20 2019-05-10 2019-06-14 2022-06-14 arsenic combined pollution based Agricultural Land Implementation Selection and arsenic pollution in Pollution Management. linwu county.

HNHNZ003 / Technical guidance for regional Component 1: Individual treatment of cadmium- Demonstration of Risk- Under IBRD / 87770 Post Consultant Open 89,550.00 0.00 2019-05-15 2019-05-01 2019-07-03 2019-06-06 2019-07-24 2019-06-20 2019-08-28 2021-12-31 arsenic combined pollution based Agricultural Land Implementation Selection and arsenic pollution in Pollution Management. Hengnan county.

HNLSTZ003 / Technical Component 1: guidance for treatment of Individual Demonstration of Risk- Under Heavy Metal contaminated IBRD / 87770 Post Consultant Open 44,780.00 0.00 2019-05-15 2019-05-10 2019-07-03 2019-07-24 2019-08-28 2021-12-31 based Agricultural Land Implementation farmland in Lengshuitan Selection Pollution Management. district.

HNYZZ003 / Technical Component 1: Individual guidance for heavy metal Demonstration of Risk- Under IBRD / 87770 Post Consultant Open 80,600.00 0.00 2020-03-10 2020-03-06 2020-04-28 2020-03-29 2020-05-19 2020-04-10 2020-06-23 2023-06-23 pollution control in Yizhang based Agricultural Land Implementation Selection county. Pollution Management.

HNZFZ002 / Technical Component 1: Individual guidance for heavy metal Demonstration of Risk- Under IBRD / 87770 Post Consultant Open 44,780.00 0.00 2020-03-10 2020-04-24 2020-04-28 2020-05-15 2020-05-19 2020-05-21 2020-06-23 2023-06-23 pollution control in based Agricultural Land Implementation Selection Zhongfang county Pollution Management.

HNAHZ001 / Technical Component 1: guidance for district Individual Demonstration of Risk- Pending treatment of heavy metal IBRD / 87770 Post Consultant Open 44,780.00 0.00 2020-04-10 2020-05-29 2020-06-19 2020-07-24 2023-07-25 based Agricultural Land Implementation pollution project in Anhua Selection Pollution Management. county.

HNHYZ004 / Technical Component 1: guidance for the Individual Demonstration of Risk- Under implementation of agronomic IBRD / 87770 Post Consultant Open 85,075.00 0.00 2020-06-10 2020-05-20 2020-07-29 2020-06-23 2020-08-19 2020-06-28 2020-09-23 2023-12-31 based Agricultural Land Implementation measures in Hengyang Selection Pollution Management. county.