Eau Claire Area Improvements Program

V05 •Click to edit Master text styles

Our Team

Project & Subject Daniel England Matter Experts Dennis Hoffart Katherine Hikita Joyce Tand

Engagement & Communications Natalie Coombes Stephanie Lake

V05 •Click to edit Master text styles

AGENDA 1. Investing in Eau Claire 2. Project overview & Update: • Flood Barrier • Eau Claire Promenade • Eau Claire Plaza Redesign • Jaipur Bridge Replacement • 3 Avenue Walking and Wheeling 3. Construction Impacts & Timeline 4. Next Steps 5. Questions

V05 •Click to edit Master text styles

Investing in Eau Claire

We're working towards building more resilient and vibrant communities that support future growth and development for the people who live, work, visit and travel the area.

To help reduce repeated disruptions and impacts to the community, we are working together and coordinating all the individual projects happening in the area, Including:

• Downtown Flood Barrier & Eau Claire Promenade • Eau Claire Plaza Redesign • Jaipur Bridge Replacement • Ramps Upgrades • 3 Avenue Walking and Wheeling Upgrades • Tomorrow’s Chinatown •

V05 •Click to edit Master text styles Building flood protection for downtown Remembering the 2013 flood In downtown Calgary: • Buildings, roadways, and park spaces were flooded • Emergency critical services were affected • Head offices, businesses and government facilities were closed • C-Train and bus service was disrupted • Homes and personal property were damaged

V05 •Click to edit Master text styles Downtown Flood Barrier & Eau Claire Promenade

V05 •Click to edit Master text styles Downtown Flood Barrier & Eau Claire Promenade

Our goals for the Promenade focus on: • A space for the City and Community • Accommodate all users for all of Calgary • Connect people to River • Builds a vibrant centre city riverfront • Design a diversity of social spaces for mental well- being • Promoting active, healthy lifestyles, incorporate strategies for year-round healthy, active lifestyles – a better space for walking, jogging, biking, etc. • Provide a continuous, safe and accessible riverfront promenade • Designate efficient pathways for safe alternate modes of transportation like scooters

V05 •Click to edit Master text styles Downtown Flood Barrier & Eau Claire Promenade: Lagoon

Eau Claire Lagoon looking east

V05 •Click to edit Master text styles Downtown Flood Barrier & Eau Claire Promenade: Centre Street

Looking west: Sien Lok Park on the left

V05 •Click to edit Master text styles Downtown Flood Barrier & Eau Claire Promenade: Riverwalk

Looking west at Centre Street

Looking west at 1st Street SE

V05 •Click to edit Master text styles

Jaipur Bridge Replacement

V05 11 •Click to edit Master text styles

Jaipur Bridge Replacement

V05 12 •Click to edit Master text styles

Eau Claire Plaza Redesign

Goals of the Plaza redesign are: • Vibrancy • Flexibility • Sustainability • Authenticity • Connectivity • Accessibility

The plaza is the gateway into this area and a destination that compliments the Eau Claire Promenade, West Eau Claire Park, Prince's Island Park and Jaipur Bridge.

V05 •Click to edit Master text styles

Eau Claire Plaza Redesign

V05 •Click to edit Master text styles 3 Avenue Walking and Wheeling in Chinatown and Eau Claire

V05 15 •Click to edit Master text styles

Business & Community Consultation What has been done: • Information sessions – April & October 2019 • Engagement and Stakeholder Relations: August 2020

Ongoing: • coordination meetings with Tomorrow's Chinatown & Green Line Internal teams

Going forward: • Our commitment to keeping business accesses open throughout construction.

V05 •Click to edit Master text styles

October Information Sessions - comments & concerns

• Is this permanent?

• Why 3rd Avenue South?

• Why now?

• What is next?

V05 •Click to edit Master text styles

What We Heard: Overall

The City hosted online engagement to provide citizens with an overview of the project and collect input on the 3 Avenue South Walking and Wheeling Upgrades project. The online engagement was available from August 12 – September 2, 2020. The online page received approximately 3836 views with 864 contributions of feedback. Due to COVID-19 restrictions, The City of Calgary was unable to host in-person engagement opportunities, however the online engagement was extended to collect feedback.

Next Steps

• Design team to review all of the What We Heard report content

• Next phase of public engagement in Winter 2021

V05 18 •Click to edit Master text styles

Construction Impact

Core work hours : • 7am – 7pm • Monday – Saturday *there is potential for work outside core hours as needed & communication will be provided in advance

What to expect: • An increase in noise and vibrations throughout construction. • Installation of piles that will generate ground vibrations in localized areas. • Soil disturbance and dust emissions. • An increase in truck and equipment traffic accessing the construction site(s) and surrounding areas. • Pathway, sidewalk, and roadway closures and detours.

V05 •Click to edit Master text styles

Construction & Community Impacts • Our commitment to keeping business accesses open throughout construction.

• Lagoon will be drained in July 2021, and remain empty until April 2022 for construction.

Tree Impacts & Removal

• To complete the Jaipur Bridge Replacement, Downtown Flood Barrier & Eau Claire Promenade, and Eau Claire Plaza Redesign, 160 trees on the south side of the will be removed.

• Tree removal anticipated to start November 2020.

V05 •Click to edit Master text styles

Eau Claire Area Improvements

Construction Timeline

Construction for the enabling works is expected to start in the winter of 2020 with project completion expected by the fall of 2023. Construction will be phased to minimize impact and keep Prince's Island Park accessible at all times.

2020 2021 2022 2023

• Remove utilities • Construction start in • Centre Street • Work complete from the existing Riverwalk, Centre work complete Jaipur bridge Street and the Eau and open • Tree removal Claire Lagoon • Contractor • Drain Lagoon procurement • Start work in the Lagoon for Jaipur Bridge

V05 •Click to edit Master text styles

NEXT STEPS

Jaipur Bridge • Contractor procurement • Confirm and communicate the construction schedule

Downtown Flood Barrier and Eau Claire Promenade • Contractor procurement • Tag trees in the area for removal

3 Avenue Walking and Wheeling Upgrades • Design team to review all of the What We Heard report content • Next phase of public engagement in Winter 2021

Eau Claire Plaza • Finalize funding and designs

V05 •Click to edit Master text styles

Questions