SOCIAL IMPACT ASSESSMENT STUDY

FINAL REPORT

Land Acquisition for construction of proposed SV Station at Marampilly

for the Salem LPG Pipe Line

Requiring Agency Kochi Salem Pipeline Private Limited

February 23, 2018

SIA Unit

Rajagiri College of Social Sciences Rajagiri P.O , Pin: 682 104 Ph: 0484 29110-332 www.rajagirioutreach.org

SOCIAL IMPACT ASSESSMENT STUDY

FINAL REPORT

Land Acquisition for construction of proposed SV Station at

Marampilly for the Kochi Salem LPG Pipe Line

Requiring Agency Kochi Salem Pipeline Private Limited

February 23, 2018 SIA Unit

Rajagiri College of Social Sciences Rajagiri P.O Kalamassery, Pin: 682 104 Ph: 0484 29110-332 www.rajagirioutreach.org

Abbreviations

BPCL Bharat Petroleum Corporation Limited IOCL Indian Oil Corporation Limited

LA Land Acquisition LPG Liquefied Petroleum Gas MoEFCC Ministry of Environment, Forest and Climate Change MSW Master of Social Work NGO Non Governmental Oganisation KSPPL Kochi Salem Pipe Line Private Limited NH National Highway

NHAI National Highway Authority of

MMTPA Million Metric Tonneper Annum

PCB Pollution Control Board

PESO Petroleum and Explosives Safety Organisation

PNGRB Petroleum and Natural Gas Regulatory Board

RoU Right of Use

RTFCTLARR Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act

SIA Social Impact Assessment

List of Tables

Table 6.1.1 Age Group and Gender

Table 6.1.2 Marital status of Project Affected Persons

Table 6.1.3 Educational Attainment of Project Affected Persons

CONTENTS

CHAPTER 1 - EXECUTIVE SUMMARY 1.1. Introduction - Project and Public Purpose 1.2. Location 1.3. Size and Attributes of Land Acquisition 1.4. Alternatives Considered 1.5. Social Impact 1.6. Mitigation Measures 1.7. Assessment of Social Impacts at different Phases of Project

CHAPTER 2 - DETAILED PROJECT DESCRIPTION 1.1. Background of the Project 1.2. Rationale of the project 1.3. Details of the project size, location, capacity, outputs, production targets, costs and risks 1.4. Examination of Alternatives 1.5. Phases of Project Construction 1.6. Core design features and size and type of facilities 1.7. Need for ancillary infrastructural facilities 1.8. Work Force Requirements (temporary and permanent) 1.9. Details of Studies Conducted Earlier 2.10 Applicable Law and Policies

CHAPTER 3 - TEAM COMPOSITION, METHODOLOGY AND SCHEDULE OF SOCIAL IMPACT ASSESSMENT 3.1. List of all team members with qualifications 3.2. Methodology & Tools 3.3. Sampling Methodology Used

3.4. Overview of information/ data sources used 3.5. Process and Schedule of Activities 3.6. Public Hearing

CHAPTER 4 - LAND ASSESSMENT 3.1. Information about affected area 3.2. Area of impact 3.3. Total land requirement for the project 3.4. Present use of public land in the vicinity of the project area 3.5. Land(if any) already purchased, alienated, leased or acquired, and the intended use for each plot of land required for the project 3.6. Quantity and location of land proposed to be acquired for the project 3.7. Nature, present use and classification of land and if agricultural land, irrigation coverage and cropping patterns 3.8. Size of holding, ownership patterns, land distributions and number of residential houses 3.9. Land prices and recent changes in ownership, transfer and use of lands over the last 3 years

CHAPTER 5 - ESTIMATION AND ENUMERATION 5.1. Families which are directly affected 5.2. Families which are indirectly impacted by the project 5.3. Inventory of productive assets and significant lands

CHAPTER 6 - SOCIO-ECONOMIC AND CULTURAL PROFILE 6.1. Demographic details 6.2. Income and poverty level 6.3. Vulnerable group 6.4. Land Use and Livelihood 6.5. Local economic activities

6.6. Factors that contribute to local livelihoods

CHAPTER 7 - SOCIAL IMPACT MANAGEMENT PLAN 7.1. Approaches to Mitigation 7.2. Measures to avoid mitigate and compensate impact 7.3. Measures those are included in the terms of Rehabilitation and Resettlement 7.4. Measures that the Requiring Body has stated it will introduce in the Project Proposal 7.5. Alterations to project design and additional measures that may be required to address the extend and intensity of impacts across various groups as identified during the Social Impact Assessment process 7.6. Detailed Mitigation Plan

CHAPTER 8 - SOCIAL IMPACT MANAGEMENT PLAN INSTITUTIONAL FRAMEWORK 8.1 Institutional Structures and Key Persons

CHAPTER 9 - SOCIAL IMPACT MANAGEMENT BUDGET AND FINANCINGOF MITIGATION PLAN

8.1. Costs of all resettlement and rehabilitation costs 8.2. Annual budget and plan of action 8.3. Funding sources with breakup

CHAPTER 10 - SOCIAL IMPACT MANAGEMENT PLAN MONITORING AND EVALUATION 9.1. Key Monitoring and Evaluative indicators 9.2. Reporting mechanisms and monitoring roles 9.3. Plan of independent evaluation

CHAPTER 11 - ANALYSIS OF COSTS AND BENEFITS AND RECOMMENDATION ON ACQUISITION

LIST OF ANNEXURES

Annexure 1 (a) : 4 (1) Gazette Notification

Annexure 1 (b) : 4 (1) Notification ()

Annexure 1 (c) : 4 (1) Notification (English)

Annexure 1 (d) : KSPPL Marampilly SV Station Alignment Sketch

Annexure 2 : Socio Economic Survey Questionnaire

Annexure 3 (a) : Public Hearing Notification (Deepika)

Annexure 3 (b) : Public Hearing Notification (Deshabhimani)

Annexure 4 : SIA in News

Annexure 5 : Notice to the affected families

Annexure 6 (a) : List of participants – affected families

Annexure 6 (b) : Participants - officials

Annexure 7 : Government of – Revenue Department- State Policy for Compensation and Transparency in Land Acquisition. Annexure 8 : Details of affected families

1

CHAPTER 1 EXECUTIVE SUMMARY

1.1 Project and public purpose Kochi Salem Pipeline Private Limited (KSPPL) is a Joint Venture of Bharat Petroleum Corporation Limited and Indian Oil Corporation Limited with a 50% equity shares each. The project envisages laying of 12”/8”dia , 429 km LPG pipeline from Kochi to Salem connecting their dispatch terminals at Kochi Refinery and Puthuvypeen and Receipt terminals at Udayamperoor, Palakkad, Coimbatore, Erode and Salem LPG plants of BPCL/IOCL. Authorisation for the project is received from PNGRB (Petroleum and Natural Gas Regulatory Board) and has approvals from MoEF & CC (Ministry of Environment, Forest and Climate Change), PCB (Pollution Control Board), PESO (Petroleum and Explosives Safety Organisation) and from NHAI, Railways, Irrigation, PWD etc for the crossings of the pipeline in Kerala. The project is intended to reduce the movement of LPG through road and transport through pipeline which is considered to be the most safest mode of LPG transport. The pipeline will have Sectionalising Valve Stations at every 12 Kms for closing the pipeline in segments for any other purpose. The size of the SV Station will be normally 2500 square meters (50 x 50 meters) for accommodating the valve and for building a station for accommodating CP panels, SCADA panels and telecom panels and emergency power supplies. Two such SV stations are planned at Thekkumbagam and Marampilly. This Social Impact Assessment Study analyses the Impact on Kochi – Salem LPG Pipeline Project – Acquisition of land for the construction of Sectionalising Valve Station at Marampilly.

1.2 Location The proposed area is located in the District, Kunnathunadu Taluk, Marampilly Village owned by M.I Muhamed Haris (Resurvey No 65/15-2) and M.A Najeeb (Resurvey No 65/15-3).

Social Impact Assessment Land Acquisition for construction of proposed SV Station at Marampilly for the Kochi Salem LPG Pipe Line – Final Report

2

1.3 Size and attributes of land acquisition As per the Kerala Gazette Notification No 50/2017 dated 19.12.2017, approximately 0.1990 hectare land is proposed to be acquired for the Construction of Sectionalising Valve Station. The proposed land is Wet Land and presently used for agricultural purpose.

1.4 Alternatives Considered The pipeline route is selected after considering a detailed route survey and studying the various alternative routes possible for laying the pipeline. The major portion i.e.,60% of the proposed pipeline in Kerala passes through the existing RoU of M/s. Petronet CCK Limited, whose pipeline is in operation since 2001 without any risk. Further, more than 90% of this pipeline passes through agricultural lands and the passage of pipeline through populated and residential areas is limited to the maximum extent possible. Additional protection by way of increased thickness and depth is adopted for such areas which cannot be avoided.

1.5 Social Impact While conducting the Social Impact Assessment, the SIA team observed that the proposed acquisition is using for agriculture purpose and no one is residing in the project area. The agricultural activities of the families will be hindered, apart from that, there shall be no other adverse impacts to ecology or related aspects.

1.6 Mitigation Measures The alignment of the proposed project is designed in a way that the passage of pipe line through populated and residential areas is limited to the maximum extent possible. Thus the impact of the acquisition is also minimized, further safety and security measures to be adopted are ensured by the requiring body. Permits and consent from concerned authorities including PNGRB and MoEF had also been taken by the requiring body. (Source: http://www.ksppl.com/statutory- documents). The implementing agency shall comply all the provisions of the

Social Impact Assessment Land Acquisition for construction of proposed SV Station at Marampilly for the Kochi Salem LPG Pipe Line – Final Report

3

clearances regarding the implementation of the project. Periodical monitoring of the same are also recommended.

Social Impact Assessment Land Acquisition for construction of proposed SV Station at Marampilly for the Kochi Salem LPG Pipe Line – Final Report

4

CHAPTER 2

DETAILED PROJECT DESCRIPTION

2.1 Background of the Project KSPPL is a Joint Venture formed between BPCL and IOCL with 50% participation each, for the execution and operation of a 429 km (224 km in Kerala and 205 km in Tamilnadu) long 12”/8” dia pipeline being constructed from Kochi to Salem along with associated state of the art Telecom, SCADA and APPS systems involving 2 dispatch terminals, 5 receipt stations and 34 SV stations at an estimated investment of Rs. 1112 Cr including IDC.

The project is envisaged for transportation of LPG from BPCL, Kochi Refinery (after its expansion from 9.5 MMTPA to 15.5 MMTPA) and from the proposed IOCL import terminal Puthuvypeen to BPCL/IOCL LPG plants at IOCL Udayamperoor, BPCL Palakkad, BPCL Coimbatore, IOCL Coimbatore, Erode, and Salem. The project is intended to reduce the movement of LPG through road, and transport it through pipeline which is considered to be the safest mode of LPG transport.

Authorisation for the project is received from PNGRB (Petroleum and Natural Gas Regulatory Board) and has approvals from MoEF & CC (Ministry of Environment, Forest and Climate Change), PCB (Pollution Control Board), PESO (Petroleum and Explosives Safety Organisation) and from NHAI, Railways, and Irrigation PWD etc. for the crossing of the pipeline in Kerala.

2.2 Rationale of the project Pipeline mode of transport is considered to be the safest mode of transport of petroleum products and Kerala Govt. has insisted for movement of LPG through pipeline instead of roadways, which is prone to accidents and related major consequences. The project envisages the movement of LPG through pipeline from Kochi Refinery and IOCL, Puthuvypeen to the bottling plants of IOCL and BPCL as

Social Impact Assessment Land Acquisition for construction of proposed SV Station at Marampilly for the Kochi Salem LPG Pipe Line – Final Report

5

per the product demand pattern. LPG is mainly consumed for domestic purposes. Thus the proposed project shall be considered as a public purpose as per Section 2 of RTFCTLARR Act, 2013 (30 of 2013).

2.3 Details of the project size, location, capacity, outputs, production targets, costs and risks

i. Pipeline Starting Point : Kochi, Kerala ii. Pipeline Terminating Point : Salem, Tamil Nadu iii. Pipeline Length : 429 Kms iv. Pipeline Specification : API 5L X65/70 Grade v. Pipeline Capacity : 1.53 MMPTA including common Carrier Capacity vi. Pipeline Size : 12”/8” (6.4/7.1/7.9/8.8/9.5mm) vii. Product : LPG viii. Design Pressure : 95 Kg/ cm2 ix. SV Stations : 34 Nos x. Project Cost : Rs.1112 Crore (including IDC) xi. Scheduled Date of Completion : 25.02.2019 xii. Environment Impact Assessment is carried out by M/s Mecon Limited and all the mitigations suggested for avoiding risk during the construction and operation of the pipeline is taken care of. Further EIL (Engineers India Limited) have carried out the HAZOP studies for the pipeline and the recommendations are being implemented.

2.4 Examination of Alternatives The pipeline route is selected after considering detailed route survey and studying the various alternative routes possible for laying the pipeline. The major portion i.e.,60% of the proposed pipeline in Kerala passes through the existing RoU of M/s.

Social Impact Assessment Land Acquisition for construction of proposed SV Station at Marampilly for the Kochi Salem LPG Pipe Line – Final Report

6

Petronet CCK Limited, whose pipeline is in operation since 2001 without any risk. Further, more than 90% of this pipeline passes through agricultural lands and passage of pipeline through populated and residential areas is limited to the maximum extent possible. Additional protection by way of increased thickness and depth is adopted for such areas which cannot be avoided

2.5 Phases of Project Construction The project execution in Kerala is divided into three phases: I. Kochi Refinery to Udayamperoor (12 Kms) This portion of the pipeline is commissioned and is in operation since August 2017. II. Kochi Refinery to BPCL Palakkad Bulk Terminal The work related to the above pipeline is in progress. All the materials required for this portion have been procured and contracts awarded. RoU for laying the pipeline is mostly acquired. III. IOCL Puthuvypeen to Kochi Refinery This will be taken up in synchronization with the construction of Puthuvypeen terminal by IOCL.

2.6 Core design features and size and type of facilities The pipeline is constructed as per ASME 31.6 complying OISD 141 and224 (Oil Industry Safety Directorate) standards and the material used for construction are as per API standards. The pipeline will have Sectionalising Valve Stations every 12 Kms for closing the pipeline in segments for any purpose. The pipeline is cathodically protected against corrosion using impressed current which is regularly monitored. This is apart from three LPE coating provided for the pipeline. The entire cross country portion of the pipeline is laid underground keeping a minimum depth of 1.5 meters. The size of the SV station will be normally 50 x 50 (2500 Square Meters) for accommodating the valve and for building a station for accommodating

Social Impact Assessment Land Acquisition for construction of proposed SV Station at Marampilly for the Kochi Salem LPG Pipe Line – Final Report

7

CP panels, SCADA panels and telecom panels and emergency power supplies. One such SV station is planned at Marampilly.

2.7 Need for ancillary infrastructural facilities

The project is about construction of pipeline which will have apart from the pipeline, Sectionalising Valve Stations, Receipt and Dispatch Terminals.

2.8 Work Force Requirements

Normal work force during construction will be around 350 and permanent work force upon commencement will be around 20.

2.9 Details of Studies Conducted Earlier

Environment Impact Study was conducted by M/s. Mecon Limited, a Govt. of India enterprise which has the approval for conducting such studies as per Ministry of Environment and Forest and all the suggestions and mitigation measures given in the report are complied with.

2.10 Applicable Law and Policies

The applicable laws on land acquisition, rehabilitation and resettlement for the proposed project are:

. The Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 . Government of Kerala – Revenue Department -State Policy for Compensation and Transparency in Land Acquisition . Right to Information Act, 2005

Social Impact Assessment Land Acquisition for construction of proposed SV Station at Marampilly for the Kochi Salem LPG Pipe Line – Final Report

8

CHAPTER 3 TEAM COMPOSITION, METHODOLOGY AND SCHEDULE OF SOCIAL IMPACT ASSESSMENT

3.1 List of all team members with qualifications The study team is headed by the Project Director, RAJAGIRI outREACH, who is the Chairperson of the SIA Unit. A team of six members having experience in conducting Social Impact Assessment studies and socio-economic surveys were assigned for data collection, monitoring of data collection, coordination and report preparation of the study. Representatives from the Revenue Department supported the investigators to identify the affected families.

Sl.No Name Qualification and Experience Designation MeenaKuruvilla MSW, 30 years in 1 Director Chairperson - SIA Unit development RajagirioutREACH sector MSW, Project 21 years in 2 Princy Jacob Coordinator - SIA Unit development sector MSW, 20 years in 3 Ligi V. E Research Officer - SIA Unit development sector M A Sociology, PGDHS; 13 years in 4 Linda Chacko Research Associate - SIA development Unit sector MSW, Documentation 1 year in 5 Arun Mathews George Officer – SIA Unit development sector BA – Research Associate 23 years in 6 Biju C .P development sector

Social Impact Assessment Land Acquisition for construction of proposed SV Station at Marampilly for the Kochi Salem LPG Pipe Line – Final Report

9

3.2 Methodology & Tools

The objective of Social Impact Assessment (SIA) is to enumerate affected land and structures, affected families and persons, to identify social impacts, and to prepare Social Impact Management Plan (SIMP). In order to capture data for the present exercise, both primary as well as secondary sources were systematically collected. SIA unit had also examined the records and documents including the alignment drawing of the proposed project. SIA team had also made a site visit along with the land revenue officials for information dissemination. Questionnaires and interview schedules were used as tools for data collection.

3.3 Sampling Methodology Used As a part of SIA, Census Socio-Economic survey has been conducted by experienced members of SIA Unit to list out the adverse impacts of the proposed project. Before the actual household Socio-Economic Survey, all the properties that were likely to be affected by the project were identified with the support of the Revenue Department staff. The survey was conducted through door-to-door personal interview. In this interview, the size and nature of the land was recorded. The details of affected families, possession of legal documents, data related to social profile, family details, occupation, source of income, family expenditure, self employment activities, and employment pattern were collected. Majority of the interview schedule has been pre-coded, except those reflecting the opinion and views of PAFs, which have been left open-ended. Before filling the questionnaires, the affected families were asked to provide a copy of the necessary documents they need to produce as proof of their ownership of the property.

3.4 Overview of information/ data sources used Secondary source information was collected from various concerned departments including Office of the Special Tahsildar (LA), NH II, and a host of other literatures. Thus, secondary source information complemented the primary

Social Impact Assessment Land Acquisition for construction of proposed SV Station at Marampilly for the Kochi Salem LPG Pipe Line – Final Report

10

data elicited through field survey from the affected people and other stakeholders. Understanding was created about the physical, social, economic, and cultural set-up of the project area before undertaking detailed field investigations. 3.5 Process and Schedule of Activities 16-10-2017 - District Collector, entrust RAJAGIRI outREACH to conduct the SIA study 19-12-2017 Publication of 4 (1) notification in Kerala Gazette

21-12-2017 - Discussion with members of affected family

25-01-2018 - Draft Report Submission

29-01-2018 - Held Public Hearing

23-02-2018 - Final Report Submission

Public Hearing

Social Impact Assessment Land Acquisition for construction of proposed SV Station at Marampilly for the Kochi Salem LPG Pipe Line – Final Report

3.6 PUBLIC HEARING Land Acquisition for construction of proposed SV Station at Marampilly for the Kochi Salem LPG Pipe Line Project

Venue: Vazhakkulam Conference Hall Date & Time: 29.01.2018; 02.00 PM Participants: Project Affected Family members, Local Self Government Representatives, KSPPL Officials, Special Tahsildar (LA), ALuva, Social Impact Assessment Unit (RAJAGIRI outREACH)

Major Concerns/ Necessities Raised by the Land Owners in the Public Hearing

Sl No Affected Family Survey No Raised Concerns/ Necessities Remarks by the Requiring Body 1 Muhammed ReSurvey 1). The proposed land is converted land. LAO can determine the Haris No Huge investment in terms of money and compensation payable as per the Mandaattikudiyil, 65/15-2 human effort has been made for making the Act/ prevailing guidelines taking Vadakke land so. The property was filled with soil in to consideration the Vazhakkulam, by 6 feet height. A well has been digged, improvements Marampilly electricity connection was availed and a motor house was also constructed. All vegetable required for household needs are being cultivated in the said land. The land is not inherited, rather purchased with his own earnings. So acquisition of the land is very aching. By making minor change in the plan/alignment the acquisition of the

12

said land can be avoided. Kindly make change in the alignment and exclude the land from acquisition.

2). There are lands which are not converted The specific land is chosen based and are open lands. Why those lands are on technical/ operational/ safety not being considered for acquisition. requirements and hence cannot be changed.

3). Since the proposed acquisition land is LAO to decide on this as per land already converted, the requiring body will acquisition guidelines be benefitting from the same. So the compensation should be provided accordingly after considering the improvements in the property.

4). The land was purchased with the No separate land will be provided intention of using it for residential purpose. All the preparations for had been already made. Since the same was intended for the purpose of housing, whether separate land will be provided as compensation?

5) The land is being acquired by private KSPPL is a joint venture of BPCL limited company. How does the same is and IOCL in which bot h defined as ‘public purpose’? companies hold 50% shares each. Since no company is hold

Social Impact Assessment Land Acquisition for construction of proposed SV Station at Marampilly for the Kochi Salem LPG Pipe Line – Final Report

13

morethan 50% share, the company has been termed as private limited company as per companies Act.

6). If there are no ‘wet now dry’ land in the The land value will be determined radius of 3 KM, whether the extent will be by considering the sale deed of increased for valuing the market price? similar and similarly located sites executed prior to 3 years of notification with a radius of 5 Kms. The land value will be determine as per the condition stipulated in section 26 of RFCTLARR Act 2013

7) Whether the land value will be Yes ascertained by considering the value of land with similar characteristics?

8) While collector call for negotiation Prior intimation regarding the whether prior intimation regarding the meeting will be given and the basic amount / land value will be given? land value arrived will be Whether collector himself will be present in intimated at the meeting. The the negotiation meetings. Whether the District Collector himself decision regarding the land value pricing conducting the negotiations and can be intimated on a later stage, or should the negotiated price will be it be informed in the meeting itself ? intimated by the DC at the meeting subject to approval of SLEC

Social Impact Assessment Land Acquisition for construction of proposed SV Station at Marampilly for the Kochi Salem LPG Pipe Line – Final Report

14

2 Najeeb Re survey 1). The proposed land is converted land The specific land is chosen based Mandaattikudiyil, No and adjacent land is low lying to the on technical/ operational/ safety Vadakke 65/15-3 proposed land. Large investment in terms requirements and hence cannot be Vazhakkulam, of money and human effort has been changed Marampilly delivered for making the land in the present condition. The garment unit functioning in the adjacent area was intended to shift to this area. By making slight variation in the alignment, the acquisition of the proposed land can be avoided. The necessary

changes shall be made and acquisition should be avoided.

2). If acquisition is unavoidable, LAO to decide as per the land considering the above facts and acquisition guidelines improvement made in the property compensation shall be availed.

Social Impact Assessment Land Acquisition for construction of proposed SV Station at Marampilly for the Kochi Salem LPG Pipe Line – Final Report

CHAPTER 4 LAND ASSESSMENT

4.1. Information about affected area The land proposed to be acquired for the project is owned by M.I Muhammed Haris (0.0992 hectares) and M.A Najeeb (0.0930 hectares) located at Resurvey No 65/15-2 and Resurvey No 65/15-3 respectively. The proposed land is at Block 24, Marambilly Village, Kunnathunadu Taluk, .

Proposed Acquisition Sketch

16

4.2. Area of impact The proposed land acquisition shall affect the owners losing their property. Nearly 0.1922 hectares of land shall be acquired for the project. 2 properties owned by 2 different individuals are affected by the acquisition. The proposed land is used for agricultural purpose which will be adversely affected by the proposed project.

4.3. Total land requirement for the project For the construction of SV station at Marampilly for proposed Kochi – Salem LPG pipeline, approximately 2500 square meter (0.25 hectare) of land is required at Marambilly Village.

4.4 Present use of public land in the vicinity of the project area The area in the vicinity of the project area are owned by private parties and no public land is available in the surrounding area.

4.5 Land (if any) already purchased, alienated, leased or acquired, and the intended use for each plot of land required for the project No land is purchased, alienated, leased or acquired already in the area for the requirement of the proposed project.

4.6 Quantity and location of land proposed to be acquired for the project Nearly 0.1922 hectares of land is proposed to be acquired for the proposed project. The properties are located at a distance of approximately 800 meters away from Marampilly Junction in Aluva – KSRTC Bus route.

4.7 Nature, present use and classification of land and if agricultural land, irrigation coverage and cropping patterns

The proposed land is wet land according to the records of the land officials. The land owners had made improvements in the land, elevated the plot by filling with soil after building proper basement. The land is a converted property which the land owners using for agriculture presently. Mr Haris has invested his wealth and health in the land to make the land as a good yielding productive asset. They

Social Impact Assessment Land Acquisition for construction of proposed SV Station at Marampilly for the Kochi Salem LPG Pipe Line – Final Report

17

cultivate plantation crops such as coconut, mango, jackfruit; horticulture crops such as plantain,; and cash crops such as ginger, turmeric and others such as teak and guava. For irrigational purpose an open well is dug from which water is pumped to the agriculture using electric motor. The land owner Mr Haris has availed electricity also for the same.

4.8. Size of holding, ownership patterns, land distributions and number of residential houses The total area of acquisition proposed is nearly 0.1922 hectares, in which 0.0992 hectares is owned by M I Muhammed Haris (Resurvey No 65/15-2) and 0.0930 hectares of land is owned by M A Najeeb (Resurvey No 65/15-3). The proposed area is wet land used for agricultural purpose and is not used for residential purpose.

4.9. Land prices and recent changes in ownership, transfer and use of lands over the last 3 years As per the information given by the respondents, no transactions on the proposed acquiring land had been taken place in the affected area for the last three years.

Proposed Acquisition Land

Social Impact Assessment Land Acquisition for construction of proposed SV Station at Marampilly for the Kochi Salem LPG Pipe Line – Final Report

18

CHAPTER 5 ESTIMATION AND ENUMERATION

5.1 Families which are directly affected Two families i.e. (M.A Najeeb and M.I Muhammed Haris) land owners of the proposed project area are considered to be directly affected by the project. The area planned to be procured is not hampering the livelihood of the respondents. The proposed project area is an agricultural land where they cultivate coconut, mango, jack fruit, teak, guava, sapota, plantain, ginger, turmeric etc. For irrigation, they dug an open well and pump house. Mr M I Muhammed Haris had availed an electricity connection at his land for his use. He had made ample effort to make the land as a productive asset. Apart from agriculture there are no other economic activities being carried out in the area.

5.2 Families which are indirectly impacted by the project There shall be no indirect impact by the acquisition of land for the proposed project.

5.3 Inventory of productive assets and significant lands The only economic activity in the affected area is the cultivation of various crops. As per the estimation the project will result in the loss of the below mentioned agricultural products.

Sl Frequency Trees/ Crop Affected No Resurvey No 65/15-2 Resurvey No 65/15-3 1 Coconut tree 25 18 2 Teak 1 1 3 Jackfruit tree 2 1 4 Mango Tree 4 1 5 Guava tree 2 -

Social Impact Assessment Land Acquisition for construction of proposed SV Station at Marampilly for the Kochi Salem LPG Pipe Line – Final Report

19

6 Sapota tree 1 - 7 Plantain 100 5 In addition to the above mentioned crops, cash crops such as turmeric, ginger, food crops such as Colocasia, Elephant Yam are also cultivated in the area.

The land owners had made improvements in the land, elevated the plot by filling with soil after building proper basement. The land is a converted property which the land owners using for agriculture presently. For irrigation, Mr M I Muhammed Haris dug an open well and pump house and availed an electricity connection at his land for his use.

Social Impact Assessment Land Acquisition for construction of proposed SV Station at Marampilly for the Kochi Salem LPG Pipe Line – Final Report

20

CHAPTER 6 SOCIO-ECONOMIC AND CULTURAL PROFILE

6.1 Demographic Details

The demographic details such as age, gender, religious group, social group, marital status and educational attainment status of the project affected families are included in this section.

Table 6.1.1 Age Group and Gender

Gender Age in years Total Male Female 0-18 1 2 3 19-30 1 2 3 31-45 2 1 3 46-59 - 1 1 60 and above 2 1 3 Total 6 7 13

Table 6.1.1 reveals the age group distribution of the affected persons in the area. 2 male respondents and 1 female are belong to the age group above 60 years of age. 1 female member is in the age group of 46-59.

Religious Group & Social Group Both the affected families are following Muslim religion and belong to OBC group.

Table 6.1.2 Marital status of Project Affected Persons Marital Status Frequency Percent Married 10 76.9

Unmarried 3 23.1

Total 13 100

Social Impact Assessment Land Acquisition for construction of proposed SV Station at Marampilly for the Kochi Salem LPG Pipe Line – Final Report

21

Table 6.1.2 depicts that among the total 13 members in the affected families10 are married and 3 are unmarried. No widows/widowers and divorcees are included among the affected population.

Family Pattern Both the affected families are joint families.

Table 6.1.3 Educational Attainment of Project Affected Persons

Description Frequency Percent

Up to 5th standard 4 30.8 5th to plus two 4 30.8 Degree 1 7.7 PG/Professional Course 4 30.8 Total 13 100

Table 6.1.3 reveals about the information regarding the educational attainment of the project affected persons in the area, 1 member attained graduation, 4 members are having post graduate/professional course education.

6.2 Income and Poverty Level Both the affected families belong to APL section based on the classification by Public Distribution System. One of the family has revealed that they have monthly income above Rs.100, 000.00 while the other family earns Rs .6000/- per month

Occupational Pattern Among the total of 13 affected persons, 6 of the members are dependents who are students/ elderly. 3 members are engaged in business activities for their livelihood measures. 2 members are employed in private sector.

6.3 Vulnerable Groups Among the total 13 affected persons in the area 4 are women, 3 children and 3 elderly who all should be considered as vulnerable population in the area.

Social Impact Assessment Land Acquisition for construction of proposed SV Station at Marampilly for the Kochi Salem LPG Pipe Line – Final Report

22

6.4 Land Use and Livelihood The land owners cultivate plantation crops such as coconut; food crops such as colocasia, elephant yam, horticulture crops such as mango, jackfruit; and cash crops such as ginger, turmeric and others in the project effected area. Presently no families are residing in the project area so there is no direct impact on their housing.

6.5. Local economic activities The major economic activities that were observed in the affected area are cultivation of plantation crops, cash crops.

6.6. Factors that contribute to local livelihoods The land is used for agricultural purpose, and is one of the sources of income for the 2 affected families. Apart from agriculture, no other economical activities are being carried out in the area.

Social Impact Assessment Land Acquisition for construction of proposed SV Station at Marampilly for the Kochi Salem LPG Pipe Line – Final Report

23

CHAPTER 7 SOCIAL IMPACT MANAGEMENT PLAN

7.1 Approaches to Mitigation There shall be no displacement of families by the proposed acquisition. Primary source of livelihood of families are also not affected. The impact of the project is the loss of agriculture land for the affected families. Commencement of the present land acquisition laws and policies shall mitigate the impact of the proposed project.

7.2 Measures to avoid mitigate and compensate impact Provisions of compensation for the land acquisition under the RTFCTLARR Act, 2013 shall be enough to mitigate impacts regarding loss of land.

7.3. Measures those are included in the terms of Rehabilitation and Resettlement Since there shall be no displacement of families by the proposed land acquisition, rehabilitation and resettlement are not required here.

7.4. Measures that the Requiring Body has stated it will introduce in the Project Proposal An Environment Impact Study is already conducted by M/s. Mecon Limited, a Govt. of India enterprise which has the approval for conducting such studies as per Ministry of Environment and Forest and all the suggestions and mitigation measures given in the report are complied with.

7.5. Alterations to project design and additional measures that may be required to address the extend and intensity of impacts across various groups as identified during the Social Impact Assessment process Not Applicable

7.6. Detailed Mitigation Plan Not Applicable

Social Impact Assessment Land Acquisition for construction of proposed SV Station at Marampilly for the Kochi Salem LPG Pipe Line – Final Report

24

CHAPTER 8 SOCIAL IMPACT MANAGEMENT PLAN INSTITUTIONAL FRAMEWORK

8.1 Institutional Structures and Key Persons The RTFCTLARR Act, 2013 defines the Administrator appointed by the State Government as the person responsible for the preparation of the Rehabilitation and Resettlement Scheme for affected families of Land Acquisition. Subject to the superintendence, directions, and control of the appropriate Government and the Commissioner for Rehabilitation and Resettlement, the formulation, execution and monitoring of the Rehabilitation & Resettlement Scheme shall be vested in the Administrator. In the Land Acquisition for Construction of the proposed SV station at Marampilly for Kochi - Salem pipeline project, the major mitigation measures from the acquisition can be handled by providing the appropriate compensation under the RTFCTLARR Act, 2013.

As per G.O. (Ms.) No.485/2015/RD, dated 23/09/2015, The Kerala State Policy for Compensation and Transparency in Land Acquisition,

The District Level Fair Compensation, Rehabilitation and Resettlement Committee comprises the:

. District Collector . Administrator for resettlement and rehabilitation, . Land Acquisition officer, . Finance Officer, . Representatives of the requiring body to take financial decisions on its behalf, . Representatives of Local Self Government Institution

Note: (Since no one is displaced by the project, no rehabilitation is required)

Social Impact Assessment Land Acquisition for construction of proposed SV Station at Marampilly for the Kochi Salem LPG Pipe Line – Final Report

CHAPTER 9

SOCIAL IMPACT MANAGEMENT BUDGET AND FINANCING OF MITIGATION PLAN

9.1. Costs of all resettlement and rehabilitation costs Not Applicable

9.2. Annual budget and plan of action Not Applicable

9.3. Funding sources with breakup Not Applicable

26

CHAPTER 10

SOCIAL IMPACT MANAGEMENT PLAN MONITORING AND EVALUATION

10.1 Key Monitoring and Evaluative indicators Not Applicable

10.2 Reporting mechanisms and monitoring roles Not Applicable

10.3 Plan of independent evaluation Not Applicable

Social Impact Assessment Land Acquisition for construction of proposed SV Station at Marampilly for the Kochi Salem LPG Pipe Line – Final Report

27

CHAPTER 11

ANALYSIS OF COSTS AND BENEFITS AND RECOMMENDATION ON ACQUISITION

The project is intended to reduce the movement of LPG through road and transport through pipeline which is considered to be the most safest mode of LPG transport. The pipeline route is selected after considering a detailed route survey and studying the various alternative routes possible for laying the pipeline. The major portion of this pipeline in Kerala passes through the existing RoU of M/s. Petronet CCK Limited, whose pipeline has been in operation since 2001 without any risk. Further, more than 90% of this pipeline passes through agricultural lands and the passage of pipeline through populated and residential areas is limited to the maximum extent possible. Additional protection by way of increased thickness and depth is adopted for such areas which cannot be avoided.

While conducting the Social Impact Assessment, the SIA team observed that the proposed acquisition is using for agriculture purpose and no one is residing in the project area. The land owners had made improvements in the land, elevated the plot by filling with soil after building proper basement. The land is a converted property which the land owners using for agriculture presently. For irrigation, Mr M I Muhammed Haris dug an open well and pump house and availed an electricity connection at his land for his use.

Due to the acquisition of land the agricultural activities of the families will be hindered and the owner cannot be able to engage in any agricultural activity, or construction of any buildings in future. Apart from that, there shall be no other adverse impacts to ecology or related aspects.

The project is treated as a public purpose project under the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and

Social Impact Assessment Land Acquisition for construction of proposed SV Station at Marampilly for the Kochi Salem LPG Pipe Line – Final Report

28

Resettlement Act, 2013 (30 of 2013) Section 2. Considering the public advantage and interest, and treating the project as a vital need, the project implementation is recommended.

Social Impact Assessment Land Acquisition for construction of proposed SV Station at Marampilly for the Kochi Salem LPG Pipe Line – Final Report

(SolQOOo CD (TU(3 4

( qc/8 11(3) d9>06nace>)

oflS96RJ>3aJCno

mmi« cr\5l4-13203/17

(2«fe®@ cruf8da)Of3 09/12/2015 ©ej a u © ( cruocjL>oo6m) a)(ni(3 649/2015/oai Oj|©6TO>OaJO) (Qj (D«%|nJ(5laOO(d(OTO)1a5o a\}<0) 0(5 ^ 0)Qgo cgm(d(JL)1ajo(TucoTO)1aao ojmicniDOnJCDajiolaexggg (oraoid&oao © ro ^ (Cda>(© 30, 2013) (Q jd& oo^gg cfegd^Qos -qjc>(0)ejc/8 (Dl(8qjno1

^CCOOQSOnjjiggg nJ§1da>C0)1(08 Oj1oi(d1.!3j]|gf3 (gffll 63(03 ©oJOgD (5^0105^(030)1(0, ©T5(0)0(Q)(0)“ 6)<&>Q'$ - CCTUeJo ©©aJn^ ©©£J08 S.V (©1(D0^o V -

2013 - ©oi (gal n$6>g§<£6)ej1(o3 on^oooxaooQ) (Do^nj©1oO0(5(CT0)l05o

(r y (0) 0(5 ^(0)cgo ojcr)(oa51ojocrua3TO)laoo njo):ouooaJ(D(oio>1(ra(8f3f3 (srooic&ooo (STO)^

(Cc63(0 (5T0)d^v 30, 2013) 4-)0 Old&cxJ' (1)-)° gaJOJceaojleiei Ol^OJ(TUQdft>o8d06)aony(O)£DOQQ)l, 83l^y0 d0Dg<^>(8, (0)0©

(051(03ffl0O51^jl(5l

gDCn-jooS, (© age io s3l^yo(© ej crootgan^ (ng(0)^o«ejo(0) oi1ejcQ)1(03(0T0)(08

0^6 0)1^0 (2) 00830)1(51 © D § " (5 1 ^ r^)O6O)Od030(OTO)1©D 0)1(2)00 (5T5n5O5O(T\5ld063(TT)

(5l(0)1(D)1^Jg3£ CTUOqjoO^ (^(0)^0^010(0) fiJOCDo (DSgffi2>(TD(0)ln0o (TOO£gaO^ (o=j(0)^0f>eJ0(0)

0)1(8 qyaD6TD oJ(UD(0)1 (0)0$0O0de63OT)(0)1O5o ^ffl(O)ei©c^§(O!O)1(D>1<5ld063OT5. fD D (oJ(g)1CQ)

(56TT§“ fflO(T\)(O!O)l(Dd0t>o (0)1 (8oJ0Gcfi6)61^(0)060)“. ©(03 dft>0©60)01050^Jo 6 0)000(030)1(58 gb§OJ008 aJ0§f3f3(0)^j. gal^J a4)O6TT)0

( w o ^ c f i o '.cfecm^cnos q3(s^js3“ : fflOomSg^

(^*8308 dkltf& W OD^^tolfflteCTO.)

j o flo i® 6 n )o o©©1

00.19.90 rolejo c^crodtoQ! 1 caoocojlg^i 65/15

(o^O sSl^jjO cfeg<%$

g(5ic)(90jlo8 (Qj^orao

C03gd^c3 (oy)(C?> nfi)) [See rule 11(3)]

NOTIFICATION C4-13203/17 Dated : 24/11/2017

WHEREAS, it appears to the Government of Kerala that the land specified in the schedule below is needed or likely to be needed for a public purpose, ie for the construction of SV Station for the proposed Kochi Salem

LPG Pipe Line.

AND WHEREAS, in exercise of the powers conferred in sub-section (1) of section 4 of the Right to Fair Compensation and Transparency in Land

Acquisition, Rehabilitation and Resettlement Act, 2013 (Central Act 30 of

2013), Government of Kerala have decided to conduct a Social Impact

Assessment in the area specified in the schedule below.

Now, therefore, sanction is accorded to the District Level Social Impact

Assessment Unit, Rajagiri Educational Alternatives and Community

Health( Out Reach), Rajagiri RO, Kalamassery, Ernakulam District to conduct a Social Impact Assessment Study and to prepare a Social Impact Management

Plan as provided in the Act, the process shall be completed within a period of two months months, not exceeding six months in any case. SCHEDULE

District Emakulam Village Marampilly, and Desom Vadakkevazhakkulam Taluk Kunnathunadu

—------—•—~—---«-----:--- — i SL.No. Village Suvey Number Description Extent H. Are. Sq. Meter 1 Marampilly Block 24 Wet as perBTR 00.19.90 Resurvey 65/15

Total 00.19.90

(Sd/-) District Collector

Forwarded by order

Deputy Collector (LA)

T13

Annexure 1(d)

1

Socio Economic Survey for Social Impact Assessment Study Land Acquisition for Construction of SV Station at Marampilly for KSPPL, Ernakulam District

SIA Ref No Interviewer’s Name Survey Date Supervisor Name Data Entry Staff’ Name Data Entered Date Data verified by, and Date

Name of the respondent______

Name of the Affected Family (Head)______

Place/ Location Q.1 Identification Ward No. Name of Panchayath

ASSET DETAILS

Q. 2 Type of property a) Open land b) Nilam c) Nilam Nikathu Purayidam

Q.3 Type of use a) Open Land b) Agriculture c) Residential d) Others Specify______

Q.4 Address details Address of the Affected Property (with pincode) Communication Address (with pincode)

Q.5 Contact Number:

Socio Economic Survey - SIA for SV Station at Marampilly for KSPPL 2

Q.6Name of title holder/s of the property (specify the names of all the members specified as per the title deed)

Date of acquiring of the property (approx)

Details of transactions made on the property

within the last three years

Q.7 Acquisition by a) Hereditary b) Purchase c) Encroached d)Lease/Rent

Q. 8 Property Details a) Survey No______b) Total Area owned______c) Area of acquisition______

Q.9 Extent of acquisition: Fully Partially

Q.10 Whether you will be displaced: Yes No

Q.11 Religious Group: Hindu Muslim Christian Other Specify______

Q.12 Social Group: SC ST OBC General Others Specify______

Q.13 Ration Card Yes No Ration Card Number______

Q.14 Type of Ration Card APL BPL AAY Not Applicable

Q.15 Family Pattern Joint Nuclear Individual

Socio Economic Survey - SIA for SV Station at Marampilly for KSPPL 3

Q.16 FAMILY MEMBERS - DETAILS

Education

Sl.N

Monthly o Marital Major Name Age Sex Job Status diseases Income

of the family the of

ontinuing

C

Completed Relationship with the Head Head the with Relationship

Socio Economic Survey - SIA for SV Station at Marampilly for KSPPL 4

Q.17 Family Monthly Income______Q.18 Family Monthly Expenditure______

Q.19 No of adult earning members______Q.20 No of dependents ______

Q.21 Major Source of Income ______

Q.22 Livelihood (Major Source of Income) of Family Affected Yes No

Q.23 Whether agriculture is affected Yes No

Q.24 If Yes, Mention loss Number of trees/ Sl No Affected Crop Agriculture area affected crops affected

Q.25.Are you aware of the proposed Keezhmurikadavu Bridge approach Road project ? Yes No

Q.26 If yes, source of information Newspaper Internet/social media

TV/ Media Community members

All of the above Others Specify______

Q.27 Opinion about the project ______

______

Socio Economic Survey - SIA for SV Station at Marampilly for KSPPL 5

Q.28 Views regarding acquisition of land______

______

Q.29 Additional Information, If any______

______

Socio Economic Survey - SIA for SV Station at Marampilly for KSPPL

Annexure 8

Social Impact Assessment Study – SV Station Construction for KSPPL at Marampilly Details of Affected Family Members

Najeeb M A Muhammed Haris Mandattikudiyil House Name, Address Mandattikudiyil House Vadakkevazhakkulam and Contact No of Vadakkevazhakkulam Marampilly, Ernakulam District Affected Family Marampilly, Ernakulam District Ph: 98951 96691 Ph: 91598 37866 81299 54904

Resurvey No Resurvey No Survey No 65/15-2 65/15-3 Block 24 Block 24

Description Wet Land Wet Land

Type of Use Agricultural Land Agricultural Land

Area of Acquisition 0.0992 (Hectare) 0.0930

Extent of Acquisition Fully Fully

Rajagiri College of Social Sciences Rajagiri P.O Kalamassery, Pin: 682 104 Ph: 0484 29110-332 www.rajagirioutreach.org