Language: English Original: English
PROJECT: MOMBASA - NAIROBI – ADDIS ABABA ROAD CORRIDOR PROJECT PHASE II
PROJECT APPRAISAL REPORT
Date: June 2009
Team Leader: A. OUMAROU, Transportation Engineer, OINF.2
Team Members N. KULEMEKA, Socio-Economist, OINF.2 D. KIDANE, Infrastructure Specialist, ETFO Appraisal Team T. OPIYO, Infrastructure Specialist, KEFO
Sector Manager: J. RWAMABUGA, OINF.2 Sector Director: G. MBESHERUBUSA, OINF Regional Director: D. GAYE, OREA/OREB
R. SHERMAN Procurement Specialist, ORPF.1 L. EHOUMAN Transport Economist, OINF.1 Peer Reviewers P. KARANI Environmental Officer, OWAS M. AJIJO Consultant Transport Economist, ONRI
TABLE OF CONTENTS
I. STRATEGIC THRUST & RATIONALE ...... 1 1.1. PROJECT BACKGROUND...... 1 1.2. PROJECT LINKAGES WITH COUNTRIES STRATEGIES AND OBJECTIVES ...... 1 1.3. KEY DEVELOPMENT ISSUES...... 2 1.4. RATIONALE FOR BANK’S INVOLVEMENT...... 2 1.5. DONORS COORDINATION...... 3 II. PROJECT DESCRIPTION ...... 3 2.1. CORRIDOR DEVELOPMENT PROGRAM AND PHASING...... 3 2.2. PROJECT DEVELOPMENT OBJECTIVES...... 4 2.3. PROJECT COMPONENTS ...... 4 2.4. TECHNICAL SOLUTION RETAINED AND OTHER ALTERNATIVES EXPLORED ...... 5 2.5. PROJECT TYPE...... 6 2.6. PROJECT COST AND FINANCING ARRANGEMENTS ...... 6 2.7. PROJECT’S TARGET AREA AND BENEFICIARIES ...... 7 2.8. PARTICIPATORY PROCESS FOR PROJECT DESIGN AND IMPLEMENTATION ...... 8 2.9. BANK GROUP EXPERIENCE, LESSONS REFLECTED IN PROJECT DESIGN...... 9 2.10. KEY PERFORMANCE INDICATORS ...... 10 III. PROJECT FEASIBILITY...... 10 3.1. ECONOMIC AND FINANCIAL PERFORMANCE...... 10 3.2. ENVIRONMENTAL AND SOCIAL IMPACTS...... 11 IV. IMPLEMENTATION...... 12 4.1. IMPLEMENTATION ARRANGEMENTS ...... 12 4.2. MONITORING ...... 14 4.3. GOVERNANCE ...... 14 4.4. SUSTAINABILITY ...... 15 4.5. RISK MANAGEMENT...... 16 4.6. KNOWLEDGE BUILDING ...... 17 V. LEGAL INSTRUMENTS AND AUTHORITY ...... 17 5.1. LEGAL INSTRUMENT...... 17 5.2. CONDITIONS ASSOCIATED WITH BANK’S INTERVENTION ...... 17 5.3. COMPLIANCE WITH BANK POLICIES ...... 18 VI. CONCLUSIONS AND RECOMMENDATION...... 18 6.1 CONCLUSION...... 18 6.2 RECOMMENDATIONS ...... 19
ETHIOPIA – COMPARATIVE SOCIO-ECONOMIC INDICATORS ...... 20 KENYA – COMPARATIVE SOCIO-ECONOMIC INDICATORS ...... 21 KENYA - BANK GROUP ONGOING PROJECTS AS OF MAY 2009...... 22 ETHIOPIA - BANK GROUP ONGOING PROJECTS AS OF MAY 2009...... 23 KENYA - RELATED PROJECTS FINANCED BY THE BANK AND OTHER DONORS...... 24
ETHIOPIA - RELATED PROJECTS FINANCED BY THE BANK AND OTHER DONORS...... 25 MAP OF PROJECT AREA ...... 26 MOMBASA-NAIROBI-ADDIS ABABA ROAD CORRIDOR DEVELOPMENT PROGRAM ...... 27 COUNTRY AND SECTOR BRIEF ...... 28 LESSONS LEARNED...... 36 PROJECT DETAIL COSTS ...... 37 IMPLEMENTATION ARRANGEMENTS...... 39 FINANCIAL MANAGEMENT AND DISBURSEMENT ARRANGEMENTS...... 41 PROCUREMENT ARRANGEMENTS...... 43 AUDIT ARRANGEMENTS ...... 46 SUMMARY OF FINANCIAL AND ECONOMIC ANALYSIS ...... 47 ENVIRONMENTAL AND SOCIAL ANALYSIS ...... 49 PROJECT PREPARATION AND APPRAISAL ...... 57 APPLICATION OF THE BANK ROAD UNIT COST STUDY RECOMMENDATIONS...... 58
Currency Equivalents As of 01.04.2009
1 UA = 1 SDR 1 UA = 1.4674 USD 1 UA = 119.696 KES 1 UA = 16.2183 ETB
Fiscal Year 8 July – 7 July (Ethiopia) 1 July – 30 June (Kenya)
Weights and Measures
1metric tonne = 2204 pounds (lbs) 1 kilogramme (kg) = 2.200 lbs 1 metre (m) = 3.28 feet (ft) 1 millimetre (mm) = 0.03937 inch (“) 1 kilometre (km) = 0.62 mile 1 hectare (ha) = 2.471 acres
Acronyms and Abbreviations
ADB African Development Bank KeNHA Kenya National Highway Authority ADF African Development Fund KES Kenya Shilling ADT Average Daily Traffic KPA Kenya Ports Authority AFD Agence Francaise de Developpement KRB Kenya Roads Board AIDS Acquired Immune Deficiency Syndrome LC Local Cost ASAL Arid & Semi Arid Lands MoFED Ministry of Finance and Economic Development CBO Community Based Organization MTP Medium Term Plan COMESA Common Market for Eastern & Southern Africa NACC National AIDS Control Council EAC East African Community NEPAD New Partnership for Africa's Development EIRR Economic Internal Rate of Return NGO Non-governmental Organization ERA Ethiopian Roads Authority NPV Net Present Value ESAP Environmental and Social Assessment Procedures OPADC Oromia Pastaralist Area Development Commission Plan for Accelerated and Sustained Development to End ESIA Environmental and Social Impact Assessment PASDEP Poverty ESMP Environmental and Social Management Plan PAP Project Affected Persons ETB Ethiopian Birr PCR Project Completion Report EU European Union PID Project Implementation Document FE Foreign Exchange PS Permanent Secretary FTA Free Trade Area RAP Resettlement Action Plan GOE Government of Ethiopia RFP Request for Proposals GOK Government of Kenya RRA Rural Roads Authority GPN General Procurement Notice RSDP Road Sector Development Program HDM Highway Design and Maintenance Standard Model SPN Specific Procurement Notice ICB International Competitive Bidding STI Sexually Transmitted Infection IDA International Development Association TA Technical Assistance IGAD Intergovernmental Agency for Development TEU Twenty-foot Equivalent Unit JICA Japan International Cooperation Agency VOC Vehicle Operating Costs
i
Loan Information Client’s information
BORROWERS: ETHIOPIA KENYA
EXECUTING AGENCY: ETHIOPIAN ROADS AUTHORITY KENYA NATIONAL HIGHWAY AUTHORITY
Financing plan
Source Amount (UA) Instrument
ADF 210,000,000 Loan EUROPEAN UNION 76,000,000 Grant GOV. OF ETHIOPIA 16,820,000 Counterpart GOV. OF KENYA 26,180,000 Counterpart TOTAL COST 328,760,000
ADB’s key financing information
Loan currency Unit of Account (UA) Interest type* Not Applicable Interest rate spread* Not Applicable Service Charge* 0.75% on amount disbursed and outstanding Commitment fee * 0.50% on the un-disbursed loan amount Tenor 50 years Grace period 10 years NPV (base case) US$ 91.54 million EIRR (base case) 21.7%
Timeframe - Main Milestones (expected)
Concept Note approval March, 2009 Project approval July, 2009 Effectiveness December, 2009 Last Disbursement December, 2015 Completion December, 2014 Last repayment December 2059
ii
PROJECT SUMMARY
Project Overview
The Mombasa-Nairobi-Addis Ababa Road Corridor Project aims at promoting trade and regional integration between Ethiopia and Kenya by improving transport communications between the two countries. The project involves the construction to bitumen standard of 438 km road sections including 245 km Merille River-Marsabit-Turbi road section in Kenya and 193 km Ageremariam-Yabelo-Mega road section in Ethiopia. The total cost of the project is UA 328.76 million. The project is co-financed by the Bank Group (64%), the European Union (23%) and the Governments of Ethiopia and Kenya (13%). The expected outcomes of the project include reduced transport and shipping costs between Kenya and Ethiopia; reduced transit time for import and export goods; and increased volume of Ethiopian transit goods using the port of Mombasa. The development of the corridor will expand market sizes beyond national boundaries and foster a conducive and enabling environment for the private sector and for attracting foreign direct investments. In addition to enhancing trade and strengthening regional integration, the project will contribute to poverty reduction in both countries by increasing access to markets and social services for the surrounding areas, and communities, and by empowering women and other disadvantaged groups through adequate roadside socio-economic infrastructure and services.
Needs Assessment
Ethiopia and Kenya share more than 1000 km of common border, and have a combined population of more than 100 million people. Yet, there is currently not a single all-weather road connecting the two countries. The main road connecting Addis Ababa to Nairobi has more than 700 km of missing links. The poor condition of the road represents a major constraint to trade between the two countries. The development of the Mombasa-Nairobi- Addis Ababa transport corridor is warranted by the anticipated great trade potential between Kenya and Ethiopia and to a lesser extent between the Horn and East Africa countries to include Uganda, Tanzania, Eritrea, and Djibouti. The corridor will also serve as the most cost effective transit route to Mombasa Port for import/export goods to/from southern Ethiopia.
Bank’s Added Value
The rationale for Bank involvement is threefold: (a) The Bank is already involved in the financing of the first phase of the project and the feasibility studies for the second phase. Therefore, the continued support of the Bank is logical; (b) the objective of the project to address the development constraints caused by poor transport infrastructure and regional interconnectivity is in line with the Bank medium term strategy (2008-2012) on promoting infrastructure development and regional integration; and (c) by supporting this flagship regional integration project, the Bank will continue to play a leadership role in the implementation of the key priorities of NEPAD’s infrastructure action plan.
Knowledge Management
The project provides a good opportunity to expand the knowledge on the impact of regional infrastructure on cross-border trade and on appropriate legal and institutional arrangements for transport facilitation particularly regarding the operation of one-stop-border posts. The project component on Monitoring, Evaluation, and Knowledge Building was designed specifically to capture the knowledge during project implementation and disseminate it amongst policy makers, regional economic communities, and development agencies.
iii
MOMBASA-NAIROBI-ADDIS ABABA ROAD CORRIDOR PHASE II PROJECT
RESULTS-BASED FRAMEWORK
PERFORMANCE ASSUMPTIONS/ HIERARCHY OF OBJECTIVES EXPECTED RESULTS REACH INDICATIVE TARGETS INDICATORS RISKS
Sector Goal Impacts Beneficiaries Impacts Indicators Impacts Targets 1 Favorable macro- 1 Promote trade and regional 1 Increased Intra-regional trade between Ethiopia 1 Volume of trade 1 Trade between Ethiopia and Kenya estimated to grow economic integration. and Kenya and Eastern & Horn of Africa regions Populations from US$ 48 M (2007) to US$ 200 M (500%) by 2017 conditions and of Ethiopia, Source: Kenya and Ethiopia Customs 2 Intra-COMESA trade for Ethiopia, Eritrea, Djibouti terms of trade. Kenya, statistics; Trade statistics from currently stagnant, to grow at part or above the 11% COMESA COMESA, IGAD, UNCTAD, WTO COMESA average by 2017; Member States
Project Objective Outcomes Beneficiaries Outcomes Indicators Outcomes Targets 1 Ethiopia & Kenya remain 1 To improve transport 1 Transport and logistics costs between Addis Freight 1 Transport and shipping costs 1 Port of Mombasa transit goods to/from Ethiopia to committed to communications between Kenya and Ababa and Nairobi are reduced; transit and Shippers, 2 Transit time for imports and increase from zero in 2009 to 500,000 t in 2014; and regional Ethiopia for the benefit of both travel times are reduced Exporters and exports to over 1000,000 t or 20% of total Ethiopian sea fret by cooperation countries and the region. Importers 2018. within 2 Port of Mombasa becomes cost-effective 3 Volume of transit goods to/from Transport COMESA. alternative for Ethiopia’s import/export shipping Ethiopia using the port of 2 Average transport cost of US$ 0.50 per veh-km on the Operators 3 Technical and Operational Capacity of Kenya Mombasa corridor in 2009 reduced by 20% by 2011; and by 50% 2 Peace and Business by 2014. stability is Road Agencies is strengthened 4 Performance of Roads Agencies community maintained in 4 Improved economic and social welfare of towns 3 Transit and travel time of 5 days between Addis and 5 Average household income Kenya and along the corridor Nairobi in 2009 reduced by 20% (1 day) by 2011; and by 60% (3 days) by 2014 Ethiopia. Source: Ethiopia Roads Transport 4 Technical, Operational, Financial Management & Authority, Port of Mombasa, NCTTCA Procurement capacity of Roads Agencies adhere to Transit transport surveys; customs broadly accepted good practices by 2011. statistics, Financial & Procurement Capacity Assessment of AfDB or World 5 30% average household income increase by 2017 in Bank, AfDB project M&E the project zone of influence.
Activities/Inputs Outputs Beneficiaries Output Indicators Output Targets 1 Availability of counterpart 1 Construction of Merille River- 1 Road between Merille River and Turbi (245 km) Contractors, 1 Km of road constructed and open 1 80 km of road in Ethiopia and 110 km of road in Kenya funding. Marsabit-Turbi road in Kenya (UA in Kenya constructed to bitumen standard consultants, to traffic. completed and opened to traffic by project mid-term in 2 Security 209.09 M). 2 Road between Ageremariam and Yabelo (193 Business 2 Design Reports, Business Plan 2012 situation does 2 Rehabilitation of Ageremariam- km) in Ethiopia rehabilitated to AC standard. community, Reports, Process Management 2 245-km Merille River-Turbi road in Kenya and 193-km not prevent population in Yabelo-Mega road in Ethiopia (UA 3 Technical Reports, Specifications and Cost Reports validated by GOK and Ageremariam- Yabelo road in Ethiopia completed and execution of the project 91.71 M). Estimates for dualling of Mombasa-Nairobi Road Agencies. opened to traffic by 2014. works area Kenya 3 Consulting services for construction completed. 3 Number of Roadside Socio- 3 All Technical Design Reports, Business Plan Reports, 3 Effective Roads supervision, design, evaluation, and Economic infrastructure built. & Process Management Reports validated by coordination of 4 Roadside socio-economic infrastructure Agencies and audit services (UA 11.42 M) stakeholders by 2011. project constructed their staff 4 Number of ICT & Survey implementation 4 Construction of OSBP and Roadside 5 ICT & Survey Equipment & Software acquired Equipment & Software Acquired 4 Three Road Stations and one OSBP built in Ethiopia; socio-economic infrastructure (UA Two Road Stations and one OSBP built in Kenya by 4 Construction 6 5-Year business plans for Road Agencies 5 Number of staff-weeks of training 9.33 M), 2013. costs completed 6 Number of people sensitized to 5 Technical Assistance for Kenya 5 180 pieces of computer stations, servers, printers and escalation 7 Management & Staff of Roads Agencies trained road safety, STDs, and HIV/AIDS Roads Agencies (UA 2.63 M). related software acquired by 12/10. within in various areas 7 Number of jobs created predictable 6 Compensation & Resettlements (UA 6 172 staff-weeks of training in road management, M&E, 8 Population of project area and road users bounds 4.57 M) financial management, procurement delivered by sensitized to Road Safety, STIs, and HIV/AIDS Source: ERA/ KENHA management 2011. 9 Employments created reports, Progress reports, supervision reports, Completion reports 7 3000 people (50% women) sensitized to road safety, STIs, and HIV/AIDS by 2014. 8 2000 skilled and unskilled jobs (30% women) created by 2014.
iv PROJECT IMPLEMENTATION TIMEFRAME
v
REPORT AND RECOMMENDATION OF THE MANAGEMENT OF THE ADB GROUP TO THE BOARD OF DIRECTORS ON PROPOSED LOANS TO ETHIOPIA AND KENYA FOR THE MOMBASA-NAIROBI-ADDIS ABABA ROAD CORRIOR PHASE II PROJECT
Management submits the following Report and Recommendation on proposed loans for UA 85.00 million to the Federal Democratic Republic of Ethiopia and for UA 125.00 million to the Republic of Kenya to finance the Mombasa-Nairobi-Addis Ababa Road Corridor Phase II Project. I. STRATEGIC THRUST & RATIONALE 1.1. Project Background 1.1.1 The project road is an important section of the Trans-African Highway Cairo-Cape town. Within Ethiopia and Kenya, the road is a link on the main Addis Ababa – Nairobi - Mombasa corridor (see map in Appendix 1). The Kenyan section of the road between Isiolo and Moyale is about 525 km and was constructed as a gravel road in 1974. On the Ethiopian Side of the border, the road is entirely bitumen-paved from Moyale to Addis Ababa. However, the section of the road between Moyale and Ageremariam is more than 40 years old. It has deteriorated and requires reconstruction/rehabilitation. In July 2003, the GOK and the GOE approached the Bank to request the financing of the road under the Bank multinational window. Owing to the low level of project preparation for some of the missing links and the need to mobilize the required financing, the corridor development had to be carried out in phases. For the first phase, the ADF Board of Directors approved a loan of UA 33.60 million and a grant of UA 2.55 million to finance the construction of the 136-km Isiolo- Merille section of the road in Kenya and the feasibility and design studies for 366 km road section in Kenya and another 302 km of road section in Ethiopia in readiness for the second phase. After a slow start due to procurement delays and insecurity in the project area, the implementation of the first phase is now progressing at a satisfactory pace with the contractual completion date set for April 2010. The feasibility and detail design studies of the remaining missing links have been completed and provide the basis for this second phase of the project. 1.2. Project linkages with countries strategies and objectives 1.2.1 The Mombasa-Nairobi-Addis Ababa Road Corridor Project is in line with Ethiopia’s and Kenya’s Poverty Reduction Strategies as well as the Bank Group’s assistance strategies to the two countries. Ethiopia’s second Poverty Reduction Strategy (2005-2010), known as the Plan for Accelerated and Sustained Development to end Poverty (PASDEP) accords high priority to infrastructure development to support industrialization and development and commercialization of agriculture. Within the context of the fifth pillar of PASDEP, Strengthening the Infrastructure backbone of the Country, Ethiopia’s five-year Road Sector Development Strategy III is putting emphasis on expanding the road network and improving regional trade corridors and port linkages. In support of Ethiopia’s PASDEP, Infrastructure Development is one of the three pillars of the Bank Group Country Strategy Paper (CSP) 2006-2009. The Ageremariam-Moyale section of the Mombasa-Nairobi-Addis corridor is programmed for Bank financing under the ADF-XI Indicative Lending Program for Ethiopia in the CSP. It will contribute to PASDEP and CSP objectives of improving trade corridors and linkages to ports.
1.2.2 Kenya’s development strategy, Vision 2030 and the Medium Term Plan (MTP) 2008- 2012 identifies infrastructure development as the main pillar in the GOK’s quest in transforming Kenya into a globally competitive economy and in expanding intra-regional trade with neighboring countries. The MTP underscored also the importance of infrastructure to enhance incomes and social welfare in rural areas. In support of the MTP, one of the two
1
the pillars of the Bank Group Kenya Country Strategy Paper 2008-2012 is Infrastructure Development for Enhanced Growth. The development of the Mombasa-Nairobi-Addis road corridor with a branch to southern Sudan is one the key regional infrastructure programs under the MTP. The project is programmed for Bank financing under ADF-XI Indicative Lending Program in the CSP. The project outcomes will contribute to the objective of the CSP and the MTP by enhancing trade expansion into neighboring countries and strengthening Kenya’s position as a natural transport hub for East Africa. 1.3. Key Development Issues 1.3.1 Ethiopia and Kenya share more than 1000 km of common border, and have a combined population of more than 100 million people. Yet, there is currently not a single all- weather road connecting the two countries. The main road connecting Addis Ababa to Nairobi has more than 700 km of missing links including 366 km of gravel road in Kenya and more than 300 km of low standard and deteriorated paved road in Ethiopia. The poor condition of the road represents a major constraint to trade between the two countries. COMESA trade statistics show for example that the value of trade between Kenya and Uganda in 2007 is 10 times more important than trade between Kenya and Ethiopia, despite the fact that Uganda has only 25 million people compared to the estimated 75 million for Ethiopia. This disparity, and the apparent marginalization of the horn of Africa countries from the recent intra-COMESA trade boom are largely explained by the lack of reliable road transport infrastructure to link them to the rest of the region, which is consistent with the findings of a World Bank study which estimated the elasticity of the flow of trade with respect to transport costs to about –3. It implies for example that the volume of trade between two countries would drop by 20%, if transport costs between them were to increase by 10%.
1.3.2 Ethiopia, as a landlocked country, relies on the neighbouring transit countries for its sea freight. In order to reduce transport cost and improve the competitiveness of the Ethiopian economy, the Government is striving to diversify its access to seaports as much as possible. About 20% of the Ethiopian sea freight traffic originating or destined to southern and south-western Ethiopia would normally be attracted to the Mombasa port, which has this region of Ethiopia as its natural catchment area via Moyale. However, the poor condition of the corridor forces the totality of this traffic to transit through more distant ports.
1.3.3 While addressing the road infrastructure bottleneck is paramount to foster trade between the two countries, it should go hand in hand with reforms programs in the areas of transport facilitation and trade liberalization – the so-called non-physical barriers. Both Ethiopia and Kenya are members of COMESA; but while Kenya has also joined the COMESA Free Trade Area (FTA), Ethiopia has not and continues to trade on preferential terms applying 10% discount to duties granted to “the Most Favored Nation” to all COMESA member states except Djibouti and Sudan with which it has bilateral agreements. Ethiopia and Kenya are at an advance stage of negotiating a bilateral trade agreement. The proposed improvement of the transport connectivity between the two countries underscores the need for Ethiopia and Kenya to move quickly to conclude the agreement. From the Facilitation standpoint, both countries have ratified the key COMESA instruments and common standards to facilitate regional transport and trade including harmonized axle load limits, harmonized transit charges, regional carrier licensing, regional third-party motor vehicle insurance, Regional Customs Bond Guarantee, and Single Customs Document. The two countries are in the process of re-engineering an existing transport transit agreement to take into account the recent development in transport facilitation and the status and condition of the transport and communication infrastructure along the corridor. 1.4. Rationale for Bank’s involvement 1.4.1 The rationale for Bank involvement is threefold: (a) The Bank is already involved in the financing of the first phase of the project and the feasibility studies for the second phase.
2
The first phase is progressing at a satisfactory pace and the feasibility studies for the second phase have demonstrated the economic viability of the operation. Therefore, the continued support of the Bank is logical. (b) The objective of the project to address the development constraints caused by poor transport infrastructure and regional interconnectivity is in line with the Bank medium term strategy (2008-2012) on promoting infrastructure development and regional integration. The Bank has developed extensive experience in Kenya and Ethiopia as well as multinational infrastructure projects across Africa. (c) The project road is a continental priority under the Trans-African Highway Network and a flagship regional integration project under the NEPAD short-term infrastructure action plan; by supporting the project, the Bank will continue to play its leadership role in the implementation of the key priorities of NEPAD. 1.5. Donors coordination 1.5.1 Donor coordination in Kenya is carried out at both sector and national levels. The Kenya Coordination Group meetings, chaired by the Minister of Finance, provide regular opportunities for the government and the resident donor community to discuss matters of mutual concern. Development partners meet among themselves each month in the Development Coordination Group (DCG), chaired by the Embassy of Denmark. The DCG meetings offer an effective forum for aid co-ordination among development partners, to better align assistance with government programs, and to coordinate assistance more effectively among themselves. The Harmonization, Alignment, and Coordination Group, which includes the Ministry of Finance, actively promote the Paris Declaration on aid effectiveness. All 17 of its members, covering some 90% of total official development assistance (ODA) to Kenya, have joined to formulate the Kenya Joint Assistance Strategy (KJAS). The ADB Kenya Field Office is currently the Chair of the Roads and Transport Sector Donor Group and leads sector policy dialogue with the government. The group meets regularly to harmonize donors’ response and positions with respect to institutional, policy and projects’ financing and implementation issues.
1.5.2 In Ethiopia, aid coordination is carried out through the Consultative Group (CG) meetings, which provides opportunities for donors both bilateral and multilateral to periodically review Ethiopia’s development programs and co-ordinate their development assistance. The co-financing under the Road Sector Development Program (RSDP) has facilitated the complementarities of the development partners’ efforts and the extensive internal donor co-ordination involved in monitoring program implementation. The Bank actively participates in the Government-Donor Transport Sector Working Group. The Working Group is chaired by the Minister of Transport and Communications and co-chaired by one donor on a rotation basis, the European Commission holding the current co- chairmanship.
1.5.3 During Project Preparation and Appraisal, the Bank project team held extensive consultations with the main donors actively engaged in the transport sector in Ethiopia and Kenya particularly the EU, the World Bank, AFD, and JICA. The European Union is co- financing the project with the Bank, which is one of the positive outcomes of the Bank’s engagement with the other donors. II. PROJECT DESCRIPTION 2.1. Corridor Development Program and Phasing 2.1.1 The development of the Mombasa-Nairobi-Addis Ababa Road Corridor into a viable trade route required an integrated approach, which took into account the construction or improvement of the road, the capacity expansion of the port of Mombasa, the construction of transit infrastructure facilities, and the policy and operational changes for trade and transport facilitation. The Corridor Development Program and Action Plan are shown in Appendix 5.
3
The Development was planned in three phases owing to the magnitude of the program, the low level of project preparation for some of the missing links and transit facilities, and the need to mobilize the required financing.
2.1.2 Phase I of the Program comprised the following: (i) Construction to bitumen standard of the 136-km road section between Isiolo and Merille River in Kenya co-funded by AfDB and GOK; (ii) the expansion of Mombasa port facilities co-funded by JICA and GOK; and (iii) the feasibility and engineering design studies for two corridor links in both Kenya and Ethiopia totalling 670 km, and an Inland Container Terminal funded by AfDB in readiness for the second and Third Phases of the Program.
2.1.3 The proposed Phase II of the Program involves: (i) the construction to bitumen standard of 438 km road sections including 245 km Merille River-Marsabit-Turbi road section in Kenya and 193 km Ageremarian-Yabelo-Mega road section in Ethiopia; (ii) the construction of road stations and one-stop-border post facilities; and (iii) policy action to sign a bilateral transit transport agreement. Phase II is co-financed by the AfDB, the EU, the GOE, and the GOK.
2.1.4 The planned Phase III will include: (i) Rehabilitation of 300-km Awasa-Ageremarian and Mega-Moyale, and construction of an Inland Container Terminal in Ethiopia; (ii) Construction to bitumen standard of 125-km Turbi-Moyale in Kenya; and (iii) Transport facilitation program to operationalize the bilateral transit transport agreement. Consistent with its commitment to this corridor, the Bank will take the lead in mobilizing other donors to finance the third and final phase of the program. 2.2. Project Development Objectives 2.2.1 The sector goal of the project is to promote trade and regional integration. The expected long-term impact of the project includes increased intra-regional trade between Ethiopia and Kenya and the Eastern and Horn of Africa regions.
2.2.2 The objective of the project is to improve transport communications between Kenya and Ethiopia for the benefit of both countries and the region. The expected outcomes of the project include (a) reduced transport and shipping costs between Kenya and Ethiopia; (b) reduced transit time for import and export goods; (c) increased volume of Ethiopian transit goods using the port of Mombasa. 2.3. Project components 2.3.1 The project will consist of the following components: A. Road Construction Civil Works (UA 300.08 million) Ethiopia - Road Construction Civil Works: This component involves the construction to bitumen standard (Asphalt Concrete) with 7-m carriageway and 1.5-m shoulders of the road section between Ageremariam and Mega (193 km). The civil works will be subdivided in two (2) separate contracts: (Lot 1) Ageremariam-Yabelo (94.5 km); (Lot 2) Yabelo-Mega (97.5 km). Kenya - Road Construction Civil Works - This component involves the construction to bitumen standard (Asphalt Concrete) of the road section Merille River-Marsabit-Turbi (245 km) with 7-m carriageway and 2-m shoulders. It will be subdivided in two contracts: (Lot 1) Merille River-Marsabit (122 km); and (Lot 2) Marsabit-Turbi (123 km) B. Border Posts and Roadside Socio-Economic Infrastructure (UA 9.33 million)
4
Ethiopia - This component involves the construction and equipment of two (2) Road Stations in Ageremariam, Yabelo, the construction of One-Stop-Border-Post facilities in Moyale, and the drilling of twelve community water wells. The Road Stations will incorporate public sanitation, market stands and shops, secured parking area, repair and refuelling stations, etc. They will provide business opportunities for local residents and serve as venues for the provision of multiple public services such as, health care, education and training activities, and cultural activities. Kenya – This component involves the construction and equipment of two (2) Road Stations in Marsabit and Turbi, the construction of One-Stop-Border-Post facilities in Moyale, the construction and equipment of security outposts, and the drilling of community water wells and water harvesting schemes. C. Consulting Services for Supervision, Design and Audit (UA 11.42 million) Ethiopia - Consulting Services for Construction Supervision, and Audit: Engineering consulting firms will provide construction supervision services for the civil works described above. The supervision services will also be divided in two (2) lots corresponding to the civil works contracts; Technical and Financial Audit will be a separate consultancy component. Kenya - Consulting Services: (1) Consulting services for construction supervision of the civil works described above; (2) consulting services for detail design of dual carriageway of some sections; (3) Consulting services for evaluation and knowledge building; and (4) Project Technical and Financial Audit. D. Technical Assistance (UA 2.63 million) Kenya - Technical Assistance for Highway Authorities: The technical assistance include consulting services to develop Five-Year Business plans; development of modern business processes; capacity in procurement and financial management; project coordination costs, and provision of specialized ICT and software for modern highway management systems. E. Compensation and Resettlement (UA 4.57 million) Ethiopia - Compensation and Resettlement of Project Affected People – This component makes provision for the adequate compensation and resettlement of Project Affected People identified in the Project Environmental and Social Impact Assessment. Kenya - Compensation and Resettlement of Project Affected People – This component makes provision for the adequate compensation and resettlement of Project Affected People identified in the Project Environmental and Social Impact Assessment. 2.4. Technical solution retained and other alternatives explored 2.4.1 The design consulting firms evaluated several alternative design, maintenance, and financing strategies for the road. The recommended option is a 7-m Asphalt-paved carriageway with 1.5-m to 2.0-m sealed shoulders. This design was found to be technically, economically, and environmentally the most adequate solution. Stage-construction with an initial lower standard pavement and subsequent reinforcement was assessed and rejected because of the major risk of future construction costs as well as the remoteness of the project area. The scope for private sector participation in the financing of the project was assessed but not pursued because of low risk-adjusted financial returns.
5
2.5. Project type 2.5.1 The ADF financing will support the construction and rehabilitation of identified economic and social infrastructure. The investments against which funds are to be disbursed are well defined and specific. Therefore, the specific project loan has been chosen as the most appropriate instrument for the intervention of the Bank in this operation.
2.6. Project cost and financing arrangements Project Cost 2.6.1 The project cost estimate (net of taxes) is UA 328.76 million (USD 482.40 million) of which the foreign exchange cost is UA 212.83 million (USD 312.29 million) or 65% of the total, and the local cost is UA 115.93 million (USD 170.11 million) or 35% of the total. The cost of the project components located in Ethiopia is UA 101.57 million (USD 149.05 million) or 31% of the total; while the cost for the components in Kenya is UA 227.18 million (USD 333.36 million) or 69% of the total cost. The project cost estimates are based on feasibility and detail design studies of the project as well as international norms and average unit prices for the recruitment of high quality consulting firms and individual consultants for similar services. The cost estimates also took into account the recommendations of the 2008 Bank’s study on the unit costs of road construction, which is detailed in Annex C1. The project cost estimates by component and by country are summarized in Tables 2.1 and 2.2 below. Detailed costs and expenditure schedules are provided in Annex B3.
Table 2.1 - Project Cost Estimate by Component (Net of Taxes) USD (Million) Unit of Account (Million) Component Foreign Local Foreign Local Total Total Exchange Cost Exchange Cost A. Road Construction Civil Works 245.79 132.35 378.14 167.51 90.20 257.70 B. Roadside Amenities 8.90 4.79 13.69 6.06 3.27 9.33 C. Consultancies & Audit 13.40 3.35 16.75 9.13 2.28 11.42 D. TA Institutional Support 3.09 0.77 3.86 2.11 0.53 2.63 E. Resettlement & Compensation 0.00 6.71 6.71 0.00 4.57 4.57 Total Base Cost 271.18 147.98 419.16 184.81 100.84 285.65 Physical Contingency 22.68 12.21 34.89 15.45 8.32 23.78 Price Contingencies 18.43 9.93 28.36 12.56 6.76 19.33 Total 312.29 170.11 482.40 212.83 115.93 328.76
Table 2.2 - Project Cost Estimate by Component and by Country (Net of Taxes) Ethiopia Kenya Component US$ UA US$ UA Million Million Million Million A. Road Construction Civil Works 117.02 79.75 261.12 177.95 B. Roadside Amenities 6.33 4.32 7.36 5.01 C. Consultancies & Audit 6.33 4.32 10.42 7.10 D. TA Institutional Support - - 3.86 2.63 E. Resettlement & Compensation 1.81 1.23 4.90 3.34 Total Base Cost 131.49 89.61 287.66 196.04 Physical Contingency 8.78 5.98 26.11 17.80 Price Contingencies 8.78 5.98 19.58 13.35 Total 149.05 101.57 333.36 227.18
6
Sources of Finance 2.6.2 The proposed project will be co-financed by the Bank Group, the EU, the GOE, and the GOK. The AfDB Group is the lead financing agency and will provide 64% of the total financing requirements equivalent to UA 210 million (USD 308.15 million). The AfDB financing will be in the form of two ADF loans to Ethiopia and Kenya amounting respectively to UA 85.00 million and UA 125.00 million. The EU will co-finance the project in Kenya on parallel basis for UA 76 million representing 23% of the overall project cost. The Governments counterparts’ contributions represent 13% of the cost and are made up of UA 16.57 million from the Government of Ethiopia and UA 26.18 million from the Government of Kenya. The financing plan for the project is shown in Tables 2.3 below.
Table 2.3 - Sources of Financing (in UA million) AfDB Financing EU Financing Counterpart Country Cost Amount Percent Amount Percent Amount Percent
Ethiopia 101.57 85.00 84% - 16.57 16% - Kenya 227.18 125.00 55% 76.00 33% 26.18 12%
Total Project 328.76 210.00 64% 76.00 23% 42.76 13%
2.6.3 The total ADF contribution to the project is UA 210 million. Fifty percent (50%) of the ADF resources for the project will come from the ADF-XI PBA-based national allocations for Kenya and Ethiopia. The remaining 50% will come from the regional operations (RO) envelope. The source of ADF financing is shown in Table 2.4 below.
Table 2.4 – Source of ADF Loans (UA Million) ADF-XI PBA Country ADF-XI Loan Allocation RO Envelope Country Amount Amount Percent Amount Percent
Ethiopia ADF Loan 85.00 40.00 47% 45.00 53%
Kenya ADF Loan 125.00 65.00 52% 60.00 48%
Total Project 210.00 105.00 50% 105.00 50%
2.7. Project’s target area and Beneficiaries 2.7.1 In the general sense, the project road corridor by linking Kenya and Ethiopia, would affect the whole of east and horn of Africa regions. As such, in terms of trade and regional integration, the project area extends beyond Kenya and Ethiopia to include Uganda, Tanzania, Eritrea, and Djibouti. However, the corridor being developed in phases, the project area of influence for the first and second phases lies mostly in the Northeast arid and semi arid region (ASAL) of Kenya and the Oromia Region of Ethiopia.
2.7.2 The ASAL region is an area primarily of pastoralists with relatively few services. Livestock and dairy production dominate the local economy. The region accounts for 67% of the red meat and 12% of the milk consumed in Kenya. Livestock production and productivity, and the development of the livestock industry in general, are constrained by a number of factors including poor veterinary services, and poor access to markets all of which are greatly compounded by the lack of good road infrastructure. In recognition of these facts, the
7
GOK has created the Ministry of Northern Kenya to assist the region to fully integrate into the national economy. Improving road infrastructure in the area will have a positive impact in stimulating growth in the local economy, improving security, and reducing poverty.
2.7.3 The Oromia Region is one of the nine governmental regions of Ethiopia. About 89% of the population is supported by subsistence agriculture. There is a wide variety of farm animals and crops based on the favorable climate, rich soils and normally sufficient rainfall. The main cash crops are coffee and khat. The development prospects brought by the road are critical to the development of the region and to better integrating it into national development. Stakeholders anticipate better market access, increased tourism, and better distribution and lower cost for agricultural inputs, industrial goods and manufactured goods. Stakeholders also expect improved public services including health and education, and more efficient, less expensive distribution of food relief.
2.7.4 The road will strengthen the link of both border regions to their national capitals and economic heartland and to social services. The road also has good tourism development potential, which can generate many unskilled as well as skilled jobs. Other long-term project beneficiaries include freight shippers, exporters and importers, transport operators, the business community and the wider population of Ethiopia and Kenya.
2.8. Participatory process for project design and implementation 2.8.1 The formulation, design, and financing of the project benefited from the wide consultations carried out by the Design Consultants and the Bank project appraisal team, through bilateral meetings, town hall meetings and sharing of interim and final project design reports. The key stakeholders consulted include government agencies, regional economic communities (EAC & COMESA), project beneficiaries, the donor community (AFD, EU, JICA, World Bank), corridor groups, transport operators, shippers’ associations, manufacturers associations, Community-based organizations, and NGOs.
2.8.2 One of the positive outcomes of the engagement with other donors is the forging of a partnership with the EU to co-finance the project to the tune of UA 76 million. As a result of consultations with project beneficiaries and transport operators, the project has incorporated roadside socio-economic infrastructure – the so-called “Michinoeki”1 - that will enhance the benefit of the road to the communities living in its zone of influence. The road stations will provide much stronger links between local communities and the users of the roads by offering business opportunities for local residents and serving as possible venues for the provision of multiple public services such as, health care (including HIV/AIDS care), education and training activities, and cultural activities. The scope for private sector participation in the financing of the operation was assessed during consultations but deemed insignificant because of below average risk-adjusted financial return. However, the Management and operation of the Road Stations will mostly rely on PPP arrangements.
2.8.3 Consultations and participatory process will continue during project implementation to provide regular feedback from the key stakeholders. The Regional Project Coordination Committee discussed under the Project Implementation Section will carry it out. The process will also aim to achieve greater complementarities and synergies between the project and other related projects such as the JICA-funded US$ 223 million port of Mombasa expansion or the ADF-funded Nairobi-Thika Highway and Arusha-Namanga-Athi River road project on the same Cairo-Cape town Transafrican Highway. These synergies will globally improve the region’s logistic chains and result in greater competitiveness of traded goods and exports.
1 Michinoeki (Concept Originated in Japan) are spaces for rest and exchange along highways. They create connections between the highway and local communities.
8
2.9. Bank Group experience, lessons reflected in project design Status and Impact of Prior Bank Intervention in the Sector 2.9.1 The Bank Group has since 1967 participated in the financing of 18 operations in the transport sector in Kenya amounting to UA 368.41 million and covering 16 projects in the road sub-sector, one railway project, and one road study. Fifteen of the operations have been completed. The transport projects financed by the Bank Group include the construction of more than 1000 km of paved roads, and the maintenance and rehabilitation of 2900 km of rural roads. The completed projects have made a significant contribution towards strengthening the infrastructure base of the Kenyan economy by improving mobility and access to socio-economic opportunities for several millions of people, and linking rural and urban areas in the most productive provinces of the country, including Nyanza, Western, Central and Rift Valley. In Ethiopia, the Bank Group has since its first sector intervention in 1967, financed 15 operations in the transport sector for a total amount of UA 311.17 million consisting of 13 projects and two studies of which eleven had been successfully completed and one terminated/cancelled. The intervention in the road sector has been significant and involved construction of 1,890 km of rural roads in four regions, construction of 386 km of link roads, maintenance of 2485 km of district roads and 143 km of rehabilitation of the section on the Addis Ababa – Djibouti export corridor. These interventions have led to opening up of isolated and inaccessible areas to markets. Post evaluation undertaken for the completed projects has indicated that the constructed roads have brought about an all round improvement and growth in production in the agricultural and livestock sectors. Lessons Learned and Reflected in project Design 2.9.2 The project design has taken into account lessons learned from the ongoing phase I of the project as well as previous interventions of the Bank and other donors in the transport sector in both Kenya and Ethiopia. In past interventions of the Bank, implementations have been characterized by long start-up delays, low disbursement levels, lack of local counterpart funds, and poor reporting and auditing. For multinational projects, poor or inappropriate regional coordination with ill-defined responsibilities and lack of resources has been one of the weaknesses that were identified. For the ongoing phase I of the project, insecurity in the project area and the scarcity of water for construction have posed a significant challenge. In addition, due to an unprecedented level of construction activity in Kenya, shortages of locally sourced construction material (lime) have been detrimental to the project.
2.9.3 The proposed project design for the second phase of the operation has reflected these lessons. By starting procurement prior to board approval (Advance Contracting), project start-up delay will be considerably reduced by up to six months. The GOK has engaged in several institutional reforms including the establishment of autonomous highway authorities in order to improve governance and management in the road sector. The project includes a Technical assistance to support the newly established Highway Authorities to address poor reporting and auditing and improve on project management. The increases in fuel levy, and budgetary allocation in Kenya, and donor road sector budget support in Ethiopia have remarkably improved the mobilization resources for road financing in both countries. However, to minimize the risk for inadequate budgeting of local counterpart funds, particularly in Kenya, the ADF loan will cover all the project expenditure except for compensation and resettlement costs. The project design includes a strong regional project coordination steering committee with appropriate budgetary provisions to address poor cross-border coordination observed in past projects. Finally, the project design incorporated alternative design options and various sources of construction inputs supply to mitigate potential shortages of water and locally sourced material such as cement, and lime.
9
2.10. Key performance indicators 2.10.1 The achievement of the project objectives would produce the following outcomes: (i) Reduced transport and shipping costs between Kenya and Ethiopia; (ii) Reduced transit time for import and export goods; (iii) increased volume of Ethiopian transit goods using the port of Mombasa.
2.10.2 Basic indicators for monitoring and evaluating project outcomes are included in the Project Results Framework. The outcome and impact indicators will be reviewed at the start of project implementation and include: (i) Volume of cross-border trade between Kenya and Ethiopia; (ii) transport and shipping costs of a 20-ft container from Mombasa to Addis Ababa; (iii) transit volumes and time from Ethiopia to Mombasa port; (iv) other socio-economic outcome indicators that are indirectly influenced by the project such as income levels, Production and productivity levels of key commodities will also be monitored in Northern Kenya and Southern Ethiopia. The project design consultants have collected some of the baseline data. Additional baseline values will be collected at the beginning of project implementation by the Supervision consultant. The indicators will be measured at project inception, completion, and 3 years later, and results compared with the baseline. Where relevant, indicators will be disaggregated by gender. Funding will be provided under the project for monitoring up to project completion. The consultant for the Evaluation and Knowledge Building component will be responsible for data collection and analysis under the supervision of the Ethiopian Roads Authority and the Kenya National Highway Authority. III. PROJECT FEASIBILITY 3.1. Economic and financial performance 3.1.1 The economic viability of the project has been assessed within the broad framework of Cost Benefit Analysis using the Highway Development Management Tool (HDM) - IV that was found to be appropriate. A discount rate of 12.0%, which is the opportunity cost of capital in Kenya and Ethiopia, has been used for the economic evaluation. The costs taken into account are the capital costs and the routine and periodic maintenance costs. For the economic analysis, these financial costs were converted into economic costs by applying a standard conversion factor (SCF) of 0.78. The economic benefits are calculated as the difference between the “with the project” and “without the project” scenarios. The benefits include road user incremental benefits in terms of Vehicle Operating Cost savings, time savings for passengers and cargo, and road maintenance savings because of the new facility. The Residual value after 20 years of service has been estimated at 25% of the original economic investment cost. 3.1.2 The measures of project worth used are the EIRR, and NPV. Table 3.1 below gives a summary of the economic analysis, whose details are presented in Annex A5.
Table 3.1: Key Economic and Financial Figures EIRR (base case) 21.7% NPV (12% Discount) US$ 91.54 million EIRR (15% decrease in benefits) 16% EIRR (15% increase in costs) 14.5% EIRR (+15% costs & -15% benefits) 12.5%
10
3.2. Environmental and Social impacts Environment 3.2.1 Consistent with Bank’s ESAP, the project is Category 1 since it entails significant earth works and vegetation clearing stretching over a long distance. The road passes through several biodiversity-rich and ecologically sensitive areas. The major environmental impacts will be due to destruction of forests and vegetation, disruption of animal migration routes, and poaching. It is also likely to cause significant displacement of households. Full ESIA and RAP reports and ESMPs have been prepared, and the ESIA/RAP Summary was posted on the Bank website on 20 February 2009.
3.2.2 The potential impacts include soil erosion and run-off, overgrazing, vegetation clearance, dust, noise and vibration, water pollution and wildlife conservation measures. The main social impact will be the relocation of PAPs due to widening and realignments. The project has developed an elaborate program of monitoring of environmental and social impacts with responsibilities and costs identified. All these issues have been addressed in the respective ESMPs and RAPs. The financial provisions to cover the related costs including HIV/AIDS prevention programmes and road safety campaigns and monitoring have been included in the project. Climate change 3.2.3 The project area is arid and semi-arid and exhibits desert characteristics especially on Kenyan side. The area has very low rainfall and is prone to drought. In some high attitude areas however, above average rainfall (800 – 1000mm) may be experienced resulting in flash floods. In such instances, the project design has incorporated storm drains and drainage systems away from homes and property, raised level of road embankment and intensified erosion protection measures such as grassing, sodding and mulching. On the other hand, rising temperatures due to climate change would exacerbate water shortages. To mitigate this, an extensive program of gravity fed water distribution coordinated by OPADC is underway in Ethiopia. Similar initiatives are ongoing through the Ministry of Northern Kenya (the Arid Lands Resource Management Project and the Drought Management Initiative supported by World Bank and European Commission, respectively). The project has incorporated water supply provision along the project road.
3.2.4 Increased traffic may lead to increased gas emissions. The two countries are taking measures to monitor air pollution and curb emissions. NEMA in Kenya has provisions for controlling air pollution and is developing guidelines with UNEP assistance. The EPA has prepared guidelines “Ambient Environment Standards for Ethiopia” with assistance from UNIDO. The project on its part has made provisions for financing an elaborate program of tree planting along the perimeter of the road reserve to act as a carbon sinks. Already ongoing, in the two countries, at district level, are community based indigenous tree planting programs, which will take advantage of the project inputs. At Moyale, (Ethiopia), there is a program of food for work linked to the Food Security Pastoral Development Office. Gender 3.2.5 The major impact on women will emanate from dislocation that may occur. The communities are pastoralists where women bear the burden of the necessities of the relocation process including house (tukul) construction. In addition, the patriarchal traditions, give men control over household income, and therefore may be inclined to control compensation payments. To mitigate the burden of relocation and control of finances is to sensitize community leaders, elders and CBOs to ensure and monitor the compensation process. The potential of an increase in the spread of HIV/AIDS may disproportionately
11
affect girls and women due to an influx of migrant male workers. Measures of mitigation will include targeted awareness and prevention interventions. Women in the project area are engaged in sell of milk and meat (sheep and goat) and roadside vending. The project will provide milk and slaughter facilities and roadside market space for their use. The project will improve the wellbeing of women by providing potable water resulting in time and energy savings. This in turn is expected to have beneficial repercussions on family health and education for girls. Social 3.2.6 The project is expected to enhance the standard of living and socio-economic welfare of the people living within its zone of influence. During construction, over 2000 skilled and unskilled jobs will be created injecting into the two local economies an estimated USD 240,000 per month in form of wages. The workforce will create a demand for services, such as catering and hospitality, supply of provisions, and thereby encourage small scale and micro ventures to be established. Among the project interventions, contributing towards wealth creation and distribution, are construction of roadside amenities, milk houses and processors and slaughterhouses (for goats and sheep). Wellbeing of the people will be improved through improved access to social facilities such as potable water, health facilities, schools and enhanced security.
3.2.7 However, during and after construction traffic accidents will increase due to higher traffic volumes and speeds, and there is a risk of the spread of STI/ HIV/AIDS. Road safety and STI/HIV/AIDS awareness campaigns have been proposed to mitigate these impacts. The project has included financial provisions under the bill of quantities for the civil works and special clauses for the contractors to conduct or sub-contract to NGOs the campaign against the spread of HIV/AIDS. Urban expansion and higher immigration rates along the project road will lead to greater demand on infrastructure services and natural resources; this will require regulation by the regional / district planning authorities in both countries. Involuntary resettlement 3.2.8 Approximately 89 households (445 persons) will be affected (and may require relocation) by the road works on the Marsabit – Turbi road section; while the Moyale – Yabelo section has an estimated 524 households (2620 people) that will be affected with 150 requiring relocation. Land take, destruction of buildings (dwelling and commercial), house fences, loss of trees and crops, and loss of livelihoods will occur because of this road project. Bank Policy on Involuntary Resettlement requires that a full resettlement action plan be prepared if more than 50 households (200 persons) are displaced. In this case, the project has had full resettlement actions plans (RAPs) prepared for the two sides of the road and estimated resettlement and compensation costs are estimated at KES4.71 million and ETB20.0 million, respectively.
IV. IMPLEMENTATION
4.1. Implementation arrangements Executing Agencies 4.1.1 The Kenyan National Highways Authority (KENHA) will be the executing agency for the components of the project located in Kenya, while the Ethiopian Roads Authority (ERA) will be the executing agency for the components of the project located in Ethiopia. The Ethiopian Roads Authority (ERA) and the Ministry of Roads (now being replaced by the Kenya National Highway Authority) have well established financial management and procurement capacities. The two agencies have considerable experience in implementing projects financed by donors including the ADF, IDA and the EU. Therefore, they have proven
12
capacities in meeting the reporting and procurement requirements of the Bank. However, the Kenya National Highway Authority being a newly established agency, its procurement and financial management capacity will be strengthened through technical assistance provided under this project. The two agencies will each appoint a senior engineer as Project Manager and focal points for the project. More details on Implementation Arrangements are provided in Annex B3.
4.1.2 Most of the project components will be implemented in parallel and independently. However, close cooperation is necessary for the project to achieve its long-term development impacts. The overall cross-border coordination of the project will be provided by a joint Regional Project Coordination Committee (RPCC). The Permanent Secretary of Ministry of Roads in Kenya and the State Minister of Ministry of Works and Urban Development in Ethiopia will co-chaired the RPCC. Its membership will include General Managers of Ethiopian Roads Authority and Kenya National Highway Authority, a representative of IGAD, a representative of COMESA, key stakeholder ministries in charge of transport, immigration, customs, tourism, and livestock. The joint committee will raise coordination/harmonization issues that may hamper or negatively affect the development of the road corridor and advise on the necessary corrective measures. The establishment of the RPCC, its composition and terms of reference shall be agreed upon between Ethiopia and Kenya in an MOU. The signing of the MOU will be a Covenant of the loan. 4.1.3 Some progress has been made in aid harmonization and the implementation of the Paris Declaration on Aid Effectiveness, particularly in information sharing and coordination of missions in both countries. However, concerns over governance and inadequacy of country systems, some of which do not adhere to broadly accepted good practices, have prevented Development Partners from moving faster on this agenda. The present project alignment and harmonization include the use of the countries financial management systems, and the use of existing government entities for project implementation therefore avoiding the creation of parallel project implementation units. Procurement 4.1.4 All procurement of civil works and acquisition of consulting services financed by the Bank will be in accordance with the Bank's Rules & Procedures for Procurement of Goods and Works, or as appropriate Rules & Procedures for the Use of Consultants, using the relevant Bank Standard Bidding Documents. The procurement of components funded by the EU will follow EU procedures. For the components financed by the Bank, the different procurement and consultants’ selection methods, the requirements for prequalification, post-qualification, and prior review, the estimated costs of procurement packages, and the procurement plans were agreed upon with ERA and KENHA. The procurement arrangement details are provided in Annex B5. Disbursement and Audit Arrangements 4.1.5 The loans will be disbursed for categories of expenditure including civil works, goods, consulting services, and miscellaneous project coordination costs. The Direct Payment Disbursement Method will be used for all the project components, except for the technical assistance, which will be disbursed through special account. All disbursements will follow the procedures and standard supporting documents outlined in the Bank’s Disbursement Hand Book. Independent auditors will audit the project accounts annually. The audit reports of the ongoing phase I of the project have been submitted by both Ethiopia and Kenya. The reports were reviewed and found to adhere to accepted good practices. Further disbursement details are provided in Annex B4.
13
4.2. Monitoring 4.2.1 The Ethiopian Roads Authority (ERA) and Kenya National Highway Authority (KENHA) shall regularly provide the Bank with quarterly progress reports for the project including the implementation of the environmental and social action plan, in the established format covering all project activities. These reports will include physical, financial, social, and environmental indicators, which will assist in verifying the delivery of the project outputs. A semi-annual project coordination meeting with the participation of the two executing agencies and the regional economic communities IGAD, COMESA, and EAC will be held every six month to ensure that proper execution and cooperation is maintained. In addition, monitoring of the project will be done through the Bank’s semi-annual supervision missions, in accordance with the Bank Group’s Operations manual. The Bank will undertake the project mid-term review in 2012 to identify any major constraints facing the project and provide the required corrective measures. The following table summarizes the project monitoring timeframe and monitoring process. Table 4.1 – Implementation Monitoring Timeframe
Monitoring process / Timeframe Milestone feedback loop
Q4 - 2009 Project Launching Supervision and Progress Report
Q2 - 2010 Procurement of Civil Works Completed Procurement Plan/Progress Report
Q3 - 2010 All Contractors Mobilization Completed Supervision and Progress Report
Q2 - 2011 30% of Civil Works completed Supervision and Progress Report
Q1 - 2012 60% of Civil Works completed Midterm Review & Progress Report
Q1 – 2013 Substantial completion of civil works Supervision and Progress Report
Q1 – 2014 End of Defects Liability period Supervision and Progress Report
Q1 – 2014 Project Completion Project Completion Report
4.3. Governance 4.3.1 Transparency and accountability in public financial management has improved considerably in Kenya. Donors’ support including the IDA-funded Public Sector Management Technical Assistance Project and the ADF-funded Institutional Support for Good Governance have improved financial accountability framework and strengthened regulatory institutions. The Public Procurement Act of 2005 has created bodies for the regulation of Public Procurement and has resulted in greater transparency in procurement matters. In the road sector, governance will be enhanced with the operationalization of the Kenya Roads Act of 2007, which provided a clear mandate and legal identity for each organization involved in the road sector. The Act has now limited the role of the Ministry of Roads to policy formulation and regulatory functions, while Autonomous Road Agencies will handle executive functions of planning, programming, development, and maintenance of roads on commercial basis with a management contract signed with the Minister.
4.3.2 In Ethiopia, the ongoing programs such as the Good Governance Package of the District Level Decentralization Program (DLDP); the Public Sector Capacity Building program (PSCAP); and the Expenditure Management Control Program (EMCP) are intended to address the challenges related local governance and lack of capacity. The 2007 Public Expenditure Financial Accountability Report concludes that although weak institutional
14
capacity requires attention, the fiduciary systems in place are adequate. The report highlights improvements in the quality of accounting records, fiscal reporting and external auditing. The existing governance structure in the road sector is generally well perceived by development partners active in the sector. The Ethiopian Roads Authority (ERA) is an autonomous Federal Government Agency with its own Board. A Road Inspectorate Unit, which is accountable to the ERA Board, provides independent inspection and monitoring reports on the performance of the road sector operations.
4.3.3 The specific governance risk mitigation measures of the present project include: (i) the appointment of independent Financial and Technical Audit firms to ensure that funds are used efficiently and for the intended purposes; (ii) Bank prior review and approval of all project procurement activities; and (iii) the use of direct disbursement methods to channel project funds to contractors and service providers.
4.4. Sustainability 4.4.1 The sustainability of the project will depend largely on the ability of the two governments to plan, program, finance, and implement timely maintenance of the road. Sustainability will also depend on the implementation of effective axle-load-control programs to prevent overloaded trucks from prematurely destroying the road.
4.4.2 The planning, programming, and implementation of road maintenance in Ethiopia is done under a holistic sector wide approach – the Maintenance Action Plan (MAP-4) under the Road Sector Development Program (RSDP). The Ethiopian Roads Authority implements the program. In Kenya, the newly established Kenya National Highway Authority (KeNHA) is now providing the needed streamlined management and improved governance structure to tackle road maintenance problems in the country. As mandated by the Kenya Roads Act 2007, KeNHA is currently finalizing five-year Road Sector Investment Program to guide the development and maintenance of the road sector. The recurrent costs after project completion include the routine maintenance expenditure of the road undertaken annually at a cost of US$ 500,000 in both Kenya and Ethiopia; and the periodic maintenance every ten years in the form of resealing or asphalt overlay to protect the investment estimated a US$ 13 million in Ethiopia and US$ 15 million in Kenya.
4.4.3 Both countries have established ring-fenced road maintenance funds to secure stable flow of funds for road maintenance. The resources mobilized by the Ethiopian Road Fund Administration rose from ETB 165 million in 1998 to more than ETB 700 million in 2008. The resources of the Road Fund can cover the annual maintenance needs of the network in maintainable condition estimated at ETB 650 million. The Kenya Road Maintenance Fuel Levy Fund (RMLF) is the biggest road fund in sub-Saharan Africa. The fund is managed by the Kenya Roads Board and raised KES 19 billion (US$ 270 million) in 2008 from fuel levy and other road user charges. The amount is adequate to cover all periodic and routine maintenance needs of the network but not including the backlog maintenance.
4.4.4 The above-mentioned institutional arrangements for the management, financing, and maintenance of roads have lead to the application of sound road assets management and resulted in improved sustainability of road investments in both Ethiopia and Kenya. Another policy direction that will ensure sustainability is the increased role of the private sector in routine and periodic maintenance limiting the role of the force account units to emergency response only. As of date, private contractors in Kenya carry out about 95% of periodic and routine maintenance. In Ethiopia, the restructuring of ERA has transformed it from a supplier of road infrastructure to a manager and purchaser of services and works for network maintenance and development. Following its policy of commercialisation of its force account unit, ERA is increasingly contracting out road maintenance to match the pace of
15
development of the domestic contracting capacity. The share of private sector in periodic maintenance works in Ethiopia is expected to increase from the current 50% to 100% over the next five years. This policy direction will lead to improved efficiency in road maintenance and the emergence of strong domestic construction industry and further enhance sustainability.
4.4.5 Both Ethiopia and Kenya are implementing policy measures with respect to axle- load-control on their respective road networks with technical assistance funded by Development Partners. These measures include the introduction of improved axle configurations, the construction of additional weighbridge stations, and more efficient rules enforcement. These protective measures and the improve sector governance and maintenance funding mechanisms will contribute to the sustainability of the project.
4.5. Risk management 4.5.1 The successful implementation of the project and achievement of its development objectives predicates on several assumptions, each of which may constitute a potential risk: Risk of political and civil unrest – both Ethiopia and Kenya have recently experienced post- election violence and civil unrest. Both countries have weathered those storms. The mitigation of such risks is beyond this project; however, the repeat of similar events in the near future is unlikely. Insecurity in the project area is a major concern and may prevent the orderly execution of the works – Lessons learned from ongoing construction activities have been incorporated in the design of the project to address insecurity and mitigate this risk including the provision of special security personnel by the government and the construction of several security outposts. Unpredicted escalation of construction costs – The risk of uncontrolled construction costs are mitigated by having detail design documents and having substantial provisions for contingencies. In addition, the global economic slowdown will have a dampening effect on oil prices and positive outcome on competition. Fiscal impacts of the Global Economic Crisis will affect the capacity of the concerned governments to meet counterpart contributions – Despite improved fiscal discipline in both Kenya and Ethiopia, the likelihood of this risk is high. The risk will be mitigated in Ethiopia by the donor-funded road sector budget support, which provides the government with more budgeting flexibility. In Kenya, the risk will be mitigated by the ADF loan financing all project activities therefore reducing its immediate fiscal impact on government treasury. Implementation risk due to newly established executing agency in Kenya – An Interim Management Committee provided under the Kenya Road Act has been set up to oversee the change management process and the smooth transfer of functions, rights, powers, and project portfolios. The committee has prepared a roadmap to facilitate the process of operationalizing the newly established Roads Authority. Therefore, disruption to project implementation will be minimized; in addition, the present project has incorporated a technical assistance to strengthen the institutional capacity of the Road Authorities. Commitment of the two countries to COMESA regional economic cooperation and integration initiatives that would boost intra regional trade – Kenya and at a slower pace Ethiopia have been pursuing COMESA open trade agenda. Therefore, a reversal of these decades’ old commitments and policies is unlikely. This risk is further mitigated by the fact that the project will incorporate a trade and transport facilitation component to address non- tariff barriers by harmonizing transport and customs standards and improving document flows.
16
4.6. Knowledge building 4.6.1 The type of knowledge expected to emerge from this operation stem directly from its anticipated outcomes. Several empirical studies point out the critical role of transport in reducing transactions costs, fostering cross-border trade, and improving the general welfare of affected populations. The project provides a good opportunity to test this hypothesis and expand the knowledge in this area. In addition, there is limited knowledge on appropriate legal and institutional arrangements for transport facilitation particularly regarding the operation of one-stop-border posts. By tackling this aspect, the project will produce valuable information. The project component on Monitoring, Evaluation, and Knowledge Building was designed specifically to capture the knowledge during project implementation and disseminate it amongst regional economic communities, policy makers, and development agencies involved in infrastructure development in Africa.
V. LEGAL INSTRUMENTS AND AUTHORITY
5.1. Legal instrument 5.1.1 The Bank instruments to finance this operation are two ADF concessionary loans to Ethiopia and Kenya. The loan to Ethiopia amounts to UA 85 million broken down in UA 45 million (53%) from the Regional Operations Envelope and UA 40 million (47%) from Ethiopia’s ADF-XI PBA-based allocation. The loan to Kenya amounts to UA 125 million broken down in UA 60 million (48%) from the Regional Operations Envelope and UA 65 million (52%) from Kenya’s ADF-XI PBA-based allocation. The standard ADF loan terms and conditions are applicable to the two loans.
5.2. Conditions associated with Bank’s intervention Conditions Precedent to the Entry into Force of the Loan Agreement 5.2.1 The entry into force of the Loan Agreements shall be subject to the fulfillment by the Borrowers of the provisions of Section 12.01 of the General Conditions Applicable to Loan Agreements and Guarantee Agreements of the Fund.
Conditions Precedent to First Disbursement of the Loans 5.2.2 The obligation of the Fund to make the first disbursement of the Loans shall be conditional upon the entry into force of the Loan Agreement and the fulfillment of the following conditions:
By both the Government of Ethiopia and the Government of Kenya (i) Submitted a resettlement action plan (RAP) together with a works and compensation schedule detailing the sections into which each lot of the civil works will be divided, and a timeframe for the compensation of project affected persons with respect to all such sections in form and substance satisfactory to the Fund; and
(ii) Submitted evidence of having compensated and/or resettled all project affected persons with respect to the first section of the first lot of the civil works in accordance with the RAP and the works and compensation schedule;
By the Government of Ethiopia (iii) Having appointed a senior engineer with qualifications and experience acceptable to the fund to serve as Project Manager;
17
By the Government of Kenya (iv) Having opened a foreign currency project account in a bank acceptable to the fund into which the proceeds of the loan to cover eligible expenditures for the technical assistance component will be deposited as required.
Other Conditions of the Loan (i) The Borrowers shall have jointly provided evidence to the Fund that a Road Transport Services Agreement between Ethiopia and Kenya, for a transit regime and transport facilitation for the effective utilization of the corridor, has been signed by December 31, 2011;
(ii) The Borrowers shall have jointly provided evidence to the Fund that an MOU between Ethiopia and Kenya establishing a cooperation framework for coordinating the development, financing, operation, management of the corridor has been signed by June 30, 2010;
(iii) The PS Ministry of Roads – Kenya shall submit to the fund yearly by 31 March, detailed budgets for the institutional training program of the roads Authorities, and the project coordination and oversight costs funded by the project for review and no- objection.
5.3. Compliance with Bank Policies ( ) This project complies with all applicable Bank policies. ( ) The project does not require any exception from Bank policies.
VI. CONCLUSIONS AND RECOMMENDATIONS
6.1 Conclusion 6.1.1 The project is expected to contribute to enhance trade and regional integration between Ethiopia and Kenya, by reducing general transport costs, increasing market sizes beyond national boundaries, increasing economic output, and giving rise to other socio- economic benefits. The Economic Internal Rate of Return has been estimated at 21.7%, which is higher than the opportunity cost of capital in Kenya and Ethiopia.
6.1.2 In addition to enhancing trade and strengthening regional integration, the project will contribute to poverty reduction in both countries by increasing access to markets and social services for the surrounding areas, and communities, and by empowering women and other disadvantaged groups through adequate roadside socioeconomic infrastructure and services. For Kenya, the project will improve access to Northern Kenya and enhance integration with the rest of the country. For Ethiopia, the road will also provide a cost effective alternative outlet to the sea. The project road will also enhance the development effectiveness of several other donor-funded projects in agricultural, health, and education in the two countries.
6.1.3 The project road is one of the missing links on the Trans-African Highway Cairo- Capetown and is one of the key priorities of the New Partnership for Africa’s Development (NEPAD) and part of its short-term action plan for infrastructure. It is also consistent with the Bank’s Medium Term Strategy (2008-2012) and the Bank Group’s Policy on Regional Economic Cooperation and Integration.
18
6.2 Recommendations 6.2.1 Management recommends that the Board of Directors approve the proposed loans of UA 85.00 million, and UA 125 million respectively to the Federal Democratic Republic of Ethiopia and the Republic of Kenya for the purposes of financing the project described in this report and subject to the above-stipulated conditions.
19 Appendix 1
MOMBASA – NAIROBI – ADDIS ABABA ROAD CORRIDOR – PHASE II PROJECT Ethiopia – Comparative Socio-Economic Indicators Develo- Develo- Year Ethiopia Africa ping ped Countries Countries Basic Indicators GNI per capita US $ Area ( '000 Km²) 1 104 30 307 80 976 54 658 Total Population (millions) 2007 83.1 963.7 5 448.2 1 223.0 1200 Urban Population (% of Total) 2007 16.7 39.8 43.5 74.2 1000 800 Population Density (per Km²) 2007 75.3 31.8 65.7 23.0 600 GNI per Capita (US $) 2006 180 1 071 2 000 36 487 400 Labor Force Participation - Total (%) 2005 42.0 42.3 45.6 54.6 200 0 Labor Force Participation - Female (%) 2005 41.9 41.1 39.7 44.9 2001 2002 2003 2004 2005 2006 Gender -Related Development Index Value 2005 0.393 0.486 0.694 0.911
Human Develop. Index (Rank among 174 countries) 2005 169 n.a. n.a. n.a. Ethiopia Africa Popul. Living Below $ 1 a Day (% of Population) 2004 12.5 34.3 … …
Demographic Indicators Population Growth Rate - Total (%) 2007 2.5 2.3 1.4 0.3 Population Growth Rate - Urban (%) 2007 4.2 3.5 2.6 0.5 Population < 15 years (%) 2007 43.8 41.0 30.2 16.7 Population Growth Rate (%) Population >= 65 years (%) 2007 3.1 3.5 5.6 16.4 2.7 Dependency Ratio (%) 2007 87.7 80.1 56.0 47.7 2.6 Sex Ratio (per 100 female) 2007 99.0 99.3 103.2 94.3 Female Population 15-49 years (% of total population) 2007 23.4 24.2 24.5 31.4 2.5 Life Expectancy at Birth - Total (years) 2007 52.9 54.2 65.4 76.5 2.4 Life Expectancy at Birth - Female (years) 2007 54.3 55.3 67.2 80.2 2.3
Crude Birth Rate (per 1,000) 2007 38.2 36.1 22.4 11.1 2.2 Crude Death Rate (per 1,000) 2007 13.0 13.2 8.3 10.4 2.1 Infant Mortality Rate (per 1,000) 2007 86.9 85.3 57.3 7.4 2002 2003 2004 2005 2006 2007 Child Mortality Rate (per 1,000) 2007 145.3 130.2 80.8 8.9
Total Fertility Rate (per woman) 2007 5.3 4.7 2.8 1.6 Ethiopia Africa Maternal Mortality Rate (per 100,000) 2005 673.0 723.6 450 8 Women Using Contraception (%) 2005 14.7 29.9 61.0 75.0
Health & Nutrition Indicators Physicians (per 100,000 people) 2004 1.5 39.6 78.0 287.0 Nurses (per 100,000 people) 2004 13.7 120.4 98.0 782.0 Life Expectancy at Birth (years) Births attended by Trained Health Personnel (%) 2005 6.0 50.4 59.0 99.0 Access to Safe Water (% of Population) 2006 42.0 62.3 80.0 100.0 71 Access to Health Services (% of Population) 2004 55.0 61.7 80.0 100.0 61 51 Access to Sanitation (% of Population) 2004 13.0 45.8 50.0 100.0 41 31 Percent. of Adults (aged 15-49) Living with HIV/AIDS 2005 2.2 4.7 1.3 0.3 21 Incidence of Tuberculosis (per 100,000) 2005 343.9 300.7 275.0 18.0 11 1 Child Immunization Against Tuberculosis (%) 2006 72.0 83.7 85.0 93.0 2002 2003 2004 2005 2006 2007 Child Immunization Against Measles (%) 2006 63.0 75.4 78.0 93.2 Underweight Children (% of children under 5 years) 2005 38.0 28.6 27.0 0.1 Daily Calorie Supply per Capita 2004 1 840 2 436 2 675 3 285 Ethiopia Africa Public Expenditure on Health (as % of GDP) 2005 3.0 2.4 1.8 6.3
Education Indicators Gross Enrolment Ratio (%) Primary School - Total 2006 97.8 96.4 91.0 102.3 Primary School - Female 2006 91.7 92.1 105.0 102.0 Infant Mortality Rate Secondary School - Total 2006 34.0 44.5 88.0 99.5 ( Per 1000 ) Secondary School - Female 2006 28.0 41.8 45.8 100.8 98 Primary School Female Teaching Staff (% of Total) 2006 45.4 47.5 51.0 82.0 96 94 Adult Illiteracy Rate - Total (%) 2007 52.5 33.3 26.6 1.2 92 Adult Illiteracy Rate - Male (%) 2007 45.7 25.6 19.0 0.8 90 Adult Illiteracy Rate - Female (%) 2007 59.3 40.8 34.2 1.6 88 Percentage of GDP Spent on Education 2006 6.0 4.5 3.9 5.9 86 84 82 Environmental Indicators 80 2002 2003 2004 2005 2006 2007 Land Use (Arable Land as % of Total Land Area) 2005-07 10.0 6.0 9.9 11.6 Annual Rate of Deforestation (%) 2000-07 0.8 0.7 0.4 -0.2 Annual Rate of Reforestation (%) 2000-07 10.0 10.9 … … Ethiopia Africa Per Capita CO2 Emissions (metric tons) 2005-07 0.1 1.0 1.9 12.3
Sources : ADB Statistics Department Databases; World Bank: World Development Indicators; last update : July 2008 UNAIDS; UNSD; WHO, UNICEF, WRI, UNDP; Country Reports Note : n.a. : Not Applicable ; … : Data Not Available;
20 Appendix 1
MOMBASA – NAIROBI – ADDIS ABABA ROAD CORRIDOR – PHASE II PROJECT Kenya – Comparative Socio-Economic Indicators Develo- Develo- Year Kenya Africa ping ped Countries Countries Basic Indicators GNI per capita US $ Area ( '000 Km²) 580 30 307 80 976 54 658 Total Population (millions) 2007 37.5 963.7 5 448.2 1 223.0 1200 Urban Population (% of Total) 2007 21.4 39.8 43.5 74.2 1000 800 Population Density (per Km²) 2007 63.3 31.8 65.7 23.0 600 GNI per Capita (US $) 2006 580 1 071 2 000 36 487 400 Labor Force Participation - Total (%) 2005 50.7 42.3 45.6 54.6 200 0 Labor Force Participation - Female (%) 2005 47.1 41.1 39.7 44.9 200 200 200 200 200 200
Gender -Related Development Index Value 2005 0.521 0.486 0.694 0.911 1 2 3 4 5 6
Human Develop. Index (Rank among 174 countries) 2005 148 n.a. n.a. n.a. Kenya Africa Popul. Living Below $ 1 a Day (% of Population) 2005 45.9 34.3 … …
Demographic Indicators Population Growth Rate - Total (%) 2007 2.7 2.3 1.4 0.3 Population Growth Rate - Urban (%) 2007 5.1 3.5 2.6 0.5 Population < 15 years (%) 2007 42.7 41.0 30.2 16.7 Population Growth Rate (%) Population >= 65 years (%) 2007 2.6 3.5 5.6 16.4 2.7 Dependency Ratio (%) 2007 83.2 80.1 56.0 47.7 2.6 Sex Ratio (per 100 female) 2007 99.4 99.3 103.2 94.3 2.5 Female Population 15-49 years (% of total population) 2007 24.4 24.2 24.5 31.4 2.4 Life Expectancy at Birth - Total (years) 2007 54.1 54.2 65.4 76.5 2.3 Life Expectancy at Birth - Female (years) 2007 55.2 55.3 67.2 80.2 2.2 Crude Birth Rate (per 1,000) 2007 39.2 36.1 22.4 11.1 2.1 Crude Death Rate (per 1,000) 2007 11.8 13.2 8.3 10.4 2.0 Infant Mortality Rate (per 1,000) 2007 64.4 85.3 57.3 7.4 20 20 20 20 20 20 Child Mortality Rate (per 1,000) 2007 104.1 130.2 80.8 8.9 02 03 04 05 06 07
Total Fertility Rate (per woman) 2007 5.0 4.7 2.8 1.6 Kenya Africa Maternal Mortality Rate (per 100,000) 2005 560 724 450 8 Women Using Contraception (%) 2003-06 39.3 29.9 61.0 75.0
Health & Nutrition Indicators Physicians (per 100,000 people) 2007 27.6 39.6 78.0 287.0 Nurses (per 100,000 people) 2007 121.9 120.4 98.0 782.0 Life Expectancy at Birth (years) Births attended by Trained Health Personnel (%) 2003-05 41.6 50.4 59.0 99.0 Access to Safe Water (% of Population) 2006 57.0 62.3 80.0 100.0 71 Access to Health Services (% of Population) 2004 77.0 61.7 80.0 100.0 61 51 Access to Sanitation (% of Population) 2004 43.0 45.8 50.0 100.0 41 31 Percent. of Adults (aged 15-49) Living with HIV/AIDS 2005 6.1 4.7 1.3 0.3 21 Incidence of Tuberculosis (per 100,000) 2005 641.0 300.7 275.0 18.0 11 1 Child Immunization Against Tuberculosis (%) 2006 92.0 83.7 85.0 93.0 2002 2003 2004 2005 2006 2007 Child Immunization Against Measles (%) 2006 77.0 75.4 78.0 93.2 Underweight Children (% of children under 5 years) 2003-05 19.9 28.6 27.0 0.1 Daily Calorie Supply per Capita 2004 2 149 2 436 2 675 3 285 Kenya Africa Public Expenditure on Health (as % of GDP) 2006 2.5 2.4 1.8 6.3
Education Indicators Gross Enrolment Ratio (%) Primary School - Total 2006 107.4 96.4 91.0 102.3 Primary School - Female 2006 113.4 92.1 105.0 102.0 Infant Mortality Rate Secondary School - Total 2006 32.4 44.5 88.0 99.5 ( Per 1000 ) Secondary School - Female 2005 47.0 41.8 45.8 100.8 100 Primary School Female Teaching Staff (% of Total) 2005 44.8 47.5 51.0 82.0 90 80 Adult Illiteracy Rate - Total (%) 2007 11.8 33.3 26.6 1.2 70 Adult Illiteracy Rate - Male (%) 2007 7.6 25.6 19.0 0.8 60 50 Adult Illiteracy Rate - Female (%) 2007 16.1 40.8 34.2 1.6 40 Percentage of GDP Spent on Education 2006 8.1 4.5 3.9 5.9 30 20 10 Environmental Indicators 0 2 2 2 2 2 2 Land Use (Arable Land as % of Total Land Area) 2005-07 7.0 6.0 9.9 11.6 002 003 004 005 006 007 Annual Rate of Deforestation (%) 2000-07 0.5 0.7 0.4 -0.2 Annual Rate of Reforestation (%) 2000-07 1.0 10.9 … … Kenya Africa Per Capita CO2 Emissions (metric tons) 2005-07 0.3 1.0 1.9 12.3
Sources : ADB Statistics Department Databases; World Bank: World Development Indicators; last update : July 2008 UNAIDS; UNSD; WHO, UNICEF, WRI, UNDP; Country Reports Note : n.a. : Not Applicable ; … : Data Not Available;
21 Appendix 2
MOMBASA – NAIROBI – ADDIS ABABA ROAD CORRIDOR – PHASE II PROJECT Kenya - Bank Group ongoing Projects as of May 2009
PROJECT NAME Main Sector Financing Source Approval Effect. Date Closing Approved Disbursement Date Amount UA Ratio A - Public National Projects 1. Roads 2000 - Districts Rural Transport/ ADF Loan 12.07.2001 29.04.2002 30.12.2008 20,000,000 42.30% Roads Rehabilitation Project Roads 2. Nairobi - Thika Highway " ADF Loan 21.11 2007 29.07.2008 Dec. 2010 117,850,000 0.00% Improvement Project " ADF Grant 21.11 2007 29.07.2008 Dec. 2010 3,150,000 0.00% 3. Rift Valley Water Supply and Water & ADF Loan 07.07.2004 21.12.2004 31.12.2009 13,040,000 43.01% Sanitation Project Sanitation " ADF Grant 07.07.2004 6.09.2004 31.12.2009 5,020,000 40.39% 4. Water Services Boards Support " ADF Loan Nov-07 26.11.2008 Dec. 2011 35,190,000 0.00% Project " ADF Grant Nov-07 - Dec. 2011 10,070,000 0.00% 5. Green Zones Development Agriculture ADF Loan 12.10.2005 27.02.2006 31.12.2013 25,040,000 35.77% Support Project 6. Ewaso Ng'ïro North Natural " ADF Loan 22.04.2005 27.09.2005 31.12.2012 13,590,000 20.33% Resources Conservation Project " ADF Grant 22.04.2005 16.06.2005 31.12.2012 2,890,000 34.65% 7. ASAL-Based Livestock and " ADF Loan 17.12.2003 22.09.2004 31.12.2011 18,410,000 51.92% Rural Livelihoods Support Project " ADF Grant 17.12.2003 09.08.2005 31.12.2011 3,170,000 59.03% 8. Kimira- Oluch Smallholder " ADF Loan 31.05.2006 21.09.2006 30.09.2013 22,978,992 2.46% Farm Improvement Project " ADF Grant 31.05.2006 20.10.2007 30.09.2013 1,153,332 2.08% 9. Small-Scale Horticulture " ADF Loan 05.09. 2007 20.5.2008 Jan. 2014 17,000,000 1.20% Development Project 10. Education III Project Social ADF Loan 17.12.2003 24.11.2004 31.12.2010 24,260,000 1.03%
" ADF Grant 17.12.2003 24.11.2004 31.12.2010 6,750,000 0.73%
11. Rural Health III Project " ADF Loan 07.07.2004 15.03.2005 31.12.2010 17,180,000 11.09%
" ADF Grant 07.07.2004 15.03.2005 31.12.2010 6,000,000 52.86% 12. Kenya Institutional Support to Institutional ADF Grant 26.07.2006 08.12.2007 30.09.2009 5,520,000 14.20% Good Governance reforms 13. Community Empowerment & " ADF Loan 17.12.2007 - Mar. 2013 17,000,000 0.00% Institutional Support Project 14. Kisumu District Primary Schools Water and Sanitation " AWF 19.12.2006 29.01.2007 Sep-08 198,317 100.00% Project 15. Technical Industrial Vocational and Entrepreneurship Social ADF Loan 16.12.2008 - 31.12.2013 25,000,000 0.00% Training (TIVET) 16. Integrated Land and Water Water & AWF 1,936,000 0.00% Management Sanitation Sub-total 412,396,641 11.49%
B. Public – Multinational Projects 17. Mombasa - Nairobi - Addis Transport/ ADF Loan 13.12.2004 07.04.2005 31.12.2010 33,600,000 20.90% Ababa Road Corridor Project Roads " ADF Grant 13.12.2004 07.04.2005 31.12.2010 1,200,000 29.01% 18. Arusha - Namanga - Athi " ADF Loan 13.12.2006 30.04.2007 31.12.2012 49,241,000 8.01% River Road Development Project 19. Creation of Sustainable Tsetse Agriculture ADF Loan 08.12.2004 07.04.2005 31.12.2011 6,550,000 48.49% Eradication Program 20. Nile Equitorial Lakes Electric Energy ADF Loan 27.11.2008 - 31.1.2014 17,730,000 0.00% Grid - NELSAP Sub-total 108,321,000.00 13.38%
Sub total (A + B) 520,717,641 11.89%
C. Other Projects 21. African Virtual University Social ADF Grant 13.12.2004 07.03.2005 30.09.2009 5,000,000 57.57% Support Project Total 525,717,641 12.32%
22 Appendix 2
MOMBASA – NAIROBI – ADDIS ABABA ROAD CORRIDOR – PHASE II PROJECT Ethiopia - Bank Group ongoing Projects as of May 2009
PROJECT NAME Main Sector Financing Approval Effect. Closing Approved Disbursement Source Date Date Amount UA Ratio Koga Irrigation And Watershed Agriculture ADF Loan 19.07.01 30.06.10 25.02.02 32,590,100.00 48.91% Management Project Koga Irrigation And Watershed Agriculture ADF Grant 19.07.01 30.06.10 25.02.02 1,330,000.00 75.45% Management Project Koga Irrigation And Watershed Agriculture ADF Loan 19.07.01 1,639,767.69 100.00% Management Project Rural Finance Interm. Support Agriculture ADF Loan 13.10.03 31.12.09 07.07.04 27,170,000.00 61.12% Project Rural Finance Interm. Support Agriculture ADF Grant 13.10.03 31.12.10 13.10.03 8,000,000.00 77.95% Project Agriculture Sector Support Agriculture ADF Loan 12.02.04 31.12.10 25.01.05 21,240,000.00 49.05% Programme Agriculture Sector Support Agriculture ADF Grant 12.02.04 31.12.10 25.01.05 17,761,200.00 34.23% Programme Genale Dawa River Basin Agriculture ADF Grant 16.11.01 30.12.09 27.06.02 3,928,000.00 96.58% Integ. Dev. Mas Awash River Flood Control Agriculture ADF Grant 15.10.03 30.06.09 19.08.04 1,830,000.00 92.29% Study Livestock Development Agriculture ADF Grant 05.03.04 30.06.09 05.03.04 2,340,000.00 57.71% Masterplan Study Fisheries Resources Agriculture ADF Grant 16.05.05 30.12.09 16.05.05 920,000.00 100.00% Development Study Instl Sup.For Women Affairs Agriculture ADF Grant 15.09.04 31.12.09 15.09.04 1,060,000.00 97.52% Office Wacha-Maji Road Upgrading Transport ADF Loan 13.10.03 31.03.10 18.06.04 22,710,000.00 34.55% Project Wacha-Maji Road Upgrading Transport ADF Grant 13.10.03 31.03.10 13.10.03 990,000.00 71.50% Project Butajira - Hossaina -Sodo Transport ADF Loan 16.11.01 30.12.09 19.03.02 41,310,000.00 71.02% Road Project Butajira - Hossaina -Sodo Transport ADF Loan 16.11.01 4,860,463.39 100.00% Road Project Jimma-Mizan Road Upgrading Transport ADF Loan 12.01.07 31.12.12 03.10.07 65,000,000.00 18.98% Project Mombasa-Nairobi-Addis Transport ADF Grant 1,350,000.00 Corridor Phase I Project Harar Water Supply & Water ADF Loan 08.11.02 30.09.10 09.12.03 19,890,000.00 68.42% Sanitation Project Sup/Sanit Harar Water Supply & Water ADF Grant 08.11.02 30.09.10 08.11.02 1,120,000.00 7.30% Sanitation Project Sup/Sanit Harar Water Supply & Water ADF Loan 08.11.02 250,503.16 100.00% Sanitation Project Sup/Sanit Rural Water Supply & Water ADF Grant 25.02.06 31.12.10 25.02.06 43,610,000.00 14.63% Sanitation Program Sup/Sanit Emergency Humanitarian Water ADF Grant 21.08.06 31.10.06 333,237.81 0.00% Assistance - 2006 Sup/Sanit Water Water Information Systems ADF Grant 31.10.06 30.12.09 31.10.06 445,307.35 90.00% Sup/Sanit Rural Electrification Project Power ADF Loan 14.03.02 30.06.09 12.12.02 37,670,000.00 87.66%
Rural Electrification Project Power ADF Loan 14.03.02 399,196.03 100.00%
Rural Electrification Project Ii Power ADF Loan 12.01.07 31.12.13 02.11.07 87,200,000.00 9.16%
Education Iii Social ADF Loan 20.11.98 30.06.09 19.07.00 32,000,000.00 98.85%
Education Iii Social ADF Grant 20.11.98 30.06.09 17.11.99 300,000.00 50.00%
Education Iii Social ADF Loan 20.11.98 11,502,394.67 100.00%
Rural Health Services Project I Social ADF Loan 17.12.98 30.06.09 22.09.99 29,670,000.00 65.15%
Rural Health Services Project I Social ADF Loan 17.12.98 8,852,537.93 100.00% Privatisation Technical Multi-Sector ADF Grant 08.03.01 30.06.09 08.03.01 3,000,000.00 99.92% Assistance Project Capacity Building Of Mofed Multi-Sector ADF Grant 15.01.02 30.06.09 15.01.02 519,171.00 92.23% Humanitarian Flood-Relief Multi-Sector ADF Grant 17.05.07 31.12.07 333,237.81 0.00% Assistance Ethiopia-Creation Of Agriculture ADF Loan 16.05.05 31.12.11 09.01.06 9,550,000.00 8.49% Sustainable Tsetse Ethiopia_Djibouti Power ADF Loan 16.05.05 30.12.09 08.08.06 20,880,000.00 42.09% Interconnection - Et Protection Of Basic Services Ii Multi-Sector ADF Grant 20.01.09 31.12.11 20.01.09 110,000,000.00 45.48%
Total 673,555,116.84 47.38%
23 Appendix 3
MOMBASA – NAIROBI – ADDIS ABABA ROAD CORRIDOR – PHASE II PROJECT Kenya - Related Projects Financed by the Bank and Other Donors USD Project Title Donor Region million North and South Rift Roads 2000 Districts Rural Roads Maintenance Programme AfDB 29 Valley Districts Multinational: Mombasa - Nairobi - Addis Ababa Road AfDB Eastern Province 54 Corridor Development: Isiolo - Moyale Road (A2): Phase I Multinational: Arusha – Namanga - Athi River Road AfDB Rift Valley Province 72 Development: Athi River - Namanga Road (A104) Nairobi/ Central Nairobi - Thika Highway Improvement (A2) AfDB 166 Provinces Muranga, Maragwa, Roads 2000 Maintenance Programme AFD 29 Nyandarua AFD Rift Valley 26 Mai Mahiu – Narok Road KfW Rift Valley 26 BADEA / Wote - Makindu Road (E707) Eastern Province 25 OPEC BADEA / Emali - Oloitokitok Road (C102) Rift Valley 30 OPEC BADEA / Dundori - Ol Kalou - Njabini Road (C69) Central 0.2 OPEC Kipsigak- Serem- Shamakhoko Road China Rift Valley 16
Gambogi - Serem Road (D329) China Rift Valley 4 Rehabilitation and expansion of the JKIA - Museum Hill - China Nairobi 27 Gigiri Road Construction of the Eastern By-pass China Nairobi 113 Agricultural Sector Programme Support - Agricultural Roads DANIDA Coast, Eastern 4 Sub-component Northern Corridor Rehabilitation Programme – Phase II EC Kenya 87 Strengthening of Capacity on Supervision and Operations JICA Nairobi 3 for Roads Maintenance Works through Contracting Construction of Nairobi Missing Links No. 3, 6 & 7 JICA Nairobi 13
Mombasa Port Development Project JICA Mombasa 223
Roads 2000 Maintenance Programme KfW Rift Valley , Nyanza 12
Roads 2000 Maintenance Programme SIDA Nyanza 25
World Bank 160 Northern Corridor Transport Improvement Project Kenya NDF 15 Northern Corridor Transport Improvement Project - World Bank Kenya 253 Additional financing Northern Corridor Rehabilitation Programme – Phase III EC Kenya 82
Roads 2000 Maintenance Programme Phase. II EC Eastern Province 15
KfW 17 Rural Road Rehabilitation in Mt. Kenya Region & Central Eastern / Central Kenya Province EC 31
Dualling of Nairobi-Dagoretti Corner Road (C60/C61) JICA* Nairobi 11 North Eastern Construction of the Garissa - Modogashe Road BADEA/OPEC* 45 Province TOTAL FOR ONGOING PROJECTS 1,612 * Not concluded
24 Appendix 3
MOMBASA – NAIROBI – ADDIS ABABA ROAD CORRIDOR – PHASE II PROJECT Ethiopia - Related Projects Financed by the Bank and Other Donors
Road Amount Contract Name Donor Length USD Million (km) Butajira-Hossaina AfDB 95 19.67 Hossaina-Sodo AfDB 94 19.26 Jimma-Bonga AfDB 107 62.07 Bonga-Mizan AfDB 120 67.22 Wacha-Maji AfDB 175 70.17 Sub-total 591 238.40 Nazareth-Assela World Bank 79 16.04 Assela-Dodola Junction World Bank 117 36.10 Dodola Junction-Goba World Bank 130 33.62 Gondar-Debark World Bank 99 62.50 Adigrat-Adiabun World Bank 109 25.62 Adiabun-Shire World Bank 92 38.81 Gobgob-Gashena World Bank 86 20.54 Gashena-Woldia World Bank 108 33.55 Aposto-Irbamoda World Bank 94 59.80 Irbamoda-Wadera World Bank 109 55.89 Wadera-Negele World Bank 65 26.23 Dera-Magna World Bank 119 24.34 Magna-Mechara World Bank 120 42.36 Assosa-Blue Nile World Bank 70 18.10 Blue Nile-Guba World Bank 66 21.77 Nekempt-Mekenajo World Bank 127 27.21 Sub-total 1,590 542.46 Addis Ababa-Jimma EU 342 36.73
Dembi-Bedele BADEA 62 21.25 Metu-Gore BADEA 26 11.19 Gore-Gambella BADEA 144 67.94 Sub-total 232 100.38 Mekenajo-Nejo OPEC Fund 61 12.54 Nejo-Mendi OPEC Fund 70 13.37 Sub-total 131 25.91
Azezo-Gint BADEA/OPEC/SAUDI 87 22.36
Gint-Metema BADEA/OPEC/SAUDI 98 22.52
Assosa-Kurmuk BADEA/OPEC/SAUDI 97 45.50
Sub-total 282 90.38 Goha Tsion-Dejen JICA 41 28.89 Addis Ababa-Ambo KfW 112 15.61 Ambo-Gedo KfW 65 27.32 Sub-total 177 42.93 Total 3,386 1,106.08
25 Appendix 4 Map of Project Area
26 Appendix 5 Mombasa-Nairobi-Addis Ababa Road Corridor Development Program Cost Component/Action Phase Year Source of Finance (UA M)
Studies 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 AfDB EU JICA GOE GOK Others Detail Design Isiolo-Moyale (Kenya) Phase 1 1.20 Detail Design Moyale-Ageremarian (Ethiopia) Phase 1 1.00 Detail Design Inland Container Terminal (Ethiopia) Phase 1 0.35 Detail Design Awasa Ageremariam (Ethiopia) Phase 2 0.65 Detail Design Dual Carriageway (Kenya) Phase 2 3.00 Sub-Total Studies 6.20 Infrastructure Improvements Construction Isiolo - Merille River (Kenya) Phase 1 50.00 Expansion of Mombasa Port (Kenya) Phase 1 175.00 Sub-Total Construction Phase 1 225.00 Construction Merille River Marsabit (Kenya) Phase 2 96.99 Construction Marsabit - Turbi (Kenya) Phase 2 112.20 Construction Ageremariam-Yabelo (Ethiopia) Phase 2 43.99 Construction Yabelo-Mega (Ethiopia) Phase 2 47.72 Construction of Road Stations & OSBP Phase 2 9.33 Sub-Total Construction Phase 2 310.23 Construction Turbi-Moyale - Kenya Phase 3 130.00 Construction Mega-Moyale (Ethiopia) Phase 3 50.00 Construction Ageremariam-Awasa (Ethiopia) Phase 3 120.00 Construction of Inland Container Terminal (Ethiopia) Phase 3 15.00 Sub-Total Construction Phase 3 315.00 Policy and Operational Actions Bilateral Trade Agreement Kenya-Ethiopia Phase 2 Road Transit Transport Agreement Phase 2 Trade and Transport Facilitation Program Phase 3 5.00 Program Total Cost 861.43 53 175 313 320 Legend Provided or Pledged Financing Year in which Funding was Secured/Expected Phase 3 Potential Funding Source
27 ANNEX A MOMBASA – NAIROBI – ADDIS ABABA ROAD CORRIDOR – PHASE II PROJECT Country and Sector Brief
Kenya Economic Outlook
With a population of 38.6 million (UN estimate) and a land area of 569 thousand square kilometers, Kenya has the largest GDP in eastern Africa. Kenya averaged 5.4% economic growth during 2002-2007, although this suffered in the post election unrest in 2008. Nevertheless poverty (45.9% in 2007) is still a problem with the poorest 20% of the population receiving only 6% of national income. Kenya is not well endowed with mineral resources, but has rich agricultural land and abundant wildlife. The lack of adequate infrastructure (transport, electricity and telecommunications) seriously inhibits economic growth. Among its regional trading partners, Kenya exports mostly manufactured goods.
Over the past 5 years there has been a small movement away from agriculture and industry and toward services, largely tourism. In 2007, 23% of real GDP was in agriculture, 16% in industry and 60% in services. Agriculture is characterized by a commercial export sector and a large subsistence sector. Kenya is the most industrialized country in East Africa. Industry emphasizes agro-processing, textiles and consumer goods, while services include the booming tourism and telecommunications sector. The construction sector grew by 6.9% in 2007 and is expected to remain strong. Between 2000/1 and 2005/6, Kenya was able to hold its budget deficit to an average 1.6%. Nevertheless, recovery efforts and infrastructure rehabilitation have raised the 2008/9 budget deficit to 5.4%.2 Kenya’s economic growth rate fell to between 2 and 2.5% in 2008 as a result of post-election violence and global factors. The Government’s official growth forecast of 4 to 4.5 in 2009 is probably overly optimistic as the global slowdown begins to affect tourism and horticulture exports and the impact of the drought is felt.3
Inflation: Inflation in Kenya is strongly influenced by food prices which are volatile due to periodic drought and rising demand. It climbed from 11.7% in 2004 to 14.5% in 2006, but dropped to 9.7% in 2007. This was nevertheless high in relation to its neighbors – Uganda at 6.1%, Tanzania at 7% and Sudan at 8%.4
Investment and Growth Strategies: Vision 2030 guides development spending. The Government plans to invest US$25 billion in key growth sectors, such as infrastructure, skills training and social services. The goal is to make Kenya a middle income country by 2030. In keeping with this goal, the 2008/9 budget provides KSh 65 billion for road works, rural electrification, port dredging and the submarine fiber optic cable. Agriculture accounts for about 20% of wage employment plus jobs in the agro-processing area and informal sector. Liberalization in tea marketing is leading to expansion and the horticultural sector is attracting substantial foreign investment. Mining is a minor part of the economy, however, there is some international investment planned. Kenya is already the most industrialized country in East Africa. With tax concessions for industrial growth, the sector is achieving healthy growth rates.
Ethiopia Economic Outlook
With a population between 74 and 81 million living in an area 1.2 million square kilometers, Ethiopia’s economy has been growing quite rapidly since reforms began in 1991. Ethiopia’s GDP remains strongly influenced by the yields of its rain-fed agriculture, which also affects the agro-processing industries and the service economy. Ethiopia has considerable mineral resources which have yet to be developed. The GDP growth rate was 11.1% in 2006-7, with an annual average between 2002/3 and 2006/7 of 8.7%.
2 Economist Intelligence Unit, “Kenya Country Profile 2008”, pp. 17-22. 3 The Times, “What Crunch Means for Africa”, March 12, 2009. 4 Economist Intelligence Unit, op. cit., p. 23. 28 ANNEX A In 2006/7, 43% of Ethiopia’s GDP was from agriculture and related activities, 12.5% from industry and 38.2% from services. About 80% of the population draws its livelihood from agriculture, including livestock. The road system is geared to delivery and redistribution of agricultural produce from Addis Ababa, making intra-regional trade more difficult. There is a recent effort to design roads that foster intra-regional trade as well. The project road will meet this objective by linking Southern Ethiopia directly to East Africa and the Port of Mombasa. The services sector grew by 13.5% in 2006/7. It is led by trade, hotels and restaurants at 14.7%, real estate at 7.6% and transport and communications at 5.2%. Industrial growth has been strong, growing by 9.4% in 2004/5, 10.2% is 2005/6 and 11% in 2006/7. Manufacturing is centered at Addis Ababa and Dire Dawa, but the government is seeking to increase its role in regional capitals.5
Inflation: Inflation is strongly influenced by food prices, which have a 60% weighting in the national consumer price index. Even with good harvests, the high price of fuel has kept the inflation rate high. Government protection of food prices to maintain a production incentive for growers is another factor. The inflation rate for 2007 was 17.2 % and the average between 2003 and 2007 is 12.7%.6
Investment and Growth Strategies: The government has an active program for strengthening the agricultural sector. It is encouraging greater trading in food crops, partial land tenure reform, improved coffee marketing and domestic processing, further increasing the export horticulture industry and local and foreign private investment in the livestock industry. Ethiopia is one of the largest livestock producers in Africa. About 10% GDP comes from livestock and 30% of the agriculture labor force is in livestock. Since opening the sector to private investment, it has become a significant export earner. Transport will play a key role in expansion of this sector. Exploration of mineral, oil and gas resources has been encouraged by the government. Manufacturing accounts for a small percentage of GDP. It is led by food, beverages, textiles/garments and cottage industries. The government conducted some privatization of SMEs in the 1990s, but most firms are still in state ownership, especially the larger ones. There are a number of large foreign investor/Ethiopian owned consortia. The government is seeking foreign investors to strengthen the leather products sector.
Regional Trade within COMESA
Both countries are members of COMESA (Common Market for Eastern and Southern Africa). COMESA is Africa’s largest trading bloc with 19 member countries, land area of 12 million square kilometers, population of 389 million and a combined annual import and export trade of US$14 billion. It began as a preferential trade agreement and has now formed a Free Trade Area, which Kenya has joined, but Ethiopia is still studying to determine whether to join.
The following tables demonstrate the current trade among COMESA members. Exports from Kenya to COMESA countries in 2007 increased by 14.3%, accounting for 69.5% of total exports to African countries. Exports to EAC countries increased by 20.8% in 2007. Imports from COMESA went up by 62.8% while those from EAC more than doubled in 2007. The major sources of Kenyan imports within the block are Egypt, Uganda, Tanzania, Swaziland and Mauritius. The table also demonstrates the positive balance of trade Kenya has been able to maintain within COMESA. The continual growth in exports and imports confirms the potential of trade among East African countries and the impact of reducing tariffs and a transition from reliance on customs duties to increased production based tax in fostering economic and revenue growth.
It should be noted that COMESA countries are also the leading export destination for Uganda having now exceeded EU exports. Total exports for Uganda rose 40% between 2006 and 2007, which is attributed to higher commodity prices, aggressive marketing with local industries
5 Economist Intelligence Unit, “Ethiopia Country Profile 2008”, pp. 22-24. 6 Ibid., p. 31
29 ANNEX A to produce for the export market and relative peace and recovery in Southern Sudan. This suggests that trade with Uganda via the project corridor offers good opportunities for Ethiopia.
Table A1: Total Kenyan Trade with COMESA Member States, 2001-2007
IMPORTS EXPORTS Year CIF Value USD Percent increase/ FOB Value USD Percent increase/ Trade balance decrease decrease 2001 629 ,002,506 629,002,506 2002 121,460,404 669,444,786 64.29% 547,984,382 2003 155,439,389 29.97% 809,310,027 20.89% 653,870,638 2004 183,456,635 18.02% 939,678,502 16.10% 756,221,867 2005 204,094,211 11.24% 1,182,752,146 25.86% 978,657,935 2006 241,886,174 18.51% 1,038,803,320 87.82% 796,917,146 2007 421,671,069 74.32% 1,271,174,065 22.36% 849,502,996
Average 2003-07 241,309,496 1,048,343,612 807,034,116 Average 2005-07 289,217,151 1,164,243,177 875,026,026 Source: Kenya National Bureau of Statistics, Economic Survey 2008 , p. 136.
Ethiopian imports from COMESA countries have shown a constant increase during this period. Exports have shown much more volatility, but in most years an increase in value. A high percentage of Ethiopia’s exports are agriculturally based and the volatility reflects the impact of periodic droughts on production. During the first three years, there is a favorable balance of trade, but it is negative in the latter four years. The overall figures suggest the potential for increased trade growth with the improved road connection between the regions.
Table A2: Total Ethiopian Trade with COMESA Member States (2001-2007)
IMPORTS EXPORTS TRADE BALANCE Year CIF Value USD Percent increase/ FOB Value USD Percent increase/ decrease decrease 2001 47,707,456 11.54% 78,015,817 31.65% 30,308,361 2002 54,011,120 13.21% 63,695,512 -18.36% 9,684,393 2003 91,255,846 68.96% 141,737,366 122.51% 50,475,520 2004 101,334,854 11.04% 48,870,276 -65.52% -52,464,578 2005 136,988,885 35.18% 92,223,537 88.71% -44,765,348 2006 191,784,706 40.00% 92,382,820 0.17% -99,401,886 2007 196,408,118 2.41% 119,465,249 29.32% -76,942,869
Average 2003-07 143,554,481 98,935,850 -44,618,631 Average 2005-07 175,060,569 101,357,202 -73,703,367 Source: Statistics Provided by the Ministry of Trade and Industry, Addis Ababa, Ethiopia
Opportunities for Trade between East African and the Horn of Africa Countries
Some people interviewed argued that East African countries produce similar products making trade with outside regions more attractive. Nevertheless, the tables just presented suggest that there is considerable opportunity for intra-regional trade within East Africa and that the free trade area and customs union have a strong impact on this trend. The very fact that the East African countries rely heavily on agricultural commodities, means that in times of drought, the best source of food and other agricultural commodities may be a neighboring country with better weather conditions in that year.
All of Ethiopia’s top 10 exports to the COMESA region are agricultural, including live animals. Ethiopia’s top 10 imports from COMESA countries are petroleum products, cement, vegetable oils and cigarettes. Kenya is a major trading partner, as well as Uganda, Sudan and Djibouti. Kenya exports to Ethiopia include in order of value products of iron and steel, tobacco,
30 ANNEX A vegetable materials, cleansing preparations, insecticides, paper and paperboard, vegetable fats, aluminium, stationery and sugar confectionery. Kenyan imports from Ethiopia include edible vegetables, spices, tools, coffee, engineering equipment, metal containers, oil seeds, used clothing and iron. In both directions, there is a flow of both agricultural commodities and manufactured goods. To Uganda, Ethiopia exports coffee, vegetables and cuttings, also candles, synthetic fibre, footwear and handbags. From Uganda, Ethiopia imports both agricultural commodities and heavy equipment. With the amount of project equipment imports to Ethiopia in recent years, this should be an area of growth for the corridor. With Sudan and Djibouti, it is necessary to identify which are goods in transit and which are imports and exports. With Sudan, Ethiopia exports primarily agricultural products and imports primarily petroleum products. This suggests there is a diversity of demand and product areas that can be expanded.
The Regional Transport Gateways
Djibouti Port: The Port of Djibouti has been a major port for Ethiopia for the past 100 years, with the exception of 1977 - 1998. The war with Eritrea, left Ethiopia a land-locked country. Currently 98% of Ethiopian traffic uses the Port of Djibouti. Before the Eritrean conflict, Djibouti Port volume ranged from 1.2 to 1.7 million tonnes a year including 200,000 – 400,000 tonnes of domestic traffic. In 2007, port traffic reached 7.5 million tonnes of which 5.6 million tonnes is Ethiopian transit traffic.
The Port of Djibouti has been managed by Dubai World since May 2000. The aim of the concession is to provide efficient service, market the port internationally and attract foreign investment. There has been growth in all areas of port activity in the period from 2005-7. The high volume of Ethiopian traffic has brought significant revenue and job creation to Djibouti through port charges, handling, forwarding, ship repairs and other indirect employment.
Mombasa Port - Cargo traffic increased 10.7% from 14.40 million tonnes in 2006 to 15.96 million tonnes in 2007. A major problem is the imbalance with 81.8% of the total cargo being imports. This disadvantages both the shipping lines and the inland transport operators and thereby affects tariffs. The container traffic is well above the volume for which the port was designed. A second terminal is planned for 2013, about the time that the project road will be completed. In the meantime, container congestion is a problem. Moving unloaded cargo immediately to inland depots and consolidating for shipment at inland depots is advantageous in maintaining efficient operations at the port. Kenya Ports Authority is currently implementing a port community based, integrated information system in which all inputs will be made electronically and where possible remotely as well. Once installed, this system can be used to provide advanced arrival information and document handling through the entire port and inland intermodal system. Cargo owners, logistics companies, customs and other border agencies will all be able to input information electronically and track cargo processing and movement, thereby enabling logistics companies to plan operations for maximum efficiency. Transport on through bills of lading to Nairobi, Kampala, or even Isiolo or Moyale will address some of the congestion at the port, make Mombasa more competitive with other corridors and make movement of goods more seamless. Intra-regional and Overseas Trade Corridors
East Africa is served by several main routes emanating from the key regional ports. The Northern Corridor connects the Port of Mombasa with Nairobi, Kampala, Kigali and Bujumbura. It is also considered to include routes through Uganda and Rwanda to DRC and several northward routes to southern Sudan. A second major artery connects Nairobi to Tanzania through Namanga. Tunduma-Dodoma-Namanga-Moyale is one of the six priority corridors for the East African Community (EAC). Once improved through this project and EAC efforts, it will link Ethiopia – Kenya – Tanzania – Zambia into a trading system as well. The road network also incorporates connections to Kisumu, Entebbe, Mwanza and other regional centers. Therefore the Addis Ababa –Nairobi – Mombasa route, not only connects Ethiopia to an
31 ANNEX A alternative port, but also to a road network that connects it to all of East Africa and beyond to DRC and Zambia. As a result, the project road enables much greater penetration of Ethiopian products into East African markets and of East African products into markets in the Horn of Africa.
In addition to direct shipments from the Port of Mombasa, the Port operates an inland depot at Nairobi which would also be served by this route. It enables overseas goods to have a direct bill of lading to Nairobi and to be warehoused and cleared by customs there for onward shipment on the project road to Ethiopia and the Horn region. The Nairobi depot is served by road and rail from Mombasa allowing for competition on volumes and price. It would allow a more flexible road transport system, shortening the total road distance from Ethiopian/Horn origins and destinations and allowing transporters to build roundtrips based on a combination of regional and/or overseas cargoes. By reducing time and increasing two-way loads it would reduce cost and increase vehicle utilization (number of trips per year) on the route. It also increases the potential income from warehousing and logistics services in Nairobi. Several inland container depots are under discussion on both the Kenya section of the highway and the Ethiopian section of the highway so that direct bills of lading can be used further inland.
The Ethiopian road network emanates from Addis Ababa, which is the distribution and consolidation hub for the country. The project road will provide East Africans with good access to the Ethiopian market and distribution system to surrounding population centers within Ethiopia and to Somalia, especially Somaliland, Djibouti and bordering areas of Sudan. The development of this road would enhance the role of Addis Ababa as a transport hub for the Horn region utilizing dry ports that it is establishing to facilitate trade. This economic opportunity would be enhanced by capacity building for the Ethiopian logistics and road transport companies. Trade and Transport Facilitation
To be a competitive corridor, the goal of the project should be seamless movement throughout the corridor for travellers, tourists and commercial cargo. COMESA has developed instruments to facilitate cross-border travel and trade. Both Kenya and Ethiopia are members of COMESA and have implemented most of the instruments. Kenya and Ethiopia signed a bilateral transport and traffic agreement in 1979 that establishes reciprocal recognition of licenses, registration and access. A new draft for this agreement has been written, but not yet signed and ratified. Prior to this, a bi-lateral working group, including both public and private sectors, should review transport operations between the two countries and what works well on other corridors. Based on this analysis, the proposed agreement should be modified to provide for a full cross-border and transit regime. It should be negotiated and then signed by the two countries prior to completion of construction. This road provides a major corridor linking all of the East African Community and beyond to the Horn of Africa. It is unlikely to realize its potential unless the transit regime is reviewed.
Various measures should be instituted during the course of construction so that they are completed by the inauguration of the Regional Corridor. Regulations need to be standardized and the COMESA facilitation instruments fully implemented in both countries. This entails conclusion and implementation of the revised road transport agreement between Ethiopia and Kenya. The Agreement refers on a number of issues to obeying the rules of the country traveled in. As much as possible, these regulations should be harmonized and stated clearly in the agreement. Recognizing the need for controls along the route, such as weighbridges, customs controls or security checks, they need to be minimized and coordinated as much as possible, so that they do not become bottlenecks. Examples for agreement include:
Overload limits, vehicle dimensions, road worthiness and enforcement: There should be agreement on all four of these so that vehicles can be loaded for the route without being forced to load for the lowest weight. This was the goal for setting a limit for the whole COMESA region. Kenya is currently investing in new weighbridges because of the problems with keeping
32 ANNEX A the calibration consistent. Vehicles should be weighed when they leave the port or shipper depot, once when they cross the border and on arrival at their destination, if necessary to check load integrity. Seals should be introduced as much as possible to avoid the need for inspections of cargo at borders or enroute. Common road worthiness standards and inspections should be developed. Enforcement methods should be similar in the two countries.
Community-based system: This system is now being implemented. It will enable the port, customs, and logistics companies to input and access information electronically thereby simplifying and expediting the process of clearance. It will support through bills of lading to Nairobi. This would mean that the shipping line would take responsibility for shipment to Nairobi and the landside transport and logistics would begin at Nairobi to the final destination. With the development and improvements at the Port of Djibouti, these improvements at Mombasa are particularly important as well as maximizing direct trader input.
Customs reform: The East Africa Trade and Transport Facilitation Project, funded by the World Bank and African Development Bank, is providing assistance to the Revenue Agencies in Kenya, Uganda, Rwanda and Tanzania to facilitate improvements in the transit regime on the Northern and Central Corridors. Several measures are being adopted that can be applied on the Mombasa – Nairobi – Addis Ababa Corridor when it is completed.