Komunala Tolmin, Javno podjetje d.o.o.

Elaborat o oblikovanju cen izvajanja storitev javne službe oskrbe s pitno vodo na obmo čju ob čine

Direktor

Tolmin, marec 2018 Berti Rutar, univ. dipl. inž.

VSEBINA

1. PREDRA ČUNSKA IN OBRA ČUNSKA KOLI ČINA OPRA VLJENIH 2 STORITEV JAVNE SLUŽBE IN STROŠKOV IZVAJANJA STORITEV JAVNE SLUŽBE ZA PRETEKLO OBRA ČUNSKO OBDOBJE

2. IZRA ČUN OBRA ČUN SKE CENE STORITEV JA VNE SLUŽBE IN 5 OBRA ČUNSKE CENE JAVNE INFRASTRUKTURE

3. POJASNILA ODMIKOV OB RA ČUNSKE CENE OD POT RJENE IN 6 ZARA ČUNANE CENE

4. PRIMERJAVA KOMUNALE TOLMIN D.O.O. S POVPRE ČJEM 6 PANOGE

5. PREDRA ČUNSKA KOLI ČIN A OPRAVLJENIH STORIT EV JAV NE 7 SLUŽBE IN STROŠKOV IZVAJANJA STORITEV JAVNE SLUŽBE ZA PRIHODNJE OBRA ČUNSKO OBDOBJE

6. OBSEG POTREBNIH OSNO VNIH SREDSTEV ZA IZV AJANJE 9 STORITEV JAVNE SLUŽBE ZA PRETEKLO IN PRIHODNJE OBDOBJE

7. DONOS NA VLOŽENA OSN OVNA SREDSTVA ZA PRE TEKLO IN 9 PRIHODNJE OBRA ČUNSKO OBDOBJE

8. ŠTEVILO ZAPOSLENIH Z A IZVAJANJE STORITEV JAVNE SLUŽBE 9

9. VIŠINA NAJEMNINE ZA UPORABO JAVNE INFRAS TRUKTURE 11

10. STOPNJA IZKORIŠ ČENOS TI JAVNE INFRASTRUKT URE 17

11. IZRA ČUN PREDRA ČUNSKE CENE STORITEV JAVNE SLUŽBE IN 18 PREDRA ČUNSKE CENE JAVNE INFRASTRUKTURE

1 1. PREDRA ČUNSKA IN OBRA ČUNSKA KOLI ČINA OPRAVLJENIH STORITEV JAVNE SLUŽBE IN STROŠKOV IZVAJANJA STORITEV JAVNE SLUŽBE ZA PRETEKLO OBRA ČUNSKO OBDOBJE

1.1. Koli čina opravljenih storitev javne službe

1.1.1. Predra čunska koli čina prodane pitne vode v m 3

Leto Gospodar. Negospodar. Gospodinjstvo Skupaj 2017 38.000 11.500 197.500 247.000

1.1.2. Obra čunska koli čina prodane pitne vode v m 3:

Leto Gospodar. Negospodar. Gospodinjstvo Skupaj 2010 29.658 14.025 207.498 251.181 2011 36.803 11.291 207.920 256.014 2012 42.038 5.605 206.334 253.977 2013 38.949 6.778 201.470 247.197 2014 37.832 11.850 198.421 248.103 2015 40.290 12.553 204.937 257.780 2016 38.769 11.862 198.573 249.204 2017 43.824 13.448 197.502 254.774

1.1.3. Predra čunsko število priklju čkov na javni vodovod

Priklju ček Število/mesec do DN20 1.955 DN25 63 DN40 8 DN50 12 DN80 7 DN100 DN150 SKUPAJ: 2.045

1.1.3. Predra čunsko število priklju čkov na javni vodovod

Priklju ček Število/mesec do DN20 1.996,08 DN25 36,92 DN40 8,08 DN50 12,08 DN80 8,00 DN100 0,00 DN150 0,00 SKUPAJ: 2.061,17

2 1.2 Predra čunski in obra čunski stroški izvajanja storitev javne službe za preteklo obra čunsko obdobje

v € Predra čunski stroški Obra čunski stroški POSTAVKA Znesek % Znesek % I. STROŠKI VODARINA 108.370,00 100,0 119.512,00 100,0 1. Neposredni proizvajalni stroški 71.138,00 65,6 77.857,00 65,1 1.1. Neposredni stroški materiala 14.900,00 13,7 15.475,00 12,9 1.1.1. Stroški el. energije 5.100,00 6.652,00 1.1.2. Stroški pogonskega goriva 2.300,00 2.388,00 1.1.3. Stroški materiala za pripravo vode 1.1.4. Stroški nakupa vode 1.1.5. Drugi stroški materiala 7.500,00 6.435,00 1.2. Neposredni stroški storitev 5.700,00 5,3 3.075,00 2,6 1.2.1. Stroški intelektualnih in osebnih storitev 1.2.2. Stroški prevoznih storitev 1.2.3. Stroški vzdrževanja 1.700,00 1.752,00 1.2.4. Stroški kontrole in analize vode 1.2.5. Stroški drugih storitev 4.000,00 1.323,00 1.3. Neposredni stroški dela 50.538,00 46,6 59.307,00 49,6 1.4. Drugi neposredni stroški 2. Posredni proizvajalni stroški 0,00 0,0 0,00 0,0 2.1. Posredni stroški materiala 2.2. Stroški amortizacije poslovno potrebnih sredstev 2.3. Posredni stroški storitev 2.4. Posredni stroški dela 2.5. Drugi posredni proizvajalni stroški 3. Splošni nabavno - prodajni stroški 1.050,00 1,0 1.131,00 0,9 3.1. Stroški materiala 3.2. Stroški amortizacije poslovno potrebnih sredstev 1.050,00 1.131,00 3.3. Stroški storitev 3.4. Stroški dela 3.5. Drudi splošno nabavno - prodajni stroški 4. Splošni upravni stroški 14.300,00 13,2 16.239,00 13,6 4.1. Stroški materiala 4.2. Stroški amortizacije poslovno potrebnih sredstev 4.3. Stroški storitev 4.4. Stroški dela 4.5. Drugi splošno upravni stroški 14.300,00 16.239,00 5. Obresti zaradi financiranja opravljanja JS 0,0 0,0 6. Neposredni stroški prodaje 2.800,00 2,6 3.059,00 2,6 7. Neposredni stroški vodnega povra čila 18.580,00 17,1 18.584,00 15,5 8. Drugi poslovni odhodki 450,00 0,4 2.585,00 2,2 9. Donos na vložena posl. potrebna sredstva 52,00 0,0 57,00 0,0

PRIHODKI VODARINA 112.176,00 100,0 115.897,00 100,0 Prihodki iz cene 109.026,00 97,2 113.038,00 97,5 Drugi prihodki 2.500,00 2,2 2.623,00 2,3 Finan čni prihodki 650,00 0,6 236,00 0,2

PORA ČUN 2016 -4.629,00 -4.629,00

REZULTAT VODARINA -823,00 -8.244,00

3 II. STROŠKI OMREŽNINA - VODA 87.322,00 100,0 77.182,00 100,0 1. Najemnina infrastrukture 57.752,00 66,1 55.159,00 71,5 2. Zavarovanje infrastrukture JS 570,00 0,7 535,00 0,7 3. Obnova in vzdrževanje priklju čkov 29.000,00 33,2 21.488,00 27,8 4. Pla čilo za vodno pravico 0,0 0,0 5. Odškodnine za infrastrukturo 0,0 0,0 6. Nadomestilo za kmetijsko dejavnost 0,0 0,0 7. Odhodki financiranja 0,0 0,0

PRIHODKI OMREŽNINA - VODA 85.710,00 98,4 81.775,00 100,0 Cena 84.310,00 98,4 81.775,00 100,0 Drugi prihodki 1.400,00 0,0 0,0

PORA ČUN 2016 6.313,00 6.313,00

REZULTAT OMREŽNINA - VODA 4.701,00 10.906,00

III. REZULTAT DEJAVNOSTI 3.878,00 2.662,00 SKUPNI STROŠKI 195.692,00 196.694,00 SKUPNI PRIHODKI 197.886,00 197.672,00 PORA ČUNI 1.684,00 1.684,00

4 2. IZRA ČUN OBRA ČUNSKE CENE STORITEV JAVNE SLUŽBE IN OBRA ČUNSKE CENE JAVNE INFRASTRUKTURE

2.1. Obra čunska cena storitev javne službe

V letu 2017 je bilo na vodovodnih sistemih v občini Kobarid prodano 254.774m3 pitne vode. Prodaja je bila ve čja od na črtovane, imtudi ve čja od prodaje v letu 2016. Pri vzdrževanju vodovodov je nastalo za 119.512€ stroškov. Pri izračunu cene po enoti moramo upoštevati tudi za 2.859€ drugih prihodkov.

116.653€ : 254.774m3 = 0,4579€/m 3

2.2. Obra čunska cena javne infrastrukture

Število priklju čkov na javni vodovod:

Priklju ček Število/mesec do DN20 1.996,08 DN25 36,92 DN40 8,08 DN50 12,08 DN80 8,00 DN100 0,00 DN150 0,00 SKUPAJ: 2.061,17

Izra čun višine omrežnine:

Priklju ček Število/mesec Število/leto Faktor SKUPAJ do DN20 1.996,08 23.953 1 23.953,00 DN25 36,92 443 3 1.329,00 DN40 8,08 97 10 970,00 DN50 12,08 145 15 2.175,00 DN80 8,00 96 50 4.800,00 DN100 0,00 100 0,00 DN150 0,00 200 0,00 2.061,17 24.734 33.227,00

Stroški omrežnine 79.620,00 € Omrežnina 2,3962 €

5 3. POJASNILA ODMIKOV OBRA ČUNSKE CENE OD POTRJENE IN ZARA ČUNANE CENE

Nastali stroški na vzdrževanju vodovodov so višji od planiranih. Ve čji so materialni stroški in stroški dela. Nižji so stroški dela na vzdrževanju priklju čkov. Prodaja vode je bila pri gospodarstvu zaradi dobre turisti čne sezone bistveno višja od planirane, pri gospodinjstvu pa nižja.

4. PRIMERJAVA KOMUNALE TOLMIN D.O.O. S POVPRE ČJEM PANOGE

Podro čje oskrbe s pitno vodo spada med dejavnost, in sicer Zbiranje, pre čiš čevanje in distribucija vode E36:

Komunala Tolmin Povpre čje d.o.o. panoge E36 Pospešena pokritost kratkoro čnih obveznosti 1,93 1,48 Gospodarnost poslovanja 1,02 1,02 Povpre čna bruto mese čna pla ča v € 1.457,22 1.587,96

Podatki so za leto 2016.

6 5. PREDRA ČUNSKA KOLI ČINA OPRAVLJENIH STORITEV JAVNE SLUŽBE IN STROŠKOV IZVAJANJA STORITEV JAVNE SLUŽBE ZA PRIHODNJE OBRA ČUNSKO OBDOBJE

5.1. Predra čunska koli čina prodane vode v prihodnjem obra čunskem obdobju v m 3

Leto Gospodar. Negospodar. Gospodinjstvo Skupaj 2018 39.000 12.000 197.000 248.000

5.2. Predra čunsko število priklju čkov na javni vodovod v prihodnjem obra čunskem obdobju

Priklju ček Število/mesec do DN20 1.996,00 DN25 36,00 DN40 8,00 DN50 12,00 DN80 8,00 DN100 0,00 DN150 0,00 SKUPAJ: 2.060,00

7 5.3. Predra čunski stroški izvajanja storitev javne službe v prihodnjem obra čunskem obdobju

v € Predra čunski stroški POSTAVKA Znesek % I. STROŠKI VODARINA 113.067,00 100,0 1. Neposredni proizvajalni stroški 70.357,00 62,2 1.1. Neposredni stroški materiala 15.600,00 13,8 1.1.1. Stroški el. energije 6.700,00 1.1.2. Stroški pogonskega goriva 2.400,00 1.1.3. Stroški materiala za pripravo vode 1.1.4. Stroški nakupa vode 1.1.5. Drugi stroški materiala 6.500,00 1.2. Neposredni stroški storitev 3.100,00 2,7 1.2.1. Stroški intelektualnih in osebnih storitev 1.2.2. Stroški prevoznih storitev 1.2.3. Stroški vzdrževanja 1.800,00 1.2.4. Stroški kontrole in analize vode 1.2.5. Stroški drugih storitev 1.300,00 1.3. Neposredni stroški dela 51.657,00 45,7 1.4. Drugi neposredni stroški 2. Posredni proizvajalni stroški 0,00 0,0 2.1. Posredni stroški materiala 2.2. Stroški amortizacije poslovno potrebnih sredstev 2.3. Posredni stroški storitev 2.4. Posredni stroški dela 2.5. Drugi posredni proizvajalni stroški 3. Splošni nabavno - prodajni stroški 1.131,00 1,0 3.1. Stroški materiala 3.2. Stroški amortizacije poslovno potrebnih sredstev 1.131,00 3.3. Stroški storitev 3.4. Stroški dela 3.5. Drudi splošno nabavno - prodajni stroški 4. Splošni upravni stroški 17.500,00 15,5 Stroški materiala Stroški amortizacije poslovno potrebnih sredstev Stroški storitev Stroški dela Drugi splošno upravni stroški 17.500,00 5. Obresti zaradi financiranja opravljanja JS 0,0 6. Neposredni stroški prodaje 3.000,00 2,7 7. Neposredni stroški vodnega povra čila 18.522,00 16,4 8. Drugi poslovni odhodki 2.500,00 2,2 9. Donos na vložena posl. potrebna sredstva 57,00 0,1

PRIHODKI VODARINA 113.116,00 100,0 Prihodki iz cene 110.286,00 97,5 Drugi prihodki 2.600,00 2,3 Finan čni prihodki 230,00 0,2

PORA ČUN 2017 -8.244,00

REZULTAT VODARINA -8.195,00

8 II. STROŠKI OMREŽNINA - VODA 81.620,00 100,0 1. Najemnina infrastrukture 57.085,00 69,9 2. Zavarovanje infrastrukture JS 535,00 0,7 3. Obnova in vzdrževanje priklju čkov 24.000,00 29,4 4. Pla čilo za vodno pravico 0,0 5. Odškodnine za infrastrukturo 0,0 6. Nadomestilo za kmetijsko dejavnost 0,0 7. Odhodki financiranja 0,0

PRIHODKI OMREŽNINA - VODA 78.333,00 100,0 Cena 78.333,00 100,0 Drugi prihodki 0,0

PORA ČUN 2017 10.906,00

REZULTAT OMREŽNINA - VODA 7.619,00

III. REZULTAT DEJAVNOSTI -576,00 SKUPNI STROŠKI 194.687,00 SKUPNI PRIHODKI 191.449,00 PORA ČUNI 2.662,00

Prihodki vodarine in omrežnin so izra čunani na podlagi veljavnih cen. Pri izra čunu smo upoštevali tudi pora čuna vodarine in omrežnine za leto 2017.

6. OBSEG POTREBNIH OSNOVNIH SREDSTEV ZA IZVAJANJE STORITEV JAVNE SLUŽBE ZA PRETEKLO IN PRIHODNJE OBDOBJE

Za izvajanje službe se uporablja eno osebno vozilo, ob časno tudi poltovorno vozilo. V letu 2017 je bilo za potrebe vzdrževanja vodovodov v ob čini Kobarid prevoženih okoli 23.000km.

7. DONOS NA VLOŽENA OSNOVNA SREDSTVA ZA PRETEKLO IN PRIHODNJE OBRA ČUNSKO OBDOBJE

V skladu z 2. Členom uredbe o metodologiji za oblikovanje cen storitev obveznik ob činskih gospodarskih javnih služb varstva okolja predvidevamo na vložena osnovna sredstva donos v višini 57€.

9 8. ŠTEVILO ZAPOSLENIH ZA IZVAJANJE STORITEV JAVNE SLUŽBE

Na vzdrževanju vodovodov v ob čini Kobarid so zaposleni delavci kot je prikazano v spodnji tabeli. Za podro čje kvalitete pitne vode ter izdelavo poro čil, evidenc in programa oskrbe s pitno vodo je v podjetju zaposlen univ. dipl. inž., ki skrbi za to podro čje v vseh treh ob činah, kjer opravljamo dejavnost, pri čemer zaradi velikosti vodovodnih sistemov odpade četrtina njegovega dela na ob čino Kobarid. Za vodenje vzdrževanja je zadolžen vodja vzdrževanja, pri čemer četrtina njegovega dela odpade na ob čino Kobarid. Za ostalo vzdrževanje vodovodnih sistemov sta potrebna 2 vodovodna inštalaterja in 0,5 PK delavca.

Dela in naloge Štev. del. Bruto/leto Dr.st.d./letno Prispevki/leto Skupaj/leto univ.dipl.inž. 0,25 23.548,61 € 1.264,51 € 3.608,46 € 7.105,40 € vodja vzdrževanja 0,25 24.229,24 € 1.125,57 € 3.718,01 € 7.268,21 € KV instalater I. 1 17.475,26 € 1.666,55 € 2.630,63 € 21.772,44 € KV instalater II. 1 16.625,38 € 1.490,81 € 2.493,80 € 20.609,99 € PK delavec 0,5 13.809,75 € 2.734,90 € 2.040,51 € 9.292,58 € 51.675,01 €

10 9. VIŠINA NAJEMNINE ZA UPORABO JAVNE INFRASTRUKTURE

Komunala Tolmin d.o.o. upravlja v ob čini Kobarid vodovode na obmo čju celotne ob čine, razen naselij , Gorenje Drežniške Ravne in Avsa.

Neodpisana Za časna Naziv Nabavna vred. Popravek vred. vrednost amortizacija PARC.ŠT.1094/150,125M2 K.O.IDR 944,29 0,00 944,29 ZELENICA 86M2 K.O. 2.202,85 0,00 2.202,85 PARCELA VL.ŠT.43 K.O.DREŽNICA 1.380,17 0,00 1.380,17 PARC.ŠT.10/4 K.O. 554,81 0,00 554,81 PARC.ŠT.1225/3 IN 1237/2 1.270,18 0,00 1.270,18 PARC.ŠT.2755 K.O. 997,43 0,00 997,43 PARC.ŠT.2840/4K.O.SUŽID 734,75 0,00 734,75 PARC.ŠT.377/36 13M2 54,25 0,00 54,25 PARC.ŠTEV.3575/470 VL.ŠTEV.586 1.821,04 0,00 1.821,04 ZEMLJIŠCE DREŽNICA 166 M 572,79 0,00 572,79 ZEMLJIŠCE LIBUŠNJE 520/10 878,67 0,00 878,67 ZEMLJIŠCE LIVEK 166 M 517,58 0,00 517,58 ZEMLJIŠCE SEDLO 76 M2 262,24 0,00 262,24 PARC.ŠT.1222/2 182M2K.O.DREŽNI 1.121,02 0,00 1.121,02 PARC.ŠT.1303/23 IN PARC.1303/102 33,05 0,00 33,05 PARC.ŠT.1303/23 IN ŠT.1303/102 20.040,00 0,00 20.040,00 PARC.ŠTEV.3575/474 PAŠNIK VL.ŠTEV.537 K.O.KRED 520,00 0,00 520,00 PARC.ŠTEV.3575/477 VL.ŠTEV.139 K.O.KRED 400,00 0,00 400,00 CEVOVOD 190.695,27 92.959,54 97.735,73 5.720,86 CEVOVOD BREGINJ-LTŽ. 11.676,03 1.809,79 9.866,24 233,52 CEVOVOD DR.RAVNE-PE HD 5.140,77 1.490,85 3.649,92 154,22 CEVOVOD DREŽNICA-T,PVC 26.228,62 12.851,98 13.376,64 786,86 CEVOVOD IDRSKO-LTŽ. 50.897,18 13.229,98 37.667,20 1.017,94 CEVOVOD JEVŠ ČEK-PEHD 15.210,32 4.411,00 10.799,32 456,31 CEVOVOD KOBARID-LTŽ. 256.689,96 59.845,40 196.844,56 5.133,80 CEVOVOD KOBARID-POC. 56.117,85 27.424,72 28.693,13 1.683,54 CEVOVOD KOBARID-T,PVC 169.481,20 81.306,13 88.175,07 5.084,44 CEVOVOD KOSEC-PEHD 6.980,00 1.465,80 5.514,20 209,40 CEVOVOD KRED-LTŽ. 79.596,46 12.864,22 66.732,24 1.591,93 CEVOVOD -LTŽ. 36.442,39 6.116,74 30.325,65 728,85 CEVOVOD LADRA-PE 14.860,00 3.120,60 11.739,40 445,80 CEVOVOD LADRA-SMAST-LTŽ. 12.581,51 3.761,20 8.820,31 251,63 CEVOVOD LADRA-SMAST-POC. 10.693,48 4.810,52 5.882,96 320,80 CEVOVOD LADRA-SMAST-T,PVC 116.449,81 54.153,17 62.296,64 3.493,49 CEVOVOD LIVEK 49.519,31 24.253,59 25.265,72 1.485,58 CEVOVOD LIVŠKE RAVNE-T,PVC 75.014,78 34.205,73 40.809,05 2.250,44 CEVOVOD ROBI Č-LTŽ. 1.040,97 223,10 817,87 20,82 CEVOVOD ROBI Č-POC. 37.663,92 9.227,67 28.436,25 1.129,92 CEVOVOD ROBIDIŠ ČE-POC. 25.080,34 25.080,34 0,00 0,00 CEVOVOD ROBIDIŠ ČE-T,PVC 15.599,28 6.922,54 8.676,74 467,98 CEVOVOD SEDLA STARO S.-LTŽ. 19.450,06 3.722,96 15.727,10 389,00 CEVOVOD SEDLO-STARO SELO 24.136,06 5.189,26 18.946,80 482,72

11 CEVOVOD SEDLO-STARO SELO-POC. 37.985,91 18.478,47 19.507,44 1.139,58 CEVOVOD SEDLO-STARO SELO-T,PVC 306.214,32 147.294,28 158.920,04 9.186,43 CEVOVOD ST.SELO-LTŽ. 71.891,54 11.624,99 60.266,55 1.437,83 CEVOVOD STARO SELO-LTŽ 11.596,45 2.106,88 9.489,57 231,93 CEVOVOD STARO SELO-PE HD 18.642,33 3.806,15 14.836,18 559,27 CEVOVOD SUŽID 25.156,66 12.326,79 12.829,87 754,70 CEVOVOD -POC. 27.165,21 11.259,85 15.905,36 814,96 CEVOVOD SVINO-T,PVC 10.406,91 4.925,03 5.481,88 312,21 CEVOVOD TRNOVO OB SOCI-POC. 27.702,72 13.574,31 14.128,41 831,08 CEVOVOD TRNOVO OB SOCI-T,PVC 37.863,85 18.552,06 19.311,79 1.135,92 CEVOVOD VRSNO-LTŽ. 14.046,92 4.234,53 9.812,39 280,94 CEVOVOD VRSNO-POC. 20.398,36 9.995,22 10.403,14 611,95 CEVOVOD VRSNO-T,PVC 36.725,04 17.995,30 18.729,74 1.101,75 ČRPALIŠCE KOBARID MRZLI STUDEN 18.847,26 4.857,27 13.989,99 471,18 ČRPALIŠCE LIVŠKE RAVNE 3.369,50 1.765,67 1.603,83 84,24 ČRPALIŠCE POD SKALCO 17.335,62 8.091,55 9.244,07 433,39 ELEKTROOPREMA VODOHRANA IDRSKO 6.682,09 3.341,05 3.341,04 668,21 ELEKTROOPREMA VODOHRANA LIVEK 4.711,35 471,13 4.240,22 471,13 ELEKTROOPREMA VODOHRANA SEDLO 11.739,20 904,36 10.834,84 1.173,92 ELEKTROOPREMA VODOHRANA VRSNO 4.343,50 0,00 4.343,50 434,35 HIDRANTI KOBARID 22.705,09 9.069,31 13.635,78 454,10 HIDRANTI 1 X ROBIDIŠ ČE 401,67 168,69 232,98 8,03 HIDRANTI 10 X DREŽNICA 4.016,71 1.686,95 2.329,76 80,33 HIDRANTI 13 X BREGINJ LOGJE 5.221,72 2.193,09 3.028,63 104,43 HIDRANTI 2 X SVINO 2.771,54 813,54 1.958,00 55,43 HIDRANTI 3 X LIVŠKE RAVNE 1.205,01 506,13 698,88 24,10 HIDRANTI 3 X SUŽID 1.205,01 506,13 698,88 24,10 HIDRANTI 37 X SEDLO-ST.SELO 15.141,83 6.292,38 8.849,45 302,84 HIDRANTI 4 X TRNOVO OB SO ČI 2.142,25 899,72 1.242,53 42,84 HIDRANTI 6 X LIVEK 2.410,03 1.012,26 1.397,77 48,20 HIDRANTI 6 X VRSNO 2.410,03 1.012,26 1.397,77 48,20 HIDRANTI 9 X LADRA-SMAST 3.615,04 1.518,36 2.096,68 72,30 HIDRANTI IDRSKO 1.877,82 563,36 1.314,46 37,56 HIDRANTI JEVŠ ČEK 980,80 215,73 765,07 19,62 HIDRANTI KOSE Č 941,45 131,81 809,64 18,83 HIDRANTI KRED 1.948,00 319,28 1.628,72 38,96 HIDRANTI LADRA 1.770,00 275,00 1.495,00 35,40 HIDRANTI ROBI Č 1.439,66 287,93 1.151,73 28,79 HIDRANTI ST.SELO 3.715,00 576,90 3.138,10 74,30 HIDRANTI STARO SELO 607,58 121,48 486,10 12,15 JAŠKI KOBARID 30.855,45 12.802,43 18.053,02 617,11 JAŠKI 1 X LIVŠKE RAVNE 508,78 216,27 292,51 10,18 JAŠKI 17 X BREGINJ LOGJE 10.184,24 4.297,55 5.886,69 203,68 JAŠKI 3 X ROBIDIŠ ČE 2.648,29 961,25 1.687,04 52,97 JAŠKI 3 X SUŽID 1.526,35 648,65 877,70 30,53 JAŠKI 3 X SVINO 4.580,85 1.465,77 3.115,08 91,62 JAŠKI 31 X SEDLO-ST.SELO 16.617,28 6.859,60 9.757,68 332,35 JAŠKI 4 X VRSNO 2.035,13 864,90 1.170,23 40,70 JAŠKI 5 X LADRA-SMAST 9.534,46 3.590,20 5.944,26 190,69 JAŠKI 5 X DREŽNICA 2.543,92 1.081,17 1.462,75 50,88 JAŠKI 5 X TRNOVO OB SO ČI 1.271,96 540,57 731,39 25,44 JAŠKI 6 X LIVEK 3.052,70 1.297,41 1.755,29 61,05

12 JAŠKI IDRSKO 1.647,56 502,54 1.145,02 32,95 JAŠKI JEVŠ ČEK 2.837,59 638,46 2.199,13 56,75 JAŠKI KOSEC 2.425,00 351,63 2.073,37 48,50 JAŠKI KRED 15.898,10 2.760,42 13.137,68 317,96 JAŠKI LADRA 10.431,09 1.654,10 8.776,99 208,62 JAŠKI ROBI Č 4.819,73 988,00 3.831,73 96,39 JAŠKI ST.SELO 9.730,04 1.565,65 8.164,39 194,60 JAŠKI STARO SELO 7.973,95 1.571,06 6.402,89 159,48 OMREŽJE VODOVDA SEDLO-NL 8.677,50 173,55 8.503,95 173,55 OMREŽJE VODOVDA SEDLO-PE 4.555,00 91,10 4.463,90 91,10 OMREŽJE VODOVOD DREŽNICA-JE(POC.CEVI- 373,74 11,21 362,53 11,21 JEKLO)OMREŽJE VODOVOD DREŽNICA-PE 2.135,60 384,41 1.751,19 64,07 OMREŽJE VODOVODA -NL 13.510,18 1.080,81 12.429,37 270,20 OMREŽJE VODOVODA BORJANA-PE 18.290,34 1.980,35 16.309,99 521,90 OMREŽJE VODOVODA BORJANA-POC.CEVI-JEKLO 3.158,41 379,01 2.779,40 94,75 OMREŽJE VODOVODA BREGINJ-JE(POC.CEVI-JEKLO) 2.179,00 0,00 2.179,00 65,37 OMREŽJE VODOVODA BREGINJ-NL 12.350,83 0,00 12.350,83 247,02 OMREŽJE VODOVODA BREGINJ-PE 13.303,32 1.662,06 11.641,26 376,01 OMREŽJE VODOVODA DREŽNICA-NL 19.773,04 2.372,77 17.400,27 395,46 OMREŽJE VODOVODA DREŽNICA-PE 5.238,36 628,60 4.609,76 157,15 OMREŽJE VODOVODA DREŽNICA-POC.CEVI-JEKLO 1.240,50 176,56 1.063,94 37,21 OMREŽJE VODOVODA HOMEC-PE 8.915,94 356,64 8.559,30 178,32 OMREŽJE VODOVODA IDRSKO-NL 230.401,57 31.839,26 198.562,31 4.608,03 OMREŽJE VODOVODA IDRSKO-PE 5.379,48 1.116,24 4.263,24 161,38 OMREŽJE VODOVODA IDRSKO-POC.CEVI-JEKLO 9.385,19 1.947,43 7.437,76 281,56 OMREŽJE VODOVODA JEVŠ ČEK-NL 4.865,25 389,23 4.476,02 97,31 OMREŽJE VODOVODA JEVŠ ČEK-PE 5.470,15 656,41 4.813,74 164,10 OMREŽJE VODOVODA JEVŠ ČEK-POC.CEVI-JEKLO 3.989,00 718,02 3.270,98 119,67 OMREŽJE VODOVODA -JE(POC.CEVI- 127,11 3,81 123,30 3,81 JEKLO)OMREŽJE VODOVODA KOBARID-JE(POC.CEVI- 2.899,00 0,00 2.899,00 86,97 JEKLO)OMREŽJE VODOVODA KOBARID-NL 299.352,16 24.132,95 275.219,21 5.987,04 OMREŽJE VODOVODA KOBARID-PE 32.945,46 4.734,01 28.211,45 974,51 OMREŽJE VODOVODA KOBARID-POC.CEVI-JEKLO 28.923,12 3.934,81 24.988,31 867,69 OMREŽJE VODOVODA KOSE Č-NL 32.805,30 2.464,18 30.341,12 656,10 OMREŽJE VODOVODA KOSE Č-PE 17.377,23 1.862,61 15.514,62 493,49 OMREŽJE VODOVODA KOSE Č-POC.CEVI-JEKLO 4.294,52 515,35 3.779,17 128,84 OMREŽJE VODOVODA KRED-NL 3.807,45 216,47 3.590,98 76,15 OMREŽJE VODOVODA KRED-PE 4.521,67 180,86 4.340,81 90,43 OMREŽJE VODOVODA LADRA-NL 57.199,15 6.712,75 50.486,40 1.143,98 OMREŽJE VODOVODA LADRA-PE 15.606,07 2.544,14 13.061,93 468,18 OMREŽJE VODOVODA LADRA-POC.CEVI-JEKLO 866,50 155,96 710,54 25,99 OMREŽJE VODOVODA LIVEK-NL 3.113,32 62,27 3.051,05 62,27 OMREŽJE VODOVODA LIVEK-PE 839,44 33,58 805,86 16,79 OMREŽJE VODOVODA LOGJE -PE 19.083,14 2.462,59 16.620,55 572,49 OMREŽJE VODOVODA LOGJE-NL 22.463,04 1.544,22 20.918,82 449,26 OMREŽJE VODOVODA LOGJE-PE 6.789,00 407,34 6.381,66 135,78 OMREŽJE VODOVODA LOGJE-POC.CEVI-JEKLO 571,25 68,55 502,70 17,14 OMREŽJE VODOVODA -JE(POC.CEVI-JEKLO) 224,02 6,72 217,30 6,72 OMREŽJE VODOVODA -PE 5.993,33 329,57 5.663,76 131,09 OMREŽJE VODOVODA MLINSKO-POC.CEVI-JEKLO 1.889,53 226,75 1.662,78 56,69 OMREŽJE VODOVODA -NL 6.887,55 0,00 6.887,55 137,75 OMREŽJE VODOVODA PODBELA-PE 3.039,90 0,00 3.039,90 60,80

13 OMREŽJE VODOVODA POTOKI-PE 9.368,04 1.372,97 7.995,07 278,11 OMREŽJE VODOVODA SEDLO-NL 58.810,79 3.683,92 55.126,87 1.176,21 OMREŽJE VODOVODA SEDLO-PE 57.951,89 4.552,10 53.399,79 1.449,85 OMREŽJE VODOVODA SMAST-NL 1.085,45 130,26 955,19 21,71 OMREŽJE VODOVODA STANOVIŠ ČE-PE 1.524,00 228,60 1.295,40 45,72 OMREŽJE VODOVODA STARO SELO-NL 20.502,73 798,62 19.704,11 410,05 OMREŽJE VODOVODA STARO SELO-PE 2.136,67 384,60 1.752,07 64,10 OMREŽJE VODOVODA STARO SELO-POC.CEVI- 3.855,12 693,92 3.161,20 115,65 JEKLOOMREŽJE VODOVODA SUŽID-NL 35.981,24 2.155,08 33.826,16 719,62 OMREŽJE VODOVODA SUŽID-PE 31.596,23 2.389,29 29.206,94 767,05 OMREŽJE VODOVODA SVINO-NL 1.983,53 198,35 1.785,18 39,67 OMREŽJE VODOVODA SVINO-PE 11.481,20 1.377,75 10.103,45 344,44 OMREŽJE VODOVODA TRNOVO OB SO ČI-PE 355,68 14,22 341,46 7,11 OMREŽJE VODOVODA TRNOVO-NL 2.880,69 288,06 2.592,63 57,61 OMREŽJE VODOVODA VRSNO-NL 1.988,00 0,00 1.988,00 39,76 OMREŽJE VODOVODA VRSNO-PE 30.591,46 1.431,17 29.160,29 731,09 OPREMA ZA PRIPRAVO VODE BREGINJ 5.969,49 2.387,80 3.581,69 596,95 OPREMA ZA PRIPRAVO VODE DREŽNICA 3.232,40 646,48 2.585,92 323,24 OPREMA ZA PRIPRAVO VODE IDRSKO 8.097,89 4.048,95 4.048,94 809,79 OPREMA ZA PRIPRAVO VODE KOSE Č 627,20 62,72 564,48 62,72 OPREMA ZA PRIPRAVO VODE LADRA-SMAST 2.870,40 1.722,24 1.148,16 287,04 OPREMA ZA PRIPRAVO VODE LIVEK 14.896,23 1.489,62 13.406,61 1.489,62 OPREMA ZA PRIPRAVO VODE SEDLO 5.684,00 568,40 5.115,60 568,40 OPREMA ZA PRIPRAVO VODE SUŽID 925,37 555,22 370,15 92,54 OPREMA ZA PRIPRAVO VODE SVINO 2.933,40 1.466,70 1.466,70 293,34 OPREMA ZA PRIPRAVO VODE TRNOVO 3.327,07 1.663,54 1.663,53 332,71 RAZTEŽILNIK KOBARID JEZERCA 4.016,71 1.433,96 2.582,75 100,42 RAZTEŽILNIK KOBARID MAGOZD 5.355,61 5.355,61 0,00 0,00 RAZTEŽILNIK LADRA-SMAST ZAKRAJ 6.426,74 2.294,31 4.132,43 160,67 RAZTEŽILNIK SEDLO-S.SELO-PODB 4.909,03 1.433,46 3.475,57 122,73 RAZTEŽILNIK SEDLO-ST.S.KRED 6.694,52 2.389,93 4.304,59 167,36 RAZTEŽILNIK SEDLO-ST.S.POTOKI 2.008,36 717,05 1.291,31 50,21 STROJNA OPREMA VODOHRANA LIVEK 1.850,58 185,06 1.665,52 185,06 STROJNA OPREMA VODOHRANA SEDLO 11.352,28 0,00 11.352,28 1.135,22 VODOHRAN BREGINJ 100 M3 103.097,00 19.382,23 83.714,77 2.577,42 VODOHRAN BREGINJ LOGJE 25 M3 7.347,15 2.484,34 4.862,81 183,68 VODOHRAN DREŽNICA 79.789,20 30.858,98 48.930,22 1.994,73 VODOHRAN DREŽNIŠKE RAVNE 37.589,63 11.187,93 26.401,70 939,74 VODOHRAN IDRSKO 49.095,07 14.974,05 34.121,02 1.227,38 VODOHRAN JEVŠ ČEK 54.837,99 5.483,80 49.354,19 1.370,95 VODOHRAN KOBARID 100 M3 27.216,02 9.653,72 17.562,30 680,40 VODOHRAN KOBARID 360 M3 269.470,00 50.660,36 218.809,64 6.736,75 VODOHRAN KOBARID IDRSKO 15 M3 10.041,78 10.041,78 0,00 0,00 VODOHRAN KOBARID-DEZINFEKCIJA 8.950,00 6.802,00 2.148,00 895,00 VODOHRAN KOBARID-ELEKTROOPREMA 16.580,00 12.136,56 4.443,44 1.658,00 VODOHRAN LADRA-SMAST LADRA 40M 6.962,30 2.485,52 4.476,78 174,06 VODOHRAN LADRA-SMAST SMAST 100 42.911,86 15.319,54 27.592,32 1.072,80 VODOHRAN LIBUŠNJE 45.205,61 14.951,13 30.254,48 1.130,14 VODOHRAN LIVEK 100 M3 40.245,70 13.802,55 26.443,15 1.006,14 VODOHRAN LIVŠKE RAVNE 50 M3 51.903,26 17.676,29 34.226,97 1.297,58 VODOHRAN ROBIDIŠ ČE 25 M3 15.899,48 15.899,48 0,00 0,00 VODOHRAN SEDLO 106.674,14 2.666,85 104.007,29 2.666,85

14 VODOHRAN SEDLO-ST.S.BORJANA 1.305,43 465,98 839,45 32,64 VODOHRAN SEDLO-ST.S.KRED 35.407,32 9.952,50 25.454,82 885,18 VODOHRAN SEDLO-ST.S.PODBELA 8.702,87 3.106,96 5.595,91 217,57 VODOHRAN SEDLO-ST.S.POTOKI 6.527,15 6.527,15 0,00 0,00 VODOHRAN SEDLO-ST.S.STANOVIŠ ČE 3.916,29 1.398,07 2.518,22 97,91 VODOHRAN SEDLO-ST.S.STARO SELO 10.617,69 8.799,30 1.818,39 265,44 VODOHRAN SUŽID 100M3 58.245,43 19.453,31 38.792,12 1.456,14 VODOHRAN SVINO 40 M3 15.263,50 5.449,16 9.814,34 381,59 VODOHRAN TRNOVO OB SO ČI 62 M3 10.791,56 3.852,57 6.938,99 269,79 VODOHRAN VRSNO 72.877,53 0,00 72.877,53 1.821,94 VODOHRAN VRSNO 60 M3 26.108,62 26.108,62 0,00 0,00 VODOHRAN VRSNO-SELCE 25 M3 8.702,87 3.106,96 5.595,91 217,57 VODOVODNI JAŠKI BORJANA 4.728,33 189,14 4.539,19 94,57 VODOVODNI JAŠKI BORJANA-BET 4.221,42 337,72 3.883,70 84,43 VODOVODNI JAŠKI BREGINJ 7.080,07 287,19 6.792,88 141,61 VODOVODNI JAŠKI DREŽNICA 2.605,48 52,11 2.553,37 52,11 VODOVODNI JAŠKI DREŽNICA-BET. 7.258,57 775,97 6.482,60 145,17 VODOVODNI JAŠKI HOMEC 3.175,38 127,02 3.048,36 63,51 VODOVODNI JAŠKI IDRSKO-BET. 36.213,64 5.009,55 31.204,09 724,27 VODOVODNI JAŠKI JEVŠ ČEK-BET. 1.755,39 210,65 1.544,74 35,11 VODOVODNI JAŠKI JEZERCA 733,38 14,67 718,71 14,67 VODOVODNI JAŠKI KOBARID 151.247,13 14.608,42 136.638,71 3.024,94 VODOVODNI JAŠKI KOBARID-BET 6.870,50 115,46 6.755,04 137,41 VODOVODNI JAŠKI KOSE Č 5.994,33 451,63 5.542,70 119,88 VODOVODNI JAŠKI KRED 5.136,12 279,56 4.856,56 102,73 VODOVODNI JAŠKI LADRA-BET. 20.161,78 2.350,92 17.810,86 403,24 VODOVODNI JAŠKI LIVEK 1.326,45 53,06 1.273,39 26,53 VODOVODNI JAŠKI LOGJE 9.977,47 760,80 9.216,67 199,55 VODOVODNI JAŠKI MAGOZD 861,52 17,23 844,29 17,23 VODOVODNI JAŠKI MLINSKO 2.547,36 136,61 2.410,75 50,95 VODOVODNI JAŠKI PODBELA-BET 3.128,50 0,00 3.128,50 62,57 VODOVODNI JAŠKI POTOKI 3.813,45 341,15 3.472,30 76,27 VODOVODNI JAŠKI SEDLO 27.190,68 1.620,09 25.570,59 543,81 VODOVODNI JAŠKI STARO SELO 1.550,00 62,00 1.488,00 31,00 VODOVODNI JAŠKI STARO SELO-BET. 1.882,27 225,88 1.656,39 37,65 VODOVODNI JAŠKI SUŽID 14.243,89 677,72 13.566,17 284,88 VODOVODNI JAŠKI SVINO 987,00 78,96 908,04 19,74 VODOVODNI JAŠKI TRNOVO OB SO ČI 718,00 28,72 689,28 14,36 VODOVODNI JAŠKI VRSNO 4.986,79 0,00 4.986,79 99,74 ZAJETJE BREGINJ LOGJE-KOKOŠAR 10.041,78 3.584,92 6.456,86 251,04 ZAJETJE DREŽNICA POD KAMNOM 3.347,26 3.347,26 0,00 0,00 ZAJETJE KOBARID KALI 4.016,71 4.016,71 0,00 0,00 ZAJETJE KOBARID NA ZAJETJU 4.016,71 4.016,71 0,00 0,00 ZAJETJE KOBARID POTOCEK 4.016,71 4.016,71 0,00 0,00 ZAJETJE KOBARID TRESILO 30.742,22 8.325,30 22.416,92 768,56 ZAJETJE LADRA-SMAST ZA POTOKOM 62.384,05 27.060,51 35.323,54 1.559,60 ZAJETJE LADRA-SMAST ZAKRAJ 8.286,36 2.792,73 5.493,63 207,16 ZAJETJE LIVEK-POD KUKOM 1 1.606,68 573,60 1.033,08 40,17 ZAJETJE LIVEK-POD KUKOM 2 4.284,49 1.529,54 2.754,95 107,11 ZAJETJE LIVŠKE RAVNE-V BANTU 15.372,09 5.185,70 10.186,39 384,30 ZAJETJE ROBIDIŠ ČE-IVANEC 8.033,42 8.033,42 0,00 0,00 ZAJETJE SEDLO-STARO S.KONJIK 2.410,03 860,36 1.549,67 60,25

15 ZAJETJE SEDLO-STARO S.NA BAJER 2.142,25 764,77 1.377,48 53,56 ZAJETJE SEDLO-STARO S.NA LAZNA 5.355,61 5.355,61 0,00 0,00 ZAJETJE SEDLO-STARO S.REPEC 13.389,04 4.779,81 8.609,23 334,73 ZAJETJE SEDLO-STARO S.STUDENC 1.606,68 573,60 1.033,08 40,17 ZAJETJE SEDLO-STARO S.ZA BULCE 6.341,63 2.223,29 4.118,34 158,54 ZAJETJE SEDLO-STARO S.ZBIRULJA 2.677,81 2.677,81 0,00 0,00 ZAJETJE SUŽID-ZA MLINOM 1 2.677,81 955,98 1.721,83 66,95 ZAJETJE SUŽID-ZA MLINOM 2 4.284,49 1.529,54 2.754,95 107,11 ZAJETJE SVINO-MO ČILA 8.836,76 3.154,69 5.682,07 220,92 ZAJETJE TRNOVO OB SOCI ZA LOM. 3.213,37 1.147,13 2.066,24 80,33 ZAJETJE VRSNO KURNIK 1 8.033,42 8.033,42 0,00 0,00 ZAJETJE VRSNO KURNIK 2 4.016,71 1.433,96 2.582,75 100,42 ZUNANJA UREDITEV VODOVODA BORJANA 9.400,21 1.504,03 7.896,18 376,01 ZUNANJA UREDITEV VODOVODA BREGINJ 4.610,00 922,00 3.688,00 184,40 ZUNANJA UREDITEV VODOVODA DREŽNICA 2.269,99 363,20 1.906,79 90,80 ZUNANJA UREDITEV VODOVODA HOMEC 814,75 65,18 749,57 32,59 ZUNANJA UREDITEV VODOVODA IDRSKO 85.429,43 23.536,96 61.892,47 3.417,18 ZUNANJA UREDITEV VODOVODA JEVŠ ČEK 2.108,99 462,49 1.646,50 84,36 ZUNANJA UREDITEV VODOVODA KOBARID 32.354,88 5.989,48 26.365,40 1.294,20 ZUNANJA UREDITEV VODOVODA LADRA 23.452,16 5.479,12 17.973,04 938,09 ZUNANJA UREDITEV VODOVODA LOGJE 5.745,54 732,95 5.012,59 229,82 ZUNANJA UREDITEV VODOVODA MLINSKO 409,41 65,51 343,90 16,38 ZUNANJA UREDITEV VODOVODA POTOKI 5.828,76 1.165,75 4.663,01 233,15 ZUNANJA UREDITEV VODOVODA SEDLO 28.841,89 2.046,02 26.795,87 1.153,68 ZUNANJA UREDITEV VODOVODA STARO SELO 4.758,44 378,17 4.380,27 190,34 ZUNANJA UREDITEV VODOVODA SUŽID 3.159,72 385,32 2.774,40 126,39 ZUNANJA UREDITEV VODOVODA SVINO 1.058,10 169,29 888,81 42,32 ZUNANJA UREDITEV VODOVODA VRSNO 5.808,07 0,00 5.808,07 232,32 PARC.ŠT.787/194 K.O.SMAST 930,52 0,00 930,52 SKUPAJ: 5.601.991,64 1.528.301,24 4.073.690,40 144.887,15 *podatki ne vklju čujejo osnovnih sredstev, ki so aktivirana v decembru 2017 ter nepremi čnin v izgradnji.

Javna infrastruktura je izkoriš čena 39.40%, kar pomeni, da moramo pri izra čunu najemnin upoštevati amortizacijo v višini 57.085,54€.

16 10. STOPNJA IZKORIŠ ČENOSTI JAVNE INFRASTRUKTURE

Maksimalna zmogljivost Potencial črpališ č in Prodane dolo čen v Minimalna cevovodov, Zap. št. Vodovodni sistem Ime vira koli čine 2017 z vodni pravici v izdatnost l/s minimalna izgubami v m3 m3 zmogljivost vodnih virov v m3 1. Breginj - Logje KOKOŠAR 37.843 5,0 37.843 16.614 2. Drežnica POD KAMNOM 31.536 2,0 31.536 14.753 3. Idrsko POTO ČEK 47.304 1,5 47.304 25.116 4. Jevš ček LINJEVEC 3.154 presiha/ 0 1.286 5. Kobarid MRZLI STUDENEC 473.040 10,0 126.144 101.425 6. Kobarid TRESILO 157.680 8,0 252.288 7. Kose č NA STUDENCU 252.288 0,3 9.461 4.123 8. Ladra - Smast ZAKRAJ 47.304 2,7 47.304 23.667 9. Ladra - Smast ZA POTOKOM 47.304 1,5 47.304 10. Livek POD SKALCO 15.768 0,4 12.614 11. Livek POD KUKOM SP 15.768 0,5 15.768 10.692 12. Livek POD KUKOM ZG 15.768 0,4 12.614 13. Livške Ravne V BANTU 3.154 0,1 1.577 1.938 14. Sedlo - Staro selo REPEC 63.072 1,3 40.997 56.221 15. Sužid ZA MLINOM 1 9.460 0,3 9.461 10.233 16. Sužid ZA MLINOM 2 9.460 0,3 9.461 17. Svino MO ČILO 12.614 0,2 6.307 5.937 18. Trnovo ob So či ZA ZLOMI ČO 25.229 2,0 25.229 15.569 19. Vrsno - Selce KURNIK ZG. 12.614 0,4 12.614 10.031 20. Vrsno - Selce KURNIK SP. 9.460 1,1 9.460 1.289.820 755.286 297.605 č Izkoriš enost: 39,40%

17 11. IZRA ČUN PREDRA ČUNSKE CENE STORITEV JAVNE SLUŽBE IN PREDRA ČUNSKE CENE JAVNE INFRASTRUKTURE

11.1 Predra čunska cena storitev javne službe

Glede na prodane koli čine vode v letu 2017 je predvideno, da se bo v letu 2018 na vodovodnih sistemih v občini Kobarid prodalo 248.000m3 pitne vode, pri čemer predvidevamo, da bo pri tem nastalo za 113.067€ stroškov. Pri izra čunu cene po enoti moramo upoštevati tudi za 2.830€ drugih prihodkov in negativni pora čun iz leta 2017 v višini 8.244€.

118.481€ : 248.000m3 = 0,4777€/m 3

11.2. Predra čunska cena javne infrastrukture

Število priklju čkov na javni vodovod:

Priklju ček Število/mesec do DN20 1.996,00 DN25 36,00 DN40 8,00 DN50 12,00 DN80 8,00 DN100 0,00 DN150 0,00 SKUPAJ: 2.060,00

Izra čun višine omrežnine:

Priklju ček Število/mesec Število/leto Faktor SKUPAJ do DN20 1.996 23.952 1 23.952,00 DN25 36 432 3 1.296,00 DN40 8 96 10 960,00 DN50 12 144 15 2.160,00 DN80 8 96 50 4.800,00 DN100 0 0 100 0,00 DN150 0 0 200 0,00 2.060 24.720 33.168,00

Stroški omrežnine 70.714,00 € Omrežnina 2,1320 €

Pri izra čunu omrežnine smo upoštevali tudi pora čun omrežnine za leto 2017 v višini 10.906€.

18