Upcoming Roadworks September 2021

Table below covers main City Council scheduled roadworks for September 2021. Note: it does not cover every piece of maintenance work and dates may change due to weather or other unforeseen circumstances.

Latest updates on roadworks, road closures and events information can be found on the WCC website at: https://wellington.govt.nz/services/parking-and-roads/road-works/road-works-and-road-closures

LOCATION TYPE OF WORK INDICATIVE TRAFFIC MANAGEMENT (unless noted, all OTHER INFORMATION DATES work is day work) Southern Suburbs Evans Bay Parade Cycleway Construction September 2020 Stop / go traffic management from 9am to Crews starting work at the Greta Point end – Weka Bay to to October 2021 4pm weekdays. Traffic down to one lane of the project. Within the work site there is Greta Point during the day. Pedestrians and cyclists a 30kmh speed restriction from Weka Bay to please follow the direction of crews on site. Greta Point. Miramar Avenue Cycle path, footpath and May to Please take extra care through the work Scope of works includes landscape construction. November 2021 site. intersection Lyall Parade, Lyall Heritage seawall May 2020 – end Part of footpath closed. Day works Bay strengthening of September 2021 – Concrete repairs on the April 27th – end Footpath works, pedestrians and cyclists can Day works Grass Street to heritage sea wall of November still use the area but take care past the work Carlton Gore 2021 site. Road Lookout Road, Road patches August – 10 Half Road closures to take place between Access to the lookout will always be Sept Alexander Rd and the lookout for phase one available. Traffic will be detoured to access and Thane Road to the lookout for phase the lookout accordingly. two. Pre-seal work in preparation for road resurfacing within the next 6 months.

Wellington City Council | 1 of 7 LOCATION TYPE OF WORK INDICATIVE TRAFFIC MANAGEMENT (unless noted, all OTHER INFORMATION DATES work is day work) Waitoa Road, Construction of 22 June – Stop / go traffic management. Motorists Day works. For more information go to the Moxham Ave & roundabout November 2021 please take extra care through this work WCC website project page. Please note this Hataitai Road area to accommodate pedestrians, cyclists work will impact on parking through the and construction crew. work area. Buckey Road, Kerb, channel and 2 August –16 Stop / go traffic management and reduced Pre-seal work in preparation for road Southgate footpath renewal September speed limit resurfacing within the next 6 months. 2021 Ohiro Road, Kerb, channel and 13 September Stop / go traffic management and reduced Pre-seal work in preparation for road Brooklyn footpath renewal 21 – 8 October speed limit resurfacing within the next 6 months. 21 Section between Borlase St and Happy Valley Road. Maple Grove, Kerb, channel and 6 – 24 Resident assess only closure. Pre-seal work in preparation for road Kingston footpath renewal September 21 resurfacing within the next 6 months. Tully Street, Kerb, channel and 29 July – 3 Sept Contraflow and reduced speed limit Pre-seal work in preparation for road Kilbirnie footpath renewal 21 resurfacing within the next 6 months. Bay Road, Kerb, channel and 19 – 23 Sept 21 Stop / go traffic management and reduced Night works, from 7pm – 6am. Extensive Kilbirnie footpath renewal speed limit comms to go out. Tirangi Road, Kerb, channel and 6 – 24 Sept 21 Resident assess only closure. Pre-seal work in preparation for road Kilbirnie footpath renewal resurfacing within the next 6 months. Edinburgh Kerb, channel and 27 Sept – 22 Resident assess only closure. Pre-seal work in preparation for road Terrace, footpath renewal October resurfacing within the next 6 months. Berhampore CBD Suburbs

Wellington City Council | 2 of 7 LOCATION TYPE OF WORK INDICATIVE TRAFFIC MANAGEMENT (unless noted, all OTHER INFORMATION DATES work is day work) Farmers Lane, Improvements to widen 02 August – 3 Resident assess only closure. The lane will be resurfaced to provide a Wellington pedestrian space September 21 wider pedestrian area with planter boxes Central being installed. Northern Suburbs Ngaio Gorge Slip Stabilisation project 12 October Traffic reduced to one lane controlled traffic Further information on WCC website project 2020 to 2022 control signals. page. Albemarle Road, Remedial works to April 27th to end Stop / go traffic management and reduced Day works by number 7, retaining wall of October 2021 speed limit Northland Mt Pleasant Road Slope stabilisation works May to October Stop go traffic management controlled by 2021 traffic signals. Day works. Main Road, Tawa Footpath, sump, kerb 01 September Stop/go traffic management. Day work. Day work. Letter drop provided to and channel to 29 Reduced speed limit residents/businesses, major engagement maintenance and road September 2021 planned. Date could potentially be pushed repairs out Chisbury Street, Footpath and drainage 06 September Stop/go traffic management. Day work. Day work. Letter drop provided to maintenance and road to 13 Reduced speed limit residents/businesses, major engagement repairs September 2021 planned. Date could potentially be pushed out Branscombe Footpath and drainage 14 September Stop/go traffic management. Day work. Day work. Letter drop provided to Street, maintenance and road to 20 Reduced speed limit residents/businesses, major engagement Johnsonville repairs September 2021 planned. Date could potentially be pushed out Takarau Gorge Pavement repairs 21 September Stop/go traffic management. Day work. Day work. Letter drop provided to Road, Rural to 28 Reduced speed limit residents/businesses, major engagement September 2021

Wellington City Council | 3 of 7 LOCATION TYPE OF WORK INDICATIVE TRAFFIC MANAGEMENT (unless noted, all OTHER INFORMATION DATES work is day work) planned. Date could potentially be pushed out Rajkot Terrace, Footpath and drainage 08 September Stop/go traffic management. Day work. Day work. Letter drop provided to Broadmeadows maintenance and road to 14 Reduced speed limit residents/businesses, major engagement repairs September 2021 planned. Date could potentially be pushed out Kanpur Drive, Footpath and drainage 02 September Stop/go traffic management. Day work. Day work. Letter drop provided to Broadmeadows maintenance and road to 07 Reduced speed limit residents/businesses, major engagement repairs September 2021 planned. Date could potentially be pushed out Elliot Street, Footpath and road 15 September Stop/go traffic management. Day work. Day work. Letter drop provided to Johnsonville repairs to 23 Reduced speed limit residents/businesses, major engagement September 2021 planned. Date could potentially be pushed out Alwyn Place, Footpath maintenance 02 September Stop/go traffic management. Day work. Day work. Letter drop provided to Newlands and road repairs to 08 Reduced speed limit residents/businesses, major engagement September 2021 planned. Date could potentially be pushed out Batchelor Street, Footpath and drainage 09 September Stop/go traffic management. Day work. Day work. Letter drop provided to Newlands maintenance and road to 05 October Reduced speed limit residents/businesses, major engagement repairs 2021 planned. Date could potentially be pushed out Mathieson Drainage repairs 07 September Stop/go traffic management. Day work. Day work. Letter drop provided to Avenue, to 10 Reduced speed limit residents/businesses, major engagement September 2021 planned. Date could potentially be pushed out

Wellington City Council | 4 of 7 LOCATION TYPE OF WORK INDICATIVE TRAFFIC MANAGEMENT (unless noted, all OTHER INFORMATION DATES work is day work) Hatton Street, Drainage repairs 13 September Stop/go traffic management. Day work. Day work. Letter drop provided to to 17 Reduced speed limit residents/businesses, major engagement September 2021 planned. Date could potentially be pushed out Karori Road, Footpath maintenance 20 September Stop/go traffic management. Day work. Day work. Letter drop provided to Karori and road repairs to 24 Reduced speed limit residents/businesses, major engagement September 2021 planned. Date could potentially be pushed out Onslow Road, Footpath, Kerb and 01 September Stop/go traffic management. Day work. Day work. Letter drop provided to Khandallah channel maintenance to 09 Reduced speed limit residents/businesses, major engagement and storm damage September 2021 planned. Date could potentially be pushed repairs out Benares Street, Footpath, Kerb and 10 September Stop/go traffic management. Day work. Day work. Letter drop provided to Khandallah channel maintenance to 15 Reduced speed limit residents/businesses, major engagement September 2021 planned. Date could potentially be pushed out Indus Street, Road repairs 16 September Stop/go traffic management. Day work. Day work. Letter drop provided to Khandallah 2021 Reduced speed limit residents/businesses, engagement planned. Date could potentially be pushed out Raumati Terrace, Road repairs 17 September Stop/go traffic management. Day work. Day work. Letter drop provided to Khandallah to 20 Reduced speed limit residents/businesses, engagement planned. September 2021 Date could potentially be pushed out Onslow Road, Drainage maintenance 21 September Stop/go traffic management. Day work. Day work. Letter drop provided to Khandallah and road repairs to 24 Reduced speed limit residents/businesses, engagement planned. September 2021 Date could potentially be pushed out

Wellington City Council | 5 of 7 LOCATION TYPE OF WORK INDICATIVE TRAFFIC MANAGEMENT (unless noted, all OTHER INFORMATION DATES work is day work) Cashmere Road repairs 27 September Stop/go traffic management. Day work. Day work. Letter drop provided to Avenue, to 30 Reduced speed limit residents/businesses, engagement planned. Khandallah Date could potentially be pushed out

How we determine what surface to use in each location https://wellington.govt.nz/services/parking-and-roads/road-works/maintenance-programmes/road-resealing/choosing-the-seal

Map of upcoming work for 2021/22 https://gis.wcc.govt.nz/LocalMaps/Viewer/?map=d322a03511294abcbe83a253b8700c02

Background information about resurfacing maintenance work across Wellington’s roading network https://wellington.govt.nz/services/parking-and-roads/road-works/maintenance-programmes/road-resealing

Information about surfacing, including technical definitions https://wellington.govt.nz/~/media/services/parking-and-roads/road-works/files/chip-seal-road-brochure.pdf?la=en

Definitions: Dig out – a repair to a small section of the road structure Pre-seal repairs – structural repairs to small sections of the road. We usually combine this with repairing or replacing sections of the pedestrian footpath, kerb and channel. This work is done two to three months before the surfacing work. This gives the road repairs time to settle and cure.

Wellington City Council | 6 of 7 Sump – road drain TTM – temporary Traffic Management TSL – Temporary Speed Limit

Wellington City Council | 7 of 7