PRE-FEASIBILITY REPORT

For

Enhancement of Production through Opencast Method of Mining in Gare Palma IV/4 Coal Mine of 1.5 MTPA Production Capacity in 885.525 ha Area

At

Village- Banjikhol, PO: Milupara, Tehsil ,

District- , State-

Project Proponent

Hindalco Industries Limited

.

Submitted to

Ministry of Environment Forest & Climate Change (MoEF&CC) New Delhi

July, 2019

Pre-Feasibility Report for Enhancement of Production through Opencast Method of Mining in Gare Palma IV/4 Coal Mine, Chhattisgarh

CONTENTS

Sr. No. Title Page no. 1 EXECUTIVE SUMMARY 3 2 INTRODUCTION OF THE PROJECT/BACK GROUND INFORMATION 4 3 PROJECT DESCRIPTION 8 4 SITE ANALYSIS 24 5 PLANNING BRIEF 29 6 PROPOSED INFRASTRUCTURE 30 7 REHABILITATION AND RESETTLEMENT (R&R) PLAN 31 8 PROJECT SCHEDULE & COST ESTIMATES 32 9 ANALYSIS OF PROPOSAL (FINAL RECOMMENDATIONS) 32

Tables

No. Title Page no. 1 CAPTIVE CONSUMPTION IN THE END USE PLANTS 4 2 DEMAND AND SUPPLY GAP 6 BOUNDARY COORDIANTES OF GARE PALMA IV/4 COAL MINE 8 3 4 STRATIGRAPHIC SUCCESSION IN 13 5 COAL SEAM SEQUENCE IN GARE PALMA IV/4 BLOCK 15 6 SCHEDULE FOR COAL PRODUCTION AND OVERBURDEN REMOVAL 17 7 DETAIL QUALITY OF THE SEAMS 20 8 QUALITY OF WASTES – TO BE GENERATED AND SCHEME OF 22 MANAGEMENT AND DISPOSAL 9 LAND USE PATTERN AT THE END OF MINE LIFE AND POST 24 CLOSURE 10 LAND DETAILS OF THE GARE PALMA IV/4 COAL BLOCK 25 11 NEAREST WATER BODIES 26 12 NEAREST FOREST BLOCK WITHIN 10 KM RADIUS 26 13 CLIMATOLOGICAL DATA STATION: IMD, RAIGARH 28

Figures

No. Title Page no. 1 LOCATION MAP OF GARE PALMA IV/4 COAL MINE (INDEX MINE) 9 2 GOOGLE MAP-COORDINATES OF BOUNDARY POINTS OF GP IV/4 10 3 STUDY AREA MAP 10 KM RADIUS OF GARE PALMA IV/4 COAL 11 BLOCKS 4 ULTIMATE PIT CONFIGURATION PLAN 19 5 FLOW DIAGRAM SHOWING THE SCHEMATIC OPERATION OF OB & 23 COAL EXCAVATION Annexure I Mine Plan Applied for Approval vide Lr No HIL/GP-IV/4/Mine 33 Plan/2019-20/234 dated 31st May,2019 II Existing Environmental Clearance of 1 MTPA 34 III Transfer of EC 44 IV Amendment of EC 48

VIMTA Labs Limited, Hyderabad 2 Pre-Feasibility Report for Enhancement of Production through Opencast Method of Mining in Gare Palma IV/4 Coal Mine, Chhattisgarh

1.0 EXECUTIVE SUMMARY

Sr. No. Description Details 1 Name of the Project Gare Palma IV/4 Coal Mine Total land requirement for 2 885.525 ha the project 27.16 million tonnes [(Open cast- 3 Mineable reserves 24.35 MT+ UG-2.81 MT)] 4 Total overburden generation 220.52 million m3 5 Quantity of external dump 85.98 million m3 6 Quantity of internal dump 134.54 million m3 228.25 ha (including top soil 7 Total External dump area dump) 8 Top soil thickness 1.0-18 m Average stripping ratio (coal : 9 1: 10.14 overburden) Opencast mining by shovel- 10 Method of mining dumper 11 Ultimate depth 96 m bgl 12 Maximum production capacity 1.5 MTPA 13 Expected life of mine 18 years 14 Working hours 3 shift per day 15 Quarry floor area 324.14 ha 16 Quarry surface area 359.50 ha 17 Number of seams/sections Total 6 Nos of coal seams 18 Average seam gradient 20 to 50 19 Maximum bench height 6 m Minimum width is twice the height 20 Bench width of bench 21 Water requirement (Mine) 562 m3/day 1.5 MVA of power is required for 22 Power requirement & source the mine and is sourced from 33 kV Dolnara Substation of CGPDL. 23 Manpower requirement 945 nos It is a running mine and R & R is done as per the Adarsh Chhattisgarh Punarvas Niti 2007 & The Right to Fair Compensation 24 Rehabilitation and Resettlement and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013. The Rehabilitation Action Plan has been approved by State Government.

VIMTA Labs Limited, Hyderabad 3 Pre-Feasibility Report for Enhancement of Production through Opencast Method of Mining in Gare Palma IV/4 Coal Mine, Chhattisgarh

2.0 INTRODUCTION OF THE PROJECT/ BACKGROUND INFORMATION

2.1 Identification of Project and Project Proponent

Gare Palma IV/4 coal block was earlier allotted to M/s Jayaswal Neco Ltd. for captive coal mining. Hon’ble Supreme Court vide judgment dated 25th August 2014 read with its order dated 24th September 2014 cancelled the allotments of 204 coal blocks including Gare-Palma IV/4. In pursuance of the provisions of The Coal Mines (Special Provisions) Second Ordinance 2014 this coal mine was earmarked for non- regulated sector and was put on E-auction in which M/S Hindalco Industries Ltd. was the Successful Bidder. Accordingly, this Coal Mine has vested in M/S Hindalco Industries Ltd. with effect from 1st April 2015 vide Vesting Order under Clause (b) of sub rule 2 of rule 7 and sub-rule 1 of rule 13 Order No. 104/16/2015/NA dated 23rd March 2015.

Hindalco Industries Limited, metals flagship company of the Aditya Birla Group, is the industry leader in aluminium and copper. With a consolidated turnover of US$18 billion, Hindalco is the world’s largest aluminium rolling company and one of Asia’s biggest producers of primary aluminium. Its state-of-art copper facility comprises a world-class copper smelter and a fertiliser plant along with a captive jetty. The copper smelter is among the world’s largest custom smelters at a single location. In , the company’s aluminium units across the country encompass the gamut of operations from bauxite mining, alumina refining, coal mining, captive power plants and aluminium smelting to downstream rolling, extrusions and foils. Today, Hindalco ranks among the global aluminium majors as an integrated producer and a footprint in 10 countries outside India.

Hindalco has been accorded Star Trading House status in India. Its aluminium is accepted for delivery under the High-Grade Aluminium Contract on the London Metal Exchange (LME), while its copper quality is also registered on the LME with Grade A accreditation.

2.2 Brief Description of Nature of the Project

The Gare Palma IV/4 Opencast Coal mine of 1.5 MTPA capacity is a captive coal mine of HINDALCO. As per the Vesting Order, the coal of this mine is to be used for captive consumption in the end use plants as described in Table–1.

TABLE–1 CAPTIVE CONSUMPTION IN THE END USE PLANTS

Sr. Name of Specified Address Configuration Capacity No. End use Plant 1 Captive power plant of Lapanga 6X 150 MW 900 MW Aditya Aluminium Dist. Sambalpur Project 2 Captive power plant Hirakud 4X 100 MW 467.5 MW Of Hirakud complex Dist. Sambalpur 1X 67.5 MW Odisha

VIMTA Labs Limited, Hyderabad 4 Pre-Feasibility Report for Enhancement of Production through Opencast Method of Mining in Gare Palma IV/4 Coal Mine, Chhattisgarh

The Gare Palma IV/4 opencast coal mine has an area of about 885.525 ha and situated in the eastern part of Gare Palma Coalfield. It is a running mine having production capacity of 1MTPA [(OC-0.56+ UG-0.44 MTPA)] presently. Revised Mining Plan (including Mine Closure Plan) for Gare Palma IV/4 Coal Block (4th Revision) has been prepared based on geological report namely “Geological Note on Detailed Coal Exploration in Gare Palma IV/4 Block, Mand Raigarh Coalfield, ., Chhattisgarh state”, August 2018 prepared by South West Pinnacle Limited and “Geological Report on Detailed Coal Exploration in Gare Palma IV/4 & IV/5 (Integrated), Mand Raigarh Coalfield, Raigarh District., Chhattisgarh state”, December 2017 prepared by South West Pinnacle Limited. It has been prepared based on the fresh exploration undertaken by M/s Hindalco Industries Limited.

Net Available Geological Reserves has been estimated as 64.955 Million Ton. The Revised Mining Plan (including Mine Closure Plan) for Gare Palma IV/4 Coal Block (4th Revision) has been prepared for switching to total mechanised opencast mining from the present mix of underground mining and opencast mining method with the following assumptions:

i. To maintain the production programme for first three years as per the approved Revised Mining Plan & Mine Closure Plan (3rd Revision) of Gare Palma IV/4 Coal Mine i.e. 0.44 MTPA by underground production and 0.56 MTPA by opencast mining; ii. To convert the entire mining operation to opencast mining in fourth and fifth year; and iii. To increase the annual production from 1.0 MTPA to 1.5 MTPA in the fifth year and then to maintain 1.5 MTPA as the target/peak annual production rate.

2.3 Need for the Project

Revision of the Approved 3rd Revision of Mining Plan of Gare Palma IV/4, August 2018 has been necessary for the following reasons:

1. After analyzing the information for location of historical boreholes w.r.t revised block boundary as per certification of CMPDI, chemical analysis data, geophysical data, seam data co-relation with the surrounding new boreholes and underground and opencast mine working, etc. 74 boreholes have been shortlisted for the preparation of the “Geological Note on Detailed Coal Exploration in Gare Palma IV/4 Block, Mand Raigarh Coalfield, Raigarh District., Chhattisgarh state”, August 2018 prepared by South West Pinnacle Limited and “Geological Report on Detailed Coal Exploration in Gare Palma IV/4 & IV/5 (Integrated), Mand Raigarh Coalfield, Raigarh District., Chhattisgarh state”, December 2017 prepared by South West Pinnacle Limited. Seams I, L1, L2, II, IIT, IIB, III, IV and V have been considered in this report and the estimated Net Geological Reserve considered in the 4th revision has been increased to 64.955 Mt (which includes the Reserve already depleted till 31.03.2018). This Revised Mining Plan (including Mine Closure Plan) for Gare Palma IV/4 Coal Block (4th Revision) has been prepared based on the above Geological Note, August 2018. The mining plan is applied for approval vide Lr No HIL/GP-IV/4/Mine Plan/2019- 20/234 dated 31st May, 2019 and enclosed as Annexure-I. The existing EC,

VIMTA Labs Limited, Hyderabad 5 Pre-Feasibility Report for Enhancement of Production through Opencast Method of Mining in Gare Palma IV/4 Coal Mine, Chhattisgarh

transfer of EC & its amendment are enclosed as Annexure–II, Annexure–III & Annexure–IV respectively.

2. It is a running mine and the underground mining operations through developments of seams II and III have been completed. Only depillaring can be done to continue the production of underground mining. It will be difficult to match the rated production capacity in this case. Multiplicity of seams will stand in the way except by stowing for which adequate stowing material is not available. Extraction Percentage of the reserves will also be less by underground method of mining compared to the opencast method.

3. It has been found that the stripping ratio and other conditions are favorable to convert the entire mining operations upto the Bendra Nala (flowing to the south) to opencast mining and it will be safer and will yield higher extraction percentage.

Hence, the Revised Mining Plan (including Mine Closure Plan) for Gare Palma IV/4 Coal Block (4th Revision) has been planned for complete opencast mining operations except for initial three years in which both opencast and underground working has been considered same as earlier approved 3rd Revision of Mining Plan of Gare Palma IV/4. The total extractable coal has increased to 23.06 Mt which is almost double of the extractable reserve 12.71 Mt planned earlier in 3rd revision. The annual production target has been increased to 1.5 MTPA against 1 MTPA in earlier 3rd revision and mine life has increased to 18 years compared to 13 years earlier.

2.4 Demand-Supply Gap

The coal of this project is meant for captive used for linked EUP and the requirement of coal for this project is as below (w.r.t. 3rd revision of Mining Plan). The demand and supply gap is tabulated in Table-2.

TABLE -2 DEMAND AND SUPPLY GAP

Parameters Details Blast Observation Clinker "MTPA" Power Plant "kW" Furnace "MTPA" Capacity of the end - - Aditya: Hirakud: - - - use plant 900 MW 467.5 MW Capacity of the Project - - 1 MTPA - - - - "MTPA" Raw Coal availability - - 1 MTPA - - - - from this project "MTPA" Washed coal ------availability "MTPA" Reject "MTPA" ------Station Heat Rate "K - - 2615 2637 - - - Cal/Kwhr Avg Calorific Value of ------Coal "Kcal/Kg" Raw coal - - 4600 4600 - - - Washed coal ------VIMTA Labs Limited, Hyderabad 6 Pre-Feasibility Report for Enhancement of Production through Opencast Method of Mining in Gare Palma IV/4 Coal Mine, Chhattisgarh

Parameters Details Blast Observation Clinker "MTPA" Power Plant "kW" Furnace "MTPA" Reject "MTPA" ------Specific consumption - - 0.568 - - - - "Kg/Kwhr" Consumption Norm - - NA - - - - (Kg/Tonne) Plant Load Factor/ - - 85% - - - - Capacity Utilization Coal Requirement - - 3.81 - - - - "MTPA" Total Requirement for - - 5.81 - - - - the End Use Plants "MTPA"

All numbers have been calculated at G9 grade as per the MSTC detail for the said coal block

Proposed modification in requirement as per the 4th Revision of Mining Plan.

Source of coal requirement Coal from this project "MTPA" 1.5 Linkages/ E-auction from CIL/open market "MTPA" 3.31 Other block of the Company "MTPA" 1.10 Total availability "MTPA" 5.81

2.5 Import vs. Indigenous Production

There will not be any import for the proposed open cast mining of Gare Palma IV/4 coal mine.

2.6 Export Possibility

The coal will not be exported from the proposed open cast mining of Gare Palma IV/4 coal mine.

2.7 Domestic / export Markets

Gare Palma IV/4 open cast coal mine has been vested in M/s Hindalco Industries Ltd. with effect from 1st April 2015 vide Vesting Order, under Clause (b) of sub rule 2 of rule 7 and sub-rule 1 of rule 13 Order No. 104/16/2015/NA dated 23rd March 2015. As per the vesting order, coal from this mine is used for captive consumption in the captive power plant of Aditya Alumina projects at Lapanga and Hindalco complex, Hirakud, Odisha.

2.8 Employment Generation (Direct and Indirect) due to the project About 945 persons will get direct employment in various services. Direct and indirect employment avenues will be created due to this project and the project proponents would contribute effectively to improvement in educational, medical and communication facilities which would improve the living conditions of the people.

VIMTA Labs Limited, Hyderabad 7 Pre-Feasibility Report for Enhancement of Production through Opencast Method of Mining in Gare Palma IV/4 Coal Mine, Chhattisgarh

3.0 PROJECT DESCRIPTION

3.1 Type of project including interlinked and interdependent projects, if any.

Gare Palma IV/4 open cast coal mine of 1.5 MTPA of capacity is the captive coal mine of Hindalco Industries Ltd and as per the vesting coal from this mine is used for captive consumption in the captive power plant of Aditya Alumina projects Lapanga and Hindalco complex, Hirakud, Odisha.

3.2 Location

The Gare Palma IV/4 open cast mine is located at about 55 km from district HQ Raigarh in village Banjikhol in Tamnar tehsil of Raigarh District. of Chhattisgarh State. The block is covered in the Survey of India Topo sheet No. 64 N/8 & 64 N/12. The boundary coordinates of Gare Palma IV/4 Coal Mine is given in Table-3.

TABLE–3 BOUNDARY COORDIANTES OF GARE PALMA IV/4 COAL MINE

Point Latitude Longitude A 22008’ 30.840” N 830 31’ 16.008” E B 220 10’ 20.850” N 830 32’ 37.378” E C 220 10’ 3.844” N 830 33’ 37.747” E D 22008’3.332” N 830 32’ 13.979” E E 22007’ 40.125” N 830 32’ 10.659” E

The index map, google map and study area map (10 km buffer) are presented in Figures–1 to Figure-3 respectively.

VIMTA Labs Limited, Hyderabad 8 Pre-Feasibility Report for Enhancement of Production through Opencast Method of Mining in Gare Palma IV/4 Coal Mine, Chhattisgarh

IV/4 Block ML Boundary Location

FIGURE–1 LOCATION MAP OF GARE PALMA IV/4 COAL MINE (INDEX MINE)

VIMTA Labs Limited, Hyderabad 9 Pre-Feasibility Report for Enhancement of Production through Opencast Method of Mining in Gare Palma IV/4 Coal Mine, Chhattisgarh

Boundary co-ordinates of Gare Palma IV/4 Coal Mine

Point Latitude Longitude A 22008’ 30.840” N 830 31’ 16.008” E B 220 10’ 20.850” N 830 32’ 37.378” E C 220 10’ 3.844” N 830 33’ 37.747” E D 22008’ 3.332” N 830 32’ 13.979” E E 22007’ 40.125” N 830 32’ 10.659” E

FIGURE–2 GOOGLE MAP-COORDINATES OF BOUNDARY POINTS OF GP IV/4

VIMTA Labs Limited, Hyderabad 10 Pre-Feasibility Report for Enhancement of Production through Opencast Method of Mining in Gare Palma IV/4 Coal Mine, Chhattisgarh

FIGURE-3 STUDY AREA MAP 10 KM RADIUS OF GARE PALMA IV/4 COAL BLOCKS

VIMTA Labs Limited, Hyderabad 11 Pre-Feasibility Report for Enhancement of Production through Opencast Method of Mining in Gare Palma IV/4 Coal Mine, Chhattisgarh

3.3 Details of Alternate sites considered and the basis of selecting sites, particularly the environmental the proposed gone into should be highlighted.

No alternative site for this project could be envisaged. As mining in coal block area is due to site specific location of deposition of coal deposit.

3.4 Size or Magnitude of Operation

Hindalco is proposing opencast mining of 1.5 MTPA capacity at Gare Palma IV/4 coal mine in Mand Raigarh Coal Field, Raigarh district to meet partial requirement for its captive power plant Aditya Alumina of 900 MW (6x150 MW) capacity located at Lapanga and Power plant of Hirakud Complex of capacity 467.5 MW (4x100 MW +1x67.5 MW) located at Hirakud in Odisha. The net extractable reserve is 23.06 MT and the life of the mine will be 18 years.

3.5 Project Description with Process Details

3.5.1 Physiography

Physiographically, the block IV/4 can be divided into the hilly terrain covered by Forest in the north-central and eastern part and relatively plain country north and south of it. The area is traversed by the southwest-northeast trending Dumar nala in the north and Bendra nala in the south. Kelo River is the main drainage in the area and flows in west of the adjacent Gare Palma IV/5 coal block.

The elevation of the area north of the hilly terrain varies between 268 m and 330 m whereas the hill rises upto 432 m above mean sea level. Southern part of area is depicted by rolling topography. The area immediate to the south of terrain is more or less plain with gentle slope towards southeast and the elevation ranges between 264 m and 290 m. The area south of Bendra nallah is represented by a rolling topography with ground elevation ranging between 267 m and 301 m and this part is mostly covered by forest. Isolated hillocks of lesser magnitude are also evident in the west central part. The drainage of the sub block is controlled by Kelo River that flows in WNW of the adjacent Gare Palma IV/5 coal block. Dumar and Bendra nalas collect water from slopes of the terrain and discharge into Kelo River. Water from Kelo River is finally discharged into River.

3.5.2 Regional Geology

Gare Palma IV/4 coal block form a part of Mand Raigarh coal field. Mand Raigarh Coalfield is located in Raigarh district in Chhattisgarh state. It lies in the valley of the , a tributary of the Mahanadi. The Mand Raigarh Coalfield covers an area of about 900 sq. km in the north-westerly continuity of the Coalfield of Odisha. Mand Raigarh Coalfield includes the areas earlier known as North Raigarh, South Raigarh and Mand River Coalfields. Of at least twelve seams in the Mand Valley, the Mand and Taraimar seams are important.

The Coalfield is a part of the extensive spread of Gondwana Formations, extending from Hasdeo - Arand Coalfield through Raigarh basin to Ib River Coalfield to the south-east in the Sambalpur district of Odisha. The is also a western

VIMTA Labs Limited, Hyderabad 12 Pre-Feasibility Report for Enhancement of Production through Opencast Method of Mining in Gare Palma IV/4 Coal Mine, Chhattisgarh

extension of the Mand River Coalfield. A large part of the intervening terrain in between these coalfields is covered by Kamthi sediments. The field has a potential for mining of power grade coal, much of which can be extracted through open cast mining. Gare block has been identified for captive mining by private companies.

The Mand Raigarh Basin stretches between Latitudes 21 45’ & 22 42’ and Longitudes 83 01’ & 83 44’ extending over an area of about 900 sq km in the ⁰ ⁰ Raigarh district of Chhattisgarh State. The stratigraphic succession in Mand Raigarh ⁰ ⁰ coalfield as a whole is furnished in Table–4.

TABLE–4 STRATIGRAPHIC SUCCESSION IN MAND RAIGARH COALFIELD

Group Formation Description of Lithology Thickness Range (m) Recent / Sub- Soil \ Sandy soil & laterite Recent Alluvium

------Unconformity ------Lower to Kamthi Coarse to pebbly to medium grained 250 Middle Triassic sandstones and red clay

------Unconformity ------Upper Permian Raniganj Fine to coarse grained sandstone, 150 – 200 siltstone, grey shale, carbonaceous shale and thin coal seams. Middle Permian Barren Grey to black shale, fine to medium 250 – 300 Measures grained sandstone and their alterations.

Lower Permian Barakar Coarse, pebbly to conglomeratic 350 - 500 sandstone, grey shale and coal seams. Upper Talchir Siltstones, rhythmites, sandstones, Few metres to Carboniferous conglomerates tillites and green to 150 khaki greento yellow colour splintery shale. ------Unconformity ------Faulted Contact ------Pre-cambrian Chhattisgarh Quartzite, hard fgd sandstone, limestone ------Unconformity ------Archaens Basement Granite gneisses, mica schists, quartzites intruded by pegmatite and quartz veins *Source: GSI (1988)

The geological formations in the Mand Raigarh Coalfield as described by GSI are presented below:

Archaeans: The Archaeans occur along the northern as well as southern boundaries of coalfield and are represented by garnetiferous granite gneisses, mica schists, & pegmatites. These are exposed to the north-east of Dharamjaygarh. The contact

VIMTA Labs Limited, Hyderabad 13 Pre-Feasibility Report for Enhancement of Production through Opencast Method of Mining in Gare Palma IV/4 Coal Mine, Chhattisgarh

with Talchir is observed in Konja nala and in the east of Dharamjaygarh (GSI, 1984).

Chhattisgarh Formation: Achaeans are overlain by Chattisgarh Formation represented by quartzites and phyliites. These are ferruginous at places and found to be forming hill ranges in the southern part of the coalfield.

Talchir Formation: Exposures of Talchir Formation are found in the northern part of Dharamjaygarh- Khargaon area. In this part, the maximum thickness of Talchir is about 40 m and it is represented by boulder bed, grey to greenish grey shale, fine to medium grained sandstone and siltstone. Borehole information reveals that the thickness of Talchir formation is not less than 162 m (ref- GSI Borehole no MRK-5). The Talchirs are not contiguous and pinch out strike-wise. Metamorphics are in direct contact with the Barakars at many places.

Barakar Formation: Barakar is a major coal bearing formation in the coalfield which overlies conformably with gradational contact. Most of the area of Barakar formation is covered by forest and alluvium with limited exposure of the formational rocks in nallas and river sections. Total thickness of this formation in northern part is 706 to 840 m (Kamar Guru et al 1980) while that in the southern part as in Chhal is about 950 m (GSI Borehole no. MRC-1 & MRC-5). The major rocks are mainly sandstone with subordinate shale, frequently interbanded with carbonaceous shales and coal seams. The sandstones are poorly sorted, white to greyish white in color. The fine grained sandstones are micaceous while coarse grained are massive and arkosic. On the basis of gross lithological attributes (GSI 1989), the formation has been sub divided as: Lower, Middle and Upper members. The middle member is more argillaceous and the lower & upper members are more arenaceous. Only the lower and upper members are present in Gare area (GSI, 1992).

Barren Measure Formation: Barakar formation is conformably overlain by Barren Measure formation comprising of greyish black to black shale and fine to medium grained sandstone. Argillaceous facies is predominant over arenaceous facies in this formation and frequently occurs as thick alternation with the latter. The thickness of this formation is about 250 to 300 m.

Raniganj Formation: Raniganj formation conformably overlies Barren Measure Formation. With gradational contact. Major lithologies in this formation are fine to coarse grained sandstone, siltstone, grey shale, carbonaceous shale and thin coal seams. The formation has scanty exposure and mostly covered by alluvium.

Kamthi Formation: Kamthi formation lies unconformably overlies Raniganj Formation and occurs as NW-SE running linear patch in central and south-eastern part of the coalfield. These form hill range in many places. The major lithologies are coarse to pebbly sandstone with red clay bands. The sandstones are highly ferruginous and cross bedded. Total thickness of Kampthi formation is about 250 m.

Igneous Intrusives: Occurrence of several dykes stretching from 6 to 26.5 kms, Sills and flows have been noted in the northern part of the coalfield. The basic rocks are fine grained basalts to coarse grained gabbroid types.

VIMTA Labs Limited, Hyderabad 14 Pre-Feasibility Report for Enhancement of Production through Opencast Method of Mining in Gare Palma IV/4 Coal Mine, Chhattisgarh

Coal Seams:

12 coal seams designated as XII and below occur in Barakar formations in the area. The younger seams i.e., IV and above are generally high moisture and high ash (Grade E to G) power coal, whereas seams III, II & I are likely to contain superior grade coals (Grade A-D). The coalfield is likely to contain over 500 million tonnes of superior grade coal which could be utilized as such or after beneficiation for sponge iron production.

As per inventory of Geological Resources of Indian coal (as on 1st April,2018) prepared by the GSI, Mand-Raigarh Coalfield contains 30249.41 million tonnes of coal reserves up to a depth of 1200 m.

3.5.3 Geo Mining Characteristics

 Strike & Dip

The Barakar Formations occupies the Gare Palma IV/4 block; with sub-horizontal beds having more or less NW-SE strike of beds and the dip usually varying between 2° and 5° towards the south-west.

3.5.4 Seam Description

Description of Coal Seams

Four prominent coal seams viz. II, III, IV & V and 2 local seams viz. L1 & L2, are found developed in the block. The details of Coal Seam Sequence in Gare Palma IV/4 Block are tabulated in Table–5.

TABLE–5 COAL SEAM SEQUENCE IN GARE PALMA IV/4 BLOCK

Seam Description The seam occurs within the depth range of 8.72 m to 52.81 m. Seam V occurs as a cluster of 4 thin splits viz. V1, V2, V3 and V4. Ex-band thickness of Seam V V ranges between 0.52 m (HSG4-50) and 11.50 m (HSG4-42). The net geological reserves within the seam is 3.385 MT (on I100 basis). The grade of the seam (I- 100 basis) varies from G9 – G14. Occurs as composite seam in the block below seam V. The seam occurs within the depth range of 14.65 m to 86.12 m. Seam IV thickness ranges between 0.66m (HSG4-46) & 2.69m (HSG4-37); and general thickness range is between 1.40 m IV & 2.40 m. The net geological reserves within the seam is 5.983 MT (on I100 basis). The grade of the seam (I-100 basis) varies from G7 - G11 (GCV: 4089 – 5248 kCal/kg). It is the most prominent seam in the block, occurs as composite seam. The seam occurs within the depth range of 19.15 m to 149.20 m. Thickness ranges between 0.15 m (NCM-10) and 6.10 m (HSG4-26); and the general thickness range is III between 1.10 m and 5.00 m. The net geological reserves within the seam is 29.435 MT (on I100 basis). The grade of the seam (I-100 basis) varies from G3 - G14 (GCV : 3366 – 6446 kCal/kg). Second most prominent seam in the block; occurs as composite seam in major II part of IV/5; splits in to distinct II-Top and II-Bottom in northern and north-

VIMTA Labs Limited, Hyderabad 15 Pre-Feasibility Report for Enhancement of Production through Opencast Method of Mining in Gare Palma IV/4 Coal Mine, Chhattisgarh

Seam Description eastern parts of the Gare Palma IV/4. The seam occurs within the depth range of 71.91 m to 190.50 m (NCM-10) Seam II thickness ranges between 0.31 m (HSG4-44) and 8.47 m (HSG4-39); and the general thickness range is between 1.50 m and 7.50 m. The net geological reserves within the seam is 6.183 MT (on I100 basis). The grade of the seam (I-100 basis) varies from G3 - G13 (GCV : 3551 – 6520 kCal/kg). local seam in northern part of block; occurs below seam II & II-Bottom; The seam occurs within the depth range of 40.59 m (HSG4-51) to 52.45 m & the general thickness range is between 1.10 m and 1.50 m considered in reserves L2 estimation. The net geological reserves within the seam is 0.103 MT (on I100 basis). The grade of the seam (I-100 basis) varies from G3 – G9 (GCV : 4615 – 6670 kCal/kg). Local seam in central western & north-western parts; occurs above seam I: The seam occurs within the depth range of 34.90 m (NCM-14) to 51.56 m. Seam L1 thickness ranges between 0.50 m (HSG4-08) and 1.56 m (NCM-14); and the L1 general thickness range is between 0.60 m and 1.30 m considered in reserves estimation. The net geological reserves within the seam is 0.263 MT (on I100 basis).

3.5.5 Production Capacity & Calendar Programme

Gare Palma IV/4 has been an operational mine and currently the coal is being taken out by both opencast as well as underground mining method. The 3rd revision of Mining Plan of Gare Palma IV/4, August 2018 has been approved vide letter No. 34011/04/2018 (CPAM) dated 13.12.18 for rated capacity of 1.0 MTPA out of which productions by opencast is 0.56 MTPA and by underground is 0.44 MTPA.

It has been proposed in this Revised Mining Plan (including Mine Closure Plan) for Gare Palma IV/4 Coal Block (4th revision) to continue the production programme as per that proposed in the latest approved 3rd Revision of the Mining plan, August 2018. Accordingly, mining operations will be both by opencast and underground method till first three years. The underground mining will include depillaring of seams III and II which have already been developed. Opencast is being done in two sections namely North pit and South pit as these are existing in north and south of Dumar Nala. The 1st and 3rd year stage plans have thus been reproduced as proposed in 3rd Revision of the mining plan, August 2018. The mining plan is applied for approval vide Lr No HIL/GP-IV/4/Mine Plan/2019-20/234 dated 31st May 2019 enclosed as Annexure–1.

The 4th and 5th years will be the conversion years of underground operations to opencast mining. Mining operations will be ceased by underground method in 4th year.

In the north pit dismantling of all the underground infrastructures and inclines will take place. The North pit opencast operations which is concentrated towards the eastern side will now be advancing towards the Western side. The split seam II Top is the base seam till the workable seam thickness of II Bottom is obtained as the mine progresses towards the western side. North pit will be exhausted by the end of 5th year.

VIMTA Labs Limited, Hyderabad 16 Pre-Feasibility Report for Enhancement of Production through Opencast Method of Mining in Gare Palma IV/4 Coal Mine, Chhattisgarh

In the south pit opencast mining operations will be advancing towards both western side as well as southern side towards Bendra Nala in the 5th year of mine life. From 6th years onwards the opencast mining operations will be concentrated fully in the South pit. The mining operations initially be on seam III floor as other seams are not developed in this region. The bottom seam II is encountered in the 7th year and the mining operations goes down to the floor of seam II. The mining operations will be advancing to reach the final opencast mine boundary both in the southern side upto the safe distance from the Bendra Nala and also to attain the final shape in the western side. After reaching the final shape in southern boundary and corresponding western boundary the operations will be advancing towards the northern side.

Total extractable reserve has been estimated as 23.06 Mt. Out of this 21.74 Mt is by opencast mining and 1.32 Mt is by underground mining operations. Corresponding to 21.74 Mt of opencast coal extraction, 220.52 Mcum of overburden removal has been estimated. The average stripping ratio of the opencast mine is 10.14 cum/t. The production schedule for coal production and overburden removal is shown in the following Table-6. TABLE–6 SCHEDULE FOR COAL PRODUCTION AND OVERBURDEN REMOVAL

Production Calendar Coal OB Stripping Ratio Cummu- Year Year UG Annual OC Annual Total Annual lative Annual Cum Annual Average Mt Mt Mt Mt MCum MCum cum/t cum/t 1 18-19 0.44 0.56 1.0 1 4.49 4.49 8.02 8.02 2 19-20 0.44 0.56 1.0 2 4.49 8.98 8.02 8.02 3 20-21 0.44 0.56 1.0 3 4.73 13.71 8.45 8.16 4 21-22 0 1.0 1.0 4 9 22.71 9.00 8.47 5 22-23 0 1.0 1.0 5 13 35.71 13.00 9.70 6 23-24 0 1.5 1.5 6.5 17 52.71 11.33 10.18 7 24-25 0 1.5 1.5 8.0 20 72.71 13.33 10.89 8 25-26 0 1.5 1.5 9.5 20 92.71 13.33 11.34 9 26-27 0 1.5 1.5 11.0 20 112.71 13.33 11.65 10 27-28 0 1.5 1.5 12.5 20 132.71 13.33 11.87 11 28-29 0 1.5 1.5 14.0 20 152.71 13.33 12.05 12 29-30 0 1.5 1.5 15.5 13 165.71 8.67 11.69 13 30-31 0 1.5 1.5 17.0 13 178.71 8.67 11.40 14 31-32 0 1.5 1.5 18.5 13 191.71 8.67 11.16 15 32-33 0 1.5 1.5 20.0 13 204.71 8.67 10.96 16 33-34 0 1.5 1.5 21.5 10 214.71 6.67 10.64 17 34-35 0 1.5 1.5 23.0 5 219.71 3.33 10.14 18 35-36 0 0.06 0.06 23.06 0.81 220.52 13.50 10.14 Total 1.32 21.74 23.06 220.52 10.14

3.5.6 Geological & Mining Characteristics

In Gare Palma IV/4 block, there are seven seams namely Seam V, IV, III, II, L2, L1 and I. Seam II is splitted into II Top and II Bottom seams in the north side of fault F3-F3’. Seams III, II, II Top and II Bottom seams are workable seams in the area above Bendra Nala. Seam L2 & L1 and Seam I are developed in only limited areas in the block north of Domar Nala but are inaccessible for mining due to depth and VIMTA Labs Limited, Hyderabad 17 Pre-Feasibility Report for Enhancement of Production through Opencast Method of Mining in Gare Palma IV/4 Coal Mine, Chhattisgarh

narrow width of the North Pit. Seam IV & V incrop in the area south of Bendra Nala. The major part of Seams lies under the existing dump of Gare Palma IV/2 coal mine. The area south of Bendra Nala has not been considered favorable for opencast mining as the stripping ratio goes beyond 1:20.

North and south pits have been proposed for expansion in order to take out the underground working after their operations cease at the time of starting of its conversion to opencast. The ultimate pit configuration plan is represented in Figure- 4.

The ultimate pit of north pit of the Gare Palma IV/4 mine has been delineated as follows:

East: Upto the existing eastern boundary of north pit West: Keeping 7.5 m from the block boundary North: Keeping 7.5 m from the block boundary, Upto a vertical cut-off stripping ratio of 10 and upto seam extent South: Keeping safe distance of 60 m from the Domar Nala.

The ultimate pit of south pit of the Gare Palma IV/4 mine has been delineated as follows:

East: Upto a vertical cut-off stripping ratio of 10 and upto seam extent West: Keeping 7.5 m from the block boundary North: Keeping safe distance of 60 m from the Dumar Nala South: Keeping safe distance of 60 m from the Bendra Nala.

3.5.7 Product–Mix Quality

Existing opencast mine has been working in two pits namely north pit which is in north of Dumar nala and south pit which is in south of Dumar Nala and will continue as such. In Gare Palma IV/4 block there are seven seams namely Seam V, IV, III, II, L2, L1 and I. Seam II is splitted into II Top and II Bottom seams in the north side of fault F3-F3’. Seams III, II, II Top and II Bottom seams are workable seams in the area above Bendra Nala. Seam L2 & L1 and Seam I are developed in only limited areas in the block north of Domar Nala but are inaccessible for mining due to depth and narrow width of the North Pit. Seam IV & V incrop in the area south of Bendra Nala. The major part of Seams lies under the existing dump of Gare Palma IV/2 coal mine. The area south of Bendra Nala has not been considered favorable for opencast mining as the stripping ratio goes beyond 1:20. So only seam III & seam II and seam IIT and II B is considered for mining and the detail quality of the seams is given in Table–7.

VIMTA Labs Limited, Hyderabad 18 Pre-Feasibility Report for Enhancement of Production through Opencast Method of Mining in Gare Palma IV/4 Coal Mine, Chhattisgarh

FIGURE-4 ULTIMATE PIT CONFIGURATION PLAN

VIMTA Labs Limited, Hyderabad 19 Pre-Feasibility Report for Enhancement of Production through Opencast Method of Mining in Gare Palma IV/4 Coal Mine, Chhattisgarh

TABLE-7 DETAIL QUALITY OF THE SEAMS

SEAM M % ASH% VM% FC% GCV in Grade (K Cal/Kg) III 2.2-7.1 16.1-49.8 19.4-32.7 27.5-48.3 3366-6446 G14-G3 II 2.9-6.9 13.7-44.8 17.0-30.3 34.2-53.7 3551-6520 G13-G3 II T 3.2-6.6 9.1-41.5 23.9-36.1 31.5-53.0 4057-6785 G11-G2 II B 2.2-6.1 8.6-45.6 20.9-34.3 29.9-52.5 3637-6942 G13-G2

3.5.8 Transportation of Coal

It is proposed that coal from the mine will be dispatched by road to its end use plant located at Aditya Alumina, Lapanga (130 km) & Hirakud (160 km) in Odisha in covered trucks. In future, a nearby upcoming railway siding may be used for loading and evacuation of coal.

3.6 Raw materials required along with estimated quantity, likely source, marketing area of final product/s, Mode of transport of raw material and finished product.

No raw material is required as this is a mining activity. Only explosive to blast coal & OB and diesel for transportation of vehicles, operation of HEMM and generators in case of Power failure. Coal dispatch will be continued as per prevailing system and the ROM coal produced from mine will be hauled by 40T rear dumper and will be stored at surface stock yard. The same will be loaded on dispatch trucks by pay loaders for dispatch to end use plants. A CHP system has been proposed at surface for receiving, crushing of coal up to (-) 100 mm size, conveying and loading into trucks. In future a nearby upcoming railway siding may be used for loading and evacuation of coal. A CHP system has been proposed at surface. Coal from hoppers, shall be loaded in to trucks through vibrating feeders / Hydraulic Gate provided below each hoppers. Coal will be transported at nearby siding for final loading into railway wagons for transportation up to consumer plant.

Coal will be finally loaded into railway wagon at nearby upcoming/proposed siding through mechanized loading system or transported to EUP (end use plant).

3.7 Resource Optimization/ Recycling and Reuse envisaged in the Project, if any, should be given.

Resources like explosives, diesel oil, machinery, land, power and water are fully optimized to minimize unnecessary losses during the process of excavation and supply of coal to the captive plant. The peak production capacity from mine will be 1.5 million tonnes per annum. The coal does not require beneficiation. The resources which are used in the mining will be recycled by various methods. Sludge generated from domestic wastewater treatment will be composted and used as manure. Used oil from HEMM & DG set, will be sold to the authorized vendors. The Mine seepage water collected at settling pits will be treated at ETP/RO and used for domestic

VIMTA Labs Limited, Hyderabad 20 Pre-Feasibility Report for Enhancement of Production through Opencast Method of Mining in Gare Palma IV/4 Coal Mine, Chhattisgarh

purposes such as dust suppression, mining activity, irrigation to surrounding villages.

3.8 Availability of Water its Source, Energy/ Power Requirement and Source

3.8.1 Power

Presently an underground coal mine is running in this block. To meet the power requirement of this mine one number 33/11/3.3 kV substation has been installed. Installed transformation capacity of this substation is 1 X 33/11, 5 MVA; 1 X 33/11, 6.3 MVA and 1 X 33/3.3, 5 MVA. This substation receives power at 33 kV from Dolnara Substation of CGPDL. Approximate distance of this substation from this block is around 8 km.

It is envisaged to develop an opencast coal project in this block which will subsume the existing underground mine, electrical load of the opencast project envisages mainly consists of pumps, CHP, workshop, colony, illumination system etc. All the shovels and excavators shall be diesel driven. It is estimated that total power demand for mining operation in this this block will be around 1.5 MVA.

To meet this demand, It is envisaged that existing power supply arrangement at 33 kV will be used to meet the power requirement of this project.

3.8.2 Water Supply & Sewerage

It is proposed that requirement of potable water requirement is met from the mine seepage water. The mine water is being stored in the mine pit for setlling and storage and later treated with latest Reverse Osmosis (R.O.) technology for which established RO plant of 7500 Litre per hour capacity, which is distributed for the use of mine staffs & workers and supplied to R & R colony. For supply of pure and clean drinking water tap has been provided in the R & R villages and small overhead tanks are also built-up.

3.9 Quantity of wastes to be generated and scheme for their Management/ Disposal

Solid Waste

Out of the total volume of OB estimated of 220.52 Mm3 top soil is 17.02 Cu.m. The mine have two pits the north pit north of Dumer nala and the south pit south of Dumer nala upto Bendra nala. In north pit most of the overburden material 12.69 Mcum will be accommodated inside the internal dump D5. However, a small overburden 0.23 Mcum which cannot be accommodated inside will be accommodated in the external dump D6 in the north-east of it flushing to the internal dump. The maximum RL of the dumps D5 and D6 will reach +320 m in North pit. The dump height is around 50 m above the ground level.

In the south pit opencast mining operations will be advancing towards both western side as well as southern side towards Bendra nala in the 5th year of mine life. Dumping of overburden will start in the internal dump D2. About 12.29 Mcum of overburden will be accommodated in the internal dump D2. Entire overburden

VIMTA Labs Limited, Hyderabad 21 Pre-Feasibility Report for Enhancement of Production through Opencast Method of Mining in Gare Palma IV/4 Coal Mine, Chhattisgarh

cannot be accommodated on top of the internal dump. So the external dumping will start towards the eastern side as well in dump D1. About 8.10 Mcum of overburden material will be accommodated in this external dump D1 till 5th year of mining operations. The dump RL will be +327 m RL.

Top soil from both the north and south pit will be used for reclamation purpose and excess will be stacked separately for reclamation purpose. An external dump space D3 has been allocated for accommodation of 2.4 Mcum Topsoil in south of Bendra nala.

Top soil from both the north and south pit will be used for reclamation purpose and excess will be stacked separately for reclamation purpose. An external dump space D3 has been allocated for accommodation of 2.4 Mcum topsoil in south of Bendra nala. The advancement of the south pit in 6th year towards its northern side will involve chopping of the western peak. It involves pre-stripping of large volume of overburden. Advancement till 10th year is crucial as the accommodation of very large quantity 119.79 Mcum of cumulative overburden is involved. Not much internal dumping space will not be created till such time. Only 34.04 Mcum overburden will be accommodated in internal dump D2 upto a maximum dumping height of 70 m (RL+340 m). External dumping space in dump D1 towards the eastern side flushing with the internal dump D2 is sufficient for accommodation of 35.85 Mcum overburden material only upto the maximum dumping height of 70 m (RL+340 m). Additional dumping space is needed to accommodate the balance overburden dump. It is required in the 7th year as shown in the below Table - 8.

TABLE -8 QUALITY OF WASTES – TO BE GENERATED AND SCHEME OF MANAGEMENT AND DISPOSAL

Produ- External Dump Internal Dump ction Calendar D3 Total Year Year D1 (Top Soil) D4 D6 Total D2 D5 Total Dump Mcum Mcum Mcum Mcum Mcum Mcum Mcum Mcum Mcum 1 18-19 0.00 2.49 2.00 4.49 4.49 2 19-20 0.00 2.49 2.00 4.49 4.49 3 20-21 0.00 2.73 2.00 4.73 4.73 4 21-22 4.00 1.20 5.20 0.80 3.00 3.80 9.00 5 22-23 4.10 1.20 0.23 5.53 3.78 3.69 7.47 13.00 6 23-24 15.05 15.05 1.95 1.95 17.00 7 24-25 12.70 2.35 15.05 4.95 4.95 20.00 8 25-26 15.05 15.05 4.95 4.95 20.00 9 26-27 15.05 15.05 4.95 4.95 20.00 10 27-28 15.05 15.05 4.95 4.95 20.00 11 28-29 0.00 20.00 20.00 20.00 12 29-30 0.00 13.00 13.00 13.00 13 30-31 0.00 13.00 13.00 13.00 14 31-32 0.00 13.00 13.00 13.00 15 32-33 0.00 13.00 13.00 13.00 16 33-34 0.00 10.00 10.00 10.00 17 34-35 0.00 5.00 5.00 5.00 18 35-36 0.00 0.81 0.81 0.81 Total 35.85 2.40 47.50 0.23 85.98 121.85 12.69 134.54 220.52

VIMTA Labs Limited, Hyderabad 22 Pre-Feasibility Report for Enhancement of Production through Opencast Method of Mining in Gare Palma IV/4 Coal Mine, Chhattisgarh

3.10 Schematic Representations of the Feasibility Drawing which give information of EIA purposed:

Flow diagram showing the schematic operation of OB & coal excavation which give information of EIA purpose is shown below Figure-5. These are the activities which are the source for pollution. The pollution will be mitigated effectively by adopting suitable control and mitigation measures.

Stacked in top soil dump & spread in pit dump for Soil excavation reclamation

Drilling, blasting and Stacked at external dump excavation and and in pit dumping transportation of OB

Drilling & blasting in coal After reclamation in inpit face for coal excavation dumping, plantation of & transportation the dump

Transported to CHP for

crushing and stacked at stockyard

Despatch to EUP in

covered truck

FIGURE-5 FLOW DIAGRAM SHOWING THE SCHEMATIC OPERATION OF OB & COAL EXCAVATION

VIMTA Labs Limited, Hyderabad 23 Pre-Feasibility Report for Enhancement of Production through Opencast Method of Mining in Gare Palma IV/4 Coal Mine, Chhattisgarh

4.0 SITE ANALYSIS

4.1 Connectivity

Gare Palma-IV/4 Block in Gare area of Mand Raigarh Coalfield falls under the Tamnar Tehsil, Raigarh district in Chhattisgarh state. This block is located in the south-eastern part of Mand Raigarh Coalfield, close to the Odisha State Border (Chhattisgarh State – Odisha State - 3.8 km, SE).

It is located about 15 km north east of the tehsil town of Tamnar and 55 km north- east of the district headquarter, Raigarh. The nearest railway station is Raigarh located in Howrah –Mumbai route.

b) Rail Link

The nearest railway station Raigarh is about 55 km (by road) away from the coal mine. Raigarh located in Howrah –Mumbai route.

c) Air Link

Raipur is the nearest airport to the coal mine, which is situated around 330 km from the mine site and connected by all-weather road. The newly opened Jharsuguda airport is about 145 km from the mine.

4.2 Land Details

The total requirement of land for Gare Palma IV/4 opencast coal mine of 1.5 MTPA capacity is 885.525 ha including 472.41 ha of forest land. The land lease hold area, village-wise forest land & Revenue land. The land details for mining and the land use pattern at the end of the mine life and post closure are given in Table–9 & Table- 10 respectively.

TABLE-9 LAND USE PATTERN AT THE END OF MINE LIFE AND POST CLOSURE

(Area in ha) Name of the Villages Type Land Category Total #Kondkel Banjikhol Beljor Dongamahua Non-tribal Pvt. Land 88.752 2.34 16.446 18.883 126.421 Revenue Tribal Pvt. Land 93.079 49.659 50.919 2.089 195.746 Land Govt. Land 14.031 61.637 9.78 5.5 90.948 Sub Total 195.862 113.636 77.145 26.472 413.115 Revenue Forest Land 30.831 0 16.387 7.377 54.595 671-789 (P) P.F. 118.03

666-785 (P) P.F. 106.63

657-776 (P) R.F. 74.086

Forest 658-777 (P) R.F. 24.867

Land 659-778 (P) R.F. 50.467

665-784 (P) R.F. 38.324

611-787 (P) R.F. 1.294

663-782 (P) R.F. 4.117

Sub Total 472.41

Grand Total (ha) 885.525 #Jaripatra part of Kondkel

VIMTA Labs Limited, Hyderabad 24 Pre-Feasibility Report for Enhancement of Production through Opencast Method of Mining in Gare Palma IV/4 Coal Mine, Chhattisgarh

TABLE-10 LAND DETAILS OF THE GARE PALMA IV/4 COAL BLOCK

Pre- Land use Post Post Mining (proposed) - Mining Closure ha (ha) (ha) Tenancy 322.167 Excavation Area 359.5 Govt Non- 90.948 Backfilled Area 238.68 Forest Forest Excavated Void 120.82 Reserve 193.155 Top Soil Dump External 15.68 15.68 Protected 224.66 External Dump 212.57 212.57 C-J-B-J 54.595 Infrastructure 10.44 10.44 Sub-Total 472.41 Safety / Rationalisation Zone 7.04 7.04 (Forest) Agricultural Plantation/Green Zone 55.28 55.28 72.76 Water body/ Diversion of 9.45 9.45 9.45 Nala/River/Canal Public/Comp Use 307.3 Other(Constrained and 75.45 75.45 2.84 inaccessible area) Forest land (return) 353.06 Undisturbed/ Mining Right 140.115 140.115 140.115 for UG Total (ha) 885.525 Total 885.525 885.525 885.525

4.3 Topography and Drainage

Physiographically, the block IV/4 can be divided into the hilly terrain covered by forest in the north-central and eastern part and relatively plain country north and south of it. The area is traversed by the southwest-northeast trending Dumar nala in the north and Bendra nala in the south. Kelo River is the main drainage in the area and flows in west of the adjacent Gare Palma IV/5 coal block.

The elevation of the area north of the hilly terrain varies between 268 m and 330 m whereas the hill rises upto 432 m above mean sea level. Southern part of area is depicted by rolling topography. The area immediate to the south of terrain is more or less plain with gentle slope towards southeast and the elevation ranges between 264 m and 290 m. The area south of Bendra nallah is represented by a rolling topography with ground elevation ranging between 267 m and 301 m and this part is mostly covered by forest. Isolated hillocks of lesser magnitude are also evident in the west central part.

The drainage of the sub block is controlled by Kelo River that flows in WNW of the adjacent Gare Palma IV/5 coal block. Dumar and Bendra nalas collect water from slopes of the terrain and discharge into Kelo River. Water from Kelo River is finally discharged into Mahanadi River.

The HFL of Kelo River near Milupara village is 264 m. There is no back water problem due to steep gradient of river and its side slopes.

VIMTA Labs Limited, Hyderabad 25 Pre-Feasibility Report for Enhancement of Production through Opencast Method of Mining in Gare Palma IV/4 Coal Mine, Chhattisgarh

4.4 Existing Land Use Pattern, Shortest Distances from the Periphery of the Project to periphery of the Forests, Water Bodies.

Gare Palma IV/4 coal mine cover an area of about 885.525 ha in four villages, namely Jaripatra part of Kondkel, Banjikhol, Beljhor & Dongamahua. The area exhibits a land use pattern that mainly consists of forest and agricultural land. Forest land is 472.41 ha (53.35%), Tenancy land 322.167 ha (36.38%) and govt non forest land 90.948 ha (10.27%). The land use plan and details for Gare Palma IV/4 coal mine are presented in Table-9 and Table-10 respectively.

Nearest Water bodies in the 10 km radius of the proposed coal mine are given in Table- 11. TABLE- 11 NEAREST WATER BODIES

Sr. No. Rivers & Nalas 1 Dumer nala Within ML area 2 Bendra nala Within ML area 3 Kelo river 1.2 km, WNW 4 Karanara nala 2.3 km, SW 5 Koledega nala 6.3 km, S 6 Basundra nadi 10.4 km, E 7 Pajhar nadi 10.9 km, W 8 Digi nala 12.1 km, WSW

Nearest forest blocks within 15 km radius of the proposed mine are given in Table– 12. TABLE-12 NEAREST FOREST BLOCK WITHIN 10 KM RADIUS

Sr. No. Reserve Forests and Protected Forest: 1 TOLGE Reserve Forest (RF) Within lease TOLGE EAST Reserve Forest within the ML 2 area Within lease 3 Silot RF 1.3 km, NW 4 Gare RF 2.5 km, W 5 PF near Khamharia 3.6 km, NW 6 PF near Tehli Rampur 4.1 km, SW 7 RF Near Sakta 4.2 km, NW 8 Jamkani RF 4.5 km, SE 9 PF near Sarai Tola 4.5 km, WNW 10 Tolge West RF 5.6 km, N 11 PF near Dhornala 5.7 km, SW 12 PF near Dholnara 5.9 km, NW 13 PF near Dhornala 7.3 km, NW 14 Deodongar RF 8.0 km, NW 15 Rampur PF 8.2 Km, NW 16 PF near Tilaipali 9.0 km, NNW 17 RF near Ourajor village 9.3 km, SE 18 PF near Bhalumuda 9.5 km, NW VIMTA Labs Limited, Hyderabad 26 Pre-Feasibility Report for Enhancement of Production through Opencast Method of Mining in Gare Palma IV/4 Coal Mine, Chhattisgarh

Sr. No. Reserve Forests and Protected Forest: 19 Deodongri RF 10.1 km, NNW 20 Bhawarkhor RF 10.1 km, ENE 21 Barkachhar RF 10.1 km, SSW 22 Osakothi RF 10.1 km, NE 23 Gidhapahar RF 10.6 km, NE 24 Garhdongari RF 11.3 km, S 25 Dandpani RF 11.9 km, NE 26 Near Pithampur RF 12.2 km, SSE 27 PF near Banai 12.4 km, WNW 28 PF near Amaghat 12.7 km, SW 29 PF Near Kherkhad 12.8 km, WNW 30 Samaruma, RF 13.6 km, SW 31 PF Devgarh 14.1 km, WSW 32 Amaghat PF 14.2 km, SW 33 Pajhar PF 14.3 km, SW

No wild life sanctuary is located within 10 km radius of the mine.

4.5 Infrastructure Facility

It is a running project and required infrastructure is in place. The project life with target capacity of 1.5 MTPA has been estimated as 18 years. The detail of the infrastructure is as below:

4.5.1 Buildings

A provision of 10.44 ha of land for construction of township for quarters at proposed location has been made.

Provisions for community facilities and service buildings like workshops, stores, statutory buildings etc. have been considered.

 Community Buildings

Community facilities have been considered as there are adequate existing facilities for the same.

 Offices

Adequate additional provisions have been made towards GM office mine site office. The proposed buildings have been envisaged as RCC-cum-brick masonry structures.

 CHP: A coal handling plant with 400-500 TPH capacity has been proposed at surface for receiving, crushing of coal up to (-) 100 mm size, conveying and loading into trucks.

 Workshops and Stores

It is a running project and the workshop is already existing.

VIMTA Labs Limited, Hyderabad 27 Pre-Feasibility Report for Enhancement of Production through Opencast Method of Mining in Gare Palma IV/4 Coal Mine, Chhattisgarh

 Sub-station

As it is a running project substation is already existing to meet the requirement.

 Magazine : Provision for magazine building has been made in the report.

 Statutory Buildings: There are provisions for canteen, first aid centre, rest shelter, vocational training centre, pit head bath etc. The areas for various statutory buildings have been considered on the basis of BPE guidelines.

4.6 Soil Classification

Soil is ranging in thickness 1.0 m to 18 m and is of residual in nature. It is generally yellowish to reddish brown in colour and sandy in nature.

4.7 Climatic Data from Secondary Sources

Secondary information on meteorological conditions has been collected from nearest IMD station at Raigarh which is at a distance of 55 km, from the ML area. IMD data for ambient temperature, relative humidity, wind speed and rainfall is given in the Table-13.

TABLE-13 CLIMATOLOGICAL DATA STATION: IMD, RAIGARH

Monthly Wind Atmospheric Pressure Temperature Relative Humidity Rainfall Speed (hPa) (0C) (%) Month (mm) 0830 1730 Kmph 0830 Hrs 1730 Hrs Max Min Total Hrs Hrs January 991.6 987.6 31.3 9.1 65 46 14.5 3.2 February 989.4 985.6 35.0 11.5 60 36 14.5 4.2 March 987.4 982.6 40.1 16.1 46 26 17.6 4.3 April 983.5 978.5 43.4 21.0 39 22 12.8 4.8 May 979.7 974.8 45.3 23.1 44 26 38.8 5.3 June 976.1 972.2 43.6 23.2 64 51 204.3 5.9 July 976.4 973.5 36.0 22.5 83 75 399.3 5.1 August 977.2 974.3 34.3 22.9 84 78 441.9 5.1 September 981.3 977.8 34.9 22.5 80 74 234.0 3.9 October 986.6 982.8 34.9 18.2 71 60 42.2 3.3 November 990.3 986.4 33.1 13.5 64 51 7.5 3.1 December 992.5 988.3 30.5 10.0 65 47 2.0 2.8 Range 992.5-972.2 9.1-45.3 22.0-84.0 1429.4 2.8-5.9 Source: IMD Climatological Normals (1971-2000)

4.8 Available Social Infrastructure

It is a running project and the company is implementing various schemes for the development of the area. Social infrastructure like road and rail, communication, health, sanitation, community centres, education, financial institutions, income source, etc. are well established due to the presence of HINDALCO.

VIMTA Labs Limited, Hyderabad 28 Pre-Feasibility Report for Enhancement of Production through Opencast Method of Mining in Gare Palma IV/4 Coal Mine, Chhattisgarh

Social Infrastructure available in this area are:

 Well-connected road to district and state headquarters;  Power supply network and communication network;  Hospital;  Schools; and  Necessary market facilities and shops.

5.0 PLANNING BRIEF

5.1 Planning Concept

Gare Palma IV/4 coal mine was allocated to Hindalco Industries Limited, being successful bidder in the auction process conducted by Ministry of Coal, Government of India under the provisions of Coal Mines (Special Provisions) Act, 2015. The mine was allocated vide the Vesting Order no.104/13/2015/NA & 104/16/2015/NA dated 23rd March 2015 issued by Nominated Authority under the Act. As per the vesting order the coal produced from the mine will be used for captive consumption in the captive power plant of Aditya Alumina project Lapanga, and Hirakud complex, Hirakud, of Sambalpur district, Odisha.

5.2 Population Projection

It is a running mine and R & R activities are going on for Banjikhol and Jaripatra part of Kondkel village. The proposed mining activities will provide employment to persons of different skills and trades. The local population will have preference to get an employment. The employment potential will ameliorate economic conditions of these families directly and provide employment to many other families indirectly who are involved in business and service oriented activities. This in-turn will improve the socio-economic conditions of the area. Total manpower required for 1.5 MTPA production is 945. Services for security, canteen rest house, colony maintenance & Transportation of coal from the mine to EUP (end use plant), biological reclamation and sanitation are proposed to be out sourced. This will give rise to indirect employment generation by the company. It is obvious to assume that the activities of the mining operations will improve the socio-economic levels in the mine area.

5.3 Land Use Planning (Breakup along with greenbelt etc.)

The land details and the land use pattern during mining and at the end of the mining is given in Table-9 & Table-10 respectively.

5.4 Assessment of Infrastructure and Amenities/Facilities

It is a running project and most of the infrastructure required is present in the mine. Only the CHP proposed is to be constructed in the lease area for crushing of 1200 mm coal to -100 mm for bunkering and despatch.

VIMTA Labs Limited, Hyderabad 29 Pre-Feasibility Report for Enhancement of Production through Opencast Method of Mining in Gare Palma IV/4 Coal Mine, Chhattisgarh

6.0 PROPOSED INFRASTRUCTURE

6.1 Industrial Area

It is a running mines and store, magazine, HSD filling station, office buildings, sub- station, statutory buildings such as first aid centre, rest shelter, canteen are exist in the site.

6.2 Residential Area

The residential buildings and allied facilities of the project are already existing.

6.3 Greenbelt

It is a running project and green belt has been developed along the road, office building and in reclaimed OB dump. 74500 nos. of plants are planted within the mining lease so far and the green development will continue as per the approved mining plan in future also.

6.4 Social Infrastructure

It is a running project and within the mine canteen, first aid centre and rest shelter and office buildings are established. The CER activities of HINDALCO in and around the project area are already exist and helps in construction of school building, inducting community teachers, buses for school children, support to blind school, computer classes in rural and back ward area, organising regular health camps in the vicinity villages, construction of toilets, installing solar light in villages etc for the development of the area. With the continuation of the mine, there will be substantial improvement in the overall economy of the local people in the form of additional income through employment, development of infrastructure in surrounding areas such as transport facility, health and education.

The objective of CER is to:

 Significantly improve the physical quality of life;  Create opportunities for livelihood;  Improve the level of education including adult education;  Create health awareness among women; and  Ensure availability of safe drinking water.

6.5 Connectivity

It is addressed in Section-4.1.

6.6 Drinking Water Management (Source & Supply of Water)

It is proposed that requirement of potable water requirement is met from the mine seepage water. The mine water is being storage in the mine pit for settling and storage and later treated with latest Reverse Osmosis (RO) technology for which established RO plant of 7500 Litre per hour capacity, which is distributed for the use

VIMTA Labs Limited, Hyderabad 30 Pre-Feasibility Report for Enhancement of Production through Opencast Method of Mining in Gare Palma IV/4 Coal Mine, Chhattisgarh

of mine staffs & workers and supplied to R & R colony. For supply of pure and clean drinking water tap has been provided in the R & R villages and small overhead tanks are also built up.

6.7 Sewerage System

Domestic and industrial effluents will be disposed off after suitable treatment in the effluent treatment plants (STP/ ETP) located in colony and industrial area.

6.8 Industrial Waste Management

Mine Discharge

The mine discharge will be used to meet the requirement of the afforestation / plantation, dust suppression, firefighting, other industrial, domestic applications. The RO water be used for portable drinking water and supplied to the R & R colony for use.

Washery Effluent: Not Applicable

Workshop Effluent: The workshop effluent will be treated properly in effluent treatment plant and reused.

Domestic Effluent: STP will be provided. Sludge after digestion will be used as manure / compost.

6.9 Solid Waste Management

The total overburden generated as per the Mining Plan is 220.52 Mm3 of which only 85.98 Mm3 is proposed to be dumped externally, while the remaining 134.54 Mm3 of OB is proposed to be dumped internally. Details are given in Section-3.9.

6.10 Power Requirement & Supply / Source :

It is envisaged that existing power supply arrangement at 33 kV will be used to meet the power requirement of this project.

7.0 REHABILITATION AND RESETTLEMENT (R&R) PLAN

7.1 Policy to be adopted in respect of the project affected persons including home oustees, land oustees and landless labourers:

It is a running project and R & R activities are already in progress as per Adarsh Chhattisgarh Punarvas Niti 2007 & The Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013. The Rehabilitation Action Plan has been approved by State Government.

VIMTA Labs Limited, Hyderabad 31 Pre-Feasibility Report for Enhancement of Production through Opencast Method of Mining in Gare Palma IV/4 Coal Mine, Chhattisgarh

8.0 PROJECT SCHEDULE & COST ESTIMATES

8.1 Likely date of start of construction and likely date of Completion

It is a running mine of 1 (One) MTPA capacity (UG-0.44 MTPA + OC-0.56 MTPA).

Net available geological reserves has been estimated as 59.466 Million tonnes after adjustment for the mine production till 31.03.2018. The revised mining plan (including mine closure plan) for Gare Palma IV/4 Coal Block (4th Revision) has been prepared to switching to total mechanised opencast mining from the present mix of underground mining and opencast mining method with the following assumptions:

i. To maintain the production programme for first three years as per the approved Revised Mining Plan & Mine Closure Plan (3rd Revision) of Gare Palma IV/4 Coal Mine i.e. 0.44 MTPA by underground production and 0.56 MTPA by opencast mining; ii. To convert the entire mining operation to opencast mining in fourth and fifth year; and iii. to increase the annual production from 1.0 MTPA to 1.5 MTPA in the fifth year and then to maintain 1.5 MTPA as the target/peak annual production rate.

8.2 Estimated project cost along with analysis in terms of economic viability of the project.

It is a running mine and the estimated project cost will be about Rs. 420 crores.

9.0 ANALYSIS OF PROPOSAL (FINAL RECOMMENDATIONS)

9.1 Financial and Social Benefits

This is a running mine with production capacity of 1.0 MTPA. People of this area have already tasted the benefits of the project by development of road and communication in the area, better school facilities, and health and sanitation. Various CER activities undertaken by the company helps in increasing the employment potential of the youth and ladies of this area. By running this project will improve the socio-economic status of the society in the region by generating direct and indirect employment opportunities. The project will contribute additional revenue to the State & Central exchequers in the form of taxes, cess, etc. In The last four years, GP Mines have contributed Rs 2200 crores to state Govt towards premium and duties.

***********

VIMTA Labs Limited, Hyderabad 32 Pre-Feasibility Report for Enhancement of Production through Opencast Method of Mining in Gare Palma IV/4 Coal Mine, Chhattisgarh

ANNEXURE-I MINE PLAN APPLIED FOR APPROVAL VIDE LR NO HIL/GP-IV/4/MINE PLAN/2019-20/234 DATED 31ST MAY, 2019

VIMTA Labs Limited, Hyderabad 33 Pre-Feasibility Report for Enhancement of Production through Opencast Method of Mining in Gare Palma IV/4 Coal Mine, Chhattisgarh

ANNEXURE-II EXISTING ENVIRONMENTAL CLEARANCE OF 1 MTPA

VIMTA Labs Limited, Hyderabad 34 Pre-Feasibility Report for Enhancement of Production through Opencast Method of Mining in Gare Palma IV/4 Coal Mine, Chhattisgarh

VIMTA Labs Limited, Hyderabad 35 Pre-Feasibility Report for Enhancement of Production through Opencast Method of Mining in Gare Palma IV/4 Coal Mine, Chhattisgarh

VIMTA Labs Limited, Hyderabad 36 Pre-Feasibility Report for Enhancement of Production through Opencast Method of Mining in Gare Palma IV/4 Coal Mine, Chhattisgarh

VIMTA Labs Limited, Hyderabad 37 Pre-Feasibility Report for Enhancement of Production through Opencast Method of Mining in Gare Palma IV/4 Coal Mine, Chhattisgarh

VIMTA Labs Limited, Hyderabad 38 Pre-Feasibility Report for Enhancement of Production through Opencast Method of Mining in Gare Palma IV/4 Coal Mine, Chhattisgarh

VIMTA Labs Limited, Hyderabad 39 Pre-Feasibility Report for Enhancement of Production through Opencast Method of Mining in Gare Palma IV/4 Coal Mine, Chhattisgarh

VIMTA Labs Limited, Hyderabad 40 Pre-Feasibility Report for Enhancement of Production through Opencast Method of Mining in Gare Palma IV/4 Coal Mine, Chhattisgarh

VIMTA Labs Limited, Hyderabad 41 Pre-Feasibility Report for Enhancement of Production through Opencast Method of Mining in Gare Palma IV/4 Coal Mine, Chhattisgarh

VIMTA Labs Limited, Hyderabad 42 Pre-Feasibility Report for Enhancement of Production through Opencast Method of Mining in Gare Palma IV/4 Coal Mine, Chhattisgarh

VIMTA Labs Limited, Hyderabad 43 Pre-Feasibility Report for Enhancement of Production through Opencast Method of Mining in Gare Palma IV/4 Coal Mine, Chhattisgarh

ANNEXURE-III TRANSFER OF EC

VIMTA Labs Limited, Hyderabad 44 Pre-Feasibility Report for Enhancement of Production through Opencast Method of Mining in Gare Palma IV/4 Coal Mine, Chhattisgarh

VIMTA Labs Limited, Hyderabad 45 Pre-Feasibility Report for Enhancement of Production through Opencast Method of Mining in Gare Palma IV/4 Coal Mine, Chhattisgarh

VIMTA Labs Limited, Hyderabad 46 Pre-Feasibility Report for Enhancement of Production through Opencast Method of Mining in Gare Palma IV/4 Coal Mine, Chhattisgarh

VIMTA Labs Limited, Hyderabad 47 Pre-Feasibility Report for Enhancement of Production through Opencast Method of Mining in Gare Palma IV/4 Coal Mine, Chhattisgarh

ANNEXURE-IV AMENDMENT OF EC

VIMTA Labs Limited, Hyderabad 48 Pre-Feasibility Report for Enhancement of Production through Opencast Method of Mining in Gare Palma IV/4 Coal Mine, Chhattisgarh

VIMTA Labs Limited, Hyderabad 49