1. Introduction

1.1 The FIFEplan Local Development Plan was adopted on 21 September 2017 (Click here to view Adopted FIFEplan) it sets out the Council’s planning strategies and policies to guide and manage future development in . It describes where and how the development will take place in the area over the 12 years from 2014-2026 to meet the future environmental, economic, and social needs, and provides an indication of development beyond this period. FIFEplan is framed by national and regional policy set by the National Planning Framework and the two Strategic Development Plans. Other strategic policies and Fife Council corporate objectives also shape the land use strategy as illustrated below.

3

1.2 This Action Programme accompanies FIFEplan by identifying what is required to implement FIFEplan and deliver its proposals, the expected timescales and who is responsible. Throughout the preparation of the plan, Fife Council has maintained close partnerships with key stakeholders, the Scottish Government, and other organisations named in the document. These organisations have a responsibility to alert the Council of any changes to the proposals. The Action Programme is important to Fife Council because the implementation of FIFEplan will require actions across different Council services.

•The LDP Action Programme FIFEplan lists the infrastructure required to support Action Programme development promoted by the Plan

•The Council prepares their Plan for Fife business plan for the year. Local Outcome •New projects can be Improvement Plan proposed for prioritisation at this stage.

•Project priorities are decided which are then Council reflected in updates to the Action Programme.

4

Policy and Supplementary Guidance

1.3 In monitoring the implementation of the Fife Local Development Plan, the existing policies have been reviewed to confirm compliance with Scottish Planning Policy and any changes that have taken place since the plan was prepared. The policy objectives will also be reviewed to map these against updated council objectives as set out in “A Plan for Fife” Local Outcome Improvement Plan which have evolved from the Council plan objectives that existed when FIFEplan was prepared.

1.4 The policies will also be monitored to identify any issues arising from their use in practice, how they assist in delivering the Plan’s spatial strategy, and to identify any change in circumstances or unintended consequences. Supplementary Guidance will also be reviewed for the same reasons.

1.5 Monitoring the development plan and delivery of proposals will be used to identify matters which may need to be updated or reviewed in future versions of the Local Development Plan. To see proposed updates for policy & guidance see section 7. Policies.

Strategic Environmental Assessment and Habitat Regulations Appraisal

1.6 Strategic Environmental Assessment and Habitats Regulations Appraisal (for European Protected sites) have been carried out alongside the preparation of FIFEplan, and informing its content. Following the adoption of FIFEplan a Post-Adoption Statement has been prepared as part of the Strategic Environmental Assessment process. The Post-Adoption Statement outlines how environmental assessment has been taken into account and made a difference to FIFEplan. The Post-Adoption Statement also identifies a number of indicators to be monitored every two years.

Related Information

1.7 Throughout the Local Development Plan period, the Council will prepare other corporate policy documents and strategies relevant to the Development Planning process - such as the Local Housing Strategy and Fife Economic Strategy. These will have their own timescales for preparation and review which means they will not necessarily coincide with the review of FIFEplan. The Action Programme and its annual updates will provide an opportunity to identify changes to other corporate plans which have a bearing on the development planning process and explain if and how they affect the delivery of FIFEplan’s policies and proposals.

5

Monitoring and Gate Check Evidence

1.8 Proposals in the Planning Bill on a review of the Scottish Planning System include introduction of a gate check local development plan reviews. The evidence to be recorded and checked at the gate check stage will be informed in part by information monitored and recorded through this Action Programme. There is also a proposal for action programmes to become delivery programmes for local development plans and this document has been written with that in mind. It is the first step in a series of changes to be introduced the actions needed to deal with obstacles to delivering FIFEplan.

* Cost information will be added over time as it becomes available or is updated

6

The Action Programme is a live working document which will be regularly monitored. It will be updated annually to show which proposals have been changed or completed, and to identify new proposals which have emerged since the Local Plan was published.

Review and updates

1.10 This Action Programme will be updated annually with information available from the development agencies, key stakeholders, and regular audits such as the Fife Housing Land Audit. The Action Programme will be prepared to a timetable which allows for relevant updates to be taken into account in the Council’s budget setting and in updates to the Plan for Fife Local Outcomes Improvement. Each future edition of the Action Programme will indicate the change for each proposal since the previous Programme was published; as this is the first Action Programme in this format and includes new proposals, no change is shown in this edition. The indicative timescale is shown below:

Housing / Housing Opportunity Site Site Site specific actions Delivery Status/Next Steps Cellardyke Who: Muir Homes This site is under construction. 339 houses approved and Caravan Park Est. Capacity: 331 250 completions to date. 10/01104/ARC (ANS 001) Area: 10.7 ha 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

TIMESCALES FOR IMPLEMENTATION

✔ On track ✘ Not on track

No Schedule

Scheduled

Complete 7

Annual review of the Action Programme against the Housing Land Audit

April - June July - Sept Oct – Dec Jan - Mar

Step 1: Identify how much Step 2: Consultation with Step 3: Finalise Housing Step 4: Financial modelling land is available and rate of developers/Homes for Land Audit and budget requirements delivery . Tri-partite meeting are informed by the Action Update infrastructure held. Programme actions (incl. timing) with input from key agencies and issue new Action Programme.

Capital planning for schools/transport/waste disposal/etc.

Final Housing Land Audit Initial update of Draft Housing Land Housing Land Audit Audit Action Programme What is needed When is is needed Who the delivery agent is Fife Council How much is it costing budget set Other Actions. Fife Council budget review

Implement infrastructure & other actions to address constraints on land and support higher delivery rates.

8

2. Spatial Strategy

2.1 FIFEplan’s spatial strategy is a Fife-wide statement of how Fife should develop over the lifetime of the plan. It is framed by national and regional policy set by the National Planning Framework and the two Strategic Development Plans covering Fife: SESplan and TAYplan. The spatial strategy is reproduced below.

2.2 Taking account of the two Strategic Development Plans, FIFEplan's housing land supply will be met by proposing development focused on towns and villages having regard to the range of facilities, local need, and likely impact on their location. Proposals for employment, housing, and local services are, where possible, located in close proximity to encourage sustainable and healthier lifestyles and to make integration with existing communities easier.

2.3 The table below sets out proposals that will be required for successful delivery of the spatial strategy. So as to avoid duplication, proposals which relate to strategic transport interventions; strategic education proposals and strategic development area/strategic land allocations are listed separately within later sections of the document. The following should be read in conjunction with the Local Development Plan and the Planning Obligations Supplementary Guidance.

9

10

Spatial Strategy Proposal Lead Cost Status / Next Steps 1 Longannet Power Station Scottish Power Currently The March 2017 Longannet Task Force meeting agreed that a site steering group (LWD034) unknown considering how best possible scenarios for future uses of the Longannet site can be explored and discussed. Demoiltion was also confirmed to be under way and likely to occur until 2021.

Proposed terms of reference for the site steering group have been established and the steering group have met as agreed from September 2017.

The overall purpose for the group is:  To identify appropriate and viable options for the future use of the site formerly occupied by Longannet Power Station, recognising that the site and location are of national significance.

 To receive updates on the clearance and demolition of the Longannet site including specifically the remediation of the ash lagoons at Longannet and Valleyfield. A proposal of application notice for the latter was received in December 2017 - 17/03865/PAN 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 ✔

2 Rosyth Port Landowner/ Currently Land safeguarded & promoted through the context of the Fife Energy Corridor. Rosyth Private Sector unknown Port forms part of the spatial strategy of the plan and has policy protection. The area includes proposals ROS013, and ROS020. The Rosyth waterfront development framework has been produced and approved to coordinate the range of sites and uses at this strategic location.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

3 Burntisland Port Landowner/ Currently Safeguarded & promoted through the context of the Fife Energy Corridor. Burntisland private sector unknown Port forms part of the spatial strategy of the plan and has policy protection. 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 2017/18

11

Proposal Lead Cost Status / Next Steps 4 Methil – Energy Park Fife Scottish Currently Safeguarded & promoted through the context of the Fife Energy Corridor. Methil Energy (BKN003) Enterprise unknown Park Fife forms part of the spatial strategy of the plan and has policy protection.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 ✔

5 Inverkeithing Port Landowner/ Currently Safeguarded & promoted through the context of the Fife Energy Corridor. Inverkeithing private sector unknown Port forms part of the spatial strategy of the plan and has policy protection. The area includes proposal INV009. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

6 Inner Forth Landscape RSPB Currently The Inner Forth Landscape Initiative recognises cultural and natural heritage, enabling Initiative unknown local people and visitors to understand the importance of the Inner Forth to the environment and cultural development of Scotland. The Inner Forth Landscape Initiative, will run between May/June 2014 and April 2018 championing up to 50 projects across the area.

The existing Inner Forth Landscape Initiative (IFLI) is scoping next steps beyond the life of the current programme to recognise and promote the role that the river Forth has and the potential of this area to be an industrial and leisure asset for Scotland. Fife Council are exploring involvement and input where this can support the local outcome improvement plan, The Plan For Fife 2017. 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 2017/18 ✔

7 Living Lomonds Landscape Fife Coast & Currently Promote Lomond Hills as a recreational & cultural resource through environmental Partnership Countryside unknown improvements to the regional park. Trust 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 COMPLETE

12

Proposal Lead Cost Status / Next Steps 8 St Ninian’s Restoration Fife Council Currently Restoration is complete. The developer must prepare a master plan for the future (LWD033) unknown development of the area for Fife Council approval. PPP of masterplan anticipated in June 2018. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 ✔ 9 Westfield Private Sector Currently The Thornton to Levenmouth and Thornton to Westfield spur rail lines are in private unknown ownership and should be safeguarded for future rail use. The rail lines must also be safeguarded against prejudicial development on adjacent land.

Any proposed residential development adjacent to the railways must be set back from the railway lines.

Application agreed by Committee for Planning permission in principle for restoration and development of former opencast site including power generation/storage; waste recovery/recycling; employment uses (Class 4 (light industry only) with ancillary office space, Class 5 and 6); rail off-loading facility, glass houses and other associated infrastructure (16/03661/EIA)

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 ✔

10 Greenbelt Fife Council N/A Designated in the adopted FIFEplan

2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 COMPLETE

11 Greenbelt Fife Council N/A Designated in the adopted FIFEplan 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 COMPLETE

13

Proposal Lead Cost Status / Next Steps 18 Glenrothes Regeneration Land owner/ Currently The Glenrothes West Charrette is progressing towards the final reporting stage. Public & focus for employment Private Sector/ unknown consultation engagements are now complete with updates/newsletters all accessible at Fife Council https://engb.facebook.com/goldenglenrothes/ The appointed consultants, Planning Aid for Scotland, will be presenting an overview of the final Charrette Report and latest iterations of designs for the future redevelopment of the Glenwood Centre at a meeting to be attended by key elected members and senior Council officials on 28th February. It is then anticipated that the final report will be published in early/mid-March.

North Street Redevelopment (GLE029) - a series of public realm/environmental improvements will be delivered during 2018. These include green open space (Former Glenrothes House), improved walking and cycling opportunities, improvements to surfaces between the new development and Kingdom Centre, traffic calming measures and introduction of a 20mph zone.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 ✔ 20 Rosyth focus for Land owner/ Currently Rosyth waterfront development framework completed and approved at South West Fife employment Private Sector/ unknown Area Committee on 13th December 2017. Regular dialogue will be set up with landowners Fife Council/ to progress delivery. Scottish Enterprise 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 Proposal Lead Cost Status / Next Steps 21 Forth Crossing (LWD016) Transport Funded Crossing now complete and operational. Scotland through national government

2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 COMPLETE

14

Proposal Lead Cost Status / Next Steps

22 Hovercraft Link (KDY039) Landowner Currently Land at the Stagecoach Bus Garages site will be safeguarded for a potential cross Forth unknown transport link. No support from City of Council so unlikely to progress.

Site has planning permission for a ferry terminal 14/03976/FULL

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

25 Safeguarded Leven rail Fife Council Currently Levenmouth Sustainable Transport Study – a Strategic Transport Appraisal Guidance link - Thornton to Leven unknown (STAG) Report was produced (Dec 2016). The preferred option being to re-open the rail and Thornton to Westfield line to Levenmouth. rail lines (LEV005) Transport Scotland commitment to progress next steps on feasibility (2017) - GRIP

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

27 Cupar Relief Road Cupar North £11m To be delivered as part of the Cupar Strategic Land Allocation. The relief road is to be Consortium/ provided by the completion of the 600th house. Stephen Homes 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

15

Proposal Lead Cost Status / Next Steps 28 Safeguard Dunfermline Fife Council/ Currently In line with Scottish Transport Appraisal Guidance (STAG), a transport Pre-Appraisal /Alloa rail link Transport unknown including analysis of problems, opportunities, objective setting and option generation Scotland/ has been undertaken (2017). The study area is defined by the Forth Estuary and the Network Rail bridge crossings (The Clackmannanshire Bridge and the Kincardine Bridge) to the south, the A985 trunk road running east -west through the area (connecting the M90/A92 and the M80 corridor), key connectors to the local road network and the Longannet freight- only rail line running parallel to the Forth. Further appraisal is necessary but is in part dependent on proposal LWD034 (Longannet Power Station).

The existing freight-only rail line is seen as an opportunity regarding future re- development of the Longannet site and gives a potential for West Fife as a possible passenger line. The route of the link should be safeguarded from development.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

29 Safeguard rail halt - Fife Council/ Currently Land at the Bawbee Bridge, Leven, will be safeguarded for the provision of a rail halt and Bawbee Bridge, Leven Transport unknown station facilities associated with the possible long-term re-introduction of passenger rail (LEV008) Scotland/ services to Levenmouth. Network rail Further discussions between the council and Transport Scotland will take place.

Levenmouth Sustainable Transport Study - Stag Report produced (Dec 2016)

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

16

Proposal Lead Cost Status / Next Steps 30 Safeguard rail halt - Fife Council Not identified LDP Safeguard only. Newburgh (NEB004) /Private sector Strategic transport network improvements will include junction and car parking improvements in addition to the safeguarding and provision of serviced employment land.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

31 Safeguard rail halt - Fife Council Currently LDP safeguard only. Wormit (WOR004) /Private sector unknown The project is not supported by the Strategic Transport Projects Review, and there is currently no commitment or approval for it from Transport Scotland. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

17

3. Strategic Transport Proposals

3.1 Traffic arising from new development has an impact on the transport network across Fife. Fife Council has undertaken an assessment of the probable traffic impacts of the combination of committed developments and future development generated through the additional land use allocations in the SESplan area of Fife. The transport methodology set out within FIFEplan and the Planning Obligations Supplementary Guidance is not repeated here but in summary a zonal methodology is adopted within Fife and a proportionate cost attributed to contributing development dependent on type, size and impact. A summary of the anticipated delivery requirements is as follows:

18

Kirkcaldy & Glenrothes Strategic Transport Interventions

Kirkcaldy Contribution Zone 2018-2021 Contributions to be collected towards actions. Delivery strategy to be agreed. Core Zone £4,695 per dwelling (see diagram below for contributing sites). Intermediate 5km Zone £1,441* per dwelling (see diagram below for contributing sites). Outer Zone £316 per dwelling (see diagram below for contributing sites).

Detailed Intervention Anticipated Cost Lead Next Steps/Update Redhouse Roundabout Improvements (KDY025) £10.6 M Murray Estates/other Safeguarded in Plan. (additional works developers/Fife Council/ to be carried out Transport Scotland by Murray Estates)

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Gallatown Roundabout (KDY025) £1.4 M Murray Estates/other Safeguarded in Plan. developers/Fife Council/ Transport Scotland

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Mitchelston Road (KDY025) £5.9 M Murray Estates/other Safeguarded in Plan. developers/Fife Council/ Transport Scotland 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

19

Detailed Intervention Anticipated Cost Lead Next Steps/Update Standing Stane Link Road (KDY025) £7.1 M Murray Estates/other Safeguarded in Plan. developers/Fife Council/ Transport Scotland 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Randolph Road Improvements (KDY025) £0.8 M Murray Estates/other Safeguarded in Plan. developers/Fife Council/ Transport Scotland 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Abbotshall Road/Nicol Street, Abbotshall £1.0M Fife Council/ Fife Safeguarded in Plan. Road/Forth Avenue, Forth Avenue Oriel Road Infrastructure Investment Junctions (KDY045) Fund (FIIF)

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Chapel Interchange Signalisation (KDY046) A92 £0.7 M Fife Council/ Fife Safeguarded in Plan. Route Strategy Improvements Infrastructure Investment Fund (FIIF)

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

*Sites located within these intermediate zones will be required to pay both zone costs to reflect the inter-relationship of likely traffic impacts across each zone. (Costs stated are subject to verification in costed Transport Assessments. Updates have been applied from a 2009 base up to 2017 against Building Cost Information Service (BCIS). Further updates at time of assessment will be necessary in line with BCIS or comparable industry standards.

The costs in this table will be updated regularly and may reduce through direct provision of infrastructure by development at Kirkcaldy East or the impact of infrastructure delivery programmes such as the Edinburgh and South Scotland City Deal.

20

Glenrothes Contribution Zone Contributions to be collected towards actions. Delivery strategy to be agreed.

Core Zone £4,695 per dwelling (see diagram below for contributing sites). Intermediate 5km Zone £1,441* per dwelling (see diagram below for contributing sites). Outer Zone £316 per dwelling (see diagram below for contributing sites).

Detailed Intervention Anticipated Cost Lead Next Steps/Update Bankhead Roundabout signalisation £1.3 M Fife Council/ Fife Land safeguarded. Delivery dependent on the (GLE036) Infrastructure Investment progression of housing sites. Fund (FIIF) and Transport Scotland

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

North Glenrothes (Preston roundabout £1.3M Fife Council/ Fife Land safeguarded. Delivery dependent on the junctions signalisation) Infrastructure Investment progression of housing sites. (GLE036) Fund (FIIF) and Transport Scotland

2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 2017/18

*Sites located within these intermediate zones will be required to pay both zone costs to reflect the inter-relationship of likely traffic impacts across each zone. (Costs stated are subject to verification in costed Transport Assessments. Updates have been applied from a 2009 base up to 2017 against Building Cost Information Service (BCIS). Further updates at time of assessment will be necessary in line with BCIS or comparable industry standards.

The costs in this table will be updated regularly and may reduce through direct provision of infrastructure by development at Kirkcaldy East or the impact of infrastructure delivery programmes such as the Edinburgh and South Scotland City Deal.

21

22

Dunfermline Contribution Zone Contributions to be collected towards actions. Delivery strategy to be agreed.

Core Zone £5,332 per dwelling (see diagram below for contributing sites). Intermediate 5km Zone £2,428 per dwelling (see diagram below for contributing sites). Outer Zone £456 per dwelling (see diagram below for contributing sites).

Detailed Intervention Anticipated Cost Lead Next Steps/Update (for works outwith development site) Northern Link Road (DUN067) £14.3 M Private Sector (Wellwood Wellwood has planning consent and is under ‘share’) construction and will deliver part of the Northern Link Road.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Improvement of Road / Whitefield £1.4M Private Sector Safeguarded in Plan. Road Junction (DUN067) (Halbeath ‘share’)

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Signalise Bothwell Gardens Roundabout £0.5M Fife Council/Fife Safeguarded in Plan. (DUN069) Infrastructure Investment Fund (FIIF) 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Signalisation of Pitreavie Roundabout £0.9M Fife Council/ Fife Safeguarded in Plan. including widening of approach lanes Infrastructure Investment (DUN070) Fund (FIIF)

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

23

Detailed Intervention Anticipated Cost Lead Next Steps/Update (for works outwith development site)

Kings Road / Admiralty Road Roundabout £1.4M Private Sector/Fife Council/ Safeguarded in Plan. Junction Signalisation (ROS018) Fife Infrastructure Investment Fund (FIIF)

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Western Distributor Road (DUN068) £1.2M Fife Council/ Fife Safeguarded in Plan. Forth Street / Elgin Street Junction / Link Road Infrastructure Investment Fund (FIIF

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Western Distributor Road (DUN068) £17M Fife Council/ Fife Safeguarded in Plan. Grange Drive link road, Rumblingwell/William Infrastructure Investment St Junction, William St/ Pittencrief St Junction, Fund (FIIF Coal Road/Lovers Loan, Grange Drive/ Queensferry Rd roundabout

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Costs stated are subject to verification in costed Transport Assessments. Updates have been applied from a 2009 base up to 2017 against Building Cost Information Service (BCIS) civil engineering forecasts. Further updates at time of assessment will be necessary in line with BCIS or comparable industry standards.

24

25

4. Education

4.1 New residential development across Fife will have an impact on the pressures placed upon the school estate. Certain types of development which includes new residential development will be required to provide education contributions where there is a shortfall in local school capacity as a direct result of new development. Where obligations are necessary to mitigate for additional impacts of development, this will take the form of either direct school and nursery provision, or financial contributions towards the cost of creating accommodation for increased pupil numbers.

Secondary education provision – Kirkcaldy and Dunfermline

4.2 There are existing secondary school capacity issues across Kirkcaldy and Dunfermline, this will be exacerbated by the high levels of development expected to take place over the next 20 - 30 years. As detailed within Planning Obligation Supplementary Guidance, a more strategic view is deemed appropriate when considering secondary school obligations in these towns. The level of developer contributions are given below.

26

Settlement Cost of development Number of Cost per 3 Lead Status related education contributing bedroom unit improvements houses Kirkcaldy – Windmill £3,800,000 3,506 £1,071 Fife Council Extension to Viewforth Secondary School dependent on Road Campus phasing of SLAs in Kirkcaldy. Extension 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Dunfermline – £36,000,000 5,934 £6,067 Fife Council The existing secondary schools are expected to reach additional Secondary capacity in 2022. A new school in Dunfermline will be School Capacity required by then. Contributions will still be sought towards this school after 2022.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Primary Schools 4.3 Impacts on primary school infrastructure are dealt with through the Planning Obligations Supplementary Guidance and education estate assessments. While the impact of new development has already been modelled the solutions to these impacts is ongoing. For each school detailed assessment is required to determine the best approach to dealing with any infrastructure shortfall. For the next iteration of this Action Programme the Council will produce a timeline highlighting the expected points at which primary school infrastructure will be required, the type of intervention needed and its cost per unit for the sites in the relevant school catchment.

27

5. Strategic Development Areas/Strategic Land Allocations

5.1 There are nine Strategic Development Areas / Strategic Land Allocations in Fife, which include Cupar, Dunfermline, Kirkcaldy, Levenmouth, Lochgelly, St. Andrews and Ore & Upper Leven Valley. These locations present the best opportunity to develop established settlements at a scale that can deliver community infrastructure and services benefits. Over a 20 year timeframe, it is estimated that over 31,000+ houses as well as employment/commercial land will be provided. There is an estimated investment value of approximately £3 billion which includes £66 million of roads infrastructure and £40 million of strategic education.

5.2 Challenges remain around infrastructure funding and the phasing of development but market is beginning to again recognise the attractiveness and value of strategic growth such as this for Fifers and across the city region.

28

29

CUP001 Action Lead Cost Status / Next Steps Cupar North: Planning Applications Cupar North Currently Planning application submitted (15/04279/EIA) (includes delivery of employment Consortium unknown land, health care, renewables etc.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 ✔ Gilliesfaulds: Planning Applications Stephen Homes Currently Planning application submitted (17/00536/FULL) (includes delivery of employment unknown land, renewables etc.)

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 ✔ Funding and construction of the Cupar North £11M To be completed no later than completion of the 600th house which is associated relief road including Consortium/ currently anticipated in 2031/32 (2017 HLA). junctions with the A91 Stephen Homes 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

New primary school and nursery Cupar North £10M for 1 ½ Cost to be met from Consortium site and pro-rata payments from Gilliesfaulds. provision Consortium stream school Options to deliver the school and early years provision are being developed for plus additional discussion with the developers. transition requirements 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Financial contribution to secondary Cupar North TBC Possible need to contribute towards enlargement of Bell Baxter. education Consortium 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

30

Action Lead Cost Status / Next Steps Land for care home(s) and additional Cupar North Land to be Land provided through Consortium planning application. primary healthcare facilities Consortium provided at agreed market value.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 ✔ Drainage Infrastructure Scottish Water TBC Scottish Water is working closely with the Cupar North Consortium to develop a /Development detailed drainage plan for the Northern section of the site. A drainage model is Community due to be completed in 2018 allowing a more detailed Network Impact Assessment to be carried out by Scottish Water. Drainage Upgrades identified will be funded by developers. Interim surface water removal solutions are being investigated to support earlier phases of the site.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 ✔ Water Infrastructure Scottish Water TBC A Water Impact Assessment is required for the site. /Development Community

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

31

32

DUN035 Action Lead Cost Status/ Next Steps Wellwood: Planning Applications (includes I &H Brown Currently Planning Permission in Principle approved 03/06/2016 - 13/03683/EIA delivery of employment land, health care, Unknown Section 75 executed 19/05/2016.First phase under construction. renewables etc.) Persimmon on site. The first houses were occupied in February 2018.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 ✔

Broomhall: Planning Applications (includes Stirling Currently Planning Permission in Principle submitted Dec. 2017 - 16/04155/EIA delivery of employment land, health care, Developments Unknown renewables etc.)

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 ✔ Berrylaw: Planning Applications (includes Landowner Currently No information is available. Fife Council as Planning Authority will delivery of employment land, health care, Unknown review the continued inclusion of this proposal in the LDP. renewables etc.) 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Wellwood: Strategic and local road I &H Brown Currently Onsite works include partial delivery of the Northern Link Road. improvements, including a Northern Link Road Unknown and Western Distributor 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Broomhall: Strategic and local road Stirling Currently Onsite works will include partial delivery of the Western Distributor improvements, including a Northern Link Road Developments Unknown and Western Distributor 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

33

Action Lead Cost Status / Next Steps Wellwood: New primary schools and nursery. I &H Brown / Currently Primary school to be provided by developer. Modular unit to be Fife Council Unknown provided by the developer at McLean Primary School by 100 units to provide transitional capacity

Primary school to be provided by 300th house. anticipated to be 2019/2020

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Broomhall: New primary schools and nursery. Stirling Currently Developer agreed 2016 that a second primary school would be Developments / Unknown provided on site. Some capacity at Pitreavie Primary School 2 double Fife Council modular units at Pitreavie Primary School to be provided by the developer to provide longer term transitional capacity.

Education advise first school to be provided by 2027.

Second school to be provided when capacity of first school is breached. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Berrylaw: contributions towards primary school Landowner/ Currently Contributions required towards primary school provision for provision Developer /Fife Unknown Dunfermline N/W/SW SLA Council

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Secondary Education Developer/ £6,067 Dunfermline wide contributions towards additional secondary capacity Fife Council are now sought – see Planning Obligations Supplementary Guidance 2017.

Additional capacity required by 2022. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

34

Action Lead Cost Status / Next Steps Wellwood: Identification of suitable sites for Developer/ NHS Fife Currently Land for potential healthcare facilities identified in the approved healthcare Unknown masterplan in community hub. 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 2017/18 ✔ Broomhall: Identification of suitable sites for Developer/ NHS Fife Currently Land to be made available for healthcare provision. healthcare / Fife Council Unknown 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 ✔ Wastewater Infrastructure Scottish Water Currently A Strategic Network Impact Assessment for the Dunfermline /Development Unknown Catchment has been initiated by Scottish Water to understand the Community cumulative impact of development on the drainage infrastructure. The outputs of this activity are expected in mid-2018. Interim solutions are being assessed with developers in the meantime to ensure development is being accommodated.

In addition to the network studies, detailed Flow and Load/Process Unit assessments are being carried out at both the Ironmill Bay and Dunfermline Wastewater Treatment Works in 2018 to better understand any potential upgrade requirements to accommodate all forecast flows from proposed development in the catchment. Development is currently being permitted in lieu of any results or upgrade activities. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 ✔

35

Action Lead Cost Status / Next Steps Water Infrastructure Scottish Water Currently Water infrastructure is strong within the Dunfermline catchment, but /Development Unknown the cumulative effect of development will potentially require localised Community network upgrades. Individual Water Impact Assessments are a likely requirement with Scottish Water ultimately aiming to deliver a Strategic Network Impact Assessment within the next 2 years detailing any strategic upgrades required to support development. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

36

37

Kent Road – DUN038 Action Lead Cost Status/ Next Steps Planning Applications (includes delivery of Mactaggart Currently Proposal of Application Notice (PAN) received 18/00100/PAN employment land, health care, renewables etc.) and Mickel Unknown Homes 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Contributions to new primary and secondary Fife Council £6,067 Dunfermline – wide contributions towards additional secondary capacity school provision are now sought – see Planning Obligations Supplementary Guidance 2017.

Additional capacity required by 2022. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Wastewater Infrastructure Scottish Water TBC A Strategic Network Impact Assessment for the Dunfermline Catchment /Development has been initiated by Scottish Water to understand the cumulative Community impact of development on the drainage infrastructure. The outputs of this activity are expected in mid-2018. Interim solutions are being assessed with developers in the meantime to ensure development is being accommodated.

In addition to the network studies, detailed Flow and Load/Process Unit assessments are being carried out at both the Ironmill Bay and Dunfermline Wastewater Treatment Works in 2018 to better understand any potential upgrade requirements to accommodate all forecast flows from proposed development in the catchment. Development is currently being permitted in lieu of any results or upgrade activities.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 ✔

38

Action Lead Cost Status/ Next Steps Water Infrastructure Scottish Water TBC Water infrastructure is strong within the Dunfermline catchment, but the /Development cumulative effect of development will potentially require localised Community network upgrades. Individual Water Impact Assessments are a likely requirement with Scottish Water ultimately aiming to deliver a Strategic Network Impact Assessment within the next 2 years detailing any strategic upgrades required to support development. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

North Dunfermline (Colton) (DUN039) Action Lead Cost Status/ Next Steps Planning Applications (includes delivery of I & H Brown Currently 18/00256/PAN submitted employment land, health care, renewables etc.) Unknown 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Strategic and local road improvements, including I & H Brown Currently Onsite works include partial delivery of the Northern Link Road. a Northern Link Road (DUN039, 041,043,044) and Unknown Western Distributor 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Contributions to new primary and secondary Fife Council £6,067 Dunfermline – wide contributions towards additional secondary capacity school provision are now sought – see Planning Obligations Supplementary Guidance 2017.

Additional capacity required by 2022.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

39

Action Lead Cost Status/ Next Steps Wastewater Infrastructure Scottish Water TBC A Strategic Network Impact Assessment for the Dunfermline Catchment /Development has been initiated by Scottish Water to understand the cumulative Community impact of development on the drainage infrastructure. The outputs of this activity are expected in mid-2018. Interim solutions are being assessed with developers in the meantime to ensure development is being accommodated.

In addition to the network studies, detailed Flow and Load/Process Unit assessments are being carried out at both the Ironmill Bay and Dunfermline Wastewater Treatment Works in 2018 to better understand any potential upgrade requirements to accommodate all forecast flows from proposed development in the catchment. Development is currently being permitted in lieu of any results or upgrade activities. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 ✔ Water Infrastructure Scottish Water TBC Water infrastructure is strong within the Dunfermline catchment, but the /Development cumulative effect of development will potentially require localised Community network upgrades. Individual Water Impact Assessments are a likely requirement with Scottish Water ultimately aiming to deliver a Strategic Network Impact Assessment within the next 2 years detailing any strategic upgrades required to support development. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Craigluscar Road/ Road (DUN040) and North Dunfermline (Swallow Drum) (DUN041) Action Lead Cost Status/ Next Steps Planning Applications (includes delivery of Developer Currently Pre-application submission made employment land, health care, renewables etc.) unknown 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

40

Action Lead Cost Status/ Next Steps Strategic and local road improvements, including Developer/ Currently Onsite works include partial delivery of the Northern Link Road. a Northern Link Road (DUN039, 041,043,044) and Landowner unknown Western Distributor

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

New primary schools and nursery Developer TBC Primary school required estimated date 22/23

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Contributions to a new secondary school Fife Council £6,067 Dunfermline – wide contributions towards additional secondary capacity are now sought – see Planning Obligations Supplementary Guidance 2017.

Additional capacity required by 2022.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Identification of suitable sites for healthcare Developer/ Currently Land to be made available for healthcare provision as part of facilities NHS Fife / Fife unknown masterplanning of each site. Council 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Wastewater Infrastructure Scottish Water TBC A Strategic Network Impact Assessment for the Dunfermline Catchment /Development has been initiated by Scottish Water to understand the cumulative Community impact of development on the drainage infrastructure. The outputs of this activity are expected in mid-2018. Interim solutions are being assessed with developers in the meantime to ensure development is being accommodated.

In addition to the network studies, detailed Flow and Load/Process Unit

41

Action Lead Cost Status/ Next Steps Wastewater Infrastructure (continued) Scottish Water TBC assessments are being carried out at both the Ironmill Bay and /Development Dunfermline Wastewater Treatment Works in 2018 to better understand Community any potential upgrade requirements to accommodate all forecast flows from proposed development in the catchment. Development is currently being permitted in lieu of any results or upgrade activities.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 ✔ Water Infrastructure Scottish Water TBC Water infrastructure is strong within the Dunfermline catchment, but the /Development cumulative effect of development will potentially require localised Community network upgrades. Individual Water Impact Assessments are a likely requirement with Scottish Water ultimately aiming to deliver a Strategic Network Impact Assessment within the next 2 years detailing any strategic upgrades required to support development.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Carnock Road (DUN042) Action Lead Cost Status/ Next Steps

Planning Applications (includes delivery of Developer Currently No information is available. Fife Council as Planning Authority will review employment land, health care, renewables etc.) unknown the continued inclusion of this proposal in the LDP. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Contributions to a new secondary school and/or Fife Council £6,067 Dunfermline – wide contributions towards additional secondary capacity provision of land are now sought – see Planning Obligations Supplementary Guidance 2017.

Additional capacity required by 2022. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

42

Action Lead Cost Status/ Next Steps Wastewater Infrastructure Scottish Water TBC A Strategic Network Impact Assessment for the Dunfermline Catchment /Development has been initiated by Scottish Water to understand the cumulative Community impact of development on the drainage infrastructure. The outputs of this activity are expected in mid-2018. Interim solutions are being assessed with developers in the meantime to ensure development is being accommodated.

In addition to the network studies, detailed Flow and Load/Process Unit assessments are being carried out at both the Ironmill Bay and Dunfermline Wastewater Treatment Works in 2018 to better understand any potential upgrade requirements to accommodate all forecast flows from proposed development in the catchment. Development is currently being permitted in lieu of any results or upgrade activities.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 ✔ Water Infrastructure Scottish Water TBC Water infrastructure is strong within the Dunfermline catchment, but /Development the cumulative effect of development will potentially require localised Community network upgrades. Individual Water Impact Assessments are a likely requirement with Scottish Water ultimately aiming to deliver a Strategic Network Impact Assessment within the next 2 years detailing any strategic upgrades required to support development. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

43

Halbeath (DUN043) Action Lead Cost Status/ Next Steps Planning Applications (includes delivery of Taylor Wimpey Currently Planning Permission in Principle submitted - 17/01677/EIA and employment land, health care, renewables etc.) unknown 17/01686/EIA

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 ✔ Strategic and local road improvements, including Taylor Wimpey Currently Onsite works include partial delivery of the Northern Link Road. a Northern Link Road (DUN039, 041,043,044) and unknown Western Distributor 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

New primary schools and nursery Taylor Wimpey Currently New primary school proposed at Halbeath as part of a current / Fife Council unknown application. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Contributions to a new secondary school Taylor Wimpey £6,067 Dunfermline – wide contributions towards additional secondary capacity / Fife Council are now sought – see Planning Obligations Supplementary Guidance 2017.

Additional capacity required by 2022. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Identification of suitable sites for healthcare Taylor Wimpey Currently Land to be made available for healthcare provision as part of facilities / NHS Fife / unknown masterplanning of each site. Fife Council

2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 2017/18 ✔

44

Action Lead Cost Status/ Next Steps Wastewater Infrastructure Scottish Water TBC A Strategic Network Impact Assessment for the Dunfermline Catchment /Development has been initiated by Scottish Water to understand the cumulative Community impact of development on the drainage infrastructure. The outputs of this activity are expected in mid-2018. Interim solutions are being assessed with developers in the meantime to ensure development is being accommodated.

In addition to the network studies, detailed Flow and Load/Process Unit assessments are being carried out at both the Ironmill Bay and Dunfermline Wastewater Treatment Works in 2018 to better understand any potential upgrade requirements to accommodate all forecast flows from proposed development in the catchment. Development is currently being permitted in lieu of any results or upgrade activities.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 ✔ Water Infrastructure Scottish Water TBC Water infrastructure is strong within the Dunfermline catchment, but the /Development cumulative effect of development will potentially require localised Community network upgrades. Individual Water Impact Assessments are a likely requirement with Scottish Water ultimately aiming to deliver a Strategic Network Impact Assessment within the next 2 years detailing any strategic upgrades required to support development. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Land to the north of Wellwood (DUN044) Action Lead Cost Status/ Next Steps Planning Applications (includes delivery of Omnivale Currently Planning Permission in Principle submitted for land to the north of employment land, health care, renewables etc.) unknown Wellwood - 17/00103/PPP

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 ✔ 45

Action Lead Cost Status/ Next Steps

Strategic and local road improvements, including Omnivale Currently Onsite works include partial delivery of the Northern Link Road. a Northern Link Road (DUN039, 041,043,044) and unknown Western Distributor 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Contributions to a new primary and secondary Omnivale / £6,067 Dunfermline – wide contributions towards additional secondary capacity school provision Fife Council are now sought – see Planning Obligations Supplementary Guidance 2017.

Additional capacity required by 2022. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Wastewater Infrastructure Scottish Water TBC A Strategic Network Impact Assessment for the Dunfermline Catchment /Development has been initiated by Scottish Water to understand the cumulative Community impact of development on the drainage infrastructure. The outputs of this activity are expected in mid-2018. Interim solutions are being assessed with developers in the meantime to ensure development is being accommodated.

In addition to the network studies, detailed Flow and Load/Process Unit assessments are being carried out at both the Ironmill Bay and Dunfermline Wastewater Treatment Works in 2018 to better understand any potential upgrade requirements to accommodate all forecast flows from proposed development in the catchment. Development is currently being permitted in lieu of any results or upgrade activities.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 ✔

46

Action Lead Cost Status/ Next Steps

Water Infrastructure Scottish Water TBC Water infrastructure is strong within the Dunfermline catchment, but the /Development cumulative effect of development will potentially require localised Community network upgrades. Individual Water Impact Assessments are a likely requirement with Scottish Water ultimately aiming to deliver a Strategic Network Impact Assessment within the next 2 years detailing any strategic upgrades required to support development. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Chamberfield Road (DUN046) Action Lead Cost Status/ Next Steps Planning Applications (includes delivery of Landowner/ Currently No information is available. Fife Council as Planning Authority will review employment land, health care, renewables etc.) Developer unknown the continued inclusion of this proposal in the LDP.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Contributions to a new primary and secondary Fife Council £6,067 Dunfermline – wide contributions towards additional secondary capacity school provision are now sought – see Planning Obligations Supplementary Guidance 2017.

Additional capacity required by 2022.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

47

Action Lead Cost Status/ Next Steps Wastewater Infrastructure Scottish Water TBC A Strategic Network Impact Assessment for the Dunfermline Catchment /Development has been initiated by Scottish Water to understand the cumulative Community impact of development on the drainage infrastructure. The outputs of this activity are expected in mid-2018. Interim solutions are being assessed with developers in the meantime to ensure development is being accommodated.

In addition to the network studies, detailed Flow and Load/Process Unit assessments are being carried out at both the Ironmill Bay and Dunfermline Wastewater Treatment Works in 2018 to better understand any potential upgrade requirements to accommodate all forecast flows from proposed development in the catchment. Development is currently being permitted in lieu of any results or upgrade activities. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Water Infrastructure Scottish Water TBC Water infrastructure is strong within the Dunfermline catchment, but the /Development cumulative effect of development will potentially require localised Community network upgrades. Individual Water Impact Assessments are a likely requirement with Scottish Water ultimately aiming to deliver a Strategic Network Impact Assessment within the next 2 years detailing any strategic upgrades required to support development. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

48

49

Kirkcaldy East – KDY025 Action Lead Cost Status/ Next Steps Planning Applications (includes delivery of Murray Estates Currently Planning application 10/01774/EIA approved for Kingslaw site employment land, health care, renewables etc.) (Kingslaw site) unknown

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 ✔

New and enhanced footpath/cycle links to town Developer / Currently To be provided by developers as part of applications on site. centre Fife Council unknown 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Introduction of a new bus/enhanced existing service Developer Currently To be implemented alongside phase 3 of the Kingslaw to provide a sustainable and alternative mode of unknown development once the through road is introduced. travel to key destinations within the town 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Safeguard land for the route of the Standing Stane Developer Currently Route to be provided by Murray Estates over their land holdings. Link Road that passes through the Kingslaw site, unknown Contributions from other sites in area will provide the bridge including the crossing over the east coast main line over the railway and remaining part of road to east of railway. and land to the west of the Standing Stane Road. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 ✔

Improvements to the Gallatown roundabout Murray Estates £1.4M Dependent on phasing of Kingslaw application 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

50

Action Lead Cost Status/ Next Steps Provision of a roundabout on Mitchelston Road (at Murray Estates £5.9M To be delivered alongside phase 3 of Kingslaw application. the junction of the A921 and the Mitchelston Estate) 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Improvements at Redhouse Roundabout and part of Murray Estates £11M To be delivered alongside phasing of Kingslaw application. the Standing Stane link, to the west side of the east coast main line will be provided by the development at Kingslaw. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

The remainder including the further expansion of Transport Scotland See Strategic Funded by contributions across Kirkcaldy and Glenrothes area. the Redhouse Roundabout, the remainder of the / Fife Council / Transport Contributions based on distance from infrastructure. See A915, Standing Stane Link Road and improvements Developers section strategic transport section for more information. to Randolph Road and Boreland roundabout will all be provided by development at the rest of the Kirkcaldy East SLA.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Kingslaw: New primary school and nursery with Fife Council / Currently One primary school to be provided as part of phase 4 of Kingslaw associated recreation and play facilities Developers unknown development. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Boreland: New primary school and nursery with Fife Council / Currently Site to provide other primary school at as yet unknown date. associated recreation and play facilities Developers unknown 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

51

Action Lead Cost Status/ Next Steps Contributions sought towards secondary school Fife Council / £1,071 per £1,071 per house using cross Kirkcaldy methodology. provision Developers house 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Identification of suitable sites for healthcare Fife Council / NHS Currently Land to be made available for healthcare provision as part of facilities /Developers unknown masterplanning of each site. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Wastewater Infrastructure Scottish Water Currently A Drainage Impact Assessment has been carried out for the initial /Development unknown Kingdom Park allocation of the SDA. Scottish Water is currently Community (Dec 17) working with the developer to agree solutions and understand proposed delivery plans. 135 sewer connections have been permitted prior to any network mitigation measures. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 ✔

Water Infrastructure Scottish Water/ Currently Water infrastructure requirements are understood by the Development unknown development community following a Water Impact Assessment Community and delivery plans are being developed in conjunction with Scottish Water. 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 2017/18 ✔

52

53

Kirkcaldy South West – KDY026 Action Lead Cost Status / Next steps Planning Applications (includes delivery of Cala Currently Planning application submitted for mixed use development - employment land, health care, renewables etc.) unknown 10/03561/EIA

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 ✔

Contributions will also be required to necessary Cala £4,695 per Funded by contributions across Kirkcaldy area. Contributions based strategic transport interventions dwelling on distance from infrastructure. See strategic transport section for more information.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

New and enhanced footpath/cycle links to town Cala £40,000 Identified within the Masterplan submitted as part of the planning centre, coastal path network and surrounding application. parks/leisure facilities

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Access/junction and transport corridor upgrades Cala £75,000 Identified within the Masterplan submitted as part of the planning including new footpaths/cycleways to coastal application. path, the town centre, Balwearie Golf Course, and Beveridge Park

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

54

Action Lead Cost Status / Next steps Introduction of a new bus/enhanced existing Cala Currently Identified within the Masterplan submitted as part of the planning service to provide a sustainable and alternative unknown application. Buses will use the core road network, the roads will be mode of travel to key destinations within the designed to accommodate buses and allow ease of movement town through these routes. Buses will link the key destinations and residential areas within the settlement; provide links back to Kirkcaldy Town Centre and access to wider destinations on the existing road network.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Access Path & Secure Route to School Cala Approx. Detailed route drawn up and costed – agreement to be reached on £372,000 implementation. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Provision of a 1.5 stream Primary School and Cala £11,650,000 School location identified within Masterplan submitted as part of nursery (specification to include community *based on the planning application. access) current costs 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 ✔

Transporting pupils to “Virtual” Primary School Cala £30 - £40K per To be agreed with Education. annum 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Secondary school Contributions Cala £1,071 per £1,071 per house using cross Kirkcaldy methodology. dwelling 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

55

Action Lead Cost Status / Next steps Identification of suitable sites for healthcare Developer/ NHS Currently Land to be made available for healthcare provision as part of facilities Fife/ Fife Council unknown masterplanning of each site.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 ✔ Wastewater Infrastructure Scottish Water/ Currently A Drainage Impact Assessment will be required to understand what Developer unknown impact, if any, this development is likely to have on the existing drainage infrastructure. Any unacceptable impacts will need to be mitigated by potential drainage infrastructure upgrades.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Water Infrastructure Scottish Water/ Currently A Water Impact Assessment will be required to understand what Developer unknown impact, if any, this development is likely to have on the existing drainage infrastructure. Any unacceptable impacts will need to be mitigated by potential drainage infrastructure upgrades.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

56

57

Levenmouth Strategic Land Allocation - LVA001 Action Lead Cost Status/ Next Steps Planning Applications (includes delivery of Developer Currently Proposal of Application Notice (June 2015). PAN consultation took employment land, health care, renewables etc.) unknown place during Summer 2015 and Spring 2017. Final PAN Consultation anticipated early 2018. EIA Scoping complete (June 2016). 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Contributions will also be required to necessary Developer Currently Funded by contributions across Kirkcaldy and Glenrothes area. strategic transport interventions in the Kirkcaldy unknown Contributions based on distance from infrastructure. See strategic and Glenrothes Area. transport section for more information.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

New and enhanced footpath /cycle routes linking Developer Currently Specific requirements to be determined as part of the planning to existing core paths, the River Leven Valley, the unknown application. network and surrounding parks/leisure facilities.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Access/junction and transport corridor upgrades, Developer Currently Final route of Levenmouth Link Road to be determined through the including upgrades to Percival Road and provision unknown masterplanning process. of an east-west link road between Percival Road, Methilhaven Road and Sea Road. Specific requirements to be determined as part of the planning application. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Introduction of a new/ enhanced bus service to Developer Currently Specific requirements to be determined as part of the planning provide a sustainable and alternative mode of unknown application. travel to key destinations within the town. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

58

Action Lead Cost Status/ Next Steps A new primary school and nursery with Developer Currently Specific requirements to be determined as part of the planning associated recreation and play facilities. unknown application. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Contributions sought towards additional Developer Currently Land to be made available for secondary school provision as part of secondary school capacity. unknown masterplanning of each site. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Identification of suitable sites for healthcare Developer/ Currently Land to be made available for healthcare provision as part of facilities NHS Fife / Fife unknown masterplanning of each site. Council 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 ✔ Drainage Infrastructure Scottish Water/ Currently A Drainage Impact Assessment will be required to understand what Development unknown impact, if any, this development is likely to have on the existing Community drainage infrastructure. Any unacceptable impacts will need to be mitigated by potential drainage infrastructure upgrades. Joint drainage solution for employment land and wider SLA are currently being explored.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 ✔ Water Infrastructure Scottish Water/ Currently A Water Impact Assessment will be required to understand what Development unknown impact, if any, this development is likely to have on the existing Community drainage infrastructure. Any unacceptable impacts will need to be mitigated by potential drainage infrastructure upgrades. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

59

60

Lochgelly Strategic Land Allocation - LGY007 Action Lead Cost Status/ Next Steps Planning Applications (includes delivery of Developer Currently No information is available. Fife Council as Planning Authority will employment land, health care, renewables etc.) unknown review the continued inclusion of this proposal in the LDP. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Contributions will also be required to necessary Developer Currently Funded by contributions across Dunfermline and West area. strategic transport interventions in the unknown Contributions based on distance from infrastructure. See strategic Dunfermline and West Area. transport section for more information.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

New and enhanced footpath/cycle routes linking Developer Currently To be implemented as part of wider development. to existing core paths, and surrounding unknown parks/leisure facilities. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Access/junction upgrades (as identified in the Developer Currently To be implemented as part of wider development. Lochgelly Transport Assessment or information unknown that supersedes that document). 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Introduction of a new/enhanced bus service to Developer Currently Specific requirements to be determined as part of planning provide a sustainable and alternative mode of unknown application. travel to key destinations within the town. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

61

Action Lead Cost Status/ Next Steps A new primary school and nursery with Developer Currently Specific requirements to be determined as part of the planning associated recreation and play facilities unknown application. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

A contribution to the Secondary School Developer TBC Specific requirements to be determined as part of the planning application. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Park and play area provision and/or contribution Developer Currently Specific requirements to be determined as part of the planning to enhancement of greenspaces close to unknown application. residential areas. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Community facilities including healthcare. Developer/ Currently Specific requirements to be determined as part of the planning NHS Fife / unknown application. Fife Council The need to identify land for relevant healthcare infrastructure will be addressed through the masterplanning process.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Drainage Infrastructure Scottish Water/ Currently Scottish Water is carrying out a Strategic Network Impact Assessment Development unknown of the Lochgelly drainage network. This is due to be completed by Community Summer 2018, following which any network mitigation will be better understood. Developer responsibilities and contributions will also be clarified at this time. Drainage capacity within the Lochgelly catchment is currently limited. Early engagement with Scottish Water

62

Action Lead Cost Status/ Next Steps Drainage Infrastructure (continued) Scottish Water/ Currently to understand individual development requirements as early as Development unknown possible is highly recommended. Community 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 ✔ Water Infrastructure Scottish Water/ Currently Water infrastructure within the Lochgelly catchment is currently Development unknown subject of capital works by Scottish Water due to a small number of Community historical low pressure customer issues. A Water Impact Assessment is a likely requirement of any notable development within the catchment where network upgrades may be required to be carried out by developers.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

63

64

St Andrews Strategic Development Area – STA001 Action Lead Cost Status/ Next Steps Craigtoun: Planning Applications (includes Mount Melville Ltd Currently Application submitted - 15/01823/EIA delivery of employment land, health care, unknown Processing Agreement in place setting out timescales. renewables etc.) Committee March 2018 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 ✔ North Haugh: Planning Applications (includes St Andrews West LLP Currently 18/00280/EIA - Planning in Principle for Mixed Use Development delivery of employment land, health care, unknown (comprising Residential (Circa 900 private and affordable homes); renewables etc.) University Uses; Secondary School; Business and Employment; Retail; Care Home; Hotel; Green Network; Road Link; and, associated Infrastructure).

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Road link between A91 and Craigtoun Road to St Andrews West LLP Currently Planning application submitted for construction of link road and minimise impact of development on the town unknown roundabout - 17/03467/FULL centre and improve travel around the town.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 ✔

A new community primary school and nursery Mount Melville Ltd / Currently To be agreed as part of the planning application. with associated recreation and play facilities St Andrews West LLP unknown

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

New Madras Secondary to be built at North Fife Council Currently Although shown as part of the overall Masterplan Fife Council are to Haugh. unknown submit a separate planning application for the new Madras Secondary School. Planning Application submitted - 18/00295/FULL.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

65

Action Lead Cost Status/ Next Steps Drainage Infrastructure Scottish Water Currently Scottish Water is in close contact with the development community /Development unknown within the St Andrews Catchment and are developing a drainage Community strategy for the SDA. A Strategic Network Impact Assessment is being funded by Scottish Water and is likely to be completed by Summer 2018. A delivery plan for any necessary network upgrades will follow soon after.

A recent Flow and Load/Process Unit Assessment at the St Andrews Wastewater Treatment Works have identified a small area of capital investment to enable the initial 500 housing units with a larger upgrade likely in future years to support the remainder. Scottish Water is currently funded for this particular element (Part 4) of the drainage system. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 ✔ Water Infrastructure Scottish Water Currently A Strategic Water Impact Assessment will be carried out by Scottish /Development unknown Water to ensure any cumulative impact of development on the St Community Andrews network is understood.

2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 2017/18 ✔

66

67

Kelty South West (KEL005) – capacity 900 houses Action Lead Cost Status/ Next Steps Planning Applications (includes delivery of I&H Brown Currently Live application – 16/03915/EIA employment land, health care, renewables etc.) unknown

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 ✔ Contributions will also be required to necessary I&H Brown £2,428 per Funded by contributions across Dunfermline and West area. strategic transport interventions in the dwelling Contributions based on distance from infrastructure. See strategic Dunfermline and West Area. transport section for more information.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

A 3.5 ha employment area to remain next to I&H Brown Currently To be agreed as part of the planning application. Junction 4 unknown 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Provision of Primary School I&H Brown £10,000,000 Specific requirements and timescale for delivery to be determined as part of the planning application.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Additional secondary school capacity I&H Brown TBC Specific requirements to be determined as part of the planning contribution. application. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Identification of suitable sites for healthcare I&H Brown/NHS Currently Land to be made available for healthcare provision as part of facilities Fife /Fife Council unknown masterplanning of each site. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

68

Action Lead Cost Status/ Next Steps Drainage Infrastructure Scottish water Currently A Drainage Impact Assessment is required to understand what impact, if /I&H Brown unknown any the new development will have on the existing infrastructure. Network upgrades may be required to support the development. These must be funded and carried out at the developers’ expense. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 ✔ Water Infrastructure Scottish Currently A Water Impact Assessment is required to understand what impact, if Water/I&H unknown any the new development will have on the existing infrastructure. Brown Network upgrades may be required to support the development. These must be funded and carried out at the developer’s expense. 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 2017/18 ✔

Glencraig East (GLC001) – capacity 275 houses Action Lead Cost Status/ Next Steps Planning Applications (includes delivery of Landowner/ Currently No information is available. Fife Council as Planning Authority will employment land, health care, renewables etc.) Developer unknown review the continued inclusion of this proposal in the LDP.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Contributions will also be required to necessary Landowner/ Currently Funded by contributions across Dunfermline and West area. strategic transport interventions in the Developer unknown Contributions based on distance from infrastructure. See strategic Dunfermline and West Area. transport section for more information. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Contributions to education capacity Landowner/ Currently Contributions to be determined as part of the planning application Developer unknown process.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

69

Action Lead Cost Status/ Next Steps Vehicular access from the B920 shall be taken by Landowner/ Currently To be agreed as part of the planning application. means of a 4-arm roundabout located at the mid- Developer unknown point on the site frontage. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Drainage Infrastructure Scottish water Currently A Drainage Impact Assessment is required to understand what impact, /Developer unknown if any the new development will have on the existing infrastructure. Network upgrades may be required to support the development. These must be funded and carried out at the developers’ expense. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Water Infrastructure Scottish Water Currently A Water Impact Assessment is required to understand what impact, if /Developer unknown any the new development will have on the existing infrastructure. Network upgrades may be required to support the development. These must be funded and carried out at the developer’s expense.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Cardenden Road West (CDD004) – capacity 110 houses Action Lead Cost Status/ Next Steps Planning Applications (includes delivery of Developer Currently No information is available. Fife Council as Planning Authority will employment land, health care, renewables etc.) unknown review the continued inclusion of this proposal in the LDP. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

70

Action Lead Cost Status/ Next Steps

Contributions will also be required to necessary Developer Currently Funded by contributions across Kirkcaldy and Glenrothes area. strategic transport interventions in the Kirkcaldy unknown Contributions based on distance from infrastructure. See strategic and Glenrothes Area. transport section for more information.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Contributions to education capacity Developer Currently Contributions to be determined as part of the planning application unknown process. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Drainage Infrastructure Scottish Water Currently A Drainage Impact Assessment may be required to understand what / Developer unknown impact, if any the new development will have on the existing infrastructure. Network upgrades may be required to support the development. These must be funded and carried out at the developers’ expense.

Existing Scottish Water drainage infrastructure (combined sewers) traverse the site and will require to be adequately protected both during and after construction. Early engagement with Scottish Water is highly recommended.

Early engagement with Scottish Water is recommended. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

71

Cardenden Road East (CDD005) – capacity 170 houses Action Lead Cost Status/ Next Steps Planning Applications (includes delivery of Developer Currently No information is available. Fife Council as Planning Authority will employment land, health care, renewables etc.) unknown review the continued inclusion of this proposal in the LDP.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Contributions will also be required to necessary Developer Currently Funded by contributions across Kirkcaldy and Glenrothes area. strategic transport interventions in the Kirkcaldy unknown Contributions based on distance from infrastructure. See strategic and Glenrothes Area. transport section for more information.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Contributions to education capacity Developer Currently Contributions to be determined as part of the planning application unknown process. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Drainage infrastructure Scottish Water/ Currently A Drainage Impact Assessment may be required to understand what Developer unknown impact, if any the new development will have on the existing infrastructure. Network upgrades may be required to support the development. These must be funded and carried out at the developers’ expense.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Water Infrastructure Scottish Water / Currently A Water Impact Assessment may be required to understand what Developer unknown impact, if any the new development will have on the existing infrastructure. Network upgrades may be required to support the development. These must be funded and carried out at the developers’ expense.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

72

Laurence Park South (KLS001) – capacity 211 houses Action Lead Cost Status/ Next Steps Planning Applications (includes delivery of Developer Currently No information is available. Fife Council as Planning Authority will employment land, health care, renewables unknown review the continued inclusion of this proposal in the LDP. etc.) 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 Contributions will also be required to Developer Currently Funded by contributions across Kirkcaldy and Glenrothes area. necessary strategic transport interventions in unknown Contributions based on distance from infrastructure. See strategic the Kirkcaldy and Glenrothes Area. transport section for more information.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Contributions to education capacity Developer Currently Contributions to be determined as part of the planning application unknown process.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Drainage infrastructure Scottish Water/ Currently A Drainage Impact Assessment may be required to understand what Developer unknown impact, if any the new development will have on the existing infrastructure. Network upgrades may be required to support the development. These must be funded and carried out at the developers’ expense. 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 2017/18

73

Action Lead Cost Status/ Next Steps

Water Infrastructure Scottish Water/ Currently A Water Impact Assessment may be required to understand what Developer unknown impact, if any the new development will have on the existing infrastructure. Network upgrades may be required to support the development. These must be funded and carried out at the developers’ expense.

A Scottish Water Trunk Main traverses the site. Early engagement with Scottish Water is essential to ensure appropriate measures are in place to manage this asset both during and after construction. Stand- off distances may need to be agreed beforehand.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Laurence Park North (KLS002) – capacity 14 houses Action Lead Cost Status/ Next Steps Planning Applications (includes delivery of Developer Currently No information is available. Fife Council as Planning Authority will employment land, health care, renewables etc.) unknown review the continued inclusion of this proposal in the LDP . 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Contributions will also be required to necessary Developer Currently Funded by contributions across Kirkcaldy and Glenrothes area. strategic transport interventions in the unknown Contributions based on distance from infrastructure. See strategic Kirkcaldy and Glenrothes Area. transport section for more information.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Contributions to education capacity Developer Currently Contributions to be determined as part of the planning application unknown process. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

74

Land to the north of Lumphinnans (LPH003) – capacity 300 houses Action Lead Cost Status/ Next Steps Planning Applications (includes delivery of Developer Currently No information is available. Fife Council as Planning Authority will employment land, health care, renewables etc.) unknown review the continued inclusion of this proposal in the LDP.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 Contributions will also be required to necessary Developer Currently Funded by contributions across Dunfermline and West area. strategic transport interventions in the unknown Contributions based on distance from infrastructure. See strategic Dunfermline and West Area. transport section for more information.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Contributions to education capacity Developer Currently Contributions to be determined as part of the planning application unknown process. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Attention is drawn to the possibility of a shallow Developer Currently To be carried out as part of planning application. coal deposit: the potential for extraction prior unknown to or as part of the development shall be investigated

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

75

Action Lead Cost Status/ Next Steps Drainage Infrastructure Scottish Currently A Drainage Impact Assessment will be required to understand what Water/ unknown impact, if any the new development will have on the existing Developer infrastructure. Network upgrades may be required to support the development. These must be funded and carried out at the developers’ expense.

A viable surface water solution involving SUDS must be understood prior to applying for technical approval. Scottish Water will not approve a surface water connection to the existing Combined Sewer network.

Scottish Water existing combined sewers traverse the site. Early engagement with Scottish Water is essential to ensure appropriate measures are in place to manage these assets both during and after construction. Stand-off distances may need to be agreed beforehand.

Early engagement with Scottish Water is highly recommended. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Water Infrastructure Scottish Currently A Water Impact Assessment may be required to understand what Water/ unknown impact, if any the new development will have on the existing Developer infrastructure. Network upgrades may be required to support the development. These must be funded and carried out at the developers’ expense. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

76

Land North and West of Thornton (THO003) – capacity 900 houses Action Lead Cost Status/ Next Steps Planning Applications (includes delivery of Developer Currently No planning applications received. employment land, health care, renewables etc.) unknown

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Contributions will also be required to necessary Developer Currently Funded by contributions across Kirkcaldy and Glenrothes area. strategic transport interventions in the unknown Contributions based on distance from infrastructure. See strategic Kirkcaldy and Glenrothes Area. transport section for more information.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Provision of Primary School and nursery. Developer Currently Specific requirements and timescale for delivery to be determined as unknown part of the planning application. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Additional secondary school capacity Developer TBC Specific requirements to be determined as part of the planning contribution. application. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Identification of suitable sites for healthcare Developer/NHS Currently Land to be made available for healthcare provision as part of facilities Fife/Fife Council unknown masterplanning of each site. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

A vehicular route linking Main Street and Developer Currently Specific requirements to be determined as part of the planning Strathore Road is required. unknown application. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

77

Action Lead Cost Status/ Next Steps A Development Framework should be prepared Developer Currently The development framework is to be produced by the developers of by the developer for Fife Council approval. unknown the site. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Drainage Infrastructure Scottish Water/ Currently A Drainage Impact Assessment has been carried out by the developer Developer unknown to understand whether any network mitigation is required to permit connection to the existing public system. Results of that assessment are currently under review by Scottish Water’s modelling team (Dec 17) and a clear direction is expected in early 2018.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Spittal Farm, Elmbank Terrace/Station Road (THO004) – capacity 73 houses Action Lead Cost Status/ Next Steps Planning Applications (includes delivery of Developer Currently No information is available. Fife Council as Planning Authority will employment land, health care, renewables etc.) unknown review the continued inclusion of this proposal in the LDP. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Contributions will also be required to necessary Developer Currently Funded by contributions across Kirkcaldy and Glenrothes area. strategic transport interventions in the unknown Contributions based on distance from infrastructure. See strategic Kirkcaldy and Glenrothes Area. transport section for more information.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Contributions to education capacity Developer Currently Contributions to be determined as part of the planning application unknown process. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

78

Land off Main Street (THO005) – capacity 6 houses Action Lead Cost Status/ Next Steps Planning Applications (includes delivery of Developer Currently No information is available. Fife Council as Planning Authority will employment land, health care, renewables unknown review the continued inclusion of this proposal in the LDP. etc.) 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

79

6. Settlement Proposals (with Actions)

6.1 The interventions needed to deliver the proposed development sites in the Local Development Plan are listed below. The tables below set out the interventions that will be required for successful delivery of each proposed development; these will be required to be delivered if and when sites come forward. So as to avoid duplication proposals which relate to strategic transport interventions and strategic development area/strategic land allocations are listed separately within earlier sections of the document. The following should be read in conjunction with the Local Development Plan, the Planning Obligations Supplementary Guidance and Housing Land Audit.

Anstruther and Cellardyke (Click here to view interactive map) Housing/Housing Opportunity Site Site Site specific actions Delivery Status/Next Steps Cellardyke Who: Muir Homes This site is under construction. 339 houses approved and 250 completions Caravan Park Est. Capacity: 331 to date. 10/01104/ARC (ANS001) Area: 10.7 ha 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 ✔

Crichton Street Who: Private Sector This site is complete. (ANS002) Est. Capacity: 5 Area: 0.1 ha 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 COMPLETE

Bankwell Road Who: Private Sector Planning Permission in Principle granted for the erection of 11 flatted (ANS003) Est. Capacity: 11 dwellings (Renewal of 07/01394/EOPP and 10/03972/PPP) 14/00318/PPP Area: 0.2 ha 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

80

Site Site specific actions Delivery Status/Next Steps Depot, Who: Fife Council/ No information is available. Fife Council as Planning Authority will review Pittenweem Private Sector the continued inclusion of this proposal in the LDP. Road (ANS004) Est. Capacity: 12 Area: 0.4 ha 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Employment Site Site specific actions Delivery Status/Next Steps St Andrews Retain scope to link site to the Who: Fife Council/ Planning permission has been granted for parts of this site (16/00804/FULL Road extension established employment area to the Private Sector and 17/00856/FULL and 17/03834/FULL) for industrial uses. (ANS005) south. Area: 3.2 ha

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Development Opportunity Site Site specific actions Delivery Status/Next Steps Adjacent to fire Who: Fife Council No information is available. Fife Council as Planning Authority will review station Area: 0.1 ha the continued inclusion of this proposal in the LDP. (ANS006) 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

81

Allotments Site Site specific actions Delivery Status/Next Steps Fife Council is actively pursuing the Who: Fife Council/ No information is available. Fife Council as Planning Authority will review the (ANS007) identification of appropriate land for Private Sector continued inclusion of this proposal in the LDP. allotment use in the Anstruther area. Area: 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Blairhall (Click here to view interactive map) Housing/Housing Opportunity Site Site Site specific actions Delivery Status/Next Steps Land south of Fund on-site infrastructure including Who: Private Sector 07/02860/WOPP Land To South Of Blairhall, Fife Blairhall vehicular access from South Street. Est. Capacity: 64 Outline planning permission for residential development and community (BLA001) Provide a financial contribution to Area: 2.5 ha and recreational facilities with associated roads, landscaping play areas, car contribute to the overall restoration of parking and pond the Comrie Colliery site during the lifetime of the Local Plan.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Comrie Castle Who: Private Sector No information is available. Fife Council as Planning Authority will review the (BLA002) Est. Capacity: 15 continued inclusion of this proposal in the LDP. Area: 1 ha Dunfermline wide contributions towards additional secondary capacity are now sought – see Planning Obligations Supplementary Guidance 2017. Additional capacity required by 2022

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

82

Site Site specific actions Delivery Status/Next Steps Land West of Who: Omnivale 16/02408/PPP Land To North And West of Rintoul Avenue. Planning Rintoul Avenue Est. Capacity: 6 permission in principle for residential development (Section 42 application (BLA003) Area: 1.7 ha to vary condition 3 of planning permission in principle reference 10/04238/PPP) 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

South Avenue Who: Fife Council No information is available. Fife Council as Planning Authority will review the (BLA004) Est. Capacity: 15 continued inclusion of this proposal in the LDP. Area: 0.8 ha 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Burntisland (Click to view interactive map) Housing/Housing Opportunity Site Site Site specific actions Delivery Status/Next Steps Alcan Site Who: Private Sector This site is complete. (BUR001) Est. Capacity: 96 Area: 5.5 ha 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 COMPLETE

Grange Farm Who: Deveron Homes Site is under construction. 6 houses completed. 11/06418/FULL (BUR002) Est. Capacity: 37 Area: 2.8 ha 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 ✔

83

Site Site specific actions Delivery Status/Next Steps Land at Haugh Who: Fife Council/ Private Sector No information is available. Fife Council as Planning Authority Road (BUR003) Est. Capacity: 20 will review the continued inclusion of this proposal in the LDP. Area: 2.3 ha 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Grange Distillery Grange Road to be upgraded to Who: Bandron Ltd No information is available. Fife Council as Planning Authority (BUR005) provide access to this site. Est. Capacity: 49 will review the continued inclusion of this proposal in the LDP. Area: 1.8 ha 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Greenmount Who: Private Sector Site has planning permission for 11 dwellings and is under Hotel (BUR006) Est. Capacity: 20 construction. 15/00825/PPP Area: 0.8 ha 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 ✔

Employment Site Site specific actions Delivery Status/Next Steps Roundhouse, Who: Fife Council Planning permission granted for erection of office building and North of Area: 0.6 ha associated infrastructure - 08/03525/CFULL Lammerlaws Road (BUR008) 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

84

Site Site specific actions Delivery Status/Next Steps South of Who: Private Sector Planning permission granted for erection of storage building Lammerlaws Area: 0.5 ha (Class 6) and boundary fence - 16/01092/FULL Road (BUR009) 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Railway Sidings Who: Private Sector No information is available. Fife Council as Planning Authority (BUR010) Area: 1.6 ha will review the continued inclusion of this proposal in the LDP. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Development Opportunity Site Site specific actions Delivery Status/Next Steps Former cinema Who: Private Sector Planning permission granted for erection of 8 flatted dwellings site, High Street Est. Capacity: 40 and ground floor retail (class 1) unit - 08/03012/CFULL (BUR004) Area: 0.1 ha 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Sports Facility Site Site specific actions Delivery Status/Next Steps Lammerlaws Who: Fife Council This site has planning permission for a floodlit synthetic turf Road Area: 0.5 ha pitch and multi-use games area – works complete. (BUR007) 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 COMPLETE

85

Cairneyhill (Click here to view interactive map) Housing/Housing Opportunity Site Site Site specific actions Delivery Status/Next Steps Pitdinnie Road Provide a financial contribution to help fund the Who: Private Sector Planning permission in principle granted for residential (CNH001) provision of multi-use community facility (per CNH Est. Capacity: 10 development, serviced site for community hall and MUGA with 004). Area: 0.7 ha associated engineering, landscaping and infrastructure works (14/04038/PPP and 16/02529/ARC and 17/03501/ARC)

Dunfermline wide contributions towards additional secondary capacity are now sought – see Planning Obligations Supplementary Guidance 2017. Additional capacity required by 2022 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Conscience Cross fund the provision of employment land on site Who: Wemyss Estate No information is available. Fife Council as Planning Authority Bridge (north) CNH 002 Est. Capacity: 100 will review the continued inclusion of this proposal in the LDP.

(CNH002) Provision of a vehicular access to Glen Moriston Area: 4.9 ha Drive with the internal street network being Dunfermline wide contributions towards additional secondary designed to allow vehicular/ pedestrian access to the capacity are now sought – see Planning Obligations land to the north of Cairneyhill linking with sites CNH Supplementary Guidance 2017. 004, CNH005 and CNH006. Additional capacity required by 2022

Scottish Water may require Drainage Impact Assessment to understand impact on existing network.

Require Pre-Development Enquiry submission to Scottish Water to fully assess. Existing Scottish Water infrastructure (Trunk and Distribution mains) within potential footprint of site. These will require management / protection. Early engagement with Scottish Water is essential) 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

86

Site Site specific actions Delivery Status/Next Steps Land north of Provision of a vehicular access from the A994 Who: Avant Homes Planning permission in principle granted for residential Cairneyhill via CNH 002. A vehicular access from the D13 Est. Capacity: 250 development, serviced site for community hall and MUGA with (CNH005*) (by means of a 3-arm roundabout) shall be Area: 17 ha associated engineering, landscaping and infrastructure works provided if CNH002 does not progress. The (14/04038/PPP and 16/02529/ARC and 17/03501/ARC) vehicular access shall be provided prior to occupation of the 100th dwelling. Dunfermline wide contributions towards additional secondary capacity are now sought – see Planning Obligations Scottish Water: A Drainage Impact Assessment Supplementary Guidance 2017. is required to understand what impact, if any, Additional capacity required by 2022 this development will have on the existing network. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 ✔

Employment Site Site specific actions Delivery Status/Next Steps Conscience Who: Private Sector The site is within an area with planning permission in principle Bridge South Area: 0.9 ha for mixed use, residential and business development, with (CNH003) associated infrastructure - 07/01350/WOPP 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Leisure/Community Facilities Site Site specific actions Delivery Status/Next Steps Land to North of Who: Private Sector Planning permission in principle granted for residential Cairneyhill Area: development, serviced site for community hall and MUGA with (CNH004) associated engineering, landscaping and infrastructure works (14/04038/PPP and 16/02529/ARC and 17/03501/ARC)

2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 2017/18

87

Flooding and Drainage System Site Site specific actions Delivery Status/Next Steps Land east of This site along with site CNH002, CNH004 and Who: Private Sector Planning permission in principle granted for residential Pitdinnie Road CNH005 will contribute to providing settlement Area: 1.3 ha development, serviced site for community hall and MUGA with (CNH006) wide improvements to the local flooding and associated engineering, landscaping and infrastructure works drainage network and provide new Sustainable (14/04038/PPP and 16/02529/ARC and 17/03501/ARC) Urban Drainage Scheme (SUDS) solutions to resolve issues associated with localised flooding. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Charlestown (Click here to view interactive map) Housing/Housing Opportunity Site Site Site specific actions Delivery Status/Next Steps Land at the old Who: Avant Homes This site has planning permission for the erection of 4 semi- school Est. Capacity: 5 detached dwellinghouses with associated parking and (CHL002*) Area: 0.4 ha landscaping. 15/01888/FULL

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Employment Site Site specific actions Delivery Status/Next Steps Land at Scottish The preferred use will be cottage industry or Who: Private Sector No information is available. Fife Council as Planning Authority Lime Centre craft and enterprise employment. Area: 0.3 ha will review the continued inclusion of this proposal in the LDP. (CHL001) 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

88

Development Opportunity Site Site specific actions Delivery Status/Next Steps Land at The council will work with the landowner and the Who: Private Sector No information is available. Fife Council as Planning Authority Charlestown local community to consider the regeneration Area: 2 ha will review the continued inclusion of this proposal in the LDP. Harbour (Ballast potential of the site and the adjacent Bank) Charlestown Harbour and Charlestown Kilns. Site is listed on Buildings at Risk Register. (CHL003) Any proposals for the site shall include plans and specifications for the repair and restoration of Charlestown Harbour and Charlestown Kilns and shall be based on appropriate environmental, conservation, design and technical assessments.

Development must not take place in the intertidal area. All access will be via existing site access and will not be taken over the foreshore.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Conservation Area Extension Site Site specific actions Delivery Status/Next Steps Camsie House Who: Fife Council Conservation area appraisal/management plan (CHL004) Area: 3.2 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

89

Colinsburgh (Click here to view interactive map) Housing/Housing Opportunity Site Site Site specific actions Delivery Status/Next Steps South East of Scottish Water: A Drainage Impact Assessment Who: Private Sector No information is available. Fife Council as Planning Authority Village is potentially required to understand what Est. Capacity: 43 will review the continued inclusion of this proposal in the LDP. (COB001) impact this development will have on the Area: 4.7 ha existing network. This should be initiated by the developer. In addition, a Growth Project may be required at the Colinsburgh WWTW which serves this catchment. Scottish Water is funded for growth following the provision of the 5 Growth Criteria.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

South Wynd Who: Private Sector No information is available. Fife Council as Planning Authority Depot Est. Capacity: 5 will review the continued inclusion of this proposal in the LDP. (COB002) Area: 0.3 ha 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

School Expansion Site Site specific actions Delivery Status/Next Steps Main Street Before work begins on the school expansion, Who: Fife Council No information is available. Fife Council as Planning Authority (COB003) agreement should be reached on the relocation Area: <0.1 ha will review the continued inclusion of this proposal in the LDP. of the existing smiddy to an alternative acceptable location.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

90

Cowdenbeath (Click here to view interactive map) Housing/Housing Opportunity Site Site Site specific actions Delivery Status/Next Steps Beath Glebe Who: Private Sector No information is available. Fife Council as Planning Authority (COW001) Est. Capacity: 33 will review the continued inclusion of this proposal in the LDP. Area: 1.3 ha 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

King Street 2 Who: Fife Council This site has planning permission and is currently under (COW002) Est. Capacity: 70 construction. (13/03814/FULL and 14/02248/FULL and Area: 2.2 ha 15/02374/FULL) 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 ✔

Leuchatsbeath Who: Bellway Homes This site has planning permission and is currently under (COW003) Est. Capacity: 406 construction. 10/04151/FULL and 12/02201/FULL Area: 21 ha 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 ✔ Adjacent to gas Who: Private Sector Planning permission granted for remediation works to works (COW004) Est. Capacity: 5 undertake decontamination of gas works - 17/03152/FULL Area: 0.2 ha 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Rosebank Who: Private Sector No information is available. Fife Council as Planning Authority (COW005) Est. Capacity: 35 will review the continued inclusion of this proposal in the LDP. Area: 0.9 ha 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

91

Employment Site Site specific actions Delivery Status/Next Steps Glenfield Who: Private Sector No information is available. Fife Council as Planning Authority Industrial Estate Area: 1.6 ha will review the continued inclusion of this proposal in the LDP. (COW006) 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Woodend Who: Private Sector Planning application submitted for change of use from open Industrial Estate Area: 0.5 ha to space to storage for vehicles in conjunction with vehicle (COW007) hire business (Class 6) including siting of portacabin and erection of associated fencing (retrospective) - 17/02472/FULL 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Woodend Who: Private Sector This site has planning permission for the erection of 6 Business Centre Area: 0.8 ha residential care units. 13/01166/FULL (COW009) 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Development Opportunity Site Site specific actions Delivery Status/Next Steps Former Social Who: Fife Council/ Private Currently being developed as a Community Hub by Fife Work Office Sector Council Community Learning and Development. Due to open (COW008) Area: 0.3 ha shortly. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

92

Site Site specific actions Delivery Status/Next Steps Former Police Who: Aldi Planning permission granted for erection of retail foodstore Station site Area: 0.8 ha (Class 1) with ancillary works including car parking, access (COW010) and landscaping - 14/00803/FULL 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

North End Park Who: Private Sector Planning permission granted for Class 1 retail units. (COW011) Area: 2.1 ha 15/04183/FULL 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

High Street Development should be designed to provide Who: Fife Council/ Private Funding fully assembled, being developed under delegated Gap site public open space fronting onto the High Street. Sector road authority powers therefore planning permission not (COW012) This space may take the form of a square suitable Area: 0.6 ha required. Work due to start on site April/May 18 and for public gatherings and allow scope for trading completed by September 18. market stalls.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 ✔

Crail (Click here to view interactive map) Housing/Housing Opportunity Site Site Site specific actions Delivery Status/Next Steps Pinkerton Who: Private Sector This site is complete. Farm Phase 2 Est. Capacity: 62 (CRA001) Area: 1.9 ha 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 COMPLETE

93

Site Site specific actions Delivery Status/Next Steps Crail North A revised Indicative Development Framework, is to Who: Fife Council/ Fife Council will begin the preparation of the revised (CRA002) be prepared by the council in collaboration with Private Sector Framework in late 2017 with the completion anticipated in landowners and/or developers. The community will Est. Capacity: 320 2018. be consulted on the revised development Area: 12.1 ha framework and its preparation.

Investigate the need for the on-site provision of primary health care facilities.

The proposal will also provide an extension to the existing cemetery and 0.5 hectares of employment land.

Scottish Water: Drainage and Water Impact Assessments will be required to understand what if any impact this development has on existing water and wastewater infrastructure. The developer must carry these out prior to receiving technical approval. The cumulative impact of growth in this catchment will potentially trigger a growth requirement at the Crail WWTW. Scottish Water is funded for growth following the provision of the 5 growth criteria. No forecast of constraint due to lack of capacity at WWTW to date. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

94

Crossford (Click here to view interactive map) Allotments Site Site specific actions Delivery Status/Next Steps Keavil Farm/ The site will be safeguarded for allotment use. Who: Fife Council Fife Council Allotment Strategy Update considered (Thursday 31 Nursery Alternative uses will not be supported if this results Area: 3.4 ha Aug 2017) by Fife Council Community & Housing Services (CRF001) in the loss of allotments which continue to meet Committee. Site identified as a high priority meeting existing and demand. expected demand/s.

Delivery monies to be identified (Fife Council) and Crossford Community Association management partnership to be agreed.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Cupar (Click here to view interactive map)

Proposals around Cupar include the Cupar Strategic Development Area (CUP 001)

Housing/Housing Opportunity Site Site Site specific actions Delivery Status/Next Steps St Columba’s Who: C Kennedy Development Brief produced; approved by North East Fife Area (CUP002) Est. Capacity: 15 Committee (12th November 2008). Area: 0.4 ha Planning application submitted for 8 flatted dwellings and 4 dwellinghouses. 16/00149/PPP

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

95

Site Site specific actions Delivery Status/Next Steps Kirk Wynd Who: Private Sector Site forms part of a wider development proposal “Cupar Inner (CUP003) Est. Capacity: 5 Court”. A Mixed housing and enterprise development utilising the Area: 0.1 ha derelict “backlands” and part of Fife Council’s underutilised car park. Development led by Kingdom Housing with Fife Council and Cupar Development Trust. Under the CARS/THI programme we are erecting full building height mesh screening with building image.

2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 2017/18

Provost Wynd, Who: Private Sector No information is available. Fife Council as Planning Authority will Former Est. Capacity: 10 review the continued inclusion of this proposal in the LDP. Leuchars Area: 0.2 ha Removals (CUP004) 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Employment Site Site specific actions Delivery Status/Next Steps Prestonhall Proposed relief road to be provided as part of Who: Private Sector No information is available. Fife Council as Planning Authority will East (CUP009) CUP001. Area: 8.4 ha review the continued inclusion of this proposal in the LDP.

Access may also be achieved through the adjacent trading estate to the west subject to achieving control of land, and the redevelopment of the existing Council depot.

Development2017/18 Opportunity2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 Site Site specific actions Delivery Status/Next Steps

96

Site Site specific actions Delivery Status/Next Steps Former Granary Who: Private Sector Planning permission garnted to convert, alter and extend Site, Station Area: 0.2 ha pub/nightclub to form class 2 offices and erect office/retail and Road (CUP005) 26 flatted dwellings on site of demolished rear extension and auction mart, form access and parking - 05/01493/EOPP 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Former ATS Who: Private Sector Development brief to be updated. Depot, St Area: 0.1 ha Site landscaped and temporary use licence granted for “street Catherine Street food” vending. /East Bridge (CUP006) 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Moathill Site Who: Private Sector No information is available. Fife Council as Planning Authority will (CUP007) Area: 0.2 ha review the continued inclusion of this proposal in the LDP. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Bonnygate Gap Who: Fife Council/ Development Brief approved by North East Fife Area Committee Site, Bonnygate Private Sector (November 2012). (CUP008) Area: <0.1 ha Site now fully acquired by Fife Council. Site forms part of a wider development proposal “Cupar Inner Court”. A Mixed housing and enterprise development utilising the derelict “backlands” and part of Fife Council’s underutilised car park. Development led by Kingdom Housing with Fife Council and Cupar Development Trust. Under the CARS/THI programme we are erecting full building height mesh screening with building image. Cemetery2017/18 Extension 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 Site Site specific actions Delivery Status/Next Steps

97

Site Site specific actions Delivery Status/Next Steps Ceres Road Who: Fife Council No information is available. Fife Council as Planning Authority will (CUP010) Area: 0.6 ha review the continued inclusion of this proposal in the LDP.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Drumoig (Click here to view interactive map) Housing/Commercial Leisure/Community Facility Site Site specific actions Delivery Status/Next Steps Drumoig A Development Framework must be prepared by Who: Drumoig Planning permission in principle granted for 36 houses at (DRG001) the developer for Fife Council approval. Developments Ltd Drumoig (15/01977/PPP) as part of mixed use Est. Capacity: 30 development.(17/02241/ARC) Local shop needed (could have residential Area: accommodation above). 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

98

Dunfermline and Halbeath (Click here to view interactive map)

Proposals around Dunfermline include the Dunfermline N/W/SW Strategic Land Allocation; the North Dunfermline Strategic Development Area; a number of strategic transport proposals; and a strategic education proposal.

Housing/Housing Opportunity Site Site Site specific actions Delivery Status/Next Steps 5-7 Comely Park Who: Comely Park Ltd This site has planning permission for housing. 11/04436/FULL (DUN001) Est. Capacity: 5 Area: 0.3 ha 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

6 Hill Street Who: Private Sector This site is complete. (DUN002) Est. Capacity: 6 Area: 0.1 ha 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 COMPLETE

Beveridge House Who: Private Sector This site has planning permission for housing. 11/00502/FULL (DUN003) Est. Capacity: 6 Area: 0.1 ha 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Brucefield Hotel Who: Private Sector This site is complete. (DUN004) Est. Capacity: 6 Area: 0.2 ha 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 COMPLETE

99

Site Site specific actions Delivery Status/Next Steps East Dunfermline Who: Private Sector This site is complete. North (C) Est. Capacity: 170 (DUN005) Area: 7.3 ha 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 COMPLETE

Campbell Street Who: Miller Homes This site has planning permission for housing and is under (DUN006) Est. Capacity: 184 construction. 74 units completed. 06/01651/WFULL Area: 2.2 ha 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 ✔

90 Campbell Street Who: Tuscan Planning permission has lapsed. (DUN007) Developments Est. Capacity: 24 Area: 0.2 ha 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

East Dunfermline Who: Taylor Wimpey This site has planning permission for housing - 81 units. North (F) Est. Capacity: 84 (DUN008) Area: 12.4 ha 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 COMPLETE

Kingdom Gateway Scottish Water: Early engagement with Scottish Who: Private Sector This site is complete. (G) (DUN009) Water recommended. Potential requirement Est. Capacity: 139 for network upgrades. Site requirements to be Area: 8.4 ha understood in context of wider development plans. 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 COMPLETE

100

Site Site specific actions Delivery Status/Next Steps Kingdom Gateway Who: Taylor Wimpey/ This site has planning permission for housing. (EF1) Registered Social 65 houses completed. (15/01882/FULL) (DUN010) Landlord Est. Capacity: 110 2018/19 2019/20 2020/21Area: 3.2 ha 2021/22 2022/23 2023/24 Post 2024 COMPLETE

Kingdom Gateway Who: Private Sector This site has outline planning permission for housing. (EF2) Est. Capacity: 80 (DUN011) Area: 2.3 ha 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 COMPLETE

Kingdom Gateway Who: Dundas Estates This site has planning permission and is under construction. (EF3) Est. Capacity: 105 25 units completed. (DUN012) Area: 5.6 ha 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 ✔ Trondheim Who: Private Sector This site is complete. Parkway West Est. Capacity: 80 (DUN013) Area: 2.5 ha 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 COMPLETE

Kingdom Gateway Who: Dundas Estates This site has planning permission for housing and is under (EF4) Est. Capacity: 54 construction. 22 units completed. (DUN014) Area: 1.6 ha 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 2017/18 ✔

101

Site Site specific actions Delivery Status/Next Steps Kingdom Gateway Who: Private Sector This site has planning permission for housing and is under (EF5) Est. Capacity: 27 construction. (DUN015) Area: 1.3 ha 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 COMPLETE

Woodmill Filling Who: Private Sector Planning permission has lapsed. Station Est. Capacity: 12 (DUN016) Area: 0.2 ha

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

East Dunfermline Who: Taylor Wimpey/ This site has planning permission for housing. 160 houses (North B) Persimmon completed. 10/04690/ARC, 13/01981/ARC and 14/03079/ARC (DUN017) Est. Capacity: 180 Area: 8.1 ha

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 ✔ Kingdom Gateway Who: Taylor Wimpey This site has planning permission for housing and is under (HI) (DUN018) Est. Capacity: 274 construction. 181 houses completed. 06/04235/WARM. Area: 8.3 ha 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 2017/18 ✔ Masterton Farm Who: Private Sector This site has planning permission for housing. 15/00801/PPP (DUN019) Est. Capacity: 35 Area: 1.1 ha 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

102

Site Site specific actions Delivery Status/Next Steps Rear of 179 Who: Private Sector This site has planning permission for housing. 14/00199/PPP Rumblingwell Est. Capacity: 35 (DUN020) Area: 1 ha

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

South Fod Farm Who: Barratt/ David This site has planning permission for housing 15/04144/FULL (DUN021) Wilson Est. Capacity: 26 Area: 2.6 ha 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Leys Park Road Who: Private Sector This site has planning permission for housing. (DUN022) Est. Capacity: 60 Area: 0.9 ha 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 COMPLETE

110 Halbeath Road Who: Tuscan This site has planning permission for housing. 07/02773/FULL (DUN023) Developments Est. Capacity: 9 Area: 0.1 ha 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

103

Site Site specific actions Delivery Status/Next Steps Blacklaw Road Scottish Water: Early consultation with Scottish Who: Private Sector This site has planning permission for housing and/or other (DUN024) Water regarding Surface Water management Est. Capacity: 131 uses. 10/00972/FULL and 10/04191/FULL plans is highly recommended. Scottish Water Area: 4.7 ha Dunfermline wide contributions towards additional secondary will not permit surface water into the existing capacity are now sought – see Planning Obligations combined sewer network. Supplementary Guidance 2017.

Additional capacity required by 2022

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Land North of Who: Private Sector This site has planning permission for a care home. Yewtree House, Est. capacity: 16 09/03109/FULL Masterton Area: 0.6 hectares (DUN025) 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

North West Corner Who: Private Sector No information is available. Fife Council as Planning Authority of Whitefield Road Est. Capacity: 13 will review the continued inclusion of this proposal in the LDP. (DUN026) Area: 0.5 ha

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

South West Corner Who: Private Sector No information is available. Fife Council as Planning Authority of Whitefield Road Est. Capacity: 11 will review the continued inclusion of this proposal in the LDP. (DUN027) Area: 0.4 ha 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

104

Site Site specific actions Delivery Status/Next Steps Meadowland Scottish Water: A Drainage Impact Assessment Who: Taylor Wimpey This site has planning permission for residential development - (DUN028) is required to understand what, if any impact this Est. Capacity: 90 16/02345/FULL. site will have on the existing sewer network. A Area: 6.3 ha Dunfermline wide contributions towards additional secondary Strategic Network Impact Assessment for the capacity are now sought – see Planning Obligations Dunfermline catchment is underway. However, Supplementary Guidance 2017. a standalone DIA may be acceptable if timescales Additional capacity required by 2022 require.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Lynebank Hospital A masterplan should be prepared by the Who: Barratt/ David Planning permission granted for construction of 114 (DUN029 a & b) developers and/or landowners for approval by Wilson residential units and ancillary development - 16/00557/FULL Fife Council for the hospital complex as a whole. Est. Capacity: 200 The master plan should address the need to Area: 7.6 ha Application submitted for erection of 33 houses (amendments ensure that development on the site does not to 15/04144/FULL and 16/00557/FULL) – 17/01901/FULL have an adverse effect on hospital activities. PAN submitted for residential development - 17/04076/PAN Scottish Water: A Drainage Impact Assessment is required to understand what, if any impact this site will have on the existing sewer network. A Strategic Network Impact Assessment for the Dunfermline catchment is underway. However, a standalone DIA may be acceptable if timescales require.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

105

Site Site specific actions Delivery Status/Next Steps Land at Masterton Who: Private Sector Dunfermline wide contributions towards additional secondary (west of Masterton Est. Capacity: 45 capacity are now sought – see Planning Obligations Road) (DUN030) Area: 1.7 ha Supplementary Guidance 2017. Additional capacity required by 2022

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Paton Street North Who: Campion Homes This site has planning permission and is under construction. 2 (DUN031) Timescale: units completed. 15/00850/FULL – Appeal sustained Est. Capacity: 30 Area: 1.5 ha 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 ✔

Paton Street South Who: Kingdom Housing This site has planning permission and is under construction - (DUN032) Association 15/00850/FULL Est. Capacity: 20 Area: 1 ha 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 ✔ School Row Who: Private Sector No information is available. Fife Council as Planning Authority (DUN033) Est. Capacity: 20 will review the continued inclusion of this proposal in the LDP. Area: 1 ha 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

106

Site Site specific actions Delivery Status/Next Steps Pittencrieff Street Who: Development Brief approved August 2006. (DUN034) Est. Capacity: This site is complete. Area: 1.1 ha 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 COMPLETE

Elliot Street Who: Fife Council The site will planning permission for 30 affordable flatted (DUN036) Est. Capacity: 19 dwellings - 15/02633/FULL Area: 0.6ha

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Dover Heights Who: Scottish Enterprise Proposal of application notice for residential development (DUN037) / Fife Council submitted - 17/03507/PAN. Est. Capacity: 220 Dunfermline wide contributions towards additional secondary Area: 12 ha capacity are now sought – see Planning Obligations Supplementary Guidance 2017. Additional capacity required by 2022

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

107

Site Site specific actions Delivery Status/Next Steps Halbeath South Scottish Water: A Drainage Impact Assessment Who: Private Sector This site has planning permission and is under construction - (DUN047) has been carried out for this site. Extensive Est. Capacity: 380 13/02306/ARC network upgrades have been identified. Area: 18.2 ha However, interim solutions are being implemented to permit connections in the short/medium term. A Strategic Network Impact Assessment is being carried out by Scottish Water to understand the cumulative effect on the Dunfermline catchment and a drainage strategy is being created to support all development in the catchment. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 ✔ Abbeyview Centre Any new development must replace or refurbish Who: Fife Council No information is available. Fife Council as Planning Authority (DUN071) existing housing and retail units. Est. Capacity: will review the continued inclusion of this proposal in the LDP. Area: 1.5 ha

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Employment Site Site specific actions Delivery Status/Next Steps Carnegie Campus 3 Who: Private Sector No information is available. Fife Council as Planning Authority (DUN048) Area: 1.9 will review the continued inclusion of this proposal in the LDP. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

108

Site Site specific actions Delivery Status/Next Steps Carnegie Campus 1 Who: Fife Council/ No information is available. Fife Council as Planning Authority (DUN049) Scottish Enterprise will review the continued inclusion of this proposal in the LDP. Area: 8.5 ha 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Elgin Street Who: Private Sector No information is available. Fife Council as Planning Authority Industrial Estate Area: 0.7 ha will review the continued inclusion of this proposal in the LDP. (DUN050) 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Axis Point Who: Private Sector No information is available. Fife Council as Planning Authority (DUN051) Area: 5.3 ha will review the continued inclusion of this proposal in the LDP. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Calais Muir (Central) Who: Private Sector No information is available. Fife Council as Planning Authority (DUN052) Area: 4.9 ha will review the continued inclusion of this proposal in the LDP.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Calais Muir (South) Who: Private Sector No information is available. Fife Council as Planning Authority (DUN053) Area: 7.8 ha will review the continued inclusion of this proposal in the LDP.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

109

Site Site specific actions Delivery Status/Next Steps Carnegie Campus 2 Who: Private Sector This site has previously received planning permission for 2 (DUN054) Area: 0.4 ha office blocks - 06/02867/WFULL 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Pitreavie Drive Who: Private Sector This site has planning permission in principle for Class 4 office (DUN055) Area: 0.3 hectares buildings - 13/01817/PPP 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Calais Muir (North) Who: Scottish No information is available. Fife Council as Planning Authority (DUN056) Enterprise will review the continued inclusion of this proposal in the LDP. Area: 4.2 ha 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Pitreavie Way Who: Private Sector Planning permission granted for employment uses - (DUN057) Area: 3.5 ha 14/02367/FULL 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Carnegie Campus 4 Who: Private Sector This site has planning permission for a car park extension - (DUN058) Area: 1.1 ha 12/04386/FULL and a photovoltaic farm - 11/05315/FULL 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

110

Site Site specific actions Delivery Status/Next Steps Halbeath Who: Private Sector Planning permission in principle granted for mixed use Interchange Area: development for classes 1 (retail), 4 (business), 5 (general (DUN059) industrial), 6 (warehousing and distribution), 7 (hotel), 9 (residential) and 10 (education) with on-site installation of renewable energy plant. 14/00809/PPP 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

South of Elliot Street Who: Private Sector No information is available. Fife Council as Planning Authority (DUN060) Area: 1.3 ha will review the continued inclusion of this proposal in the LDP. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Development Opportunities Site Site specific actions Delivery Status/Next Steps New Row Gap Site Development must secure townscape Who: Fife Council/ No information is available. Fife Council as Planning Authority (see Central enhancement and landscape improvements. Private Sector will review the continued inclusion of this proposal in the LDP. Dunfermline Area: <0.1 ha Framework Diagram) (DUN061)

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Viewfield House (see Development must secure townscape Who: Fife Council/ Planning permission granted for new replacement lighting - Central Dunfermline enhancement and landscape improvements. Private Sector 13/03166/FULL Framework Diagram) Area: <0.1 ha (DUN062) 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

111

Site Site specific actions Delivery Status/Next Steps High Street gap site, Who: Fife Council/ Developer interest in the gap site for Leisure use - no firm City Centre (see Private Sector proposals to date. Central Dunfermline Area: 0.4 ha Framework Diagram) (DUN063) 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Walmer Drive Who: Private Sector No information is available. Fife Council as Planning Authority (see Central Area: 1.1 ha will review the continued inclusion of this proposal in the LDP. Dunfermline Framework Diagram) (DUN064) 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

City Square, Who: Private Sector No information is available. Fife Council as Planning Authority Dunfermline Town Area: 0.6 ha will review the continued inclusion of this proposal in the LDP. Centre (see Central Dunfermline Framework Diagram) (DUN072) 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

112

Development Opportunities Site Site specific actions Delivery Status/Next Steps Winterthur Lane Who: Private Sector This site has planning permission for a supermarket Development (see Area: 4.7 ha development with petrol filling station. The site is under Central Dunfermline construction. 14/01431/FULL Framework Diagram) (DUN073) 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Pilmuir Works (see Who: Private Sector Planning application submitted for erection of new buildings Central Dunfermline Area: 1.9 ha and conversion, part demolition, extension and refurbishment Framework Diagram) of existing buildings to form residential units and ancillary (DUN074) commercial floorspace (Classes 1,2, sui generis take away and sui generis licensed premises and (Class 10) with associated infrastructure, parking, landscaping and access – 17/03292/FULL 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Carnegie Drive Retail There is an opportunity for refurbishment and Who: Fife Council No information is available. Fife Council as Planning Authority Park (see Central redevelopment of the retail park to bring it up to Area: 5.6 ha will review the continued inclusion of this proposal in the LDP. Dunfermline a modern standard. This could include proposals Framework Diagram) for a new supermarket and new food and drink (DUN075) outlets.

Fife Council will work with the site promoter to facilitate an acceptable strategy for the commercial centre.

Pedestrian links will be required on Carnegie Drive to better link this area back to Core Retail Area. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

113

Site Site specific actions Delivery Status/Next Steps Museum & Art Who: Fife Council The museum and art gallery is now completed and open. Gallery (see Central Area: Dunfermline Framework Diagram) (DUN076) 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 COMPLETE

Transport Site Site specific actions Delivery Status/Next Steps Appin Crescent Who: Fife Council Potentially not required. Bypass (DUN065) Cost: Funding: 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Charlestown Rail The feasibility of constructing this link has not yet Who: Fife Council Continue to safeguard land for a possible rail link. Junction been established and is not approved by Transport Cost: See Spatial Strategy section above. (DUN066) Scotland. In the meantime, the route of the link Funding: should be kept clear of development.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

114

Elie and Earlsferry (Click here to view interactive map) Housing/Housing Opportunity Site Site Site specific actions Delivery Status/Next Steps Land to the south Development within this Plan period will be restricted Who: Private Sector Planning applications submitted: of A917, East of to 80 houses across the two identified sites. Est. Capacity: 80 Elie/ Land to north of Grange Road A development framework will be required to guide • Land to the south of  17/04096/PAN and 18/00043/SCR (EAE001*) the design and layout of these sites and longer term A917, East of Elie growth. The development framework will be Capacity: 55 produced through further consultation with the Area: 5.0 ha community through the ENCAP process. This process will identify requirements for community facilities • Land to north of  17/04097/PAN and 18/00042/SCR and employment provision on the sites East of Elie. Grange Road Capacity: 25 Requirements and delivery of planning obligations Area: 5.9 ha must be agreed across both sites in combination.

The development is required to be phased to avoid capacity issues at Elie Primary School.

Scottish Water: Drainage and Water Impact Assessments may be required to fully assess these developments on the existing Scottish Water network. Early engagement with the Scottish Water Development Services team via the Pre-Development Enquiry process is highly recommended. In addition, a Growth project is required on the Elie Septic Tank to accommodate additional connections. Scottish Water is funded for Growth following the provision of the 5 Growth criteria. However, timescales to complete any required upgrades could impact on proposed developer build out plans.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

115

Falkland (Click here to view interactive map) Housing/Housing Opportunity Site Site Site specific actions Delivery Status/Next Steps St John’s Works A Development Framework will be required. The Who: Private Sector Buildings recently demolished and site cleared. (FAL001*) preparation of the Development Framework will Est. capacity: 100 involve public consultation and engagement with the Area: 3.7 ha Site being actively marketed. local community.

0.5 ha of employment land is to be retained.

Scottish Water: Early engagement via the Scottish Water Pre-Development Enquiry process is recommended to fully understand proposed flows. Recent activity at the Bowhouse WWTW has highlighted sufficient capacity but the serving network may need review. Water has sufficient capacity.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Glenrothes (Click here to view interactive map)

Proposals around Glenrothes include strategic transport proposals at Bankhead roundabout and Preston roundabout.

Housing/Housing Opportunity Site Site Site specific actions Delivery Status/Next Steps Balgeddie Riding Who: Tulloch The site has planning permission (03/02294/CFULL and School Est. Capacity: 72 10/04470/FULL) First phase complete 2017. Next phase not (GLE001) Area: 9.2 ha programmed. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

116

Site Site specific actions Delivery Status/Next Steps Lochtybridge Who: Raith The site has planning permission 05/00236/FULL and is (GLE002) Developments under construction. Est. Capacity: 120 Area: 10.4 ha 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 ✔ Viewfield Housing/ The housing developer shall be obliged to safeguard Who: Fife Council Site part of Fife Council Affordable Housing programme. Employment an area of approximately 5 hectares within the site Est. Capacity: 360 (GLE003) for employment related uses within Classes 4,5 Area: 14.3 ha Proposal of Application Notice submitted for mixed use and/or 6 development including employment, affordable residential units, green space/network, access and associated Scottish Water: A Drainage Impact Assessment is infrastructure (17/01889/PAN) required to understand what impact, if any this development will have on the existing network. The developer will be required to carry out any mitigation works that are identified.

A Water Impact Assessment may also be required. However, a Pre-Development Enquiry should be submitted to Scottish Water with proposed flows to understand this in more detail.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Land to the south Scottish Water: A Water Impact Assessment will be Who: Private Sector Site forms part of larger masterplan area for former Tullis of Cadham Road required to understand what impact, if any this Est. Capacity: 200 Russell site which has been progressed with the support of (GLE004) development will have on the existing water network. Area: 9.9 ha Fife Task Force. Work is ongoing to progress the A92 Action The developer will be required to carry out any Plan and transport appraisal(s) for Mid Fife. mitigation works that are identified. In addition, an existing Scottish Water combined sewer traverses the A pre-application enquiry submitted for major development, site from East to West. This will need to be comprising residential led mixed-use development, including

117

Site Site specific actions Delivery Status/Next Steps (GLE004) continued adequately managed both during and after employment/business use (including retail), care home, construction. Early engagement with Scottish Water industrial and energy use, distillery, data centre, open space, is recommended. parkland and associated development (17/02663/PREAPP).

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Whitehill Industrial A n indicative development framework is required for Who: Private Sector Planning permission granted (10/01059/PPP & 11/02184/PP) Estate the whole site (including GLE035). Any development Est. Capacity: 230 – Section 42 applications approved to extend timescales (GLE005) on site GLE005 must conform to the provisions of site Area: 10 ha (17/01885/PPP & 17/01887/PPP). GLE035.

Housing development will cross subsidise new industrial and business facilities in the employment area to the south and will assist with their financial viability.

A neighbourhood centre should be provided. The opportunity exists for residential development above the neighbourhood facilities.

Two points of access are required. Access into employment site GLE019 is to be provided.

Scottish Water: A Drainage Impact Assessment may be required to understand what impact, if any this development will have on the existing network. The developer will be required to carry out any mitigation works that are identified. Early engagement with Scottish Water is highly recommended.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

118

Employment Site Site specific actions Delivery Status/Next Steps Crompton Road Who: Fife Council No information is available. Fife Council as Planning Authority East (GLE006) Area: 7.6 ha will review the continued inclusion of this proposal in the LDP. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Crompton Road Who: Private Sector No information is available. Fife Council as Planning Authority North (GLE007) Area: 1.6 ha will review the continued inclusion of this proposal in the LDP. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Crompton Road Who: Scottish No information is available. Fife Council as Planning Authority West (GLE008) Enterprise will review the continued inclusion of this proposal in the LDP. Area: 5.1 ha 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Dalton Road 1 Who: Fife Council No information is available. Fife Council as Planning Authority (GLE009) Area: 2.6 ha will review the continued inclusion of this proposal in the LDP. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Dalton Road 2 Who: Fife Council No information is available. Fife Council as Planning Authority (GLE010) Area: 0.5 ha will review the continued inclusion of this proposal in the LDP.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Detroit Road Who: Fife Council Planning permission granted for erection of 4 industrial units (GLE011) Area: 2.2 ha (Class 4 & 5) - 07/03502/CFULL

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

119

Site Site specific actions Delivery Status/Next Steps Eastfield East Who: Private Sector No information is available. Fife Council as Planning Authority (GLE012) Area: 1.3 ha will review the continued inclusion of this proposal in the LDP. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Eastfield West Who: Private Sector No information is available. Fife Council as Planning Authority (GLE013) Area: 0.7 ha will review the continued inclusion of this proposal in the LDP. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Fife Food Centre Who: Fife Council Planning permission granted for erection of industrial (GLE014) Area: 1.8 ha building (Class 5), formation of car park and attenuation pond with bridge - 07/02401/CFULL 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Land at Leslie Road Development on this site will contribute to providing Who: Fife Council Site being marketed as part of larger development site which (GLE015) pedestrian links into the defined town centre and to Area: 0.6 ha now includes former police station site (police station Riverside Park. buildings now demolished). 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Naysmith Road Who: Private Sector No information is available. Fife Council as Planning Authority (GLE016) Area: 0.3 ha will review the continued inclusion of this proposal in the LDP. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Pentland Park Who: Fife Council Planning permission granted for erection of single storey North (GLE017) Area: 0.2 ha office building (Class 4) with associated car parking, landscaping and external bin store - 14/02047/FULL 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

120

Site Site specific actions Delivery Status/Next Steps Pentland Park Who: Fife Council No information is available. Fife Council as Planning Authority South (GLE018) Area: 0.6 ha will review the continued inclusion of this proposal in the LDP. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Land south of Fife Who: Private Sector InchDairnie Distillery - Permission granted for construction of Airport Area: 10.9 ha malt distillery and associated maturation warehouses with (GLE019) associated parking and landscaping (12/03846/FULL). 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Southfield South Who: Scottish No information is available. Fife Council as Planning Authority East Enterprise will review the continued inclusion of this proposal in the LDP. (GLE020) Area: 10.9 ha 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Spectrogon, Who: Private Sector/ No information is available. Fife Council as Planning Authority Southfield Scottish Enterprise will review the continued inclusion of this proposal in the LDP. Industrial Estate Area: 1.1 ha (GLE021) 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Wheatstone Place Who: Private Sector/ No information is available. Fife Council as Planning Authority Dalton Road A Fife Council will review the continued inclusion of this proposal in the LDP. (GLE022) Area: 1.7 ha 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

121

Site Site specific actions Delivery Status/Next Steps Whitworth Road Who: Fife Council Planning permission granted for erection of biomass fuel (GLE023) Area: 1.9 ha pellet production building - 12/04322/FULL Queensway2017/18 East 2018/19 2019/20 2020/21Who: Fife Council2021/22 Planning2022/23 permission granted2023/24 to extend the use ofPost this 2024 site as (GLE 024) Area: 1.5 ha a temporary car park for the Biomass Power Plant - 14/02389/FULL Queensway Who: Fife Council/ Planning permission granted for erection of data centre. expansion Private Sector 17/02546/FULL (GLE 025) Area: 4.2 ha 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Westwood Park Housing development to cross-subsidise the business Who: Fife Council This site has planning permission. 12/01300/PPP (GLE026) park. Est. Capacity: 420 Area: 40.6 ha 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Whitehill Industrial Site GLE035 includes site GLE005 and an Who: Private Sector Planning permission granted (10/01059/PPP & Estate employment area to the south. Est. Capacity: 230 11/02184/PPP) – Section 42 applications granted to extend (GLE035) Area: 22.2 ha timescales (17/01885/PPP & 17/01887/PPP) Prior to any planning application being submitted a masterplan is required to be undertaken for the whole site.

Housing development on site GLE0 05 will cross subsidise new industrial and business facilities in the employment area to the south and will assist with their financial viability.

A neighbourhood centre should be provided within site GLE 005. The opportunity exists for residential development above the neighbourhood facilities. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

122

Development Opportunities Site Site specific actions Delivery Status/Next Steps North Street/ Who: Private Sector Planning permission granted. 15/03140/PPP & Falkland Gate Area: 16/02458/ARC (GLE029) In addition to and to complement development at the former CISWO Social Club and Fife Council Car Park a series of public realm/environmental improvements will be delivered during 2018. These include green open space (Former Glenrothes House), improved walking and cycling opportunities, improvements to surfaces between the new development and Kingdom Centre, traffic calming measures and introduction of a 20mph zone. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Queensgate Who: Private Sector This site has outline planning permission for bulky goods (GLE030) Area: 4.1 ha retailing (13/02357/PPP). Variation to conditions granted to amend range of goods which can be sold (15/02008/PPP) 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Albany Gate Who: Private Sector Planning application granted for creation of access and car (GLE031) Area: parking, landscaping and associated works including making good exposed walls following removal of part of shopping centre (former co-op store and former Forum Hotel) (17/00296/FULL) 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Marchmont Gate Who: Private Sector No information is available. Fife Council as Planning Authority (GLE032) Area: will review the continued inclusion of this proposal in the LDP. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

123

Site Site specific actions Delivery Status/Next Steps South Street Car Who: Private Sector No information is available. Fife Council as Planning Authority Parks (GLE033) Area: will review the continued inclusion of this proposal in the LDP. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

North Street Who: Private Sector Planning application approved (14/02799/FULL) redevelopment Area: (GLE034) 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 COMPLETE

School Site Site specific actions Delivery Status/Next Steps Collydean Who: Fife Council Pre-application enquiry submitted for an affordable housing Additional School Area: 2.5 ha development for supported living (Aberlour Child Care Trust) Grounds (GLE027) – 17/03701/PREAPP 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Stenton Primary Who: Fife Council No information is available. Fife Council as Planning School Area: 2.4 ha Authority will review the continued inclusion of this (GLE028) proposal in the LDP.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

124

Gowkhall (Click here to view interactive map) Housing/Housing Opportunity Site Site Site specific actions Delivery Status/Next Steps Land North of Improve and upgrade the local road network Who: Premier This site has planning permission and is currently under Clune Road specifically the junction into the site off the existing Properties construction. 15/02112/FULL (GWH001*) residential street (Clune Road) and the surfacing of Est. Capacity: 10 Clune Road to accommodate the additional Area: 1.3 hectares vehicular trips generated from the development.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 ✔

Guardbridge (Click here to view interactive map) Housing/Housing Opportunity Site Site Site specific actions Delivery Status/Next Steps Main Street South Who: Private Sector Development complete. (GUA001) Est. Capacity: 7 Area: 0.2 ha

2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 COMPLETE

Motray Park Who: Private Sector Planning permission in principle was granted in October (GUA002) Est. Capacity: 49 2014 (13/02959/PPP) for 49 residential units with associated Area: 1.9 ha parking and landscaping. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

125

Site Site specific actions Delivery Status/Next Steps Seggie Farm Sites GUA003 and GUA005 are to be covered by a Who: Private Sector Proposal of Application Notice submitted by Persimmon (GUA003) single masterplan, to be prepared by the developer Est. Capacity: 350 Homes in March 2017. for approval by Fife Council. Area: 14.4 ha Planning application - 18/00078/FULL for 357 residential Identify suitable locations for proposed open space units including landscaping proposals submitted January and community woodland 2018. (GUA005).

Scottish Water: Scottish Water: A Drainage Impact Assessment is required to understand what impact, if any this development will have on the existing network. The developer will be required to carry out any mitigation works that are identified. A Water Impact Assessment is also required. Growth will ultimately be required at the Guardbridge WWTW to facilitate all planned development, but this is not expected to impact upon the developers’ proposed build out schedule. 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 2017/18

Employment Site Site specific actions Delivery Status/Next Steps Site of Former A further development framework / masterplan Who: Private Sector In October 2014, a planning permission in principle Curtis Fine Papers requires to be provided and agreed with the council. Area: 9.6 ha 14/01933/PPP and a planning permission 14/02334/EIA (GU 004) It should reflect the terms of the 2014 permissions. If were granted for the redevelopment of the site. The former new uses are proposed, they require to be included permission proposes university (class 10) and business in the development framework/ masterplan, and related uses comprising ongoing industrial, storage, they should be the subject of appropriate community distribution and office uses, with research and development engagement and consultation. (class 4). The latter permission proposes a renewable energy centre, biomass fuel storage and processing, and district There is the potential for some residential heating pipeline works. The aim of the permissions is to accommodation for postgraduate students of the create a sustainable power and research campus. university to be provided as part of the development

126

Site Site specific actions Delivery Status/Next Steps (GUA004) of the site, in which case a contribution to primary In August 2017 a reserved matters planning application was continued education provision will be required. submitted for the refurbishment and change of use of buildings and other works 17/02628/ARC The final form of the development shall deliver a

minimum of one hectare of employment land or 3500 square metres of gross floor space for classes 4 or 5 industrial uses separate from any uses directly related to the biomass energy centre shown in zone 1 or class 10 (university) activities. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Avalon Business Who: Private Sector No information is available. Fife Council as Planning Authority Park (GUA006) Area: 0.3 ha will review the continued inclusion of this proposal in the LDP. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Community Woodland/Open Space Site Site specific actions Delivery Status/Next Steps Seggie Farm Sites GUA003 and GUA005 are to be covered by a Who: Private Sector Proposal of Application Notice submitted 17/00812/PAN (GUA005) single masterplan prepared by the developer for Fife Area: 5.9 ha Council approval.

Public access to the area must be assured. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

127

High Valleyfield (Click here to view interactive map) Housing/Housing Opportunity Site Site Site specific actions Delivery Status/Next Steps Woodhead Farm Who: RSR Homes This site has planning permission 06/02754/WFULL for (HVF001) Est. Capacity: 31 housing and the site is under construction. Area: 1.5 ha 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 ✔ Land to the north A masterplan will be prepared by landowners in Who: Private Sector Sites marketed and promoted (for employment use) of Woodhead Farm conjunction with the council for the full site area Est. Capacity: 50 December 2016 by Fife Council for Longannet Task Force – Road (HVF002) showing the allocation of land uses, access and Area: 6.1 ha see www.investinfife.co.uk/upperforth infrastructure arrangements, structural landscaping and development phasing. Key requirements include: Site in multiple (2) ownerships with no current evidence (2017) of developer activity. Serviced employment land will occupy approximately Site owners to be identified and approached. 50% of the total developable site area.

A financial contribution from housing development on site towards provision of onsite serviced employment land to be secured through an appropriate legal agreement.

Open space provision close to spine pathway through the village.

Provision of pedestrian access to the school.

Upgrading of the access route to Valleyfield Woodland Park.

Road and path connections to the surrounding area including creation of a safe pedestrian crossing point on the B9037.

128

Site Site specific actions Delivery Status/Next Steps (HVF002) Scottish Water: Early engagement with Scottish continued Water is highly recommended to understand drainage requirements.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Abbey Street Who: Fife Council No information is available. Fife Council as Planning (HVF003) Est. Capacity: 10 Authority will review the continued inclusion of this Area: 0.1 ha proposal in the LDP. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Chapel Place/ Who: Fife Council No information is available. Fife Council as Planning Carlyle Street Est. Capacity: 10 Authority will review the continued inclusion of this (HVF004) Area: 0.3 ha proposal in the LDP. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Kincardine, New Row & Tulliallan (Click here to view interactive map) Housing/Housing Opportunity Site Site Site specific actions Delivery Status/Next Steps Burnbrae East Who: Private Sector No information is available. Fife Council as Planning Authority (KCD001) Est. Capacity: 30 will review the continued inclusion of this proposal in the LDP. Area: 2 ha Dunfermline wide contributions towards additional secondary capacity are now sought – see Planning Obligations Supplementary Guidance 2017. Additional capacity required by 2022

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

129

Site Site specific actions Delivery Status/Next Steps Kincardine A development proposal for the entire site including the Who: Private Sector/ The uses stated are consistent with planning permission Eastern phased release of this site and KCD003 should include : Registered Social reference 13/00357/PPP and 17/02330/PPP, this consent Expansion Landlord also includes land adjacent the settlement boundary to the Provision of 50 affordable housing units. Phase 1 Est. Capacity: 300 south east and north east. Notwithstanding the uses above (KCD002) Community facilities contribution. Area: 10.5 ha and associated planning permission it is important that Phasing plan including the delineation of the site development proposals on this site (and those associated boundaries to include only the land allocated through with it) take account of the topography, utility and design the local plan. constraints of the site. A flood risk assessment must be Provision of a fully-accessed serviced business park. undertaken prior to development on this site.

Provision of a neighbourhood park. Subject to S75 Landscaping of the site.

Set-aside land for the extension of the cemetery. Dunfermline wide contributions towards additional secondary capacity are now sought – see Planning New local access road between Walker Street and Toll Obligations Supplementary Guidance 2017. Road. Additional capacity required by 2022 Provision of a site for a shop/general convenience store.

Provision of a site for recycling.

Diversion of the existing overhead power line outwith the site.

Scottish Water: A Drainage Impact Assessment is required to understand what impact, if any this site will have on the existing public drainage system. Any network upgrades must be funded and carried out by the developer. In addition, the Kincardine WWTW will require growth to accommodate all development within the catchment. Scottish Water is funded for growth following the provision of the 5 growth criteria. The developer should engage closely with Scottish Water to understand timescales for the delivery of any upgrades to reduce risk to proposed build out plans. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

130

Site Site specifications Delivery Status/Next Steps Kincardine As per KCD002 above. Who: Private Sector/ The uses stated are consistent with planning permission Eastern Registered Social 13/00357/PPP and 17/02330/PPP this consent also includes Expansion Phase Scottish Water: A Drainage Impact Assessment is Landlord land adjacent the settlement boundary to the south east and 2 (KCD003) required to understand what impact, if any this site will Est. Capacity: 190 north east. Notwithstanding the uses above and associated have on the existing public drainage system. Any Area: 4.5 ha planning permission it is important that development network upgrades must be funded and carried out by the proposals on this site (and those associated with it) take developer. In addition, the Kincardine WWTW will account of the topography, utility and design constraints of require growth to accommodate all development within the site. A flood risk assessment must be undertaken prior to the catchment. Scottish Water is funded for growth development on this site. following the provision of the 5 growth criteria. The developer should engage closely with Scottish Water to Dunfermline wide contributions towards additional understand timescales for the delivery of any upgrades secondary capacity are now sought – see Planning to reduce risk to proposed build out plans. Obligations Supplementary Guidance 2017. Additional capacity required by 2022 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Kincardine Multi Who: Fife Council This site has planning permission - 16/01548/FULL Storey Flats Est. Capacity: 130 (KCD004) Area: 4 ha 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Land North and This site will be developed for affordable housing Who: Kingdom Development partially underway (2017/18). 14/04252/PPP & East of Burnbrae purposes and may include a residential nursing home. Housing Association 15/00453/FULL House Est. Capacity: 36 (KCD005) Area: 2 ha Erection of 60 bed care home, 16 care apartments, 36 social housing units and associated parking and site infrastructure. Dunfermline wide contributions towards additional secondary capacity are now sought – see Planning Obligations Supplementary Guidance 2017. Additional capacity required by 2022 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

131

Employment Site Site specific actions Delivery Status/Next Steps Kincardine Power The council will work with the landowner to consider Who: Fife Council On behalf of the Longannet Task Force, a report has been Station 4 East future redevelopment options for this site to be based Area: 3.8 ha commissioned on the feasibility of creating an Employment (KCD006) on appropriate environmental, technical and land use Park to serve the sub-region between Stirling, Alloa, assessments of the full site of the former power station. Kincardine and Falkirk.

These assessments should take into account the This is one of a number of sites in the Upper Forth sub- desirability of making provision for landscaping along the region that have the potential to drive economic growth. It south-west boundary of the site to improve the amenity has been appraised against indicators of strategic location, of the adjacent footpath and cycleway and of making market demand, potential impacts, site constraints and provision for a new section of footpath and cycleway deliverability. across the westernmost part of the site. Next steps are to discuss with partners and stakeholders (including the landowner) a preferred option and consider feasibility and delivery. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Development Opportunities Site Site specific actions Delivery Status/Next Steps North Approach Development should seek to provide active frontages Who: Private Sector The Coalfields Regeneration Trust (CRT) have led the Road (KCD011) onto North Approach Road and will contribute to / Transport Scotland Kincardine charrette, with funding support from the providing quality pedestrian links into the defined town /Fife Council Scottish Government and Fife Council. The Action Plan (15 centre area. Area: 0.1 ha September 2017) includes proposals to revitalise the Village Centre – comprising:  changes to road layouts and encouraging events and activities in the centre;  provision of visitor hub with appropriate facilities;  re-thinking the North Approach Road and making improvements, including possible de-trunking, junction simplification where it meets A977.

132

Site Site specific actions Delivery Status/Next Steps (KCD011) Delivery Funding sought and Community Development continued Trust established. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Conservation Area Extension Site Site specific actions Delivery Status/Next Steps High Street Who: Fife Council The Coalfields Regeneration Trust (CRT) have led the (KCD012) Area: Kincardine charrette, with funding support from the Scottish Government and Fife Council. The Action Plan (15 September 2017) includes proposals to revitalise the Village Centre – comprising:  a wider review of movement within the village centre; shop front improvements with both awareness campaign targeting owners and a grant scheme; tidying up back lanes; and provision of facilities related to sport, recreation, health and wellbeing.

Conservation Area Appraisal

Delivery Funding sought and Community Development Trust established 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Regent St, George Who: Fife Council As KCD012 St & Parklands Area: (KCD013) 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

133

Site Site specific actions Delivery Status/Next Steps Kirk Street Who: Fife Council As KCD012 (KCD014) Area: 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Kirk Brae Who: Fife Council As KCD012 (KCD015) Area: 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Kirkcaldy & Dysart (Click here to view interactive map)

Proposals around Kirkcaldy include the Kirkcaldy East Strategic Land Allocation; the Kirkcaldy South West Strategic Land Allocation; a number of strategic transport proposals including the hovercraft link; and a strategic education proposal.

Housing/Housing Opportunity Site Site Site specific actions Delivery Status/Next Steps 8 Anderson Street Who: Private Sector Planning permission granted. 17/01209/PPP (KDY001) Est. Capacity: 9 Area: 0.1 ha 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Capshard North Who: Ambassador This site has planning permission and is under construction - (KDY 002) Homes/ Barratt 109 units completed. 05/03215/CFULL Est. Capacity: 189 Area: 11.7 ha

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 ✔

134

Site Site specific actions Delivery Status/Next Steps Chapel Extension, Who: Dundas Estates This site has planning permission for a 60 bed care home and John Smith BP Est. Capacity: 285 26 extra care units- 86 units completed. 12/01673/FULL. (KDY003) Area: 12.9 ha

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 ✔ Dunnikier Maltings Who: Robertson This site has planning permission and is under construction - (KDY004) Partnership/ Fife 61 units completed. 06/03707/CARM. Council Est. Capacity: 199 Area: 4 ha 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 ✔ Ferrard Road Who: Abbotshall This site has planning permission and is under construction- 71 (KDY005) Homes units completed 16/03589/ARC Est. Capacity: 119 Area: 1.9 ha 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Katherine Street Who: Private Sector Planning permission granted June 2014. 13/03751/FULL (KDY006) Est. Capacity: 5 Area: 0.2 ha

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

18 Pottery Street Who: Private Sector Site complete (KDY007) Est. Capacity: 6 Area: 0.2 ha 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 COMPLETE

135

Site Site specific actions Delivery Status/Next Steps 45 Pottery Street Who: Private Sector Site complete (KDY008) Est. Capacity: 5 Area: 0.1 ha 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 COMPLETE

Forth Park Hospital Scottish Water: Careful consideration of Who: Private Sector This site has planning permission in principle. 10/02309/PPP (KDY010) management of Surface Water should be Est. Capacity: 69 and 17/00936/OBL considered. Scottish Water will only permit Area: 2.4 ha surface water to the combined network where no other viable surface water solution is available and proven to be so. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Park Road / Lawson Who: Private Sector Site completed Road (KDY011) Est. Capacity: 37 Area: 0.4 ha

2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 COMPLETE

257-261 High New development must have active frontage to Who: Private Sector Planning permission granted for erection of 26 flats and 293 Street the High Street and be of a quality appropriate Est. Capacity: 26 square metres of retail accommodation (demolition of existing (KDY012) to its historic surroundings. Area: 0.2 ha building), formation of car parking/vehicular access and landscaping - 05/00026/CFULL

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Viewforth Terrace Who: Private Sector No information is available. Fife Council as Planning Authority (KDY013) Est. Capacity: 26 will review the continued inclusion of this proposal in the LDP. Area: 0.6 ha 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

136

Site Site specific actions Delivery Status/Next Steps Smeaton Road Who: Private Sector No information is available. Fife Council as Planning Authority (KDY015) Est. Capacity: 19 will review the continued inclusion of this proposal in the LDP. Area: 0.5 ha 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Junction Road Who: Ian Sneddon The eastern part of this site has planning permission for 20 (KDY016) Est. Capacity: 38 flats. 09/01464/CFULL and 17/02078/FULL Area: 1 ha 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Den Road Former Access to be taken from Dunnikier Road via Who: Private Sector No information is available. Fife Council as Planning Authority Tramworks site Thornhill Drive. Est. Capacity: 90 will review the continued inclusion of this proposal in the LDP. (KDY018) Area: 2.8 ha

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Victoria Fields Should housing be proposed, there should be a Who: Private Sector Prior Notice of Application for a residential development has (KDY019) maximum of 100 units and any remaining part of Est. Capacity: 100 been received. 17/01381/PAN the site should be used to provide employment Area: 4.3 ha land.

Permanent vehicular access to the site must be taken only from Calender Avenue. Access from employment land to be taken from Smeaton Road.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

137

Employment Site Site specific actions Delivery Status/Next Steps Dunnikier Business Who: Private Sector Full Planning Permission granted for the west of the site for a Park Area: 5.3 ha 19.8MW Gas Peaking Plant and 20MW battery storage plant (KDY020) (April 2017) 16/04195/FULL and for 5 business units (Class 5) in the centre of the site (April 2015) 15/00605/FULL

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Midfield Road 1 Who: Private Sector No information is available. Fife Council as Planning Authority Mitchelston IE Area: 1.6 ha will review the continued inclusion of this proposal in the LDP. (KDY021) 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Wheatfield Road Who: No information is available. Fife Council as Planning Authority (KDY022) Area: 2.2 ha will review the continued inclusion of this proposal in the LDP. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Hayfield (former Who: Planning application submitted for planning permission in Babygro) Area: 1.6 ha principle for the erection of 48 flats and 26 townhouses - (KDY023) 17/02103/PPP 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Smeaton Road Who: Private Sector No information is available. Fife Council as Planning Authority (KDY024) Area: 0.9 ha will review the continued inclusion of this proposal in the LDP. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

138

Development Opportunities Site Site specific actions Delivery Status/Next Steps Hayfield Road A design brief should be prepared to encourage Who: Private Sector No information is available. Fife Council as Planning Authority (KDY014) development to provide a strong street frontage Est. capacity: 60 will review the continued inclusion of this proposal in the LDP. with clearly defined articulation of building form Area: 1.9 ha creating a gateway to Denburn Road. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Factory Road Who: Private Sector Application has been received for this site along with KDY 044 /Nairn Street Est. capacity: 68 for affordable housing development 17/02443/PAN (KDY017) Area: 1.7 ha 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Millie Street Who: Private Sector No information is available. Fife Council as Planning Authority (KDY027) Area: 1.4 ha will review the continued inclusion of this proposal in the LDP. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Former car sales The design brief should recognise the ‘gateway’ Who: Private Sector Part of site being used for a bathroom showroom. Car sales on garage, Millie character of this site and the importance of Area: 0.5 ha the remainder of the site Street (KDY028) creating a high quality prominent frontage. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Victoria Road, Who: Private Sector Renewed application for a Class 1 retail development on part Former Power Area: 0.8 ha of the site. Demolition of the B listed building has been Station (KDY029) approved and agreed with Historic Environment Scotland.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

139

Site Site specific actions Delivery Status/Next Steps Victoria Road Who: Private Sector This site has planning permission and is under construction. (KDY030) Area: 0.9 ha 16/01317/FULL and 16/03790/FULL

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 ✔

Charlotte Street Any car parking spaces that are lost through Who: Private Sector/ No information is available. Fife Council as Planning Authority (KDY031) redevelopment of this site must be replaced Fife Council will review the continued inclusion of this proposal in the LDP. within Kirkcaldy Town Centre. Area: 0.7 ha 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

YWCA and former The possibility of reopening the cinema should Who: Kings Theatre Proposals being taken forward by the Kings Theatre Trust to cinema (KDY032) be investigated and if this is not possible, other Trust /Alec Cruickshank redevelop both the YWCA and former ABC Cinema for Leisure leisure uses should be considered in the Est. capacity: 11 use. Plans include redeveloping the cinema to its former use as development of this site. Area: 0.2 ha a music venue and developing the YWCA as restaurant/wedding venue including training partnership with Fife College.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

The Postings and New development must provide active frontage Who: Zurich Assurance No information is available. Fife Council as Planning Authority former Territorial onto Hunter Street and where possible make / MOD will review the continued inclusion of this proposal in the LDP. Army site creative re-use of existing buildings. Area: 1.4 ha (KDY033) Any car parking spaces that are lost through redevelopment of this site must be replaced within Kirkcaldy Town Centre. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

140

Site Site specific actions Delivery Status/Next Steps Thistle Street car Any development must provide improvements Who: Private Sector/ No information is available. Fife Council as Planning Authority parks (KDY034) to car parking within Kirkcaldy town centre. Fife Council will review the continued inclusion of this proposal in the LDP. Area: 0.7 ha 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Former swimming Any development must contribute towards Who: Private Sector/ 17/03551/FULL planning application for redevelopment of pool site improvements to car parking within Kirkcaldy Fife Council former swimming pool and erection of cinema, leisure and (KDY035) town centre. Est. capacity: 11 food and drink/public house has been submitted Area: 0.3 ha Planning Permission granted for demolition of existing building and work started.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 ✔ Former Jackie O’s Who: Mars Pension Site now completed – 30 flats with commercial at ground floor nightclub Fund/ LaSalle - developed by Alex Penman 14/01221/FULL (KDY036) Investment Management Ltd Area: 0.1 ha 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 COMPLETE

Forth House, A masterplan covering the whole site should be Who: Fife Council No information is available. Fife Council as Planning Authority Abbotsford Road developed. Area: 0.8 ha will review the continued inclusion of this proposal in the LDP. (KDY037) 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

141

Site Site specific actions Delivery Status/Next Steps Former Bus Painters Who: Private Sector Site has planning permission for a superstore (retail class 1) Garage site Area: 1.1 ha 16/02147/FULL (KDY038) 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Invertiel Who: Private Sector No information is available. Fife Council as Planning Authority (KDY039) Area: 2.5 ha will review the continued inclusion of this proposal in the LDP. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Nairn Street Fife Council will work with key stakeholders to Who: Private Sector A PAN has been received for this site along with KDY 017 for (KDY044) facilitate appropriate development in this Area: 3.4 ha affordable housing development 17/02443/PAN location and to explore the potential for reopening of pedestrian linkages under the railway line to Den Road. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Leisure/Community Facility Site Site specific actions Delivery Status/Next Steps Windmill Road Who: Fife Council The development of a new secondary school is complete. (KDY040) Area: 6.3 ha

2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 COMPLETE

Chapel Area – North Who: Fife Council No information is available. Fife Council as Planning Authority of Chapel Retail Park Area: 1.4 ha will review the continued inclusion of this proposal in the LDP. (KDY047) 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

142

Cemetery Site Site specific actions Delivery Status/Next Steps West Kirkcaldy A site search will be undertaken within the Who: Fife Council No information is available. Fife Council as Planning Authority (KDY041) Local Development Plan period to identify and Area: will review the continued inclusion of this proposal in the LDP. reserve land for a new cemetery on the western side of Kirkcaldy. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Retail Park Extension Site Site specific actions Delivery Status/Next Steps Central Fife Retail Demonstrate that the proposal addresses Who: Private Sector No information is available. Fife Council as Planning Authority Park South either have a quantitative or qualitative Area: 2.1 ha will review the continued inclusion of this proposal in the LDP. (KDY042) deficiency and otherwise accords with the provisions of Policy 6, Town Centres First. Other non-retail uses could also be considered after 2026. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Business, hotel, commercial leisure Site Site specific actions Delivery Status/Next Steps John Smith Business Who: Private Sector This site has outline planning permission. Family restaurant is Park, Chapel Area: 19.9 ha now complete 16/00925/FULL (KDY043)

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 ✔

143

Leslie (Click here to view interactive map) Housing/Housing Opportunity Site Site Site specific actions Delivery Status/Next Steps Leslie House The units within the garden grounds will cross Who: Muir Homes Ltd This site has planning permission for conversion of Leslie House (LES001) subsidise refurbishment of Leslie House. Any Est. Capacity: 29 to 17 flats and erection of dwelling- houses within the grounds further development of garden ground outwith Area: 10 ha (06/00218/CFULL). Following a fire the conversion of Leslie the current consent will be resisted. House has not proceeded.

Residential development of 28 units within the grounds

approved on appeal. 14/01916/FULL

Discussions with developers on alternative proposals for Leslie House and pre-application enquiry submitted (17/02839/PREAPP)

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Prinlaws Mill Scottish Water: A Scottish Water Trunk Main Who: Private Sector Proposal of application for proposed masterplan and (LES002) traverses the site. This asset will require careful Est. Capacity: 85 redevelopment of Prinlaws Mill agreed (15/03577/PAN) consideration both during and after construction. Area: 3.4 ha Minimum stand-off distances will be required which may impact on development plans.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

South of Who: Private Sector Proposal of application for proposed masterplan and Walkerton Drive Est. Capacity: 42 redevelopment of Prinlaws Mill agreed (15/03577/PAN) (LES003) Area: 1.7 ha 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

144

Conservation Area Extension Site Site specific actions Delivery Status/Next Steps Leslie Who: Fife Council Conservation Area Appraisal (LES004) Area: 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Leven (Click here to view interactive map)

Proposals in Leven include the Thornton to Leven & Thornton to Westfield Rail lines; and the safeguarding of land at Bawbee Bridge for a rail halt.

Housing/Housing Opportunity Site Site Site specific actions Delivery Status/Next Steps Leven Vale South Who: Private Sector This site is complete. (LEV001) Est. Capacity: 75 Area: 3.1 ha 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 COMPLETE

Leven Vale West Who: Muir Homes This site has planning permission and is under construction. (LEV002) Est. Capacity: 200 05/04048/CFULL and 11/02826/FULL Area: 11 ha

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 ✔ Land at Cupar Who: Campion Homes This site has planning permission and is under construction. Road (LEV003) Est. Capacity: 100 15/03936/FULL Area: 5.4 ha 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 ✔

145

Employment Site Site specific actions Delivery Status/Next Steps Mountfleurie Who: Private Sector No information is available. Fife Council as Planning Authority will (LEV004) Area: 1.2 ha review the continued inclusion of this proposal in the LDP.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Development Opportunities Site Site specific actions Delivery Status/Next Steps Former Gasworks Who: Private Sector Planning application submitted for erection of single storey site (LEV006) Est capacity: 8 restaurant with drive thru land, car parking, landscaping and Area: 0.4 ha associated works including outdoor seating, canopies and play area 17/00073/FULL 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Former Who: Private Sector This site has full planning permission for 14 affordable Threeways Inn/ Area: 0.4 ha residential units. 15/02674/FULL North Street Gap Site (LEV007)

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 ✔

146

Levenmouth Area (Click here to view interactive map)

Proposals around the Levenmouth area include the Levenmouth Strategic Land Allocation LVA001; and the Thornton to Leven & Thornton to Westfield Rail lines.

Road Proposal Site Site specific actions Delivery Status/Next Steps Levenmouth Link The link road shall be developed in a phased Who: Fife Council The majority of the Link Road will be delivered as part of the Road (LVA002) manner during the period of the Local Plan, and its Cost: development of the Strategic Development Area. See LVA 001 route will be safeguarded from prejudicial Funding: for further details. development.

The final route will be determined through the masterplanning process.

The Levenmouth Link Road will be part funded through planning obligations. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

School/Community Facilities Site Site specific actions Delivery Status/Next Steps Levenmouth Who: Fife Council School complete Academy, Area: Methilhaven Road (LVA003) 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 COMPLETE

147

Lochgelly (Click here to view interactive map)

Proposals around the Lochgelly area include the Lochgelly Strategic Land Allocation.

Housing/Housing Opportunity Site Site Site specific actions Delivery Status/Next Steps Hugh Place Scottish Water: A Strategic Drainage Impact Who: Fife Council This site has planning permission - 11/02054/FULL (LGY001) Assessment is underway to understand the Est. Capacity: 25 cumulative impact of development on Lochgelly. Area: 1.2 ha Developers should keep in close contact with Scottish Water to understand what, if any, network upgrades are required to accommodate development in the area.

A water modelling exercise is also underway. Close co-operation with Scottish Water is highly recommended. 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 COMPLETE

148

Site Site specific actions Delivery Status/Next Steps South Street Scottish Water: A Strategic Drainage Impact Who: Housing Part of his site has planning permission 10/00299/FULL and is (LGY002) Assessment is underway to understand the Association complete. cumulative impact of development on Lochgelly. Est. Capacity: 32 Developers should keep in close contact with Area: 0.5 ha Scottish Water to understand what, if any, network upgrades are required to accommodate development in the area.

A water modelling exercise is also underway. Close co-operation with Scottish Water is highly recommended 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

The Avenue Scottish Water: A Strategic Drainage Impact Who: Private Sector Application for amendment to previous permission is awaiting (LGY003) Assessment is underway to understand the Est. Capacity: 90 decision. 17/02676/FULL cumulative impact of development on Lochgelly. Area: 6.6 ha Developers should keep in close contact with Scottish Water to understand what, if any, network upgrades are required to accommodate development in the area.

A water modelling exercise is also underway. Close co-operation with Scottish Water is highly recommended

Discussions are underway (Dec 17) with the developer to accommodate initial builds whilst modelling exercise is completed.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 ✔

149

Site Site specific actions Delivery Status/Next Steps West Cartmore Scottish Water: A Strategic Drainage Impact Who: Fife Council No information is available. Fife Council as Planning Authority will (LGY004) Assessment is underway to understand the Est. Capacity: 60 review the continued inclusion of this proposal in the LDP. cumulative impact of development on Lochgelly. Area: 3.7 ha Developers should keep in close contact with Scottish Water to understand what, if any, network upgrades are required to accommodate development in the area.

A water modelling exercise is also underway. Close co-operation with Scottish Water is highly recommended

Scottish Water: water main traverses site. This asset will need to be adequately managed both during and after construction. Minimum stand-off distances may be enforced.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Employment Site Site specific actions Delivery Status/Next Steps Cartmore Who: Private Sector No information is available. Fife Council as Planning Authority will Industrial Estate Area: 3.6 ha review the continued inclusion of this proposal in the LDP. Extension (LGY005)

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

150

Site Site specific actions Delivery Status/Next Steps Lochgelly Who: Fife Council No information is available. Fife Council as Planning Authority Industrial Park Area: 2.3 ha will review the continued inclusion of this proposal in the LDP. (LGY006) 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Development Opportunity Site Site specific actions Delivery Status/Next Steps Former Fab-Tek Who: Private Sector This site has planning permission for retail use. 13/00470/FULL site , High Street Area: 1.1 ha (LGY008) 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Adjacent Library, Who: Private Sector St Andrews Church and Town House: Main Street Area: 0.8 ha (LGY009)  Church Currently being re-developed by Fife Council. Planning Permission Granted for Phase 1 which will deliver the improved building which will complete by February 2018. Phase 2 – Preferred option for the building is a Regional Climbing and Bouldering Centre. Planning permission will be sought to create an extension to the existing building to accommodate the climbing wall.  Town House has been converted into 4 affordable housing units, with adjacent land also developed for 12 new affordable housing units by FC.  Area to the North of Church developed by Ore Valley Housing Association again for Affordable Housing (think 15 units).  Area between the Church and Town House – a town square will be created with public realm and soft landscaping.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 ✔ 151

Leisure/Community Site Site specific actions Delivery Status/Next Steps Muir Park Who: Fife Council No information is available. Fife Council as Planning Authority will (LGY010) Area: 0.8 ha review the continued inclusion of this proposal in the LDP. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Cartmore Road This site should be safeguarded for educational Who: Fife Council No information is available. Fife Council as Planning Authority will (LGY011) use until further assessment by Fife Council’s Area: review the continued inclusion of this proposal in the LDP. Education Service has been undertaken and preferred site(s) identified. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Assessment of Transport Options Site Site specific actions Delivery Status/Next Steps Launcherhead The consideration of options requires an Who: Fife Council No information is available. Fife Council as Planning Authority will Park assessment of the viability and deliverability of Cost: review the continued inclusion of this proposal in the LDP. (LGY012) providing a relocated rail station based on Scottish Funding: Transport Appraisal Guidance (STAG) principles. Dependent on the outcome of the assessment, a robust business case will follow.

Transport Scotland currently has no plans to fund or deliver a station at this location and an alternative source of funding will require to be identified.

Discussion and agreement with Transport Scotland and Network Rail is required.

152

Site Site specific actions Delivery Status/Next Steps (LGY012) In the event that the preferred option is to continued relocate the existing rail station, land at Launcherhead Park will be safeguarded.

If playing fields are lost as a consequence of the relocation of the station, they will have to be replaced elsewhere.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Lochore (Click here to view interactive map) Housing/Housing Opportunity Site Site Site specific actions Delivery Status/Next Steps Capledrae Farm Community open space will be provided to north Who: Private Sector No information is available. Fife Council as Planning Authority (LHR001) east of the site. This shall include tree planting to Est. Capacity: 100 will review the continued inclusion of this proposal in the LDP. create a well-defined edge between new Area: 5.1 ha development and the countryside. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

North of Ivanhoe Who: Koncept Homes This site has planning permission. 17/00806/FULL Crescent, Lochore Est. Capacity: 28 (LHR002) Area: 0.6 ha 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

153

Employment Site Site specific actions Delivery Status/Next Steps Loanhead Avenue Who: Fife Council No information is available. Fife Council as Planning Authority (LHR003) Area: 5.2ha will review the continued inclusion of this proposal in the LDP. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Other Site Site specific actions Delivery Status/Next Steps Lochore Fife Council, through the Lochore Meadows Who: Fife Council No information is available. Fife Council as Planning Authority Meadows Country Park Management Group, will produce a Area: will review the continued inclusion of this proposal in the LDP. (LHR004) masterplan for Lochore Meadows. This will set out the future plans for the park. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Methil & Methilhill (Click here to view interactive map) Housing/Housing Opportunity Site Site Site specific actions Delivery Status/Next Steps South Grove Who: Housing This site is complete. (MET001) Association Est. Capacity: 10 Area: 0.6 ha 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 COMPLETE

154

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 Site Site specific actions Delivery Status/Next Steps Methilhill House Who: Private Sector This site has outline planning permission for conversion of the (MET002) Est. Capacity: 9 dwellinghouse to form 4 flats and erection of 5 dwelling houses Area: 0.4 ha - 03/02455/COPP.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Sea Road/ Chemiss Access to this site must be taken from Sea Road at a Who: Private Sector No information is available. Fife Council as Planning Authority Road, Methilhill location to be agreed with Fife Council. Est. Capacity: 24 will review the continued inclusion of this proposal in the LDP. (MET003) Area: 1 ha

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Glencast Foundry Methil Brae would need to be upgraded to Who: Robertson Site under construction for 123 homes. 15/00937/FULL (MET004) accommodate development on this site. Partnership Homes Est. Capacity: 100 Area: 5.2 ha 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 ✔

Employment Site Site specific actions Delivery Status/Next Steps Methil Docks Who: Private Sector Planning permission granted on part of site for ground- Business Park - Area: 3.4ha mounted solar panels. 16/00033/FULL Land north of Bayview Football Stadium (MET005) 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

155

Site Site specific actions Delivery Status/Next Steps Methil Docks Who: Private Sector Planning permission granted for erection of 4 business units Business Park - Ajax Area: 0.8ha (Class 4) - 05/04237/CFULL Way (MET006) 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Methil Docks Who: Private Sector No information is available. Fife Council as Planning Authority Business Park - Area: 0.9ha will review the continued inclusion of this proposal in the LDP. West of Doctors surgery(MET007) 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Methil Docks Who: Private Sector No information is available. Fife Council as Planning Authority Business Park - Area: 0.8ha will review the continued inclusion of this proposal in the LDP. West of Thomson House (MET008) 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Energy Park Fife - Who: Scottish No information is available. Fife Council as Planning Authority Barclay Brothers Enterprise will review the continued inclusion of this proposal in the LDP. site (MET009) Area: 1.3ha 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

156

Development Opportunity Site Site specific actions Delivery Status/Next Steps Methil Power A design framework/ master-plan should be Who: Private Sector No information is available. Fife Council as Planning Authority Station (MET011) produced to provide detailed design guidance for Area: 4.4 ha will review the continued inclusion of this proposal in the LDP. development within this area and should take into account the recommendations from the Bawbee Bridge design led consultation charrette in 2013. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Milton of Balgonie (Click here to view interactive map) Housing/Housing Opportunity Site Site Site specific actions Delivery Status/Next Steps Balfour Place/ Main A master plan shall be prepared to guide Who: Private Sector No information is available. Fife Council as Planning Authority Street (MOB001) development, including the final number of houses Est. Capacity: 63 will review the continued inclusion of this proposal in the LDP. proposed. Area: 2.1 ha

Scottish Water: A Water Impact Assessment is required to understand what, if any, impact this development will have on the existing water network. Any network upgrades identified must be funded and carried out by the developer.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

157

Newburgh (Click here to view interactive map)

Proposals in Newburgh include the safeguarding of land for a rail halt.

Housing/Housing Opportunity Site Site Site specific actions Delivery Status/Next Steps South of Cupar A Development Framework covering sites NEB 001 Who: A&J Stephen Proposal of Application Notice agreed (17/02027/PAN) Road (NEB001) and NEB 002 should be prepared by the developer Est. Capacity: 225 for Fife Council approval with input from all land Area: 8.8 ha owners and following consultation with the local community. This will identify the limits and phasing of development.

Separation must be maintained between housing at the eastern edge of Newburgh and the houses in Burnside to avoid settlement coalescence.

Scottish Water: Water and Drainage Impact Assessments are required to understand what impact, if any, this development has on existing water and drainage infrastructure. Any upgrades identified as part of this process must be funded and delivered by the developer. In addition, Growth is required at the Newburgh WWTW to accommodate this development. Scottish Water has received the 5 growth criteria from the developer and is progressing with activities at the works to accommodate this.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

158

Site Site specific actions Delivery Status/Next Steps Land North of A Development Framework covering sites NEB 001 Who: A&J Stephen Proposal of Application Notice agreed (17/02027/PAN) Cupar Road, and NEB 002 should be prepared by the developer Est. Capacity: 50 Newburgh for Fife Council approval with input from all land Area: 1.9 ha (NEB002*) owners and following consultation with the local community. This will identify the limits and phasing of development.

Scottish Water: Water and Drainage Impact Assessments are required to understand what impact, if any, this development has on existing water and drainage infrastructure. Any upgrades identified as part of this process must be funded and delivered by the developer. In addition, Growth is required at the Newburgh WWTW to accommodate this development. Scottish Water has received the 5 growth criteria from the developer and is progressing with activities at the works to accommodate this.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Mugdrum East Who: Private Sector Planning permission granted for erection of 8 dwellinghouses - (NEB003) Est. Capacity: 8 08/01910/FULL Area: 0.2 ha 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

159

Newport on Tay (Click here to view interactive map) Housing/Housing Opportunity Site Site Site specific actions Delivery Status/Next Steps Ericht Road, Development should not break the skyline when Who: St Fort Estate No information is available. Fife Council as Planning Authority Newport viewed from Dundee’s Waterfront. Est. Capacity: 100 will review the continued inclusion of this proposal in the LDP. (NEW001) Area: 5.6 ha 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

South of Victoria Who: Private Sector No information is available. Fife Council as Planning Authority Park, Newport Est. Capacity: 50 will review the continued inclusion of this proposal in the LDP. (NEW002) Area: 2 ha

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Development Opportunity Site Site specific actions Delivery Status/Next Steps North West of Who: Private No information is available. Fife Council as Planning Authority Forgan Area: 2.8 ha will review the continued inclusion of this proposal in the LDP. Roundabout (NEW003) 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

160

Oakley (Click here to view interactive map) Housing/Housing Opportunity Site Site Site specific actions Delivery Status/Next Steps Woodburn There is potential to develop the site in conjunction Who: Registered No information is available. Fife Council as Planning Authority Crescent with adjacent OAK 005 site. Social Landlord will review the continued inclusion of this proposal in the LDP. (OAK001) Est. Capacity: 9 Area: 0.2 ha 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Land at Pavilion & A masterplan for the whole area covered by OAK Who: Fife Council/ Planning application - 16/01828/PAN Bowling Green 002/OAK003/ OAK004 is required to ensure a well Private Sector Dunfermline wide contributions towards additional secondary (OAK002) planned development. The masterplan exercise will Est. Capacity: 15 capacity are now sought – see Planning Obligations be carried out by the appropriate landowners and Area: 0.5 ha Supplementary Guidance 2017. developers, in consultation with the council. Additional capacity required by 2022

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Land to north of As per OAK002 above. Who: Private Sector Planning application - 16/01828/PAN Oakley (OAK003) Est. Capacity: 260 Dunfermline wide contributions towards additional secondary Scottish Water: A Drainage and Water Impact Area: 14.1 ha capacity are now sought – see Planning Obligations Assessment will be required to understand the Supplementary Guidance 2017. impact this proposed development will have on the Additional capacity required by 2022 existing public network. Any network upgrades

identified must be funded and delivered by the developer. Early engagement with Scottish Water is highly recommended. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

161

Site Site specific actions Delivery Status/Next Steps Holy Name Primary There is potential to develop the site in conjunction Who: Fife Council Planning application approved - 17/02725/FULL. School (OAK005) with adjacent OAK001 site. Est. Capacity: 15 Erection of 23 affordable dwellings with associated resident's Area: 1 ha hub, infrastructure and formation of vehicular access.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Employment Site Site specific actions Delivery Status/Next Steps Land north of Masterplan exercise will be carried out by the Who: Private Sector Planning application - 16/01828/PAN Industrial Estate appropriate landowners and developers, in Area: 1.9 (OAK004) consultation with the council.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Rosyth (Click here to view interactive map)

Proposals around Rosyth include the signalisation of Kings Road/Admiralty Road Junction (ROS018)

Housing/Housing Opportunity Site Site Site specific actions Delivery Status/Next Steps Admiralty Road Who: Private Sector No information is available. Fife Council as Planning Authority (ROS001) Est. Capacity: 12 will review the continued inclusion of this proposal in the LDP. Area: 0.2 ha 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

162

Site Site specific actions Delivery Status/Next Steps Brankholme Lane Who: Private Sector The site has outline planning permission for housing. (ROS002) Est. Capacity: 9 06/02327/WOPP Area: 0.1 ha

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Cochranes Hotel Who: Private Sector The site has planning permission for housing. 08/02136/WFULL (ROS003) Est. Capacity: 54 and 11/00020/FULL Area: 0.7 ha 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Primrose Lane 2 Who: Private Sector/ Pre-application submission submitted for this site. (ROS004) Registered Social Dunfermline wide contributions towards additional secondary Landlord capacity are now sought – see Planning Obligations Est. Capacity: 175 Supplementary Guidance 2017. Area: 7.4 ha Additional capacity required by 2022 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Castlelandhill Who: Private Sector No information is available. Fife Council as Planning Authority (north) Est. Capacity: 150 will review the continued inclusion of this proposal in the LDP. (ROS016) Area: 10.7 ha Dunfermline wide contributions towards additional secondary capacity are now sought – see Planning Obligations Supplementary Guidance 2017. Additional capacity required by 2022

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

163

Housing/Retail/Care Home/Hotel Site Site specific actions Delivery Status/Next Steps Land at Admiralty Who: Kapital The site has planning permission (11/06658/PPP ) - 62 units Road & East of Developments completed. Brankholm Est. Capacity: 450 (ROS015) Area: 12.2 ha

2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 2017/18 ✔

Employment Site Site specific actions Delivery Status/Next Steps Rosyth Europarc 3 Who: Private Sector Rosyth waterfront development framework has been produced (ROS005) Area: 0.6 ha and approved. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Rosyth Waterfront Who: Private Sector Rosyth waterfront development framework has been produced 1 (ROS006) Area: 16.8 ha and approved. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Rosyth Europarc 1 Who: Private Sector Rosyth waterfront development framework has been produced (ROS007) Area: 3.1 ha and approved.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Rosyth Europarc 2 Who: Private Sector Rosyth waterfront development framework has been produced (ROS008) Area: 2.4 ha and approved.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

164

Site Site specific actions Delivery Status/Next Steps Rosyth Waterfront Who: Private Sector Rosyth waterfront development framework has been produced 2 (ROS009) Area: 10 ha and approved. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Rosyth Waterfront Who: Private Sector Rosyth waterfront development framework has been produced 3 (ROS010) Area: 1 ha and approved.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Admiralty Park Who: Private Sector No information is available. Fife Council as Planning Authority (ROS011) Area: 6.9 ha will review the continued inclusion of this proposal in the LDP. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Transport Site Site specific actions Delivery Status/Next Steps Rosyth The Rosyth rail link should be safeguarded to serve Who: Private Sector Rosyth waterfront development framework has been produced International the container terminal. Area: 24.5 ha and approved. Container Terminal Proposed development and ancillary works shall (ROS013) therefore only occur as set out within the Rosyth International Container Terminal (Harbour Revision) Order 2013. Subsection 5(1) of that Order being the primary reference point for permissible development or works.

A Construction Environmental Action Plan and other measures as detailed in the 2013 Harbour Revision Order is necessary prior to development on this site. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

165

Site Site specific actions Delivery Status/Next Steps Rosyth Rail Halt Who: Fife Council The site has planning permission. 08/00984/EIA Park and Choose Area: 7.2 (ROS014) 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Rosyth Bypass Who: Fife Council No information is available. Fife Council as Planning Authority (ROS019) will review the continued inclusion of this proposal in the LDP. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Leisure/Community/Tourist Related Development Site Site specific actions Delivery Status/Next Steps Rosyth Waterfront The proximity of the site to the Ferry terminal Landowner/ Private The site is occupied by the compound for the Queensferry 4 (ROS012) provides opportunity to develop a Gateway to sector Crossing until December 2018. Scotland and other tourist and community related developments. Further detail will be necessary as Rosyth waterfront development framework has been produced part of any development proposal. All proposals and approved. The Rosyth waterfront development framework must make use of the existing transport networks adds some flexibility over the location of these uses within the and topography. waterfront area.

Retail development will be tourist related and be limited to no more than 1,858 sq.m. gross floorspace.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 ✔

166

Biomass Facility Site Site specific actions Delivery Status/Next Steps Rosyth Renewable In accordance with Scottish Ministers approval in Who: Fife Council Rosyth waterfront development framework has been produced Energy Plant January 2014 consent was granted under section 36 Area: and approved. The Rosyth waterfront development framework (ROS020) of the Electricity Act 1989 (the Electricity Act) for has been produced. The draft Rosyth waterfront DF adds some construction and operation of Rosyth Biomass flexibility over uses for this site electricity generating station at the Port of Rosyth - Future applications and proposals shall reflect the conditions set out in the consent notice – see link below : http://www.scotland.gov.uk/Resource/0044/0044 2350.pdf

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Saline (Click here to view interactive map) Housing/Housing Opportunity Site Site Site specific actions Delivery Status/Next Steps North Main Street Who: Private Sector This site has planning permission and is currently under (SAL001) Est. Capacity: 10 construction - 13/01241/FULL Area: 3.7 ha

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 ✔

167

Site Site specific actions Delivery Status/Next Steps Kinnedar Mains The following will be required in support of Who: Allanwater This site has planning permission and is currently under (SAL002) development of the site: Homes construction. 11/03913/PPP and 15/03023/ARC Est. Capacity: 70 -A landscape framework; Area: 3.1 ha -A drainage strategy; -A design framework; -A phasing strategy for the whole site; and -A public art strategy for the whole site.

The development of the site will contribute to a funding package to secure the rehabilitation, including decontamination, of the nearby Comrie Colliery. The details of how and when this will be implemented shall be confirmed through future planning permissions and associated legal agreements.

Scottish Water: A Drainage Impact Assessment is required to understand the impact this development may have on the existing development. Any upgrade requirements must be funded and carried out by the developer. A Growth project is required at the Saline WWTW to facilitate this development. An early Flow and Load/Process Unit assessment is currently planned. Scottish Water is funded for growth following the provision of the 5 growth criteria.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 ✔

168

Site Site specific actions Delivery Status/Next Steps West Road Scottish Water: A Drainage Impact Assessment is Who: Gladman No information is available. Fife Council as Planning Authority (SAL003) required to understand the impact this Developments will review the continued inclusion of this proposal in the LDP. development may have on the existing Est. Capacity: 130 Dunfermline wide contributions towards additional secondary development. Any upgrade requirements must be Area: 8.4 ha capacity are now sought – see Planning Obligations funded and carried out by the developer. A Growth Supplementary Guidance 2017. project is required at the Saline WWTW to facilitate Additional capacity required by 2022 this development. An early Flow and Load/Process

Unit assessment is currently planned. Scottish Water is funded for growth following the provision of the 5 growth criteria. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Saline Park A development framework for the whole site Who: Housing This site has planning permission in principle - 13/02421/PPP and (SAL004) comprising the following: Association 16/01183/PPP -a landscape framework; Est. Capacity: 52 -a drainage strategy; Area: 2.1 ha -a design framework; -a public art strategy for the whole site.

In the event of the submission of a revised or further proposal, account must be taken of adjacent ancient woodland which shall be the subject of detailed survey to determine the need for and depth of any protective buffer strip. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

169

St Andrews (Click here to view interactive map)

Proposals around the St Andrews area include the St Andrews Strategic Land Allocation (STA001).

Housing/Housing Opportunity Site Site Site specific actions Delivery Status/Next Steps Grange Road Scottish Water: A Scottish water funded Strategic Who: University of St Planning application submitted for erection of 61 dwellings (STA002) Drainage Impact assessment is currently underway Andrews (accommodation for University of St Andrews), formation of for the St Andrews catchment. The results are Est. Capacity: 50 access roads, parking, amenity space and drainage expected in Summer 2018. Grange Road is included Area: 2.2 ha infrastructure - 17/03554/FULL within this study and may have some form of contribution to any upgrades that are required. Close engagement with Scottish Water is recommended. A growth project is underway at St Andrews WWTW. A small capital project will enable immediate development in St Andrews. Timescales not expected to impact build out plans. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

New Park School Who: Private Sector This site is under construction. Development to be in line with (STA003) Est. Capacity: 21 findings of planning appeal ref: P/PPA/250/760 Area: 1.5 ha

2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 2017/18 ✔

St Leonards Who: Robertson Majority of site complete. (STA006) Homes Est. Capacity: 240 Area: 4.4 ha

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 ✔

170

Employment Site Site specific actions Delivery Status/Next Steps St Leonards Lodge This site is to be developed in conjunction with Who: Private Sector This site has full planning permission. 14/01157/FULL (STA007) STA 006. Area: 0.2 ha

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Strathtyrum The prominent location at an important entry to the Who: Private Sector No information is available. Fife Council as Planning Authority (STA008) town demands a high standard of design and finish Area: 7.1 ha will review the continued inclusion of this proposal in the LDP. and low density development with a high standard of landscaping.

The employment potential of the site suits research and development, high technology development, proposals which require links to the university.

General industrial use not appropriate.

Hotel use would also be acceptable as part of a development of the site. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

171

Development Opportunity Site Site specific actions Delivery Status/Next Steps East Sands Updated or amended versions of the design Who: Fife Council, The East Sands Urban Design Framework was approved in (STA014) framework will be the subject of consultation with University of St 2010 and will continue to be used in the consideration of the community. Andrews, The Crown development proposals in the East Sands area. Estate, St Andrews Harbour Trust, Private Sector Area: 13 ha 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Conservation Area Extension Site Site specific actions Delivery Status/Next Steps Fleming Place, Who: Fife Council Extension of conservation area approved at committee. Kinnessburn & Park Area: Requires to be advertised before the conservation area is Street (STA009) formally extended. 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 COMPLETE

Hepburn Gardens Who: Fife Council Extension of conservation area approved at committee. (STA010) Area: Requires to be advertised before the conservation area is formally extended. Conservation Area Appraisal. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Other Site Site specific actions Delivery Status/Next Steps West Sands Who: Fife Coast & A planning application was submitted for construction of a (STA011) Countryside Trust new visitor centre (ref: 14/02756/FULL - but was refused. Area: 0.3 ha 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

172

Site Site specific actions Delivery Status/Next Steps Botanic Gardens Development uses must be sympathetic and Who: University of St Planning permission approved for siting of four workshop (STA012) complementary to the continued role of the wider Andrews/Friends of /storage containers and erection of garage /storage building area as a Botanic Garden. the Botanic Gardens associated with botanic gardens - 16/03913/FULL Area: 0.5 ha

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

St Monans (Click here to view interactive map) Housing/Housing Opportunity Site Site Site specific actions Delivery Status/Next Steps West of Manse Scottish Water: A Drainage Impact Assessment is Who: Muir Homes A first phase of development for 57 homes was granted full (STM001) required to assess the impact of this development Est. Capacity: 100 planning permission subject to a Section 75 agreement. on the existing public drainage network. A drainage Area: 4.5 ha However, the applicant has subsequently withdrawn the model is currently being built to accommodate this application. 14/03773/PAN exercise. In addition, Growth is required at the St Monans WWTW. Scottish Water is funded for Growth following provision of the 5 growth criteria. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Employment Site Site specific actions Delivery Status/Next Steps Netherton Who: Fife Council/ No information is available. Fife Council as Planning Authority Industrial Estate Private Sector will review the continued inclusion of this proposal in the LDP. (STM002) Area: 0.8 ha

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

173

Allotments Site Site specific actions Delivery Status/Next Steps West of Manse Should reflect the principles set out in the Who: Fife Council This proposal will be delivered as part of site STM001. (STM003) Indicative Development Framework diagram. Area: 0.7 ha

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Cemetery Site Site specific actions Delivery Status/Next Steps Cemetery, Who: Fife Council No information is available. Fife Council as Planning Authority St Monans Church Area: 0.4 ha will review the continued inclusion of this proposal in the LDP. (STM004) 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Stratheden (Click here to view interactive map) Health/Low Density Housing/Hotel/Leisure/Education/Open Space Site Site specific actions Delivery Status/Next Steps Stratheden Development intentions and design statement to be Who: NHS Fife No information is available. Fife Council as Planning Authority Hospital prepared by developers for public consultation and Area: 28.6 ha will review the continued inclusion of this proposal in the LDP. (SED001) subsequent Fife Council approval. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

174

Strathkinness (Click here to view interactive map) Housing/Housing Opportunity Site Site Site specific actions Delivery Status/Next Steps Main Street/ Who: Private Sector Site complete. Sunnyside Est. Capacity: 32 (STK001) Area: 1.8 ha 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 COMPLETE

South of Who: Fife Council Conditional Planning Permission in Principle granted subject Recreation Ground Est. Capacity: 16 to legal agreement (15/04130/PPP) (STK002) Area: 0.6 ha

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Bonfield Road, A phased approach to development may be required Who: Avant Homes Conditional Planning Permission in Principle granted subject Strathkinness to avoid capacity issues at Strathkinness Primary Est. Capacity: 50 to legal agreement (15/04130/PPP) (STK003) School. Area: 3.9 ha

Scottish Water is in direct discussion with the developer’s design consultation team regarding drainage solutions for the site. Surface Water removal options are being considered to permit access to the existing network without the need for a drainage impact assessment.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

175

Tayport (Click here to view interactive map) Housing/Housing Opportunity Site Site Site specific actions Delivery Status/Next Steps Links Road 2 Who: Private Sector No information is available. Fife Council as Planning Authority (TAY001) Est. Capacity: 6 will review the continued inclusion of this proposal in the LDP. Area: 0.1 ha 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Net Drying Green Who: Private Sector No information is available. Fife Council as Planning Authority (TAY002) Est. Capacity: 10 will review the continued inclusion of this proposal in the LDP. Area: 0.2 ha 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

North of Spearshill Who: Private Sector No information is available. Fife Council as Planning Authority Road (TAY003) Est. Capacity: 12 will review the continued inclusion of this proposal in the LDP. Area: 0.5 ha 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Nelson Street Who: Private Sector No information is available. Fife Council as Planning Authority (TAY004) Est. Capacity: 5 will review the continued inclusion of this proposal in the LDP. Area: 0.1 ha 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Scotscraig Works Who: Private Sector No information is available. Fife Council as Planning Authority (TAY005) Est. Capacity: 25 will review the continued inclusion of this proposal in the LDP. 2017/18 2018/19 2019/20 2020/21Area: 0.9 ha 2021/22 2022/23 2023/24 Post 2024

176

Employment Site Site specific actions Delivery Status/Next Steps Shanwell Road Who: Private Sector No information is available. Fife Council as Planning Authority (TAY006) Area: 0.3 ha will review the continued inclusion of this proposal in the LDP.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Leisure/Community Site Site specific actions Delivery Status/Next Steps Abertay Works Fife Council will re-allocate the site for employment Fife Council/ Tayport Planning permission granted for community facilities. Funding (TAY007) and residential uses if the community group are Community & Sports in the process of being secured by Tayport Community Trust. unable to secure planning permission and funding Centre Action Group 15/03784/FULL before the end of 2015. Est. capacity: 15 Area: 1.3 ha 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Cemetery Extension Site Site specific actions Delivery Status/Next Steps Cemetery Who: Fife Council Extension complete. (TAY008) Area: 0.8 ha 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 COMPLETE

Car Park Site Site specific actions Delivery Status/Next Steps Links Road Who: Fife Council No information is available. Fife Council as Planning Authority (TAY009) Area: 0.2 ha will review the continued inclusion of this proposal in the LDP. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

177

Allotments Site Site specific actions Delivery Status/Next Steps Tayport Fife Council is actively pursuing the identification of Who: Fife Council Planning permission granted to form community garden at (TAY010) appropriate land for allotment use in the Tayport Area: Pond Lane/New Street, Tayport (15/01157/FULL ) area. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Torryburn (Click here to view interactive map) Woodland Management Plan Site Site specific actions Delivery Status/Next Steps Craigflower A Woodland Management Plan is to be prepared by Who: Fife Council/ Partnership delivery scoping to occur with community group/s Woodland the landowners for implementation, monitoring, Private Sector (West Fife Woodlands) – explore links to Participatory (TOR001) and review by Fife Council. Any proposed work in Area: 18.2 ha Budgeting initiative and funding (4 March 2017) the management plan must be consistent with Local Development Plan policies in relation to priority habitats and species.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

West Wemyss (Click here to view interactive map) Housing/Leisure/Community/Commercial Site Site specific actions Delivery Status/Next Steps Wemyss Estate Land Any development on this site must stabilise the cliff Who: Private Sector Application 13/01684/ARC for the erection of 42 dwellings, at West Wemyss face and secure the future of the B listed Shorehead Est. Capacity: 42 formation of vehicular access, car parking and roads including (WW 001) house. Area: 3.6 ha engineering works to reprofile and stabilise the cliff face was approved on 3 June 2016.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

178

Windygates (Click here to view interactive map) Housing/Housing Opportunity Site Site Site specific actions Delivery Status/Next Steps Balcurvie Meadows Who: Private Sector This site is complete. (WDY001) Est. Capacity: 56 2.9 ha

2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 COMPLETE

Land at Temple Scottish Water: Early engagement with Scottish Who: Carneil Homes No information is available. Fife Council as Planning Authority (WDY002) Water is required to understand water and Est. Capacity: 75 will review the continued inclusion of this proposal in the LDP. drainage requirements. A water and/or drainage Area: 3.4 ha impact assessment may be requested to understand the impact this site may have on the existing network. Any upgrade works identified on the network must be funded and carried out by the developer. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Rail Freight Facilities Site Site specific actions Delivery Delivery Update/Next Steps Cameron Bridge Land at Cameron Bridge, Windygates, will be Who: Private Sector No information is available. Fife Council as Planning Authority (WDY003) safeguarded for the provision of rail freight Area: 2.8 ha will review the continued inclusion of this proposal in the LDP. facilities associated with the operation of the adjacent and nearby Diageo plants.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

179

Wormit (Click here to view interactive map)

Proposals in Wormit include the safeguarding of land for a rail halt.

Housing/Leisure/Community/Commercial Site Site specific actions Delivery Status/Next Steps Wormit Farm Who: Private Sector Proposal of Application Notice (16/03773/PAN) submitted (Housing) Est. Capacity: 30 by Persimmon Homes for sites WOR 001, WOR 002 and (WOR001) Area: 1.2 ha WOR 003. Application submitted for 44 houses submitted (17/02224/FULL)

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Wormit Sandpit Who: Private Sector Proposal of Application Notice (16/03773/PAN) submitted (WOR002) Est. Capacity: 47 by Persimmon Homes for sites WOR 001, WOR 002 and Area: 1.9 ha WOR 003. Application submitted for 44 houses submitted (17/02224/FULL ).

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

South of Wormit To be developed only once a substantive start to Who: Private Sector Proposal of Application Notice (16/03773/PAN) submitted Farm (WOR003) construction has been made at both sites WOR01, Est. Capacity: 135 by Persimmon Homes for sites WOR001, WOR002 and Wormit Farm (Housing) and WOR02, Wormit Area: 5.5 ha WOR003. Sandpit.

Scottish Water: A Water Impact Assessment is required to understand what impact, if any, this development will have on the existing water infrastructure. The developer will be responsible for funding and carrying out any upgrades identified.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

180

Countryside Area (outwith town and village boundaries)

Strategic proposals in Fife’s countryside include Longannet Power Station; and the Forth Crossing

Housing/Housing Opportunity Site Site Site specific actions Delivery Status/Next Steps Bellfield Given the sensitive rural location of this site no Who: Private Sector This site has planning permission in principle (14/01095/PPP), (LWD036) more than 5 dwellings would be allowed. Proposals Est. Capacity: 5 an extension to this consent was granted in 2017 in excess of this number will be treated as contrary maximum (17/00496/PPP) to FIFEplan. Area: 1.3 ha

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Employment Site Site specific actions Delivery Status/Next Steps Westfield Green Who: Private Sector Planning permission for a Biomass Power Station and associated Business Park Area: 103.4 ha facilities was approved on 17 September 2008 (07/00170/CEIA) (LWD009) and further Planning Permission (08/02825/EIA) was granted on 25 April 2011.

Application submitted for discharge of Planning Obligation 07/00170/CEIA for construction and operation of a biomass facility comprising a combined 40.6 Mwr heat and power plant, pellet manufacturing plant, biomass stockpiling and processing area and associated roadways (decision not implemented) (17/03871/OBL) Planning application submitted for the installation and operation of up to ten gas engines with a generating capacity of 19.96MW and ancillary development on land at the former Westfield opencast coal site (17/03377/FULL )

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

181

Site Site specific actions Delivery Status/Next Steps Mossmorran This land is to be safeguarded for the potential Who: Private Sector No information is available. Fife Council as Planning Authority potential expansion expansion of Mossmorran. Area: 284 ha will review the continued inclusion of this proposal in the LDP. (LWD020) 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Cemetery Extension Site Site specific actions Delivery Status/Next Steps Boarhills Cemetery Site to be determined during lifetime of Local Plan Who: Fife Council No information is available. Fife Council as Planning Authority (LWD023) in consultation with the local community. Area: 2 ha will review the continued inclusion of this proposal in the LDP. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

St Andrews To include Green Burial area. Fife Council No information is available. Fife Council as Planning Authority (LWD026) Area: 4 ha will review the continued inclusion of this proposal in the LDP.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Hotel/Leisure/Tourism Site Site specific actions Delivery Status/Next Steps Craigtoun Country Further explore options for the long-term Who: Fife Council/ Improvements being taken forward by the Friends of Craigtoun Park (LWD021) sustainable management and operation of Private Sector Park. Craigtoun Country Park, both through a continuing Area: 16.3 ha partnership with the Friends of Craigtoun Country Park and/or complementary tourism-related projects linked to the upgrading of the park (including sensitive, small scale, commercial leisure or hotel development). 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

182

Leisure/Tourism/Recreation Site Site specific actions Delivery Status/Next Steps Crail Airfield Developers to prepare a development brief and Who: Private Sector Proposal of Application Notice for mixed use development (LWD022) undertake community consultation for Fife Council Area: 145.6 ha submitted - 14/03593/PAN. approval. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Castlehill Mine A housing allocation incorporating environmental Who: Private Sector Planning permission in principle granted for residential (LWD032) principles is anticipated subject to detailed Area: development comprising 38 dwelling houses and 6 live/work assessment. A development brief for Fife Council Est. capacity: 35 units with associated landscaping - 10/04168/PPP approval is necessary. (Section 42 application approved to amend condition 5 of 10/04168/PPP) - 15/00816/PPP

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Extension of Landfill and Recycling Centre Site Site specific actions Delivery Status/Next Steps Lower Melville Detailed consideration of the layout, height and Who: Fife Council Fife Council recycles nearly 55% of municipal waste at two sites Woods, Ladybank landform, together with assessment of the Area: 68.6 ha operated on behalf of the Council, including Lower Melville (LWD027) environmental health factors affecting site Wood. Further development in the general area of the site will development and the impact on the amenity of be restricted, in the main to land immediately to the west of local residents, will be subject to local consultation the existing site, a redundant sand and gravel quarry. It is most as part of any planning application. unlikely that development proposals will include landfilling of waste; however, proposals may be brought forward for other Further development in the general area of the site waste and resource management activities including pre will be restricted, in the main, to land immediately processing of waste prior to removal from site for energy and to the west of the existing site, a redundant sand heat recovery elsewhere, biomass production, composting, and gravel quarry. recycling, and resource recovery from waste. Any such proposals will be the subject of detailed planning applications

183

Site Site specific actions Delivery Status/Next Steps (LWD027) which will address appropriate environmental considerations continued and associated issues such as visual impact. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Pilgrim Way Long Distance Footpath Site Site specific actions Delivery Status/Next Steps St Andrews to Route to be identified via Fife Council Core Path Who: Fife Coast and Funding understood to be received (Heritage Lottery Fund) and Dunfermline Plan. Countryside Trust marketing underway. (LWD028) Area: Abbot House to be re-developed as a Community Arts Space and Café/restaurant as well as provision of accommodation to service the developing “Pilgrims Way” and tourist information.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 ✔

Park Improvements Site Site specific actions Delivery Status/Next Steps Silverburn Park, Following appropriate consultation a development Who: Fife Council Planning permission for camping site, community allotments Leven (LWD029) plan will be produced for Silverburn Park within the Area: and other facilities granted (15/01094/FULL). Fife Council has period of the Local Plan. This will examine the announced plans to transform the derelict Silverburn House possibility of limited development within the park into a training centre and museum. Survey work is taking place to cross subsidise future improvements and new in relation to the Mill buildings. facilities in the park.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

184

Settlement Proposals with no Actions

Aberdour Housing/Housing Opportunity Site Site Lead Est. Capacity Status Hillside School (ABD001) Private Sector 70 Application for Planning Permission in Principle for wider site with 125 houses received and under consideration. 17/01870/PPP

Scottish Water: Drainage Impact Assessment required. Growth at WWTW required. Potential conflict with existing trunk main to North of site. Close engagement with Scottish Water essential.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Land at Wester Aberdour Private Sector 20 Scottish Water: Growth of the Waste Water Treatment Works may be required to (ABD002) accommodate this site, depending on progress of Hillside School (ABD001) above. Scottish Water is funded for growth following the provision of the 5 criteria. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Auchtermuchty Housing/Housing Opportunity Site Site Lead Est. Capacity Status/Next Steps East of Stratheden Place (AUC001) Private Sector 18 Pre-application enquiry submitted for residential development on this site and surrounding land (17/03828/PREAPP)

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

185

Site Lead Est. Capacity Status/Next Steps Land west of Millflat (AUC002) Muir Homes 30 No information is available. Fife Council as Planning Authority will review the continued inclusion of this proposal in the LDP. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Employment Site Lead Site Area Status/Next Steps North of Old Station, (Sterling Fife Council/ 1 ha No information is available. Fife Council as Planning Authority will review the continued Warehouse) (AUC003) Private Sector inclusion of this proposal in the LDP. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Auchtertool Housing/Housing Opportunity Site Site Lead Est. Capacity Status/Next Steps Camilla Farm (AUT001) William Wright 16 This site has planning permission and is currently under construction - 10 units completed

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 ✔ Ballingry Housing/Housing Opportunity Site Site Lead Est. Capacity Progress Flock House South (BGY001) Abbotsgate 40 This site has planning permission for housing. 09/01160/WARM and 16/03630/OBL Developments 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

186

Site Lead Est. Capacity Status/Next Steps Land to the east of Ballingry Private Sector 105 Proposal of Application Notice for erection of residential development, landscaping, (BGY002) open space and associated infrastructure 16/03600/PAN

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Ballingry Road (BGY003) Fife Council 25 Development Brief for site approved June 2005.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Development Opportunity Site Lead Site Area Status/Next Steps Former Benarty Centre Fife Council 2.7 ha This site has been demolished and has potential to be redeveloped. (BGY004)

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Balmerino and Kirkton of Balmerino Housing/Housing Opportunity Site Site Lead Est. Capacity Status/Next Steps Opposite Balmerino Abbey/ Memorial Headon 5 Planning permission 09/00408/EFULL for 5 houses was granted on 04/08/2011. Cottages (BAL001) Developments Permission to extend the time period to commence development by an additional 3 years was granted in November 2016 (16/02603/FULL)

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

187

Balmullo Housing/Housing Opportunity Site Site Lead Est. Capacity Status/Next Steps Balmullo Farm (BLO001) TD Forster & Son 23 No information is available. Fife Council as Planning Authority will review the continued inclusion of this proposal in the LDP.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Land at Burnbrae Nursery, Clay Road Private Sector 20 No information is available. Fife Council as Planning Authority will review the (BLO002) continued inclusion of this proposal in the LDP.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Buckhaven

Proposals around the Buckhaven area include the Fife Energy Park BKN003.

Housing/Housing Opportunity Site Site Lead Est. Capacity Status/Next Steps Denbeath Parish Church, Buckhaven Ravenscraig 12 Planning permission granted for change of use and conversion of church to form 2 (BKN001) Restoration dwelling houses and 10 flats including demolition of rear church hall and single storey hallway and formation of car park - 06/04224/CFULL

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

188

Employment Site Lead Site Area Status/Next Steps Factory Road, Buckhaven Private Sector 0.6 ha An application has been submitted for affordable housing on this site (BKN002) (17/02894/FULL)

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Cardenden, Dundonald, Aucherderran and Bowhill

Proposals in Cardenden include sites which form part of the Ore/Upper Leven Valley Strategic Development Area (Cardenden Road West CDD 004 and Cardenden Road East CDD 005)

Housing/Housing Opportunity Site Site Lead Est. Capacity Status/Next Steps Bowhill Colliery (CDD001) Enterprise Homes 27 Proposal of Application Notice for residential development of 56 dwellings 17/03148/PAN

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Cardenden South (CDD002) Private Sector 60 Scottish Water: Early engagement recommended. DIA may be required depending on details submitted as part of the Pre-Development Enquiry process. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Dundonald South (CDD003) Brackenlea/Barratt 450 This site has planning permission 06/04043/CFULL

Scottish Water: Early engagement regarding intentions with Water Supply is highly recommended. Water Impact Assessment may be required.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

189

Site Lead Site Area Status/Next Steps Woodend Road (CDD006) Private Sector 145 Scottish Water: Early engagement regarding intentions with Water Supply and drainage is highly recommended. Water Impact Assessment and Drainage Impact Assessment may be required. A Scottish Water trunk main also traverses the site. This will need to be carefully managed both during and after construction. Minimum stand-off distances will be required.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Employment Site Lead Site Area Status/Next Steps Cardenden Road (CDD007) Fife Council 1.8 ha No planning application received

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Bowhill Colliery (CDD008) Fife Council 1.5 ha No information is available. Fife Council as Planning Authority will review the continued inclusion of this proposal in the LDP. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Development Opportunity Site Lead Site Area Status/Next Steps Auchterderran Centre (CDD009) Private Sector 1.5 ha No planning application received for redevelopment. Listed building consent for external alterations and to make good exposed walls 16/03923/LBC

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

190

Carnock Housing/Housing Opportunity Site Site Delivery Est. Capacity Staus/Next Steps Carneil Road (CNK001) A&J Stephen 45 The site is under construction for housing - 08/00287/WFULL.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 ✔ Ceres Housing/Housing Opportunity Site Site Lead Est. Capacity Status/Next Steps Land at Baltilly (CER001) Private Sector 19 No information is available. Fife Council as Planning Authority will review the continued inclusion of this proposal in the LDP. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Coaltown of Balgonie Housing/Housing Opportunity Site Site Lead Est. capacity Status/Next Steps Coaltown of Balgonie East Private Sector 88 Scottish Water: A Water Impact Assessment is required to understand the impact (CLB001) on the existing network. Should network upgrades be required, these must be funded and carried out by the developer. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

191

Site Lead Site Area Status/Next Steps Land to the north of Pyetree Road Private Sector 23 Scottish Water: A Water Impact Assessment may be required to understand the (CLB002) impact on the existing network. Should network upgrades be required, these must be funded and carried out by the developer. A Pre-Development enquiry should be submitted to Scottish Water to allow a more comprehensive understanding of the site requirements.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

North of Main Street Lundin Homes 50 Scottish Water: A Water Impact Assessment is required to understand the impact (CLB003) on the existing network. Should network upgrades be required, these must be funded and carried out by the developer. In addition, a Scottish Water Sewer lies within the footprint of the site. This must be carefully managed both during and after construction. Early engagement with Scottish Water is recommended.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Coaltown of Wemyss Housing/Housing Opportunity Site Site Lead Est. Capacity Status/Next Steps Coaltown of Wemyss North Lundin Homes 110 This site has planning permission and is partly complete - 13/02728/FULL and (CLW001) 16/04199/FULL

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 ✔

192

Site Lead Site Area Status/Next Steps Land south of Coaltown of Wemyss Private Sector 125 This site has planning permission in principle. 16/00139/PPP and 16/03177/OBL (CLW002) Scottish Water: A Drainage Impact Assessment is required to understand the impact on the existing network. Should network upgrades be required, these must be funded and carried out by the developer. In addition, Growth is required at the serving WWTW. Scottish Water is funded for Growth following the provision of the 5 growth criteria. Early engagement with Scottish Water is highly recommended to ensure growth plans are linked with proposed build out plans.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Crossgates, Fordell and Mossgreen Housing/Housing Opportunity Site Site Lead Est. capacity Status/Next Steps North Knowe , Inverkeithing Road Private Sector 174 This site is complete (CRO001) 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 COMPLETE

Land to the west of Old Perth Road Private Sector 200 Scottish Water: A Drainage Impact Assessment will be required to understand what, (CRO002) if any, impact this development has on the existing wastewater network. Should network upgrades be required, these must be funded and carried out by the developer.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Gallows Knowe (CRO003) Miller Homes 150 This site has planning permission and is currently under construction - 15/01222/FULL 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 ✔

193

Site Lead Site Area Status/Next Steps Rear of Hillview Crescent Private Sector 5 The site has planning permission - 10/02470/PPP (CRO004) 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Manse Road (CRO005) Private Sector 9 The site has outline planning permission for erection of 9 dwellinghouses - 06/00454/WOPP and permission for formation of an access road - 09/02879/FULL

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Builders Yard adjacent to Primary Private Sector 18 No information is available. Fife Council as Planning Authority will review the School (CRO006) continued inclusion of this proposal in the LDP.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Crosshill Housing/Housing Opportunity Site Site Lead Est. Capacity Status/Next Steps Former Meedies Neuk Bar Private Sector 14 Planning permission granted on appeal - 08/01799/WFULL. (CRH001)

2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 COMPLETE

194

Culross Housing/Housing Opportunity Site Site Lead Est. capacity Status/Next Steps Blackadder Haven (CUL001) Housing 3 No information is available. Fife Council as Planning Authority will review the Association continued inclusion of this proposal in the LDP. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Cuparmuir Housing/Housing Opportunity Site Site Lead Est. Capacity Status/Next Steps Sawmill (CPM001) Private Sector 37 No information is available. Fife Council as Planning Authority will review the continued inclusion of this proposal in the LDP. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Dairsie Housing/Housing Opportunity Site Site Lead Est. Capacity Status/Next Steps South of Osnaburgh Court Campion Homes 40 Planning application approved at appeal for formation of access road - (DAI001) 16/02510/FULL Planning application submitted for erection of 40 dwellinghouses, formation of access roads, parking, amenity space and SUDS - 17/02946/FULL

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

195

Dalgety Bay and Hillend Housing/Housing Opportunity Site Site Lead Est. capacity Status/Next Steps OCLI, Donibristle Industrial Estate Private Sector 125 Site complete (DGB001) 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 COMPLETE

Fulmar Way 2 (DGB002) Muir Homes 50 Application in for 44 units (16/00998/FULL) - pending decision.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

St David's Harbour – Harbour Place Private Sector 24 The site has planning permission for 24 flats, a restaurant/bistro, parking, lighthouse, (DGB004) walkway, landscaping and vehicular access. Detailed conditions and requirements are set out in planning appeal ref no. PPA-250-2114-1

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Employment Site Lead Site Area Status/Next Steps Ferris Way (DGB005) Private Sector 0.6 ha No information is available. Fife Council as Planning Authority will review the continued inclusion of this proposal in the LDP.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

196

Site Lead Site Area Status/Next Steps Fulmar Way 1 (DGB006) Private Sector 0.1 ha Temporary change of use granted from class 6 storage yard to sui generis drive through car wash facilities, including the demolition of existing canopies and erection of screens for car wash bays (renewal of application reference 10/03264/FULL) (15/03730/FULL) - The use authorised by this permission shall be discontinued on or before 31st of January 2021 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Hillend/ Donibristle Industrial Fife Council/ 1.9 ha Planning Permission in principle granted in Feb 2016 for a mixed use development Estates Western Edge Private Sector comprising a Class 1 retail unit, a restaurant with licensed bar (Class 3), a drive-thru (DGB007) restaurant (Class 3), a business unit (Class 4) and children's indoor play area (Class 11) (13/02953/PPP)

Planning permission pending for mixed use development comprising: a restaurant with licensed bar (class 3); a unit for class 6 use (with ancillary trade counter); a commercial unit for class 3 and hot food takeaway use; (17/02837/FULL ) 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Muirton Way (DGB008) 1.2 ha The southern part of the site has full planning permission granted for 10 starter units and a children’s nursery (March 2014). There is a planning application pending consideration for the remainder of the site for a mixed development comprising: Starter and Trade Counter Units (Class 4, 5 and 6), Office Accommodation (Class 4), Retail (Class 1), Financial and Professional Services (Class 2), Food and Drink (Class 3). 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 East Wemyss

197

Housing/Housing Opportunity Site Site Lead Est. Capacity Status/Next Steps West of Randolph Street Private Sector 86 This site has planning permission. 16/03177/OBL (EWS001) Scottish Water. Early engagement with Scottish Water is recommended. A WIA and DIA may be required to understand what, if any, impact this site has on existing infrastructure. Any network upgrades identified as part of that process must be funded and carried out by the developer. In addition, whilst early phased of the site can be accommodated at the East Wemyss WWTW (48 housing unit published capacity as of Dec 17), to accommodate the entire development growth may be required. Scottish Water is funded for growth following the provision of the 5 growth criteria. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Gauldry Housing/Housing Opportunity Site Site Lead Est. capacity Status/Next Steps Priory Road North (GAU001) A&J Stephen 20 No information is available. Fife Council as Planning Authority will review the continued inclusion of this proposal in the LDP. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

198

Glencraig

Proposals in Glencraig include a site which forms part of the Ore/Upper Leven Valley Strategic Development Area (Glencraig East GLC001)

Housing/Housing Opportunity Site Site Lead Est. Capacity Status/Next Steps Glencraig West (GLC002) Fife Council 50 Fife Council has approved a development brief for this site.

Scottish Water: Early engagement with Scottish Water is recommended. A WIA and DIA may be required to understand what, if any, impact this site has on existing infrastructure. Any network upgrades identified as part of that process must be funded and carried out by the developer. In addition, a Scottish Water combined sewer currently traverses the proposed site footprint. Close management of this asset will be required both during and after construction. Stand-off distances may be enforced. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Hill of Beath Housing/Housing Opportunity Site Site Lead Est. Capacity Status/Next Steps North of Hill of Beath Keepmoat 115 This site has planning permission for erection of 134 residential units including SUDS, (HOB001) open space, access and associated services 16/03491/FULL and is currently under construction. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 ✔

199

Employment Site Lead Site Area Status/Next Steps Cement Works by the B981 Private Sector 1 ha No information is available. Fife Council as Planning Authority will review the (HOB002) continued inclusion of this proposal in the LDP.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Kelty

Proposals around the Kelty area include a site which forms part of the Ore/Upper Leven Valley Strategic Development Area (Kelty South West KEL 005).

Housing/Housing Opportunity Site Site Lead Est. Capacity Status/Next Steps Bath Street Extension 1 (KEL001) Private Sector 130 This site is complete. 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 COMPLETE

Bath Street Extension 2 (KEL002) Private Sector 18 This site is complete.

2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 COMPLETE

Elmwood Terrace (KEL003) Private Sector 30 No information is available. Fife Council as Planning Authority will review the continued inclusion of this proposal in the LDP.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

200

Site Lead Est. Capacity Status/Next Steps Netherton Farm (KEL004) Private Sector 236 Scottish Water: Early engagement with Scottish Water is recommended. A DIA is required to understand what, if any, impact this site has on existing drainage infrastructure. A Water Impact Assessment may also be required. Submission of a pre-development enquiry detailing proposed flows will confirm either way. Any network upgrades identified as part of that process must be funded and carried out by the developer. In addition, a Scottish Water combined sewer currently traverses the proposed site footprint. Close management of this asset will be required both during and after construction. Stand-off distances may be enforced.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Old Gas Works (KEL008) Private Sector 44 No information is available. Fife Council as Planning Authority will review the continued inclusion of this proposal in the LDP.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Kinghorn Housing/Housing Opportunity Site Site Lead Est. Capacity Status/Next Steps Lochside (KNH001) Private Sector 110 Planning permission granted for 133 dwellings in May 2016 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Viewforth Place (KNH002) Private Sector 18 Planning application submitted for erection of 19 flatted dwellings and 3 dwellinghouses with associated works including parking and landscaping - 17/03314/FULL 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

201

Cemetery Site Lead Site Area Status/Next Steps East of Kinghorn Loch Fife Council 3.4 ha including Planning permission granted for an eco-cemetery and cemetery. (KNH003) KNH004 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

East of Kinghorn Loch Fife Council 3.4 ha including Planning permission granted for an eco-cemetery and cemetery. (KNH004) KNH003

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Kinglassie

Proposals in Kinglassie include the sites which form part of the Ore/Upper Leven Valley Strategic Development Area - Laurence Park South (KLS001); Laurence Park North (KLS002)

202

Inverkeithing Housing/Housing Opportunity Site Site Lead Est. Capacity Status/Next Steps Borelands Reservoir (INV001) Lochay Homes 18 The site is complete Ltd

2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 COMPLETE

The Royal Hotel (INV002) Private Sector 8 The planning permission for this site has lapsed

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Roods (INV003) Private Sector 50 Scottish Water: No surface water to combined sewer. Foul only. Agreement required prior to technical approval granted by Scottish Water.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Former Inverkeithing Primary School, Private Sector 42 This site has planning permission and listed building consent for housing. A revised Roods Road (INV004) planning application for demolition of the listed building and erection of 28 units is currently under consideration - 17/01429/LBC 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

203

Site Lead Site Area Status/Next Steps Spencerfield (INV005) Taylor Wimpey 295 The outcome of planning appeal PPA-250-2232 is that the reporter is minded to grant planning permission in principle for 295 residential units, including affordable units (25% of total number for site) with associated access road and infrastructure. 15/01147/PPP)

Planning application submitted for erection of 295 No residential development with associated access road and infrastructure (16/03554/ARC)

Scottish Water: A Drainage Impact Assessment is required to understand the impact this may have on existing drainage infrastructure. Any network upgrades identified as part of this process must be funded and carried out by the developer.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Employment Site Lead Site Area Status/Next Steps Belleknowes Industrial Estate 1 Private Sector 1.9 ha No information is available. Fife Council as Planning Authority will review the (INV006) continued inclusion of this proposal in the LDP. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Belleknowes Industrial Estate 2 Private Sector 0.3 ha No information is available. Fife Council as Planning Authority will review the (INV007) continued inclusion of this proposal in the LDP. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Belleknowes Industrial Estate 3 Private Sector 0.8 ha No information is available. Fife Council as Planning Authority will review the (INV008) continued inclusion of this proposal in the LDP. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

204

Site Lead Site Area Status/Next Steps Former Caldwell Mill (INV009) Private Sector 8.2ha No information is available. Fife Council as Planning Authority will review the continued inclusion of this proposal in the LDP.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Conservation Area Extension Site Lead Site Area Status/Next Steps Friary Gardens (INV010) Fife Council 0.7 ha The conservation area extension will be finalised in late 2017 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 ✔

Church Street/High Street Fife Council 0.3 ha The conservation area extension will be finalised in late 2017. (INV011) 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 ✔

Other Proposal Site Lead Site Area Status/Next Steps Fraser Avenue Fife Council 4 ha Planning Permission in Principle granted in 2015 for demolition of the existing houses. (INV012) Permission granted for development of 53 houses on the land to the north of the site in 2016. 15/03844/PPP and 17/04054/ARC

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

205

Kingsbarns Housing/Housing Opportunity Site Site Lead Est. Capacity Status/Next Steps West of the Square (KIN001) Ogilvie Homes 40 Part of this site is complete. An application for 18 houses on the remaining part of the site was recently approved following an appeal to the DPEA (PPA-250-2295 and 17/00596/FULL 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Cemetery Site Lead Site Area Status/Next Steps South west of the Village (KIN002) Fife Council 2 ha No information is available. Fife Council as Planning Authority will review the continued inclusion of this proposal in the LDP.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Kennoway Housing/Housing Opportunity Site Site Lead Est. Capacity Status/Next Steps Hallfields Farm 5a (KEN001) Paddle Homes 66 This site has planning permission and is under construction (06/02215/CARM and 10/01950/FULL

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 ✔ Land between Halfields Gardens and Private Sector 190 Scottish Water: Drainage and Water Impact Assessments are required to understand Leven Road (KEN002) what, if any, upgrades are required to accommodate this development. Any network upgrades must be funded and carried out by the developer. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

206

Site Lead Site Area Status/Next Steps Langside Crescent, South Private Sector 25 No information is available. Fife Council as Planning Authority will review the continued (KEN003) inclusion of this proposal in the LDP.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Langside Crescent (KEN004) Ian R Jarvis 5 Planning permission granted for erection of 5 one and a half storey dwellinghouses, Builders domestic garages and access road - 04/02100/CFULL. Site under construction.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 ✔ Old Station Road (KEN005) Private Sector 30 No information is available. Fife Council as Planning Authority will review the continued inclusion of this proposal in the LDP.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Kennoway School (KEN 006) Private Sector 60 Site under construction - 04/01474/CARM

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 ✔

Employment Site Lead Site Area Status/Next Steps East of Sandy Brae Industrial Estate Fife Council 3.5 ha No information is available. Fife Council as Planning Authority will review the continued (KEN007) inclusion of this proposal in the LDP.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

207

Kingseat Housing/Housing Opportunity Site Site Lead Est. Capacity Status/Next Steps Road (KST001) Taylor Wimpey 50 This site has planning permission 15/03116/FULL for 59 residential units and is currently under construction. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 ✔

Ladybank Housing/Housing Opportunity Site Site Lead Est. Capacity Status/Next Steps Commercial Crescent Ladybank 19 This site has planning permission for erection of 45 affordable residential units (LAD001) Homes (15/03306/FULL). Section 42 application submitted for removal of condition 12 which restrict dwellings to affordable housing (17/01236/FULL).

Application submitted for erection of 34 residential units with associated infrastructure and formation of vehicular access (17/01452/FULL ).

Cupar Road (LAD 002) Andrew Davie 60 This site has planning permission 05/02569/EFULL (granted on 28/03/2007). This Homes consent was amended in 2008 to include the erection of three additional dwellings (08/02805/FULL ). The access road has been constructed.

Scottish Water: A Drainage Impact Assessment is required to understand what, if any network upgrades are required to accommodate this development. Any upgrade works identified must be funded and carried out by the developer. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

208

Site Lead Est. Capacity Status/Next Steps Monksmoss (LAD003) 60 This site received planning permission 04/01863/EARM on 06/02/2006

Scottish Water: A Drainage Impact Assessment is required to understand what, if any network upgrades are required to accommodate this development. Any upgrade works identified must be funded and carried out by the developer. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

The Road End, Loftybank Campion Homes 23 This site has planning permission for erection of 23 affordable residential units (LAD004) 15/02828/FULL granted on 17 November 2015.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Employment Site Lead Site Area Status/Next Steps The Beeches (LAD005) Private Sector 2.1 ha No information is available. Fife Council as Planning Authority will review the continued inclusion of this proposal in the LDP.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Largoward Housing/Housing Opportunity Site Site Lead Est. Capacity Status/Next Steps Hall Park West (LAR001) Private Sector 10 This site is complete. 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 COMPLETE

209

Leuchars Housing/Housing Opportunity Site Site Lead Est. Capacity Status/Next Steps The Castle Field/Doocot Field Avant Homes/ 200 Outline permission granted on southern half of the site for residential development (LEU001) Ogilvie Homes (including parking, landscaping, recreational and open space facilities), employment development and access road alterations at Dovecot Field/Henderson Meadow - 07/00073/EOPP

Water and Drainage Impact Assessments are required to understand what, if any network upgrades are required to accommodate this development. Any upgrade works identified must be funded and carried out by the developer. Water and drainage infrastructure sit within the Western edge of this proposed development This infrastructure will have to be carefully managed both during and after construction. Stand-off distances may be enforced. Early engagement with Scottish Water highly recommended.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Limekilns Conservation Area Extension Site Lead Site Area Status/Next Steps Factor’s Brae (LKS001) Fife Council 0.04 ha Conservation Area Appraisal

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Brucehaven Road (LKS002) Fife Council 0.1 ha Conservation Area Appraisal 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

210

Site Lead Site Area Status/Next Steps Sandiland/ The Wellhead (LKS003) Fife Council 1.1 ha Conservation Area Appraisal 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Lower Largo Housing/Housing Opportunity Site Site Lead Est. capacity Status/Next Steps East of Durham Wynd, Lower Largo Lundin Homes 60 Planning application approved for residential development of 61 units with associated (LLA001) access, landscaping and drainage infrastructure - 14/04211/FULL. Under construction.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Lumphinnans

Proposals in Lumphinnans include a site which forms part of the Ore/Upper Leven Valley Strategic Development Area (Land to the North of Lumphinnans LPH003).

Housing/Housing Opportunity Site Site Lead Est. Capacity Status/Next Steps Lochgelly Road (LPH001) Moray Estate 100 No planning application submitted

Scottish Water: A Pre-Development Enquiry must be submitted by the developer to Scottish Water to ensure an appropriate review of existing infrastructure capacity. A DIA and WIA may be requested following this activity. Any network upgrades identified must be funded and carried out by the developer. A trunk main and combined sewer traverses a section of this site. These must be carefully managed during and after construction. Stand-off zones may be enforced. Early engagement with Scottish Water is highly recommended. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

211

Site Lead Est. Capacity Status/Next Steps Sycamore Crescent (LPH002) Fife Council 50 Fife Council has approved a development brief for this site. 14/02304/FULL and 16/00486/FULL A Pre-Development Enquiry must be submitted by the developer to Scottish Water to ensure an appropriate review of existing infrastructure capacity. A DIA and WIA may be requested following this activity. Any network upgrades identified must be funded and carried out by the developer.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Markinch Housing/Housing Opportunity Site Site Lead Est. Capacity Status/Next Steps Markinch South Miller King/ 300 Planning permission in principle approved (15/04097/PPP). (MAR001) Persimmon Homes Reserved matters applications submitted for 70 residential units (17/01975/ARC; 17/01976/ARC ; 17/02043/ARC) – Persimmon Homes.

Scottish Water: Early engagement with Scottish Water is highly recommended. A Drainage Impact Assessment may be required to facilitate this site. . Any network upgrades identified must be funded and carried out by the developer. A water main and combined sewer traverses a section of this site. These must be carefully managed during and after construction. Stand-off zones may be enforced. Early engagement with Scottish Water is highly recommended.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

212

Site Lead Est. Capacity Status/Next Steps Sweetbank Park Terrace Harvester Homes 38 Pre-application submitted for proposed housing development (17/01627/PREAPP) (MAR002) 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Brunton Road (MAR003) Private Sector 15 Planning permission in principle for residential development granted on appeal - 09/01076/PPP

Proposal of Application Notice agreed for renewal of planning permission 09/00659/PPP for proposed residential development - 14/01563/PAN

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Pittenweem Housing/Housing Opportunity Site Site Lead Est. Capacity Status/Next Steps St Margaret’s Farm (PIT001) Private Sector 70 No information is available. Fife Council as Planning Authority will review the continued inclusion of this proposal in the LDP.

Scottish Water: A Water and Drainage Impact Assessment may be required to facilitate this site. Any network upgrades identified must be funded and carried out by the developer Early engagement with Scottish Water is recommended.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

213

Cemetery Extension Site Lead Site Area Status/Next Steps Cemetery (PIT002) Fife Council 0.3 hectares No information is available. Fife Council as Planning Authority will review the continued inclusion of this proposal in the LDP. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Star of Markinch Housing/Housing Opportunity Site Site Lead Est. Capacity Status/Next Steps West End Dairy (SOM001) Campion Homes 20 No information is available. Fife Council as Planning Authority will review the continued inclusion of this proposal in the LDP.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Springfield Housing/Housing Opportunity Site Site Lead Est. capacity Status/Next Steps Land East of Pennyacre Court Lundin Homes 5 Development to be in line with findings of planning appeal PPA-250-732. (SPF001) 06/03134/EFULL

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

East of Crawford Park Campion Homes 50 Planning permission granted (15/01189/FULL). Site under construction. (SPF002) 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 ✔

214

Site Lead Est. capacity Status/Next Steps Derelict Dairy Farm behind Main Private Sector 8 No information is available. Fife Council as Planning Authority will review the Street (SPF003) continued inclusion of this proposal in the LDP 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Thornton

Proposals in Thornton includes sites which form part of the Ore/Upper Leven Valley Strategic Development Area (Land North and West of Thornton THO003; Spittal Farm, Elmbank Terrace/Station Road THO004; Land off Main Street THO005)

Housing/Housing Opportunity Site Site Lead Est. Capacity Status/Next Steps Auction Mart (THO001) Private Sector 26 This site has planning permission 02/01266/CFULL and is partially complete.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Burnbank Terrace (THO002) Private Sector 6 This site is complete.

2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 COMPLETE

Network Rail Land to the east of Private Sector 10 No information is available. Fife Council as Planning Authority will review the Thornton (THO006) continued inclusion of this proposal in the LDP. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

215

Site Lead Site Area Status/Next Steps Orebank Terrace/ Strathore Road Private Sector / 294 Application submitted for 43 affordable dwellings on north east section of the site (THO007) Fife Council (17/02594/FULL)

Scottish Water: A Water and Drainage Impact Assessment may be required to facilitate this site. Any network upgrades identified must be funded and carried out by the developer Early engagement with Scottish Water is recommended.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Employment Site Lead Site Area Status/Next Steps The Former Rothes Colliery Private Sector 9 ha No information is available. Fife Council as Planning Authority will review the (THO008) continued inclusion of this proposal in the LDP.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Riverside (THO009) Private Sector 3.5 ha No information is available. Fife Council as Planning Authority will review the continued inclusion of this proposal in the LDP.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Townhill Leisure/Community Facility Site Lead Site Area Status/Next Steps Townhill Power Station Site Private Sector 5.9 ha No information is available. Fife Council as Planning Authority will review the (TWH001) continued inclusion of this proposal in the LDP. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

216

Countryside Area with no Actions (outwith town and village boundaries) Housing/Leisure/Community/Commercial Site Lead Est. Capacity/ Status/Next Steps Site Area Standalane, Nr Saline (LWD001) Private Sector 7/ 0.5 ha This disused steading has planning permission for housing 07/04014/WFULL and 15/01473/OBL

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Glenduckie Farm, Lindores Private Sector 12/ 0.6 ha This site has planning permission - 13/00346/FULL (LWD003) 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Pitlair 2, Bow of Fife (LWD004) Private Sector 8/ 0.5 ha This site has planning permission - 13/03407/FULL

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 ✔ Russell Mains, Springfield Private Sector 6/ 0.7 ha Site complete. (LWD005) 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 COMPLETE

Cameron (Housing) (LWD006) Private Sector 15/ 1.2 ha Under construction - 10/04483/PPP and 14/03703/ARC 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 ✔

217

Employment Site Lead Site Area Status/Next Steps Begg Farm (LWD002) Private Sector 102 ha This site has planning permission for a large number of bonded warehouses and associated ancillary development, including tank farm and bulk liquid storage, distribution uses, access road and landscaping. Site is under construction. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 ✔ Cameron (Employment 1) Private Sector 0.1 ha Planning permission granted for erection of industrial storage units (Class 6) - (LWD007) 08/03304/EFULL

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Cameron (Employment 2) Private Sector 0.1 ha This site was granted planning permission for a change of use of land to Class 6 (LWD008) Storage and Distribution (13/00759/FULL). This site is complete. 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 COMPLETE

Former British Telecom Depot, Private Sector 4.3 ha No information is available. Fife Council as Planning Authority will review the Crossford (LWD010) continued inclusion of this proposal in the LDP.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Halbeath Triangle North East Private Sector 1.1 ha Planning permission granted for erection of three temporary buildings, water (LWD019) storage container, HGV parking, temporary lighting, security barrier and fencing (retrospective) -17/03458/FULL

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

218

Site Lead Site Area Status/Next Steps Land at Halbeath (LWD030) Fife Council/ 10.2 ha No information is available. Fife Council as Planning Authority will review the Private Sector continued inclusion of this proposal in the LDP.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Land West of Forgan Roundabout Fife Council/ 2.9 ha No information is available. Fife Council as Planning Authority will review the (LWD 031) Private Sector continued inclusion of this proposal in the LDP.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Transport Site Lead Site Area Status/Next Steps South East of the Tay Bridge Fife Council/ Land safeguarded for provision of a park-and-choose facility. Roundabout at the A92/B946 SEStran junction (LWD017)

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Car Park Extension Site Lead Site Area Status/Next Steps Leuchars Railway Station Fife Council/ 0.7 ha Opened in July 2017- providing 178 new parking spaces at Leuchars. (LWD013) Scottish Government 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 COMPLETE

219

Cemetery Extension Site Lead Site Area Status/Next Steps Culross Cemetery Extension Fife Council 1.9 ha No information is available. Fife Council as Planning Authority will review the (LWD014) continued inclusion of this proposal in the LDP. 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Carnbee Cemetery (LWD024) Fife Council 2 ha No information is available. Fife Council as Planning Authority will review the continued inclusion of this proposal in the LDP.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Kemback Cemetery (LWD025) Fife Council 2 ha No information is available. Fife Council as Planning Authority will review the continued inclusion of this proposal in the LDP.

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

Leisure/ Community Facilities Site Lead Site Area Status/Next Steps Brankstone Grange Fife Council 8.8 ha This site has outline planning permission for one house and subdivision of (LWD015) Brankstone Grange. The site has planning permission for the erection of holiday chalets - 14/01476/FULL

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

220

Visitor centre/Holiday units/Housing Site Lead Est. Capacity/ Status/Next Steps Site Area Northbank Farm, Lathockar Private Sector 15/ 9.4 ha This site has planning permission - 15/00727/ARC (LWD035) Other2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024 Site Lead Site Area Status/Next Steps Comrie Colliery (LWD018) Private Sector Planning permission granted (13/03396/FULL) for reclamation and extraction of coal and red shale by surface mining methods, restoration and re-profiling of existing colliery bings and associated contaminated land, and the formation of an ancillary haulage road, staff and storage facilities (Variation of Condition 55 (timing of completion of site restoration works) of planning permission 10/01458/EIA

Dunfermline wide contributions towards additional secondary capacity are now sought – see Planning Obligations Supplementary Guidance 2017. Additional capacity required by 2022

2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Post 2024

221

7. Policies

7.1 Policies will be monitored and reviewed as they are applied and tested in planning appeals. When FIFEplan was written, the policies were mapped against the outcome of the Council Plan at that time. The Council Plan has since been replaced by the Plan for Fife Local Outcomes Improvement Plan and so the Action Programme will re-map FIFEplan's policies against the outcomes in the Plan for Fife."

7.2 All policies will be further reviewed future editions of this Action Programme once the new Scottish Planning Policy and National Planning Framework arrangements are known after the introduction of the new Planning Act. That Act will be granted Royal Assent following the Scottish Parliament’s consideration of the Planning (Scotland) Bill in the course of 2018.

Policy 1: Development Principles Development proposals must address their development impact by complying with the following relevant criteria and supporting policies, where relevant:

Criteria Relevant Policy Actions/Next Steps Mitigate against the loss in infrastructure capacity Policy 3 Infrastructure and Services Statutory Supplementary Guidance on Planning caused by the development by providing additional Policy 4 Planning Obligations Obligations submitted to Scottish Government on capacity or otherwise improving existing infrastructure 19/12/2017 Avoid the loss of valuable cultural, tourism, and Policy 3 Infrastructure and Services community resources Protect Fife’s existing and allocated employment land Policy 5 Employment Land and Property Make town centres the first choice for uses which Policy 6 Town Centres First attract a significant number of people, including retail, leisure, entertainment, recreation, cultural and community facilities, as well as homes and businesses, and accord with the town centres spatial frameworks In the case of proposals in the countryside or green Policy 2 Homes belt, be a use appropriate for these locations Policy 7 Development in the Countryside Policy 8 Houses in the Countryside Policy 9 Green Belt Policy 11: Low Carbon Fife

222

Criteria Relevant Policy Actions/Next Steps Protect sport and recreation facilities and the amenity Policy 3 Infrastructure and Services of the local community and businesses Policy 10 Amenity Safeguard the character and qualities of the landscape Policy 13 Natural Environment and Access Update Statutory Supplementary Guidance on Policy 15 Minerals Making Fife’s Places Avoid flooding and impacts on the water environment Policy 12 Flooding and the Water Environment Safeguard or avoid the loss of natural resources, Policy 13 Natural Environment and Access Produce Statutory Supplementary Guidance on including effects on internationally designated nature Policy 15 Minerals Minerals conservation sites

Safeguard the characteristics of the historic Policy 14 Built and Historic Environment Update Statutory Supplementary Guidance on environment, including archaeology Making Fife’s Places Not compromise the performance or safety of strategic Spatial Strategy diagram infrastructure or, alternatively, assist in the delivery of necessary improvements to mitigate impact arising from development

Development Proposals must be supported by information or assessments to demonstrate that they will comply with the following relevant criteria and supporting policies, where relevant:

Criteria Relevant Policy Actions/Next Steps Meet the requirements for affordable housing and Policy 2 Homes Update Statutory Supplementary Guidance on Houses in Multiple Occupation Affordable Housing and Houses in Multiple Occupation Provide required on-site infrastructure or facilities, Policy 3 Infrastructure and Services including transport measures to minimise and manage future levels of traffic generated by the proposal Provide measures that implement the waste Policy 3 Infrastructure and Services Produce Statutory Supplementary Guidance on Low management hierarchy as defined in the Zero Waste Carbon Fife Plan for Scotland

223

Criteria Relevant Policy Actions/Next Steps Provide green infrastructure as required in settlement Policy 3 Infrastructure and Services Update Statutory Supplementary Guidance on proposals and identified in the green network map Making Fife’s Places Provide sustainable urban drainage systems in Policy 3 Infrastructure and Services accordance with any relevant drainage strategies applying to the site or flood assessments Meet the requirements of any design briefs or Policy 13 Natural Environment and Access development frameworks prepared or required for the Policy 14 Built and Historic Environment site Provide a layout and design that demonstrates Policy 14 Built and Historic Environment Update Statutory Supplementary Guidance on adherence to the six qualities of successful places as Making Fife’s Places set out in the Government's Creating Places policy Provide for energy conservation and generation in the Policy 3 Infrastructure and Services Produce Statutory Supplementary Guidance on Low layout and design Policy 11 Low Carbon Fife Carbon Fife Policy 13 Natural Heritage, Woodland, and Access Policy 14 Built and Historic Environment Contribute to achieving the area’s full potential for Policy 11 Low Carbon Fife Produce Statutory Supplementary Guidance on Low electricity and heat from renewable sources, in line Carbon Fife. with national climate change targets, giving due regard to relevant environmental, community and cumulative Add requirement for district heating to relevant impact considerations sites as and when information becomes available.

Policy 2: Homes Plan for Fife LOIP links: Increasing Opportunity and Reducing Poverty & Inequality | Improving quality of life in local communities | Promoting a sustainable society. Outcomes: An increase in the availability of homes of a good quality to meet local needs. The provision of a generous supply of land for each housing market area to provide development opportunities and achieve housing supply targets across all tenures. Maintaining a continuous five year supply of effective housing land at all times. Statutory Supplementary Guidance: Affordable Housing | Houses in Multiple Occupation in Central St Andrews Conservation Area

224

225

Policy 3: Infrastructure and Services Plan for Fife LOIP links: Growing a vibrant economy | Increasing Opportunity and Reducing Poverty & Inequality | Improving quality of life in local communities | Promoting a sustainable society. Outcomes: New development is accompanied, on a proportionate basis, by the site and community infrastructure necessary as a result of the development so that communities function sustainably without creating an unreasonable impact on the public purse or existing services. Statutory Supplementary Guidance: Making Fife’s Places

Policy 4: Planning Obligations Plan for Fife LOIP links: Growing a vibrant economy | Improving quality of life in local communities | Promoting a sustainable society Outcomes: New development provides for additional capacity or improvements in existing infrastructure to avoid a net loss in infrastructure capacity. Statutory Supplementary Guidance: Planning Obligations Framework

Policy 5: Employment Land and Property Plan for Fife LOIP links: Growing a vibrant economy | Increasing opportunity and reducing poverty & inequality | Promoting a sustainable society. Outcomes: An increase in the percentage of settlements in Fife with a population of 5,000 or more which have an immediately available 7 year supply of employment land. Improved employment prospects. More opportunities for economic investment.

Policy 6: Town Centres First Plan for Fife LOIP links: Growing a vibrant economy | Increasing opportunity and reducing poverty & inequality | Improving quality of life in local communities | Promoting a sustainable society. Outcome: Thriving town centres in Fife which are hubs of activity in the local community and act as a focus for commercial, leisure, and cultural services.

Policy 7: Development in the Countryside Plan for Fife LOIP links: Increasing opportunity and reducing poverty & inequality | Promoting a sustainable society. Outcome: A rural environment and economy which has prosperous and sustainable communities and businesses whilst protecting and enhancing environmental quality.

226

Policy 8: Houses in the Countryside Plan for Fife LOIP links: Increasing opportunity and reducing poverty & inequality | Promoting a sustainable society. Outcome: A rural environment and economy which has prosperous and sustainable communities and businesses whilst protecting and enhancing environmental quality.

Policy 9: Green Belt Plan for Fife LOIP links: Improving quality of life in local communities. | Promoting a sustainable society. Outcome: Development in the Dunfermline and St Andrews Green Belts is managed to protect and enhance these towns' respective character, landscape settings, and identities.

Policy 10: Amenity Plan for Fife LOIP links: Improving quality of life in local communities. Outcome: Places in which people feel their environment offers them a good quality of life.

Policy 11: Low Carbon Fife Plan for Fife LOIP links: Growing a vibrant economy. | Promoting a sustainable society. Outcome: Fife Council contributes to the Climate Change (Scotland) Act 2009 target of reducing greenhouse gas emissions by at least 80% by 2050. Energy resources are harnessed in appropriate locations and in a manner where the environmental and cumulative impacts are within acceptable limits. Statutory Supplementary Guidance: Low Carbon Fife

Policy 12: Flooding and the Water Environment Plan for Fife LOIP links: Improving quality of life in local communities | Promoting a sustainable society. Outcome: Flood risk and surface drainage is managed to avoid or reduce the potential for surface water flooding. The functional floodplain is safeguarded. The quality of the water environment is improved.

227

Policy 13: Natural Environment and Access Plan for Fife LOIP links: Improving quality of life in local communities | Promoting a sustainable society. Outcomes: Fife's environmental assets are maintained and enhanced; Green networks are developed across Fife; Biodiversity in the wider environment is enhanced and pressure on ecosystems reduced enabling them to more easily respond to change; Fife's natural environment is enjoyed by residents and visitors.

Policy 14: Built and Historic Environment Plan for Fife LOIP links: Growing a vibrant economy | Improving quality of life in local communities | Promoting a sustainable society Outcomes: Better quality places across Fife from new, good quality development and in which environmental assets are maintain, and Fife's built and cultural heritage contributes to the environment enjoyed by residents and visitors.

Policy 15: Minerals Plan for Fife LOIP links: Growing a vibrant economy. | Improving quality of life in local communities. | Promoting a sustainable society. Outcome: The environmental and cumulative impacts of minerals extraction, including commercial peat extraction, will be closely managed so that a balance is achieved between the safeguarding and responsible extraction of workable minerals and environmental protection. The economic or conservation value of minerals is recognised and their working and use is within acceptable environmental limits. Statutory Supplementary Guidance: Minerals

In addition to planning policy contained within the Local Development Plan a range of publications have been designed to answer some of your planning queries, copies of these documents can be viewed on our Fife Direct website via the following link: Planning Guides and Forms

228

8. Appendix

SESplan

TAYplan

FIFEplan

Housing Land Audit

Employment Land Audit

Planning Obligations Supplementary Guidance

Affordable Housing Supplementary Guidance

Making Fife’s Places Supplementary Guidance

Mineral’s Supplementary Guidance

Transport Assessments - SDAs at West/North West Dunfermline, Lochgelly, Cupar, Kirkcaldy East and Kirkcaldy South West.

DPEA