Appendix 9A (ii)

Initial Environmental Examination (DRAFT)

April 2015

IND: Orissa Integrated Irrigated Agriculture and

Water Management Investment Program: Tranche 2 Kanjhari Subproject (Tranche-2 Preparation)

IEE & Public Consultation Report (compliant with ADB Safeguard Policy Statement 2009)

Prepared by Department of Water Resources (DoWR), Project Management Unit (PMU) for the Asian Development Bank.

This initial environmental examination is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. Your attention is directed to the “terms of use” section of this website.

In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Department of Water Resources (DoWR) Project Management Unit (PMU)

Orissa Integrated Irrigated Agriculture and Water Management Investment Programme (OIIAWMIP) ( ADB Loan No. 2444 and OFID Loan No. 1251-P)

Kanjhari Subproject (Tranche-2 Preparation)

Initial Environmental Examination (IEE) & Public Consultation Report (compliant with ADB Safeguard Policy Statement 2009)

August 2014

assisted by Institutional Strengthening and Project Management Consultants (ISPMC)

Hydrosult, Division of SNC- Lavalin Inc. in association with Sutra Consulting Pvt. Ltd., SBH Consultants Pvt. Ltd and N.K. Buildcon Pvt. Ltd

PREFACE

This “IEE & Public Consultation Report” for the proposed Kanjhari Subproject is intended to comply with the ADB prerequisites for Preparation of Tranche-2 subproject of the OIIAWIMP.

This 2nd Draft of the document complies with ADB Guidelines related to the Safeguard Policy Statement 2009; as well as incorporating suggestions and responding comments made by ADB in the Aide Memoire of February 2012; and addresses specific IEE requirements in ADB correspondence on 20 February 2012 as well as similar comments made during July 2014 applicable from other IEEs .

A tabular guidance on the responses and compliance with the above mentioned ADB comments/requirements is presented on the following pages.

This Report supersedes the Report on IEE & Public Consultation prepared for the proposed Subproject under ADB TA - 4814- during May 2008 by STUP Consultants.

August 2014 ISPMC

(‘’Compliance to ADB Comments Dated 20 Feb 2012’’ & July 2014 similar comments applicable from other IEES ’table to follow this page)

Compliance to ADB Comments Dated 20th Feb. 2012 & July 2014 (Similar comments made in other IEEs)

Kanjahari Subproject

General Comments:

Item ADB Comments EA Response JULY 2014 Comments (similar to other IEEs ) The EARF had changed to – if Executive summary incorporated that is the case you may want to be with abbreviations where ever consistent across all documents necessary Please elaborate on the acronym Not implementing agency. Suggest you Chapter 1.0 -Introduction state the work will be sourced to incorporated with last three line in private contractors. the project will be Para 2 implemented Para on ADB safeguard statement - Chapter -2.0 Para 11 content delete deleted Please elaborate on the acronym OSG revised to in Para 20 line 2 In general baseline data is very old? Chapter 4.0 – Updated with latest No recent ones to add – because 2006 information para 108 and data is of no use for a 2014 project. If annexure 6, Table 15,16,18,23,24 not for all atleast for those that are and para extremely relevant to the project such 119,120,121,122153,154,155,159 as water quality etc and Figure 7, 8, 9, 10 We would also need to disclose the Chapter 6.0 Para 217 shifted key findings of the IEE at least a one or from 61 to 66 two page document in the SIO Office Add Environmental officer also Chapter 7.0 – Para 218 incorporated with Environmental officer Chapter 8.0 minor revisions and incorporated some para 227,236,Table 36, 38 and Para 279 Comments Dated 20th Feb. 2012 The IEE should follow format and level The report is modified as per the of description as required by ADB requirements of ADB safeguards 1 safeguard Policy Statement 2009 statement 2009 and the necessary information incorporated in the IEE report. Paragraphs under the local legislation The IEE report is replaced with which states “since most projects subproject specification under OIIAWMIP … revise to be information, kindly refer Section relevant to the projects under 2.7 Para 21 and Section 2.10, discussion. Likewise, the paras which Para 30 2 states that several of irrigation projects in Orissa have not obtained prior approval from Ministry of Environment and Forests, please state if the recommendation on obtaining the permission from Forestry Department Item ADB Comments EA Response (FD) has taken place or not, and if not why. Furthermore, the requirement of getting FDs permission to cut any trees on the embankment should be carried forward to the Environment Management Plan (EMP). Make sure figures can be read, Rectified sources for all tables, and graphs etc. 3 Make sure standard abbreviations are used for example meters (m) and not Mt etc., Under project description include a The IEE is appended with description of landuse that the canal landuse information and passes through. Provide description of provided with different forest type all project interventions (include soft details, kindly refer Section 3.11 measures as well not limiting to only Paras 67, 68, 69, 70, 71 and 72 construction related activities and project and post project management. As the canal passes through reserved 4 forest, please include dates when the canals were originally built and dates when the area was declared as protected forests. Identify clearly the distances and respective chainages of areas under reserved forest, village forests and elephant crossings. Define what a village forest is. Please quantity where eve possible the The IEE report is incorporated expected volume of earth works, spoil with tentative quantities of cutting etc and indentify potential locations and borrow earth required for the subproject, kindly refer Section 3.22 Para 84, 85 86, Table 26 provides the details of tentative construction materials and lead distance as per the preliminary 5 estimate prepared by DoWR, Para section n presents about disposal of debris and spoil and Section Table 26 states the tentative quantities of different materials required for the subproject as per tentative estimates. Experience from Tranche -1 has As per the procurement reconfirmed that as part of the designs conditions identification of borrow sites must be identified in borrow areas is the responsibility advance of construction of Contractor, however keeping implementation as it has serious in view of the forest areas, 6 implications on costs as well as WUAs have identified potential potential environmental impacts. farmers who are willing to give Therefore, iin the IEEs please include lands for borrowing, the potential potential borrow sites and discuss the farmers list is enclosed in the environmental implications for each of Annexure 4. Kindly refer Section Item ADB Comments EA Response these sites. 5.7, sub-section iii, b

Section on implementation of EMP The necessary things were should be based on structure incorporated kindly refer Chapter discussed and what you agree with 8 Environmental Management PD and department. Also please Plan. identify the training needs and provide costing for this as well under EMP. I 7 think you had already identified what the training requirements are). This section should also describe the role of the WUAs during operations with respect to monitor and their training requirements as well. In all EMPs not necessarily just this The necessary things were IEE please clearly specify where the incorporated kindly refer Chapter responsibility to implement the action 8 Environmental Management lies within. In most rows, it identifies Plan. the contractor and the DoWR. Some of those could be responsible to 8 supervise. So please review all EMPS carefully, and identify, clearly where the contractor is only responsible to implement. Otherwise , during implementation, contractor will wash his hands off saying responsibility is with the DoWR and We recommend that maps be obtained The necessary Topo-map sheet from FD and by overlaying the canal with reserved forest boundaries layout, you will be able to confirm if were collected and verified with any part of the works will progress i.e. the Forest Ranger and the with the area still under the Cadastral maps were collected jurisdiction of the FDs, if so relevant and verified for the subproject. 9 approvals must be obtained from the FD for work within their jurisdiction. Please ensure that the PMU has records of these maps, until after the project closure so that they are available for review during any mission.

Detailed Comments: 20th Feb. 2012

IEE Reference ADB Comments EA Response This title would be more appropriate if its Its modified to Expected expected improvements rather than Improvements refer Section Section 2.5 comparison as the list provides the 3.8, Pg – 28. expected improvements Please clarify regarding the statement The paragraph is modified that under GOI regulations this is a kindly refer Section 3.3 and Para 18 category B Para 56 of the IEE report. Pg – 15. Para 33 Last sentence in protected forests all Appended with necessary IEE Reference ADB Comments EA Response activities are permitted unless prohibited is correction kindly refer confusing Section 2.13, Para 35, Pg. 10. Please confirm if this is applicable to this Kindly refer Section 2.10, project and if it is the case by when these Para 30, Pg. 9. Para 35 approvals will be sought and if obtained , please attach the approvals as annexure (VIII) do we want to encourage that? Also Revised kindly refer Section Para 44 any clearances required from FD to do the 2.21 , section C subsection b renovation work? Pg 13 . Last part of para is unclear. There is a Kindly refer Section 4.17 and statement that “there are no core Para 145,Pg. 42 explained elephant habitation reserves in the project in detail. area of influence and the sentence just preceding that talks about the elephant transit path and discussions with community too ( provided in a later chapter) mention the presence of elephants. Para 87

Table 6.11 is very useful but it would be Incorporated with the useful where you state right main canal suggestion kindly refer and left main canal to give total length of Project Description refer these canals to enable the reader to get a Section section 3.5 clear prospective of what percentage of subsection g, Table 7, 8, and the canal length traverses through the 9 and Paras 67, 68, 69, forest reserves. Is it within the elephant 70,71 and 72 Pg 20 to 23. corridor or not that is unclear. It is unclear how the construction of new Explained in details kindly bridges will lead to reducing water refer Section 5.6 Para 168, Under section contamination, could you please expand? Bullet -8 under mitigation 7.5 Also, it states that need to redesign of left measures , Pg 49 main canal due to elephant transit path what is the expected redesign What are included as separate Incorporated with the paragraphs are more appropriate as bullet suggestions, Kindly refer points following a small discussion in the revised para 172 pg. 53 paragraph. Para 105 and 106 make no mention of the forest. This should be Section 7/ 6.1 discussed here onwards Please rephrase para 108, it is not very Modified refer, Para 180 clear at present bullet 12 Pg. 54 Para 111 states that borrow pits should be avoided within forest areas, better use a stronger word that it will not be permitted Impact due to erosion is not covered in Revised kindly refer Section this section, put appropriate section to be 5.7 subsectioniv & V pg. 53, 7.6.3 included in. 54and 5.19 Pg. 53,54 and 55. To demonstrate that it will be negligible, Incorporated kindly refer describe typical types of construction Para 186 pg.55 7.6.4 vehicles expected at site Issues related to disposal of soil need to IEE Reference ADB Comments EA Response be discussed and it is disposed of adjoining the banks measures to prevent it from eroding need to discussed Potential impacts on forest areas? Are Incorporated with necessary there access roads/ routes which heavy` information kindly refer vehicles can ply through, is there a need Section 5.7 sub section v & Para 120 to build haulage roads, storage of ix pg 54 & 55. materials, labour camps, possible siting of borrow sites within forest areas, what measures will be taken to avoid such Please expand on potential impacts of Revised and incorporated increasing area under irrigation and with necessary information Para 121 impact on forest kindly refer Section 5.7, subsection x pg. 56. Mentions decrease in vector borne Base line scenario was diseases – has this been an issue? There provided kindly refer section was little mention under baseline scenario. D subsection I, para 159 pg. Also the para refers to farmers using tube 45 Para 122 well water for irrigation switching to surface water irrigation has the design taken in to consideration this increase? If Kindly refer revised Para 197 so please state or else this could lead to Pg. 58. potential conflict among users. Second line may need to be rephrased. Modified kindly refer revised Para 124 The way it stated at present is confusing Para no 198 pg. 58 Expand how the water quality and quality Incorporated with the Para 125 will be impacted and proposed mitigating necessary suggestions measures kindly refer para 201 pg. 59 Note possible impacts on unique and Incorporated and modified endangered species, but in the baseline with necessary changes section, it clearly states in Para 88 that after consulting the SIO staff there are no endangered species. Need to and Forest Dept. Officials check with forest department on this. This kindly refer Section 5. 8 paragraph should mention possibilities of subsection e & f, Pg. 60 Para 127 increasing the irrigation land area (as done previously by encroachers)and how this will be avoided The need for canal crossing at elephant Details provided in the crossings points should also be included Section 5..8, Para 210, Pg. with chainages of locations provided 60 As discussed during the mission, it Modified and revised tables appears that what is included under the incorporated with the Table 7.1 environmental impacts are not impacts suggestion. Kindly refer please check this table again Table 29, 30, 31, 32 , 33, 34 and 35 Pg. 73 to 99. What is stated under environmental Modified and revised tables aesthetics is unclear regarding the proper incorporated with the guarding should be done and even suggestion. Kindly refer protective measures”. Please clarify Table 29, 30, 31, 32 , 33, 34 Table 8.1 Under impact of land use include the and 35 Pg. 73 to99. selection criteria for borrow sites/ disposal sites Impact on top soil. Please describe which IEE Reference ADB Comments EA Response IS code you are referring to Under de-silting, Please include the disposing of in forest areas is prohibited Haulage routes – Is it expected that there will be a need for new ones? Then specify what are the options or requirements with in the forest areas Dumpsites – Please mention what you told me during mission regarding the disposal of scrap metal, how it become the property of the Irrigation department (( in that is the case for this place as well) Please check that there are two rows Incorporated kindly refer regarding temporary closure of canals and Chapter 8 Tables Table 29, only the second line is appropriate one, 30, 31, 32 , 33, 34 and 35 Please delete the other Pg. 74 to100. Please include a chance find procedure Incorporated kindly refer Section 5.26 and Table 32 item no. 24. Discuss occupational health and safety, Incorporated kindly refer community health and safety aspects Section 5.7 subsection xi, pg. 57 and Table 32 item 17, 18, 19, 20 Under impact on bio-diversity, how to Incorporated in Section 5.8 maintain the protected forests from being subsectin g para 209 pg. 06 cleared should be discussed Relocation of utilities? Power line etc Incorporated kindly refer Para 5.5,5.6 Pg. 47 and 48 and Table 29 Item no. 3 pg. 73 With respect to the Chapter on EMP and Incorporated the suggestions institutional arrangements, please prepare kindly refer the Chapter 8 this chapter in line with what we discussed from Pg. 68 to 108. during the mission. Including the two types of monitoring, project related, and monitoring for water resources management etc., identify clearly parameters and locations. Also, include in the cost the costs associated with tree replanting and proposed training at all levels.

Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

CONTENTS

No Contents Pg.No List of Abbreviations Executive Summary i- vii 1.0 INTRODUCTION 1 - 5 1.1 Project Background 1 1.2 Purpose of the Report 3 1.3 Extent of the IEE Study 3 1.4 Methodology 3 1.5 Project Location 4 1.6 Structure of the IEE Report 4 2.0 POLICY, LEGAL AND ADMINISTRATIVE FRAMEWORK 6 - 13 A Mandatory Requirement ( Funding Agency) 6 B Mandatory Requirement(National) 7 C Clearance Required for the subproject 13 3.0 DESCRIPTION OF THE PROJECT 14 - 28 3.1 Background 14 3.2 Deficiencies in the existing irrigation system 15 3.3 Environmental Category of the project 15 3.4 Scope of Work 15 3.5 Description of Subproject Components 16 3.6 Implementation Arrangement 27 3.7 Onfarm Development Works (OFD) 28 3.8 Expected Improvements 28 4.0 DESCRIPTION OF THE ENVIRONMENT 29 - 45 A Physical Environment 29 B Ecological Resources 41 C Economic Development 43 D Demographic Status 44 5.0 ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATING 46 - 60 MEASURES 5.1 Introduction 46 5.2 Subproject Activities 46 5.3 Subproject Activities during operation & Maintenance phase 47 5.4 Possible Environmental Impact and Mitigation Measures 47 5.5 Impact Due to Project Location 47 5.6 Impact during Planning and Design Phase 48 5.7 Impact during Construction Phase 49 5.8 Impact during Operation & Maintenance Phase 59 6.0 INFORMATION DISCLOSURE, CONSULTATION AND 61 – 66 PARTICIPATION 6.0 General 61 6.1 Stages and level of Consultation 61 6.2 Community level Consultations 61 6.3 Consultations with Institutional Stakeholders 64 6.4 Summary of Public Consultation 65 6.5 Future Consultation and Disclosure 66 7.0 GRIEVANCE REDRESS MECHANISMS 67 - 67 8.0 ENVIRONMENTAL MANAGEMENT PLAN 68 – 108 8.1 General 68 8.2 Institutional Arrangement 68 8.3 Institutional Strengthening and Project Management 69 Consultants (ISPMC) 8.4 Responsible for carrying out monitoring measures - Staffing 69 Requirements 8.5 Reporting System or Responsible for Reporting 70

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

No Contents Pg.No 8.6 Environmental Mitigation Plan 71 8.7 Environmental Monitoring Plan 100 8.8 Performance Indicators 104 8.9 Environmental Management and Monitoring Plan (EMMP) 104 Costs 8.10 Environmental Training 106 8.11 Strengthening Environmental Knowledge & Management 106 Capability 8.12 Training Budget 108 8.13 Environmental Monitoring reporting 108 9.0 RECOMMENDATI ONS 109 10.0 CONCLUSI ON 110 List of Tables List of Figures List of Annexure Photo Plates

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

List of Tables

CONTENTS Pg.No Table 1 Proposed Subprojects 2 Table 2 List of National Parks and Sanctuaries in OIIAWMP Area 9 Table 1 Basic Features of Canal system of Kanjhari sub project 16 Table 4 Reservoir Storage 17 Table 5 Basic Features of Canal system of Kanjhari sub project 18 Table 6 Canal Categorization 20 Table 7 Showing Kanjhari Canal System Passing Reserved Forest - Details 21 Table 8 Showing Kanjhari Canal System Passing through Protected Forest 21 Table 9 Showing Kanjhari Canal System passing through village forest 22 Table 10 Showing the Structures of Left and Right Main Canal 23 Table 11Showing Structures of Distributaries, Minors and Sub-minors 25 Table 12 Showing Mean daily Temperature and RH 30 Table 13 Keonjhar District Monthly Normal Rainfall along with Rainy Days 30 Table 14 Showing Monthly Evaporation Data for the Kanjhari 31 Table 15 Showing the land utilization pattern in Keonjhar district and project 33 covered blocks Table 16 List of Past flood and area damaged by Flood in Odisha 36 Table 17 Showing Water Quality of Kanjhari Dam 38 Table 18 Water Quality of Baitarni River near Anandpur 39 Table 19 Indian Standard for the Surface Water (CPCB Standard) 39 Table 20 Ground Water Resources 40 Table 21 Distribution of Forest in Keonjhar Forest Division 42 Table 22 Showing the Fauna found in the forest of the subproject 43 Table 232 Showing different mines with number of people employed for Keonjhar 43

Table 24 Showing the different work force as per 2001 census 45 Table 25 Showing the list of Structures in the Kanjhari Canal System 46 Table 26 Showing the Approximate quantities of Material required for the sub- 50 project Table 27 Issues of the Public Consultation 61 Table 28 Showing details of consultations with stake holders 64 Table 29 Environmental Parameters Checklist for Anticipated Impacts and 73 Mitigation Measures for Kanjhari Sub project – Pre-construction activity ( Impacts due to location) – Environmental Mitigation Plan Table 30 Environmental Parameters Checklist for Anticipated Impacts and 75 Mitigation Measures for Kanjhari Sub project – Pre-construction activity ( Impacts during design and survey – Environmental Mitigation Plan Table 31 Environmental Parameters Checklist for Anticipated Impacts and 77 Mitigation Measures for Kanjhari Sub project – Pre-construction activity ( Main Canal, Distributaries,and minors executed by Contractor) –Pre- construction Activity - Environmental Mitigation Plan Table 32 Environmental Parameters Checklist for Anticipated Impacts and 81 Mitigation Measures for Kanjhari Sub project – Pre-construction activity ( Main Canal, Distributaries,and minors executed by Contractor) –Construction Phase - Environmental Mitigation Plan Table 33 Environmental Parameters Checklist for Anticipated Impacts and 92 Mitigation Measures for Kanjhari Sub project – Pre-construction activity ( sub minors executed by WUAs) –Pre Construction Activity - Environmental Mitigation Plan Table 34 Environmental Parameters Checklist for Anticipated Impacts and 93 Mitigation Measures for Kanjhari Sub project – Pre-construction activity ( sub minors executed by WUAs) –Construction Activity - Environmental Mitigation Plan Table 35 Environmental Parameters Checklist for Anticipated Impacts and 98 Mitigation Measures for Kanjhari Sub project Operation & Maintenance phase -

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

Environmental Mitigation Plan Table 36 Showing the suggested Environmental Monitoring 101 Table 37 showing the performance Indicators 104 Table 38 Showing the Environmental Monitoring Cost 105 Table 39 Proposed Training Module for capacity building of SIO and WUAs 107 Table 40 Showing the training budget 108

List of Figures

Figure 1 Location Map of Kanjhari – Command Area 4 Figure 2 Satellite Map Showing Kanjhari Dam 14 Figure 3 Schematic Diagram of Left Main Canal 18 Figure 4 Schematic Diagram of Right Main Canal 19 Figure 5 Typical Cross section of Main canal at RD 13.890 23 Figure 6 Annual Isohyte Map of Orissa 31 Figure 7 Land Utilization of Keonjhar District 33 Figure 8 Land Utilization of Keonjhar Block 34 Figure 9 Land Utilization of Patana Block 34 Figure 10 Land Utilization of Ghatagoan Block 34 Figure 11 Seismic Zone of Odisha 35 Figure 12 Organizational Structure of the DoWR for the OIIAWMIP project 68

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

List of Annexure

Annexure 1 Index Map of the Kanjhari Irrigation subproject showing ayacut area Annexure 2 List of Odisha State Pollution Control Board approved Crushers Annexure 3 Quarry area map of Kanjhari Irrigation Project Annexure 4 List of Potential farmers willing to give earth for Borrow areas Annexure 5 Map Showing Kanjhari Irrigation Sub-Project and its canal system along with elephant transit path Annexure 6 Monthly Average Rainfall Data of Kanjhari Sub-project (1979 – 2013) Annexure 7 Forest cover map of Odisha Annexure 8 Project benefited villages along with Population details( Census 2011) Annexure 9 Summary of Consultations with Stake holders in different project benefited villages Annexure 10 List of participants of Poipani Village Annexure 11 List of participants of Sarasposii Village Annexure 12 List of participants of Boda Jamuposi Village Annexure 13 List of participants of Chakko Village Annexure 14 List of participants of Saradhapur Village Annexure 15 List of participants of Bolaniposi Village ANNEXURE 16: Environmental Monitoring – Check list - Contractors ANNEXURE 16a: Environmental Monitoring – Check list - WUAs ANNEXURE 17: Parameters for Ground water Analysis as per IS : 10500:1991 ANNEXURE 17a: Parameters for Surface water Analysis as per IS : 2296 :1992 ANNEXURE 17b: Parameters for Soil /Silt Analysis

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

List of Abbreviations

$ US. Dollar % Percentage ADB Asian Development Bank C Centigrade CAD Command Area Development CCA Cultural Command Area CFO Conservator of Forests CPCB Central Pollution Control Board CTA Component Technical Assistance Cu.mecs Cubic meters D.S.L Dead Storage Level DFO Divisional Forest Officer DG Diesel Generator DOWR Department of Water Resources Dy.SIO Deputy Sub project Implementation Officer EC Environmental Clearance EIA Environment Impact Assessment EMP Environmental Management Plan ERM Extension, Renovation and Modernization F.R.L Full Reservoir Level FB Foot Bridge Ft Feet GoI Government of India ha Hectares Ham Hectare Meter HMP Hot Mix plant HR Head Regulator IEE Initial Environmental Examination IND India IS Indian Standard ISPM Institutional Strengthening and Project Management IWRM Integrated Water Resources Management KM/ km/ Km Kilo meters KVA Kilo Voltage l Litres M Meters M3 / cu.m Cubic Metre MFF Multi-tranche Financing Facility MFI Multilateral Financing Institutions Mg Milli grams mm Millimetres MoEF Ministry of Environment & Forests NAAQS National Ambient Air Quality Standards NABET National Accreditation Board for Education and Training NABL National Accreditation Board for Testing and Calibration Laboratory NBSS National Bureau of Soil Survey NBSS&LUP National Bureau of Soil Survey and Landuse Planning NGO Non Governmental Organisation NIC National Informatics Centre NWP National Water Policy O&M Operation and Maintenance

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

OIIAWMIP Orissa Integrated Irrigated Agriculture and Water Management Investment Program OM Operation Manaul OP Operational Policies PF Protected Forest PIM Participatory Irrigation Management PMU Project Management Unit PP Pani Panchayat PPE / PPG Personnel Protective Equipments / Personnel Protective Gears PPME Project Performance Monitoring and Evaluation PPTA Project Planning and Technical Assistance PUC Pollution under Control Certificate RD Reduced Distance REA Rapid Environmental Assessment RF Reserved Forest RPM Respirable Particulate Matter Sec Seconds SIO’s Sub- Project Implementation Officers SOI Survey of India SPCB State Pollution Control Board WMM Wet Mix Macadam WUAs Water Users Association

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIWMIP)

EXECUTI VE SUMMARY

1. PROJECT BACKGROUND

i. The “Orissa Integrated Irrigated Agriculture and Water Management Investment Program” (OIIAWMIP) is an initiative by the Department of Water Resources (DoWR) of the Government of Odisha. It is intended to undertake the improvement of irrigation service delivery with Pani Panchayat(PP) empowerment and to enhance the productivity and sustainability of irrigated agriculture, thereby contributing to rural poverty reduction by increasing rural economic growth in the four northern river basins (Brahmani, Baitarani, Burhabalanga, and Subrenerekha river basins) and a part of Delta areas. The Government of Odisha had obtained a multi- tranche financing facility(MFF) loan from the Asian Development Bank(ADB), titled MFF N0. 0022 and Loan No. 2444 IND(INDIA). The loan includes funds for upgrading or undertaking extension, renovation and modernization(ERM) work in 6 major, 9 medium and 4 creek irrigation projects. ii. The “Orissa Integrated Irrigated Agriculture and Water Management Investment Program” (OIIAWMIP) is classified as Category B according to the Environment Policy (2002) of the Asian Development Bank (ADB). Initial environmental examinations (IEEs) were undertaken for two major and three medium irrigation schemes, and two sample community-based minor lift irrigation schemes during the Project planning and Technical Assistance(PPTA) stage; IEEs for four major and 2 medium were prepared during the Component for Technical Assistance(CTA) stage. An environmental assessment and review framework (EARF) was also prepared during the PPTA stage, to guide the environmental assessment of further subprojects. Kanjhari is not one of the subprojects included by either the PPTA or CTA for preparation of IEEs. The present report deals with the Initial Environmental Examination Report for the Kanjhari subproject, as per the new ADB Safeguard Policy Statement(SPS), June, 2009. 2. EXTENT OF THE I EE STUDY iii. The IEE is normally part of the Appraisal Report. However, for the Kanjhari Sub- project, an IEE has not been prepared during either the PPTA or CTA period; in addition, the detailed project report for the Kanjhari sub-project was only recently prepared. Therefore, this subproject required the preparation of a complete IEE. Specific environmental aspects were assessed in September and October, 2011. This report has been prepared on the basis of site visits and the completion of ADB’s Rapid Environmental Assessment (REA) Checklist. 3. METHODOLOGY iv. The general methodology adopted to accomplish the Initial Environmental Examination includes: • Review of legal and statutory requirements; • Review of feasibility study; • Preliminary reconnaissance to identity environmentally sensitive issues relating to the subproject and base line conditions; • Collection of Primary and secondary data; • Stakeholders Consultations; • Identify and assess the potential impacts of the subproject on the base line conditions and recommend mitigation measures to offset the identified adverse impacts; • Formulate Environmental Management Plan including review of Institutional set up and • Capacity Building.

i IEE & PC Kanjhari August 4

Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIWMIP)

4. DESCRI PTI ON OF THE PROJECT v. The Kanjhari medium irrigation sub-project is one of the sub-projects that have been proposed under the OIIAWMIP. Kanjhari is located in Baitrani Basin; it has been constructed across the river Kanjhari, a tributary of Baitarani Basin near revenue village Chakka of Keonjhargarh tahasil, Keonjhar district. The dam lies between latitude – 210.35’.394” N to 210.36’.048” & longitude 850.43’.470” to 850.43’.421”E to (Toposheet No.73G/10). The scheme falls under the North Central Plateau agro-climatic zone of Odisha and Agro –ecoregion 12 of agro-ecological region of India characterized by hot sub humid eco-regions with red and lateritic soils (J2 C3/4 of Agro-Ecological Regions of India, National Bureau of Soil Survey(NBSS Publ. 24). The Kanjhari project was started under World Bank Assistance in the year 1978-79 and completed in the year 1990-91. At present, the dam is providing irrigation to 9,740 hectares(ha) during Khariff & 2800 ha during Rabi covering Keonjhar, & Patna Tahasil under the ayacut area of the project. The dam consists of a Homogeneous rolled fill earth dam of 1245 meters(m) length, 29.50 m height having Central masonry ogee crested chute Spillway of length 111.50 m. The crest level of the Spillway is 402.50 m, fitted with 7 Nos of radial gates of size 12 m x 6 m having flood discharge capacity of 2286 Cumecs and its live storage capacity of 3451.66 Hecta-meter(Ham). The entire command area is irrigated over both sides of the canal. The distribution system consists of two main canals, 1 No. Distributary, 13 Nos Minors and 47 Nos of Sub-Minors. The total length of the distribution system, including the Left Main Canal(LMC) & Right Main Canal(RMC), is 176.252 kilometer(Km).

5. SCOPE OF WORK vi. The Initial Environment Examination(IEE) has been prepared for Kanjhari subproject which covers: • Renovation and modernization of the canal system by regulators, without increasing the command area. This entails the restoration back to the designed command area, without extending and widening the canal systems, and minimizing the losses by repairing the existing structures, and if necessary, the construction of additional structures as per the field requirement. Improvement of dam top road and repair of horizontal and vertical drains of the dam. • Bringing the canals to the original design section and providing necessary lining or guard walls as necessity and site conditions in the left and right main canals, distributaries and minor and sub-minor to arrest the present seepages seepage as well as canal breaches caused by shrinkage and cracking of embankments. • Improving hydraulic performance of main system canals, checking for prism shape and stability, and also works to reduce rainfall runoff erosion of sediment into the canals. • Remodeling of existing Hydraulic control structures for improved flow control and flow measurement along the left and right bank main canals and to off taking minors and sub- minors canals. • Construction of new and repair of cross drainage structures like and properly designed drainage inlets to minimize entry of sediment into the canals. • Providing additional new bridges and repairing the existing ones for improved access across canals. • Renovating the outlets of the main canal, distributaries, minor and sub-minors. • Improving the banks of left main canal, right main canal and Gambharia minor is built in to the sub-project for a length of 42 km for better access • Providing some tube wells along the entire length of left and right main canal, distributaries, minors and sub-minors was kept to provide water during canal closure period.

ii IEE & PC Kanjhari August 4

Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIWMIP)

6. ENVI RONMENTAL CATEGORY OF THE PROJECT vii. This sub- project is also classified as “Category B” as per Environmental Guidelines for Asian Development Bank’s Safeguard Policy Statement, 2009. This project is of a similar nature to the sub-projects of the PPTA and CTA, which were prepared earlier. This sub-project does not have any major environmentally sensitive issues within the existing project area. There are no wild life sanctuaries or national parks, eco-sensitive zones, protected monuments, endangered or exotic species of plants are present in the region, except movement of wild elephants in the project environs. Although expansion and modernization of existing sub-projects (Irrigation / River valley) may involve Ministry of Environment and Forest (MoEF) clearance, the present sub-project does not extend to an additional command areas; hence, no clearance is required. Since the project components include mainly renovation works, with no extension and widening of the canal system, the impact on natural resources is negligible, temporary and mitigable. 7. PROJECT ALTERNATI VES viii. The project has little or no scope for alternatives in terms of locations, as it is an existing project and the scope of the present project is to improve the performance of an existing system without increasing the command and to cater to the needs of the people. The originally designed areas will be improved, through the rehabilitation of sections of the canals and by modernizing the system with regulators, minimizing the losses by repairing structures and constructing additional structures as per requirements. The investment costs are largely for the rehabilitation and upgrading of the existing systems. As the original design appears to be adequate, alternative solutions for rehabilitation are not foreseen at this time.

8. CLEARANCES REQUI RED FOR THE SUBPROJECT ix. After reviewing the various applicable environmental acts and statutes, as applicable to Government of India, Govt. of Odisha and ADB some of the clearances that are to be obtained by SIO(Subproject Implementation Officer: Superintendent Engineer for major sub project and Executive Engineer for medium subproject) / Contractor are: a. Permission from State Forest Department - In the sections of the canal where it passes through the reserved forest areas, SIO/ DoWR shall obtain necessary permission for undertaking renovation / repair of the canals before initiating the civil works and to the possible extent tree cutting shall be avoided, if any trees need to be cut it shall be done after taking permission. b. Consent from Odisha State Pollution Control Board(OSPCB) - All the construction contractors should obtain consent under the water and air act from Odisha State pollution control board before commencement of construction work for the plant and machinery (Hot Mix, wet mix macadam(WMM), Batching, Crusher, Diesel Generator greater than 15 kilo-volt- ampere(KVA) they establish for the projector if they are procuring from the vendor, the contractor should ensure that the vendors has the requisite consents from the State Pollution Control Board of Odisha. The list of crushers whose consents has been given by OSPCB, Keonjhar as on September, 2011 is enclosed as Annexure 2. c. Permissions from Department of Mines and Geology : i. Contractor would obtain permission for transporting the soil from the Department of Mines and Geology or local bodies as applicable, along with the mutual agreement with the land owner in case of private lands. ii. Contractor would obtain permission for extracting boulders before quarrying; if the extraction of the boulder is being procured from the existing quarry/supplier, it shall be ensured that, the requisite license/ lease has been obtained from the concerned Authority.

iii IEE & PC Kanjhari August 4

Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIWMIP)

iii. Contractor would obtain permission for extracting sand before quarrying ; if the extraction of boulder is being procured from the existing quarry/supplier, it shall be ensured that the requisite license/ lease has been obtained from the concerned Authority. d. Permission from Commissioner of Explosives - If the Contractor stores diesel or stores blasting materials he has to obtain permission or if procuring or executing through vendors he must ensure that the vendor has obtained permission. e. Permission from District Health Officer - Contractor would obtain permission for establishing labour camps. f. Pollution under Control Certificates - Vehicles and machineries engaged in the construction of the project will comply with the Motors Vehicle act and will be required to obtain pollution under control certificate. 9. BASELI NE ENVI RONMENTAL STATUS x. The baseline environmental overview is as follows : a. Topography- The elevation in the project command area varies from 380 to 400 m; the highest contour is 488 m near the dam as per SOI Toposheet F45N10 & F45N14. The elevation in the region is around 50 m and the slope ranging from 10-20 meters/ kilometer. b. Climate -The average annual rainfall is 1535 mm. in the district. The average annual rainfall in sub project area based on rainfall from 176 to 2012 is 1280mm. The climate of the district is characterized by an oppressively hot summer with high humidity during March to July, and cold from November to February. Summer generally commences in the month of March. In the project area the average yearly evaporation average for the last 23 years is 584 mm. c. Geology & Soils - While the geology of the dam site consists of rocks of massive granite and dolerite intrusive, these rocks are exposed as small outcrops on the right bank and as a large exposure on the right edge of the riverbed. The dolerite dykes trending in N-S direction are exposed on the abutment hills and as scattered outcrops on the left bank. A thin dyke of dolerite trending E-W cut across the axis around RD 720 m. The subproject falls under earthquake risk zone-II (Low damage risk zone) of India The project area covers Kendhujhar, Patna, and Ghatgaon tehsils, the soils in these tehsils are mainly Balisahi series and Raghubera series. d. Landuse - The landuse of the project area is dam is surrounded by forest, while the left canal system in the initial reach pass through the reserved forest land, protected forest, village forest and passes through mostly agricultural lands, waste lands like rocky outcrops or unculturable waste lands, and small local nallas and a very small portion of the left canal and Padampur minor of the left canal passes through the elephant transit path at Padmakesarpur R.F. While the right main canal also originates in the reserved forest, protected forest and village forests and passes through mostly crop and waste land like rocky outcrops or unculturable waste lands, local nallas and also from Poipani R.F. The project sites are not located in areas prone to water logging, salinization and flash floods. e. Agro-climatic condition - he Keonjhar district falls in the North central plateau agro- climatic zone of Odisha. The district is primarily an agricultural district but rich in mineral deposits and has vast deposits of Iron, Manganese and Chrome Ores. f. Water Resources - The water quality of the Kanjhari river is not monitored. The Kanjhari dam catchment area is forest land. It is likely that water quality of this river is very pristine, apart from some erosion, as there are no pollution sources in its catchment area as it is mainly a forest area. The general ground water depth in the command area was enquired and it was found the depths of the existing tube wells are varying from 40 to 100’ in the head villages and 200’ to 250’ in the tail end villages. The water level gets reduced after the canal water supply gets stopped as observed by the tail end villagers.

iv IEE & PC Kanjhari August 4

Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIWMIP)

g. Biodiversity - The dominant species of the study area are Sal, Asan, Jamu, Kendu, Arjuna, Kurei, Teak, Ghurudu, Eucalyptus, Barakoli, Dhaki and Pokagungha, etc., in the forest areas, while Sal, Mahua, neem, mangium, mango, peepal, tamarind, custard apple and bamboo are common in the command area. Important animal species found in the forests of the subproject /district include elephant, deer, bear, monkeys, peafowl, Red Jungle fowl, Red Spur fowl, Black Partridge, Grey Horn Bill, Green Pigeon and Ducks. As per the Red data book of IUCN elephants are endangered species and sloth bear occupies vulnerable status and rest of the animals are least concerned. There are no government notified core habitations like elephant reserves or sanctuaries with in the area of influence of the project area. As per the Keonjhar district wild life census there are 41 elephants found in the forests of the district, but near the subproject mostly elephants from the state move during harvesting period in search of food. The forest department has identified the path where movement of elephant is taking place called as elephant transit path which happens to pass through certain sections of the command area and the catchment area and a small portion of the left main can tail end portion passes through that elephant transit path. The elephants move from one forest to another. i. Demography - The project covers 87 villages with 19 PPs covering Ghatagaon, Keonjhar and Patna blocks with 62199 numbers of beneficiaries. As per the 2011 census, the project benefited villages have nearly 13,550 households with a population of 58643. The percentage of Scheduled caste(SC) population in these villages is around 7.65%, the Scheduled Tribes (ST) population is around 57.12% and the literacy is around 57.77%. 10. ANTI CI PATED ENVI RONMENTAL I MPACTS AND MI TI GATI ON MEASURES: xi. The potential positive and negative impacts were identified in relation to design, construction and operation for the proposed renovation works. The negative environmental impacts, both direct and indirect, associated with the project location and mitigative measures, and the impacts arising due to the construction phase of the project will be temporary and short term in nature. xii. The direct and short term impacts concern the implementation stage of the ERM works which can be mitigable with environmental management plan(EMP) implementation. Mitigation reduce measures have been developed to reduce all negative impacts to acceptable levels. Special measures like identification of forest areas, potential farmers willing to give earth for borrow areas in private land and protection and safety measures for workers have been addressed in the EMP. 11. I NFORMATI ON DI SCLOSURE, CONSULTATI ON AND PARTI CI PATI ON xiii. In the most recent notification of the Ministry of Environment and Forests of 14 September 2006, (referred to in section III E of this IEE) modernization of irrigation projects does not require Public Consultation. However, Public Consultation and Information Disclosure is an essential element of the ADB Safeguard Policy Statement 2009, and included in the internal project procedures. The process of stakeholder, public consultation as well as outcome of consultations and information disclosure adopted for the subproject has been developed. xiv. The subproject stake holders of the project include: • Project benefitted communities or stakeholders or Pani Panchayat members, • Institutional stake holders such as Pollution Control Board(PCB), government institutions like Water Resource Department, State Pollution Control Board, Forest Department, Fisheries department, revenue etc., xv. The Kanjhari subproject benefited community information, dissemination and consultation sessions took place during the Participatory “Walkthrough” Survey, from the 14th to 25th September, 2011, in which farmers took part, including the members of the Pani Panchayat. During this Walkthrough Survey, PP the farmers were consulted on the need for rehabilitation, and their ideas, concerns and requests have been reflected in IEE document. The Consultation was carried out in six different villages (Poipani, Sarasposi, Boda Jamuposi, Chaka, Saradhapur

v IEE & PC Kanjhari August 4

Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIWMIP)

and Bolaniposi) as part of the environmental screening covering the head, middle and tail end villages. xvi. The Institutional stake holders that were consulted were: Divisional Forest Office, Keonjhar, State Pollution Control Board, Regional Office, Keonjhar, District Fisheries Department, Keonjhar, NIC Keonjhar, and non-government organization(NGO’s). The feedback and suggestions obtained from these departments were used in screening the subproject and planning the activities. xvii. Summary findings of Consultation sessions with benefited communities are: • The PP is keen for the proposed renovation and assured that they will cooperate in all implementation aspects. • The tail end villagers want to see the canal levels rectified and re-sectioning needs to be done which would get them water. • The villagers want the breaches rectified and the lining of the guard walls for the main canals, as well as the sub-minor and minor repair of some structures. • The Villagers are ready to accommodate the short term impacts that may arise during construction phase • At present, farmers are depending on inorganic pesticides and fertilizers; they need to be made aware of the ill effects of these, and awareness need to be developed on organic farming. The environmental awareness program will be required, focusing on the usage of banned pesticide, as well as personal safety during application of pesticide. • At present, farmers are not aware of the quality of soil and water quality; they require support from the allied departments. • Planning of construction activities can be initiated after the kharif crop and proper consultation with PP/ VSS and the forest department in establishing labour camps and equipment at the sites need to be done.

12. GRI EVANCE REDRESS MECHANI SM xviii. The grievance mechanism for the subproject has been developed and discussed in the IEE report. 13. ENVI RONMENTAL MANAGEMENT PLAN (EMP) xix. An EMP is mandatory and consists of the following features : (i) Institutional Arrangement required for the subproject; (ii) staffing requirement for EMP implementation; (iii) Reporting System and the responsibilities of different institutions involved in EMP implementation (iv) Environmental Monitoring plan with the check list of anticipated impacts and suggested mitigation measures and the responsibility of different institutions and also stages of implementation (v) Suggesting Environmental monitoring plan with showing locations of monitoring, frequency and stage of monitoring; (vi) performance indicators for the subproject (vii) Environmental Monitoring and Management Costs and (viii) Capacity building requirements. 14. RECOMMENDATI ON xx. Recommends the subproject to be rated Category B for the following reasons: (i)There are no significant adverse impacts associated with this project. Instead the project is expected to improve irrigation facilities and enhance economic growth of the area; (ii) Increased irrigation will also help in planting of more trees thereby increasing the environmental conditions of the area adding to the greenery and general aesthetics of the area; (iii) The indirect benefits of the project will be lowered levels of out migration as the communities will have more opportunity of securing income from within the village; (iv) There will be growth in living standard of people,

vi IEE & PC Kanjhari August 4

Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIWMIP)

which will encourage proper education, social awareness, health facility and prosperity amongst the people; (v) The IEE clearly states in its findings that there will be no significant impact in the local environmental condition due to construction and operation of the project and preference shall be given to the local labour for carrying out the work. xxi. Mitigation - Canal system close to reserved, protected and village forest areas at many places, dam portion, left canal tail end portion and Padampur minor falls under elephant transit paths, so adequate preventive measures need to be observed such as not establishing construction camps/ plants and material in these areas. xxii. The SIO in consultation with WUAS had identified potential borrow areas in private land which will also reduce impacts arising due to borrowing in the forest areas etc. Contractor may be required to abide by regulations pertaining to “sensitive / restricted” areas as well as by observing decent working practices (strict monitoring in not cutting any trees for fire wood in the forest areas, not hunting any wild life) and providing facilities at construction camp. 15. CONCLUSI ON xxiii. The IEE has assessed potential environmental impacts associated with the subproject. There are no adverse impacts that are significant and complex in nature expected from implementation of this subproject. xxiv. The subproject is expected to improve the existing degraded irrigation infrastructure and will be put to beneficial use to the society. This will boost agriculture growth in the area and will bring prosperity to the region. xxv. By improving the irrigation infrastructure economic disparity between head end and tail end users will be reduced. xxvi. The potential adverse impacts are minimal as no additional land is required, and the impacts that may arise with construction and operation because of vicinity to forest and elephant paths can be mitigated through stringent monitoring and adopting strict construction practices by the Contractor and water users associations(WUAs)and implementing the suggested EMP measures. xxvii. IEE assessment confirmed the subproject Category B classification and will not require detailed EIA to be undertaken except obtaining required permits and certification as suggested in the IEE report.

vii IEE & PC Kanjhari August 4

Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIWMIP)

1. I NTRODUCTI ON

1.1 Project Background

1. The Asian Development Bank (ADB) has agreed with national and state governments to fund the project in Odisha, which will include support for irrigated agriculture development and integrated water resources management, with a loan of $189 million in the form of a sector loan to utilize multi-tranche financing facility (MFF). The Government of India is promoting state-level sector reforms through its National Water Policy (NWP) 1987 and 2002, which advocates Participatory Irrigation Management(PIM) and Integrated Water Resource Management(IWRM) to promote and sustain more efficient water use. Agriculture is the backbone of the Odisha and rural poverty remains highest in India. However, the low performance of the existing irrigation infrastructure impairs agricultural productivity growth and diversification. About 30% of the present command area hardly receives any irrigation, due to poor system design, lack of field channels, limited accountability in system management to farmers, and insufficient maintenance. The Government of Odisha, in compliance with its State Water Policy, is prioritizing the improved performance of existing infrastructure in partnership with WUAs, as this is considered the fastest and most cost-effective way to expand reliable irrigation and to serve as a conduit to intensified, high value agriculture.

2. To support the process, in the late 1990s, the Government of Odisha gradually developed the policy, planning and institutional basis for irrigation and water resources. Specific steps taken included: (i) promulgation of the State Water Policy and State Water Plan adopting PIM and IWRM principles, (ii) establishment of a legal framework for WUAs, (iii) substantial increase in the water tariff and Operation and Maintenance(O&M) financing, and (iv) capacity strengthening of the Department of Water Resources (DOWR). As an effort towards attaining these objectives, the Government had applied for MFF No. 0022 and Loan No 2444 IND from the Asian Development Bank, and as a result, has started the “Orissa Integrated Irrigated Agriculture and Water Management Investment Program” (OIIAWMIP). The project has a wide objective to improve the irrigation service delivery with PP empowerment to enhance the productivity and sustainability of irrigated agriculture, thereby contributing to rural poverty reduction by increasing rural economic growth and reducing poverty in the four northern river basins (Brahmani, Baitarani, Burhabalanga, and Subrenerekha river basins) and a part of Mahanadi Delta areas. The executing agency is the Department of Water Resources (DoWR). The DoWR, Odihsa will be the implementing agency and the projects are operated through a Project Management Unit (PMU), and the works will be outsourced to private contractors selected under National Competitive Bidding.

3. The Institutional Strengthening and Project Management(ISPM) consulting services recruited were assisting in the preparation and implementation of sub-projects, and working closely with the Project Management Unit (PMU).

1 IEE & PC Kanjhari August 4

Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

4. The “Orissa Integrated Irrigated Agriculture and Water Management Investment Program” (OIIAWMIP) was classified as category B according to the Environment Policy (2002) of the Asian Development Bank (ADB). An initial environmental examination (IEE) were undertaken for two major irrigation (Taladanda and Mahandi Chitrotpala Island Irrigation) and three medium irrigation schemes(Sunei, Gohira and Remal), and two sample community-based minor lift irrigation schemes during PPTA stage; and four major irrigation schemes (Machhagaon, Pattamundai, HLC Range -1 and ) and 2 medium irrigation (Kanbahal and Ramiala) during CTA stage. The following sub-projects were proposed under the program (Table1.1). An environmental assessment and review framework (EARF) was also prepared to guide the environmental assessment of further subprojects. Kanjhari is not one of the subprojects included by either PPTA or CTA for the preparation of IEEs. OIIAWMIP Project is to be implemented in 3 tranches; this sub-project is part of tranche -2. The present report deals with the Initial Environmental Examination Report for the Kanjhari subproject, as per the new ADB Safeguard Statement June 2009.

Table 1 : Proposed Subprojects

Nr Name Water Source Tranche FS Basin Area (ha) Status A1: Major Subprojects - ERM 1 Taladanda canal Mahanandi river delta I PPTA Mahanadi delta 32,684 2 Machhagaon canal Mahanandi river delta II CTA Mahanadi delta 34,870 3 Pattamundai Mahanandi river delta II CTA Mahanadi delta (Brahmani) 23,032 4 HLC Range I Mahanandi - Birupa II CTA Mahanadi (Brahmani) 14,700 5 Jajpur canal II CTA Baitarani 13,100 118,386 A2: Medium subprojects - ERM 1 Bankabal Dam III ISPM Subernarekha 7,200 2 Khandkai Dam III ISPM Subernarekha 7,990 3 Nesa Dam III ISPM Subernarekha 1,202 4 Sunei* Dam I PPTA Burhabalanga 10,000 5 Remal* Dam I PPTA Baitarani 4,313 6 Gohira* Dam I PPTA Brahmani 8,304 7 Kansbahal Dam II CTA Brahmani 4,615 8 Ramiala Dam II CTA Brahmani 6,128 9 Kanjhari Dam II ISPM Baitarani 9,300 59,052 B: Major Subprojects - Completion of Scheme 1 Mahandi Chitrotpala Island Irrigation* Mahanandi river delta I PPTA Mahanadi delta 13,261 13,261 C1: Creek Irrigation (& drainage control) 1 Bada Mahara III ISPM Mahanadi delta 776 2 Pada Mahara III ISPM Baitarani 353 3 Samudrapasa III ISPM Brahmani ? 415 4 Natiajore III ISPM Baitarani 1,560 3,104 C2: Pilot Drainage & Survey & Investigations III

D: Minor Irrigation - Lift ALL 800 Existing schemes / defunct 16,000 River or groundwater 600 Existing schemes / stabilisation 12,000 1,400 28,000 Total 221,803

Notes: 1. In addition to the above three PP refinement schemes are proposed, for non-infrastructure interventions

(Source: I nception Report I SPM Consultant – January 2010)

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

1.2 Purpose of the report 5. Kanjhari irrigation system is one of the sub-projects to be funded under Tranche -2. The sub project proposes rehabilitation and resectioning of an existing medium irrigation scheme. Kanjhari irrigation subproject is a medium irrigation scheme in Baitarani basin. It has been constructed across the river Kanjhari, a tributary of the Baitarani basin near revenue village Chakka of Keonjhargarh Tahasil, Keonjhar District. The Initial Environmental Examination (IEE) report investigates the environmental impacts based on the preliminary design and estimates. It is mandatory that the sub- project considered for implementation complies with all relevant environmental requirements of the Government of India, the State Government of Odisha, and ADB’s safeguard Policy Statement (SPS) 2009. The Environment Impact Assessment (EIA) Notification of 2006, Govt. of India is the basis for environmental assessment. The expansion and modernization of existing projects or activities listed in the Schedule to this notification with addition of capacity beyond the limits specified for the concerned sector, project or activities which cross the threshold limits given in the Schedule, after expansion or modernization require environmental clearance. As this sub-project involves renovation of the existing canals to its original designed capacity, repair of existing structures and construction of some new additional structures (Village Road Bridges, outlets etc) are involved in the project without increase in the command areas or no new canal are proposed, so doesn’t require any environmental clearances.

1.3 Extent of the I EE study 6. The IEE is normally part of the Appraisal Report. However, for the Kanjhari Sub- project an IEE has not been prepared, either during the PPTA or CTA periods; the detailed project report for the Kanjhari sub-project was prepared only recently. Therefore, this subproject required a preparation of a complete IEE. Specific environmental aspects were assessed in September and October, 2011. This report has been prepared on the basis of a site visit and the completion of ADB’s Rapid Environmental Assessment (REA) Checklist.

1.4 Methodology 7. The general methodology adopted to accomplish the Initial Environmental Examination includes:

• Review of legal and statutory requirements; • Review of feasibility study reports and previous reports; • Preliminary reconnaissance to identity environmentally sensitive issues relating to the subproject and base line conditions; • Collection of Primary and secondary data; • Stakeholders Consultations and consultation with experts and institutions; • Identification and assessment of the potential impacts of the subproject on the base line conditions and the recommendation of mitigation measures to offset the identified adverse impacts; • Formulation of an Environmental Management Plan, including the review of the Institutional set up and; • Capacity Building.

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

• Preparation of draft IEE report and an updated IEE report and incorporation of ADB comments 1.5 Project Location 8. The Kanjhari irrigation subproject is a medium irrigation scheme in Baitarani basin. It has been constructed across the river Kanjhari, a tributary of the Baitarani Basin near revenue village Chakka of Keonjhargarh Tahasil, Keonjhar District. The Kanjhari rises in the hills of Gonasika and flows in the north –east and meets Baitarani in the south of Udayapur. It is 56 Km in length and covers important villages like Ramachandrapur, Raghunathpur and Poipani in its course. The dam lies between latitude – 210.35’.394” N to 210.36’.048” & longitude 850.43’.470” to 850.43’.421”E to (Survey of India :Topo Sheet No.73G/10 1:50,000 scale), the location map is shown as Figure 1 Annexure -1

Figure 1

1.6 Structure of I EE Report 9. In line with the ADB’s SPS 2009, the IEE report has 10 chapters. The details are as:

1. Executive Summary: The section deals briefly with the critical facts, significant findings and recommendations. 2. Chapter 1: I ntroduction This chapter describes with overview of the project, purpose of the report, study methodology and project location 3. Chapter 2: Policy, Legal and Administrative Frame work chapter provides environmental management and protection policies, regulations as per the Ministry of Environment, Govt. of India, Govt. of Odisha and ADB environmental policies and the required clearance for the subproject. 4. Chapter -3: Description of the Project This chapter briefly describes the present condition of the various structures under the Kanjhari irrigation subproject and a description of the proposed engineering recommendations.

IEE & PC Kanjhari 4 August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

5. Chapter 4: Description of the Environment. The section includes baseline conditions for the physical and natural environment, socio economic and demographic profile of the project area. The data presented in the report is gathered from secondary sources. 6. Chapter 5: Anticipated Environmental I mpacts and Mitigation Measures Chapter describes the extent of the impacts of the project activity on the existing environment. The focus of section is on the adverse impacts however the beneficial impacts are also reported in this chapter. 7. Chapter 6: I nformation Disclosure, Consultation and Participation chapter gives information on consultation, stages and levels of consultation process and findings of the public consultation conducted in six villages as part of the project. 8. Chapter 7 Grievance Redress Mechanism chapter provides the proposed mechanism for grievances.

9. Chapter 8: Environmental Management Plan Chapter describes the measures recommended for mitigating the adverse impacts arising out of the project. This chapter also emphasizes on the roles and responsibilities, regular monitoring activities, supervision and reporting of monitoring of various environmental components during different phases of the project. 10. Chapter 9 Gives findings and recommendations of the IEE study. 11. Chapter 10 includes the conclusion of the IEE study.

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

2. POLI CY, LEGAL AND ADMI NI STRATI VE FRAMEWORK

10. The environmental management and protection policies, regulations and administrative framework governing the project are reviewed in this section. The review includes sector-specific environmental policies and regulations of the Government of India, State Govt of Odisha, ADB’s Safeguard Policy Statement, June, 2009, and the administrative framework of various agencies, such as the Ministry of Environment and Forest (MoEF), the Pollution Control Boards and other bodies associated with the implementation of the proposed subproject.

A. MANDATORY REQUI REMENTS (FUNDI NG AGENCY)

2.1 Asian Development Bank’s Safeguard Policy Statement (June 2009) 11. The following are the requirements under Asian Development Bank’s safeguard policy. 2.2 Environment Categorization 12. ADB uses a classification system to reflect the significance of a project’s potential environmental impacts. A project’s category is determined by the category of its most environmentally sensitive component, including direct, indirect, cumulative, and induced impacts in the project’s area of influence. Each proposed project is scrutinized as to its type, location, scale, and sensitivity and the magnitude of its potential environmental impacts. Projects are assigned to one of the following four categories based on the Operations Manual Section F1 and Operational Procedures (OP) March 2010: Category A: Projects with potential for significant adverse environmental impacts which are irreversible, diverse, or unprecedented. An environmental impact assessment (EIA) is required to address significant impacts. Category B: Projects judged to have some adverse environmental impacts, but of a lesser degree and or significance than those of category A projects. An initial environmental examination (IEE) is required to determine whether or not significant environmental impacts warranting an EIA are likely. If an EIA is not needed, the IEE is regarded as the final environmental assessment report. Category C: Projects unlikely to have adverse environmental impacts. No EIA or “IEE is required, although environmental implications are still reviewed. Category F1: Projects are classified as category F1, if they involve a credit line though a financial intermediary. The financial intermediary must apply on environmental management system; otherwise all subprojects will result in insignificant impacts. 2.3 Environmental Management Plan 13. It addresses the potential impacts and risks identified through the process of environmental assessment and the level of details and complexity of the EMP. It identifies impacts and risks and the priority measures and actions that will commensurate with the project. 2.4 Public Disclosure 14. The IEE summary will be translated in to local language and disclosed to Water Users Association (WUA) level. The copy of the full IEE will be available with subproject Implementation Office (SIO) and Project Management Unit (PMU) and will be made available for the stakeholders as and when asked for. A copy of the IEE Summary will be disclosed through the DOWR website and in ADB website as well.

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

B. MANDATORY REQUI REMENTS (NATI ONAL)

2.5 Environmental Regulatory and Policy Framework for Subproject Selection 15. The environmental regulations of the Government of India have laid out various policy guidelines, acts and regulations pertaining to the sustenance of environment. The acts that are applicable to this project are summarized in the sections below. 2.6 Constitutional Provisions 16. The Constitution of India, in Article 48, of Directive Principles of the State, states that “the state shall endeavour to protect and improve the environment and to safeguard forests and wildlife of the country”. Further Article 51-A (g), of fundamental duties, emphasizes that, “It shall be the duty of every citizen of India to protect and improve the natural environment including forests, lakes, rivers and wildlife and to have compassion for living creatures”. These two provisions of the constitution are the guiding principles for the environmental legislation in India. 17. The Government of India has laid down various policy guidelines, regulations, acts and legislations pertaining to the sustainability and protection of the environment and its various components. The statutory requirements for the proposed road projects are discussed briefly in the following paragraphs. 2.7 The Environment (Protection) Act, 1986 and the Environmental I mpact Assessment Notification, 14th September 2006 18. The Environmental (Protection) Act, 1986 is the umbrella legislation providing for the protection of the environment in the country. This act provides the Environment (Protection) Rules, which were formulated in 1986. The Environmental Impact Assessment Notification, 1994 and the various amendments thereto have been notified under this act. The Ministry of Environment and Forests (MoEF) has enacted a new notification under the Environmental Protection Act, 1986 related to environmental clearance (EC) of the developmental projects with effect from September 14, 2006. 19. According to this notification, developmental projects are classified as category A and Category B based on their size, nature, location and possible environmental impacts. All the projects included in Category A require environmental clearance from the MoEF, Government of India. The list of projects or activities requiring environmental clearance and their categorization is given in schedule of this notification. According to this notification, expansion and modernization of existing projects or activities listed in the schedule to this notification with addition of capacity beyond the limits specified for the concerned sector, project or activities which cross the threshold limits given in the Schedule after expansion or modernization. 20. During discussions held with officials of the department of environment and forests Government of Odisha(Go). The state department of environment (DOEn) is of the view that new irrigation projects encompassing a command area less than 500 ha need not require EC. In view of this all the new major, medium and minor projects that are likely to increase the command area more than 500 ha and will need an EC from the SEIAA and projects whose command area increases equal to or more than 10,000 ha will need an EC from the central government. 21. This Kanjhari sub-project is an existing medium irrigation project where renovation of existing canals to its original designed capacity, repair of existing structures and construction of new additional structures like village bridges, bathing ghats etc are involved in the project activities. Since no new canals and no additional command area are being increased this sub-project doesn’t require environmental clearance as per the provisions of EIA notification 2006.

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

2.8 The Water and Air (Prevention and Control of Pollution) Acts 22. The Water (Prevention and Control of Pollution) Act, 1974 resulted in the establishment of the Central and State level Pollution Control Boards, (CPCB and SPCB) whose responsibilities include managing water quality and effluent standards, as well as monitoring water quality, prosecuting offenders and issuing licenses for the construction and operation of developmental projects requiring water as a resource. The Air (Prevention and Control of Pollution) Act, 1981, empowers the SPCBs to enforce air quality standards set by the CPCB. 23. During the construction phase of the project, if plants like concrete mixing plants, hot mix plants, crushers, diesel generators etc are installed., will require consent {consent for establishment (CFE) and consent for Operation (CFO)} from the Odisha State Pollution Control Board(OSPCB) pursuant to the Water (Prevention and Control of pollution) Act of 1974, The Water Cess Act of 1977 and the Air (Prevention and Control of Pollution) Act of 1981. 24. This consent will be taken by the construction contractor. If the contractor is procuring the material from the vendors, he must ensure that the vendor’s have consent from the OSPCB. This would be applicable to all the major, medium and minor sub projects of this loan programme. 2.9 The Hazardous Waste (Management and Handling) Rules, 1989 25. The Central Government formulated these rules under the Environment (Protection) Act, 1986. Under Section 7 of these rules it is required that the operator or occupier of a facility dealing with hazardous waste ensures that hazardous waste is packaged in a suitable manner for storage and transport and that the labeling and packaging shall be easily visible and be able to withstand physical conditions and climatic factors. 26. Bituminous and other materials used in construction are considered as hazardous in nature. Section 9 of these Rules also requires that in case of an accident during transportation of hazardous wastes, the operator or occupier of a facility shall immediately report to the SPCB in the prescribed form. This statute applies to the contractor’s if they are involved, in handling (including storing) and transshipment of hazardous bituminous materials during construction or black topping of the project dam roads. 2.10 The Forest (Conservation) Act, 1980 27. The Forest (Conservation) Act, 1980 pertains to the cases of diversion of forest area for non-forestry use. The forest management rules, 2003 provide the guidelines for conversion of forest land for non-forest purposes. According to these rules the process of obtaining forest clearance under the new amendment varies with the legal status of the forestland to be diverted. There are two types of forests namely, reserved and protected, whose forest land can be diverted for non forest purposes. Reserved Forest (RF) is an area notified under the provisions of the Indian Forest Act or the State Forest Acts, with a full degree of protection. In Reserved Forest, all activities are prohibited unless permitted. Protected Forest (PF) is an area notified under the provisions of Indian Forest Act or the State Forest Acts with a limited degree of protection. In Protected Forests all activities are permitted unless prohibited through a government notification. It also restricts felling of trees and regulates diversion of forestland for non-forest use.

a In the case of Reserved Forest (i) If the area of forests to be cleared or diverted exceeds 40 ha then prior permission will be granted by MoEF, GOI, New Delhi. (ii) If the area of forest to be cleared or diverted is between ‘5 to 40’ ha, then the case would be put to the state advisory committee for consideration. The committee after

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

studying the case will make its recommendation to the MoEF, GOI for formal approval. (iii) If the area of forest to be cleared or diverted is below or equal to 5 ha, then the MoEF regional office is empowered to give the approval. (iv) If the area to be clear-felled has a forest density of more than 40%, permission to undertake any work is needed from the Central Government, irrespective of the area to be cleared. b. In the case of Protected Forest

28. The MoEF regional office is empowered to accord Forest clearance for an area up to 5 hectares, which is to be cleared. 29. The procedure for getting the forest clearance is as follows: (i) The user agency will submit an application to the District Forests Officer (DFO) seeking conversion of forest land for non forests purpose. (ii) The DFO will scrutinise the application and forward it to the state conservator of forests (CFO) with his recommendations. (iii) The state forest department will estimate the cost of compensatory afforestation as twice the cost of area likely to be submerged/ acquired and suggest the user agency to deposit this amount to the state forests department. (iv) The state forests department will also identify the land for compensatory afforestation and submit the application along with a compensatory afforestation plan to the Secretary MoEF, Government of India. (v) The expert committee scrutinizes the application and state government’s proposal for compensatory afforestation. If required, the committee will also under take site visits. (vi) The committee accords approval provided the application and compensatory afforestation proposals are satisfactory (vii) The state government submits the compliance report stating the status of implementation of compensatory afforestation plan and conditions given in MoEF’s first stage clearance. (viii) After review of the compliance report MoEF accords formal forest clearance. 30. This sub-project is an existing project involving forest areas but initiated before 1980 or Forest Act, so SIO has to obtain permission for renovating the canal for the sections passing through the reserved forest from State Forest Department before initiating the works. However, there are very few trees on the canal embankments i.e. within ROW if any tree need to cut under unavoidable situation, then SIO should obtain permission for tree cutting from State Forest Department. 2.11 The Wild Life (Protection) Act, 1972 31. The Wildlife (protection) Act, 1972 has allowed the government to establish a number of National Parks and Sanctuaries over the past 25 years, to protect and conserve the flora and fauna of the state. The act will be applicable to this project if the command area of any sub project encroach any National Park or Sanctuary which houses habitats of wild animals. The wild life sanctuaries and national parks in the river basins under consideration are given in Table 2 below. This sub project doesn’t fall under within these national parks or sanctuaries.

Table 2 List of National Parks and Sanctuaries in OI I AWMP Area

Sl. Name of the Protected Area Area Sq. Km. No. (PA) National Parks 1. Bhitarkanika 145.00

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

Sl. Name of the Protected Area Area Sq. Km. No. (PA) 2. Similipal 845.70 Sanctuaries 1. Bhitarkanika 672.00 2. Samilipal 2200.00 3. Satakosia Gorge 795.52 4. Hadagarh 191.06 5. Khalasuni 116.00 6. Kuldiha 272.75 7. Gahirmatha (Marine) 1435.00 (Source: Wild life, Odisha, Forest Department, Government of Odisha, 2013) 32. No National parks or Sanctuaries or core declared habitations are present within the sub-project area except movement of wild elephants in the project corridor.

2.12 The Motor Vehicles Act, 1988 33. In 1988, the Indian Motor Vehicles Act empowered the State Transport Authority (usually the Road Transport Office) to enforce standards for vehicular pollution and prevention control. The authority also checks emission standards of registered vehicles, collects road taxes, and issues licenses. In August 1997, the Pollution Under Control Certificate (PUC) programme was launched in an attempt to crack down on the vehicular emissions in the States. Since this act is applicable for all states, this will be applicable for this project.

34. All the vehicles that will be used in construction of the subprojects will have to comply with the PUC norms set down under this act. 2.13 The Ancient Monuments and Archaeological Sites and Remains Act, 1958 35. According to this Act, the area within the radii of 100 meters (m) and 300m from the “protected property” are designated as a “protected area” and “controlled area” respectively. No development activity (including building, mining, excavating, blasting) is permitted in the “protected area” and development activities likely to damage the protected property are not permitted in the “controlled area”, without prior permission of the Archaeological Survey of India (ASI), if the site/remains/ monuments are protected by ASI. The likely subprojects command area does not have any protected property and therefore, this act will not be applicable for the project. However, there may be a possibility that artifacts of coins, structures, fabrics or any other archaeological relics may be identified during the construction phase. If such a situation would arise this Act would then apply. However, in case of chance finds, the contractors will be required to follow a protocol; as defined in the Environmental Management Plan. 2.14 Land Acquisition and Resettlement & Rehabilitation: 36. The following acts and policies would be applicable to the sub-projects under OIIAWMIP. i. Land Acquisition Act, 1894 (LAA-1894) 37. In India, compensation for land acquisition (LA) and resettlement assistance for project-affected people is governed by the Land Acquisition Act (LAA), 1894 which has been amended from time to time. Under the Land Acquisition Act of 1894,

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

compensation is paid only to the legal titleholders and does not provide any compensation package to the non-titleholders like encroachers, squatters etc. LAA, as amended in 1984 provides the legal framework for land acquisition for a public purpose in India. It enables the State Government to acquire private lands for a public purpose, and seeks to ensure that no person is deprived of land except under the Act ii.National Rehabilitation and Resettlement Policy, 2007 (NRRP-2007) 38. The National Rehabilitation and Resettlement Policy, 2007 (NRRP-2007) was adopted by the Government of India in 31st October, 2007 to address development-induced resettlement issues. The policy provides for the basic minimum requirements, and all projects leading to involuntary displacement of people must address the rehabilitation and resettlement issues comprehensively. The State Governments, Public Sector Undertakings or agencies, and other requiring bodies shall be at liberty to put in place greater benefit levels than those prescribed in the NRRP-2007. The principles of this policy may also apply to the rehabilitation and resettlement of persons involuntarily displaced permanently due to any other reason. iii.The Orissa Resettlement and Rehabilitation Policy, 2006 39. The State Government of Odisha in 2006 have framed and adopted a comprehensive resettlement and rehabilitation policy named “The Orissa Resettlement and Rehabilitation Policy, 2006” in order to ensure sustained development through a participatory and transparent process. It shall apply to all those projects, for which acquisition of private land under Land Acquisition Act, 1894 or under any other law's for the timebeing in force or proclamation inviting objections in case of Government land is notified. This shall also be applicable to all projects for which land is acquired through negotiation under the provisions of this Policy. iv. I nvoluntary Resettlement Policy of Asian Development Bank 40. The Safeguard Policy Statement (2009) of Asian Development Bank’s (ADB) is being followed for preparing this resettlement plan. The main objectives of the ADB policy include: • to avoid involuntary resettlement wherever possible; • to minimize involuntary resettlement by exploring project and design alternatives; • to enhance, or at least restore, the livelihoods of all affected persons in real terms relative to pre-project levels; and to improve the standards of living of the affected poor and other vulnerable groups 41. This sub-project Kanjhari doesn’t require any land acquisition nor were any encroachments in the form of structures noticed. 2.15 Public Liability I nsurance Act, 1991 42. This Act provides for public liability insurance for the purpose of providing immediate relief to the persons affected by an accident occurring while handling any hazardous substance and for matters connected therewith or incidental thereto. The transportation of hazardous substances by vehicle use is also included. This statute would apply on the implementers of the Project. 2.16 Central Pollution Control Board (CPCB) 43. It is a statutory authority attached to the MoEF located at New Delhi. The main responsibilities of CPCB include the planning and implementation of water and air pollution programmes; advising the Central Government on water and air pollution programmes; setting air and water standards and co-ordinating with the SPCBs. 2.17 Odisha State Pollution Control Board (OSPCB) 44. The OSPCB is the government agency responsible for ensuring the compliance to relevant standards related to discharges in the environment. The activities of the

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

OSPCB include, planning and executing state level air and water quality initiatives; advising the state government on air, water and industry issues; establishing standards based on National Minimum standards and enforcing and monitoring of all activities within the state under the Air Act, the Water Act and the Cess Act. 2.18 Applicability of I nternational Environmental Agreements 45. In addition, international conventions such as the International Union for Conservation of Nature and Natural Resources1 (IUCN), Convention on Migratory Species of Wild Animals (CMS)2 and Ramsar Convention on Wetlands of International Importance3 are applicable for selection and screening of sub-projects under restricted / sensitive areas. India is a party to these conventions 2.19 Odisha State Legislations and Acts and Other relevant Guidelines/ Standards 46. Over and above, the project also gives due importance to the Indian standards, norms, guidelines and management procedures related to canal or irrigation projects such as IS 4701 reaffirmed 1995 i.e. Code of Practice for Earth work on canals and IS 4839 (part -1)1992, etc. 47. The Government of India in the Ministry of Labour & Employment have enacted the Building and Other Construction Workers (Regulation of Employment and Conditions of Service of the Buildings and other Construction Workers and to provide their safety, health and welfare measures. To enforce the same the Government of Odisha has formulated rules namely the Orissa Building and other Construction Workers (Regulation of Employment and conditions of Service) Rules, 2002. As per the act Government has to deposit 1 % cess of the cost approved as per the tendered notification. The amount needs to be deducted from the bill at the time of making payment to the contractor. 48. According to the Child Labour Act, children at the age of 14 to 18 years, if employed shall not be engages in hazardous working conditions. 49. The constitution of India has provisions for ensuring the health and wellbeing of all employees need to be protected and the state has the duty to ensure protection. For this sub-project, the mitigation measures were based on the World Bank Environmental, Health and Safety (EHS) Guidelines. 2.20 Orissa minor mineral concession Rules 1990 amended 2004 50. As per the act, no person shall undertake any quarrying operations for the purpose of extraction, collection and /or removal of minor minerals except under and in accordance with terms and conditions of the quarry lease, permit and / or auction sale, various rules which are important and relevant to the project activities are stated below: • Extraction, collection, and / or removal of minor minerals by a person from his own land for normal agricultural operations or other bonafide domestic consumptions shall not be construed as quarrying operations. • The government may have restrictions in granting a quarry lease; for an area upto 5 Ha, the permit and lease should be obtained from Tahasildhar, Revenue Department,

1 The IUCN provides Red List of Threatened Species which provides comprehensive information on the global conservation status of plants and animal species. The IUCN Red List is applicable for assessing global risk of extinction for species world over. The objective of the list is to highlight and convey the need for species conservation issues to public, policy makers and researchers 2 CMS also known as Bonn Convention, recognized that states must be the protectors of migratory species that live within or pass through their national jurisdictions, and aim to conserve terrestrial, marine and avian migratory species through out their ranges. Migratory species threatened with extinction are listed on the Appendix I of the Convention. The signatories have to strive towards protecting these species. 3 The convention on Wetlands of International importance ( Ramsar Convention) provides the framework for national action and international cooperation for the conservation and wise use of wetlands and their resources, As per this there are 25 designated wetlands in India, Chilka in Orissa is one among them

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

Govt. of Odisha and above 5 Ha, from the Sub-Collector, and in the case of Forest Lands, it should be from Divisional Forest Officer and for the minor minerals other than those specified in item I(1) of Schedule III, regardless of location, from the Mining Officer and Deputy Director of Mines, Department of Steel & Mines. • Chapter II section 14 sub. Section 8 states the conditions of quarry lease; it states that the lease shall not carry on or be allowed to be carried out on , any quarrying operations at any point with in a distance of: (a). One hundred meters from any railway line, national highway, state highway or any reservoir; or (b) with in a distance of 50 meters from any tank, canal, road (other than National or State highways) except under and under in accordance with the permission of the Collector. • Section 21 and 23 states lessee shall ensure major erosion and observe all such environmental safeguards as provided in the act and in case of granite quarry, proper reclamation should be done with plantation. • It also states if the land leased out is a private land, the lessee shall pay a reasonable compensation, as agreed upon between the lessee and the owner of the land. • It also states that the depth of quarry below the surface shall not exceed six meters. C. CLEARANCES REQUI RED FOR THE SUBPROJECT 51. After reviewing the various applicable environmental acts and statutes, as applicable to Government of India, Govt. of Odisha and ADB some of the clearances that are to be obtained by SIO / Contractor are: i. Permission from State Forest Department - In the sections of the canal where it passes through the reserved forest areas, SIO/ DoWR shall obtain necessary permission for undertaking renovation / repair of the canals before initiating the civil works and to the possible extent tree cutting shall be avoided, if any trees need to be cut it shall be done after taking permission. ii. Consent from Odisha State Pollution Control Board - All the construction contractors should obtain consent under the water and air act from Odisha State pollution control board before commencement of construction work for the plant and machinery (Hot Mix, WMM, Batching, Crusher, Diesel Generator greater than 15 KVA) they establish for the projector if they are procuring from the vendor, the contractor should ensure that the vendors has the requisite consents from the State Pollution Control Board of Odisha. The list of crushers whose consents has been given by OSPCB, Keonjhar as on September, 2011 is enclosed as Annexure 2. iii. Permissions from Department of Mines and Geology : a) Contractor would obtain permission for transporting the soil from the Department of Mines and Geology or local bodies as applicable, along with the mutual agreement with the land owner in case of private lands. b) Contractor would obtain permission for extracting boulders before quarrying; if the extraction of the boulder is being procured from the existing quarry/supplier, it shall be ensured that, the requisite license/ lease has been obtained from the concerned Authority. c) Contractor would obtain permission for extracting sand before quarrying ; if the extraction of boulder is being procured from the existing quarry/supplier, it shall be ensured that the requisite license/ lease has been obtained from the concerned Authority. iv. Permission from Commissioner of Explosives - If the Contractor stores diesel or stores blasting materials he has to obtain permission or if procuring or executing through vendors he must ensure that the vendor has obtained permission. v. Permission from District Health Officer - Contractor would obtain permission for establishing labour camps. vi. Pollution under Control Certificates - Vehicles and machineries engaged in the construction of the project will comply with the Motors Vehicle act and will be required to obtain pollution under control certificate.

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

3. DESCRI PTI ON OF THE PROJECT 3.1 Background

52. The Kanjhari Irrigation sub-project is a medium category irrigation scheme in Baitarani Basin with an earthen dam and distribution (canals) system. It has been constructed across the river Kanjhari, a tributary of the Baitarani Basin near revenue village Chakka of Keonjhargarh Tahasil, Keonjhar District. The Kanjhari subproject was started under World Bank assistance in the year 1978-79 and completed in the year 1990-91. The administrative approval of the project was given for an amount of Rs 737.77 Lakhs vide No Irr. 1PP-2/79-35916 Dt 24.10.79 of Irrigation and Power Department, Government of Odisha, , initially, but the revised cost of the project increased to Rs 3319.20 Lakhs. Since 1991, the project has been providing irrigation to three tribal and backward blocks of the Keonjhar District, i.e. Ghatagaon, Keonjhar and Patna. At present, the dam is providing irrigation to 9,740 Ha during Khariff & 2800 Ha during Rabi (DPR Nov. 2011) in Keonjhar, Ghatgaon & Patna Tahasil under the ayacut area of the Project.

53. The Kanjhari river originates in the hills of Gonasika and flows in the north –east and meets Baitarani in the south of Udayapur. It is 56 Km in length and covers important villages like Ramachandrapur, Raghunathpur and Poipani in its course. The Kanjhari dam lies between latitude – 210.35’.394” N to 210.36’.048” & longitude 850.43’.470” to 850.43’.421”E and falls in Survey of India Topo Sheet reference No.73G/10, 1: 50,000 scale), the location map is shown as Figure 2. The scheme falls under the North Central Plateau agro-climatic zone of Odisha and Agro –ecoregion 12 of agro-ecological region of India characterized by hot sub humid eco-regions with red and lateritic soils (Reference : J2 C3/4 of Agro-Ecological Regions of India, NBSS Publ. 24). The Keonjhar district is surrounded by the Singhbhum district of Jharkhand in the North, Jajpur in the South, and Sundargarh in the West and Mayurbhanj and in the East. The National Highway-215 passing through Keonjhargarh bi-sects the district into two similar natural regions. To the East of this Highway are the planes of and a portion of Sadar Sub-division. To the West is a range of lofty hills which contains some of the highest peaks of Odisha namely Gandhamardan (3477 ft.), Mankadnacha (3639 ft.), Gonasika (3219 ft.) and Thakurani (3003 ft.). 54. The Dam is located 18 Km away from Keonjhar district headquarters. The Sub-division office at Kanjhari is 0.5 Km from the dam site and the division office at Anandapur is 68 Km away. The Kanjhari dam and canal system is shown in satellite imagery in Figure. 2

Figure 2

IEE & PC Kanjhari 4 August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

3.2 Deficiencies in the existing irrigation system 55. Irrigation water is an important factor influencing agriculture production. The efficiency of irrigation is largely governed by reliable water supply and the efficient functioning of irrigation subproject was intimately concerned with agricultural productivity and benefits. These deficiencies may be broadly grouped under four important categories viz. engineering and agronomical Engineering related • The canal and canal structures of the project were constructed more than 23 years ago require modifications. • The conveyance capacities of the canals have been decreased in some cases due to silting or slipping of the banks, resulting in increased bed levels hindering the design flow of the canal • Some structures in the Canal system are in a bad state and require repair, and some structures need reconstruction after dismantling. • The heavy transmission loss in canals is to be controlled, by bringing the canal section, bed level; bank slopes etc., to design section and by lining the canal system at selected vulnerable places. • No flow measurement except at the reservoir. • Repair of some bridges and need for additional bridges. • Need for outlets, screw gear shuttering arrangements on every channel. • With the modifications in the canal system, such as lining of the canal in identified reaches, the repair and remodelling of the existing canal structures and bringing the canal section to designed section, the losses will be minimized and the carrying capacity and efficiency of the canal system shall improve, so that the irrigation requirements of the command can be easily and smoothly supplied. Agronomical • Poor water use efficiency has resulted in poor equity of distribution. • Optimum utilization of the advanced technology in agriculture can only result in increased production. The basic pre-requisite is that required quantity of water for crops is to be ensured at a recommended frequency of supply. This is not possible now with the present poor irrigation infrastructure.

3.3 Environmental Category of the project

56. This sub-project is an existing medium irrigation project, does not have any major environmentally sensitive issues within the existing project area. No wild life sanctuaries, eco-sensitive zones, protected monuments, endangered or exotic species of plants are present in the region, while endangered species like elephants are present in the forests of the area. Since the project components include mainly renovation work, with no extension and widening of canal system, the impact on natural resources is negligible, temporary and mitigable, hence, this sub- project can be classified as “Category B” as per the Environmental Guidelines for Asian Development Bank’s Safeguard Policy Statement, 2009 This project is of a similar nature to the sub-projects of the PPTA and CTA which were prepared earlier. 3.4 Scope of Work 57. The difficulties inherent in operating and maintaining the existing system, coupled with no major rehabilitation or upgrading since original construction, has resulted in siltation of canals, slipping of banks, damage of structures requiring repair and reconstruction. Due to the increasing population and increased habitation need for additional bridges and outlets are arising. So rehabilitation of Kanjhari irrigation system is essential to reduce the conveyance losses and transmission loss in the canal and facilitate irrigation for people of Ghatagaon, Keonjhar and Patna blocks of Keonjhar district.

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

3.5 Description of Subproject Components a. Reservoir, Dam and Spillway 58. The dam consists of a homogeneous rolled fill earth dam of 1245 M length, 29.50 M height, with a central masonry ogee crested chute spillway of length 111.50 M. The crest level of the spillway is 402.50 M, fitted with 7 Nos of radial gates of size 12 M x 6 M, with a flood discharge capacity of 2286 cumecs. The entire command area is irrigated over both sides of the canal. Originally, the project was approved for irrigating 9,740 Ha of CCA through its canal system in Keonjhar, Patna and Ghatgaon Tahasil. At present, it is catering to the 7,600 ha of irrigation fully, and 2140 ha partially (as per the DPR Kanjhari, Nov.2011). The salient features of the Kanjhari sub- project are mentioned in Table 3.

Table 3 Basic Features of Kanjhari sub project

S.No General Features 1 Type of sub-project Medium irrigation system 2 River basin Baitarani Basin 3 District Keonjhar, Odisha 4 Name of river Kanjhari Tribute of Baitarani 5 Latitude 210.35’.394” N to 210.36’.048” N 6 Longitude 850.43’.470”Eto 850.43’.421”E 7 Location of reservoir Chaka, Tahasil- Keonjhargarh 8 Catchment area 358.00 Sq.Km 9 Command area 9,740 Ha 10 Number of PPs 19 11 No. Of Villages Served 87 Reservoir Data 1 Full Reservoir Level ( F.R.L) 408.50 m 2 M.W.L ( Original) 409.10 m 3 Dam Top level 411.50 m 4 Dead Storage Level ( D.S.L) 398.00 m 5 Gross Storage Capacity at FRL 4051.66 Ham 6 Dead Storage capacity at DSL 600.00 Ham 7 Live Storage Capacity at FRL 3451.66 Ham 8 Area of Submergence at FRL 515.40 Ha 9 Area at Submergence at DSL 10 Area at Submergence at MWL 516.40 Ha. Spillway 1 Type of spillway Centrally situated ogee type with radial crest gates

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

2 Length of Spillway 111.50 m 3 Crest Level of spillway RL 402.50 m 4 Discharge capacity of FRL 2286.00 Cumec. 5 No. of radial gates 7 No. of gates of size 12.00 m x 6.00 m

59. The earthen dam is of homogenous rolled earth filled type, 1245.00 m in length and 29.50 m in height from the deepest bed level of river. The overall condition of the dam is good. The ogee shaped gravity type spillway has 7 no’s of Radial Gates to discharge 2286 cumecs of flood water. All the 7 gates are in good condition and operational. The gates of both the Left and Right Head Regulators of the Left and Right Main Canals are in good condition and regulate the flow perfectly.

60. With its live storage capacity of 3451.66 Ham, Kanjhari is a “Medium” category reservoir. Design flood flows were based on the “Standard Project Flood”. The recommended spillway design flood increased from 600 Ham to 4051.66 Ham. With all seven gates open, the revised design flood of 2286 m3/s passes with no increase in the design MWL of 408.5 m. Given the 3.0 m available freeboard this is considered acceptable. The maximum observed spillway discharge was approximately 1700 m3/s on 22nd September, 2011, which resulted in damage of wing wall and temporary MS Bridge and approach road (Source: SIO Kanjhari). The flood routing study of Kanjhari Irrigation Project was carried out, but with the revised designed flood of 2286 Cumecs. It was observed that a maximum level of 408.50 m was attained when all the gates are in operating stage. As the TBL is 411.50 m, it is still available above maximum water level. Moreover, a 0.86 m high parapet wall was also provided over the dam and strengthening in the stilling basin has been carried out for the revised flood. The stage storage rating curve of the Kanjari dam is shown below in Table 4. Table 4 Showing Reservoir storage

Elevation 398 399 400 401 402 403 404 406 407 408 408.5 Storage 600 780 1020 1280 1560 1860 2200 2960 3360 3820 4051.66

(Note: Elevation in mts and Storage in Ha.m)

b. Dam: 61. The earthen dam is of Homogenous rolled earth filled type having 1245.00 m in length and 29.50 m in height from the deepest bed level of river. The overall condition of the dam is good; no major repair is proposed under the subproject except repair of horizontal and vertical drains and relaying of dam top road. c. Spillway & Gates: 62. The ogee shaped gravity type spillway has 7 No’s of Radial Gates to discharge 2286 Cumecs of flood water. All the 7 No of gates are in good condition and operational also no repair is proposed under the subproject. The side walls of spill way channel are in damaged condition which needs reconstruction. These works are not being considered under ADB works and will be undertaken by grants of DoWR. d. Head Regulators: 63. The gates of both Left & Right Head Regulators of Left & Right Main Canals are in good condition regulating the flow perfectly, they do not require any repair. e. Distributary System General Features 64. The distribution system consists of two main canals (left and right), 1 No Distributary, 13 nos Minors and 47 nos of Sub-Minors. The total length of the distribution system,

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

including the Left Main Canal and Right Main Canal is 176.252 Km. The right and left distribution system is shown as a schematic diagram (Figure 3 and Figure 4). The basic features of the canal system are presented in Table 5.

Table 5 Basic Features of Canal system of Kanjhari sub project

Canal System

Head Regulator LHR RHR Design Discharge 5.74 Cumecs 6.75 Cumecs Sill level 396.50 m 396.50 m Size of vent 1.5 x 2m 1.5 x 2 m No. of gates 1 1 Length of canal 21.100 Km 15.100 Km Length of Minor / Sub-minors ( 176.252 Km including left and right canal)

(Source: Salient Features, DPR of Kanjhari sub –project.)

Figure - 3

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

Figure 4

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

f. Classification of Canals under OIIAWMIP 65. Classification of canals in accordance to discharge is necessary because: (i) the works aqnd O&M of main, branch & distributary canals will remain the responsibility of the DoWR; While (ii) O &M of minors and sub-minor system will become responsibility of the PPs in accordance with the PIM Act, 2002 and Rules, 2003. Canal classification adopted under the OIIAWMIP is in Table 6. Table 6 Showing Canal Categorization

No Name of Canal Category of Discharge Typical Command O&M Canal (m3/ s) Area (ha) Responsibility Main System Infrastructure: O & M DoWR 1 Varies: Main/ Branch/ Main Canal/ >10 15,000 to 40,000 DoWR ( Appex and Distributary Branch Canal Distributary Level PPs 2 Distributary 1.0 - 10.0 1,500 to 15,000 Minor System Infrastructure: O & M (WUAs) 3 Distributary/ Minor/ Sub- Minor 0.2 – 1.0 250 to 1,500 PP Irrigator Group minor/ Water courses 4 Sub-minor/ 0.04 – 0.20 40 - 250 (Chak) Water Course On- farm System Infrastructure: O &M by PP ( Irrigator Group) ( Field system only to be developed if desired by PP for warabundi) 5 CAD / Field Channels Field Channels 0.030-0.040 30 – 40 ( Chak / PP Irrigator Group Sub- Chak 6 Lateral 0.010 – 0.030 2 to 8 ( Sub- Chak Farmers Channel 66. In the sub-project as per the above classification it has 8 distributaries – (left and right main canal is considered as Main distributaries, one branch distribuary ( Dhanurjyapur), Gambaria minor, Padampur minor, Brundabanpur minor, Golfulla minor and Tail minor), 11 minors and 39 sub-minors. g. Land use and Right of Way (ROW) of the canal system 67. The dam is surrounded by forest, while the left canal system in the initial reach pass through the reserved forest4, protected forest5, and village forest6 and passes through mostly agricultural lands, waste lands like rocky outcrops or uncultivable waste lands, and small local nallas and a very small portion of the left canal and Padampur minor of the left canal passes through the elephant transit path at Padmakesarpur R.F.

4 Reserved forest is an area notified under the provisions of Indian Forest Act or the State Forest Acts, with a full degree of protection. In Reserved forest all activities are prohibited unless permitted by a government notification. 5 Protected Forest is an area notified under the provisions of Indian Forest Act or the State Forest Acts, with a limited degree of protection. In protected forests all activities are permitted unless prohibited specially through a notification. Protected Forest – meaning of – Land has to be one which is not included in a reserved forest – In case of unreserved forest, a notification in terms of Sec. 34 has to be issued, declaring the applicability of the Chapter –IV of the Act: 1992 (II) Orissa Land Rights 185. 6 Village Forest is an area notified by State Government constituting any land at their disposal to be a village forest for the benefit of any village community or group of village communities, and may in the like manner vary or cancel such notification. It states land at the disposal of government include all unoccupied land, all temporarily occupied or occupied without permission whether assessed or un assessed, all communal forests but does not include land recorded in the name of any private person or institution in the record of rights in force which is prepared and maintained or is deemed to be prepared and maintained under the Orissa Survey and Settlement Act, 1958.

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

68. While the right main canal also originates in the reserved forest, protected forest and village forests and passes through mostly crop and waste land like rocky outcrops or unculturable waste lands, local nallas and also from Poipani R.F. 69. The sub project doesn’t require additional land as existing right of way is sufficient for the resectioning, the route of the canal system passes through reserved forest is around 11 .720 Km The route of existing canal system passing through different forest areas is presented in Table 7, Table 8 and Table 9. Table 7 Showing Kanjhari Canal System Passing Reserved Forest - Details

RD (Canal / Length in m S.No Canal name Forest Type Site Location) in m Start End 1 Left Main Canal 0 200 200 R.F Raghunathpur

2 Left Main Canal 6600 6800 200 do 3 Left Main Canal 12500 13300 800 R.F Padmakesharpur 4 Patadhanurjaypur sub-minor 0 200 200 R.F Padmakesharpur 5 Patadhanurjaypu sub-minor 800 1470 670 R.F Padmakesharpur 6 Purunia sub-minor 400 2800 2400 R.F Padmakesharpur 7 Kantiapada sub-minor 1100 1400 300 R.F Padmakesharpur 8 Padampur minor 3100 4100 1000 R.F Padmakesharpur 9 Right Main Canal 1800 2000 200 Pipilia RF 10 Right Main Canal 6800 8700 1900 Poipani RF 11 Right Main Canal 14100 14500 400 Barigoan RF 12 Kamalabahali 2900 3700 800 Jaganathpur R.F 13 Tail minor 650 1800 1150 Patna R.F 14 Jamunaposi minor 2400 2700 300 Patna RF 15 Dhanunjoypore disty 4300 4800 500 Patna RF 16 Golaphula minor 500 1000 500 Patna RF 17 Brundabanpur Sub-minor 1900 2100 200 Patna RF Total Length 11720 ( Source : SI O staff)

70. The route of the existing canal system or existing right of way passing through protected forest is around 3.025 Km and the details are as : Table 8 Showing Kanjhari Canal System Passing through Protected Forest

S.No Canal name RD (Canal / Site Length Acquired Land ROW Location)in m in m width available in m Start End 1 Left Main Canal 2530 2570 040 50 2 Left Main Canal 3600 3710 110 60 3 Left Main Canal 4555 4600 045 50 4 Left Main Canal 4850 4940 090 55 5 Left Main Canal 4955 5015 060 55 6 Left Main Canal 5460 5550 090 40

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

7 Left Main Canal 5750 6070 320 40 8 Left Main Canal 6140 6145 005 40 9 Left Main Canal 6210 6295 085 40 10 Left Main Canal 6445 6755 310 70 11 Left Main Canal 6815 6845 030 70 12 Left Main Canal 8085 8165 080 50 13 Gambharia minor 2120 2370 250 20 14 Right Main Canal 3990 4150 160 55 15 Tail minor 160 520 360 20 16 Tail minor 520 700 180 60 17 Tail minor 720 780 060 60 18 Tail minor 780 1070 290 25 19 Tail minor 1105 1185 080 20 20 Tail minor 3800 3910 110 30 21 Tail minor 6950 6965 015 20 22 Jamunaposi minor 2100 2305 205 40 23 Dhanurjoypur Disty 3420 3470 050 40 Total Length 3025 ( Source : SI O staff)

71. The route of the existing canal system or existing right of way passing though village forest is around 3.670 Km and the acquired land details are as:

Table 9 Showing Kanjhari Canal System Passing Village Forest - Details

S.No Canal name RD (Canal / Site Length in Acquired Land ROW Location) in m m width available in m Start End 1 Left Main Canal 6355 6445 090 70 2 Left Main Canal 8385 8695 310 50 3 Left Main Canal 13648 13805 157 45 4 Left Main Canal 16945 17110 165 40 5 Left Main Canal 17640 17780 140 65 6 Left Main Canal 17790 18270 480 70 7 Left Main Canal 18740 18900 160 50 8 Left Main Canal 19615 19670 055 50 9 Dumuria minor 1200 1248 048 20 10 Dumuria minor 2010 2070 060 20 11 Khadiadiha minor 1200 1460 260 15 12 Gambharia minor 3800 3825 025 25 13 Gambharia minor 4170 4220 050 20 14 Padmapur minor 3220 3425 205 30 15 Gambharia minor 7370 7400 030 20 16 Gambharia minor 7435 7465 030 20 17 Right Main Canal 500 800 300 50 18 Right Main Canal 1220 1410 190 65 19 Right Main Canal 5280 5360 080 50 20 Right Main Canal 5360 5370 010 50 21 Right Main Canal 6950 7000 010 50 22 Right Main Canal 12930 13060 130 60 23 Poipani minor 1590 `1740 150 20 24 Kamalabahali minor 2685 2780 095 20 25 Kamalabahali minor 4850 4960 110 15 26 Kathabari minor 1390 1525 135 20

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

27 Tail minor 1640 1735 095 55 28 Brundanpur minor 3390 3450 060 30 29 Brundanpur minor 1470 1510 040 30 Total Length 3670 ( Source : SI O staff)

72. The available acquired land in the main canal (left and right) i.e. Right of Way is ranging from 40 m to 70 m both the sides, in the minors its around 20 to 30 m both sides and in the sub-minors its around 12 to 20 m both the sides. No additional land acquisition is required. Resectioning of the canals has been proposed under this sub- project, for the left and right main canal the L.S and D.S has been approved by the Chief Construction Engineer, Anandapur barrage project, Salpada on 1st July 2011( As per preliminary detailed estimate for Kanjhari Oct. 2011). The typical cross section of the main canal at RD13.890 Km is enclosed in Figure 5. 73.

Figure -5

h. Left and Right Main Canal Structures 74. The distribution system consists of two main canals ( left and right),the left canal is unlined with a full discharge of 5.74 m3/s, with 6 Nos of minors and 5 Nos of sub- minor off-taking canals and 40 direct outlets. The right main canal is unlined with a fully supply of 6.75 m3/s, there are 7 off-taking canals (one distributary, four minors and two sub-minors) and 20 direct out lets. The number of different structures present in the left and right main canals as per inventory, the structures that are going to be repaired / renovated and new structures that are going to be constructed are shown in Table 10. Table 10 Showing the Structures of Left and Right Main Canal

I tem Structure LMC RMC No Inventory Repair/ New Inventory Repair/ New Renovation Renovation 1 Head Regulators 13 11 0 8 7 0 2 Cross Regulator 5 0 0 3 0 0 3 Escape 1 0 0 1 0 0 4 Fall 2 0 0 0 0 0 5 Aqueduct 5 4 0 3 2 0 6 Canal syphon 0 0 0 0 0 0 7 Drainage syphon 26 0 0 20 0 0 8 Bridges (VRB) 16 10 3 10 9 2 9 Outlet 40 40 0 20 20 3

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

(i)Head Regulators 75. The left main canal has 13 head regulators at. Out of these 11 RD (0.35; 1.25; 2.30; 3.80; 4.00; 8.20;11.40;17.80;19.80; 21.10; and 21.10 Km) are proposed in the preliminary estimate for repair. In the right main canal there 8 no.s of head regulator out of which 7(RD 6.30; 8.94; 9.90; 10.42; 14.68; 15.06; and 15.10 Km) are proposed for repair. Repairs like cutoff, shutter gear box repair and dry stone packing near side embankments. (ii)Cross Regulators 76. The left main canal has 5 cross regulators RD (1.38; 3.92; 8.31; 11.70; and 17.80 Km) and there are three cross regulators in the right main canal RD (10.66; 15.10 and 15.06 Km) these are in good condition and doesn’t require any repair. (iii)Escape 77. There is one escape in the left at RD (16.70 Km) and right main canal at RD ( 8.50 Km) as these are in good condition doesn’t require any repair. (iv)Fall 78. There are two falls in the left main canal at RD 11.70 and 16.64 Km these are in good condition doesn’t require repair. (V). Aqueducts 79. There are 5 number of aqueducts out which four have been proposed for repair RD 2.485; 12.23; 13.40 and 14.96 Km. In the right main canal there are three aqueducts out of which two are proposed for repair at RD 1.10 and 11.99 Km. (vi)Drainage Syphon 80. There are 26 number of drainage syphon in the left main canal and 20 numbers in the right main canal all these are in good condition. (vii)Village Road Bridges 81. There are 16 number of VRBs in the left main canal out of which 10 are proposed for repair ( RD 1.65; 3.92; 4.60; 5.40; 9.54; 10.76; 14.15; 17.70; 19.70; and 21.00 Km), in addition three new bridges are proposed at RD 0.80; 13.10; and 15.60 to facilitate easy movement of people. The right main canal 10 VRBs out of which 9 number have been proposed for repair at RD 0.13; 3.40; 4.10; 4.70; 6.30; 8.97; 10.01; 12.70; and 13.35 Km and two new bridges at RD 2.48 and 11.60 Km. (viii) Outlets 82. The left main canal has 40 outlets and all these are going to be repaired and in the right main canal 20 outlets are there and all these are going to be repaired in addition three new out lets are proposed at RD 5.00; 12.80; and 13.36 Km to meets the demands of the people. (ix) Distribution system structures 83. The other distribution system structures are 1 No Distributary, 11 nos Minors and 45 nos of Sub-Minors (not as per OIIAWMIP canal classification). The structures present in the distribution system that are proposed for repair and renovation are presented in Table 11.

IEE & PC Kanjhari 4 August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

Table 11 Showing Structures of Distributaries, Minors and Sub-minors

I tem Structure Left and Right Distributary, Minors and sub- No minors I nventory Repair/ Renovation New Head Regulators 42 15 0 Cross Regulator 0 0 0 Escape 0 0 0 Fall 371 85 0 Aqueduct 5 0 0 Canal syphon 102 0 0 Drainage syphon 6 0 0 Bridges (VRB) 102 39 0 Outlet 472 219 0

i. Earth work and Turfing 84. Earth work in the left and right main canals, distributaries, minors and sub-minors would be carried out for resection of the canals. Most of the canal sections have eroded over period resulting in under section due to rain cuts and failure of slopes in many places; hence it is necessary to restore the canal banks to its design section. This involves filling of the earth material, the approx. quantities required in the left and right main canal is around 1,74,781 cum and for distributaries, minors and sub- minors it requires approx. 135.27 cum. In addition approximately 65481 cum of earth is also required near the structures. 85. The canal and structure are very old and do not function properly. In many places, the Canal section has gone out of form. Widening of the canal section has resulted in a reduction of velocity of flow, which causes silt deposit in bed, and formation dunes that bar the bed. This ultimately results in poor performance of canal supply. The canals have been constructed with locally available soils. The embankments have not been properly maintained in many places. All these have resulted in heavy seepage loss and the tail reaches were found to be deprived of water most of the time. So in order to bring back the canal to its design bed level requires desilting and cutting of canal bed. The approximate quantity of cutting would be around 82,566 cum in the left and right main canal and approx. 24,576 cum in the distributaries, minors and sub-minors. In addition the approximate quantity of cutting material generated at structures is around 2229 cum. The 40 % of this quantity will be reused in the filling material. 86. Provision for compaction of the main canals has been built under the project by Powered Road Roller (PRR)/ Vibratory Roller and the ordinary compaction (HRR) to be done in distributaries, minor and sub-minors. 87. To protect the canal from erosion in the completed earth sections of the canals a provision for turfing has been made. j. Canal Lining and Guard wall 88. In the vulnerable reaches of the canals and upstream and downstream of structure and filling and cutting zones of the main canal, a provision for lining approx. 5700m and for distributaries minors and sub-minors 5620 m has been proposed in the preliminary estimate. Approx. 3200m of guard wall construction is built in the project to restrict the seepage for the main canal only.

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

k. Service Road 89. A provision for improvement of service bank of left main canal, right main canal and Gambharia minor is built in to the sub-project for a length of 42 Km. Improvement of dam top road of approx. length 1.134 m is also proposed under the sub-project. l. Drilling Tube wells 90. A provision for drilling 82 number of tube wells along the entire length of left and right main canal, distributaries, minors and sub-minors was kept to provide water during canal closure period. m. Construction Materials 91. The below are the list of provisional construction materials that the Contractor may need to procure for the sub-project. The preliminary estimate provides a provision to approximate carriage and conveyance of materials i.e. lead distance involved are given below and the map showing the locations are shown in Annexure -3. • Cement may be procured from Keonjhar the approx. average distance is 35Km. • Steel may be procured from Bhubaneswar approx. average distance is 220 Km • Steel (shuttering and centering) may be procured from a approx. distance of 170 Km i..e . • Granite and other Stone products may be procured from the quarry at Dimbo the approx. average distance is around 37 Km. In addition the tentative list of approved crushers ( State Pollution Control Board )available within the district as on September 2011 is enclosed as Annexure 2 • Sand may be procured from a distance of approx. 60 Km from River Baitarini – • Gravel may be procured from distance of approx. 29 Km from Gopalpur • R.C.C Hume Pipe may be procured from approx. distance of 40Km from Drupada near Keonjhar town. • Earth generated from cutting shall be utilized in filling. The remaining earth quantity shall be procured by the contractor from private lands as per the procurement procedures; the estimate has a provision for hiring earth from private lands. Borrow areas in forest areas shall be avoided and borrow areas shall be identified prior to implementation at proposal and after award of contract. However keeping in view of the requirements of the IEE report some potential farmers (24) who are willing to give earth from their own lands have been tentatively identified by the PPs covering an area of approx.20 Ha which can be utilized by the contractor for borrow areas, the potential list of farmers / PPs enclosed as Annexure 4. These potential locations shall be verified for the suitability of the material by the SIO staff and the list of potential people will be provided to the Contractor. As per the contractual conditions an agreement with the land owner will be reached by the contractor and he will also ensure to take the necessary permission for operating these borrow areas. The necessary royalty would be deducted by the SIO staff from the Contractor. Contractor would try to procure earth within a lead of 5 Km of the canal system in small quantities.

n. Disposal of Debris &Spoil 92. The material generated from dismantling old structures would be reused to the possible extent. Any materials like wood or iron would be taken in to the dead stock of water resources department and auctioned by the competent authority.

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

93. The generated cutting material suitable for the filling would be utilized to the possible extent. The remaining material generated (small quantity) may be tested for suitability and necessary material testing shall be carried out and unsuitable material shall be utilized in the spoil banks of the existing main canals and in the low lying sections of the canal bank with in the available ROW after toe line, a provision for turfing the spoil banks to avoid the erosion is suggested. However, if any additional material is generated it would be disposed by identifying a suitable places like old borrow areas, quarry sites and low lying govt. land by taking appropriate permission from the SIO and competent authority. The silt shall be tested for heavy metals and pesticide residues also before disposal and some quantities can be distributed to the adjacent farmers by involving PP. o. Drainage System 94. The natural drainage in the command area is toward the Kanjhari river which bisects the scheme. There are several ephemeral drains crossed by the left and right bank main canals as they follow the contour. No field drains or drainage channels were ever built and there is no drainage congestion in the area. p. Access Roads 95. The subproject is well connected with the road net work. There is one road that connects to NH 215 which is in good condition provides access to the project site. The other main access road in the command area is Dhenkikote to Keonjhar via Patna which is also in good condition. In addition several villages roads are in good condition and connects the sub-project. In addition the canal embanKment serves also as a service road for the villagers of the command area. q. Elephant transit paths 96. The forest department has identified the path where movement of elephant is taking place in Keonjhar district called as elephant transit path which happens to pass through certain sections of the catchment area and a small portion of the left main canal tail end portion (RD 21.000km) and Padampur minor(RD 3.100 to 4.100Km) passes through that elephant transit path. The elephants move from one forest to another. The elephant path at Kanjhari sub-project is part of migratory elephant path in search of food and water passing through Sarindha, Jharkhand State, , Nayagad, Soyakali, Keonjhar, Gopalpur, Kanjhari and Patna during harvesting period mainly (Nov to Jan & May to June mid). The elephant transit path passing through sub-project is not one of the fourteen paths the Government of Odisha proposed under Corridor Development Program (Harsha Bardhan Udgata 2011). The top sheet showing the elephant transit path is attached as Annexure 5. r. Plantation 97. To increase the aesthetic value of the area and also to compensate any tree loss that may arise due to unavoidable tree cutting, the subproject is built with a provision for 1000 trees plantation in the area i.e. along the canal system. 3.6 I mplementation Arrangement 98. Detailed Survey, Design and estimates for the sub-project shall outsourced and will be carried out by a Consulting Firm through PMU in consultation with SIO staff. 99. Procurement of civil works for the sub-project related to main canal, distributaries and minors shall be divided into different contract packages and tendered. Water Resources Department through PMU in consultation with the concerned C.E’s/ S.E/E.Es as per the provisions of Odisha Public Works Department(OPWD) code and in line with ADBs procurement policy shall call for tenders and through national competitive bidding, different contractors shall be selected and they will be executing the civil works under the supervision of respective Subproject Implementing Officers (SIOs).

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

100. For sub-minors execution of civil work shall be carried out by different Water Users Associations (PPs) of the respective subproject through an agreement between SIO and SIO / Executive Engineer of the respective sub-project. 3.7 Onfarm Development Works (OFD) 101. The onfarm development works include watercourses, field channels and field drains. In the traditional system of irrigation the responsibility of distribution system ends at outlet. So distribution of water beyond the outlets remains the responsibility of the farmers. OFD works under Kanjhari sub-project command area had been contemplated to be taken up separately insteps by Command Area Development (CAD) wing of Water Resources Department separately in consultation with the farmers of the concerned WUAs. The CAD water management activities will be funded by the OSG through the centrally sponsored program (CSP) for CAD works without availing OIIAWMIP fundsmain canal bank are proposed. 3.8 Expected I mprovements

i) Improving the crop yield. ii) Increasing the intensity of Rabi crop. iii) Ensuring equitable distribution of water from head to tail and the redesign of outlets and regulators. iv) Rationalization of outlets, so that disparity between sizes of chaks are brought down and kept within a reasonable size, varying between 12 to 25 Ha. v) Renovation of outlets, so that each outlet draws only the proportionate share. Outlets will be capable of drawing full discharge under half supply condition in the parent channel, the primary reason for tail enders being deprived of irrigation facilities. vi) Due to the inadequacy of funds, proper maintenance has not been taken up. Lack of maintenance has caused ill distribution of water and reduces the water use efficiency. The renovation and remodeling structures of channels have to be done to make the system efficient. vii) Regulation devices have been tampered, mainly due to the inadequacy of irrigation water to meet the water demand of crops. Along with the system improvement, the regulator devices and outlet capacity are to be redesigned and replaced. viii) Lining has been proposed at places where there is profuse seepage through pervious soil and rock fissures and also of cattle passing; bathing Ghats where the canal banks are more susceptible to failure.

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

4. DESCRI PTI ON OF THE ENVI RONMENT

102. The baseline environment of the project influence area such as climate, physiography, biological and socioeconomic environment of the project influence area has been discussed in this chapter. A. PHYSI CAL ENVI RONMENT 4.1 Physiography and relief 103. The length of the district length from north to south is nearly 145 Km and the average breadth from East to West is about 65 Km, dividing into two widely dissimilar tracts-the lower and the upper Kendujhar. The former is a region of valleys and low lands, while the latter includes mountainous highlands with a general slope from North to South. The highlands, consisting of clusters of rugged crags, afford a safe retreat to its inhabitants in troubled times. The mountaintops appear to be sharp ridged or peaked from the low lands, but in reality, with extensive tablelands on their summits, are fit both for pasture and for tillage. The average elevation in its central part is about 500m. At places, isolated hills rise abruptly from the plains. But most of the areas have a general elevation of over 600m, which forms the watershed of some rivers. 104. The National Highway-215 transient through Keonjhargarh divides the district into two regions; to the east are the planes of Anandapur and a portion of Sadar Sub- division and to the West is a range of lofty hills which contains the highest peaks of Odisha, namely, Gandhamardan (3477 ft.), Mankadnacha (3639 ft.), Gonasika ( 3219 ft.) and Thakurani ( 3003 ft.). 105. The river Baitarani originates from Gonasika Hills and flows to the north near the border of the Singhbhum district of Jharkhand and it again flows East entering Anandapur Sub-division and the district of Bhadrak. 106. The elevation in the project command area varies from 380 to 400 m; the highest contour is 488 m near the dam as per Survey Of India, Toposheet No. F45N10 & F45N14, 1:50,00 scale. The elevation in the region is around 50 m and the slope ranging from 10-20 m / Km as per NATMO District Planning Map series of Kendujhar, Odisha). From the survey data, the bed level from the Mean Sea level for left bank is max 396.55m and minimum is 388.94 m and for the right main canal the max is 396.55m and min is 393.04 m. 4.2 Climate 107. The climate of the district is characterised by an oppressively hot summer with high humidity during March to July, and cold from November to February. Summer generally commences in the month of March. The temperature begins to rise rapidly, attaining the maximum in the month of May. During the summer, the maximum temperature is 38.20 C. The weather becomes more pleasant with the advent of the monsoon in June and remains as such up to the end of October. The temperature in the month of December is lowest, i.e. 11.70 C. Sometimes it even drops down to 70 C. The average annual rainfall is 1534.5 mm. The mean daily maximum and minimum temperature along with relative humidity of Keonjhar is presented in Table 12

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

Table 12 Showing Mean daily Temperature and RH

WEATHER ANALYSI S REPORT Mean daily Mean daily Relative Humidity Month 0830 1730 max temp in °C min. temp in °C ( in IST ) January 25.4 11.7 62 51 February 28.3 14.4 59 43 March 33.2 18.6 51 36 April 36.9 22.7 53 41 May 38.2 24.6 56 42 June 34.2 24.7 70 65 July 29.7 23.1 82 80 August 29.6 23.6 83 81 Septem ber 29.8 22.5 82 81 October 29.2 20.2 77 70 Novem ber 27.0 14.8 64 55 Decem ber 25.1 11.7 63 54 Annual 30.5 19.4 67 58

(Source: kendujhar.nic.in)

4.3 Rainfall 108. Keonjhar average annual rainfall of the district was 1551.17 mm in 2006, which was higher than the normal rainfall, i.e. 1487.7 mm (Source: District Statistical handbook Keonjhar 2007). The monthly normal rainfall along with the number of rainy days for Keonjhar district is presented in Table.13. Rainfall in the State is unevenly distributed both spatially and temporally. The distribution of rain fall is shown as Annual Isohytes in Map Figure 6. The average annual rainfall for the Kanjhari sub project for the period 1979 to 2013 is 1280mm, the highest rainfall recorded at dam site was 2027 mm in the year 2013. The monthly rainfall data for the period 1976 to 2013 is shown in Annexure 6.

Table 13 Keonjhar District Monthly Normal Rainfall along with Rainy Days

S.No Month Rainfall in mm Rainy days 1 January 14.6 0.9 2 February 33.8 2.1 3 March 33.1 2.4 4 April 42.1 2.8 5 May 94.8 5.7 6 June 241.4 11.0 7 July 318.0 15.5 8 August 343.6 16.1 9 September 241.1 12.0 10 October 101.3 5.1 11 November 20.5 1.1 12 December 3.4 0.3 Annual 1487.7 75.0 (Source: Odisha Agricultural Statistics 2009-2010)

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

Figure 6

(Source: State of Environment Report) 109. Kanjhari irrigation dam rainfall data for the period 1979 to 2010 is attached as Annexure 6. The Mean rainfall comes to 1240 mm. 4.4 Humidity 110. The relative humidity is generally high i.e., about 75 percent in the south –west monsoon and post –monsoon months; in other months afternoons are comparatively drier. In the summer, relative humidity varies between 35 to 40%. 4.5 Evaporation 111. The evaporation data of the Khanjari dam for the years 1987 to 2010 is presented in the below Table 14. The evaporation is highest in the month of May, ranging from 48.66 mm in the year 2010, to 109.48 mm in the year 1991. The average yearly evaporation for the last 23 years comes to 583.9 mm.

Table 14 Showing Monthly Evaporation Data for the Kanjhari

Year January February March April May June July August September October November December Total 1987 25.97 21.91 22.46 22.59 21.48 114.41 1988 24.30 48.12 57.44 68.52 79.85 48.86 37.54 30.45 25.24 26.41 26.44 25.23 498.40 1989 28.04 55.75 63.27 65.02 74.42 46.02 34.28 30.76 25.13 25.48 23.81 22.72 494.70 1990 25.35 50.35 52.04 61.23 76.61 46.63 39.74 38.57 34.86 39.15 40.87 39.09 544.49 1991 42.37 83.14 83.04 96.30 109.48 67.23 42.93 37.30 32.98 38.95 40.72 38.28 712.72 1992 40.17 71.76 69.07 74.14 82.98 51.81 40.00 40.36 37.03 36.86 36.05 31.65 611.88 1993 32.34 59.83 57.71 64.89 74.07 45.71 46.70 43.84 37.67 40.50 41.24 37.76 582.26 1994 38.43 74.67 68.36 69.25 70.38 44.19 45.55 42.36 37.06 39.72 41.15 37.23 608.35 1995 38.94 73.74 68.98 68.60 82.80 57.63 47.15 44.30 37.18 40.34 40.65 38.33 638.64 1996 40.69 72.30 67.53 66.43 62.10 38.93 40.90 42.13 37.13 35.98 33.88 31.78 569.78 1997 34.51 66.76 66.79 78.82 93.20 56.45 46.31 43.33 37.62 39.64 40.96 38.65 643.04 1998 41.50 78.85 72.08 73.38 68.81 41.44 39.69 28.91 30.54 39.18 41.68 38.18 594.24

1999 38.77 70.70 63.75 60.31 50.83 35.82 48.55 43.51 37.31 39.63 40.67 39.00 568.85

2000 41.81 74.95 69.98 68.66 65.08 40.80 44.92 36.64 32.18 38.48 38.20 36.03 587.73 2001 39.56 75.72 73.57 83.91 89.47 55.81 45.42 39.90 35.53 40.17 41.02 38.79 658.87

2002 40.85 75.40 67.39 65.46 54.55 34.60 24.16 32.73 37.36 36.20 33.69 31.58 533.97

2003 33.22 63.62 62.80 71.62 80.04 49.18 45.57 42.06 36.72 39.62 40.99 39.31 604.75 2004 42.48 77.16 72.78 73.09 61.95 37.26 45.31 42.48 37.48 39.57 39.98 37.47 607.01

2005 39.63 74.14 66.78 65.72 56.08 34.19 47.78 44.10 36.56 39.55 40.94 39.09 584.56

2006 42.02 77.94 71.11 70.62 63.43 30.81 28.03 43.12 37.62 39.12 38.77 36.63 579.22

2007 39.52 74.50 70.15 70.62 58.98 35.39 39.61 43.59 37.11 38.70 39.80 37.87 585.84 2008 41.37 76.98 83.47 68.71 56.47 34.51 43.17 42.38 35.90 37.37 37.16 37.01 594.50

2009 38.00 69.05 60.64 56.70 49.86 27.17 30.81 40.66 37.50 38.64 37.48 35.30 521.81

2010 37.50 68.25 59.93 54.57 48.66 27.60 26.60 30.96 32.18 39.72 40.64 39.15 505.76

(Source: SI O, Kanjhari Dam)

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

4.6 Wind 112. Winds are mostly light to moderate with some increase in force in the summer and monsoon season. The morning winds are generally from south or south west during the summer and monsoon season and during other seasons north-west, north and north-east. In the afternoons, winter winds are mainly calm and blow from south – east or south. During monsoon season, the winds blow predominantly from the south –east, south and south –west directions. 4.7 Geology 113. The Keonjhar district has distinctive rocks which are some of the oldest rocks in the world, covering an area of 100 sq. Km at Asanpat, i.e. nearly 38,000 million years old. They must date from before peninsular India broke away from Antartica and moved north. The rocks found in Nuasahi in the southern part of Keonjhar are intruded by granites and gneisses which may be equated with singhbhum granites. The Koira – Noamundi group comprising the basal gritty sandstone – quartzite with interbedded conglomerate basic lava and tuff with excelled development of banded iron formation cherts, clay shale, black and banded shale overlies the Singhbhum Granite uncomfortably. The iron formation of Gandhamardhan hill lying west of Kendujhar are associated with quartzites, ferruginous shale, basalt and tuff forms the south –eastern boundary of this group in the district. While the rocks of Kolhan group comprise sandstone conglomerate with purple shale occur as small outliers on the Koira group of rocks with an unconformity at the base. Dolerite dykes intrusive partly into Iron-ore and partly into Koira – Noamundi group form lineal topographical features in the flat granite terrain to the north and east of kendujhar (Source District Gazetteers – Kendujhar). 114. While the geology of the dam site consists of rocks of massive granite and dolerite intrusive, these rocks are exposed as small outcrops on the right bank and as a large exposure on the right edge of the riverbed. The dolerite dykes trending in N-S direction are exposed on the abutment hills and as scattered outcrops on the left bank. A thin dyke of dolerite trending E-W cut across the axis around RD 720 m (Soruce: Kanjhari irrigation project report- 1980). 115. In the dam site, the granite is of biotite – granite in composition with medium to coarse grained at places porphyritic, unfoliated and traversed by E-W and N-S directions. The dolerite exposures are covered with boulders mostly.

4.8 Soils & Drainage 116. Physiographically Odisha State has been divided into seven physiographic regions namely Eastern ghat, Garhjat hills, Dandakaranaya region, Mahanadi basin, Bengal Basin, Utkal basin and Mahanadi delta. 117. While the study area of Keonjhar district falls in the Garhjat hills (including Mayurbanj, Keonjhar, Dhenkanal, , etc) occupying around 26.4 % of the States geographical area. The project area covers Kendhujhar, Patna, and Ghatgaon Tehsils the soils in these tehsils are mainly Balisahi series and Raghubera series. The Balisahi series are of fine mixed, hyperthermic, typic Haplustepts locally known as Balia Chikita Mati. These are gently sloping soils ranging from 3 to 8% with moderate erosion, normal relief. The soils are of granite genesis and moderately well drained and with moderate permeability. The thickness of the solumn ranges from 60 to 85 cm. The texture of a horizon ranges from sandy clay to sandy loam, while the horizon B texture varies from sandy clay loam to silty clay. These soils have a land capability subclass of IIIes and irritability sub-class of 3t. 118. While Ghatgaon block has Raghubra series with fine loamy, mixed hyperthermic, typic Rhodustalfs locally known as Balia Dorasa Mati. These are moderately sloping with 8 to 15% with severe soil erosion and excessive relief. These are of Granite and

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

granite gneiss parent material with well drained and with moderate permeability. The solumn is more than 100 cm thick; a horizon texture varies from sandy loam to sandy clay. B horizon texture varies from sandy clay to sandy clay as per Soil Series of Odisha, NBSS&LUP publication. 4.9 Land Utilization Pattern 119. The different land use along with geographical area is presented in Table 15 for the Keonjhar distrct, as well as for the blocks covered by Kanjhari sub-project. As per the Odisha Agricultural Statistics 2012-2013 published by the Directorate of Agriculture and Food Production, Odisha, the forest area in Keonjhar district is around 37% area covered under trees and grooves is around 1 %, area under permanent pastures and culturable waste is around 3% each, area covered under land put to non-agricultural use is around 9%, area under barren and unculturable land is around 11%, area under current fallow is around 6% and other fallow are absent and area under net sown area is around 30%. The land utilisation pattern is also presented in graph Figure 7.

Table 15 Showing the land utilization pattern in Keonjhar district and project covered blocks

S.No Land Use Keonjhar Keonjhar Patna Block Ghatagoan 2012 -2013 Block 2009 2009 Block 2009 Area in Ha 1 Geographical Area 830000 450.62 416.23 sq.Km 465.76 sq.Km sq.Km 2 Forest Area 310000 4211 4767 9597 3 Misc. Tree & 6000 381 365 367 Grooves 4 Permanent Pastures 20000 1638 1574 1286 5 Culturable waste 26000 5105 3127 4365 6 Land put to non 77000 4378 2564 2158 agricultural use 7 Barren & 93000 1620 3031 3116 Unculturable land 8 Current Fallow 51000 5465 9928 7120 10 Other Fallow 0 1066 1896 2355 11 Net sown Area 247000 21545 14673 16176 (Source: Odisha agricultural statistics 2012-2013 and District Statistical Handbook 2009)

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

4.9 Land Utilization in Kanjhari sub project covered blocks

120. As per the District Statistical Handbook Keonjhar 2009 Published by Directorate of Economics and Statistics, Odisha, the forest area in Keonjhar block is around 9%, area covered under trees and grooves is around 1 %, area under permanent pastures is 4% and area covered under culturable waste is around 11% , area covered under land put to non-agricultural use is around 10%, area under barren and unculturable land is around 4%, area under current fallow is around 12% and other fallow is around 2% and area under net sown area is around 47%. The land utilisation pattern is also presented in graph Figure 8. 121. As per the District Statistical Handbook Keonjhar 2009 Published by Directorate of Economics and Statistics, Odisha, the forest area in Patna block is around 11%, area covered under trees and grooves is around 1 %, area under permanent pastures is 4% and area covered under culturable waste is around 7% , area covered under land put to non-agricultural use is around 6%, area under barren and unculturable land is around 7%, area under current fallow is around 24% and other fallow is around 5% and area under net sown area is around 35%. The land utilisation pattern is also presented in graph Figure 9. 122. As per the District Statistical Handbook Keonjhar 2009 Published by Directorate of Economics and Statistics, Odisha, the forest area in Ghatgoan block is around 20%, area covered under trees and grooves is around 1 %, area under permanent pastures is 3% and area covered under culturable waste is around 9% , area covered under land put to non-agricultural use is around 5%, area under barren and unculturable land is around 7%, area under current fallow is around 15% and other fallow is around 5% and area under net sown area is around 35%. The land utilisation pattern is also presented in graph Figure 10.

IEE & PC Kanjhari 4 August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

4.10 Agriculture and I rrigation

123. The Keonjhar district falls in the North central plateau agro-climatic zone of Odisha. The district is primarily an agricultural district but rich in mineral deposits and has vast deposits of Iron, Manganese and Chrome Ores. Nearly 37 percent of its total area is covered with tracts of dense forests as per Odisha Agricultural Statistics 2009- 2010. But the district, in spite of its immense mineral and forest wealth, still remains economically backward and the yields are moderate to low because of primitive cultivation practices. The Keonjhar district is divided into three agro-climatic zones, while the sub-project area falls in the Sub-mountainous region covering Champua and Jhumpura, Kendujhargarh, Ghatgoan, Patna and Saharpada. The region is less mountainous but hilly with gradual sloppy terrain subject to soil erosion. The valley pockets only have comparatively deeper soil and fertile soils. 124. The irrigation potential in the district under Kharif through major /medium irrigation is approx. 26494 Ha, under minor irrigation is around 21146 Ha and lift irrigation is around 3272 ha as on 2006-2007. While in the project area, i.e. kharif area under major / medium is around 2174 Ha in Ghatagaon block, around 2651Ha in Keonjhar sadar and in Patna block is around 6075 Ha. The area under minor irrigation during kharif for Ghatagaon block is around 2062Ha, in Keonjhar sadar it is 4047 and in Patna block is around 557 Ha. While in the project area i.e rabi area under major / medium is around 1262 Ha in Ghatagaon block, around 1015Ha in Keonjhar sadar and in Patna block is around 1145 Ha. 125. The area under minor irrigation during rabi for Ghatagaon block is around 362 Ha, in Keonjhar sadar it is 349 and in Patna block is nearly absent as per the district statistical hand book of Keonjhar 2007. The Keonjhar district has a cropping intensity during the year 2009-2010 is 149 %, net sown area is around 285000 Ha and gross cropped area is around 426000 Ha. The area under autumn rice in the district is around 22.73 thousand Ha and the paddy yield is around 1510 kg/ ha and the rice yield is around 1012 kg/ ha and the production is 46.92 thousand metric tons and the area under winter rice is 147.12 thousand Ha and the paddy yield is around 2344 kg/ ha and the rice yield is around 11570 kg/ ha and the production is 231.04 thousand metric tons as per the Odisha Agriculture Statistics 2009-2010. 126. The consumption of chemical fertilizers in the country is 128.58 kg/Ha during 2008- 2009 and in the State of Odisha it is around 61.50 kg/ Ha during the same period. While in the Keonjhar district it is 33.96 during 2009-2010. 4.11 Earthquake Zone / Sensitivity

127. The Bureau of Indian Standards has categorised India into 5 seismic zones depending upon the degree of proneness to earthquakes. The Zone I signify a lesser degree, while Zone V is of highest Figure 6.6 order. The northern Figure 11 and southern most parts of Odisha are classified as Zone I and remaining parts of the state are classified under Zone II & Zone III. The entire state of Odisha is in general underlain by a north-

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

eastern extension of the peninsular shield of the Precambrians, which is tectonically a very stable zone. The subproject falls under earthquake risk zone-II (Low damage risk zone) of India. The earth quake zone of Orrisa is in Figure 11. 4.12 Flood

128. On the country, Odisha state is the most chronically flood affected one. The east flowing rivers like Baitarani, Mahanadi, Subarnarekha, Brahmani, and Rushikulya cause floods between June to October, when monsoon become active and due to depression in the Bay of Bengal with heavy precipitation occurring almost every third. 129. A flood routing study of Kanjhari Irrigation Project was carried out, but with the revised designed flood of 2286 Cumecs. It was observed that a maximum level of 408.50 Mt was attained when all the gates are in operating stage. As the TBL is 411.50 m it is still available above maximum water level. Moreover, a 0.86 m high parapet wall has also provided over the dam, and strengthening in stilling basin was carried out for the revised flood. In the Knajhari sub-project area, flooding is not a problem, but the Baitrani basin is partly under the flood prone zone. Table 16 below indicates the flood status of the project area of Odisha.

Table 16 List of Past flood and area damaged by Flood in Odisha

Sr. Year and Rivers Affected Dist./ Area Loss/ Damage Reported No. month under project area Average Average Public Utility Human Livestock 1 1960 Mahanadi, Cuttack, Dhenkanal Not Not Average 6 lakh (August) Brahmani and available available acre of cropped Baitarani area damaged 2 1961 Mahanadi, Cuttack, Dhenkanal Not Not Average 0.48 lakh (Sept) Brahmani and available available acre of cropped Baitarani area damaged 3 1964 Mahanadi, Cuttack, Dhenkanal, Not Not Average 1.35 lakh (July- Aug) Brahmani and available available acre of cropped Baitarani area damaged 4 1971 Mahanadi, Cuttack, Sundergarh 8 75 Average 3.34 lakh (July- Oct.) Brahmani and acre of cropped Baitarani area damaged 5 1974 Mahanadi, Cuttack, Dhenkanal Not Not Average 2.16 lakh (August) Brahmani and available available ha cropped area Baitarani damaged 6 1980 Mahanadi, Cuttack, Dhenkanal 16 3300 Average 0.638 (Sept.) Brahmani and lakh ha. cropped Baitarani area damaged 7 1982 (Aug- Mahanadi Cuttack, Dhenkanal 32 6500 Average 3.0 lakh Sept.) ha. cropped area damaged 8 1984 (June Mahanadi, Cuttack, Dhenkanal 7 0 Average 1 lakh ha. – Sept.) Brahmani and of cropped area Baitarani damaged 9 1985 Mahanadi, Cuttack 3 587 Average 0.33 lakh (Aug- Sept.) Brahmani and ha. of cropped Baitarani area damaged 10 1986 Mahanadi Cuttack, Dhenkanal 3 74 Average 0.24 lakh ha. of cropped area damaged 11 1991 Mahanadi, Cuttack, Dhenkanal 10 229 Average 1.3 lakh (July- Brahmani and ha. of cropped August) Baitarani area damaged 12 1992 (June Mahanadi Cuttack, Dhenkanal 8 250 Average 0.8 lakh – August) ha. of cropped area damaged

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

Sr. Year and Rivers Affected Dist./ Area Loss/ Damage Reported No. month under project area Average Average Public Utility Human Livestock 13 1994 (July- Mahanadi, Cuttack, Jajpur, 10 Average 2.5 lakh September) Brahmani Jagatsinghpur, ha. of cropped , Sundergarh area damaged 14 1995 (May Mahanadi Cuttack, Dhenkanal, 11 Average 3.5 lakh – Jagatsinghpur, Jajpur, ha. of cropped November) Kendrapara area damaged 15 1997 (June Mahanadi Cuttack, Dhenkanal, 10 17 Average 1.8 lakh & August) Jagatsinghpur, Jajpur, ha. of cropped Kendrapara, Sundergarh area damaged 16 1999 (July - Mahanadi, Cuttack, Jagatsinghpur, 4 Average 0.8 lakh August Brahmani, Kendrapara, Jajpur ha. of cropped Baitarani area damaged 17 2001 (July- Mahanadi, Cuttack, Dhenkanal, 25 4537 Average 2 lakh ha. August) Brahmani Jajpur, Jagatsingpur, of cropped area kendrapara, Sundergarh damaged 18 2003 (July Mahanadi, Cuttack, Jajpur, 14 450 Average 0.8 lakh – October) Baitarani Jagatsinghpur, ha. of cropped Kendrapara area damaged 19 2006 (July Mahanadi, Cuttack, Dhenkanal, 15 300 Average 0.6 lakh – August) Brahmani, Jajpur, Jagatsingpur, ha. of cropped Baitarani Kendrapara area damaged 20 2007 (July- 27, 12, 15 districts Aug – Sept) respectively 21 2008( Jun & Subarnarekha, Angul, , Bhadrak, 110 50163 258155 houses Sept) Burhabalang, Boudh, damaged, Baitarani, Bolangir, , 4.45 lakh Ha. Mahanadi, Cuttack, cropped area, Rushikulya, Gajpati, Jagatsinghpur, 0.14 th Ha Vansadhara Jajpur, sandcast, 651 Kendrapara, Khurda, breaches in rivers, Kalahandi, 1276 Keonjhar, Mayurbhanj, breaches in Nuapara, canals. Nayagarh, , Rayagada, Sambalpur, Sonepur - 22 2009( Aug Balasore, Bhadrakh, 59 NA Rs.483.02 Cr of & Sept.) Bolangir, Cuttack, Ganjam, Public utility Jajpur, Kalahandi, damage. Kandhamal, Kendrapara, Koenjhar, Koraput, Mayurbhanj, Nayagarh, Puri, Subarnapur, Sundargarh. 16 Districts 23 2010( Aug.) Kalahandi, Nabarangpur, 14 1454 Crop damage Koraput, Boudh, Rs.2921.2 Rayagada, . Hectare 24 2011( June, Subarnarekha, Angul ,Balasore,Bargarh, 82 1493 Crop damage Aug, Sept) Jalaka, Bhadrakh, Boudh, Cuttack, 260256.52 Mahanadi, Deogarh, Dhenkanal, Hectare Brahamani, Jagatsinghpur, Jajpur, Baitarani, , Kendrapara, Budhabalanga. koenjhar, Khurda, Mayurbhanj, Nayagarh, Nuapada, Puri, Sambalpur, Subarnapur, Sundargarh. Districts 25 2012( Aug. , 3 Crop damage & Nov.) Khandhamal,Nayagarh,Kal 1061.82 Hectare. ahandi & Ganjam. 5 Districts Rs.21386.37 lakh

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

Sr. Year and Rivers Affected Dist./ Area Loss/ Damage Reported No. month under project area Average Average Public Utility Human Livestock Public utility damage 26 2013( June, Baitarani, Kalahandi ,Nabarangpur, 70 Crop damage July, Aug & Budhabalanga, Koraput, Gajapati, 12.80 Lakh Oct) Rusikulya, Rayagada, Malkangiri, Hectare. Subarnarekha Mayurbhanj, Bhadrakh, Rs.21766.87 & Jalaka. Balasore, Koenjhar, Crores Public Jajpur, Deogarh, Puri, utility damage Khordha, Mayurbhanj, Nayagarh, Cuttack, Bolangir & Ganjam. 19 Districts. (Source: Official website of State of Odisha & Office of Special Relief Commissioner , Bhubaneswar) Remark : From the year 1960 to 1992 the districts mentioned in the column No.5 related to undivided 13 districts of the States of Orissa.) 4.13 Water Resources and Surface Quality

130. Water resources are important natural resources of the country. Around 4000 billion Cum meters is obtained from precipitation and snow fall in the country. From the above, about 1869 billion Cum is available in the shape of surface water and replenish able ground water. Out of the above, i.e. 690 billion cubic meters from surface water and 432 billion Cum from ground water can be put to beneficial use (State of Environment Report, Odisha 2006). Odisha is fortunate to have abundant water resources, both surface and ground water, compared to its size and population to the national level. The water resources of Odisha are dependent on rainfall. 131. The rivers of the Keonjhar district emerge from the hilly tracts into the plains with great velocity and are charged with a large volume of water during monsoon season. In summer they become almost dry. The beds of the rivers are usually rocky which render them unfit for navigation. There are a large number of hill streams which form the major water resources of the district. The streams and rivers of the district are Baitrani, Aradei or Ororai, Kanjhari, Seeta, Kukurkara, Kusai, Musal, Samakoi, Machhakandana, Karo etc. The largest of all is the Baitrani in the district. Kanjhari originates in the hills of Gonasika and flows north-easterly and joins Baitrani south of Udayapur. The Kanhari passes through villages like Ramachandrapur, Raghunathpur and Poipani stretching a length of 56 Km. 132. The water quality of the Kanjhari river is not monitored. The Kanjhari dam catchment area is forest land. It is likely that water quality of this river is very pristine, apart from some erosion, as there are no pollution sources in its catchment area as it is mainly a forest area. The visual observation during field visit confirms that water in the reservoir is crystal clear except during rainy days, free from turbidity and algal growth. District Fisheries Dept. has monitored some parameters of water quality for the Kanjhari dam during the year 2005 is presented in Table 17.

Table 17 Showing Water Quality of Kanjhari Dam

Sl.No Chemical Parameter Results 1 Colour Bluish Green 2 pH range 6.8 to 7.8 3 Transparency 50 -70 cm 4 Temperature 250 c to 320 C 5 Dissolved Oxygen 3 to 6 PPm 5 Carbon dioxide 6ppm 6 Total Alkalinity 22 ppm

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

7 Total Hardness 32 ppm 8 Nitrogen as Nitrate 0.5 ppm 9 Phosphrous 0.4 ppm

133. Odisha State Pollution Control Board monitors water quality of Baitarani at Anandpur. This data is reported in Table 18 and Indian standards for classification of surface water quality are given in Table 19.

Table 18 Water Quality of Baitarni River near Anandpur

Year pH DO BOD TC(MPN/ 100 Designate Existing Source of (mg/ l) (mg/ l) ml) d Class Pollution Class 2009 7.7(6.9 8.1(7.3 to 1.6(1.1 to 3250(2400 to C C - to 8.2) 9.0) 1.9) 4300) 2010 7.8(7.6 7.9(6.8 to 1.7(1.4 to 5328 (3500 to C Single - to 8.3) 8.4) 2.0) 9200) deviation of TC 2011 7.8(7.3 7.3(5.6 to 1.6(0.6 to 7209(1700 – C Doesn’t Human to 8.2) 10.3) 2.4) 28,000) confirm activity to C 2012 7.8(7.3 7.7(6.3 to 1.4(0.8 to 5158(1100 to C Doesn’t Human to 8.2) 10.2) 2.0) 9200) confirm activity to C

(Source: State Pollution Control Board, Odisha, www.ospcboard.org)

Table 19 I ndian Standard for the Surface Water (CPCB Standard)

Sl.No Parameters A B C D E 1 pH 6.5-8.5 6.5-8.5 6.5-8.5 6.0 2 Colour ,Hazen unit, 10 300 300 - - max 3 Total Suspended Not Not Not Not Not Solid specified in specified in specified specified specified in Standard Standard in Standard In Standard Standard 4 Total Dissolved 500 - 1500 - 2100 Solid, mg/l, max 5 Free Ammonia (as - - - 1.2 - N),mg/l, max 6 Sulphate 400 - 400 - 1000 (as SO4), mg/l, max 7 Total Hardness as Not Not Not Not Not CaCO3 specified specified specified specified specified 8 Total Alkalinity as Not Not Not Not Not CaCO3 specified specified specified specified specified 9 Lead(as Pb) mg/l, 0.1 - 0.1 - - max 10 Dissolved Oxygen, 6 5 4 4 - mg/l, max 11 BOD, mg/l, min 2 3 3 - - 12 COD Not Not Not Not Not specified specified specified specified specified

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

Note: A- Drinking water source without conventional treatment but after disinfection. B- Outdoors bathing C- Drinking water source with conventional treatment followed by disinfection. D- Propagation of wildlife, fisheries. E- Irrigation, Industrial cooling, controlled, controlling waste disposal

134. It is observed that Baitarni water quality at Anandpur meets Central Pollution Control Boards (CPCB)’s class C water quality criteria. The presence of coliform in water quality shows that there is domestic waste discharge in the river. In India, the Central Pollution Control Board (CPCB) has developed a concept of designated best use and classified water based on the surface water quality (IS: 2296- 1992) into five classes i.e. A – E. The different classes are: A- Drinking Water Source without conventional treatment but after disinfection; B- Outdoor bathing (Organised); C- Drinking water source after conventional treatment and disinfection; D- Propagation of Wild life and Fisheries and E -Irrigation, Industrial Cooling, and Controlled Waste disposal. The criteria of parameters considered along with the standards as per IS: 2296 – 1992 is enclosed as Annexure 17b. 4.14 Groundwater Resources 135. Odisha has an annually replenish able ground water resource of 21,01,128 HM and 60 % of it is considered as safe use. About 1,22,272 HM is committed for domestic and industrial requirement for the coming 25 years. Table 20 shows the utilisable ground water resources for different needs for the state of Odisha and Keonjhar district and is presented in Table 20. Table 20 Ground Water Resources

District Ground water Utilisable Annual draft Gross Stage of GW resource for for I rrigation annual Resource development assessed(HM) Domestic use (HM) draft for all and uses (HM) I ndustrial use (HM) Odisha State 2101128 112272 236044 310689 14.79 Keonjhar 132291 4954 12713 16042 12.13

136. According to the ground water data available in the State of Environment 2006 report, the ground water potential in Keonjhar district is estimated to be 132291 Hm of which 4954 Hm is utilizable for domestic and industrial use. The annual draft for irrigation use is 12,713 Hm. The area is rich is surface water resource and hence, there is less dependence on ground water. The general ground water depth in the command area was enquired and it was found the depths of the existing tube wells are varying from 40 to 100’ in the head villages and 200’ to 250’ in the tail end villages. The water level gets reduced after the canal water supply gets stopped as observed by the tail end villagers. 4.15 Ambient Air quality

137. The Central Pollution Control Board and State Pollution Control Board maintain database on the ambient air quality of the state. However, such a database is limited

IEE & PC Kanjhari 4 August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

to major cities/ urban centres and some selected industrial areas. No secondary data is available for the project district, particularly representing the rural areas. 138. Along the proposed rehabilitation of the canal system, there is neither industrial activity nor significant vehicular traffic contributing to air pollution. Therefore, the ambient air quality is expected to be within the National Ambient Air Quality Standards (NAAQS) for all parameters (oxides of nitrogen, oxides of sulphur, carbon monoxide, hydrocarbaon, benzene, carbon monoxide) excepting the dust or particulate matter. The occasional vehicular movement on unpaved roads lead to formation of dust clouds over short periods. The airborne dust increases the concentration of both the Suspended Particulate Matter (SPM) and Respirable Particulate Matter (RPM< 10 micron) beyond the limits of the NAAQS. 4.16 Ambient Noise levels

139. The sub-project is located in a pristine environment with forest patches in between. The canals passes through mostly agricultural field hence the sound levels are within the CPCB permissible limits. The traffic along the canal road is also negligible. B. B. ECOLOGI CAL RESOURCES

(i)Fisheries 140. The production of fish in Keonjhar district during 2010 -2011 is around 7250.86 M.T entire this is fresh water. While the sub-project covered blocks Keonjhar has 998.25 M.T, Ghatagaon has 468.66 M.T and Patna has 584.53 M.T, while the production of Kanjhari Dam is 2.75 MT, as per the figures provided District Fisheries Office, Keonjhar. The type of fish found in the area are rohi (Labeo rohita), bhakur (Catla catla), mirkali (Cirrhina mrigala), L. calbasa, L. beta, C carpio, M. Seenghala, M.mystus, Chaela bacaila, Golden mahaseans (Endangered),Wallago attu, C. marulius, C.Striatus, C.punctatus, C. gachua etc. (ii)Biodiversity- Flora and Fauna

141. The forests of Keonjhar district are of monsoon type classified as: (i) Tropical moist deciduous forests and (b) Tropical semi-evergreen forest. The Sal (Shorea robusta) forests dominate with a mixed community of species representing dry deciduous vegetation and thorny xerophytic communities showing degradation. The tropical moist deciduous forests constitutes species like Shorea robusta, Terminalia tomentosa, Diospyrous melanoxylon, and Schleichera oleosa, Anogeissus laatifoli, Ougeini cojenensis, Adina cordifolia, Protium serratum etc. 142. The tropical semi-evergreen forest is confined to the hilly area and characterized by Diospyrous peregrine, Macaranga peltata, Dillenia pentagyna, Mesua ferrea, Strychnis potatorum, Syzygium cumini, Terminalia belerica etc. 143. The forest cover of the State as per the 2001 assessment made by the Forest Survey of India, therefore stands at 48838 sq.Km, which is 31.4% of the state’s geographical area( Annexure -7 Odisha Forest Map). This also accounts for 7.2% of Country’s total forest cover. The reserved forest of the district consists of mostly steep hills and narrow widening valley, while the Keonjhar district has 37.3% under forest cover and the study area falls in Keonjhar forest division which has 39.3 % of the division geographical area under forest, i.e. 2493.48 Sq.Km (Figures provided by Forest Dept 2011). Keonjhar forest division has 7 ranges, blocks covered are 9, and the total numbers of VSS formed are 405. The distribution of forest in Keonjhar forest division is presented in Table 21.

IEE & PC Kanjhari 4 August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

Table 21 Distribution of Forest in Keonjhar Forest Division

S.No Type of Forest Area in Sq.Km 1 Reserved Forest 1173.78 2 Protected Reserved Forest(PRF) 225.01 3 Protected Forest 12.50 4 DPF &UDF 206.58 5 Village Forest ( Rev. Forest) 632.85 6 Other ( Non forest with Plantation) 242.76 7 Total 2493.48 (Source: Forest Department, Keonjhar: 2012)

144. Based on discussions with local forest officials and through public consultation with local people, Vana Samrakshana Samities (VSS) groups and confirmed by reference to official records with the Department of Forestry, it has been confirmed that there are no national parks and wild life sanctuaries within the vicinity of the project. However, the Dam is located within the forest area surrounded by Raghunathpur R.F, Narayanpur R.D and Pipilia R.F of Keonjhar Forest Division. These forests were declared as reserved forest through notification No. 10721-12F-42(m/2) 58D26/27th March 1958 published in the State government Gazette of 4th April 1958 part III pg. 289. The details of the canal system passing through the reserved forest, protected and village forest areas in different sections are shown in Table 7, 8 and 9. 145. As per the Keonjhar district wild life census there are 41 elephants found in the forests of the district, but near the subproject mostly elephants from the Jharkhand state move during harvesting period in search of food. The forest department has identified the path where movement of elephant is taking place called as elephant transit path which happens to pass through certain sections of the catchment area and and a small portion of the left main canal tail end portion (RD 21.000km) and Padampur minor(RD3.100 to 4.100Km) passes through that elephant transit path. The elephants move from one forest to another. The elephant path at Kanjhari sub-project is part of migratory elephant path passing through Sarindha, Jharkhand State, Champua, Nayagad, Soyakali, Keonjhar, Gopalpur, Kanjhari and Patna during harvesting period mainly ( Nov to Jan& May to June mid). Even the elephant transit path passing through sub-project is not one of the fourteen paths the Government of Odisha proposed under Corridor Development Program (Harsha Bardhan Udgata 2011). The top sheet showing the elephant transit path is attached as Annexure 5. There are no government notified core habitations like elephant reserves or sanctuaries with in the area of influence of the project area. 146. The dominant species of the study area are Sal, Asan, Jamu, Kendu, Arjuna, Kurei, Teak, Ghurudu, Eucalyptus, Barakoli, Dhaki and Pokagungha, etc., in the forest areas, while Sal, Mahua, neem, mangium, mango, peepal, tamarind, custard apple and bamboo are common in the command area. There are no threatened or endangered plant species in the command area as per the available local information and based on the discussions with the locals and forest officials. 147. The important minor forest produce of the area are kendu leaves, sal seeds, mohwa flowers and seeds, honey and wax, resins, tasar, myrabolob, tamarind, amla, etc. 148. The important animals found in the forests of the sub-project area are presented in the Table 22. As per the Red data book of IUCN elephants are endangered species and sloth bear occupies vulnerable status and rest of the animals are least concerned. As per the Wild life census 2010 Keonjhar forest division has around 41 elephants.

IEE & PC Kanjhari 4 August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

Table 22 Showing the Fauna found in the forest of the subproject

Sl.No Common name Scientific name ICUN conservation status 1 Elephant Elephas maximus E 2 Deer Odocoileus virginianus LC 3 Sloth Bear Melursus ursinus V 4 Barking Deer Muntiacus muntjak - 5 Monkeys Macaca mulatta LC 6 Pea fowl Pavo cristatus LC 7 Red Jungle fowl Gallus gallus LC 8 Red Spur fowl Galloperdix spadicea LC 9 Black Partridge Melanoperdix nige LC 10 Grey Horn Bill Ocyceros birostris LC 11 Green Pigeon Treron sphenura LC 12 Ducks Anas platyrhincos LC

(Note – LC - Least Concerned; E- Endangered and V – Vulnerable); (Source : DFO office Keonjhar).

C. ECONOMI C DEVELOPMENT

149. The district of Keonjhar is highly rich in mineral resources and has vast deposits of Iron, Manganese and Chrome Ores. About 30 percent of its total area is covered with tracts of dense forests. But the district, in spite of its immense mineral and forest wealth, still remains economically backward. (i) I ndustries and Mining Mineral Development

150. Around 188 small scale industries were established during the year 2006-2007 with a capital investment of about Rs. 3840.18 lakhs generating 909 no’s of employment. 222 cottage industries were set up during the same period are with a capital investment of Rs.153.26 generating employment to 666 persons. Handloom industries i.e. no of looms established, were 2097, generating employment to 2088 persons. 151. The district is bestowed with extensive deposits of iron-ores and manganese ores with chromite, china clay, gold, talc and soapstone, pyrite, bauxite, glass sands, building stones and road metals, etc. The different mines with number of people employed etc for the district is presented in the Table 23. In the project area most of the people are dependent on agriculture and work in the nearby areas, etc. Table 23 Showing different mines with number of people employed for Keonjhar

Name of No. Area Covered No.of Output in Value in Rs Quantity the ore/ of in (Ha) Workers (‘000 Mt) Export mineral work employe abroad ing d (in ‘000 mine MT) s Chromites 4 409.96 813 134 1304088 - Iron ore 86 25639.41 10348 51815 120521690 11940 Manganese 29 5583.70 3016 372 4602756 - Pyrophyelite 5 177.90 35 5 905 -

IEE & PC Kanjhari 4 August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

Quartzite 7 177.9 -- 4.5 900 - Mangnesite 1 40.47 - - - 35 Serpentine 1 40.47 - 1 NA - Total 133 32069.81 14213 52331.5 126430339 11975 (Source: District Statistictical Handbook – 2011)

(ii) I nfrastructure- Transportation

152. As on 2009, there are 287 Km length of national highways, 79 Km length of state highways, 78 Km length of major district roads, 367 Km length of other district roads, 252 Km length of forest roads, 2435 Km length of grampanchayat roads, and 1189 Km length of village roads are operating in the district connecting different rural and urban areas.

D. DEMOGRAPHI C STATUS

153. As per the Census 2011, the total population of Odisha state is 4,19,74,218 with a growth rate of 14 while Keonjhar district has a total population of 1,801,733 with a growth rate of 15.3. The literacy of the Odisha state is 73.45 % while that of Keonjhar district is 68.2%, while the female literacy of the Odisha State is 64.36 % and that of Keonjhar is 58.3%. The district ranks 8th position in terms of population and the percentage of population to the state is 4.24. The percentage of growth of population of compared to 2001 -2011 for the State of Odisha is 14 and the Keonjhar district is 15.3 i.e. annual growth rate of 1.44 for the district. The sex ratio for the district is 977 per 1000 males. 154. As per the 2011 census, the tribal population of Keonjhar district is 45.4%, the different tribes present in the area are Bhuyan, Gond, Ho, Juangs, Kolha and Munda etc. The sub-project covers the three blocks of Keonjhar district i.e. Ghatagaon, Keonjhar and Patna. The Ghatgaon block has a total population of 102117 and it has 11.62 % of Schedule caste (SC) and 44.5 % of Schedule tribes (ST) population, Keonjhar block has 136567 total populations and 10.23 % of SC and 49.25 % of ST population and the Patna block has a total population of 92513 and has 7.4 % of SC and 51.6 % of ST population. 155. The project covers 87 villages (list enclosed as Annexure 8) covering Ghatagaon, Keonjhar and Patna blocks with 62199 numbers of beneficiaries. As per the 2011 Census, the project benefited villages have nearly 13550 households with a population of 58,643. The percentage of SC population in these villages is around 7.65%, the ST population is around 57.12% and the literacy is around 57.77%. 156. Education infrastructure, such as available schools and colleges in the project covered blocks include : Number of primary schools – 141, middle schools – 48 and secondary schools - 33 in Ghatagaon block, Number of primary schools –131 , middle schools – 55 and secondary schools - 39 in Keonjhar block, No of primary schools – 115 , middle schools –58 and secondary schools - 36 in Patna block. 157. The total number of workers, main workers, marginal workers and non-workers for the district and block are mentioned in the below Table 24.

IEE & PC Kanjhari 44 August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

Table 24 Showing the different work force as per 2001 census

Name of the Total Workers Main Workers Marginal Non- Workers district/ block Workers Keonjhar District 621226 395160 226066 940764 Ghatagaon 44271 24651 19620 57846 Keonjhar 56538 31870 24668 80029 Patna 43748 25911 17437 49165 158. As per the Statistical hand book of Keonjhar district, the wages for skilled labour during the period 2008 -2009 for skilled labour is Rs. 11 5.42 to 135.81 and agricultural labour for men is around Rs.65.12 and for women its is 49.36 and other agricultural labour is Rs. 54.42 for women and 63.37 for men. However, when enquired, the local market rate for the period seems to be around Rs. 100 + food for agricultural labour. a. Health

159. The medical infrastructure s available within the district as well as project covered blocks during the year 2008 -09 includes 186 doctors in the district while Ghatagaon block has 10, Keonjhar has 7 and Patna has 12. There are 34 dispensaries in the district; Ghatgoan block has 3, Keonjhar block has 4 and Patna block has 2. There are 3 PHC in Ghatagaon block, Keonjhar block has 5 and Patna block has 4. 160. Thirty four per cent of the total land area of the district is covered with forest and having innumerable streams and springs. There are irrigation reservoirs, canals and sub-canals with enormous potential for mosquito breeding. A. fluviatilis(species S) and A. culicifacies (species B and C) are the main vectors with a predominance of the former in hilly forest areas. DDT is sprayed to control malaria. The incidence of malaria was high during 1999. The number of deaths due to malaria in the district is 48; the percentage of malaria cases detected to the number of samples collected is 9.56 %, as per 2006 data. Eleven numbers of HIV cases were found positive in the district. b.Places of Historical, Archaeological and Religious Significance.

161. The district has three beautiful waterfalls which act as a tourist attraction; Badaghagra, 60 Km from keonjhar, Sanaghagra, 30 Km from Keonjhar and Mruga Mahadev near Keonjhar. Even the Kanjari dam, which is surrounded by reserved forest with aesthetic value, acts as a tourist destination. There are no major historical or archaeological or religious spots.

IEE & PC Kanjhari 4 August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

5. ANTI CI PATED ENVI RONMENTAL I MPACTS AND MI TI GATI NG MEASURES 5.1 Introduction

162. The positive and negative impacts associated with this project are described in this chapter. The negative environmental impacts, both direct and indirect associated with the project location and impacts arising due to the construction phase of the project will be temporary and short term in nature. The direct and short term impacts concern the implementation stage of the ERM works. During the operation phase, indirect impacts expected are long term and are in general positive. For purposes of this IEE report, the environmental impacts in the study area have been discussed during the pre construction, construction and operation phase of the project. Identification of these impacts is followed by recommendations of appropriate cost effective mitigation measures. These impacts along with the mitigation measures are given in the following sections:

5.2 Subproject Activities: • No additional land is required as there is no proposal for new canals for extension for covering additional area and no land acquisition is involved. • Improvement of dam top road and repair of horizontal and vertical drains of the dam. • Bringing the canals to the original design section and providing necessary lining or guard walls as necessity and site conditions in the left and right main canals, distributaries and minor and sub-minor to arrest the prevent seepages / percolations as well as canal breaches caused by shrinkage and cracking of embankments. • Improving hydraulic performance of main system canals, checking for prism/ trapezoidal shape and stability, and to reduce rainfall runoff /erosion of sediment into the canals. • Remodelling of existing Hydraulic control structures for improved flow control and installing flow measurements devices along the left and right main canals, minors and sub- minors canals as per the necessity. • Construction of new and repair of cross drainage structures like and properly designed drainage inlets to minimize entry of sediment into the canals. • Providing additional new bridges and repairing the existing ones for improved access across canals. • Renovating the outlets of the main canal, distributaries, minor and sub-minors. • Improving the banks on the main canal and distributaries for better access. 163. The list of structures that are likely to be undertaken repair/ renovation proposed under the sub project in the left, right, distributaries, minors and sub-minors are stated in the Table 25.

Table 25 showing the list of Structures in the Kanjhari Canal System

I tem Structure Left, Right Main canal, Distributaries, Minors No and Sub-minors Inventory Repair/ Renovation New Head Regulators 63 33 0 Cross Regulator 8 0 0 Escape 2 0 0 Fall 373 85 0 Aqueduct 13 6 0 Canal syphon 102 0 0 Drainage syphon 52 0 0 Bridges (VRB) 128 58 5 Outlet 532 279 3

IEE & PC Kanjhari 4 August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

5.3 Subproject Activities during operation & Maintenance phase

• Maintenance for water availability • Maintenance of canal for equitable irrigation • Maintain drainage system in agricultural field

5.4 Possible Environmental I mpact and Mitigation Measures

164. The possible impacts on environment due to the subproject have been discussed from the following aspects • Impact Due to Project Location • Impact During Planning and design phase • Impact During the construction phase • Impact During operation phase

5.5 I mpact Due to Project Location

165. The environmental issues that may arise due to the present project location are minimal: • No land acquisition, no resettlement (structures) and no change in landuse and landcover will take place, as the proposal envisages the rehabilitation, upgradation of the canal system without increasing the command area or any new canals. • No encroachments as per the Joint survey carried out by SIO staff and ISPMC R& R Specialist • The canal system (main canals, distributaries, minor and sub-minors) in some sections of the canal pass through the reserved forest, protected forest and village forests of Keonjhar division. • As the sub-project falls adjacent to the existing elephant transit path near the dam portion, left main canal tail end portion and Padampur minor passes through the existing elephant transit path (Annexure 5) • No impact on archaeological, monumental, religious and cultural sites will take place as these are not present within the ROW. • During the field visit and during interaction with PP members and SIO staff it was revealed some areas like forest, grazing land have been encroached and started cultivation few years back • There are some large girth trees on the canal embankments which may likely get affected or may require removal. • Utilities like electric poles / line, transformers are present on the canal may get affected due to the proposed work. 166. The mitigation measures proposed are:

• Demarcation of ROW before executing the canal works by the SIO in the presence of PP and addressing any disputes in consultation with PP and in accordance with the R & R policy. • PMU / SIO with the help of ISPMC R & R specialist conducted a joint survey and found no encroachment which would effect the proposed work hence no Resettlement Plan is required for the sub project. • No additional impact on forest land is anticipated as it is an existing canal system where some sections of main canals, distributaries both minor and sub-minors pass through the reserved forest, protected forest and village forests of Keonjhar division • Proper planning and taking precaution would be taken by the contractor while executing the works in consultation with the PP members and local people

IEE & PC Kanjhari 4 August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

• As the sub-project falls adjacent to the existing elephant transit path near the dam portion, left main canal tail end portion and Padampur minor passes through the existing elephant transit path and sitting of camps/machines/ materials shall not be avoided by the contractor. • During the field visit and during interaction with PP members and SIO staff it was revealed some areas like forest, grazing land have been encroached and started cultivation few years back while doing micro plan preparation the assessment of encroached areas need to done and the scope for legalizing the users keeping in view of the usufruct right of the downstream users need to be planned. • During the survey PMU /SIO along with the survey team and Design Engineers shall identify the number of trees likely to get affected and to the possible extent should avoid tree cutting. • Utilities like electric poles / line, transformers are present on the canal may not affect the proposed work , if any SIO comes across in any minors or sub minors shall identify such poles that need to be shifted.

5.6 I mpact during Planning and Design Phase

167. The planning phase will include further detailed topographic and geotechnical surveys and hydrological assessments which will provide information for the detailed designs of the scheme. As such impacts during this planning phase may be limited to erroneous or inadequate field assessments and data interpretation. These impacts could manifest themselves in the following manner:

• Incorrect survey in order to align / resection of canal may result in errors in the alignments and change in the section • Incorrect hydrological assessment of flood magnitude, drainage problem resulting in under- design of conveyance system, leading to hydraulic/structural failure; • Incorrect and insufficient geotechnical survey if not adequately taken into account the geology of the area may result in structural failure. Improve the efficiency of the canal by reducing the water losses. • There are some encroachments within the command area like forest, grazing lands etc have been converted to agricultural lands few year back which can be monitored by PPs by identifying illegal outlets and monitoring them by involving PPs, VSS members, Forest guards, Forest officials and DoWR staff. • The left main canal tail end portion and Padampur minor passes through the existing elephant transit path. • Some large girth trees present on the embankment may get affected or may require tree cutting. • Utilities like electric poles / electric lines were found within the ROW on the canal embankment. • No Archaeological sites are within the project area but while excavation work chance find protocol would be used. • Identification of potential sites or locations for drilling tube wells 168. The mitigation measures proposed would include:

• Thorough hydrological assessment using all available background data and making use of flood simulation software to better estimate optimum design flows. This is to be conducted as the starting point to the design process and will be checked and verified in accordance with project quality assurance procedures; • A geotechnical survey, topographical survey and a soil survey particularly along the axis of the canal side should be conducted at the beginning of the design process to reduce the risk of costly design revisions during construction, or worse the failure of a scheme due to a design based on erroneous parameters; • The design should be checked in accordance with project quality assurance and quality control procedures.

IEE & PC Kanjhari 4 August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

• The scope for improving the designs or carrying capacity of the minors and sub-minors to support the increased command areas ( encroached forest land and grazing lands) without effecting the tail end users • Desilting, lining of the canals and minor repairs to existing structures will improve operation of the canals and positively impact on the hydrology of the project. • Modifications of drop structures and regulators, and construction of permanent outlets with gates will improve the efficiency of canal operation and reduce water losses. • Redesigning of canals if required to suit the additional command area that are converted to agricultural lands from forest and grazing lands etc., • Construction of new bridges( left main canal RD 0.800; 13.100 and 15.600 Km and right main canal RD 2.480 and 11.600 Km will reduce water contamination and facilitate the local people in crossing the canal. At these location except RD 0.800 of left main canal the people and animals are crossing the canals polluting the canal water as village roads have been laid till either side of the canal leaving the canal portion by providing these bridges it improve the accessibility and also may reduce water contamination occurring due to movement of people, animals and vehicles. • The left main canal tail end portion and Padampur minor passes through the existing elephant transit path, the suggestion of the local inhabitants is to provide a food bridge designs may accommodate Foot Bridge at left main canal- tail end portion to facilitate easy movement of elephants and people. • Some large girth trees present on the canal embankment may require removal or tree cutting. During survey and design PMU/ SIO staff along with survey team and in consultation with design engineers shall identify the number of trees that may get affected. To the possible extent tree cutting shall be avoided, if any tree shall be removed from the ROW before commencement of actual work it shall be done in consultation and with the permission of State Forest Department. Stacking, transport and storage of wood shall be done as per the relevant norms. All efforts shall be made to preserve the trees to the possible extent. • Utilities like electric poles / lines /transformers/ water pipelines existing within ROW may not be affected if any identified during survey in the minor and sub-minors which are likely to be damaged during widening or strengthening the canal embankment or may cause hindrance to the movement of construction equipment, the PMU/ SIO in consultation with design team may identify the utilities that may need shifting, if they need to be relocated proper planning and contingency for shifting need to be planned by the SIO in consultation with the PMU • Tube wells locations shall be away from dumps, refuse piles, storage facilities, fuel storage areas, seepage pits, pit toilets, septic tanks, surface water bodies, drains, field fertilized with dung. 5.7 I mpact during Construction Phase

169. Most of the impacts during construction phase are temporary or short term in nature and can be mitigated by using appropriate methods. Impacts during construction phase has been assessed under the following aspects: • Pre-construction activities like selection of Camps, Borrow areas, Quarry etc • Construction Method • Source of materials and process of procurement of material like earth from borrow areas, Quarry areas, mining of sand • Transportation of construction materials used in the construction • Storage of materials and • Work site maintenance and • Labour related issues like their shelter, facilities etc 170. Most of the impacts during construction phase are temporary or short term in nature and can be mitigated by using appropriate methods.

IEE & PC Kanjhari 4 August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

i. Construction Method 171. Rehabilitation and resection of the existing canal system will involve earth moving equipment like excavators, rollers, tippers, tractors, concrete mixers, vibrators, dozers, etc and stripping and leveling of borrow areas etc. Materials will be brought through trucks and offloaded and lifted through manually (head load) where the approach roads in the minors and sub minors are narrow. Excavation and manual digging and cutting would be involved. The excess material would be disposed off within the low lying areas of right of way ii. Sources of Materials 172. The approximate quantities of different materials as identified by SIO staff as part of preliminary estimate is shown in Table 26.

Table 26 Showing the Approximate quantities of Material required for the sub-project

Sl.No Materials Approx. Estimated Quantities in cum 1 Moorum 31452.48 Cum 2 Sand 11386.35 Cum 3 Stone Boulders 2800.10 Cum 4 Steel 586.36 Qntl 5 Granite Material (IRC G I) 2730.00 Cum 6 Metal 5112.24 Cum 7 Granite metal chips( 20, 10 & 6mm) 16237.18 Cum 8 Cement 67436.35 Qntl 9 H.P 150 mm dia pipes 863 number 10 H.P 450 mm dia pipes 255 number iii. Pre construction activities by the contractor 173. After finalizing the contractor before the contractor commence his work the Contractor along with the SIO staff shall identify:

• Contractor shall identify potential sites for work camps, stockpiles, storage areas and disposal sites with the help of SIO staff and takes the approval of the SIO manager. • Contractor shall identify the potential locations for sources of borrow areas, quarry and other materials if any required and take the prior approval of the SIO Manager 174. The mitigation measures proposed are: • The responsibility of establishing camps, stock piles, storage areas and disposal sites mainly lies with the Contractor, however before commencement of work; with help of SIO staff shall identify the potential sites within the sub-project. He shall avoid locations within the reserved, protected, village forest and elephant transit paths. However, if it is deemed necessary to locate elsewhere, sites to be considered will not damage any property, vegetation, irrigation, drainage and drinking water supply. Residential areas will not be considered and sensitive locations need to be avoided like schools if any. All locations identified for disposal need to be included in the design specifications and on plan drawings. a. Camp • Contractor shall avoid establishment of camp / plant in forest areas and elephant transit paths.

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

• Contractor shall prioritize areas with in or nearest possible vacant space within the subproject without affecting property, forest, vegetation, elephant paths drinking water sources and away from the water bodies and the canal system. • All construction plants shall be sited sufficiently away from the elephant paths, settlements and agricultural operations or any commercial establishments. Such plants shall be located at least 100m away from the nearest dwelling preferably in the downwind direction. • The Contractor shall submit a detailed layout plan for all such plant sites established and approved by the SIO manager. • Arrangements to control dust pollution through provision of wind screen, water sprinklers and dust extraction systems shall have to be provided at all such sites. • If any contractor has to establish crushers, hot mix plants and batching plants shall comply with the requirements of the relevant emission control legislations. Consent for Establishment and Operation from state pollution control board Odisha shall be obtained before establishment and operation and a copy to be submitted to the SIO Manager.

b. Borrow areas • If earth material is required or need to procured from borrow pits. • Finalisation of borrow areas for earth and all logistic arrangements as well as compliance to environmental requirements, as applicable shall be the sole responsibility of the Contractor. • Contractor shall identify the potential borrow areas and take permission from SIO manager before operating any borrow areas. • Contractor shall identify the potential borrow areas and take permission from SIO manager before operating any borrow areas. Earth material should be taken from barren land or selected borrow area during lean period as per IS Code 1498 after taking approval from SIO Manager. The criteria of selection is as follows: Selection Criteria of Borrow areas is as follows: I S 4701: 1982 • No borrow pits shall be dug with in 5m of the toe of the embankment, if the depth of the borrow pit is less than 0.5m it shall be after 5m of the toe of the embankment and if the pit depth shall be more than 0.5m it shall be 10m of the toe of the embankment or within such a distance from the toe of the bank where a 4:1 hydraulic gradient line cuts the ground surface, which ever more. • Borrow pits shall not be more than 1m in depth and 25 m in length. • A clear distance of 1m shall be left between the pits • The bed of borrow pits shall be left reasonably smooth and even. • Contractor shall not be permitted to lift any material from the forest areas. • The Contractor shall not start borrowing earth from selected borrow area until the mutual agreement is signed between landowner and Contractor. Copy of the document shall be submitted to SIO manager. • The Contractor in addition to the established practices, rules and regulation will also consider following criteria before finalizing the locations. 1) The borrow area should not be located in agriculture field unless unavoidable i.e. barren land is not available. 2) The borrow pits should not be located along the roads. 3) The loss of productive and agricultural land should be minimum. 4) The loss of vegetation is almost nil or minimum. 5) Sufficient quality of soil is available. 6) The Contractor will ensure the availability of suitable earth. • The Contractor will ensure the availability of suitable earth. The Contractor shall obtain representative samples from each of the identified borrow areas and have these tested at the site laboratory following a testing programme as approved by the concerned Engineer. It shall be ensured that the fill material compacted to the required density. WUAs have identified potential farming willing to give earth material; the list of farmers is enclosed as Annexure 4. These potential sites shall be verified for the suitability after finalising the Contractor and he will enter into mutual agreement with land owners and finalise the borrow areas in consultation with the SIO Manager before operation.

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

• WUAs have identified potential farmers willing to give earth material, the list of farmers is enclosed as Annexure 4. These potential sites shall be verified for the suitability after finalizing the Contractor and he will enter into mutual agreement with land owners and finalize the borrow areas in consultation with the SIO Manager before operation. • Planning of haul roads for accessing borrow areas shall be undertaken during this stage. The haul roads shall be routed to avoid agricultural areas as well as forest areas as far as possible and shall use the existing village roads wherever possible c. Quarry areas • The Contractor shall finalize the quarry for procurement of construction materials after assessment of the availability of sufficient materials, quality and other logistic arrangements. • A preliminary survey has been carried out by the SIO and identified the quarry as shown in Annexure -3. • If extraction shall be done, prioritize sites already permitted by the Mining or concerned department, • Contractor shall purchase materials and finalize vendors who have valid permissions. The list of potential crusher who has valid license from State Pollution Control board, Odisha is enclosed for reference as Annexure 3. • If other sites are necessary and the contractor want to use, let the contractor obtain necessary permission from the concerned regulatory authority and inform SIO Manager. • The contractor shall avoid all forest areas for quarrying.

d. Sand

• The sand shall be procured from identified (by SIO) sand mines as far as possible. If Contractor wishes to procure from other sources he shall obtain the lease agreement of the supplier 175. Most of the impacts during construction phase are temporary or short term in nature and can be mitigated by using appropriate methods.

iv. I mpact on Land Use: 176. Land acquisition will be not required for this subproject. No major adverse impact is expected on the living conditions of the inhabitants. Storage of construction materials and silt at construction sites may temporarily change local land use status. The disposal of debris and silt shall be done properly. The Table 7, 8 & 9 shows the details of reserved, protected and village forest areas, these shall be prohibited by the Contractor for using as Camps/ Storage places or dumping places.

177. The mitigation measures proposed are: 178. The Contractor while working in main canal, distributaries and minors and WUAs while working in sub-minors shall follow the below: • Construction materials / silt should be stored properly and proper appropriate measures shall be taken while disposing the debris and silt. • To the possible extent the materials like stone and other reusable materials shall be utilized in the construction. • The iron and wood if any generated shall be taken into the surplus stock and the scrap shall be auctioned as per the procedures of Odisha Water Resources Department. • The suitable material generated from cutting shall be used in the filling after material testing and obtaining necessary approval from the SIO. The remaining unsuitable material shall be disposed on the left side of the main canal after the toe line within the ROW and also in the adjacent suitable available land along the canal after obtaining necessary permission from the competent authority.

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

v. I mpact of soil – soil erosion and siltation: 179. Soil erosion will take place during earthworks, such as filling and cutting for re- sectioning of the canals and disposal of cutting earth in the spoil bank. The impact will be localized, short-term and minor. These activities will be conducted in the dry season. Mitigating and safeguarding measures to prevent excessive dust will be taken up by the contractor. Further safeguards associated with on-site activity and clean-up will be incorporated into the procurement documents. 180. The mitigation measures proposed are: 181. The Contractor while working in main canal, distributaries and minors and WUAs while working in sub-minors shall follow the below: • Confirming excavations operations and slope stabilization work during the dry season only and compaction in main canal by powered road roller and vibratory roller and in the distributaries, minors and sub-minors by ordinary compaction • Careful construction planning for surface protection particularly before monsoon season and planning of turfing activities in the inner slope of the canal and a provision for turfing the spoil bank is also suggested. • Earth material and selection of Borrow area as per IS code 1498 1970 reaffirmed 1970. • Earthworks operations shall be strictly limited to the areas to be occupied by the permanent Works and approved borrow areas and quarries, unless otherwise permitted by the Project Manager. Due provision shall be made for temporary drainage. Erosion and/or instability and/or sediment deposition arising from earthwork operations not in accordance with the Specifications shall be made good immediately. • The Contractor shall obtain the permission of the Project Manager before opening up any borrows or quarries. Such borrow pits and quarries may be prohibited or restricted in dimensions and depth by the Project Manager where: ƒ they might affect the stability or safety of the Works or adjacent property; ƒ they might interfere with natural or artificial drainage or irrigation; ƒ they may be environmentally unsuitable. ƒ the contractor should enter into an equitable agreement with landowner for borrow area redevelopment if any landowner requires and after completion of the borrow area the contractor obtains a “Satisfaction Letter “ or “No – objection Letter” from the land owner on a stamp paper • At least 14 days before he intends to commence opening up any approved borrow pit or quarry, the Contractor shall submit to the Project Manager his intended method of working and restoration. These shall include but not be limited to: • the location, design and method of construction of any access track; (ii) the volume and nature of materials to be removed; (iii) the sequence and method of excavation of materials; • measures for controlling runoff and sediment from the site during operations such avoiding deep cutting of borrow areas and arrangement for drainage along the natural gradient; and • Proposals for site restoration including approximate finished levels, drainage, erosion and sediment control, slope stabilisation and re-vegetation, including reinstatement of any access track. • The operation of borrow pits or borrow areas shall not be permitted until the method of working for that particular pit or area has been approved by the Project Manager in writing. Restoration shall be to the satisfaction of the Project Manager • Soil erosion will take place during earthworks, such as filling and cutting for re-sectioning of the canals. The impact will be localized, short-term and minor. These activities will be conducted in the dry season. Mitigating and safeguarding measures to prevent excessive dust will be taken up by the contractor. Further safeguards associated with on-site activity and clean-up will be incorporated into the procurement documents. • Borrow pits shall not be permitted within the forest areas.

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

• Borrow-pits, other than those in agricultural fields, will be covered with a layer of top-soil and grass-pitching. • The rehabilitation of the borrow areas shall be done by the contractor as per the land owners requirements. vi. I mpact on Access Roads and Haulage Roads 182. Deterioration in quality of roads and damage to some of the existing bridges on the canal anticipated while transporting the materials. There is a need for using existing cart roads within the forest areas and canal embankment service road within the forest areas so there is a scope for some damage or deterioration. 183. The mitigation measures proposed are: 184. The Contractor while working in main canal, distributaries and minors and WUAs while working in sub-minors shall follow the below: • Limited construction period, careful planning on the movement of vehicles and restrictions on construction workers movement and adequate monitoring shall be carried out by the contractor • All existing roads used by vehicles of the contractor or any of his suppliers of material shall maintain during construction period. Clear any materials dropped by the vehicles on the access roads. • There is no need for construction new haulage roads within the forest areas where the canal passes, as the canal embankment itself serves as service road which can be utilised for transporting material and even the forest areas have exiting forest cart roads which can be utilised with the permission of local forest department and they need to be maintained.

vii. I mpact on Water Quality: 185. Water used in construction process is not in the large quantities. Thus impact on water quantity is negligible. However there would be other minor impacts that may arise are: • Inadequate drainage in the temporary camp site resulting poor sanitation condition and surface and ground water pollution and promote breeding of mosquitoes. • Contamination of ground and surface water due to inappropriate disposal of spoil materials, debris and waste • Contamination of water due to fuels and lubricants and construction waste waters • Erosion of canal embankments due to improper compaction 186. The mitigation measures proposed are:

• The Contractor while working in main canal, distributaries and minors and WUAs while working in sub-minors shall follow the below: • Proper disposal/reuse of construction spoils and silt generated from desilting operation considering environmental safeguard • Arrangement to drain out wastewater from construction site should be planned as per the site conditions i.e. along the natural gradients. The Contractors are hiring buildings for Camp as these are scattered works. If Contractor establishes any Camp he shall ensure adequate drainage and sanitation at the site. • The contractor shall procure the fuel from the nearest authorized outlets, if any minor storage if he has to make he shall ensure he doesn’t contaminate the area. • Contractor shall avoid oil spillages etc., • Contractor shall not wash his vehicles in the canals • Contractor shall ensure or install equipments in such a way that the waste water doesn’t enter the canal during monsoon season. • Contractor shall ensure proper compaction after completion of the earthwork, for the main canal compaction has to be done by Powered Road Roller or Vibratory Roller and in the distributaries, minors and sub-minors by hand roller.

IEE & PC Kanjhari 4 August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

• To protect the canal from erosion in the completed earth work of the sections of the canals a provision for turfing has been made

viii. I mpact on Air Quality: 187. Deterioration of air quality would be mainly due to fugitive dust emission from construction activities, and gaseous emissions from construction equipments and vehicular movements (equipment like concrete mixers, vibrators, hot mix, and vehicles like lorry, tractors, roller, dozers, excavators, etc). These impacts would be short term in nature and limited to the project site and construction phase only. 188. The mitigation measures proposed are: 189. The Contractor while working in main canal, distributaries and minors and WUAs while working in sub-minors shall follow the below: • Contractor shall ensure trucks carrying soil, sand and stone will be duly covered to avoid spilling. • Contractor shall ensure adequate dust suppression measures such as regular sprinkling of water especially at the time of construction along the village corridor will be undertaken. Contractor shall ensure that all construction equipments and vehicles are in good working condition, properly tuned and maintained to keep emissions within permissible limits.

ix. I mpact on Noise Level: 190. The construction phase will see the operation of only light construction machinery, which is known to emit sounds with moderate decibel (dB). Temporary impacts in the immediate vicinity of project site may occur due to noise generated from construction activities superimposed with existing vehicular noise. The magnitude of impact will depend upon specific types of equipment to be used, the construction methods employed and scheduling of the work. The construction noise will be intermittent and of short duration and mostly during day time. 191. The mitigation measures proposed are: 192. The Contractor while working in main canal, distributaries and minors and WUAs while working in sub-minors shall follow the below: • In order to reduce these impacts it will be ensured that all construction equipment and vehicles used in construction shall strictly conform to the MoEF / CPCB standards. • All vehicles exceeding the limits shall be fitted with exhaust silencers. • Regular servicing of all construction vehicles and machinery shall be done regularly and during servicing the effectiveness of exhaust silencers shall be checked. • All the construction sites within in 150m of the nearest habitation, noisy construction work such as crushing, operation of DG sets and any high noise construction equipments shall be stopped during night time between 10.00pm and 6.00 am. • Working hours of the construction activities around sensitive areas like schools / hospitals upt a distance of 100m shall be restricted.

x. I mpact on Biological Environment: 193. The project site does not include any rare or endangered species of plant. The migratory elephants are the endangered species in the area and sloth bear is under Vulnerable category and the rest of the animals are of least concern status (Table 22). Most of these animals are confined to reserved forest hence the impact due to the present construction activities will be negligible, Thus, no impacts on rare / endangered species are envisaged due to site operations. The canal system passes through reserved forest, protected forest and village forest the details are provided in Table 7,8 and 9 so while working in the forest areas there might be some scope for disturbance to the wild life and trees these can be mitigated through strict monitoring and contractor adhering to

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

standards. The increased irrigation facilities in the area will actually enhance the environmental conditions resulting in more greenery. There is also a possibility of planting more trees by farmers due to the easy availability of water. Only few canal side trees will be felled during construction phase. 194. The mitigation measures proposed are: • The Contractor while working in main canal, distributaries and minors and WUAs while working in sub-minors shall follow the below: • The Contractor and WUAs will obtain the permission from state forest department while working in the reserved forests. • Contractor shall ensures that no trees shall be cut by the workers while working in the forest areas • Contractor shall ensure the workers are not involved in any hunting or poaching areas • Contractor shall not create paths existing cart tracks shall be used or canal service road shall be utilized. • The Contractor shall ensure while working in forest areas, all works shall be carried out during day time only. • The Contractor shall not dump material in the forest areas only existing ROW available within the canal shall be used for dumping / storing materials. • The Contractor shall not be permitted to establish Camps / labour camps within forest areas. • The sub-project has provision for planting around 1000 trees along the canal banks against the tree loss if any • Plantation of indigenous tree species along the irrigation canal compensates loss of flora. • The survival of trees needs to be monitored by the WUAs and SIO staff.

xi. Impact on Social Environment 195. Most of the social impacts related to development of irrigation project are positive. Some of the impacts and mitigation measures are as follows:

• The sub project is to be implemented on a community participative basis, with full consultation during the planning and design process. • Due to the proposed irrigation project some of gross command area like forest and grazing have been converted few years back due to encroachments, the tribal and traditional dwellers are being granted rights over the forest land in addition to the community rights as per the provisions of Schedule Tribes and Other Forest Dwellers Recognition of Rights Act 2006t this act would permit to legalize some areas, so in head portion based on the available water if the users are legal water right may be allowed after seeing the crop water requirement, but in the tail end portions the scope may be less, so PP in consultation with SIO staff decide the possibility of giving water or not. Since there is scope for reducing the certified command area due to the increasing demand for housing because of growing population those deprived areas may be given water in the future. • Most impacts pertaining to the establishment of the proposed scheme are positive in nature, the soils in the area will become more stable and the area will have a source of irrigation and farm use water, which has a positive impact on the agriculture of the area, thereby enhancing farm incomes.

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

• During the construction phase, there may be an influx of migrant skilled and unskilled workers in the project area. This will be restricted to the construction phase of the project. Efforts will be made to recruit local workers from the area as a priority to create employment opportunities and provide a sense of well being among local people as well as social compatibility among the people. • Labour/construction camps will be sited based on consultation with local communities with the priority of causing the least disruption to the residents and the surrounding environment. Transport routes for materials to the site, given the proximity of the residents houses etc. will also be selected with community consultation such that minimal disturbance will be made to residents. Given the proximity of the houses to the entry road to the site, the final selection of the entry route to the site for construction purposes will need to be carefully monitored for impacts during the construction period. • The location of key infrastructure under the main contract advises to be away from reasonable distance from the communities, therefore the camp sites are unlikely to cause disturbance to the communities. • For construction activities undertaken close to communities, movement of construction equipment, vehicles and personnel will be regulated to avoid traffic jams and noise. • After completion of all construction activities, excess construction material and debris, is should be removed from the site and disposed of in the low lying areas within ROW.

xii. Occupational Health and Safety 196. The potential impacts of occupational hazards are minor due to handling of cement and working in excavations. Few sections of the canals (left main canal RD 0.800; 13.100 and 15.600Km and right main canal RD 2.480 and 11.600Km) people are crossing the canals to reach the either side of the roads, so construction of new bridges are proposed at these locations, so Contractor while working at these places he ensures proper safety requirements. These impacts can be mitigated through proper safety measures. The Construction contractor will be required to:

• Develop and implement site specific safety and health plan which include measures like: (a) proper safety measures while working at VRB’s (b) ensuring all workers are provided with and use of Personal Protective Equipments (PPE); (c) contractor ensuring all workers follow the documented procedures and providing health and safety training to the workers • Providing first aid kits at the work sites at all times • Providing insurance including medical coverage for workers • Providing basic amenities like drinking water, clean eating areas, sanitation etc • Safety and security of the work sites etc • Providing proper lighting arrangement while working in the nights • Moving equipment and vehicles equipped with back alarms or flag men • Maintaining equipment properly and ensuring the workers are not exposed to noise high noise level and use of hearing protection etc if required should be enforced • Providing appropriate sign boards while excavation / construction work and providing proper barricades for preventing people and animals.

xiii. Community Health and Safety

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

• Most sections of the canals are passing through reserved forest, protected forest, village forest, elephant paths, crop lands except few locations canal passes through nalas and roads. The canal bank serves as an access road in the command areas. So construction Contractor shall avoid all forest areas and elephant transit paths and should ensure the materials he dumps or equipments he installs will not obstruct the movement of local people or wildlife in the area also. If necessary he will ensure proper safety measures in the areas and take dust suppression measures adequately to prevent dust pollution etc. The Contractor or WUAs while working in the sections of the forest areas shall ensure they will not light Halogen lamps, shall not establish any crusher, digging of trenches above 10’; shall not use any explosive devices without appropriate permission and avoid liquor etc • If any electric lines are noticed along the canal which may obstruct so SIO Contractor shall identify and l ensure all precautions and shall prevent any danger from electrical line or equipments and ensures that they doesn’t cause any inconvenience to the people. The SIO shall identify the electric poles / lines that may hinder the movement people and machines during construction and SIO shall request the local electricity department for shifting such poles/ lines by depositing the required shifting charges from the department contingency funds. • The Contractor Camp is not permitted in the forest areas. The contractor Camp can cause some temporary disturbance, if established near the residential areas care should be taken while identifying the areas and ensure the place is not polluted due to the storage of oils/ fuels used for construction. While storing fuel he ensures he practices approved practices of storing fuels and train the staff in handling and recovering the materials. Provide proper lighting, sanitation and drinking water facilities for the workers and staff. If the contractor constructs any temporary structures he will follow the approved practices and clear the site and handover to the concerned and take a no –objection or satisfaction letter from the land owner.

xiv. Impact on Archaeological sites during excavation • No Archaeological sites are within the project area but while excavation work chance find protocol would be used. • While excavating or dismantling any structure if any fossils, coins, articles of value / antiquity and remains of archaeological interest discovered on the site shall be the property of the Government and shall be dealt with as per the provisions of the relevant legislation • The Contractor shall take reasonable precautions to prevent his workmen or any other persons from damaging or removing any such articles, if any articles found shall be brought to the notice of SIO and Environment Specialist and shall seek the direction of Archaeological Survey of India (ASI) before contractor recommencing the work xv. Environmental Issues Related to Project Operation 197. Despite restrictions on resources use in the protected areas, it was observed that encroaching activities are occurring in the upper areas of the catchment and overall forest cover in the area has been degraded by human activities. In general, deforestation and mismanagement of arable land continues. Overgrazing by livestock is considered to be a leading cause of soil degradation. The scope for increased conflict in the usufruct right of the downstream users needs to be addressed while planning the legalization of the additional command area. 198. More stable water flows would reduce the occurrence for vector-borne diseases. Environment awareness, including health and sanitation is recommended to improve quality of life. The impacts of operating and maintenance on increased downstream flow will be positive.. This is not only cheaper, but also saves groundwater and energy. 199. The improvements to outlet structures, to replace the current cut-bunds as existing practice, will improve the downstream flow. The proposed repair of canal and structures

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

will reduce the losses and assure reliable water fore, agriculture, domestic and livestock needs. No mitigation measures are recommended. 200. At present no water logging as a result of irrigation occurs. In the post-project situation, over-irrigation is less likely to occur. Hence, a positive impact on possible salinization hazard and leaching of fertilizer and pesticides to the groundwater. Presently under the project measuring devices are proposed which can help in measuring the discharge / quantity of water. As per the rainfall data for the last 30 years it reveals there is normal rainfall, so the quantity of water available in the area is not a problem for sub- project. The quality of the water in the subproject will not have much impact as the erosion in the catchment is less due to forest, no industries were observed so impact on water is negligible. If any due to the increased fertilizer may be monitored in the future, however at present scenario the usage of fertilizers and pesticides in Keonjhar district is very low. 201. The intensification of agriculture may also result in increased use of agrochemicals including mineral fertilizers and pesticides, which may result in soil and water contamination. Although the use of agrochemical is currently far less than the level applied in productive agriculture systems, these need to be carefully monitored, and mitigated through agriculture extension that promotes (i) optimum, informed use of mineral fertilizers in combination with organic manure and bio fertilizer, (ii) promotion of the concept of integrated pest management, focusing on cost effective and environmentally friendly or benign pest management techniques; and (iii) emphatic discouragement of the use of persistent and banned pesticides. 5.8 I mpact during Operation & Maintenance Phase a) I mpact on I rrigation Water Quality and Quantity 202. Periodic testing of water for chemical and biological properties will help in establishing a database on water quality. This will help in taking planning decision and remedial measures for any adverse impacts on the water quality. The result of the testing if disseminated to the pani panchayats would help in bringing awareness to the local people. Weed removal should be done regularly and community should be made aware of the causes of weed growth and washing of domestic animals and letting domestic sewage into the canal should be checked with help of pani panchayats. If proper water planning not done with PP there could lead to conflicts within the WUAs. Hence WUA, Apex committee and Distibutary committees shall be involved in the water planning and distribution.

b)I mpact on canal system due to weeds 203. Fast multiplying weeds impairs flow of water and reduces water availability and damages structures and increases mosquitoes if unchecked. So regular deweeding and checking of weeds by mechanical means or by usage of herbicides if necessary. PP and community members shall be made aware and encouraged to prepare vermi-compost etc. Pani Panchayat members including community members shall be made aware and encouraged to prepare compost / vermi compost etc. The State Agriculture Policy 2013 emphasizes on the provision of assistance for organic farming i.e. provision of subsidy for establishing vermi compost units, so linkages shall be established with the local agriculture department. c)I mpact on the aesthetics 204. After completion of works, replanting of economically and aesthetically important plants can be ensured along the canal. Greening of the area may offset the ecological effects of the clearing and felling of any trees during construction phase. So monitoring of trees and their survival planted along the canal shall be ensured. d)I mpact due to non -maintenance 205. The responsibility of maintaining main canal, distributaries likes with the SIO staff and minor and sub-minors with WUAs. The responsibilities of PP are as:

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

• Removal of silt and proper up keeping off minor/ sub-minor/ water courses / field channels and field drains • Repair and maintenance of inspection path and service roads • Removal of grass, shrubs and bushes from the canal embanKment and canal beds • Repair and maintenance of all structures in the distribution system handed over for operation and maintenance. • Restoration of banks – earthwork • Repairs to lining, painting, plastering and replacing damage portions to structures etc.

e)Soil modification 206. Agriculture practiced by beneficiary farmers will intensify as a result of infrastructure improvements. The nature and extent of improvements will be influenced by agriculture extension. The changes in agriculture practices may result in soil modifications, including increased susceptibility to slumping, reduced nutrient status and impaired structure if the organic matter content is not maintained. These can be mitigated by including sustainable land use practices in the agriculture extension component. These include (i) continued use of traditional terrace construction and management of water flows, (ii) the use of deep rooting grasses and shrubs to further strengthen bunds and terrace walls, and (iii) promotion of continued use of organic based practices like use of bio-fertilizers. f)Soil and water contamination due to agrochemicals 207. The intensification of agriculture may also result in increased use of agrochemicals including mineral fertilizers and pesticides, which may result in soil and water contamination. Although the use of agrochemical is currently far less than the level applied in productive agriculture systems, these need to be carefully monitored, and mitigated through agriculture extension that promotes (i) optimum, informed use of mineral fertilizers in combination with organic manure, (ii) promotion of the concept of integrated pest management, focusing on cost effective and environmentally friendly or benign pest management techniques; and (iii) emphatic discouragement of the use of persistent and banned pesticides. g) Biodiversity 208. Biodiversity in the catchment may not be affected much. While in the ayacut / command area may be affected by increased specialized mono-cropping, use of agrochemicals, introduction of alien (invasive) species, and introduction of high yielding varieties (HYV) at the expense of traditional low yielding varieties. The conversion of ecosystems such as forests land in the command area has happened many years ago might not have affected as no threatened flora was found in these forests hence negligible impact on biodiversity. However, these can be mitigated by (i) awareness raising through the agriculture extension component and through training and support to WUAs of the importance of maintaining diversity of farming practices and local landscape, (ii) promoting under the agriculture extension component the maintenance of variety of production of both cash and subsistence crops and (iii) promoting under the agriculture extension component the use of indigenous multi-purpose trees for soil protection, watershed management and cash crop production. 209. The renovation and modernization of this project will have beneficial impacts in terms of improved irrigation and road facilities in the area that increase overall agriculture production and improved economic conditions of the area. 210. Encroachments in the forest areas may be monitored by preparing the micro plan in which the legal and illegal outlets, forest and agricultural areas can be demarcated. The illegal out lets and changes if any happening in the forest areas falling under respective Pani Panchayats can be brought to the notice of SIO staff and they will communicate to the local forest department. The sub-project will constitute a monitoring team constituting PP members (WUAs), Vana Samrakshan Samities (VSS), SIO staff of the subproject, local forest guard and local forest staff and NGO involved in the PP strengthening who will monitor the encroachments regularly.

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

211. The Elephant crossing points as part of elephant transit path are catchment area and a small portion of the left main canal tail end portion (RD 21.000km) and Padampur sub minor(RD 3.100 to 4.100Km)

6. I NFORMATI ON DI SCLOSURE, CONSULTATI ON AND PARTI CI PATI ON 6.0 General

212. The consultation, participation and disclosure has been taken up as an integral part of environmental assessment process for this project and was used as a tool to inform and educate stakeholders about the proposed project. It helped in identification of needs of the local population that is likely to be benefited / affected. Aiming at promotion of public understanding and fruitful solutions of developmental problems such as local needs of farmers and problem and prospect associated with irrigation facilities, various sections of community, people, affected persons in the project process and other stakeholders were consulted through individual consultations. It was attended by local farmers, gram panchyat members, Vana Samrakshana Samithies (VSS) members and engineers from DOWR. The findings were incorporated in project design as part of project preparation and consultation will be carried out at construction stage of the project. 6.1 Stages and Level of Consultation

213. For the Kanjhari subproject consultations took place during the Participatory “Walkthrough” Survey carried between 14th to 25th September 2011, in which farmers took part including the members of the Pani Panchayat. Focussed group discussions were also carried out in different villages involving small groups of people from different communities, professions etc. The need for rehabilitation, and their ideas and demands have been reflected in the in the consultations. The Consultation were carried out in different villages as part of environmental screening covering head, middle and tail end villages. The consultations were of two types:

¾ Community / local level involving Project benefitted communities, stakeholders or Pani Panchayat members, residents, labour and other professionals ¾ Institutional level consultation involving officials from key government departments like State Pollution Control Board regional office, local bodies, Water Resource Department officals, Fisheries department, Forest Department, etc.,

6.2 Community level Consultations

214. Consultations were held between 18th to 25th September 2011 in different villages covering head, middle and tail end through focused group discussions to inform the people about the sub-project as well as to capture their views and difficulties of the existing sub- project. The consultations were carried out in six villages and the village wise issues are presented in the Annexure 9 and the list of participants is also enclosed as Annexure 10 to 15. The different issues captured during public consultation are presented in the Table 27 below:

Table 27 I ssues of the Public Consultation

Sl. Key Perception of village community Action to be Taken No. I ssues/ Demands

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

Sl. Key Perception of village community Action to be Taken No. I ssues/ Demands 1 Awareness of the Pani panchayat members heard about the Tail end villages want a project – including proposed improvement of the Kanjhari proper resection of the coverage area scheme but common People were not canal to reach the aware of the project activities they heard water to the tail end during the meeting for the first time. The villages, proper stake holders believes the proposed repairs designing of the canal are essential and it helps the tail end should be considered villages and improve the economy of the villages 2 Presence of any The dam is surrounded by reserved forest The information would forest, wild life or on three sides and some portions of the be used in locating the any sensitive / canal main and minors pass through contractor camps as unique reserved forest patches. In addition the well as in scheduling environmental project is located adjacent to the elephant work necessary components nearby transit path and a portion of the left main consultation will be the project area canal passes through the elephant path. carried out time to time with forest department and VSS groups while commencing the wroks 3 Presence of There are no historical / cultural as per the Information noted and historical/ cultural villagers along the ROW of the canal, with no impact on the sites in the village and near to the canal there present work are a few old temples which are not affected to the present work

4 Occurrence of flood The project areas doesn’t have flood Proper designing of problem but during the recent i.e drainage outlet will be September 2011 had flood which has absolutely required occurred for the first time since the during detail designing. construction of the project 5 Drainage problem – The breaching of canals and siltation of the Canal lining will be canal water seepage canals is resulting in seepage and water required to check loss logging in the head and middle reaches of of water, if required the canal proper drainage may be required 6 Salinity problem No salinity problem in the area as reported Points are noted by people. 7 Testing of soil, silt Soil was tested by agriculture department Routine testing of and water but the farmers are not aware and water agricultural soil, silt from the dam was tested by fisheries and irrigation water is department once. part of EMP.

8 Cultivation practices At present head reach and middle reach Ensure sufficient during Kharif and villages are cultivation paddy both in the available water in entire Rabi seasons kharif and rabi while the tail end farmers command area during cultivate rainfed kharif mostly Rabi season by said irrigation scheme

Application of organic manure will improve water holding capacity

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

Sl. Key Perception of village community Action to be Taken No. I ssues/ Demands and soil health 9 Use of fertilizer and Farmers at present are using chemical Support from pesticides for fertilizer like DAP, Urea, Super phosphate agricultural extension cultivation of crops and potash in low to medium dosages of services is much fertilizer. While pesticides like Themat, etc needed and Pesticides are being used. those having long residual persistence in No organic fertilizer nor pesticide is being soil should be used in the area except cow dung monitored and banned. Testing of soils is needed

10 Safety aspects Farmers are not using any personnel Safety precaution like during spraying/ protective equipments while handling the use of noise mask/ application of fertilizers or pesticides cloth and hand gloves pesticide will be suggested through awareness program 11 Occurrence of No information available but farmers say Application of organic pesticide due to the runoff water from the fields fish fertilizer (that have contamination of might be getting affected binding characteristics) surface water and and non use of banned contamination of fish pesticide are necessary 12 Availability of labour Head reach villages mentioned availability If labour available from during construction of labour may be a problem during intense beneficiary village no time cropping season and they said they do not need to bring have objection if outside labour visit and the construction worker tail end villages mentioned they are ready from outside. to help during the construction period if Further community works are taken up after kharif crop. consultation will be required before starting of work 13 Access road to The canal have access by canal bank road Dust suppression project site and if required it would be repaired and all measures will be the villages are having kutcha roads required while transportation of construction material 14 Setting up worker Villagers have said there is lot places in the Proper consultation camp site within the villages to locate the camp and the with the villagers can be village contractor can hire some houses for the taken up before camp within the villages. establishing the camp and in most of the

villages local labour will be available so there may not be a need for a camp 15 Dust and noise Construction period is for a short period and The EMP is built with pollution and the activities are mostly away from the provision for dust disturbances during habitation so the impact is minimal and the suppression and proper construction work community are ready to accept the minor monitoring would be

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

Sl. Key Perception of village community Action to be Taken No. I ssues/ Demands disturbances. taken up during construction 16 Safety of residents As per the opinion of stake holders, the Safety measures are during construction disturbance due to transportation of integral with EMP phase and plying of construction material will be minimal as the vehicle for canal is away from the habitations. construction activities 17 Conflict among Due to the present bad condition of the Point noted beneficiaries canal system there are some conflicts in the downstream users tail end villages, they expressed if the canal system improves the conflict would reduce. 18 Enhancement of At present there is shortage of drinking Provision for drinking other facilities water some provision for drinking water can water is built within the be made project scope 19 Non availability of The middle and tail end farmers expressed Time to time canal water during after kharif they do not have any problem in consultation would be construction taking up the proposed construction activity done as they are not receiving the water at present. While the head reach farmers are willing to co-operate if the canal has to be closed for a season. 6.3 Consultation with I nstitutional stakeholders:

215. As part of the process the following personnel (Table 28) from different departments were consulted along with the staff of Water Resources Department of Kanjhari subproject:

Table 28 Showing details of consultations with stake holders

Sl.No Department / Place Participant I ssue Date 1 Regional Office - Mr. B.K. Nayak Requirement of 20th Sept. 2011 statutory clearance State Pollution Control Regional Officer Board, DD College Road, Monitoring of water,

Bariapet, Keonjhar air , noise and Licensed quarry

2 Regional Office , Mr. Bijay Kumar Sethi Requirement of 20th Sept. 2011 statutory clearance State Pollution Control Asst. Environmental Board DD College Road, Engineer Monitoring of water, Bariapet, Keonjhar air , noise and

Licensed quarry

3 Forest Office, Opp. Mr. S. K. Mohanty Forest clearance 20th & 21st Sept. Collectorate, Keonjhar 2011 Divisional Forest Elephant path Officer and Wild life Wild life census Warden Forest Cover

IEE & PC Kanjhari 4 August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

4 Forest Office, Opp. Mr. S. Samantaray Forest clearance 20th & 21st Sept. Collectorate, Keonjhar 2011 Asst. Conservator of Elephant path Forests Wild life census

Forest Cover Forest Office, Opp., Mr. Fulai Hembram Forest clearance 29th March 2012 Keonjhar 5 Ranger Sadar, Elephant path Keonjhar Wild life census Encroachments 6 District Fisheries Office Mr. Pramod Kumar Fish production in 24th Sept. 2011 Rout kanjhari tank and Near Mining School Road species present Asst. Fisheries Officer Keonjhar & Inc. District Fisheries Officer

7 Collectorate, Keonjhar Mr. Jai Chand Mishra District Gazetteer 23th Sept. 2011 Senior Clerk

8 National Informatics Mr. Patnaik Census information 24th Sept. 2011 Centre (NIC)

Regional Office Keonjhar 9 IDEAL Development Ms. Sabitha Singh Experiences of the 26th Sept. 2011 Agency (NGO) organisation – with

VSS, education and Keonjhar health issues

10 Land Acquisition Office Mr. Samal On Land Acquisition 30th March 2012 details – village forest , Keonjhar area 6.4 Summary of Public Consultation are: • The Villagers are keen for the proposed renovation and they assured that they will cooperate in all aspects for implementation of the prestigious project which they would benefit form. • The tail end villagers want to get the canal levels rectified and re-sectioning needs to be done which would get them water. • The villagers want breaches rectified and linning and guards walls for the main canals, as well as sub-minor and minors and repair of some structures. • The Villagers are ready to accommodate the short term impacts that may arise during construction phase • At present, farmers are depending on inorganic pesticides and fertilizers; they need to be made aware of the ill effects and awareness need to be developed on organic farming. An Environmental awareness program will be required on usage of pesticide, as well as personal safety during the application of pesticide. • At present, farmers are not aware of the quality of soil and water; they need support from the allied departments.

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

• Planning of construction activities can be initiated after kharif crop and proper consultation with PP/ VSS and forest department in establishing labour camps and equipments at sites need to be done. 216. The approach adopted for the Project ensures that all sub-projects are community driven. Design and implementation involves the groups potentially influenced by the schemes, ensuring a very high level of public awareness and involvement at each stage. Procedures for public consultation and disclosure are incorporated in sub-project implementation guidelines prepared for the project. In accordance with the main issues identified in the project implementation in the Project Completion Report (PCR), essential elements incorporated into procedures for the Project include (i) understanding the project during the planning phase, (ii) physical and financial contributions during the construction phase, and (iii) taking ownership for operation, maintenance and management of the irrigation systems after construction.

6.6 Future Consultation and Disclosure

217. During construction period also consultations will be carried out with affected persons, stakeholders. Small meetings with the Pani Panchayat members and farmers and other vulnerable communities including women will consulted to address any issues related to the proposed construction. The findings would be presented in the monitoring reports that would be submitted to ADB. The brief executive summary of the IEE would be translated into local language and it would be made available to local people at SIO office. 218. As per the ADB SPS 2009, for Environment Category “B” subproject, the following documents will be submitted to ADB for disclosure on ADB’s website. • Draft IEE • Final IEE • A new or updated IEE and corrective action plan prepared during project implementation, if any, and • Environmental Monitoring reports

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

7. GRI EVANCE REDRESS MECHANI SMS

219. A joint social and environmental redress mechanism will be implemented under the Project. The Grievance Redressal Committee will be constituted at PMU level comprising of the Project Director, Resettlement Officer, Environmental Officer, representatives from local non-governmental organization(NGOs), elected representatives from Municipality / Panchayat, representatives of affected persons including vulnerable groups and women in the committee. It is proposed GRC will meet regularly (at least once a month) on a prefixed date. All the grievances of the people will be reviewed and resolved within 6 weeks of the date of submission. Through public consultations and disclosure, the APs will be informed that they have a right to grievance redressed. The APs can call upon the support of the NGO to assist them in presenting their grievances or queries to GRC. 220. Grievances and suggestions from local and affected people may come-up related to inappropriate implementation of the project and components of EMP. Grievance re-dress mechanism shall be translated in and posted to the respective village/Panchayat office by Contractor on behalf of the OIIAWMIP at least 6 weeks prior to commencement of construction works. 221. The expected range of grievances to be handled through this mechanism will encompass but not limited to the following: i) nuisance from noise, dust, borrow earth, disposal of spoil and temporary blocking of access; ii) contamination of receiving water from runoff iii) emissions from increase vehicular traffic and stationary sources like hot mix plant, WMM etc., ;iv) conflict between local residents and migrant workers; v) ownership of vegetation for clearing; and vi) damage compensation. These issues will be addressed through acknowledgement, evaluation and corrective action and response approach. Grievances from public or stakeholders concerning the project and EMP implementation will be received by the concerned Executive Engineer (SIO Manager) of the sub-project. The Executive Engineer shall refer the application to PD, PMU who with the help of Construction Management Specialist, Quality Control and Assurance Specialist and Environment specialist of ISPMC then assess the grievances/suggestions and if they are found to be genuine and acceptable, shall be moved to GRC and they will be resolved within 6 weeks from the date of receipt. In site the Contractor shall provide a sign board notifying the contact details of the GRC 222. This mechanism is non-judicial in nature and does not preclude the affected people coursing their grievances to the courts. The corrective action will be started as per the action plan indicated to the stakeholder. The action taken and the outcome shall form a part of half yearly report to ADB.

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

8. ENVI RONMENTAL MANAGEMENT PLAN 8.1 General

223. This chapter describes the Environmental Management and Monitoring Plan (EMP) to mitigate the likely adverse impacts arising from this project. This chapter also provides institutional requirements and environmental monitoring plans required to effectively implement the environmental mitigation measures into the project. 8.2 I nstitutional Arrangement

224. The Figure 12 shows the organization structure of the DoWR for the OIIAWMIP project.

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

Note:EIC – Engineer in Chief; C.E –Chief Engineer; S.E- Superintendent Engineer; E.E – Executive Engineer, A.E – Assistant Engineer, J.E – Junior Engineer; CAD – Command Area Development, O &M – Operation& Maintenance; D.D – Deputy Director; PPSU – Pani Panchayat Support unit; ISPMC- Institutional Strengthening and Project Management Consultants)

Figure 12 Organization structure of the DoWR for the OI I AWMI P project

The key agencies involved in implementation of EMP are:

225. DoWR is the Executing Agency for OIIAWMIP. The DoWR has been reorganized to constitute a Command Area Development and Participatory Irrigation Management Directorate (CAD&PIM Directorate) for more effectively integrating irrigation system management and on-farm development through participation of the Pani Panchayats. The Project is being implemented through the existing setup technically headed by EIC. Special Secretary, DoWR has been designated as the Engineer-in-Chief for OIIAWMIP. Special Secretary, DoWR will advise and guide on overall implementation matters including PIM-CAD. 226. A Project Management Unit (PMU) has been established within the CAD&PIM Directorate with a Project Director of the rank of Chief Engineer operating under the overall guidance of Additional Secretary cum Director CAD - PIM with the overall responsibility of program implementation. Chief Engineer cum Project Director, PMU will exercise the powers vested by the OPWD code for execution of all civil works. At the field level Sub-project Implementation Offices (SIO) have been formed to implement the program. For Major irrigation sub-projects the concerned Superintending Engineer is the Sub-project manager and the concerned Executive Engineer is the Sub-project manager for Medium irrigation Sub-projects. The Sub-Project Manager, who is a Superintending Engineer (SE) for major irrigation systems and an EE for medium schemes, will manage the Technical Cell as well as monitor and guide the CAD and PP Support Cells for effective integration and coordination of the sub-project activities, under the support and guidance of PMU, EIC (P&D), and ISPM Consultants provided through regular PMU-SIO meetings. 227. DoWR for effective implementation of Tranche-2 sub-projects under OIIAWMIP proposes to create one Circle, four Divisions, 12 Sub-Divisions under the Chief Engineer – cum – Project Director, PMU. Circle: One Superintending Engineer S.E will be in charge of circle office. He will be responsible for the managing the Technical Cell as well as monitor and guide the CAD and PP Support Cells for effective integration and coordination of the sub-project activities. Division: Under each division one Executive Engineer (E.E) will be in charge of the division for, processing tender and bid documents executing the works, check measurement etc. He will ensure the quality of the ongoing works etc. Sub-Division: Under each sub-division Assistant Engineer / Asst. Executive Engineer shall be incharge of the sub-division office. He will be supported by field functionaries like Junior Engineer and other field for execution, check measurement, monitoring the works and ensuring the quality of the work. 228. The Junior Engineer at the field level will be responsible for day to day environmental monitoring and the overall supervision and responsibility of EMP implementation will be with the concerned SIO ( S.E for Major sub project and E.E for medium sub project).

8.3 I nstitutional Strengthening and Project Management Consultants (I SPMC)

229. The ISPMC will have an Environment Specialist, Resettlement Specialist and Indigenous group Specialist who will support the PMU in advising and monitoring the EMP measures with help of SIO Staff and WUAs. The ISPMC will assist in reviewing all the contractors monthly environmental reports submitted by Contractors through SIO in consultation with PMU. They will assist the PMU in preparing environmental monitoring reports and other reports like preparation of IEEs, RP and social assessment reports 8.4. Responsible for carrying out monitoring measures - Staffing Requirements

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

230. As per the “ Environmental Assessment and Review Frame work (EARF) prepared for the project it states that “PMU will be responsible to undertake (i) environmental screening at subproject identification stage; (ii) preparation of IEEs/EIAs at subproject appraisal stage; and (iii) environmental management and mitigation during subproject implementation and operational stage. At appraisal, IEEs /EIAs will be done with the engagement of consulting firms who would be guided by the project environmental specialist. Environmental management and mitigation will be undertaken by the construction contractors during construction phase under the supervision of the designated staff in the subproject management offices (SIOs) and monitored by PMU environmental cell. The consultants mobilized for institutional strengthening and project management will also be entrusted to provide necessary capacity development of the DOWR engineers and SIO (S.E for major sub project and E.E for medium subproject) in terms of environmental planning and management”.

231. The PMU / SIO of DoWR assisted by the WUAs, and the Institutional Strengthening and Project Management Consultants (ISPMC) will be guiding the implementation of the EMP. During project works the responsibility to implement environmental mitigation and safeguards shall be primarily on the Contractor for main canal, distributaries and minors and monitored by the SIO (S.E for major sub project and E.E for medium subproject). The field level Junior Engineer shall be made responsible for monitoring the EMP activities of the Contractors on a day to day basis. The SIO staff and WUAs with the help of ISPMC, Environment Specialist will monitor the EMP implementation of the Contractor. 232. While the implementation of sub-minors shall be on WUAs and monitored by SIO. Pani Panchayat Support Unit (PPSU) is the state level apex agency who is responsible for strengthening the PP activities. Under PPSU one Environmental Monitoring Specialist was recruited to provide capacity building of the PPs. He may be made responsible for the monitoring of WUAs along with SIO staff and these will work under the overall guidance of ISPMC. The WUAs will end up leading O&M responsibilities with the help of Environmental Monitoring Specialist of PPSU, CAD unit. 233. The current structure of DoWR indicates that they have no environmental management system. The WUAs will end up leading O&M responsibilities. Neither DOWR nor the WUAs are currently in a position to assume EMP responsibility. Their institutional capabilities and capacities will have to be developed and strengthened under the Project. 234. So for effective monitoring there is a need to designate or made in charge one Junior Engineer (Technical / Works) from each sub-project to look into the environmental aspects, he may be named as “ Environmental Co-ordinator” who would be working under the guidance of National Environment Specialist- ISPMC in addition to his regular duties. The Environmental Co-ordiantors would be trained time to time; this will ensure proper and systematic environmental monitoring and ensuring timely compliances from the contractors. In addition Junior Engineer (O&M) would also be trained along with the Junior Engineer (Technical / Works) who will monitor after the completion of works i.e. during “Operation and Maintenance Period”. 235. To make environmental monitoring integral in to the system and since the projects are of larger scale there is a need for systematic and continuous monitoring. To ensure systematic monitoring the ISPMC had developed formats presented in Annexure-.16 & 16a. The format has to be filled up and submitted by the Contractor / WUAs to SIO staff on a monthly basis. The Contractors / WUAs and SIO shall be trained for filling up the format during the project period. 236. As per the Technical Specification for construction of civil works of ADB assisted schemes, DoWR, Odisha Section – 6 Clause – 1.23 – Sub – Clause 1.23.2 Contractors shall be designate as “Safety Officers” and he shall also be made responsible for environmental issues and he shall be named as an “Environmental Co-ordinator” from the Contractors side and he shall also be trained on the environmental issues. 8.5 Reporting System or Responsible for Reporting

237. Reporting system suggested under this project is three tier systems:

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

¾ Reporting of the Contractor and WUAs to the SIO staff.(For the civil works implemented by Contractors monitoring shall be done SIO with the help of ISPMC and for the civil works carried out by WUAs monitoring shall be done by SIO with the help of PPSU Environmental Monitoring Specialist). ¾ Reporting of ISPMC, Environment Specialist after evaluating the contractor reports and evaluating the indicators at PMU level (The reports submitted by Contractors shall be evaluated by ISPMC Environment Specialist and feedback provided to SIO and PMU); In addition, ISPMC, Resettlement Specialist for resettlement issues and Vulnerable Group Specialist responsible for preparing Indigenous People Development Plan (IPDP) and for any social related issues. ¾ PMU reporting to ADB and PMU shall submit annual environmental monitoring report to ADB

238. Environmental monitoring suggested involves regular checking of the parameters suggested in the environmental management plan to ascertain the mitigation measures are achieved as the work progress. It provides the necessary feedback and midcourse corrections for project management to keep the program to achieve the expected outputs. 239. The reporting system starts with the construction Contractor who is the main executor of the implementation activities. The Contractor will report on a monthly basis to SIO staff as per the check list provided in the Annexure16 to the Junior Engineer. Junior Engineer at the field will be responsible for ensuring EMP implementation in consultation with SIO, he on the basis of daily visits to the site and observations evaluates and submit to the SIO manager. This will form the basis for evaluating the Contractor on the implementation process.

240. For the works executed by Pani Panchayat or WUAs similar simplified reporting system is proposed, the PPs have to complete a check list Annexure 16a and submit to the SIO staff, the Environment Monitoring Specialist recruited under PPSU, CAD unit will evaluate on a monthly basis and submit to the PMU and ISPMC. 241. The Environment Specialist, ISPMC during period visits spot checks the sites and evaluates the monthly reports submitted by the Junior Engineer and PPSU Environmental Monitoring Specialist and on this basis brief quarterly reports would be prepared and submitted to the PMU and on a yearly basis a detailed report with corrective action plans would be prepared. 242. The PMU will submit the annual reports prepared during the construction phase to the ADB. The PMU in the monthly meetings should discuss the implementation of EMP with the SIO staff and ISPMC and suggest remedial measures to the contractor.

8.6 Environmental Mitigation Plan

243. An Environmental Management and Monitoring Plan (EMP) is key to ensure a safe and clean environment. The desired results from the environmental mitigation measures proposed in the project can only be obtained with a management plan to assure its proper implementation & function. The EMP outlines the plans for the proper implementation of mitigation measures to reduce the adverse impacts arising out of the project activities. The EMP has been prepared addressing issues such as: ¾ Mitigation measures for abatement of adverse impacts caused during the construction and operation stage; ¾ Details of management plans; ¾ Institutional set up identified/recommended for implementation of the EMP; ¾ Post project environmental monitoring programme to be undertaken;

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

¾ Expenditures for environmental protection measures and budget for EMP. ¾ The major impacts due to different project activities and their mitigation measures have been identified in Chapter 5. The environmental parameters checklist for the anticipated impacts and suggested mitigation measures with implementation and supervision responsibility during Pre construction Table 29 and 30; Pre construction activity for the works executed by contractor Table 31, Construction phase for the works executed by contractor Table 32; Preconstruction activities for the works executed by WUAs Table 33 and Construction phase for the works executed by WUAs Table 34 and Operation & maintenance phases Table 35 for the kanjhari subproject is shown below:

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

Table 29 Environmental Parameters Checklist for Anticipated Impacts and Mitigation Measures for Kanjhari Sub-project - Pre Construction Activity (Impacts due to Location)-Environmental Mitigation Plan

Sl. I EE Responsibility Remarks No Significant Impact Implementa Super Field / Activity Anticipated I mpact Recommended Mitigation Measure No Significa tion vision nt Modera Minor Major I mpact te

1 Land Acquisition Not likely to cause specific No land acquisition is involved only existing ROW is being SIO PMU environmental problems as long as used steps are made to select sites √ which are not located in protected/inhabited areas etc.

2 Encroachments During the interaction with PP Joint Survey conducted by PMU & ISPMC R&R Specialist SIO PMU & members it was revealed some side and found no encroachments which will affect the civil ISPMC cutting lands have been converted works or with in Right of Way. Hence no RP is prepared R & R into agricultural lands or for the sub project Speciali encroached with in the command st while preparing micro plans SIO with the help of WUAs area, these may get affected. the assessment of areas for identifying the legal and illegal outlets and increase the scope for improved water planning and distribution to the tail end users. √

During the field visit and during interaction with PP members and SIO staff it was revealed some areas like forest, grazing land have been encroached and started cultivation few years back.

3 Utilities Electric poles/ electric lines within Mostly these may not get affected in the main canal if SIO PMU& the ROW may get damaged or any likely to affected in the minor or sub-minors PMU/ ISPMC some need to be shifted mainly in SIO should Identify the electric poles which may be a the minors and sub-minors hinderance as per the designs. During survey and √ detailed estimate a contingency plan for shifting if necessary should be done and the utilities need to be shifted if necessary with the appropriate permission from the electicity department as per the provisions

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

Sl. I EE Responsibility Remarks No Significant Impact Implementa Super Field / Activity Anticipated I mpact Recommended Mitigation Measure No Significa tion vision nt Modera Minor Major I mpact te

4 Tree cutting Removal of trees planted on the To the possible extent the desig should reduce or avoid SIO PMU& embanKment with in the ROW tree cutting. ISPMC If any trees need to be removed from the ROW before actual commencement of work, it shall be done in permission with the State Forest Department.

Stacking, transport and storage of wood shall be done as per the relevant norm. All efforts shall be made to preserve trees including evaluation of miinor deisgns , adjustmentment / alternatives to save trees to the possible extent.

5 Forest Areas The canal system (main canals, No additional impact on forest land as it is an existing SIO PMU& distributaries, minor and sub- canal system where some sections of main canals, ISPMC minors) in some sections pass distributaries both minor and sub-minors pass through through the reserved forest, the reserved forest, protected forest and village forests √ protected forest and village forests of Keonjhar division. Permission from State forest of Keonjhar division. department need to be taken for the sections of the canal passing through R.F before undertaking repair/

renovation.

6 Elephatn Path As the sub-project falls adjacent to As the sub-project falls adjacent to the existing elephant SIO PMU& the existing elephant transit path transit path near the dam portion, left main canal tail end ISPMC near the dam portion, left main portion and Padampur minor passes through the existing √ canal tail end portion and elephant transit path and sitting of camps/machines/ Padampur minor passes through materials shall not be avoided by the contractor. the existing elephant transit path

IEE & PC Kanjhari 4 August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

Table 30 Environmental Parameters Checklist for Anticipated Impacts and Mitigation Measures for Kanjhari Sub-project Pre Construction Activity (Impacts during Design and Survey)-Environmental Mitigation Plan

Sl. I EE Responsibility Remarks No Significant Impact Implementa Supervis Field / Activity Anticipated Impact Recommended Mitigation Measure No Significa tion ion nt Modera Minor Major I mpact te During detailed, the PMU/ SIO with the help of survey team 1 Trees cutting Change in Aesthetic value √ SIO staff with PMU, Some trees and in consultation with Deisgn Engineers shall assess the the help of Design are noted number of trees that may likely to be affected due to the survey team engineer, on the designs. ISPMC canal If some trees may be required to be cut to the possible embanKme extent trees cut would be minimized Some part of the Project nts budget shall be consider for tree-planting activities wherever places available along the canal / distributaries. Suitable species suitable to the area need to be selected in consultation with horticultural department / Forest Department. The proposed tentative budget is shown in Table 38 This would also have the added value of employing water conservation methodologies and thus increased sustainability of the system and stability of canal slope. The number of electric poles that need to be shifted shallll be 2 Utilities Electric poles/ electric lines within √ SIO staff with PMU, identified, if necessary to be shifted SIO shall include some the ROW may be damaged or some the help of Design contingency plan for shifting in consultation with the need to be shifted in minors and survey team engineer, electricity department.. sub-minors ISPMC

3 Impact on Water losses leading to reduced During project planning, desilting, lining of the canals and √ SIO Staff PMU and productivity due to efficiency of the canal. minor repairs to existing structures will improve operation of Design water losses Engineer, the canals and positively impact on the hydrology of the ISPMC project. Modifications of drop structures and regulators, and construction of permanent outlets with gates will improve the efficiency of canal operation and reduce water losses.

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

Sl. I EE Responsibility Remarks No Significant Impact Implementa Supervis Field / Activity Anticipated Impact Recommended Mitigation Measure No Significa tion ion nt Modera Minor Major I mpact te There are some encroachments PMU 4 Encroachments √ SIO Staff within the command area like forest, The scope for improving the designs or carrying capacity of & ISPMC grazing etc have been converted to the minors and sub-minors to support the increased command agricultural lands few years back areas (encroached forest land and grazing lands) without effecting the tail end users. Few encroachers in the forest areas are being given right to cultivate, so to check the new encroachments PMU / SIO shall for a team along with WUAs, VSS members and Forest guard/Forest staff who will monitor the encroachments if any during and after construction to check the increase of encroachments with in the forest areas. PMU 5 Elephant transit Impact on existing elephant transit √ SIO Staff The left main canal tail end portion and Padampur minor & ISPMC path path. passes through the existing elephant transit path designs may

accommodate Foot Bridge at left main canal- tail end portion to facilitate easy movement of elephants and people to cross the canal. PMU 6 Proposed Tube well Scope for changes in ground water A preliminary need assessment and identification of potential √ SIO Staff Drilling sites for the proposed drilling based on the peoples need to be carried out. The sites or locations identified shall be away from dumps, refuse piles, storage facilities, pit toilets, fields fertilized with dung, septic tanks, drains , away from flooding areas. Identify the locations which are socially acceptable Care shall be taken not to locate the tube wells adjacent to the existing tube wells , the distance between two tube wells proposed shall be as per the Odisha State Ground water department rules. Odisha state ground water department should be consulted for the proposed depth and precautions while drilling, and suitability of the proposed site for quantity and quality before finalization of the drilling site by the SIO.

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

Table 31 Environmental Parameters Checklist for Anticipated Impacts and Mitigation Measures for Kanjhari Sub Project (Main canal, Distributaries and Minors executed by Contractors) - Pre Construction Activity (Construction Contractor) --Environmental Mitigation Plan

Sl. I EE Responsibility Remarks No Significant Impact Implementa Super Field / Activity Anticipated I mpact Recommended Mitigation Measure No Significa tion vision nt Modera Minor Major I mpact te Contractor shall avoid establishment of camp / plant in 1 Establishment of Camp / Disruption to traffic flow and √ Contractor SIO forest areas and elephant transit paths. Plants sensitive receptors and change land Staff, Contractor shall prioritize areas with in or nearest use as well as aesthetic value of PMU possible vacant space within the subproject without area and affecting property, forest, vegetation, elephant paths ISPMC drinking water sources and away from the water bodies and the canal system. All construction plants shall be sited sufficiently away from the elephant paths, settlements and agricultural operations or any commercial establishments. Such plants shall be located at least 100m away from the nearest dwelling preferably in the downwind direction. The Contractor shall submit a detailed layout plan for all

such plant sites established and approved by the SIO manager. Arrangements to control dust pollution through provision of wind screen, water sprinklers and dust extraction systems shall have to be provided at all such sites. If any contractor has to establish crushers, hot mix plants and batching plants shall comply with the requirements of the relevant emission control legislations. Consent for Establishment and Operation from state pollution control board Odisha shall be obtained before establishment and operation and a copy to be submitted to the SIO Manager.

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

Sl. I EE Responsibility Remarks No Significant Impact Implementa Super Field / Activity Anticipated I mpact Recommended Mitigation Measure No Significa tion vision nt Modera Minor Major I mpact te 2 Sources of Materials Borrow areas-Extraction of If additional material is required or procured from borrow √ Contractor SIO materials like earth etc., can pits. Finalization of borrow areas for earth and all logistic Staff disrupt natural drainage, vegetation arrangements as well as compliance to environmental and and resulting in accelerated erosion requirements, as applicable shall be the sole PMU and leading to water stagnation, responsibility of the Contractor. ISPMC ponding and pollution Contractor shall identify the potential borrow areas and take permission from SIO manager before operating any borrow areas. Earth material should be taken from barren land or selected borrow area during lean period as per IS Code 1498 after taking approval from SIO Manager. The criteria of selection is as follows: Selection Criteria of Borrow areas is as follows: IS 4701: 1982 No borrow pits shall be dug with in 5m of the toe of the embankment, if the depth of the borrow pit is less than 0.5m it shall be after 5m of the toe of the embankment and if the pit depth shall be more than 0.5m it shall be 10m of the toe of the embankment or within such a distance from the toe of the bank where a 4:1 hydraulic gradient line cuts the ground surface, which ever more. Borrow pits shall not be more than 1m in depth and 25 m in length. A clear distance of 1m shall be left between the pits The bed of borrow pits shall be left reasonably smooth and even. Contractor shall not be permitted to lift any material from the forest areas. The Contractor shall not start borrowing earth from selected borrow area until the mutual agreement is signed between landowner and Contractor. Copy of the document shall be submitted to SIO manager. The Contractor in addition to the established practices, rules and regulation will also consider following criteria before finalizing the locations.

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

Sl. I EE Responsibility Remarks No Significant Impact Implementa Super Field / Activity Anticipated I mpact Recommended Mitigation Measure No Significa tion vision nt Modera Minor Major I mpact te 1) The borrow area should not be located in agriculture field unless unavoidable i.e. barren land is not available. 2) The borrow pits should not be located along the roads. 3) The loss of productive and agricultural land should be minimum. 4) The loss of vegetation is almost nil or minimum. 5) Sufficient quality of soil is available. 6) The Contractor will ensure the availability of suitable earth. The Contractor shall obtain representative samples form each of the identified borrow areas and have these tested at the site laboratory following a testing programme as approved by the concerned Engineer. It shall be ensured that the fill material compacted to the required density.

WUAs have identified potential farmers willing to give earth material, the list of farmers is enclosed as Annexure 4. These potential sites shall be verified for the suitability after finalizing the Contractor and he will enter into mutual agreement with land owners and finalize the borrow areas in consultation with the SIO Manager before operation.

Planning of haul roads for accessing borrow areas shall be undertaken during this stage. The haul roads shall be routed to avoid agricultural areas as well as forest areas as far as possible and shall use the existing village roads wherever possible.

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

Sl. I EE Responsibility Remarks No Significant Impact Implementa Super Field / Activity Anticipated I mpact Recommended Mitigation Measure No Significa tion vision nt Modera Minor Major I mpact te Quarry areas-Extraction of The Contractor shall finalize the quarry for procurement √ Contractor SIO materials like earth etc., can of construction materials after assessment of the Staff disrupt natural drainage, vegetation availability of sufficient materials, quality and other and and resulting in accelerated erosion logistic arrangements. PMU and leading to water stagnation, A preliminary survey has been carried out by the SIO and ISPMC ponding and pollution identified the quarry as shown in Annexure 3. If extraction shall be done, prioritize sites already permitted by the Mining or concerned department,

Contractor shall purchase materials and finalize vendors who have valid permissions. The list of potential crusher who has valid license from State Pollution Control board, Odisha is enclosed for reference as Annexure 2. If other sites are necessary and the contractor want to use, let the contractor obtain necessary permission from the concerned regulatory authority and inform SIO Manager. Sand The sand shall be procured from identified (by SIO)sand √ Contractor SIO mines as far as possible. If Contractor wishes to procure Staff from other sources he shall obtain the lease agreement and of the supplier PMU ISPMC 3 Drilling of tube wells Possibility of drilling tube wells in a The contractor along with SIO staff should locate all the √ Contractor SIO near distance and change in water potential sites proposed for drilling and initiate drilling as Staff quality per the provisions of the contract and PMU ISPMC

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

Table 32 Environmental Parameters Checklist for Anticipated Impacts and Mitigation Measures for Kanjhari Subproject (Main canal, Distributaries and Minors executed by Contractors) - Construction Phase --Environmental Mitigation Plan

Sl. I EE Responsibility Remarks No Significant Impact Implementat Superv Field / Activity Anticipated I mpact Recommended Mitigation Measure No Significa ion ision nt Modera Minor Major I mpact te

1 Inadequate monitoring Potential damages to system likely to Contractor to execute works in accordance with standard √ Contractor SIO during construction stages be maximized as a result of neglect Contract Specification. Provision of site supervisory staff to Staff, on part of contractor. ensure quality control and adherence to contract PMU requirements. Monthly progress reporting and recording of and community complaints/ objections. Issues to be resolved ISPMC jointly with Project (SIO), PMU and ISPMC.

2 Tube well drilling Scope for contamination of water The Contractor after tube well drilling shall purge and √ Contractor SIO decontaminate before it is put to use Staff, Tube well shall be sealed and its pedal shall be sealed PMU properly to avoid mixing of impurities mixing with ground and water ISPMC A concrete pad around the tube well shall be constructed

If any vegetation shall be removed from construction site / 3 Site clearance –Clearing Damage to existing vegetation zone before commencement of construction shall be carried √ Contractor SIO and grubbing out such that damage to the surrounding vegetation other Staff, than identified vegetation proposed for clearing is minimal. PMU and Only ground cover/ shrubs that impinge directly at the work ISPMC site shall be removed prior approval from SIO staff and in consultation with Environment Specialist To the possible extent the materials like stone and other 4 Disposal of debris from Scope for contamination of soil and reusable materials shall be utilized in the construction. √ Contractor SIO dismantling structures and blockage of natural drains and The iron and wood generated if any would be disposed off as Staff, spoil pollution of ground water by a surplus stock and scrap shall be auctioned as per the PMU , dumping of construction spoils procedures of Odisha Water Resources Department. ISPMC

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

Sl. I EE Responsibility Remarks No Significant Impact Implementat Superv Field / Activity Anticipated I mpact Recommended Mitigation Measure No Significa ion ision nt Modera Minor Major I mpact te

Affect agricultural land / forest land The generated cutting material (small qunatity) suitable for 5 Disposal of canal silt and change in land use for stacking filling shall be utlized to the possible extent. √ Contractor SIO Before disposal of silt The remaining mateirals shall be tested for material Staff, of silt chemical suitability and shall be disposed on the spoil bank of the PMU , testing shall canals after toe line with in the ROW. ISPMC be carried out. However, if any excess found shall be dispossed off in old borrow areas, quarries,low lying government areas etc after taking appropriate permission from SIO staff If available in excess after testing for pesticide and heavy metails it can be distributed to farmers for using in agricultural fields. If the silt is found to be contamiinated then it should not be distributed to farmers however the contractor with the help of SIO shall identify low lying waste lands or play grounds and disposed off in that area and some plantation can be made on this area. A provision for turfing the spoil bank is also suggested. Disposal of silt in the forest areas is prohibited. Loss of productive soil and plant Before beginning the construction of embankments the 6 Stripping , Stocking and nutrients – impact on production surface area of ground to be occupied shall be cleared of all √ Contractor SIO Damage to top agricultural roots and vegetable matter and stripped to a suitable depth Staff, soil due to earth work as per IS: 4701 - 1982 PMU , (i) Depth of stripping 5.0 to 7.5 cm for soil ISPMC containaing light grasscover (ii) Depth upto to bottom of ploughed zone usally 15.0 to 22.5 cm in agricultural land. Top soil may be preserved and resued in turfing activities if possible in borrow areas bunds or if excess shall be distributed to farmers for using in the agricultural lands Project activities shall be carried out during lean period and non- monsoon period for minimizing loss.

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

Sl. I EE Responsibility Remarks No Significant Impact Implementat Superv Field / Activity Anticipated I mpact Recommended Mitigation Measure No Significa ion ision nt Modera Minor Major I mpact te

Loss of productive soil and plant Contractor shall not be permitted to borrow areas in forest 7 Earth from Borrow areas nutrients – impact on production areas √ Contractor SIO for construction Contractor shall identify location of borrow areas and get staff, approval from SIO staff and in consultation ISPMC. PMU Earth material should be taken from barren land or selected and borrow area during lean period as per IS Code 1498 after ISPMC taking approval from SIO Manager. Borrow areas should be dug as per IS code :4701 and prior approval from the competent authorities must be taken before execution and mutual agreement with the land owners should be taken by the contractor and ensure the borrow areas should not have any environmental issues like water logging etc. Borroqw pits shall be drained to avoid stagnation of water. The bottom level of pits should be fixed with reference to the prevailing ground slope towards the nearest natural drainage course. Borrow areas should be avoided in agricultural areas as well as forest areas. Required permission should be obtained from the authorized person as stipulated in the Odisha state minor minerals act and if operating in private lands mutual agreement and no objection certificate need to be produced to SIO by the contractor.

Can disrupt natural drainage, The contractor shall obtain materials from approved 8 Quarry operation vegetation and results in accelerated quarries only after the consent of Department of mines and √ Contractor SIO erosion Geology and District Administration. If any crusher need to staff, be established it shall be done after obtaining proper PMU consents for establishment and operation from the statutory and agencies. ISPMC All the materials pruchased shall be from the approved vendors

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

Sl. I EE Responsibility Remarks No Significant Impact Implementat Superv Field / Activity Anticipated I mpact Recommended Mitigation Measure No Significa ion ision nt Modera Minor Major I mpact te Storage of construction materials may Temporary impact – materials should be stored properly 9 Storage of Construction temporary change local land use avoiding agricultural lands and forest lands while working in √ Contractor SIO Only materials like sand, stone the sectioons of the canal passing through forest areas. staff, rehabilitation etc PMU work no and change in ISPMC land use

Deterioration in quality of road Limited construction period, careful planning, 10 Use of access roads and condition and damage of forest cart restrictions on construction workers movements, √ Contractor SIO Transporting of roads wiithin the forest areas adequate monitoring. staff, Construction materials and All existing roads used by vehicles of the contractor or any of PMU Haul Road Management his suppliers of material shall maintain properly during and construction period and clear any materials dropped by the ISPMC vehicles.There is no need for construction new haulage roads within the forest areas where the canal passes, as the canal embanKment itself serves as service road which can be utilised for transporting material and even the forest areas have exiting forest cart roads which can be utilised with the permission of local forest department and they need to be maintained.

IEE & PC Kanjhari 4 August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

Sl. I EE Responsibility Remarks No Significant Impact Implementat Superv Field / Activity Anticipated I mpact Recommended Mitigation Measure No Significa ion ision nt Modera Minor Major I mpact te

Contractor and his material shall cover vehicles while 11 Transporting of materials Dust pollution – nuisances and transporting materials. √ Contractor SIO and operation of health hazards to travelers / Careful planning to minimize and offset losses staff, equipment neighbors / workers Construction practices in accordance with PMU Specification, community consultation prior to detailed and The areas adjoining to ISPMC construction sites would be design and adequate monitoring shall be carried out subjected to the air pollution Temporary impact on air quality shall be mitigated by from both due to construction using water sprinklers. Trucks carrying dirt, earth work (including operation Of material, sand and metal to and from construction site, equipments) and vehicle should be limited and wetted to prevent material being movement with construction spilled on public roads. materials Necessary protection has to be taken to meet relevant emission standards for all construction machinery and vehicle, maintaining construction equipment in good condition and servicing diesel engines for reduction of emissions. The contractor shall ensure all the vehicles, equipments and machinery used for construction are well maintained and confirm that emissions levels comply with the relevant statutory requirements of CPCB and Motor Vehicle Rules

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

Sl. I EE Responsibility Remarks No Significant Impact Implementat Superv Field / Activity Anticipated I mpact Recommended Mitigation Measure No Significa ion ision nt Modera Minor Major I mpact te

12 Noise from vehicles, plants Nuisances to travelers/ workers All construction plants and equipment used in construction √ Contractor SIO and equipments and and neighbors if increase in shall strictly conform to the MoEF / CPCB noise standards staff, Vibration hazards sound levels – health hazard PMU All vehicles and equipment used in construction shall be and fitted with exhaust silencers ISPMC Regular servicing of all construction vehicles and machinery shall be done regularly and during servicing the effectiveness of exhaust silencers shall be checked All the construction sites with in 150m of the nearest habitation, noisy construction work such as crushing, operation of DG sets and any high noise construction equipment shall be stopped during night time between 10.00 pm and 6.00 am. Working hours of the construction activities around sensitive areas like schools / hospitals upto a distance of 100m shall be restricted.

13 Contamination of water Water pollution from fuel and The contractor shall procure fuel from the nearest oulet if √ Contractor SIO due to fuel and lubricants lubricants any minor storage if he does he shall ensure the land is not staff, and construction waters contaminated. PMU and Contractor shall avoid oil spillage etc. ISPMC Contractor shall not wash his vehicle in the canals Contractor shall ensure or install equipment in such a way that the waste water doesn’t enter the canal during monsoon period.

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

Sl. I EE Responsibility Remarks No Significant Impact Implementat Superv Field / Activity Anticipated I mpact Recommended Mitigation Measure No Significa ion ision nt Modera Minor Major I mpact te

Close consultation with community during planning and 14 Interference with existing Disruption of services and land design stages necessary, Few sections of the canals (left √ Contractor SIO road network and traffic, uses and settlements adjacent main canal RD 0.800; 13.100 and 15.600Km and right main staff, blockage of access ways. to the canal. Road in some canal RD 2.480 and 11.600Km) people are crossing the PMU Restriction on movements sections runs parallel to canals. canals to reach the either side of the roads, so construction and of communities of new bridges are proposed at these locations, so ISPMC Contractor while working at these places he ensures proper safety requirements. Construction implementation in accordance with specification, prior agreement with community on alignment of access roads and irrigation infrastructure, and monitoring is required Contractor shall if necessary prepare a traffic management plan in consultation with the local police and ensure adequate safety measure. Employment of stringent construction practices and 15 Soil Erosion and Siltation Degraded embanKments, monitoring √ Contractor SIO damage to soil and general land Confirming excavations opearions and slope stabilisation staff, value. Increased sedmentation work during the dry season only and compaction in main PMU build-up and clogging of canal by powered road roller and vibtratory roller and in the and surrounding waterways. distributaries, minors and sub-minors by ordinary compaction ISPMC Careful construction planning for surface protection particularly before monsoon season and provision of turfing and plantation. Plantation can be taken up on the canal embaKments with the available funds under plantation and also with the other ongoing shcemes of Govt. Odisha like social forestry programmes etc. Damage to natural drainage patterns Assessment of existing drainage channels during 16 Stocking materials or construction stages. Contractor to maintain natural drainage, √ Contractor SIO Blockage of natural Presently natural Drains are stipulate in Contract Specification. Provision of site Staff, drainage with materials dominat with weeds supervision during construction implementation. PMU and ISPMC

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

Sl. I EE Responsibility Remarks No Significant Impact Implementat Superv Field / Activity Anticipated I mpact Recommended Mitigation Measure No Significa ion ision nt Modera Minor Major I mpact te

Workers health would get affected Contractor shall provide the necessary personnel Protective 17 Personnel Safety Measures Equipment (PPE) like foot wear, gloves, protective goggles √ Contractor SIO for Labour and eye –shields etc for workers emplyed in concrete, Staff, crusehrs, welders and bitumen work PMU Ear plugs to workers exposed to loud noise and workers and working in crushers etc if the contractor establishes. ISPMC The contractor shall comply with all the regulations regarding safe scaffoldiing, ladders, working platforms, excavations and safe emans of entry and engress The contractor shall not employ any person below age of 14 years for any work and no pregnant women. The contractor shall comply with all the relevant provisions of the Orissa Buidlings and other Construction Workers ( Regulations of Employment and conditions of service) Rules 2002 and shall also comply with the precautions as required for ensurig the safety of thw worKmen as per International Labour Organisation (ILO) Convention No 62 as far as thise are applicable to this contract. Disruption of services and may lead The contractor shall take all necessary measures for 18 Traffic and Safety to accidents maintining the traffic during construction and errect safety √ Contractor SIO barricades, safety ribbons and safety boards including sign Staff, boards, flags and other measures as per the requirement PMU and ISPMC

Loss of public / workers health status Project staff to provide basic health and safety trainings to 19 Protection of public and all construction workers and providing periodic health check √ Contractor SIO workers health and safety ups and AIDS awareness camps Staff, PMU and ISPMC

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

Sl. I EE Responsibility Remarks No Significant Impact Implementat Superv Field / Activity Anticipated I mpact Recommended Mitigation Measure No Significa ion ision nt Modera Minor Major I mpact te

Scope for electric socks and While giving level or marking workers should ensure they 20 Risk from Electric Poles / electrocution hazard take preventive measures while working with electric lines. √ Contractor SIO lines and electrical The contractor shall take all required precautions to prevent Staff, equipments danger from electrical equipmetns and esnures that he PMU doesn’t place or stack any material that may cause danger and or inconvenince to any person or public ISPMC All machines and equipments and lighting used will be as per the IS standards and shall mainatian properly withoout any defects. Along the canal side few trees are Close consultation with community prior to detailed design to 21 Damage to different flora presnt- during renovation work those identify important flora/fauna habitats. Careful planning of √ Contractor SIO No forest land / fauna habitats trees will be felled infrastructure alignment prior to construction/ Staff, exist along the implementation. Stipulate in Conditions of Contract and PMU canal provision of site supervision. and ISPMC The Contractor and WUAs will obtain the permission from state forest department while working in the reserved forests. Contractor shall ensures that no trees shall be cut by the workers while working in the forest areas Contractor shall ensure the workers are not involved in any hunting or poaching areas Contractor shall not create paths existing cart tracks shall be used or canal service road shall be utilized. The Contractor shall ensure while working in forest areas, all works shall be carried out during day time only.

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

Sl. I EE Responsibility Remarks No Significant Impact Implementat Superv Field / Activity Anticipated I mpact Recommended Mitigation Measure No Significa ion ision nt Modera Minor Major I mpact te

The Contractor shall not dump material in the forest areas only existing ROW available within the canal shall be used for dumping / storing materials. The Contractor shall not be permitted to establish Camps / labour camps within forest areas. Plantation of trees along the irrigation canal compensate loss of flora Contractor shall take reasonable precaution to prevent his workers from damaging any flora or fauna of the area including fishig or hunting of any animals in the area. If by chance if the contractor sights any animal (wild) the contractor shall inform the SIO staff and Environment Specialist and need to be reported to the State Forest Department immeidately and shall take appropriate steps / measures in consultation with Forest Department Officials. Non availability of irrigation water and 22 Temporary closure of Consultation with local Water Users Associations members or √ Contractor SIO impact on production and livelihood Panu Panchayt memebers befor closing the canal irrigation system of farmers Staff, The construction activities will be scheduled after Kharif crop PMU period only and ISPMC Proper information shall be given to the farmers By Chance if any Archaeological While excavating or dismantling any structure if any fossils, 23 Digging activity – Chance property is found while digging coins, articles of value / antiquity and remians of √ Contractor SIO found Archaeological archaelogical interest discovered on the site shall be the Staff, property property of the Government and shall be dealt with as oer PMU the provisions of the relevant legislation and ISPMC The Contractor shall take reasonable precautions to prevent his worKmen or any other persons from damaging or removing any such articles, if any articles found shall be brought to the notice of SIO and Environment Specialist and shall seek the direction of Archaelogical Survey of India (ASI) before contractor recommencing the work

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

Sl. I EE Responsibility Remarks No Significant Impact Implementat Superv Field / Activity Anticipated I mpact Recommended Mitigation Measure No Significa ion ision nt Modera Minor Major I mpact te

Scope for providing improper The Contractor shall provide the basic accomodatios as per 24 Provision of Basic accomodation and basic amenities to the provisions of the Orissa Building and Construction √ Contractor SIO Ameneties and proper workers Workers Rules Staff, accomodation The location and layout of the labour camps shall be PMU provided to the SIO staff and take his approval and The Contracator will ensure all the basic amenities like ISPMC provision of drinking water at work site and camps and proper sanitation facilities and arrangement for eating the food. The drinking water he provides shall be as per the IS 10,500. Scope for not clearing materials from The Contractor shall ensure that he clears all the unwmanted 25 Clearing of site before the site especially cutting materils materials from the canal bed which may effect or obstruct √ Contractor SIO monsoon and from the canal bed and materiasl after releasing the water into canal Staff, Demobilization of used for construction In the tube wells drilled areas pits if any removed shall be PMU contractor refilled and All excess materials and debris shall be cleared ISPMC

Scope for wrong species selection and SIO shall consult horticultural department before selecting 26 Tree plantation not able to survive the tree species that would be planted along the canal √ SIO staff PMU Approriate distance shall be maintained and Regular and maintenance shall be carried out. ISPMC

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

Table 33 Environmental Parameters Checklist for Anticipated Impacts and Mitigation Measures for Kanjhari Sub Project( Sub Minors executed by WUAs ) - Pre construction Activity --Environmental Mitigation Plan

Sl. I EE Responsibility Remarks No Significant Impact Implementat Superv Field / Activity Anticipated I mpact Recommended Mitigation Measure No Significa ion ision nt Modera Minor Major I mpact te

1 Sources of Materials Extraction of materials like earth WUAs shall identify the potential borrow areas and take √ PP/ WUAs SIO etc., can disrupt natural drainage, appropirate permission from the regulating agencies and Staff vegetation and resulting in shall enter into mututal agreements with the land owners. and accelerated erosion and leading to WUAS shall obtain SIO manager permission before operating PMU any borrow areas. water stagnation, ponding and ISPMC pollution Selection Criteria of Borrow areas is as follows: IS 4701: 1982 No borrow pits shall be dug within 5m of the toe of the embankment, if the depth of the borrow pit is less than 0.5m it shall be after 5m of the toe of the embankment and if the pit depth shall be more than 0.5m it shall be 10m of the toe of the embankment or within such a distance from the toe of the bank where a 4:1 hydraulic gradient line cuts the ground surface, which ever more. Borrow pits shall not be more than 1m in depth and 25 m in length. A clear distance of 1m shall be left between the pits The bed of borrow pits shall be left reasonably smooth and even. WUAs shall not be permitted to lift any materials from the forest areas. WUAs shall purchase materials and finalize vendors who have valid permissions in consultation with SIO staff.

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

Table 34 Environmental Parameters Checklist for Anticipated Impacts and Mitigation Measures for Kanjhari Sub Project ( Sub Minors executed by WUAs ) - Construction Activity --Environmental Mitigation Plan

Sl. I EE Responsibility Remarks No Significant Impact Implementat Supervisi Field / Activity Anticipated I mpact Recommended Mitigation Measure No Significa ion on nt Modera Minor Major I mpact te

1 Inadequate monitoring Potential damages to system likely to WUAs to execute works in accordance with standard √ PP/ WUAs SIO Staff, during construction stages be maximized as a result of neglect Contract Specification. PMU and on part of contractor. ISPMC

2 Site clearance –Clearing Damage to existing vegetation If any vegetation shall be removed from construction site / √ PP/ WUAs SIO Staff, and grubbing zone before commencement of construction shalll be carried PMU and out such that damage to the surrouding vegetation other ISPMC than identifieid vegetation proposed for clearing is minimal. Only ground cover/ shrubs that impinge directly at the work site shall be removed prior approval from SIO staff and in consultation with Environment Specialist

3 Disposal of debris from Scope for contamination of soil and To the possible extent the materials like stone and other √ PP/ WUAs SIO Staff, dismantling structures and blockage of natural drains and reusable materials shall be utlized in the construction. PMU , spoil pollution of ground water by The iron and wood generated if any would be dispossed off PPSU and dumping of construction spoils as a dead stock and scrap shall be autioned as per the ISPMC procedures of Odisha Water Resoruces Department.

4 Disposal of canal silt Affect agricultural land and change in The sub-minors shall generated very low quantities of √ PP/ WUAs SIO Staff, Before land use for stacking of silt cutting material if any generates material suitable for filling PMU , disposal of shall be utlized to the possible extent. The remaining PPSU and silt chemical mateirals shall be utilized in filling in the low lying sections ISPMC testing will the canal bank within the available ROW be required If available in excess after testing for pesticide and heavy metails it can be distributed to farmers for using in agricultural fields

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

Sl. I EE Responsibility Remarks No Significant Impact Implementat Supervisi Field / Activity Anticipated I mpact Recommended Mitigation Measure No Significa ion on nt Modera Minor Major I mpact te

5 Stripping , Stocking and Loss of productive soil and plant Before beginning the construction of embankments the √ PP/ WUAs SIO SIO Damage to top agricultural nutrients – impact on production surface area of ground to be occupied shall be cleared of all Staff, PMU soil due to earth work roots and vegetable matter and stripped to a suitable depth , PPSU as per IS: 4701 - 1982 and (i) Depth of stripping 5.0 to 7.5 cm for soil containaing light ISPMC grasscover (ii) Depth upto to bottom of ploughed zone usally 15.0 to 22.5 cm in agricultural land. Top soil may be preserved and resued in turfing activities if possible in borrow areas bunds or if excess shall be distributed to farmers for using in the agricultural lands Project activities shall be carried out during lean period and non- monsoon period for minimizing loss. 6 Earth from Borrow Loss of productive soil and plant WUAs shall identify location of borrow areas and get √ PP/ WUAs SIO areas for construction nutrients – impact on production approval from SIO staff and in consultation ISPMC. Staff, Earth material should be taken from barren land or PMU , selected borrow area during lean period as per IS PPSU Code 1498 after taking approval from SIO Manager. and ISPMC Borrow areas should be dug as per IS code :4701 and prior approval from the competent authorities must be taken before execution and mutual agreement with the land owners should be taken by the contractor and ensure the borrow areas should not have any environmental issues like water logging etc. Borrow areas should be avoided in agricultural areas as well as forest areas. Required permission should be obtained from the authorized person as stipulated in the Orissa state minor minerals act and if operating in private lands mutual agreement and no objection certificate need to be produced to SIO by the contractor.

IEE & PC Kanjhari 4 August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

Sl. I EE Responsibility Remarks No Significant Impact Implementat Supervisi Field / Activity Anticipated I mpact Recommended Mitigation Measure No Significa ion on nt Modera Minor Major I mpact te

7 Quarry operation Can disrupt natural drainage, The WUAS shall obtain materials from approved √ PP/ WUAs SIO vegetation and results in quarries only. Staff, accelerated erosion All the materials pruchased shall be from the PMU , approved vendors. PPSU and ISPMC 8 Storage of Construction Storage of construction materials Temporary impact – materials should be stored √ PP/ WUAs SIO Only materials like sand, may temporary change local land properly avoiding agricultural lands in consultation Staff, rehabilitati use stone etc with local people PMU , on work PPSU no change and in land use ISPMC 9 Use of access roads and Deterioration in quality of road Limited construction period and small quanties of √ PP/ WUAs SIO Transporting of condition materials involved, so care need to be taken and Staff, Construction materials if any damages the WUAs shall maintain PMU , and Haul Road PPSU Management and ISPMC C 10 Interference with Disruption of services and land Close consultation with community during planning √ PP/ WUAs SIO existing road network uses and design stages necessary. since local communties Staff, and traffic, blockage of are involved they will take precautions in protecting PMU , access ways. Restriction the interest and safety of the people living around. PPSU on movements of and Construction implementation in accordance with communities ISPMC specification, prior agreement with community on alignment of access roads and irrigation infrastructure, and monitoring

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

Sl. I EE Responsibility Remarks No Significant Impact Implementat Supervisi Field / Activity Anticipated I mpact Recommended Mitigation Measure No Significa ion on nt Modera Minor Major I mpact te

11 Soil Erosion and Siltation Degraded embankments, damage to Employment of stringent construction practices and √ PP/ WUAs SIO Staff, soil and general land value. Increased monitoring PMU , sedimentation build-up and clogging Confirming excavations opearions and slope stabilisation PPSU and of surrounding waterways. work during the dry season ISPMC Careful construction planning for surface protection particularly before monsoon season and provision of turfing and plantation

12 Stocking materials or Damage to natural drainage patterns Assessment of existing drainage channels during √ PP/ WUAs SIO Staff, Co- Blockage of natural Presently natural Drains are with construction stages. WUAs to maintain natural drainage, PMU , odrination drainage with materials weeds stipulate in Contract Specification. Provision of site PPSU and with CADA supervision during construction implementation. ISPMC division recommend ed 13 Protection of public and Loss of public / workers health status Awareness to workers / staff to provide basic health and √ PPSU SIO Staff, workers health and safety safety trainings to all construction workers PMU , PPSU and ISPMC 14 Risk from Electric Poles / Scope for electric socks and While giving level or marking workers should ensure they √ PP/ WUAs SIO Staff, lines and electrical electrocution hazard take preventive measures while working with electric lines. PMU , equipments The WUAs shall take all required precautions to prevent PPSU and danger from electrical equipmetns and esnures that he ISPMC doesn’t place or stack any material that may cause danger or inconvenince to any person or public

15 Damage to different Along the canal side few trees are WUAS shall take reasonable precaution to prevent his √ PP/ WUAs SIO Staff, flora/fauna habitats presnt- during renovation work those workers from damaging any flora or fauna of the area PMU , trees will be felled including fishig or hunting of any animals in the area. PPSU and If by chance if the WUAS sights any animal (wild) the WUAs ISPMC shall inform the SIO staff and Environment Specialist and need to be reported to the State Forest Department immeidately and shall take appropriate steps / measures in consultation with Forest Department Officials

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

Sl. I EE Responsibility Remarks No Significant Impact Implementat Supervisi Field / Activity Anticipated I mpact Recommended Mitigation Measure No Significa ion on nt Modera Minor Major I mpact te

16 Digging activity – Chance By Chance if any Archaeological While excavating or dismantling any structure if any fossils, √ PP/ WUAs SIO Staff, found Archaeological property is found while digging coins, articles of value / antiquity and remians of PMU , property archaelogical interest discovered on the site shall be the PPSU and property of the Government and shall be dealt with as oer ISPMC the provisions of the relevant legislation The WUAs shall take reasonable precautions to prevent his worKmen or any other persons from damaging or removing any such articles, if any articles found shall be brought to the notice of SIO and Environment Specialist and shall seek the direction of Archaelogical Survey of India (ASI) before WUAs recommencing the work 17 Clearing of site before Scope for not clearing materials from The WUAs shall ensure that he clears all the unwmanted √ WUAs SIO Staff monsoon and the site especially cutting materils materials from the canal bed which may effect or obstruct Demobilization of from the canal bed and materiasl after releasing the water into canal contractor used for construction

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

Table 35 Environmental Parameters Checklist for Anticipated Impacts and Mitigation Measures for Kanjhari- Subproject Operation & Maintenance Phase-- Environmental Mitigation Plan

Sl. I EE Responsibility Remarks No Significant Impact Implementat Supervisi Field / Activity Anticipated I mpact Recommended Mitigation Measure No Significa ion on nt Modera Minor Major I mpact te

1 Overall Environmental Competent O&M plus monitoring Monitoring of irrigation water quality and soil quality will be √ WUAs & SIO PMU and Presently problem necessary. required during operation phase for maintaining best staff PPSU Env. soil and productive environment. Monitoring irrigation Specialist water not The proposed sampling locations, parameters to be tested in monitored and frequency are provided in Table 36 and most of the proposed buget and stage of testing is provided in Table 38 cases of this chapter.

2 Impact on canal system Growth of weeds impairs flow of Regular deweeding and checking of weeds by mechanical √ WUAs & SIO PMU and due weeds growth water and reduces water availability, means or by usage of herbicides if necessary. staff PPSU Env. damages structures and becomes Monitoring habitat of mosquitoes Involving community and PP members in undertaking regular Specialist cleaning and encouraging the PP to prepare compost with the help of agriculture department.

3 Non Restoration of Ecological unbalancing Monitoring of survival of tree planted along the canal √ WUAs & SIO PMU and aesthetics after staff PPSU Env. construction activity overall After completion of works, replanting of economically and Monitoring ecological impact. aesthetically important plants can be ensured along the Specialist canal area. Greening of this area may offset the ecological effects of the clearing and felling of trees during the construction phase. Further in course of time the population of avian fauna may go up and enhance the biological diversity.

4 Modification of soil The changes in agriculture practices Continued use of deep rooting grasses and shrubs to further √ WUAs & SIO PMU and may result in soil modifications, strengthen bunds and terrace walls, and promotion of staff PPSU Env. including increased susceptibility to continued use of organic based practices – use of bio Monitoring slumping, reduced nutrient status and fertilizer and vermi-compost. Specialist impaired structure if the organic matter content is not maintained.

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

Sl. I EE Responsibility Remarks No Significant Impact Implementat Supervisi Field / Activity Anticipated I mpact Recommended Mitigation Measure No Significa ion on nt Modera Minor Major I mpact te

5 Soil and water Increased use of agrochemicals Optimum utilization of chemical fertilizer and discourage √ WUAs & SIO PMU and Presently contamination due to including mineral fertilizers and utilization of long persistence and banned pesticide staff PPSU Env. use of bio- agrochemicals pesticides, which may result in soil Monitoring fertilizer and and water contamination. Use of bio fertilizer and vermi-compost to minimize Specialist organic contamination manure is Post project water quality both surface and ground water, limited silt and soil shall be monitored for the pollutants

• Biodiversity may be affected by 6 Impact on biodiversity increased specialized mono- Awareness raising through the agriculture extension √ WUAs & PPSU PMU and cropping, use of agrochemicals, component and promoting under the agriculture extension PPSU Env. introduction of alien (invasive) component the use of indigenous multi-purpose trees for soil Monitoring species, introduction of high yielding protection, watershed management and cash crop Specialist varieties (HYV). production, optimum use of agrochemical Monitoring of encroached area under Encroachments in the forest areas may be monitored by forest areas may increase preparing the micro plan in which the legal and illegal outlets , forest and agricultural areas can be demarcated. The illegal out lets and changes if any happening in the forest areas falling under respective Pani Panchayats can be brought to the notice of SIO staff and they will communicate to the local forest department. The sub-project may constitute a monitoring team constituting PP members (WUAs), Vana Samrakshan Samities (VSS), SIO staff of the subproject, local forest guard and local forest staff and NGO involved in the PP strengthening who will monitor the encroachments regularly.

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

8.7 Environmental Monitoring Plan

244. Environmental Monitoring is an essential component of any developmental project, it is an integral; part of any environmental assessment process. Any intervention in the form of development shall have complex-inter relationships between people, natural resources, biotic and other forces resulting in a new environment. So it is essential to monitor critical environmental parameters in the pre- project scenario, during and post project scenario. The monitoring program suggested mainly meeting the data base requirements of water resources department on water quality, soil quality and silt etc. The impacts arising through construction are minimal like change in turbidity etc. The parameters suggested for monitoring ground water, surface water, silt and soil is presented in Annexure 17, 17a & b. 245. The monitoring can be carried out by (i) PMU outsourcing to a Laboratory for all the subprojects , or (ii) SIO outsourcing to a laboratory directly. The suggested parameters, description of sampling locations and different stages of monitoring required along with suggested frequency is shown in Table 36 246. The environmental monitoring during the different phases of the subproject implementation can be carried out by a recognized laboratory (i.e approved by State Pollution Control Board, Odisha or National Accreditation Board for Testing and Calibration Laboratory (NABL) or National Accreditation Board for Education and Training (NABET) or any Ministry of Environment and Forests (MoEF) recognized laboratory,

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

Table 36 Showing the Suggested Environmental Monitoring

Sl.No Parameter to Parameter / I ndicators Location Responsibility Frequency be monitored

Pre- Construction Stage ( Baseline data)

1 Ground water Physico, chemical, bacteriological preferably from the SIO /Laboratory Once before start (IS: 10,600) parameters. Total of 34 parameters as per newly drilled tube of the project for IS: 10,600:1991 details in Annexure 17 wells under the project baseline data ( 4 locations)

2 Surface water Physico, chemical, bacteriological Barrage and canal SIO /Laboratory Once before start (IS: 2296: 1992) parameters. Total 39 parameter including water of the project for pesticide residues as per IS: 2296: baseline data (4 locations) 1992,details in Annexure 17a

3 Silt Phyiso- chemical, micro and macro nutrients SIO /Laboratory Once before start and pesticide residue. Total 27 parameters of the project for Silt from Canal including 4 pesticide residue details in baseline data Annexure 17b (4 locations)

4 Soil Phyiso- chemical, micro and macro nutrients (Soils from canal SIO /Laboratory Once before start and pesticide residue. Total 27 parameters Adjacent - agricultural of the project for including 4 pesticide residue details in fields and preferably baseline data Annexure 17b water logged areas)

(4 locations)

Construction Stage

1 Ground water Physico, chemical, bacteriological preferably from the SIO /Laboratory Twice a year for (IS: 10,600) parameters. Total of 34 parameters as per newly drilled tube the construction IS: 10,600:1991 details in Annexure 17 wells under the project of 3 years

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

(4 locations)

2 Surface water Physico, chemical, bacteriological Barrage and canal SIO /Laboratory Twice a year for (IS: 2296: 1992) parameters. Total 39 parameter including water the construction pesticide residues as per IS: 2296: of 3 years (4 locations) 1992,details in Annexure 17a

3 Silt Phyiso- chemical, micro and macro nutrients SIO /Laboratory Twice a year for and pesticide residue. Total 27 parameters the construction Silt from Canal including 4 pesticide residue details in of 3 years Annexure 17b (4 locations)

4 Soil Phyiso- chemical, micro and macro nutrients (Soils from canal SIO /Laboratory Once in a year and pesticide residue. Total 27 parameters Adjacent - agricultural times during including 4 pesticide residue details in fields and preferably construction Annexure 17c water logged areas) period of 3 yrs ( i.e. Between April (4 locations) to May

6 Dust Monitoring Visual Observation Entire Project Corridor SIO Daily

6 Noise Observation Entire Project Corridor SIO Daily

Operation & Maintenance Phase ( Post Project)

1 Ground water Physico, chemical, bacteriological preferably from the SIO /Laboratory Once after after (IS: 10,600) parameters. Total of 34 parameters as per newly drilled tube completion of IS: 10,600:1991 details in Annexure 17 wells under the project works (4 locations)

2 Surface water Physico, chemical, bacteriological Barrage and canal SIO /Laboratory Once after after (IS: 2296: 1992) parameters. Total 39 parameter including water completion of pesticide residues as per IS: 2296: 1992, works (4 locations) details in Annexure 17a

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)

3 Silt Phyiso- chemical, micro and macro nutrients SIO /Laboratory Once after and pesticide residue. Total 27 parameters completion of Silt from Canal including 4 pesticide residue details in works Annexure 17b (4 locations)

4 Soil Phyiso- chemical, micro and macro nutrients (Soils from canal SIO /Laboratory Once after and pesticide residue. Total 27 parameters Adjacent - agricultural completion of including 4 pesticide residue details in fields and preferably Annexure 17c water logged areas) (4 locations)

Kanjhari sub project tentative Locations for monitoring: (1.) Dam (2.) Left Main canal RD 8.20km, (3) Right Min Canal RD 11.80 km (4) ; Mayurpose minor RD 0.300

(Note: The tentative budget proposed is shown in Table 38)

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program(OIIAWMIP)

8.8 Performance I ndicators: 247. The monitoring programme constitutes performance indicators (Table 37) and necessary budgetary provisions.

Table 37 Showing the Performance I ndicators

I ndicator Description of the item Stage Responsibility

Statutory Obtaining CFE & CFO -Statutory Pre construction Contractor Clearance requirement from regulatory bodies and construction Borrow area No. of Borrow areas identified and Pre and Post Contractor verified Construction No. of sites redevelopment and no- objection certificate produced after handing over site Quarry No. of Quarry sites identified and Pre and Post Contractor verified Construction No. of sites redevelopment and no- objection certificate produced after handing over site Disposal sites Quantity of Debris and Spoil disposed Construction and Contractor off Post Construction Dust Control No. of times watering carried out Construction Contractor period Encroachments No. of Encroachments identified Pre and Post SIO No. of encroachers and squatters Construction rehabilitated as per RAP provisions

Environmental No .of times testing( Ground water, Pre, Construction Contractor /SIO monitoring Silt, Surface water, Silt and Soil) carried out and Post Ground water, during construction and operation Construction Surface water and Soil Use of PPE No. of work sites provided with PPE Construction Contractor Usage of safety No. of sites safety arrangements made Construction Contractor measures and sign and sign boards installed boards Turfing Length of turfing carried out Construction and Contractor post construction Plantation No. of trees cut and no.of trees planted Construction and Contractor and Post SIO Construction Health camps No. of medical and health camps Construction Contractor including AIDS awareness camps conducted

8.9 Environmental Management and Monitoring Plan (EMMP) Costs

260. Most of the mitigation measures require the Construction Contractors to adopt good site practice, which should be part of their normal regular procedures, so there are unlikely to be major costs associated with compliance. In addition to this, any costs of mitigation by the construction contractors or SIO are included in the budgets for the civil works. All the environmental costs like dust suppression (sprinkling of water), borrow area

IEE & PC Kanjhari 4 August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program(OIIAWMIP)

rehabilitation, haulage road maintenance, safety etc are all inclusive under overheads of item rates as per revised schedule of rates, Govt. of Odisha. 261. Environmental monitoring will be integrated into the Project performance monitoring and evaluation (PPME) system. The majority of activities involved are translating actions suggested in the EMP to be implemented by the Construction Contractor and WUAs. The implementation period stipulated for the sub-projects are three years of construction phase and three years of post construction phase is suggested for environmental monitoring. The environmental monitoring suggested here is developed keeping in view of the needs of the Department of Water Resources as suggested in the EARF. The DoWR want to monitor surface water and ground water to assess the impacts of upstream urbanization and industrialization and it also want to monitor level of deterioration of water quality due to increased use of fertilizers and pesticides within and outside the command area. In addition the department wants to assess contaminants in the silt and soil in the command area. So the SIO, DoWR will be responsible for the implementation of environmental monitoring (Surface water, Ground water, Soil and Silt testing). 262. The monitoring shall be carried out by recognized laboratories { i.e., laboratories approved by State Pollution Control Board, Odisha, or National Accreditation Board for Testing and Calibration Laboratory (NABL) or (National Accreditation Board for Education and Training (NABET) or any Ministry of Environment and Forests (MoEF) recognized laboratory}. 263. The impacts arising out of the construction are minimal and the responsibility of implementation of the EMP mainly lies with the Contractor monitored by SIO staff. In addition to environmental safeguards taken up the contractor and sub project level environmental monitoring shall be carried out by the SIO/ PMU. The total environmental monitoring and management cost for the sub-project covering three years of construction phase and three years of post construction stage are shown in Table 38. 264. Table 38 Showing Environmental Monitoring Cost

Environmental Suggested Frequency and Unit rate in Rs Total cost in Parameter No. of period of monitoring Rs locations

Pre - construction period monitoring( baseline data) before commencement of civil works Surface water 4 4x1 (4) 10,000 40,000 Ground water 4 4x1(4) 10,000 40,000 Silt 4 4x1(4) 12,500 50,000 Soil 4 4x1(4) 12,500 50,000 Sub-total 1,90,000 Construction Phase Surface water 4 4x2x3(24) 10,000 2,40,000 Ground water 4 4x2x3(24) 10,000 2,40,000 Silt 4 4x2x3(24) 12,500 3,00,000 Soil 4 4x1x3(12) 12,500 1,50,000 Sub-total 9,30,000 Operation and Maintenance phase – Post construction Surface water 4 4X1(4) 10,000 40,000 Ground water 4 4X1(4) 10,000 40,000

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program(OIIAWMIP)

Environmental Suggested Frequency and Unit rate in Rs Total cost in Parameter No. of period of monitoring Rs locations

Silt 4 4X1(4) 12,500 50,000 Soil 4 4X1(4) 12,500 50,000 Sub-total 1,90,000 Grand Total 13,10,000 Cost of 1000 1200 12,00,000 Plantation / plant with 3 yrs maintenance cost

8.10 Environmental Training

265. The basic requirement of the environmental training is to strengthen the knowledge of PMU/ SIO, DoWR and WUAs on environmental aspects.

8.11 Strengthening Environmental Knowledge & Management Capability

266. The capacity and skills of the DoWR to carry out environmental management of irrigated agriculture schemes will need to be developed to be responsive and proactive to the needs and perceptions of environmental management in their jurisdictions during and following Project completion. The institutional strengthening of environmental management will be blended within the activities. The focus will be on building the capacity and capability of the SIO, DoWR to assume their responsibilities in carrying out REAs, IEEs and implementing EMPs. The organizational framework in the DoWR for this to occur will be establishment of new environmental division as per EARF.

267. Awareness raising will initially socialize the environmental assessment and EMP procedures among the project stakeholders. In addition meetings, seminars and some short courses will be organized to raise awareness within the DoWR. ISPM Environmental consultant during the field visits will also give on-field training on the implementation of EMP to the Contractor staff and SIO staff by the ISPMC and WUAs with the help of PPSU – Environmental Monitoring Specialist. In addition training programs would be conducted to the Contractor staff and SIO staff, DoWR by the ISPMC and for WUAs by the PPSU – Environmental Monitoring Specialist with the available funds of the PMU under training. The list of appropriate training module and tentative time frame is given in Table 39 and the required budget is suggested in Table 40.

268. Participatory Mechanisms are the building blocks for the success of the Project. Besides the DoWR and WUAs, the community needs to get involved in developing the foundation of future environmental management of irrigated agriculture in the State. Results of Environmental monitoring carried out during construction would be disseminated to WUA / PP members for raising awareness through PPSU Environmental Monitoring specialist and these would be built into the PPME System Participatory Environmental Monitoring guidelines shall be developed with the assistance of the environmental monitoring specialists of PPSU through the PIM Component for use by DoWR and WUA staff during construction and O&M. Lessons learned from past environmental management initiatives will be used to reinforce public participation as an essential aspect to instill a sense of ownership and stewardship among all stakeholders that will be involved in environmental management and the use of resources. Measures to

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program(OIIAWMIP)

involve active participation of the community will be included to help ensure more effective and appropriate management, since the stakeholders (those using the resources) can become involved in a voluntary way in some of the basic monitoring (e.g., soil erosion point sources) and regulating various activities under the EMP.

269. An environmental monitoring programme is important as it provides useful information and helps to i) assist in detecting the development of any unwanted environmental situation, and thus, provides opportunities for adopting appropriate control measures, and ii) evaluate the performance and effectiveness of mitigation measures proposed in the EMP and suggest improvements in management plan, if required. Table 39 Proposed Training Module for Capacity building of SI O and WUAs

Training Type Item/ subject of Training Target Group Time I tem No 1 Orientation Need for Initial Environmental PMU, SIO staff , Pre- Training Examination Report and PPSU staff, Construction Overview of important Contractors and Environmental Regulation and WUAs while frame work to the project executing Applicable statutory construction of Environmental Clearances – by minors the SIO staff and Contractor 2 Training on 1. Environmental & Safety PMU, SIO staff , Twice Environmental & Aspects Relevant to PPSU staff, during Safety Aspects Construction Contractors and Construction Relevant to Environmental obligations as WUAs while period Construction per Contract Clauses and executing technical specification ( construction of covering issues and impacts minors related to Borrow areas, Quarries, Aggregates, Top soil usage, Disposal of construction debris, handling of hazardous materials and dust suppression measures) Safety measures and usage of PPE’s during construction

2.Implementation of Environmental Monitoring Plans Importance of EMP and parameters to be monitored Parameters for Environmental Monitoring ( Surface water, Ground Water, Silt and Soil) Precautions to be taken while sampling Monitoring frequency

3 Environmental Environmental issues during PMU, SIO staff After Issues during operation and post project PPSU staff and Construction maintenance and Parameters for Environmental WUAs

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program(OIIAWMIP)

Operation Monitoring ( Surface water, Ground Water, Silt and Soil) Precautions to be taken while sampling Monitoring frequency

8.12 Training Budget

270. The approximate cost involved under training is shown in Table 40.

Table 40 showing the training budget

Sl.No Training Details Unit rate Frequency Total cost 1 Orientation training on Rs. 25,000 4 times during Rs.1,00,000 the EMP project period implementation to SIO Staff and Contractors for a group 40 to 50 people 2 Orientation training on Rs. 25,000 4 times during Rs.1,00,000 the EMP project period implementation to SIO Staff and WUAS for a group 40 to 50 people Total 2,00,000

8.13 Environmental monitoring reporting

271. The environmental reporting system has been discussed in detail under section E of this Chapter the contractors and WUAs shall submit monthly report to the SIO as provided in Annexure 9 and 9a of this report. The summary of status of EMP implementation shall be provided by PMU to ADB periodically through Quarterly Progress Report (QPR). PMU shall also submit Environmental Monitoring Report describing the status of EMP implementation in detail to ADB on a annual basis for Category “B” projects.

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program(OIIAWMIP)

9. RECOMMENDATI ONS

272. Recommends the subproject to be rated Category B for the following reasons: (i)There are no significant adverse impacts associated with this project. Instead the project is expected to improve irrigation facilities and enhance economic growth of the area; (ii) Increased irrigation will also help in planting of more trees thereby increasing the environmental conditions of the area adding to the greenery and general aesthetics of the area; (iii) The indirect benefits of the project will be lowered levels of out migration as the communities will have more opportunity of securing income from within the village; (iv) There will be growth in living standard of people, which will encourage proper education, social awareness, health facility and prosperity amongst the people; (v) The IEE clearly states in its findings that there will be no significant impact in the local environmental condition due to construction and operation of the project and preference shall be given to the local labour for carrying out the work. 273. Mitigation - Canal system close to reserved, protected and village forest areas at many places, dam portion, left canal tail end portion and Padampur minor falls under elephant transit paths, so adequate preventive measures need to be observed such as not establishing construction camps/ plants and material in these areas. 274. The SIO in consultation with WUAS had identified potential borrow areas in private land which will also reduce impacts arising due to borrowing in the forest areas etc. Contractor may be required to abide by regulations pertaining to “sensitive / restricted” areas as well as by observing decent working practices (strict monitoring in not cutting any trees for fire wood in the forest areas, not hunting any wild life) and providing facilities at construction camp. 275. Any Issues related to encroachments need to be addressed as per the R & R policy. Any impact associated with the project activities will be minor in nature and will be restricted only during the construction phase of the project. Increased levels in ground water increase in soil salinity, increased levels of insecticides and pesticides are some of the major impacts during project operation. Increased ground water level is a beneficial impact and hence no mitigation measures are recommended. It is suggested that local villagers should be educated through pani panchayat about rational use of water, chemical fertilizers and pesticides to reduce soil salinity and protect surface and ground water quality.

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program(OIIAWMIP)

10. CONCLUSI ON

276. The IEE has assessed potential environmental impacts associated with the subproject. There are no adverse impacts that are significant and complex in nature expected from implementation of this subproject. The subproject is expected to improve the existing degraded irrigation infrastructure and will be put to beneficial use to the society. This will boost agriculture growth in the area and will bring prosperity to the region. By improving the irrigation infrastructure economic disparity between head end and tail end users will be reduced. 277. The potential adverse impacts are minimal as no additional land is required, and the impacts that may arise with construction and operation because of vicinity to forest and elephant paths can be mitigated through stringent monitoring and adopting strict construction practices by the Contractor and WUAs and implementing the suggested EMP measures. 278. IEE assessment confirmed the subproject Category B classification and will not require detailed EIA to be undertaken except obtaining required permits and certification as suggested in the IEE report.

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program(OIIAWMIP)

REFERENCES

¾ Sehgal, J., Mandal, D.K Mandal C & Vadivelu, S (1982) Agro- Ecological Regions of India, Second Edition. Technical Bulletin, NBSS&LUP, Publ. 24 pg. 72 to 74. NBSS&LUP, Nagpur, India. ¾ Odisha Minor Mineral Concession Rules 1990 amended 2004, Department of Steel & Mines. Government of Odisha. ¾ Soil Series of Odisha Technical Bulletin, NBSS Publ 119, National Bureau of Soil Survey and Landuse Planning (ICAR) in co-operation with Directorate of Soil Conversation (Survey), Govt. of Odisha, Bhubaneswar. ¾ Census of India 2011, Provisional Population Totals, Odisha Series 22, Directorate of Census Operations, Odisha ¾ Detailed Project Report for Improvement of Kanjhari Irrigation Project & Its Canal System, Water Resources Department, Government of Odisha August 2011. ¾ Odisha Agriculture Statistics 2009 – 2010, Directorate of Agriculture & Food Production, Odisha, Bhubaneswar ¾ District Statistical Hand Keonjhar- 2007, Directorate of Economics and Statistics, Odisha, Bhubaneswar ¾ Agro-Climatic Zone Specific Research, Indian Perspective under NARP, Indian Council of Agricultural Research, New Delhi ¾ Odisha District Gazetteer, Govt. Of Odisha. ¾ State of Environment Report Odisha, 2006 published by State Pollution Control Board Odisha ¾ Census 2011 ¾ District Statistical Handbook 2009 ¾ State Pollution Control Board Web site

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program(OIIAWMIP)

ANNEXURES

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program(OIIAWMIP)

ANNEXURE - I I NDEX MAP OF KANJHARI I RRI GATI ON SUB-PROJECT SHOWI NG AYACUT AREA

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program(OIIAWMIP)

Annexure-2 LI ST OF ODI SHA STATE POLLUTI ON CONTROL BOARD APPROVED CRUSHERS

IEE & PC Kanjhari 4 August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program(OIIAWMIP)

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program(OIIAWMIP)

Annexure-3 QUARRY AREA MAP OF KANJHARI I RRI GATI ON PROJECT

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program(OIIAWMIP)

Annexure-4 LI ST OF POTENTI AL FARMERS WI LLI NG O GI VE EARTH FOR BORROW AREAS

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program(OIIAWMIP)

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program(OIIAWMIP)

Annexure-5 MAP SHOWI NG KANJHARI I RRI GATI ON SUB-PROJECT AND I TS CANAL SYSTEM ALONG WI TH THE ELEPHANT TRANSI T PATH

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program(OIIAWMIP)

Annexure-6 MONTHLY AVERAGE RAI NFALL DATA OF KANJHARI SUB-PROJECT -1979 -2013

Rainfall in mm Year January February March April May June July August September October November December Total 1979 0 0 0 0 0 0 0 77.45 199.95 10.144 0 20.32 307.86 1980 32.00 0.25 115.56 81.52 54.63 374.38 238.61 83.47 258.29 81.67 1.50 0.25 1322.13 1981 8.78 16.91 30.61 119.61 123.43 189.42 221.04 296.12 279.85 7.87 0.62 2.50 1296.76 1982 20.40 83.19 75.30 15.67 101.47 243.52 151.90 380.47 164.36 28.19 2.30 0.00 1266.77 1983 10.16 90.34 32.58 45.88 74.53 126.20 268.48 350.87 237.30 73.20 0.00 5.75 1315.29 1984 13.10 14.95 0.00 7.52 54.57 240.11 193.27 442.00 90.18 53.62 0.00 0.00 1109.32 1985 50.50 64.05 0.00 38.00 152.35 262.95 229.40 385.70 384.15 209.10 0.00 0.00 1776.20 1986 74.40 29.70 39.90 39.30 121.60 242.35 314.62 260.75 149.88 152.70 28.75 34.05 1488.00 1987 2.00 6.70 51.90 34.75 28.50 92.80 206.25 196.25 81.10 46.75 71.25 1.75 820.00 1988 0.00 114.75 35.65 97.50 46.30 263.50 218.30 375.25 234.75 50.00 2.50 0.00 1438.50 1989 0.00 0.00 6.25 12.50 104.75 486.50 191.00 326.00 170.00 25.00 0.00 0.20 1322.20 1990 0.00 27.00 84.50 89.50 95.50 355.50 165.50 212.50 163.50 153.50 58.00 6.00 1411.00 1991 17.00 0.00 52.00 44.50 70.00 143.00 278.50 443.00 155.00 97.50 19.50 5.00 1325.00 1992 5.00 16.00 0.00 45.00 168.00 166.00 216.00 292.00 140.00 37.00 2.00 0.00 1087.00 1993 0.00 0.00 5.00 172.00 233.00 303.30 325.00 194.00 216.00 152.00 2.00 0.00 1602.30 1994 0.00 50.00 0.00 20.00 140.00 229.00 436.00 305.00 280.00 115.00 0.00 0.00 1575.00 1995 57.00 29.00 3.00 10.00 261.00 192.00 258.00 327.00 221.00 115.00 170.00 0.00 1643.00 1996 10.00 6.00 0.00 43.00 39.00 304.00 149.00 356.00 62.00 13.00 12.00 0.00 994.00 1997 21.00 0.00 40.00 196.00 71.00 264.00 148.00 316.00 246.00 60.00 13.00 81.00 1456.00 1998 72.00 11.00 20.00 42.00 37.00 328.00 117.00 58.00 212.00 120.00 25.00 0.00 1042.00 1999 0.00 0.00 0.00 0.00 172.00 270.00 195.00 423.00 257.00 392.00 3.00 0.00 1712.00 2000 0.00 15.00 3.00 32.00 70.00 200.00 132.00 140.00 100.00 10.00 0.00 0.00 702.00 2001 3.00 0.00 127.00 67.00 120.00 160.00 293.00 259.00 128.00 133.00 0.00 0.00 1290.00 2002 39.00 0.00 26.00 20.00 117.00 155.00 235.00 182.00 138.00 18.00 2.00 0.00 932.00 2003 0.00 35.00 45.00 55.00 105.00 192.00 190.00 178.00 130.00 260.00 10.00 18.00 1218.00 2004 0.00 16.00 14.00 95.00 20.00 170.00 315.00 345.00 94.00 102.00 0.00 0.00 1171.00 2005 25.00 0.00 55.00 45.00 55.00 301.00 369.00 78.00 194.00 212.00 0.00 4.00 1338.00 2006 0.00 0.00 12.00 18.00 114.00 167.00 257.00 452.00 231.00 64.00 22.00 0.00 1337.00 2007 0.00 75.00 50.00 90.00 70.00 277.00 274.00 256.00 215.00 62.00 59.00 0.00 1428.00 2008 35.00 8.00 40.00 40.00 30.00 309.00 161.00 204.00 269.00 8.00 9.00 0.00 1113.00 2009 0.00 0.00 0.00 0.00 118.00 48.00 131.00 202.00 188.00 53.00 17.00 0.00 757.00 2010 0.00 0.00 44.00 3.00 121.00 109.00 173.00 203.00 286.00 98.00 10.00 21.00 1068.00 2011 0.00 15.00 1.00 67.00 133.00 203.00 156.00 342.00 718.00 30.00 0.00 0.00 1665.00 2012 138.00 2.00 0.00 140.00 49.00 120.00 193.00 371.00 262.00 119.00 41.00 0.00 1435.00 2013 0.00 0.00 0.00 20.00 71.00 280.00 495.00 318.00 341.00 502.00 0.00 0.00 2027.00 Avg 1279.75

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program(OIIAWMIP)

Annexure-7

FOREST COVER MAP OF ODI SHA

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program(OIIAWMIP)

Annexure-8

PROJECT BENEFI TED VI LLAGES ALONG WI TH POPULATI ON DETAI LS

SL BLOCK NAME GP- NAME VILLAGE NAME No_HH TOT_P TOT_M TOT_F P_SC P_ST P_LIT NO 1 KOENJHAR MAIDANKEL BARKHANDA 41 170 92 78 0 2 112 2 KOENJHAR KATHABARI DHANURJAYAPUR 280 1257 614 643 81 881 695 3 KOENJHAR RAGHUNATHPUR KANIPOSI 73 321 163 158 92 42 219 4 KOENJHAR RAGHUNATHPUR KAJALEIPASI 50 209 114 95 64 55 141 5 KOENJHAR MAIDANKEL DEOBANDHA 101 452 227 225 0 358 321 6 KOENJHAR MAIDANKEL JAGANNATHPUR 57 251 135 116 0 0 189 7 KOENJHAR MAIDANKEL KERI 305 1297 647 650 185 469 875 8 KOENJHAR MAIDANKEL CHHEMANDIBIL 91 440 213 227 5 343 247 9 KOENJHAR RAGHUNATHPUR JAJAPASI 156 653 322 331 19 356 311 10 KOENJHAR KATHABARI BARIGAON 221 1011 532 479 0 604 603 11 KOENJHAR KATHABARI LAXMIPASI 112 512 268 244 0 385 245 12 KOENJHAR KATHABARI BHODABAHALI 64 258 129 129 53 0 180 13 KOENJHAR KATHABARI KATHABARI 280 1257 614 643 81 881 695 14 KOENJHAR KATHABARI JAGANNATHPUR 122 746 430 316 67 644 572 15 KOENJHAR KATHABARI KAMALABAHAL 101 429 222 207 0 27 296 16 KOENJHAR RAGHUNATHPUR DIMIRIA 165 724 355 369 17 50 402 17 KOENJHAR RAGHUNATHPUR HALADAHARPUR 240 1085 537 548 28 395 629 18 KOENJHAR RAGHUNATHPUR KHADIADIHA 154 700 357 343 24 631 358 19 KOENJHAR RAGHUNATHPUR MAJURAPOSI 102 409 208 201 6 156 248 20 KOENJHAR RAGHUNATHPUR CHAKA 124 574 292 282 27 161 415 21 KOENJHAR RAGHUNATHPUR KALIABEDA 79 358 180 178 21 184 254 22 KOENJHAR RAGHUNATHPUR DHAGOTHA 38 137 67 70 0 0 81 23 KOENJHAR KATHABARI KHAJURIPANI 100 381 198 183 135 3 211

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program(OIIAWMIP)

24 GHATAGAON TORANIPOKHARI DWARIKAPASI 134 510 251 259 144 196 271 25 GHATAGAON TORANIPOKHARI VANDARIPASI 46 159 79 80 62 0 97 26 GHATAGAON TORANIPOKHARI DHOBAPITANA 229 849 432 417 20 438 498 27 GHATAGAON TORANIPOKHARI GOPAPUR 116 511 265 246 0 462 360 28 GHATAGAON TORANIPOKHARI KHUDUPATULI 58 235 121 114 0 109 131 29 GHATAGAON TORANIPOKHARI PAIPANI 380 1741 880 861 86 913 913 30 GHATAGAON TORANIPOKHARI MATHURAPASI 180 838 410 428 14 265 444 31 GHATAGAON BHOLABEDA BHOLABEDA 518 2196 1071 1125 193 1785 1186 32 GHATAGAON BHOLABEDA AMBUAPADA 273 1153 578 575 0 763 638 33 GHATAGAON BHOLABEDA RAIKUDAR 83 357 181 176 2 271 194 34 GHATAGAON SARASPOSI BHALUKIPATALI 169 770 396 374 0 651 493 35 GHATAGAON SARASPOSI SARASAPASI 110 543 262 281 41 467 365 36 GHATAGAON SARASPOSI BHARANDIA 115 499 256 243 0 499 276 37 GHATAGAON SARASPOSI GOBARABEDA 166 654 335 319 96 307 437 38 GHATAGAON SARASPOSI BRUNDABANAPUR 104 443 202 241 1 199 288 39 GHATAGAON PIPILIA MUNDATANGAR 64 252 137 115 1 34 153 40 GHATAGAON MUKTAPUR DALANGAPANI 123 574 296 278 0 410 351 41 PATNA JAMUNAPASI JAMUNAPASI 341 1386 682 704 153 816 887 42 PATNA KANTIAPADA KANTIAPADA 389 1582 789 793 350 984 971 43 PATNA JAMUNAPOSI PADMAPUR 89 345 178 167 0 181 175 44 PATNA CHEMANA BHRUNGARAJ 87 324 161 163 0 180 156 45 PATNA RAJNAGAR NUAKHAMANA 266 1139 519 620 42 842 550 46 PATNA JAMUNAPOSI PADMAKESARPUR 83 377 190 187 12 338 216 47 PATNA JAMUNAPOSI BURUDIPASI 48 PATNA JAMUNAPOSI KODAKHAMANA 204 779 377 402 53 132 463 49 PATNA KANTIAPADA JAMUNALIA 171 792 407 385 8 496 342 50 PATNA CHEMANA BARADANGUA 109 500 246 254 59 209 341 51 PATNA CHEMANA DHANURJAYPUR 91 343 176 167 3 96 260 52 PATNA JAMUNAPOSI GODIPOKHARI 224 954 469 485 10 681 703

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program(OIIAWMIP)

53 PATNA KHIREITANGIRA DALANGA 253 1110 564 546 64 390 666 54 PATNA CHEMANA RENGALABEDA 148 633 329 304 83 165 386 55 PATNA CHAKUNDAPAL JADICHATAR 175 785 385 400 110 552 443 56 PATNA KENDEIPOSI MAHISAMUNDI 256 1103 566 537 58 1015 605 57 PATNA KENDEIPOSI KASHIPUR 102 426 217 209 6 224 269 58 PATNA RAJNAGAR NUAGAONBALAVADRAPUR 135 587 292 295 0 372 344 59 PATNA KENDEIPOSI BADAGAHMARIA 202 859 425 434 67 470 448 60 PATNA CHAKUNDAPAL SANAGAHMARIA 134 557 287 270 0 201 264 61 PATNA KHIREITANGIRA TALAPADA 53 222 107 115 0 218 86 62 PATNA CHAKUNDAPAL SARADHAPUR 160 684 350 334 50 606 358 63 PATNA KANTIAPADA PATADHANURAJAYAPUR 100 410 197 213 1 154 240 64 PATNA CHAKUNDAPAL CHAKUNDAPAL 234 1002 493 509 128 808 581 65 PATNA KENDEIPOSI KENDEPASI 210 882 417 465 183 519 552 66 PATNA KENDEIPOSI KHUNTAPADA 194 1118 557 561 8 1057 401 67 PATNA KANTIAPADA MANPUR 175 706 364 342 35 20 388 68 PATNA KANTIAPADA BHOGAPASI 49 200 103 97 35 154 133 69 PATNA CHAKUNDAPAL JANHEIPASI 60 240 118 122 0 165 168 70 PATNA KANTIAPADA BANANIPASI 141 585 295 290 39 100 372 71 PATNA KANTIAPADA PURUNIA 94 397 184 213 0 44 210 72 PATNA CHAKUNDAPAL SHYAMSUNDARPUR 63 226 122 104 5 0 143 73 PATNA TANGARAPADA BRAHAMANIDEO 212 950 480 470 21 830 563 74 PATNA MUSAKHORI MUSAKHORI 386 1615 824 791 499 774 941 75 PATNA MUSAKHORI GIRIDHINA 20 94 45 49 0 94 61 76 PATNA TANGARAPADA BALIBANDHA 161 633 315 318 52 39 372 77 PATNA TANGARAPADA GALAPHULA 190 827 422 405 6 755 415 78 PATNA PATNA KHAMUA 252 1098 546 552 26 774 559 79 PATNA PATNA DIMIRIDIHA 160 662 319 343 120 535 336 80 PATNA PATNA PUTULIA 138 616 294 322 29 181 353 81 GHATAGAON TARA SANAJAMUPOSI 49 199 106 93 27 43 129

IEE & PC Kanjhari 4 August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program(OIIAWMIP)

82 PATNA TANGARAPADA ANKURA 257 1209 617 592 399 695 778 83 PATNA SARASAKHOLA SARASKHOLA 385 1793 913 880 130 1079 968 84 GHATAGAON BADAJAMUPASI BADAJAMUPASI 158 640 310 330 10 272 336 85 PATNA RAJNAGAR NUAKHAMANA 266 1139 519 620 42 842 550 13550 58643 29344 29299 4488 33498 33876 TOTAL % COMPARED TO TOT-POP 50.04 49.96 7.65 57.12 57.77

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program(OIIAWMIP)

Annexure-9 SUMMARY OF CONSULTATI ON WI TH STACK HOLDERS I N DI FFERENT PROJECT BENEFI TED VI LLAGES

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program(OIIAWMIP)

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program(OIIAWMIP)

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program(OIIAWMIP)

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program(OIIAWMIP)

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program(OIIAWMIP)

Annexure-10 LI ST OF PARTI CI PANTS OF POI PANI VI LLAGE

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program(OIIAWMIP)

Annexure-11 LI ST OF PARTI CI PANTS OF SARASPOSI VI LLAGE

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program(OIIAWMIP)

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program(OIIAWMIP)

Annexure-12 LI ST OF PARTI CI PANTS OF BADA JAMUPOSI VI LLAGE

IEE & PC Kanjhari 4 August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program(OIIAWMIP)

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program(OIIAWMIP)

Annexure-13 LI ST OF PARTI CI PANTS OF CHAKO VI LLAGE

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program(OIIAWMIP)

Annexure-14 LI ST OF PARTI CI PANTS OF SARADHAPUR VI LLAGE

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program(OIIAWMIP)

Annexure-15 LI ST OF PARTI CI PANTS OF BOLANI POSI VI LLAGE

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program(OIIAWMIP)

IEE & PC Kanjhari August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program(OIIAWMIP)

Annexure 16 ENVIRONMENTAL MONITORING – CHECK LIST- CONTRACTORS (To be filled by the Contractor) Monthly Report Reporting Month: …………….. I. Package Description 1.1 Contract Package 1.2 Name of the Contractor 1.3 Name of the Sub-project 1.4 Work Completed for the Month Earth work/ Concrete work/ Masonry / Others Specify Earth Work -Filling Qty……. Loc……. Earth Work -Cutting Qty……. Loc……. Concrete work Qty……. Loc……. Lining Qty……. Loc……. Turfing Qty……. Loc……. Service Road Qty……. Loc…….

II. Establishment of Contractors Camp Yes / No 1 Usage of Camp Plant / Machines/ Labour

1.1 If Plant Crusher unit/ HMP/ WMM / Any Other

If material purchased from Vendor Name of the Vendor

1.2 If Machinery stocking Yes / No

Sl.N0 Type of Machinery in Operation Number Fitness/ PCB Remarks – certificate Repair under obtained taken at cam p / sent to Garage 1 Paver

2 Rollers

3 Excavators

4 Dumpers

5 Vehicles ( Tractors/ Trucks)

Others

6

IEE & PC Kanjhari 4 August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program(OIIAWMIP)

1.3 If Labour Permanent / Transit

S.No Particulars Remarks i Total Number of Labourers employed? ii Number of Male labourers? iii Number of female labourers? iv Number of local labourers? v Name the village from where the labour come from? vi Number of migrant labourers? vii Number of dwelling units in the camp? viii Type of dwellings ? Pucca : No. Kutcha :No. ix Water Supply provided? x Drinking water supply provided? Tube well/ Open Well/ Tanker/ etc xi Number of Toilets provided? xii Type of Toilet ? Leach pit / Soak Pit / Septic tank xii Number of Bath rooms provided? xiii Are Separate Bath rooms provided for women? Yes / No xiv Washing plat forms provided? xv Drainage facility provided? xvi Crèche facility provided? xvii Availability of Health centre ? Nearest xviii First Aid Facility Available? xix Health Camp / HIV awareness conducted? Yes / No If yes provide details xx Fuel used in the Camp? Fire wood/ Kerosene/ LPG xxi Does the Camp has Workshop for Repair? Yes / No xxii Any Oil Spill taking Place? Yes / No xxiii Oil / Grease traps / solid plat forms provided? Yes / No

IEE & PC Kanjhari 4 August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program(OIIAWMIP)

1.4 Storage of Fuel Temporary/ Permanent 1.5 Type of Fuel Stored? HSD/ Petrol 1.5.1 License Obtained? Yes/ NO 1.6 Any Blasting Material Stored? Yes/ NO 1.6.1. License Obtained ? Yes/ NO

III. Borrow Area Management 1. No. of Borrow Area approved? 2. No. of Borrow Area Rehabilitated/ Re-developed? 3. Permission Obtained for Borrow areas Private - land Owner / Govt. Land – Panchayat /Revenue (Note: Attach Copies of Permission Letter) 4.Details of Borrow Areas

Sl. No. Description B.A. - 1 B.A. - 2 B.A. - 3 4.1 Capacity of the Borrow Area 4.2 Percentage of the capacity exhausted 4.3 Total quantity of the Earth Excavated (in cum.) 4.4 Quantity of Top Soil Removed from the Borrow Area 4.5 Location of stored top Soil that was removed 4.6 Quantity of Top Soil Stored at the beginning of the month 4.7 Quantity of Top Soil utilized at the end of the month 4.8 Location(s) where Top Soil has been utilized (Specify on a Location Plan)

IV. Haulage Road Existing Road/ Temp Road Created 1. Maintenance of Haulage Road done ? Yes / No 2. Dust Suppression Measures taken ? Yes / No

V. Quarries Under Operation Yes / No 1. If Yes, Number of Quarries in Use and locations? 2. If No, Name of Vendor, the material Purchased and SPCB Certificate of Vendor to be Enclosed? 3. Are the Vehicles used for Supplying material covered ? Yes / No

VI. Erosion Control Measures: Silt Traps/ Construction in Lean Season / Compaction Taken up VII. Dump Sites: Identified - Yes / No Low lying areas Used - Yes/ No Disposal Sites – identified - Yes/ No

IEE & PC Kanjhari 4 August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program(OIIAWMIP)

VIII Storage of Material: Adj . to Canal / ROW/ etc 1. Blockage of Natural drains Yes / No

IX Dust Control Measure:

Sl.No. Dust Control Devices Dust control devices are available. – Yes/ N

1 Sprinkling of Water Sprinkling of water carried out. Yes/ No

2 Cover on the vehicles Yes/ No

3 Cover on stack materials Yes/ No X. Noise Control Measure: S.No. Measure Remarks

1 Machines establishes in Habitation Yes / No

2 Away from Habitations Yes / No

3 Machines Sent for Maintenance regularly Yes / No

XI. Safety Measures Taken: Sl. Description No. 1 Whether first aid post established at site? Yes/No

2 Whether safety helmets given to all workmen at site? Yes/No

3 Whether safety belts / ribbons used at work site Yes/No

4 Whether gum boots, tarring unfits, spectacles etc. given to Yes/No person handling bitumen?

XII. Environmental Monitoring Details

Sl.No Type of Test No. of Locations Date of Test last Remarks conducted 1 Ground Water 2 Surface Water 3 Silt 4 Soil

Signature of the Contractor / Representative Signature of the SIO Staff Name of the Contractor Name of the SIO Staff Date Date Verified

IEE & PC Kanjhari 4 August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program(OIIAWMIP)

Annexure – 16a ENVIRONMENTAL MONITORING – CHECK LIST- WUA (To be filled by the WUAs) Monthly Report Reporting Month: ……………..

I. Package Description 1.1 Contract Package

1.2 Name of the WUA

1.3 Name of the Sub-project

1.4 Work Completed for the Month Earth work/ Concrete work/ Masonry / Others Specify

Earth Work -Filling Qty……. Loc…….

Earth Work -Cutting Qty……. Loc…….

Concrete work Qty……. Loc…….

Lining Qty……. Loc…….

Turfing Qty……. Loc…….

Service Road Qty……. Loc…….

II Material purchased from Vendor Ye Yes / No

Granite Yes / No

Sand Yes / No

Morrum Yes / No

Details of the Vendor Labour Employed Yes / No

S.No Particulars Remarks i Total Number of Labourers employed? ii Number of Male labourers? iii Number of female labourers? iv Number of local labourers? v Name the village from where the labour comes from?

IEE & PC Kanjhari 44 August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program(OIIAWMIP)

2.1 V. Storage of Fuel Yes / No

VI . Borrow Area Management 4. No. of Borrow Area approved? 5. No. of Borrow Area Rehabilitated/ Re-developed? 6. Permission Obtained for Borrow areas Private - land Owner / Govt. Land – Panchayat /Revenue (Note: Attach Copies of Permission Letter) 4.Details of Borrow Areas

Sl. No. Description B.A. - 1 B.A. - 2 B.A. - 3

4.1 Capacity of the Borrow Area

4.2 Percentage of the capacity exhausted

4.3 Total quantity of the Earth Excavated (in cum.)

4.4 Quantity of Top Soil Removed from the Borrow Area

4.5 Location of stored top Soil that was removed

4.6 Quantity of Top Soil Stored at the beginning of the month

4.7 Quantity of Top Soil utilized at the end of the month

4.8 Location(s) where Top Soil has been utilized (Specify on a Location Plan)

3.1 VII Haulage Road Existing Road/ Temp Road Created

3. Maintenance of Haulage Road done ? Yes / No 4. Dust Suppression Measures taken ? Yes / No

VIII. Quarries Under Operation Yes / No 4. If Yes, Number of Quarries in Use and locations? 5. If No, Name of Vendor, the material Purchased and SPCB Certificate of Vendor to be Enclosed? 6. Are the Vehicles used for Supplying material covered ? Yes / No

IX. Dump Sites: Identified - Yes / No Low lying areas Used - Yes/ No Disposal Sites – identified - Yes/ No

IEE & PC Kanjhari 4 August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program(OIIAWMIP)

X. Storage of Material: Adj . to Canal / ROW/ etc XI. Blockage of Natural drains Yes / No

XII. Dust Control Measure: Sl.No. Dust Control Devices Dust control devices are available. – Yes/ N

1 Sprinkling of Water Sprinkling of water carried out. Yes/ No

2 Cover on the vehicles Yes/ No

3 Cover on stack materials Yes/ No XIII. Noise Control Measure: S.No. Measure Remarks 1 Machines establishes in Habitation Yes / No

2 Away from Habitations Yes / No

3 Machines Sent for Maintenance regularly Yes / No

XIV. Safety Measures Taken:

Sl. Description No. 1 Whether first aid post established at site? Yes/No

2 Whether safety helmets given to all workmen at site? Yes/No

3 Whether safety belts / ribbons used at work site Yes/No

4 Whether gum boots, tarring unfits, spectacles etc. given to Yes/No person handling bitumen?

XV. Environmental Monitoring Details

Sl.No Type of Test No. of Locations Date of Test last Remarks conducted

1 Ground Water

2 Surface Water

3 Silt

4 Soil

Signature of the WUAs Representative Signature of the SIO Staff Name of the WUA Name of the SIO Staff Date Date Verified

IEE & PC Kanjhari 4 August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program(OIIAWMIP)

Annexure 17 PARAMETERS FOR GROUND WATER ANALYSI S AS PER I S 10500:1991 S.No Parameter Essential Characteristics 1 Colour Hazen Units, Max 2 Odour 3 Taste 4 Turbidity NTU, Max 5 pH Value 6 Total hardness( as CaCO3) mg/L, Max 7 Iron (as Fe) mg/L, Max 8 Chlorides (as Cl) mg/L, Max 9 Residual, free chlorine mg/L, Max Desirable Characteristics 10 Dissolved solids mg/L, Max 11 Calcium (as Ca) mg/L, Max 12 Copper (as Cu) mg/L, Max 13 Manganese (as Mn) mg/L, Max 14 Sulphate (as SO4) mg/L, Max 15 Nitrate (as NO3) mg/L 16 Fluoride (as F) mg/L, Max 17 Phenolic compounds (as C6H5OH) mg/L, Max 18 Mercury (as Hg) mg/L, Max 19 Cadmium (as Cd) mg/L, Max 20 Selemium (as Se) mg/L, Max 21 Arsenic (as As) mg/L, Max 22 Cyanide (as CN) mg/L, Max 23 Lead (as Pb) mg/L, Max 24 Zinc (as Zn) mg/L, Max 25 Anionic Detergents (as MBAS) mg/L, Max 26 Chromium (as Cr 6+) mg/L, Max 27 Polynuclear aromatic hydrocarbons (as PAH) g/L, max 28 Mineral Oil mg/L, Max 29 Pesticides mg/L, Max DDT/ Endosulphan/ phorate/ carbofuran/ monocrotophos 30 Radioactive materials a). Alpha emitters Bq/L. Max b). Beta emitters Bq/L Max 31 Alkalinity mg/L. Max 32 Aluminium (as Al) mg/L, Max 33 Boron, mg/L, Max 34 E-coli

IEE & PC Kanjhari 4 August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program(OIIAWMIP)

Annexure 17a PARAMETERS FOR SURFACE WATER ANALYSI S 2296:1992 Sl.No Characteristics 1 Dissolved Oxygen (DO)mg/l, min 2 Biochemical Oxygen demand (BOD)mg/l, max 3 Total coliform organisms MPN/100ml, max 4 pH value 5 Colour, Hazen units, max. 6 Odour 7 Taste 8 Total dissolved solids, mg/l, max. 9 Total hardness (as CaCO3), mg/l, max. 10 Calcium hardness (as CaCO3), mg/l, max. 11 Magnesium hardness (as CaCO3), mg/l, max. 12 Copper (as Cu), mg/l, max. 13 Iron (as Fe), mg/l, max. 14 Manganese (as Mn), mg/l, max. 15 Chlorides (as Cu), mg/l, max. 16 Sulphates (as SO4), mg/l, max. 17 Nitrates (as NO3), mg/l, max. 18 Fluorides (as F), mg/l, max. 19 Phenolic compounds (as C2H5OH), mg/l, max. 20 Mercury (as Hg), mg/l, max. 21 Cadmium (as Cd), mg/l, max. 22 Selenium (as Se), mg/l, max. 23 Arsenic (as As), mg/l, max. 24 Cyanide (as Pb), mg/l, max. 25 Lead (as Pb), mg/l, max. 26 Zinc (as Zn), mg/l, max. 27 Chromium (as Cr6+), mg/l, max. 28 Anionic detergents (as MBAS), mg/l, max. 29 Barium (as Ba), mg/l, max. 30 Free Ammonia (as N), mg/l, max 31 Electrical conductivity, micromhos/cm, max 32 Sodium absorption ratio, max 33 Boron, mg/l, max 34 Pesticides i) DDE ii) DDT iii) Endosulfan iv) Endosulphan Sulfate v) Monocrotophos vi) Carbofuran vii) Phorate 35 COD 36 Turbidity 37 Aluminium as Al 38 Sodium as Na % 39 Residual Sodium Carbonate (RSC)

IEE & PC Kanjhari 4 August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program(OIIAWMIP)

Annexure 17b PARAMETERS FOR SOI L / SI LT ANALYSI S

S.No Parameter 1 pH 2 EC 3 Organic Carbon “C” 4 Texture 5 Phosphorous ( P) 6 Potassium ( K) 7 Sulphur (S) 8 Calcium (Ca) 9 Magnesium (Mg) Heavy metals 10 Chromium (Cr) 11 Lead (Pb) 12 Cadmium (Cd) 13 Fluoride (Fl) 14 Nickel ( Ni) 15 Arsenic (Ar) 16 Mercury (Hg) Micro-nutrients 17 Boron (B) 18 Copper(Cu) 19 Iron (Fe) 20 Manganese (Mn) 21 Molybdenum (Mo) 22 Zinc(Zn) Pesticides 23 DDT 24 Endosulphan 25 Phorate 26 Carbofuran 27 Monocrotophos

IEE & PC Kanjhari 4 August 4 Orissa Integrated Irrigated Agriculture and Water Management Investment Program(OIIAWMIP)

PHOTO PLATES

IEE & PC Kanjhari August 4 PHOTO PLATES

Right Main Canal

Scouring and breach of Right Main canal RD 0+400 Km

Right Main Canal Silted and with bushes at RD 1+700 km

Right Main with Scouring and Damaged lining

Right Main Canal with damaged lining at RD 2+500km

Scouring of the Right Main canal at RD 4+200 Km

Gopapur Sub –Minor silted and with weeds

LEFTIN MA CANAL

Scouring and Siltation of Left Main Canal at RD 0+250 Km

Water Logging at Left Main Canal at RD 0+800 Km

Left Main Canal with Scouring and Siltation at RD 1+370 Km

Left Main canal with boulders blocking the canal at RD 2+000Km

Left Main Canal at RD 4+500 Km

LMC at Kantipada with PP President and members showing the silted, weeded canal

Kantipada Sub‐Minor With weeds and Siltation and passing through forest area

Poipani minor silted and with weeds under Right main canal

Poipani minor silted and with weeds under Right main canal

Brundabanpur minor canal breaching and water logging

Jamunapasi Minor Canal silted and water not reaching – tail end

Domestic sewage mixing with canal near Chaka village – Mayurposi minor RD 0+200 Km

Mayurposi minor with weeds and siltation

Forest near the Dam site