Environmental Monitoring Report PAK: Jamshoro Power Generation Project

Environmental Monitoring Report PAK: Jamshoro Power Generation Project

Environmental Monitoring Report 2020 1st Semestral Report November 2020 PAK: Jamshoro Power Generation Project Prepared by the Jamshoro Power Company Limited (JPCL), with the assistance of Mott MacDonald Limited (United Kingdom) in joint venture with MM Pakistan (Pvt) Ltd (Pakistan), for the Islamic Republic of Pakistan and the Asian Development Bank. This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgements as to the legal or other status of any territory or area. Semi-annual Environment Monitoring Report January to June 2020 October 2020 Project Number: 47094-001 Reporting period: Month Year: January to June 2020 Islamic Republic of Pakistan: Jamshoro Power Generation Project Financed by the Asian Development Bank Mott MacDonald Prepared by: L Stone Victory House Trafalgar Place Mott MacDonald Brighton BN1 4FY United Kingdom T +44 (0)1273 365000 mottmac.com For Jamshoro Power Company Limited Endorsed by (JPCL) Semi-annual Environment Monitoring Report January to June 2020 October 2020 Mott MacDonald Limited. Registered in England and Wales no. 1243967. Registered office: Mott MacDonald House, 8-10 Sydenham Road, Croydon CR0 2EE, United Kingdom Mott MacDonald | Semi-annual Environment Monitoring Report January to June 2020 Issue and Revision Record Revision Date Originator Checker Approver Description 01 16.10.202 Laura Stone Jim JMV for Dario Reported information in the 0 Venetucci Cacciatore absence of most Contractor supplied reporting Document reference: 334014 | JPCL-R-02916 | A33014-MML-JPCL-R-02916 Information class: Standard This Report has been prepared solely for use by the party which commissioned it (the 'Client') in connection with the captioned project. It should not be used for any other purpose. No person other than the Client or any party who has expressly agreed terms of reliance with us (the 'Recipient(s)') may rely on the content, information or any views expressed in the Report. This Report is confidential and contains proprietary intellectual property and we accept no duty of care, responsibility or liability to any other recipient of this Report. No representation, warranty or undertaking, express or implied, is made and no responsibility or liability is accepted by us to any party other than the Client or any Recipient(s), as to the accuracy or completeness of the information contained in this Report. For the avoidance of doubt this Report does not in any way purport to include any legal, insurance or financial advice or opinion. We disclaim all and any liability whether arising in tort, contract or otherwise which we might otherwise have to any party other than the Client or the Recipient(s), in respect of this Report, or any information contained in it. We accept no responsibility for any error or omission in the Report which is due to an error or omission in data, information or statements supplied to us by other parties including the Client (the 'Data'). We have not independently verified the Data or otherwise examined it to determine the accuracy, completeness, sufficiency for any purpose or feasibility for any particular outcome including financial. Forecasts presented in this document were prepared using the Data and the Report is dependent or based on the Data. Inevitably, some of the assumptions used to develop the forecasts will not be realised and unanticipated events and circumstances may occur. Consequently, we do not guarantee or warrant the conclusions contained in the Report as there are likely to be differences between the forecasts and the actual results and those differences may be material. While we consider that the information and opinions given in this Report are sound all parties must rely on their own skill and judgement when making use of it. Information and opinions are current only as of the date of the Report and we accept no responsibility for updating such information or opinion. It should, therefore, not be assumed that any such information or opinion continues to be accurate subsequent to the date of the Report. Under no circumstances may this Report or any extract or summary thereof be used in connection with any public or private securities offering including any related memorandum or prospectus for any securities offering or stock exchange listing or announcement. By acceptance of this Report you agree to be bound by this disclaimer. This disclaimer and any issues, disputes or claims arising out of or in connection with it (whether contractual or non-contractual in nature such as claims in tort, from breach of statute or regulation or otherwise) shall be governed by, and construed in accordance with, the laws of England and Wales to the exclusion of all conflict of laws principles and rules. All disputes or claims arising out of or relating to this disclaimer shall be subject to the exclusive jurisdiction of the English and Welsh courts to which the parties irrevocably submit. 334014 | JPCL-R-02916 | A | 33014-MML-JPCL-R-02916 | October 2020 Mott MacDonald | Semi-annual Environment Monitoring Report January to June 2020 Contents Abbreviations 1 1 Introduction 2 1.1 Preamble 2 1.2 Headline information 2 2 Project description and current activities 3 2.1 Project description 3 2.2 Project contracts and management 4 2.3 Project activities during current reporting period 5 2.4 Description of any changes to project design 7 2.5 Description of any changes to agreed construction methods 8 3 Environmental safeguard activities 11 3.1 General description of environmental safeguard activities 11 3.2 Site inspections/audits – remediation lots 3 and 5 11 3.3 Site inspections/audits – 660MW power plant 12 3.4 Issues tracking (based on non-conformance notices) 17 3.5 Trends 18 3.6 Unanticipated environmental impacts or risks 19 4 Results of environmental monitoring 20 4.1 Overview of monitoring conducted during current period 20 4.2 Lot 5 – Colony sewage treatment plant 20 4.2.1 Overview 20 4.2.2 Trends 22 4.2.3 Summary of monitoring outcomes 22 4.2.4 Material resources utilisation 22 4.2.5 Waste management 22 4.2.6 Health and safety 23 4.2.7 Training 23 4.2.8 Conclusion 23 4.3 660MW power plant – main contract 23 4.3.1 Trends 26 4.3.2 Summary of monitoring outcomes 26 4.3.3 Material resources utilisation 26 4.3.4 Waste management 26 4.3.5 Health and safety 27 4.3.6 Training 28 334014 | JPCL-R-02916 | A | 33014-MML-JPCL-R-02916 | October 2020 Mott MacDonald | Semi-annual Environment Monitoring Report January to June 2020 5 Functioning of the CEMMP 30 5.1 CEMMP review 30 5.1.1 Lot 5 30 5.1.2 660MW power plant – main contract 30 6 Good practice and opportunity for improvement 32 6.1 Good practice 32 6.2 Opportunities for improvement 32 6.2.1 Lot 5 – Colony sewage treatment plant 32 6.2.2 660MW power plant – main contract 33 7 Summary and recommendations 36 7.1 Summary 36 7.2 Recommendations 37 Annexes 38 A. EHS photographs 39 A.1 Remediation Lot 3 39 A.2 Lot 5 40 A.3 2x660 MW EPC 42 B. 660MW Site location/layout plan 44 C. Lot 5 contractor monitoring report 46 D. 660MW main build contractor monitoring reports, January – June 2020 47 Tables Table 1: Main organisations 4 Table 2: Main project construction activities 6 Table 3: Worker numbers (maximum) during reporting period 7 Table 4: Environmental safeguard audits 11 Table 5: EHS meetings January to June 2020 12 Table 6: Lot 5 resource use January – June 2020 22 Table 7: Main build environmental and H&S monitoring/reporting 24 Table 8: Health and safety statistics 27 Figures 334014 | JPCL-R-02916 | A | 33014-MML-JPCL-R-02916 | October 2020 Mott MacDonald | Semi-annual Environment Monitoring Report January to June 2020 Figure 1: Actual progress against schedule 7 Figure 2: Rehabilitation/remediation Lots 1 to 6 9 Figure 3: Extract of Siemens-HEI ‘Summary of EHS Issues Highlighted by JPCL and PIC’ 18 Figure 4: Extract of Siemens-HEI ‘Summary of EHS Issues Highlighted by JPCL and PIC’ 19 Figure 5: EHS training trends presented in April-June 2020 EHS Report 29 Figure 6: 660MW power plant layout 45 Photos Photo 1: Rains and ponding of water resulting in lateral scope erosion and growth of vegetation 39 Photo 2: Open duct on the top slab of the newly constructed septic tank to be covered 40 Photo 3: Unsuitable location for electricity meter at the JPCL quarter at Septic tank III 40 Photo 4: Drinking coolers should be labelled as suitable for drinking water, clean and chilled and kept in a shaded area with seating provided 41 Photo 5: Inappropriate kitchen facilities for workers 41 Photo 6: Non-conformance raised regarding working at height and scaffolding 42 Photo 7: Sub-standard scaffolding at the circulating water pipeline area 43 Photo 8: Unsafe working at height at the stack area 43 334014 | JPCL-R-02916 | A | 33014-MML-JPCL-R-02916 | October 2020 Mott MacDonald | Semi-annual Environment Monitoring Report 1 January to June 2020 Abbreviations ADB Asian Development Bank CEMMP Construction environmental management and monitoring plan EMR Environmental monitoring review GHCL Genco Holdings Company Limited HEI Harbin Electric International JPCL Jamshoro Power Company Limited JPGP Jamshoro Power Generation Project MW Megawatt PIU Project implementation unit PIC Project implementation consultant PMU Project management unit SAEMR Semi-annual environmental monitoring report 334014 | JPCL-R-02916 | A | 33014-MML-JPCL-R-02916 | October 2020 Mott MacDonald | Semi-annual Environment Monitoring Report 2 January to June 2020 1 Introduction 1.1 Preamble 1.

View Full Text

Details

  • File Type
    pdf
  • Upload Time
    -
  • Content Languages
    English
  • Upload User
    Anonymous/Not logged-in
  • File Pages
    59 Page
  • File Size
    -

Download

Channel Download Status
Express Download Enable

Copyright

We respect the copyrights and intellectual property rights of all users. All uploaded documents are either original works of the uploader or authorized works of the rightful owners.

  • Not to be reproduced or distributed without explicit permission.
  • Not used for commercial purposes outside of approved use cases.
  • Not used to infringe on the rights of the original creators.
  • If you believe any content infringes your copyright, please contact us immediately.

Support

For help with questions, suggestions, or problems, please contact us