Northeast Anthony Henday Drive

Northeast Anthony Henday Drive

Northeast Anthony Henday Drive Bill van der Meer Urban Construction Manager - Edmonton Alberta Transportation Project Background 2 Edmonton Ring Road Northwest completed Nov 2011 Northeast to be completed October 2016 Southwest completed Southeast 2006 completed 2007 Completion of the Northeast section will make Anthony Henday Drive the first complete ring road around a Canadian city. 3 Project Scope 4 Project Scope • 27 kilometres of freeway: – Anthony Henday Drive, from Whitemud Drive to Yellowhead Trail – 9 km of reconstructed freeway – Anthony Henday Drive, from Yellowhead Trail to Manning Drive – 9km of new freeway – Yellowhead Trail, east of the river to east of Sherwood Drive – 6km of of reconstructed freeway – Sherwood Park Freeway, west of 17 St to Ordze Crescent – 3 km of reconstructed freeway • 9 interchanges 2 flyovers • 47 bridges (includes NSR crossing) • 24 stormwater ponds • 103 overhead signs 5 Whitemud Drive • Resurfacing of existing cloverleaf interchange • Addition of one lane on SB-WB ramp 6 Sherwood Park Freeway • Completely new Parclo interchange • Elevated Directional EB-NB ramp • 4 new bridge structures N 7 Sherwood Park Freeway/17 Street • Existing half diamond • New full diamond interchange • 1 new bridge structure 8 Baseline Road/101 Avenue • Reconstruction of existing interchange to meet geometric requirements • Signalized ramp intersection • 3 new bridge structures N 9 Petroleum Way Underpass • Evacuation route for Petro Canada refinery • Road to be widened with grading for 4 lanes; 2 lanes paved in Stage 1 • Existing bridge culvert structure to be removed and replaced with new ultimate stage structure 10 Yellowhead Trail • Systems Interchange • 6 new bridge N structures on 3 elevations • New major, multi- level, free-flow interchange replacing existing service interchange 11 Yellowhead Trail • 2 basket weaves N 12 Yellowhead Trail N CP Railway N • 9 new rail crossing structures 13 Yellowhead Trail • Modification to 2 existing rail structures 14 Yellowhead Trail/Broadmoor Boulevard • Existing parclo interchange to be replaced. • 1 new bridge structure N 15 Yellowhead Trail/Sherwood Drive • Existing right-in-right-out intersection to be replaced with new grade-separated interchange • 1 new bridge structure N 16 130 Avenue EWMC access • New grade-separated interchange • 1 new bridge structure • Access to EWMC and gravel operations to be maintained Waste Management Centre N 17 North Saskatchewan River Crossing • New four-span twin bridge structures across the North Saskatchewan River Looking north N 18 153 Avenue • New grade-separated interchange in ‘greenfield’ • 1 new bridge structure 18 Street N 19 Victoria Trail/CN Crossings Anthony Henday Drive • New Victoria Trail underpass • Flyovers at Coronado and Vegreville CN crossings 26 Street N 20 Manning Drive • 3 new bridge structures • Paving of already graded east leg to be completed as part of NEAHD. N Manning Drive 21 Project information 22 Project Costs • Net present value $1.81B • Largest provincial road contract ever • Previous Alberta Projects – Northwest Ring Road $1,420M net present value – Southeast Ring Road $497M net present value – Northeast Stony Trail $651M net present value 23 Challenges • Construction on existing roads • 9 rail crossings • North Saskatchewan River crossing • 500+ identified potential utility conflicts including major pipelines 24 Detour Standards • Yellowhead Trail, Anthony Henday Drive - 2 lanes each direction at all times • Baseline Road, Sherwood Park Freeway, Broadmoor Boulevard, Sherwood Drive, Whitemud Drive – 2 lanes each direction at all times • All other roadways – 1 lane each direction at all times 25 Technical Requirements • Maintain existing traffic movements throughout construction at all loops and ramps, at- grade intersections • Maintain access to properties affected by construction • Submit traffic accommodation plans for approval 26 Yellowhead Trail/Anthony Henday Drive • 4 Stages to construction • June 2012 to August 2016 • Various detours 27 The Contract • Design, Build, Finance, Operate • Innovative solutions • Integrate design, construction and maintenance • More rapid implementation • Fixed price • Fixed completion date • 30 year warranty 28 The Team • Client – Owner - Alberta Transportation – Owner's Engineer - ISL Engineering • Concessionaire – Capital City Link Group Partnership (CCLGP) • Design/Build Contractor Team – Flatiron Dragados Aecon Lafarge (FDAL) – AECOM, Stantec and MMM • Operations/Maintenance – Volker Stevin 29 The Program • Contract Award May 2012 • Traffic Availability October 2016 30 Drive-through 31 Any Questions? 32.

View Full Text

Details

  • File Type
    pdf
  • Upload Time
    -
  • Content Languages
    English
  • Upload User
    Anonymous/Not logged-in
  • File Pages
    32 Page
  • File Size
    -

Download

Channel Download Status
Express Download Enable

Copyright

We respect the copyrights and intellectual property rights of all users. All uploaded documents are either original works of the uploader or authorized works of the rightful owners.

  • Not to be reproduced or distributed without explicit permission.
  • Not used for commercial purposes outside of approved use cases.
  • Not used to infringe on the rights of the original creators.
  • If you believe any content infringes your copyright, please contact us immediately.

Support

For help with questions, suggestions, or problems, please contact us