Technical Feasibility and Life Cycle Cost Assessment of a Photovoltaic Array on Trinity Dam, Trinity County, Ca

Technical Feasibility and Life Cycle Cost Assessment of a Photovoltaic Array on Trinity Dam, Trinity County, Ca

TECHNICAL FEASIBILITY AND LIFE CYCLE COST ASSESSMENT OF A PHOTOVOLTAIC ARRAY ON TRINITY DAM, TRINITY COUNTY, CA By Caleb Aaron Patrick A Project Presented to The Faculty of Humboldt State University In Partial Fulfillment for the Requirements for the Degree Masters of Science in Environmental Systems: Energy, Technology and Policy Committee Membership Dr. Arne Jacobson, Committee Chair Dr. Steven Hackett, Committee Member Dr. Peter Alstone, Committee Member Dr. Margaret Lang, Program Graduate Coordinator May 2018 ABSTRACT TECHNICAL FEASIBILITY AND LIFE CYCLE COST ASSESSMENT OF A PHOTOVOLTAIC ARRAY ON TRINITY DAM, TRINITY COUNTY, CA Caleb Patrick Public lands owned by the Bureau of Land Management are increasingly being used for photovoltaic (PV) system development. Although numerous policies support PV deployment on public lands, those managed by the Bureau of Reclamation have not been considered for PV development. Hydro-electric embankment dams, both publicly and privately owned, may have the potential to be development sites for distributed PV systems. A technical feasibility report was conducted for a case study of a PV installation on Trinity Dam, Trinity County, CA, and found embankment dams could potentially be feasible development sites. A mounting analysis found that a concrete slab reinforced with rebar could be used to mount a PV array on Trinity Dam. A nominal 1 MW-dc PV system was designed and used to determine lifetime system production and to conduct the economic analysis. The hypothetical system at the Trinity Dam site is estimated to have a lifetime energy production of approximately 30 GWh and would displace about 8,000 metric tons of CO2-equivalent. Non-profit and private ownership scenarios were considered to estimate the economic feasibility of a 1MW-dc distributed PV system on Trinity Dam. System costs and benefits were calculated and analyzed for a 25-year investment. A life cycle cost assessment found that a non-profit system connected behind the meter for on-site consumption would have a levelized cost of energy of $0.056/kWh, ii a discounted payback period of 8.7 years, and an internal rate of return of 9%. A privately owned system would produce a levelized cost of energy of $0.04/kWh, a discounted payback period of 4.9 years, and an internal rate of return of 16%. Based on the LCCA for a 1 MW-dc system on Trinity Dam, it is recommended that a non-profit or private investment could be economically beneficial if the system was installed behind the meter to serve on-site loads under the PG&E E-19 rate tariff. In a front of the meter PPA contract scenario, a non-profit investment would have a DPB of more than 25 years and a private investment would have a DPB of 16.2 years. Therefore, an investment in a front of the meter system for Trinity Dam is not recommended unless a higher PPA rate can be negotiated with the utility. iii ACKNOWLEGEMENTS I would like to first acknowledge my committee chairperson, Dr. Arne Jacobson, for all his assistance and advice throughout this research journey. I would like to thank the other members of my committee, Dr. Steven Hackett and Dr. Peter Alstone for their interest, assistance and support. I would also like to thank Michael Griffin, Structure Design and Engineering, LLC, for a detailed analysis of the mounting feasibility for photovoltaics on Trinity Dam; Zack Zoller for coaching me through photovoltaic system design and application; Don Bader, BOR; Larry Ball, BOR; Russel Knight, WAPA; Wilson Head, WAPA; Barry Mortimeyer, BOR; Paul Hauser, General Mgr, TPUD; Andy Lethbridge, TPUD; Jim Bowman and Israel Patterson, BOR; Brian Lipps, Dsire.org; Dennis Sullivan, Manager Competitive Solicitations, PG&E; Jeffrey Tang, Suntech; and my family and friends that have supported me along the way. iv TABLE OF CONTENTS 1 INTRODUCTION ................................................................................................................... 1 2 BACKGROUND ..................................................................................................................... 4 2.1 Photovoltaics ........................................................................................................................ 4 2.2 PV Grid Interconnection ...................................................................................................... 6 2.3 Earth and Rock-fill Hydro-electric Embankment Dams in CA ......................................... 13 2.4 PV on Embankment Dams ................................................................................................. 14 2.5 PV Development on Federal Lands ................................................................................... 17 2.6 Financing PV Development on Federal Embankment Dams ............................................ 20 2.7 PV Ownership Structure .................................................................................................... 26 2.8 Balancing PV Variability ................................................................................................... 27 3 METHODS ............................................................................................................................ 28 3.1 Technical Feasibility .......................................................................................................... 28 3.2 Economic Feasibility ......................................................................................................... 30 4 TRINITY DAM CASE STUDY ............................................................................................ 31 4.1 Trinity Dam Regional Context ........................................................................................... 31 4.2 Technical Feasibility .......................................................................................................... 34 4.2.1 Potential for locally distributed PV ........................................................................ 34 4.2.2 Potential for distributed PV .................................................................................... 36 4.2.3 Ownership structure ............................................................................................... 38 4.2.4 Site analysis ........................................................................................................... 41 4.2.5 Solar resource ......................................................................................................... 44 4.2.6 Mounting recommendation .................................................................................... 49 4.2.7 System design ........................................................................................................ 54 4.3 Economic Feasibility ......................................................................................................... 57 4.3.1 Trinity Dam system ownership structure ............................................................... 58 4.3.2 Life cycle cost assessment ..................................................................................... 59 4.4 Summary of Results ........................................................................................................... 72 4.4.1 Technical report ..................................................................................................... 72 v 4.4.2 Economic report ..................................................................................................... 73 5 DISCUSSION AND CONCLUSIONS ................................................................................. 74 Works Cited ................................................................................................................................... 77 APPENDIX A: Civil Engineering Calculations ............................................................................ 87 APPENDIX B: LCCA Computation Formulas ............................................................................. 97 APPENDIX C: PVWattsTM Production Estimate, 1MW-dc Nominal System Production Estimate, Trinity Dam, Trinity County, CA .................................................................................................. 99 APPENDIX D: 1 MW System Design Specifications ................................................................. 100 APPENDIX E: Module Cost, Structural BOS Cost, PII Cost, and Land Lease Cost Sensitivity Analysis ....................................................................................................................................... 104 APPENDIX F: List of Potentially Qualified Embankment Dams in California .......................... 107 vi LIST OF TABLES Table 1: Current Incentives for Distributed PV (Database of State Incentives for Renewables and Efficiency, 2018) ................................................................................... 22 Table 2: PVWattsTM Location Comparison ...................................................................... 47 Table 3: Lifetime Production Estimates for 1 MW-dc PV Array Using PVWattsTM Data ........................................................................................................................................... 48 Table 4: Trinity Dam System Component Costs .............................................................. 61 Table 5: PVWattsTM Production Estimate ...................................................................... 99 Table 6: E-19 Rate Module Cost, Structural BOS Cost, PII Cost, and Land Lease Cost Sensitivity Analysis .......................................................................................................

View Full Text

Details

  • File Type
    pdf
  • Upload Time
    -
  • Content Languages
    English
  • Upload User
    Anonymous/Not logged-in
  • File Pages
    117 Page
  • File Size
    -

Download

Channel Download Status
Express Download Enable

Copyright

We respect the copyrights and intellectual property rights of all users. All uploaded documents are either original works of the uploader or authorized works of the rightful owners.

  • Not to be reproduced or distributed without explicit permission.
  • Not used for commercial purposes outside of approved use cases.
  • Not used to infringe on the rights of the original creators.
  • If you believe any content infringes your copyright, please contact us immediately.

Support

For help with questions, suggestions, or problems, please contact us