A Case Study in Temporary Works (Fig 2)

A Case Study in Temporary Works (Fig 2)

Design is not a commodity A case study in temporary works (fig 2) (fig 3) (fig 1) Project: Lee Tunnel Client: Various Lee Tunnel tapering rebate wall requires design experience The Lee Tunnel forms part of the Thames Tideway Scheme and is designed for the storage and conveyance of sewage mixed with rainwater, running from Abbey Mills Pumping Station down to Beckton Sewage Treatment Works. Members of the team here at PDMA worked at different times on different parts of the scheme for several different contractors. Adaptation key to success Initially the team’s involvement was with Slipform International, who required support for the lining of a 40m diameter shaft. The standard Slipform equipment had to be adapted for a single-sided shaft lining with a tapering rebate. Following construction of the tunnels, the standard Slipform equipment was adapted a second time to form a tapering wall, keyed into the rebate at each side of the shaft. To enable the formwork to taper, the normal fixed joints between members, on which the rig relies for stability, had to be pinned. Alternative load paths were introduced to achieve this, with a sophisticated computer analysis undertaken to help convince the client that the finished rig would be stable. The analysis used out-of-balance load cases in accordance with Eurocode 0, which describes the basis and general principles for structural safety, serviceability (fig 1) design and durability. Although a challenge to demonstrate the rig was stable Immersed tubes being loaded under this loading, it was ultimately successful. into River Thames. (fig 2) Slipforming the tapering wall in the shaft at Beckton (fig 3) Free flow cofferdam for installation of immersed tubes. (fig 5) (fig 6) (fig 4) Dredged channel requires retaining wall design The outfall from the Lee Tunnel was constructed as an immersed tube installed in a dredged channel. It was members of our team responsible for designing the free-flow sheet pile retaining walls required to support the ground adjacent to the channel and to allow the 3m diameter tubes to be floated into position. (fig 7) Part of the new outfall and retaining walls had to be installed under an existing jetty which carried services to a docking facility. It was not permitted to disturb the jetty, so a scheme was devised to lower pre- cast beams under the jetty, which would then be sunk in place like a caisson whilst the ground was removed under the jetty. This challenging project required the innovation and expertise of our highly experienced engineer, Mike Tindale, who commented: “To avoid settlement of the existing jetty foundations, it was essential to avoid loss of ground during (fig 8) installation of the temporary works. “A further complication was that all the necessary work would have to be carried out under water. “Our scheme was carefully detailed so that the components fitted together perfectly to avoid any paths where ground might enter the excavation. We predicted settlement and this was monitored throughout the construction period, ensuring it was kept within tolerable levels.” At the end of the outfall there is a reinforced concrete headwall, which is below low water level. (fig 4) Isometric View of Proposed We were asked to design this by the contractor, and we designed the permanent Headwall. works so that the formwork could be used as a bulkhead to enable the headwall to be floated into position and installed at the end of the free-flow retaining walls. (fig 5) Maximum Absolute Stress Contours for the Selfweight The outfall itself is heavily skewed, which required finite element analysis in (L.C. 1). accordance with Eurocode 7, to ensure the design achieved the required solution. (fig 6) Maximum Absolute Stress Contours for Serviceability (L.C. 2). (fig 7) Maximum Absolute Stress Contours for Design Approach 1 (Combination 1) (L.C. 3) (fig 8) Maximum Absolute Stress Contours for Design Approach 1 (Combination 2) (L.C. 4) HIGHLIGHTS • Permanent and temporary works design on the same project • Designs for three different contractors • All elements of temporary and permanent works design were challenging Head Office 0808 196 1460 PDMA Consulting Engineers Limited, [email protected] Concorde House, Union Drive, To view more case studies, visit Sutton Coldfield, www.pdmace.com West Midlands, B73 5TE.

View Full Text

Details

  • File Type
    pdf
  • Upload Time
    -
  • Content Languages
    English
  • Upload User
    Anonymous/Not logged-in
  • File Pages
    4 Page
  • File Size
    -

Download

Channel Download Status
Express Download Enable

Copyright

We respect the copyrights and intellectual property rights of all users. All uploaded documents are either original works of the uploader or authorized works of the rightful owners.

  • Not to be reproduced or distributed without explicit permission.
  • Not used for commercial purposes outside of approved use cases.
  • Not used to infringe on the rights of the original creators.
  • If you believe any content infringes your copyright, please contact us immediately.

Support

For help with questions, suggestions, or problems, please contact us