North Burnett Regional Council Civil Works Program 2020-21 Duration Start Finish % Complete Area Maintenance Crew (Biggenden) 140.5d 07/01/20 03/25/21 87% RMPC Slashing 12d 07/01/20 07/21/20 100%Biggenden Berries Road - Medium Formation Grade (Ch 2.24 - 11.37) 11d 07/22/20 08/07/20 100%Biggenden Swindle Creek Rd - Medium Formation Grade (Ch 0.00 - 5.25) 8d 08/11/20 08/21/20 100%Biggenden Longatong Rd - Medium Formation Grade (Ch 0.00 - 7.46) 6d 08/25/20 09/02/20 100%Biggenden Cherelly Orchard Rd - Medium Formation Grade & Pipe Install (Ch 0.00 - 7.07) 15d 09/03/20 09/29/20 100%Biggenden RMPC - Wing Walls 19C 6d 09/30/20 10/08/20 100%Biggenden RMPC - Extra Wide Slashing Area Coalstoun Lakes 6d 10/09/20 10/20/20 100%Biggenden DTMR Gayndah Mount Perry Road - Gravel Resheet (Ch 29.24 - 30.71) 10d 10/21/20 11/05/20 100%Biggenden DTMR Gayndah Mount Perry Road - Maintenance Grade (Ch 14.00 - 29.59) 6d 11/06/20 11/17/20 100%Biggenden Nulla Creek Rd - Medium Formation Grade (Ch 0.00 - 4.26) 7d 11/18/20 11/27/20 100%Biggenden Paradise Dam Rest Area - Shoulder Repairs 2d 12/01/20 12/02/20 100%Biggenden Wilson Valley - Medium Formation Grade (Ch 0.00 - 14.45) 3d 12/03/20 12/08/20 100%Biggenden Fowlers Road - Light Formation Grade 3d 12/09/20 12/11/20 100%Biggenden Town and Depot Clean Up 4d 12/15/20 12/18/20 100%Biggenden RMPC - Patching and Guideposts 4d 01/12/21 01/15/21 100%Biggenden Airport Repairs & Town Street Mowing 7d 01/19/21 01/29/21 100%Biggenden Bitumen Rehab Work 8d 02/02/21 02/12/21 100%Biggenden Plum Creek Road - Medium Formation Grade (Ch 0.00 - 3.64) 2d 02/16/21 02/17/21 100%Biggenden RMPC Pipe Separations/Other Bitumen Work 3d 02/18/21 02/23/21 100%Biggenden Bitumen Rehab Work 3d 02/24/21 02/26/21 100%Biggenden Aberdeens Road - Medium Formation Grade (Ch 0.00 - 8.74) 5d 03/02/21 03/09/21 0%Biggenden Lime Mines Rd - Medium Formation Grade (Ch 0.00 - 3.05) 3d 03/10/21 03/12/21 0%Biggenden Farrells Road - Medium Formation Grade (0.00 - 8.46) 4d 03/16/21 03/19/21 0%Biggenden Hunters Road - Medium Formation Grade (Ch 0.00 - 2.25) 1d 03/16/21 03/16/21 0%Biggenden Walla Lane - Medium Formation Grade (Ch 0.00 - 0.14) 0.5d 03/17/21 03/17/21 0%Biggenden Witton Road - Medium Formation Grade (Ch 0.00 - 1.47) 2d 03/17/21 03/19/21 0%Biggenden Sandarrah Road - Medium Formation Grade (Ch 0.00 - 3.22) 2d 03/19/21 03/24/21 0%Gayndah Fletchers Lane - Medium Formation Grade (Ch 0.00 - 0.98) 1d 03/24/21 03/25/21 0%Gayndah Maintenance Crew (Eidsvold) 154d 07/02/20 04/22/21 80% Rockmelon Lane - Medium Formation Grade (Ch 0.00 - 7.20) 4d 07/02/20 07/08/20 100%Eidsvold Mesner Road - Medium Formation Grade (Ch 0 - 1.02) 1d 07/09/20 07/09/20 100%Eidsvold Ross Crossing Rd - Medium Formation Grade (Ch 0.00 - 9.66) 6d 07/10/20 07/21/20 100%Eidsvold Barrule Rd - Medium Formation Grade (Ch 0.00 - 16.36) 11d 07/22/20 08/07/20 100%Eidsvold Disclaimer: Proposed Future Works Program is subject to change without notice or approval as it is dependant on resources, materials and weather permitting. North Burnett Regional Council Civil Works Program 2020-21 Duration Start Finish % Complete Area Old Rawbelle Rd - Medium Formation Grade (Ch 64.31 - 85.66) 19d 08/11/20 09/10/20 100%Eidsvold Glencoe Rd - Medium Formation Grade (Ch 72.90 - 91.00) 9d 09/11/20 09/25/20 100%Eidsvold Private Works 2d 09/29/20 09/30/20 100%Eidsvold Racecourse Road - Medium Formation Grade (Ch 0.00 - 1.23) 1d 10/01/20 10/01/20 100%Eidsvold Radio Station Road - Medium Formation Grade (Ch 1.93 - 6.04) 2d 10/02/20 10/06/20 100%Eidsvold Calrossie Rd - Medium Formation Grade (Ch 0.00 - 16.85) 5d 10/07/20 10/14/20 100%Eidsvold Knockbreak Road - Medium Formation Grade (0.00 - 3.64) 2d 10/15/20 10/16/20 100%Eidsvold Coonambula Road - TIDS Widen and Overlay (Ch 11.20 - 13.00) 31d 10/20/20 12/10/20 100%Eidsvold Town and Depot Clean Up 5d 12/11/20 12/18/20 100%Eidsvold Coonambula Road - Medium Formation Grade (Ch 19.19 - 43.37) 8d 01/12/21 01/22/21 100%Eidsvold Stanmore Rd - Resheet 5d 01/27/21 02/03/21 100%Eidsvold Coonambula Road - Medium Formation Grade (chelt - barrule) 2d 02/04/21 02/05/21 100%Eidsvold Lochaber Road - Gravel Resheet (Ch 2.00 - 3.00) 5d 02/09/21 02/16/21 100%Eidsvold Gayndah Mundubbera Road - Signage Installation 1d 02/17/21 02/17/21 95%Eidsvold Burnett Highway - Insitu Stabilistation 1d 02/18/21 02/18/21 100%Eidsvold Three Moon Creek Road - Medium Formation Grade (Ch 0.00 - 6.18) 4d 02/19/21 02/25/21 90%Eidsvold Barram Road - Medium Formation Grade (Ch 0.00 - 9.65) 5d 02/26/21 03/05/21 0%Eidsvold Coonambula Road - Patch Gravel 6d 03/09/21 03/17/21 0 Gravelly Creek Road - Light Formation Grade (Ch 0.00 - 7.74) 4d 03/18/21 03/24/21 0%Eidsvold Mount Eagle Road - Light Formation Grade (Ch 0.00 - 20.55) 11d 03/25/21 04/15/21 0%Eidsvold Annual Leave 4d 04/16/21 04/22/21 Maintenance Crew (Gayndah) 143d 07/01/20 03/30/21 89% Old Eidsvold-Lochaber Rd - Medium Formation Grade (Ch 0.00 - 30.00) 18d 07/01/20 07/30/20 100%Gayndah Tilleys Rd - Medium Formation Grade (Ch 0.00 - 6.61) 3d 07/31/20 08/05/20 100%Gayndah Parkers Rd - Medium Formation Grade (Ch 0.00 - 2.61) 3d 08/06/20 08/11/20 100%Gayndah Binjour Branch Creek Rd - Medium Formation Grade (Ch 4.09 - 13.45) 7d 08/12/20 08/21/20 100%Gayndah Plowey Lane - Medium Formation Grade (Ch 0.00 - 1.80) 1d 08/25/20 08/25/20 100%Gayndah Top Gurgeena Road - Medium Formation Grade (Ch 7.63 - 15.25) 3d 08/26/20 08/28/20 100%Gayndah Tudors Rd - Medium Formation Grade (Ch 0.00 -5.20) 3d 09/01/20 09/03/20 100%Gayndah Black Horse Creek Rd - Medium Formation Grade (Ch 0.00 - 17.88) 7d 09/04/20 09/16/20 100%Gayndah Scanlans Road - Medium Formation Grade (Ch 1.13 - 4.24) 2d 09/17/20 09/18/20 100%Gayndah Linsketts Road - Medium Formation Grade (Ch 0.00 - 1.08) 1d 09/22/20 09/22/20 100%Gayndah Boyd Road - Medium Formation Grade (Ch 0.00 - 1.53) 1d 09/23/20 09/23/20 100%Gayndah Little Woodmillar Road - Medium Formation Grade (Ch 0.00 - 4.60) 2d 09/24/20 09/25/20 100%Gayndah Disclaimer: Proposed Future Works Program is subject to change without notice or approval as it is dependant on resources, materials and weather permitting. North Burnett Regional Council Civil Works Program 2020-21 Duration Start Finish % Complete Area Tableland Road - Medium Formation Grade (Ch 1.90 - 5.61) 2d 09/29/20 09/30/20 100%Gayndah East Woodmillar Road - Medium Formation Grade (Ch 0.00 - 11.75) 3d 10/01/20 10/06/20 100%Gayndah Daltons Road - Medium Formation Grade (Ch 0.00 - 0.75) 1d 10/07/20 10/07/20 100%Gayndah Huths Road - Medium Formation Grade (Ch 0.00 - 0.50) 1d 10/08/20 10/08/20 100%Gayndah Back Woodmillar - Medium Formation Grade (Ch 0.00 - 6.80) 5d 10/09/20 10/16/20 100%Gayndah The Ridges Road - Medium Formation Grade (Ch 0.00 - 3.63) 3d 10/20/20 10/22/20 100%Gayndah Bushnell Road - Medium Formation Grade (Ch 0.00 - 0.82) 1d 10/23/20 10/23/20 100%Gayndah Ban Ban Springs Road - Medium Formation Grade (Ch 0.00 - 3.88) 2d 10/27/20 10/28/20 100%Gayndah Brian Pastures Road - Medium Formation Grade (Ch 5.01 - 13.35) 4d 10/29/20 11/04/20 100%Gayndah Bitumen Rehab Works 22d 11/05/20 12/11/20 100%Gayndah Town Streets- Broom And Tidy 4d 12/15/20 12/18/20 100%Gayndah Top Gurgeena- Reseal Prep Shoulder Works 2d 01/12/21 01/13/21 100%Gayndah Safety Day 1d 01/14/21 01/14/21 100%Gayndah Crew Holidays 4d 01/15/21 01/21/21 100%Gayndah Mundubbera Dump 1d 01/22/21 01/22/21 100%Gayndah Reseal stone stockpile areas-Munduberra and Gayndah 3d 01/27/21 01/29/21 100%Gayndah Bitumen Rehab Works 4d 02/02/21 02/05/21 100%Various Mount Debatable Road - Medium Formation Grade (Ch 0.00 - 4) first section 2d 02/09/21 02/10/21 100%Gayndah Beinke Road - Medium Formation Grade (Ch 0.00 - 0.82) 1d 02/11/21 02/11/21 100%Gayndah McConnell Road - Medium Formation Grade (Ch 0.00-0.94) 1d 02/12/21 02/12/21 100%Gayndah Mount Debatable Road - Medium Formation Grade (4.00-9.54) 2d 02/16/21 02/17/21 100%Gayndah Smiths Road - Medium Formation Grade (Ch 0.00 - 3.64) 2d 02/18/21 02/19/21 100%Gayndah Mount Lawless Road - Medium Formation Grade (Ch 0.00 - 2.65) 1d 02/23/21 02/23/21 100%Gayndah Elystan Road - Scour repair 1d 02/24/21 02/24/21 100%Gayndah Biggenden Pavement Rehab 2d 02/25/21 02/26/21 100%Biggenden Dents Road - Medium Formation Grade (Ch 0.00 - 2.60) 1d 03/02/21 03/02/21 100%Gayndah Lara Road - Medium Formation Grade (Ch 0.00 - 1.25) 1d 03/03/21 03/03/21 0%Gayndah Yenda Road - Medium Formation Grade (Ch 7.45 - 28.83) 10d 03/04/21 03/19/21 0%Gayndah Elystan Road - Medium Formation Grade (Ch 0.00 - 11.84) 5d 03/23/21 03/30/21 0%Gayndah Maintenance Crew (Monto) 194d 07/01/20 06/30/21 64% Cooks Rd - Medium Formation Grade (Ch 0.00 - 9.20) 8d 07/01/20 07/14/20 100%Monto Keyworths Rd - Medium Formation Grade (Ch 0.00 - 4.30) 1d 07/15/20 07/15/20 100%Monto Fairweathers Rd - Medium Formation Grade (Ch 0.00 - 6.60) 5d 07/16/20 07/23/20 100%Monto Voss Rd - Medium Formation Grade (Ch 0.200 - 4.51) 3d 07/24/20 07/29/20 100%Monto Disclaimer: Proposed Future Works Program is subject to change without notice or approval as it is dependant on resources, materials and weather permitting.

View Full Text

Details

  • File Type
    pdf
  • Upload Time
    -
  • Content Languages
    English
  • Upload User
    Anonymous/Not logged-in
  • File Pages
    9 Page
  • File Size
    -

Download

Channel Download Status
Express Download Enable

Copyright

We respect the copyrights and intellectual property rights of all users. All uploaded documents are either original works of the uploader or authorized works of the rightful owners.

  • Not to be reproduced or distributed without explicit permission.
  • Not used for commercial purposes outside of approved use cases.
  • Not used to infringe on the rights of the original creators.
  • If you believe any content infringes your copyright, please contact us immediately.

Support

For help with questions, suggestions, or problems, please contact us