Aberdeen to Inverurie Redoubling: Don Viaduct

Aberdeen to Inverurie Redoubling: Don Viaduct

Staging Diagrams V1.2 Highlands Enhancement Programme Aberdeen to Inverurie Redoubling – Don Viaduct Robert McCafferty (Technical Head of Track BAM Nuttall) and David Herron (Associate Director AECOM) Background – Aberdeen to Inverness Line prior to HEP Inverness Nairn Keith Kennethmont Aberdeen Forres Elgin Huntly Insch Inverurie Dyce • Aberdeen to Inverness = 107 miles, mostly single line • 5 ½ miles of double track – Insch to Kennethmont • Passing Loops at stations at Dyce, Inverurie, Huntly Keith, Elgin, Forres and Nairn • 2hrs 18mins average journey time - 10 trains in either direction per day • Additional Aberdeen to Inverurie and Inverness to Elgin services at peak times Strategic Transport Projects Review (STPR) – 2008 Transport Scotland Output Requirements Keith Inverness Nairn Aberdeen Forres Elgin Huntly Insch Inverurie Dyce Dalcross Kintore • Hourly service between Aberdeen and Inverness • Half hourly service between Inverness and Elgin including a new station at Dalcross • Half hourly service between Aberdeen and Inverurie including a new station at Kintore • A circa 2 hour end to end journey time • Maintain, as a minimum, the ability to deliver existing freight access rights on the route • Requiring Interventions throughout the route Forres Station & Loop - 2017 Before • Single Platform Station • 266m radius curve • 20mph PSR • Token Exchange signalling After • 1880m passing Loop • NR60 F21.5 turnouts at either end • 75mph main line, 50mph on Loop • Simultaneous arrival in to station • Twin Platform Station with footbridge & Lifts • 2 LX’s closed • New overbridge and works on A96 Elgin Station & Loop - 2017 Before • 630m passing loop • GF operated turnout from main line in to yard • Token Exchange signalling • Manually controlled level crossing After • 1330m passing loop • NR60 F21.5 turnouts at either end • 75mph main line, 50mph on Loop • Simultaneous arrival in to station • MCB CCTV level crossing Aberdeen to Inverurie Redoubling 17 16 15 14 13 12 11 10 9 8 7 6 5 4 3 2 1 0 Inverurie Dyce Aberdeen • Aberdeen to Inverurie = 17 miles. 17 miles of redoubling sounds easy…….right? • Racing Line • Existing components – F7 sleepers with mills clips (1958) – Bullhead CWR (1989) – Timber sleepers with elastic spikes and 98lb rail (1958) • In total 40,000m of new track to be laid Aberdeen to Inverurie – Summary of proposed works • 40,000m of new track including 15 new point ends • 85000m3 of earthworks • 4300m of retaining walls • 30 Structures altered (extensions, infill, removal, strengthening) • 3 Level Crossing removals, 3 upgrades. • New station at Kintore • Plus re-signalling and new telecoms throughout along with associated ancillary civils, resulting in the closure of 2 signal boxes Don Viaduct – Existing Structure Superstructure Substructure • A single track supported on rail bearers spanning between • Superstructure is supported by 8 No. 2.1m diameter cross girders that are in turn supported from the two main granite masonry piers and 2 No. granite masonry outer girders. abutments. • No existing decking, other than an open mesh access walkway. Don Viaduct – Outline Design Proposed Superstructure Solution Impact on Substructure Replace Cross Girders Substructure Strengthening required. 85 new cross girders / trimmers 164 new stiffeners Strengthening of Main Girders New cantilever walkway Don Viaduct – Outline Design and impact of additional GI Substructure Solution Results of additional GI Don Viaduct – Outline Design and impact of additional GI Resultant Solution Don Viaduct – Focus Group Focus Group established May 2018 Meeting held every week to Open collaborative forum that completion of design. achieved integrated design / construction / fabrication with Network Aim of focus group was to – Rail engineers kept fully appraised • Resolve design issues during design process. • Incorporate construction preferences • Incorporate fabrication preferences • Consider safety during construction Don Viaduct – Focus Group Outcome Outcome of Focus Group Don Viaduct – Focus Group Outcome Outcome of Focus Group Shock Transmission Units Waybeam Geometry Don Viaduct – Safety in Design AIP Proposed Detail GRIP 5 Detail following Focus Group Installed Detail Don Viaduct – Track Installation • Longitudinal timbers • Schwihag BCR7 Baseplates with 33C1 Guard Rails • Gathering panels on approach • Transition at south end requires tapered shim under baseplate to achieve correct inclination and crossfall • Reduced installation tolerances Don Viaduct – Track Installation – Setting Out - Vertical Normal renewal = low rail level, ballast depth, sleeper and rail type – all known to within the mm Not Don Viaduct! Don Viaduct – Track Installation – Setting Out - Horizontal Setting out horizontal easier – co-ordinate for each bolt hole = 2112 setting out points Don Viaduct – Track Installation – Setting Out – Other things to consider • Baseplate centres (max 650mm) • Centre of baseplate fixing hole hole to edge of waybeam (min 75mm) • Centre of baseplate fixing hole to end of waybeam (min 150mm) • Max shim depth (30mm) • Baseplate rotation (+/-2mm) • Baseplate pair squareness (+/-5mm) • Agreed during design phase we would achieve reduced installation tolerances for horizontal and vertical Don Viaduct – Track Installation Problems……. Don Viaduct – Track Installation – Post Blockade Monitoring Don Viaduct • Before • During • After A2I Phase 2 – Completed Works • 45,000m of new track including 20 new point ends • 90,000m3 of earthworks • 4,300m of retaining walls • 33 Structures altered (extensions, infill, removal, strengthening) • 4 Level Crossing removals, 6 upgrades. • New station at Forres and Kintore • Closure of 4 signal boxes • Plus re-signalling and new telecoms throughout with associated ancillary civils. Aberdeen to Inverurie Redoubling – Don Viaduct Thank you .

View Full Text

Details

  • File Type
    pdf
  • Upload Time
    -
  • Content Languages
    English
  • Upload User
    Anonymous/Not logged-in
  • File Pages
    25 Page
  • File Size
    -

Download

Channel Download Status
Express Download Enable

Copyright

We respect the copyrights and intellectual property rights of all users. All uploaded documents are either original works of the uploader or authorized works of the rightful owners.

  • Not to be reproduced or distributed without explicit permission.
  • Not used for commercial purposes outside of approved use cases.
  • Not used to infringe on the rights of the original creators.
  • If you believe any content infringes your copyright, please contact us immediately.

Support

For help with questions, suggestions, or problems, please contact us