STATEMENT of ENVIRONMENTAL EFFECTS Proposed Electricity Generating Works 190 Rodhams Road, Uranquinty

STATEMENT of ENVIRONMENTAL EFFECTS Proposed Electricity Generating Works 190 Rodhams Road, Uranquinty

STATEMENT OF ENVIRONMENTAL EFFECTS Proposed Electricity Generating Works 190 Rodhams Road, Uranquinty September 2020 Project Number: 19-890 DOCUMENT VERIFICATION Project Title: Proposed Electricity Generating Works 190 Rodhams Road, Uranquinty Project Number: 19-890 Project File Name: \\10.0.14.1\Active\Projects\2019\19-890 Sandy Creek Solar Farm\Report Revision Date Prepared by Reviewed by Approved by Final 10/09/2020 J. Neuer, E. Matthews, S. Anderson L. Olesen - Jensen J. Duck/Z. Jokadar/ B. Poulton NGH Consulting prints all documents on environmentally sustainable paper including paper made from bagasse (a by-product of sugar production) or recycled paper. Statement of Environmental Effects Proposed Electricity Generating Works 190 Rodhams Road, Uranquinty TABLE OF CONTENTS 1. Introduction ............................................................................................................................................ 1 1.1. Overview .................................................................................................................................................. 1 1.2. Applicant And Land Ownership ............................................................................................................... 1 1.3. This Report .............................................................................................................................................. 1 1.4. Background ............................................................................................................................................. 2 1.5. Subject Land And Locality ....................................................................................................................... 3 2. The Development Proposal .................................................................................................................. 6 2.1. General Overview .................................................................................................................................... 6 2.2. Proposal Summary .................................................................................................................................. 6 2.3. Proposed Infrastructure ........................................................................................................................... 7 2.3.1. Solar arrays .............................................................................................................................. 7 2.3.2. Inverters and transformers ....................................................................................................... 8 2.3.3. Perimeter fencing and security CCTV ..................................................................................... 9 2.3.4. Distribution line connection and cabling .................................................................................. 9 2.3.5. Site access ............................................................................................................................. 10 2.3.6. Meteorological stations .......................................................................................................... 10 2.4. Construction .......................................................................................................................................... 10 2.4.1. Site preparation and earthworks ............................................................................................ 10 2.4.2. Temporary construction facilities ........................................................................................... 10 2.4.3. Materials and resources ......................................................................................................... 11 2.4.4. Personnel and work hours ..................................................................................................... 12 2.5. Operation ............................................................................................................................................... 12 2.5.1. Operation activities ................................................................................................................ 12 2.5.2. Transport and access ............................................................................................................ 13 2.5.3. Materials and resources ......................................................................................................... 13 2.5.4. Personnel and work hours ..................................................................................................... 13 2.5.5. Lighting ................................................................................................................................... 13 2.5.6. Refurbishment and upgrading ................................................................................................ 14 2.6. Decommissioning And Rehabilitation .................................................................................................... 14 2.7. Justification For The Project .................................................................................................................. 14 2.7.1. Strategic need ........................................................................................................................ 14 2.7.2. Socio-economic benefits ........................................................................................................ 17 2.8. Consultation ........................................................................................................................................... 18 NGH Pty Ltd | 19-890 - Final | i Statement of Environmental Effects Proposed Electricity Generating Works 190 Rodhams Road, Uranquinty 3. Environmental Analysis ...................................................................................................................... 20 3.1. Site Analysis .......................................................................................................................................... 20 3.1.1. Site description....................................................................................................................... 20 3.1.2. Existing land use .................................................................................................................... 20 3.1.3. Character and landscape ....................................................................................................... 22 3.2. Post-European Heritage ........................................................................................................................ 24 3.3. Aboriginal Cultural Heritage .................................................................................................................. 26 3.3.1. Existing conditions ................................................................................................................. 26 3.3.2. Potential impacts .................................................................................................................... 26 3.3.3. Recommendations ................................................................................................................. 26 3.4. Land Use And Resources ..................................................................................................................... 30 3.4.1. Existing conditions ................................................................................................................. 30 3.4.2. Potential impacts and recommendations ............................................................................... 35 3.5. Biodiversity Considerations ................................................................................................................... 37 3.5.1. Existing conditions ................................................................................................................. 37 3.5.2. Potential impacts .................................................................................................................... 39 3.5.3. Recommendations ................................................................................................................. 40 3.6. Bushfire ................................................................................................................................................. 42 3.6.1. Existing conditions ................................................................................................................. 42 3.6.2. Recommendations ................................................................................................................. 44 3.7. Flood and overland flow ........................................................................................................................ 45 3.7.1. Existing conditions ................................................................................................................. 45 3.7.2. Potential Impacts.................................................................................................................... 46 3.7.3. Recommendations ................................................................................................................. 46 3.8. Consideration Of Other Hazards ........................................................................................................... 46 3.8.1. Land slip ................................................................................................................................. 46 3.8.2. Acid sulfate

View Full Text

Details

  • File Type
    pdf
  • Upload Time
    -
  • Content Languages
    English
  • Upload User
    Anonymous/Not logged-in
  • File Pages
    142 Page
  • File Size
    -

Download

Channel Download Status
Express Download Enable

Copyright

We respect the copyrights and intellectual property rights of all users. All uploaded documents are either original works of the uploader or authorized works of the rightful owners.

  • Not to be reproduced or distributed without explicit permission.
  • Not used for commercial purposes outside of approved use cases.
  • Not used to infringe on the rights of the original creators.
  • If you believe any content infringes your copyright, please contact us immediately.

Support

For help with questions, suggestions, or problems, please contact us