Gatwick and the Brighton Main Line

Gatwick and the Brighton Main Line

GATCOM: Gatwick and the Brighton Main Line Gatwick and the Brighton Main Line Paul Harwood – Director Route Investment, Network Rail 24 Jan 19 / 1 GATCOM: Gatwick and the Brighton Main Line Thameslink Resilience Programme and the Three Bridges to Brighton Blockade 24 Jan 19 / 2 GATCOM: Gatwick and the Brighton Main Line Improving resilience and reliability Thameslink Resilience Programme - a £300m programme to improve reliability for passengers on key routes both north and south of the Thameslink ‘core’ through central London, cutting asset failures by a targeted 15% ahead of expanded Thameslink timetables. The programme will boost the reliability of all services, including Southern & GEX, travelling on these routes. We are targeting those areas where the most significant asset- related delays currently originate. £205m is being spent on the railway in Sussex and Kent. ► £67m is being spent on the Brighton Main Line 24 Jan 19 / 3 GATCOM: Gatwick and the Brighton Main Line Why Three Bridges to Brighton? ➢ VTB3 Brighton to Balcombe Tunnel Jct is a two line section of railway. ➢ 49% of trains presenting late at the ‘core’ are impacted by the VTB3 section of railway. ➢ Delays through this section are impacted heavily by repeat failing assets. 24 Jan 19 / 4 GATCOM: Gatwick and the Brighton Main Line Blockade and story so far Already delivered a lot of work over 9 weekends ➢ Successfully delivered complicated and integrated packages of work including major junction and track renewals at Gatwick and Earlswood, drainage works, embankment strengthening etc. ➢ No over-runs ➢ Experience of managing large numbers of passengers and running complex bus replacement operations. Blockade is a much greater level of complexity ➢ Increased volume of work to be delivered in phases ➢ Peak passenger volumes, weekday closures BUT… ➢ Safer and more efficient with just one overall handback risk. 24 Jan 19 / 5 GATCOM: Gatwick and the Brighton Main Line Blockade – Scope of Works Worksite B – BAM Nuttall (IPSE) Worksite A – S&C Alliance Primary Works Primary Works - Haywards Heath Drainage Works - Balcombe Tunnel Jn (S&C Alliance) (IPSE) Secondary Works Secondary Works - Balcombe Tunnel Drainage - Station improvements (WDSE) (WDSE) - Various Maintenance (Brighton DU) - Balcombe Station improvements Worksite C – Kier Signalling (IPSE) & footbridge renewal (IPSE) Primary Works - Signal Head & Track Circuit Worksite E – WDSE/Maintenance Renewals, Westplex signalling Planned Works system upgrade (IPSE) - Signal Head Conversions (WDSE) Secondary Works - Plumpton Station improvements - Wivelsfield Platform Refurb (IPSE) and footbridge refurbishment - Folly Hill Conductor Rail Renewal (IPSE) (IP Track) - Cooksbridge Station - Burgess Hill Conductor Rail improvements and footbridge Renewal (IP Track) refurbishment (IPSE) - Patcham Tunnel Down Track - Various Maintenance (Brighton Renewal (IP Track (Worksite D) DU) - Tunnel inspections and Repairs (WDSE) - Re-Railing (Brighton DU) 24 Jan 19 / 6 GATCOM: Gatwick and the Brighton Main Line Passenger communications 24 Jan 19 / 7 GATCOM: Gatwick and the Brighton Main Line Media & digital communications 24 Jan 19 / 8 GATCOM: Gatwick and the Brighton Main Line Stakeholder & Community Engagement ➢ Full stakeholder database and business toolkit ➢ Joint weekly newsletters to line of route MPs, CRMs to businesses ➢ Regular engagement with 400 local stakeholders, av. engagement rate 69%, over 150 in-depth conversations to date ➢ Postcards to 13,750 businesses ➢ Numerous articles in business publications ➢ Monthly updates to 7,500 directly impacted lineside neighbours ➢ Posters in community locations ➢ Art competition launched for 58 local schools Henry Smith MP at Three Bridges Stephen Lloyd MP at Eastbourne 24 Jan 19 / 9 GATCOM: Gatwick and the Brighton Main Line Summary Good progress in all key areas supported by an ongoing assurance process ➢ Positive stakeholder support ➢ Outstanding passenger awareness ➢ High confidence in our engineering works based on the planning and record in delivering enabling works ➢ Operational activities progressing and under control ➢ Passenger management preparations and associated enabling works on programme 24 Jan 19 / 10 GATCOM: Gatwick and the Brighton Main Line Gatwick Station Project 24 Jan 19 / 11 GATCOM: Gatwick and the Brighton Main Line Challenges 24 Jan 19 / 12 GATCOM: Gatwick and the Brighton Main Line Scheme Summary ➢ Will tackle problems of pedestrian crowding and poor access/egress ➢ Provides station capacity to tackle existing problems and future growth scenarios ➢ Supports a more reliable and efficient service by reducing platform dwell times resulting from access/egress issues ➢ A completely new concourse above the existing platforms 5, 6, and 7 ➢ Five new lifts and eight new escalators and four new stairways ➢ Improved connections to the existing interchange and overbridges ➢ Almost doubling existing rail concourse, providing more space 24 Jan 19 / 13 GATCOM: Gatwick and the Brighton Main Line Indicative Timeline Milestone Date Detail Design commences Spring 2019 Early works (to be agreed) Spring 2019 Start of main track works May 2020 (Phase 1: closure of platform 7) First Christmas Possession Christmas 2020 Continue track works January 2021 (Phase 2: closure of platform 5/6) Scheme open to the public December 2022 24 Jan 19 / 14 GATCOM: Gatwick and the Brighton Main Line Scheme Proposal 24 Jan 19 / 15 GATCOM: Gatwick and the Brighton Main Line Brighton Main Line Strategy and proposals for ‘unblocking the Croydon Bottleneck’ 24 Jan 19 / 16 GATCOM: Gatwick and the Brighton Main Line Brighton Main Line – the Croydon bottleneck Performance on the BML is impacted by low capacity junctions in the Selhurst triangle and insufficient platforms at East Croydon This is one of the most severe constraints on the busiest part of the UK network; a train every 45 seconds Our proposals for new flyovers and dive-unders and a station upgrade would fix the bottleneck Consultation with local people has started Our design activity is ongoing 24 Jan 19 / 17 GATCOM: Gatwick and the Brighton Main Line Croydon bottleneck – consultation summary ➢ Local focus: the first phase of consultation (November 2018) focussed on the immediate Croydon local area (line of route communications is ongoing) ➢ Well attended: 400+ attendees / 1000+ online responses ➢ High levels of support: the principle of “unblocking the Croydon bottleneck” by grade separation and providing extra platforms at East Croydon station appears to be widely accepted – over 90% support ➢ First step towards future land acquisition: affected landowners were advised with issues being worked through with NR specialists ➢ Do it faster: The most common response was “just get on with it” ➢ Local issues: a major concern was how we would reconstruct Lower Addiscombe Road bridge (1/2 mile north of East Croydon) – this will inform our next stages of activity 24 Jan 19 / 18 GATCOM: Gatwick and the Brighton Main Line Croydon bottleneck – outputs ➢ Performance: a step-change improvement by greatly reducing secondary delay due to the ‘flat’ junctions in Selhurst ➢ Capacity: Croydon upgrade (plus minor other supporting schemes) could allow +6 main line trains per peak hour, consistent with forecast growth. This could be higher if Clapham Junction and Victoria are also addressed in the longer term. ➢ Station improvements: far better passenger experience at East Croydon and Norwood Junction, part of a phased programme of major station improvements on the BML ➢ Local regeneration: support ongoing regeneration of central Croydon. 24 Jan 19 / 19 GATCOM: Gatwick and the Brighton Main Line Croydon bottleneck – timeline ➢ Further consultation: second, third and final phases of consultation in 2019 ➢ Design: concept development to 2020 ➢ TWA process: potentially 2021-2022, subject to funding ➢ Scheme commitment: opportunity to align with GTR refranchising ➢ Enabling works: aim to get critical path enabling works on site by 2023 ➢ Benefits: phased from late 2020s (multiple stages of grade separation) ➢ Completion: indicatively 2030 24 Jan 19 / 20 GATCOM: Gatwick and the Brighton Main Line Thank You 24 Jan 19 / 21.

View Full Text

Details

  • File Type
    pdf
  • Upload Time
    -
  • Content Languages
    English
  • Upload User
    Anonymous/Not logged-in
  • File Pages
    21 Page
  • File Size
    -

Download

Channel Download Status
Express Download Enable

Copyright

We respect the copyrights and intellectual property rights of all users. All uploaded documents are either original works of the uploader or authorized works of the rightful owners.

  • Not to be reproduced or distributed without explicit permission.
  • Not used for commercial purposes outside of approved use cases.
  • Not used to infringe on the rights of the original creators.
  • If you believe any content infringes your copyright, please contact us immediately.

Support

For help with questions, suggestions, or problems, please contact us