Distribution System Planning Tutorial

Distribution System Planning Tutorial

DISTRIBUTION SYSTEM PLANNING TUTORIAL MN Power Systems Conference November 6, 2014 CONNEXUS ENERGY • 128,000 customers Hwy 65 • 1,000 sq. miles territory • 44 substations • 8,800 miles distribution Hwy 10 • 12.47 kV • Wholesale supplier – Great River Energy 2 OUTLINE Planning – reacting “Reactive Planning” • Externalities – stuff comes up not planned for • Reactive Planning Backfeeding – Contingency Planning • Emergency vs Alternate Normal • Capacity Planning Case Example – Johnsville Transformer Failure • Capacity Planning • Reactive Planning • Contingency Event 3 “REACTIVE PLANNING” Events or Plans by Others – direct effect to Distribution Plant Construct Review • Road construction (road moves) • Infrastructure failure (cable) “Adjust” plan Select Forecast New “Opportunities” • New developments (why didn’t we hear about his last year?) Identify Solutions • Large Load Development – ex: Data center Other “Externalities” • Economic changes (crash of 2008) • Conservation (by plan, or trying reducing due to higher energy costs) Need to plan; scan your environment ; be prepared to react; adjust (re-create) the “plan” Quote by a Senior Planning Engineer: “the forecast will never be correct” 4 PLANS BY OTHERS… ROAD CONSTRUCTION Distribution Lines Located in Public Road Right-of-way • Permitting required for construction • No “easement” cost • Risk – utility bears cost if needed due to road construction Can We Plan for Road Work? • Plan “road moves” capital budget • Challenge: Entities have plan, not always executed to plan • Often details not defined until after utility budgeting season • Road projects often crop up during the year 5 ROAD MOVE “PLANNING” Design (or redesign) time Budget Plan Permitting Complete Construction time System Analysis & Variance to “planned” budget Engineering Planning Complete Planning Year Construction Year Contact Rd Agencies for Plans24 Rd Construction Complete Receive Final Schedule / Details Rd Construction Start from Rd Agencies 6 ROAD MOVE PLANNING – ANNUAL CAPITAL SPENDING 1.40 Mean Median Std Deviation 1.20 1.00 1.01 0.22 1.00 0.80 0.60 0.40 0.20 0.00 2006 2007 2008 2009 2010 2011 2012 2013 7 CABLE PLANT – FAILURE TRENDING 6000 •988 miles of cable installed before 1981. 5000 • higher than normal failure rates. 4000 OH 3000 Cable 2000 Miles Miles of Wire Cable installed in 1981-1988 begins to 1000 reach its 30-year life in 2010. 0 1969 1972 1975 1978 1981 1984 1987 1990 1993 1996 1999 2002 2005 8 MAINLINE CABLE FAILURE – ANNUAL CAPITAL SPENDING Mean Median Std Deviation 1.80 1.60 1.00 1.13 0.49 1.40 1.20 1.00 0.80 0.60 0.40 0.20 0.00 2006 2007 2008 2009 2010 2011 2012 2013 9 SYSTEM EXPANSION & IMPROVEMENTS – ANNUAL CAPITAL SPENDING Capacity, Voltage, Protection Mean Median Std Deviation 1.60 1.00 0.98 0.30 1.40 1.20 1.00 0.80 0.60 0.40 0.20 0.00 2006 2007 2008 2009 2010 2011 2012 2013 10 ANNUAL SYSTEM DEMAND – PICTURE FROM 2007 Growth Customers kWhs Sum of Subs Pk kW Actual through 2007 2.000 Projected 2008 1.500 Period Ave Growth 1996-2001 7.1% 2001-2006 4.2% 1.000 1996-2006 5.5% 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 11 TREND FOR HISTORY VS ACTUAL DEMAND Total System Demand - MW 900 Annual Growth 800 5.00% 700 600 Average Annual Growth 500 0.43% 400 300 200 100 0 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 12 COMPARISON – LINE CONSTRUCTION ACTIVITIES 1.80 System Expansion 1.60 Road Moves 1.40 Cable Replacement 1.20 1.00 0.80 0.60 0.40 0.20 0.00 2006 2007 2008 2009 2010 2011 2012 2013 13 TOTALIZED – LINE CONSTRUCTION ACTIVITIES Cable Replacement Std Deviation 1.29 Road Moves 0.18 Per unit of 1.17 System Expansion 14% average 1.05 18% 0.95 0.95 0.94 0.98 3% 23% 17% 12% 17% 46% 0.66 43% 7% 43% 60% 53% 41% 44% 70% 39% 40% 42% 34% 49% 37% 35% 34 13% 34 2006 2007 2008 2009 2010 2011 2012 2013 14 KEYS TO REACTIVE PLANNING How to react to global shift? • Continue towards long range plan • Shift time frame of execution How to minimize capital costs but be ready to serve? Construct Review • Defer major investment until absolutely needed; • Reduce lead time to complete Select Forecast Identify Solutions 15 ALMOST NEED A SUBSTATION???? Example Problem: Load is close to needing substation expansion, but not quite… “Plan - Defer - React” Substation Elements: 1. Risk high dollar Or… 2. Risk deferring the Plan: Do Up Front (Preparation) expenditure and the substation, load comes and • Engineering load doesn’t come? cannot build fast enough to • Land Acquisition meet demand? • Site Preparation Defer – React: Do when absolutely needed • Structures • Bus work / switchgear • Transformer Economic Risk Reliability / customer service risk 16 CONTINGENCY PLANNING (AND REACTING…) 17 CONTINGENCY PLANNING Build plant to handle loss / failure / needed alternate source of power Issues to address: • Investment made Reliability; Revenue Duration of backfeed • Emergency only? To what level of capacity to you build additional plant • Extended? (“alternate normal”) for contingency operations? • 100% of peak load Design contingency operation; • Less than 100% • ANSI A (110 volts at meter) Need plan for a 100% peak event • ANSI B (114 volts at meter) Need operational plan to execute Use emergency equipment ratings, or Use N-1? What do you do if event becomes N-2? normal load ratings? 18 LOAD DURATION CURVE – PEAK LOAD 106 % Peak without AC 100% Controllable AC potential - 100% 93 % penetration 93% peak ->20 hrs/yr (0.22%) 90% 82 % Total residential central AC demand 80% Peaking Load - 330 hrs 70% 60% 50% 40% 30% 20% 10% 0% 19 RELIABILITY RISK BASED ON % OF BACKFEED CAPABILITY Backfeed Exposure Cost Impact Capacity 10 yr NPV (% of peak load) Days / Year Hours / Day Per unit No backfeed design 81 - 140 14 - 16 1.0 70 25 - 30 12 - 14 1.15 80 10 - 14 10 - 12 1.34 90 3 - 7 6 - 10 1.57 100 0 0 1.66 20 EQUIPMENT LOADING – “NORMAL” VS “EMERGENCY” Plant Equipment “Normal” “Emergency” Incremental capacity (%) Cable (750 MCM Al) 475 532 12% OH Wire (4/0 ACSR) 330 440 33% Substation Transformer 28 MVA 35 MVA 25% 21 STRATEGY ELEMENTS Planning & Design Strategy: • Design feeders into multiple sections – backfeed per section • Shift load to 2nd tier substation – leverage existing transformer capacity • High probability of extended backfeed? Consider “normal load ratings” for contingency plan • Quantify and understand the risk (voltage, capacity, degree of shortfall) • Have spare equipment (i.e., transformer) ready to roll Operational Strategy: • Plan for placing emergency transformer in service in 24 hours. • Have a plan for contingency system operation • Have a plan to execute the plan ! 22 JOHNSVILLE SUBSTATION – FEEDER TIES TO 1ST TIER SUBS HAM BUL JON BLN VTN APT SLP 23 SCADA TRACE – TRANSFORMER TEMPERATURE 24 TRANSFORMER DAMAGE 25 CONTINGENCY PLANNING Feeder BF Source Details (Range B requirement is 114 v.) Result JON01 HAM04 106.9 v. 6.1 MW un-served JON06 > 114 v. not applicable SLP02 109.6 v. 6.1 MW un-served "Section Switch" is TP disconnects 2170-S: 111.7 v.; 4/0 JON01 Sec 1 SLP02 ACSR 102% 4.7 MW un-served > 114 v.; ALSO > 114 v. if HAM04 BF JON02 with JON01 Sec 2; BUT 110.5 v. & 4/0 ACSR 114% if HAM04 BF JON02 JON01 Sec 2 HAM04 & 03 with JON01 Sec 2 1.8 MW OK JON02 HAM04 > 114 v. 2.8 MW OK JON03 > 114 v. not applicable JON03 JON02 > 114 v. not applicable JON02 -HAM04112.2 v. 2.2 MW un-served JON04 BLN05 110.1 v. 4.4 MW un-served HAM02 112.2 v.; 4/0 ACSR 109% 4.4 MW un-served JON04 Sec 1 BLN05 "Section Switch" is disconnects 475-S: 113.6 v. 1.3 MW un-served JON04 Sec 2 HAM02 > 114 v. 3.1 MW OK JON05 APT05 > 114 v. 4.6 MW OK JON06 > 114 v. not applicable JON06 JON01 > 114 v. not applicable JON05 > 114 v. not applicable SLP06 113.8 v. 5.0 MW un-served 26 LOADING SUMMARY Projected peak: 24.8 MVA Backfeed ability through distribution: 12.3 MW (~50%) • System as is • Plant normal load ratings Feeder sectionalizing enhancement 5 MW ___________________________________________________ Remaining shortfall: ~7.5 MW (~30%) 27 “ALTERNATE NORMAL” - PLAN • 14 MVA “Spare” transformer • Feeder section switches • Tap phase changes • LDC settings changes 28 N-2 RISK…. With 14 MVA spare transformer, backfeed to OTHER subs still short by 8 MW Feeder BF Source Details (Range B requirement is 114 v.) Result HAM04 JON01 111.2 v. 4.4 MW un-served SLP02 JON01 > 114 v. 4.8 MW OK HAM04 JON02 > 114 v. 4.4 MW OK BLN05 JON04 112.7 v., 4/0 ACSR 107% 6.7 MW un-served HAM02 JON04 111.0 v., 4/0 ACSR 105% 6.1 MW un-served APT05 JON05 > 114 v. 4.3 MW OK SLP06 JON06 > 114 v. 3.6 MW OK 29 CONTINUING CHANGE / EVOLUTION Business Drivers: Tools & Strategies: Grid efficiency IVVC – Integrated Volt/VAR Control Conservation CVR – Conservation Voltage Reduction Reliability FLISR – Fault Detection, Isolation, System Restoration Line Sensors AMI Communications System DMS – Demand Management System 30 31 .

View Full Text

Details

  • File Type
    pdf
  • Upload Time
    -
  • Content Languages
    English
  • Upload User
    Anonymous/Not logged-in
  • File Pages
    31 Page
  • File Size
    -

Download

Channel Download Status
Express Download Enable

Copyright

We respect the copyrights and intellectual property rights of all users. All uploaded documents are either original works of the uploader or authorized works of the rightful owners.

  • Not to be reproduced or distributed without explicit permission.
  • Not used for commercial purposes outside of approved use cases.
  • Not used to infringe on the rights of the original creators.
  • If you believe any content infringes your copyright, please contact us immediately.

Support

For help with questions, suggestions, or problems, please contact us