Enbridge Pipelines Inc

Enbridge Pipelines Inc

TABLE OF CONTENTS 1.0 Application Overview/Executive Summary 2.0 Project Description 2.1 Engineering Design Details 2.2 Engineering Design Philosophy and Onshore Pipeline Regulations 2.3 Quality Assurance Program 2.4 Alternatives 3.0 Environmental and Socio-Economic Assessment 3.1 Project Description 3.2 Environmental and Socio-Economic Setting 3.3 Regulatory Consultation 3.4 Effects Assessment 3.5 Cumulative Effects Assessment 3.6 Inspection, Monitoring and Follow Up 4.0 Economics 4.1 Supply 4.2 Transportation Matters 4.3 Markets 4.4 Financing 5.0 Public Interest/Consultation 5.1 Principles and Goals of the Public Consultation Program 5.2 Design of the Public Consultation Program 5.3 Implementing the Public Consultation Program 6.0 Appendices Appendix 1 Drawings Appendix 2 Public Notification Letter to Stakeholders Appendix 3 Enbridge Corporate Social Responsibility Policy Appendix 4 Environmental and Socio-Economic Assessment References Appendix 5 Filing Manual Checklists 1.0 APPLICATION OVERVIEW / EXECUTIVE SUMMARY Project Name: Access Pipeline Receipt Facilities at Enbridge’s Edmonton Terminal Project Cost: $5,700,000 In response to a request from Access Pipeline Inc. (“Access”), Enbridge Pipelines Inc. (“Enbridge”) is applying for approval to construct a custody transfer metering system and associated facilities at Enbridge’s existing Edmonton Terminal. Access is planning to construct a new NPS 24 pipeline in a pipe rack across the Enbridge Edmonton Terminal with deliveries of commodities to Enbridge and Kinder Morgan, Inc. These facilities are required by Access in order to receive Devon Energy and MEG Energy heavy synbit blend production into the Enbridge system at Enbridge’s Edmonton Terminal. Project components consist of a meter manifold and prover skid, Quality Assurance building, belowground sump tank, and associated electrical and instrumentation components. Access has indicated that the initial maximum instantaneous flow rates will be 18,600 m3/d (117,000 barrels per day), with ultimate design flow rates of up to 127,186 m3/d (800,000 barrels per day). Enbridge understands that Access has received AEUB approval for their pipeline and pipe rack (AEUB Licence Number 46674). Construction activities will take place from March 2007 (pending receipt of regulatory approval) until December 2007. The new metering facilities are expected to be in-service by December 31, 2007. 2 2.0 PROJECT DESCRIPTION 2.1 ENGINEERING DESIGN DETAILS The transfer facility at the Enbridge Edmonton Terminal will include the installation of the following new components: • a NPS 24, SCH 80, Gr 241, Cat 1, supply connection from Access to the new metering manifold; • automatic sampling and density measurement systems in a common building; • a custody transfer metering manifold with 3 – 12” PD meters, 24” input and output headers, and a NPS 16 connection to a common skid mounted NPS 30 bi-directional meter prover; • a NPS 24, SCH 80, Gr 241, Cat 1, discharge line from the metering manifold to Manifold 201; • a NPS 14, SCH 80, Gr 241, Cat 1, relief line from the metering manifold to Manifold 204; • a new electrical building complete with MCC for power and control for all pumps, valves, and instrumentation; • a custody transfer flow computer, PLC system, and SCADA connections to both Enbridge and Access facilities; • a 5000 USG sump tank and drainage system; and • components necessary for full cathodic protection of underground facilities. The proposed transfer facility will require the modification of the following existing components: • a new NPS 24 discharge connection to existing 34” TK 26 tank line; • a new NPS 24 discharge connection to existing 48” TK 27 tank line; • a new NPS 14, SCH 80, Gr 241, Cat 1, relief connection at Manifold 204; and • MCC and control system modifications. Enbridge will control the facilities from the Enbridge Pipeline Control Centre, located in the Enbridge Tower in Edmonton. Together this work will comprise “the Project”. 3 2.2 ENGINEERING DESIGN PHILOSOPHY AND ONSHORE PIPELINE REGULATIONS Enbridge has filed with the NEB its Operations and Maintenance Manuals and shall comply with all of the requirements of the Onshore Pipeline Regulations, 1999 (“OPR”), to the extent they are relevant to the Project. Further, Enbridge shall design and construct the Project in accordance with CSA Z662-03, and Enbridge’s Engineering Standards, as well as Enbridge's Environmental Guidelines for Construction (2003) (“EGC”). The relevant Enbridge manual references are listed below: Engineering Standards D02-101 Design Basis, Electrical Rev. Oct 22, 2002 D02-103 Design Basis, Station and Terminal Rev. Oct 30, 2003 D02-104 Hazardous Area Classification Rev. Sep 1, 1999 D02-105 Fire Protection, Extinguishment Rev. Jan 6, 2000 D02-106 Noise & Acoustic Dampening Rev. Sep 1, 1999 D03-104 Weld Inspection Rev. Sep 1, 1999 D03-105 Shop Inspection Rev. Sep 1, 1999 D04-101 Cathodic Protection Rev. Oct 30, 2003 D04-102 Painting, Coating & Lining Rev. Jul 14, 2000 D05-101 Berm, Containment Rev. Oct 30, 2003 D05-102 Site Preparation, Earthwork, Grading, Road & Pavement Rev. Sep 1, 1999 D05-103 Trenches, Underground Lines Rev. Sep 1, 1999 D05-202 Foundation, Station & Terminal Rev. Sep 1, 1999 D05-301 Buildings, Station & Terminal Rev. Sep 1, 1999 D05-302 Laboratory, Sample & Sample Storage Buildings Rev. Sep 1, 1999 D05-401 Platforms, Stairs & Ladders Rev. Apr 29, 2003 D06-102 Piping Design, Station and Terminal Rev. June 13, 2000 D06-103 Crossing Design, Mainline Rev. Nov 15, 1999 D06-104 Piping and Fittings, Steel Rev. Nov 15, 1999 D06-105 Valve, Steel Rev. June 15, 2000 D07-201 HVAC, Building, Station & Terminal Rev. Nov 15, 1999 D07-202 Heat Tracing Rev. Nov 15, 1999 D07-301 Sump System Design Rev. Nov 15, 1999 D09-101 Oil Measurement, Mechanical Rev. Nov 15, 1999 D09-102 Oil Measurement, Electrical Rev. Nov 15, 1999 D09-103 Sampler Rev. Nov 15, 1999 4 D10-101 Power System Design Rev. Oct 29, 2002 D10-103 Switchgear & Motor Control Center Rev. Oct 24, 2002 D10-104 Auxiliary Power Supplies Rev. Dec 1, 1999 D10-105 Power System Protective Relaying Rev. Nov 21, 2002 D10-106 Substation Grounding Rev. Dec 1, 1999 D10-107 Surge Protection & Insulation Coordination Rev. Dec 1, 1999 D10-201 Wiring Methods Rev. Dec 1, 1999 D10-202 Grounding Methods Rev. Dec 1, 1999 D11-201 Lighting, Indoor Rev. Dec 1, 1999 D11-202 Lighting, Outdoor Rev. Dec 1, 1999 D11-301 Valve Actuation and Control Rev. Dec 1, 1999 D12-101 Control, Pump Station Rev. Nov 08, 2002 D12-102 Control, Injection & Delivery Facility Rev. Dec 1, 1999 D12-104 Pressure Relief Rev. Oct 2, 2003 D12-201 Instrumentation, General Rev. Nov 26, 2002 D12-202 Gas Detection Rev. Dec 1, 1999 D12-203 Fire Detection Rev. Dec 1, 1999 D12-205 Programmable Logic Controllers Rev. Dec 1, 1999 D12-208 Pressure Control System Rev. Feb 21, 2006 Enbridge Environmental Guidelines for Construction December 2003 Enbridge Waste Management Plan October 2004 Operating and Maintenance Procedures April 2006 Book 7: Emergency Response All of the above-referenced documents have been previously filed with the NEB. 5 2.3 QUALITY ASSURANCE PROGRAM During installation, on-site inspection personnel will monitor all construction activities to ensure all design measures are properly implemented throughout the construction process, and are in accordance with Enbridge and Industry standards. Non Destructive Testing (“NDT”) techniques will be used to check the integrity of welded components. 2.4 ALTERNATIVES Access is proposing to construct a new pipeline in a pipe rack across the Enbridge Edmonton Terminal in order to receive Devon Energy and MEG Energy heavy synbit blend production into the Enbridge system at Enbridge’s Edmonton Terminal. Current metering facilities at the Edmonton Terminal will not be able to accommodate the volumes that will be transported on the new Access pipeline. A receipt meter manifold is required to accept the incremental volumes and to deliver to existing tankage at Enbridge’s Edmonton Terminal. Therefore, no other alternative was considered in the development of this project. 6 3.0 ENVIRONMENTAL AND SOCIO-ECONOMIC ASSESSMENT This Environmental and Socio-Economic Assessment (“ESA”) has been undertaken in accordance with the NEB’s Filing Manual under section 58 of the NEB Act. Pursuant to Guide A.2.1 of the Filing Manual , the level of detail contained within this assessment corresponds to the nature and magnitude of the anticipated environmental impacts. 3.1 PROJECT DESCRIPTION Enbridge’s Edmonton Terminal is located at SE 5-53-23 W4M within Sherwood Park east of Edmonton, Alberta (Figure 1). Due to the industrial setting of the area, it is not considered to be environmentally sensitive. The Kinder Morgan Edmonton Terminal is located immediately to the west and the Petro- Canada refinery is located immediately north of the site. Baseline Road and Shell Canada property are located directly to the south and Highway 216 and Provincial Public Works and Services lands are located directly east of the Terminal. Apart from NEB approval, no additional environmental permits, other than relevant notification, will be required to construct the Project at the Enbridge Edmonton Terminal. Notification under Alberta’s Water Act Code of Practice for withdrawal / release of hydrostatic test water will be required for the Project. 7 8 3.2 ENVIRONMENTAL AND SOCIO-ECONOMIC SETTING A summary of the biophysical and socio-economic elements pertaining to the Project is provided in Table 1. Information collected was obtained from existing literature and Internet searches. The study areas discussed in the assessment include: project footprint (area of disturbance) or a local study area (defined as approximately 400 m). The nearest residence is located approximately 1800 m southeast of the site. Table 1 Summary of Biophysical and Socio-Economic Elements and Considerations Biophysical and Socio- Economic Elements Summary of Considerations Physical Environment • The Project lies within the Lake Edmonton Plain Physiographic Division of the Eastern Alberta Plains Physiographic Region (Pettapiece 1986).

View Full Text

Details

  • File Type
    pdf
  • Upload Time
    -
  • Content Languages
    English
  • Upload User
    Anonymous/Not logged-in
  • File Pages
    46 Page
  • File Size
    -

Download

Channel Download Status
Express Download Enable

Copyright

We respect the copyrights and intellectual property rights of all users. All uploaded documents are either original works of the uploader or authorized works of the rightful owners.

  • Not to be reproduced or distributed without explicit permission.
  • Not used for commercial purposes outside of approved use cases.
  • Not used to infringe on the rights of the original creators.
  • If you believe any content infringes your copyright, please contact us immediately.

Support

For help with questions, suggestions, or problems, please contact us