Building Information Modeling

Building Information Modeling

Journée d’échanges 12 Février 2015 - Charleroi Building Information Modeling dr. ir. Thomas Vandenbergh “Build it digitally before physically” Producing more accurate information and making early decisions Pilot Project Keersluis, Heumen Assemble models Egemin (Autodesk Inventor) Keersluis, Heumen BED (Autodesk Revit) Boorsma (Tekla) 1 hour Clash detection Keersluis, Heumen Automatically (5 min) Manually (2 hours) BIM for tenders Quantity take off Grand Stade FFR Illustration of structural concept Our BIM benefits The Grand Egyptian Museum The Grand Egyptian Museum Location West border of Cairo near the pyramids of Giza 20th January 2012 9 KMO The Grand Egyptian Museum • galleries:92.600 m2 • conference center:40.700m2 • sec. spaces & buildings:34.000m2 • 195 000m² total building floor area • 471 000m² total land area • site works • excavations 190 000 m³ • concrete 149 000 m³ • reinforcement 33 400 Ton • formwork 620 000 m² • steel structure 6 350 Ton Period of work completion : 1200 calender days Start : Feb 2012 The Grand Egyptian Museum Client : The Egyptian Ministry of Culture – Supreme Council of Antiquities - Technical committee for Project Implementation of The Grand Egyptian Museum Project Bank : The Incorporated Administrative Agency – Japan International Cooperation Agency (JICA) Engineer : Hill International – EHAF JV Architect : Henegan Pen Architects (IR) Consultant structure : OVE Arup & Partners Consultant MEP : Buro Happold Contractor Grid System Peak of more than 4000 people 4000 than more of Peak Number 1000 2000 3000 4000 5000 6000 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 Months 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 Manpower 36 37 38 39 40 Tender for GEM one BIM model 5000 drawings Understanding a complex structure Understanding a complex structure Animated construction schedules Schedule (Primavera) Animated schedule (Navisworks) in 2 days BIM model (Revit) Quantities Concrete curve Traditional method (2 days) BIM (30min) and more accurate Project award Contractual obligations • BIM management • Initial modeling based on design drawings • On site trade coordination • On site information extraction (BOQ and monthly progress status) • On site shop drawing production • As-built model for facility management BIM Method Statement • Project description • Core collaboration team and roles • Contractual requirements • BIM phases and milestones • Model division, LOD, coding system, naming convention… • Authoring tools BIM Phases BIM zone = civil zone Model division Organization chart BIM and TO Main Building - Roof Main Building Main Building Conference Centre Coordination Total Clashes Resolved on Jan 8 th 2013 = 8706 • Steel-Concrete: 200 • Architectural: 2907 • Architectural-Civil: 437 • MEP-MEP: 4686 • MEP-Civil: 476 Total Clashes detected on March 2 nd 2013 = 29631 • Arc – Civil: 5050 • MEP-MEP: 24581 Coordination 3D illustration of RFI’s Conference Center – Ground Floor Museum Zone – Ground Floor Museum - First Floor Model Coordination • Clash Detection & Resolution Model Coordination • Clash Detection & Resolution Shop drawing production BIM based almost 2x faster than CAD based Further benefits Model based quantity extraction – 76% of BOQ items • 2 to 3 times faster • Structure: 101/453 • Architecture: 1305/1687 • MEP: 2986/3631 • forecast of quantities for value engineering • quantities for erection methods • quantities for procurement • quantities for monthly statements • visual support for internal/external meetings (e.g. location of security camera’s) Challenges and difficulties Difficulties • client requires BIM but PMC is unable to judge on performed work Confidential • hard to recruit BIM staff • even harder to recruit BIM staff with technical expertise • few subcontractors can deliver a model Difficulties • collaboration with rest of ‘traditional CAD’ technical office BIM helps for highlighting clashes but does not solve them! Coordination should be reviewed in models and not on drawings Share information • software limits: file size, number of shop drawings, complex geometries… • open standards are not (yet) perfectly reliable • BIM is easy to blame! Future challenges • Link with structural analysis geometrical model vs. analytical model • Bill of quantities • Planning resources and cost (5D) • BIM on site & Tablets (code bars…) • BIM for Facility Management (equipment, room by room…) Implementation difficulties • How to share/receive models? Legal liability… • Change in practice: construction knowledge earlier in the project • Earlier involvement of subcontractors e.g. MEP First 3 to 6 months often in 2D since MEP, façade… come later in the contract • Different contract type: Integrated Project Delivery? BIG room, metrics, contracts… Questions? dr. ir. Thomas Vandenbergh Regiocentrale Zuid Maasbracht (NL) – Jul‘10 BESIX Engineering Department Ecluse Lanaye (BE) – Brussels, Belgium May‘11 [email protected] Blue Radisson Hotel +32497274370 Andermatt (SW) – Sep‘11 Keersluis Heumen (NL) – Oct‘10 Radartoren Oostende(BE) – Jul‘12 Sofaz Tower (AZ) – Sep‘11 Carpe Diem Tower (FR) – Aug‘10 Louvre Abu Dhabi (UAE) – Oct‘12 Parkeergarage Extension Stade RSCA Parking Vonk en Vlam Rotterdam (NL) – May‘11 (BE) – Jun‘11 (NL) – Jun‘12.

View Full Text

Details

  • File Type
    pdf
  • Upload Time
    -
  • Content Languages
    English
  • Upload User
    Anonymous/Not logged-in
  • File Pages
    43 Page
  • File Size
    -

Download

Channel Download Status
Express Download Enable

Copyright

We respect the copyrights and intellectual property rights of all users. All uploaded documents are either original works of the uploader or authorized works of the rightful owners.

  • Not to be reproduced or distributed without explicit permission.
  • Not used for commercial purposes outside of approved use cases.
  • Not used to infringe on the rights of the original creators.
  • If you believe any content infringes your copyright, please contact us immediately.

Support

For help with questions, suggestions, or problems, please contact us