National Rivers Authority Thames Region Water Resources Development Options Final Report Volume 2 Technical Appendices April

National Rivers Authority Thames Region Water Resources Development Options Final Report Volume 2 Technical Appendices April

NATIONAL RIVERS AUTHORITY THAMES REGION WATER RESOURCES DEVELOPMENT OPTIONS FINAL REPORT VOLUME 2 TECHNICAL APPENDICES APRIL 1992 Record of Issue Issue Details Originator Date Approved Date «» \ A l o»i 2.<a /wt^i ‘ 1 S I * 1- Howard Humphreys & Partners Ltd Cobham Resource Consultants Thorncroft Manor Avalon House Dorking Road Marcham Road Leatherhead Abingdon Surrey Oxford KT22 8JB 0X14 1UG ENVIRONMENT AGENCY 089492 APPENDIX 2 ENGINEERING AND HYDROLOGY DATA ENGINEERING ENGINEERING Engineering Criteria The following design criteria have been used in drawing up the development options. Storage Impounding Dams and bunds have been taken as earth fill Dams and embankments with crest width of 8m, u/s slopes Bunded Reservoirs of 1 on 3.5 and d/s slopes of 1 on 3, freeboard has been taken as 2m. Bankside Storage The volume of bankside storage for Severn Thames transfer has been taken as 3 days storage at the maximum transfer rate. Gravel Pits It has been assumed that gravel pits will be on average 6m deep, the cut off slurry trench will be 600mm wide and will extend lm into the clay beneath the gravel. Adjacent pits will utilise a common cut-off and that access roads will be constructed round the perimeter of all pits. T ransmissiun Pipelines In sizing pipelines a limiting velocity of between 1.5 and 2.0 m/s has been adopted. The friction coefficient ’C’ in the Hazen Williams formula for calculating head loss has been taken as 135. Pipelines have been assumed to be in ductile iron. Pumping Pumps Maximum pumping head has been limited to 150m. For heads greater than this multiple inline pumping stations have been adopted. Engineering Elements The sizes of engineering elements adopted for the development scenarios are: Scenario 1A Stage Item Size Drayton Reservoir lOOMm3 Tunnel 2.5m dia x 4000m Pumps 600 Ml/d 3125 Kw installed Staines Storage lOMm3 increase Embankments Northern reservoir by 3 m Raised Southern reservoir by 6m Pumps Addition capacity of approximately 450 kW assumed Effluent Sand Filters 90 Ml/d capacity Reuse Effluent pumps 90 Ml/d 80 Kw installed (Mogden) Ozoniser 90 Ml/d Tunnel 2000m dia x 6500m Transfer Pumps 90 Ml/d 80 Kw installed (Deephams) Sand Filters 50 Ml/d capacity Effluent Pumps 50 Ml/d 45 Kw installed Ozoniser W V M Transmission Main 70mm L < 1000m Transfer Pumps 50 Mid 130 Kw installed Scenario 2 Stage Item Size Drayton As Scenario 1A Severn-Thames Deerhurst Intake 400 Ml/d Transfer Low Lift Pumps 400 Ml/d 1040 Kw installed Bankside Storage 1.2 Mm3 (Severn) High Lift Pumps 400 Ml/d 9700 kW installed (2 stations) Transmission 2000mm dia 76,000m Scenario 2A Stage Item Size Drayton As Senario 1A Sevem-Thames Deerhurst Intake 400 Ml/d Transfer Low Lift Pumps 400 Ml/d 1040 Kw installed Bankside Storage 1.2 Mm3 (Severn) Highlift Pumps 400 Ml/d 9700 Kw installed (2 stations) Transmission 2000mm dia L = 53,000m Bankside Storage 1.2 Mm3 (Thames) Pumps to Drayton 400 Ml/d 2100 Kw installed Scenario 2B Stage Item Size Sevem-Thames Deerhurst Intake 400 Ml/d Transfer Low Lift Pumps 400 Ml/d 1040 Kw installed Bankside Storage 1.2 Mm3 (Severn) tj t a a a \ r t / A c\nr\r\ 1^17 m: g r*u i i l u i i i p a TVU iril/U P r \ J \ J IWTT U i J l O i L W U (2 stations) Transmission 2000mm dia L = 53,000mm Bankside Storage 1.2 Mm3 (Thames) Pumps Thames - 400 Ml/d 2100 Kw installed Drayton Drayton As Scenario 1A Scenario 3 Stage Item Size Sevem-Thames Deerhurst Intake 400 Ml/d Transfer Low Lift Pumps 400 Ml/d 1040 Kw installed Bankside Storage 1.2 Mm3 (Severn) High Lift Pumps 400 Ml/d 9700 kW installed (2 stations) Transmission 2000mm dia L = 53,000m Bankside Storage (Thames) 1.2 Mm3 Anglia- Thame, Stort Trent-Thame Trent Intake 700 Ml/d Trent-Witham Transmission 2400mm dia L = 10,000m Witham-Wansford Transmission 2400m dia L = 70,000m With am Pumps 700 Ml/d 13400 Kw installed Wansford - Gt Ouse Transmission 2200mm dia L = 40,000m Wansford Pumps 600 Ml/d 9400 Kw installed Gt Ouse - Waddesdon Res 2000mm dia L = 73,000m Gt Ouse PumDs 100 Ml/d 1750 Kw installed (2 stations) Waddesdon Dam 17m high 35Mrft3 storage Denver-Stort Kenneti Pumps 200 Ml/d 3700 Kw installed Kennett-Kirtling Green Transmission 1400mm dia L = 14,000m Stour Improvement 11,000m Wixoe Pumps 200 Ml/d 2400 Kw installed Wixoe-Gt Sampford (Pant) 1400mm dia L = 10,000m Pant (Gt Bardfield) - Stort 1400mm dia L = 28,000m Gt Bardfield Pumps 200 Ml/d 2300 Kw installed Scenario 3A Stage Item Size Severn-Trent As Scenario 3 Transfer Anglia - Thame, Stort, Grafham As Scenario 3 Denver-Stort Kennett Pumps 200 Ml/d 3700 Kw installed Kennett-Kirtling Green 1400mm dia L = 14,000m Stour Improvement 11,000m Wixoe Pumps 200 Ml/d 2400 Kw installed Wixoe-Gt Sampford (Pant) 1400mm dia L = 10,000m Pant (Gt Bardfield) - Stort 1000mm dia L = 28,000m Gt Bardfield Pumps 100 Ml/d 1350 Kw installed Grafham-Luton Grafham-Luton 1000m dia L = 45,000m Grafham Pumps 100 Ml/d 2000 Kw installed Stage Item Size Severn-Trent As Scenario 3 Transfer Anglia - Thame, Stort, Roding As Scenario 3 Denver-Stort/ Kennett Pumps 200 Ml/d 3700 Kw installed Roding Kennett-Kirtling Green 1400mm dia L = 14,000m Stour Improvement 11,000m Wixoe Pumps 200 Ml/d 2400 Kw installed Wixoe-Gt Sampford (Pant) 1400mm dia L = 10,000m Gt Bardfield - High Roding 1400mm dia L = 15,000m Gt Bardfield Pumps 200 Ml/d 2300 Kw installed High Roding - Sawbridgeworth 1000mm dia L = 13,000m High Roding - Longfordbridge 1000mm dia L = 17,000m (Roding) RESERVOIR LAYOUTS DOWN AMPNEY TENTATIVE GRAVEL PIT LAYOUT RESERVOIR STORAGE LEVELS QUANTITY STORED IN WADDESDON RESERVOIR QUANTITY STORED (Ml) 1923 1929 1935 1941 1947 1953 1959 1965 1971 1977 1983 1989 YEAR SCEN3.3 2020 DEMANDS QUANTITY STORED IN DOWN AMPNEY RESERVOIR QUANTITY STORED (Ml) 1923 1929 1935 1941 1947 1953 1959 1965 1971 1977 1983 1989 YEAR SCEEN 3.3 2020 DEMANDS STORAGE IN DRAYTON RESERVOIR MEAN DAILY STORAGE (Ml) 1923 1929 1935 1941 1947 1953 1959 1965 1971 1977 1983 YEAR SCEN 1.2 2011 SCEN2.3 2021 DEMANDS DEMANDS I RIVER FLOWS RIVER FLOW AT DAYS'WEIR SCENARIO 1.2 (Thousands) MEAN MEAN MONTHLY FLOW (M l/D ) MONTH □ NATUR + NATUR 'O NATUR RIVER FLOW AT DAYS'WEIR SCENARIO 2.3 (Thousands) MEAN MEAN MONTHLY FLOW (M l/D ) MONTH □ NATUR + KlATUR '0 NATUR RIVER FLOW AT DAYS WEIR SEVERN TRANSFER AT 400 Ml/D (Thousands) MEAN MEAN MONTHLY FLOW (M l/D ) MONTH □ .'NATUR + NATUR ' © NATUR RIVER LEE FLOW AT FIELDS WEIR SCENARIO 3.3 MONTH □ NATUR + NATUR 'O NATUR RIVER THAME FLOW AT CHEVINGTON SCENARIO 3.3 (Thousonds) MEAN MEAN MONTHLY FLOW (M l/D ) MONTH D NATUR + NATUR *0 NATUR MONTHLY MEAN, MAX AND MIN FLOWS RIVER THAMES AT BUSCOT (0900) 1979 - 1991 MONTH MONTHLY MEAN, MAX AND MIN FLOWS RIVER THAME AT SHABBINGTON (1 9 7 0 ) 1967 - 1991 (Thousands) FLOW FLOW (M L /D ) MONTH APPENDIX 3 ENGINEERING COSTS ENGINEERING COSTS Engineering costs have been based on data derived from the following sources: - Water Research Centre - Technical Report TR61 Water Research Centre - External Report 72E Central Water Planning Unit - Severn to Thames water Transfers Thames Water - Water Resources Strategy Wessex Database Civil Engineering Howard Humphreys - Internal cost data Costs have been presented at late 1991 rates and in order to arrive at these rates escalation has been based on the published public works and construction materials indices. The following tables give the cost parameters used for capital and annual operating expenditure. The costs given in the tables of capital costs do not include engineering costs or contingencies. Because of the very outline nature of the designs included in the options a contingency allowance of 25 % has been made in the costing of options. Engineering costs have generally been taken as 4% of its capital cost for design and head office supervision of construction and 4 % of capital cost for site supervision of construction. Occasionally these rates have been varied depending on job size and type. These costs have been spread over estimated design and construction periods. CAPITAL COSTS Item Works Cost/Unit Cost Remarks Storage Impounding Dams (earth fill) 17.4 * F ill08 Cost in £ million Fill : Volume of embankment in Mm3 Bunded Reservoirs 5.15 x V o l048 Cost in £ million Vol : Storage in Mm3 Bankside storage on £0.027M per Ml/d transfer From CWPU 1977 costing for 3 days Severn/Thames transfer storage at 225 Ml/d transfer Gravel Pit £30 per m2 of Cut-off trench Assumes 600mm wide slurry trench to maximum depth of 10m along perimeter of gravel pit. Winning of gravel assumed to cover cost of excavating any minor bunding and landscaping Transmission Pipelines 12.45 x 104 x D ' 848 Cost in £ per metre D: diameter in mm Based on ductile iron pipes Tunnels 2.0m dia £200/m £2000/h 2.5m dia £300/m £3000/m i i i CAPITAL COSTS Item Works Gost/Unit Cost Remarks Pumping Pumping Plant 11.3 x Kw06 Cost in £ thousands Kw = Installed water power including standby plant Based on HH recent tenders and Halcrow example in national strategic options Pump House 16 x 79 Cost in £ thousands Q = Throughput in Ml/d Based on TR61 with constant revised and adjusted for HH and Halcrow examples Tertiary Treatment of Filters 0.628 Q 0653 Cost in £ million Effluent Q = Throughput in Ml/d Formula derived from TR61 escalated and upper confidence limit applied O^oniser £14000 per Ml/d throughput Based on manufacturer’s budget quotation Miscellaneous Drayton Reservoir £225m From estimate provided by NRA - TR Land £4900 per hectare Agricultural Land 1 OPTION C - DRAYTON RESERVOIR SUMMARY £ millions DIRECT AND ENGINEERING COSTS Total Storage 103 Mm3 on two sites (Main and Regulating Reservoir)

View Full Text

Details

  • File Type
    pdf
  • Upload Time
    -
  • Content Languages
    English
  • Upload User
    Anonymous/Not logged-in
  • File Pages
    198 Page
  • File Size
    -

Download

Channel Download Status
Express Download Enable

Copyright

We respect the copyrights and intellectual property rights of all users. All uploaded documents are either original works of the uploader or authorized works of the rightful owners.

  • Not to be reproduced or distributed without explicit permission.
  • Not used for commercial purposes outside of approved use cases.
  • Not used to infringe on the rights of the original creators.
  • If you believe any content infringes your copyright, please contact us immediately.

Support

For help with questions, suggestions, or problems, please contact us