Moose Cree First Nation Emergency Preparedness and Response Centre

Moose Cree First Nation Emergency Preparedness and Response Centre

Lightweight Steel Framing Case Studies CS 00-37 Moose Cree First Nation Emergency Preparedness and Response Centre MOOSE CREE FIRST NATION EMERGENCY PREPAREDNESS & RESPONSE CENTRE JAMES BAY, ONTARIO (Reprinted with permission from ArcelorMittal Dofasco Steel Design, 2009) It was a race against time to build the facility ity in the remote north,” emphasizes Lehari, to a closed-in state in one construction season noting that shipping to Moose Factory is via – including the pouring of a 2,323m2 (25,000 train from Cochrane and then either by barge DESIGN AND CONSTRUCTION sq. ft.) engineered concrete slab. As well, in the summer or ice road in the winter.“ So TEAM fabrication and erection needed to be lightweight steel in knock-down form proved OWNER: as simple as possible given the lack of a to be the most economical system to ship,” Moose Cree First Nation local highly-skilled labour force. remarked Lehari. ARCHITECT: Two Row Architect FNA Building Systems Inc. was chosen to The lightweight nature of the LSF system supply the complete light steel framing (LSF) also proved to be an economical advantage in CONSTRUCTION MANAGER: building system and provide construction erection of the foundations. The site consisted FNA Building Systems Inc. management services for the project. The ll material and a building structural system for the 2,583 m2 high water table. In winter, frost can reach LIGHT STEEL FRAMING SUPPLIER: (27,800 sq. ft.) EPR Centre used light steel ground depths of eight feet so conventional Bailey Metal Products framing for the load-bearing walls, wind bear- strip foots and foundation walls were cost- STEEL DECK/STEEL ROOF oor trusses prohibitive. “FNA’s engineers designed a six CLADDING SUPPLIER: at the mezzanine, a steel deck with concrete oating slab to support the Agway Metals Inc. topping at the mezzanine and prepainted superstructure only possible because of ng. FNA worked in conjunction with the lightweight LSF system.” LOAD-BEARING AND WIND- the Moose Cree First Nation to establish a BEARING WALL government funded training program for local The LSF wall and roof assemblies, combined SYSTEMS: FNA Building Systems workers FNA President, Tom Lehari explains, with rigid and spray foam insulation, contrib- Inc. “The EPR Centre of Excellence Light Steel and cient levels of the FLOOR TRUSS AND ROOF TRUSS cient Construction Training Project building. The Walls are R32 and the roof is R52. SYSTEMS: was implemented to provide trainees with ec- FNA Building Systems Inc. high quality training and work experience in tively wrapped with insulation, providing for a cient construction tightly sealed building envelope and elimina- techniques, as well as in commercial building tion of expansion, contraction or building nishing work.“ movement. A temporary fabrication facility was estab- All in all, the use of light steel framing lished at Moose Factory and FNA shipped cant to successfully achieving a precut material and components, which were number of project requirements – from design then assembled over the course exibility for interior partitions and work, and of the winter months. Construction on site speed and simplicity of construction to energy started in the spring. Wall panels were ciency and sustainable development shipped to the site in July and assembly of the mandated by the Moose Cree First Nation. superstructure took place in July and August. The superior energy performance of the building will contribute to approximately “The light steel framing system proved to 53% lower annual energy costs than the be the logical choice in building this facil- 1 Model National Energy Code of Canada. Lightweight Steel Framing Case Studies CS 00-37 Precut material and components, were assembled over the course of the winter months in Moose Factory. Construction on site started in the spring. Wall panels were shipped to the site in July and assembly of the super- structure took place in July and August. The superior energy performance of the building (wall R value achieved was 32 and the roof R Value achieved was 52). Quantities of framing involved: Total exterior wall 256m (840 linear feet) Total exterior 152.4mm (6”) stud 3,456m (11,340 linear feet) Material – Grade 33 (MPA230) Total steel deck 4,366m2 (47,000 sq. ft.) Canadian Sheet Steel nished metal roof 4,180m2 (45,000 sq. ft.) Building Institute The construction season in remote 652 Bishop St. N., Unit 2A northern Ontario is relatively short – Cambridge, ON N3H 4V6 Roof truss system 1.36m (39’-0”) with spans beginning, on average, in June and Tel: (519) 650-1285 ending early October with the winter Fax (519) 650-8081 Standing seam steel roof .45mm (.0179”) prepainted galvanized, freeze. That presents an incred- www.cssbi.ca le 6-150F ible challenge to any major building project, but the use of steel was the le RD36 ideal solution for a superstructure in Moose Factory, Ontario in the James Bay region. 2 le CD36 composite deck..

View Full Text

Details

  • File Type
    pdf
  • Upload Time
    -
  • Content Languages
    English
  • Upload User
    Anonymous/Not logged-in
  • File Pages
    2 Page
  • File Size
    -

Download

Channel Download Status
Express Download Enable

Copyright

We respect the copyrights and intellectual property rights of all users. All uploaded documents are either original works of the uploader or authorized works of the rightful owners.

  • Not to be reproduced or distributed without explicit permission.
  • Not used for commercial purposes outside of approved use cases.
  • Not used to infringe on the rights of the original creators.
  • If you believe any content infringes your copyright, please contact us immediately.

Support

For help with questions, suggestions, or problems, please contact us