BART Oakland Airport Connector Fact Sheet

BART Oakland Airport Connector Fact Sheet

CAPITAL PROJECTS PROGRAM Project Fact Sheet PROJECT SPONSOR BART Oakland Airport Connector Bay Area Rapid Transit (BART) Project Number: 603.0 | Complete PROJECT DESCRIPTION The BART Oakland Airport Connector (OAC) project constructed a 3.2 mile Automated Guideway Transit (AGT) system to connect the BART Coliseum Station to the Oakland International Airport. The AGT alignment runs mainly in the Hegenberger Rd. median and along Airport Dr. to the terminus at the new airport terminal. PROJECT STATUS Work began on the project in November 2010. Construction of the Airport AGT and Coliseum Stations, Maintenance and Storage Facility and the elevated steel truss New BART OAC Alignment guideway are complete. Project Highlights The automated people mover system is designed to reduce the BART hosted a public celebration on November 21, 2014 and invited the community to explore the new stations, average travel and wait time, artwork and take a free ride increase passenger capacity and provide a more frequent, seamless BART began service on November 22, 2014. The driverless transit connection between the AGT system is an automated people mover system which Coliseum Station and Oakland provides a seamless transit connection between the International Airport. The new “train BART system and the Oakland International Airport to plane” service opened to the public on November 22, 2014, in For more information visit the BART OAC Opening time for the 2014 holiday season. Celebration webpage provided by the Metropolitan Transportation Commission Project Fact Sheet BART Oakland Airport Connector | Project Number: 603.0 | Complete PROJECT COST ESTIMATE PROJECT FUNDING Cost Estimate by Phase ($ X 1,000) Funding by Fund Source ($ X 1,000) Scoping $ 0 Measure B $ 89,052 PE/Environmental $ 3,800 Federal $ 25,000 Final Design (PS&E) $ 13,132 State $ 78,866 Right-Of-Way $ 12,297 Regional $ 146,199 Utility Relocation $ 3,140 Local $ 144,994 Design/Build $ 451,742 Other $ 0 Equipment Purchase $ 0 TOTAL Expenditures: $ 484,111 Total $ 484,111 PROJECT SCHEDULE Begin - End Project Phase 2010 2011 2012 2013 2014 2015 2016 MM/YY PE/Environmental 08/98 - 07/02 Final Design (PS&E) 07/02 - 05/09 Right-Of-Way 07/02 - 02/10 Construction (DBOM) 09/10 - 12/13 System Testing 06/13 - 11/14 First vehicle tow along the aerial guideway above Interstate 880. Photograph provided by BART, January 2014. The BART OAC Service opened to the public on November 22, 2014. Note: The information on this fact sheet is subject to periodic updates. Alameda CTC | 1111 Broadway, Suite 800 | Oakland, Ca. 94607 | (510) 208-7400 | www.alamedactc.org .

View Full Text

Details

  • File Type
    pdf
  • Upload Time
    -
  • Content Languages
    English
  • Upload User
    Anonymous/Not logged-in
  • File Pages
    2 Page
  • File Size
    -

Download

Channel Download Status
Express Download Enable

Copyright

We respect the copyrights and intellectual property rights of all users. All uploaded documents are either original works of the uploader or authorized works of the rightful owners.

  • Not to be reproduced or distributed without explicit permission.
  • Not used for commercial purposes outside of approved use cases.
  • Not used to infringe on the rights of the original creators.
  • If you believe any content infringes your copyright, please contact us immediately.

Support

For help with questions, suggestions, or problems, please contact us