TECHNICAL BRIEFING WORK ON THE RÉSEAU EXPRESS MÉTROPOLITAIN APRIL 25, 2018 2018-2019 SCHEDULE Project progress • Contract signed with the winning consortia on April 12, 2018 • Project office set up for the REM • NouvLR is at the intensive planning stage • Design-build • Preparatory work has been carried out in the field since March 2018 • Summer 2018: work will actively start on all branches 2018-2019 SCHEDULE Québec’s largest public transit project in the last 50 years • A linear project – a 67-km route almost as long as the Montréal metro • Many different trades – nearly 34,000 jobs during the construction • Coordination with 11 municipalities, 8 boroughs and 5 public transit organizations – project office with more than 1 000 experts 2018-2019 SCHEDULE A project involving several partners Project Realization • Infrastructure engineering, • Rolling stock, systems and operation procurement and construction and maintenance services Project Integration Coordination committees Coordination Work impact Mobilité Montréal – government committees – management committees departments, ARTM and committees municipalities and transit authorities partners More than 20 work planning and monitoring committees 2018-2019 SCHEDULE Overview of the work • Implementation of a new technology: automated electric light rail on fully dedicated lines (dedicated corridor) • Construction of Rive-Sud, airport and Sainte-Anne-de-Bellevue branches • Conversion of the route to accommodate a light rail on the Deux-Montagnes line • Crossings closed • Modernization of the Mont-Royal Tunnel • Construction of three connections to the metro (McGill, Édouard-Montpetit and Bonaventure) and an intermodal station (Correspondance A40) • Construction of 26 REM stations • Enclosed and weatherproof station buildings, and designed for universal access 2018-2019 SCHEDULE Ground-level station 2018-2019 SCHEDULE Elevated station 3 4 2 1 1. SOUTH SHORE CALENDRIER 2018-2019 Legend Work in progress in the indicated period Work continuing in the indicated period Work with significant impacts Preparatory work along the entire route • Geotechnical surveys • Location and relocation of public and municipal services Preparatory work on Marc- Cantin Street Construction of structure above CN/Malo/Leduc Preparatory work on Highway 10 median Reconfiguration of Highway 10 2018 2019 Construction of the elevated structure on Highway 10, the terminal station and De Rome Blvd. Jan. to May to Sept. to Jan. to May to Sept. April Aug. Dec. April Aug. to Dec. 2018-2019 SCHEDULE Summer 2018 Reconfiguration of Highway 10 Target area 2018-2019 SCHEDULE Summer 2018 Reconfiguration of Highway 10 Maintaining two lanes in each direction Future Du Quartier Station 2018-2019 SCHEDULE Summer 2018 CN/Malo/Leduc construction Target area DIX30 Leduc Blvd. REM WORK Summer 2018 Construction of a structure above the CN track (Malo/Leduc) Coordination with Ville de Brossard Construction of Lachine Canal bridge Relocation Set up an exit ramp of Marc-Cantin Street Construction of from Highway 10 to Taschereau Blvd. Construction of temporary Panama elevated Pointe- terminal Saint-Charles Construction of structure temporary access ramp at Lapinière Blvd. Construction of structure above CN/Malo/Leduc Preparatory work on Highway 10 median Construction of Du Quartier Station 2018 2019 Construction of the elevated structure on Highway 10, the terminal station and De Rome Blvd. Jan. to May to Sept. to Jan. to May to Sept. April Aug. Dec. April Aug. to Dec. Construction of De la Commune bridge Construction of Lachine Canal Relocation bridge of Marc-Cantin Street Construction of Construction of REM elevated Pointe- Panama terminal Saint-Charles Demolition of structure Chevrier tunnel Construction of structure above CN/Malo/Leduc Preparatory work on Highway 10 median Construction of Station Du Quartier 2018 2019 Construction of the elevated structure on Highway 10, the terminal station and De Rome Blvd. Jan. to May to Sept. to Jan. to May to Sept. April Aug. Dec. April Aug. to Dec. Prep. work on Gare Centrale Construction of bridge over Île-des-Sœurs Construction of REM Channel Panama terminal Construction of Station Panama Construction of Île- des-Sœurs Station Construction of Montée Gobeil artwork Construction of REM structures and tracks in Highway 10 median Construction of Station Du Quartier 2018 2019 Construction of the elevated structure on Highway 10, the terminal station and De Rome Blvd. Jan. to May to Sept. to Jan. to May to Sept. April Aug. Dec. April Aug. to Dec. Summer 2018 Maintenance of preferential bus accesses Small stretch of reserved lane removed Panama Chevrier terminal terminal Temporary terminal Milan Blvd. Pelletier Blvd. Lapinière Blvd. Taschereau Blvd. Taschereau To Champlain Bridge To South Shore Leduc Blvd. 2019 New access ramp for Chevrier terminal Chevrier tunnel closure Future REM terminal Chevrier terminal Temporary terminal Milan Milan Blvd. Pelletier Blvd. Lapinière Blvd. Taschereau Blvd. Taschereau To Champlain Bridge To South Shore Several scenarios under study for the trip home Leduc Blvd. New access ramps for the Chevrier and Panama terminals 2019 Highway 10 middle lane closed off for the work Future REM terminal Temporary terminal Milan Milan Blvd. Pelletier Blvd. Lapinière Blvd. Taschereau Blvd. Taschereau To Champlain Bridge To South Shore Several scenarios under study for the trip home Leduc Blvd. 2. MCGILL AND ÉDOUARD-MONTPETIT REM WORK Summer 2018 Excavation and construction of future REM entrance structure Coordination with Ville de Montréal and Université de Montréal REM WORK Fall 2018 Construction of future connection – obstruction on McGill College Coordination with Ville de Montréal and the STM 3. DEUX-MONTAGNES LINE Construction of a temporary workshop for the Deux- Montagnes trains Reconfiguration of Cornwall bridge Preparatory work along the entire route: • Geotechnical surveys • Location and relocation of public and municipal services 2018 2019 Jan. to May to Sept. to Jan. to May to Sept. April Aug. Dec. April Aug. to Dec. Construction of a temporary workshop for the Deux- Montagnes trains Construction of a temporary garage for the Mascouche trains Construction of Mont-Royal Station Reconfiguration of Cornwall bridge Excavation of Édouard-Montpetit Construction of Station Station Canora 2018 2019 Jan. to May to Sept. to Jan. to May to Sept. April Aug. Dec. April Aug. to Dec. Construction of Construction of a temporary temporary platforms at Reconstruction of garage for the Du Ruisseau Henri-Bourassa bridge Mascouche trains (summer 2019) Construction of Correspondance A40 Station Construction of Mont-Royal Station Reconfiguration of Reconstruction of Cornwall bridge Côte-Vertu bridge (summer 2019) Construction of Reconstruction Canora Station of CP bridge Switch Excavation of installation in Édouard-Montpetit Excavation of Mont-Royal Station Station McGill via 2018 2019 tunnel McGill College Avenue Jan. to May to Sept. to Jan. to May to Sept. April Aug. Dec. April Aug. to Dec. Construction of two new railway bridges 2018 2019 Jan. to May to Sept. to Jan. to May to Sept. April Aug. Dec. April Aug. to Dec. April 2018 Work mainly done on weekends (Friday night to Monday morning) Alternative service for some stations (Friday evening to Monday morning) June 2018 Work during the week – south segment closed off Change to Deux-Montagnes and Mascouche schedules Deux-Montagnes: two departures in the morning / one departure in the evening removed (from or to the stations on the Island of Montréal) Construction of Construction of Construction of south Construction of south portion Station A40 portion of Stations Stations Édouard- Canora and Mont-Royal Montpetit and McGill Spring 2019 Work during the week – north segment closed off Change to Deux-Montagnes and Mascouche schedules Deux-Montagnes: two departures in the morning / one departure in the evening removed (from or to the stations on the Island of Montréal) Construction of Construction of Construction of south Construction of New south portion A40 Station and north portions of Édouard-Montpetit switch to Canora and Mont-Royal and McGill Stations be built Stations Fall 2019 Work during the week – north segment closed off (extension) Change to Deux-Montagnes and Mascouche schedules Deux-Montagnes: two departures in the morning / one departure in the evening removed (from or to the stations on the Island of Montréal) Construction of Construction Construction of south Construction of Édouard- south portion of A40 Station and north portions of Montpetit and McGill Canora and Mont-Royal Stations Stations Early 2020 Intensive work – stretch from Du Ruisseau to Central Station closed off Alternative transit solutions required 4. AIRPORT AND WEST ISLAND Demolition of Preparatory work along the entire route Doney branch • Geotechnical surveys • Location and relocation of public and municipal services Geotechnical investigations and studies Relocation of public utilities (Alfred-Nobel Blvd.) Surveying 2018 2019 Jan. to May to Sept. to Jan. to May to Sept. April Aug. Dec. April Aug. to Dec. Preparatory work along the entire route • Geotechnical surveys • Location and relocation of public and municipal services Lay foundation for continuous Excavation at the elevated structure Technoparc (on the whole branch) 2018 2019 Jan. to May to Sept. to Jan. to May to Sept. April Aug. Dec. April Aug. to Dec. Installation of superstructure Lay foundation for continuous elevated structure (on the whole branch) Work at the Technoparc Boring of Airport

View Full Text

Details

  • File Type
    pdf
  • Upload Time
    -
  • Content Languages
    English
  • Upload User
    Anonymous/Not logged-in
  • File Pages
    52 Page
  • File Size
    -

Download

Channel Download Status
Express Download Enable

Copyright

We respect the copyrights and intellectual property rights of all users. All uploaded documents are either original works of the uploader or authorized works of the rightful owners.

  • Not to be reproduced or distributed without explicit permission.
  • Not used for commercial purposes outside of approved use cases.
  • Not used to infringe on the rights of the original creators.
  • If you believe any content infringes your copyright, please contact us immediately.

Support

For help with questions, suggestions, or problems, please contact us