Dalmarnock Power Station, Riverside

Dalmarnock Power Station, Riverside

Case Studies

DALMARNOCK POWER STATION, RIVERSIDE, GLASGOW Description: Form of Contract: Duration:

Land Reclamation and Remediation NEC3 Option A 60 weeks

Contract Value: Client:

£3,400,000 Clyde Gateway

Clients Representative: Grontmij

This reclamation contract was on the site of the once colossal Dalmarnock Power Station, located in the East End of Glasgow. The power station was closed in 1977 and subsequently demolished to ground level with the demolished structures used to backfill the substantial underground voids (basements, tunnels etc). Our scope of work involved major land reclamation, remediation of contaminated soils, bulk earthworks and drainage to provide development platforms on the 9ha site. The site is located in a sensitive area bounded by residential properties, the River Clyde and a railway line which required close liaison with all stakeholders for the duration of the project.

Dalmarnock Road
Drainage

Crib wall
Borrow Pit
Dalmarnock Road

Tunnel

SUDS Pond
Power Station Building Footprint
Railway Line

Perimeter Wall River Clyde Walkway

River Clyde

By far the largest element of the reclamation works involved the controlled demolition of the old power station foundations. Over 60,000m3 of reinforced concrete (R.C.) was broken out, at depths up to 5m. Careful consideration was given to neighbouring properties during this stage of the work. To reassure residents during this stage of the contract, we undertook numerous structural surveys of properties prior to demolition and established vibrographs at strategic locations to monitor vibration during demolition. All concrete was processed to provide engineered fill for the required development platform.

www.ihbrown.com

Case Studies

The removal of the substantial perimeter wall included a section which ran parallel with the River Clyde Walkway. We developed our methodology to facilitate demolition operations whilst maintaining access to pedestrians. Using a combination of timber hoarding and banksmen we removed the brickwork wall and the significant R.C. foundations without closing the walkway.

The demolition of an existing reinforced concrete tunnel located under the footpath of Dalmarnock Road was a particularly complex aspect of the reclamation scope. Working collaboratively with our client’s site team, we developed a solution which involved retaining the Dalmarnock Road side wall and tunnel base slab (highlighted blue) to prevent the road from being undermined. The roof slab was carefully saw-cut and removed along with the side wall to the site side (highlighted red). Our methodology allowed us to maintain two-way traffic flows through the reduced excavation requirement.

Roadside wall and base slab retained and backfilled
Soffit & Side Wall removed
Photo from within tunnel against

In addition to the removal of R.C. foundations, we also had to selectively excavate and treat contaminated soils (hydrocarbons, heavy metals) from locations on site. In total 12,000m3 of soils were excavated and treated during bulk earthwork operations. Forming the base layer of development platform earthworks, contaminated soils were treated with a mixture of lime and cement and placed, at depth, in a solidified fill layer. This solidified layer was then capped using the 60,000m3 of recycled concrete fill and finished with 17,000m3 of site won sub-soils and 8,500m3 of imported topsoil. We worked closely with the Client’s Designer to develop the earthworks solution to overcome a shortfall in sub-soils by establishing a borrow pit within the site to provide the balance of material required.

A remarkable discovery, in the form of unexploded ordinance, was made during bulk earthworks operations. Our site management staff were commended by the emergency services and Client for the manner in which this unexpected incident was dealt with.

The drainage element of the project included both onsite and offsite works. A new section of 1050mm diameter sewer was constructed on Dalmarnock Road under traffic management. Onsite drainage included the construction of a substantial SUDS pond with two outfalls to the River Clyde. A Crib Wall was constructed to overcome a level difference and limited space between the pond and the existing road bridge.

Reclamation works were finished off with a variety of landscaping, a perimeter fence and surfaced paths and access tracks.

Continuing our commitment to community benefit initiatives, we recruited and trained two new employees who had previously been in long term unemployment.

www.ihbrown.com

View Full Text

Details

  • File Type
    pdf
  • Upload Time
    -
  • Content Languages
    English
  • Upload User
    Anonymous/Not logged-in
  • File Pages
    2 Page
  • File Size
    -

Download

Channel Download Status
Express Download Enable

Copyright

We respect the copyrights and intellectual property rights of all users. All uploaded documents are either original works of the uploader or authorized works of the rightful owners.

  • Not to be reproduced or distributed without explicit permission.
  • Not used for commercial purposes outside of approved use cases.
  • Not used to infringe on the rights of the original creators.
  • If you believe any content infringes your copyright, please contact us immediately.

Support

For help with questions, suggestions, or problems, please contact us