Performance of Floor Slabs in Excavations Using Top-Down Method of Construction and Correction of Inclinometer Readings

Performance of Floor Slabs in Excavations Using Top-Down Method of Construction and Correction of Inclinometer Readings

Journal of GeoEngineering,Hwang, R.N., Vol.Moh, 2, No.Z.C.: 3, Performancepp. 111-121, Decemberof Floor Slabs 2007 and Correction of Inclinometer Readings in Deep Excavations 111 PERFORMANCE OF FLOOR SLABS IN EXCAVATIONS USING TOP-DOWN METHOD OF CONSTRUCTION AND CORRECTION OF INCLINOMETER READINGS Richard N. Hwang1 and Za-Chieh Moh2 ABSTRACT The performance of floor systems in two cases in which excavations were carried out using the top-down method of con- struction is compared and is correlated with the progressive movements of diaphragm walls at the top four floor levels. It has been found that the progressive movements of walls at the first floor level will be limited to 2 mm per stage subsequent to the casting of the slabs for typical basement excavations and, up to, 6 mm for very large sites with flexible floor systems. Inclinometer read- ings can be corrected by referencing to the movements at the top to make them reasonable. Key words: Deep excavation, toe movement, top-down construction, floor slabs. 1. INTRODUCTION Toe movement, mm Movements of walls are routinely monitored by using incli- 01020304050 nometers during excavation. It is usually assumed that the toes of 0 inclinometers will not move and wall movements at other depths L: Length of Wall are computed accordingly. However, readings frequently indicate 5 L=24m outward movements in the upper portion of inclinometers in later stages of excavations. Except in rare cases, it is highly unlikely 10 for diaphragm walls to move outward and the readings could well L=30m be erroneous due to movements at the toes of inclinometers. 15 For excavations using the bottom-up method of construction, Depth of Excavation, m Excavation, of Depth 20 wall movements are a result of shortening of struts and can be L=35m correlated with strut load measurements. Data indicate that the shortening of struts at the first and the second level is usually 25 very small and toe movements of inclinometers can be back- Fig. 1 Movements of toes of diaphragm walls in excavations calculated by assuming that the walls would not move at the first using the bottom-up method of construction (after or the second strut level once the struts at these levels were pre- Hwang et al. 2007a) loaded. For very large sites, inward movements, say, up to, a couple of millimeters, can be allowed between consecutive stages above-mentioned procedures of correcting inclinometer readings of excavation as a result of shortening of long struts. Once toe are still applicable. movements are obtained, inclinometer readings at all other The performance of floor slabs observed in two case histo- depths can be corrected accordingly. Figure 1 shows the potential ries is studied and correlated to the recorded wall movements. As lateral movements at the toes of diaphragm walls of different shown in Fig. 2, although the two sites are located in two differ- lengths in the T2, TK2, and K1 Zones of the Taipei basin back- ent geological zones, they are not too far away from each other analyzed by using this approach (Hwang et al. 2007a). For dia- and, hence, the ground conditions at these sites are quite similar. phragm walls of 35 m in length, for example, the toes could In Case 1, the movements at the top of inclinometers were moni- move by 20 mm if excavation is carried out to a depth of 15 m. tored by precision survey and readings at other depths were cali- Movements of such a magnitude will certainly affect the results brated accordingly. Therefore, the performance of floor slabs in of analyses and can not be overlooked. this case is considered reliable and representative. On the other For excavations using the top-down method of construction, hand, the inclinometer readings in Case 2 had to be corrected to diaphragm walls are propped by floor slabs in which the axial make the progressive movements of the diaphragm walls rea- loads are not monitored. Attempts are made herein to study the sonable because movements at the top of inclinometers were not monitored. The performance of floor slabs is then compared with performance of floor slabs based on wall movements to see if the that in Case 1 to see if the corrections made are real. Manuscript received November 6, 2007; accepted December 12, 2. CASE 1 – DEEP EXCAVATION IN THE TK2 2007; revised December 17, 2007. 1 Senior Vice President, corresponding author, Moh and Associates, ZONE Inc., Taipei, Taiwan, R.O.C. (email: richard.hwang@maaconsul- tants.com) Construction for this 15-story hotel commenced in 1997 and 2 President, Moh and Associates, Inc., Taipei, Taiwan, R.O.C. the hotel was open for business in 1999. The site, as depicted in 112 Journal of GeoEngineering, Vol. 2, No. 3, December 2007 Danshui (Tamshui) River Legend: Carpark Entrance Taipei Main Station SID-1 N Case 1 SID-2 7F 1B Main Block BK1 Case 2 N A Jilong (Keelung) River 13F 1~3 story shops 73.8 m TK3 BK2 2B SID-7 WL B B (Fig. 5) SID-3 SC 28.3m K3 Annex T2 TK2 K2 HC K1 A B3 SID-8 SID-5 T1 TK1 (Fig. 4) T1 B2 B1 H2 98.2 m C H1 Fig. 3 Site plan and locations of inclinometers, Case 1 S YH H3 YH SID-3 SID-5 1F~3F Dahan (Tahan) River Ground Level, GL shops Xindian (Hsintien) River CL GL -3.0m 0 4 km VI SM Geological Map: Lee (1996) Un-reinforced V with CL seams 5<N<7 t=1000mm Fig. 2 Geological zoning map of the Taipei basin and locations GL -13.0m IV CL Final Excavation of the sites N = 4 GL -26.6m GL -28.0m Reinforced III SM t=1000mm N = 10 GL -32.0m Fig. 3, has a L-shape with an annex attached to the east of the GL -34.0m CL main block and is about 74 m in the north-south direction and II 28.3m 98 m in the east-west direction. It is located in the TK2 Zone of SM Sungshan Formation the Taipei basin. At the surface is the so called Sungshan Forma- CL N = 18 Diaphragm Walls GL -52.0m I SM N = 27 t=1200mm tion which consists of 6 alternating sublayers of silty sand and GL -54.0m GL -55.0m silty clay as depicted in Fig. 4. The excavation for the 7-level Chingmei Gravels basement was carried out to a maximum depth of 26.6 m in 8 GM stages by using the top-down method of construction. Diaphragm Note: not to scale walls of 1200 mm in thickness were used and were braced by Section A-A (Fig. 3) floor slabs. All the walls extended to a depth of 55 m and, theo- retically, penetrated into the Chingmei Gravels by 1 m. The pene- Fig. 4 Ground conditions and configuration of cross walls, trations, however, were not confirmed during installation of indi- Case 1 vidual panels. There were buildings on the east and west of the site and buttresses were used to reduce the movements of walls as a building protection measure. The configuration of the buttresses 13F is given in Fig. 5. There were a few shops to the north of the an- nex. Therefore, in addition to buttresses, three cross walls were SID-7 added to further reduce wall movements as depicted in Fig. 3 and -0m Ground Level 1 –0.60m GL -3.0m –4.55m their configuration is shown in Fig. 4. The buttresses and cross 2 –5.55m –9.05m 2B 3 –10.05m walls were all 1000 mm in thickness and were cast using con- -13.55m 4 –14.55m 2 –17.55m crete with a compressive strength of 14 N/mm . 5 –18.55m –21.05m 6 –24.50m –22.05m 7 –24.35m 2.1 Inclinometer Readings and Wall Deflection Profiles 8 Un-reinforced Buttresses, There were 6 inclinometers installed inside the diaphragm t=1000mm Final Excavation wall panels for monitoring wall movements. Because the lower GL -26.6m portion of some of the inclinometers, namely, inclinometers SID- GL -40.0m 2, SID-3, SID-5, and SID-7, were damaged and readings could Sungshan 6m or 8m not be taken, the movements of the top of all the inclinometers Formation were measured by survey and wall movements at other depths GL-54m GL -55.0m were calibrated accordingly. Figure 6 shows the wall movements recorded by inclinometers SID-1 and SID-8 which were installed Diaphragm Wall t=1200mm Chingmei Gravels in the northern and the southern walls of the main block respec- Note: not to scale tively. The readings of these two inclinometers were not affected by buttresses or cross walls. Section B-B (Fig. 3) The readings of inclinometers installed in walls with but- Fig. 5 Sequence of excavation and configuration of buttresses, tresses and cross walls are shown in Figs. 7 and 8. The maximum Case 1 Hwang, R.N., Moh, Z.C.: Performance of Floor Slabs and Correction of Inclinometer Readings in Deep Excavations 113 Wall Deflection, mm Wall Deflection, mm Table 1 Maximum wall movements, Case 1 0 50 100 150 0 50 100 150 0 0 Maximum wall movements, mm Notes SID-1 SID-8 Inclinometer Max. Ave. 10 10 Main block SID-1 108.0 114.8 Flat walls (N&S walls) SID-8 121.6 20 20 Main block SID-2 78.5 86.8 With buttresses (E&W walls) SID-7 95.0 30 30 Depth, m Depth, m Depth, Annex SID-3 39.6 With buttresses 54.1 (N&S walls) SID-5 68.5 and cross walls 40 3rd Dig 40 3rd Dig 4th Dig 4th Dig 5th Dig 5th Dig 50 6th Dig 50 6th Dig 7th Dig 7th Dig 2.2 Progressive Wall Movements at Floor Levels 8th Dig 8th Dig 60 60 The movements of the northern and the southern walls at the Fig.

View Full Text

Details

  • File Type
    pdf
  • Upload Time
    -
  • Content Languages
    English
  • Upload User
    Anonymous/Not logged-in
  • File Pages
    12 Page
  • File Size
    -

Download

Channel Download Status
Express Download Enable

Copyright

We respect the copyrights and intellectual property rights of all users. All uploaded documents are either original works of the uploader or authorized works of the rightful owners.

  • Not to be reproduced or distributed without explicit permission.
  • Not used for commercial purposes outside of approved use cases.
  • Not used to infringe on the rights of the original creators.
  • If you believe any content infringes your copyright, please contact us immediately.

Support

For help with questions, suggestions, or problems, please contact us