CENTRAL ELECTRICITY REGULATORY COMMISSION NEW DELHI Petition No. 611/MP/2020 Coram: Shri P. K. Pujari, Chairperson Shri I. S. Jh

CENTRAL ELECTRICITY REGULATORY COMMISSION NEW DELHI Petition No. 611/MP/2020 Coram: Shri P. K. Pujari, Chairperson Shri I. S. Jh

CENTRAL ELECTRICITY REGULATORY COMMISSION NEW DELHI Petition No. 611/MP/2020 Coram: Shri P. K. Pujari, Chairperson Shri I. S. Jha, Member Shri Arun Goyal, Member Shri P. K. Singh, Member Date of Order: 24th May, 2021 In the matter of Petition under Section 79 of the Electricity Act, 2003 and the statutory framework governing the procurement of power through competitive bidding and Article 11 read with Article 13.5 and Article 4.5.3 of the Power Purchase Agreement dated 17.12.2019 executed between Solar Energy Corporation of India Limited and Rihand Floating Solar Private Limited seeking directions to restrain SECI from invoking the bank guarantees and for returning the bank guarantees. And In the matter of Rihand Floating Solar Private Limited. SP Centre, 41/44, Minoo Desai Marg Colaba, Mumbai, Maharashtra …Petitioner Versus Solar Energy Corporation of India Limited D-3, 1st Floor, Wing-A, Prius Platinum Building, District Centre, Saket, New Delhi – 110 017 ….Respondent Parties Present: Shri Sujit Ghosh, Advocate, RFSPL Ms. Mannat Waraich, Advocate, RFSPL Shri M. G. Ramachandran, Senior Advocate, SECI Ms. Tanya Sareen, Advocate, SECI Ms. Anushree Bardhan, Advocate, SECI Shri Ajay Kumar Sinha, SECI Shri Abhishek Kumar Ambasta, SECI Shri Abhinav Kumar, SECI Order in Petition No. 611/MP/2020 Page 1 of 16 ORDER The Petitioner, Rihand Floating Solar Private Limited, has filed the present Petition under Section 79 of the Electricity Act, 2003 (hereinafter referred to as „the Act‟) seeking direction to the Respondent, Solar Corporation of India Limited („SECI‟) to return the bank guarantee dated 25.9.2019 submitted by the Petitioner as a consequence of termination of the Power Purchase Agreement (PPA) dated 17.12.2019 in accordance with Article 4.5.3 read with Article 13.5 of the PPA. The Petitioner has made the following prayers: “(a) Direct SECI to return the Bank Guarantee dated 25.09.2019 submitted by the Petitioner on account of the termination of the PPA dated 17.12.2019 which is in accordance with Article 4.5.3 read with Article 13.5 of the PPA dated 17.12.2019; and (b) In the interim, injunct SECI from encashing the Bank Guarantee dated 25.09.2019 or taking any other coercive steps detrimental to the interest of the Petitioner.” Submission of the Petitioner 2. The brief facts of the case as submitted by the Petitioner are as under: (a) On 6.9.2018, SECI issued Request for Selection (RfS) for setting up of 150 MW (Packages A, B and C of 50 MW each) grid-connected floating solar power project at Rihand Dam in the State of Uttar Pradesh (hereinafter referred to as „the Project‟) in line with the “Guidelines for Tariff Based Competitive Bidding Process for Procurement of Power from Grid Connected Solar PV Power Projects” (hereinafter referred to as „the Guidelines‟) dated 3.8.2017 issued by the Ministry of Power, Government of India. After completion of bidding, on 5.9.2019, SECI issued Letter of Award („LoA‟) in favour of Shapoorji Pallonji Infrastructure Capital Co. Pvt. Ltd. (SP Infra) for 50 MW. Pursuant to issuance of the LoA, the Petitioner Company was incorporated as a Special Purpose Vehicle of SP Infra, inter-alia, for the development of the Project. (b) On 17.12.2019, the Petitioner executed PPA with SECI. As per the PPA, Order in Petition No. 611/MP/2020 Page 2 of 16 the Project is scheduled to be commissioned on 3.9.2021. (c) In order to meet obligation under the PPA, the Petitioner undertook studies with the help of M/s Sterling and Wilson Solar Limited (SWL), M/s Aryatech (technical consultant) and M/s Geosense Surveys (survey agency). M/s Geosense Surveys obtained necessary permissions in February 2020 and completed the initial bathymetry survey. Based on the initial bathymetry survey data, M/s Aryatech identified locations where the detailed bathymetry survey was required to be conducted. (d) Rihand Dam Reservoir has been formed over an area which has numerous mountains, ridges and valleys. Accordingly, accurate mapping of these geological formations are essential primary data for safe design of the floating structures of Solar Power Plant to be installed at such sites. The detailed feasibility studies were required to be conducted over three to four months and it was also required to be conducted when the water level was lowest in the reservoir. This study was expected to be conducted from February to May 2020 prior to the commencement of monsoon. (e) As the Project was the first of its kind in the country, the Petitioner through its parent company, namely, SP Infra initiated discussions and commenced inquiries for floater systems, for such large capacity floating solar projects, from overseas. Certain overseas suppliers were in the process of setting up their manufacturing facilities in India to cater to the floating solar projects in the domestic market. However, the same would take around 6 months to be operational. However, from March 2020, the survey activities at the reservoir site had come to a standstill due to nationwide lockdown imposed by Government of India to contain the spread of COVID-19 pandemic. Also, no confirmation could be obtained from the suppliers regarding exact date when the supplies could be made. (f) In the meanwhile, the Government of India, Ministry of Finance, Department of Expenditure vide Office Memorandum dated 19.2.2020 declared/ notified (by referring to para 9.7.7 of the „Manual for Procurement of Goods‟) that the Order in Petition No. 611/MP/2020 Page 3 of 16 outbreak of Covid-19 in China or any other country would be considered as a natural calamity and the Force Majeure clause may be invoked wherever appropriate. (g) Subsequently, Ministry of New and Renewable Energy (MNRE) vide its Office Memorandum dated 20.3.2020 while acknowledging the Office Memorandum dated 19.2.2020 issued by Ministry of Finance declaring outbreak of Covid-19 in China as an event of Force Majeure, directed renewable energy implementing agencies to treat delay on account of disruption of supply chains due to the spread of coronavirus in China or any other country, as a Force Majeure event. On 24.3.2020, Ministry of Home Affairs, Government of India imposed a nation-wide lockdown which extended from time to time vide orders dated 14.4.2020, 1.5.2020 and 17.5.2020. (h) Accordingly, the Petitioner vide its letters dated 18.3.2020, 29.4.2020 and 15.5.2020 invoked Force Majeure under Article 11 of the PPA and informed SECI that on account of continuing of spread of Covid-19, it would be unable to estimate the impact on time and cost at this stage. The Petitioner also informed SECI that despite best efforts, due to the onset of monsoon, such feasibility studies can only be carried out in February 2021, once the monsoon water recedes. Based on this, the Petitioner anticipated a minimum delay of 300 days in the Project Commissioning Schedule. (i) Pursuant to the MNRE‟s Office Memorandum dated 17.4.2020 wherein MNRE had directed that all the Renewable Energy implementing agency will treat the period of lockdown due to Covid-19 as Force Majeure and that agencies shall grant the extension of time for the entire period of lockdown plus 30 days for normalization, SECI on 19.5.2020, declared that the lockdown period will be considered between 25.3.2020 and 17.5.2020 (both days inclusive) and extended the date of financial closure from 4.12.2020 to 26.2.2021 and date of commissioning of the Project from 3.9.2021 to 26.11.2021. Further, in the said letter, it was also declared that any claim for extension of time prior to or beyond the period can be requested for along with supporting documents. Order in Petition No. 611/MP/2020 Page 4 of 16 (j) In the meanwhile, in the second half of May 2020, the survey team re- grouped at the site of the Project to carry out the balance activities of the feasibility study. However, due to the increased water level, recent cyclones and low visibility due to heavy rains, the progress of survey was badly affected. Thereafter, vide letter dated 15.6.2020, Geosense Surveys informed SWL who further communicated to the Petitioner that the survey activities could not be completed. (k) SWL vide email dated 1.7.2020 also informed the Petitioner about the e- mail received from the proposed manufacturer of floaters, Ciel and Terre (“C&T”) showing its inability to finalise a location for the manufacturing setup due to Covid-19 pandemic and nation-wide lockdown. (l) MNRE vide Office Memorandum dated 30.6.2020 clarified that the period of lockdown is to be treated from 25.3.2020 to 31.5.2020 and the extension would be granted from 25.3.2020 till 31.5.2020 plus 30 days for normalization. (m) Since the cumulative and individual effects of Force Majeure have caused an unreasonable delay in execution of the Project, the Petitioner proceeded to exercise its right to terminate the PPA in accordance with Article 13.5.1 of the PPA. As per the said Article, if Force Majeure event or its effect continue for a period beyond specified under Article 4.5.3 (which is 3 months), either party has the right to terminate the PPA without any further liability to other party. Therefore, in view of the circumstances, cumulative delays and the right available under Article 13.5.1 of the PPA, the Petitioner has terminated the PPA on 18.8.2020.

View Full Text

Details

  • File Type
    pdf
  • Upload Time
    -
  • Content Languages
    English
  • Upload User
    Anonymous/Not logged-in
  • File Pages
    16 Page
  • File Size
    -

Download

Channel Download Status
Express Download Enable

Copyright

We respect the copyrights and intellectual property rights of all users. All uploaded documents are either original works of the uploader or authorized works of the rightful owners.

  • Not to be reproduced or distributed without explicit permission.
  • Not used for commercial purposes outside of approved use cases.
  • Not used to infringe on the rights of the original creators.
  • If you believe any content infringes your copyright, please contact us immediately.

Support

For help with questions, suggestions, or problems, please contact us