Running Head: UNIT 3: SCOPE, TIME, and COST MANAGEMENT

Running Head: UNIT 3: SCOPE, TIME, and COST MANAGEMENT

<p> Unit 3:Scope, Time, and Cost Management 9</p><p>Running Head: UNIT 3: SCOPE, TIME, AND COST MANAGEMENT</p><p>Unit 3: Scope, Time, and Cost Management</p><p>Dale Henderson</p><p>Kaplan University</p><p>Professor Chad McAllister</p><p>IT511: Information Systems Project Management</p><p>June 24, 2013 Unit 3:Scope, Time, and Cost Management 9</p><p>Unit 3: Scope, Time, and Cost Management</p><p>1. Explain project scope management in terms of its processes.</p><p>Project scope management is the work that is or is not going to be done, it gives the </p><p> team and stakeholders understanding what products that will be produced and the processes</p><p> the project team will use to produce them, it is what defines and control the project </p><p> knowing what work is to be done and what work will not be done (Schwalbe, 2011).</p><p>There are five processes that work with the project scope management and they are: </p><p>(1) Collecting requirement which defines and documents and the tasks of which products </p><p> are produced within the project as well as the many processes used in creating them. (2) </p><p>Defining the scope which requires examining the project charter, requirements documents, </p><p> and organizational process assets to produce a scope statement, adding more information as</p><p> requirements are produced and change request are approved. (3) Creating the WBS is </p><p> subdividing the deliverables into smaller chunks that are more manageable components. (4)</p><p>Verifying scope is the formalizing acceptance of the deliverables within the project. </p><p>Stakeholders, such as customer and sponsors for the project, inspect and accept the </p><p> deliverables during this process. If the deliverables are not accepted, the customers or </p><p> sponsor usually request changes. (5) Controlling the changes to the project within the entire</p><p> life of the project, these scope changes are a challenge for information technology because </p><p> they influence the team the ability to meet project time and cost goals, so project managers </p><p> must make sure they weigh the costs and benefits of scope changes (Schwalbe, 2011).</p><p>2. Compare and contrast the five approaches for creating work breakdown structures.</p><p>The five approaches of creating a WBS are: Unit 3:Scope, Time, and Cost Management 9</p><p>1. Using guidelines: It is very important to follow guidelines if they exist because, many </p><p> organizations have their own guidelines so it is important to see if the organization you </p><p> are working for have their own guidelines and many organization use the U.S </p><p>Department of Defense (DOD) for example (Schwalbe, 2011).</p><p>Many organizations will have their own guidelines in creating a WBS through </p><p> guidelines and templates develop through Microsoft Project 2007 or whatever of </p><p> version they might be using at their organization, so again check with the organization </p><p> to see what guidelines they are using.</p><p>2. The analogy approach: In this approach you are using a similar project’s WBS as a </p><p> starting point. This similar WBS will give a starting point for defining the scope for the </p><p> new projects and developing costs estimates, some organizations will keep and archive </p><p> repository of WBS and other project documentation on file to help people working on </p><p> projects. Microsoft Project and many other software tools include sample files to assist </p><p> in creating WBS’s and Gantt charts, examining these files will help people understand </p><p> different ways to create a WBS.</p><p>3. The top-down approach: A conventional approaches that for a construction of a WBS. </p><p>Starting with the largest items and is than broken down into lower items, this process </p><p> refines the work into greater and greater levels of detail. After the process is finished, </p><p> all resources should be assigned at the work package level. This approach is best suited </p><p> to project managers who have vast technical awareness and a big picture perspective</p><p>4. The bottom-down approach: This approach as many specific tasks are identified by </p><p> team members related to the project as possible. The members than aggregate the tasks </p><p> and organize them into summary activities, or higher levels in the WBS. Instead of Unit 3:Scope, Time, and Cost Management 9</p><p> using guidelines for creating a WBS or viewing similar projects, they could and more </p><p> than likely will by listing detailed tasks they think will need in order to create the </p><p> application after that has been completed they will put these detailed task in categories, </p><p> then they group these categories into higher level categories. Some people have found it</p><p> helpful that writing all possible tasks down on notes and placing them on a wall will </p><p> help them see all the work required for the project and develop logical groupings for </p><p> performing the work. This approach can be time consuming, but it will be an effective </p><p> way to create a WBS. This approach is used a lot by project managers for projects that </p><p> represent entirely new systems or approaches to doing a job, or to help create buy-in </p><p> and synergy with a project team (Schwalbe, 2011).</p><p>5. The mind-mapping approach: This is a technique that uses branches radiating out from </p><p> a core idea to structure thoughts and ideas. Instead of writing tasks down in a list or </p><p> immediately trying to create a structure for tasks, mind-mapping allows people to write </p><p> and even draw pictures of ideas in a nonlinear format. This gives a more visual, less-</p><p> structured approach to defining and then grouping task can unlock creativity among </p><p> individuals and increase participation and morale among teams. Mind-mapping is </p><p> popular among project managers and can be used in WBS s using the top-down or </p><p> bottom-up approach (Schwalbe, 2011).</p><p>3. Explain project time management in terms of its processes.</p><p>Project time management is defined and in simplest terms that involves the process to </p><p> ensure timely completion of a project and probably one of the most important aspects of a </p><p> project. Seams simple? But in fact it is not as simple as it seems, there are six main </p><p> processes involved to in the project management plan and they are: Unit 3:Scope, Time, and Cost Management 9</p><p>1. Defining activities: The activities that are identified that must be performed by team </p><p> members and stakeholders to produce the project deliverables. An activity or task is an </p><p> element of work normally found on the WBS that has an expected duration, a cost and </p><p> resource requirements. The main outputs are activity list, activity attributes, and </p><p> milestone list.</p><p>2. Sequencing activities: Identifying and documenting the relationships between project </p><p> activities. The main outputs include project schedule network diagrams and project </p><p> document updates.</p><p>3. Estimating activity: Is the process of estimating how many resources people, </p><p> equipment, and materials a project team should use to perform activities. The main </p><p> outputs are activity resource requirements, resource breakdown structure, and project </p><p> document updates.</p><p>4. Estimating activity durations: Is the process of estimating the number of work periods </p><p> that are needed to complete individual activities. The outputs are activity duration </p><p> estimates and project document updates.</p><p>5. Developing the schedule: The process of analyzing activity sequences, activity resource</p><p> estimates, and activity duration estimates to create the project schedule. The outputs are</p><p> project schedule, a schedule baseline, schedule data, and project document updates.</p><p>6. Controlling the schedule: This process controls and manages changes to the project </p><p> schedule. Outputs include work performance measurements, organizational process </p><p> assets updates, change requests, project management plan updates, and project </p><p> document updates. Unit 3:Scope, Time, and Cost Management 9</p><p>4. Formulate the steps for creating a critical path analysis.</p><p>Many projects fail because they do not meet the schedule expectations in the Critical </p><p>Path Analysis, which is a network diagramming technique used to predict total project </p><p> duration. The critical path is a series of activities that determine the earliest time by which </p><p> the project can be completed. It is the longest path through the network diagram and has the</p><p> least amount of slack and float. Slack or float is the amount of time an activity may be </p><p> delayed without delaying a succeeding activity or the project finish date (Schwalbe, 2011).</p><p>The first step that must be done is to develop a network diagram, which in turn </p><p> requires a good activity list based on the WBS, these will include all the tasks within </p><p> included in the project and estimates on the duration of each task</p><p>The next step is to know what order these task will be accomplished. Task </p><p> dependencies is how this is done there are four dependencies and they are as listed below</p><p>Dependency Description Finish-to-start (FS) A relationship where the “from” activity must finish before the “to” activity or successor can start. Start-to-start (SS) A relationship in which “from” activity cannot start until the “to” or successor is started. Finish-to-finish (FF) A relationship where the “from” activity must be finished before the “to” activity or successor can be finished. One task cannot finish before another finishes. Start-to-finish (SF) A relationship where the “from” activity must start before the “to” activity can be finished. This type of relationship is rarely used. Unit 3:Scope, Time, and Cost Management 9</p><p>Next the task or drawn out on some form of paper, whiteboard or anything else that is </p><p> available at that time, usually paper though. The project manager will usually be the one </p><p> doing this he or she will make sure it goes by. The diagram will have the entire task </p><p> required on it for the project and this drawing will have arrows which are connected to </p><p> nodes to illustrate the sequence of activities, a node is the starting and ending point of an </p><p> activity. All that is drawn is put into the network diagram and is all the work that must be </p><p> performed to complete the project.</p><p>Next step is to make sure the tasks that are being performed are assigned to member of </p><p> the team who can perform and complete the task they are assigned to. The longest path or </p><p> path containing the critical tasks is what is driving the completion date for the project. </p><p>Slack time can be assigned to people with less experience. Slack time is the amount of time</p><p> an activity can be delayed without delaying a succeeding activity or the project finish date. </p><p>The critical path is the shortest path to complete a task and projects are always changing </p><p> and that means critical paths can change also, so it is always important to monitor it at all </p><p> times.</p><p>5. Explain project cost management in terms of its processes.</p><p>Project cost management is basically to complete the project with in the budget that </p><p> has been agreed on. Many projects fail because the client or organization ran out of money </p><p> and it is the responsibility of the project manager that it is under the budget and there are </p><p> three processes and they are:</p><p>1. Estimating costs: The process of coming up with an approximation or estimate of </p><p> the costs of resources needed to complete the project. Outputs are activity cost </p><p> estimates, basis of estimates, and project document updates. Unit 3:Scope, Time, and Cost Management 9</p><p>2. Determining the budget: The process allocating the overall estimate to individual </p><p> work items to establish a baseline for measuring performance. The outputs are </p><p> cost performance baseline, project funding requirements and project document </p><p> updates.</p><p>3. Controlling costs: The process of controlling changes to the project budget. The </p><p> main outputs are work performance measurements, budget forecasts, </p><p> organizational process asset updates, change requests, project management plan </p><p> updates, and project document updates.</p><p>6. Compare and contrast the three basic types of cost estimating using the dimensions of </p><p> accuracy, speed, and purpose. </p><p>Type of Cost Estimate Accuracy Speed Purpose Rough order of magnitude -50 percent to +100. Not a The estimate time range can 3 Provides an estimate of what </p><p>(ROM) very accurate estimate a very or more years prior to project the project will cost.</p><p> wide open range completion Budgetary estimate -10 to +25 percent more Completed 1 to 2 years prior Is used to allocate money into </p><p> accurate than an ROM to project completion an organization budget.</p><p> estimate. Definite Estimate -5 to +10 percent. The most Completed 1 year or less prior An accurate estimate of project</p><p> accurate of the 3. to project completion. costs. Much more detailed </p><p> budget.</p><p>References: Unit 3:Scope, Time, and Cost Management 9</p><p>Schwalbe, K. (2011). Information Technology Project Management (6 ed.). Boston: Cengage </p><p>Learning.</p><p>Reference The Project Management Hut. (2013). Retrieved June 24, 2013, from WBS Training - What art </p><p> the project management benefits?: http://www.pmhut.com/wbs-training-what-are-the-</p><p> project-management-benefits Unit 3:Scope, Time, and Cost Management 9</p><p>Sap Help Portal. (n.d.). Retrieved June 24, 2013, from What is a Work Breakdown Structure?: </p><p> http://help.sap.com/saphelp_45b/helpdata/en/4c/225bd746e611d189470000e829fbbd/c</p><p> ontent.htm</p><p>Schwalbe, K. (2011). Information Technology Project Management (6 ed.). Boston: Cengage </p><p>Learning.</p>

View Full Text

Details

  • File Type
    pdf
  • Upload Time
    -
  • Content Languages
    English
  • Upload User
    Anonymous/Not logged-in
  • File Pages
    10 Page
  • File Size
    -

Download

Channel Download Status
Express Download Enable

Copyright

We respect the copyrights and intellectual property rights of all users. All uploaded documents are either original works of the uploader or authorized works of the rightful owners.

  • Not to be reproduced or distributed without explicit permission.
  • Not used for commercial purposes outside of approved use cases.
  • Not used to infringe on the rights of the original creators.
  • If you believe any content infringes your copyright, please contact us immediately.

Support

For help with questions, suggestions, or problems, please contact us