Practice Problem: Chapter 15, Short Term Scheduling

Practice Problem: Chapter 15, Short Term Scheduling

<p> Practice Problem: Chapter 15, Short Term Scheduling</p><p>Problem 1:</p><p>Assume that Susan is a sorority pledge coordinator with four jobs and only three pledges. The table below gives the expected time for each pledge to do each job.</p><p>Job 1 Job 2 Job 3 Job 4</p><p>Alice 4 9 3 8</p><p>Barbara 7 8 2 6</p><p>Jennifer 3 4 5 7</p><p>If she wishes to minimize the time taken, to whom should she assign which job?</p><p>1 Problem 2: Five jobs are to be done at custom furniture shop:</p><p>Job Days Date Promised to Finish (in Days from Today)</p><p>A 2 5</p><p>B 8 8</p><p>C 6 12</p><p>D 4 10</p><p>E 1 4</p><p>Compare the effect of the scheduling methods (A) FCFS (first come, first served), (B) EDD (earliest due date), and (C) SPT (smallest processing time).</p><p>2 Problem 3: The following six jobs are waiting to be processed:</p><p>Job Hours Time to Due Process</p><p>#407 2 7</p><p>#281 8 16</p><p>#306 4 4</p><p>#429 10 17</p><p>#038 5 15</p><p>#998 12 18</p><p>Develop the appropriate sequencing for these jobs using the Critical Ratio criteria.</p><p>3 Problem 4: Five jobs go through two work centers, as shown below:</p><p>Job Hours Required </p><p>Varnishing Painting (Center 1) (Center 2)</p><p>R 4 5</p><p>S 17 7</p><p>T 14 12</p><p>U 9 2</p><p>V 11 6</p><p>What is the appropriate sequence for these jobs?</p><p>4 ANSWERS</p><p>Problem 1: First, begin with the following assignment table:</p><p>Job 1 Job 2 Job 3 Job 4</p><p>Alice 4 9 3 8</p><p>Barbara 7 8 2 6</p><p>Jennifer 3 4 5 7</p><p>Dummy 0 0 0 0</p><p>Note: The “dummy” must be added because we have four jobs and only three people.</p><p>Solve this table for the set of assignments giving the minimum total job time.</p><p>Your final table should look like:</p><p>Job 1 Job 2 Job 3 Job 4</p><p>Alice 0 4 0 3</p><p>Barbara 4 4 0 2</p><p>Jennifer 0 0 3 3</p><p>Dummy 1 0 2 0</p><p>5 The set of optimal assignments would then be: Alice - Job 1 Barbara - Job 3 Jennifer - Job 2 Dummy - Job 4 Note that Job 4 does not get done since it is assigned to the “Dummy.”</p><p>Problem 2: (A)</p><p>FCFS</p><p>Sequence Process Flow Due Lateness Time Time Date</p><p>A 2 2 5 0</p><p>B 8 10 8 2</p><p>C 6 16 12 4</p><p>D 4 20 10 10</p><p>E 1 21 4 17</p><p>TOTALS 21 69 33</p><p>Average completion time  69 / 5  13.8 days</p><p>Average number of jobs in the system  69 / 21  3.28 jobs Average lateness  33 / 5  6.6 days</p><p>Utilization  21/ 69  30.4%</p><p>6 (B)</p><p>EDD</p><p>Sequence Process Flow Due Lateness Time Time Date</p><p>E 1 1 4 0</p><p>A 2 3 5 0</p><p>B 8 11 8 3</p><p>D 4 15 10 5</p><p>C 6 21 12 9</p><p>TOTALS 21 51 17</p><p>Utilization  21/ 51  41.2%</p><p>(C)</p><p>SPT</p><p>Sequence Process Flow Due Lateness Time Time Date</p><p>E 1 1 4 0</p><p>A 2 3 5 0</p><p>D 4 7 10 0</p><p>C 6 13 12 1</p><p>B 8 21 8 13</p><p>TOTALS 21 45 14</p><p>7 Average completion time  45 / 5  9 days</p><p>Average number of jobs in the system  45 / 21  2.14 jobs Average lateness  14 / 5  2.8 days</p><p>Utilization  21/ 45  46.7%</p><p>Problem 3:</p><p>Job Hours to Time Computed Process Due Critical Ratio</p><p>#407 2 7 7/2 = 3.5</p><p>#281 8 16 16/8 = 2.0</p><p>#306 4 4 4/4 = 1.0</p><p>#429 10 17 17/10 = 1.7</p><p>#038 5 15 15/5 = 3.0</p><p>#998 12 18 18/12 = 1.5</p><p>8 Critical Critical Ratio Ratio Sequence</p><p>#306 1.0</p><p>#998 1.5</p><p>#429 1.7</p><p>#281 2.0</p><p>#038 3.0</p><p>#407 3.5</p><p>Problem 4:</p><p>9</p>

View Full Text

Details

  • File Type
    pdf
  • Upload Time
    -
  • Content Languages
    English
  • Upload User
    Anonymous/Not logged-in
  • File Pages
    9 Page
  • File Size
    -

Download

Channel Download Status
Express Download Enable

Copyright

We respect the copyrights and intellectual property rights of all users. All uploaded documents are either original works of the uploader or authorized works of the rightful owners.

  • Not to be reproduced or distributed without explicit permission.
  • Not used for commercial purposes outside of approved use cases.
  • Not used to infringe on the rights of the original creators.
  • If you believe any content infringes your copyright, please contact us immediately.

Support

For help with questions, suggestions, or problems, please contact us