<p> Jetpur - Somnath Section of NH-8D</p><p>PROJECT STATUS REPORT AS ON 31 May ’14</p><p>PHYSICAL PROGRESS OF THE PROJECT</p><p>The Progress of the major works carried out at the site in the month of May 2014 is as follows: ROAD WORKS:</p><p>Sl. Descriptio Uni Total Cumulative Qty Cumulative % Work No. n t Qty (2 Qty Achieved Achieved Qty Achieved Achieved till 30 April '14 in May '14 till 31 May '14 till 31 May Lane) '14</p><p>1 Clearing & Km 246.9 182.39 6.78 189.17 76.62% Grubbing 2 Embankment Km 246.9 176.16 4.18 180.34 73.04% 3 Sub grade Km 246.9 161.78 6.26 168.04 68.06% 4 Granular Sub Km 246.9 157.53 5.13 162.66 65.88% Base 5 Wet Mix Km 246.9 152.79 4.57 157.35 63.73% Macadam 6 Median Kerb Km 246.9 134.93 4.34 139.27 56.41% 7 Dense Km 246.9 145.64 5.30 150.94 61.13% Bituminous Macadam 8 BC Km 246.9 116.91 10.00 126.91 51.40% 9 DLC Cu 5292 1911 535 2446 46.22% m 10 PQC Cu 11996 2670 580 3250 27.09% m</p><p>WORK IN PROGRESS</p><p>Sl. Uni WIP Qty till 31st May N Description t ‘14 o 1 Embankment Km 8.53 2 Sub grade Km 3.65 3 Granular Sub Base Km 1.25 4 Wet Mix Macadam Km 1.30 5 Median Kerb Km 0.40 6 Dense Bituminous Macadam Km 0.0</p><p>4 L a n i n g o f J e t p u r - S o m n a t h S e c t i o n ( K m . 0 . 0 0 0 t o 1 2 7 . 6 0 0 ) o f N H - 8 D i n t h e S t a t e o f G u j a r a t o n D B F O P a t t e r n u n d e r N H D P P h a s e I I I Jetpur - Somnath Section of NH-8D</p><p>STRUCTURE WORKS:</p><p>Physical Progress status of Structures</p><p>Scope as per Balance to S No T ype of Structure C A (No of C ompleted In Progress Start Locations)</p><p>1 Hume Pipe C ulverts 32 27 2 3</p><p>2 Box / Slab C ulverts 84 55 3 25</p><p>3 Minor Bridges 84 75 1 8</p><p>4 PUP / C UP 11 7 0 3</p><p>5 VUP 5 1 2 2</p><p>6 Major Bridges - New 11 11 0 4</p><p>7 Major Bridges - W idening 0 0 0</p><p>8 RoB 4 0 3 1</p><p>9 Fly Over 1 1 0 0</p><p>T otal : 232 177 11 46 100% 76% 5% 20%</p><p>4 L a n i n g o f J e t p u r - S o m n a t h S e c t i o n ( K m . 0 . 0 0 0 t o 1 2 7 . 6 0 0 ) o f N H - 8 D i n t h e S t a t e o f G u j a r a t o n D B F O P a t t e r n u n d e r N H D P P h a s e I I I Jetpur - Somnath Section of NH-8D</p><p>FINANCIAL PROGRESS OF THE PROJECT</p><p>The Financial Progress of the major works carried out in the Project till the month of April 2014 is as follows: Cumulativ % Financial Financial Cumulati Cumulativ % % e Financial Financia Progress Progress ve e Financial Financial Financial Progress l for May '14 for May Financial Progress Progress Progress achieved Progres (Planned) '14 Progress till date Planned Achieved till April s (Achieve till date (Achieved) till date till date '14 achieved d) (Planned) till April '14 (crores) % (crores) (crores) (crores) (crores) % % 549.73 56.04% 33.06 25.21 866.38 574.94 88.32% 58.61%</p><p>4 L a n i n g o f J e t p u r - S o m n a t h S e c t i o n ( K m . 0 . 0 0 0 t o 1 2 7 . 6 0 0 ) o f N H - 8 D i n t h e S t a t e o f G u j a r a t o n D B F O P a t t e r n u n d e r N H D P P h a s e I I I </p>
Details
-
File Typepdf
-
Upload Time-
-
Content LanguagesEnglish
-
Upload UserAnonymous/Not logged-in
-
File Pages3 Page
-
File Size-