Cost Variance = EV-AC = $20,000 $25,000 = - $ 5,000

Cost Variance = EV-AC = $20,000 $25,000 = - $ 5,000

<p>Given the following information for a one-year project, answer the following questions. Recall that PV is the planned value. EV is the earned value, AC is the actual cost, and BAC is the budget at completion. PV = $23,000 EV = $20,000 AC = $25,000 BAC = $120,000 a. What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project?</p><p>Cost Variance is calculated as EV-AC and indicates the difference between the budgeted cost and the actual cost of completed work. Cost Variance = EV-AC = $20,000 – $25,000 = - $ 5,000</p><p>Schedule Variance is calculated as EV-PV and indicates the degree to which the value of completed work differs from that planned. Schedule Variance = EV-PV = $20,000 - $23,000 = -$ 3,000</p><p>Cost Performance Index (CPI) = EV/AC = 20,000/25,000 = 0.8 or 80%</p><p>Schedule Performance Index = EV/PV = 20,000 / 23,000 = 0.86 or 86% b. How is the project doing? Is it ahead or schedule or behind schedule? Is it under budget or over budget?</p><p>The project is not doing well. Because the Cost variance and Schedule variance are negative.A negative Schedule variance means the project is behind schedule and a negative Cost variance means the project is over cost. c. Use the CPI to calculate the estimate at completion (EAC) for this project. Is the project performing better or worse than planned?</p><p>EAC = BAC/CPI = $ 120,000/.8 = $ 150,000</p><p>The project is performing worse than planned because the new estimate is $150,000 which is $30,000 more than initial estimate. d. Use the schedule performance index (SPI) to estimate how long it will take to finish this project. Estimated time to complete = Time estimate / SPI = 12 months / .86 = 13.9 The project is projected to take 13.9 months to complete so it is estimated that it will take 1.9 months more than planned. e. Sketch the earned value chart based for this project</p><p>Earned value chart for the project for 5 months </p>

View Full Text

Details

  • File Type
    pdf
  • Upload Time
    -
  • Content Languages
    English
  • Upload User
    Anonymous/Not logged-in
  • File Pages
    2 Page
  • File Size
    -

Download

Channel Download Status
Express Download Enable

Copyright

We respect the copyrights and intellectual property rights of all users. All uploaded documents are either original works of the uploader or authorized works of the rightful owners.

  • Not to be reproduced or distributed without explicit permission.
  • Not used for commercial purposes outside of approved use cases.
  • Not used to infringe on the rights of the original creators.
  • If you believe any content infringes your copyright, please contact us immediately.

Support

For help with questions, suggestions, or problems, please contact us