B Practice Problem: Chapter 3, Project Management /B

B Practice Problem: Chapter 3, Project Management /B

<p> Practice Problem Chapter 3—Project Management</p><p>Problem 1: The following represent activities in a major construction project. Draw the network to represent this project.</p><p>Activity Immediate Predecessor</p><p>A -</p><p>B -</p><p>C A</p><p>D B</p><p>E B</p><p>F C, E</p><p>G D</p><p>H F, G</p><p>1 Copyright ©2014 Pearson Education, Inc. Problem 2: Given the following Time Chart and Network Diagram, find the Critical Path.</p><p>Activity a m b t Variance</p><p>A 2 3 4 3 1/9</p><p>B 1 2 3 2 1/9</p><p>C 4 5 12 6 16/9</p><p>D 1 3 5 3 4/9</p><p>E 1 2 3 2 1/9</p><p>Problem 3: What is the variance in completion time for the critical path found in Problem 2?</p><p>2 Copyright ©2014 Pearson Education, Inc. Problem 4: A project has an expected completion time of 40 weeks and a standard deviation of 5 weeks. It is assumed that the project completion time is normally distributed. a. What is the probability of finishing the project in 50 weeks or less? b. What is the probability of finishing the project in 38 weeks or less? c. The due date for the project is set so that there is a 90% chance that the project will be finished by this date. What is the date?</p><p>Problem 5: Development of a new deluxe version of a particular software product is being considered. The activities necessary for the completion of this project are listed in the table below along with their costs and completion times in weeks.</p><p>Activity Normal Crash Normal Crash Immediate Time Time Cost Cost Predecessor</p><p>A 4 3 2,000 2,600 -</p><p>B 2 1 2,200 2,800 A</p><p>C 3 3 500 500 A</p><p>D 8 4 2,300 2,600 A</p><p>E 6 3 900 1,200 B, D</p><p>F 3 2 3,000 4,200 C, E</p><p>G 4 2 1,400 2,000 F</p><p> a. What is the project expected completion date? b. What is the total cost required for completing this project on normal time? c. If you wish to reduce the time required to complete this project by 1 week, which activity should be crashed, and how much will this increase the total cost?</p><p>3 Copyright ©2014 Pearson Education, Inc. ANSWERS:</p><p>Problem 1:</p><p>Problem 2: Critical path: ACDE = 14</p><p>Problem 3:</p><p>Total variance = variances of activities on critical path 1 16 4 1 2 Total Total variance= + + + = 2 = 2.55 9 9 9 9 9 Ands = 2.55 = 1.6</p><p>4 Copyright ©2014 Pearson Education, Inc. Problem 4:</p><p>X -m 50 - 40 a. Z= = = 2 s 5 Therefore: P(X� 50) � P (Z 2) 0.97725 X-m - 2 b. Z= = = - 0.4 s 5 Therefore: P(X� 38) � P(Z= 0.4) 0.34458 c. 90%� Z= 1.28 = (c - m ) / s - c 40 / 5 Therefore: c =1.28*5 + 40 = 46.4weeks</p><p>Problem 5:</p><p> a.</p><p>Project completion time is therefore tA+ t D + t E + t F + t G =4 + 8 + 6 + 3 + 4 = 25 b. Total cost= $2,000 + $2200 + $500 + $2,300 + $900 + $3,000 + $1,400 = $12,300 $2,600- $2,300 $300 c. Crash D 1 week at an additional cost of = = $75 8- 4 4</p><p>5 Copyright ©2014 Pearson Education, Inc.</p>

View Full Text

Details

  • File Type
    pdf
  • Upload Time
    -
  • Content Languages
    English
  • Upload User
    Anonymous/Not logged-in
  • File Pages
    5 Page
  • File Size
    -

Download

Channel Download Status
Express Download Enable

Copyright

We respect the copyrights and intellectual property rights of all users. All uploaded documents are either original works of the uploader or authorized works of the rightful owners.

  • Not to be reproduced or distributed without explicit permission.
  • Not used for commercial purposes outside of approved use cases.
  • Not used to infringe on the rights of the original creators.
  • If you believe any content infringes your copyright, please contact us immediately.

Support

For help with questions, suggestions, or problems, please contact us