DRAFT BASIC ASSESSMENT REPORT for HARI PV GRID CONNECTION INFRASTRUCTURE

DRAFT BASIC ASSESSMENT REPORT for HARI PV GRID CONNECTION INFRASTRUCTURE

DRAFT BASIC ASSESSMENT REPORT for HARI PV GRID CONNECTION INFRASTRUCTURE On Remaining Extent Farm Geel Kop 456 In terms of the National Environmental Management Act (Act No. 107 of 1998, as amended) & 2014 Environmental Impact Regulations Prepared for Applicant: Hari PV (Pty) Ltd Date: 13 January 2021 Author of Report: Dale Holder Author Email: [email protected] Report Reference: KAI632/33 Department Reference: 14/12/16/3/3/1/2294 Case Officer: Click here to enter Case Officer Name DOCUMENT TRACKING DOCUMENT HISTORY REVISION DATE AUTHOR Draft Basic Assessment Report 13 January 2021 Dale Holder Draft Environmental Management Programme 13 January 2021 Dale Holder APPROVAL FOR RELEASE NAME TITLE SIGNATURE Dale Holder Senior Environmental Practitioner DISTRIBUTION DISTRIBUTION LIST Department of Environment, Forestry and Fisheries Potential and Registered Interested and Affected Parties Hari PV (Pty) Ltd SUBMISSION AND CORRESPONDENCE SUBMISSION / CORRESPONDENCE DATE Application form Submitted 9 December 2020 Application form Acknowledged 18 December 2020 Draft Basic Assessment Report Submitted 13 January 2021 Draft Basic Assessment Report Acknowledged Pending Comment on Draft Basic Assessment Report Pending Final Basic Assessment Report Submitted Pending APPOINTED ENVIRONMENTAL ASSESSMENT PRACTITIONER: Cape EAPrac Environmental Assessment Practitioners PO Box 2070 George 6530 Tel: 044-874 0365 Fax: 044-874 0432 Report written & compiled by: Dale Holder (Ndip Nature Conservation), who has over 16 years’ experience as an environmental practitioner. Registrations: Director, Louise-Mari van Zyl (MA Geography & Environmental Science [US]; Registered Environmental Assessment Practitioner with the Interim Certification Board for Environmental Assessment Practitioners of South Africa, EAPSA). Ms van Zyl has over fifteen years’ experience as an environmental practitioner. PURPOSE OF THIS REPORT: I&AP Review and Comment APPLICANT: Hari PV (Pty) Ltd CAPE EAPRAC REFERENCE NO: KAI632/33 DEPARTMENT REFERENCE: 14/12/16/3/3/1/2294 SUBMISSION DATE: 13 January 2021 Draft Basic Assessment Report in terms of the National Environmental Management Act, 1998 (Act No. 107 of 1998 as amended) & Environmental Impact Regulations2014 (as amended) Hari PV Grid Connection Infrastructure Remaining Extent Farm Geel Kop 456 Submitted for: Stakeholder Review & Comment This report is the property of the Author/Company, who may publish it, in whole, provided that: • Written approval is obtained from the Author and that Cape EAPrac is acknowledged in the publication; • Cape EAPrac is indemnified against any claim for damages that may result from any publication of specifications, recommendations or statements that is not administered or controlled by Cape EAPrac; • The contents of this report, including specialist/consultant reports, may not be used for purposes of sale or publicity or advertisement without the prior written approval of Cape EAPrac; • Cape EAPrac accepts no responsibility by the Applicant/Client for failure to follow or comply with the recommended programme, specifications or recommendations contained in this report; • Cape EAPrac accepts no responsibility for deviation or non-compliance of any specifications or recommendations made by specialists or consultants whose input/reports are used to inform this report; and • All figures, plates and diagrams are copyrighted and may not be reproduced by any means, in any form, in part or whole without prior written approved from Cape EAPrac. Report Issued by: Cape Environmental Assessment Practitioners Tel: 044 874 0365 PO Box 2070 Fax: 044 874 0432 17 Progress Street, George 6530 Web: www.cape-eaprac.co.za Cape EAPrac Draft Basic Assessment Report REPORT DETAILS Title: Draft Basic Assessment Report for Hari PV Grid Connection Infrastructure Purpose of this report: The Draft Basic Assessment Report for the Hari PV Grid Connection Infrastructure is made available to all registered and potential Interested and Affected Parties (I&APs) for review and comment and all comments received will be incorporated into the Final Basic Assessment Report that will be submitted to the competent authority for decision making. This BAR forms part of a series of reports and information sources that are being provided during the Basic Assessment Process for the proposed Hari PV Grid Connection Infrastructure near Keimoes in the Northern Cape Province. Registered I&APs will be given an opportunity to comment on the following reports as part of this environmental process: - Draft Basic Assessment Report, - All Specialist Studies, and - Draft Environmental Management Programme. In accordance with the regulations, the objectives of an environmental process are to, through a consultative process: (a)identify the relevant policies and legislation relevant to the activity; (b) motivate the need and desirability of the proposed activity, including the need and desirability of the activity in the context of the preferred location; (c) identify and confirm the preferred activity and technology alternative through an impact and risk assessment and ranking process; (d) identify and confirm the preferred site, through a detailed site selection process, which includes an impact and risk assessment process inclusive of cumulative impacts and a ranking process of all the identified alternatives focusing on the geographical, physical, biological, social, economic, and cultural aspects of the environment; (e) identify the key issues to be addressed in the assessment phase; (f) agree on the level of assessment to be undertaken, including the methodology to be applied, the expertise required as well as the extent of further consultation to be undertaken to determine the impacts and risks the activity will impose on the preferred site through the life of the activity, including the nature, significance, consequence, extent, duration and probability of the impacts to inform the location of the development footprint within the preferred site; and (g) identify suitable measures to avoid, manage or mitigate identified impacts and to determine the extent of the residual risks that need to be managed and monitored. The Draft Basic Assessment Report is available to all registered and potential interested and affected parties for a 30-day review and comment period extending from 13 January 2021 – 11 February 2021. All comments received during this comment period will be incorporated into the Final BAR that is herewith submitted to the DEFF for Decision making. Prepared for: Hari PV (Pty) Ltd Published by: Cape Environmental Assessment Practitioners (Pty) Ltd. (Cape EAPrac) Authors: Mr Dale Holder Cape EAPrac Ref: KAI632/33 DEA Case officer & Ref. No: Samkelisiwe Dlamini 14/12/16/3/3/1/2294 Date: 13 January 2021 To be cited as: Cape EAPrac, 2020. Draft Basic Assessment Report for Hari PV Grid Connection Infrastructure. Report Reference: KAI632/33. George. Cape EAPrac Draft Basic Assessment Report TECHNICAL CHECKLIST The following technical checklist is included as a quick reference roadmap for the proposed project. Applicant Details Hari PV (Pty) Ltd Company 2020 / 156305 / 07 Registration Number: BBBEE Status: N/A Project Name: Hari PV Grid Connection Infrastructure Site Details Remaining Extent of the Farm Geel Kop No 456 Grid connection Substation to which No new substation is being considered in this Basic Assessment. project will connect. The Hari PV grid connection infrastructure will connect the authorised Hari PV facility substation to the Geel Kop collector switching station. The Hari PV facility substation and Geel Kop collector switching station have been considered and assessed as part of separate Basic Assessment processes. Feeder bay The project will include the construction and operation of a feeder bay located within associated with the the footprint of the Geel Kop collector switching station. project Power line/s Power line required The project will include the construction and operation of a single circuit power line (up to 132kV) required to connect the facility substation to the Hari PV feeder bay at the Geel Kop collector switching station. Voltage of overhead 33kV or 132kV power line Height of the Power <32m Line Servitude Width Maximum of 31m – 36m. Auxiliary Infrastructure Other Additional Access tracks/roads infrastructure Infrastructure Laydown areas Details of access The grid connection infrastructure for the Hari PV facility will require the roads development of an access road with a width of between 4 and 8 meters to gain access to the Hari PV feeder bay located at the Geel Kop collector switching station. Extent of areas Approximately 1- 2 ha of laydown areas will be required (Laydown areas will not required for laydown exceed 2ha) of materials and equipment Hari PV (Pty) Ltd proposes the construction and operation of a single circuit powerline (up to 132kV in capacity) and associated infrastructure (collectively referred to as “grid connection infrastructure”) required for the connection of the Hari PV facility substation to the Geel Kop collector switching station on the Remaining Extent of the Farm Geel Kop No 456. Associated infrastructure for the grid connection solution will include a feeder bay at the Geel Kop collector switching station, an access road, laydown areas, a fibre and optical ground wire (OPGW) layout, insulation and assembly structures. A grid connection corridor of approximately 300m wide and 3.2 km long is being assessed to allow for the optimisation of the grid connection and associated infrastructure.

View Full Text

Details

  • File Type
    pdf
  • Upload Time
    -
  • Content Languages
    English
  • Upload User
    Anonymous/Not logged-in
  • File Pages
    162 Page
  • File Size
    -

Download

Channel Download Status
Express Download Enable

Copyright

We respect the copyrights and intellectual property rights of all users. All uploaded documents are either original works of the uploader or authorized works of the rightful owners.

  • Not to be reproduced or distributed without explicit permission.
  • Not used for commercial purposes outside of approved use cases.
  • Not used to infringe on the rights of the original creators.
  • If you believe any content infringes your copyright, please contact us immediately.

Support

For help with questions, suggestions, or problems, please contact us