PHX Sky Train Stage 2 at Phoenix Sky Harbor International Airport

PHX Sky Train Stage 2 at Phoenix Sky Harbor International Airport

PROJECT PHX Sky Train Stage 2 at Phoenix Sky Harbor International Airport by Andrew Mish, Modjeski and Masters Inc. The Phoenix Sky Harbor International of this program is the Stage 2 project scheduled in 2022, the extension Airport (PHX) is poised to see a to build a 2.2-mile extension of the will allow the automated train to significant increase in the number Phoenix Sky Train from Terminal 3 to run from the Rental Car Center east of travelers using the facility in the the Rental Car Center. This extension through the airport, with stops at all coming years. According to the City will provide a direct link for passengers existing passenger terminals and a new of Phoenix Aviation Department, 2019 between the airport and the Rental Car passenger drop-off/pickup station, was a record year for PHX, with just Center. The trains will depart every 3 to before terminating at the 44th Street shy of 46.3 million passengers traveling 5 minutes with a travel time of 8 minutes Station, which connects to the Valley through the airport. This was a 5% to and from the terminals, providing a Metro Rail serving Phoenix and other increase over the nearly 44 million significant improvement to the current local communities. passengers using the PHX facility just shuttle bus system, which can require up two years prior, in 2017. to 30 minutes of wait and travel time. Stage 2 Extension Bridges Stage 2 of the Phoenix Sky Train To handle the increasing volume of Construction is ongoing; however, provides two guideways for automated PHX travelers, the City of Phoenix has precast concrete element delivery is trains. The project lengthens the existing undertaken a nearly $2 billion capital complete, with terminal construction tracks by approximately 2.2 miles with investment program to expand and and train testing to run through nearly 7000 ft on guideway bridges. improve airport services. A major part 2021. Upon the project’s completion, The guideway bridges support the Cantilevered ends of pier girder segments with lower corbels are ready for installation of post-tensioning. Photo: Hensel Phelps. PHX SKY TRAIN AT PHOENIX SKY HARBOR INTERNATIONAL profile AIRPORT, STAGE 2 / PHOENIX, ARIZONA BRIDGE DESIGN ENGINEER: Gannett Fleming, Phoenix, Ariz. PRECAST CONCRETE ENGINEER: Modjeski and Masters Inc., Littleton, Colo. PRIME CONTRACTOR: Hensel Phelps, Phoenix, Ariz. TEMPORARY WORKS SUBCONTRACTOR: Pulice Construction, Phoenix, Ariz. PRECASTER: EnCon Arizona LLC, Phoenix, Ariz., dba Tpac—a PCI-certified producer PRECAST CONCRETE FORM SUPPLIER: Helser Industries, Tualatin, Ore. 6 | ASPIRE Summer 2020 automated people mover system, which for demolition over the next year. This the project engaged a design firm that consists of Bombardier Innovia APM 200 unit required special staged construction had expertise with precast, PT concrete vehicles. Live loads used for design were analysis and significant temporary works design and construction to provide provided by the vehicle manufacturer (for details, see the Concrete Bridge precast concrete engineering services. and based on the vehicle configurations Technology article on page 34). The designer, contractor, precaster, that can be used with the system. The and precast concrete engineer met extension also includes two depressed Project Delivery regularly to develop the concepts and sections to carry trains underneath two To speed project delivery from design procedures that would be incorporated future aircraft taxiway bridges. through construction, the owner decided into the final design and construction to use a construction manager at risk process. The elevated guideway bridges include (CMAR) method. With this method, the 80 spans of precast concrete U-girders, owner retains the design team to start All parties invested in the success of which vary in length from 55 to 198 the design process. Once significant the project and shared ideas openly ft. The substructure consists of 5- to progress has been made on the design, throughout the entire design process. 6-ft-deep concrete pier caps on single- typically 30% to 60%, the owner When 60-in.-deep pretensioned or double-column piers founded on initiates a second contract to hire a concrete U-girders were selected as the drilled shafts. The column diameters construction manager. The designer and typical girder system for the skyway range from 5 to 8 ft. All substructure construction manager collaborate as the bridges, the precaster shared the concrete was cast-in-place. design progresses into the final stages. capabilities of its U-girder casting beds The construction manager provides input to ensure that the designs considered The two taxiway bridges are single-span on constructability and can offer insights the girder section and tensioning structures, which vary in length from 33 to the designer that may add value to capacity of the casting facility. All to 35 ft and are composed of precast the project. The CMAR arrangement also girders used straight strand patterns concrete voided rectangular box girders. allows for earlier starts to construction of 0.6-in.-diameter strands, with up to The project also includes a facilities activities. Once the design is significantly 51 strands per girder. The design used access road bridge constructed using complete, the construction manager a combination of debonding and top precast concrete voided slab girders provides a guaranteed maximum price to strands to control top tensile stresses at with a single span of 42 ft. the owner to construct the project. transfer of the pretensioning force. The 60-in.-deep U-girders varied in length In total, the bridges constructed in Stage The precaster from 55 to 103 ft and were used on 2 used 446 individual precast concrete the pretensioned simple-span portions girders, including two hundred ninety-six selected for the project of the elevated guideway bridges. For 60-in.-deep precast concrete U-girders, engaged a design firm the continuous PT bridge unit, the final twenty-four 78-in.-deep precast concrete design used 78-in.-deep U-girders to U-girders, 118 precast concrete voided that had expertise with achieve the longer spans needed to rectangular box girders, and eight precast precast, PT concrete span across the future taxiway and over concrete voided slabs. The 78-in.-deep the existing Terminal 2 building. Arriving U-girders were used in a continuous, design and construction at this cross section was a collaborative post-tensioned (PT) bridge unit that was to provide precast process among the precaster, precast constructed to span over an existing concrete engineer, contractor, and and active airport terminal building and concrete engineering designer. The precaster needed to a future taxiway. Although the bridge services. modify its existing forms to cast the alignment was curved at some locations, 78-in.-deep sections. Girder weights it was possible to use straight girder Project Team Collaboration were an important consideration for segments to construct the PT bridge unit. One of the key components handling at the precast plant, shipment The terminal building, Terminal 2, was in contributing to the success of the to the jobsite, and crane capacity for use during construction, but it saw its last project was the collaboration of the erection. All parties worked together to flight in February 2020 and is scheduled project team. The precaster selected for achieve the final design solution. CITY OF PHOENIX AVIATION DEPARTMENT, OWNER POST-TENSIONING SUPPLIER: DYWIDAG Systems International, Long Beach, Calif. PROJECT DESCRIPTION: 2.2-mile-long extension of the automated train system, including 6988 ft on guideway bridges, to connect Terminal 3 of the airport to the Rental Car Center. The project included a 676-ft-long five-span, continuous post-tensioned superstructure unit with drop-in girder segments that crosses a future taxiway and a terminal building. STRUCTURAL COMPONENTS: Two hundred ninety-six 60-in.-deep precast, pretensioned concrete U-girders, twenty-four 78-in.-deep precast, post-tensioned concrete U-girders, 118 precast concrete voided rectangular box girders, and eight precast concrete voided slabs; cast-in-place concrete composite deck slab; cast-in-place concrete pier caps on single- or double-column piers founded on drilled shafts PHX SKY TRAIN TOTAL PROJECT BUDGET: $745 million ASPIRE Summer 2020 | 7 Approx. Limits of Five-Span PT Unit Approx. Location of Future Drop-In Span Taxiway Terminal 2 Aerial view of the completed PHX Sky Train guideway structure, including the five-span continuous PT unit, drop-in span, and other major features. Photo: Tpac. Site Conditions and Beyond the challenge of the existing team members, 78-in.-deep U-girders Construction Challenges conditions, the design of this bridge were chosen to accomplish the design Constructing more than 2 miles of unit also had to span a future aircraft objectives for this unit. guideway track through an existing taxiway. The design for the taxiway airport presented numerous challenges. required a 162-ft-wide, 40-ft-tall Precast Concrete Buried utilities had to be avoided, obstacle-free area to accommodate Engineering and Staged relocated, or carried by the new the aircraft clearance envelope. A span Construction structures. Pier locations were constrained of 198 ft was required over the future For the challenging bridge unit at by underground utilities and clearance taxiway, and a span of 163 ft was Terminal 2, the precaster, precast to existing building structures, and an required to accommodate the crossing concrete engineer, and engineer of access road running under the terminal of the existing terminal building. record for the project worked together walkway further restricted site access These requirements exceeded the to deliver a girder section that could and limited crane placement, falsework simple-span capabilities of the 60-in.- be cast with only minor modifications locations, and girder delivery. Aircraft deep U-girders used for most of the to the precaster’s existing U-girder taxiways needed to be accommodated, other guideway bridges.

View Full Text

Details

  • File Type
    pdf
  • Upload Time
    -
  • Content Languages
    English
  • Upload User
    Anonymous/Not logged-in
  • File Pages
    4 Page
  • File Size
    -

Download

Channel Download Status
Express Download Enable

Copyright

We respect the copyrights and intellectual property rights of all users. All uploaded documents are either original works of the uploader or authorized works of the rightful owners.

  • Not to be reproduced or distributed without explicit permission.
  • Not used for commercial purposes outside of approved use cases.
  • Not used to infringe on the rights of the original creators.
  • If you believe any content infringes your copyright, please contact us immediately.

Support

For help with questions, suggestions, or problems, please contact us