LOROL – Who Are We

LOROL – Who Are We

Transforming the Overground LOROL – Who Are We A LOROL Perspective A joint venture between DB Regio and MTR of Hong Kong Awarded a 7 year concession to run the Overground network from November 2007. Last Thursday we were three! A concession – similar to a DfT franchise except that TfL take the majority of the revenue and many of the of the outputs are more tightly specified. For us ‘Opening New Railways’ means: The East London Line Plus a transformed North London Railway (described back in 2006 as London’s forgotten railway) We will transform our railway, connecting communities across London The Overground TfL Objectives / Our Contracted Obligations Step change in passenger experience Full integration into the TfL network Significant station upgrades Improved train service performance Successful commissioning of the East London Line Introduction of new trains More trains, increased ridership and revenue 2012 Olympics So How are we doing 3 years on? East London Line Oyster pay as you go and full station staffing from day 1 Opened 27 April 2010 More trains on time and increased off peak services The East London Line – up and running New stations at Imperial Wharf and Shepherds Bush New platforms at Stratford Station refurbishment programme on site at the majority of stations. 6 stations complete to date All eligible stations are DfT ‘Secure Stations’. A team of Travel Safe Officers covering afternoons and evenings Youngest fleet in the country TfL procured class 378s LOROL procured class 172s 4 car trains on the Euston - Watford line & NLL / WLL East London Line continued East London Line continued With a fleet of new trains, eight new stations and six miles of new railway... 300 new staff to the rail industry and a new control centre at New Cross Gate East London Line …One of the Best Performing Railways in the Country Opened 4 weeks early East London Line PPM 100% 98.87% 100% 98.17% 98.09% 132 new drivers Period PPM 97.25% YTD 95.20% 94.61% 80 new members of stations staff 93.27% 96.34% 8 new stations – maintenance and cleaning arrangements to keep 90% 90% them pristine New Control at New Cross Gate 80% 80% % M P Over the first 6 months an average of 96.34% arrived with 5 minutes P – one of the best performing railways in the country! 70% 70% 85% of passengers ‘satisfied or very satisfied’ 20,000 use the route each day and growing fast 60% 60% 50% 50% 2009/10 P8 2009/10 P9 2009/10 P10 2009/10 P11 2009/10 P12 2009/10 P13 2010/11 P1 2010/11 P2 2010/11 P3 2010/11 P4 2010/11 P5 2010/11 P6 2010/11 P7 Rail Pe r iod New Trains – Transforming the Fleet Overground train service performance th PPM 91.065 (MAA) at start of Concession to 94.215 (MAA – Oct 10). From 8 to A new fleet of 8 x class 172 trains on the Gospel Oak to Barking Line 5th in the national league table All units in service from October 2010 New trains continued – 51 x 378s Procured by TfL 4 Car Trains – On the DC, WLL and NLL The new class 378s with open ‘tube-style’ interiors A 33% increase in Capacity. Over half of NLL services are now 4 car Replacing 35 year old class 313 trains Transforming the Stations Transforming the Stations Refurbishment of 44 inherited stations in progress. 6 complete, with the …to this, the same station transformed by LOROL’s refurbishment work programme due to finish in Spring of next Year Headstone Lane station before LOROL took over From this… Still to Come And to Finish – Some Statistics East London Line extension through to Highbury (8 trains an hour 835 trains each day will go through to provide direct interchange with the NLL from 4% of all national rail services on just 0.6% of the national network Spring 2011) Average age of the fleet – less than a year Higher frequency NLL and WLL with 8 trains per hour between The most modern fleet in the country Willesden and Stratford in the peaks (May 2011) Passenger journeys up 60% in a year 4 trains per hour all day on the WLL (May 2011) 52 million passenger journey a year 4 trains per hour all day service on the Gospel Oak to Barking Line (January 2011) A workforce of 1200 – doubled in 3 years Olympics Ticketless travel at around 3% Customer satisfaction up 7% in a year (TfL CSS survey) “We will transform our railway connecting communities across London” “We will transform our railway connecting communities across London”.

View Full Text

Details

  • File Type
    pdf
  • Upload Time
    -
  • Content Languages
    English
  • Upload User
    Anonymous/Not logged-in
  • File Pages
    3 Page
  • File Size
    -

Download

Channel Download Status
Express Download Enable

Copyright

We respect the copyrights and intellectual property rights of all users. All uploaded documents are either original works of the uploader or authorized works of the rightful owners.

  • Not to be reproduced or distributed without explicit permission.
  • Not used for commercial purposes outside of approved use cases.
  • Not used to infringe on the rights of the original creators.
  • If you believe any content infringes your copyright, please contact us immediately.

Support

For help with questions, suggestions, or problems, please contact us