Pine Creek Fish Passage Conceptual Engineering Design January 31, 2007 Prepared for: Yakama Nation Harbor Consulting Engineers Engineers ● Planners ● Surveyors HARBOR CONSULTING ENGINEERS, INC. January 31, 2007 Yakama Nation Fisheries Division P.O. Box 151 Toppenish, WA 98948 Attention: Mr. Gregory Morris Regarding: Pine Creek Fish Passage Conceptual Engineering Design Dear Mr. Morris: Harbor Consulting Engineers is pleased to submit our Pine Creek Fish Passage Conceptual Engineering Design report. Included in the report are conceptual design drawings illustrating the proposed design alternatives. In addition, preliminary construction cost estimates for the alternatives have been included. Harbor Consulting Engineers has completed a preliminary evaluation of the feasibility of restoring fish passage to native habitat in Pine Creek. The existing site conditions and flow regime at Pine Creek have created unique challenges for the design alternatives. Several alternatives were considered and are discussed in the report; however, the most feasible alternative appears to be a combination of a concrete fish ladder and a fishway culvert. This alternative appears to provide the best potential for fish passage at the least cost. It was discovered that Pine Creek is on the Washington State Department of Transportation (WSDOT) inventory of Fish Passage Barriers. The restoration project is currently in the Engineering Scoping phase and inline to receive funding in 2012. At this time no restoration design has been adopted. We have enjoyed the opportunity to work with Yakama Nation on this challenging project, and we look forward to discussions to follow. If there are any questions, please don’t hesitate to contact us. Sincerely, Harbor Consulting Engineers, Inc. John R. Hutchins, P.E., S.E. Principal 3006 Fuhrman Avenue East ▪ Seattle, Washington 98102 ▪ Telephone 206.709.2397 ▪ Facsimile 206.709.2398 Table of Contents Objectives Page 1 Existing Site Conditions Page 1 Existing Hydraulic Conditions Page 3 John Day Dam Pool Page 6 Fish Passage Design Page 8 Conclusions Page 10 List of Figures Figure 1 - Location Map Page 2 Figure 2 - Hydrograph: Rock Creek near Roosevelt, USGS Gauge 1436600 Page 3 Figure 3 - Life History of Anadromous Fish Species Found in WIRA 31 Page 4 Figure 4 - Annual Flow Duration Page 5 Figure 5 - Lake Umatilla Water Surface Elev. for Period of Record Page 7 Figure 6 - Lake Umatilla Water Surface Elev. Jan. 2000 through Jan, 2007 Page 7 List of Tables Table 1 - Miscellaneous Stream Flow Data for Pine Creek near Mouth Page 3 Table 2 - Rock/Pine Creek Drainage Comparison Page 4 Table 3 - John Day Dam Forebay Elevation Statistics 1996-2006 Page 6 Appendices Appendix A - Conceptual Design Drawings: Fishway Alternative Appendix B - Conceptual Design Drawings: Bridge Alternative Appendix C - Preliminary Construction Cost Estimates Appendix D - Photograph Log OBJECTIVES The primary objectives of this report are to identify the current impediments to fish passage at the Washington State Route 14 and Burlington Northern Santa Fee (BNSF) crossings at Pine Creek, approximately 30 nautical miles up-river of John Day Dam, and develop conceptual alternatives to restore access to existing upstream habitat. Our investigation has been divided into two efforts. The first of which involves identifying the current fish passage barrier(s) and investigating the feasibility of restoring partial passage, utilizing existing facilities. The second effort consists of the conceptual design of alternatives to restore full, unimpeded access to upstream habitat. EXISTING SITE CONDITIONS Pine Creek is a small volatile stream with a basin area of approximately 56.8 square miles (36,352 acres). Flowing through Klickitat County in southern Washington State, Pine Creek feeds Lake Umatilla on the Columbia River upstream of the John Day Dam (See Figure 1). The Pine Creek drainage is located in the Wood/Alder Creek subbasin of Water Resource Inventory Area (WRIA) 31 as identified in the Level 1 Watershed Assessment dated November, 2004. For much of its downstream reach, Pine Creek exists as a subsurface channel flowing under an alluvium deposition zone from June through November. At its confluence with the Columbia River, Pine Creek expands to a small riparian pool from which a system of five culverts passes flow under State Route 14 and the BNSF railroad to Lake Umatilla. The system of five culverts consists of three separate culvert arrangements. These culverts were constructed when the highway and railroad were relocated in the 1960’s to accommodate the construction the John Day Dam. The culvert arrangement most utilized is a single 10-foot diameter pipe constructed at original river grade. Currently, the entrance is fully submerged near the middle of the riparian pool. This culvert discharges into Lake Umatilla at a depth of approximately 30 feet at its invert. It is believed that this culvert was originally intended to be a temporary structure to pass expected flows during construction of a permanent culvert; however it is the primary culvert in use today. The second culvert, believed to be the intended permanent structure, is composed of three 10-foot diameter pipes sharing a common concrete entrance headwall located on the east side of the pool. The upstream invert of these culverts is at elevation 268.8, several feet above the pool water surface much of the year. An additional single 10-foot diameter pipe is located on the west side of the pool with an upstream invert elevation of 270.7. The location and orientation of all culverts are shown in Appendix A on Drawings 1 and 2. A large volume of sediment and woody debris has in-filled the previous creek channel nearly 15 feet and obstructed the entrance to the submerged culvert. Only a small opening crossed with woody debris exists to pass stream flows. The constricted culvert entrance has created a barrier to fish passage due to physical obstructions and high water velocities. Attempts were made to locate and inspect the upstream entrance of this culvert to determine its actual invert, location, orientation and extent of the current blockage. These attempts included an underwater inspection by a U.S. Geological Survey (USGS) diver, field survey, and an exploration with an underwater camera lowered from the water surface. Unfortunately, these attempts were unsuccessful at locating the culvert. The approximate location and invert of 1 the culvert were finally determined by performing transects across the pond with a drop line lowered from the water surface. These data were compared with existing and historical topography and the known downstream location of the culvert and appears to be consistent. Project Site Project Location Location Project Figure 1 – Location Map 2 EXISTING HYDRAULIC CONDITIONS Harbor Consulting Engineers has conducted a historical records search and field survey in an attempt to determine the present hydraulic conditions and dominate hydrologic processes at Pine Creek. As no USGS continuous stream flow gauges are or have been installed on Pine Creek, it was difficult to identify actual existing surface water discharge quantities. Several historical records were located and are outlined in Table 1 below, however the dates of these records span up to 50 years with no continuous period of measurement found. Depending on changes in land use and climatic conditions since the time of data collection, these stream flow measurements may not reflect the current flow regime at Pine Creek. Table 1 –Miscellaneous Stream Flow Data for Pine Creek near Mouth Frequency/Type Flow (cfs) Date Source 50-year 2960 1960± USACE Design Memorandum No. 1 60-day low 0.193 8/2/2001 WDFW – SSHEAR Report Spot Measurement 29.4 3/4/1982 USGS (1989) Spot Measurement 18.7 4/19/1982 USGS (1989) Spot Measurement 1.94 5/24/1982 USGS (1989) Significantly more data are available for Rock Creek, hydrologically similar to Pine Creek, located 15 miles to the west. Pine Creek is expected to display a hydrograph similar to that of Rock Creek characterized by steep rising limbs and high ratios of peak to average flows; the result of rapid stream flow response during storm events do to infiltration limited terrain. The hydrograph for Rock Creek near Roosevelt, Washington is shown below in Figure 2 for the USGS period of record dating from 10-01-1962 to 9-30-1968. 10000 Rock Creek near Roosevelt 1000 ) 100 10 Mean Daily Discharge (cfs Discharge Mean Daily 1 0.1 19631964 1965 1966 1967 1968 Water Year Figure 2 – Hydrograph: Rock Creek near Roosevelt, USGS Gauge 14036600 3 During dry summer months, surface water flows in both Pine and Rock Creeks typically recede and become intermittent with flows going subsurface for extended reaches. This is illustrated on the Rock Creek hydrograph as periods of zero flow between water years. The 1965 water year is an exception with minimal surface flow sustained throughout the year. A straight-line comparison of drainage area, average annual precipitation, and basin elevation for the Rock Creek and Pine Creek drainages was used to determine anticipated average annual flows for Pine Creek. The results of this comparison are shown below in Table 2. These values can provide a rough estimate of expected flows for conceptual design; however a more detailed analysis should be completed prior to any further design work. Table 2 – Rock/Pine Creek Drainage Comparison Rock Creek Pine Creek Ratio Basin Area1 258 sq mi 56.8 sq mi 0.22 Average Annual Precipitation1 16.2 in 10.8 in 0.66 Average Basin Elevation1 2162 ft 1904 ft 0.88 Average Annual Flow 46 cfs2 11.5 cfs 0.25 Average Flow: November - April 94 cfs2 23.5 cfs 0.25 Notes: 1 Data from: Level 1 Watershed Assessment (2004) 2 USGS Gauge 14036600 Rock Creek near Roosevelt An annual flow duration curve was created to identify the design flow range for fish passage at Pine Creek.
Details
-
File Typepdf
-
Upload Time-
-
Content LanguagesEnglish
-
Upload UserAnonymous/Not logged-in
-
File Pages34 Page
-
File Size-