Decision 3585-D03-2016 Altalink 2012 and 2013 Deferral Accounts

Decision 3585-D03-2016 Altalink 2012 and 2013 Deferral Accounts

Decision 3585-D03-2016 AltaLink Management Ltd. 2012 and 2013 Deferral Accounts Reconciliation Application June 6, 2016 The Alberta Utilities Commission Decision 3585-D03-2016: AltaLink Management Ltd. 2012 and 2013 Deferral Accounts Reconciliation Application Proceeding 3585 Application 1611090-1 June 6, 2016 Published by The Alberta Utilities Commission Fifth Avenue Place, Fourth Floor, 425 First Street S.W. Calgary, Alberta T2P 3L8 Telephone: 403-592-8845 Fax: 403-592-4406 Website: www.auc.ab.ca Contents 1 Decision .................................................................................................................................. 1 2 Introduction, procedural schedules and motions ............................................................... 2 3 Background to the application and structure of the decision ........................................... 4 4 Direct assign capital deferral account ................................................................................. 8 4.1 Common matters ............................................................................................................ 8 4.1.1 Inclusion of partially completed projects .......................................................... 8 4.1.2 Accuracy and purpose of baseline estimates .................................................. 10 4.1.3 Rate impact to customers ................................................................................ 13 4.1.4 Impact of disallowance ................................................................................... 15 4.1.5 Prudence test and burden of proof .................................................................. 19 4.1.6 Roles and responsibilities of the AESO, TFOs and Commission ................... 24 4.1.7 In-service date targets ..................................................................................... 30 4.1.8 Timing of DACDA and general tariff applications ........................................ 35 4.1.9 Filing requirements ......................................................................................... 39 4.1.10 Cost and performance audits ........................................................................... 51 4.1.11 Project cost escalation and related allowances ............................................... 57 4.1.12 Treatment of contingency allowances ............................................................ 63 4.1.13 Capitalized labour and E&S costs ................................................................... 65 4.1.14 EPCM agreement matters ............................................................................... 68 4.1.14.1 EPCM labour pricing under original SNC-ATP MSA ................. 69 4.1.14.2 EPCM costs and competitive procurement processes .................. 70 4.1.14.3 Risk Reward mechanism............................................................... 79 4.1.14.4 EPCM service provider obligation to provide fixed price ............ 82 4.1.14.5 Enforcement of EPCM contractual obligations ............................ 87 4.1.14.6 EPCM agreement contracted material/contracted labour surcharges ....................................................................................................... 91 4.1.15 Treatment of accruals ...................................................................................... 94 4.1.16 Line optimization and design issues ............................................................... 96 4.1.16.1 Professional practice requirements ............................................... 97 4.1.16.2 Tower selection and tower utilization ......................................... 100 4.1.17 Use of rig mats .............................................................................................. 114 4.1.18 Use of helicopters ......................................................................................... 119 4.1.19 ADC proposal ............................................................................................... 123 4.1.20 Other matters ................................................................................................. 124 4.1.20.1 Customer contributions ............................................................... 124 4.1.20.2 Land compensation ..................................................................... 125 4.2 System projects .......................................................................................................... 127 4.2.1 D.0305 – Cassils to Bowmanton (CB) .......................................................... 127 4.2.1.1 Recovery requested ..................................................................... 127 4.2.1.2 Project overview ......................................................................... 128 4.2.1.3 Key project variances .................................................................. 129 4.2.1.4 In-service date ............................................................................. 130 4.2.1.5 Use of rig mats ............................................................................ 132 4.2.1.6 Use of helicopters ....................................................................... 133 4.2.1.7 Pipeline mitigation ...................................................................... 134 Decision 3585-D03-2016 (June 6, 2016) • i 4.2.1.8 Analysis of change notices .......................................................... 138 4.2.1.9 Summary of findings................................................................... 139 4.2.2 D.0371 – Heartland ....................................................................................... 140 4.2.2.1 Recovery requested ..................................................................... 140 4.2.2.2 Project overview ......................................................................... 140 4.2.2.3 Key project variances .................................................................. 141 4.2.2.4 Inclusion of 2014 costs ............................................................... 143 4.2.2.5 Transmission line design............................................................. 146 4.2.2.6 EDTI charges .............................................................................. 150 4.2.2.7 Use of rig mats ............................................................................ 151 4.2.2.8 Use of helicopters ....................................................................... 151 4.2.2.9 Pipeline mitigation ...................................................................... 152 4.2.2.10 Delays attributed to monopole section ruling ............................. 161 4.2.2.11 12S substation project delays ...................................................... 164 4.2.2.12 Graham construction ................................................................... 167 4.2.2.13 Analysis of change notices .......................................................... 173 4.2.2.14 Land acquisition issues ............................................................... 175 4.2.2.15 Request for cost and performance audit ...................................... 178 4.2.2.16 Summary of findings................................................................... 179 4.2.3 Other major system projects ......................................................................... 180 4.2.3.1 D.0030.01 – Yellowhead Area Transmission Development Hinton- Edson Development .................................................................... 180 4.2.3.1.1 Recovery requested ..................................................................... 180 4.2.3.1.2 Project overview ......................................................................... 181 4.2.3.1.3 Key project variances .................................................................. 182 4.2.3.2 D.0030.03 – Yellowhead Area Transmission Development Cherhill Area Development ........................................................ 184 4.2.3.2.1 Recovery requested ..................................................................... 184 4.2.3.2.2 Project overview ......................................................................... 184 4.2.3.2.3 Key project variances .................................................................. 185 4.2.3.3 D.0108 – SE Development – Brooks Area ................................. 186 4.2.3.3.1 Recovery requested ..................................................................... 186 4.2.3.3.2 Project overview ......................................................................... 187 4.2.3.3.3 Key project variances .................................................................. 188 4.2.3.4 D.0213 – Edmonton Region 240-kV Lines Upgrades ................ 189 4.2.3.4.1 Recovery requested ..................................................................... 189 4.2.3.4.2 Project overview ......................................................................... 189 4.2.3.4.3 Key project variances .................................................................. 190 4.2.3.5 D.0238 – Athabasca Area Telecom Development ...................... 191 4.2.3.5.1 Recovery requested ..................................................................... 191 4.2.3.5.2 Project overview ......................................................................... 192 4.2.3.5.3 Key project variances .................................................................. 193 4.2.3.6 Hanna Region transmission system development projects ......... 194 4.2.3.6.1 D.0353 – Hanna Area Transmission

View Full Text

Details

  • File Type
    pdf
  • Upload Time
    -
  • Content Languages
    English
  • Upload User
    Anonymous/Not logged-in
  • File Pages
    323 Page
  • File Size
    -

Download

Channel Download Status
Express Download Enable

Copyright

We respect the copyrights and intellectual property rights of all users. All uploaded documents are either original works of the uploader or authorized works of the rightful owners.

  • Not to be reproduced or distributed without explicit permission.
  • Not used for commercial purposes outside of approved use cases.
  • Not used to infringe on the rights of the original creators.
  • If you believe any content infringes your copyright, please contact us immediately.

Support

For help with questions, suggestions, or problems, please contact us