Resettlement Corrective Action Plan

Project Number: 49228-002 September 2020

IND: State Highway Investment Program −Tranche 1

Prepared by Public Works Department, Government of Rajasthan for the Asian Development Bank. This document is being disclosed to the public in accordance with the ADB Safeguard Policy Statement.

This corrective action plan is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature.

In order to achieve satisfactory compliance with relevant national and state acts and the loan agreement governing L3534-IND: Rajasthan State Highway Investment Program - Tranche 1, the Public Works Department, Government of Rajasthan (RPWD) will implement the corrective action plan detailed in Table 1 given below. RPWD, through project implementation units, will undertake consultation meetings with affected persons to disclose and explain the corrective action plan. The external monitor will monitor, validate and report on the implementation of the corrective action plan to the project management unit and Asian Development Bank.

Table-1:Corrective Action Plan Balance Action Affected Compensation as on Persons/ paid up to Compensation Target PKG Road Name District Sub-Division 30-06- Remarks CPRs June 2020 paid up to BalanceTill Completion 2020 th th (Nos) (Nos) 19 September 19 (No s) (Nos) 2020 (Nos) 1 2 3 4 5 6 7 8 9 10 11 Titleholders Kanwas-Khanpur-Aklera Jhalawar Khanpur 439 81 358 264 175 Oct-20 (SH-74) Kota Kanwas 54 0 54 8 46 Oct-20 Sub Total= 4931 81 412 272 221 Deoli-Kanwas Road (SH- Kota Kanwas 190 115 75 126 64 Oct-20 74A) Sub Total= 190 115 75 126 64 Package-1 Alot-Gangdhar- Suwansara Road (SH- Jhalawar Gangdhar 62 16 46 16 46 Oct-20 19C) Sub Total= 62 16 46 16 46 Kherli-Pahadi Road (SH- Alwar Kathumar 282 20 8 25 3 Oct-20 22) Bharatpur Nagar 42 22 20 22 20 Oct-20 Sub Total= 70 42 28 47 23 Barmer-Sindhari-Jalore Sayala 24 0 24 0 24 Oct-20 Jalore Package-2 Road (SH-16) Jalore 13 0 13 0 13 Oct-20 Sub Total= 37 0 37 0 37 138 0 138 20 118 Nov-20 -Tarnau- Nagaur 11 11 0 11 0 Completed Deedwana-Mukundgarh Package-3 Deedwana 204 92 112 92 112 Dec-20 Road (SH-8, 19, 60, 82 A, Sikar Laxmangarh 482 84 398 192 290 Dec-20 83) Churu Sujangarh 64 0 64 0 64 Dec-20

1 As per QPR June 2020, there were 522 APs, after revision of award Aps had decreased to 493. 2 As per QPR June 2020, number of APs were 24, at the time of mutation number had increased to 28 . 2

Balance Action Affected Compensation as on Persons/ paid up to Compensation Target PKG Road Name District Sub-Division 30-06- Remarks CPRs June 2020 paid up to BalanceTill Completion 2020 th th (Nos) (Nos) 19 September 19 (No s) (Nos) 2020 (Nos) 1 2 3 4 5 6 7 8 9 10 11 Sub Total= 899 187 712 315 584 Peelibanga-Lakhuwali December Hanumangarh Hanumangarh 13 0 13 0 13 Road (MDR-103) 2020 Sub Total= 13 0 13 0 13 Roopangarh-Naraina Jaipur Dudu 1 0 1 0 1 Oct-20 Road (SH-100) Sub Total= 1 0 1 0 1 Churu Sujangarh 87 0 87 0 87 Dec-20 Sikar-Ganeri- Nagaur Ladnu 541 0 541 141 400 Dec-20 Jaswantgarh Road (SH- Dhod 22 21 1 21 1 Oct-20 20/20A) Sikar Laxmangarh 207 73 134 89 118 Nov-20 Sub Total= 857 94 763 251 606 Singhana-Buhana- Haryana Border Road Jhunjunu Buhana 217 46 171 74 143 Dec-20 (SH-13B) Package-4 Sub Total= 217 46 171 74 143 Payment of 7 TH pending due to Neem Ka title dispute, Ajeetgarh-Chala Road 27 15 12 20 7 Nov-20 Sikar Thana amount already (SH-13) deposited with LAO Khandela 7 7 0 7 0 Completed Sub Total= 34 22 12 27 7 1745 Grand Total 2873 603 2270 1128

Non-Titleholders 6 Structures are saved during civil Package- Kanwas-Khanpur-Aklera Khanpur 255 246 9 246 9 Oct-20 work and 3 Jhalawar 1 (SH-74) structures under Court Case Aklera 3 3 0 3 0 Completed 3

Balance Action Affected Compensation as on Persons/ paid up to Compensation Target PKG Road Name District Sub-Division 30-06- Remarks CPRs June 2020 paid up to BalanceTill Completion 2020 th th (Nos) (Nos) 19 September 19 (No s) (Nos) 2020 (Nos) 1 2 3 4 5 6 7 8 9 10 11 Kota Kanwas 64 64 0 64 0 Completed Sub Total= 322 313 9 313 9 Deoli-Kanwas Road (SH- 1 Structure saved Kota Kanwas 42 41 1 41 1 Completed 74A) during civil work Sub Total= 42 41 1 41 1 Alot-Gangdhar-Suwansara Jhalawar Gangdhar 42 42 0 42 0 Completed Road (SH-19C) Sub Total= 42 42 0 42 0 Pending due to Alwar Kathumar 26 24 2 24 2 Oct-20 Kherli-Pahadi Road (SH- death of owner 22) Nagar 5 5 0 5 0 Completed Bharatpur Pahadi 1 1 0 1 0 Completed Sub Total= 32 30 2 30 2 Sanderao-Bali-Mundara Package- Pali Bali 4 4 0 4 0 Completed Road (SH-16) 2 Sub Total= 4 4 0 4 0 Nagaur 54 0 54 0 54 Nov-20 Ladnu 17 17 0 17 0 Completed Nagaur-Tarnau-Deedwana- Nagaur Jayal 20 20 0 20 0 Completed Mukundgarh Road (SH-8, Deedwana 33 33 0 33 0 Completed 19, 60, 82 A, 83) Sikar Laxmangarh 29 29 0 29 0 Completed Jhunjunu Navalgarh 22 17 5 17 5 Nov-20 Package- Sub Total= 175 116 59 116 59 3 Sanju-Tarnau Road (SH- Nagaur Jayal 21 4 17 17 4 Nov-20 60) Sub Total= 21 17 4 17 4 Roopangarh-Naraina Road Jaipur Dudu 37 36 1 36 1 Oct-20 (SH-100) Sub Total= 37 36 1 36 1 Sikar 4 0 4 0 4 Oct-20 Sikar-Ganeri-Jaswantgarh Sikar Dhod 1 0 1 0 1 Oct-20 Road (SH-20/20A) Package- Nagaur Ladnu 10 0 10 0 10 Oct-20 4 Sub Total= 15 0 15 0 15 Singhana-Buhana-Haryana Jhunjunu Buhana 53 43 10 43 10 Oct-20 Border Road (SH-13B) 4

Balance Action Affected Compensation as on Persons/ paid up to Compensation Target PKG Road Name District Sub-Division 30-06- Remarks CPRs June 2020 paid up to BalanceTill Completion 2020 th th (Nos) (Nos) 19 September 19 (No s) (Nos) 2020 (Nos) 1 2 3 4 5 6 7 8 9 10 11 Sub Total= 53 43 10 43 10 Bidasar-Nokha Road (SH- Churu Bidasar 19 0 19 17 2 Oct-20 20) Bikaner Nokha 1 0 1 0 1 Oct-20 Sub Total= 20 0 20 17 3 Grand Total 763 629 134 659 104 Community Property and Resources Khanpur 21 0 21 17 4 Nov-20 Kanwas-Khanpur-Aklera Jhalawar Aklera 1 0 1 0 1 Nov-20 (SH-74) Kota Kanwas 6 0 6 5 1 Oct-20 Sub Total= 28 0 28 22 6 Bill submitted for Deoli-Kanwas Road (SH- Kota Kanwas 1 0 1 0 1 Oct-20 payment by 74A) Package- Concessionaire Sub Total= 1 0 1 0 1 1 M/s BG(Raj.)HPL, Alot-Gangdhar-Suwansara Jhalawar Gangdhar 11 0 11 5 6 Nov-20 which is under Road (SH-19C) process Sub Total= 11 0 11 5 6 Kherli-Pahadi Road (SH- Alwar Kathumar 5 0 5 3 2 Oct-20 22) Bharatpur Nagar 5 0 5 5 0 Completed Sub Total= 10 0 10 8 2 Barmer 1 0 1 1 0 Completed Barmer Sindhari 6 0 6 2 4 Nov-20 Balance Barmer-Sindhari-Jalore Bill submitted by CPRs Road (SH-16) Concessionaire Jalore Sayala 10 0 10 2 8 saved M/s Dinesh Package- during civil Chandra Tollways 2 work Private Limited for Sub Total= 17 0 17 5 12 payment, which is Sanderao-Bali-Mundara under process Pali Bali 1 0 1 1 0 Completed Road (SH-16) Sub Total= 1 0 1 1 0 1 CPR saved Nagaur-Tarnau-Deedwana- Nagaur 7 0 7 0 7 Nov-20 Package- during civil work Mukundgarh Road (SH-8, Nagaur 3 1 CPR saved 19, 60, 82 A, 83) Ladnu 2 0 2 0 2 Nov-20 during civil work 5

Balance Action Affected Compensation as on Persons/ paid up to Compensation Target PKG Road Name District Sub-Division 30-06- Remarks CPRs June 2020 paid up to BalanceTill Completion 2020 th th (Nos) (Nos) 19 September 19 (No s) (Nos) 2020 (Nos) 1 2 3 4 5 6 7 8 9 10 11 1 CPR saved Jayal 2 1 1 1 1 Completed during civil work Bill not submitted Deedwana 2 0 2 1 1 Oct-20 byConcessionaire for payment All CPRs are Sikar Laxmangarh 3 0 3 0 3 Completed saved during civil work Sub Total= 16 1 15 2 143 Sanju-Tarnau Road (SH- Nagaur 1 CPR saved 4 0 4 1 3 Nov-20 60) Jayal during civil work Sub Total= 4 0 4 1 34 Roopangarh-Naraina Road Jaipur Dudu 1 1 0 1 0 Completed (SH-100) Sub Total= 1 1 0 1 0 Sikar-Ganeri-Jaswantgarh Sikar Sikar 2 0 2 0 2 Nov-20 Road (SH-20/20A) Nagaur Ladnu 1 0 1 0 1 Nov-20 Sub Total= 3 0 3 0 3 Bill not submitted Singhana-Buhana-Haryana Jhunjunu Buhana 5 0 5 3 2 Nov-20 byConcessionaire Package- Border Road (SH-13B) for payment 4 Sub Total= 5 0 5 3 2 Bill submitted for Bidasar-Nokha Road (SH- Churu Bidasar 4 0 4 2 2 Nov-20 payment,which is 20) under process Sub Total= 4 0 4 2 2 Grand Total= 101 2 99 50 515

3 6 CPR has been saved in Nagaur-Tarnau-Deedwana-Mukundgarh Road (SH-19 etc.) thus effective number decreased to 8. 4 1 CPR is saved in Sanju-Tarnau Road (SH-60) thus effective no decreased to 2. 5 7 CPRs are saved during construction thus 44 CPRs have to be constructed.