Draft Initial Environmental Examination

September 2018

IND: Urban Services Improvement Program – Water Supply Improvement in Karahi Padlya, & Rajpur Towns

Package No: MPUSIP-2B

Prepared by Madhya Pradesh Urban Development Company, Government of Madhya Pradesh for the Asian Development Bank.

This initial environmental examination is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature.

In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

CURRENCY EQUIVALENTS (as on 1 Feb 2016) Currency Unit - Conversion INR 1.00 = $ 0.015 $ 1.00 = INR 66.00 Abbreviations

ADB – Asian Development Bank ASO – Assistant Safeguard Officer CFE – Consent for Establishment CFO – Consent for Operation CPCB – Central Pollution Control Board CWS – Clear Water Sump EA – Executing Agency EE – Executive Engineer EHS – Environmental Health &Safety EIA – Environmental Impact Assessment EMP – Environmental Management Plan; GOI – Government of GOMP – Government of Madhya Pradesh HDPE – High Density Poly-ethylene HFL – Highest Flood Level IA – Implementing Agency IEE – Initial Environmental Examination; LPCD – Liters per Capita per Day MFF – Multi-tranche Financing Facility MLD – Million Liters per Day MOEF – Ministry of Environment and Forest MPPCB – Madhya Pradesh Pollution Control Board MPUDC – Madhya Pradesh Urban Development Company NOC – No Objection Certificate OHT – Over Head Tank PMC – Project Management Consultant PHED – Public Health Engineering Department PIU – Project Implementation Unit; PMU – Project Management Unit PO – Project Officer PWD – Public Works Department REA – Rapid Environmental Assessment Checklist RoW – Ri ght of Way SEIAA – State Environmental Impact Assessment SPS – SAauthofeguriatyr d Policy Statement,2009 UDHD – Urban Development & Housing Department UDLB – DepUarrbtmane nLto cal Body WTP – Water Treatment Plant WRD – Water Resources Department WSS – Water Supply Scheme

2

WEIGHTSAND MEASURES

˚C DegreeCelsius km kilometer LPCD Liter per capita per day mm Milli meter m meter MLD Million liter per day MCM Million Cubic Meter Nos Number sq.km Square Kilometer

3

TABLE OF CONTENTS

I. EXECUTIVE SUMMARY ...... 8 II. INTRODUCTION ...... 13 A. Background ...... 13 B. Purpose of this IEE Report ...... 14 C. Report Structure ...... 15 III. DESCRIPTION OF THE PROJECT ...... 16 A. Project Area ...... 16 B. Existing Water Supply Situation ...... 16 C. Proposed Project ...... 18 IV. POLICY, LEGAL AND ADMINISTRATIVE FRAMEWORK ...... 29 A. ADB Policy ...... 29 B. National Environmental Laws ...... 29 V. DESCRIPTION OF THE ENVIRONMENT ...... 33 A. Methodology Used for Baseline Study...... 33 B. Baseline Environmental Profile ...... 33 C. Subproject Site Environmental Features ...... 46 VI. ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES 54 A. Pre-Construction Impacts – Design & Location ...... 54 B. Environmental Audit of Existing Water Treatment Plant ...... 63 C. Construction Impacts ...... 65 D. Operation and Maintenance Impacts ...... 66 E. Project benefits ...... 67 VII. PUBLIC CONSULTATION AND INFORMATION DISCLOSURE ...... 68 A. Overview ...... 68 B. Public Consultation ...... 68 C. Information Disclosure ...... 69 VIII. GRIEVANCE REDRESS MECHANISM ...... 70 A. Project Specific Grievance Redress Mechanism ...... 70 IX. ENVIRONMENTAL MANAGEMENT PLAN ...... 72 A. Implementation Arrangements ...... 72 B. Environmental Management Plan ...... 72 C. EMP Compliance Responsibilities ...... 90 D. Training Needs ...... 92 E. Monitoring and Reporting ...... 93 F. EMP Implementation Cost ...... 94 X. CONCLUSION AND RECOMMENDATIONS ...... 95

4

LIST OF TABLES

Table 1: Proposed Water Supply Subproject Components ...... 19

Table 2: Applicable Environmental Regulations ...... 30

Table 3: WHO Ambient Air& Noise Quality Guidelines ...... 32

Table 4: Baseline Environmental Features of the Subproject Towns ...... 34

Table 5: Site Environmental Features – Karahi Padlya ...... 46

Table 6: Site Environmental Features – Kasrawad ...... 48

Table 7: Site Environmental Features - Pansemal ...... 50

Table 8: Site Environmental Features – Rajpur ...... 51

Table 9: Water Source Selection & Sustainability ...... 56

Table 10: Salient Features of ...... 60

Table 11: Narmada River Water Quality ...... 61

Table 12: Gomai River Water Quality ...... 61

Table 13: Salient Features of Kasrawad WTP ...... 63

Table 14: Compliance with Applicable National and State Regulations ...... 64

Table 15: Design Stage Environmental Management Plan ...... 74

Table 16: Pre-Construction State Environmental Management Plan ...... 75

Table 17: Construction Stage Environmental Management Plan ...... 78

Table 18: Operation Stage Environmental Management Plan ...... 86

Table 19: Construction Stage Environmental Monitoring Plan ...... 87

Table 20: Operation Stage Environmental Monitoring Plan ...... 88

Table 21: Outline Capacity Building Program on EMP Implementation ...... 92

Table 22: Cost Estimates to Implement the EMP ...... 94

5

LIST OF FIGURES

Figure 1: Subproject location ...... 17

Figure 2: Key Plan of Karahi Padlya WSS ...... 22

Figure 3: Details of Intake arrangements of Karahi Padlya WSS ...... 23

Figure 4: Details of Intake arrangements of Kasrawad WSS ...... 23

Figure 5: Keyplan of Kasrawad WSS ...... 24

Figure 6: Key Plan of Rajpur WSS...... 25

Figure 8: layout plan of intake WELL –Pansemal WSS ...... 26

Figure 9: Conceptual process flow diagram of WTP ...... 27

Figure 10: layout plan of WTP ...... 28

Figure 12: Location of ASI excavated site w.r.t. Kasrawad town ...... 42

Figure 13: Site Environ Features of Kasrawad town ...... 43

Figure 14: Site Environ Features of Kari- Padlya town ...... 44

Figure 15: Subproject Environ of Pansemal town ...... 45

6

LIST OF APPENDICES

Appendix 1: REA Checklist ...... 97

Appendix 2: National Ambient Air Quality Standards ...... 112

Appendix 3: Vehicle Exhaust Emission Norms ...... 113

Appendix 4: National Ambient Air Quality Standards in Respect of Noise...... 113

Appendix 5: Extract From Construction & Demolition Management Rules, 2016 ...... 114

Appendix 6: Salient Features of Major Labor Laws Applicable to Establishments Engaged in

Construction of Civil Works ...... 120

Appendix 7: Water Test Reports ...... 122

Appendix 8: Stakeholder consultation ...... 124

Appendix 9: Sample Grievance Registration Form ...... 142

Appendix 10: Sample Outline Traffic Management Plan ...... 144

Appendix 11: Drinking Water Standards ...... 151

Appendix 12: SAMPLE ENVIRONMENTAL SITE INSPECTION REPORT ...... 153

Appendix 13: Quarterly Reporting Format for Assistant Safeguards Officer ...... 155

7

I. EXECUTIVE SUMMARY 1. Government of Madhya Pradesh with loan funding from Asian Development Bank (ADB) has proposed to implement Madhya Pradesh Urban Services Improvement Project (MPUSIP), herein after referred as ‘the Project’. Madhya Pradesh Urban Development Company Limited (MPUDC) shall be the Implementing Agency and the State Urban Development and Housing Department (UDHD) shall be the executing agency for the Project.

2. The Project components are as follows:

(i) Component 1: Improvements to water supply and sewerage services in identified towns ➢ Continuous, pressurized, safe and sustainable drinking water through private household metered connections to 350,000 households with about 1.7million population resident in sixty-four towns in the State of Madhya Pradesh in Central India; and ➢ Sewage and storm water collection and treatment services proposed initially in two (2) identified towns (Khajuraho and Rajnagar) servicing about 42,000 population resident in 8000 households;

(ii) Component 2: Institutional Strengthening ➢ Capacity Building of implementing agencies (IAs), participating Urban Local Bodies (ULBs) and service utilities in contract management and service delivery for ensuring long term sustainability of services; ➢ Setting up of geographic information system (GIS) based water and sanitation asset management and service delivery monitoring; and ➢ Structured behavioral change campaigns to ensure the improvement in public health and cost recovery of service delivery.

(iii) Component 3: Project Management and Administration Support. This component will support the smooth and effective implementation and operation of the Project which includes expert support in Project design and implementation (design, procurement and Contract and Project Management, safeguards etc.), and project administration through Executing and Implementing Agencies.

3. The key outcome envisaged from the project is “effective urban water service delivery model rolled out in selective urban clusters of the State with the objective of achieving the following performance indicators by the year 2022.

4. The Subproject. Pansemal, Rajpur, Karahi Padlya and Kasrawad are located respectively in the districts of and in the western part of Madhya Pradesh state. These are small towns having the status of Municipal Council (Nagar Parishad) and population as per 2011 census was: Karahi Padlya- 10700, Kasrawad- 22750, Pansemal – 12166 and Rajpur- 20947. Improvement of water supply in these four towns will be implemented under a single Design-Build-Operate (DBO) contract package. The objective of the subproject is to achieve safe and sustainable water services both in terms of services to customers, cost recovery, providing 100% coverage with continuous, pressurized and safe drinking water services and achieving progressively increasing cost recovery by expanding the coverage and increasing operating efficiency. The subproject includes the following civil works. a) Karahi Padlya: (i) Intake well on Narmada River, (ii) Water Treatment Plant (WTP) of 1.40 MLD; (iii) One Over Head Tank (OHT) of 200 KL capacity (L): (iv) Raw Water Transmission (v) Distribution network and (vi) consumer connections, and flow meters. b) Kasrawad: (i) Intake well on Narmada River, (ii) Water Treatment Plant (WTP) of 3.12 MLD; (iii) One Over Head Tank (OHT) of 115 KL capacity: (iv) Raw Water

8

Transmission (v) Distribution network and (vi) consumer connections, and flow meters. c) Pansemal: (i) Intake well on Gomai Dam, (ii) Water Treatment Plant (WTP) for 0.95 MLD; (iii) Clear water sump of 21300 Litres (L): (iv) Raw Water Transmission of 360 meters & Clear Water Transmission of 1577 meters; (v) Distribution network (12.05 km), and (vi) consumer connections, and flow meters. d) Rajpur : (i) Intake well on Narmada River, (ii) Water Treatment Plant (WTP) of 1.40 MLD; (iii) Clear water sump (L): (iv) Raw Water Transmission (v) Distribution network and (vi) consumer connections, and flow meters.

3. Screening and assessment of potential impacts. ADB requires the consideration of environmental issues in all aspects of the Bank’s operations, and the requirements for environmental assessment are described in ADB’s Safeguard Policy Statement (SPS), 2009. As per the GoI EIA Notification, 2006, these subprojects do not require EIA study or environmental clearance. The potential environmental impacts of the subproject have been assessed using ADB Rapid Environmental Assessment Checklist for Water Supply. Then potential negative impacts were identified in relation to pre-construction, construction and operation of the improved infrastructure.

4. Categorization. Based on results of the assessment and ADB SPS, the subproject is classified as environmental Category B, i.e., the subproject is judged to be unlikely to have significant adverse environmental impacts. An initial environmental examination (IEE) is required to determine whether significant environmental impacts warranting an environmental impact assessment are likely.

5. Aim of this IEE is to (i) provide critical facts, significant findings, and recommended actions; (ii) present the national and local legal and institutional framework within which the environmental assessment has been carried out; (iii) provide information on existing geographic, ecological, social and temporal context including associated facilities within the subproject’s area of influence; (iv) assess the subproject’s likely positive and negative direct and indirect impacts to physical, biological, socioeconomic and physical cultural resources in the subproject’s area of influence; (v) identify mitigation measures and any residual negative impacts that cannot be mitigated; (vi) describe the process undertaken during project design to engage stakeholders and the planned information disclosure measures and the process for carrying out consultation with affected people and facilitating their participation during project implementation; (vii) describe the subproject’s grievance redress mechanism for resolving complaints about environmental performance; (viii) present the set of mitigation measures to be undertaken to avoid, reduce, mitigate, or compensate for adverse environmental impacts; (ix) to describe the monitoring measures and reporting procedures to ensure early detection of conditions that necessitate particular mitigation measures; and (x) identify indicative costs and who is responsible for carrying out the mitigation and monitoring measures.

6. Description of the Environment. The subproject includes the locations of Pansemal, Rajpur, Karahi Padlya and Kasrawad towns and their surroundings. In all the four towns intake wells will be proposed on river/reservoir banks on government lands, while the WTPs including clear water sumps are proposed close to the intake wells with sufficient government land. These components of the scheme are proposed away from the town and are mostly surrounded by agricultural lands and rivers/reservoirs. None of the components however proposed on any forest land. Other components like – Over head tanks, distribution pipeline network, domestic connections etc., are proposed within the limit of Municipal Boundary of the

9 town. The raw water transmission mains which are connecting intake well to WTP will be laid outside the town and clear water transmission mains from WTP to Over head tanks will be partly outside and partly within the Municipality limit. Project area experience a subtropical climate, typical to north India, hot summers, cold and dry winters and monsoon rains. While there is no natural habitat left within the town areas, the areas near river intake wells are comparatively intact though most of the lands there too converted into agricultural use. There are no protected areas, like wildlife sanctuaries, national parks, nor there did any historically, archeologically protect areas in the vicinity. Towns are densely populated in the core/old town areas with narrow lanes mostly covering the residential areas with small and closely built houses, while other expanding areas of the towns are having broad lanes and sufficient spaces. Commercial areas are along the main roads with broad lanes having running traffic for most of the time.

7. Potential environmental impacts. The subproject area will not arise any significant adverse impacts due to: (i) small size population and their water demand, (ii) components proposed in the schemes are of comparatively is of small quantities & their effect will be locally which is manageable and controllable and (iii) predicted impacts are site-specific and likely to be associated with the construction process and are produced because the process is invasive, involving excavation and earth movements.

8. Environmental impacts arise due to the project design or because of the locations chosen for the project components are not significant. The proposed water supply schemes include design of new water source which is the nearest surface water body, that include construction of intake well in water body. From the river Discharge Gauge analysis it is observed that minimum volume in Narmada River in last 10 years was 3937 MCM while the combine estimated requirement of the three towns (i.e Kasrawad, Rajpur and Karahi padlya) for the ultimate design year (2048) is only 2.77 MCM, which is only 0.0007%. Hence the Narmada River is adopted as sustainable water source for the proposed water supply schemes. For Pansemal WSS Gomai Dam is proposed water source whose dead storage capacity is 3 MCM, whereas highest tank level capacity is 6 MCM. The ultimate year water requirement of the town is only 0.34 MCM which is just 5% of HTL. Water quality is good and there are no potential pollution sources in the vicinity that could affect the water quality.

9. By the time of execution phase, potential negative impacts may arise from disturbance of residents, businesses, increase in traffic, increase in noise level and dusts and the need to dispose moderate quantities of waste soil during construction phase and generation of sludge from the WTP during operation and maintenance phase. However, there are well-developed methods for mitigation, minimization to acceptable levels are proposed here.

10. Environmental Management Plan As a part of mitigate measures in order to achieve acceptable levels in the negative impacts, an environmental management plan (EMP) has been proposed. All the locations are selected considering the minimum adverse environmental affects. These include (i) locating facilities on government-owned land to avoid the need for land acquisition and relocation of people; and (ii) laying of pipes in RoW alongside main/access roads, to reduce acquisition of land and impacts on livelihoods specifically in densely populated areas of the town.

11. The EMP given here includes the design measures for (i) safe disposal of sludge coming out of wash water tanks from WTP to reduce effluent (iii) energy efficient pumping equipment and (iv) quick leak detection and rectification to save the resources, etc. During execution phase, the EMP includes mitigation measures such as (i) implementation of traffic management plan in coordination with local traffic police to minimize traffic impacts (ii) 10 awareness campaigns and consultations to inform residents and businesses of potential disturbances; (iii) provision of walkways and planks over trenches to ensure access will not be impeded; (iv) use of noise-dampening measures in areas with sensitive receptors such as hospitals, schools, places of worships and other silence-zones; (v) use of dust-suppression methods such as watering and/or covering of stockpiles; and (vi) finding beneficial use of excavated materials to extent possible to reduce the quantity that will be disposed off. As for the O&M phase, facilities will need to be repaired from time to time, but environmental impacts will be much less than those of the construction period as the work will be infrequent, affecting small areas only. The design of the WTP includes dewatering and drying areas as part of sludge management. The EMP includes mitigation measures and monitoring plan to ensure compliance to environmental standards during O&M phase.

12. The EMP will guide the environmentally-sound construction of the subproject and ensure efficient lines of communication between Madhya Pradesh Urban Development Company (MPUDC), project management unit (PMU), project implementing unit (PIU), consultants and contractors. The EMP will (i) ensure that the activities are undertaken in a responsible non-detrimental manner; (i) provide a pro-active, feasible and practical working tool to enable the measurement and monitoring of environmental performance on site; (ii) guide and control the implementation of findings and recommendations of the environmental assessment conducted for the subproject; (iii) detail specific actions deemed necessary to assist in mitigating the environmental impact of the subproject; and (iv) ensure that safety recommendations are complied with. The EMP includes a monitoring program to measure the environmental condition and effectiveness of implementation of the mitigation measures.It will include observations on- and off-site, document checks, and interviews with workers and beneficiaries.

13. The contractor will be required to submit to PMU, for review and approval, a site environmental plan (SEP) including (i) proposed sites/locations for construction work camps, storage areas, hauling roads, lay down areas, disposal areas for solid and hazardous wastes; (ii) specific mitigation measures following the approved EMP; (iii) monitoring program as per SEP; and (iv) budget for SEP implementation. No works are allowed to commence prior to approval of SEP. A copy of the EMP/approved SEP will be kept on site during the construction period at all times. The EMP included in the bid and contract documents. Non-compliance with, or any deviation from, the conditions set out in this document constitutes a failure in compliance.

14. Consultation, disclosure and grievance redress mechanism. The stakeholders were involved in developing the IEE through discussions on-site and public consultation at several places in the town, after which views expressed were incorporated into the IEE and in the planning and development of the project. The IEE will be made available at public locations and will be disclosed to a wider audience via the ADB, MPUDC and PMU websites. The consultation process will be continued and expanded during project implementation to ensure that stakeholders are fully engaged in the project and have the opportunity to participate in its development and implementation. A grievance redress mechanism is described within the IEE to ensure any public grievances are addressed quickly.

15. Implementation Arrangements. Urban Development and Housing Department (UDHD) of Government of Madhya Pradesh is the Executing Agency and Madhya Pradesh Urban Development Company (MPUDC) is the Implementing Agency. Project Management Unit (PMU) attached to MPUDC is responsible for implementation, and will be supported by Program Implementation Units (PIUs). Several teams of Design Consultants, and a Program Management Consultant (PMC),will support PMU & PIUs. Infrastructure will be designed, built, and operated by DBO contractor for 10 years, after which it will be transferred to ULBs. Project Officer (Environment) at PMU and Assistant Safeguard Officer (ASO) at each of the PIU will be responsible for environment safeguards tasks, and will be supported by PMC. Contractor personnel will include an Environment, Health and Safety (EHS) supervisor.

11

16. Monitoring and Reporting. The PMU and PMC will be responsible for monitoring. The PMDC will submit quarterly and semi-annual monitoring reports to PMU, and the PMU will review and send the semi-annual monitoring reports to ADB. ADB will post the environmental monitoring reports on its website.

17. Conclusions and Recommendations. The subproject is therefore unlikely to cause significant adverse impacts. The potential impacts that are associated with design, construction and operation can be mitigated to standard levels without difficulty through proper engineering design and the incorporation or application of recommended mitigation measures and procedures. Based on the findings of the IEE, there are no significant impacts and the classification of the project as Category “B” is confirmed. No further special study or detailed environmental impact assessment (EIA) needs to be undertaken to comply with ADB SPS (2009) or GoI EIA Notification (2006). Project will require permission of Water Resources Department (WRD) for water abstraction, intake construction, and consent of Madhya Pradesh Pollution Control Board (MPPCB) for WTPs. These permissions/approvals shall be obtained prior to award of contracts.

18. This IEE will be updated during the detailed design stage by the DBO contractor to reflect any changes, amendments and will be reviewed and approved by PMU.

12

II. INTRODUCTION A. Background 1. Government of Madhya Pradesh with loan funding from Asian Development Bank (ADB) has proposed to implement Madhya Pradesh Urban Services Improvement Project (MPUSIP), herein after referred as ‘the Project’. Madhya Pradesh Urban Development Company Limited (MPUDC) shall be the Implementing Agency and the State Urban Development and Housing Department (UDHD) shall be the executing agency for the Project.

2. The Project components are as follows:

(i) Component 1: Improvements to water supply and sewerage services in identified towns B. Continuous, pressurized, safe and sustainable drinking water through private household metered connections to 350,000 households with about 1.7million population resident in sixty-four towns in the State of Madhya Pradesh in Central India; and C. Sewage and storm water collection and treatment services proposed initially in two (2) identified towns (Khajuraho and Rajnagar) servicing about 42,000 population resident in 8000 households;

(ii) Component 2: Institutional Strengthening D. Capacity Building of implementing agencies (IAs), participating Urban Local Bodies (ULBs) and service utilities in contract management and service delivery for ensuring long term sustainability of services; E. Setting up of geographic information system (GIS) based water and sanitation asset management and service delivery monitoring; and F. Structured behavioral change campaigns to ensure the improvement in public health and cost recovery of service delivery.

(iii) Component 3: Project Management and Administration Support. This component will support the smooth and effective implementation and operation of the Project which includes expert support in Project design and implementation (design, procurement and Contract and Project Management, safeguards etc.), and project administration through Executing and Implementing Agencies.

3. The key outcome envisaged from the project is “effective urban water service delivery model rolled out in selective urban clusters of the State with the objective of achieving the following performance indicators by the year 2022.

(i) Access to piped water supply coverage increased to 95% of the households from 33% in 2015 in 64 towns; (ii) Women's drudgery for fetching water reduced by 80% (from spending an average of 55 minutes in 2015 to 10 minutes); (iii) Coverage of households with access to improved sanitation systems increased to 80% from 30% in 2015; (iv) Wastewater collection and/or safe sanitation service coverage increased to at least 80% of the households from 0% in 2015 in two towns; (v) Incidence of water logging/flooding reduced to two incidents per annum in four towns; and (vi) Women access to functioning sanitation systems increased to 95% from 25% in 2015 (in poor settlements) in four towns

4. The key outputs envisaged from the project are:

13

(i) Output 1: Water supply infrastructure improved in 64 project towns and flood and sanitation infrastructure improved in two project towns with the following measurable indicators: ➢ Improved water supply capacity of 186ml/day installed in 64 towns; ➢ 4,000 km water supply networks installed in 64 towns; ➢ 350,000 households provided with metered house connections including 100 government schools; ➢ 8 MLD sewage or septage treatment plants constructed; and ➢ Installation of 120 km sewer and drainage mains and networks.

(ii) Output 2: Sustained urban infrastructure operation and management

➢ 23 performance-based contract (PBC) operation and maintenance (O&M) water supply contracts for 64 ULBs signed and operated; ➢ ULBs institute volumetric water charges for recovery of water service O&M costs ➢ ULBs’ water tariff collection ratio improved to 90% from 50% in 2014 based on the water meters’ readings ➢ 100% operating cost recovery (excluding debt service) achieved; ➢ GIS system established for effective O&M of water services

5. The subproject towns of Pansemal, Rajpur, Karahi-Padliya and Kasrawad area located in the western part of Madhya Pradesh state, and improvement of water supply in these four towns is one of the subprojects proposed under MPUSIP. The objective of the subproject is to achieve safe and sustainable water services both in terms of services to customers, cost recovery and conservation of precious water resources. The subproject envisages providing 100% coverage of population with continuous, pressurized and safe drinking water services and achieving progressively increasing cost recovery by expanding the coverage and increasing operating efficiency. The subproject includes civil works (Intake well, WTP, raw and clear water transmission, overhead tanks, distribution network, consumer connections and flow meters), project implementation and management, and non-physical investments. A detailed description of the components is provided in Section III.

A. Purpose of this IEE Report

6. ADB requires the consideration of environmental issues in all aspects of the Bank’s operations, and the requirements for environmental assessment are described in ADB’s Safeguard Policy Statement (SPS), 2009. The potential environmental impacts of the subproject have been assessed using ADB Rapid Environmental Assessment Checklist for Water Supply (Appendix 1). Then potential negative impacts were identified in relation to pre- construction, construction and operation of the improved infrastructure, and results of the assessment show that the subproject is unlikely to cause significant adverse impacts. Thus, this initial environmental examination (IEE) has been prepared in accordance with ADB SPS’s requirements for environment category B projects

7. To understand the environment-related aspects of the project, a detailed Environmental Analysis and Assessment study is required. The study will involve collection and analysis of information regarding the environmental issues related to the project and preparation of an Initial Environmental Examination (IEE) and Environmental Management Plan (EMP), to be duly integrated in the overall design of the project. The IEE study is expected to focus on the positive health and environmental benefits, through supply of safe drinking water and creation of integrated sanitary conditions in the project area/region. The proposed assessment study will suggest several environmental mitigation measures to be included in the project design, due to which the project is expected to have a net positive benefit for the people in the project area.

14

B. Report Structure 8. This Report contains the following nine (9) sections: (i) Executive summary; (ii) Introduction (iii) Description of the project (iv) Policy, legal and administrative framework (v) Description of the environment; (vi) Anticipated environmental impacts and mitigation measures; (vii) Public consultation and information disclosure; (viii) Grievance redress mechanism; (ix) Environmental management plan, and (x) Conclusion and recommendation

15

III. DESCRIPTION OF THE PROJECT A. Project Area 9. Project area comprises the urban areas and surroundings of Pansemal, Rajpur, Karahi Padlya & Kasrawad situated respectively in districts of Barwani & Khargone in western part of Madhya Pradesh state. Towns are located in adjoining district, and in a distance range of about 120-140 km from each other. As per the census 2011, , Karahi Padlya had a population of 10,035 and area 3.00 sq. Km, Kasrawad 22,750 and area 3.88 sq. km, Pansemal 12,166 area 6.14 sq.km and Rajpur 20,947 and area 9.00 sq. km.

10. Subproject components are located within the urban and surroundings. While intake well and WTPs are located outside the towns, all other components are located within the towns.

B. Existing Water Supply Situation 1. Karahi Padliya 11. Water supply system in Karhi is dependent on surface source (Gagan Talab) and ground water source in the form of tube wells. There is absence of dedicated water supply scheme as on today. The water is being supplied to the town, after preliminary treatment of chlorination. There are 2 nos. tube well, 2 nos. dug wells and three OHTs in Karhi. Condition of two overhead tanks are structurally good. Rest one overhead tank of 40 KL has damaged. Total water supply in the town is 0.50 MLD at the rate of 36 LPCD after transmission losses 20%. The supply is alternate day. There is an existing clear water pipe line of 160 mm dia. PVC pipe. The existing distribution systems (consists of GI and PVC pipes) cover the 40% town, while the rest of the town is dependent on hand pumps and mobile tankers.

2. Kasarawad 12. The water is being supplied to the town, after preliminary treatment of chlorination. There are 2 nos. tube well 2 nos. dug wells and three over head tanks in Karhi. Condition of two overhead tanks are structurally good. Rest one overhead tank of 40 KL has damaged. As a ground sources the town have 14 hand pumps and 3 tube wells with motor and pumps for drinking and non- drinking purposes. For storage system, there is 1 RCC over head tank in ward no. 14 having capacity of 4.5 Lac Lit. There is also 2 nos. of GSR one new and one old having new GSR capacity 800 KL and old GSR 300 KL. There is an existing raw water line 4000 m long dia. 200 mm CI pipe from Narmada river to Exiting water treatment plant. For treatment of raw water there is a WTP of capacity of 3.12 MLD on Nava todi raod. It is 15 years old and is in good condition. this WTP is taken into account for new system and it is sufficient for Kasrawad Nagar Parishad. Distribution system consists of GI, CI and PVC pipes. The duration and frequency of water supply is twenty minute on alternate day. Kasrawad Nagar Parishad has divided into 15 wards. The per capita supply of water is 35.52 lpcd at alternate day.

3. Pansemal

13. Presently 19 tube wells with power pumps are the main source of water supply in Pansemal. In addition there are 4 hand pumps. Overall 530 KL water is supplied daily in one hour through distribution networks. There are 2 over head tanks, one is 450 KL and other is 90 KL capacity. There is 135 public stand post and 1153 private connections. Almost all 15 wards are covered with water supply system. For the present population rate of supply is 40 lpcd which is much below the prescribed norm 70 lpcd. The existing supply 0.53 mld will be maintained up to ultimate stage with their pumping mains and tube wells.

14. As informed by the Pansemal Municipal authority, the existing distribution net work comprises of GI, MS and PVC. The details are not available. These pipes were laid from time 16 to time as and where required. These pipes may have been rusted being GI and MS and more than 35 years old. Therefore, these are not considered for laying new distribution system.

15. Overall, the current water supply systems in all the four facing similar issues predominantly resulting from receding groundwater sources, low coverage and unreliable supply, inadequate infrastructure and heavy water losses.

4. Rajpur 16. Presently the main sources for supplying drinking water in the town are the Narmada river and Narrula Talab. The tube wells are located in the various parts of the town. There are 5 tube wells which are used to supply water to the population. Apart from these there are 5 Hand pumps which are also located in various parts of the town. The per capita water supply per day is 35 LPCD (alternate days). There is 1.0 MLD capacity WTP at Narmada River. From Narmada River raw water is pumped through 200 mm dia. of DI pipe line. It is around 12 years old. From Narrula pond 200 mm dia of CI pipeline is used to bring the water. It is very old pipeline. Pipe line from Narrula Pond source has damaged at several places. There is an existing raw water line 6000 m long dia. 200 mm DI & 500 m CI pipe from Narmada river and Narrula pond to Exiting water treatment plant. Pipeline from Narmada River to existing WTP 6553 m long is in good condition and it will be used. For treatment of raw water there is a WTP of capacity of 1.00 MLD. According to design of WTP for intermediate year it comes 2.48 MLD and there is only 1.00 MLD capacity of WTP, hence there is proposed an additional WTP of 1.50 MLD capacity near existing WTP. Distribution system consists of 300 mm to 150 mm GI, CI, PVC, AC Pipes.

Figure 1: Subproject location

17

Karahi Padliya Rajpur

Kasrawad

Pansemal

C. Proposed Project 17. As the water table is depleting all over, therefore, now it is not a reliable source for a permanent scheme in all the four towns. As part of this project, it is proposed to develop comprehensive water supply schemes in each of the four project towns. Proposals include new reliable water sources, water treatment plants, over head tanks, energy efficient pumping machinery, raw & clear water transmission mains and distribution network covering the whole town. Project will also provide consumer connections with flow meters. Bulk flow meters are proposed at strategic locations to monitor the system performance efficiency.

18. Following Table 1 shows the proposed water supply systems along with nature and size of components in four subproject towns. Figure 2 to Figure 11 show the proposed water systems, component layouts etc.

19. Project benefits. The subproject aims to achieve safe and sustainable water services both in terms of services to customers, cost recovery and conservation of precious water resources. The subproject will provide continuous, pressurized and safe drinking water services to entire population of the towns (100% coverage). Besides achieving progressively increasing cost recovery by expanding the coverage and increasing operating efficiency, the subproject will improve the overall environmental quality of the town. It will reduce the reduced time and costs of households in accessing alternative sources of water, and will lead to better public health particularly reduction in waterborne and infectious diseases.

20. After the approval of the detailed project report, bid will be prepared and tenders are likely to be invited by June 2016, and the contract will be awarded by December 2016. Construction is likely to start in April 2017, and will take about 24 months.

18

Table 1: Proposed Water Supply Subproject Components

Particulars Karahi Padliya Kasrawad Pansemal Rajpur I. Water demand 1 Current year 0.92 MLD 2.06 MLD 0.56 MLD 1.86 MLD (2016) 2 Base year 1.24 MLD 2.67 MLD 0.62 MLD 2.28 MLD (2018) 3 Design year 1.58 MLD 3.33 MLD 0.95 MLD 2.70 MLD (2033) II. Source 1 Alternatives 1. Narmada river 1. Narmada river 1. Ground Water 2. Gomai Dam 1. Narmada river 2 Selected Narmada river Narmada river Gomai Dam Narmada river source Intake well in the river on the Intake well in the river on the right Intake well in the dam on the Intake well in the dam on the right bank. bank. right bank. right bank. River flows in the north-east side of the town. III. Proposed system 1 From source to Raw water abstraction from Raw water abstraction from Narmada Raw water abstraction from Raw water abstraction from consumer Narmada river → raw water river → raw water transmission Gomai river → raw water Narmada river → raw water supply transmission (pumping) → (pumping) → treatment → clear transmission (pumping) → transmission (pumping) → treatment → clear water water transmission (pumping) → treatment → clear water treatment → clear water transmission (pumping) → storage → distribution → house transmission (pumping) → transmission (pumping) → storage → distribution → house connections with meters storage → distribution → house storage → distribution → house connections with meters connections with meters connections with meters IV. Proposed components 1 Water intake Intake well (Circular Dia. 6.0 m, Intake well: Circular Dia. 6.0 m, Intake well (5m dia, 18m deep in Intake Well: Circular Dia. 6.0 m, Height – 20.0 m) Height 21.0 m [Pump Floor Level RCC) Height 24.0 m [Pump Floor Level (153.50 m) – Pump suction (139.20 m) – Pump suction

Location: Karahi padliya town is Level(132.50 m)] Level(115.36 m)] Location:. Intake on the Dam located north of the river. Water Location: Kasrawad town is situated Location: On the bank of river (WRD Land) will be abstracted from the left just 5 km from Narmada river. Water Narmada at village datwada bank side of river at village will be abstracted from the right bank () Bahegaon. side of river

2 Pumping Raw water pumping station at Raw water pumping station at intake Raw water pumping station at Raw water pumping station at

Particulars Karahi Padliya Kasrawad Pansemal Rajpur stations intake near Narmada River near Narmada River intake near Gomai dam intake near Narmada River. Two nos. vertical turbine type Two nos. vertical turbine type pump Raw water Pump: Two nos. vertical turbine type pump with 100% as standby is with 100% as standby is proposed. Type of pump …Water pump with 100% as standby is proposed. The discharge of each The discharge of each pump is 33.71 lubricated turbine pumps proposed. The discharge of each pump is 15.66 LPS and head is LPS and head is 49.60 meter. The Number of pumps … 2 Nos pump is 28.79 LPS and head is 155.97 meter. The rating of each rating of each pump is 23.76 KW. Capacity of each pump … 11.99 99.58 meter. The rating of each pump is 40.73 KW. pump is 34.70 KW. Provision of 2 numbers Centrifugal Lps Provision of 2 numbers Provision of 2 numbers type pump having discharge 2.57 ML Total head …16 m Centrifugal type pump having Centrifugal type pump having or 32.45 LPS and head of 74 m with Kw of each pump…2.39 discharge 2.19 ML or 27.65 LPS discharge 1.17 ML or 14.77 LPS suitable motor is proposed with 100 Combined efficiency … 80% and head of 131.20 m with and head of 53.00 m with percent standby at WTP. suitable motor is proposed with suitable motor is proposed with Clear Water pump: 100 percent standby at WTP. 100 percent standby at WTP Type of pump …Centrifugal pumps Number of pumps … 2 Nos Capacity of each pump …11.99 Lps Total head …32 m Kw of each pump… 4.77 Combined efficiency … 80%

3 Raw water Length-12030 m, Dia.150 mm Length- 3150 m, Dia. 250 mm DI K9 360 m length - 200 mm dia DI Length- 100 m, Dia. 200 mm DI transmission DI K9 pipe K9 From intake to WTP 4 WTP Capacity: 1.40 MLD 3.15 MLD capacity existing WTP will Capacity: 0.94 MLD Capacity: 1.50 MLD be utilized; at present no improvements are proposed; during the detailed design phase, DBO Contractor will review the WTP working, identify if any improvements are necessary and undertake the same Location : On Government land Location: existing WTP Location: On a government land Location: On Government land at ward no. 9 in southern outskirts of the at village Chapri Fata (- source near the intake. Chikli Road) near existing OHT

Particulars Karahi Padliya Kasrawad Pansemal Rajpur 5 Reservoirs / 50 KL of sump well at WTP for Location Capacity Staging Clear water sump at WTP No new Reservoirs /tank tanks storing Clear water after Capacity: 21600 liters constructed for proposed WSS. treatment from WTP and 1 OHT OHT (in KL) Height Existing Clear water sump well at proposed at Prakash Nagar on WTP is structurally good in government land and 2 existing Ward 115 12 condition and hence utilized for OHTs are utilized for proposed No.5 the proposed scheme and 2 project. existing OHTs are also used for

the proposed project. 6 Clear water 150- 200 mm dia DI-K9 pipe 150- 250 mm dia DI-K9 pipe from the 1500 m - 150 mm dia DI pipe 150-300 mm dia DI-K9 pipe from transmission clear water sump to the from the clear water sump to the clear water sump to the proposed From the clear water sump (at proposed OHT, along the road. proposed OHT, along the main OHT, along the main roads. WTP) to the proposed OHT (at Total length- 22.89 Km roads. Total length -3.895 km the other end of the town), along Total length- 3.602 km the main roads. 77 m - 100 mm dia DI pipe From Junction point to the existing OHT (in the middle of the town), along the main roads. 7 Distribution Zone 1- Dia 110-200 mm, total Zone 1- Dia 110-280 mm, total length 12.056 km – 63 mm to 355 mm Zone 1- Dia 110-250 mm, total network length 2.641 Km 22.546 Km HDPE-10 length 22.728 Km Zona 2- Dia 110-250 mm, total Zona 2- Dia 110-200 mm, total length Zone 2- Dia 110-250 mm, total Location: Along the public roads length 17.456 km 11.027 km length 17.791 km in the entire town. Zone 3- Dia 110-250 mm, total Zone 3- Dia 110-280 mm, total length Zone 3- Dia 110-250 mm, total length 5.791 km 8.243 km length 11.701 km Total length- 25.888 km Total length- 41.816 km Total length- 52.220 km 8 Consumer Domestic- 1342 nos, non- Domestic- 840 nos, non- domestic- 3200 no,s – at each house in the Domestic- 913 nos and connects with domestic- 50 nos 50 nos town nondomestic- 300 meters

Figure 2: Key Plan of Karahi Padlya WSS

Figure 3: Details of Intake arrangements of Karahi Padlya WSS

Figure 4: Details of Intake arrangements of Kasrawad WSS

23

Figure 5: Keyplan of Kasrawad WSS

24

Figure 6: Key Plan of Rajpur WSS

25

Figure 7: layout plan of intake WELL –Pansemal WSS

Figure 8: Conceptual process flow diagram of WTP

Figure 9: layout plan of WTP

IV. POLICY, LEGAL AND ADMINISTRATIVE FRAMEWORK

A. ADB Policy

21. ADB requires the consideration of environmental issues in all aspects of ADB’s operations, and the requirements for environmental assessment are described in ADB SPS, 2009. This states that ADB requires environmental assessment of all ADB investments.

22. Screening and categorization. The nature of the environmental assessment required for a project depends on the significance of its environmental impacts, which are related to the type and location of the project; the sensitivity, scale, nature, and magnitude of its potential impacts; and the availability of cost-effective mitigation measures. Projects are screened for their expected environmental impacts, and are assigned to one of the following four categories:

(i) Category A. Projects could have significant adverse environmental impacts. An EIA is required to address significant impacts. (ii) Category B. Projects could have some adverse environmental impacts, but of lesser degree or significance than those in category A. An IEE is required to determine whether significant environmental impacts warranting an EIA are likely. If an EIA is not needed, the IEE is regarded as the final environmental assessment report. (iii) Category C. Projects are unlikely to have adverse environmental impacts. No EIA or IEE is required, although environmental implications are reviewed. (iv) Category FI. Projects involve a credit line through a financial intermediary or an equity investment in a financial intermediary. The financial intermediary must apply an environmental management system, unless all projects will result in insignificant impacts.

23. Environmental management plan. An EMP, which addresses the potential impacts and risks identified by the environmental assessment, shall be prepared. The level of detail and complexity of the EMP and the priority of the identified measures and actions will be commensurate with the project’s impact and risks.

24. Public disclosure. ADB will post the safeguard documents on its website as well as disclose relevant information in accessible manner in local communities:

(i) for environmental category A projects, draft EIA report at least 120 days before Board consideration; (ii) final or updated EIA and/or IEE upon receipt; and (iii) Environmental monitoring reports submitted by the implementing agency during project implementation upon receipt.

B. National Environmental Laws

25. Environmental Assessment. The GoI EIA Notification of 2006 (replacing the EIA Notification of 1994), sets out the requirement for Environmental Assessment in India. This states that Environmental Clearance (EC) is required for specified activities/projects, and EC must be obtained before any construction work or land preparation (except land acquisition) may commence. Projects are categorized as A or B1 or B2 depending on the scale of the project and the nature of its impacts. None of the components of this water supply subproject falls under the ambit of the EIA Notification 2006, and, therefore no category assigned, and thus no EIA study and EC required for the subproject.

29

26. Applicable environmental regulations. Besides EIA Notification 2006, there are various other acts, rules, policies and regulations currently in force in India that deal with environmental issues that could apply to infrastructure development. The specific regulatory compliance requirements of the subproject are shown in Table 2.

Table 2: Applicable Environmental Regulations Law Description Requirement Madhya Pradesh Prepared in accordance with the National Water Permission of WRD, State Water Policy, it states that “for environmental balance, GoMP: Policy, 2003 skillful and planned management of all types of developmental activities, economic use on • Construction of equitable basis and in view of the prime Intakes (River importance of water for all human and other living Narmada ) beings, an effective and sound water policy is • Construction of intake necessary”. at Gomai Dam Policy is detailed in 17 sections dealing with different aspects of water resources. No. 7 deals with Water Allocation Priorities, and according to which drinking water supply shall have the highest priority followed by irrigation, power, tourism, etc. Water Resource Department is nodal department for permitting different uses of water resources. Policy also states that “clear provision for reservation of drinking water shall be made in irrigation projects” Water (Prevention Act was enacted to provide for the prevention and WTPs require CTE (prior and Control of control of water pollution and the maintaining or to start of constriction) Pollution) Act of restoring of wholesomeness of water, by Central and CFO (prior to start of 1974, Rules of and State Pollution Control Boards and for operation) from MPPCB. 1975, and conferring and assigning to CPCB/SPCBs powers amendments &functions relating to water pollution control. Application has to be submitted online at Control of water pollution is achieved through http://www.mppcb.nic.in/x administering conditions imposed in consent gn.html issued under to this Act. These conditions regulate the quantity and quantity of effluent, the Existing WTP in location of discharge and the frequency of Kasrawad does not have monitoring of effluents. Any component of the CTE and CTO from subproject having the potential to generate MPPCB therefore it has to sewage or trade effluent will come under its be obtained. purview. Such projects have to obtain Consent to Establish (CTE) & Consent to Operate (CTO) under Section 25 from Madhya Pradesh Pollution Control Board (MPPCB) Environment Emissions and discharges from the facilities to be Appendix 2 provides (Protection) Act, created or refurbished or augmented shall comply applicable standards for 1986 and CPCB with the notified standards ambient air quality. Environmental Appendix 3 provides Standards. vehicular emission norms

Noise Pollution Rule 3 of the Act specifies ambient air quality Appendix4 provides (Regulation and standards in respect of noise for different applicable noise Control) Rules, areas/zones. standards. 2000 amended up to 2010. Indian Drinking Gives details of the permissible and Appendix 11provides Water desirable limits of various parameters in drinking water standards

Standards drinking water as per the Burea of Indian Standards Municipal Solid Rules to manage municipal solid waste Solid waste generated at 30

Law Description Requirement Wastes generated; provides rules for segregation, proposed facilities shall be Management storage, collection, processing and disposal. managed and disposed in Rules, 2016 accordance with the MSWM Rules Construction & Rules to manage construction & to waste resulting Construction & demolition Demolition Waste from construction, remodeling, repair and waste generated from the Management demolition of any civil structure. Rules define C&D project construction shall Rules, 2016 waste as waste comprising of building materials, be managed and debris resulting from construction, re-modeling, disposed as per the rules repair and demolition of any civil structure. (Appendix 5) Labor Laws The contractor shall not make employment Appendix 6 provides decisions based upon personal characteristics applicable labor laws unrelated to job requirements. The contractor including amendments shall base the employment relationship upon issued from time to time equal opportunity and fair treatment, and shall not applicable to discriminate with respect to aspects of the establishments engaged employment relationship, including recruitment in construction of civil and hiring, compensation (including wages and works. benefits), working conditions and terms of employment or retirement, and discipline. The contractor shall provide equal wages and benefits to men and women for work of equal value or type.

27. ADB SPS Requirements. During the design, construction, and operation of the project the PMU and PIUs are required to apply pollution prevention and control technologies and practices consistent with international good practice, as reflected in internationally recognized standards such as the World Bank Group’s Environment, Health and Safety Guidelines (IFC’s General EHS Guidelines1 and Sector Specific (Water and Sanitation) Guidelines2). These standards contain performance levels and measures that are normally acceptable and applicable to projects. When Government of India regulations differ from these levels and measures, the PMU and PIUs will achieve whichever is more stringent. If less stringent levels or measures are appropriate in view of specific project circumstances, the PMU and PIUs will provide full and detailed justification for any proposed alternatives that are consistent with the requirements presented in ADB SPS. International acceptable air and noise quality guidelines are provided below:

1https://www.ifc.org/wps/wcm/connect/554e8d80488658e4b76af76a6515bb18/Final%2B- %2BGeneral%2BEHS%2BGuidelines.pdf?MOD=AJPERES 2 https://www.ifc.org/wps/wcm/connect/e22c050048855ae0875cd76a6515bb18/Final%2B- %2BWater%2Band%2BSanitation.pdf?MOD=AJPERES

31

Table 3: WHO Ambient Air& Noise Quality Guidelines

32

V. DESCRIPTION OF THE ENVIRONMENT

A. Methodology Used for Baseline Study

28. Data collection and stakeholder consultations. Focused Group Discussion, field visits, site surveys and social surveys were conducted through the different wards covering every section of society was conducted and data collected and analyzed accordingly with respect to the proposed subproject sites and the with respect to the need of water supply in all the four towns here.

29. The survey broadly covered the following:

(i) Project details, reports, maps, and other documents prepared by technical experts of design consultant team. (ii) Discussions with technical experts, municipal authorities and relevant government agencies like WRD, Revenue Department, Forest Department, MPPCB, etc. (iii) Secondary data from previous project reports & published articles, if any, and (iv) Literature on land use, soil, geology, hydrology, climate, socioeconomic, and planning documents collected from Government agencies and websites.

30. Ocular inspection. Several visits to the project sites were made during IEE preparation period in 2016 to assess the existing environment (physical, biological, and socioeconomic) and gather information with regard to the proposed sites and scale of the proposed project. A separate socioeconomic study was conducted to determine the demographic information, existing service levels, stakeholder needs and priorities.

B. Baseline Environmental Profile

31. Following Table 4 presents the baseline environmental profile of subproject towns of Pansemal, Rajpur, Karahi Padliya and Kasrawad. It is organized in terms of physical, ecological, economical, and socio cultural resources.

33

Table 4: Baseline Environmental Features of the Subproject Towns

Baseline Karahi Padaliya Kasrawad Pansemal Rajpur characteristics Location Karhi is a Nagar Parishad in Kasrawad is a Nagar Parishad of Pansemal is located at 21°65‘ N Rajpur is a Town & Nagar of Madhya Khargone district in Madhya latitude and 74.°7‘ E longitude at an Parishad is located in Barwani Pradesh State, India. The Pradesh state. It is located at elevation of 242 m, in in the state of Madhya geographical Location of Town is Latitude 22°13' N & Longitude District in the western part of MP. It Pradesh. The geographical given as: Latitude- 21.8334 N 75°06' E and is indicated on survey is at about 48.6 km from Barwani. Location of Town “Rajpur” is Longitude- 75.6104 E of India topo-sheet no. 46N12. The given as below. Town is situated at average city of Kasrawad is situated in Latitude- 210 93’ N elevation of 219 m from Mean Sea South west of Madhya Pradesh of Longitude- 750 13’ E Level. Khargone district. Town is situated at average Town is situated at average elevation of 225 m from Mean elevation of 189 m from Mean Sea Sea Level. Level.

Connectivity Karhi is very well connected by Kasrawad is well connected to In view of regional connectivity, The town is 27 km away from road to the Barwah , Khargone by state highway SH-1 Pansemal is well connected by the district head quarter and hence to all major towns and and Indore by SH-35 and NH- road network. There are direct Barwani. cities of the state. There is no 3.The town is only 33 km away roads which connect other important railway station near to Karhi in less from the district headquarters in town in Madhya Pradesh. The town than 10 km. However Indore Khargone city. Kasrawad is is connected to Bombay NH 03 Junction is 55 km from Karhi. connected by bus routes to Indore by SH 39 at the distance of 45km at is 28 km from Karhi. (70 km), Khargone (30 km) and . Maheshwar (9 km). Maheshwar is a major tourist destination of the Khargone district.

Area & The area of the town is spread The population of the Kasrawad Pansemal Nagar Parishad extends Population over in 3000.00 Ha (3.00Sq Kms ) Nagar Parishad as per 2011census to an area of 6.14 sq. km, divided The Population of Rajpur as per information given by Nagar is 22750. into 15 wards, and houses Nagar Parishad as per 2011 Parishad and Population is as per The area of the town is spread over population of 12,166 (2011 census) census is 20947.The area of the 2011 census 10035 in 3.88 Sq Kms as per 2011 data. town is spread over in 9000.00 Ha (9.00Sq Kms ) as per 2011 data Topography Karhi is situated on an uneven The town forms almost central Topography is predominantly plain, Rajpur is situated on an uneven tract of land and the general section of Narmada valley which is having almost equal elevation tract of land and the general

Baseline Karahi Padaliya Kasrawad Pansemal Rajpur characteristics ground slope is towards eastern bordered by Vindhya scarp in the throughout the town having natural ground slope is towards eastern side. A major Nallah flowing North and the Satpura ranges in terrain of the area has slope from side. A major Nallah flowing through the centre of Karhi city the South. The main drainage is east to west. Nearest River Gomai through the centre of Rajpur city forms the main drainage system of formed being Narmada River and that flows in the west of the town. forms the main drainage system Karhi. various small nallas and rivulets Average elevation is 242 above of Rajpur. join to Narmada. MSL. Pansemal is predominantly plain topography. Soils & The soil in the region is mostly The soil strata in the town are Soils in the region is mostly black The soil in the region is mostly geology medium black soil. The soil in the mostly medium black cotton soil. cotton but has a rocky terrain. black cotton but has a rocky region is less productive in terrain. The soil in the Nimar comparison to nearby region like region is less productive in region. The natural terrain of comparison to nearby region like the area has slope from east to Malwa region. The natural west and central area has slope terrain of the area has slope from north to south. from east to west and central area has slope from north to south.

Climate Study area experiences a temperate climate characterized by a hot summer, well-distributed rainfall during the south-west monsoon season and mild winter. The year may be divided into four seasons: Winters(cold season) from November/December to February, and followed summers (hot season) from March to about the middle of June. The period from middle of June to September is the south-west monsoon season. October and November form the post-monsoon period • Average rainfall: 801 mm (Karahi), 878 mm (Kasrawad), 831 mm (Pansemal), • Most of the rainfall is received during the southwest monsoon of June to September, and it ranges between: 85% - 89.3% • May is the hottest month with average max temperature (day) of 41.4oC and average minimum temperature (night) of 26.5oC • January is the coldest month with average max temperature (day) of 25.6oC and average minimum temperature (night) of 8.4oC • Annual mean min & max temperature: 31.6º C and 18.2º C • Humidity: highest during monsoon (88% in Aug), lowest in summer (38%); May driest month. • Wind speed: 6.8 kmph (June), 2.3 kmph (November), and average – 4.3 kmph

Surface water Gagan Talab is small earthen dam There is Narmada River About 88% of the district lies in Presently there are two surface approximately 6 km away from the approximately 7 km from the Narmada Basin and 12% in Tapti water source Narmada River Karhi town. It dries up in the Kasrawad town. It is Perennial Basin. The major tributaries of and Narrula pond. Narrula pond summer. River. No storage structure will be Narmada are Deb and Gomai. No is small earthen tank required. There is already water major tributary of Tapti flows in the approximately 7 km away from supply from river Narmada. Hence district. The surface water availability the Rajpur. Presently this source is reliable and sufficient at 75% dependability for both the approximately 0.4 ML water is 35

Baseline Karahi Padaliya Kasrawad Pansemal Rajpur characteristics for augmentation of Kasrawad Basins is 966.70 MCM of which drawn from this source 0.6 ML water supply scheme. But there is 921.95 MCM is from Narmada Basin is drawn from river Narmada. no intake well in the scheme. and 44.75 MCM from Tapti Basin. But Narulla Pond dries up in the The district area is drained mainly by summer. Narmada River the Narmada River and its tributaries approximately 20 km from the like Gomai and Deb. All of these Rajpur town. It is perennial river. tributaries flow from south to north No storage structure will be and join Narmada. Similarly, required. There is already water tributaries like Tori, Churi, supply from river Narmada. Dudhikheda etc. flow from north to south. Major rivers are perennial to semi perennial. Groundwater Khargone district is underlain by mainly Basaltic lava flows of Deccan Deccan traps are basaltic lava flows and form the most predominant and trap. Dynamic ground water resources of the district have been widespread hydrogeological formations in the district. The alluvial estimated for base year - 2008/09 on block-wise basis . There are nine deposits are confined mainly to Narmada & Goi rivers and are not very number of assessment units (block) in the district which fall under non- extensive in thickness. The thickness of alluvium in the piezometer at command (99 %) and command (1.%- Bhagwanpura, Kasrawad and Anjad has been found to be 10 m. Controlled pumping tests results on Khargone) sub units. Bhagwanpura, Bhikhangaon and Jhirnia are number of dug wells in the district shows that the yield of wells tapping categorized as safe. Khargone, Maheshwar and Barwha blocks of the vesicular basalts and massive traps ranges from 24 to about 70 district are categorized as semi critical. The highest stage of ground cu.m/day. The specific capacity of wells varies from 25 lpm/m of water development is computed as 90 % in Khargone. The net ground drawdown to 285 lpm/m of drawdown in weathered vesicular basalt.The water availability in the district is 77,219 ham and ground water draft for specific capacity of wells in alluvial aquifer is about 490 lpm/m of all uses is 55,848 ham, making stage of ground water development 72% drawdown. As per chemical analysis data of pre-monsoon, 2011, ground (76 % in 2003/04) as a whole for district. water in the area is generally alkaline in nature and the pH values are Ground water quality in the district is accessed annually by CGWB on the within acceptable limits. The Chloride concentration in the area is below basis of water samples collected from hydrograph stations in the district. 250 mg/l. The higher chloride values generally coincide with areas Groundwater in the district is generally fresh to saline as electric having high EC thus indicating that the salinity in ground water is mainly conductivity values varies between 260 to 4150 μs/cm at 25° C. Fluoride due to chloride. Concentration of magnesium and calcium in Barwani in the district ranges from 0.01 to 0.89 mg/l and the nitrate concentration district are within permissible limits. The nitrate concentration in the ranges from 1.2 to 620 mg/l. district ranges between 2.5 – 68 mg/l with only Sendhwa having a value of 68 mg/l. The fluoride concentration in the district ranges between 0.14 to 0.61 mg/l. The total hardness in the district ranges between 65 to 530 mg/l falling within permissible limit. Air quality No air quality data available, No air quality data available, No air quality data available, No air quality data available, however, there are no air pollution however, there are no air pollution however, there are no air pollution however, there are no air sources, except the dust, which is sources, except the dust, which is sources, except the dust, which is mainly due to dry weather, mainly due to dry weather, mainly due to dry weather, activities pollution sources, except the

36

Baseline Karahi Padaliya Kasrawad Pansemal Rajpur characteristics activities like traffic movement. activities like traffic movement. like traffic movement. dust, which is mainly due to dry weather, activities like traffic movement. Ecological Main Vindhya Reserve forest is Kasrawad Reserve forest located A reserve forest fairly dense mixed There is no Ecological sensitive located in the North of the town in the south direction approx. 4-5 jungle is located in the south of the area near by sub project town. approx 10 km from the Karahi km from town. town away from the Gomai river at a Padaliya town, none of the project distance of 70km from the town. components come under it. There is no Ecological sensitive area near by sub project town. Economic Karahi Padlya NP recently formed The town has developed around Pansemal town consists of main The spatial growth of the development with two villages named Karahi the State Highway 1. If we see the town and two remote clusters Rajpur is strongly dictated by and Padlya. The residential growth pattern during last decade, dispersed along the main roads its physical setting as well as Land use clusters are situated in pockets the town has developed mostly in passing through the town. The its location in the regional among these clusters massive North-East direction towards residential clusters are situated in context. The town is regionally agricultural plots between them. Mandleshwar along SH-1. The pockets among these clusters linked with Barwani, town has also shown growth leaving massive agricultural plots and through the main towards South along Khargone between them. The main public road. Movement corridors road (SH-1) and along Gawla road. and semi‐public assemblage can be leading to other cities have Although lesser, but the town has seen to be located at the core area triggered development along also shown growth towards West of town and along Khetia‐Sendhwa them. along road (SH-35) and road. The town has 32% residential, towards North-West along 4% transportation, 5% public Sadgaon road. semi‐public, 4% Industrial and less than 1% commercial land use. Agricultural land is 32%, open/vacant land is 11% and the rest 12% comprises of two rivers which are passing through from north and the south direction of the town. Pansemal has good connectivity with other places around. The town is linked to other cities and towns by road network. The town doesn’t have public transportation facility. The rivers are passing through from north 37

Baseline Karahi Padaliya Kasrawad Pansemal Rajpur characteristics and south direction of the town. The water body has a surface area of 0.24 sq.Km Agriculture & Karahi Padlya is predominantly an Khargone is known for the Thread Pansemal is predominantly an Rajpur is mainly known for the industry agricultural economy, and there Manufacturing activities in the agricultural economy, and there are production of chilly in the state, are large tracts of municipal area is region and there are few Spinning large tracts of municipal area is still Rajpur is the sub-mandi of Anjad still under the agriculture. Cotton , Mills (Thread Manufacturing Unit) under the agriculture. Corn, pulses, mandi, but in the point of view of Banana, wheat, etc are the main in Bhilgaon village which is around wheat, etc are the main crops. chilly business; it is the second crops.Karahi padlya has small at 3 Kms. distance from the town. Pansemal has small scale industries biggest mandi in the district. The scale Cotton industries and various There are 6 Spinning Mills / and various processing units. It could mandi is situated on the outer processing units. Ginning factories in Kasrawad town be develop as an industrial city. The side of the city, the location of also which are located in the major Industrial units are operated mandi gives advantage to the peripheral area (outside the Lal from the ward 6, 14, and 15. city as well as to mandi itself. Dora area) of the town along SH - 38, adjoining to Ward-6 & 11 and one Spinning Mill/ Ginning factory is located within the town in Ward- 11. Infrastructure Roads are quite broad in most of Roads are quite broad in most of Roads are quite broad in most of the Roads are quite broad in most of - transport the areas of the Karahi Padliya the areas of the Kasrawad town. areas of the Pansemal town. The the areas of the Rajpur town. town. The main roads, where there The main roads, where there are main roads, where there are The main roads, where there are are commercial and transport commercial and transport activities, commercial and transport activities, commercial and transport activities, are congested with are congested with pedestrians, are congested with pedestrians, activities, are congested with pedestrians, traffic and activities. traffic and activities. The major traffic and activities. The major pedestrians, traffic and activities. The major modes of transportation modes of transportation in the city modes of transportation in the city The major modes of in the city are cycle, motorcycle are cycle, motorcycle and auto are cycle, motorcycle and auto transportation in the city are and auto rickshaws. Public modes rickshaws. Public modes of rickshaws. Public modes of transport cycle, motorcycle and auto of transport such as city bus, mini transport such as city bus, mini such as city bus, mini buses etc are rickshaws. Public modes of buses etc are not prevalent in the buses etc are not prevalent in the not prevalent in the city. There is transport such as city bus, mini city. There is no proper city. There is no proper no proper infrastructure for bus stand buses etc are not prevalent in infrastructure for bus stand but the infrastructure for bus stand but the but the connectivity of the town with the city. There is no proper connectivity of the town with other connectivity of the town with other other cities is good. Pansemal falls infrastructure for bus stand but cities is good. cities is good. on Khetia - Sendhwa road hence bus the connectivity of the town with connectivity is good. other cities is good. Sewerage, The city does not have an The city does not have an The city does not have an The city does not have an sanitation & underground sewage system. underground sewage system. underground sewage system. Also underground sewage system. drainage Also there is no separate Also there is no separate there is no separate sewerage and Also there is no separate

38

Baseline Karahi Padaliya Kasrawad Pansemal Rajpur characteristics sewerage and storm water network sewerage and storm water network storm water network in the city. The sewerage and storm water in the city. The area completely in the city. The area completely area completely lacks in network in the city. The area lacks in underground sewerage lacks in underground sewerage underground sewerage system for completely lacks in underground system for conveyance of system for conveyance of conveyance of household sewerage system for household wastewater. Also there household wastewater. Also there wastewater. Also there is no conveyance of household is no treatment facility in the form is no treatment facility in the form treatment facility in the form of STP wastewater. Also there is no of STP in the town. The prevalent of STP in the town. The prevalent in the town. The prevalent sewerage treatment facility in the form of sewerage systems generally sewerage systems generally systems generally practiced by the STP in the town. The prevalent practiced by the people in town is practiced by the people in town is people in town is individual septic sewerage systems generally individual septic tanks privately individual septic tanks privately tanks privately maintained by the practiced by the people in town maintained by the respective maintained by the respective respective households is individual septic tanks households households Open drains (18 km total length) privately maintained by the along the roads cater to both respective households wastewater and rainwater, and dispose into naala / stream ultimately discharged into Gomai River. There are individual toilets in some houses with septic tanks, the outflow from which is disposed into open drains, pit latrines, and open defecation is also prevalent Solid waste Town has an efficient system of Town has an efficient system of Town has an efficient system of Town has an efficient system of management waste collection. Door to door waste collection. Door to door waste collection. Door to door waste collection. Door to door collection is done in all the wards collection is done in all the wards collection is done in all the wards collection is done in all the wards between 8 am in morning to 2 pm between 8 am in morning to 2 pm in afternoon. Sweeping of roads between 8 am in morning to 2 pm in between 8 am in morning to 2 in afternoon. Sweeping of roads and cleaning of drains is done afternoon. Sweeping of roads and pm in afternoon. Sweeping of and cleaning of drains is done in morning and waste is collected cleaning of drains is done in roads and cleaning of drains in morning and waste is collected along road side. After collecting the morning and waste is collected along is done in morning and waste along road side. After collecting the waste from different areas & road side. After collecting the waste is collected along road side. different sources it is being waste from different areas & from different areas & different After collecting the waste from transported with tractors/dumpers different sources it is being to the dumping site sources it is being transported with different areas & different transported with tractors/dumpers tractors/dumpers to the dumping site. sources it is being transported to the dumping site with tractors/dumpers to the dumping site Demographic Population of the Nagar Parishad Population of the town as per 2011 Population of the town as per 2011

39

Baseline Karahi Padaliya Kasrawad Pansemal Rajpur characteristics The Population of Rajpur characteristics is 10070, Since it is a newly census was 22750 increased from census was 12,166 increased from Nagar Parishad as per 2011 formed Nagar Parishad other 19050 in 2001. 10,744 in 2001. census is 20947. census data are not available Growth rate 2001-2011: 11.6% Growth rate 2001-2011: 11.6% Sex ratio- 954 Sex ratio – 959 (2011), Sex ratio – 965 (2011), Literacy rate - 68.4 % (female) literacy rate - 75.3% literacy rate 82.1 (male) – 82.8 and 83.6 % (Male) (State 2011). Literacy rate 68.9 (female) SC population – 11.85% ST population – 23.17% History, There is no heritage & There are no various places of There is no heritage & There is no heritage & culture & archaeological site in the town. interest in in Kasrawad town - such archaeological site in the town. archaeological site in the town. tourism as the Bhavani Mata Temple, ancient Kailash Kund and Baba ki Mazar on Gangleshwar Parvat. These are of local importance and there are no protected / notified monuments or places of archeological or historical or cultural importance. An Archeological Survey of India (ASI) excavated site is about 2 km away from Kasrawad town; none of the project component located in or close to it.

40

41

Figure 10: Location of ASI excavated site w.r.t. Kasrawad town

42

Figure 11: Site Environ Features of Kasrawad town

43

Figure 12: Site Environ Features of Kari- Padlya town

44

Figure 13: Subproject Environ of Pansemal town

C. Subproject Site Environmental Features

32. Features of the selected subproject sites are presented in the following table.

Table 5: Site Environmental Features – Karahi Padlya S. Infrastructure Location & Site Photograph No Environmental Features 1 Intake well cum 21º 37’ 38 “ Latitude pump house 73º 42’ 30” Longitude

On the bank of Narmada River at Village Bahegaon.

3 Raw water Raw Water transmission line Transmission pipelines will be mostly laid along the main roads. Pipes will be laid Underground. The transmission main leading to Intake well to WTP, the land owned by Govt; this land is vacant, and pipeline will be laid with the permission.

4 WTP with sump WTP is proposed to well construct at Bahegaon Village on government vacant land, there is no forest land.

46

5 Clear water From WTP to the transmission (12 proposed OHTs, km) CWRM will be laid within the RoW.

6 Distribution Pipes will be laid network (12. km) within the road right of way (ROW) - in road’s earthen shoulder in wider roads, and within the carriageway in narrow roads, where there is no space. Roads in the Karahi Padlya are quite broad everywhere and pipelines can be laid easily by the side of road on the earthen shoulder.

There are no trees along the road.

47

7 Proposed OHT Proposed OHT site is (100 KL) free of vegetation cover and land is vacant. Land use around the site is residential

Table 6: Site Environmental Features – Kasrawad S. Infrastructure Location & Environmental Site Photograph No Features 1 Intake well cum In the bank of Narmada River, pump house there is proposed R.C.C. intake well of 6 m diameter and 21 m height and 6 m height masonry pump house to collect and lift water up to treatment works. H.F.L. and River bed level is 152.00 m and 134.00 m respectively. River bed is at 134.00 m keeping the invert level of intake well 4.5 m below the bed level of the river at 129.50 m. The pump floor (153.50 m) is kept as 1.5 m above the H.F.L. (152.00 m). The suction level 132.50 m for pumping of raw water is kept as 1.5 m below from river bed level. The difference of suction level and pump floor level is 21.00 m and height of intake well works out to 21.00 m. the diameter of intake well has been decided 6 m on the basis of space required for housing two numbers of 32 HP pumps. 3 Raw water It is proposed raw water rising Rising Main main 3150 M long. of Dia. 250 mm DI K9 from intake to WTP along RoW

48

4 WTP with sump Existing WTP is used for the well proposed project, hence no new construction proposed for WTP.

5 Clear water From WTP to three OHTs in transmission the Town by the side of road (1.577 km) on its earthen bund covering total distance of 3895 meters.

6 Distribution Pipes will be laid within the network (12. km) road right of way (ROW) - in road’s earthen shoulder in wider roads, and within the carriageway in narrow roads, where there is no space. Roads in the Kasrawad are quite broad everywhere and pipelines can be laid easily by the side of road on the earthen shoulder. There are no trees along the road.

49

7 OHTs One OHT is proposed having 115 KL capacity and staging height of 12 m at ward no. 5.

Table 7: Site Environmental Features - Pansemal S. Infrastructure Location & Environmental Site Photograph No Features

1 Water intake Jack well cum pump house will be facilities built in Gomai reservoir, under the control of Water Resources Department, GoMP.

Impoundment of water in the dam started in the year 2016-17. Dam is used irrigation. Water level in the dam is usually high in the post monsoon season, and recedes with release of water in the period of October /November to January / February. There are no notable sensitive features. Raw water pipeline will be laid underground from the jack well intake to WTP site along an existing road 4 WTP with WTP site is located adjacent to the sump well Gomai Dam.

Total area required is 1.5 ha; site is owned by Revenue Department, GoMP.

5 Clear water From WTP to two OHTs in the transmission Pansemal Town by the side of road (1.577 km) on its earthen bund covering total distance of 1577 meters.

50

6 Distribution Pipes will be laid within the road network (12. right of way (ROW) - in road’s km) earthen shoulder in wider roads, and within the carriageway in narrow roads, where there is no space. Roads in the Pansemal are quite broad everywhere and pipelines can be laid easily by the side of road on the earthen shoulder. There are no trees along

the road. 7 Proposed OHT 577 m towards North-West of (100 KL) proposed WTP (At existing 90KL OHT location).

8 Existing OHT At existing Water Works Station in (450 KL) Pansemal.

Table 8: Site Environmental Features – Rajpur S. Infrastructure Location & Environmental Site Photograph N Features o 1 Intake well cum In the bank of Narmada River, pump house there is proposed RCC intake well of 6 m dia and 24 m height

51

3 Raw water There is existing RWRM 6553 transmission line m long and 200 mm dia DI- K9 from Narmada river to existing WTP. It is in good condition and is taken into account for new system. Additional 100m long 200mm DI-K9 is proposed for connecting of raw water pipeline to proposed WTP.

4 WTP with sump Site is located on a hillock at well village Chapri. Site is currently vacant Site is owned by government and located adjacent to an existing road.

5 Clear water It is proposed clear water feeder transmission main of total 22863 m long of (1.577 km) 150-300 mm DI K9.

52

6 Distribution Pipes will be laid within the road network (12. km) right of way (ROW) - in road’s earthen shoulder in wider roads, and within the carriageway in narrow roads, where there is no space. Roads in the Rajpur are quite broad everywhere and pipelines can be laid easily by the side of road on the earthen shoulder. There are no trees along the road.

53

VI. ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES 33. Potential environmental impacts of the proposed infrastructure components are presented in this section. Measures to minimize/mitigate negative impacts, if any, are recommended along with the agency responsible for implementation. Monitoring actions to be conducted during the implementation phase is also recommended.

34. Screening of potential environmental impacts are categorized into four categories considering subproject phases: location impacts and design impacts (pre-construction phase), construction phase impacts and operations and maintenance phase impacts.

a. Location impacts include impacts associated with site selection and include loss of on-site biophysical array and encroachment either directly or indirectly on adjacent environments. It also includes impacts on people who will lose their livelihood or any other structures by the development of that site. b. Design impacts include impacts arising from Investment Program design, including technology used, scale of operation/throughput, waste production, discharge specifications, pollution sources and ancillary services. c. Construction impacts include impacts caused by site clearing, earthworks, machinery, vehicles and workers. Construction site impacts include erosion, dust, noise, traffic congestion and waste production. d. O&M impacts include impacts arising from the operation and maintenance activities of the infrastructure facility. These include routine management of operational waste streams, and occupational health and safety issues.

35. Screening of environmental impacts has been based on the impact magnitude (negligible/moderate/severe – in the order of increasing degree) and impact duration (temporary/permanent).

36. This section of the IEE reviews possible project-related impacts, in order to identify issues requiring further attention and screen out issues of no relevance. ADB SPS (2009) require that impacts and risks will be analyzed during pre-construction, construction, and operational stages in the context of the project’s area of influence.

37. The ADB Rapid Environmental Assessment Checklist in http://www.adb.org/documents/guidelines/environmental_assessment/eaguidelines002.aspis used to screen project for environmental impacts and to determine the scope of the IEE.

38. In the case of this project (i) most of the individual elements are relatively small and involve straightforward construction and operation, so impacts will be mainly localized and not greatly significant;(ii) proposed water abstraction from the sources is very small compared to overall water availability (iii) most of the predicted impacts are associated with the construction process, and are produced because that process is invasive, involving excavation and earth movements; and some works are located in the reservoir and (iv) being mostly located in an urban area, will not cause direct impact on biodiversity values. The proposed project components locations are belongs to the government property and existing roads, hence land acquisition and encroachment on private property will not happen in this case. A. Pre-Construction Impacts – Design & Location

39. Design of the Proposed Components. Technical design of the (i) intake well, , (ii) water treatment plant; (iii) raw water and clear water transmissions mains (iv) over head tanks, and (v) distribution network, connections, flow meters, etc., follows the relevant national planning and design guidelines, focusing on providing a robust system which is easy to operate, sustainable, efficient and economically viable. Besides, the project also included the following environmental considerations:

54

(i) Recovering backwash water from treatment process and achieving zero discharge of wastewater from WTPs. (ii) Treatment and disposal management of sludge from treatment process. (iii) Minimizing water losses from pipelines by perfect jointing and alignments using appropriate techniques (iv) Designing the entire system to maintain optimal flow and terminal pressure, and optimising the overall energy usage (v) Reducing the incidence of water borne diseases by providing 100% population including urban poor with potable water supplies (vi) Improve water use efficiency and reduce water wastage at household level by recording and monitoring the water usage, and charging the consumers as per usage; due consideration to urban poor (vii) Minimize unaccounted for water (UFW) losses using district metered area approach with flow meter and pressure logging arrangements to identify and rectify the leaks, and unauthorized connections (viii) Using low-noise and energy efficient pumping systems

40. Water Source & Sustainability. As the subproject towns are located far from each other (100-150 km) there was no possibility of a combined source/ bulk water scheme. Therefore, independent water supply schemes are proposed for 4 towns separately based on the most feasible water source considering techno-economic and environmental considerations as elucidated below (Table 9).

55

Table 9: Water Source Selection & Sustainability

Subproject Alternative Sources Selected Source and Associated Impacts due to abstraction Town Karahi Groundwater: Presently Karhi water supply is based on ground Narmada River: Padlya water. There are 2 tube wells in the town. Water is drawn from The population of Karhi on census year 2011 is 10035.The city is these tube wells. Water is also drawn from dug well near developing and the population is expected to reach about 29724 by the Prempura and Gagan Talab. Total 0.50 ML water is supplied at year 18917. The requirement of water in the year 2033 would be about an average rate of 36 lpcd. But during the summer yield of 1.24 MLD. City water supply is intermittent. Presently water supply these tube wells & wells reduces considerably. Private tube source are Tube wells. Tube wells become dry up in summer season wells are extra deep ranging from 150 m to 180 m and even and it is insufficient to cater the demand @ 70 Lpcd for present and more. The drawl from these tubes well is very high. Hence projected population of Karhi Nagar Parishad. Hence tube wells and ground water source is not sustainable. As per hydro Gagan talab are not dependable source. geomorphologic map of the area prepared by National Remote In the bank of Narmada River, there is proposed R.C.C. intake well of 6 Sensing Agency, Department of Space, Govt. of India, m diameter and 20 m height to collect and lift water up to treatment Hyderabad, the recharge conditions in the area is moderate to works. H.F.L. and River bed level is 157.50 m and 140.50 m good. Rock is vesicular in nature plateau weathered type basalt. respectively. River bed is at 140.50 m keeping the invert level of intake The HGM of the area is enclosed. well 4.5 m below the bed level of the river at 136.00 m The pump floor (159.00 m) is kept as 1.5 m above the H.F.L. (157.50 m). The suction Surface Source:- point (139) is kept as 1.5 m below from the River Bed Level and There are Two main sources near Karhi town:- difference of suction point level and pump floor level is 20.00 m. The 1. Gagan Talab: - It is small earthen dam approximately 6 km height of intake well works out to 20 m and diameter of intake well has away from the Karhi town. It dries up in the summer. Hence it been decided 6 m on the basis of space required for housing two can’t be taken as source for Karhi town. Some Irrigation is also numbers each of 47 HP pumps. done from this pond. Dug well has been drilled near this pond to Detailed survey was conducted for selection of site. The selected site is bring water into the Karhi town. nearest, and will have required quantity of water. 2. Narmada River: - There is Narmada River approximately 12 (Salient Features of Narmada is given below in para 41) km from the Karhi town. It is perennial river. No storage structure will be required.

Kasrawad Ground Water: There are 3 nos. of tube wells in the town. Narmada River: Water is drawn from these tube wells also for the isolated area. The population of Kasrawad on census year 2011 is 22750.The city is Total 1.25 ML water is supplied at an average rate of 35.52 developing and the population is expected to reach about 39873 by the LPCD from the both sources. But during the summer yield of year 2048. The requirement of water in the year 2033 would be about these tube wells & wells reduces considerably. Private tube 2.67 MLD. City water supply is intermittent. Presently water supply

wells are extra deep ranging from 150 m to 180 m and even source is Narmada River and Tube wells. Tube wells are not more. The drawl from these tubes well is very high. Hence dependable source and it is insufficient to cater the demand @ 70 Lpcd ground water source is not sustainable. As per hydro for present and projected population of Kasrawad Nagar Parishad. geomorphologic map of the area prepared by National Remote Narmada river is perennial river and it is sufficient source. But present Sensing Agency, Department of Space, Govt. of India, water supply arrangement from Narmada River is not sufficient. Hyderabad, the recharge conditions in the area is moderate to Presently 1.25 MLD water supply is being made which accounts for a good. Rock is vesicular in nature plateau weathered type basalt. per capita supply of only 35.52 Lpcd. In the bank of Narmada River, The HGM of the area is enclosed. there is proposed R.C.C. intake well of 6 m diameter and 21 m height Narmada River: - There is Narmada River approximately 7 km and 6 m height masonry pump house to collect and lift water up to from the Kasrawad town. It is Perennial River. No storage treatment works. H.F.L. and River bed level is 152.00 m and 134.00 m structure will be required. There is already water supply from respectively. River bed is at 134.00 m keeping the invert level of intake river Narmada. Hence this source is reliable and sufficient for well 4.5 m below the bed level of the river at 129.50 m. The pump floor augmentation of Kasrawad water supply scheme. But there is (153.50 m) is kept as 1.5 m above the H.F.L. (152.00 m). The suction no intake well in the scheme. level 132.50 m for pumping of raw water is kept as 1.5 m below from river bed level. The difference of suction level and pump floor level is 21.00 m and height of intake well works out to 21.00 m. the diameter of intake well has been decided 6 m on the basis of space required for housing two numbers of 32 HP pumps. Detailed survey was conducted for selection of site. The selected site is nearest, and will have required quantity of water.

Rajpur Narrula Tank : - It is small earthen tank approximately 7 km Narmada River- away from the Rajpur. Presently approximately 0.4 ML water is The population of Rajpur on census year 2011 is 20947.The city is drawn from this source 0.6 ML is drawn from river Narmada. developing and the population is expected to reach about 32320 by the But Narulla Pond dries up in the summer. Hence it can’t be year 2048. The requirement of water in the year 2033 would be about taken as source for Rajpur town. Some Irrigation is also done 2.28 MLD. City water supply is intermittent. Presently water supply from this pond. Dug well has been drilled near this pond to bring source is Narmada River, Narruala pond and Tube wells. Narrula pond water into the Rajpur town. and Tube wells become dry up in summer season and it is insufficient to cater the demand @ 70 Lpcd for present and projected population of Narmada River : - There is Narmada River approximately 20 Rajpur Nagar Parishad. Hence these are not dependable source. km from the Rajpur town. It is perennial river. No storage Narmada river is perennial river and it is sufficient source. structure will be required. There is already water supply from river Narmada. But there is no intake well in the scheme.

57

Subproject Alternative Sources Selected Source and Associated Impacts due to abstraction Town Pansemal Groundwater: Present water supply is based on groundwater, Gomai Dam is selected considering the water availability, quality, and and is not sufficient to cater the present water demand. proximity. Gomai Dam Pansemal water requirement is just about 0.95 MLD, which can be easily met by the Dam.

Dam water sustainability and environmental considerations. The gross storage capacity of Gomai reservoir is 6 MCM, while the water requirement for the project is 0.95 MLD or 0.34 MCM per year, which is about 5.6%.

The manufacturer year of Gomai dam is 2015 and the impoundment of water in Gomai dam was started in the year 2016-17, and water level records are available from 2017. Maximum water level was recorded in the monsoon period of 2017, during which, as per the local information, the dam was overflown for about 18 days.

.

58

59

Salient Feature of River Narmada 41. Narmada basin extends over states of Madhya Pradesh, Gujarat, Maharashtra and Chhattisgarh having an area of 98,796 Sq.km which is nearly 3% of the total geographical area of the country with maximum length and width of 923 & 161 km. It lies between 72°38’ to 81°43’ east longitudes and 21°27’ to 23°37’ north latitudes. It is bounded by the Vindhyas on the north, by the Maikala range on the east, by the Satpuras on the south and by the Arabian Sea on the west. The hilly regions are in the upper part of the basin, and lower middle reaches are broad and fertile areas well suited for cultivation. Narmada is the largest west flowing river of the peninsular India. It rises from Maikala range near Amarkantak in Anuppur district of Madhya Pradesh, at an elevation of about 1057 m. The total length of the river is 1,312 km and for the first 1079 km it flows in Madhya Pradesh and thereafter forms the common boundary between Madhya Pradesh and Maharashtra for 35 km, and Maharashtra and Gujarat for 39 km. In Gujarat State it stretches for 159 km. Its important tributaries are the Burhner, the Banjar, the Sher, the Shakkar, the Dudhi, the Tawa , the Ganjal, the Kundi, the Goi and the Karjan which joins from left whereas the Hiran, the Tendoni, the Barna, the Kolar, the Man, the Uri, the Hatni and the Orsang joins from right. Narmada drains into the Arabian Sea through the Gulf of Khambhat. The major part of basin is covered with agriculture accounting to 56.90%. Water bodies cover 2.95% of the total basin area. The basin spreads over 20 parliamentary constituencies (2009) comprising 15 of Madhya Pradesh, 3 of Gujarat, and 1 each of Chhattisgarh and Maharashtra. The Narmada Water Disputes Tribunal has allocated the Narmada water amongst the States as below: Madhya Pradesh – 18.25 Million Acre Feet Gujarat -- 9.0 Million Acre Feet Rajasthan –0.5 Million Acre Feet Maharashtra – 28.0 Million Acre Feet

Table 10: Salient Features of Narmada River Salient Features of Narmada Basin

Basin Extent Longitude 72° 38’ to 81° 43’ E Latitude 21° 27’ to 23° 37’ N

Length of Narmada River (Km) 1312

Catchment Area (Sq.km.) 98796

Average Water Resource Potential (MCM) 45639

Utilizable Surface Water Resource(MCM) 34500

Live Storage Capacity of Completed Projects (MCM) 17806.0

Live Storage Capacity of Projects Under Construction 6835.00 (MCM)

Total Live Storage Capacity of Projects (MCM) 24641.0

26 (including 8 Gauge No. of Hydrological Observation Stations of CWC site)

No. of Flood Forecasting Stations of CWC 4

Table 11: Volume of Narmada river at Mandleswar (Mandleshwar is located approx. 6 km upstream from Kasrawad, 10 km downstream from Karhi padlya and 60 km upstream from Rajpur from proposed intake location) Unit- MCM Season 2004- 05-06 06-07 07-08 08-09 09-10 10-11 11-12 12-13 13-14 2005

Monsoon 15840 26182 23976 15089 7178 12839 14423 33194 32516 51905

Non- 3937 8058 9749 9665 9322 15227 14038 - 12985 13137 Monsoon

Annual 19777 34240 33724 24754 16500 28066 28461 44849 45501 65042

Source: Integrated Hydrological Data Book (2015), CWC From the above river Discharge Gauge analysis it is observed that minimum volume in Narmada River in last 10 years was 3937 MCM while the combine estimated requirement of all the three towns for the ultimate design year (2048) is 2.77 MCM, which is only considering 22 hour pumping. Hence the Narmada River is adopted as sustainable water source for the proposed water supply schemes. 72. Water quality. Existing water quality of Narmada River is good, as per MPPCB Narmada river water quality comes under category “B” river and is suitable for domestic supply after conventional treatment and disinfection.

Table 12: Narmada River Water Quality Parameter Narmada River Drinking water standards* Temperature, oC 28 - Turbidity, NTU 48.2 5-10 Color, Hazen units 12 5-25 pH 8.18 6.5-8.5 Suspended solids 06 750 – 2000 Total dissolved solids (mg/l) 196 500-2000 Chlorides (mg/l) 18 250-1000 Total Coliform 140 10 Source: Sampling survey 28/06/2014 by Design consultant Team * standards prescribe lower and higher values for parameters, except pH; lower value is the ‘desirable limit’ while higher value is the ‘permissible limit in the absence of alternate source’; there is only lower value for parameters which have no relaxation.

Table 13: Gomai Dam Water Quality Parameter Gomai River Drinking water standards* Turbidity, NTU 0.62 5-10 pH 7.48 6.5-8.5 Electrical conductivity (µs/cm) 620 750 – 2000 Total dissolved solids (mg/l) 372 500-2000 Total alkalinity (mg/l) 196 - Total hardness (mg/l) 192 300-600 Phosphate (as P) 0.008 75-200 61

Parameter Gomai River Drinking water standards* Chlorides (mg/l) 39.98 250-1000 Sodium (mg/l) 14 Sulphates (mg/l) 4.62 200-400 Fluoride (mg/l) 1.06 1-1.5 Nitrate (mg/l) 1.62 45-100 Source: Sampling survey by Design consultant team * standards prescribe lower and higher values for parameters, except pH; lower value is the ‘desirable limit’ while higher value is the ‘permissible limit in the absence of alternate source’; there is only lower value for parameters which have no relaxation.

42. Use of Chlorine as disinfectant. It is proposed to use chlorine at WTPs for disinfection of treated water prior to supply to consumers. There is invariably a safety risk when chlorine is handled. Safety precautions are necessary to ensure the safety of workers and citizens. To avoid any risk, the chlorination facility will be provided with the following:

(i) Chlorine neutralization pit with a lime slurry feeder (ii) Proper ventilation, lighting, entry and exit facilities (iii) Facility for isolation in the event of major chlorine leakage (iv) Personal protection and safety equipment for the operators in the chlorine plant (v) Provide training to the staff in safe handling and application of chlorine; this shall be included in the contract of Chlorinator supplier (vi) Supplier of Chlorinator equipment shall provide standard operating manual for safe operation and as well as maintenance and repairs; preferably these shall be provided both in English and Languages

43.

44. Sensitive project locations. None of the subproject components are located in the forest areas, nor is any pipeline aligned through the forests.

45. Similarly proposed works in the river bed (intake) may damage the river bed, lead to degradation of water quality due to increase in turbidity and contamination from fuels and lubricant used in construction work. Increase in silt content and water turbidity, chemical quality can affect the aquatic life. Measures are included in the EMP to avoid, minimize these impacts.

46. Removal of trees and vegetation will be minimize by best alignment and layout planning of facilities, however, this cannot be avoided fully. Appropriate measures in terms of compensatory tree plantation is included in the EMP.

47. Utilities. Telephone lines, electric poles and wires, water lines within the proposed project locations may require to be shifted in few cases. To mitigate the adverse impacts due to relocation of the utilities, the contractor, in collaboration with ULB will be required to implement appropriate measures. These are given in the EMP.

48. Site selection of construction work camps, stockpile areas, storage areas, and disposal areas. Priority is to locate these near the project location. However, if it is deemed necessary to locate elsewhere, sites to be considered will not promote instability and result in destruction of property, vegetation, irrigation, and drinking water supply systems. Residential areas will not be considered for setting up construction camps to protect the human environment (i.e., to curb accident risks, health risks due to air and water pollution and dust, and noise, and to prevent social conflicts, shortages of amenities, and crime). Extreme care will be taken to avoid disposals near forest areas, water bodies, or in areas which will

49. Site selection of sources of materials. Significant quantities of coarse aggregate and 62 fine aggregate will be required for construction works. Requirement of gravel is limited. Contractor should procure these materials only from the quarries permitted/licensed by Mines and Geology Department. Contractor should, to the maximum extent possible, procure material from existing quarries, and creation of new quarry areas should be avoid as far as possible. It will be the construction contractor’s responsibility to verify the suitability of all material sources and to obtain the approval of Department of Mines & Geology and local revenue administration.

B. Environmental Audit of Existing Water Treatment Plant 50. There is an existing WTP in Kasrawad of capacity 3.12 MLD, which will be used for the project with necessary improvements. At present no improvements or rehabilitation of this existing WTP is proposed, however, the working of WTP will be further reviewed by DBO Contractor during detailed design phase, and improvements, if any required, will be undertaken. As per the ADB SPS 2009, this is an associated facility and therefore the component operation shall comply with the ADB and applicable environmental laws of India. A review of environmental performance of WTP is conducted to (i) assess the compliance of the existing WTP with environmental legislations; (ii) improve environmental performance; and (iii) increase the Kasrawad Nagar Parishad knowledge, thus increasing its ability to continually improve and minimize future potential liabilities. A more detailed environmental audit and risk assessment shall be carried out during detailed design stage. Treated water quality laboratory report of WTP (Appendix 14) shows that all the tested physio-chemical parameters are in compliance with the drinking water standards.

Table 14: Salient Features of Kasrawad WTP Location Near Nava Todi road Start of operation (year) 2002 Owned by Kasrawad Nagar Parishad Capacity 3.12 million liters per day (MLD) Water supply source Narmada River Water treatment process Treatment process: The treatment process is conventional, and has following units: Coagulation flocculation, chemical dosing, filtration. Materials: All civil structures are made of reinforced cement concrete, and mechanical units like the clariflocculator bridge, etc. are of mild steel. Backwash water and -filter backwash water is let into open drains as there is no sludge management recycling of backwash into inlet - the settled sludge from the bottom of the clarifiers is periodically flushed into the drains. -This practice of discharge of backwash and sludge directly into the drains, wastes water, pollutes and silts receiving water bodies. -the untreated backwash and sludge flushing ultimately reaches disposed into nearby water body which is flowing near the site. Chlorination system Presently Chlorination system is not functioning, because ULB staff is not well aware of working of Chlorination system. Also Chlorine dosage system is not proper; there are no safety precautions in place. No safety systems like leak detection or emergency alarm or lime slurry pit available in the facility. Operators are not aware of safety measures or actions to be performed during any emergency. safety equipment like masks and oxygen cylinders are provided at the facility, but are not in usable condition. There have no instances of any chlorine gas leakage till date as reported by the 63

local WTP staff.

Table 15: Compliance with Applicable National and State Regulations Act / Rule Clearance requirement Compliance Status of WTP EIA Notification The EIA Notification of 2006 and N/A 2009 (replacing the EIA Notification of 1994) states that Environmental clearance is not environmental clearance is required as WTPs are not listed in required for certain defined the EIA Notification’s “Schedule of activities/projects. Projects Requiring Prior Environmental Clearance” Manufacture, Storage of chlorine (threshold N/A Storage, and Import quantity greater than 10 tons will of Hazardous require clearance from Madhya Normally 8 tonners (of capacity Chemical Rules, Pradesh Pollution Control Board 900 kg each) are stored at the 1989 (MPPCB). However, PMU needs site, which is less than 10 tons to liaise with the MPPCB if there are any changed to this statute requirement Water (Prevention Consent to operate from MPPCB Non-compliant and Control of At present there is no Consent Pollution) Act of obtained from the MPPCB for this 1974, Rules of 1975, plant. This is mandatory and and amendments needs to be obtained.

Air (Prevention and Control of Pollution) Act of 1981, Rules of 1982 and amendments. Environment Emissions and discharges from (Protection) Act, 1986 the facilities to be created, and CPCB refurbished, or augmented shall Environmental comply with the notified Standards standards. a. Air emissions No significant air emissions.

b. Effluent Non-compliant

Filter backwash water is let into open drains and the settled sludge from the bottom of the clarifiers is periodically flushed into open drains directly that ultimately reach river Bebus. A proper treatment and disposal is necessary Forest (Conservation) As per Rule 6, every user N/A Act, 1980 and Forest agency, who wants to use any Conservation Rules, forest land for non-forest WTP is not located in notified 2003 as amended purposes shall seek approval of forest lands. the central government.

51. Based on the above review, the following table details out the issues of concerns and provides for Corrective Action Plan (CAP) which needs to be implemented as part of the project. 64

Table 16: Corrective Action Plan for Environmental Compliance of Existing WTP in Kasrawad Concern Action Required Timeline Responsible Agency and Funding Source Statutory non-compliance : Obtain CTO from CTO to be obtained Kasrawad Nagar WTP is operating without MPPCB prior to operation Parishad, and mandatory consent to operate MPUDC (CTO) from Madhya Pradesh Pollution Control Board Poor backwash wastewater - Provision of backwash Issues of concerns to MPUDC and be addressed by the MPUSIP funds and sludge management – recirculation system – to start of operation of discharged untreated into avoid discharge and also Rehabilitated WTP natural drains to recover raw water -Provision of sludge collection, thickening, drying and reuse/disposal system

Poor handling of chlorination Improvements to Same as above MPUDC and system and lack of safety chlorination already MPUSIP funds measures included in the subproject.

C. Construction Impacts 52. Construction works. Civil works in the project include linear excavation for laying pipes along the roads, placing pipes in the trench and refilling with the excavated soil. The trenches will be of 0.4 m – 0.7 m wide and 0.8 to 1 m depth. Subsequent to completion of works, road reinstatement will be undertaken by the contractor as part of the civil works. The roads in the core city area of all the towns are very narrow and congested with pedestrians and vehicles (mainly 2-wheelers), while the roads in outer areas are wide.

53. Earth work excavation will be undertaken by machine (backhoe excavator) or manually and include danger lighting and using barricades at every 100 m.. Sufficient care will be taken while laying so that existing utilities and cables are not damaged and pipes are not thrown into the trenches or dragged, but carefully laid in the trenches. As trenches are a maximum of 1.2 m, there is no risk of collapse of trenches or risk to surrounding buildings. Once they are laid, pipes will be joined as per specification and then tested for any cracks of leakages. The minimum working hours will be 8 hours daily, the total duration of each stage depends on the soil condition and other local features. About 95% of the excavated soil will be used for refilling the refilling the trench after placing the pipe and therefore residual soil after pipe laying and refilling is not significant. This excel soil shall be used for construction.

54. Other civil works in the subproject include construction of intake cum pump house on the river bank, raw water pumping station including laying of water intake pipe, water treatment plants, overhead tanks identified sites. These works will be confined to sites, and construction will include general activities like excavation for foundation, construction of foundations, columns, walls and roof in cement concrete and masonry, and fixing of mechanical and electrical fixtures, etc.

55. Although construction of these project components involves quite simple techniques of civil work, the invasive nature of excavation and the project locations in the built-up areas of 65 the town where there are a variety of human activities, will result in impacts to the environment and sensitive receptors such as residents, businesses, and the community in general. The following are anticipated impacts, which are temporary and for short duration:

(i) Dust and air emissions from construction activities and equipment / vehicles affecting the ambient air quality (ii) Impacts on natural drainage, surface water bodies due to disposal of construction waste and silt / chemical laden run off from work areas (iii) Impacts on river eco-system due to river bed construction (iv) Impacts due to disposal of surplus soil, construction waste, debris etc., (v) Impacts due to noise and vibration from consultation activities (vi) Impacts due to collection of groundwater in trenches & disposal of the same (vii) Impact/public inconvenience/ accessibility issues due to excavation on public roads (narrow old town roads), movement of trucks carrying construction material (viii) Impacts on business, activities, people due to loss/restricted access to public/private/business/sensitive areas (schools, hospitals), etc., (ix) Occupation health and safety impacts on workers (x) Health Impacts due to removal of existing AC (asbestos cement) pipes (xi) Community health and safety impacts due to construction in an urban area (xii) Impacts due to establishment/operation of temporary construction camps

56. The above impacts are typical for construction in urban areas, and therefore are common to all the four subproject towns. These are negative but short-term and reversible by mitigation measures. There are well-developed and proven measures and construction practices to avoid, mitigate and/or minimize these impacts to acceptable levels. These measures are given in the construction phase EMP applicable to all four towns.

D. Operation and Maintenance Impacts

57. Operation and Maintenance of the water supply system will be carried out by the DBO Contractor for 10 years, and after which the respective municipalities will operate and maintain the infrastructure. During the system design life (15/30 years for mechanical/civil components),it shall not require major repairs or refurbishments and should operate with little maintenance beyond routine actions required to keep the equipment in working order. The stability and integrity of the system will be monitored periodically to detect any problems and allow remedial action if required. Any repairs will be small-scale involving manual, temporary, and short-term works involving regular checking and recording of performance for signs of deterioration, servicing and replacement of parts.

58. Recurrence of pipe bursting and leakage problems can be managed by the leak detection and water auditing surveys. The ULBs will be required to ensure that the leak detection and rectification time is minimized.

59. Provision for recirculation system for filter backwash – backwash water from filter beds will be sent to a storage tank, and after allowing adequate time for settlement of solids, clarified water will be pumped to WTP inlet. This arrangement will avoid pollution and also minimize wastage of water. Water treatment process will generate sludge from sedimentation of particulate matter in raw water, flocculated and precipitated material resulting from chemical coagulation, residuals of excess chemical dosage, plankton etc; and waste from rinsing and back washing of filter media containing debris, chemical precipitates, straining of organic debris and plankton. Accumulated sludge from Tube Settler, filter backwash etc., will be disposed-off at sludge drying beds for natural drying. Dried sludge will be disposed off in a land fill or used as soil conditioner if it is suitable 66

E. Project benefits 60. During the construction phase, there are likely to be positive impacts through employment generation, increase in local revenue from the project activities. During the operation phase also, there is potential for employment generation, though limited, as the improved and expanded water infrastructure requires additional workforce.

61. The citizens of Pansemal, Rajpur, Karahi Padliya & Kasrawad will be the major beneficiaries of the improved water supply system, as they will be provided with a constant supply of better quality water, piped into their homes at an appropriate pressure. The project will improve the over-all health condition of the towns as water borne diseases will be reduced, so people should spend less on healthcare and lose fewer working days due to illness, so their economic status should also improve, as well as their overall health. This should also improve the environment of these areas, should deliver major improvements in individual and community health and well-being.

67

VII. PUBLIC CONSULTATION AND INFORMATION DISCLOSURE

A. Overview

62. The active participation of stakeholders including local community, NGOs/CBOs, and the media in all stages of project preparation and implementation is essential for successful implementation of the project. It will ensure that the subprojects are designed, constructed, and operated with utmost consideration to local needs, ensures community acceptance, and will bring maximum benefits to the people. Public consultation and information disclosure is a must as per the ADB policy.

63. Most of the main stakeholders have already been identified and consulted during preparation of this IEE, and any others that are identified during project implementation will be brought into the process in the future. Primary stakeholders of the subproject are: residents, shopkeepers and businesspeople who live and work alongside the roads in which network improvements will be provided and near sites where facilities will be built (WTP and over head tanks), and government and utility agencies responsible for provision of services in Pansemal, Rajpur, Karahi Padliya & Kasrawad ,WRD, Revenue Department, Forest Department (FD), and MPPCB, etc., Secondary stakeholder are: NGOs and CBOs working in the area, community representatives, beneficiary community in general, government agencies, the executing and implementing agencies (MPUDC, PMU and PIUs), Government of India and the ADB. Details of Consultation at each town enclosed in appendix 8.

B. Public Consultation

64. The public consultation and disclosure program is a continuous process throughout the project implementation, including project planning, design and construction.

1. Consultation during Project Preparation

65. Institutional consultations were conducted with the relevant Governmental Departments such as WRD, RD, MPPCB, FD, etc. The subproject proposals are formulated in consultation with Pansemal, Rajpur, Karahi Padliya & Kasrawad Nagar Parishads to suit the requirements of the respective towns.

66. Focus-group discussions with affected persons and other stakeholders were conducted to learn their views and concerns. The household survey was designed, conducted and executed with multiple objectives to identify areas requiring critical interventions, set priorities, assess ground realities, gather information and engage the local communities, build trust and seek first hand insights. The goal is to accelerate the process of addressing the root causes and implement the most appropriate development processes using sustainable.

67. The goal of the survey was to gather data, insights and information that will help us to prepare an Execution Plan for the water supply augmentation scheme for all the four towns. The Survey was conducted with the help of members of the local communities and residents of the area under supervision and guidance.

68. The people are willing to extend their cooperation as the activities are proposed to improve the water supply service levels and the living standards. Stakeholder expressed their concern regarding water charges, affordability, disturbance and loss of business due to the work in market area (dust, road closure etc.). The project team explained the proposed mitigation measures to mitigate / minimize such issues.

68

2. Consultation during construction

69. Prior to start of construction, ULB and PIU with the assistance of PMC will conduct information dissemination sessions at various places and solicit the help of the local community, leaders/prominent for the project work. At each ward/neighborhood level, focus group meetings will be conducted to discuss and plan construction work with local communities to reduce disturbance and other impacts.

70. A constant communication will be established with the affected communities to redress the environmental issues likely to surface during construction phases and also regarding the grievance redress mechanism. ULB/PIU and PMC will organize public meetings and will appraise the communities about the progress on the implementation of EMP. Meeting will also be organized at the potential hotspots/sensitive locations before and during the construction.

C. Information Disclosure

71. Executive summary of the IEE will be translated in Hindi and made available at the offices of PMU, PIU, Nagar Parishad offices, and also displayed on their notice boards. Hard copies of the IEE will be accessible to citizens as a means to disclose the document and at the same time creating wider public awareness. Electronic version of the IEE in English and Executive Summary in Hindi will be placed in the official website of the MPUDC, PMU after approval of the IEE by Government and ADB. Stakeholders will also be made aware of grievance register and redress mechanism.

72. Public information campaigns to explain the project details to a wider population will be conducted. Public disclosure meetings will be conducted at key project stages to inform the public of progress and future plans. Prior to start of construction, the PMU/PIU will issue Notification on the start date of implementation in local newspapers A board showing the details of the project will be displayed at the construction site for the information of general public.

73. Local communities will be continuously consulted regarding location of construction camps, access and hauling routes and other likely disturbances during construction. The road closure together with the proposed detours will be communicated via advertising, pamphlets, radio broadcasts, road signage, etc.

69

VIII. GRIEVANCE REDRESS MECHANISM

A. Project Specific Grievance Redress Mechanism

74. A program-specific grievance redress mechanism (GRM) shall be established to receive, evaluate, and facilitate the resolution of AP’s concerns, complaints, and grievances about the social and environmental performance at the level of the project. The following GRM provides a time-bound and transparent mechanism to voice and resolve social and environmental concerns linked to the project.

75. A common GRM will be in place for social, environmental, or any other grievances related to the project. The GRM will provide an accessible and trusted platform for receiving and facilitating resolution of affected persons’ grievances related to the program. The multi-tier GRM for the project is outlined below, each tier having time-bound schedules and with responsible persons identified to address grievances and seek appropriate persons’ advice at each stage, as required. ULB-wide public awareness campaigns will ensure that awareness on grievance redress procedures is generated through the campaign.

76. Who can complain: A complaint may be brought by persons who are, or could be, “directly, indirectly, materially, and adversely” affected by the project. A complaint can be submitted on behalf of the affected person/people by a representative, provided that he or she identifies the affected person/people and includes evidence of the authority to act on their behalf.

77. What the Grievance/Complain should contain: Any concerns pertaining to safeguard compliance - environment, involuntary resettlement, indigenous people, design related issues, compensation, service delivery or any other issues or concerns related to the project. The complaint must contain name, date, address/contact details of the complainant, location of the problem area, along with the problem.

78. Where to file a Complaint: Complainants will have the flexibility of conveying grievances/suggestions by dropping grievance redress/suggestion forms in complaints/suggestion boxes to be installed by project at respective Nagar Parishad Offices, PIU offices or by e-mail or by writing in a complaints register in the PIU offices or at construction site offices.

79. How to file a Complaint: The application should be precise and specific. The application can be sent either by post or through electronic means or deliver personally. A sample grievance form is at Appendix 9.

(i) Offline System - The application can be made on the application form available at all accessible places (NPs/ Office of PIUs/ construction site offices). The application should have the name and complete postal address of the applicant. (ii) Online System - Grievances pertaining to the implementation of the project can also be filed online at the website of MPUDC/PMU or by e-mails.

80. Documentation: Documentation of the complaints is important and must contain name of the complainant, date of receipt of the complaint, address/contact details of the person, location of the problem area, and how the problem was resolved. PMU with the support of PIU will have the overall responsibility for timely grievance redress, and for registration of grievances, related disclosure, and communication with the aggrieved party. All the documents made available to the public at the community level (at ward offices) and will include information on the contact number, address and contact person for registering grievances, and will be disseminated throughout the project area by the PIU.

81. Grievance/Problem Redress through Participatory Process: Efforts must be made 70 by the PIU with the support of safeguard consultants to resolve problems amicably, conflicts through participatory process with the community and the Nagar Parishads. In case of grievances that are immediate and urgent in the perception of the complainant, the Contractor, and supervision personnel from the PIU will provide the most easily accessible or first level of contact for the quick resolution of grievances. Contact phone numbers and names of the concerned staff and contractors, will be posted at all construction sites at visible locations.

82. Following process will be followed:

(i) 1st level grievance. In case of grievances that are immediate and urgent in the perception of the complainant, PMC supervising staff will direct the contractor to and ensures that it is resolved. If the grievance is not under the contractor scope, but under the program, PMC (field office) will resolve this issue. All the grievances should be resolved within 3 days of receipt of a complaint/grievance.

(ii) 2nd level grievance. All grievances that cannot be redressed at first level within 3 days will be brought to the notice of PIU and PMC Assistant Environmental Specialist. PIU will review the grievance and act appropriately to resolve it within 10 days of receipt.

(iii) 3rd level grievance. All the grievances that are not addressed at 2nd level by PIU within in 10 days of receipt will be brought to the notice of notice of the Grievance Redressal Committee (GRC)3. GRC will meet twice a month and determine the merit of each grievance brought to the committee. The GRC will resolve the grievance within 1 month of receiving the complaint. All decisions taken by the GRC will be communicated to complainant by the Nodal Officer.

83. The project GRM notwithstanding, an aggrieved person shall have access to the country's legal system at any stage, and accessing the country's legal system can run parallel to accessing the GRM and is not dependent on the negative outcome of the GRM. Alternatively, if the grievance is related to land acquisition, resettlement & rehabilitation4, the APs can approach the Land Acquisition, Rehabilitation and Resettlement Authority (LARRA) of Madhya Pradesh, established under the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation, and Resettlement Act, 2013.

84. Record-keeping. PIU will keep records of grievances received, corrective actions taken and the final outcome. The number of grievances recorded and resolved and the outcomes will be displayed/disclosed in the PIU office, ULB offices, and on the web.

3 Grievance redress committee (GRC) will be formed at town-level with members composed of: ULB Chairperson, ULB CMO, Environmental Specialist of PMC, PIU Dy.PM and PIU Community Development Officer. 4 the Authority admits grievance only with reference to the LA and R&R issues under the new Act 71

IX. ENVIRONMENTAL MANAGEMENT PLAN

A. Implementation Arrangements

85. Urban Development and Environment Department (UDED) of Government of Madhya Pradesh will be the Executing Agency for the Program, responsible for management, coordination and execution of all activities funded under the loan. Implementing Agency will be the recently established Madhya Pradesh Urban Development Company (MPUDC), a wholly owned subsidiary of GoMP. A central Project Management Unit (PMU) attached to MPUDC will be responsible for implementing the MPUSIP. The PMU will be supported by Program Implementation Units (PIUs) with flexibility to redeployment depending upon the implementation requirements.

86. The PMU and PIUs will be supported by several teams of Design Consultants in preparation of preliminary engineering designs.

87. Water Resource Review Committee (WRRC) is constituted to undertake a thorough review of the source when recommended by the Design Consultant in regard to techno- economic feasibility and sustainability especially ensuring climate change resilience, and Technical Review Committee (TRC) to review and approve the preliminary designs developed by the Design Consultants.

88. Program Management Consultant (PMC) centrally located in PMU and with field teams located in PIUs shall be responsible for implementation of the Program. All infrastructure contracts will be procured through performance-based contracts (PBCs) and include build- operate (BO) framework. Based on the preliminary designs prepared by Design Consultants, the DBO (design-build-operate) Contractor will design, construct, commission and operate for 10 years, after which it will be transferred to the respective ULB.

89. Two Committees - an Empowered Committee cum Executive Committee and a Technical Clearance and Tender Committee have been constituted by the Government to be responsible for effective and timely implementation of the Program.

90. Safeguards. At PMU, there will be two safeguard specialists: (i) Project Officer (Environment) and (ii) Social & Gender Offer, who will responsible for compliance with the environmental and social safeguards in program implementation. PO (Environment) will have overall responsibility in implementation of the investment program as per the Environmental Assessment & Review Framework (EARF) agreed between ADB and the government. At individual subproject level, PO will ensure that environmental assessment is conducted, and a project-specific is prepared and implemented, and the compliance, and corrective actions, if any are reported as required.

B. Environmental Management Plan

91. An environmental management plan (EMP) has been developed to provide mitigation measures to reduce all negative impacts to acceptable levels.

92. The EMP will guide the environmentally-sound construction of the subproject and ensure efficient lines of communication between MPUDC, project management unit (PMU), project implementing unit (PIU), consultants and contractors. The EMP will (i) ensure that the activities are undertaken in a responsible non-detrimental manner; (i) provide a pro-active, feasible and practical working tool to enable the measurement and monitoring of environmental performance on site; (ii) guide and control the implementation of findings and recommendations of the environmental assessment conducted for the subproject; (iii) detail 72 specific actions deemed necessary to assist in mitigating the environmental impact of the subproject; and (iv) ensure that safety recommendations are complied with. The EMP includes a monitoring program to measure the environmental condition and effectiveness of implementation of the mitigation measures. It will include observations on- and off-site, document checks, and interviews with workers and beneficiaries.

93. The contractor will be required to submit to PIU, for review and approval, a site environmental plan (SEP) including (i) proposed sites/locations for construction work camps, storage areas, hauling roads, lay down areas, disposal areas for solid and hazardous wastes; (ii) specific mitigation measures following the approved EMP; (iii) monitoring program as per SEP; and (iv) budget for SEP implementation. No works are allowed to commence prior to approval of SEP.

94. A copy of the EMP/approved SEP will be kept on site during the construction period at all times. The EMP included in the bid and contract documents. Non-compliance with, or any deviation from, the conditions set out in this document constitutes a failure in compliance.

95. For civil works, the contractor will be required to (i) carry out all of the mitigation and monitoring measures set forth in the approved SEP; and (ii) implement any corrective or preventative actions set out in safeguards monitoring reports that the employer will prepare from time to time to monitor implementation of this IEE and SEP. The contractor shall allocate budget for compliance with these SEP measures, requirements and actions.

96. The following tables show the potential environmental impacts, proposed mitigation measures and responsible agencies for implementation and monitoring.

73

Table 17: Design Stage Environmental Management Plan Field Anticipated Impact Mitigation Measures Responsible for Cost and Source Implementation of Funds Design of water Unsustainable • Recovering wash water from treatment process These measures Part of project supply system source; resource & • Treatment and reuse of sludge from treatment process are already costs energy use • Minimizing water losses from pipelines by perfect jointing and included in the alignments using appropriate techniques preliminary • Designing the entire system to maintain optimal flow and terminal designs. pressure, and optimizing the overall energy usage • Reducing the incidence of water borne diseases by providing DBO Contractor 100% population including urban poor with potable water supplies (DBOC)to follow, • Improve water use efficiency and reduce water wastage at enhance where household level by recording and monitoring the water usage, and possible. charging the consumers as per usage; due consideration to urban poor PMU to ensure • Minimize unaccounted for water (UFW) losses using district compliance. metered area approach with flow meter and pressure logging arrangements to identify and rectify the leaks, and unauthorized connections • Using low-noise and energy efficient pumping systems • Implement corrective action plan for existing WTP in Kasrawad, and include all corrective actions in the project design and implementation • During the design, construction, and operation of the project, apply pollution prevention and control technologies and practices consistent with international good practice, as reflected in internationally recognized standards such as the World Bank Group’s Environment, Health and Safety Guidelines (IFC’s General EHS Guidelines5 and Sector Specific (Water and Sanitation) Guidelines6). Water abstraction Project sustainability • Obtain permission from Water resources department, GoMP PMU & respective No costs; scope from Narmada & water use conflicts • Karahi Padlya, Kasrawad and Rajpur- permission / water Nagar Parishads of IA river and Gomai allocation for water abstraction from Narmada River and (process already Dam construction of intake initiated)

5https://www.ifc.org/wps/wcm/connect/554e8d80488658e4b76af76a6515bb18/Final%2B-%2BGeneral%2BEHS%2BGuidelines.pdf?MOD=AJPERES 6 https://www.ifc.org/wps/wcm/connect/e22c050048855ae0875cd76a6515bb18/Final%2B-%2BWater%2Band%2BSanitation.pdf?MOD=AJPERES

74

Field Anticipated Impact Mitigation Measures Responsible for Cost and Source Implementation of Funds • Pansemal – permission / water allocation for water abstraction from Gomai Dam and construction of intake Waste generation Environmental • Obtain consent from MPPCB for WTPs at Pansemal, Rajpur, PMU / Nagar No costs; scope from WTP pollution Karahi Padliya & Kasrawad prior to start of construction Parishad; DBOC to of IA & DBO operations prepare application, and assist as required Chlorine usage as Chlorine handling & • Provide the following measure at the chlorine application unit: These measures Project Costs disinfectant at application risk – o Chlorine neutralization pit with a lime slurry feeder are already WTPs health &safety risk to o Proper ventilation, lighting, entry and exit facilities included in the workers and general o Facility for isolation in the event of major chlorine leakage (if preliminary public needed) designs. o Personal protection and safety equipment for the operators in the chlorine plant DBOC to follow, o Provide training to the staff in safe handling and application of enhance where chlorine; this shall be included in the contract of Chlorinator possible. supplier o Supplier of Chlorinator equipment shall provide standard PMU to ensure operating manual for safe operation and as well as compliance. maintenance and repairs; preferably these shall be provided both in English and Hindi Languages

Table 18: Pre-Construction State Environmental Management Plan Field Anticipated Impact Mitigation Measures Responsible for Cost and Implementation Source of Funds EMP Unsatisfactory • Appoint EHS supervisor and designate 1 EHS coordinator (among DBO contractor Cost for Implementation & compliance to EMP the technical staff) in each town implementation reporting • Ensure that all pre-construction activities are complete prior to start of mitigation of construction work measures • Ensure timely submission of monitoring reports responsibility of contractor. Utilities Damage/ disturbance • Identify and include locations of utilities in the detailed DBOC with PIU Project costs – to telephone lines, designs/drawings to prevent unnecessary disruption of services collaboration. general electric lines, water • Prepare a contingency plan to include actions to be taken in case PMU to ensure construction lines in project area of unintentional interruption of services. compliance practice 75

Field Anticipated Impact Mitigation Measures Responsible for Cost and Implementation Source of Funds EMP Unsatisfactory • Appoint EHS supervisor and designate 1 EHS coordinator (among DBO contractor Cost for Implementation & compliance to EMP the technical staff) in each town implementation reporting • Ensure that all pre-construction activities are complete prior to start of mitigation of construction work measures • Ensure timely submission of monitoring reports responsibility of contractor. Construction Disturbance / • No construction material storage/ancillary works shall be conducted DBOC with PIU Project costs – works near forest damage to forest in the forest area; this shall be limited to actual construction area collaboration. general areas areas, wildlife and the access roads construction • No labour camps shall be located near forests (maintain minimum PIU/ PMU to practice 1km buffer) ensure • Limit the work to daylight hours only; no work after sunset compliance • No workers /personnel shall enter forest areas; it is the DBOC responsibility to take necessary precautions & prevent workers removing/damaging trees/vegetation, hunting animals • Create awareness among workers on environment & safety • No high noisy works shall be conducted • Barricade the construction area properly so that no wild animals entre the work area Construction Degradation of river • Schedule the works on river bed during summer no-flow period DBOC to follow Project costs – works on river bed course and pollution • Do not disturb river bed except the actual work area; no equipment, general (intake well) machinery shall be operated outside the work area PIU/ PMU to construction • Avoid use of fuels, chemicals & lubricants; ensure no spillage ensure practice • Clean up the area after the completion & prior to the onset of compliance monsoon flow Construction work Conflicts with local • Prioritize barren, waste, infertile, vacant lands within the area, DBOC to identify Part of project camps, stockpile community; • Shall not be located in productive agricultural lands, water bodies, locations following costs areas, storage disruption to traffic natural drainage channels, flood plains & groundwater recharge the criteria areas and waste flow and sensitive areas, forests, vegetative lands, etc. disposal areas receptors • Locate at sites that will not promote instability, flooding and result in PIU to ensure destruction of natural drainage, vegetation, irrigation, & drinking compliance and water supply; approve • For private lands, obtain land owner’s (not lessees) written consent; indicate the requirement for reinstatement to original • Site should have a minimum buffer of 0.5 – 1 km from all socially,

76

Field Anticipated Impact Mitigation Measures Responsible for Cost and Implementation Source of Funds EMP Unsatisfactory • Appoint EHS supervisor and designate 1 EHS coordinator (among DBO contractor Cost for Implementation & compliance to EMP the technical staff) in each town implementation reporting • Ensure that all pre-construction activities are complete prior to start of mitigation of construction work measures • Ensure timely submission of monitoring reports responsibility of contractor. environmentally sensitive areas (eg., residential, socio-cultural areas & water bodies (0.5 km), forests (1km), etc.,) • Take extreme care in selecting sites to avoid direct disposal to water body which will inconvenience the community. • Document site’s pre-project conditions Sources of Extraction of • Obtain material only existing borrow sites/quarries already DBOC to identify Part of project Materials materials can disrupt permitted by the Department of Mines and Geology; sources that have costs natural land contours • If new quarries sites/quarries are necessary, contractor shall be all permits, if and vegetation obtain all necessary permissions as per the law in force. required, obtain resulting in • Contractor to obtain construction materials only after written permits, and accelerated erosion, permission / approval of PIU for respective sources submit to PIU disturbance in natural • Maintain a construction material register at the site drainage patterns, PIU to check and ponding and water approve logging, and water pollution.

Consents, permits, Failure to obtain • Obtain all necessary consents, permits, clearance, NOCs, etc PMU / PIU to Part of project clearances, NOCs, necessary consents, required for the project prior to award of contact or start of civil obtain project costs etc. permits, NOCs, etc. works, as necessary. clearances; DBOC can result to design to provide revisions and/or • Include in detailed designs, drawings and documents all regulatory necessary stoppage of works conditions and provisions, where required assistance

• Contractor to identify & obtain all necessary approvals, including in compliance with labour laws, before start of construction; DBOC to obtain • Contractor to acknowledge in writing to PIU and provide copies of construction all obtained permits, clearance, NOCs, etc. permits &

77

Field Anticipated Impact Mitigation Measures Responsible for Cost and Implementation Source of Funds EMP Unsatisfactory • Appoint EHS supervisor and designate 1 EHS coordinator (among DBO contractor Cost for Implementation & compliance to EMP the technical staff) in each town implementation reporting • Ensure that all pre-construction activities are complete prior to start of mitigation of construction work measures • Ensure timely submission of monitoring reports responsibility of contractor. PIU to ensure

Health risk due to • Obtain details from PHED/NPs on location of underground AC DBOC in Part of project Asbestos Cement exposure to asbestos pipes coordination with costs Pipes materials • Locate the new piper carefully to avoid encountering AC pipes PIU and ULB • Leave the AC pipes undisturbed in the ground.

Table 19: Construction Stage Environmental Management Plan Field Anticipated Impact Mitigation Measures Responsible for Cost and Source of Funds Mitigation EMP Implementation Irreversible impact to • Project manager and all key workers will be DBOC Cost of EMP Implementation Training the environment, required to undergo training on EMP Orientation Training to workers, and implementation including spoils/waste PMC Construction contractor is responsibility of community management, Standard operating procedures and Environmental PMU. (SOP) for construction works; occupational Specialists to conduct health and safety (OH&S), core labor laws, the training Other costs responsibility of applicable environmental laws, etc. contractor. Air Quality Emissions from • Control dust by water sprinkling on exposed DBO Contractor Cost for implementation of construction vehicles, soil, stock stockpiled material on site mitigation measures equipment, and • Barricade area, provide wind sheets responsibility of contractor. machinery used for • Use tarpaulins to cover sand and other loose

78

Field Anticipated Impact Mitigation Measures Responsible for Cost and Source of Funds Mitigation installation of pipelines material when transported by trucks; Air quality monitoring costs are resulting to dusts and • Clean wheels and undercarriage of haul trucks included in the EMP costs of increase in prior to leaving construction site project concentration of • Prevent entry of traffic, public in construction vehicle-related area pollutants such as • Fit all heavy equipment, and machinery with air carbon monoxide, sulfur pollution control devices which are operating oxides, particulate correctly; all the vehicle shall meet the emission matter, nitrous oxides, norms and shall have valid pollution under and hydrocarbons. control (PUC) certificate. • Conduct air quality monitoring as per the monitoring plan. Surface water quality Mobilization of settled • Avoid earthworks during the rainy season DBO Contractor Cost for implementation of silt materials, and • Avoid stockpiling of earth fill especially during mitigation measures chemical contamination the monsoon season unless covered by responsibility of contractor. from fuels and tarpaulins or plastic sheets; lubricants during • Reuse excess spoils & materials in the Water quality monitoring costs installation of pipelines construction as far a possible are included in the EMP costs can contaminate nearby • Identify disposal sites prior to construction & of project surface water quality. dispose construction waste only at designated areas • Install temporary silt traps basins along the drainage leading to the water bodies; • Place storage areas for fuels and lubricants away from any drainage leading to water bodies; • Conduct surface quality inspection according to the Environmental Management Plan (EMP). Noise Levels Increase in noise level • Conduct noise generating activities (eg, cc road DBO Contractor Cost for implementation of due to earth-moving cutting) during day time mitigation measures and excavation • Minimize noise from construction equipment (by responsibility of contractor. equipment, and the using vehicle silencers, fitting jackhammers transportation of with noise-reducing mufflers, and use portable equipment, materials, street barriers to minimize sound impact to and people surrounding sensitive receptor; • Maintain maximum sound level not exceeding

79

Field Anticipated Impact Mitigation Measures Responsible for Cost and Source of Funds Mitigation 80 decibels (DBA) when measured at a distance of 10 m or more from the vehicle/s. • Identify any buildings at risk from vibration damage and avoiding any use of pneumatic drills or heavy vehicles in the vicinity; • Consult local communities in advance to avoid working at sensitive times, such as religious and cultural festivals. Landscape and aesthetics Impacts due to excess • Stockpiles, lubricants, fuels, and other materials DBO Contractor Cost for implementation of excavated earth, should be located away from steep slopes and mitigation measures excess construction water bodies; responsibility of contractor. materials, and solid • Avoid stockpiling any excess spoils; dispose waste such as removed immediately to designated areas concrete, wood, • Domestic solid waste generated at construction packaging materials, camps and work sites shall be properly empty containers, managed (collected, segregated, disposed spoils, oils, lubricants, properly); waste should not burned and other similar items. • Residual and hazardous wastes such as oils, fuels, and lubricants shall be disposed through approved recyclers • Environmentally restore the work sites to at least pre-project conditions; PIU to approve in writing that site is restored Ecological Resources – Loss of vegetation and • Avoid removal of vegetation / tree cutting DBO Contractor Cost for implementation of Terrestrial tree cover • If unavoidable, minimize as far as possible, and mitigation measures obtain tree-cutting permit responsibility of contractor. • Plant 10 trees for every one cut Land use Environmental Issues • The impact due to change in land use will be Not applicable Not applicable due to land use change negligible due to this project. Accessibility Traffic problems and • Confine work areas along the roads to the DBO Contractor Cost for implementation of conflicts near project minimum possible extent; all the activities, mitigation measures locations and haul road including material & waste/surplus soil stocking responsibility of contractor. should be confined to this area. Proper barricading should be provided; avoid material/surplus soil stocking in congested areas – immediately remove from site/ or brought to the as and when required 80

Field Anticipated Impact Mitigation Measures Responsible for Cost and Source of Funds Mitigation • Leave spaces for access between mounds of soil; • Provide walkways and metal sheets where required to maintain access across for people and vehicles; • Plan transportation routes so that heavy vehicles do not use narrow local roads, except in the immediate vicinity of delivery sites; • Schedule transport and hauling activities during non-peak hours; • Keep the site free from all unnecessary obstructions; • Drive vehicles in a considerate manner; • Coordinate with Traffic Police for temporary road diversions, where necessary, and for provision of traffic aids • Notify affected area by public information notices, providing sign boards informing nature and duration of construction works and contact numbers for concerns/complaints. • For works in very narrow roads o Inform the affected local population 1-week in advance about the work schedule o Plan and execute the work in such a way that the period of disturbance/ loss of access is minimum. o Provide pedestrian access in all the locations until normalcy is restored. Provide wooden/metal planks over the open trenches at each house to maintain the access. Socio-Economic – Impede the access of • Do not obstruct access; provide temporary DBO Contractor Cost for implementation of Income. residents and access, by leaving spaces in excavation, mitigation measures customers to nearby provide walkways and metal sheets for people responsibility of contractor. shops and vehicles where necessary to continue business • Increase workforce in the areas with 81

Field Anticipated Impact Mitigation Measures Responsible for Cost and Source of Funds Mitigation predominantly institutions, place of worship, business establishment, hospitals, and schools; • Consult businesses and institutions regarding operating hours and factoring this in work schedules Socio-Economic – Generate temporary • Employ local persons in construction work if DBO Contractor Cost for implementation of Employment employment and manpower is available mitigation measures increase in local responsibility of contractor. revenue Occupational Health and Occupational hazards • Comply with all national, state and local core DBO Contractor Cost for implementation of Safety which can arise during labor laws (see Appendix 6of this IEE) mitigation measures work • Following internationally recognized health responsibility of contractor. and safety standards such as the World Bank Group’s Environment, Health and Safety Guidelines (IFC’s General EHS Guidelines7 and Sector Specific (Water and Sanitation) Guidelines8). • Implement site-specific occupational health and safety (OH&S) measures, such as the following • Provided personal protective equipment (PPE) to workers(like helmet, gumboot, safety belt, gloves, nose musk and ear plugs), and ensure that they are used • Conduct OH&S training workers/staff • Do no employ ad-hoc work procedures, follow best & acceptable work practices • Document work-related accidents • Provide qualified & easily accessible first-aid facilities all times at all sites • Secure all installations from unauthorized intrusion and accident risks; • Provide potable drinking water;

7https://www.ifc.org/wps/wcm/connect/554e8d80488658e4b76af76a6515bb18/Final%2B-%2BGeneral%2BEHS%2BGuidelines.pdf?MOD=AJPERES 8 https://www.ifc.org/wps/wcm/connect/e22c050048855ae0875cd76a6515bb18/Final%2B-%2BWater%2Band%2BSanitation.pdf?MOD=AJPERES

82

Field Anticipated Impact Mitigation Measures Responsible for Cost and Source of Funds Mitigation • Provide clean eating areas where workers are not exposed to hazardous or noxious substances; • Provide H&S orientation training to all workers to ensure that they are apprised of the basic site rules of work at the site, PPEs, and preventing injuring to fellow workers; • Ensure that visitor/s do not enter hazard areas unescorted • Ensure the visibility of workers through their use of high visibility vests when working in or walking through heavy equipment operating areas; • Ensure moving equipment is outfitted with audible back-up alarms; • Mark and provide sign boards for hazardous areas such as energized electrical devices and lines, service rooms housing high voltage equipment, and areas for storage and disposal. Signage shall be in accordance with international standards and be well known to, and easily understood by workers, visitors, and the general public as appropriate; and • Disallow worker exposure to noise level greater than 85 dBA for a duration of more than 8 hours per day without hearing protection. The use of hearing protection shall be enforced actively. Community Health and Traffic accidents and • Plan routes to avoid times of peak-pedestrian DBO Contractor Cost for implementation of Safety. vehicle collision with activities and high risk areas. mitigation measures pedestrians during • Prevent public entry in to work areas through responsibility of contractor. material and waste barricading and security guards transportation • Maintain regularly the vehicles and minimize potentially serious accidents caused by equipment malfunction or premature failure. • Provide road signs and flag persons to warn of on-going trenching activities. • In very narrow streets, conduct work section- 83

Field Anticipated Impact Mitigation Measures Responsible for Cost and Source of Funds Mitigation wise (~100 m), and complete excavation, pipe laying and backfilling in minimum possible time (1 day preferably) Work Camps and Temporary air and • Establish camps only after site approval DBO Contractor Cost for implementation of worksites noise pollution from • Avoid cutting of trees/ clearing bushes mitigation measures machine operation, • Provide adequate drinking water, water for responsibility of contractor. water pollution from other uses, and sanitation facilities storage and use of • Ensure conditions of livability at work camps fuels, oils, solvents, and are maintained at the highest standards lubricants possible at all times; • Prohibit employees from poaching wildlife and Unsanitary and poor cutting of trees for firewood; living conditions for • Train employees in the storage and handling of workers materials which can potentially cause soil contamination; • Recover used oil and lubricants and reuse or remove from the site; • Manage solid waste according to the preference hierarchy: reuse, recycling and disposal to designated areas; • Ensure unauthorized persons specially children are not allowed in any worksite Post-construction clean- Damage due to debris, • Remove all spoils wreckage, rubbish, or DBO Contractor Cost for implementation of up spoils, excess temporary structures (such as buildings, mitigation measures construction materials shelters, and latrines) which are no longer responsibility of contractor. required • All excavated roads shall be reinstated to original condition. • All disrupted utilities restored • All affected structures rehabilitated/compensated • The area that previously housed the construction camp is to be checked for spills of substances such as oil, paint, etc. and these shall be cleaned up. • All hardened surfaces within the construction

84

Field Anticipated Impact Mitigation Measures Responsible for Cost and Source of Funds Mitigation camp area shall be ripped, all imported materials removed, and the area shall be top soiled and regressed • The contractor must arrange the cancellation of all temporary services. • Restore the work sites to pre-project conditions; PIU to approve in writing that site is restored

85

Table 20: Operation Stage Environmental Management Plan Field Anticipated Impact Mitigation Measures Responsible for Monitoring of Cost and Mitigation Mitigation Source of Funds Check for Loss of water, • Effective leak detection and water DBO Contractor PIU and Operating blockage and increased demand auditing to reduce the water losses respective Nagar costs leakage problems and inconvenience to Parishads of reducing the consumers & general Pansemal, water losses public Rajpur, Karahi Padliya & Kasrawad Water Impacts on public • Ensure protection of water source quality Respective Nagar PMU in Operating contamination – health (Gomai), any entry of wastewater into the Parishads of coordination with costs raw water river upstream sites should be prevented. Pansemal, Rajpur, WRD contamination at • Contamination of treated water during Karahi Padliya & source and transmission and distribution should be Kasrawad PIU and treated water prevented by quickly identifying, isolating respective Nagar during and repairing the leak section. Develop a DBO Contractor Parishads of transmission system of leak detection and rectification. Pansemal, • Conduct regular monitoring of raw & Rajpur, Karahi treated water and ensure that water Padliya & supplied at all times meets the drinking Kasrawad water standards (Appendix 11) Discharge the Pollution of streams • Backwash water will be recirculated so no DBO Contractor PIU and Operating impurities and /drains wastewater generated from WTPs respective Nagar costs other solids • Maintain the mechanical parts as per the Parishads of collected due to maintenance plan to avoid any hazards Pansemal, filtration and back Rajpur, Karahi wash Padliya & Kasrawad

Sludge Land and water • Collect the sludge from WTP units, dry in DBO Contractor PIU and Operating generation pollution, impacts on sludge drying beds, and reuse / dispose respective Nagar costs health & environment safely as per the design Parishads Increased in Water pollution, and • Sanitation facilities needs to be improved Respective Nagar PMU To be sewage impacts on public at community level and at the town level Parishads of identified - generation health and to meet the increased sewage demand Pansemal, Rajpur, respective environment Karahi Padliya & NPs Kasrawad 86

Field Anticipated Impact Mitigation Measures Responsible for Monitoring of Cost and Mitigation Mitigation Source of Funds Generation of Impacts on public • Collect solid wastes and dispose to DBO Contractor PIU and Operating waste materials health and approved disposal yards respective Nagar costs environment Parishads Occupational Health, social and • Provide appropriate PPE to workers & DBO Contractor PIU and Operating health and safety economic impacts on training on its proper use respective Nagar costs the workers • Use fall protection equipment when Parishads of working at heights. Pansemal, • Maintain work areas to minimize slipping Rajpur, Karahi and tripping hazards. Padliya & • Implement a training program for Kasrawad operators who work with chlorine regarding safe handling practices and emergency response procedures. • Prepare escape plans from areas where there might be a chlorine emission. • Install safety showers and eye wash stations near the chlorine equipment and other areas where hazardous chemicals are stored or used. • Prohibit eating, smoking, and drinking except in designated areas.

Table 21: Construction Stage Environmental Monitoring Plan Monitoring field Monitoring location Monitoring parameters Frequency Responsibility Cost & Source of Funds Construction disturbances, All work sites Implementation of dust Regularly as required Supervising Part of TOR of PIU, PMC and PMU nuisances, public & worker control, noise control, during construction; staff and safety, traffic management, & checklist to be filled safeguards safety measures. monthly once specialists Site inspection checklist to review implementation is appended at Appendix 12 Ambient air quality 6 locations • PM10, PM2.5 NO2, Once before start of DBO Contractor Cost for implementation of (2 locations in each SO2, CO construction monitoring measures town: (i) at WTP site, Quarterly (yearly 4-times) responsibility of contractor 87

(ii) distribution work during construction (2 (54 samples x 5000 per sample = site) year period considered) 270,000)

Ambient noise 6 locations • Day time and night time Once before start of DBO Contractor Cost for implementation of (2 locations in each noise levels (24 hours) construction monitoring measures town: (i) at WTP site, Quarterly (yearly 4-times) responsibility of contractor (ii) distribution work during construction (2 (54 samples x 1500 per sample = site) year period considered) 81,000) Surface water quality 1 locations (down • pH, Oil & grease, Cl, Once before start of DBO Contractor Cost for implementation of Stream of work sites F, NO3, TC, FC, construction& monitoring measures in Gomai) Hardness, Turbidity monthly during responsibility of contractor BOD, COD, DO, Total construction (3 months (12 samples x 4000 per sample = Alkalnity period considered) in 48,000) river (27 samples x 4000 per sample = 108,000) Once before start of

construction& Quarterly during construction (24)

Table 22: Operation Stage Environmental Monitoring Plan Monitoring field Monitoring location Monitoring parameters Frequency Responsibility Cost & Source of Funds Source water quality Near intake point in pH, Cl, F, NO3, TC, FC, Hardness, Turbidity BOD, Yearly twice DBO O&M costs Gomai COD, DO, Total Alkalnity (pre & post Contractor heavy metals & pesticides monsoon) Monitoring of quality Consumer end- pH, Nitrite, Nitrate, Turbidity BOD, Total Alkalnity, Monthly DBO O&M costs of water supplied to random sampling in Total coliform and Feacal coliform once Contractor consumers all zones Sludge quality and WTP Analysis for concentration of heavy metals and confirm Yearly once DBO O&M costs suitability as manure that value are within the following limits (all units are in Contractor mg/kg dry, except pH) • Arsenic - 10.00, • Cadmium - 5.00 • Chromium - 50.00 • Copper - 300.00 • Lead - 100.00 • Mercury - 0.15

88

Monitoring field Monitoring location Monitoring parameters Frequency Responsibility Cost & Source of Funds • Nickel - 50.00 • Zinc - 1000.00 • PH - 5.5-8.5

89

C. EMP Compliance Responsibilities

97. PMU Responsibilities. PO (Environment) will be supported by PMC, which will be staffed with an Environmental Specialist, and Environmental Coordinators. Key tasks and responsibilities of the PO (Environment) for this sub project include the following:

Bidding stage:

(i) Prior to invitation of bids for civil works contract, ensure that

a. Water Resources Department (WRD) permission is obtained for sourcing water from Gomai River and to construct intake well cum pump house on it. b. Consent for establishment (CFE) is obtained from MPPCB for WTP construction.

(ii) Ensure that EMP is included in bidding documents and civil works contracts. (iii) Ensure that the bid/contract documents include specific provisions requiring contractors to comply with all applicable labour laws and core labour standards including:

a. Labour welfare measures and provision of amenities b. prohibition of child labour as defined in national legislation for construction and maintenance activities; c. equal pay for equal work of equal value regardless of gender, ethnicity, or caste; d. elimination of forced labour; e. The requirement to disseminate information on sexually transmitted diseases, including HIV/AIDS, to employees and local communities surrounding the project sites. (iv) Ensure that staff required for implementation of EMP is included in the bid requirements (v) Ensure that EMP cost is included in the project cost (vi) In the pre-bid meeting, provide insight into the EARF requirements, IEE update, EMP measures, and overall compliance requirements to the bidders

Construction stage:

(i) Facilitate and ensure that all necessary environmental clearances/permissions, including that of contractor’s are in place prior to start of construction (ii) Organize an induction course for the training of contractors, preparing them on EMP implementation, environmental monitoring, and on taking immediate action to remedy unexpected adverse impacts or ineffective mitigation measures found during the course of implementation. (iii) provide oversight on environmental management aspects of subprojects and ensure EMPs are implemented by PIU and contractors (iv) Supervise and provide guidance to the PIUs to properly carry out the environmental monitoring as per the EMP (v) Oversee grievance redress mechanism to address any grievances brought about in a timely manner; ensure that records are properly maintained (vi) Consolidate monthly environmental monitoring reports from PIU and submit semi-annual monitoring reports to ADB (vii) Oversee site closures to ensure that all work / facility sites are restored properly prior to issuing work completion certificate to the contractor

Operation stage:

(i) Ensure and consent for operation (CFO) is obtained from MPPCB for WTP prior to start of operation

98. PIU Responsibilities. PIU will be headed by a Project Manager and supported by PMC. An Assistant Project Manager of PIU will be given additional responsibilities of safeguard tasks and will be designated as Assistant Environmental Officer (ASO). ASO will be supported by PDMC Environmental Specialist and Environmental Coordinator. Key tasks and responsibilities of the ASO for this subproject include the following:

(i) Provide necessary support to PIU and Nagar Parishads in obtaining permission from WRD and MPPCB; liaison with PMU and regulatory agencies (ii) Oversee day-to-day implementation of EMPs by contractors, including compliance with all government rules and regulations, take necessary action for obtaining rights of way (iii) Oversee environmental monitoring by contractors (iv) Take corrective actions when necessary to ensure no environmental impacts (v) Submit monthly environmental monitoring reports to PMU (vi) Conduct continuous public consultation and awareness (vii) Address any grievances brought about through the grievance redress mechanism in a timely manner as per the EMP

99. Contractor’s responsibilities.

Bidding stage:

(i) Understand the EMP requirements and allocate necessary resources (budget, staff, etc.,) (ii) Understand the regulatory compliance requirements related to labour welfare, safety, environment etc.,

Design stage:

(i) Review the IEE Report including the REA checklist, category and the EMP, and conduct site visits to understand the environmental sensitivity of the project sites. (ii) Update the REA checklist, confirm the category, and update/revise the IEE Report of the project reflecting the changes /amendments /additions that are effected in the project during the detailed design (iii) Update / revise and finalize the EMP (iv) Provide all necessary technical assistance to PIU / ULB in obtaining regulatory clearances/approvals. (v) Ensure that all design-related measures of the EMP, and conditions, if any, of government regulatory agencies (like MPPCB consent conditions) are duly included in the final designs.

Construction stage:

(i) Ensure that all regulatory clearances (both project related and contractor related) are in place before start of the construction work.

91

(ii) Mobilize EHS officer and Archaeological supervisor prior to start of work (iii) Confirm with PIU availability of rights of way at all project sites prior to start of work. (iv) Prepare and submit: a. Construction waste management (CWM) plan b. Traffic management (TM) plan (v) Implement the mitigation measures as per the EMP including CWM & TM Plans (vi) Follow the EMP measures/guidelines for establishment of temporary construction camps, construction waste disposal sites, and material borrow areas, etc., (vii) Implement EMP and ensure compliance with all the mitigation and enhancement measures (viii) Conduct environmental monitoring (air, noise, water etc.,) as per the EMP (ix) Undertake immediate action as suggested by PIU / PMU / PMC to remedy unexpected adverse impacts or ineffective mitigation measures found during the course of implementation (x) Submit monthly compliance reports on EMP implementation (xi) Act promptly on public complaints and grievances related to construction work and redress in a timely manner in coordination with PIU (xii) Comply with applicable government rules and regulations

Operation stage:

(i) Obtain CFO from MPPCB in coordination with the ULB, and comply with MPPCB conditions, if any, during the operation phase (ii) Implement the operation phase EMP including the monitoring plan (iii) Submit quarterly EMP implementation report

D. Training Needs

100. The following Table 21 presents the outline of capacity building program to ensure EMP implementation. The estimated cost is Rs.275,000 (excluding trainings of contractors which will be part of EMP implementation cost during construction) to be covered by the project’s capacity building program. The detailed cost and specific modules will be customized for the available skill set after assessing the capabilities of the target participants and the requirements of the project by the ES of PDMC.

Table 23: Outline Capacity Building Program on EMP Implementation Description Target Participants& Estimate Cost and Source Venue (INR) of Funds 1. Introduction and Sensitization to All staff and - Included in the Environmental Issues (1 day) consultants involved in overall program - ADB Safeguards Policy Statement the project cost - Government of India and Madhya Pradesh applicable safeguard laws, regulations and At PMU, Bhopal policies including but not limited to core (combined program for labor standards, OH&S, etc. all subprojects) - Incorporation of EMP into the project design and contracts - Monitoring, reporting and corrective action

92

Description Target Participants& Estimate Cost and Source Venue (INR) of Funds planning 2. EMP implementation (1/2 day) All PIU staff, - Part of overall - EMP mitigation & monitoring measures contractor staff and program costs – -Roles and responsibilities consultants involved in PMC will conduct - Public relations, - Consultations the Pansemal, Rajpur, at PIU office - Grievance redress Karahi Padliya & - Monitoring and corrective action planning Kasrawad subproject Part of scope of - Reporting and disclosure work of PMU, PIU, - Construction site standard operating At PIU PMC & DBOC procedures (SOP) - AC pipe protocol - Traffic management plan - Waste management plan - Site clean-up & restoration 3. Contractors Orientation to Workers (1/2 Once before start of - Contractors cost day) work, and thereafter - Environment, health and safety in project regular briefing every construction month once. Daily briefing on safety prior to start of work

All workers (including unskilled laborers)

E. Monitoring and Reporting

101. During the detailed design stage, DBO Contractor should confirm PMU the mobilization of Environmental Expert for IEE update and integrating design stage EMP into designs.

102. Prior to commencement of the works, the contractor will submit a compliance report to PIU that all identified pre-construction mitigation measures as detailed in the EMP are undertaken. Contractor should confirm EHS supervisor is mobilized and EHS coordinators are designated for each town for effective implementation of the EMU. PMU with the assistance of the PMC will review the report and permit commencement of works.

103. During construction, results from internal monitoring by the contractor will be reflected in their monthly EMP implementation reports to the PIU. PMU will review and advise contractors for corrective actions if necessary. Quarterly report summarizing compliance and corrective measures taken will be prepared by PMC field team at PIU and submitted to PMU (Appendix 13). During operation, the contractor will conduct management and monitoring actions as per the operation stage EMP, and submit to PMU and ULB a quarterly report on EMP implementation and compliance.

104. Based on monthly & quarterly reports and measurements, PMU will submit to ADB, semi-annual (6-monthly) Environmental Monitoring Reports (EMR).Once concurrence from the ADB is received the report will be disclosed on the MPUDC and PMU websites.

105. ADB will review project performance against the MPUSIP commitments as agreed in the legal documents. The extent of ADB’s monitoring and supervision activities will be

93

commensurate with the project’s risks and impacts. Monitoring and supervising of social and environmental safeguards will be integrated into the project performance management system

F. EMP Implementation Cost

106. Most of the mitigation measures require the contractors to adopt good site practice, which should be part of their normal procedures already, so there are unlikely to be major costs associated with compliance. The costs which are specific to EMP implementation and are not covered elsewhere in the projects are given below. The total costs are estimated at INR 2.43 million, which are to be covered by contractor costs.

Table 24: Cost Estimates to Implement the EMP Particulars Stages Unit Total Rate Cost Costs Numbe (INR) (INR) Covered r By A. Implementation staff 1 Environmental Design & pre Per 0.5 150,00 75,000 DBO Specialist construction month 0 Contract 1 EHS Supervisor Construction per 24 50,000 1,200,000 DBO month contract Subtotal (A) 1,275,000 B. Mitigation Measures 1 Consent for Pre Lump 150,000 Project establishments & construction sum costs consent for operation from MPPCB 2 Provision for tree Construction Per tree 100 1,000 100,000 DBO cutting & compensatory contract plantation measures 3 Traffic management at Construction Lump - - 300,000 DBO work sites sum – 3 contract (Pavement Markings, towns Channelizing Devices, Arrow Panels and Warning Lights) Subtotal (B) 550,000 C. Monitoring Measures 1 Air quality monitoring Construction / sample 54 5,000 270,000 DBOC 2 Noise levels monitoring Construction / sample 54 1,500 81,500 DBOC 3 Surface water Construction / sample 39 4,000 156,000 DBOC monitoring 4 Water and sludge Operation LS / yr - - 100,000 DBO Subtotal (C) 607,500 Subtotal (D) - Total (A+B+C) INR 2,432,500

94

X. CONCLUSION AND RECOMMENDATIONS 107. The process described in this document has assessed the environmental impacts of all elements of the Pansemal, Rajpur, Karahi Padliya and Kasrawad water supply improvement subproject. All potential impacts were identified in relation to pre-construction, construction, and operation phases. Planning principles and design considerations have been reviewed and incorporated into the site planning and design process wherever possible; thus, environmental impacts as being due to the project design or location were not significant.

108. Although none of the components are located within the forest, conduct of construction works and presence of workers, vehicles may damage /disturb the sensitive areas. Necessary precautionary measures are suggested to avoid any impacts.

109. During the construction phase, impacts mainly arise from the construction dust and noise, the need to dispose of large quantities of waste soil and import of construction material, and from the disturbance of residents, businesses, traffic and important buildings by the construction work. The social impacts (access disruptions) due to construction activities are unavoidable, as the residential and commercial establishments exist along the roads where pipes will be laid. As some of the works are conducted in rive, there is a risk of water contamination, river bed damage, etc.. Appropriate measures are suggested.

110. Anticipated impacts of water supply during operation and maintenance will be related to detection and repair of leaks, pipe bursts. These are, however, likely to be minimal, as proper design and selection of good quality pipe material shall mean that leaks are minimal. Leak repair work will be similar to the pipe-laying work. Appropriate measures to deal with backwash water and sludge from WTP is included in the project design. Application and handling of chlorine gas will involve certain risks, and appropriate measures are suggested for safe application. The DBO Contractor will implement the operation stage EMP during contract period.

111. The public participation processes undertaken during project design ensured stakeholders are engaged during the preparation of the IEE. The planned information disclosure measures and process for carrying out consultation with affected people will facilitate their participation during project implementation.

112. The project’s grievance redress mechanism will provide the citizens with a platform to redress of their grievances, and describes the informal and formal channels, time frame, and mechanisms for resolving complaints about environmental performance.

113. The EMP will assist the PMU, PIU, PMC and DBO contractor in mitigating the environmental impacts, and guide them in the environmentally sound execution of the proposed project.

114. A copy of the EMP/approved SEP shall be kept on-site during the construction period at all times. The EMP shall be made binding on all contractors operating on the site, and will be included in the contractual clauses. Non-compliance with, or any deviation from, the conditions set out in this document shall constitute a failure in compliance.

115. The project will benefit the general public by contributing to the long-term improvement of water supply systems and community livability in Pansemal, Rajpur, Karahi Padliya and Kasrawad.

116. Therefore, as per ADB SPS, the project is classified as environmental category B and

95

does not require further environmental impact assessment. However, to conform to government guidelines, the project requires (i) permission of WRD, GoMP for water abstraction and construction of intakes in Narmada and Gomai Rivers (ii) Consent for Establishment (CFE) and Consent for Operation (CFO) for WTPs from MPPCB. These permissions/approvals shall be obtained. Corrective action plan as suggested for existing Kasrawad WTP is also to be implemented.

117. This IEE shall be updated during the detailed design stage by the DBO contractor to reflect any changes, amendments and will be reviewed and approved by PMU.

96

Appendix 1: REA Checklist

I. Country/Project: India/Madhya Pradesh Urban Services Improvement program- Karahi Padliya- Water Supply Subproject Sector/Division: Urban Development & Environment Department/MPUDC Screening Questions Yes No Remarks A.PROJECT SITING IS THE PROJECT AREA • Densely populated?  The project covers entire town including the densely populated areas. There are no major negative impacts envisaged because Distribution lines will be located in unused Government lands along side the existing roads and can be constructed without causing disturbance to houses and commercial establishments. In narrow streets disruption to road users is likely and measures like best activity scheduling, alternative routes, prior information to road users, houses and shops will minimize the impact to acceptable levels. The site of WTP is located in less dense area so no negative impact envisaged. • Heavy with development activities?  No • Adjacent to or within any environmentally sensitive areas?  No

• Cultural heritage site/Historical importance

 No • Protected area  No • Wetland  No • Mangrove  No • Estuarine  No • Buffer zone of protected Area  No • Special area for protecting biodiversity  No • Bay  No B.POTENTIAL ENVIRONMENTAL IMPACTS Will the project cause…

97

• Pollution of raw water supply There are no significant water pollution sources in from upstream wastewater the catchment. Raw water quality is tested and discharge from communities, found that it is suitable for Domestic use. industries, agriculture, and soil erosion runoff?  • Impairment of historical /cultural monuments/areas, and  loss/damage to these sites?

• Hazard of land subsidence caused Not applicable, subproject does not involve by excessive ground water  groundwater abstraction pumping? • Social conflicts arising from Project does not involve land acquisition displacement of communities  /displacement .No social conflicts envisaged. • Conflicts in abstraction of raw water for water supply with other beneficial water uses for surface and ground waters?

 No, the water will be abstracted with due permission of Water Resource Department Narmada River • Unsatisfactory raw water supply (e.g. excessive pathogens or Raw water Quality is tested and found that it is mineral constituents)?  suitable for Domestic use.

Water will be treated and disinfected prior to • Delivery of unsafe water to supply. distribution system? 

• Inadequate protection of intake Water is abstracted from Narmada River there are works or wells, leading to pollution  no major polluting sources in the catchment. of water supply? • Over-pumping of ground water, leading to salinization and ground No Ground water pumping is required as Surface subsidence?  water source is selected for the project • Excessive algal growth in storage Regular cleaning of storage tanks will be conducted reservoir?  during operation. • Increase in production of sewage As per CPHEEO manual the rate of water supply is beyond capabilities of community 70lpcd for the town where sewerage scheme is not facilities?  anticipated. • Inadequate disposal of sludge from water treatment plants? Appropriate provision for sludge drying and  disposal is included in the project • Inadequate buffer zone around pumping and treatment plants to alleviate noise and other possible nuisances and protect facilities?  No

98

• Impairments associated with transmission lines and access roads?  No • Health hazards arising from Measures for safe handling of Chlorine are inadequate design of facilities for included. receiving, storing, and handling of  chlorine and other hazardous chemicals? • Health and safety hazards to workers from the management of  Measures for safe handling of Chlorine are chlorine used for disinfection and included.

• Dislocation or involuntary There is no resettlement of people for project resettlement of people  implementation. The contractor will be utilizing the local labour • Social conflicts between forces as far as possible; in case if it is construction workers from other unavoidable, labour camps and facilities will be areas & community workers  provided appropriately. No conflicts envisaged. • Noise and dust from construction Dust suppression measures such as water activities  sprinkling will be employed Excavation & Laying pipelines along public road will interfere with the traffic. • Increased road traffic due to Construction material transport will increase traffic interference of construction within city and dumping construction material on activities?  road cause traffic congestion. Proper traffic & Construction planning will be ensured to minimize the interference. Construction work during monsoon shall be carried • Continuing soil erosion, silt runoff out with due care so that silt run off due to from construction operation  construction operation is prevented. • Delivery of unsafe water due to poor O&M treatment processes (especially mud accumulations in filters) and inadequate chlorination  No, appropriate O&M will be conducted. due to lack of adequate monitoring

of chlorine residuals in distribution systems? • Delivery of water to distribution system, which is corrosive due to  Not envisaged. inadequate attention to feeding of corrective chemicals? Measures for safe handling of chlorine are • Accidental leakage of Chlorine gas  included. Water abstraction will be limited to allocate quantity • Excessive abstraction of water  for Karahi Padliya. affecting downstream water users? • Competing uses of water? Water abstraction will be limited to allocate quantity  for Karahi Padliya As per CPHEEO manual the rate of water supply is • Increased sewage flow due to 70lpcd for the town where sewerage scheme is not increased water supply?  anticipated

99

• Increased volume of sullage (wastewater from cooking and washing)and sludge from waste  No water treatment plant? • Large population influx during project construction and operation that causes increased burden on minimum influx of population during the  construction and operation period. social infrastructure and services

(such as water supply and sanitation systems)? The contractor will be advised to absorb local • Social conflicts if workers from labour forces as far as possible; in case if it is other regions or countries are unavoidable, labour would be hired for temporary hired?  phase. No conflicts envisaged.

• Risks to community health and safety due to the transport, storage, and use and/or disposal of materials such as explosives, fuel, and other chemicals during No such materials are used in project so no risk to operation and construction ?  community health & safety • Community safety risks due to both accidental and natural hazards, Proper safety measures would be ensured during the especially where the structural  construction & operation and decommissioning. elements or components of the project are accessible to members of the affected community or where their failure could result in injury to the community throughout project construction, operation, and decommissioning ?

Climate Change and Disaster Risk Questions Yes No Remarks The following questions are not for environmental categorization.They are included in this checklist to help identify Ispo tthene tPrialo cljecimat atree a an ds udbjiseacstt etor rhisaksza.r ds such as √ Semi-arid zone, unreliable rainfall, earthquakes, floods, landslides, tropicalcy clone less vegetation cover. Promote winds, storm surges, tsunami or volcanic more efficient use of water by eruptions and climate changes? reducing losses and wastage to counter increased demands due to higher temperatures.

100

Could changes in temperature, precipitation, or √ Reduction in rainfall may affect the extreme events patterns over the Project lifespan water availability from dam. Given affect technical or financial the priority for drinking water sustainability(e.g., changes in rainfall patterns disrupt supply, dead storage will be reliability utilized in case of low rain fall years of water supply; sea level rise creates salinity intrusion into proposed water supply source)? Are there any demographic or socio-economic √ No aspects of the Project area that are already vulnerable(e.g., high in cadence of marginalized populations, rural-urban migrants, illegal Settlements, ethnic minorities, women or children)?

Could the Project potentially increase the climate or √ No disaster vulnerability of the surrounding area(e.g. ,by using water from A vulnerable source that is relied upon by many user groups, or encouraging settlement in earthquake zones)?

Country/Project: India/Madhya Pradesh Urban Services Improvement program- Kasrawad- Water Supply Subproject Sector/Division: Urban Development & Environment Department/MPUDC Screening Questions Yes No Remarks A.PROJECT SITING IS THE PROJECT AREA • Densely populated? The project covers entire town including the densely populated areas. There are no major negative impacts envisaged because Distribution lines will be located in unused Government lands along side the existing roads and can be constructed without causing disturbance to houses and commercial establishments. In narrow streets disruption to road users is likely and measures like best activity scheduling, alternative routes, prior information to road users, houses and shops will minimize the impact to acceptable levels. The site of WTP is located in less dense area so no negative impact  envisaged. • Heavy with development activities?  No • Adjacent to or within any environmentally sensitive areas?  No A number of historical places are located in • Cultural heritage site/Historical Kasrawad town - such as the Bhavani Mata importance Temple, ancient Kailash Kund and Baba ki Mazar on Gangleshwar Parvat are a few  important places in the town. ASI excavation

101

site is located approx 2 km from the town, none of the project component comes under it.

• Protected area  No • Wetland  No • Mangrove  No • Estuarine  No • Buffer zone of protected Area  No • Special area for protecting biodiversity  No • Bay  No B.POTENTIAL ENVIRONMENTAL IMPACTS Will the project cause… • Pollution of raw water supply There are no significant water pollution sources in From upstream wastewater Discharge the catchment. Raw water quality is tested and from communities, found that it is suitable for Domestic use. industries, agriculture, and soil erosion runoff?  • Impairment of historical /cultural monuments/areas, and  loss/damage to these sites?

• Hazard of land subsidence caused Not applicable, subproject does not involve by excessive ground water  groundwater abstraction pumping? • Social conflicts arising from Project does not involve land acquisition displacement of communities  /displacement .No social conflicts envisaged. • Conflicts in abstraction of raw water for water supply with other beneficial water uses for surface and ground waters?

No, the water will be abstracted with due permission  of Water Resource Department from Narmada River. • Unsatisfactory raw water supply (e.g. excessive pathogens or Raw water Quality is tested and found that it is mineral constituents)?  suitable for Domestic use.

Water will be treated and disinfected prior to • Delivery of unsafe water to supply. distribution system? 

• Inadequate protection of intake Water is abstracted from Narmada River there are works or wells, leading to pollution  no major polluting sources in the catchment. of water supply?

102

• Over-pumping of ground water, leading to salinization and ground No Ground water pumping is required as Surface subsidence?  water source is selected for the project • Excessive algal growth in storage Regular cleaning of storage tanks will be conducted reservoir?  during operation. • Increase in production of sewage As per CPHEEO manual the rate of water supply is beyond capabilities of community 70lpcd for the town where sewerage scheme is not facilities?  anticipated. • Inadequate disposal of sludge from water treatment plants? Appropriate provision for sludge drying and  disposal is included in the project • Inadequate buffer zone around pumping and treatment plants to alleviate noise and other possible nuisances and protect facilities?  No • Impairments associated with transmission lines and access roads?  No • Health hazards arising from Measures for safe handling of Chlorine are inadequate design of facilities for included. receiving, storing, and handling of  chlorine and other hazardous chemicals? • Health and safety hazards to workers from the management of  Measures for safe handling of Chlorine are chlorine used for disinfection and included.

• Dislocation or involuntary There is no resettlement of people for project resettlement of people  implementation. The contractor will be utilizing the local labour • Social conflicts between forces as far as possible; in case if it is construction workers from other unavoidable, labour camps and facilities will be areas & community workers  provided appropriately. No conflicts envisaged. • Noise and dust from construction Dust suppression measures such as water activities  sprinkling will be employed Excavation & Laying pipelines along public road will interfere with the traffic. • Increased road traffic due to Construction material transport will increase traffic interference of construction within city and dumping construction material on activities?  road cause traffic congestion. Proper traffic & Construction planning will be ensured to minimize the interference. Construction work during monsoon shall be carried • Continuing soil erosion, silt runoff out with due care so that silt run off due to from construction operation  construction operation is prevented. • Delivery of unsafe water due to poor O&M treatment processes  No, appropriate O&M will be conducted. (especially mud accumulations in

filters) and inadequate chlorination due to lack of adequate monitoring

103

of chlorine residuals in distribution systems? • Delivery of water to distribution system, which is corrosive due to  Not envisaged. inadequate attention to feeding of corrective chemicals? Measures for safe handling of chlorine are • Accidental leakage of Chlorine gas  included. Water abstraction will be limited to allocate quantity • Excessive abstraction of water  for Kasrawad. affecting downstream water users? • Competing uses of water? Water abstraction will be limited to allocate quantity  for Kasrawad. As per CPHEEO manual the rate of water supply is • Increased sewage flow due to 70lpcd for the town where sewerage scheme is not increased water supply?  anticipated • Increased volume of sullage (wastewater from cooking and washing)and sludge from waste  No water treatment plant? • Large population influx during project construction and operation that causes increased burden on minimum influx of population during the  construction and operation period. social infrastructure and services

(such as water supply and sanitation systems)? The contractor will be advised to absorb local • Social conflicts if workers from labour forces as far as possible; in case if it is other regions or countries are unavoidable, labour would be hired for temporary hired?  phase. No conflicts envisaged.

• Risks to community health and safety due to the transport, storage, and use and/or disposal of materials such as explosives, fuel, and other chemicals during No such materials are used in project so no risk to operation and construction ?  community health & safety • Community safety risks due to both accidental and natural hazards, Proper safety measures would be ensured during the especially where the structural  construction & operation and decommissioning. elements or components of the project are accessible to members of the affected community or where their failure could result in injury to the community throughout project construction, operation, and decommissioning ?

104

Climate Change and Disaster Risk Questions Yes No Remarks The following questions are not for environmental categorization.They are included in this checklist to help identify Ispo tthene tPrialo cljecimat atree a an ds udbjiseacstt etor rhisaksza.r ds such as √ Semi-arid zone, unreliable rainfall, earthquakes, floods, landslides, tropicalcy clone less vegetation cover. Promote winds, storm surges, tsunami or volcanic more efficient use of water by eruptions and climate changes? reducing losses and wastage to counter increased demands due to higher temperatures. Could changes in temperature, precipitation, or √ Reduction in rainfall may affect the extreme events patterns over the Project lifespan water availability from dam. Given affect technical or financial the priority for drinking water sustainability(e.g., changes in rainfall patterns disrupt supply, dead storage will be reliability utilized in case of low rain fall years of water supply; sea level rise creates salinity intrusion into proposed water supply source)? Are there any demographic or socio-economic √ No aspects of the Project area that are already vulnerable(e.g., high in cadence of marginalized populations, rural-urban migrants, illegal Settlements, ethnic minorities, women or children)?

Could the Project potentially increase the climate or √ No disaster vulnerability of the surrounding area(e.g. ,by using water from A vulnerable source that is relied upon by many user groups, or encouraging settlement in earthquake zones)?

III. Country/Project Title: India / Madhya Pradesh Urban Services Improvement Program – Pansemal Water Supply Subproject Sector Division: Urban Development

SCREENING QUESTIONS YES NO REMARKS Water Supply A. Project Sitting Is the project area… • Densely populated? In general there are no densely populated areas in Pansemal town. There are no major negative impacts envisaged, because pipeline will be located in unused government lands alongside the existing roads and can be constructed without causing disturbance to, houses, and commercial establishments. In narrow streets, disruption to road users is likely, and measure like best activity scheduling, alternative routes, prior information to road users, houses and shops will minimize the impact to acceptable levels • Heavy with development activities? • Adjacent to or within any environmentally sensitive areas? • Cultural heritage site • Protected Area

105

• Wetland • Mangrove • Estuarine • Buffer zone of protected area • Special area for protecting biodiversity • Bay B. Potential Environmental Impacts Will the Project cause… • Pollution of raw water supply from There are no significant water pollution sources upstream wastewater discharge from in the catchment. Raw water quality is tested and communities, industries, agriculture, and found that it is suitable for domestic use soil erosion runoff? • Impairment of historical/cultural monuments/areas and loss/damage to these sites? • Hazard of land subsidence caused by excessive ground water pumping? • Social conflicts arising from displacement of communities? • Conflicts in abstraction of raw water for water supply with other beneficial water uses for surface and ground waters? • Unsatisfactory raw water supply (e.g. excessive pathogens or mineral constituents)? • Delivery of unsafe water to distribution system? • Inadequate protection of intake works or wells, leading to pollution of water supply? • Over pumping of ground water, leading to salinization and ground subsidence? • Excessive algal growth in storage reservoir? • Increase in production of sewage beyond capabilities of community facilities? • Inadequate disposal of sludge from water treatment plants? • Inadequate buffer zone around pumping and treatment plants to alleviate noise and other possible nuisances and protect facilities? • Impairments associated with transmission lines and access roads? • Health hazards arising from inadequate design of facilities for receiving, storing, and handling of chlorine and other hazardous chemicals. • Health and safety hazards to workers from the management of chlorine used for disinfection and other contaminants? • Dislocation or involuntary resettlement of people • Social conflicts between construction workers from other areas and community workers? • Noise and dust from construction All the construction machineries employed will activities? comply with noise emission standards of Central

106

Pollution Control Board. Dust suppression measures such as water sprinkling will be employed • Increased road traffic due to interference Excavation and laying pipelines along public of construction activities? roads will interfere with the traffic. Construction material transport will increase traffic within city. Proper traffic management and construction planning will be ensured to minimize the interference. • Continuing soil erosion/silt runoff from Construction work during monsoon shall be construction operations? carried out with due care so that silt run off due to construction operation is prevented. No construction will be allowed during rains. • Delivery of unsafe water due to poor O&M treatment processes (especially mud accumulations in filters) and inadequate chlorination due to lack of adequate monitoring of chlorine residuals in distribution systems? • Delivery of water to distribution system, which is corrosive due to inadequate attention to feeding of corrective chemicals? • Accidental leakage of chlorine gas? • Excessive abstraction of water affecting downstream water users? • Competing uses of water? • Increased sewage flow due to increased water supply • Increased volume of sullage (wastewater from cooking and washing) and sludge from wastewater treatment plant Climate Change and Disaster Risk Questions The following questions are not for environmental categorization. They are included in this checklist to help identify potential climate and disaster risks. • Is the Project area subject to hazards such as earthquakes, floods, landslides, tropical cyclone winds, storm surges, tsunami or volcanic eruptions and climate changes? • Could changes in temperature, Reduction in rainfall may affect the water precipitation, or extreme events patterns availability from dam. Given the priority for over the Project lifespan affect technical drinking water supply, dead storage will be or financial sustainability (e.g., changes utilized in case of low rain fall years. in rainfall patterns disrupt reliability of water supply; sea level rise creates salinity intrusion into proposed water supply source)? • Are there any demographic or socio- economic aspects of the Project area that are already vulnerable (e.g.,high incidence of marginalized populations, rural-urban migrants, illegal settlements, ethnic minorities, women or children)? • Could the Project potentially increase the climate or disaster vulnerability of the surrounding area (e.g., by using water from a vulnerable source that is relied

107

upon by many user groups, or encouraging settlement in earthquake zones)?

IV. Country/Project: India/Madhya Pradesh Urban Services Improvement program- Rajpur- Water Supply Subproject Sector/Division: Urban Development & Environment Department/MPUDC Screening Questions Yes No Remarks A.PROJECT SITING IS THE PROJECT AREA • Densely populated? The project covers entire town including the densely populated areas. There are no major negative impacts envisaged because Distribution lines will be located in unused Government lands along side the existing roads and can be constructed without causing disturbance to houses and commercial establishments. In narrow streets disruption to road users is likely and measures like best activity scheduling, alternative routes, prior information to road users, houses and shops will minimize the impact to acceptable levels. The site of WTP is located in less dense area so no negative impact  envisaged. • Heavy with development activities?  No • Adjacent to or within any environmentally sensitive areas?  No

• Cultural heritage site/Historical importance

 No • Protected area  No • Wetland  No • Mangrove  No • Estuarine  No • Buffer zone of protected Area  No

108

• Special area for protecting biodiversity  No • Bay  No B.POTENTIAL ENVIRONMENTAL IMPACTS Will the project cause… • Pollution of raw water supply There are no significant water pollution sources in from upstream wastewater the catchment. Raw water quality is tested and discharge from communities, found that it is suitable for Domestic use. industries, agriculture, and soil erosion runoff?  • Impairment of historical /cultural monuments/areas, and  loss/damage to these sites?

• Hazard of land subsidence caused Not applicable, subproject does not involve by excessive ground water  groundwater abstraction pumping? • Social conflicts arising from Project does not involve land acquisition displacement of communities  /displacement .No social conflicts envisaged. • Conflicts in abstraction of raw water for water supply with other beneficial water uses for surface and ground waters?

No, the water will be abstracted with due permission  of Water Resource Department from Narmada River. • Unsatisfactory raw water supply (e.g. excessive pathogens or Raw water Quality is tested and found that it is mineral constituents)?  suitable for Domestic use.

Water will be treated and disinfected prior to • Delivery of unsafe water to supply. distribution system? 

• Inadequate protection of intake Water is abstracted from Narmada River there are works or wells, leading to pollution  no major polluting sources in the catchment. of water supply? • Over-pumping of ground water, leading to salinization and ground No Ground water pumping is required as Surface subsidence?  water source is selected for the project • Excessive algal growth in storage Regular cleaning of storage tanks will be conducted reservoir?  during operation. • Increase in production of sewage As per CPHEEO manual the rate of water supply is beyond capabilities of community 70lpcd for the town where sewerage scheme is not facilities?  anticipated. • Inadequate disposal of sludge from water treatment plants? Appropriate provision for sludge drying and  disposal is included in the project

109

• Inadequate buffer zone around pumping and treatment plants to alleviate noise and other possible nuisances and protect facilities?  No • Impairments associated with transmission lines and access roads?  No • Health hazards arising from Measures for safe handling of Chlorine are inadequate design of facilities for included. receiving, storing, and handling of  chlorine and other hazardous chemicals? • Health and safety hazards to workers from the management of  Measures for safe handling of Chlorine are chlorine used for disinfection and included.

• Dislocation or involuntary There is no resettlement of people for project resettlement of people  implementation. The contractor will be utilizing the local labour • Social conflicts between forces as far as possible; in case if it is construction workers from other unavoidable, labour camps and facilities will be areas & community workers  provided appropriately. No conflicts envisaged. • Noise and dust from construction Dust suppression measures such as water activities  sprinkling will be employed Excavation & Laying pipelines along public road will interfere with the traffic. • Increased road traffic due to Construction material transport will increase traffic interference of construction within city and dumping construction material on activities?  road cause traffic congestion. Proper traffic & Construction planning will be ensured to minimize the interference. Construction work during monsoon shall be carried • Continuing soil erosion, silt runoff out with due care so that silt run off due to from construction operation  construction operation is prevented. • Delivery of unsafe water due to poor O&M treatment processes (especially mud accumulations in filters) and inadequate chlorination  No, appropriate O&M will be conducted. due to lack of adequate monitoring

of chlorine residuals in distribution systems? • Delivery of water to distribution system, which is corrosive due to  Not envisaged. inadequate attention to feeding of corrective chemicals? Measures for safe handling of chlorine are • Accidental leakage of Chlorine gas  included. Water abstraction will be limited to allocate quantity • Excessive abstraction of water  for Rajpur. affecting downstream water users?

110

• Competing uses of water? Water abstraction will be limited to allocate quantity  for Rajpur As per CPHEEO manual the rate of water supply is • Increased sewage flow due to 70lpcd for the town where sewerage scheme is not increased water supply?  anticipated • Increased volume of sullage (wastewater from cooking and washing)and sludge from waste  No water treatment plant? • Large population influx during project construction and operation that causes increased burden on minimum influx of population during the  construction and operation period. social infrastructure and services

(such as water supply and sanitation systems)? The contractor will be advised to absorb local • Social conflicts if workers from labour forces as far as possible; in case if it is other regions or countries are unavoidable, labour would be hired for temporary hired?  phase. No conflicts envisaged.

• Risks to community health and safety due to the transport, storage, and use and/or disposal of materials such as explosives, fuel, and other chemicals during No such materials are used in project so no risk to operation and construction ?  community health & safety • Community safety risks due to both accidental and natural hazards, Proper safety measures would be ensured during the especially where the structural  construction & operation and decommissioning. elements or components of the project are accessible to members of the affected community or where their failure could result in injury to the community throughout project construction, operation, and decommissioning ?

Climate Change and Disaster Risk Questions Yes No Remarks The following questions are not for environmental categorization.They are included in this checklist to help identify Ispo tthene tPrialo cljecimat atree a an ds udbjiseacstt etor rhisaksza.r ds such as √ Semi-arid zone, unreliable rainfall, earthquakes, floods, landslides, tropicalcy clone less vegetation cover. Promote winds, storm surges, tsunami or volcanic more efficient use of water by eruptions and climate changes? reducing losses and wastage to counter increased demands due to higher temperatures.

111

Could changes in temperature, precipitation, or √ Reduction in rainfall may affect the extreme events patterns over the Project lifespan water availability from dam. Given affect technical or financial the priority for drinking water sustainability(e.g., changes in rainfall patterns disrupt supply, dead storage will be reliability utilized in case of low rain fall years of water supply; sea level rise creates salinity intrusion into proposed water supply source)? Are there any demographic or socio-economic √ No aspects of the Project area that are already vulnerable(e.g., high in cadence of marginalized populations, rural-urban migrants, illegal Settlements, ethnic minorities, women or children)?

Could the Project potentially increase the climate or √ No disaster vulnerability of the surrounding area(e.g. ,by using water from A vulnerable source that is relied upon by many user groups, or encouraging settlement in earthquake zones)?

Appendix 2: National Ambient Air Quality Standards

S. Pollutants Time Concentration in ambient air Method of measurement No: weighted Industrial, Ecologically average Residential, Sensitive Rural & Other Areas Areas 1 Sulphur Dioxide Annual 50 20 Improved West and

(SO2) 24 hours 80 80 Geake-Ultraviolet µg/m3 fluorescence 2 Nitrogen Dioxide Annual 40 30 Modified Jacob

3 (NO2) µg/m 24 hours 80 80 &Hochheiser (Na- Arsenite) Chemiluminescence 3 Particulate Matter Annual 60 60 Gravimetric (Size less than 10 24 hours 100 100 -TOEM µm) or PM10 -Beta attenuation µg/m3 4 Particulate Matter Annual 40 40 Gravimetric (Size less than 24 hours 60 60 -TOEM 2.5 µm) or PM2.5 -Beta attenuation µg/m3 5 Carbon Monoxide 8 hours 02 02 Non Dispersive Infra Red

112

(CO) mg/m3 1 hours 04 04 (NDIR) Spectroscopy

Appendix 3: Vehicle Exhaust Emission Norms 1. Passenger Cars Norms CO( g/km) HC+ NOx(g/km) 1991Norms 14.3-27.1 2.0(Only HC) 1996 Norms 8.68-12.40 3.00-4.36 1998Norms 4.34-6.20 1.50-2.18 India stage 2000 norms 2.72 0.97 Bharat stage-II 2.2 0.5 Bharat Stage-III 2.3 0.35 (combined) Bharat Stage-IV 1.0 0.18 (combined)

2. Heavy Diesel Vehicles Norms CO( g/kmhr) HC (g/kmhr) NOx (g/kmhr) PM(g/kmhr) 1991Norms 14 3.5 18 - 1996 Norms 11.2 2.4 14.4 - India stage 2000 norms 4.5 1.1 8.0 0.36 Bharat stage-II 4.0 1.1 7.0 0.15 Bharat Stage-III 2.1 1.6 5.0 0.10 Bharat Stage-IV 1.5 0.96 3.5 0.02 Source: Central Pollution Control Board CO = Carbon Monixide; g/kmhr = grams per kilometer-hour; HC = Hydrocarbons; NOx = oxides of nitrogen; PM = Particulates Matter

Appendix 4: National Ambient Air Quality Standards in Respect of Noise

Area code Category of area/zone Limit in dB (A) Day time Night time A Industrial area 75 70 B Commercial area 65 55 C Residential area 55 45 D Silence zone 50 40

113

Appendix 5: Extract From Construction & Demolition Management Rules, 2016

114

115

116

117

118

119

Appendix 6: Salient Features of Major Labor Laws Applicable to Establishments Engaged in Construction of Civil Works

(i) Workmen Compensation Act, 1923 - The Act provides for compensation in case of injury by accident arising out of and during the course of employment.

(ii) Payment of Gratuity Act, 1972 - Gratuity is payable to an employee under the Act on satisfaction of certain conditions on separation if an employee has completed 5 years’ service or more or on death at the rate of 15 days wages for every completed year of service. The Act is applicable to all establishments employing 10 or more employees.

(iii) Employees’ PF and Miscellaneous Provisions Act, 1952 - The Act provides for monthly contributions by the employer plus workers @10 % or 8.33 %. The benefits payable under the Act are: (a) Pension or family pension on retirement or death as the case may be; (b) deposit linked insurance on the death in harness of the worker; (c) payment of PF accumulation on retirement/death etc.

(iv) Maternity Benefit Act, 1951 - The Act provides for leave and some other benefits to women employees in case of confinement or miscarriage etc.

(v) Contract Labour (Regulation and Abolition) Act, 1970 - The Act provides for certain welfare measures to be provided by the Contractor to contract labor and in case the Contractor fails to provide, the same are required to be provided by the Principal Employer by Law. The principal employer is required to take Certificate of Registration and the Contractor is required to take a License from the designated Officer. The Act is applicable to the establishments or Contractor of principal employer if they employ 20 or more contract labor.

(vi) Minimum Wages Act, 1948 - The employer is supposed to pay not less than the Minimum Wages fixed by appropriate Government as per provisions of the Act if the employment is a scheduled employment. Construction of Buildings, Roads, Runways are scheduled employment.

(vii) Payment of Wages Act, 1936 - It lays down as to by what date the wages are to be paid, when it will be paid and what deductions can be made from the wages of the workers.

(viii) Equal Remuneration Act, 1979 - The Act provides for payment of equal wages for work of equal nature to Male and Female workers and not for making discrimination against Female employees in the matters of transfers, training and promotions etc.

(ix) Payment of Bonus Act, 1965 - The Act is applicable to all establishments employing 20 or more workmen. The Act provides for payments of annual bonus subject to a minimum of 8.33 % of wages and maximum of 20 % of wages to employees drawing Rs. 3,500/- per month or less. The bonus to be paid to employees getting Rs. 2,500/- per month or above up to Rs.3,500/- per month shall be worked out by taking wages as Rs.2,500/- per month only. The Act does not apply to certain establishments. The newly set up establishments are exempted for five years in certain circumstances. Some of the State Governments have reduced the employment size from 20 to 10 for the purpose of applicability of the Act.

(x) Industrial Disputes Act, 1947 - The Act lays down the machinery and procedure for resolution of industrial disputes, in what situations a strike or lock-out becomes illegal and what are the requirements for laying off or retrenching the employees or closing down the establishment.

(xi) Industrial Employment (Standing Orders) Act, 1946 - It is applicable to all establishments employing 100 or more workmen (employment size reduced by some of the States and Central Government to 50). The Act provides for laying down rules governing the conditions of employment by the employer on matters provided in the Act and get the same certified by the designated Authority.

120

(xii) Trade Unions Act, 1926 - The Act lays down the procedure for registration of trade unions of workmen and employees. The trade unions registered under the Act have been given certain immunities from civil and criminal liabilities.

(xiii) Child Labor (Prohibition and Regulation) Act, 1986 - The Act prohibits employment of children below 14 years of age in certain occupations and processes and provides for regulation of employment of children in all other occupations and processes. Employment of child labor is prohibited in Building and Construction Industry.

(xiv) Inter-State Migrant Workmen's (Regulation of Employment and Conditions of Service) Act, 1979 - The Act is applicable to an establishment which employs 5 or more inter-state migrant workmen through an intermediary (who has recruited workmen in one state for employment in the establishment situated in another state). The inter-state migrant workmen, in an establishment to which this Act becomes applicable, are required to be provided certain facilities such as housing, medical aid, traveling expenses from home up to the establishment and back, etc

(xv) The Building and Other Construction Workers (Regulation of Employment and Conditions of Service) Act, 1996 and the Cess Act of 1996 - All the establishments who carry on any building or other construction work and employ 10 or more workers are covered under this Act. All such establishments are required to pay Cess at rate not exceeding 2% of the cost of construction as may be notified by the Government. The employer of the establishment is required to provide safety measures at the building or construction work and other welfare measures, such as canteens, first-aid facilities, ambulance, housing accommodation for workers near the workplace etc. The employer to whom the Act applies has to obtain a registration certificate from the Registering Officer appointed by the Government.

121

Appendix 7: Water Test Reports 7(a): Narmada River at u/s of Kasrawad town

122

7(b): Water Test Report of Gomai River

123

Appendix 8: Stakeholder consultation

Rajpur Town

124

125

Summary of Consultation with Stakeholders Date Locati No. of Participants Topics Discussed Issues on Particip ants 25th At 19 Elected • Present drinking water • The Nagar Parishads do not have capacity or march comm M=10 representatives, supply source and its resources to be party to sharing the loan 2016 unity F=09 Chairperson of condition repayment. hall ULB, Chief • Need of improvement • The prime concern and apprehension of the Municipal Officer, Revenue of the present ULB Chairman regarding the project was department, elder situation whether it will be a financial burden on the person • Briefing on project Nagar Parishad. objectives probable • The Chairman of the ULB expressed need for implementation the project and willingness to take it up; procedures • Rajpur Nagar Parishad is operating the water • Potential positive and supply system for the town, but capacity to be negative impacts due further built. to project • Operation and maintenance of the facilities implementation developed under the project and community • Land use and area to participation; be covered under the • project • 27th Slum M=7 Slum dwellers • Briefing on project • None of the people knew about the proposed March. area F=3 objectives probable project. On learning about the project, they 2016 T=10 implementation expressed that they were happy that the entire procedures community would be benefited from the upgraded water supply. • Potential positive and • Slum dwellers showed willingness to take water negative impacts due connections but demanded relaxation in user to project charges. implementation • People were briefed about the complaint redress • Experiences sharing mechanism. on - livelihood activities,

126

Resettlement and Rehabilitation, women empowerment, tribal development, health, education, convergence with existing government social security schemes etc. • Grievance Redress procedures 27th ward Total= 20 Community • Knowledge of project • women had heard about the proposed project march 05 F=8 , members • Present water supply and welcomed it as women are facing many 2016 M=12 situation: only half an problem in fetching water for hours.. hours of supply • Some participants did not have water alternate day connections. The women were happy to learn • Drinking water user about the proposed project. charge • Possibility of exempting the poor and vulnerable from user charge payment.

28th ward Total - Community • Status of existing • The area has insufficient and inadequate March no. 10 25 members (Low drinking water supply drinking water supply. Water from two tube 2016 (Female income group; the system; wells is presently supplied to the 10, Male men work as daily • Need for area/community. The area faces severe water - 15) laborers and the improvements to crisis during the summer season when the women are present system; ground water level drops. housewives) • Relevant information • The community welcomed the project and of the upcoming expressed need for it. However, they were project and benefits of apprehensive that their economic condition the project. would prevent them from paying water user • Potential positive and charges. negative impacts due • Possibility of exempting the poor and vulnerable from user charge payment. 127

to project • implementation • Ensuring no income loss 26th Market Total= Street vendors • temporarily shifting of • As excavation may not be possible at night as March area 18 and shopkeepers weekly vegetable labour may not get agree to work in night shift, ..2016 M=15,F market during construction will be undertaken with care to =03 excavation. avoid the weekly haat day, such that no • shifting of Street income loss takes place due the civil work. vendors. • Mobile vendors will be given sufficient notice • Shifting or adjusting and assistance to shift to nearby locations, so extended potion of that they do not face income loss. Mobile shopkeepers. street vendors agreed to the proposal. • Some small restaurant/food stall owners expressed a concern that dust during excavation may fall on / spoil eatables. Mitigation measures such as spraying of water on the excavated soil particularly around such restaurants/food stalls to ensure there is no dust flying around and other appropriate measures as per IEE shall be taken during construction. Note: Boatmen and washermen were not observed near the proposed intake well location on Narmada river, hence need for a separate consultation with them was not perceived.

128

Kasrawad- Stakeholder Consultation

Stakeholder Consultation

List of Participants in Consultation Meeting

129

Summary of Consultation with Stakeholders Date Location No. of Participants Topics Discussed Issues Participants 2nd At 13 Elected • Present drinking water • Kasrawad Nagar Parishad is operating the April Parisha M=06 representatives, supply source and its water supply system for the town, but capacity 2016 d F=07 Chairperson of condition to be further built. meeting ULB, Chief • Need of improvement of • The Chairman of the ULB expressed need for hall Municipal Officer, Revenue the present situation the project and willingness to take it up;

department, elder • Briefing on project • The Nagar Parishads do not have capacity or person objectives probable resources to be party to sharing the loan implementation repayment. procedures • The prime concern and apprehension of the • Potential positive and ULB Chairman regarding the project was negative impacts due to whether it will be a financial burden on the project implementation Nagar Parishad. • Land use and area to be • Operation and maintenance of the facilities covered under the developed under the project and community project participation; • The official from revenue department gave consent of speedy allotment for required land for project. 3rd Ward -05 M=15 Community • Briefing on project • None of the people knew about the proposed April F=3 persons objectives probable project. On learning about the project, they 2016 T=18 implementation expressed that they were happy that the entire procedures community would be benefited from the upgraded water supply. • Potential positive and • Slum dwellers showed willingness to take water negative impacts due to connections but demanded relaxation in user project implementation charges. • Experiences sharing on • People were briefed about the complaint redress - livelihood activities, mechanism. Resettlement and Rehabilitation, women empowerment, tribal

130

development, health, education, convergence with existing government social security schemes etc. • Grievance Redress procedures 3rd ward 10 Total= 20 F=8 Slum community • Knowledge of project • Women had heard about the proposed project and April , • Present water supply welcomed it as women are facing many problem 2016 M=12 situation: only half an in fetching water for hours.. hours of supply alternate • Some participants did not have water connections. day The women were happy to learn about the • Drinking water user proposed project. charge • Possibility of exempting the poor and vulnerable from user charge payment.

4th ward Total - 25 Community • Status of existing • The area has insufficient and inadequate April no. 03 (Female 10, members (Low drinking water supply drinking water supply. Water from two tube 2016 Male - 15) income group; the system; wells is presently supplied to the men work as daily • Need for improvements area/community. The area faces severe water laborers and the to present system; crisis during the summer season when the women are • Relevant information of ground water level drops. housewives) the upcoming project • The community welcomed the project and and benefits of the expressed need for it. However, they were project. apprehensive that their economic condition • Potential positive and would prevent them from paying water user negative impacts due to charges. project implementation • Possibility of exempting the poor and • Ensuring no income vulnerable from user charge payment. loss 4th Market Total= 20 Street vendors • Temporarily shifting of • As excavation may not be possible at night as April area M=15,F=05 and shopkeepers weekly vegetable labour may not get agree to work in night shift, 2016 market during construction will be undertaken with care to

131

excavation. avoid the weekly haat day, such that no • Shifting of Street income loss takes place due the civil work. vendors. • Mobile vendors will be given sufficient notice • Shifting or adjusting and assistance to shift to nearby locations, so extended potion of that they do not face income loss. Mobile shopkeepers. street vendors agreed to the proposal. • Some small restaurant/food stall owners expressed a concern that dust during excavation may fall on / spoil eatables. Mitigation measures such as spraying of water on the excavated soil particularly around such restaurants/food stalls to ensure there is no dust flying around and other appropriate measures as per IEE shall be taken during construction. Note: Boatmen and washermen were not observed near the proposed intake well location on Narmada river, hence need for a separate consultation with them was not perceived.

132

Karahi Padlya Stakeholder consultation

Stakeholder Consultation

133

Summary of Consultation with Stakeholders Date Location No. of Participants Topics Discussed Issues Participants 15th At 21 Elected • Present drinking • The Nagar Parishads do not have April community M=14 representatives, water supply source capacity or resources to be party to 2016 hall F=07 Chairperson of and its condition sharing the loan repayment. ULB, Chief • Need of • The prime concern and Municipal Officer, Revenue improvement of the apprehension of the ULB Chairman department, present situation regarding the project was whether it • Briefing on project will be a financial burden on the objectives probable Nagar Parishad. implementation • The Chairman of the ULB expressed procedures need for the project and willingness • Potential positive to take it up; and negative • Karhi padlya Nagar Parishad is impacts due to operating the water supply system project for the town, but capacity to be implementation further built. • Land use and area • Operation and maintenance of the to be covered under facilities developed under the project the project and community participation; • •

134

27th Slum area M=7 Slum dwellers • Briefing on project • None of the people knew about the March. F=3 objectives probable proposed project. On learning about 2016 T=10 implementation the project, they expressed that they procedures were happy that the entire community would be benefited from the upgraded • Potential positive and water supply. negative impacts due • Slum dwellers showed willingness to to project take water connections but demanded implementation relaxation in user charges. • Experiences sharing • People were briefed about the on - livelihood complaint redress mechanism. activities, Resettlement and Rehabilitation, women empowerment, tribal development, health, education, convergence with existing government social security schemes etc. • Grievance Redress procedures 17th ward 11 Total= 20 Community • Knowledge of project • women had heard about the April F=10 , members • Present water supply proposed project and welcomed it as 2016 M=10 situation: only half an women are facing many problem in hours of supply fetching water for hours.. alternate day • Some participants did not have water • Drinking water user connections. The women were happy charge to learn about the proposed project. • Possibility of exempting the poor and vulnerable from user charge payment.

135

17th ward no. Total - 27 Slum area (Low • Status of existing • The area has insufficient and April 09 (Female income group; drinking water inadequate drinking water supply. 2016 10, Male - the men work as supply system; Water from two tube wells is 17) daily laborers • Need for presently supplied to the and the women improvements to area/community. The area faces are housewives) present system; severe water crisis during the • Relevant summer season when the ground information of the water level drops. upcoming project • The community welcomed the and benefits of the project and expressed need for it. project. However, they were apprehensive • Potential positive that their economic condition would and negative prevent them from paying water user impacts due to charges. project • Possibility of exempting the poor and implementation vulnerable from user charge • Ensuring no income payment. loss • 18th Market Total= 10 Street vendors • temporarily shifting • As excavation may not be possible April area M=08,F=02 and of weekly vegetable at night as labour may not get agree 2016 shopkeepers market during to work in night shift, construction will excavation. be undertaken with care to avoid the

136

• shifting of Street weekly haat day, such that no vendors. income loss takes place due the civil • Shifting or adjusting work. extended potion of • Mobile vendors will be given shopkeepers. sufficient notice and assistance to shift to nearby locations, so that they do not face income loss. Mobile street vendors agreed to the proposal. • Some small restaurant/food stall owners expressed a concern that dust during excavation may fall on / spoil eatables. Mitigation measures such as spraying of water on the excavated soil particularly around such restaurants/food stalls to ensure there is no dust flying around and other appropriate measures as per IEE shall be taken during construction.

137

138

Pansemal Stakeholder Consultations

S.N. Name of Participant Participants Status 1 Om Prakash Khandelwal President ULB 2 Sangita Chouhan Vice President 3 Madhu Choudhary CMO 4 Chandrakant Choudhary Sub Engineer 5 Amit Shah Accountant 6 Shiv Charan Verma Parshad 7 Ram Avtar Soni Parshad 8 Manoj Choudhary Parshad 9 Saheb Rao Choudhary Parshad 10 Rajju Patel Local Resident 11 Ajay Mishra Local Resident 12 Lokesh Shukla Local Resident 13 Anup Mishra Local Resident 14 Rajendra Sitole Local Resident 15 Sohan Agrawal Local Resident 16 Kailash Khandelwal Local Resident 17 Alka Rathore Local Resident 18 Dinesh Badgujar Local Resident 19 Ramakant Ingle Local Resident 20 Shanbhnath Patil Local Resident 21 Bhaushinde Patil Local Resident 22 Ahemkant Ingle Local Resident 23 Deepak Mahajan Local Resident 24 Sunil Shukla Local Resident 25 M Faqir Local Resident 26 Mohan Shankar Local Resident 27 Pandurang Local Resident 28 Rajendra Solanki Local Resident

139

Foccussed Group Discussion & Data Collection During Survey

140

Summary of Consultation with Stakeholders

S.N. Location Participants Topic Discussed Issues Raised

1 Pansemal Chairman, Vice- Present drinking The Chairman and other all Nagar Chairman, CMO, water supply source and staff member of the ULB Parishad Sub Engineer, its condition expressed willingness to accept

th Office / 11 Accountant and Need of the project. March other staff improvement of the Operation and maintenance members of present situation of the facilities developed under Pansemal Briefing on the project and community Municipal Council project objectives, participation. office, Local probable implementation Probability of keeping the elected Political procedures poor and the vulnerable out of representatives Potential positive the user charge. of different and negative impacts due The existing water supply wards, Surveyor to project implementation system is in dilapidated and councilors Land use and condition and needs area to be covered under refurbishment along with water the project supply coverage (100 percent).

Drinking water Land required for the water user charge supply project will be dealt by the ULB and belongs to Municipal Council, Pansemal already.

2 Ward No. 1, 3, Local Residents Relevant information of The commencement of the

th 5, 10, 11 / 11 Male: Farmer the upcoming project in project work. Commissioning of March Businessmen, technical and the project. Scarcity of drinking Female: House environmental water in area Wife. perspective; Quality and quantity of the Status of existing water to be supplied after drinking water supply completion of the project.

system; The water is supplied for an Need for hour daily which is inadequate. improvements to present There are long queues and system. frequent quarrels over water

Relevant information of collection.

the upcoming project and The adolescent girls were benefits of the project. particularly interested in getting Potential positive and water at the household level as negative impacts due to it would reduce their workload project implementation to a great extent and give them

Ensuring no income more time for education or loss recreational activities.

Entire Plan and design Lack of water was reported has been prepared to as one of the main deterrent for supply drinking water households to build a sanitary house to house for 24 hrs toilet and practice hygiene in a day and cover the behavior. 100% area of the ward The community agreed that it after completion of entire will cooperate and manage distribution network. temporary discomfort arising

Public participation & due to construction in view of awareness. the larger benefits of getting water at the doorstep.

Appendix 9: Sample Grievance Registration Form (To be available in Hindi and English)

142

The ______Project welcomes complaints, suggestions, queries, and comments regarding project implementation. We encourage persons with grievance to provide their name and contact information to enable us to get in touch with you for clarification and feedback. Should you choose to include your personal details but want that information to remain confidential, please inform us by writing/typing *(CONFIDENTIAL)* above your name. Thank you.

Date Place of registration Project Town

Project: Contact information/personal details Name Gender * Male Age * Female Home address Place Phone no. E-mail Complaint/suggestion/comment/question Please provide the details (who, what, where, and how) of your grievance below:

If included as attachment/note/letter, please tick here: How do you want us to reach you for feedback or update on your comment/grievance?

FOR OFFICIAL USE ONLY Registered by: (Name of official registering grievance)

Mode of communication: Note/letter E-mail Verbal/telephonic Reviewed by: (Names/positions of officials reviewing grievance)

Action taken:

Whether action taken disclosed: Yes No Means of disclosure:

143

Appendix 10: Sample Outline Traffic Management Plan

A. Principles for TMP around the Water Pipes Construction Sites

1. One of the prime objectives of this TMP is to ensure the safety of all the road users along the work zone, and to address the following issues: (i) the safety of pedestrians, bicyclists, and motorists travelling through the construction zone; (ii) protection of work crews from hazards associated with moving traffic; (iii) mitigation of the adverse impact on road capacity and delays to the road users; (iv) maintenance of access to adjoining properties; and (v) addressing issues that may delay the project.

B. Operating Policies for TMP

2. The following principles will help promote safe and efficient movement for all road users (motorists, bicyclists, and pedestrians, including persons with disabilities) through and around work zones while reasonably protecting workers and equipment. (i) Make traffic safety and temporary traffic control an integral and high-priority element of project from planning through design, construction, and maintenance. (ii) Inhibit traffic movement as little as possible. (iii) Provide clear and positive guidance to drivers, bicyclists, and pedestrians as they approach and travel through the temporary traffic control zone. (iv) Inspect traffic control elements routinely, both day and night, and make modifications when necessary. (v) Pay increased attention to roadside safety in the vicinity of temporary traffic control zones. (vi) Train all persons that select, place, and maintain temporary traffic control devices. (vii) Keep the public well informed. (viii) Make appropriate accommodation for abutting property owners, residents, businesses, emergency services, railroads, commercial vehicles, and transit operations.

3. Figure A2 to Figure A12illustrates the operating policy for TMP for the construction of water pipes and the sewers along various types of roads.

C. Analyze the impact due to street closure

4. Apart from the capacity analysis, a final decision to close a particular street and divert the traffic should involve the following steps:

(i) approval from the ULB/Public Works Department (PWD) to use the local streets as detours;

144

(ii) consultation with businesses, community members, traffic police, PWD, etc, regarding the mitigation measures necessary at the detours where the road is diverted during the construction; (iii) determining of the maximum number of days allowed for road closure, and incorporation of such provisions into the contract documents; (iv) determining if additional traffic control or temporary improvements are needed along the detour route; (v) considering how access will be provided to the worksite; (vi) contacting emergency service, school officials, and transit authorities to determine if there are impacts to their operations; and (vii) developing a notification program to the public so that the closure is not a surprise. As part of this program, the public should be advised of alternate routes that commuters can take or will have to take as result of the traffic diversion.

5. If full road-closure of certain streets within the area is not feasible due to inadequate capacity of the detour street or public opposition, the full closure can be restricted to weekends with the construction commencing on Saturday night and ending on Monday morning prior to the morning peak period.

Figure A1: Policy Steps for the TMP

• Review construction schedule and methods Review

Traffic Re- • Identify initial traffic recirculation and control policy Circulation

• Identify routes for traffic diversions Traffic • Analyse adverse impact & mitigation at the detours Diversions

• Begin community consultation for consensus Full Road • Finalise or determine alternate detours Colsures

• Identify temporary parking (on and off -street ) Temporary • Discuss with CMC, owner, community for use parking

• Coordinate with theTraffic Police to enforce traffic and diversions Police Coordination

• Install traffic control devices (traffic cones, sgns, lightings, etc) Install control devices

• Conduct campaigns, publicity, and notify public about street closure Awareness

Develop a mechanism to address public grievances regarding disruptons (traffic, utilities, and diversions) Public • Redress

D. Public awareness and notifications

145

6. As per discussions in the previous sections, there will be travel delays during the constructions, as is the case with most construction projects, albeit on a reduced scale if utilities and traffic management are properly coordinated. There are additional grounds for travel delays in the area, as most of the streets lack sufficient capacity to accommodate additional traffic from diverted traffic as a result of street closures to accommodate the works.

6. The awareness campaign and the prior notification for the public will be a continuous activity which the project will carry out to compensate for the above delays and minimize public claims as result of these problems. These activities will take place sufficiently in advance of the time when the roadblocks or traffic diversions take place at the particular streets. The reason for this is to allow sufficient time for the public and residents to understand the changes to their travel plans. The project will notify the public about the roadblocks and traffic diversion through public notices, ward level meetings and city level meeting with the elected representatives.

7. The PIU will also conduct an awareness campaign to educate the public about the following issues:

(i) traffic control devices in place at the work zones (signs, traffic cones, barriers, etc.); (ii) defensive driving behaviour along the work zones; and (iii) reduced speeds enforced at the work zones and traffic diversions.

8. It may be necessary to conduct the awareness programs/campaigns on road safety during construction.

9. The campaign will cater to all types of target groups i.e. children, adults, and drivers. Therefore, these campaigns will be conducted in schools and community centres. In addition, the project will publish a brochure for public information. These brochures will be widely circulated around the area and will also be available at the PIU, and the contractor's site office. The text of the brochure should be concise to be effective, with a lot of graphics. It will serve the following purpose:

(i) explain why the brochure was prepared, along with a brief description of the project; (ii) advise the public to expect the unexpected; (iii) educate the public about the various traffic control devices and safety measures adopted at the work zones; (iv) educate the public about the safe road user behaviour to emulate at the work zones; (v) tell the public how to stay informed or where to inquire about road safety issues at the work zones (name, telephone, mobile number of the contact person; and (vi) indicate the office hours of relevant offices.

E. Install traffic control devices at the work zones and traffic diversion routes

146

10. The purpose of installing traffic control devices at the work zones is to delineate these areas to warn, inform, and direct the road users about a hazard ahead, and to protect them as well as the workers. As proper delineation is a key to achieve the above objective, it is important to install good traffic signs at the work zones. The following traffic control devices are used in work zones:

• Signs • Pavement Markings • Channelizing Devices • Arrow Panels • Warning Lights

11. Procedures for installing traffic control devices at any work zone vary, depending on road configuration, location of the work, construction activity, duration, traffic speed and volume, and pedestrian traffic. Work will take place along major roads, and the minor internal roads. As such, the traffic volume and road geometry vary. The main roads carry considerable traffic; internal roads in the new city areas are wide but in old city roads very narrow and carry considerable traffic. However, regardless of where the construction takes place, all the work zones should be cordoned off, and traffic shifted away at least with traffic cones, barricades, and temporary signs (temporary “STOP” and “GO”).

12. Figure A2 to Figure A6 illustrates a typical set-up for installing traffic control devices at the work zone of the area, depending on the location of work on the road way, and road geometrics: • Work on shoulder or parking lane • Shoulder or parking lane closed on divided road • Work in Travel lane • Lane closure on road with low volume • Street closure with detour

13. The work zone should take into consideration the space required for a buffer zone between the workers and the traffic (lateral and longitudinal) and the transition space required for delineation, as applicable. For the works, a 30 cm clearance between the traffic and the temporary STOP and GO signs should be provided. In addition, at least 60 cm is necessary to install the temporary traffic signs and cones.

14. Traffic police should regulate traffic away from the work zone and enforce the traffic diversion result from full street closure in certain areas during construction. Flagggers/ personnel should be equipped with reflective jackets at all times and have traffic control batons (preferably the LED type) for regulating the traffic during night time.

16. In addition to the delineation devices, all the construction workers should wear fluorescent safety vests and helmets in order to be visible to the motorists at all times. There should be provision for lighting beacons and illumination for night constructions.

147

Figure A2 & A3: Work on shoulder or parking lane & Shoulder or parking lane closed on divided road

148

Figure A4 & A5: Work in Travel lane & Lane closure on road with low volume

149

Figure A6: Street closure with detour

150

Appendix 151

Appendix 11: Drinking Water Standards

No. Substance or Requirement Undesirable effect outside Permissible Remarks characteristic Desirable the desirable limit in the limit absence of alternate Source Essential Characteristic 1. Colour Hazen 5 Above 5, consumer 25 Extended to 25 only if Units, Max acceptance decreases toxic Substance are not suspect in absence of alternate sources 2. Odour Unobjectiona - - a) test cold and when ble heated b) test are several dilutions 3. Taste Agreeable - - Test to be conducted only after safely has been established 4. Turbidity (NTU) 5 Above 5, consumer 10 - Max acceptance decreases 5. pH value 6.5 to 8.5 Beyond this range the No relaxation - water will after the mucous membrane and/or water supply system 6. Total 300 Encrustation in water 600 - Hardness supply structure and (mg/L) adverse effects on CaCO3 domestic use 7. Iron (mg/L, Fe) 0.3 Beyond this limit 1.0 - Max taste/appearance are affected; has adverse effects on domestic uses and water supply structure and promotes iron bacteria 8. Chlorides 250 250 Beyond effects outside the 1000 - (mg/L, Cl) Max desirable limit 9. Residual free 0.2 - - To be applicable only Chlorine (mg/L), when water is Max chlorinated. Tested at customer end. When protection against viral infection is required, it should be min. 0.5 mg/L. Desirable Characteristics 10. Dissolved solids 500 Beyond this, palatability 2000 - mg/L. Max decreases and may cause gastrointestinal irritation. 11. Calcium (mg/L, 75 Encrustation in water 200 - Ca) Max. supply structure and adverse effects on domestic use. 12. Magnesium (mg/L, 30 Encrustation in water 100 - Mg) Max supply structure and adverse effects on domestic use. 13. Copper (mg/L, Cu) 0.05 Astringent taste dis 1.5 - Max coloration and corrosion of

151

Appendix 152

pipes fittings and utensils will be caused beyond this. 14. Manganese 0.1 Beyond this limit 0.3 - (mg/L, Mn) Max taste/appearance are affected, has advers effect on domestic use and water supply structure 15. Sulphate 200 Beyond this causes gastro 400 May be extended upto (mg/L, SO4) Max. intestinal irritation when 400 provided magnesium or sodium are magnesium (as Mg) present does not exceed 30 16. Nitrate (mg/L, 45 Beyond this 100 - NO3) Max. methaemoglobinemia takes place. 17. Fluoride (mg/L, F) 1.0 Fluoride may be kept as 1.5 - Max. low as possible. High fluoride may cause fluorosis. 18. Phenolic 0.001 Beyond this, it may cause 0.002 - Compounds (mg/L objectionable taste and C6H5OH) Max. odour 19. Mercury (mg/L Hg) 0.001 Beyond this the water No Relaxation. To be tested when Max becomes toxic pollution is suspected 20 Cadmium 0.01 Beyond this the water No Relaxation. To be tested when (mg/L, Cd) Max becomes toxic pollution is suspected 21. Selenium 0.01 Beyond this the water No Relaxation. To be tested when (mg/L, Se) Max becomes toxic. pollution is suspected 22. Arsenic 0.05 Beyond this the water No Relaxation To be tested when (mg/L, As) Max. becomes toxic pollution is suspected 23. Cyanide 0.05 Beyond this the water No Relaxation To be tested when becomes toxic pollution is suspected 24. Lead (mg/L Pb) 0.05 Beyond this the water No Relaxation To be tested when Max. becomes toxic pollution is suspected 25. Zinc (mg/L, Zn) 5 Beyond this limit it can 15 To be tested when Max. cause astringent taste and pollution is suspected an opalescence in water 26. Anionic detergents 0.2 Beyond this limit it can 1.0 To be tested when (mg/L, MBAS) cause a light froth in water pollution is suspected Max 27. Chromium 0.05 May be carcinogenic above - - (mg/L, Cr6+ this limit 28. Polynuclear - May be carcinogenic - - Aromatic Hydrocarbons (mg/l, PAH) Max 29. Mineral oil 0.01 Beyond this limit, 0.03 To be tested when (mg/L) undesirable taste and pollution is suspected odour after chlorination takes place 30. Pesticides (mg/L) Absent Toxic 0.001 - max Radioactive materials 31. Alpha emitters - - 0.1 - Bq/L Max 32. Beta emitters - - 1.0 - Pci/L Max 33. Alkalinity (mg/L,) 200 Beyond this limit, taste 600 - Max becomes unpleasant 34. Aluminum (mg/L, 0.03 Cumulative effect is 0.2 Al) Max reported to cause dementia 35. Boron (mg/L) Max 1.0 - 5.0 -

152

Appendix 153

Appendix 12: SAMPLE ENVIRONMENTAL SITE INSPECTION REPORT

Project Name Contract Number

NAME: ______DATE: ______TITLE: ______DMA: ______LOCATION: ______GROUP: ______

WEATHER: Project Survey Activity Design Stage Implementation Pre-Commissioning Guarantee Period

Monitoring Items Compliance Compliance marked as Yes / No / Not applicable (NA) / Partially Implemented (PI) EHS supervisor appointed by contractor and available on site Archaeological Supervisor appointed by contractor and available on site Construction site management plan (spoils, safety, schedule, equipment etc.,) prepared Traffic management plan prepared Dust is under control Excavated soil properly placed within minimum space Construction area is confined; no traffic/pedestrian entry observed Surplus soil/debris/waste is disposed without delay Construction material (sand/gravel/aggregate) brought to site as & when required only Tarpaulins used to cover sand & other loose material when transported by vehicles After unloading , wheels & undercarriage of vehicles cleaned prior to leaving the site No AC pipes disturbed/removed during excavation No chance finds encountered during excavation Work is planned in consultation with traffic police Work is not being conducted during heavy traffic Work at a stretch is completed within a day (excavation, pipe laying & backfilling) Pipe trenches are not kept open unduly Road is not completely closed; work is conducted on edge; at least one line is kept open Road is closed; alternative route provided & public informed, information board provided Pedestrian access to houses is not blocked due to pipe laying Spaces left in between trenches for access Wooden planks/metal sheets provided across trench for pedestrian No public/unauthorized entry observed in work site Children safety measures (barricades, security) in place at works in residential areas Prior public information provided about the work, schedule and disturbances Caution/warning board provided on site Guards with red flag provided during work at busy roads Workers using appropriate PPE (boots, gloves, helmets, ear muffs etc) 153

Appendix 154

Workers conducting or near heavy noise work is provided with ear muffs Contractor is following standard & safe construction practices Deep excavation is conducted with land slip/protection measures First aid facilities are available on site and workers informed Drinking water provided at the site Toilet facility provided at the site Separate toilet facility is provided for women workers Workers camps are maintained cleanly Adequate toilet & bath facilities provided Contractor employed local workers as far as possible Workers camp set up with the permission of PIU Adequate housing provided Sufficient water provided for drinking/washing/bath No noisy work is conducted in the nights Local people informed of noisy work No blasting activity conducted Pneumatic drills or other equipment creating vibration is not used near old/risky buildings

Signature ______

Sign off

______Name Name Position Position

154

Appendix 13: Quarterly Reporting Format for Assistant Safeguards Officer

1. Introduction • Overall project description and objectives • Description of sub-projects • Environmental category of the sub-projects • Details of site personnel and/or consultants responsible for environmental monitoring • Overall project and sub-project progress and status

Status of Sub-Project Sub-Project List of Progress No. Design Pre- Construction Operational Name Works of Works Construction Phase            

2. Compliance status with National/ State/ Local statutory environmental requirements No. Sub-Project Name Statutory Environmental Status of Action Required Requirements Compliance

3. Compliance status with environmental loan covenants No. (List schedule and Covenant Status of Compliance Action Required paragraph number of Loan Agreement)

4. Compliance status with the environmental management and monitoring plan • Provide the monitoring results as per the parameters outlined in the EMP. Append supporting documents where applicable, including Environmental Site Inspection Reports. • There should be reporting on the following items which can be incorporated in the checklist of routine Environmental Site Inspection Report followed with a summary in the semi- annual report send to ADB. Visual assessment and review of relevant site documentation during routine site inspection needs to note and record the following: o What are the dust suppression techniques followed for site and if any dust was noted to escape the site boundaries; o If muddy water was escaping site boundaries or muddy tracks were seen on adjacent roads; o adequacy of type of erosion and sediment control measures installed on site, condition of erosion and sediment control measures including if these were intact following heavy rain; o Are their designated areas for concrete works, and refuelling; o Are their spill kits on site and if there are site procedure for handling emergencies; o Is there any chemical stored on site and what is the storage condition? o Is there any dewatering activities if yes, where is the water being discharged; o How are the stockpiles being managed; o How is solid and liquid waste being handled on site; o Review of the complaint management system;

Appendix 156

o Checking if there are any activities being under taken out of working hours and how that is being managed. Summary Monitoring Table Impacts Mitigation Parameters Method of Location Date of Name of (List from Measures Monitored (As a Monitoring of Monitoring Person IEE) (List from minimum those Monitoring Conducted Who IEE) identified in the IEE Conducted should be the monitored) Monitoring Design Phase

Pre-Construction Phase

Construction Phase

Operational Phase

Overall Compliance with CEMP/ EMP No. Sub-Project EMP/ CEMP CEMP/ EMP Status of Action Name Part of Being Implementation Proposed and Contract Implemented (Excellent/ Satisfactory/ Additional Documents (Y/N) Partially Satisfactory/ Measures (Y/N) Below Satisfactory) Required

5. Approach and methodology for environmental monitoring of the project • Brief description on the approach and methodology used for environmental monitoring of each sub-project

6. Monitoring of environmental impacts on project surroundings (ambient air, water quality and noise levels) • Brief discussion on the basis for monitoring • Indicate type and location of environmental parameters to be monitored • Indicate the method of monitoring and equipment to be used • Provide monitoring results and an analysis of results in relation to baseline data and statutory requirements

156

Appendix 157

As a minimum the results should be presented as per the tables below.

Air Quality Results Parameters (Government Standards) Site No. Date of Testing Site Location PM10 SO2 NO2 µg/m3 µg/m3 µg/m3

Parameters (Monitoring Results) Site No. Date of Testing Site Location PM10 SO2 NO2 µg/m3 µg/m3 µg/m3

Water Quality Results Parameters (Government Standards) Site No. Date of Sampling Site Location pH Conductivity BOD TSS TN TP µS/cm mg/L mg/L mg/L mg/L

Parameters (Monitoring Results) Site No. Date of Sampling Site Location pH Conductivity BOD TSS TN TP µS/cm mg/L mg/L mg/L mg/L

Noise Quality Results LAeq (dBA) (Government Standard) Site No. Date of Testing Site Location Day Time Night Time

LAeq (dBA) (Monitoring Results) Site No. Date of Testing Site Location Day Time Night Time

7. Summary of key issues and remedial actions • Summary of follow up time-bound actions to be taken within a set timeframe.

8. Appendixes • Photos • Summary of consultations • Copies of environmental clearances and permits • Sample of environmental site inspection report Other

157

Appendix 158

Appendix 14: Treated water quality report of Kasrwad WTP

158