ECPVSC Paper 10/2011-12 For Discussion

Buildings Energy Efficiency Funding Schemes under the Environment and Conservation Fund

Purpose

This paper seeks –

(a) Members’ agreement to approve 70 funding applications and not to accept five funding applications for the Energy Efficiency Projects (EEP) of the Buildings Energy Efficiency Funding Schemes (BEEFS) under the Environment and Conservation Fund (ECF).

(b) Members’ support to seek approval from the ECF Committee for two funding applications of values exceeding HK$2.0 million for the EEP of the BEEFS under the ECF.

Summary

2. As at 31 July 2011, a total of 215 and 1,214 applications were received for Energy-cum-carbon Audit Projects (ECA) and EEP respectively. Since the Energy Conservation Projects Vetting Sub-committee (ECPVSC) meeting on 16 May 2011, 75 funding applications have been vetted. Out of these 75 applications, 70 funding applications are recommended for approval, five funding applications are recommended not to accept due to inadequate information received for assessment.

3. In addition to the above, nine funding applications were withdrawn by the applicants which are listed below.

Projects withdrawn by the Applicants

Project No. Applicant Funding Sought Energy-cum-carbon Audit – The Incorporated Owners of $50,000.00 Hill Lodge Hill Lodge (Ref. ECA-0067) Energy Efficiency Project - The Incorporated Owners of $51,475.00 May Shing Court (Ref. May Shing Court EEP-0238)

- 1 - ECPVSC Paper 10/2011-12 For Discussion

Project No. Applicant Funding Sought Energy Efficiency Project - The Owners’ Committee of $298,545.00 Manhattan Hill (Ref. EEP-0362) Energy Efficiency Project - New Kwai Fong Gardens $112,910.00 New Kwai Fong Gardens Owners’ Committee (Ref. EEP-0371) Energy Efficiency Project - The Incorporated Owners of $196,000.00 Hung Fuk Court Hung Fuk Court (Ref. EEP-0400) Energy Efficiency Project- The Incorporated Owners of $12,395.00 Pak Lok Building Pak Lok Building (Ref. EEP-1107) Energy Efficiency Project - The Incorporated Owners of $232,710.00 Yen Fat Building Yen Fat Building (Ref. EEP-1110) Energy Efficiency Project – The Incorporated Owners of $16,480.00 Wang Fung Building Wang Fung Building (Ref. EEP-1121) Energy Efficiency Project – The Incorporated Owners of $500,000.00 European Asian Bank European Asian Bank Building Building (Ref. EEP-1150) $1,470,515.00

4. The following five applications have been rejected with the reason that inadequate information have been received from the applicants despite sending at least two reminder letters and a conclusion letter to each applicant. Thus, the information provided in the application is inadequate for the assessment to proceed further.

Projects Rejected with Inadequate Information

Project No. Application Funding Sought EEP1097 Sun Ying Industrial Centre, Energy $107,850.00 Efficiency Project EEP1101 Jubilee Garden, Energy Efficiency $255,000.00 Project

- 2 - ECPVSC Paper 10/2011-12 For Discussion

Project No. Application Funding Sought EEP1129 Yuen Long Yik Fat Building, Energy $12,295.00 Efficiency Project EEP1134 Hoi Hing Building, Energy Efficiency $57,080.00 Project EEP1136 McDonald's Building, Energy $500,000.00 Efficiency Project $932,225.00

5. The following 70 funding applications with the applied funding of value not exceeding HK$2.0 million are recommended for consideration.

Projects Recommended for Approval

Project Title Organization Duration Funding Sought Energy Efficiency The Incorporated November 2011 to Project – The Paragon Owners of The Paragon May 2012 See Note 1 (Ref. EEP0821) (7 months) (Annex I) Energy Efficiency The Incorporated September 2011 to Project – Fairway Owners of Fairway January 2013 Garden Garden (17 months) (Ref. EEP0830) (Annex II) Energy Efficiency The Incorporated November 2011 to Project – Sea Crest Villa Owners of Sea Crest August 2012 Phase I Villa Phase I (10 months) (Ref. EEP0840) (Annex III) Energy Efficiency The Owners’ Committee September 2011 to Project – of Nob Hill August 2012 (Ref. EEP0865) (12 months) (Annex IV) Energy Efficiency The Owners’ Committee September 2011 to Project – Highland Park of Highland Park November 2012 (Ref. EEP0868) (15 months) (Annex V)

- 3 - ECPVSC Paper 10/2011-12 For Discussion

Project Title Organization Duration Funding Sought Energy Efficiency The Incorporated November 2011 to Project – Valiant Owners of Valiant February 2013 Industrial Centre Industrial Centre (16 months) (Ref. EEP0878) (Annex VI) Energy Efficiency Coastal Skyline November 2011 to Project – Coastal Development Owners’ May 2012 Skyline Committee (7 months) (Ref. EEP0879) (Annex VII) Energy Efficiency The Incorporated December 2011 to Project – Pok Hong Owners of Pok Hong October 2012 Estate Estate (11 months) (Ref. EEP0890) (Annex VIII) Energy Efficiency Aberdeen Centre Kong September 2011 to Project – Aberdeen Shing Court Mutual Aid October 2011 Centre (Site 1) Kong Committee (2 months) Shing Court (Lighting) (Ref. EEP0909) (Annex IX) Energy Efficiency Aberdeen Centre Kong September 2011 to Project – Aberdeen Cheung Court Mutual October 2011 Centre (Site 1) Kong Aid Committee (2 months) Cheung Court (Lighting) (Ref. EEP0913) (Annex X) Energy Efficiency Aberdeen Centre Kong September 2011 to Project – Aberdeen Tai Court Mutual Aid October 2011 Centre (Site 1) Kong Tai Committee (2 months) Court (Lighting) (Ref. EEP0915) (Annex XI)

- 4 - ECPVSC Paper 10/2011-12 For Discussion

Project Title Organization Duration Funding Sought Energy Efficiency Aberdeen Centre Kong September 2011 to Project – Aberdeen Wing Court Mutual Aid October 2011 Centre (Site 1) Kong Committee (2 months) Wing Court (Lighting) (Ref. EEP0917) (Annex XII) Energy Efficiency Aberdeen Centre Kong September 2011 to Project – Aberdeen Hing Court Mutual Aid October 2011 Centre (Site 1) Kong Committee (2 months) Hing Court (Lighting) (Ref. EEP0919) (Annex XIII) Energy Efficiency The Incorporated September 2011 to Project – Kwun Hoi Owners of Kwun Hoi October 2011 Court, Kwun Chiu Court Court, Kwun Chiu Court (2 months) & Kwun King Court of & Kwun King Court of Aberdeen Centre Aberdeen Centre (Lighting) (Ref. EEP0921) (Annex XIV) Energy Efficiency The Incorporated September 2011 to Project – Hoi Chun Owners of Hoi Chun October 2011 Court, Hoi Chu Court, Court, Hoi Chu Court, (2 months) Hoi Shan Court, Hoi Wu Hoi Shan Court, Hoi Wu Court of Aberdeen Court of Aberdeen Centre (Lighting) Centre (Ref. EEP0923) (Annex XV) Energy Efficiency The Incorporated September 2011 to Project – Hoi Tsing Owners of Hoi Tsing October 2011 Court, Hoi Ying Court, Court, Hoi Ying Court, (2 months) Hoi Tin Court, Hoi Lung Hoi Tin Court, Hoi Lung Court of Aberdeen Court of Aberdeen Centre (Lighting) Centre (Ref. EEP0925) (Annex XVI)

- 5 - ECPVSC Paper 10/2011-12 For Discussion

Project Title Organization Duration Funding Sought Energy Efficiency The Incorporated November 2011 to Project – Sunningdale Owners of Sunningdale May 2012 Garden Garden (7 months) (Ref. EEP0943) (Annex XVII) Energy Efficiency The Incorporated September 2011 to Project – South Ocean Owners of South Ocean December 2012 Building Building (16 months) (Ref. EEP0957) (Annex XVIII) Energy Efficiency The Incorporated September 2011 to Project – Pacific View Owners of Pacific View February 2012 (Ref. EEP0958) (6 months) (Annex XIX) Energy Efficiency The Incorporated December 2011 to Project – Tung Tau Owners of Tung Tau (II) November 2012 Estate II Estate (12 months) (Ref. EEP0973) (Annex XX) Energy Efficiency The Owners Committee September 2011 to Project – The Victoria of The May 2012 Towers (9 months) (Ref. EEP0991) (Annex XXI) Energy Efficiency The Owners Committee October 2011 to Project – Yuen Long of Yuen Long Plaza June 2012 Plaza (Residential) (9 months) (Ref. EEP0995) (Annex XXII) Energy Efficiency The Incorporated December 2011 to Project – Cheung On Owners of Cheung On October 2012 Estate Estate (11 months) (Ref. EEP0998) (Annex XXIII ) Energy Efficiency The Incorporated October 2011 to Project – Eastern Owners of Eastern February 2012 Harbour Centre Harbour Centre (5 months) (Ref. EEP1004) (Annex XXIV)

- 6 - ECPVSC Paper 10/2011-12 For Discussion

Project Title Organization Duration Funding Sought Energy Efficiency The Incorporated October 2011 to Project – Tai Hing Owners of Tai Hing April 2013 Gardens, Phase I Gardens Phase I (19 months) (Ref. EEP1007) (Annex XXV) Energy Efficiency The Incorporated December 2011 to Project – Man Lok Owners of Man Lok September 2012 Building Building (10 months) (Ref. EEP1009) (Annex XXVI) Energy Efficiency The Incorporate Owners December 2011 to Project – Viking Villas of Viking Villas June 2012 (Ref. EEP1020) (7 months) (Annex XXVII) Energy Efficiency Site 1 September 2011 to Project – Site 1, Owners’ Committee May 2012 Whampoa Garden (9 months) (Ref. EEP1021) (Annex XXVIII) Energy Efficiency Owners’ Committee of January 2012 to Project – Sereno Verde Sereno Verde April 2012 (Ref. EEP1024) (4 months) (Annex XXIX) Energy Efficiency The Incorporated January 2012 to Project – Kai Yee Court Owners of Kai Yee Court April 2012 (Ref. EEP1025) (4 months) (Annex XXX) Energy Efficiency The Incorporated January 2012 to Project – Jade Court, Owners of Jade Court, March 2012 Belcher’s Street Belcher’s Street (3 months) (Ref. EEP1026) (Annex XXXI) Energy Efficiency The Incorporated January 2012 to Project – Wo Ming Owners of Wo Ming August 2012 Court Court (8 months) (Ref. EEP1028) (Annex XXXII) Energy Efficiency

- 7 - ECPVSC Paper 10/2011-12 For Discussion

Project Title Organization Duration Funding Sought Project – Cheung Sha The Incorporated December 2011 to Wan Road 158 & 158A Owners of Nos. 158 & December 2012 (Ref. EEP1029) 158A, (13 months) (Annex XXXIII) Road Energy Efficiency Oceania Heights August 2011 to Project – Oceania Owners’ Committee September 2011 Heights (2 months) (Ref. EEP1035) (Annex XXXIV) Energy Efficiency Owners’ November 2011 to Project – The Merton Committee May 2012 (Ref. EEP1038) (7 months) (Annex XXXV) Energy Efficiency The Incorporate Owners December 2011 to Project – Shield of Shield Industrial December 2012 Industrial Centre Centre (13 months) (Ref. EEP1045) (Annex XXXVI) Energy Efficiency The Owners’ Committee September 2011 to Project – The Apex of the Apex October 2011 (Ref. EEP1046) (2 months) (Annex XXXVII) Energy Efficiency The Incorporated September 2011 to Project – Le Palais Owners of Le Palais December 2011 (Ref. EEP1048) (4 months) (Annex XXXVIII) Energy Efficiency The Owners’ Committee September 2011 to Project – Sky Tower of Sky Tower November 2011 (Ref. EEP1050) (3 months) (Annex XXXIX) Energy Efficiency Site 5 Whampoa Garden September 2011 to Project – Whampoa Owners’ Committee March 2013 Garden Site 5 (18 months) (Ref. EEP1052) (Annex XL)

- 8 - ECPVSC Paper 10/2011-12 For Discussion

Project Title Organization Duration Funding Sought Energy Efficiency Estate August 2011 to Project – South Owners’ Committee May 2012 Horizons, Club House (10 months) (Lighting) (Ref. EEP1057) (Annex XLI) Energy Efficiency The Incorporated October 2011 to Project – Hung Yan Owners of Hung Yan November 2012 Building Building (14 months) (Ref. EEP1058) (Annex XLII) Energy Efficiency Site 11 Whampoa October 2011 to Project – Whampoa Garden Owners’ December 2012 Garden Site 11 Committee (15 months) (Ref. EEP1059) (Annex XLIII) Energy Efficiency Owner’s Committee of September 2011 to Project – Ever Gain Ever Gain Plaza August 2012 Plaza (12 months) (Ref. EEP1060) (Annex XLIV) Energy Efficiency Owners’ Committee of September 2011 to Project – Convention Convention Plaza December 2011 Plaza Apartments Apartments (4 months) (Ref. EEP1061) (Annex XLV) Energy Efficiency Station December 2011 to Project – Kowloon Development Owners May 2012 Station Development Committee (6 months) (Ref. EEP1062) (Annex XLVI) Energy Efficiency The Incorporated October 2011 to Project – Hung Yan Owners of Hung Yan May 2013 Building Building (20 months) (Ref. EEP1063) (Annex XLVII) Energy Efficiency The Incorporated November 2011 to Project – Yan Shing Owners of Yan Shing July 2012 Court Court (8 months)

- 9 - ECPVSC Paper 10/2011-12 For Discussion

Project Title Organization Duration Funding Sought (Ref. EEP1064) (Annex XLVIII) Energy Efficiency The Owners Committee October 2011 to Project – Waterside of Waterside Plaza April 2012 Plaza (7 months) (Ref. EEP1065) (Annex XLIX) Energy Efficiency The Incorporated September 2011 to Project – Royal Jubilee Owners of Royal Jubilee December 2011 (Ref. EEP1068) (4 months) (Annex L) Energy Efficiency The Development August 2011 to Project – Seaview Owners’ Committee of December 2011 Crescent Seaview Crescent (5 months) (Ref. EEP1069) (Annex LI) Energy Efficiency The Incorporated October 2011 to Project – Waterside Owners of Wing Ying May 2012 Plaza Building (8 months) (Ref. EEP1075) (Annex LII) Energy Efficiency The Owners Committee September 2011 to Project – Sham Wan of May 2012 Towers (9 months) (Ref. EEP1077) (Annex LIII) Energy Efficiency Site 4 Whampoa Garden October 2011 to Project – Whampoa Owners’ Committee December 2012 Garden Site 4 (15 months) (Ref. EEP1082) (Annex LIV) Energy Efficiency The Incorporated October 2011 to Project – On Lok Yuen Owners of On Lok Yuen December 2012 Building Building (15 months) (Ref. EEP1086) (Annex LV)

- 10 - ECPVSC Paper 10/2011-12 For Discussion

Project Title Organization Duration Funding Sought Energy Efficiency The Incorporated October 2011 to Project – Fuk Tsun Owners of Fuk Tsun August 2012 Factory Building Factory Building (11 months) (Ref. EEP1087) (Annex LVI) Energy Efficiency The Incorporated December 2011 to Project – Harrison Court Owners of Harrison February 2013 (Ref. EEP1088) Court, Waterloo Hill (15 months) (Annex LVII) Energy Efficiency Owners September 2011 to Project – Chelsea Court Committee June 2012 (Ref. EEP1095) (10 months) (Annex LVIII) Energy Efficiency The Incorporated November 2011 to Project – Caroline Owners of Caroline November 2012 Garden Garden (13 months) (Ref. EEP1096) (Annex LIX) Energy Efficiency The Incorporated December 2011 to Project – Yick Kwan Owners of Yick Kwan May 2012 House House (6 months) (Ref. EEP1106) (Annex LX) Energy Efficiency The Incorporated January 2012 to Project – Honiton Owners of Honiton August 2012 Building Building (8 months) (Ref. EEP1109) (Annex LXI) Energy Efficiency The Incorporated December 2011 to Project – Sam Ying Owners of Sam Ying July 2012 Building Building (8 months) (Ref. EEP1111) (Annex LXII) Energy Efficiency The Incorporated December 2011 to Project – King Yip Owners of King Yip July 2012 Building Building (7 months) (Ref. EEP1112) (Annex LXIII)

- 11 - ECPVSC Paper 10/2011-12 For Discussion

Project Title Organization Duration Funding Sought Energy Efficiency The Incorporated December 2011 to Project – King Yip Owners of Fuk Wing May 2012 Building Building ( Kwong Fuk (6 months) (Ref. EEP1113) Road) (Annex LXIV) Energy Efficiency The Incorporated December 2011 to Project – Golden Bear Owners of Golden Bear June 2013 Industrial Centre Industrial Centre (19 months) (Ref. EEP1120) (Annex LXV) Energy Efficiency The Incorporated December 2011 to Project – Fu Yau Owners of Fu Yau February 2012 Building Building (3 months) (Ref. EEP1130) (Annex LXVI) Energy Efficiency The Incorporated September 2011 to Project – Wah Sun Owners of Wah Sun December 2011 Building Building (4 months) (Ref. EEP1131) (Annex LXVII) Energy Efficiency The Incorporated January 2012 to Project – Smithfield Owners of Smithfield April 2012 Terrace Terrace (4 months) (Ref. EEP1138) (Annex LXVIII) Energy Efficiency The Owners’ Committee December 2011 to Project – Fulrich Garden of Fulrich Garden December 2012 (Ref. EEP1139) (13 months) (Annex LXIX) Energy Efficiency The Incorporated December 2011 to Project – Tung Ming Owners of Tung Ming May 2012 Building Building (6 months) (Ref. EEP1142) (Annex LXX) $18,920,497.00

6. The following two funding applications with the applied funding of value exceeding HK$2.0 million are recommended for seeking approval from the ECF Committee.

- 12 - ECPVSC Paper 10/2011-12 For Discussion

Projects recommended for seeking approval from the ECF Committee

Project Title Organization Duration Funding Sought Energy Efficiency The Incorporated March 2012 to Project – Mei Foo Sun Owners of Mei Foo Sun March 2013 See Note 1 Chuen (Stage I) Chuen (Stage I) (13 months) (Ref. EEP0996) (Annex LXXI ) Energy Efficiency The Incorporated March 2012 to Project – Mei Foo Sun Owners of Mei Foo Sun March 2013 Chuen (Stage III) Chuen (Stage III) (13 months) (Ref. EEP0997) (Annex LXXII ) $11,200,000.00

Advice sought

7. Members are invited to support the recommendation as detailed in paragraph 5 & 6 above.

The Electrical and Mechanical Services Trading Fund August 2011