Social Monitoring Report

Semiannual Report (January–June 2020) October 2020

IND: State Highway Improvement Program –Tranche 2

Prepared by Public Works Department, Government of Rajasthan for the Government of and the Asian Development Bank.

This social monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or Staff, and may be preliminary in nature.

In preparing any country program or strategy, financing any project, or by making any designation of or reference to a territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Project Management Consultant, Rajasthan State Highway Investment Program - RSHIP

Project management Consultant Services for RAJASTHAN STATE HIGHWAY INVESTMENT PROGRAM

SEMI-ANNUAL SOCIAL MONITORING REPORT (JANUARY 2020-JUNE 2020)

Implementation Agency PPP DIVISION OF

October-2020

Project Management Consultant, Rajasthan State Highway Investment Program - RSHIP

DOCUMENT/REPORT CONTROL FORM File Location Name: Semi-Annual Social Monitoring Report-R1 (January–June 2020) Consulting Services for Tranche-2 Project Management Consultant Project Name: Rajasthan State Highway Investment Program Project Number: 7061508

Revision Number: R1

REVISION HISTORY Revision # Date Prepared by Reviewed by Approved for Issue by Mr. Narendra Kumar Nawin Mr. Narendra Kumar Nawin 31-10-2020 Dr.AshokKumar Team Leader cum Sr. Team Leader cum Sr. 1 (R1) Singh Contract Management Contract Management Specialist Specialist Mr. Narendra Kumar Nawin Mr. Narendra Kumar Nawin 08-09-2020 Dr.AshokKumar Team Leader cum Sr. Team Leader cum Sr. 0 (R0) Singh Contract Management Contract Management Specialist Specialist

Issue Register

Distribution List Date Issued Number of Copies ACE, (PPP), PUBLIC WORKS DEPARTMENT, Jacob Road, Civil 08-09-2020 (R0) Line, Opp to Club. Jaipur 302006 1 no of Hard copy Government of Rajasthan & ADB from Client 31-10-2020 (R1) Office Library [SMEC office location] SMEC Project File F:\RSHIP\Deliverables\Semi-Annual Social Monitoring Report

SMEC Company Details – Site Office SMEC International Pty. Ltd. in association with SMEC (India) Private Limited Mezzanine Floor, PPP Division, PWD,Jacob Road, Civil Lines, Jaipur302006,Rajasthan, INDIA Tel: Fax: Email: [email protected] Website: www.smec.com Head Office SMEC International Pty. Ltd. in association with SMEC (India) Private Limited 1st Floor, Novus Tower, West Wing, Plot Number -18, Sector – 18, Gurgaon – 122015, Haryana, INDIA Tel: +91 1244552800, 4501100 Fax: +91 124 4501143 Email: [email protected] Website: www.smec.com

The information within this document is and shall remain the property of: PPP Division, PWD Rajasthan.

Semi-Annual Social Monitoring Report January–June 2020 Page i of v Project Management Consultant, Rajasthan State Highway Investment Program - RSHIP

Table of Content I. Project Introduction and Background ...... 1 II. Overall Objectives...... 1 III. Social Safeguard Categorization ...... 1 IV. Purpose of the Report: ...... 1 V. Monitoring Period ...... 2 VI. Project details for Tranche-2 ...... 2 VII. Resettlement Impact and Implementation ...... 4 1. LA Impacts in Tranche-2 Project as per ADB approved RPs ...... 4 2. Package-wise Involuntary Resettlement Impacts as per RPs ...... 5 3. Actual Resettlement Impacts and Implementation ...... 6 3.1 Land Acquisition as per RP and Social Impact Assessment ...... 6 3.2 Impacts on Vulnerable Household: ...... 7 3.3 Impacts on Non Title Holder DPs ...... 8 3.4 Impacts on Community Property Resources(CPR)...... 8 3.5 Loss of Community Property Resources ...... 8 VIII. Procedure for Implementation of RP ...... 9 1. Land Acquisition ...... 9 2. Acquisition of Structures from Non-Titleholders (NTH) and Community Property Resources (CPR) ...... 9 3. Selection of Implementing NGO ...... 9 4. Information Disclosure ...... 9 5. Public Consultations ...... 9 6. Land Available for Civil Work ...... 10 IX. Skill Development Training Programs ...... 11 X. Gender and Social dimension ...... 11 XI. Awareness Camps ...... 11 XII. Capacity Development ...... 12 XIII. Institutional Arrangements ...... 12 XIV. Social Safeguards Compliance In Construction Sites...... 14 1. Labour Safety and Health ...... 14 2. Provisions Created in Labour Camps in Construction Camps ...... 14 3. Road Safety Provisions ...... 15 4. Temporary Land Acquisition for Construction Camp and Providing Diversion at Construction Sites ...... 15 XV. Grievance Redressal Mechanism ...... 16 XVI. Monitoring and Reporting ...... 16 XVII. Conclusion and Action point ...... 18 1. Conclusion ...... 18 2. Action point ...... 18

Semi-Annual Social Monitoring Report January–June 2020 Page ii of v Project Management Consultant, Rajasthan State Highway Investment Program - RSHIP

LIST OF TABLES

Table 1: Details of Road Sub Project ...... 2 Table 2:Details of Land Acquisition as per RP in 6 Packages of Tranche-2 ...... 4 Table 3: Road-wise RP based Involuntary Resettlement Impacts ...... 5 Table 4: Status of Land Acquisition in ADB Tranche- 2 Project, RSHDP till the end of June 2020 ...... 6 Table 5: Road wise Impact on vulnerable Households...... 7 Table 6: Package-Wise Details of Affected NTH DPs as mentioned in RPs ...... 8 Table 7: Package-wise Details of Affected CPRs as mentioned in RPs ...... 8 Table 8: Summary of public consultation ...... 10 Table 9: Land available free from encumbrance ...... 10 Table 10: Safeguard monitoring and Reporting ...... 17

LIST OF ANNEXURES

Annexure-1: Project Information in including Entitlement Matrix for Disclosure to Public ...... 19 Annexure-2: Public Consultations ...... 29 Annexure-3:Constitution of GRC ...... 33 Annexure-4: Pictorial Documentation Safeguards Compliance in ADB Tranch-2 Project ...... 34 Annexure-5: Lease Deed made for construction camp site in Package 3, Losal-Salasar-Ratangarh Road...... 39

LIST OF FIGURES

Figure 1: Tranche-2 Road Map ...... 3 Figure 2: Institutional Arrangements at RSHIP,Tranche -2 ...... 13 Figure 3: Use of PPE at construction works in Package 3 (Losal-Salasar-Roopangarh Road) ...... 14 Figure 4: Provisions Created in Labour Camps in Construction Camps ...... 15 Figure 5: Package 2,Sardulsahar -chhaiyan Road ...... 15 Figure 6: Grievance Redressal Mechanism ...... 16

Semi-Annual Social Monitoring Report January–June 2020 Page iii of v Project Management Consultant, Rajasthan State Highway Investment Program - RSHIP

GLOSSARY

Compensation: Payment in cash or in kind for an asset or a resource that is acquired or affected by a project at the time the asset needs to be replaced.

Cut-off date: The completion date of the census of project-displaced persons is usually considered the cut-off date. A cut-off date is normally established by the borrower government procedures that establish the eligibility for receiving compensation and resettlement assistance by the project displaced persons. In the absence of such procedures, the borrower/client will establish a cut-off date for eligibility.

Displaced Persons: In the context of involuntary resettlement, displaced persons are those who are physically displaced (relocation, loss of residential land, or loss of shelter) and/or economically displaced (loss of land, assets, access to assets, income sources, or means of livelihood) as a result of (i) involuntary acquisition of land, or (ii) involuntary restrictions on land use or on access to legally designated parks and protected areas.

Entitlement: Resettlement entitlements with respect to a particular eligibility category are the sum total of compensation and other forms of assistance provided to displaced persons in the respective eligibility category.

Host communities: Communities receiving physically displaced persons of a project as resettlers.

Income restoration: Re-establishing productive livelihood of the displaced persons to enable income generation equal to or, if possible, better than that earned by the displaced persons before the resettlement.

Meaningful consultation: A process that (i) begins early in the project preparation stage and is carried out on an ongoing basis throughout the project cycle; (ii) provides timely disclosure of relevant and adequate information that is understandable and readily accessible to affected people; (iii) is undertaken in an atmosphere free of intimidation or coercion; (iv) is gender inclusive and responsive, and tailored to the needs of disadvantaged and vulnerable groups; and (v) enables the incorporation of all relevant views of affected people and other stakeholders into decision making, such as project design, mitigation measures, the sharing of development benefits and opportunities, and implementation issues.

Physical displacement: Relocation, loss of residential land, or loss of shelter as a result of (i) involuntary acquisition of land, or (ii) involuntary restrictions on land use or on access to legally designated parks and protected areas.

Replacement Cost: Replacement cost involves replacing an asset at a cost prevailing at the time of its acquisition. This includes fair market value, transaction costs, interest accrued, transitional and restoration costs, and any other applicable payments, if any. Depreciation of assets and structures should not be taken into account for replacement cost. Where there are no active market conditions, replacement cost is equivalent to delivered cost of all building materials, labour cost for construction, and any transaction or relocation costs.

Relocation assistance: Support provided to persons who are physically displaced by a project. Relocation assistance may include transportation, food, shelter, and social services that are provided to the displaced persons during their relocation. It may also include cash allowances that compensate displaced persons for the inconvenience associated with resettlement and defray the expenses of a transition to a new locale, such as moving expenses and lost work days.

Semi-Annual Social Monitoring Report January–June 2020 Page i of v Project Management Consultant, Rajasthan State Highway Investment Program - RSHIP

ABBREVIATIONS

ADB Asian Development Bank DC District Collector DH Displaced Household DP Displaced Person EA Executing Agency GOI GRC Grievance Redressal Committee IA Implementing Agency IAY Indira Awaas Yojana LA Land Acquisition RFCTLARR Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013. RLAB (Draft) Rajasthan Land Acquisition Bill NGO Non Governmental organization PD Project Director PIU Project Implementation Unit PMC Project Management Consultancy PMU Project Management Unit PROW Proposed Right-of-Way R&R Rehabilitation and Resettlement RF Resettlement Framework RO Resettlement Officer RoW Right-of-Way RP Resettlement Plan RS Resettlement Specialist (PMC) SC Scheduled Caste SDM Sub-Divisional Magistrate SO Safeguards Officer SH State Highway SPS Safeguard Policy Statement SoR Schedule of Rate (PWD) ST Scheduled Tribe

This resettlement plan is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature.

In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Semi-Annual Social Monitoring Report January–June 2020 Page ii of v Project Management Consultant, Rajasthan State Highway Investment Program - RSHIP I. Project Introduction and Background

1. The Asian Development Bank (ADB) is supporting the Government of India’s program to improve priority state road network in Rajasthan State. Public Works Department (PWD), Government of Rajasthan (GoR) is implementing Rajasthan State Highway Development Program (RSHDP) which aims to improve about 20000 km of State Highways and Major District Roads (MDR) to 2-lane or intermediate lane standard. 2. As part of RSHDP, about 2000 km of State Highways (SH) and Major District Roads (MDR)have been included under ADB financial assistance, as Rajasthan State Highways Investment Program (RSHIP) to improve the efficiency and safety of road transport in the state of Rajasthan. 3. 2000 Km of road sections proposed to be developed under ADB financial assistance, nearly 1000 Km have been identified under Tranche-1 in four different Packages. The project roads are to be constructed under two modalities i) three Packages in Annuity mode with a combined combined length of 745.269 km and ii) One Package in EPC mode with a length of 233.690 km. The total road length under Tranche -1 is 978.959 km costing Rs. 1944.220 crore. 4. In Tranche-2 four contract packages are in EPC mode and two contract packages in DBOT Hybrid Annuity Mode basis are proposed. Tranche- 2 will finance the upgrading of 754.563 km of State Highways and continue supporting the capacity building of PPP Division of the PWD particularly on safeguards implementation and monitoring and road safety. Tranche- 2 is included in ADB’s country operations business plan for India, 2019– 2021. The combined length of six packages is 754.563 km and the proposed cost of Tranche-2 packages is Rs. 1866.250 crore in eleven roads. Tranche-2 DBOT Hybrid annuity mode four EPC contract packages have been awarded between February 2019 to November 2019. 5. The Executing Agency for the project has been the State Government of Rajasthan acting through PPP Division of PWD, GoR. The PPP division of PWD, headed by Additional Chief Engineer, has establish project implementation unit (PIU) for contract packages of project roads in their respective areas. Each contract package has been undertaken by the Concessionaire/ Contractor for execution and supervised by Independent Engineer/ Authority Engineer. II. Overall Objectives

▪ RSHIP will improve the Efficiency and Safety of Transport on the State Highways of Rajasthan, thereby providing Good Quality and Connectivity for Social and Economic Activities. ▪ RSHIP will upgrade about 2,000 KM of State Highways (SH) and Major District Roads (MDRs) to two-lane plus Paved shoulder, two-lane or intermediate-lane standards in keeping with Road Safety requirements; ▪ RSHIP will enhance the Capacity Building of Public Works Department by preparing and Piloting streamlined business process and procedures for Road Asset Management., Road Safety and Project Management. III. Social Safeguard Categorization

6. The Project is classified as 'A' for involuntary resettlement (IR) as per the Safeguards Policy Statement(SPS), 2009. The project will trigger resettlement impactsmainly resulting from land acquisition,demolition of structures (residential and commercial), CPR,Tenantas well as auxiliary structures belonging to Non-Titled Households (NTH). The approved social safeguard categories for Loan 3815-IND: Rajasthan State Highway Improvement Program –Tranche-2is “A” for involuntary resettlement (IR); and “C” for Indigenous Peoples (IP). The Safeguard Policy Statement (SPS), 2009 is applicable for the Project.The identification and verification of affected households yet to be start. IV. Purpose of the Report:

7. The main objective of this monitoring report is to supervise the sub-project impacts and to determine whether resettlement goals have been achieved and more importantly whether livelihood and living standard have been restored as well as enhanced suggesting the suitable recommendations for improvement. This report covers resettlement and social safeguard monitoring results to comply with the spirit of ADB policy to ‘enhance stakeholders’ trust ‘in and ability to engage with ADB, and thereby increase the development impact (of projects) in which disclosure of safeguard monitoring is a prominent aspect.

Semi-Annual Social Monitoring Report January-June 2020 Page 1 of 45 Project Management Consultant, Rajasthan State Highway Investment Program - RSHIP V. Monitoring Period

8. This consolidated report outlines monitoring the implementation of social safeguard activities during January 2020 -June 2020. VI. Project details for Tranche-2

9. The project involves rehabilitation/reconstruction and widening of eleven existing roads totaling 754.563 kmin length. The PWD has prepared eleven Resettlement Plans (RP) during the processing of the loan with the objective to assist the affected people in improving or at least restoring their living standards to the pre-impacted level. The 11 RPs capture the involuntary resettlement impacts arising out of the proposed improvements to eleven roads. Details of sub-projects are provided in Table 1 and the index Map is presented in Figure 1.

Table 1: Details of Road Sub Project

S. Length District Road Section Road No Remarks No. (in Km) 1 , Pali Jodhpur- Sojat Road SH-58 75.700 LOA date:06 Frebruary 2019 Bhinmal - Agreement Signed on: 20 February 2019 2 Jalore PantheriPosana - SH-31A 51.580 Appointment date: 08 March 2019 Jeevana Completion date: 07 March 2021 SUB TOTAL 127.280 Churu, Bidasar - Sri 3 SH-93 A 82.2 LOA Date: 24 September 2019 Bikaner Dungargarh Kalu Agreement Signed on: 15 November 2019. Hanumangarh, Sadulshahar - Sangaria Appointed date: 05 June 2020 4 SH-102 95.3 Sriganganagar - Chaiyan Completion date: -06 December 2021 SUB TOTAL 177.500 LOA date 30 May 2019 , Sikar, Losal-Salasar- Agreement Signed on 14 June 2019 5 SH-7 78.603 Churu Ratangarh Appointed date 23 Septmber 2019 Completion date 26 March 2021 SUB TOTAL 78.603 LOA date 06 February 2019 Barmer, Siwana - Samdari - Agreement Signed on 20 February 2019 6 SH-66 90.650 Jodhpur Balesar Appointeddate 27 May 2019 Completion date 26 May 2021 SUB TOTAL 90.650 TOTAL EPC MODE 474.033 7 -Masuda-Goyla SH 26A 67.01 8 Ajmer, Tonk Arain- SH-7E 44.26 DRAFT BID Document and Schedules are NH-12 – Laxmipura – under preparation. 9 Bundi Dora – Dabi –Ranaji Ka SH-115 49.5 Guda SUB TOTAL Nasirabad- Approval of DRAFT BID document is 10 Ajmer, Nagaur Mangliyawas- SH-102 62.96 accorded from ADB as per communication of Padukalan the comment matrix on 28 August, 2019. project specific document submitted by PMC Beawar-Pisangan- SH-59, to Client on 18 October, 2019 based on 11 Ajmer, Nagaur 56.7 Tehla-Kot-Alniyawas SH 104 revised Schedules and revised Cost and its under review with Authority. SUB TOTAL 119.66 TOTAL ANNUITY MODE 280.53 Grand Total (EPC + Annuity) Mode 754.563

Semi-Annual Social Monitoring Report January-June 2020 Page 2 of 45 Project Management Consultant, Rajasthan State Highway Investment Program - RSHIP

Figure 1: Tranche-2 RoadMap

Semi-Annual Social Monitoring Report January-June 2020 Page 3 of 45 Project Management Consultant, Rajasthan State Highway Investment Program - RSHIP

VII. Resettlement Impact and Implementation

10. The towns and villages along the road sub-projects would have improved connectivity with State Highways (SH), National Highways (NH), major trading, educational and administrative centres. Further, the improved road will reduce the travel time to the residents of this area to work place, schools, hospitals and markets. Agriculturist too will benefit by being able to quickly transport their produce without delay and can expect buyers coming to their doorstep to procure food grains. Better connectivity to the SH/NH will lead to industrial growth along the sub-project road that will result in employment generation. However, the sub-project will require private land and removal of encroachments and squatting for improving the road, resulting in negative impacts to some people living along the corridor.

1. LAImpacts in Tranche-2Project as perADB approved RPs

11. Involuntary resettlement impacts have been identified in all 11 sub-projects under Tranche-2 Project. Resettlement Plan (RP) for each sub project has been prepared in September-2018describing the adverse social impacts, mitigation measures proposed, estimates of compensation & R&R assistances and entitlement matrix delineating the provisions made to eligible persons due to the project implementation.

12. Both road ofEPC Package 02Sadulshahar - Sangaria – ChaiyanRoad ,Bidasar - Sri Dungargarh - Kalu andone road of annuity Package 01(NH-12 – Laxmipura – Dora – Dabi –Ranaji Ka Guda (Mining) have no land acquisition. In these three roads there are impacts on Non Title holders,private trees and CPRs only.

13. One road of each package EPC 01(Jodhpur- Sojat Road),EPC 04(Siwana - Samdari – Balesar),Annuity 01 (Beawar – Masuda – Goyla)and both road of anniuity package 02(Nasirabad-Mangliawas-Padukalan and Beawar-Pisangan-Govindgarh-Tahla-Kot-Alniyawas)have no impact on non title holders,but in these 5 roads impact due to Land acquisitionis envisaged.

14. The available right-of-way has been fully considered for the proposed improvement and the existing right-of- way (RoW) for the road section were determined using village maps and verified at site. Since the available RoW is not sufficient to meet the design cross section for the proposed intermediate/2-lanning, the road construction would entail acquisition of private land resulting in adverse impacts to households. The private land requiredin 08 roads for the improvements is 123.0625Ha. The private land proposed for acquisition is mostly strips of land, with the width varying from 5-10m, and abetting the existing road. Further, government land will be required to be transferred for the proposed improvements. In the following Table-2 land acquisition in RPs of respective packages have been provided.

Table 2:Details of Land Acquisitionas per RP in 6 Packages of Tranche-2 Pkg. Land Acquisition (Private) Package No. Road Name No. Required in Hectare EPC-01 Bhinmal - PantheriPosana - Jeevana 0.91 1 EPC-01 Jodhpur- Sojat Road 8.2453 EPC-02 Sadulshahar - Sangaria - Chaiyan 0 2 EPC-02 Bidasar - Sri Dungargarh - Kalu 0 3 EPC-03 Losal - Salasar - Ratangarh 58.8952 4 EPC-04 Siwana - Samdari - Balesar 29.01 NH-12 – Laxmipura – Dora – Dabi – Annuity-01 0 Ranaji Ka Guda (Mining) 5 Annuity-01 Beawar – Masuda – Goyla 11.945 Annuity-01 Arai - Sarwar 1.15 Annuity-02 Nasirabad-Mangliawas-Padukalan 5.287 6 Beawar-Pisangan-Govindgarh-Tahla- Annuity-02 7.584 Kot-Alniyawas Total 123.0625

Semi-Annual Social Monitoring Report January-June 2020 Page 4 of 45 Project Management Consultant, Rajasthan State Highway Investment Program - RSHIP

2. Package-wise Involuntary Resettlement Impacts as per RPs

15. The RPs reported a total of 122.9143 hectare land acquisition (LA) requirements. Further, a total of 2295 affected HHs comprising of 12927 DPswill be impacted due to these project.Out of 2295 DHHs, 125 DHHswill be physically displaced,148 will be economically displaced,574 economically displaced titleholders losing land, 35 physically & economically displaced households,664 vulnerable households, 285 non-significant1impact and1058 titleholders losing strip of land. In addition impacts on183 CPRsarealso envisaged. The details are provided in Table 3.

Table 3: Road-wise RP based Involuntary Resettlement Impacts

s

Resources

project

-

significant

Trees

significant

(CPR)

impact

person -

-

impact)

Nameof

Displaced

losingland

households

Households Households Households stripof land

Physically &

Sub

DisplacedTH

Economically Economically Economically DisplacedHH

Total affected

Total Affected

Non

Affected Private

(Non

AffectedCommon

TitleholdersLosing

Property Property PhysicallyDisplaced Bhinmal - Impacton Vulnerable PantheriPosana 729 191 4 0 23 0 14 150 30 260 0 - Jeevana Jodhpur- Sojat 0 148 15 18 0 1 21 93 15 0 11 Road Sadulshahar - Sangaria - 2767 337 28 84 0 27 131 0 160 312 63 Chaiyan Bidasar - Sri Dungargarh - 281 46 0 3 0 0 2 41 12 65 12 Kalu Losal - Salasar - 1100 244 10 2 101 0 34 97 68 806 45 Ratangarh Siwana - Samdari - 1350 264 4 1 251 1 7 0 50 1272 20 Balesar NH-12 – Laxmipura – Dora – Dabi – 304 66 10 20 0 0 34 0 25 0 16 Ranaji Ka Guda (Mining) Beawar – 1142 291 0 0 49 0 0 241 19 0 0 Masuda – Goyla Arain - Sarwar 688 138 0 0 46 0 9 83 42 25 5 Nasirabad- Mangliawas- 489 144 0 0 23 0 1 120 34 99 3 Padukalan Beawar- Pisangan- Govindgarh- 4077 426 54 20 81 6 32 233 210 286 8 Tahla-Kot- Alniyawas Total 12927 2295 125 148 574 35 285 1058 665 3125 183

1Where the impact to structure is less than 10 percent of the total area or impact is only to the boundary wall, then such impacts are categorized as non-significant impacts as the DP is neither physically nor economically displaced

Semi-Annual Social Monitoring Report January-June 2020 Page 5 of 45 Project Management Consultant, Rajasthan State Highway Investment Program - RSHIP

16. All the 11 RPs will be updated after final SIA data. The SIA data will be finalized after appraisal by an Expert Group. The revised data on impacted people and properties will be the basis of RP implementation during project implementation of Tranche-2 Project.

3. Actual Resettlement Impacts and Implementation

17. The land acquisition process has been started by the concerned land acquisition officer and is in a very early stage. Implementation of RP has not been started due to delays in the recruitment of implementing NGO. The NGO shall verify the information already contained in the RP & the individual losses of the DPs and validate the data as well as make a joint verification with PIU on changes required if any, along with documentary evidence. Wherever required, NGO would update the census and socio-economic survey data and census and socio- economic survey questionnaire, if there are DPs who have been not covered during baseline survey and in particular the titleholders from whom land is being acquired.

3.1 Land Acquisitionas per RP andSocial Impact Assessment

18. Out of 11 sub project roads, land acquisition is not envisaged in 3 sub project roads. The remaining 8 roads having LA requirement include 4 roads of EPC packages and 4 roads of annuity packages, the process of land acquisition is in initial stage, i.e. under Section 11(Preliminary Notification for Acquisition), Section7 of LA Act ( appraisal of SIA report by the expert group ) or Section 4(1)(Requisitions for acquisition and notification for SIA . Package-wise details of LA status have been presented in Table 4.

Table 4: Status of Land Acquisition in ADB Tranche- 2 Project, RSHDP till the end of June 20202 Action by the EA (PPP Division, Action by the District Collector (DC) / State Government

PWD, Rajasthan)

Road Pkg. Package Road Name Length Remarks No. No.

(km)

Section 6, SIA6, Section

Hearing of SIA of Hearing

Public Hearing Public

for Acquisition for

of Land Records Land of

Land Acquisition Acquisition Land

Report Disclosed Report

Section 4(5), Public Public 4(5), Section

Administrator of R&R of Administrator

Section 3, Requisition Requisition 3, Section

Section 7, Appraisal of Appraisal 7, Section

Section 16, Preparation Preparation 16, Section

SIA by an Expert Group Expert an by SIA

Section 11 (5), Updating Updating (5), 11 Section

R&R Scheme, Census Survey, Survey, Census Scheme, R&R

(Private) Required in Hectare in Required (Private)

Section 4(1), Requisitions for for Requisitions 4(1), Section

Section 11 (5), Appointment of Appointment (5), 11 Section

acquisition and notified for SIA for notified and acquisition

submitted to DC for Acquisition for DC to submitted

of Section 11 Preliminary Notification Notification Preliminary 11 Section Bhinmal - Draft of Section-11 submitted to EPC-01 PantheriPosana - 51.58 0.91 √ √ √ √ √ √ √ SDM Sayala after verification 1 Jeevana from Patwari's and Tehsildar EPC-01 Jodhpur- Sojat Road 75.7 8.2453 √ √ √ √ √ √ √ Publication of Section 11 is done Sadulshahar - EPC-02 95.3 0 NA NA NA NA NA NA NA NA NA No LA Sangaria - Chaiyan 2 Bidasar - Sri EPC-02 82.2 0 NA NA NA NA NA NA NA NA NA No LA Dungargarh - Kalu Losal - Salasar - Processing for Section 11 under 3 EPC-03 78.603 58.8952 √ √ √ √ √ √ √ √ Ratangarh progress. Siwana - Samdari - 4 EPC-04 90.65 29.01 √ √ √ √ √ √ √ Publication of Section 11 is done Balesar NH-12 – Laxmipura – Annuity-01 Dora – Dabi –Ranaji 49.6 0 NA NA NA NA NA NA NA NA NA No LA Ka Guda (Mining) 5 Beawar – Masuda – Annuity-01 67.01 11.945 √ √ √ √ √ SIA report approved Goyla Publication of Sec.-11 pending Annuity-01 Arai - Sarwar 44.26 1.15 √ √ √ √ √ for sub division Nasirabad- SIA report received, under Annuity-02 Mangliawas- 62.96 5.287 √ √ √ review with Expert Group Padukalan 6 Beawar-Pisangan- SIA report received, under Annuity-02 Govindgarh-Tahla- 56.7 7.584 √ √ √ review with Expert Group Kot-Alniyawas Total 754.563 123.0625

2 Data received from PMU,Jaipur.

Semi-Annual Social Monitoring Report January-June 2020 Page 6 of 45 Project Management Consultant, Rajasthan State Highway Investment Program - RSHIP

3.2 ImpactsonVulnerable Household:

19. Vulnerable households include those living below poverty line, are landless, headed by an elderly or women, and belong to scheduled tribes or scheduled caste. According to approved RPs, the Project under tranche 2 will impact 121 women-headed households,17 scheduled tribe households,263 scheduled caste households and 148 BPL households, and 31 disabled headed households. 85 NTH not falling under the above categories also impacted, thus a total 665 Vulnerable households will be impacted in the Tranche-2 project.After identification and verification this number may increased or decresed. It is to also mention that there is no landless household impacted due to this project.

Table 5: Road wise Impact on vulnerable Households

Women Scheduled Scheduled Disabled BPL Headed Tribe (ST) Caste (SC) Headed Road Name househol Total Household headed headed Household d (WHH) household household s (DHH) Bhinmal - PantheriPosana - 2 0 28 0 0 30 Jeevana Jodhpur to Sojat Road 0 4 10 1 0 15 (Section of SH-58) Sadulshahar – Sangaria 12 1 1 37 24 75 – Chaiyan3 Bidasar – Dungargarh – 5 0 6 0 1 12 Kalu section of SH-93 LosalSalasarRatangarh Sub-project Road 9 3 42 13 1 68 SiwanaSamdariBalesar (SH-66) (Package IV) 13 2 30 2 3 50 Laxmipura-Dora-Dabi- Ranaji ka GudhaSub- 3 4 13 4 1 25 project Road Beawar-Masuda- 0 3 16 0 0 19 GoylaSub-project Road Arain-Sarwar Sub- 32 0 7 3 0 42 project Road Nasirabad-Mangliawas- 27 0 6 0 1 34 Padukalan Beawar-Pisangan- Govindgarh-Tahla-Kot- 18 0 104 88 0 210 Alniyawas

121 17 263 148 31 580

3 In RP of Sadulshahar – Sangaria – Chaiyan it is mentioned that 85 NTH not falling under above categories thus total Vulnerable household impacted in this road is 160 and total 665 vulnerable household will be impacted in Tranche--2 project.

Semi-Annual Social Monitoring Report January-June 2020 Page 7 of 45 Project Management Consultant, Rajasthan State Highway Investment Program - RSHIP

3.3 Impacts on Non Title Holder DPs

20. The process of implementation of RPs will be kicked off after mobilization of non- governmental organization (NGO). The approved RPs envisaged the impact on 437 structures of NTHs having total 900 DPs. 21. It has been found that in one road of package EPC 01(Jodhpur- Sojat Road), EPC 04 (Siwana - Samdari – Balesar), Annuity 01 (Beawar – Masuda – Goyla) and both road of anniuity Package 02 (Nasirabad-Mangliawas- Padukalan and Beawar-Pisangan-Govindgarh-Tahla-Kot-Alniyawas ) have no impact on non title holders. 22. The following Table 6 provide details of package-wise impacts on NTH DPs as mentioned in the RPs. Table 6: Package-Wise Details of Affected NTH DPs as mentioned in RPs Packag Package Total Squatter/ Road Name Encroacher Structure e No. Name NTH DPs Kiosks EPC-01 Bhinmal - PantheriPosana - Jeevana 69 14 0 14 1 EPC-01 Jodhpur- Sojat Road 0 0 0 0 EPC-02 Sadulshahar - Sangaria - Chaiyan 270 194 118 312 2 EPC-02 Bidasar - Sri Dungargarh - Kalu 73 5 0 5 3 EPC-03 Losal - Salasar - Ratangarh 139 0 31 31 4 EPC-04 Siwana - Samdari - Balesar 0 0 0 0 NH-12 – Laxmipura – Dora – Dabi – Annuity-01 304 61 5 66 Ranaji Ka Guda (Mining) 5 Annuity-01 Beawar – Masuda – Goyla 0 0 0 0 Annuity-01 Arain - Sarwar 45 3 6 9 Annuity-02 Nasirabad-Mangliawas-Padukalan 0 0 0 0 6 Beawar-Pisangan-Govindgarh-Tahla-Kot- Annuity-02 0 0 0 0 Alniyawas Total 900 277 160 437

3.4 Impacts on Community Property Resources(CPR) 3.5 Loss of Community Property Resources 23. Various types of CPR structureswill be impacted partially include frontage of structures, boundary walls, education institutions (boundary walls of schools and colleges, owned by private persons and state government). The fully impacted structures include religious structures (temple) of small size managed by the community/trust. The contractorwill reconstruct these structures with the consultation from local public. Of the total 183 CPRs, 68(37.15%)are government structures followed by 55 (30.05%) community structures,51 (27.86 %) small size religious structures and 09(4.92%)other structures like boundry wall,hand pump and borewell. The details are provided in Table 7 given below. Table 7: Package-wise Details of Affected CPRs as mentioned in RPs Type of CPRs Name of Sub-Project Religious Govt. Total CommunityStructure Other Structure Structure Bhinmal - PantheriPosana - Jeevana 0 0 0 0 0 Jodhpur- Sojat Road 3 1 4 3 11 Sadulshahar - Sangaria - Chaiyan 15 19 29 0 63 Bidasar - Sri Dungargarh - Kalu 2 5 5 0 12 Losal - Salasar - Ratangarh 10 14 21 0 45 Siwana - Samdari - Balesar 8 3 6 3 20 NH-12 – Laxmipura – Dora – Dabi – 4 8 1 3 16 Ranaji Ka Guda (Mining) Beawar – Masuda – Goyla 0 0 0 0 0 Arain - Sarwar 2 3 0 0 5 Nasirabad-Mangliawas-Padukalan 2 1 0 0 3 Beawar-Pisangan-Govindgarh-Tahla- 5 1 2 0 8 Kot-Alniyawas

Semi-Annual Social Monitoring Report January-June 2020 Page 8 of 45 Project Management Consultant, Rajasthan State Highway Investment Program - RSHIP

Total 51 55 68 9 183 VIII. Procedure for Implementation of RP

1. Land Acquisition 24. In Tranche-2, the land will be acquired in the same manner as in Tranche-1 following the procedures of RFCTLARR Act and the provisions of approved entitlement matrix in the resettlement plans. The process of land acquisition involves submission of land requisition to DC by acquiring body (RPWD), conducting SIA, and engaging the State Machinery (District Collectorate and Revenue Department) as Land is a State Subject and its acquisition for Public Purpose (such as developing infrastructure like road networks in the State) is vested solely with the District Administration where the District Collector (DC) acquires the land from the private owner and hands over to the EA. The process of LA ends with disbursement of payment to the private owner, possession of land by the DC and finally handing over the parcel of land to the EA.

25. As shown in the status Table 4, the process of land acquisition in Tranche-2 is in initial stage, i.e. under Section 11( Preliminary Notification for Acquisition), Section 7 of LA Act ( appraisal of SIA report by the expert group ) or Section 4(1)( Requisitions for acquisition and notification for SIA ).

2. Acquisition of Structures from Non-Titleholders (NTH) and Community Property Resources (CPR) 26. This is a very important aspect of RP implementation which involves clearing of ROW occupied by non- titleholder (NTH) occupants for various purposes like living in residences, establishing commercial structures like shops and the likes. Moreover, CPRs like temples, mosques, churches or community sitting areas or chabutras, water tanks, tube-wells, wells etc. which are used for community purposes but not owned by any individual are also needed to be demolished / dismantled to clear the ROW for the purpose of project implementation.

27. All the structures of the NTH identified under the RP will be surveyed and verified at the ground by implementing NGO. Several activities required as part of RP implementation will be conducted by the staff of IAs/PIUs, who were assisted by NGOs and PMC. Such activities include conducting consultations with DPs and other stakeholders, disclosure of entitlement matrix, dissemination of project information, identification and verification of DPs, preparation of Micro-Plans (MPs), preparation and distribution of identity cards (IDs), opening of Bank Accounts of DPs where needed, compensation and assistance in disbursement, coordination with DPs, experts of PMC, officials of revenue and line departments, organizing GRC meetings, data collection for monitoring and reporting, updation of RPs as required, etc. At the field level, along with the PIU officials, NGOs performed major role in carrying out these and other activities required for RPs implementation. However, as NGO is yet to be appointed under Tranche- 2 Sub-projects RP implementation for affected non-titleholder DPs could not be initiated.

3. Selection of Implementing NGO 28. Evaluation of technical proposal for hiring of RP implementing NGO was completed ,due to complaints received by govt. of Rajasthan, bid evaluation committee cancelled the bid on 11.03.2020 and fresh Notice Inviting Tender (NIT) was published on 29 june 2020 with the 30 th July as last date for submission of proposal and pre-bid meeting on 10 th July

4. Information Disclosure 29. The leaflet summarizing the project information, impacts, eligibility criteria, Entitlement Matrix (EM) was translated in the local language (Hindi). The leaflets were made available by the office of ACE(PPP) vide letter no.7(143)SHA/PPP/2015/D-79 dated 16.04.2019 to the PD, PIUs. The copy of the leaflet distributed for Tranche- 1 which have similar entitlement has been provided as Annexure 1Distribution of leaflet for Tranche- 2 project is pending due to non availiability of NGO. RPs were disclosed on the ADB websites.

5. Public Consultations 30. Regular public consultations are very much necessary to implement the RPs in a proper and smooth manner.. During the reporting period, initial consultations were done by PMC Resettlement Expert and Environmental expert in February 2020. From March 2020consultations could not be organized due to COVID-19 pandemic situation. The major issues raised by NTHs and other stakeholders are given below:

Semi-Annual Social Monitoring Report January-June 2020 Page 9 of 45 Project Management Consultant, Rajasthan State Highway Investment Program - RSHIP

a. Compensation b. Valuation of the impacted structure at market rate and accordingly disbursement of enhanced compensation amount; c. Local people should be employed in the project works; d. Avoid impact in busy markets and congested locations; e. Provide speed breakers near the school and other public places; and f. Construct drainage along the road in the market and built-up areas. Table 8:Summary of public consultation No of consultation Participants Name of Road held Male Female Rajola-Kalan (Jodhpur-Sojat Road) 1 22 0 Birdawas (Jodhpur-Sojat Road) 1 20 0 Kakelaon (Jodhpur-Sojat Road) 1 39 0 Meli (Siwana-Samdari-Balesar Road) 1 41 0 Deora (Siwana-Samdari-Balesar Road) 1 33 0 Karmavat (Siwana-Samdari-Balesar Road) 1 39 0 Bhinmal-Pantheri-Poshana-Jeevana Road) 3 25 0

31. The field staff responded to the concerns and issues raised by DPs and other stakeholders and addressed those into the Project as appropriate. The public consultation details by PMC experts are given in Annexure 2.

6. Land Available for Civil Work 32. As per ADB SPS 2009 norms no DP or CPR will be dislocated unless and until these are compensated fully and supported with resettlement assistances.

33. Since the Implementation of RP has been not started, the Concessionaire/contractor has been provided vacant stretches of subprojects to work where there is no involuntary resettlement impact. However, the Concessionaire will not work in settlement areas where RP has not been implemented fully and the areas are declared free from encumbrances.LA is in initial phase and payment of NTH has not been started, status of road length free from encumbrances as confirmed by PIU is depicted in Table No. 9.

Table 9: Land available free from encumbrance Length Available Length Sl. free from Private LA Package Name of Highway (km) No. encumbrance Extent (Ha) (effective) (km) EPC-01 Bhinmal - PantheriPosana - Jeevana 51.58 48.38 0.91 1 EPC-01 Jodhpur- Sojat Road 75.7 70.71 8.2453 EPC-02 Sadulshahar - Sangaria - Chaiyan 95.3 91 0 2 EPC-02 Bidasar - Sri Dungargarh - Kalu 82.2 80 0 3 EPC-03 Losal - Salasar - Ratangarh 78.603 61.802 58.8952 4 EPC-04 Siwana - Samdari - Balesar 90.65 79.65 29.01 NH-12 – Laxmipura – Dora – Dabi – Annuity-01 49.6 33.77 0 Ranaji Ka Guda (Mining) 5 Annuity-01 Beawar – Masuda – Goyla 67.01 66.94 11.945 Annuity-01 Arai - Sarwar 44.26 44.26 1.15 Annuity-02 Nasirabad-Mangliawas-Padukalan 62.96 61.56 5.287 6 Beawar-Pisangan-Govindgarh-Tahla- Annuity-02 56.7 56.69 7.584 Kot-Alniyawas Total 754.563 632.960 123.0625

Semi-Annual Social Monitoring Report January-June 2020 Page 10 of 45 Project Management Consultant, Rajasthan State Highway Investment Program - RSHIP

IX. Skill Development Training Programs

34. As per the provision of RPs, the livelihood improvement and skill development program is required to be provided to a member of DP family belonging to the vulnerable or severely affected category. No such training program was held during the reporting period. X. Gender and Social Dimension

35. RSHIP Tranche 2 included impacts and opportunities on social diversity and gender to ensure the effective mobilization and participation of women, people with disabilities and marginalized groups in society. RSHIP are taking all our efforts to increase women participation in this tranche 2 implementation. Gender Features

Project feature Action

Constructing bus stop shelters with locations (a) Presently development of 6 roads is under being finalized after community consultations; implementation stage wherein construction of 128 bus raised sidewalk and hard shoulder that will be shelters is proposed. Location of these Bus Shelters will be beneficial to pedestrians, elderly, women, and finalized after community consultations. children. (b) Construction of raised sidewalk is proposed on Losal- Salasar-Ratangarh Road in entire 78.603 km length. Construction of this sidewalk is under progress along the development of road work to facilitate pedestrian movement.

(c) Hard shoulders (Granular or paved) are proposed on all 6-State Highways in entire 474 km length. Construction work of these shoulders is being carried out along with the Road. Integrating road safety features for the elderly, Safety features for the elderly, women, children, and people women, children, and people with disabilities with disabilities, such as proper signage and marked into road design such as proper signage and crossings throughout the alignment are being incorporated marked crossings throughout the alignment in road design. Conducting road safety and safe mobility Road safety and safe mobility campaigns will be organized campaigns in affected communities within the by the Contractors. project area, targeting 50% women Undertaking awareness building sessions on Awareness-building sessions for (a) sexually transmitted STI (including HIV), basic health and hygiene, infections (STIs), including HIV; (b) basic health and and human trafficking for project-affected hygiene; and (c) human trafficking in project-affected villages within the project area, targeting 50% villages (with a target audience of 50% women) are being women organized by the Contractors & would also be organized separately by NGO. Encouraging civil works contractors to engage Civil Contractors have engaged available women as wage women workers as wage laborers and labourers on equal pay for equal work. ensuring equal pay for equal work .

XI. Awareness Camps

36. In line with the provisions of RPs, NGO has to organise the camps for the local community and workforce engaged in the project works. These were aimed to create awareness about HIV/AIDS, human trafficking, health

Semi-Annual Social Monitoring Report January-June 2020 Page 11 of 45 Project Management Consultant, Rajasthan State Highway Investment Program - RSHIP

and hygiene, and road safety aspects. No camp was organised due to non mobilization of NGO in this reporting period. XII. Capacity Development

37. ADB staff during the review missionsin November 2019 imparted training on11th&12th November 2019 onADB’s safeguard policy, social and environmental safeguard requirements, resettlement planning, implementation and monitoring. About 26 and31 participants from PWD, NGO (Tranche-1),Authority /Independent Engineer, contractors and PMC have attended the training programs at conference room of RPPWD Jaipur. XIII. Institutional Arrangements

38. PPP Division, PWD, GovernmentRajashthan, Project Management Unit (PMU) is overall in charge of coordination between the Project Implementation Units (PIU) and in prioritizing Sub-projects for subsequent Tranche-s based on social safeguards compliance.

39. The Jurisdictional Additional Collector will be the administrator for land acquisition, resettlement, and rehabilitation. The jurisdictional additional collector, being the competent authority for land acquisition, will also look into resettlement and rehabilitation and he and/or she will be supported by the project director, PIU in implementing the resettlement plans. The Jurisdictional Additional Collector will be the administrator for land acquisition, resettlement, and rehabilitation. The jurisdictional additional collector, being the competent authority for land acquisition, will also look into resettlement and rehabilitation and he and/or she will be supported by the project director, PIU in implementing the resettlement plans. In accordance with the provisions of the RFCTLARR Act ,the competent authority will pass a Rehabilitation and Resettlement (R&R) Award. All the affected land owners who are eligible for R&R assistance will be notified along with details of eligible assistance as per the provisions of RFCTLARR Act. Similarly, the list of those affected non- title holders will also be notified along with the details of R&R assistance and a separate R&R award enquiry will be conducted for the non- titleholders.

40. The Executing Agency (EA) for the Project is responsible for the implementation of RPs in accordance with ADB’s Safeguards and applicable national and state policies. EA has an established wing for the PPP Division at Jaipur HQs.TheAdditional Chief Engineer (CE), supported by the SuprintendingEngineeris responsible for the overall implementation of the ADB funded RSHIP. Also, the Executive Engineer (EE) designated asProject Director (PPP cell) /Nodal Safeguards Officer is assisted by an Assistant Engineer. Six Project Implementation Units (PIUs) have been established at Ajmer, Kota,Jalore,Laxamangarh, Hanumangarh and Sikar, which are responsible for RPs implementation in the field. Each PIU is headed by a Project Directorand assisted by one Assistant Engineer (AE) for each Package. AEs are designated as Assistant Safeguards Officers (ASO) who are responsible for the management of social and environmental safeguards at the road Sub-project level.

41. The EA is also supported by the PMC (SMEC) to provide technical inputs and monitor the progress of RPs implementation. The Resettlement Specialist of PMC visiting the sites intermittently to facilitate supervision and monitoring process in coordination with PIUs and implementing agency-NGO. Further, the PMC expert is visiting the sites frequently to safeguard social issues and provide inputs to PIUs regularly. The EA reported that the RP implementation NGO will be recruited shortly.

Semi-Annual Social Monitoring Report January-June 2020 Page 12 of 45 Project Management Consultant, Rajasthan State Highway Investment Program - RSHIP

Figure 2: Institutional Arrangements at RSHIP,Tranche -2

PWD, Rajasthan Govt

ACE (PPP)

SE (PPP)

External Moniter Project Director-HQ

PMC

PIUs Land Acquisition Officers (Tranche--2)

PD PD PD PD PD PIU PIU PIU PIU PIU Hanumangarh Jalore Laxmangarh Ajmer Jaipur

IE/AE

NGO

Semi-Annual Social Monitoring Report January-June 2020 Page 13 of 45 Project Management Consultant, Rajasthan State Highway Investment Program - RSHIP

XIV. Social Safeguards Compliance In Construction Sites.

42. In addition to complying with social safeguards requirements in implementation of RPs, there is a scope for considering the issues of labourers working in construction activities in the project to be safeguarded. Safeguards compliance in construction of subprojects has been discussed in the following subsections.

1. Labour Safety and Health 43. The Concessionaire / Contractor is required to provide for support in complying with labour safety and labour health standards. Labourers working in construction must be provided with personal protection equipment (PPE) and construction supervisors must ensure that the PPE are used by labourers for their safety at work. At construction camps and sites provision of first aid is a necessity and the Concessionaire should ensure availability of first aid kit for ready use. Moreover, in case of accidents the Concessionaire must have arrangements of immediate hospitalization of injured workers and take care of his / her medical treatment. All the labourers must be provided with insurance coverage by the Concessionaire.

44. From sample field visits labour safety has been noticed as being taken care and workers are using PPE at construction site. The following picture shows workers wearing PPE while at work.

Figure 3: Use of PPE at construction works in Package 3 (Losal-Salasar-Roopangarh Road)

2. Provisions Created in Labour Camps in Construction Camps 45. It has been noted that there is no labour camp at construction camp sites. For road construction works local labourers are engaged and thus provisions for labour camp have not been considered.

Semi-Annual Social Monitoring Report January-June 2020 Page 14 of 45 Project Management Consultant, Rajasthan State Highway Investment Program - RSHIP

Figure 4:Provisions Created in Labour Camps in Construction Camps Camp Package 3,Losal-Salasar-Ratangarh road Camp package 2,Sardulsahar -chhaiyan Road

3. Road Safety Provisions 46. The Concessionaire has made required provisions for ensuring road safety at construction sites. Pictures (Figure 4) showing provision of isafety boards.

Figure 5:Package 2,Sardulsahar -chhaiyan Road 4. Temporary Land Acquisition for Construction Camp and Providing Diversion at Construction Sites 47. For locating construction camp the required land has to be acquired on temporary basis following legal procedures so as to comply with safeguards regulations. Site visits and data collection from field shows that this compliance has been taken care of by the Concessionaire. Annexure 5provides for the Lease Deed made for construction camp site in Package 3,Losal-Salasar-ratangarh road.

Semi-Annual Social Monitoring Report January-June 2020 Page 15 of 45 Project Management Consultant, Rajasthan State Highway Investment Program - RSHIP

XV. Grievance Redressal Mechanism

48. As per the provisions of RPs, the grievance redressal mechanism has been established to receive, evaluate and facilitate the resolution of concerns, complaints, and grievances of NTHs and other stakeholders related to social and environmental aspects under the Project.

49. Accordingly, the Govt of Rajasthan has constituted the Grievance Redressal Committee (GRC)videLetter No.F7(143)SHA/PPP/2015/D-903 dated 20/09/2018 at state leveland PIU level on 20 September 2018. The first level GRC members include PD of the concerned PIU as Chairperson and Executive Engineer /Assistant engineer of the concerned PIU asMember Secretary.The second level GRC headed by Additional Chief Engineer, PPP Division Jaipur as chairman, Superintending Engineer(ADB/WB),PMU as Member Secretary and local member of repute& standing in the society as a member to be nominated by Secretary PWD, Government of Rajasthan. (Annexure 3).

Figure 6: Grievance Redressal Mechanism

Grievance Displaced Persons Govt.portal / NGO/PIU

Not redressed

GRC Chaired by PD Grievance PIU Grievance Redressed 4 weeks W Not redressed

Second Level of Grievance Redressal Additional Chief Engineer Grievance Redressed (Appellate Authority) 4 weeks

W

Not redressed Jurisdictional LARR

50. Up to the end of this reporting period not a singlegrievance has beenreceived. XVI. Monitoring and Reporting

51. PIUs along with the experts of PMCs monitored the implementation of RPs. Each PIU will held review meetings with the implementing NGO staff, every month or when required. The PMU at Jaipur will held review meetings with the PIUs, implementing NGOs and PMC experts.PMC expert periodically monitored the progress of land acquisition, R&R and related activities. The PIUs coordinated with the revenue department/SDM for LARR. NGOs will provide the data to prepare the monitoring reports on monthly basis. The experts of PMCs verified and compiled data and prepared reports and submit to PMU. PMU further verified and submitt these reports to ADB on semi-annual basis.

Semi-Annual Social Monitoring Report January-June 2020 Page 16 of 45 Project Management Consultant, Rajasthan State Highway Investment Program - RSHIP

52. An external monitor will be hired under theProject to review and verify the monitoring reports prepared by PIU, monitor the work carried out by NGO and provide necessary guidance on implementation of RPs. The external monitoring will include but not limited to: (i) review and verify the monitoring reports prepared by PIU; (ii) monitor the work carried out by NGO and provide training and guidance on implementation; (iii) review the grievance redressal mechanism and report on its working; (iv) mid-term impact assessment through sample surveys amongst displaced persons for midterm corrective action; (v) consultation with DPs, officials, community leaders for preparing review report; (vi) assess the resettlement efficiency, effectiveness and efficiency of PIU, impact and sustainability, and drawing lessons for future resettlement policy formulation and planning. Some of the important task of external monitoring is the feedback of the DPs who receives compensation and assistance and also alerts on the risks, non- compliances and early warnings in the implementing.

Table 10:Safeguard monitoring and Reporting S.No. Type of Report Responsibility 1 Monthly NGO 2 Semi-Annual NGO/PMC/PIU 3 Quarterly EM

Semi-Annual Social Monitoring Report January-June 2020 Page 17 of 45 Project Management Consultant, Rajasthan State Highway Investment Program - RSHIP

XVII. Conclusion and Action Point

1. Conclusion 53. No any progress since previous reporting period in respect of R&R and Land Acquisition.LA for Tranche-2 Project has been progressing very slowly. Out of 11 Sub-project road there is land acquisition in 8 roads, which is in initial stage. Section 11 of RFCTLARR has been initiated in 04 roads of EPC packages while in other 4 roads of annuity packages, section 7 (approval of SIA report by expert group) has been completed till the end of the reporting period.

2. Action point a. Appointment of Implementing NGO have been readvertised evaluation of proposal need to complete for appointment of implementing NGO. b. Alternative arrangement have been taken care for package 3 Losal - Salasar - Ratangarh,where almost 50% LA is involved have been assigned to NGO MASM, agreement to be executed shortly (NGO is implementing Tranche- 1 Project also)4 c. Evaluation and award for Implementing NGO to be finalized as soon as possible5. d. In various ADB project PWD itself disburse the compensation to NTH instead of Revenue official. After preparation of Microplans of NTHs, RPWWD can take initiative to disbursement of compensation through its own PIU to avoid delay. e. This is to confirms that civil works in affected section will start only after the disbursement of compensation and other assistance to TH as well as NTHs and CPRs.The payments of compensation to the AP’s will be made as per the approved R & R policy and agreed Resettlement Plans (RPs). No civil work has commenced in the affected sections, without payment of compensation. f. The RPs will require to be updated once the SIAreports as per RFCTLARR Actare approved and verification of NTH and CPRs is completed.

4Supplementary agreement between RSHIP and NGO signed on 30thJuly.On 17thAugust NGO has submitted Inception report also. 5As on date evaluations of proposals received are under process.

Semi-Annual Social Monitoring Report January-June 2020 Page 18 of 45 Project Management Consultant, Rajasthan State Highway Investment Program– RSHIP Annexure-1 Annexure-1: Project Information in Hindi including Entitlement Matrix for Disclosure to Public

Semi-Annual Social Monitoring Report January-June 2020 Page 19 of 45 Project Management Consultant, Rajasthan State Highway Investment Program– RSHIP Annexure-1

Semi-Annual Social Monitoring Report January-June 2020 Page 20 of 45 Project Management Consultant, Rajasthan State Highway Investment Program– RSHIP Annexure-1

Semi-Annual Social Monitoring Report January-June 2020 Page 21 of 45 Project Management Consultant, Rajasthan State Highway Investment Program– RSHIP Annexure-1

Semi-Annual Social Monitoring Report January-June 2020 Page 22 of 45 Project Management Consultant, Rajasthan State Highway Investment Program– RSHIP Annexure-1

Semi-Annual Social Monitoring Report January-June 2020 Page 23 of 45 Project Management Consultant, Rajasthan State Highway Investment Program– RSHIP Annexure-1

Semi-Annual Social Monitoring Report January-June 2020 Page 24 of 45 Project Management Consultant, Rajasthan State Highway Investment Program– RSHIP Annexure-1

Semi-Annual Social Monitoring Report January-June 2020 Page 25 of 45 Project Management Consultant, Rajasthan State Highway Investment Program– RSHIP Annexure-1

Semi-Annual Social Monitoring Report January-June 2020 Page 26 of 45 Project Management Consultant, Rajasthan State Highway Investment Program– RSHIP Annexure-1

Semi-Annual Social Monitoring Report January-June 2020 Page 27 of 45 Project Management Consultant, Rajasthan State Highway Investment Program– RSHIP Annexure-1

Semi-Annual Social Monitoring Report January-June 2020 Page 28 of 45 Project Management Consultant, Rajasthan State Highway Investment Program– RSHIP Annexure-2 Annexure-2: Public Consultations Venue and Date of Sl. Name of the Consultation & Participants, their numbers & Gender Issues discussed and responses of local communities No. Village/Road Photographs Nos 1. Rajola-Kalan(Jodhpur- Jagdamba Kirana Store Former Sarpanch, Panchayat re-presentatives Local • Local community informally, informed that land acquisition is not an Sojat Road) Shop in Rajola-Kalan villagers, shop-keepers, The Project Manager, The issue and no land has been acquired inside the village for the Village,38+00Km, 25th Deputy Project Manager and their site team (The EPC construction of the road, however, in case, any land acquisition February 2020 Contractor), Acting Team Leader cum-The Resident happens in future, they will prefer the compensation in cash. Engineer, Senior Quantity & Material Engineer (SQME), • Local community requested the construction of speed breakers in Pavement Specialist, Assistant Bridge Engineer and The front of school/s and inside the village. Assistant Highway Engineer (Authority Engineer), The • Local community informed that there is a community water storage Environmental Specialist and The Junior Engineer (Project tank by LHS of the road, just outside the village, which is used for Management Consultant-PMC ) drinking water supply after rainwater harvesting and requested that no construction material/s or washing of vehicles/machineries Number of participants-22, Men only should be carried out in this water tank. • Local community expressed satisfaction with installation of construction zone safety signages during construction activities of the road and informed that almost no inconveniences are happening to them during the construction of the road and no accident has happened on the road since the commencement of construction activities on the road. 2. Birdawas (Jodhpur- Outside Raju Ramji’s • Mr. Raju Ram, an active local community member, on behalf of the Sojat Road) Residence, 23+00Km, Sarpanch, Panchayat re-presentatives, Local villagers, local community, drew attention of ATL/RE, AHE, ABE (AE), PM 25th February 2020 shop-keepers, The Project Manager, The Deputy Project & DPM (EPC Contractor) and ES & JE (PMC) towards the Manager and their site team (The EPC Contractor), Acting rainwater logging in the LHS of the road towards Jodhpur , just after Team Leader cum-The Resident Engineer , Senior the village and requested that few hume-pipe culverts are required Quantity & Material Engineer (SQME), Pavement to constructed, so that rainwater which is logged on LHS may Specialist, Assistant Bridge Engineer and The Assistant cross-over to water storage tanks located on RHS. ATL-cum-RE Highway Engineer (Authority Engineer), The (AE) replied that feasibility of the suggestion being given will be Environmental Specialist and The Junior Engineer (Project investigated and the local community will be informed. Management Consultant-PMC ) • The entire local community expressed agreement with the joint inspection team that the construction of longitudinal covered drains, box culverts, minor bridge and major bridge on the road will Number of participants-20, Men only be ensuring long-term climate change induced disaster resilient

Semi-Annual Social Monitoring Report January-June 2020 Page 29 of 45 Project Management Consultant, Rajasthan State Highway Investment Program– RSHIP Annexure-2 Venue and Date of Sl. Name of the Consultation & Participants, their numbers & Gender Issues discussed and responses of local communities No. Village/Road Photographs Nos performance of the road and traffic jams etc due to flooding in rain season will never be realities. 3. Kakelaon (Jodhpur- Market Shop, Kakelaon Sarpanch, Panchayat re-presentatives, Local villagers, • Local community raised the demand for providing roadside/median Sojat Road) Village, 14+660 Km, 25th shop-keepers, The Project Manager, The Deputy Project traffic lights, widening of cross-drainage structures in four lane part February 2020 Manager and their site team (The EPC Contractor), Acting and also construction of speed breaker/s in front of school/s and Team Leader cum-The Resident Engineer , Senior markets. Quantity & Material Engineer (SQME), Pavement • Local community expressed satisfaction with installation of Specialist, Assistant Bridge Engineer and The Assistant construction zone safety signages during construction activities of Highway Engineer (Authority Engineer), The the road and informed that almost no inconveniences are Environmental Specialist and The Junior Engineer (Project happening to them during the construction of the road. Management Consultant-PMC ) • Local community informally, informed that land acquisition is not an issue and no land has been acquired inside the village for the construction of the road, however, in case, any land acquisition Number of participants-39, Men only happens in future, they will prefer the compensation in cash.

4. Meli (Siwana-Samdari- Market Shop in Meli, Sarpanch, Panchayat re-presentatives, Local villagers, • Mr. Anwar, an active local community member, on behalf of the Balesar Road) 09+500Km, 26th shop-keepers, The Project Manager, The Deputy Project local community, drew attention of PD (PIU-PPP-Jalore), RE, AHE, February 2020 Manager and their site team (The EPC Contractor), Acting ABE (AE), PM & DPM (EPC Contractor) and ES & JE (PMC) Team Leader cum-The Resident Engineer , Senior towards risks existing for road accidents near the school, frequent Quanitity& Material Engineer (SQME), Pavement mass level road crossing neatr markets. hospital and religious Specialist, Assistant Bridge Engineer and The Assistant places and requested that speed breakers are required to be Highway Engineer (Authority Engineer), The constructed for effectively slowing down speeds of road traffic and Environmental Specialist and The Junior Engineer (Project for the prevention of road accident. PD (PIU-PPP-Jalore) replied Management Consultant-PMC) that effective speed control signages, rumble strips will be provided at all places being informed and ES (PMC) also informed Mr. Anwar and the local community to opt for road traffic control signal/s for Number of participants-41, Men only effective slowing down of the road traffic.

5. Deora (Siwana- Market Shop, Deora, Sarpanch, Panchayat re-presentatives, Local villagers, • Local community informally, informed that land acquisition is an Samdari-Balesar Road) 14+600 Km, 26th shop-keepers, The Project Manager, The Deputy Project issue for the land being taken up for Toll-Plaza and Realignment of February 2020 Manager and their site team (The EPC Contractor), Acting the road before it and they will prefer the compensation in cash. Team Leader cum-The Resident Engineer , Material

Semi-Annual Social Monitoring Report January-June 2020 Page 30 of 45 Project Management Consultant, Rajasthan State Highway Investment Program– RSHIP Annexure-2 Venue and Date of Sl. Name of the Consultation & Participants, their numbers & Gender Issues discussed and responses of local communities No. Village/Road Photographs Nos Engineer (ME) Assistant Bridge Engineer and The • Local community informed that there is a lot water-logging in every Assistant Highway Engineer (Authority Engineer), The rain season on either ends of railways crossing and a solution is to Safeguard Specialist and The Junior Engineer (Project be provided. The resident Engineer (AE) informed the entire local Management Consultant-PMC) community that a major bridge, has been proposed to be constructed and further explained that how the completion of this major bridge will completely solve the water-logging on either ends Number of participants-33, Men only of the railway-crossing, the entire local community felt satisfied at RE’s explanation. • Local community drew attention towards in-conveniences, being caused by materials loaded vehicles near junctions and shifting of electric poles, which should be at away at considerable distances from their residences and market shops. RE (AE) and The Project Manager (EPC Contractor) assured the community that these issues will be resolved and the issue of shifting of electric poles at proper distances & places will be taken up with the electricity department and will also get resolved. 6. Karmavat (Siwana- Ganapati Tent House- Sarpanch, Panchayat re-presentatives, Local villagers, • Local community informally, informed that land acquisition is an Samdari-Balesar Road) Market Shop in shop-keepers, The Project Manager, The Deputy Project issue for the land being taken up for the construction of bye-pass Karmavat, 23+300Km, Manager and their site team (The EPC Contractor), Acting for Samdari Town and Realignment of the road before it and they 26th February 2020 Team Leader cum-The Resident Engineer , Material will prefer the compensation in cash. Engineer (ME),, Assistant Bridge Engineer and The • The Sarpanch, on the behalf of the local community, requested PD Assistant Highway Engineer (Authority Engineer), The (PIU-PPP-Jalore) and joint inspection team that cross-drainage Environmental Specialist and The Junior Engineer (Project structure should be provided at 23+900 Km and a big crossing- Management Consultant-PMC ) circle (Traffic junction -Chauraha) should be constructed in Four- lane section, between 23+500Km to 23+600Km. PD (PIU-PPP- Number of participants-39, Men only Jalore) instructed RE/AHE (AE) to investigate the onsite feasibility of the community concern being raised by the Sarpanch. RE/AHE (AE), after the end of the consultation, went for the same and have yet to submit the report to PD (PIU-PPP-Jalore. Sarpanch and the local community, informed that water supply pipeline, beyond the petrol-pump has got damaged due to road construction activities and has not been replaced so far, also requested an earliest

Semi-Annual Social Monitoring Report January-June 2020 Page 31 of 45 Project Management Consultant, Rajasthan State Highway Investment Program– RSHIP Annexure-2 Venue and Date of Sl. Name of the Consultation & Participants, their numbers & Gender Issues discussed and responses of local communities No. Village/Road Photographs Nos possible shifting of water supply pipelines by durable PVC-black- roll-pipelines, for ensuring regular water supply. PD (PIU-PPP- Jalore) assured that water supply pipelines shifting issue will be taken with PHED and shifting will be completed on high priority basis. 7. Bhinmal-Pantheri- 1.Hotel Shop inSiyavati, Sarpanch, Panchayat re-presentatives, Local villagers, • Dr.Mahendra Singh, an elite person, on behalf of the local Poshana-Jeevana Road 39+00 Km, 27th shop-keepers, The Project Manager, The Deputy Project community, drew attention of EE (PIU-PPP-Jalore) and entire joint 2.Hotel Manager and their site team (The EPC Contractor), Acting inspection team, towards irresponsible parking of construction GanjanaMishthan ( Team Leader cum-The Resident Engineer Material vehicles by drivers, high speed driving of these vehicles in Swett ) Bhandar Shop, Engineer (ME), Assistant Bridge Engineer and The settlement areas and resulting high dust emissions and stressed 22+170Km, Assistant Highway Engineer (Authority Engineer), The on the requirement of more intensive water sprinkling on road site 3. EPC Contractor’s Environmental Specialist and The Junior Engineer (Project inside the settlement areas. The Project Manager (EPC Contractor) Quality Test Lab, Management Consultant-PMC ) assured the local community that these in-conveniences will be 08+410Km, resolved and more water-sprinkling on road sites inside the Range of participants-25, Men only settlement areas will be carried out. • Mr. Anil Singh Rathore, on behalf of the local community, drew 27th February 2020 attention of EE (PIU-PPP-Jalore) and entire team, towards the construction and maintenance of internal roads and ramps, near schools and the stadium, near the village. The Project Manager (EPC Contractor) assured the local community that these issues will be resolved in due course of time. • Local community expressed happiness with the ongoing construction of the road and also expressed their satisfaction with air and noise during the ongoing construction activities and expressed the wish that there should be more water sprinkling and more plantations on road sides and other areas around.

Semi-Annual Social Monitoring Report January-June 2020 Page 32 of 45 Project Management Consultant, Rajasthan State Highway Investment Program– RSHIP Annexure-3 Annexure-3:Constitution of GRC

Semi-Annual Social Monitoring Report January-June 2020 Page 33 of 45 Project Management Consultant, Rajasthan State Highway Investment Program– RSHIP Annexure-4 Annexure-4:Pictorial Documentation Safeguards Compliance in ADB Tranch-2 Project

Photographs-1:Consultation with female owner of Wine shop LosalSalasar Road

Photographs-2:ConsultationatLosal -salasar Road

Semi-Annual Social Monitoring Report January-June 2020 Page 34 of 45 Project Management Consultant, Rajasthan State Highway Investment Program– RSHIP Annexure-4

Photographs-3:Consultation atLosal -salasar Road

Photographs-4: Road information signage board at the end chainages of Jodhpur-Sojat Road

Semi-Annual Social Monitoring Report January-June 2020 Page 35 of 45 Project Management Consultant, Rajasthan State Highway Investment Program– RSHIP Annexure-4

Photographs-5:Road information signage board at the end chainages of Jodhpur-Sojat Road.

Photographs-6: Views of Public Consultation at Jagdamba Kirana Store, in Rajola village at 38+000 km

Semi-Annual Social Monitoring Report January-June 2020 Page 36 of 45 Project Management Consultant, Rajasthan State Highway Investment Program– RSHIP Annexure-4

Photographs-7: Views of Public Consultation at Jagdamba Kirana Store, in Rajola village at 38+000 km

Photographs-8:Public Consultation,outside Raju Ramji’s Residence, 23+00km.

Semi-Annual Social Monitoring Report January-June 2020 Page 37 of 45 Project Management Consultant, Rajasthan State Highway Investment Program– RSHIP Annexure-4

Photographs-9:Public Consultation, at the Market Shop, Kakelaon Village, 14+660 km

Photographs-10: Public Consultation, at the Market Shop, Kakelaon Village, 14+660 km.

Semi-Annual Social Monitoring Report January-June 2020 Page 38 of 45 Project Management Consultant, Rajasthan State Highway Investment Program– RSHIP Annexure-5 Annexure-5: Lease Deed made for construction camp site in Package 3,Losal-Salasar-Ratangarh Road.

Semi-Annual Social Monitoring Report January-June 2020 Page 39 of 45 Project Management Consultant, Rajasthan State Highway Investment Program– RSHIP Annexure-5

Semi-Annual Social Monitoring Report January-June 2020 Page 40 of 45 Project Management Consultant, Rajasthan State Highway Investment Program– RSHIP Annexure-5

Semi-Annual Social Monitoring Report January-June 2020 Page 41 of 45 Project Management Consultant, Rajasthan State Highway Investment Program– RSHIP Annexure-5

Semi-Annual Social Monitoring Report January-June 2020 Page 42 of 45 Project Management Consultant, Rajasthan State Highway Investment Program– RSHIP Annexure-5

Semi-Annual Social Monitoring Report January-June 2020 Page 43 of 45 Project Management Consultant, Rajasthan State Highway Investment Program– RSHIP Annexure-5

Semi-Annual Social Monitoring Report January-June 2020 Page 44 of 45 Project Management Consultant, Rajasthan State Highway Investment Program– RSHIP Annexure-5

Semi-Annual Social Monitoring Report January-June 2020 Page 45 of 45